delay analysis

46
DELAYS & DELAY ANALYSIS

Upload: toby-hunt

Post on 08-Aug-2015

98 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: Delay Analysis

DELAYS &

DELAY ANALYSIS

Page 2: Delay Analysis

• Change happens…

• Events occur that require a Contractor’s planned intent for

executing the works to be changed.

• Delays:

• Delay to progress.

• Delay to completion.

DELAYS AND DELAYING EVENTS

Page 3: Delay Analysis

• Step 1: (Analysis of Facts)

• Identify that an event has occurred.

• Step 2: (Analysis of Facts)

• Show that the event affects progress of the works.

• Step 3: (Delay Analysis)

• Demonstrate that this delay to progress causes a delay to completion.

CAUSATION

Page 4: Delay Analysis

• Planned programme:

• Accepted programme update

TIME EFFECT OF AN EVENT - PLAN

Page 5: Delay Analysis

• Condition 1:

• The event causes no delay to progress and no delay to completion.

TIME EFFECT OF AN EVENT - 1

Planned Completion

Page 6: Delay Analysis

• Condition 2:

• The event causes a delay to progress but no delay to completion.

TIME EFFECT OF AN EVENT - 2

Planned Completion

Page 7: Delay Analysis

• Condition 3:

• The event causes a delay to progress and a delay to completion.

TIME EFFECT OF AN EVENT - 3

Planned Completion 1

Planned Completion 2

Page 8: Delay Analysis

• Impact of different types of delay event.

• Impact of prospective and retrospective perspectives on the

calculation of delay to completion.

• Principles of Delay Analysis

INTRODUCTION TO DELAY ANALYSIS

Page 9: Delay Analysis

COMPONENTS

• Programme

• Events

• Progress Records/As-built

• Contract requirements

• Other supporting evidence

Page 10: Delay Analysis

• Seek agreement • What does the contract say?

– Likely or Actual delay to completion – Method Specified

• What is to be proved? – EOT or compensation or both

• What materials are available? – Availability and Integrity of an As-Planned

Programme , progress and/or As-Built Data; • Limitations on budget and time? • Complexity of Works in question • Proportionality

– Small disputes do not justify expensive and time consuming analyses

CHOOSING A METHOD

Page 11: Delay Analysis

CONTRACT TERMS

- "If the Contractor is or is likely to be unavoidably delayed in achieving a completion obligation or milestone ... either prospectively or retrospectively the time ... shall be extended“

- "... an extension of time ... shall be subject to the requirement that ... the event was the operative cause of the delay suffered ...“

• Likely to cause delay?

• Likely to cause or has caused delay?

• Has caused delay?

• To what?

• In relation to what?

Page 12: Delay Analysis

WHAT IS TO BE PROVED

• The prospective likely effect on the completion date for the purposes of an interim EOT

• A retrospective actual effect on completion for the purpose of an EOT

• A contemporaneous or retrospective actual effect on progress for the purposes of compensation for disruption

• A retrospective actual effect on the contractor’s overheads for the purpose of prolongation

Page 13: Delay Analysis

Retrospectively create a CPM programme

CPM ? As-Planned

Impacted

Programme available?

As built records available?

Updated with progress ?

Recovery or acceleration ?

As-Planned –v-

As-Built

Retrospectively create a

simulated as-built CPM

programme

As-Built But-For

Time-Impact

Illustrates the effect of an Event on the chosen

programme

Measures the effect of an Event on completion in the sequence of construction finally followed

Measures the effect of an event on completion by tracing the critical

path through change in intent

Measures the difference between planned and

actual activity durations

MATERIALS AVAILABLE

Page 14: Delay Analysis

PROPORTIONALITY

• Quick, cheap and tend to be rough

–As-planned v as-built

–As-planned impacted

• Time consuming, costly and tend to be thorough

–As-built But-for

–Time impact

Page 15: Delay Analysis

• Disregard labels, identify what is done.

• AACE International Recommended Practice No. 29R-03

METHOD

Page 16: Delay Analysis

AACEI RP 29R-03: FORENSIC SCHEDULE ANALYSIS

Table 1 – Nomenclature Correspondence (page 11)

ADVANTAGES & DISADVANTAGES

NOT PREFERENCE … OR PREJUDICE!

Page 17: Delay Analysis

• AACE International Recommended Practice No. 29R-03 Section 3

• OBSERVATIONAL

• STATIC LOGIC • GROSS1: As-Planned vs As-Built

• PERIODIC2: As-Planned vs As-Built (‘in windows’)

• DYNAMIC LOGIC • CONTEMPORANEOUS UPDATES: As-Planned vs As-Built in windows

• RE-CONSTRUCTED UPDATES: As-Planned vs As-Built in windows

• MODELLED

• ADDITIVE • SINGLE BASE: Impacted As-Planned

• MULTIPLE BASE: Time Impact Analysis / Snapshot

• SUBTRACTIVE • SINGLE SIMULATION As-Built But For / Collapsed As-Built

• MULTI SIMULATION As-Built But For

METHOD IMPLEMENTATION

Page 18: Delay Analysis

PROSPECTIVE V RETROSPECTIVE (WHEN?)

• Prospective:

–During currency of project

–Per SCL Protocol

–Contract requirement (e.g. NEC)

–Avoid disputes

• Retrospective:

–During currency of project (after the event)

–Claim preparation

–Dispute resolution (expert analysis)

Page 19: Delay Analysis

PROSPECTIVE V RETROSPECTIVE (HOW?)

• Prospective:

–Forward looking e.g. As-planned impacted, Time Impact

• Retrospective:

–Backward looking (e.g. Collapsed as-built, as-planned v as-

built)

Page 20: Delay Analysis

AS-PLANNED V AS-BUILT

• Many variances of the type

–May have a Critical Path network as the as-planned programme;

–May have a reconstructed programme as a baseline

–May be carried out in “windows” or “time slices”

• Simply compares;

–Planned programme and as-built programme

–Difference = delay & relief from LADs ( EOT)

• Often amounts to a “total time claim”

Page 21: Delay Analysis

• METHOD:

• Prepare an As-Built schedule with same activities as the As-Planned schedule.

• Identify the sequence of activities on the As-Built schedule which control the overall project duration – the Controlling Path.

• Identify critical delay by comparing the duration, sequence and timing of the controlling activities of the As-Planned and As-Built schedules.

• Research evidence to identify causes of the identified critical delays.

AS-PLANNED V AS-BUILT

Page 22: Delay Analysis

AS-PLANNED V AS-BUILT

1. identify a secondary effect

2. Infer a primary cause

3. argue that the tertiary effect has resulted from

the primary cause

DELAY

Planned bars

As built bars

Page 23: Delay Analysis

AS-PLANNED V AS-BUILT

Advantages • Cheap and quick to carry out

• Useful review of delays and possible merits of allegations

• Can be an acceptable proof where the effect is indisputably on the Critical Path, eg; • at the start of the job

• at the end of the job

• total suspension of the work

Limitations • Only retrospective

• Easily manipulated to suit the preferred case

• Cannot deal effectively with concurrent causes of delay

• Does not calculate the effect of a cause but asserts the cause of the effect

• Not related to the critical path

• Does not take account of acceleration or re-sequencing

Page 24: Delay Analysis

AS-PLANNED IMPACTED

• Based on the planned programme

• METHOD:

1.Identify the planned programme/ baseline

2.Establish excusable event based on planned intent

3.Model the event in planning software;

4.Add the event to the programme & recalculate the completion date

5.Compare revised end date to original end date.

6.Claim relief for the shift in timing on the programme

7.Repeat for next event

Page 25: Delay Analysis

AS-PLANNED IMPACTED

Contractual Completion Critical Date

foundations

structure

roof & cladding

inspections

1. Start with planned programme

Page 26: Delay Analysis

AS-PLANNED IMPACTED

Unforeseen ground

Contractual Completion Critical Date

foundations

structure

roof & cladding

inspections

Period of Delay

2. Identify a causal event

Page 27: Delay Analysis

AS-PLANNED IMPACTED

Contractual Completion

Date

Inferred delay to progress

foundations

structure

roof & cladding

inspections

Revised Completion

Date

3. Calculate effect

Causes secondary effect – a delay to progress

Causes tertiary effect – an impact on the planned completion date

Unforeseen ground

Primary cause

Page 28: Delay Analysis

IMPACTED AS-PLANNED

Advantages

• Fairly quick and easy to carry out

• Easily understood

• It can be used where as-built information is limited/ does not exist

• Can be suitable method of proof if:

• Project is of simple character

• The planned programme was realistic and achievable

• The critical path remains largely unchanged except for the effect of events

Limitations

• Ignores the as built history of the works

• Cannot deal with concurrency

• Ignores the effect of any change in sequence or acceleration

• Takes no account of:

• Progress

• Resources

• Changing logic

Page 29: Delay Analysis

• METHOD:

• Remove delays from as-built schedule to ascertain when the project would have been completed “but for” these delays. • “Gross” method – remove all at once;

• “Stepped” method – remove delays in reverse chronological order.

• Also known as “Collapsed As-Built”.

• Performed after the works are completed using as built programme as baseline

• Evaluates effect of Events on the basis of the sequence of work that was actually followed

• Analyses the earliest completion date but-for identified delaying events

AS-BUILT BUT FOR

Page 30: Delay Analysis

• Step 1: Creation of baseline

1. Create/assess as built programme

2. Identify variances between planned & actual performance & infer cause for each

3. Produce simulated as built programme

– Wind back the data-date

– Remove the “fixed” dates

– Substitute with planned dates and a logic network

• Logic can be based on updated progressed programmes produced during works

AS-BUILT BUT-FOR

Page 31: Delay Analysis

AS-BUILT BUT-FOR

• Step 2:

–Remove delay events from simulated as-built programme

–Remove delaying activities in reverse chronological order & recalculate completion date

Page 32: Delay Analysis

Unforeseen ground

Actual Completion

Date

foundations

structure

roof & cladding

inspections

1. identify secondary effect on progress

2. infer a primary cause

Original duration

AS-BUILT BUT-FOR

Page 33: Delay Analysis

Unforeseen ground

Actual Completion

Date

foundations

structure

roof & cladding

inspections

3. Convert to critical path program

AS-BUILT BUT-FOR

Page 34: Delay Analysis

Unforeseen ground

Reduced to zero days

Earliest Completion

Date

foundations

structure

roof & cladding

inspections

4. Subtract identified

effect

Secondary effect - delay to progress

Causes tertiary effect - delay to completion

AS-BUILT BUT-FOR

Page 35: Delay Analysis

AS-BUILT BUT FOR

Strengths

• Factually based on actual built times - Easily understood

• Can be used where there is no effective planned programme

• Demonstrates cause and effect of actual timing of event, in sequence in which work was actually built

• Can be used to demonstrate both

• Excusable delay

• Compensable delay ie loss and expense was suffered • Takes account of concurrency

Limitations

• Complicated • Requires accurate and complete as-built data • Requires logic reconstruction - Inferred logic may be challenged • Subjective?

• Takes no account of the planned intent

• Does not identify the effect of events on the contractors intention at the time

• Cannot deal with re-sequencing or acceleration measures

Page 36: Delay Analysis

• METHOD:

• Research details of claimed event causing delay;

• Model the event in planning software;

• Link event into updated schedule;

• Recalculate the critical path & Completion date.

• Compare revised end date to updated dated schedule end date;

• Repeat for all events in chronological order.

TIME IMPACT ANALYSIS

Page 37: Delay Analysis

• Analysis of the effects of delays – over the life of a project, – sequentially, – In light of the Contractor’s progress & future

intentions

• Update Contractor’s current planned programme to period before the Event.

• Add Event to programme & calculate effect upon the planned programme

TIME IMPACT ANALYSIS

Page 38: Delay Analysis

Preparation:

– Identify events & create ‘Fragnet’ for each event.

– List Events chronologically

– Identify planned programme current at time of Event current programme

– Check programme reasonable & fit for use as a base-line

– Re-create or review as-built programme.

– Assess progress information.

TIME IMPACT ANALYSIS

Page 39: Delay Analysis

As-planned programme

Contractual Completion Critical Date

foundations

structure

roof & cladding

inspections

TIME IMPACT ANALYSIS

Page 40: Delay Analysis

Updated programme

Contractual Completion Critical Date

foundations

structure

roof & cladding

inspections

Updated data date

Revised Completion Critical Date after

Update

Slow progress

Progress to activity

TIME IMPACT ANALYSIS

Culpable delay to completion

Page 41: Delay Analysis

Contractual Completion Critical Date

foundations

structure

roof & cladding

inspections

Event

Unforeseen ground

Revised Completion Critical Date

after Update

Updated data date

Updated programme

TIME IMPACT ANALYSIS

Progress to activity

Period of event delay to progress

Culpable delay to completion

Page 42: Delay Analysis

Impacted programme

Contractual Completion Critical Date

Foundations completed to update date

structure

roof & cladding

inspections

Revised Completion Critical Date

after Event

Remainder of foundations

Updated data date

Unforeseen ground

TIME IMPACT ANALYSIS

Progress to activity

Period of event delay to progress

Culpable delay to completion

Period of event delay to completion

Event

Page 43: Delay Analysis

TIME IMPACT ANALYSIS

• Advantages – Cause and Effect – Takes account of Progress/Resource/Logic – Is the most accurate because it uses all planned, progress and as-built information – Takes account of inadequate progress – Takes account of changes in methodology and re-sequencing – Can be used to resolve concurrent delay – Takes account of acceleration – Can deal with multiple Key Dates & Milestones

• Limitations:

– Requires high quality information – Can be time consuming and expensive – Produces a high volume of output – Complicated (and therefore slow) – Prospective results can be inaccurate – Difficult to communicate (Skanska v Egger [2004])

Page 44: Delay Analysis

SMOKE AND MIRRORS

• Smoke and mirrors - analysis that is not what it is described to be by its originator

• Found in discrepancy between description of methodology and that actually adopted

Page 45: Delay Analysis

SMOKE AND MIRRORS

• As-planned v As-built generally understood

• API & ABBF methodologies often understood

• Few really understand Time impact analysis

• “Windows”, “time impact” “time slice” and “snapshot” often used indiscriminately

Page 46: Delay Analysis

Toby Hunt

[email protected]

CONTACT

www.hillintl.com