brazos river authority invitation no. rfb # 18-09-1093

5
BRAZOS RIVER AUTHORITY INVITATION NO. RFB # 18-09-1093 Addendum 1 for the MORRIS SHEPPARD DAM COC RJV ACCESS IMPROVEMENTS OCTOBER 2018 Firm Registration Number F-1294

Upload: others

Post on 25-Apr-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BRAZOS RIVER AUTHORITY INVITATION NO. RFB # 18-09-1093

BRAZOS RIVER AUTHORITY

INVITATION NO. RFB # 18-09-1093

Addendum 1 for the

MORRIS SHEPPARD DAM

COC RJV ACCESS IMPROVEMENTS

OCTOBER 2018

Firm Registration Number F-1294

Page 2: BRAZOS RIVER AUTHORITY INVITATION NO. RFB # 18-09-1093

Addendum No. 1 Page 1 of 3 BRA RFB 18-09-1093 COC RJV Access Improvements

Brazos River Authority QUALITY • CONSERVATION • SERVICE

October 4, 2018

BRAZOS RIVER AUTHORITY COC RJV Access Improvements

RFB # 18-09-1093

ADDENDUM NO. 1 Bidders on this project are hereby notified that this Addendum shall be attached to and made a part of the above named project identified as RFB # 18-09-1093, dated September 18, 2018. The following additions, deletions, modifications, or clarifications shall be made to the appropriate sections of the Contract Documents and Drawings. These items shall have the full force and effect as the Contract Documents and Drawings and cost involved shall be included in the bid prices. Bidders shall acknowledge receipt of this Addendum in the space provided on the Bid Form. SPECIFICATION REVISIONS: A1-1 Section 00800 – Supplementary Conditions

Update references to the Standard General Conditions section references as follows: a. In item SC-3, change reference from “101 A.8” to “1.01 A.8”. b. In item SC-5, change reference from “101 A.12” to “1.01 A.12”. c. In item SC-6, change reference from “101 A.19” to “1.01 A.19”. d. In item SC-7, change reference from “101 A.20” to “1.01 A.20”. e. In item SC-9, change reference from “101 A.21” to “1.01 A.21”. f. In item SC-10, change reference from “101 A.22” to “1.01 A.22”. g. In item SC-11, change reference from “101 A.35” to “1.01 A.35”. h. In item SC-12, change reference from “101 A.36” to “1.01 A.36”. i. In item SC-13, change reference from “101 A.37” to “1.01 A.37”. j. In item SC-14, change reference from “101 A.42” to “1.01 A.42”. k. In item SC-15, change reference from “101 A.49” to “1.01 A.49”. l. In item SC-17, change reference from “102 C.1” to “1.02 C.1”. m. In item SC-22, change reference from “206 A” to “2.06 A”. n. In item SC-23, change reference from “207 A” to “2.07 A”. o. In item SC-42, change reference from “404 A” to “4.04 A”. p. In item SC-177, change reference from “1204” to “11.04”.

Page 3: BRAZOS RIVER AUTHORITY INVITATION NO. RFB # 18-09-1093

Addendum No. 1 Page 2 of 3 BRA RFB 18-09-1093 COC RJV Access Improvements

A1-2 Section 01 35 00 – Special Procedures a. Add new paragraph 4 below to 1.01 – B.

“4. Anticipated tailwater elevations for gate releases are as follows:

Number Gates Opening

Measured Tailwater at Powerhouse with Gates Operating

1 875

2 878.8

3 882.7

4 886

5 888.7

6 891

7 893.7

8 895.3

9 896.5

Elevation data was taken from the 1992 Model Study of the Morris Sheppard Dam Spillway performed by the Utah State University Foundation.”

b. Renumber subsequent paragraphs.

A1-3 Section 05 12 00 – Structural Steel Framing a. Add new paragraph 20 below to 1.2 – A.

“20. ATSM A380, Standard Practice for Cleaning, Descaling, and Passivation of Stainless Steel Parts, Equipment, and Systems.”

b. Add new paragraph B below to 2.3. “B. Descaling: Descale and passivate the framing members via chemical descaling (pickling) in conformance with ASTM A380 prior to shipment.”

c. Add new paragraph 4 below to 3.2 – E. “4. Post-installation, remove surface contaminants from the framing in conformance with ASTM A380.”

DRAWING REVISIONS: A1-4 Drawing G-2 – Site Plan

a. Delete this sheet and replace it with the attached revised sheet. The location of the boat access area south of the dam has been added to the plan.

QUESTIONS AND ANSWERS: A1-5 Q: Will BRA provide the estimated construction budget?

A: BRA does not intend to provide the Engineer’s estimated construction cost.

A1-6 Q: How much notice to evacuate the work area would BRA give in the need

for a gate release? A: Per Specification 01 35 00 – 1.01 – B – 3, BRA will notify the contractor

“as soon as reasonably possible if gate operations are expected.” For rain

Page 4: BRAZOS RIVER AUTHORITY INVITATION NO. RFB # 18-09-1093

Addendum No. 1 Page 3 of 3 BRA RFB 18-09-1093 COC RJV Access Improvements

events upstream of the dam, BRA generally would be able to provide 24 hour notice of an upcoming gate operation. For rain events at the lake, shorter notice would be likely. As such, the contractor is reminded of 01 35 00 – 1.01 – B – 5’s requirement of having personnel on call at all times.

A1-7 Q: What are the downstream water elevations for the various gate release

scenarios? A: Tailwater elevations adjacent to the Powerhouse and work area for

various gate releases has been added to Specification 01 35 00 via this addendum. Refer to previous section of the addendum.

A1-8 Q: For boat or barge access, where will the contractor be allowed to enter the

dam tailwater? A: Boat access is possible via the boat ramp off the south access road, but

access will be dependent on the tailwater elevations and boat configuration since the area around the access ramp is shallow. See revised Drawing G-2 attached to this addendum for location of the boat access area.

A1-9 Q: Can the contractor set a crane adjacent to the work area?

A: Yes, the contractor will be allowed to set a crane in the North Contract Work Area shown on Drawing G-2.

A1-10 Q: Will the contractor be allowed to use BRA’s small barge?

A: No, the contractor should price the project assuming they will provide their own boat or barge if needed.

END OF SECTION

Page 5: BRAZOS RIVER AUTHORITY INVITATION NO. RFB # 18-09-1093

NORTH CONTRACT

WORK AREA

BRA LAKE OFFICE

POWER HOUSE

AREA OF WORK

CREST GATES

- TYP OF 9

NORTH RIVERSIDE

ACCESS POINT

SOUTH BOAT

ACCESS AREA1

100 GLASS STREET

214.752.9098

DALLAS, TEXAS 75207

TBPE FIRM F-1294

JQ ENGINEERING, LLP

JQENG.COM

JQ PROJECT NO:

shaping the built environment

JOSHUA L. BRONSTAD

111301

DATEBYREVISIONNO.

COC RJV ACCESS IMPROVEMENTS

MORRIS SHEPPARD DAM AT POSSUM KINGDOM

DATE

DESIGNED

DRAWN

REVISED

CHECKED

9-17-18

JLB

AR

CS

DRAWING:

www.brazos.orgWACO, TX 76714-7555

PO BOX 75554400 COBBS DRIVE

BRAZOS RIVER AUTHORITYPROJECT ENGINEER:

FAX (254) 400-2137PH (254) 761-3137ENGINEERING DEPARTMENTTECHNICAL SERVICESBRAZOS RIVER AUTHORITY

3140100

?

10/4/18

G-2SITE PLAN

SCALE:NTS

SITE PLAN 1

NOTES:

1. SEE SPECIFICATION 01 35 00 SPECIAL

PROCEDURES FOR CONSTRUCTION CONSTRAINT

INFORMATION RELATED TO GATE RELEASES AND

BARGE OPERATION.

2. SEE SPECIFICATION 01 35 53 SECURITY

PROCEDURES FOR SITE SECURITY REQUIREMENTS.

1 ADDENDUM NO. 1 JLB 10/4/18