Demand Response Products

Upload: melanie-merilyn-lamb

Post on 01-Jan-2016

221 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Demand Response Products

Page 2: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Discussion Points

1. Setting the scene…..

2. Virtual Power Station

3. Reserves deployment order

4. Demand Response Products

Page 3: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Setting the scene…..

•“SUPPLY” is what Eskom can deliver and “DEMAND” is what the consumer

needs

•ENERGY MARKET is the day-head scheduling of “Supply” options to MEET the expected “DEMAND”

=

Page 4: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Setting the scene…..

•RESERVE MARKET is on the day “back-up” to ensure stability of the Eskom

system/grid

=

•SUPPLY side “RESERVES”

•DEMAND side “RESERVES” – Demand Response Program

Page 5: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

DEMAND RESPONSEPRODUCTS

Demand Response Programmes

Supplemental DR

Instantaneous DR

Self Generation DR

Normal DR

Emergency DR

Fixed Time DR

Page 6: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Virtual Power Station (VPS)

KZNWC CENTRALECV P S

SYSTEM OPERATOR

SUPPLY DEMAND

CC CCC C CC CCC C

x x√√

09 0010 0014 0015 00

Page 7: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

7

Illustration of typical RESERVE deployment order

Em

erg

ency

RE

SE

RV

E M

AR

KE

TE

mer

ge

ncy

re

du

ctio

n

NR

S 0

48-9

Incr

easi

ng “

Tigh

tnes

s” o

f Sup

ply

Stage 4

Load shedding and curtailment ( Stages 1& 2 )

Curtailment ( Stage 0 )

Load shedding and curtailment ( Stage 3 )

Supplemental DR

Op

erat

ing

Automatic Gen Control (AGC)

Instantaneous DR Instantaneous

ENERGY MARKET

Interruptible LoadAgreements

Max cont. rating/Emergency Level 1

Self Generation DR (Hi Rate)

Self Generation DR (Low to Medium Rate)

Open Cycle Gas Turbines

Page 8: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Normal DR

Page 9: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Demand Response Products

Supplemental DR

Supplemental Reserves> 1 MW load ( Minimum 10% of average MW demand between 5h00-22h00 during weekdays)

Minimum 30 minute notification

Pre-recorded phone call

30 minute integration metering (MV 90 or pre-approved Meter on Line)

1 x 2 hour event per day

150 on target events per year

Reduction measured against average of previous 3 similar days (CBL)

Performance linked Capacity Payment for Standby R26.70/11.21 MW / hr

Performance linked Energy Payment for load reduction at R1250/ MWh

Page 10: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

10

DR - Bidding and Scheduling

• Customer bid load availability by 9h00 day N-1

• VPS consolidate and offer load to System Operator

• System Operator instruct VPS to schedule or not schedule loads

• VPS informs Customer by 15h00 of standby instruction

Page 11: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Load Reduction and Rates

(LR)= sum [(CBL (n) – Actual Load (n)).CBL (m) – Actual Load (m))] n = first Integration Period of the Load Reduction request m = last Integration Period of the Load Reduction request

• Capacity payment

• Peak R26,70/MW (May-Aug between 6h00-09h00 & 17h00-20h00) (Sept-April between 9h00-12h00 & 18h00-21h00)

• Off-peak R11,21/MW (Including Week-ends, public holidays)

• Energy Payment –R1250/MWh

• CBL is a daily profile representing the amount of electricity the CUSTOMER would have consumed in each Integration Period for Week Days and Week-end Days

• Minimum 30 minute notification

Page 12: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Event Performance Report

Notification

Event duration

Page 13: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Customer Base Line calculation (CBL)

13

Page 14: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Monthly Performance Report

Median Monthly performance

Total monthly energy

Page 15: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Settlement Report

Page 16: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Emergency and Fixed Time DR

Page 17: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Demand Response Products (continued)

Emergency DR Fixed Time DR

Emergency Reserves Operational Reserves

When needed during emergencies Only for three Winter monthsOn the day or day ahead e-mail notification

Daily SMS reminder notification

30 minute integration metering 30 minute integration meteringNumber of events, participant’s availability dependent

One Event per day

Reduction measured against average of previous 3 similar days (CBL)

Reduction measured against previous winter weekdays profile

Performance measurement over 30 min Performance measurement over 30 min

Performance linked Energy Payment for load reduction at R1250/ MWh

Performance linked Energy Payment for load reduction at R1250/ MWh

Page 18: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

SELF GENERATION DR

Page 19: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Demand Response Products (continue)

Self Generation DR

Emergency Reserves

30 minute notification

Pre-recorded phone call

30 minute integration metering

1 x 2 hour Event per day (may contract up to 4 or 6 or 16 hours per day)

100 Events per year

Generation measured against average of previous 3 similar days (CBL)Ref. point for scaling = 60 minutes before notification

Performance measurement over 30 min

Performance linked Capacity Payment for standby at: Capacity payment = R18, 75 per MW per hour scheduled

Energy Payment for self-generation up to R3000 / MWh

Page 20: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Self Generation

Page 21: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Event Performance Report

Notification

Event duration

Page 22: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Customer Base Line calculation (CBL)

22

Page 23: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Monthly Performance Report

Median Monthly performance

Total monthly energy

Page 24: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Settlement Report

Page 25: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

DR General

• Performance needs to be >90% of Scheduled Capacity

• Reports generated by the Virtual Power Station

• Event Performance

• Monthly Performance

• Settlement/invoice

• Settlement report to Customer by 10th work day

• Invoiced by customer by 15th work day (Original invoice )

• Electronic payment by last business day

Page 26: Demand Response Products. Discussion Points 1.Setting the scene….. 2.Virtual Power Station 3.Reserves deployment order 4.Demand Response Products

Thank you

Contact details: Ferdi Becker 012 421 3396 083 450 3660 [email protected]