cesc - karnataka orders/tariff 2017/cesc order.pdf3.3 the gist of the objections, replies by cesc...

257
KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2017 OF CESC ANNUAL PERFORMANCE REVIEW FOR FY16 & REVISION OF ANNUAL REVENUE REQUIREMENT FOR FY18 & REVISION OF RETAIL SUPPLY TARIFF FOR FY 18 11 th April 2017 6 th and 7 th Floor, Mahalaxmi Chambers 9/2, M.G. Road, Bengaluru-560 001 Phone: 080-25320213 / 25320214 Fax : 080-25320338 Website: www.karnataka.gov.in/kerc - E-mail: [email protected]

Upload: others

Post on 28-Jan-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

  • KARNATAKA ELECTRICITY REGULATORY COMMISSION

    TARIFF ORDER 2017

    OF

    CESC

    ANNUAL PERFORMANCE REVIEW FOR FY16

    &

    REVISION OF ANNUAL REVENUE REQUIREMENT FOR

    FY18

    &

    REVISION OF RETAIL SUPPLY

    TARIFF FOR FY 18

    11th April 2017

    6th and 7th Floor, Mahalaxmi Chambers

    9/2, M.G. Road, Bengaluru-560 001

    Phone: 080-25320213 / 25320214

    Fax : 080-25320338

    Website: www.karnataka.gov.in/kerc - E-mail: [email protected]

    http://www.karnataka.gov.in/kerc

  • ii

    C O N T E N T S

    CHAPTER

    Page No.

    1.0 Introduction 3

    1.1 The CESC at a glance 5

    1.2 Number of Consumers, Sales in MU to various

    categories of consumers and details of Revenue

    for FY16

    5

    2 Summary of Filing and Tariff Determination

    Process

    7

    2.0 Background for current filing 7

    2.1 Preliminary Observations of the Commission 7

    2.2 Public Hearing Process 8

    2.3 Consultation with the Advisory Committee of the

    Commission

    8

    3.0 Public consultation – Suggestions / Objections

    and Replies

    9

    3.1 List of persons who filed written objections 9

    3.2 List of persons, who made oral submissions

    during the Public Hearing held on 22.02.2017

    10

    3.3 The gist of the objections, replies by CESC and

    the Commission’s views is appended to this

    order as Appendix-1

    10

    4 Annual Performance Review for FY16 11

    4.0 CESC’s Application for APR for FY16 11

    4.1 CESC’s Submission 11

    4.2 CESC’s Financial Performance as per Audited

    Accounts for FY16

    13

    4.2.1 Sales for FY16 14

    4.2.2 Distribution Losses for FY16 23

    4.2.3 Power Purchase for FY16 24

    4.2.4 RPO Compliance by CESC for FY16 28

    4.2.5 Operation and Maintenance Expenses 30

    4.2.6 Depreciation 34

    4.2.7 Capital Expenditure for FY16 35

    4.2.8 Interest and Finance Charges 46

    4.2.9 Interest on Working Capital 47

    4.2.10 Interest on Consumer Deposit 48

    4.2.11 Other Interest and Finance Charges 49

    4.2.12 Interest on belated payment of power purchase

    cost

    49

    4.2.13 Capitalisation of Interest and finance charges 49

    4.2.14 Other Debits 50

    4.2.15 Net Prior Period Charges 50

    4.2.16 Return on Equity 51

    4.2.17 Income Tax 52

    4.2.18 Other Income 52

    4.2.19 Fund towards Consumer Relations / Consumer 53

  • iii

    Education

    4.2.20 Carrying cost on Regulatory Assets 53

    4.2.21 Revenue for FY16 54

    4.2.22 Revenue and Subsidy for FY16 54

    4.3 Abstract of Approved ARR for FY16 54

    4.3.1 Gap in Revenue for FY16 56

    5.0 Revised Annual Revenue Requirement (ARR) for

    FY18

    57

    5.1 Annual Performance Review for FY16 58

    5.2 Revised Annual Revenue Requirement for FY18 58

    5.2.1 Capital Investments for FY18 58

    5.2.2 Sales forecast for FY18 63

    5.2.3 Distribution Losses for FY18 73

    5.2.4 Power Purchase for FY18 75

    5.2.5 RPO Target for FY18 78

    5.2.6 O & M Expenses for FY18 81

    5.2.7 Depreciation 84

    5.2.8 Interest on Capital Loans 86

    5.2.9 Interest on Working Capital 87

    5.2.10 Interest on Consumer Security Deposit 88

    5.2.11 Other Interest and finance charges 89

    5.2.12 Interest and other charges capitalised 90

    5.2.13 Other Debits & Prior Period Charges 90

    5.2.14 Return on Equity 90

    5.2.15 Other Income 92

    5.2.16 Fund towards Consumer Relations / Consumer

    Education

    92

    5.2.17 Contribution towards Pension and Gratuity Trust 93

    5.3 Abstract of ARR for FY18 94

    5.4 Segregation of ARR into ARR for Distribution

    Business and ARR for Retail Supply Business

    95

    5.5 Gap in Revenue for FY18 97

    6 Determination of Retail supply Tariff for FY18 99

    6.0 CESC’s Proposal and Commission’s Decision for

    FY18

    99

    6.1 Tariff Application 99

    6.2 Statutory Provisions Guiding Determination of

    Tariff

    99

    6.3 Factors considered for Tariff Setting 100

    6.4 New Tariff Proposals by CESC 101

    6.5 Revenue at Existing Tariff and Deficit for FY18 107

    6.6 Wheeling and Banking charges 136

    6.6.1 Wheeling within CESC area 137

    6.6.2 Wheeling of Energy using Transmission Network

    or network of more than one licensee

    139

    6.6.3 Charges for Wheeling of Energy by RE sources

    (non REC route) to consumer in the State

    140

    6.6.4 Charges for Wheeling Energy by RE sources

    wheeling energy from the State to a consumer /

    others outside the State and for those opting for

    140

  • iv

    renewable energy certificate (REC)

    6.6.5 Banking charges and Additional surcharge 140

    6.7 Cross Subsidy Surcharge (CSS) for FY18 140

    6.8 Other issues 143

    6.8.1 Tariff for Green power 143

    6.9 Other Tariff related issues 143

    6.10 Cross subsidy levels for FY18 146

    6.11 Effect of Revised Tariff: 146

    6.12 Summary of Tariff Order 147

    6.13 Commission’s Order 149

    Appendix 150

    Appendix - I 196

  • v

    LIST OF TABLES

    Table

    No.

    Content Page

    No.

    4.1 APR for FY16 – CESC’s Submission 12

    4.2 Financial Performance of CESC for FY16 13

    4.3 CESC’s Accumulated Profits / Losses 14

    4.4 Approved and actual Sales for FY16 15

    4.5 Format for submission of details of IP Set Installations 17

    4.6 Approved and actual Sales for FY16 22

    4.7 Penalty for exceeding targeted loss levels in FY16 24

    4.8 Source wise power purchase during FY16 25

    4.9 Difference between source-wise approved and

    Actual energy Purchase

    26

    4.10 RPO Compliance for FY16 28

    4.11 Non- Solar RPO Compliance 29

    4.12 Solar RPO Compliance 30

    4.13 O & M Expenses –CESC’s submission 31

    4.14 Approved O & M Expenses as per the Tariff Order

    02.03.2015

    31

    4.15 Inflation to be allowed for FY16 32

    4.16 Normative O&M Expenses for FY16 33

    4.17 Allowable O&M Expenses for FY16 33

    4.18 Depreciation for FY16 – CESC’s Submission 34

    4.19 Category wise Capital Expenditure of CESC for FY16 35

    4.20 Division wise summary of sample selection 39

    4.21 Category wise summary of sample selection 40

    4.22 Summary of prudence check results for CESC in FY16 42

    4.23 Gist of prudence check findings for FY16 42

    4.24 Summary of works having cost overrun 43

    4.25 Summary of works having time overrun 43

    4.26 Details of amounts disallowed in APR FY16 44

    4.27 Allowable Interest on capital Loans – FY16 46

    4.28 Allowable Interest on Working Capital for FY16 48

    4.29 Allowable Interest and Finance Charges 49

    4.30 Allowable other Debits 50

    4.31 Status of Debt Equity Ratio for FY16 51

    4.32 Allowable Return on Equity 52

    4.33 Approved Revised ARR for FY16 as per APR 55

    5.1 Revised ARR for FY18 – CESC’s submission 57

    5.2 Capital expenditure for FY18 – CESC’s Submission 60

    5.3 Additional capex sought by CESC 61

    5.4 Approved & Actual capital investment 62

    5.5 Computation of IP Set consumption 70

    5.6 Approved sales for FY18 73

    5.7 Approved and actual Distribution Losses for FY11-16 74

    5.8 Approved Distribution Losses for FY18 75

  • vi

    5.9 Power Purchase Cost as filed by CESC for FY18 75

    5.10 Approved Power Purchase quantum and cost for the

    State

    77

    5.11 Approved Power Purchase cost for CESC for FY18 78

    5.12 Estimated solar RPO for FY18 79

    5.13 Anticipated capacity addition from RE sources 79

    5.14 Anticipated solar capacity and energy during FY17

    and FY18.

    80

    5.15 O & M Expenses for FY18 – CESC’s submission 82

    5.16 Approved O & M Expenses for FY18 as per the Tariff

    Order dated 30th March, 2016

    82

    5.17 Approved O & M Expenses for FY18 84

    5.18 Depreciation – FY18 – CESC’s submission 84

    5.19 Approved Depreciation for FY18 85

    5.20 Interest on Capital Loans – CESC’s submission 86

    5.21 Approved Interest on Loans for FY18 87

    5.22 Approved Interest on Working Capital for FY18 88

    5.23 Approved Interest on Consumer Security Deposits for

    FY18

    89

    5.24 Approved Interest and Finance Charges for FY18 90

    5.25 Status of Debt Equity Ratio for FY18 91

    5.26 Approved Return on Equity for FY18 92

    5.27 Approved Revised ARR for FY18 95

    5.28 Segregation of ARR – FY18 – CESC’s submission 96

    5.29 Approved basis for Segregation of ARR – FY18 96

    5.30 Approved Revised ARR for Distribution Business – FY18 97

    5.31 Approved ARR for Retail Supply Business FY18 97

    5.32 Revenue Gap for FY18 98

    6.1 Revenue Deficit for FY18 107

    6.2 Wheeling Charges 138

  • vii

    LIST OF ANNEXURES

    SL.NO. DETAILS OF ANNEXURES Page

    No.

    I Total Approved Power Purchase Quantum and Cost

    of all ESCOMs for FY18

    210

    II Approved Power Purchase quantum and cost of

    CESC for FY18

    213

    III Proposed and approved Revenue for FY18 216

    IV Electricity Tariff – 2018 217

  • viii

    ABBREVIATIONS

    AAD Advance Against Depreciation

    AEH All Electric Home

    ABT Availability Based Tariff

    A & G Administrative & General Expenses

    ARR Annual Revenue Requirement

    ATE Appellate Tribunal for Electricity

    BST Bulk Supply Tariff

    CAPEX Capital Expenditure

    CCS Consumer Care Society

    CERC Central Electricity Regulatory Commission

    CEA Central Electricity Authority

    CESC Chamundeshwari Electricity Supply Corporation

    CPI Consumer Price Index

    CWIP Capital Work in Progress

    DA Dearness Allowance

    DCB Demand Collection & Balance

    DPR Detailed Project Report

    EA Electricity Act

    EC Energy Charges

    ERC Expected Revenue From Charges

    ESAAR Electricity Supply Annual Accounting Rules

    ESCOMs Electricity Supply Companies

    FA Financial Adviser

    FKCCI Federation of Karnataka Chamber of Commerce & Industry

    FR Feasibility Report

    FoR Forum of Regulators

    FY Financial Year

    GFA Gross Fixed Assets

    GoI Government Of India

    GoK Government Of Karnataka

    GRIDCO Grid Corporation

    HP Horse Power

    HRIS Human Resource Information System

    ICAI Institute of Chartered Accountants of India

    IFC Interest and Finance Charges

    IW Industrial Worker

    IP SETS Irrigation Pump Sets

    KASSIA Karnataka Small Scale Industries Association

    KEB Karnataka Electricity Board

    KER Act Karnataka Electricity Reform Act

    KERC Karnataka Electricity Regulatory Commission

    KM/Km Kilometre

    KPCL Karnataka Power Corporation Limited

  • ix

    KPTCL Karnataka Power Transmission Corporation Limited

    KV Kilo Volts

    KVA Kilo Volt Ampere

    KW Kilo Watt

    KWH Kilo Watt Hour

    LDC Load Despatch Centre

    MAT Minimum Alternate Tax

    MD Managing Director

    MFA Miscellaneous First Appeal

    MIS Management Information System

    MoP Ministry of Power

    MU Million Units

    MVA Mega Volt Ampere

    MW Mega Watt

    MYT Multi Year Tariff

    NFA Net Fixed Assets

    NLC Neyveli Lignite Corporation

    NCP Non Coincident Peak

    NTP National Tariff Policy

    O&M Operation & Maintenance

    P & L Profit & Loss Account

    PLR Prime Lending Rate

    PPA Power Purchase Agreement

    PRDC Power Research & Development Consultants

    REL Reliance Energy Limited

    R & M Repairs and Maintenance

    ROE Return on Equity

    ROR Rate of Return

    ROW Right of Way

    RPO Renewable Purchase Obligation

    SBI State Bank of India

    SCADA Supervisory Control and Data Acquisition System

    SERCs State Electricity Regulatory Commissions

    SLDC State Load Despatch Centre

    SRLDC Southern Regional Load Dispatch Centre

    STU State Transmission Utility

    TAC Technical Advisory Committee

    TCC Total Contracted Capacity

    T&D Transmission & Distribution

    TCs Transformer Centres

    TR Transmission Rate

    VVNL Visvesvaraya Vidyuth Nigama Limited

    WPI Wholesale Price Index

    WC Working Capital

  • x

    KARNATAKA ELECTRICITY REGULATORY COMMISSION,

    BENGALURU - 560 001

    Dated 11th April, 2017

    In the matter of:

    Application of CESC in respect of the Annual Performance Review for FY16,

    Revision of Annual Revenue Requirement for FY18 and Revision of Retail Supply

    Tariff for FY18, under Multi Year Tariff framework.

    Present: Shri M.K. Shankaralinge Gowda Chairman

    Shri H.D. Arun Kumar Member

    Shri D.B. Manival Raju Member

    O R D E R

    The Chamundeshwari Electricity Supply Corporation Ltd., (hereinafter

    referred to as CESC) is a Distribution Licensee under the provisions of the

    Electricity Act, 2003, and has, on 30.11.2016, filed the following

    applications for consideration and orders:

    a) Review of Annual Performance for the financial year 2015-16

    (FY16) and approval of revised ARR thereon.

    b) Approval for revision of ARR for the financial year 2017-18

    (FY18).

    c) Approval for revision of Retail Supply Tariff, for the financial year

    2017-18 (FY18).

  • xi

    In exercise of the powers conferred under Sections 62, 64 and other provisions

    of the Electricity Act, 2003, read with KERC (Terms and Conditions for

    Determination of Tariff for Distribution and Retail Sale of Electricity) Regulations

    2006, as amended and other enabling Regulations, the Commission has

    considered the applications and also the views and objections submitted by

    the consumers and other stakeholders. The Commission’s decisions are brought

    out in the subsequent Chapters of this Order.

  • xii

    CHAPTER – 1

    INTRODUCTION

    1.0 Chamundeshwari Electricity Supply Corporation Limited (CESC):

    The Chamundeshwari Electricity Supply Corporation Ltd., (CESC) is a

    Distribution Licensee under Section 14 of the Electricity Act, 2003

    (hereinafter referred to as the Act). The CESC is responsible for purchase

    of power, distribution and retail supply of electricity to its consumers and

    also for providing infrastructure for Open Access, Wheeling and Banking

    in its area of operation which includes five Districts of the State as

    indicated below:

    1. Mysuru

    2. Hassan

    3. Mandya

    4. Chamarajnagara

    5. Kodagu

    The CESC is a company registered under the Companies Act, 1956,

    incorporated on 19th August, 2004. The CESC commenced its operations

    on 1st April, 2005, with four districts in its area of operation.

    Susequently, the Madikeri Division (Kodagu District) which was earlier

    under the MESCOM, was transferred to the CESC with effect from 1st

    April, 2006.

    At present the CESC’s area of operations is structured as follows:

    CESC, Mysore

    HASSAN

    MANDYA

    KODAGU MYSORE

    CH NAGAR

  • xiii

    O&M Zones O&M Circles O&M Divisions

    Mysore zone

    Mysore Works Circle

    VV Mohalla

    NR Mohalla

    Nanjangud

    Hunsur

    Mysore O&M Circle

    Chamarajnagara

    Kollegala

    Madikeri

    Hassan Circle

    Hassan

    CR patna

    Arasikere

    HN Pura

    Mandya Circle

    Mandya

    Pandavapura

    Nagamangala

    Maddur

    These O & M divisions of the CESC are further divided into sixty one O&M

    sub-divisions with accounting / non-accounting sections and each O&M

    sub division section offices.

    The section offices are the base level offices looking into operation and

    maintenance of the distribution system in order to provide reliable and

    quality power supply to the CESC’s consumers.

  • xiv

    1.1 The CESC at a glance:

    The profile of the CESC is as indicated below:

    *Includes Posts & Personnel on deputation to CESC

    1.2 Number of Consumers, Sales in MU to various categories of

    consumers and details of Revenue for FY16 are as follows:

    CATEGORY

    CESC

    No. of

    Installation

    Sales in

    MU

    Revenue in

    Rs.Crs.

    Domestic 2196013 997.76 420.81

    Commercial 215323 366.75 306.84

    Industrial 38083 886.65 598.54

    Agriculture 317955 2390.44 1051.59

    Others 82665 763.63 478.45

    Total 2850039 5405.23 2856.23

    The CESC has filed its application for Annual Performance Review for FY16,

    Revision of Annual Revenue Requirement (ARR) for FY18 and revision of

    Revision of Retail Supply Tariff for FY18.

    Sl.

    No. Particulars (As on 30.09.2016) Figures

    1. Area Sq. km. 27772.8

    2

    2. Districts Nos. 5

    3. Taluks Nos. 29

    4. Population lakhs 815536

    9

    5. Consumers Lakhs 29.01

    6. Energy Sales MU 2958.56

    7. Zone Nos. 1

    8. DTCs Nos. 100063

    9. Assets (including current

    assets)

    Rs. in Crores 2669.54

    10. HT lines Ckt. kms 49289.1

    4

    11. LT lines Ckt. kms 80600.1

    4

    12. Total employees strength:

    A Sanctioned Nos.* 10428

    B Working Nos.* 5461

    13. Revenue Demand Rs. in Crores 1644.87

    14. Revenue Collection Rs. in Crores 1610.94

  • xv

    The CESC’s application, the objections / views of stakeholders thereon and the

    Commission’s decisions on the application for the Annual Performance Review for

    FY16, Revision of ARR for FY18 and Revision of Retail Supply Tariff for FY18

    are discussed in detail in the subsequent Chapters of this Order.

  • xvi

    CHAPTER – 2

    SUMMARY OF FILING & TARIFF DETERMINATION PROCESS

    2.0 Background for Current Filing:

    The Commission in its Tariff Order dated 30th March, 2016 had approved

    the ARR for FY17 to FY19 and the Revised Retail Supply Tariff of CESC for

    FY17 under the MYT principles for the control period of FY17 to FY19.

    CESC in its present application filed on 30th November, 2016 has sought

    for Annual Performance Review (APR) for FY16 based on the audited

    accounts, Revision of ARR for the second year of the second year of the

    fourth control period i.e. FY18 and revision of Retail Supply Tariff for FY18.

    2.1 Preliminary Observations of the Commission

    After a preliminary scrutiny of the application the Commission had

    communicated its observations to CESC on 20th December, 2016 which

    were mainly on the following points:

    Capital Expenditure

    Sales Forecast

    Assessment of IP set consumption

    Distribution Losses

    Power Purchase

    Issues pertaining to items of revenue and expenditure

    Other new proposals

    Compliance to Directives

    The CESC has furnished its replies on 30th December, 2016. The Commission

    had issued Rejoinders to the replies vide Commission letter dated 10th January,

    2017 and the replies to the Rejoinder were received vide letter dated 16th

    January, 2017. The replies furnished by CESC are considered in the respective

    Chapters of this Order.

    2.2 Public Hearing Process:

    As per the Karnataka Electricity Regulatory Commission (Terms and

    Conditions for Determination of Tariff for Distribution and Retail Sale of

    Electricity) Regulations, 2006, read with the KERC Tariff Regulations, 2000,

    and KERC (General and Conduct of Proceedings) Regulations, 2000, the

  • xvii

    Commission vide its letter dated 04th January, 2017 treated the

    application of CESC as petition and directed CESC to publish the

    summary of ARR and Tariff proposals in the newspapers calling for

    objections, if any, from interested persons.

    Accordingly, CESC has published the same in the following newspapers:

    Name of the News Paper Language Date of Publication

    Deccan Herald English

    06-1-2017 &

    07-1-2017

    The Hindu

    Kannada Prabha Kannada

    Vijayavani

    The CESC’s applications on APR of FY16, Revision of ARR for FY18 and

    revision of retail supply tariff for FY18 were also hosted on the web sites of

    CESC and the Commission for the ready reference and information of the

    general public.

    In response to the application of CESC, the Commission has received thirty

    statements / letters of objections. CESC has furnished its replies to all these

    objections. The Commission has held a Public Hearing on 22nd February, 2017

    at Mysore. The details of the written / oral submissions made by various

    stakeholders and the response from CESC thereon have been discussed in

    Chapter - 3 / Appendix to this Order.

    2.3 Consultation with the Advisory Committee of the Commission:

    The Commission has also discussed the proposals of the KPTCL and all the

    ESCOMs in the State Advisory Committee meeting held on 8th March, 2017.

    During the meeting the following important issues were also discussed:

    Performance of KPTCL / ESCOMs during FY16

    Major items of expenditure of KPTCL / ESCOMs for FY18

    Members of the Committee have offered valuable suggestions on the

    proposals. The Commission has taken note of these suggestions while

    passing the Order.

  • xviii

    CHAPTER – 3

    PUBLIC CONSULTATION - SUGGESTIONS / OBJECTIONS &

    REPLIES

    3.1 AS per the provisions of the section 64 of the Electricity Act, 2003, the

    Commission has undertaken the process of public consultation, to

    invite and suggestions/views/objections from the interested stake-

    holders and general public, on the application filed by CESC for

    Annual Performance Review for FY16, Revision of Annual Revenue

    Requirement for FY18 and Revision of Retail Supply Tariff for FY18. In the

    written submissions filed as well as during the public hearing, the Stake-

    holders and the public have raised several objections/ made

    suggestions, on the CESC Tariff Application. The names of the persons

    who have filed written objections and made oral submissions are given

    below:

    List of persons who filed written objections: -

    Sl

    No

    Applicatio

    n No. Name & Address of Objectors

    1 AE-01 Sri. Prem Chand, Chief Electrical Traction Engineer,

    South Western Railway.

    2 AE-02 Smt. Shroti Bhatia, VP (Regulatory Affairs &

    Communication), Indian Energy Exchange.

    3 CA-01 Sri. K. Krishna Bhat, Koodanahally Estate, Sakaleshpur

    Taluk.

    4 CA-02 Sri. Ravindra B.N & Others, Kollegal taluk.

    5 CA-03 Sri. K.C. Sudarshan, Madikeri, Kodagu.

    6 CA-04 Sri. C.A. Subbaiah, Banangala Village, Kodagu.

    7 CA-05 Laghu Udyog Bharati - Karnataka

    8 CA-06 Sri. Ravindra Prabhu, Chairman, Energy Sub

    Committee, HIEMA.

    9 CA-07 Sri. Prem Chand, Chief Electrical Traction Engineer,

    South Western Railway.

    10 CA-08 Sri. Suresh Kumar Jain, Mysore Industries Association.

    11 CA-09 Sri. Ravindra Prabhu, Vice President, KIAMA.

    12 CA-10 Sri.B. Praveen, Hon’ble General Secretary, KASSIA.

    13 CA-11 to

    CA-22

    Sri. A.B.Yogesh & Others Nanjanagud, Mysuru

    14 CA-23 to

    CA-28

    Sri K.B. Utthappa & Others, Kodagu.

  • xix

    3.2 List of the persons, who made oral submissions during the Public Hearing,

    held on 22.02.2017.

    SL.

    No.

    Names & Addresses of Objectors

    1 Sri. K. Ravindra Prabhu, KIADB Manufacturers Association &

    HIEMA

    2 Sri. S. Sudhakar Shetty, Vice President, FKCCI

    3 Sri. K.B. Lingaraju, Mysore Chamber of Commerce

    4 Sri. Suresh Kumar Jain, Mysore Industries Association

    5 Sri. Mallappa Gowda & Manjunath, KASSIA

    6 Dr. M.R. Rangantha, Bharatiya Kissan Sangha, Mysuru

    7 Sri. Jayakumar, Bharatiya Kissan Sangha, Gundlupet

    8 Sri. Ningaraju, Bharatiya Kissan Sangha, Hunsur

    9 Sri. G.R.Vidyaranya, Aam Admi Party, Mysuru.

    10 Sri. Rajiv, Bharatiya Kissan Sangha, Kodagu

    11 Sri. Chetan Jain, IEX

    12 Smt. Savitha Ranganath, Voluntary Consumer Organizations

    RTI Activist.

    13 Sri. Nagabhushana Aradhya, Mysuru

    14 Sri. Rajendra Ramapura, Bharatiya Kissan Sangha, Kollegal

    15 Sri. Somashekar, Mysuru

    16 Sri. Vasanth. S, Ex-Vice President & All ESCOMS Representative

    & Karnataka State Licensed Electrical Contractors

    Association.

    17. Sri. Ravindra, BJP Ex- District President, Kodagu

    18 Sri. M.A. Poonacha, Kodagu.

    19 Sri. N. Kumaraswamy, Bharatiya Kissan Sangha, Nanjangud.

    20 Sri. Mohammed Arief Khan For V.S ARBATTI for BWSSB

    21 Sri. D. Sagayamani Raj, Division Electric Engr. South Western

    Railways & Sri. D. Soundar Rajan, Dy. Chief Electrical Engineer,

    South Western Railways.

    3.3 The gist of the objections, replies by CESC and the Commission’s views is

    appended to this order as Appendix-1.

  • xx

    CHAPTER – 4

    ANNUAL PERFORMANCE REVIEW FOR FY16

    4.0 CESC’s Application for APR for FY16:

    CESC has filed its application for Annual Performance Review (APR) for

    FY16, revision of Annual Revenue Requirement (ARR) and revision of

    retail supply tariff for FY18 on 30th November, 2016. CESC has sought the

    Annual Performance Review (APR) for FY16 and approval of a revised

    ARR thereon based on the Audited Accounts.

    The Commission in its letter dated 20th December, 2016 had

    communicated its preliminary observations on the application of CESC.

    In its letter dated 30th December, 2016, CESC has furnished its replies to

    the preliminary observations of the Commission. The Commission had

    issued rejoinders on the replies vide letter dated 10th January, 2017 and

    the replies to the rejoinders were furnished by CESC in its letter dated 16th

    January, 2017.

    The Commission in its Multi Year Tariff (MYT) Order dated 6th May, 2013

    had approved CESC’s Annual Revenue Requirement (ARR) for FY14 –

    FY16. Further, in its Tariff Order dated 2nd March, 2015, the Commission

    had approved the APR for FY14 and had revised the ARR along with

    Retail Supply Tariff for FY16.

    During the course of Annual Performance Review (APR) for FY16, revision

    of various items of revenue and expenditure with reference to the

    audited accounts for FY16, are being discussed in this Chapter.

    4.1 CESC’s Submission:

    CESC in its application dated 30th November, 2016, has submitted its

    proposals for revision of ARR for FY16 as follows:

  • xxi

    TABLE – 4.1

    ARR for FY16 – CESC’s Submission Amount in Rs. Crores

    Sl.

    No Particulars As Filed

    1 Energy at Gen Bus in MU 6444.86

    2 Energy at Interface in MU 6256.07

    3 Distribution Losses in % 13.60

    Sales in MU

    4 Sales to other than IP & BJ/KJ 3060.25

    5 Sales to BJ/KJ 38.13

    6 Sales to IP & BJ/KJ 2306.85

    Total Sales 5405.23

    Revenue

    7

    Revenue from other than IP & BJ/KJ and

    Misc. Charges 1814.45

    8 Tariff Subsidy to BJ/KJ 23.82

    9 Tariff Subsidy to IP 1017.96

    Total 2856.23

    Expenditure

    10 Power Purchase Cost 2410.17

    11 Transmission charges of KPTCL 305.42

    12 SLDC Charges 2.16

    Power Purchase Cost including cost of

    transmission 2717.75

    13 Employee Cost 327.65

    14 Repairs & Maintenance 39.24

    15 Admin. & General Expenses 51.58

    Total O&M Expenses 418.47

    16 Depreciation 117.46

    Interest & Finance charges

    17 Interest on Loans 83.52

    18 Interest on Working capital 40.40

    Interest on belated payment of PP Cost 7.05

    19 Interest on consumer deposits 38.07

    20 Other Interest & Finance charges 0.47

    21

    Less: interest & other expenses

    capitalised 19.22

    Total Interest & Finance charges 150.29

    22 Other Debits 4.79

    23 Net Prior period Debit/Credit (5.89)

    24 Return on Equity 0.00

    25 Provision for taxation 14.97

    26

    Funds towards Consumer

    Relations/Consumer Education 0.00

    27 Other Income 105.08

    Net ARR 3312.76

  • xxii

    Considering the revenue of Rs.2856.23 Crores against a net ARR of

    Rs.3312.77 Crores, CESC has reported a gap in revenue of Rs.456.54

    Crores for FY16.

    4.2 CESC’s Financial Performance as per Audited Accounts for FY16:

    An overview of the financial performance of CESC for FY16 as per its

    Audited Accounts is given below:

    TABLE – 4.2

    Financial Performance of CESC for FY16

    Amount in Rs. Crores

    Sl.

    No. Particulars FY16

    Receipts

    1 Revenue from Tariff and misc. charges 1814.45

    2 Tariff Subsidy 1041.78

    3

    Income on account of Regulatory Asset/Truing

    up Subsidy 464.46

    Total Revenue 3320.69

    Expenditure

    4 Power Purchase Cost 2410.17

    5 Transmission charges of KPTCL 305.42

    6 SLDC Charges 2.16

    Power Purchase Cost including cost of

    transmission 2717.75

    7 O&M Expenses 418.48

    8 Depreciation 91.89

    Interest & Finance charges

    9 Interest on Loans 83.52

    10 Interest on Working capital 40.40

    11

    Interest on belated payment of power

    purchase 7.05

    12 Interest on consumer deposits 38.08

    13 Other Interest & Finance charges 0.47

    14 Less; Interest and other expenses capitalized 19.22

    Total Interest & Finance charges 150.30

    15 Other Debits 4.79

    16 Net Prior Period Debit/Credit (5.89)

    17 Other income 79.52

    18 Income tax 14.97

    Total Expenditure 3312.77

  • xxiii

    As per the Audited Accounts, CESC has earned a profit of Rs.7.92 Crores

    for FY16. The profits / losses reported by CESC in its audited accounts in

    the previous years are as follows:

    TABLE – 4.3

    CESC’s Accumulated Profit / Losses

    Particulars Amount in

    Rs. Crs

    Accumulated losses as at the end of FY10 (285.15)

    Profit earned in FY11 11.38

    Losses incurred in FY12 (123.45)

    Losses incurred in FY13 (269.63)

    Losses incurred in FY14 (15.61)

    Profits earned in FY15 40.27

    Profits earned in FY16 7.92

    Accumulated losses as at the end of FY16 (634.27)

    As seen from the above table, the accumulated loss as at the end of

    FY16 is Rs.634.27 Crores.

    APR Exercise by the Commission:

    The Commission has taken up the Annual Performance Review for FY16,

    duly considering the actual revenue and expenditure as per the Audited

    Accounts vis-à-vis the revenue and expenditure approved by the

    Commission, in its Tariff Order dated 2nd March, 2015. The item-wise

    review of expenditure and the decisions of the Commission thereon are

    as discussed in the following paragraphs:

    4.2.1 Sales for FY16:

    a) Sales - other than IP sets:

    Annual Performance Review for FY-16

  • xxiv

    The Commission in its Tariff Order 2015 dated 02.03.2015 had approved

    total sales at 5744.83 MU to various consumer categories, as against the

    proposed sale of 5798.94 MU. The Actual sales of CESC is 5405.24 MU, as

    per the application filed by CESC [D-2 FORMAT], indicating a short fall in

    sales to an extent of 339.59 MU as compared to the approved sales. The

    reduction in sales is 288.66 MU is in LT-categories and 50.93 MU in HT-

    categories. The Commission notes that, as against the approved sales of

    3084.08 MUs to categories other than BJ/KJ and IP sets, the actual sales

    achieved by CESC is 3060.24 MU, resulting in the reduction of sales to

    these categories by 23.84 MU. Further, CESC has sold 2345.00 MU to BJ/KJ

    and IP category against approved sales of 2660.75 MU resulting in

    decreased sales to these categories by 315.75 MU.

    The category-wise sales approved by the Commission in its Tariff Order

    2015 dated 02.03.2015 and the actuals for FY 16 are indicated in the

    table below:

    TABLE-4.4

    Approved and actual Sales for FY16

    Energy in MU

    Category Approved by the

    Commission Actuals Difference

    LT-2a* 959.55 954.37 -5.18

    LT-2b 7.37 7.85 0.48

    LT-3 262.46 259.57 -2.89

    LT-4b 1.17 1.12 -0.05

    LT-4c 11.57 11.59 0.02

    LT-5 137.8 136.56 -1.24

    LT-6 135.53 162.96 27.43

    LT-6 90.66 99.90 9.24

    LT-7 13.66 12.95 -0.71

    HT-1 438.07 420.40 -17.67

    HT-2a 794.17 750.08 -44.09

    HT-2b 127.16 107.17 -19.99

    HT-2c 31.09 45.15 14.06

    HT-3a & b 65.14 82.46 17.32

    HT-4 7.75 5.27 -2.48

    HT-5 0.92 2.84 1.92

    Sub total 3084.08 3060.24 -23.84

    BJ/KJ 36.28 38.13 1.85

    IP 2624.47 2306.87 -317.6

  • xxv

    Sub total 2660.75 2345.00 -315.75

    Grand total 5744.83 5405.24 -339.59

    *Including BJ/KJ installations consuming more than 18 units/month

    The Commission notes that the major categories contributing to the

    reduction in sales are HT Industries (44.09 MU), HT Commercial (19.99 MU)

    and IP sets (317.60 MU). The increase in sales is mainly in respect of LT-6

    water supply installations.

    The CESC has attributed the above variation in sales to the following:

    i. Reduction in IP set sales is due to reduction in the specific

    consumption to 7384 units/year/IP-set as against the approved

    figure of 8195 units/year/IP-set, consequent to segregation of Agri-

    feeders under NJY scheme.

    ii. Reduction in HT-2a sales is due to twelve industries consuming 180.82

    MU under Open Access.

    iii. Increase in sales to LT-water supply is due to servicing of 1252 new

    installations.

    b) Sales to IP sets

    i) In its Tariff Order dated 2nd March, 2015, the Commission had approved

    a specific consumption of IP-sets at 8,195 units/installation/annum for

    FY16, whereas, as per the data of IP-set consumption reported by the

    CESC in its Tariff filing for APR of FY16, the specific consumption works

    out to 7,469 units/installation/annum, which indicates a decrease in

    the specific consumption by 726 units/installation/annum. The total IP-

    set consumption reported for the FY16 is 2,306.87 MU as against

    2,624.47 MU sales quantum approved by the Commission. Thus, the

    specific consumption has decreased by 726 units /installation/annum

    with the corresponding decrease in sales by 317.6 MU when

    compared to the quantity approved by the Commission for the FY16.

    ii) Further, the Commission had approved 3,32,629 as the number of

    installations for FY16, whereas the actual number of installations

    serviced as reported by the CESC is 3,17,674. The difference in number

    of installations between the approved and the actuals reported is

  • xxvi

    14,955. This indicates a decrease of around 4.5 per cent in the number

    of installations serviced, as compared to the approved number of

    installations by the Commission for the FY16. Also, it is noted that the

    shortfall in the sales by 317.6 MU can be attributed to less number of

    installations serviced, when compared to the number of installations

    projected for FY16.

    iii) The Commission in its Tariff Order dated 2nd March, 2015, had

    directed the CESC to furnish feeder-wise IP-set consumption based on

    the 11 kV feeders’ energy meter data, every month, to the

    Commission, in respect of exclusive agricultural feeders segregated

    under NJY scheme considering that the energy consumed by the IP-

    sets can be accurately measured at the 11 kV level at the substations

    after allowing the losses prevailing in the distribution system, as per the

    following format prescribed by the Commission:

    TABLE-4.5

    Format for submission of details of IP set Installations

    Mo

    nth

    Na

    me

    of

    Su

    b-d

    ivis

    ion

    No

    .

    Se

    gre

    ga

    ted

    Ag

    ric

    ultu

    ral

    Fe

    ed

    ers

    in

    th

    e s

    ub

    div

    isio

    n

    Mo

    nth

    ly C

    on

    sum

    ptio

    n in

    MU

    as

    rec

    ord

    ed

    in

    all t

    he

    ag

    ric

    ultu

    ral

    fee

    de

    rs a

    t

    the

    su

    bst

    atio

    ns

    pe

    rta

    inin

    g

    to t

    he

    div

    isio

    n

    Dis

    trib

    utio

    n lo

    ss(1

    1k

    V lin

    e,

    DTC

    s,&

    LT

    lin

    e)

    Plu

    s sa

    les

    to o

    the

    r c

    on

    sum

    ers

    if

    an

    y,

    in M

    U (

    lo

    sse

    s in

    all t

    he

    ag

    ric

    ultu

    ral fe

    ed

    ers

    on

    ly

    to b

    e c

    on

    sid

    ere

    d)

    Ne

    t c

    on

    sum

    ptio

    n d

    uly

    de

    du

    ctin

    g t

    he

    Dis

    trib

    utio

    n

    loss

    (1

    1k

    V &

    LT)

    & a

    ny

    oth

    er

    loa

    ds

    if a

    ny

    No

    . o

    f IP

    se

    ts c

    on

    ne

    cte

    d

    to t

    he

    ag

    ric

    ultu

    ral fe

    ed

    ers

    in t

    he

    su

    bd

    ivis

    ion

    Av

    era

    ge

    co

    nsu

    mp

    tio

    n o

    f

    IP /

    mo

    nth

    (sp

    ec

    ific

    co

    ns

    in u

    nits

    /IP

    /mo

    nth

    )

    Tota

    l n

    o o

    f IP

    se

    ts in

    th

    e

    sub

    div

    isio

    n (

    as

    pe

    r D

    CB

    )

    Tota

    l sa

    les

    of

    IP s

    ets

    in

    MU

    1 2 3 4 5 6=(4-5) 7 8 9 10=8*9

    April to

    March

    Subdivisi

    on-1

    Subdivisi

    on-2

    Subdivisi

    on….

    iv) Considering the fact that the ESCOMs have bifurcated the 11 KV

    feeders into separate rural and agricultural feeders, the Commission

    has adopted the above methodology in the Tariff Order dated 12th

    May, 2014, for FY15, which shall be applicable for all the future

    computations. Prior to this, in the absence of universal metering of IP-

    set installations, the Commission had allowed the ESCOMs to assess

    the IP-set consumption, based on the readings of the sample meters

    fixed to the distribution transformer Centres (DTCs) feeding

  • xxvii

    predominantly IP-set loads. The sample was so selected that in each

    O&M section, two to three DTCs feeding predominantly IP-set loads,

    were covered and in each subdivision, about ten such DTCs were

    covered. As per this methodology, the overall IP-consumption for the

    Company was being assessed on the basis of specific consumption

    arrived at from the metered consumption data of sample meters fixed

    to DTCs.

    v) For instance, as per the IP-set data for FY13 submitted to the

    Commission by the CESC, a total of 798 DTCs covering 7,175 IP-sets out

    of the total 2,55,173 IP-sets in its jurisdiction, were considered for

    assessing the total IP-set consumption for the Company. It is observed

    that the sample IP-sets considered to assess the total IP-

    consumption for FY13, based on the sample DTCs meter readings,

    constituted only 2.8 per cent. Thus, a small number of IP-sets were

    considered for arriving at the total IP consumption, as compared to a

    large sample (39% in March 2016) being considered now after

    segregating the feeders under NJY. Therefore, this would be a better

    representation of sample in terms of metered consumption for

    computing the overall IP-set consumption, as compared to the

    methodology followed earlier.

    vi) Accordingly, the CESC was directed to furnish 11 kV feeder-wise IP-

    set consumption based on energy meters’ reading data in respect of

    agriculture feeders segregated under NJY scheme, duly deducting

    the distribution losses prevailing in 11 kV lines, distribution transformers

    and LT system, to the Commission, every month.

    vii) The CESC in its current tariff filing has submitted the data of IP-sets

    computing the total IP-consumption based on the specific

    consumption in respect of the exclusive agricultural feeders

    segregated under NJY, for FY16. However, as observed from the

    data, there was inconsistency in the number of installations as well as

    the total consumption (computed on the basis of exclusive

    agricultural feeders) between the data submitted to the Commission

  • xxviii

    and the data as reported in D2 format of the Tariff application.

    Further, two different figures of the IP-set consumption based on the

    exclusive agricultural feeders were submitted to the Commission as

    2,024.25 MU and 2,319.576 MU, whereas the consumption reported in

    format D2 of Tariff filing was 2,306.87 MU, indicating a large variation in

    the data submitted to the Commission.

    viii) The Commission in its preliminary observations had directed the CESC

    to justify the IP-set consumption of 2,306.97 MU reported in format D2

    of its Tariff filing with necessary data of segregated agricultural feeders

    in support of the same and also clarify the inconsistency in the

    number of installations as well as consumption data of agricultural

    feeders reported for FY16.

    ix) The CESC, in its reply to the preliminary observations made by the

    Commission, has stated that it has submitted the IP-set consumption

    based on the energy meters’ data in respect of the segregated

    agricultural feeders as desired by the Commission. The CESC while

    submitting the IP-consumption as per the agricultural feeders’ meter

    reading data has reiterated the consumption as 2,024.25 MU and

    2,319.58 MU (two different figures) and the consumption of 2,306.87

    MU as claimed in the format D2 of its tariff filing, for FY16. Thus, the IP-

    consumption of 2,306.87 MU claimed in the Tariff filing was not

    agreeing with the consumption reported on the basis of specific

    consumption arrived at from agricultural feeders’ energy meter data.

    x) Further, the CESC in its replies submitted to the Commission (on the

    Commission’s rejoinder) vide No. CESC/GM(coml.)/F-1/2016-17/19125,

    dated 18.1.2017, has revised the IP-set consumption as 2,077.97 MU

    based on the specific consumption of segregated agricultural

    feeders’ meter reading, for FY16. Also, it has stated that there is still a

    difference between the consumption reported as per Format D-2 of its

    Tariff filing and the agricultural feeders’ meter reading data furnished

    to the Commission due to the following reasons:

  • xxix

    The number of IP-set installations as at the end of March, 2016 were

    3,17,674, whereas the number of IP-sets connected to the bifurcated

    agricultural feeders was only 84,851.

    The consumption in respect of IP-sets in the bifurcated feeders was

    computed on the basis of data from agricultural feeders’ meters,

    whereas in respect of non-bifurcated and rural feeders, the

    consumption was arrived at on the basis of readings from the sample

    meters provided to DTCs predominantly feeding to the IP loads.

    The specific consumption is less in respect of certain agricultural

    feeders in Hunsur division, as the areas covered by these feeders are

    fed by Kaveri and kabini water canals and hence, these figures cannot

    be considered for non-bifurcated feeders.

    For agricultural feeders three-phase power supply is being arranged for

    7 hours as per orders of GoK and in respect of rural feeders, single-

    phase power supply is also arranged in addition to three-phase

    supply. Thus, the consumption of IP-sets in rural and non-bifurcated

    feeders is higher than those in exclusive agricultural feeders.

    The consumption by unauthorized IP-sets has also contributed to the

    difference in IP-set consumption.

    With the above justification, the CESC has requested the Commission to

    consider the sales of IP-sets as 2,306.87 MU as reported in the Format D-2 of

    its Tariff Application for the APR of FY16 and not to consider the revised

    consumption of 2,077.97 MU which was submitted based on the

    agricultural feeders’ meter reading data.

    xi) The reply submitted by the CESC for the difference in IP-set

    consumption is not convincing due to the following reasons:

    a. Even, when 84,851 number of IP-set installations under bifurcated

    feeders, out of total 3,17,67 number of IP-sets as at the end of

    March 2016, are considered, they constitute around 27%, whereas

    the IP-sets connected to DTCs (to which meters are provided)

    feeding predominantly IP-set loads constitutes insignificant

    number of IP-sets. This means the IP-set consumption based on

    specific consumption arrived at from the meter readings data of

    agricultural feeder (larger sample of 27%) needs to be considered

  • xxx

    while computing the IP-set consumption for the entire company,

    instead of considering the readings from the sample meters

    provided to DTCs feeding predominant IP loads, which is based on

    fewer IP-sets data.

    b. As regards lower consumption in Hunsur division due to availability

    of canal water, the division’s average IP-consumption could be

    considered for computation of subdivision-wise IP consumption if

    such a subdivision is not having bifurcated feeders within the same

    division.

    c. Regarding the contention that the IP consumption is more in non-

    bifurcated and rural feeders, compared to bifurcated feeders due

    to supply of single phase power in addition to three-phase power,

    it is noted that the non-bifurcated agricultural feeders are

    supplied with open delta supply/restricted supply with a relay

    arrangement in the feeders at the substations to trip the same if

    current is drawn more than the predetermined values. This would

    even out the difference in power supply position between the

    bifurcated and non-bifurcated feeders and therefore, the

    average values of IP-consumption would be the same in both

    bifurcated and non-bifurcated feeders.

    d. As regards unauthorized IP-sets, the CESC has taken them into

    account, as and when they are identified in the field by

    regularizing them and assigning them with the RR numbers. This

    means, barring a very few installations existing in the field as

    unauthorized, majority of the IP-sets are being accounted for and

    hence the consumption recorded in the exclusive agricultural

    feeders at the substation is inclusive of these unauthorized IP-sets

    also. The specific consumption of IP-sets is arrived at on the basis

    of consumption recorded in the agricultural feeders at substations,

    segregated under NJY, deducting the allowable losses prevailing

    in the 11kV line, distribution transformers and LT line. This means

    that the consumption of unauthorized IP-sets is also reflected in

  • xxxi

    the total consumption recorded in the feeders at the substations.

    Thus, the unauthorized IP-sets existing in the field are being

    accounted for and hence, the contention of the CESC that they

    are contributing to the difference in consumption is not

    acceptable.

    xii) Therefore, as discussed above, the revised IP-consumption submitted

    by the CESC as per the segregated agricultural feeders’ meter

    reading data is 2,077.97 MU and there is a difference of 228.9 MU

    (2,306.87 MU - 2077.97 MU =228.9 MU). In consumption as declared in

    tariff filing. There is no justification for accepting this consumption

    difference of 228.9 MU in consumption as declared in tariff filing.

    Hence, the Commission decides to disallow the consumption of 228.9

    MU from out of 2,306.87 MU claimed by the CESC in its Tariff filing.

    xiii) Accordingly, the Commission decides to approve IP sets sales of

    2,077.97 MU on the basis of the revised meter readings data of

    segregated agricultural feeders reported for the FY16, as against

    2,306.87 MU claimed by the CESC in its Tariff filing, after disallowing

    sales to an extent of 228.9 MU.

    In the light of the above discussion, the Commission approves total sales

    of 5176.34 MU for FY16 and the category-wise sales as indicated in the

    table above:

    TABLE – 4.6

    Approved & Actual Sales for FY16 Million Units

    Category

    Approved as

    per Tariff

    Order dated

    02.03.2015

    Actuals as

    per APR

    LT-2a* 959.55 954.37

    LT-2b 7.37 7.85

    LT-3 262.46 259.57

    LT-4b 1.17 1.12

    LT-4c 11.57 11.59

    LT-5 137.8 136.56

  • xxxii

    LT-6 135.53 162.96

    LT-6 90.66 99.9

    LT-7 13.66 12.95

    HT-1 438.07 420.4

    HT-2a 794.17 750.08

    HT-2b 127.16 107.17

    HT-2c 31.09 45.15

    HT-3a & b 65.14 82.46

    HT-4 7.75 5.27

    HT-5 0.92 2.84

    Sub total 3084.08 3060.24

    BJ/KJ 36.28 38.13

    IP 2624.47 2077.97

    Sub total 2660.75 2116.10

    Grand total 5744.83 5176.34 *Including BJ/KJ installations consuming more than 18 units/month

    4.2.2 Distribution Losses for FY16:

    CESC’s Submission:

    The Commission in its Tariff Order dated 2nd March,2015 had

    approved distribution losses for FY16 as shown in the table below:

    Distribution Loss Range FY16

    Upper limit 15.00%

    Average 14.50%

    Lower Limit 14.00%

    CESC, in its annual accounts, has reported the distribution losses

    at 13.60% for FY16.

    1 Energy at Interface Points in MU 6256.07

    2 Total sales in MU including wheeled

    energy 5405.23

    3 Distribution losses as a percentage of

    input energy at IF points 13.60%

    Commission’s analysis and decisions:

    The distribution loss of 13.60% reported by CESC is below the targeted

    losses fixed by the Commission for FY16 by 0.90% percentage points.

    However, as per the revised consumption of IP sets reckoned as

  • xxxiii

    discussed in the preceding paragraphs of this Chapter, the percentage

    of distribution losses of CESC for FY16 is 17.26%.

    In the above context, the Commission notes that the actual overall

    distribution losses of 17.26% are far beyond the approved upper limit of

    losses for FY16. Hence, penalty for exceeding the targeted loss levels

    has been factored in the APR for FY16 as detailed below:

    TABLE-4.7

    Penalty for exceeding targeted loss levels in FY16 Amount in Rs. Crores

    Particulars FY16

    Actual input at IF points as per audited accounts in

    MU 6256.07

    Retail sales in MU 5176.34

    Percentage distribution losses 17.26%

    Target Upper limit of distribution loss 15.00%

    Increase in loss–in percentage point 2.26

    Input at target loss for actual sales in MU 6089.81

    Increase in input due to increase in distribution losses

    in MU 166.26

    Average cost of power purchase in Rs./unit 4.217

    Increase in power purchase cost due to increase in

    losses in Rs. Crores 70.11

    Thus, the Commission decides to levy penalty of Rs.70.11 Crores for

    exceeding the targeted distribution loss levels for FY16.

    4.2.3 Power Purchase for FY16

    CESC Submission:

    The Commission in its Tariff order dated 30th March,2016, had approved

    source-wise quantum and cost of power purchase for FY16. CESC, in its

    application has submitted the details of actual power purchase for FY16

    for the purpose of Annual Performance Review. The details of power

    purchase are as under:

  • xxxiv

    TABLE – 4.8

    Source-wise Power Purchases during FY16

    * Source : D1 format

    Commission’s analysis and decisions: [

    1. The actual power purchase for FY16 as filed by CESC for approval of

    Annual Performance Review is 6444.86 MU amounting to Rs. 2717.75

    Crores, as against the approved quantum of 6984.52 MU amounting to

    Rs. 2369.15 Crores. This represents reduction in quantum of power

    purchase to an extent of 539.66 MU and increase in the cost by Rs.

    348.57 Crores. This has been reflected in reduced sales to an extent of

    568.50 MU in FY16.

    Source of Generation

    Actuals for FY16 Approved for FY16 Difference-between Actuals

    and Approved-for FY16

    % increase

    (+)/decrease (-)

    over an

    approved figures

    Energy

    in MUs

    Cost in

    Rs Cr.

    Rate in

    Rs per

    Unit

    Energy

    in MUs

    Cost in

    Rs Cr.

    Rate in Rs

    per Unit

    Energy

    in MUs

    Cost in

    Rs Cr.

    Rate in

    Rs per

    Unit

    Energy Cost

    KPCL Hydel

    Stations

    1030.87 114.81 1.11 1829.66 91.50 0.50 -798.79 23.29 0.61 -43.66 25.45

    KPCL-

    Thermal

    Stations

    1313.99 593.48 4.52 1826.26 715.70 3.92 -512.27 -122.22 0.60 -28.05 -

    17.08

    CGS 1724.1 539.44 3.13 1549.83 465.73 3.01 174.27 73.71 0.12 11.24 15.83

    Major IPPs 991.82 415.36 4.20 970.19 400.92 4.13 21.63 15.44 0.07 2.23 3.85

    IPPs -Minor

    (NCE

    Projects)

    469.92 167.47 3.56 627.97 235.47 3.75 -158.05 -68.00 -0.19 -25.17 -

    28.88

    Other

    States

    Projects

    4.78 8.13 17.01 21.26 3.83 1.80 -16.48 4.30 15.21 -77.52 112.2

    7

    Short

    /Medium

    term

    480.62 249.24 5.19 159.35 83.66 5.25 321.27 165.58 -0.06 201.61 197.9

    2

    U I charges 66.74 20.36 3.05

    66.74 20.36

    Sec-11 331.48 168.25 5.08

    331.48 168.25

    Transmissio

    n Charges

    (KPTCL &

    PGCIL)

    414.65

    368.78

    45.87

    SLDC

    Charges

    (POSOOC&

    SLDC)

    2.16

    3.57

    -1.41

    Energy

    Balancing 30.54 21.21 6.94

    Others

    Charges 2.19

    TOTAL 6444.86 2717.75 4.22 6984.52 2369.15 3.39 -539.66 348.57 0.82 -7.73 14.71

  • xxxv

    2. Against the approved quantum of 6984.52 MU, the actual power

    purchased by CESC is 6444.86 MU for FY16, which is about 7.73% less than

    the approved quantum.

    3. On an analysis of the source-wise approved and actual power

    purchases, the following deviations in the quantum of energy and its

    cost of purchase are observed:

    i. There is shortfall in supply from sources of power like KPCL Hydel, KPCL

    Thermal and IPP minor (RE/ NCE) as follows:

    TABLE-4.9

    Difference between Source-wise approved and Actual Energy Purchase

    Source of Generation

    Energy Difference

    between actual

    and approved in

    MU

    Cost Difference

    between actual

    and approved in

    Rs Cr.

    KPCL Hydel - 798.79* 23.29

    KPCL Thermal -512.27* -122.22**

    IPP Minor(RE/NCE ) -158.05* -68.00**

    * (-) indicates deficit **(-) indicated excess cost

    The shortfall from the conventional sources has been met from the

    un-requisitioned surplus power from CGS & major IPP sources apart from

    short-term power to a tune of 480.62 MU at a cost of Rs.249.24 Crores.

    CESC has incurred an additional cost Rs.348.57 Crores towards overall

    deficit in the availability of power, resulting in an increase in per unit cost

    by 82 Paise.

    ii. The change in the source-wise mix of supply, reconciliation of energy

    and its cost among ESCOMs have resulted in higher average power

    purchase cost of CESC at the rate of Rs.4.22 per KWh as against the

    approved rate of Rs.3.39 per KWh.

    4. In order to ensure proper accounting of energy and its cost, CESC is

    directed to reconcile the inter-ESCOM energy exchanges and its costs

  • xxxvi

    every month and it shall collect/pay the corresponding amounts out of

    the tariff subsidy received from Government of Karnataka,

    5. The Commission notes that, the SLDC has not implemented the intra-state

    ABT. As per the directions issued by the Government of Karnataka vide

    its letter dated 28th January, 2016, intra state ABT has to be

    implemented immediately by the KPTCL and ESCOMs. The Commission

    therefore directs the SLDC, KPCL and the CESC to take appropriate

    action immediately to implement intra-state ABT and to host the details

    thereof, on their respective websites.

    6. The power purchases made by the CESC during FY16 from different

    sources of generation also include the energy purchased under Section

    11 of the Electricity Act, 2003, in pursuance of the Government Order

    dated 16.09.2015. The Government, in the said order, had fixed a

    provisional tariff of Rs.5.08 Per unit subject to determination of final tariff

    by this Commission. The Commission in its order dated 18th August,2016,

    has fixed the final tariff of Rs.4.79 per unit and has ordered recovery of

    the difference amount (Rs.5.08- 4.79) from the generators. However,

    some of the generators have filed petitions before the Hon’ble ATE.

    Some of the generators have also filed review petitions before this

    Commission. The Hon’ble ATE has ordered not to recover the difference

    amount pending disposal of the petitions. Hence the power purchase

    cost allowed in this order is subject to the decision of the Hon’ble ATE

    and also this Commission.

    7. On analysis of Power Purchase cost for FY16 in respect of KPCL Hydel

    Stations, it is observed that the rates allowed per unit by ESCOMs, varies

    among ESCOMs as given bellow:

    BESCOM Rs 0.90 per unit.

    MESCOM Rs 1.45 per unit.

    CESC Rs 1.11 per unit.

    HESCOM Rs 0.91 per unit.

    GESCOM Rs 0.97 per unit.

  • xxxvii

    CESC has allowed Rs.1.11 per unit, which indicates that while making

    payment of the power purchase bills, adequate checks have not been

    exercised. In FY15 the power purchased by ESCOMs from KPCL Hydel is

    as under:

    BESCOM Rs 0.57 per unit.

    MESCOM Rs 0.56 per unit.

    CESC Rs 0.58 per unit.

    HESCOM Rs 0.56 per unit.

    GESCOM Rs 0.59 per unit.

    It is seen from the above that there is no significant variation in the rates

    allowed in FY15 among the ESCOMs, as compared with the rates paid in

    FY16. There should be justifiable reasons for the variations, which are not

    available in the tariff applications.

    In the light of this, CESC is directed to verify correctness of the payment

    made by it at the rate of Rs.1.11 per unit to KPCL Hydel power. The

    excess payment, if any, may be recovered from KPCL under intimation

    to the Commission.

    The Commission decides to approve the power purchase of 6444.86 MU

    at a cost of Rs.2717.75 Crores for the purpose of Annual Performance

    Review for FY16.

    4.2.4 Renewable Purchase Obligation (RPO) compliance by CESC for FY16:

    CESC in the petition has filed the details of RPO compliance for solar and

    non-solar RPO for 2015-16 as indicated below:

    TABLE-4.10

    RPO Compliance for FY16

    Energy Purchased-MU 6444.86

    Non-Solar energy required to be procured at 10% target-

    MU

    644.49

    Non-Solar energy actually procured excluding energy sold

    under green tariff -MU

    723.73

  • xxxviii

    Non-Solar compliance as percentage of energy purchased 11.23%

    Solar energy required to be procured at 0.25% target-MU 16.11

    Solar energy actually procured -MU 25.22

    Solar compliance as percentage of energy purchased 0.39%

    For validating the RPO compliance, the Commission had directed CESC

    to furnish the data as per a specified format, duly reconciling the data

    with audited accounts.

    CESC in their replies have furnished the following data:

    TABLE-4.11

    Non-solar RPO Compliance

    No. Particulars Quantum

    in MU

    Cost-

    Rs.Crores.

    1 Total Power Purchase quantum

    from all sources

    6444.85 2717.75

    2 Non–solar Renewable energy

    purchased under PPA route at

    Generic tariff including Non-

    solar RE purchased from KPCL

    457.39 158.17

    3 Non –solar Short-Term purchase

    from RE sources, excluding sec-

    11 purchase

    127.55 65.47

    4 Non –solar Short-Term purchase

    from RE sources under sec-11

    138.63 70.36

    5 Non-solar RE purchased at

    APPC

    0 0

    6 Non-solar RE pertaining to

    green energy sold to

    consumers under green tariff

    0 0

    7 Non-solar RE purchased from

    other ESCOMs

    0 0

    8 Non-solar RE sold to other

    ESCOMs

    0 0

    9 Non-solar RE purchased from

    any other source like banked

    energy purchased at 85% of

    Generic tariff

    0.16* 0.06

    10 Total Non-Solar RE Energy

    Purchased

    [No 2+ No.3+No.4+No.5

    +No.7+No.9]

    723.73

    11 Non-Solar RE accounted for

    the purpose of RPO

    0

  • xxxix

    [ No.10- No.5-No.6-No.8]

    12 Non-solar RPO complied in %

    [No11/No1]*100

    11.23

    * As per the breakup details furnished, it is 0.48 MU, which is reckoned for the Purpose of RPO.

    TABLE-4.12

    Solar RPO Compliance

    No. Particulars Quantum

    in MU

    Cost- Rs.

    Crs.

    1 Total Power Purchase quantum from all

    sources

    6444.85 2717.75

    2 Solar energy purchased under PPA route

    at Generic tariff including solar energy

    purchased from KPCL

    12.65 9.31

    3 Solar energy purchased under Short-

    Term, excluding sec-11 purchase

    0 0

    4 Solar Short-Term purchase from RE under

    sec-11

    0 0

    5 Solar energy purchased under APPC 0 0

    6 Solar energy pertaining to green energy

    sold to consumers under green tariff

    0 0

    7 Solar energy purchased from other

    ESCOMs

    0 0

    8 Solar energy sold to other ESCOMs 0 0

    9 Solar energy purchased from NTPC (or

    others) as bundled power

    12.56 13.51

    10 Solar energy purchased from any other

    source like banked energy purchased at

    85% of Generic tariff

    0 0

    11 Total Solar Energy Purchased

    [No2+No.3+No.4+No.5+No.7+No.9+No.10]

    25.22 22.82

    12 Solar energy accounted for the purpose

    of RPO [ No.11- No.5-No.6-No.8]

    0 0

    13 Solar RPO complied in %

    [No12/No.1]*100

    0.39

    The Commission has approved total input energy of 6444.86 MU for FY16

    in its APR. Based on this input energy, CESC was required to purchase

    644.49 MU of Non-Solar energy and 16.11 MU of solar energy to meet its

    RPO targets. Considering the data submitted by CESC, the Commission

    notes that CESC has achieved 11.23% of Non-Solar and 0.39% of solar

    RPO targets for FY16. Thus, CESC has over-achieved its non-solar and

    solar RPO targets by 1.23 percentage points and 0.14 percentage points

    respectively.

  • xl

    4.2.5 Operation and Maintenance Expenses:

    CESC’s Submission:

    In its application, the CESC, as per its audited accounts, has

    requested to approve O&M expenses of Rs.418.47 Crores for FY16.

    The break-up of O&M expenses are as follows:

    TABLE – 4.13

    O & M Expenses – CESC’s submission

    Amount in Rs. Crores

    Particulars FY16

    Employee cost

    327.65

    Administrative & General Expenses 51.58

    Repairs and Maintenance 39.24

    Total O & M Expenses 418.47

    Commission’s analysis and decisions:

    The Commission in its Tariff Order dated 2nd March, 2015 had approved

    O&M expenses for FY16 as detailed below:

    TABLE – 4.14

    Approved O&M Expenses as per Tariff Order dated 02.03.2015

    Particulars FY16

    No. of installations as per actuals as per Audited

    Accts 2864790

    Weighted Inflation Index 6.69%

    CGI based on 3 Year CAGR 4.12%

    Actual O&M expenses for FY13 - in Rs. Crs. 326.07

    Total approved O&M Expenses for FY16 – in Rs. Crs. 409.15

    The Commission in its preliminary observations, on the application of

    CESC, had sought the details of the certain expenses booked under A &

    G expenses during FY16 and noted the replies furnished.

    The Commission notes that the actual O&M expenses reported by CESC

    are more than the approved O&M expenses by Rs.9.32 Crores. The

    Commission, in accordance with the methodology adopted while

    approving the ARR for FY14-16 and subsequent APRs, proceeds with the

    determination of normative O&M expenses based on the 12 Year data

    of WPI and CPI besides considering 3 year compounded annual growth

    rate (CAGR) of consumers. Considering the Wholesale Price Index (WPI)

  • xli

    as per the data available from the Ministry of Commerce & Industry,

    Government of India and Consumer Price Index (CPI) as per the data

    available from the Labour Bureau, Government of India and adopting

    the methodology followed by the CERC with CPI and WPI in a ratio of

    80:20, the allowable rate of inflation for FY16 is computed as follows:

    TABLE-4.15

    Inflation to be allowed for FY16

    Year WPI CPI

    Compo

    site

    Series

    Yt/Y

    1=Rt Ln Rt

    Year

    (t-1)

    Product

    [(t-1)*

    (LnRt)]

    2004 98.72 111.1 108.624

    2005 103.37 115.8 113.314 1.04 0.04 1 0.04

    2006 109.59 122.9 120.238 1.11 0.10 2 0.20

    2007 114.94 130.8 127.628 1.17 0.16 3 0.48

    2008 124.92 141.7 138.344 1.27 0.24 4 0.97

    2009 127.86 157.1 151.252 1.39 0.33 5 1.66

    2010 140.08 175.9 168.736 1.55 0.44 6 2.64

    2011 153.35 191.5 183.87 1.69 0.53 7 3.68

    2012 164.93 209.3 200.426 1.85 0.61 8 4.90

    2013 175.35 232.2 220.83 2.03 0.71 9 6.39

    2014 182.00 246.90 233.92 2.15 0.77 10 7.67

    2015 177.03 261.42 244.542 2.25 0.81 11 8.93

    A= Sum of the product column 37.56

    B= 6 Times of A 225.37

    C= (n-1)*n*(2n-1) where n= No of years of data=12 3036.00

    D=B/C 0.07

    g(Exponential factor)= Exponential (D)-1 0.0771

    e=Annual Escalation Rate (%)=g*100 7.71

    For the purpose of determining the normative O & M expenses for FY16,

    the Commission has considered the following:

    a) The actual O & M expenses allowed for FY13 excluding contribution

    to Pension and Gratuity Trust.

    b) The three year compounded annual growth rate (CAGR) of the

    number of installations considering the actual number of installations

    as per the audited accounts up to FY16 at 3.92%.

    c) The weighted inflation index (WII) at 7.71% as computed above.

    d) Efficiency factor at 2 % as considered in the earlier two control

    periods.

  • xlii

    Thus, the normative O & M expenses for FY16 will be as follows:

    TABLE – 4.16

    Normative O & M Expenses for FY16

    Particulars FY16

    No. of Installations As per actuals as per Audited Accts 2848206

    Weighted Inflation Index 7.71%

    Consumer Growth Index (CGI) based on 3 Year CAGR 3.92%

    Base year actual O & M expenses for FY13 excluding

    P&G contribution - Rs. Crores 270.60

    O&M Index= 0&M (t-1)*(1+WII+CGI-X)- Rs. Crores. 349.27

    The above normative O & M expenses have been computed without

    considering the contribution to Pension and Gratuity Trust for FY16.

    The Commission has treated the employee costs on account of

    contribution to P&G Trust as uncontrollable O&M expenses. This

    component has been allowed beyond the normative O&M expenses to

    enable the ESCOMs to meet their actual employee costs.

    CESC, as per the audited accounts has incurred an amount of Rs.64.31

    Crores towards contribution to Pension and Gratuity Trust for FY 16.

    Considering the request of CESC to treat the pension and gratuity

    contribution as uncontrollable O & M expenses, the Commission

    computes the allowable O & M expenses for FY16 as follows:

    TABLE – 4.17

    Allowable O & M Expenses for FY16 Amount in Rs. Crores

    Sl.

    No. Particulars FY16

    1 Normative O & M expenses 349.27

    2 Additional employee cost (uncontrollable O & M

    expenses)

    64.31

    Allowable O & M expenses for FY16 413.58

    Thus, the Commission decides to allow an amount of Rs.413.58 Crores as

    O&M expenses for FY16.

  • xliii

    4.2.6 Depreciation:

    CESC’s Submission:

    CESC, in its application has claimed an amount of Rs.117.46 Crores as

    gross depreciation as per the audited accounts. Further, an amount of

    Rs.25.57 Crores towards the depreciation on account of assets created

    out of consumers’ contributions / grants as per Accounting Standards

    (AS) – 12, is considered under other income as per the Audited Accounts

    for FY16. Thus the net amount of depreciation claimed by the CESC in its

    tariff application is Rs. 91.89 Crores for FY16.

    The asset-wise depreciation claimed by the CESC is as follows:

    TABLE – 4.18

    Depreciation for FY16- CESC’s Submission

    Amount in Rs. Crores

    Particulars

    Opening Balance

    of Asset as on

    01.04.2015

    Closing Balance

    of Asset as on

    31.03.2016

    Depreciation

    for FY16

    Buildings 58.81 70.53 2.27

    Civil 1.79 1.93 0.10

    Other Civil 0.72 0.72 0.02

    Plant & M/c 432.87 575.16 29.77

    Line, Cable

    Network

    1505.59 1926.79 84.62

    Vehicles 4.38 4.38 0.09

    Furniture 3.90 4.23 0.19

    Office

    Equipment

    5.18 9.56 0.39

    Intangible

    assets

    2.17 2.16 0.01

    Sub Total 2015.41 2595.45 117.46

    Less: Depreciation on account of Assets created out

    of Consumer contribution/grants

    25.57

    Net Depreciation 91.89

  • xliv

    Commission’s analysis and decisions:

    In accordance with the provisions of the KERC (Terms and Conditions for

    Determination of Tariff for Distribution and Retail Sale of Electricity)

    Regulations, 2006 and amendments thereon, the depreciation for FY16

    has been determined by the Commission. Based on the opening and

    closing balances of gross blocks of fixed assets for FY16 and the

    depreciation as per audited accounts, the weighted average rate of

    depreciation works out to 5.09%. Further, as per the Accounting

    Standards (AS) – 12, an amount of Rs.25.57 Crores of depreciation on

    assets created out of consumer contribution / grants has been factored

    in and deducted from the gross depreciation for FY16.

    Based on the above, the Commission decides to allow net depreciation

    of Rs.91.89 Crores for FY16.

    4.2.7 Capital Expenditure:

    I. Capital Investment for FY16

    CESC’s submission:

    The CESC has indicated an actual capital expenditure of Rs.488.52

    Crores as against the Commission approved capital expenditure of

    Rs.317 Crores for FY16. The category-wise breakup of the expenditure

    furnished by CESC is shown in the table below:

    Table -4.19

    Category wise capital expenditure of CESC for FY16

    Amount in Rs. Crores

    Sl.

    No Schemes

    FY16 As

    approved

    FY16

    Actuals

    1 Extension & improvement 80 75.76

    2 NJY 50 247.53

    3 HVDS 20 -

    4 R-APDRP 50 21.23

    5 RGGVY(Restructured)+DDG 0 0.66

    6 Replacement of failed

    Transformers 10 5.00

    7 Service Connections 40 25.76

  • xlv

    8 Rural Electrification(General) - -

    A Electrification of Hamlets/HB/JC

    under RGGVY

    10 87.09 B

    Providing infrastructure to

    Irrigation Pump sets

    &energization of IP SETS

    C Kutir Jyothi(RGGVY)

    9 Tribal Sub Plan - -

    A Electrification of Tribal Colonies

    (RGGVY) 3 2 B Energization of IP sets

    C Kutir Jyothi (RGGVY)

    10 Special Component Plan - -

    A Electrification of

    HB/JC/AC(RGGVY)

    10 6 B Energization of IP sets

    C Kutir Jyothi(RGGVY)

    11 Tools & Plants 4 8.40

    12 Civil Engineering Works 10 9.10

    13

    Providing Meters to DTC, BJ/KJ,

    Street Light for replacement of

    electromechanical meters,

    providing modems to meters for

    communication

    30 0.00

    Total 317.00 488.52

    Commission’s analysis:

    The Commission notes that, the overall capital expenditure of Rs.488.52

    Crores incurred by CESC for FY16 has exceeded the approved capex of

    Rs.317 Crores by Rs.171.52 Crores. Some of the major categories in which

    CESC has exceeded the capex are as follows:

    i. The CESC has exceeded the approved capex limit of Rs. 50 Crores in

    “NJY program” by Rs.197.52 Crores. CESC in its replies to preliminary

    observations, has stated that, due to field constraints like Right of

    Way (RoW) and objections to lay the lines by the people, the project

    that were taken up in previous years were delayed and the

    expenditure was not booked during the previous years. During FY16

    majority of NJY feeders have been completed and billed, resulting in

    excess capex.

  • xlvi

    ii. In respect of “HVDS” works, it is stated that CESC has not utilized the

    approved capex of Rs.20 Crores, for the reason that, the ongoing

    NJY works and providing individual transformers to Ganga Kalyana IP

    Set works would render the same benefit as that of HVDS. Further,

    CESC in its replies to preliminary observations has stated that, the NJY

    Phase-I and Phase- II works cover a huge area in its jurisdiction in

    which it has increased the number of distribution transformers and

    also, it has installed individual DTCs for each of the Ganga Kalyana

    works, and hence, the HVDS is not required to be implemented.

    Though CESC has taken this stand, it is to be noted that the NJY

    program or the individual DTC for Ganga Kalyana would not result in

    the conversion of already existing lengthy LT lines emanating from

    the 11 kV feeder both in rural loads as well as for IP Sets to HT lines.

    Since the HVDS scheme is meant to reduce the HT/LT ratio, the

    Commission directs CESC to take up a study of the existing

    distribution lines and take suitable action to implement HVDS in order

    to reduce the LT lines.

    iii. In respect of “Rural Electrification (General)”, CESC has achieved a

    capex of Rs.77.09 Crores, over and above the approved capex of

    Rs.10 Crores. CESC in its replies to preliminary observations has

    stated that, these works are related to social obligation and are

    Government’s priority works and hence, CESC has incurred excess

    capex for completion of these works.

    iv. In respect of “Tools & Plants”, CESC has achieved a capex of Rs.8.4

    Crores against the approved capex of Rs.4 Crores. CESC in its replies

    to the preliminary observations made by the Commission has stated

    that, three phase energy meter testing bench, PGRS software has

    been procured during FY16. Further, it has stated that, some of the

    T& P materials which were ordered in FY15 have been billed during

    FY16 resulting in excess capex.

    v. In respect of “Providing Meters to DTC, BJ/KJ, Street Light for

    replacement of electromechanical meters, providing Modems to

  • xlvii

    meters for communication”, CESC has incurred a very meager

    /negligible capex of Rs.0.0019 Crore against the approved capex of

    Rs.30 Crores. The Commission has been directing CESC to complete

    DTC metering and conduct energy audit to quantify the distribution

    losses and take remedial measures thereon. But, CESC has not

    achieved its own set targets in the above category. CESC in its

    replies to the preliminary observations made by the Commission has

    stated that, there was a delay in tendering process due to delay in

    finalization of the technical specifications, due to which it could not

    achieve the progress in FY16.

    In the light of the above discussion on excess capex and considering the

    reasons furnished by CESC, the Commission decides to recognize the

    capital expenditure of Rs.488.52 Crores incurred by CESC for APR of FY16,

    subject to disallowance if any, as per the prudence check for FY16,

    indicated in the following paras.

    II. The prudence check of capital expenditure and material procurement

    of CESC for FY16:

    The Commission has got the Prudence check of capital expenditure for

    FY16, done through third party verification of the capital works

    categorized and also the material procurement of CESC during FY16.

    This was taken up in two parts:

    a) Prudence check of execution of the capital works of FY16:

    b) Prudence check of material procurement process of FY16:

    a) Prudence check of execution of the capital works of FY16:

    The Commission has taken up prudence check of the capital

    expenditure incurred by the CESC for the period FY16 by engaging the

    services of M/s. Pricewaterhouse Coopers Private Limited, (M/s PWC) as

    consultant, being the lowest bidder for the said job, through a

    transparent process of e-tendering to evaluate the capital expenditure

    incurred during FY16, in respect of categorized works.

  • xlviii

    The Consultant has taken a list of division-wise and cost-wise total Capex

    works carried out, categorized in the CESC during FY16. As per the scope

    of work, the sampling technique of stratified random sampling for

    finalizing the sample of projects as per KERC guidelines was taken up.

    Total number of works of CESC in category of more than Rs.6 lakhs and

    between Rs.3 lakhs to Rs.6 lakhs were much higher and exceeding the

    maximum limit of sample size specified in the KERC guidelines. Therefore,

    120 works and 50 works have been selected from each category of

    projects more