EMS Outages and Lessons Learned QSE. 2014 ERCOT Operations Training Seminar Texas Reliability Entity Jagan Mandavilli, Bob Collins, Mark Henry. Objectives. Upon completing this course of instruction, you will : - PowerPoint PPT PresentationTRANSCRIPT
2014 ERCOT Operations Training SeminarTexas Reliability Entity
Jagan Mandavilli, Bob Collins, Mark Henry
EMS Outages and Lessons LearnedQSE
2
Objectives
Upon completing this course of instruction, you will:
Recognize the typical causes and failure modes for Energy Management Systems (EMS) systems and tools
Identify the importance of some of the tools QSE’s use Identify the EMS applications critical to your operation Recognize the QSE operator’s role in identifying problems
and reporting EMS failures Identify the components of the procedures for operation of
the system during EMS failures
3
Content
● EMS Failures Communication and Control (EMS) Failures
• Inter Control Center Communication Protocol (ICCP) failures• Remote Terminal Unit (RTU) issues
EMS Applications Failures• Automatic Generation Control (AGC) Failure• SCADA failures
Backup Control center operation Loss of Operator User Interface EMS failures due to database updates Training and Live EMS Screens on same display
● Analysis of Restorations● Contributing & Root causes with examples● Common themes with examples
4
Definitions
● SCADA – Supervisory Control And Data Acquisition● EMS – Energy Management System● AGC – Automatic Generation Control● LFC – Load Frequency Control● ICCP – Inter Control Center Communications Protocol● RTU – Remote Terminal Unit● EAS – Event Analysis Sub Committee● EMSTF – Energy Management Systems Task Force● SCED – Security Constrained Economic Dispatch
5
Tools and Their Importance
● SCADA● AGC/LFC● ICCP● SCED
6
ERCOT EMS Overview
7
EMS Reliability
● EMS are extremely reliable● Extremely high industry wide availability● Systems usually have redundancy● Multiple systems are common, with on-the-fly
failover● Backup centers, sometimes manned● Communications circuits on highly redundant
ring networks● Data handling has built in error detection and
correction● Support staff available 24 x 7
8
What do EMS Problems Look Like?
● Trends flatline ● Data no longer updates● Color changes● Alarms● Strange application results● Lockup of applications● Loss of Visibility
10
NERC EMS Failure Event Analysis
● NERC and personnel examined events 81 Category 2b events (Oct 26, 2010 – Sep 3,
2013) reported 64 events – thoroughly analyzed and reviewed 54 entities reporting - 20 entities experiencing
multiple outages Restoration time for partial outages: 18 to 411 min Restoration time for complete outages: 12 to 253
min Vendor diagnostic failures – Software & Hardware
Issues Several noticeable themes
11
NERC Lessons Learned from EMS Events #1
● Remote Terminal Units Not on DC Sources The power supply to an RTU for a High Voltage
Direct Current (HVDC) converter station was not designed to be fed from station batteries, resulting in a loss of the RTU when all AC feeds to the substation were lost due to an event.
● Lesson Learned While the availability of multiple AC sources
provides a deep degree of reliability for RTUs, entities should evaluate the practicality and feasibility of powering RTUs needed for control, situation awareness, system restoration and/or post analysis from the station batteries.
Operator Training Seminar2014
12
NERC Lessons Learned from EMS Events #2
● EMS System Outage and Effects on System Operations An entity’s EMS began to lose data necessary for visibility
of portions of its transmission network causing functionality and/or solution interruptions for some of its EMS operational tools. No loss of load occurred during this event and it was quickly determined to not be a cyber security event.
● Lessons Learned All entities should have a procedure such as “Conservative
Operations” which provides possible steps they may have to take to ensure reliability. Training should be conducted routinely on all procedures especially those related to low-probability, high-impact events regardless of how often the procedures are used.
Operator Training Seminar2014
13
NERC Lessons Learned from EMS Events #3
● EMS Loss of Operators User Interface Application A control center experienced a loss of control and
monitoring functionality of the EMS due to the loss of the operator’s user interface application between its primary EMS computer/host server and the system operator consoles.
● Lessons Learned Create a ‘save case’ of settings before and after any
change to the system is made. The ‘save case’ will aid in supplying the necessary documentation needed to perform comparisons.
Analyze EMS performance on a periodic basis and evaluate if the system is meeting the needs as designed and intended.
Operator Training Seminar2014
14
NERC Lessons Learned from EMS Events #4
● SCADA Failure Resulting in Loss of Monitoring Function A Transmission Owner (TO)’s control center
experienced a SCADA failure which resulted in a loss of monitoring functionality for more than thirty minutes.
● Lessons Learned It is beneficial that Transmission Operators (TOP) and
TOs install a “heartbeat monitor” alarm to detect stale or stagnant data.
A periodic evaluation of the mismatch thresholds should be conducted for state estimator alarming specific to each operating area, such that it will allow for the optimum sensitivity while minimizing false mismatch alarms.
Operator Training Seminar2014
15
NERC Lessons Learned from EMS Events #5
● Failure of EMS Due to Over-Utilization of Disk Storage Loss of control functionality due to the hard disk on
the SCADA server being fully utilized.● Lessons Learned
SCADA equipment monitoring should include monitoring of hard disk storage utilization. Purging processes need to be set up to perform periodic clean up of disk space.
Operator Training Seminar2014
16
NERC Lessons Learned from EMS Events #6
● Indistinguishable Screens during a Database Update Led to Loss of SCADA Monitoring and Control During a planned database update and failover, an EMS
Operations Analyst inadvertently changed an online SCADA server database mode from “remote” (online) to “local” (local offline copy), which caused a loss of SCADA monitoring and control of Bulk Electric System (BES) facilities.
● Lessons Learned Changing the database mode on a server is not
recommended. A future release of EMS software should eliminate the ability to switch database modes on a server.
Operator Training Seminar2014
17
NERC Lessons Learned from EMS Events #7
● Inappropriate System Privileges Causes Loss of SCADA Monitoring An entity experienced a loss of SCADA telemetry –specifically a
loss of the channel status indicators – for 76% of its transmission system. This problem occurred during the implementation of a scheduled SCADA database update that caused one of the front-end processors to be in an abnormal state. An incorrect command was used to remedy the situation, which resulted in the channel status indicators being set to a failed state.
● Lessons Learned Entities should consider:
• Reviewing the training with respect to change management to ensure that it includes a checklist of steps required; and
• Educating SCADA support staff on global impact of commands on the entire SCADA system.
Operator Training Seminar2014
18
NERC Lessons Learned from EMS Events #8
● Loss of EMS – IT Communications Disabled Transmission System Operators lost ability to
authenticate to the EMS system, resulting in a loss of monitoring and control functionality for more than 30 minutes.
● Lessons Learned EMS network design should include, where
possible, a redundant local authentication server on the same internal network as the primary local authentication server.
Operator Training Seminar2014
19
NERC Lessons Learned from EMS Events #9
● SCADA Failure Resulting in Reduced Monitoring Functionality An entity’s primary control center SCADA Management
Platform (SMP) servers became unresponsive, which resulted in a partial loss of monitoring and control functions for more than 30 minutes. Because this loss of functionality was a result of a conflict between security software configuration changes and core operating system functions, a cyber-security event was quickly ruled out, and no loss of load occurred during this event.
● Lessons Learned Registered entities should consider a “multi-site hosting”
configuration. This configuration provides flexibility and convenience for rapid recovery capability of EMS and SCADA functions.
Operator Training Seminar2014
20
NERC Lessons Learned from EMS Events #10
● Failure of Energy Management System While Performing Database Update There was a failure of EMS while performing a
database update.● Lessons Learned
When the EMS was purchased, the vulnerability of an integrated system architecture was unknown. To eliminate this now-exposed vulnerability, it is recommended that functional separation of the PCC from the ACC be implemented.
Operator Training Seminar2014
21
Number of Reports
October 26, 2010 – September 3, 2013
2010 Q42011 Q12011 Q22011 Q32011 Q42012 Q12012 Q22012 Q32012 Q42013 Q12013 Q22013 Q3
0
2
4
6
8
10
12
22
Characteristics of EMS Outages
0102030405060708090
69
1031
12
7150
Num
ber o
f Eve
nts
23
Root Causes by Category
A1 – DesignEngineering
16%
A2 – EquipmentMaterial
25%
A3 - Individual Human Per-
formance2%
A4 – Man-agement
Organization30%
A5 - Commu-nication
5%
A6 - Training2%
AZ - Informa-tion LTA
20%
24
Contributing Causes by Category
A4 – Man-agement
Organization28%
A2 – EquipmentMaterial
32%
A1 - Design/Engineering18%
A3 - Individual Human Performance9%
A5 - Communication6% AX - Overall
Configuration 5%
A7 - Other2%
25
Top Root/Contributing Causes (in order)
● Software Failure (A2B6C07)● Design output scope LTA (A1B2C01)● Inadequate vendor support of change (A4B5C03)● Testing of Design/Installation LTA (A1B4C02)● Defective or failed part (A2B6C01)● System Interactions not considered (A4B5C05)● Inadequate risk assessment of change (A4B5C04)● Insufficient Job scoping (A4B3C08)● Post Modification Testing LTA (A2B3C03)● Inspection/Testing LTA (A2B3C02)● Attention given to wrong issues (A3B3C01)● Untimely corrective actions to known issue (A4B1C08)
26
Common Themes
1. Software Failures2. Software
Configuration/Installation/Maintenance3. Hardware Failures4. Hardware
Configuration/Installation/Maintenance5. Failover Testing Weaknesses6. Testing Inadequacies
27
Software Failures – What is Affected?
● Application Software Bug/Defect Base System – Alarms/Health Check/Syncing etc. Front End Processing Supervisory Control Applications (SCADA) AGC ICCP User Interface (UI) Relational Database Management Systems (RDBMS) Build Process Scripts Miscellaneous Scripts
● Communication Equipment Firmware/Software Bug/Defect RTUs Switches Modems Routers Firewalls
● Operating System Software Bug/Defect Unix/Linux/Windows
28
Hardware Failures
● Application Servers/Nodes Network Interface cards Server hard drive control board Aux Power regulator control
● Communication Equipment RTU Switches Routers Firewalls Fiber Optic Cables Time source
● Power Sources Uninterruptible Power Supply (UPS) External Generators Power Cables
29
Failover Testing Weaknesses
● Improper settings preventing the failover● Improper procedure to failover● System setup issues preventing failover● Improper patch management between
primary/spare/backup servers● Primary server issues reflected on
spare/backup as well – No Isolation● Improper failover configurations settings● Improper network device configuration
settings for failover● Design requirements not considering failovers
30
Testing Inadequacies
● Inadequate testing● Improper procedures to test● Incomplete scope● Not engaging all the parties involved
31
Software and Hardware Categories and Restoration Times
Hardware C/I/M
Hardware Failure -
Com
Hardware Failure - Power
Hardware Failure - Server
Software Failure - App
Software Failure -
Com
Software C/I/M
0
20
40
60
80
100
120
140
160
0
5
10
15
20
25
86
131
91
66
100
152
94
13
78
2
20
4
19
Mean Outage Restoration Time (Mins) Event Count
Rest
orati
on T
ime
in M
inut
es
Even
t Cou
nt
32
Historical Failure Restoration Data
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 770
50
100
150
200
250
300
350
400
450
Complete Outage Restoration Time Partial Outage Restoration TimeMean Complete Outage Restoration Time Mean Partial Outage Restoration TimeMean Outage Restoration Time
Mean Complete Outage Restoration Time: 56 MinutesMean Partial Outage Restoration Time: 43 MinutesMean Total Outage Restoration Time: 99 Minutes
33
Lessons Learned
● Publish information about problems and solutions
● NERC continues review of events with a working group of stakeholders and Regional personnel
● Situational Awareness workshop held in June 2013 with future workshops planned
● Dialogue with vendors to inform and improve
34
Reporting Requirements – NERC Standard EOP-004-2
● Complete loss of voice communication capability affecting a Bulk Electric System (BES) control center for 30 continuous minutes or more (same as Category 2a of EAP)
● Complete loss of monitoring capability affecting a BES control center for 30 continuous minutes or more such that analysis capability (i.e., State Estimator or Contingency Analysis) is rendered inoperable (similar to Category 2b of EAP)
● Report to ERCOT, TRE, NERC and DOE per TRE web link: http://www.texasre.org/Reliability/EOP-004disturbancereports/Pages/Default.aspx
35
Reporting Requirements – NERC Events Analysis
● Category 1f - Unplanned evacuation from a control center facility with Bulk Power System (BPS) SCADA functionality for 30 minutes or more
● Category 1h - Loss of monitoring or control, at a control center, such that it significantly affects the entity’s ability to make operating decisions for 30 continuous minutes or more. Examples include, but are not limited to the following: Loss of operator ability to remotely monitor, control BES
elements, or both Loss of communications from SCADA RTUs Unavailability of ICCP links reducing BES visibility Loss of the ability to remotely monitor and control generating
units via AGC Unacceptable State Estimator or Contingency Analysis solutions
36
What Can Operators Do?
● Watch for failures and unexpected situations● Determine the criticality and impact to the
reliability of the grid● Promptly report the failures● Log the date/time of the failure, a description
of alarms/events, time of system/function restoration
● Expect the EMS failure and prepare to react● Have the necessary back up procedure in
place and be familiar with them
37
ERCOT Procedures
● Failover procedure● Loss of AGC – Operation Guides● Constant Frequency operation● Loss of ICCP
38
Real Time Operating Procedure- Section 3.3 System Failures
Monitor Frequency for the Loss of EMS or Site Failover The ability to view an adequate Frequency source may be limited during a site-failover, database load, or if AGC is temporarily unavailable. To view the System Frequency during these conditions you may monitor the following sources. o ERCOT Control Room digital wall frequency displays o PI ProcessBook → ERCOT → TrueTime Frequency (Taylor)
and/or o PI ProcessBook → ERCOT → TrueTime Frequency (Bastrop) It may be necessary to reload the PI ProcessBook “ERCOT Main Summary” display to show the historical data.
39
Real Time Operating Procedure- Section 3.3 System Failures
EMMS (LFC and RLC/SCED) Failure
Regulation, RRS, UDBP, BP, EBP, and manual offset not functioning.
LFC (AGC): AGC is SUSPENDED or PAUSED, “Last ACE crossing zero” time on the Generation Area Status page
is not updating, AGC operation adversely impacts the reliability of the
Interconnection, SCED and EMS are not functioning,
o Problem cannot be resolved quickly REFERENCE Display: EMP Applications>Generation Area Status>Nodal Operational Status>Resource Limits Data DETERMINE:
Which QSE has ample capacity to place on constant frequency Control;
THEN: Direct the selected QSE to go on constant frequency As time permits, issue an electronic VDI
o Choose “OPERATE AT CONSTANT FREQUENCY” as the Instruction Type from QSE Level
Place ERCOT AGC into “Monitor” mode
40
Generating Unit Operations During Complete Loss of CommunicationsExcerpt from 2014 DRAFT NERC guideline for units without voice or data links to their QSE but able to generate and monitor frequency
41
Draft NERC Reliability Guideline – Frequency Chart for the ERCOT Region
42
References
● ERCOT Nodal Protocols, Sect 3.10● ERCOT Nodal Operating Guides, Sect 7● ERCOT State Estimator Standards● ERCOT Telemetry Standards● ERCOT Operating Procedure Manual, Shift
Supervisor Desk, Sect 10● NERC Events Analysis Process● NERC Standard EOP-004-2● NERC EMS Task Force● DRAFT NERC Reliability Guideline: Generating
Unit Operations During Complete Loss of Communications
43
Credits
Much of the information contained in this presentation was previously published by North American Electric Reliability Corporation (NERC) in a variety of publications. It is the result of extensive review of actual power system events over a 2 year period by the EMS Event Task Force.
Questions?
44
EXAMPlease turn your iClicker on and answer each of the following questions.
45
1. Which of the following Operator tools can lead to EMS failures?
a) SCADAb) ICCPc) AGCd) All of the above
46
2. What is the top root/contributing cause of EMS failures?
a) Inadequate vendor supportb) Hardware failurec) Inadequate testingd) Software failure
47
3. What action should ERCOT take for the loss of their LFC?
a) Monitor frequency and hope for the bestb) Place a large QSE on constant frequencyc) OOME Up unitsd) RUC units off line
48
4. Which of the following steps should an Operator take during an EMS failure?
a) Promptly report the failuresb) Determine the criticality and impact of the failure
to the reliability of the gridc) Log the date/time of the failured) Implement backup procedurese) All of the above
49
5. What is the NERC Standard that requires reporting of EMS failures?
a) NERC Events Analysis Processb) NERC Standard TOP-001-1c) NERC Standard EOP-004-2d) NERC EMS Task Force