case study: vierendeel truss installation · 2019-06-17 · case study: vierendeel truss...
TRANSCRIPT
Case Study:
Vierendeel Truss Installation
London Bridge Station Redevelopment
The Vierendeel Truss at London Bridge supports the station canopy in the “wedge void” area,
dividing the terminating platforms from the through platforms, and creating a full-height, open area
above the main concourse. This case study reviews the key challenges, programme of works,
methodology and logistics associated with its installation.
Through platforms Terminating platforms
Platform Level Concourse Level
1. Key Challenges
• Programme
• Complex Structure and Methodology
• Logistics
• Limited Space
• Proximity to the operational railway.
2. Programme
• The works commenced at the start of December 2015 with the requirement to have the truss itself
installed before the end of the year to release the installation of the platform 10 staircase and escalator.
• With the majority of fit out trades requiring a dry environment, and with southern concourse opening in
August 2016, the entire roof was required to be installed before end of March 2016.
39m 27m 31m
17.5m
5m
V-column arms RC plinth
Gun column
3. Complex Structure
• The truss itself came in six sections due
to logistics and crane restrictions. This
meant that each section had to be held
in position with temporary support
towers and subsequently welded to its
adjacent pieces.
• The Vierendeel truss is supported by the
two arms of the ‘V’ column mounted on
a massive reinforced concrete plinth via
a bespoke fabricated steel saddle.
• The adjacent roof provides the lateral
support to the slender truss and so
extensive temporary works were required until the roof structure was complete.
• The Vierendeel truss had a precamber designed into it to counter the deflection of its own self weight.
4. Methodology
• It was decided to fabricate and install the Vierendeel
truss in six sections. This was a balance between:
o The maximum benefit of off-site
prefabrication and quality control
o Minimising the number of pieces to reduce
site works and save on programme
o Site logistics and crane restrictions.
• The sections of the truss were supported by six
custom built trestles. Trestle 5 and 6 straddled the
central RC plinth to allow installation of the v-column
arms.
• The trestles were designed to:
o Support the sections of the truss as they are
brought together
o Provide lateral restraint
o Provide a covered working platform to
complete the site welding
o Incorporate a jack to allow sequential dejacking post welding to allow for the precamber of the
truss to fall out.
• Each trestle was based on a large steel grillage which spread the loads into the ground slab. This had to
span over the service trench and other access chambers in some places.
• Each trestle weighed approximately 25 tonnes.
• A complex sequence of roof installation, dejacking of the truss and trestle removal was developed to
ensure the truss remained fully restrained in each phase of the install.
• Glazing of the truss also needed to be carefully coordinated due to access.
• The roof structure came in modularised cassettes to significantly improve programme.
5. Logistics
• All material had to be delivered through existing arches and through areas of piling and foundation
works.
• Swept path analysis was completed to ensure that deliveries could be achieved.
• Special transport frames were created to deliver the steel to deal with both restricted head height and
Highways regulations.
6. Limited Space
▪ At its narrowest, the void is only two metres wide between adjacent structures.
▪ A service trench, over one metre deep, ran through the ground slab adding additional restrictions for
both temporary works and plant loadings.
7. Proximity to the operational railway
▪ Operational platforms and tracks immediately adjacent to work site.
▪ Canopy over platform 10 was restrained by temporary works protruding into work site.
▪ All lifting had to be carefully planned to ensure safety of operational railway whilst minimising restricted
hours working.
Live track and platform
Protruding temporary ties
About the author
Case Study produced by Obi Ozonzeadi, Network Rail Infrastructure Projects Development Manager, October
2018
Further information
For more information on this Learning Legacy case study please email