bob g. beaman may 13-17, 2002
DESCRIPTION
Micro-Arcsecond Imaging Mission, Pathfinder (MAXIM-PF). Electrical Power System (EPS). Bob G. Beaman May 13-17, 2002. The Phase I Hubcraft is undeployed Single Hub spacecraft attached to the Six FreeFlyer spacecraft. - PowerPoint PPT PresentationTRANSCRIPT
Final Version
Bob G. BeamanMay 13-17, 2002
Micro-Arcsecond Imaging Mission, Pathfinder (MAXIM-PF)
Electrical Power System (EPS)
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 2
Final Version
EPS Summary
The Phase I Hubcraft is undeployed Single Hub spacecraft attached to the Six FreeFlyer spacecraft.
The EPS for the Hubcraft is a distributed EPS with 10 ah LiIon batteries in each Spacecraft. Three sun side FreeFlyer spacecraft solar arrays are enough power to provide the Hubcraft power requirement.
Batteries are provided for Launch loads and contingency.
Technology areas that should be available by 2015 are: Distributed EPS, 35% eff Quad Junction solar cells, EPS Autonomy and use of Structural Batteries.
Solar Array Temp was assumed at 105 deg C.
MAXIM Pathfinder to full MAXIM. Solar array size increase by 1.4%
from 5 to 7 years additional life. Unused EPS margin may provide this. With no S/A increase full operational
requirements can accomplished except for 53 days during the 6th year and 71 days during the 7th year.
Use of 35% efficient solar cells would provide this and reduce solar array area.
Beginning Of Life (BOL) Solar Array power can accommodate up to 41.5 deg off pointing for the first year with decreasing angles as the solar array degrades.
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 3
Final Version
EPS Conclusions
There are no Big EPS show stoppers.
Dual Cosine angles are used. First +/- 30 degrees comes from an instrument requirement. And +/- 15 degrees is needed the Phase II operation to avoided one FreeFlyer from shadowing the other when they are in the same plane with the sun.
The Phase I mission Hubcraft requires 3.72 M2 from 3 FreeFlyer Spacecrafts. Each FreeFlyer Spacecraft requires 1.25 M2 for the Phase II mission which is just slightly larger. The design goal was to keep the Phase I Hubcraft solar array size to be equal for less that the 3 FreeFlyer Phase II size.
Further analysis or additional development may increase the Phase I Hubcraft solar array size. If that happens, the sun lead FreeFlyer will need additional solar panels each adjacent side. Higher efficient (35%) solar cells can be used.
Final Version
EPS Detail Charts
Micro-Arcsecond Imaging Mission, Pathfinder (MAXIM-PF)
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 5
Final Version
Electrical Power System Driving Requirements & Assumptions
Launch: 21 July 2015
Orbit: L2. No eclipses
Life: 2 year Phase I3 year Phase II
Battery: For Launch and contingency
Solar Array: Needed to provide Power for loads. Solar Array temp 105 deg C.
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 6
Final Version
Electrical Power System Options Considered
Deployed Solar Array. A body mounted Solar Array size was achievable so solar array deployments were eliminated.
Phase I “sun lead” FreeFlyer adjacent side solar panels were not needed. The Phase II FreeFlyer solar Array size was large enough to be used as one third of the Phase I Hubcraft solar array.
Baseline a distributed EPS for the Phase I Hubcraft. The distributed EPS needs to be broken up for Phase II mission phase for individual FreeFlyer spacecraft and Hub spacecraft operation.
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 7
Final Version
Electrical Power System Selected Configuration & Rationale
Use of 28% Tj GaAs solar cells. Provides enough power and will be a mainstay for 2015 launch. By 2015 35% QjGaAs cells may be available.
Use of LiIon battery. For launch loads and contingency in L2.
MAP type PSE, however must be modified to provide Distributed EPS functions. A Voltage regulated bus is recommended over a Battery Dominated Bus.
Final Version
Detector Spacecraft Phase I & II EPS Baseline
Micro-Arcsecond Imaging Mission, Pathfinder (MAXIM-PF)
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 9
Final Version
Detector Spacecraft Load AnalysisLAI MAXIM-Detector Spacecraft
5.0 Mission Life in Years
Nominal Mode Day
Nominal Mode Night
Safe Hold
EPS Load Item Description Avg. Power Watts
Avg. Power Watts
Power in Watts
Peak Power Launch Power Requirement
Total Power 743.1 743.1 148.6 1,190.3 148.6Time Period Over Which Averaging Is Done For Each Mode (min.) Contingency
Inst Global Contingency 20
Instruments with Contingency 300.0 300.0 60 450.0 60.0
X-ray CCD 50.0 50.0 10.0 75.0 10.0Contingency 20 10.0 10.0 2.0 15.0 2.0
Super Star Tracker (ISAL) 200.0 200.0 40.0 300.0 40.0Contingency 20 40.0 40.0 8.0 60.0 8.0
Instrument #3 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Instrument #4 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Instrument #5 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Instrument #6 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Spacecraft Loads with Contingency 443.1 443.1 88.6 740.3 88.6
Spcft Global Contingency 20
PSE MAP like (95.4% eff) 34 34.0 34.0 6.8 51.0 6.8Contingency 20 6.8 6.8 1.4 10.2 1.4
Electrical - Harness Losses BGB 4.3 4.3 0.9 6.4 0.9Contingency 20 0.9 0.9 0.2 1.3 0.2
Command & Data Handling Terry S. (generic) 28.0 28.0 5.6 42.0 5.6Contingency 20 5.6 5.6 1.1 8.4 1.1
Solid State Data Recorder N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Solar Array Drive Motor N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Attitude Control Eric S. 60.0 60.0 12.0 90.0 12.0Contingency 30 18.0 18.0 3.6 27.0 3.6
Com, X-Band HGA (2) (gimbales) Ron V. 1.0 1.0 0.2 16.0 0.2Contingency 20 0.2 0.2 0.0 3.2 0.0
Com, X Band Xpndr Ron V. 25.0 25.0 5.0 42.0 5.0Contingency 20 5.0 5.0 1.0 8.4 1.0
Com, S Band Xpndr Ron V. 22.0 22.0 4.4 22.0 4.4Contingency 20 4.4 4.4 0.9 4.4 0.9
Com, S Band HPA Ron V. 40.0 40.0 8.0 40.0 8.0Contingency 20 8.0 8.0 1.6 8.0 1.6
Thermal Dan N. & Wes O. 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Propulsion Bob E. 150.0 150.0 30.0 300.0 30.0Contingency 20 30.0 30.0 6.0 60.0 6.0
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 10
Final Version
Detector Spacecraft EPS Curve
LAI MAXIM-Detector Spacecraft Mission Over 5 Yr Life With Deployable Panel; 28% Eff Cells; Average Load During Day=743.1W; Average
Load During Night=743.1W
750
800
850
900
950
1000
1050
1100
0 365 730 1095 1460 1825
Mission Time (Days)
Daylight Average Solar Array Power Provided
Daylight Average Solar Array Power Required
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 11
Final Version
Detector Spacecraft Summary
Total Total
Dimensions (M) # Area or Vol Mass(Kg) Cost
Solar Array TJ GaAs 1 4.03 17.80 $2,016
Battery LiI on 10 0.19 0.13 0.08 1 0.00 5.76 $13
PSE MAP like 0.43 0.28 0.22 1 0.03 14.00 $750
Electrical Cable 2.52 $6
Total Materials $2,785Man Yr
Hardware Design/Procurement 10 $1,640
EPS I ntegration 2 $240
EPS Launch Site Support 1 $120
Grand Total 40.08 $4,785
Final Version
HubCraft Phase I EPS Baseline
Micro-Arcsecond Imaging Mission, Pathfinder (MAXIM-PF)
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 13
Final Version
Hubcraft Load Analysis
LAI MAXIM-Hubcraft, Phase I5.0 Mission Life in Years
Nominal Mode Day
Nominal Mode Night
Safe Hold
EPS Load Item Description Avg. Power Watts
Avg. Power Watts
Power in Watts
Peak Power Launch Power Requirement
Total Power 661.7 661.7 132.3 955.4 132.3Time Period Over Which Averaging Is Done For Each Mode (min.) Contingency
Inst Global Contingency 20
Instruments with Contingency 137.4 137.4 27.48 206.1 27.5
75 Module @1.46w/module 109.5 109.5 21.9 164.3 21.9Contingency 20 21.9 21.9 4.4 32.9 4.4
Beacons @ 5w 5.0 5.0 1.0 7.5 1.0Contingency 20 1.0 1.0 0.2 1.5 0.2
Star Teacker @ 10.0w off 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Laser Ranging @ 15w off 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Special Processor @ 5w off 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Instrument #6 N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Spacecraft Loads with Contingency 524.3 524.3 104.9 749.3 104.9
Spcft Global Contingency 20
PSE MAP like (95.4% eff) 30 37.0 37.0 7.4 55.5 7.4Contingency 20 7.4 7.4 1.5 11.1 1.5
Electrical - Harness Losses BGB 14.9 14.9 3.0 22.4 3.0Contingency 20 3.0 3.0 0.6 4.5 0.6
Command & Data Handling Terry S (previous #) 28.0 28.0 5.6 42.0 5.6Contingency 20 5.6 5.6 1.1 8.4 1.1
Solid State Data Recorder N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Solar Array Drive Motor N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Solar Array Drive Electronics N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Attitude Control Eric S. 60.0 60.0 12.0 90.0 12.0Contingency 30 18.0 18.0 3.6 27.0 3.6
Com, S/UHF-band Transponder (2) Ron V. 22.0 22.0 4.4 22.0 4.4Contingency 20 4.4 4.4 0.9 4.4 0.9
Com, S-Band HPA (2) Ron V. 40.0 40.0 8.0 40.0 8.0Contingency 20 8.0 8.0 1.6 8.0 1.6
Com, N/A N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Thermal Dan N. & Wes O. 80.0 80.0 16.0 120.0 16.0Contingency 20 16.0 16.0 3.2 24.0 3.2
Propulsion Bob E. 150.0 150.0 30.0 225.0 30.0Contingency 20 30.0 30.0 6.0 45.0 6.0
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 14
Final Version
Hubcraft EPS Curve
LAI MAXIM-Hubcraft, Phase I Mission Over 5 Yr Life With Deployable Panel; 28% Eff Cells; Average Load During Day=661.716W; Average
Load During Night=661.716W
600
700
800
900
1000
0 365 730 1095 1460 1825
Mission Time (Days)
Daylight Average Solar Array Power Provided
Daylight Average Solar Array Power Required
Final Version
Hub Spacecraft Phase II EPS Baseline
Micro-Arcsecond Imaging Mission, Pathfinder (MAXIM-PF)
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 16
Final Version
Hub Spacecraft Load AnalysisLAI MAXIM-Hub Spacecraft, Phane II
5.0 Mission Life in Years
Nominal Mode Day
Nominal Mode Night
Safe Hold
EPS Load Item Description Avg. Power Watts
Avg. Power Watts
Power in Watts
Peak Power Launch Power Requirement
Total Power 276.5 276.5 55.3 377.6 55.3Time Period Over Which Averaging Is Done For Each Mode (min.) Contingency
Inst Global Contingency 20
Instruments with Contingency 43.4 43.4 8.6736 65.1 8.7
9 Modules @ 1.46w/module 13.1 13.1 2.6 19.7 2.6Contingency 20 2.6 2.6 0.5 3.9 0.5
Lisa Laser 18.0 18.0 3.6 27.0 3.6Contingency 20 3.6 3.6 0.7 5.4 0.7
Beacon 5.0 5.0 1.0 7.5 1.0Contingency 20 1.0 1.0 0.2 1.5 0.2
Instrument #4 N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Instrument #5 N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Instrument #6 N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Spacecraft Loads with Contingency 233.1 233.1 46.6 312.5 46.6
Spcft Global Contingency 20
PSE MAP like (95.4% eff) 13 13.0 13.0 2.6 19.5 2.6Contingency 20 2.6 2.6 0.5 3.9 0.5
Electrical - Harness Losses BGB 1.3 1.3 0.3 1.9 0.3Contingency 20 0.3 0.3 0.1 0.4 0.1
Command & Data Handling Terry S. (generic) 28.0 28.0 5.6 42.0 5.6Contingency 20 5.6 5.6 1.1 8.4 1.1
Solid State Data Recorder N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Solar Array Drive Motor N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Solar Array Drive Electronics N/A 0.0 0.0 0.0 0.0 0.020 0.0 0.0 0.0 0.0 0.0
Attitude Control Eric S. 60.0 60.0 12.0 90.0 12.0Contingency 30 18.0 18.0 3.6 27.0 3.6
Com, S/UHF-band Omni Antennas (4)Ron V. 22.0 22.0 4.4 22.0 4.4Contingency 20 4.4 4.4 0.9 4.4 0.9
Com, S-Band HPA (2) Ron V. 40.0 40.0 8.0 40.0 8.0Contingency 20 8.0 8.0 1.6 8.0 1.6
Com, N/A N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Thermal Dan N. & Wes O. 20.0 20.0 4.0 30.0 4.0Contingency 20 4.0 4.0 0.8 6.0 0.8
Propulsion Bob E. 5.0 5.0 1.0 7.5 1.0Contingency 20 1.0 1.0 0.2 1.5 0.2
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 17
Final Version
Hub Spacecraft EPS Curve
LAI MAXIM-Hub Spacecraft, Phane II Mission Over 5 Yr Life With Deployable Panel; 28% Eff Cells; Average Load During Day=276.516W; Average Load During Night=276.516W
200
250
300
350
400
450
0 365 730 1095 1460 1825
Mission Time (Days)
Daylight Average Solar Array Power Provided
Daylight Average Solar Array Power Required
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 18
Final Version
Hub Spacecraft Summary
Total Total
Dimensions (M) # Area or Vol Mass(Kg) Cost
Solar Array TJ GaAs 1 1.50 6.62 $750
Battery LiI on 10 0.19 0.13 0.08 1 0.00 5.76 $13
PSE MAP like 0.43 0.28 0.22 1 0.03 14.00 $750
Electrical Cable 0.28 $4
Total Materials $1,516Man Yr
Hardware Design/Procurement 10 $1,640
EPS I ntegration 2 $240
EPS Launch Site Support 1 $120
Grand Total 26.7 $3,516
Final Version
FreeFlyer Spacecraft Phase II EPS Baseline
Micro-Arcsecond Imaging Mission, Pathfinder (MAXIM-PF)
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 20
Final Version
FreeFlyer Spacecraft Load AnalysisLAI MAXIM-FreeFlyer Spacecraft, Phase II
5.0 Mission Life in Years
Nominal Mode Day
Nominal Mode Night
Safe Hold
EPS Load Item Description Avg. Power Watts
Avg. Power Watts
Power in Watts
Peak Power Launch Power Requirement
Total Power 220.2 220.2 44.0 324.3 44.0Time Period Over Which Averaging Is Done For Each Mode (min.) Contingency
Inst Global Contingency 20
Instruments with Contingency 43.3 43.3 8.6544 64.9 8.7
11 Modules @1.46w/module 16.1 16.1 3.2 24.1 3.2Contingency 20 3.2 3.2 0.6 4.8 0.6
Star Tracker (Use ones in ACS) 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Laser Ranging 15.0 15.0 3.0 22.5 3.0Contingency 20 3.0 3.0 0.6 4.5 0.6
Special Processor 5.0 5.0 1.0 7.5 1.0Contingency 20 1.0 1.0 0.2 1.5 0.2
Instrument #5 N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Instrument #6 N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Spacecraft Loads with Contingency 176.9 176.9 35.4 259.4 35.4
Spcft Global Contingency 20
PSE MAP like (95.4% eff) 10 10.0 10.0 2.0 15.0 2.0Contingency 20 2.0 2.0 0.4 3.0 0.4
Electrical - Harness Losses BGB 4.4 4.4 0.9 6.7 0.9Contingency 20 0.9 0.9 0.2 1.3 0.2
Command & Data Handling Terry S. (generic) 28.0 28.0 5.6 42.0 5.6Contingency 20 5.6 5.6 1.1 8.4 1.1
N/A N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Solar Array Drive Motor N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Solar Array Drive Electronics N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Attitude Control Eric S. 60.0 60.0 12.0 90.0 12.0Contingency 30 18.0 18.0 3.6 27.0 3.6
Com, UHF xnpndr Ron V. 10.0 10.0 2.0 10.0 2.0Contingency 20 2.0 2.0 0.4 2.0 0.4
Com, N/A N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Com, N/A N/A 0.0 0.0 0.0 0.0 0.0Contingency 20 0.0 0.0 0.0 0.0 0.0
Thermal Dan N. & Wes O. 20.0 20.0 4.0 30.0 4.0Contingency 20 4.0 4.0 0.8 6.0 0.8
Propulsion Bob E. 10.0 10.0 2.0 15.0 2.0Contingency 20 2.0 2.0 0.4 3.0 0.4
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 21
Final Version
FreeFlyer Spacecraft EPS Curve
LAI MAXIM-FreeFlyer Spacecraft, Phase II Mission Over 5 Yr Life With Deployable Panel; 28% Eff Cells; Average Load During Day=220.2W;
Average Load During Night=220.2W
50
100
150
200
250
300
350
400
0 365 730 1095 1460 1825
Mission Time (Days)
Daylight Average Solar Array Power Provided
Daylight Average Solar Array Power Required
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 22
Final Version
FreeFlyer Spacecraft Summary
Total Total
Dimensions (M) # Area or Vol Mass(Kg) Cost
Solar Array TJ GaAs 1 1.25 5.5 $625
Battery LiI on 10 0.19 0.13 0.08 1 0.00 5.76 $13
PSE MAP like 0.43 0.28 0.22 1 0.03 14.00 $750
Electrical Cable 0.28 $1
Total Materials $1,389Man Yr
Hardware Design/Procurement 10 $1,040
EPS I ntegration 2 $240
EPS Launch Site Support 1 $120
Grand Total 25.5 $2,789
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 23
Final Version
EPS Technology Required
A distributed EPS system must be developed. Recommend the use of a voltage regulated system with distributed batteries and solar arrays.
By 2015 Quad junction gallium arsine (QjGaAs) solar cells at 35% efficiency would be available and can reduce mass but may increase cost and have life concerns.
Use of a Structural Battery would decrease mass. This technology should be available by 2015.
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 24
Final Version
EPS Requirements Verification.
Standard verification for PSE and Solar Array. A life test should be done on the battery design to ensure it
will meet the cycle life requirement with normal eclipse seasons.
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 25
Final Version
Electrical Power System Additional Trades to Consider
Scrub the load analysis to reduce the solar array size and battery ampere-hour requirement.
Trade Battery Dominated Bus (BDB) vs Voltage Regulated Bus (VRB) for a distributed bus design.
Peaking analysis, This EPS design has limited extra solar array due to full sun orbit and no
battery recharge requirements. Battery Life Test characteristics. Cable harness inductive characteristics that will choke the peak current. Use of a ultra capacitor near the peaking load device so harnessed do not see
peak currents. Look at propulsion orbit adjust maneuver and the power that is available.
MAXIM-PF, May 13-17, 2002Goddard Space Flight Center
Electrical Power SystemPage 26
Final Version
Electrical Power System Issues and Concerns
None