earned schedule - pmi

Upload: projectcontrols

Post on 07-Apr-2018

223 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/6/2019 Earned Schedule - PMI

    1/27

    Earned ScheduleEarned Schedule

    an extension to EVM theoryan extension to EVM theory

    Walt LipkeSoftware Division

    Tinker AFB

    [email protected]

    (405) 736-3341

    E.V.A. - 10Symposium

    May 17-20, 2005

    London, England

    Kym HendersonEducation Director

    PMI Sydney, Australia Chapter

    [email protected]

    61 414 428 537

    mailto:[email protected]:[email protected]
  • 8/6/2019 Earned Schedule - PMI

    2/27

    2

    PurposePurpose

    To discuss and encourage the application of a new

    method of schedule analysis derived from Earned

    Value Management, termed Earned ScheduleEarned Schedule.

  • 8/6/2019 Earned Schedule - PMI

    3/27

    3

    OverviewOverview

    The Problem with EVM Earned Schedule Concept

    Applications

    Status & Future

    Summary

  • 8/6/2019 Earned Schedule - PMI

    4/27

    The ProblemThe Problem

    EVA-10 SymposiumMay 18-20, 2005London, England

  • 8/6/2019 Earned Schedule - PMI

    5/27

    5

    Earned Value BasicsEarned Value Basics

    Time

    $

    BCWS

    BCWPSPI =

    ACWP

    BCWPCPI=

    BACBCWS

    ACWP

    BCWP

    SV

    CV

  • 8/6/2019 Earned Schedule - PMI

    6/27

    6

    Traditional schedule EVM metrics are good at beginning of project

    Show schedule performance trends

    But the metrics dont reflect real schedule performance at end Eventually, all budget will be earned as the work is completed,

    no matter how late you finish

    SPI improves and ends up at 1.00 at end of project

    SV improves and ends up at $0 variance at end of project

    Traditional schedule metrics lose their predictive ability over thelast third of project

    Impacts schedule predictions, EAC predictions

    Project managers dont understand scheduleProject managers dont understand scheduleperformance in terms of budgetperformance in terms of budget Like most of us!

    So, whats the problem?So, whats the problem?

  • 8/6/2019 Earned Schedule - PMI

    7/27

    7

    Earned ValueEarned Value

    Cost and Schedule VariancesCost and Schedule Variances

    +$

    -$

    001 02

    CV = BCWP - ACWP SV = BCWP - BCWS

    Note: Project completion was scheduled for Jan 02, but completed Apr 02.

    J F M A M J J A S O N D J F M A

    CV

    SV

    CV = BCWP - ACWP SV = BCWP - BCWS

  • 8/6/2019 Earned Schedule - PMI

    8/27

    8

    Earned ValueEarned Value

    Cost and Schedule Performance IndicesCost and Schedule Performance Indices

    0.0

    0.5

    1.0

    1.5

    2.0

    J F M A M J J A S O N D J F M A

    CPI

    SPI

    01 02

    Note: Project completion was scheduled for Jan 02, but completed Apr 02.

    BCWS

    BCWPSPI =

    ACWP

    BCWPCPI =

    IN

    DEX

    VALUE

  • 8/6/2019 Earned Schedule - PMI

    9/27

    Earned ScheduleEarned Schedule

    ConceptConcept

    EVA-10 SymposiumMay 18-20, 2005London, England

  • 8/6/2019 Earned Schedule - PMI

    10/27

    10

    Earned Schedule ConceptEarned Schedule Concept

    BCWS

    BCWPSPI($) =

    ATESSPI(t) =

    $

    Time

    BCWS

    BCWP

    Projection of BCWPonto BCWS

    7AT

    BCWS(May)-BCWS(June)

    BCWS(May)-BCWP($)5ES

    JuneofPortionMayofAllES

    =

    +=

    +=

    J J JF M MA A S O N

    BCWSBCWPSV($) =

    ATESSV(t) =

  • 8/6/2019 Earned Schedule - PMI

    11/27

    11

    Schedule Variance ComparisonSchedule Variance Comparison

    -400

    -300

    -200

    -100

    0

    J F M A M J J A S O N D J F M

    -3

    -2

    -1

    0

    0

    20

    40

    60

    80

    100

    J F M A M J J A S O N D J F M

    0

    0.2

    0.4

    0.6

    0.8

    1

    SV($) SV(t)

    Early Finish Project

    Late Finish Project

    $ Mo

    $ Mo

  • 8/6/2019 Earned Schedule - PMI

    12/27

    12

    Schedule Performance IndexSchedule Performance Index

    ComparisonComparison

    0.98

    1.00

    1.02

    1.04

    1.06

    1.08

    1.10

    1.12

    J F M A M J J A S O N D J F M

    0.70

    0.80

    0.90

    1.00

    1.10

    1.20

    1.30

    J F M A M J J A S O N D J F M

    SPI($) SPI(t)

    Early Finish Project

    Late Finish Project

  • 8/6/2019 Earned Schedule - PMI

    13/27

    13

    Earned Schedule IndicatorsEarned Schedule Indicators

    Key PointsKey Points::

    ES Indicators constructed to behave in anES Indicators constructed to behave in ananalogous manner to the EVM Cost Indicators,analogous manner to the EVM Cost Indicators,

    CV and CPICV and CPI

    SV(t) and SPI(t) areSV(t) and SPI(t) are notnot constrained by BCWSconstrained by BCWS

    calculation referencecalculation reference

    SV(t) and SPI(t) provideSV(t) and SPI(t) provide durationduration basedbasedmeasures of schedule performancemeasures of schedule performance

  • 8/6/2019 Earned Schedule - PMI

    14/27

    14

    SV($) versus SV(t)SV($) versus SV(t)

    BCWS

    Earned Schedule (ES)

    BCWP

    Actual TimeActual Time

    SV(t)

    $

    SV

    Earned schedule metrics relatework performed to actual time, notwork scheduled

    Retain utility over time Only return to 0 or 1.00 whereon time completion achieved

    Earned schedule metrics relatework performed to actual time, notwork scheduled

    Retain utility over time Only return to 0 or 1.00 whereon time completion achieved

  • 8/6/2019 Earned Schedule - PMI

    15/27

    ApplicationsApplications

    EVA-10 SymposiumMay 18-20, 2005London, England

  • 8/6/2019 Earned Schedule - PMI

    16/27

    16

    ES Applied to Real Project Data:Late Finish Project: SV($) and SV(t)

    Commercial IT Infrastructure Expansion Project Phase 1

    Cost and Schedule Variancesat Project Projection: Week Starting 15th July xx

    -160

    -140

    -120

    -100

    -80

    -60

    -40

    -20

    0

    20

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

    Elapsed Weeks

    Dollars(,000)

    -16

    -14

    -12

    -10

    -8

    -6

    -4

    -2

    0

    2

    Weeks

    CV cum SV cum Target SV & CV SV (t) cum

    Stop wk 19

    Re-start wk 26Sched wk 20

  • 8/6/2019 Earned Schedule - PMI

    17/27

    17

    Early Finish Project:Early Finish Project:

    SV($) and SV(t)SV($) and SV(t)Commerical IT Infrastructure Expansion Project: Phases 2 & 3 Combined

    Cost and Schedule Variancesas at Project Completion: Week Starting 9th October xx

    -25.0

    -15.0

    -5.0

    5.0

    15.0

    25.0

    35.0

    45.0

    55.0

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

    Elapsed Weeks

    Dollars($,0

    00)

    -2.0

    -1.0

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    Weeks

    Target SV & CV CV cum SV ($) cum SV (t) cum

    Stop wk 16

    Re-start wk 19

    Sched wk 25

    IEAC(t) Predictions usingIEAC(t) Predictions using

  • 8/6/2019 Earned Schedule - PMI

    18/27

    18

    IEAC(t) Predictions usingIEAC(t) Predictions using

    ESES Techniques:Techniques: Weekly Plots of IEAC(t)Weekly Plots of IEAC(t)

    Late Finish Project ExampleLate Finish Project ExampleCommercial IT Infrastructure Expansion Project Phase 1

    Earned Schedule, Independent Estimate At Completion (time) - IEAC(t)

    as at Project Completion: Week Starting 15th July xx

    0

    5

    10

    15

    20

    25

    30

    35

    40

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

    Actual Time (Weeks)

    Duration(Weeks)

    Planned Schedule Earned Schedule cum IEAC(t) PD/SPI(t)

    Stop wk 19 Re-start wk 26

    Plan Dur wk 20

  • 8/6/2019 Earned Schedule - PMI

    19/27

  • 8/6/2019 Earned Schedule - PMI

    20/27

    20

    ES vs EVM ComparisonES vs EVM Comparison

    Earned Schedule Earned Value

    SV(t) and SPI(t) valid forentire project, including early

    and late finish

    SV($) and SPI($) validitylimited to early finish projects

    Duration based predictivecapability analogous toEVMs cost based indicators

    Limited prediction capabilityNo predictive capability after

    planned completion date

    exceededFacilitates Cost ScheduleManagement (using EVM

    and ES)

    EVM Management focused toCost

  • 8/6/2019 Earned Schedule - PMI

    21/27

    Status & FutureStatus & Future

    EVA-10 SymposiumMay 18-20, 2005London, England

    TiTi B d S h d l MB d S h d l M

  • 8/6/2019 Earned Schedule - PMI

    22/27

    22

    TimeTime--Based Schedule MeasuresBased Schedule Measures

    An Emerging EVM PracticeAn Emerging EVM Practice

    Inclusion of Emerging PracticeInsert into PMI - EVM PracticeStandard

    Dr. John Singley, VP of CPM

    Included in Box 3-1 of EVMPractice Standard

    Describes basic principles ofEarned Schedule

    Provides foundation for further

    development of and researchintended to result in EarnedSchedule acceptance as a validextension to EVM

    EVM Practice Standard releasedat 2004 IPMC Conference

  • 8/6/2019 Earned Schedule - PMI

    23/27

    23

    Early AdoptersEarly Adopters

    Incorporation of ES into EVM Instruction

    Several instruction sources now offer ES as part of

    EVM Requests for information and ES calculator

    Calculator provided freely to > 50 requestors

    Tool vendor interest Growing evidence of use on real projectsreal projects

    Evidence of use in a number of countries

    USA, Australia, Sweden, Belgium Applications across weapons programs, construction,

    software development,

    Range of project size from very small and short toextremely large and long duration

    F U fF U f

  • 8/6/2019 Earned Schedule - PMI

    24/27

    24

    Foreseen Uses ofForeseen Uses of

    Earned ScheduleEarned Schedule Enables independent evaluation of schedule

    estimates: ETC(t), EAC(t)

    Client, Contractor, Program and Project Manager .

    Facilitates insight into network scheduleperformance

    Duration based Schedule indicators Identification of impediments/constraints and potential

    future rework

    Evaluation of adherence to plan

    Improvement to Scheduleand Cost prediction Client, Contractor, Program and Project Manager .

    Application of direct statistical analysis ofschedule performance

  • 8/6/2019 Earned Schedule - PMI

    25/27

    SummarySummary

    EVA-10 SymposiumMay 18-20, 2005London, England

  • 8/6/2019 Earned Schedule - PMI

    26/27

    26

    SummarySummary

    Derived from EVM data only

    Provides time-based schedule indicators

    Indicators do not fail for late finish projects

    Application is scalable up/down, just as is EVM

    Schedule prediction is better than any other EVMmethod presently used

    SPI(t) behaves similarly to CPI

    IEAC(t) = PD / SPI(t) behaves similarly to

    IEAC = BAC / CPI

    Facilitates bridging EVM to the scheduleFacilitates bridging EVM to the schedule

  • 8/6/2019 Earned Schedule - PMI

    27/27

    27

    ReferencesReferences

    1. Schedule is Different, The Measurable News,March & Summer 2003 [Walt Lipke]

    2. Earned Schedule: A Breakthrough Extension to Earned Value Theory?

    A Retrospective Analysis of Real Project Data,The Measurable News, Summer 2003 [Kym Henderson]

    3. Further Developments in Earned Schedule,The Measurable News, Spring 2004 [Kym Henderson]

    4. Connecting Earned Value to the Schedule,The Measurable News, Winter 2004 [Walt Lipke]

    5. Forecasting Project Schedule Completion by Using Earned Value MetricsPresentation by Ing. Stephan Vandevoorde, Senior Project Manager,

    Fabricom Airport Systems, Belgium6. Earned Schedule in Action,

    Publication pending, [Kym Henderson]

    http://sydney.pmichapters-australia.org.au/Click Education, then Presentations and Papers for .pdf copies, except (6)

    http://sydney.pmichapters-australia.org.au/http://sydney.pmichapters-australia.org.au/