captive coal mining final

Upload: arun-hariharan

Post on 14-Apr-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Captive Coal Mining Final

    1/22

    1

    Captive Coal Mining by Private Power Developers Issues and Road Ahead:

    Summary of recommendations

    Ministry of Coal has allocated captive mines to bulk users of coal, in public and private

    sectors. However, very few of the coal blocks have started production. Summarizedbelow are the recommendations which may be taken up by the Central Government, StateGovernment and Developers to facilitate the rapid development of coal blocks:

    1. Guidelines followed for Identification of Coal Blocks for Captive AllocationCentral Government: With reference to identification of coal blocks for allocation, the

    following should be considered:

    Coal India Ltd (CIL)/ Singareni Collieries Company Ltd (SCCL), currently, identifyblocks for allocation to private sector which are at a distance from the existing blocksof CIL/SCCL. This practice should be modified and blocks which are in the vicinity

    of CIL/SCCL and which are not included in the expansion plans of CIL/SCCL,

    should also be included in the list of captive blocks for allocation; In identifying captive coal blocks at reasonable distance from existing mines and

    projects of CIL/SCCL, it should be considered that the distance should not be at a

    disadvantage to the captive coal block developer in terms of available infrastructure

    and other facilities;

    Without disturbing the present procedure of coal block allotment, the future allotmentof coal blocks should be on the basis of better investigation and for which CMPDIL

    and other agencies should be mobilized

    State Government: The State Government and its agencies should facilitate development

    of infrastructure in the mining areas, particularly in providing right of way, railway

    clearances, water, electricity, etc.

    Developers: The captive block developers should coordinate with other coal block

    developers in proximity to jointly fund the development of Infrastructure based on a

    Master Plan prepared by an independent agency.

    2. Allocation of Coal block

    Central Government: The Ministry of Coal should not only look into the promoterbackground and the end-use, but should also give adequate weightage to the technical &

    financial capability of the applicants for timely development of the blocks. Further,

    auctioning approach may be adopted for allocation of coal blocks. However, auctioning

    of the block to the highest bidder may not be economically viable and adversely affectthe ultimate consumer. Thus, the following approaches, depending on the level of

    information available for the coal blocks, may be adopted in taking the auctioning route

    for allocation of blocks:

    Production sharing formula for fully unexplored blocks ;

    Maximum estimated production for partially explored blocks; &

    Lowest cost of power generated from coal from fully explored captive blocks withadequate information on the mineable coal reserves.

  • 7/30/2019 Captive Coal Mining Final

    2/22

    2

    3. Approvals and Clearances

    Central Government

    Central Government should bring about the legal changes to have a single windowapproach through a nodal agency at the State Level under the department of mines,which would have representation from all the concerned departments in the State

    Government. The nodal agency can pre-determine the conditions for each category ofland based on environmental sensitivity and nature of the proposed activity(prospecting, mining etc.). The nodal agency may complete the requirements of

    identification of land for compensatory afforestation, enumeration of trees, cost-

    benefit analysis, etc. before inviting application for mining lease.

    Public-Private Partnership model can be adopted in the form of a shell companyformed for each of the captive blocks allocated. Shell companies (formed by the

    Public sector) are bid out to the private sector only after obtaining clearances and landacquisition is completed.

    MoEF should segregate coal bearing areas into Go and No-Go areas for each typeof lease (Reconnaisance, Prospecting, and Mining) on the basis of the forest coverand environmental & ecological sensitivity. For areas defined as Go, it may be

    prudent to allow minimal or no forest & environmental clearances for investigative or

    prospecting purposes, with the conditionality that cutting of trees without priorpermission is not allowed. Non-coal bearing areas can be used for rehabilitation

    colonies and townships.

    A concurrence by Forest Advisory Committee or the empowered committee isrequired for obtaining forest clearance. The committee then sends a report to the

    Honble Supreme Court before sanction is accorded. This procedure needs to be

    reviewed to reduce delays in awarding clearances.

    MoEF clearances for projects which have a greater probability of commencing

    operations before the Eleventh Plan should be given priority.

    The Ministry of Coal as well as MoEF should grant consent to the developer of a coalblock to develop the block in 2-3 phases, so that production could start early.

    State Government: State Government should adopt procedures to issue the prospectinglicense within a minimum time.

    4. Land AcquisitionState Government: The procedure for land acquisition needs to be made less time

    consuming as the State Governments in large number of cases own significant portion of

    the land.

    5. Rehabilitation of Project Affected People (PAP)

    Central Government: It is recommended that the Ministry of Coal coordinate with the

    State Governments to align the State R&R Policies with the National R&R Policy.

  • 7/30/2019 Captive Coal Mining Final

    3/22

    3

    Further, the State Governments should facilitate the developers in negotiating the

    compensation package with the PAPs.

    State Government: For general development and improvement in the coalfield areas, the

    State Government could consider creating an Area Development Fund by applying a

    levy on each tonne of coal produced. This fund could be utilized for social welfare ofPAP including their health & education, improvement of infrastructure, roads, water

    supply etc.

    6. Geological Investigations & Mining plan alternate agencies

    Central Government: New agencies with the competence to perform geological

    investigations need to be set up and accredited by the Government of India. These

    agencies should be independent and unaffiliated to Coal India Limited or other publicsector coal companies. These agencies or an independent expert group should also be

    empowered to review and approve the mining plan, which would be an input to Ministry

    of Coal.

    7. Tapering coal linkage/ marketing of surplus coal

    Central Government: The timeframe for development of coal block is likely to be muchlonger than a power plant. Ministry of Coal, therefore, has decided to provide coal

    linkage on a tapering basis to the power producers who have been allotted captive coal

    blocks and whose mining plan has been approved. It is suggested that the Ministry of

    Coal should provide for the condition that the mining lease should be approved before thepower plant commences operations.

    8. Joint Allotment of Coal BlocksCentral Government: In case of joint allotment of coal blocks it has been observed that

    some of the companies in the Joint Venture do not furnish the Bank Guarantee, which

    hinders the development of the block. Companies in the consortium which furnish theBank Guarantee should be allowed to proceed with development of the coal block, and

    the partners who fail to provide the bank guarantee should be replaced with other

    companies from among the applicants whose applications are pending with the Ministry.

  • 7/30/2019 Captive Coal Mining Final

    4/22

    4

    Captive Coal Mining by Private Power Developers Issues and Road Ahead

    The rapid growth in the Indian economy has led to a robust growth in the demand for

    power. The demand for power has been constantly outpacing supply. With a view to

    reducing the demand-supply gap, large generation capacity additions have been planned.

    Notwithstanding efforts to have a diversified portfolio of fuel options in powergeneration, share of coal based generation has increased over the years and with large

    capacity additions envisaged over next decade, coal will continue to remain the primary

    source of fuel for power generation. Besides substantial coal based capacity additions,increase in demand for coal has been accentuated by improved utilization of plants,

    diminishing quality of coal and inadequate availability of gas.

    With rapid growth in demand for coal, coal supply is proving to be a major cause forconcern. Government of India (GoI) is targeting coal based generation capacity addition

    of about 53000MW by 2012 (end of the 11th

    Plan period), coal based installed capacity

    would then be more than 125 GW by 20121. In this scenario, there is an apprehension that

    coal companies may not be able to cater to the enhanced coal requirement due to resourceand other constraints. To augment the coal supply, Ministry of Coal, Government of India

    decided to allocate captive mines to bulk users of coal, in public and private sectors, andconsequently many captive coal blocks have been allocated to power developers

    2.

    In May 2007, at the Parliamentary Consultative Committee meeting of the Ministry of

    Coal3, it was announced that to meet the coal demand about 81 coal blocks with

    geological reserves of about 20 billion tonnes have been identified for allocation to

    companies, both government and private, for permissible end uses. Out of these, 41 coal

    blocks, with geological reserves of about 15.7 billion tonnes, were earmarked for thepower sector. Currently, the allocation coal mining blocks to companies, other than Coal

    India Ltd (CIL), is done either under the government company dispensation route

    4

    orthrough the captive dispensation route. These blocks for power sector, have been furthercategorized in 3 separate lists on the basis of method of allocation which are,

    Government Company Dispensation Route, Screening Committee5

    Route and Tariff

    based Bidding as per the Ministry of Power Guidelines. The details of these blocksidentified for power sector are as follows:

    Method of allocation No. of blocks Total reserves

    (Billion tonnes)

    Government dispensation route 10 6.1

    1

    Power Scenario at a Glance for All India, CEA, GoI, July 2008; White Paper on Strategy for 11th

    Plan,CEA & CII, August 20072 Under the provisions of the 1993 amendment to Coal Mines (Nationalisation) Act, 1973.3 81 coal blocks identified for allocation under captive END-USE, Press Release, PIB, GoI, 18th May 20074 Under the Government dispensation route, the block is allocated to a government company and this

    company has the right to be used for a specific end-use such as power, steel and cement.5 A screening committee has been set up in the Ministry of Coal for screening the proposals received for

    captive mining of coal & lignite. The screening committee comprises of members representing Ministry of

    Coal, Ministry of Power, Ministry of Railway, Ministry of Steel, concerned State Governments, CIL,

    CMPDIL, and Department of Industrial Policy & Promotion (Ministry of Industry).

  • 7/30/2019 Captive Coal Mining Final

    5/22

    5

    Method of allocation No. of blocks Total reserves

    (Billion tonnes)

    Tariff based bidding as perMinistry of Power guidelines

    16 6.0

    Screening committee route 15 3.6

    Total 41 15.7

    According to Ministry of Coal, till 31st

    December 2007, 170 captive coal blocks havebeen allocated, of which 15 blocks allotted to 3 PSUs and 9 private companies have

    already started producing coal. Of the 170 captive coal blocks allotted (with reserves 39.3

    billion tonnes), 76 coal blocks with reserves of about 23.6 billion tonnes have beenallotted to power sector (with 24 coal blocks allotted in 2007)

    6.

    It may be noted that production of coal through the open cast mining of coal may not

    need a lengthy lead time unlike production of coal in the case of underground mining,which involves a lengthy gestation period, particularly when the stripping ratio is high.

    Given the foregoing, one may be misled into believing that coal production can startwithin a short period from the allotted coal blocks. However, this is not the case, as theallocated mines could also involve underground mining.

    Discussions with the private sector and public sector coal mine allottees have revealedthat the lead time is atleast 4-6 years, on account of the initial planning, conducting

    geological studies to authenticate quantum and structure of reserves, obtaining several

    statutory approvals from multitude of authorities & agencies, formulating mining plan

    and getting approval, land acquisition, relief and rehabilitation issues, and infrastructuredevelopment.

    This note attempts to examine the problems being faced by the allottees of the captivecoal blocks and suggests recommendations which could shorten the actual lead time

    involved in commercial production of coal from these coal blocks.

    1. Guidelines followed for Identification of Coal Blocks for Captive Allocation

    The guidelines adopted for demarcating the blocks are such that the developers wouldface a number of problems in quickly bringing the allotted blocks to the production stage.Ministry of Coal relies on Coal India Ltd (CIL) and Singareni Collieries Company Ltd

    (SCCL), for identifying the captive coal blocks. The guidelines adopted by CIL & SCCL

    for identifying and allotting coal blocks for captive mining are as follows7:

    The blocks offered to private sector should be at reasonable distance from existing

    mines and projects of CIL in order to avoid operational problems

    Preferably, blocks in greenfield areas having less or no development of basicinfrastructure like road, rail link, etc. may be allotted to the public/private sector for

    6 Coal Directory of India 2006-07, Part-I: Coal Statistics, Ministry of Coal, GoI7 Coal Directory of India 2006-07, Part-I: Coal Statistics, Ministry of Coal, GoI

  • 7/30/2019 Captive Coal Mining Final

    6/22

    6

    captive mining. The areas where CIL has already invested in creating such

    infrastructure for opening new mines should not be handed over to the private

    sector, except on reimbursement of costs

    Blocks already identified for development by CIL where adequate funding is onhand or in sight should not be offered to the private sector

    Public/private sector should be asked to bear the full cost of exploration in theseblocks which may be offered

    For identifying blocks, the requirement of coal for about 30 years would beconsidered

    Others, which include Mine Plan approval under the provisions of Mines and

    Mineral (Development and Regulation) Act 1957, approval of the Directorate

    general of Mine Safety, and inspection by Coal Controller for an appropriateenforcement of conservation measures under the provisions of the Coal Mines

    (Conservation and Development) Act 1974.

    The fact that the blocks are identified at a distance from the existing infrastructure of the

    CIL and also that coal blocks are located in remote areas, devoid of all basicinfrastructure like road, rail links, electricity etc, it is difficult for the coal block allotteesto quickly bring the coal blocks to production stage. Development of infrastructure on a

    piece meal basis i.e. individually on block by block basis may cause drain on the

    resources of the developer, would not bring in economies of scale, and could be onerousas well. Further, the blocks identified are only regionally explored with inadequateinformation, which adds to risk and also reasons for delay in development of the blocks.

    Thus, to facilitate speedy development of coal blocks it is recommended that thefollowing should be considered in identifying and allocating coal blocks:

    If there are coal blocks in the vicinity of the CIL/SCCL blocks which are not included

    in the expansion plans of CIL/SCCL, then these blocks should also be included in thelist of captive blocks for allocation and not excluded simply because of theirproximity to CIL/SCCL blocks;

    In identifying captive coal blocks at reasonable distance from existing mines andprojects of CIL/SCCL, it should be considered that the distance should not be at a

    disadvantage of the captive coal block developer in terms of available infrastructureand other facilities;

    Without disturbing the present procedure of coal block allotment, the future allotmentof coal blocks should be on the basis of better investigation and for which CMPDIL

    and other agencies should be mobilized

    Further, in the context of inadequacies in infrastructure associated with the captive blocksidentified for allocation, it is recommended that the Central/State Government agenciesshould facilitate development and creation of infrastructure in the mining areas,

    particularly in providing right of way, railway clearances, water, electricity, etc. The

    Government could also consider pre-identification of non-coal bearing corridors to beused for rehabilitation colonies and townships.

  • 7/30/2019 Captive Coal Mining Final

    7/22

    7

    The captive block developers should coordinate with other coal block developers in

    proximity to jointly fund the development of Infrastructure based on a Master Plan

    prepared by an independent agency.

    2. Allocation of Coal block

    Allocation of coal block should not only look into the promoter background and the end-

    use, but should give importance to the technical & financial capability of the applicants

    for timely development of the blocks. The process of allocation of the block could alsotake into consideration the extent of the preparedness of the developers and the projects.

    Further, auctioning approach may be adopted for allocation of coal blocks. However, it

    may be noted that auctioning of the block to the highest bidder may not be economically

    viable, since it would get translated into a pass through in the cost of end-use product andthereby adversely affecting the ultimate consumer.

    The following approaches, depending on the level of information available for the coal

    blocks, may be adopted in taking the auctioning route for allocation of blocks:

    Status of block Possible criteria for allocation

    Fully explored Lowest cost of power generated

    Partly explored Maximum estimated production

    Totally unexplored Production sharing formula

    Auctioning on the basis of maximum proposed production or production sharing formula

    may be workable till sufficient data on the depth, seam thickness and quantity & qualityof the coal is available for the blocks put up for auction. However, once sufficient data is

    available for the blocks put up for auction, the criteria for grant of block could be linked

    to the lowest cost of power generated from captive coal block.

    3. Approvals and Clearances

    In the present legislative and regulatory framework, the allottee of a captive coal blockhas to obtain multitude of clearances and approvals as provided under the provisions of

    the Coal Mines (Nationalisation) Act, Colliery Control Rule 2004, Coal Mines

    (Conservation and Development) Act 1974 and rules thereunder, Mines and Mineral

    (Development and Regulation) Act 1957 (MMDR), Mineral Concession Rules 1960(MCR), Environment Protection Act with its rules and procedures, and Forest

    Conservation Act with its rules and procedures.

    In the federal structure of India, the State Government is the owner of the minerals

    located within the boundaries of the State. Thus, though the Central Government

    allocates the coal blocks for captive mining, the State Government grants theReconnaissance Permit (RP), Prospecting Licence and Mining Lease under the provisions

  • 7/30/2019 Captive Coal Mining Final

    8/22

    8

    of the MMDR Act and Mineral Concession Rules. However, the State Government can

    grant the mining lease only with the prior approval of the Central Government as

    provided under section 5(1) of the MMDR Act. Central Government approves theapplication only after the coal block allottee obtains the mining plan approval and obtains

    clearances from several authorities at the Central, State and District level.

    Although broadly three clearances are required, i.e. Grant of RP or ML, Environmental

    Clearance and Forest Clearance, but depending on whether the allotted block is explored

    or unexplored, in forest or non-forest area, etc. clearances may be required from multipleauthorities. The table below indicates the authorities and agencies at the Central and State

    level from whom the approvals have to be sought by the coal block allottees before actual

    production can begin:

    Approvals / Clearances Authority / Agency Involved

    Mining Lease

    Approval or Purchase of Geological Report CMPDIL (purchase could also be from

    SCCL, MECL)Directorate General of Civil Aviation andMinistry of Defence (for unexplored blocks

    if aerial reconnaissance is conceived)

    Mine Plan CMPDIL

    Coal Controller

    Mine Safety Directorate General of Mine Safety

    Mining Technology & Conservation

    Measures, and Coal Categorisation

    Coal Controller (under the provisions of

    Colliery Control Rules and the Coal Mines

    (Conservation & Development) Act)

    Mining Lease State Government (Mining Department),

    Ministry of Coal (GoI) Reviewed atvarious levels within the Departments at

    the State & Central Government level

    Environment

    EIA / EMP Studies State Pollution Control BoardState Environmental Impact Assessment

    Authority

    State Water Resource and Water SupplyDepartment

    District Administration (for various aspects

    of site clearance)

    Coal ControllerDepartment of Environment (MoEF)

    Forest

    Forest Clearance &

    Valuing Compensatory Afforestation

    Committee to Advise GoI (MoEF)

    Office of Chief Conservation of Forests,

    (Regional Office of MoEF)State Forest Department & District

  • 7/30/2019 Captive Coal Mining Final

    9/22

    9

    AuthorityDepartment of Forest (MoEF)

    State Revenue Department

    Honble Supreme Court

    Land Acquisition Ministry of Coal (under provisions ofCBA)

    State Department of Revenue

    Infrastructure (Electricity, Water,

    Railways, Road, etc)

    Appropriate Departments of the State

    Government & Ministries of Central

    Government

    It may be noted that of all the clearances, the MoEF clearance is the most timeconsuming, since many departments and issues are involved in getting environmental

    clearances and also vast majority of the coal blocks are situated on forest land. Even

    geological investigations (which require drilling for exploration) in these areas require

    MoEF approval. This approval is a lengthy process and takes a lot of time.

    The Guidelines for Allocation of Captive Blocks & Conditions of Allotment through the

    Screening Committee, Ministry of Coal, provides for the normative time limit ceilings(Appendix 1) to ensure that coal production from the allocated captive blocks commence

    production within 36 months (42 months in case the area is in forest land) of the date of

    issue of letter of allocation in Open Cast (OC) mine and in 48 months (54 months incase the area fall under forest land) from the date of said letter in Under Ground (UG)

    mines. The following chart (drawing upon the ceiling time limit provided in the

    Guideline) is an indicative depiction of the schedule of commencement of miningoperations from the time the coal block is allocated:

  • 7/30/2019 Captive Coal Mining Final

    10/22

    10

    The Guideline of MoC, mentioned above, is to ensure timely development and operationof the allocated captive blocks. In order that the allottee adheres to the timeline, the

    allottee has to provide a bank guarantee and the encashment of the bank guarantee isdependent on achievement of the milestones consistent with the normative time limit

    ceilings.

    Time limits are specified in the Mineral Concession Rules and other legislations formaximum time permissible for grant of approval on an application. This is based on the

    time to be taken from the receipt of completed application. Since basic information

    required for processing the application is available at the district level, particularly forforest clearance, unless and until all such information is available, the application is

    considered incomplete. The time taken at various levels of scrutiny delays the process.Thus, in view of the large number of approvals required, it is unlikely that the timelinespecified by MoC for development of coal block would be adhered to by the coal block

    allottees. The existing provisions of the Acts do not provide for deemed approval status

    to applications if the time lines are not adhered to and thus there is no urgency indisposing the applications within the specified time.

  • 7/30/2019 Captive Coal Mining Final

    11/22

    11

    From the above, the following limitations are thus evident in the process of grant of

    clearances and approvals, which would cause significant delay in production from the

    allotted captive blocks:

    Several parallel clearance & approval processes are to be pursued at the Central

    Government and State Government level, and the allottee has to follow-up thewith the applications with various authorities.

    Environment and Forest clearance is extremely time consuming and significantdelays arise in the public consultation process, valuation of compensatory

    afforestation, identification of non-forest land for compensatory afforestation,

    enumeration of trees and completion of cost-benefit analysis by the forestdepartments.

    The entire process of seeking approvals lack clarity, and often delays in oneprocess causes delay in the others. Besides, conditions of Mining Lease are not

    standardized and could be significantly influenced by individual judgment of thegranting authorities.

    A comparative study on grant of mining lease in Australia, Canada and India, included inthe Report of the Expert Group constituted by the Ministry of Steel for formulating

    Guidelines for Preferential Grant of Mining Leases (2005), suggests that the time taken

    for grant of mining lease in Australia is about 1-2 years (12 + months) and in Canadaabout 2-3 years (12-36 months) as compared to 7-8 years in India (though the Mineral

    Concession Rule8provides that the State Government shall dispose off the application for

    grant of mining lease within 12 months from the date of receipt of application). The

    observations of the study are listed in the following table:

    Australia Canada India

    State is fully empowered togrant mining lease

    State is fully empowered togrant mining permit (MP)

    State to grant mining lease withthe approval of the Central

    Government

    Single window process,

    involving 4 agencies:

    Department of Minerals &Energy

    Department of Environment

    National Native TitleTribunal

    Land Acquisition Authority

    in Local Government

    Minister of Minerals and

    Single window process,

    involving 3 government

    agencies:

    Department of NaturalResource

    Department of Environment

    Department of Labour

    Approvals are required from

    multitude of authorities at the

    Central, State and Districtlevels, with the different

    authorities having little or no

    coordination amongst them.Broadly 3 different clearances

    requiring submission of separate

    applications:

    (1)Approval of Grant of ML

    8 Mineral Concession (Amendment) Rules 20029 The Mining proposal approval process and minimum timeframes of process as provided in the Regulatory

    Guideline No.1 of the Division of Minerals and Energy Resources, Government of South Australia, June

    2007 are presented in Appendix 2 of this note. The regulations laid down by the Department of Industry

    & Resources, Government of Western Australia are similar.

  • 7/30/2019 Captive Coal Mining Final

    12/22

    12

    Energy is the final approvingauthority, and takes decisions in

    consultation with other

    Ministries. Close interaction

    between Department of

    Minerals and Energy andagencies responsible for

    protection of environment.

    (2) Forest Clearance(3) Environmental Clearance

    Central Government grants

    forest and environmental

    clearances on therecommendations of the state

    Government.

    Mining Lease: Time taken forgrant of mining lease is 1-2

    years. Time taken for activities

    involved are fixed & largelyadhered to, except in cases

    where public consultation

    process & stakeholder

    participation is involved.

    Applicants submit application

    for grant of lease with theMining Registrar in the

    Department of Minerals &

    Energy.

    Mining Lease: The time takenfor grant of MP is 2-3 years.

    Fixed time frames are complied

    with.

    The project can be rejected if

    there are strong chances of

    adverse socio-economic andenvironmental impacts.

    Mining Lease: Although timeframe for clearances &

    approvals are specified as less

    than an year in the various rules,the actual time taken are usually

    7-8 years for grant of ML.

    Identification of non-forest landfor compensatory aforestation

    takes long time and at times

    takes more than a decade.

    Requirement of enumeration of

    trees, cost benefit analysiscarried by the State Forest

    department is time consuming

    (10-12 months)

    Mining areas are categorized asper environmental sensitivity.

    Conditions & procedures for

    each category are predeterminedand identified in each case.

    Grant of mining leases in very

    sensitive areas require approval

    from both houses of Parliament.

    The project is first assessedfrom Environment angle, before

    processing for Mining Permit

    (MP). Once the project getsclearance from environment

    angle, the proponent makes an

    application for MP.

    -

    Applicant is required to submit

    a Bond to take care of

    environmental andrehabilitation considerations.

    Department of Natural Resource

    requires a bond or security to

    ensure that reclamation work iscarried out.

    -

    Financial & technical strengthof the applicant are taken into

    consideration before grant of

    mining lease.

    Info not available Limited emphasis being givenon the technical and financial

    strength of the applicant.

    Minimum term of mining lease

    is granted for 21 years.

    The minimum term of Mining

    Permit is 20 years.

    Mining lease is granted for 20-

    30 years

  • 7/30/2019 Captive Coal Mining Final

    13/22

    13

    Based on the above observations and discussions, the following suggestions may be

    considered to speed up the approval process and grant of mining lease:

    A single window approach through nodal agency set up at the State level under the

    department of mines with representation from all the concerned departments ofvarious ministries. The nodal agency can pre-determine the conditions for eachcategory of land based on environmental sensitivity and the nature of the proposed

    activity (prospecting, mining etc.). The nodal agency may complete the requirements

    of identification of land for compensatory afforestation, enumeration of trees, cost-benefit analysis, etc. before inviting application for ML.

    Since a single window approach may require change in legal procedure, alternately aPublic-Private Partnership model can be adopted in the form of a shell company

    formed for each of the captive blocks allocated, as has been done in the case of

    UMPPs in Power Sector wherein in shell companies (formed by the Public sector) are

    bid out to the private sector only after obtaining clearances and land acquisitionprocess completed.

    As an immediate remedial measure, MoEF should map and segregate the entire coalbearing areas into Go and No-Go areas for each type of lease (Reconnaisance,Prospecting, and Mining) on the basis of the forest cover and environmental &

    ecological sensitivity. The GoI/Ministry of Coal (MoC) by not allotting the blocks

    under the No-Go areas would prevent wastage of resource and also speed up theapproval process for grant of lease. Thus, for areas defined as Go, it may be prudent

    to allow minimal or no forest & environmental clearances for investigative or

    prospecting purposes, with the conditionality that cutting of trees without prior

    permission is not allowed. Thus, although the need for detailed environmental impactstudies, assessment of compensatory afforestation & enumeration of trees and cost-

    benefit analysis for forest clearance is required for mining approval, the same level ofdetail may not be required for limited drilling involved in prospecting or investigative

    purposes.

    Forest clearance is a contentious issue and has been further compounded by thedevelopment which requires each case of forest clearance a concurrence by Forest

    Advisory Committee or the empowered committee, which has to then send a report to

    the Honble Supreme Court before sanction is accorded. This procedure needs to be

    reviewed and the empowered Advisory Group or the empowered committee & MoEF

    could be delegated authority to accord approval in certain defined categories of forestareas.

    MoEF clearances for projects which have a greater probability of commencingoperations before the Eleventh Plan should be given priority.

    The approval for the prospecting license by the state government should be issued asthe foremost requirement within a minimum time. The developer could then develop

  • 7/30/2019 Captive Coal Mining Final

    14/22

    14

    the coal block in 2-3 phases, i.e. identify comparatively easier areas within these

    blocks (keeping in view government/private land, forest/non-forest land etc.) and get

    the required investigations, mining plan, approach etc. for the first phase so thatproduction could start early, and simultaneously also repeat the cycle of activities in

    the subsequent phases. This approach will require due consideration and consents by

    Ministry of Coal as well as Ministry of Environment and Forest.

    4. Land Acquisition

    Unlike other industries siting of a coal mine does not leave room for choice in the land to

    be acquired. Land has to be acquired where coal exists, irrespective of population base or

    existence/ density of forest land. The present procedure on land acquisition is lengthy and

    is prone to litigation. In a large number of cases, a large part of the land belongs to thegovernment, and in such cases the Government should take measures to transfer the land

    to the developers in a shorter timeframe.

    5. Rehabilitation of Project Affected People

    As regards Rehabilitation of Project Affected People (PAP) there are many prevalentResettlement & Rehabilitation (R&R) policies. The Central Government has a National

    R&R policy 2007, which provides for the State Governments to have their own policies.

    States in proposing their R & R policies to the benefit of the PAPs are more stringent on

    the project developers. Also providing employment to all PAP may not always bepossible as new technology driven mining methods is less labour intensive.

    It is recommended that the Ministry of Coal should coordinate with the StateGovernments to align the State R&R Policies with the National R&R Policy. Further, the

    State Governments should facilitate the developers in negotiating the compensation

    package with the PAPs.

    For general development and improvement in the coalfield areas, the State Government

    could consider creating an Area Development Fund by applying a levy on each tonne

    of coal produced. This fund could be utilized for social welfare of PAP including theirhealth & education, improvement of infrastructure, roads, water supply etc.

    6. Geological Investigations & Mining plan alternate agencies

    In most coal blocks allocated to companies, detailed geological investigations have not

    been done. At present, exploration for coal in India is carried out by Geological Survey ofIndia (GSI), Mineral Exploration Corporation Ltd (MECL), Singareni Collieries

    Company Ltd (SCCL), Directorates of Mines and Geology of some states. These

    agencies have limited capacity for drilling of areas (for collating data) and, currently, arealready fully stretched. Out of 22,400 km

    2of the coal bearing sedimentary formations

    identified by GSI, only about 10,200 km2, or only 45% of the total area, has been

    systematically explored through regional and promotional drilling.

  • 7/30/2019 Captive Coal Mining Final

    15/22

    15

    Apart from geological investigations, in the present legislative framework the Mining

    Plan is approved by Ministry of Coal (with technical inputs from CMPDIL). This further

    delays the whole process.

    Thus, new agencies with the competence to perform geological investigations need to be

    set up and accredited by the Government of India. These agencies should be independentand unaffiliated to Coal India Limited or other public sector coal companies. These

    agencies or an independent expert group should also be empowered to review and

    approve the mining plan, which would be an input to Ministry of Coal.

    7. Tapering coal linkage/ marketing of surplus coal

    The timeframe for development of coal block is likely to be much longer than a powerplant in view of the various problems faced by the developers. Therefore, there is a risk

    that the power plant would be commissioned prior to the commercial operations date of

    the coal mine. In order to mitigate this risk of delay in the commercial operations of the

    coal mine, Ministry of Coal has decided to provide coal linkage on a tapering basis to thepower producers who have been allotted coal blocks for captive use. The tapering linkage

    is being considered by the Ministry of Coal to facilitate the working of end-use plants incase of development of coal blocks allocated to such consumers does not synchronize

    with the operation of end-use plant. In this regard, MoC, in December 07, came out with

    a Guideline relating to issue of LoA/allocation of coal on Tapering Basis to various

    consumers. However, the application for such tapering linkage would only be consideredif the applicant has an approved mining plan for the coal block allocated.

    This is tricky and most of the captive block owners are unlikely to qualify for taperinglinkage even if their end-use plant is in an advanced stage of development. The Ministry

    of Coal should consider reviewing this condition for grant of tapering linkage to facilitate

    rapid capacity addition in power (considering the huge deficit situation in power andsustenance of economic growth), and should consider granting tapering linkage based on

    technical & financial capability of the developer and preparedness of the end-use project.

    Instead of keeping approved mining lease as criteria for considering the application of

    tapering linkage, the Ministry of Coal should provide for the condition that the mininglease should be approved before the power plant commences operations.

    8. Joint Allotment of Coal Blocks

    In some cases a coal block has been allotted to a number of companies and the allottees

    are required to submit Bank Guarantees to safeguard commercial obligations and ensuretimely development of the allotted coal blocks. If some partner companies of the

    proposed Joint Venture do not furnish the Bank Guarantee, then the development of the

    mine and of the associated power plant with the mine is held up.

    It is recommended that if in the consortium of companies granted a coal block, one or

    some of the partners are not serious, but the remaining partners are serious, then the

    progress of the development of the block by the consortium should not be jeorpardised.

  • 7/30/2019 Captive Coal Mining Final

    16/22

    16

    Thus, companies in the consortium who furnish the Bank Guarantee should be allowed to

    proceed with development of the coal block, and the partners who fail to provide the bank

    guarantee should be replaced with other companies from among the applicants whoseapplications are pending with the Ministry. However, pending the replacement of

    partners, the development of the coal block should proceed as usual. In this regard, the

    company allocated the coal block, having the requisite financial strength, could also begiven the freedom to choose partners from among the applicants whose applications are

    pending with the Ministry.

    9. Infrastructure status for Coal industry

    Coal industry needs to be given infrastructure status so as to attract more players into this

    industry and to incentivise domestic production of mining equipment. The infrastructurestatus could be for both coal mining and coal washeries. Infrastructure status for the coal

    sector would bring it to par with other sectors such as roads, railways, oil and laying of

    oil and gas pipelines.

    In the past, this proposal was rejected as bulk of the coal mining was under the public

    sector. Coal mining, however, is expected to undergo a major change in the coming yearswith production from captive coal blocks mainly by private sector companies. The main

    beneficiaries would be power companies as concessions would make coal production

    economical that would ultimately help in keeping power tariffs low. Coal companies

    would be also able to import capital equipment and spares at concessional rates.

  • 7/30/2019 Captive Coal Mining Final

    17/22

    17

    Appendices

    Appendix 1: Normative Time Limit Ceilings as provided in Guidelines for

    Allocation of Captive Blocks & Conditions of Allotment through the Screening

    Committee, Ministry of Coal

    Sno. EVENT TIME LIMIT

    in months from '0' date

    1 Allocation 0

    2 Purchase of GR 1.5

    3 Bank Guarantee 3

    4 Mining Lease Application 3

    5 Mining Plan submission 6

    6 Mining Plan approval 8

    7 Previous approval application 11

    8 Previous approval 11

    9 Forest Clearance application 12

    10 Forest Clearance 18

    11 Environment Clearance Application 12

    12 Environment Clearance 18

    13 Mining Lease grant 24

    14 Land acquisition begin 9, 19

    15 Land Acquisition 30, 36

    16 Opening permission application 34, 40 for OC

    17 Opening permission grant 35, 41 for OC

    18 Production 36, 42 for OC

    48, 54 for UG

  • 7/30/2019 Captive Coal Mining Final

    18/22

    18

    Appendix 2: (a) Flowchart of mining proposal approval process

    Source: Mining Approvals in South Australia, Regulatory Guideline No.1 of theDivision of Minerals and Energy Resources, Government of South Australia, June 2007

  • 7/30/2019 Captive Coal Mining Final

    19/22

    19

    Note: PIRSA - Department of Primary Industries and Resources; TRC - Tenement

    Review Committee - PIRSA independent peer review committee for lease application

    assessments; DAC - Development Assessment Commission; EIC - Extractive IndustriesCommittee - a Subcommittee of DAC; EPA - Environment Protection Authority; MARP

    - Mining and Rehabilitation Program; SEB - Significant environmental benefit (offset for

    native vegetation clearance)

  • 7/30/2019 Captive Coal Mining Final

    20/22

    20

    Appendix 2(b) Minimum Timeframe of Process

  • 7/30/2019 Captive Coal Mining Final

    21/22

    21

  • 7/30/2019 Captive Coal Mining Final

    22/22

    Source: Mining Approvals in South Australia, Regulatory Guideline No.1 of the

    Division of Minerals and Energy Resources, Government of South Australia, June 2007