energie du mali

28
Kennedy School of Government Case Program CR14051811.0 This case was written by Professor José A. GómezIbáñez and is intended for class discussion only and not as a source of primary data or as an example of appropriate or inappropriate policy. The case was funded in part by the World Bank. The author thanks the officials of the government of Mali and EDM and especially Dr. Ibrahim Togola and Tom Burrell of the Mali Folkecenter for their assistance. The author is responsible for all errors. (0905) Copyright © 2005 by the President and Fellows of Harvard College. No part of this publication may be reproduced, revised, translated, stored in a retrieval system, used in a spreadsheet, or transmitted in any form or by any means (electronic, mechanical, photocopying, recording, or otherwise) without the written permission of the Case Program. For orders and copyright permission information, please visit our website at www.ksgcase.harvard.edu or send a written request to Case Program, John F. Kennedy School of Government, Harvard University, 79 John F. Kennedy Street, Cambridge, MA 02138 EDM (Energie du Mali) In the spring of 2005, the government of Mali was negotiating major changes in the concession of Energie du Mali (EDM), the private firm that operated Mali’s electricity and water services. Five years earlier, in 2000, the government had held an international competition for a 20year concession that was won by Saur International, the utility operating division of the giant French construction conglomerate Bouygues. The company and the government soon became embroiled in disputes over the formula for adjusting tariffs and the difficulties the concessionaire was having in raising funds for promised investments. The two parties agreed in January 2005 that the concession should be converted into an affermage or lease contract, in which the private company would be responsible only for operations and maintenance while the government assumed responsibility for new investment. But they had yet to agree on the key details of the transition, including the amount that the government would pay to buy back EDM’s assets and the terms of the new lease. The negotiations were being watched anxiously by the international donor community, and particularly by the World Bank and the French bilateral aid agency, the Agence Française de Développement (AFD). Since the early 1990s, the World Bank, AFD and other donors had been promoting private participation as a mechanism for improving performance and increasing investment in infrastructure. The policy had had mixed results around the world, with many successes but also a number of high profile failures. But it had experienced the most difficulty in subSaharan Africa, where interest from private investors had been weaker, a relatively high proportion of the private concessions, leases, or management contracts had been cancelled and a number of others, like EDM, were in crisis. Some wondered whether leases or management contracts were more appropriate than concessions in subSaharan Africa. And many feared that

Upload: lyhanh

Post on 10-Feb-2017

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Energie du Mali

 

  

Kennedy School of Government Case Program 

CR14‐05‐1811.0

   

This case was written by Professor José A. Gómez‐Ibáñez and is intended for class discussion only and not as a source of primary data or as an example of appropriate or  inappropriate policy. The case was  funded  in part by  the World Bank. The author thanks the officials of the government of Mali and EDM and especially Dr. Ibrahim Togola and Tom Burrell of the Mali Folkecenter for their assistance. The author is responsible for all errors. (0905) 

Copyright © 2005 by  the President and Fellows of Harvard College. No part of  this publication may be reproduced, revised,  translated, stored  in a retrieval system, used  in a spreadsheet, or transmitted  in any form or by any means (electronic, mechanical, photocopying, recording, or otherwise) without the written permission of the Case Program. For orders and copyright permission information, please visit our website at  www.ksgcase.harvard.edu  or  send  a  written  request  to  Case  Program,  John  F.  Kennedy  School  of Government, Harvard University, 79 John F. Kennedy Street, Cambridge, MA 02138 

EDM  (Energie du Mali) 

 

In  the  spring  of  2005,  the  government  of Mali  was  negotiating major  changes  in  the concession of Energie du Mali  (EDM),  the private firm that operated Mali’s electricity and water services. Five years earlier, in 2000, the government had held an international competition for a 20‐year  concession  that was won  by  Saur  International,  the  utility  operating division  of  the  giant French  construction  conglomerate  Bouygues.  The  company  and  the  government  soon  became embroiled in disputes over the formula for adjusting tariffs and the difficulties the concessionaire was having in raising funds for promised investments. The two parties agreed in January 2005 that the  concession  should  be  converted  into  an  affermage  or  lease  contract,  in  which  the  private company  would  be  responsible  only  for  operations  and  maintenance  while  the  government assumed  responsibility  for new  investment. But  they had yet  to  agree on  the key details of  the transition, including the amount that the government would pay to buy back EDM’s assets and the terms of the new lease. 

The negotiations were  being watched  anxiously by  the  international donor  community, and particularly by the World Bank and the French bilateral aid agency, the Agence Française de Développement  (AFD). Since  the early 1990s,  the World Bank, AFD and other donors had been promoting  private  participation  as  a  mechanism  for  improving  performance  and  increasing investment  in  infrastructure.  The  policy  had  had mixed  results  around  the world, with many successes but also a number of high profile failures. But it had experienced the most difficulty in sub‐Saharan  Africa, where  interest  from  private  investors  had  been weaker,  a  relatively  high proportion of the private concessions,  leases, or management contracts had been cancelled and a number  of  others,  like  EDM,  were  in  crisis.  Some  wondered  whether  leases  or  management contracts were more appropriate  than concessions  in sub‐Saharan Africa. And many  feared  that 

Page 2: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

the  failure of  the EDM negotiations would sharply  reduce  the prospects  for any  form of private involvement in the region’s infrastructure. 

Mali and Sub‐Saharan Africa 

Mali  is a  large  landlocked  country on  the  southern border of  the Sahara desert with an estimated  2002  population  of  12.6  million.  Only  3.6  million  Malians  lived  in  urban  areas, principally  in  the  capital  Bamako  and  in  a  dozen much  smaller  secondary  cities  including  the legendary  Timbuktu. Mali’s  primary  exports were  cotton  and  gold,  and  it was Africa’s  largest producer  of  cotton  seeds. These  activities  generated  a  2002 per  capita  income  of  only US$2781, however, so that almost three quarters of Malian’s lived on less the $1 per day. Donor aid made up roughly 20 percent of the national income and 80 percent of investment. 

Mali  shared many of  the  same problems of other  countries  in  sub‐Saharan Africa. Sub‐Saharan Africa had just 9 percent of the world’s population but half of the countries that were poor enough to qualify for the World Bank’s most generous lending terms, half of the world’s conflict or post‐conflict states, two‐thirds of the world’s HIV infections, and the highest proportion of people living on  less  than $1 per day. The countries of  the  region were on average significantly poorer than the developing countries in most other regions. In 2004 sub‐Saharan Africa had an estimated per  capita  income of $760, a  figure only  slightly higher  than  that  in South Asia  ($610) and well below those of Latin America ($3,730) or Eastern Europe and Central Asia ($3,750). The average for the sub‐Sahara was strongly affected by the presence of the Republic of South Africa, which was substantially  better  off  than  its  neighbors.  If  South  Africa were  excluded,  the  region was  the poorest in the world. 

The  countries  in sub‐Saharan Africa were also, on average,  smaller and more  rural. The region included some countries with large populations, notably Nigeria (121 million), Ethiopia (69 million), the Democratic Republic of Congo (51 million), and South Africa (45 million). But only 10 of the 48 countries in the region had populations of over 15 million persons,2 while the remaining 38 had an average population of only 4 million.3 Only 33 percent of the population in sub‐Saharan Africa lived in urban areas, a figure comparable to that in South Asia (39 percent) but less than half that of Latin America (77 percent). 

                                                           1 The currencies used in this case are U.S. dollars and CFA francs. Between 2000 and 2005 the CFA franc

strengthened rising from approximately 750 to the dollar to 550 to the dollar. 2 In addition to the four mentioned earlier, they include Tanzania (36 million), Kenya (32 million), Uganda (25

million), Mozambique (19 million), Madagascar (17 million), Ivory Coast (16 million), and Cameroon (15 million) 3 The 38 smallest countries had a combined population of 166 million persons out of the total 605 million persons

who lived in sub-Saharan Africa in 2002.

Page 3: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Infrastructure in Sub‐Saharan Africa 

Infrastructure, along with education and HIV, was among the top concerns of politicians and the general public in sub‐Saharan Africa.4 Poverty and low levels of urbanization meant that access to infrastructure services was a much more significant problem in the region than in the rest of the world. The disparity was greatest in electricity: only 15 per cent of households had access to electricity in the average sub‐Saharan country compared to 31 per cent in the average South Asian country, 79 percent in Latin America, and 88 percent in Middle East and North Africa (Exhibit 2). But  sub‐Saharan Africa  also  lagged  behind  other  regions  in  access  to  clean water  sources  and telecommunications (Exhibits 3 and 4). 

Those with access to infrastructure did not necessarily receive good service. Electricity and water cuts were common as production often  fell short of demand, and delivered water did not always meet  the  quality  standards  of  the World Health Organization.  In many  countries  even small  firms  felt  obliged  to maintain  their  own  standby  diesel  generators. And  a  survey  in  six African countries  found  that more businesses  (48 percent) considered electricity  to be a major or very severe obstacle to their growth than corruption (40 percent).5  

The affordability of infrastructure tariffs was an understandable concern in the region, and the desire for low tariffs made it difficult to finance investments to expand production capacity or extend networks to serve new customers. Extending the networks was the most difficult problem since it cost as much as $1000 to connect a household to the electricity grid or piped water network in communities on the periphery of existing service areas, and often more for households living in isolated communities. Paying  for connections was beyond  the means of many poor households, even if the expense could be financed over time. 

Although affordability was an  issue, many households and businesses seemed willing to pay significant sums for improved infrastructure services if they were convinced that higher tariffs were the only way to get better service. The rapid spread of mobile telephones in the region during the 1990s was a case in point, since mobile telephone subscribers had to buy their own handsets in addition  to paying charges of $0.10  to $0.30 per minute. Customers might pay more  for  reliable electricity  or  water  service  since  businesses  could  dispense  with  standby  generators  and households would  suffer  fewer  illnesses. Similarly, households without  access might be  able  to pay a portion of the connection costs in as much as they would save on the expensive and inferior substitutes  they  currently used,  such as batteries or kerosene  for electricity and carter or  tanker water for piped water. 

                                                           4 Antonio Estache, “What do We Know about Sub-Saharan Africa’s Infrastructure and the Impact of its 1990s

Reforms?”, World Bank draft working paper, May 24 2005, p. 7. 5 Estache, “What do We Know?”, p. 31.

Page 4: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

The Record of PPI in Africa 

Some of the early pioneers in private participation in infrastructure (or PPI for short) had been motivated in part by ideological concerns; this was particularly true of Chile in the late 1970s and  Britain  in  the  early  1980s.  But  the  next  group  of  adopters  was  motivated  primarily  by pragmatic considerations, and particularly by  fiscal crises  that made  it  impossible  to continue  to subsidize  the  large  deficits  of  state‐owned  utility  companies.  Argentina  began  to  privatize  its infrastructure  in  1989,  for  example, after  chronic budget deficits  resulted  in hyper‐inflation  that brought  the  economy  to  a  standstill. Similarly, Mexico began  to privatize  its  infrastructure  that same  year  after  a  series  of  fiscal  and  debt  crises  during  the  1980s,  and  India’s  reforms were stimulated  after  economic  mismanagement  caused  the  country  to  nearly  run  out  of  foreign reserves  in 1991. By  the mid 1990s, many of  the multilateral and bilateral aid agencies began  to promote PPI as well. The aid agencies had been discouraged by the failure of attempts to improve the  efficiency  of  government‐owned  infrastructure  companies  in  the  1970s  and  1980s.  PPI promised to improve the efficiency of infrastructure providers and to tap private capital markets to finance  investments,  thereby  allowing  governments  and  donors  to  shift  some  of  their  scarce resources to social sectors. 

Sub‐Saharan Africa proved  to be a difficult region for PPI, however. A World Bank data base on PPI  showed  that  sub‐Saharan Africa  attracted only  $33 billion  in private  infrastructure investment  between  1990  and  2003,  less  than  4  percent  of  the  $801  billion  attracted  by  all developing countries in that same period.6 Moreover, 49 percent of the investment in sub‐Saharan Africa  went  to  a  single  country—South  Africa—and  65  percent  went  to  a  single  sector—telecommunications. The  second most  important  sector,  energy,  received only  22 percent of  the investment, mostly in the form of new generating stations built by Independent Power Producers (IPPs)  and  backed  by  take‐or‐pay  contracts with  state‐owned mining  or  electricity  companies. There had been relatively little private investment in electricity distribution and transmission and almost none in water and sanitation. 

Even so,  there had been some notable successes. The  telecommunications sector was  the most obvious case as  telephone  lines per capita quadrupled  in sub‐Saharan Africa between 1996 and 2002 (Exhibit 4). And in other sectors there were some countries and companies where the PPI experience was very favorable. In the Ivory Coast, for example, a private company had operated the water system since independence in 1960 while a separate private company had provided the electricity service since 1990. Similarly,  in Senegal a private company had successfully provided water service to the capital Dakar since 1996. 

                                                           6 As quoted in John Nellis, “The Evolution of Enterprise Reform in Africa: From State-owned Enterprises to Private

Participation—and Back?”, photocopied, World Bank, April 15, 2005, p. 20.

Page 5: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

But,  telecommunications  aside,  the  failures  seemed  as  numerous  as  the  successes  and several high profile cancellations and disputes had tarnished the reputation of PPI in the region. In the electricity sector,  for example, approximately half of  the countries  in sub‐Saharan Africa had attempted  to  involve  the  private  sector  in  the  management  of  their  electricity  distribution companies, but in roughly half of these cases either the effort was aborted before the contract was awarded or the contract was cancelled after only a few years.7 The outbreak of conflict forced the abandonment  of  privatization  in  a  few  countries,  although  the  Ivory Coast  demonstrated  that conflict  need  not  be  fatal  for  private  utilities.  That  country’s  private  water  and  electricity companies had survived the civil war of 2002‐2003 and the subsequent (and hopefully temporary) division of  the  country by  continuing  to offer  service without  taking  sides  in  the dispute. More often PPI collapsed amidst accusations by the private and the public sectors that the other side was not living up to its responsibilities (Exhibit 6 and 7). 

The difficulties were causing the established  international  infrastructure companies to be more wary of Africa. For example,  the major French water company Vivendi had  left Chad and now remained only in Niger, while the British water giant Biwater was leaving Tanzania. By 2004 Saur was operating only four systems in Africa: the water and electricity companies in Ivory Coast, the water company  in Senegal, and EDM  in Mali. And  late  that year Bouygues sold Saur along with most of its water and electricity companies and established a new subsidiary, Finagestion, to manage the few companies Bouygues retained, mainly in Africa and Italy. As the large first‐world companies  retreated,  they  were  being  replaced  to  some  extent  by  companies  from  other developing countries. For example, Rites, a subsidiary of Indian Railways, had won concession to operate  the  railways  in  three  African  countries,  while  South  Africa’s  state‐owned  electricity company, Eskom, was operating electricity concessions in several countries.8

EDM as a Public Enterprise (1960‐1995) 

EDM was  established  in 1960,  shortly after Mali’s  independence, using  capital  from  the Malian  government  and  the  French  aid  agency ADF  and  important  technical  support  from  the French state‐owned electricity company, Electricité de France (EdF).9 Initially, EDM operated small diesel‐fired  generating  plants  in  Bamako  and  several  secondary  cities.  The  cost  of  producing electricity was very high, however, both because electricity consumption was far too low to exploit economies of scale and because of the high cost of transporting diesel fuel overland to Mali. EDM could bring  in fuel by truck through the Ivory Coast or by rail through Senegal, but either route involved trips of over 1000 kilometers on poorly maintained roads and railways. 

                                                           7 Philippe Benoit, “Viewpoint: A Snapshot of PPI in Sub-Saharan Africa’s Power Sector,” draft January 12, 2005. 8 Eskom was in Uganda and Malawi. 9 Initially the Malian government owned 55 percent of EDM, ADF 39 percent and EdF 6 percent. ADF gave its

shares to the government in 1984. EdF’s shares were diluted over time with additions to capital.

Page 6: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

 The high  cost of diesel encouraged  the Malian government  to  look  for opportunities  to develop hydro power. The first small hydro plant, capable of generating 5.7 megawatts (MW), was built at Sotuba and began producing power  in 1967. Sotuba’s capacity was absorbed by  the mid 1970s, and the resulting blackouts forced the extensive rehabilitation and expansion of the thermal plants outside Bamako and eventually the development of a new dam at Sélingué which came on line  in 1980 with  the capacity of 46.2 MW. Sélingué’s capacity was absorbed by  the early 1990s, which fueled plans for a third hydro plant at the Manantali dam. 

EDM’s  problems were made more  difficult  by  the mismanagement  that  plagued many state‐owned  enterprises.  EDM’s  customer  records were  notoriously  inaccurate,  for  example,  so that many consumers didn’t  receive bills and many of  those who were billed never bothered  to pay. The company rarely cut off those who didn’t pay and, if it did, EDM employees often could be bribed to restore service or make illegal connections. 

Matters were made worse because  the government  treated EDM as something of a cash cow. EDM was one of the largest and most important enterprises in Mali, and one of the few places where  significant  amounts of  cash  accumulated. As  in other African  countries,  the government was one of the utility’s biggest customers and government agencies would often not pay their bills if  they needed  the  funds  for other purposes. But Mali  found other more  innovative ways  to  tap EDM’s  resources. When  the  Bamako  central market  burned  down  in  a  fire  caused  by  illegal electricity connections, for example, the government got a court  judgment that EDM was at fault and had to pay to have the market rebuilt even though the connections were illegal. 

The most  important way  in which  the  government  tapped  EDM  resources  during  the 1980s was by setting up a separate agency, OERHN10, to manage the Sélingué dam. EDM seemed to be having too many problems to be trusted with the new dam, and was perceived as a French‐supported  company while  the dam had been  funded by  several other  countries besides France. The decision proved an unanticipated boon to the government, however, because OERHN could charge  EDM  more  for  its  electricity  than  it  cost  to  produce,  passing  the  profit  on  to  the government. As a result, EDM’s tariffs never reflected the full savings of Sélingué’s hydro power. 

EDM’s problems led the donors to press for reform of the enterprise through performance contracts. In 1986 the World Bank, which had participated in the financing of the Sélingué hydro plant,  discovered  that  OERHN  had  not  been  inspecting  the  dam  and  that  serious  structural problems had developed that would require rebuilding the four turbine systems. The key donors decided that money to rehabilitate Sélingué would be forthcoming only if the government agreed to an annual technical inspection of the dam and implemented a performance contract with EDM. 

Performance  contracts had been developed  in France  in  the  1960s,  and had become  the most common tool for public enterprise reform in developing countries by the 1980s. A company                                                            10 L’Office d’Exploitation des Ressources Hydrauliques du Haut Niger.

Page 7: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

and  its supervising ministry would negotiate a contract spelling out the key performance targets that the company had to meet and the financial and other support that the ministry was prepared to provide. The  idea was to give the managers freedom from day‐to‐day political interference by the ministry  in return for holding them accountable for a few key targets. Performance contracts failed  to  improve  performance  in  most  countries,  largely  because  neither  party  took  their commitments  very  seriously.  The managers  often missed  their  targets while  the  governments usually reneged on promises to increase tariffs or provide subsidies.11 In any event, the approach had  little chance  to prove  itself  in Mali because  the government was overthrown  in a coup only two years after EDM signed its first performance contract. 

Mali’s first government after independence had been led by President Modibo Keita, who built a one‐party state and pursed a socialist path of development. Keita was overthrown in 1968 in a military coup led by Moussa Traoré, who established a dictatorship with himself as president. Military rule began to unravel in 1990 when the Tuareg, a tribe in the northern part of the country, rose up  to protest  their poor  treatment. The violence  that  followed undermined  support  for  the government and  in 1991 General Amedou Toumanny Touré  led a successful coup. General ATT, as  Touré  is  affectionately  nicknamed, won  his  people’s  gratitude  by  declaring  that  he  had  no interest  in  ruling  the  country  and  scheduling  elections  for  1992. Alpha Oumar Konaré won  the presidency that year, and was reelected to a second five‐year term in 1997. 

The return of democracy in 1992 slowed efforts to reform EDM at first, if only because the cabinet was reshuffled so frequently. Gradually a team emerged that was  interested  in economic reform,  led by  the  finance minister12. The minister  thought  that Malian development was better served  by  developing  a  reliable  and  affordable  electricity  system  instead  of  diverting  EDM resources  elsewhere,  and  his  position  was  reinforced  by  pressure  from  the  donors.  The government had been asking  for help  in  financing  the  third hydro project at Manantali, but at a meeting  in Paris  in April  1993  the donors—including  the French, Germans, Canadians, and  the World Bank—made reform a precondition. The performance contract was not working, and Mali could forget about Manantali unless it consolidated OERHN with EDM, hired a private company to manage EDM, raised tariffs, and improved bill collection. 

EDM under Delegated Management (1995‐1998) 

A management contract was the least intrusive of several options for private participation in EDM. Under a management contract,  the government retains  the ownership and appoints  the board  of  directors while  the  private  company  fills  a  half  dozen  or  so  of  the  key management positions.  In  a  lease  or  affermage  contract,  by  contrast,  the  government  cedes  to  the  private company  the  responsibility  for  operating  the  enterprise,  including  appointing  its  own  board  of 

                                                           11 For a discouraging account of the African experience see Nellis, “The Evolution of Enterprise Reform in Africa.” 12 Soumailia Cisse.

Page 8: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

directors,  but  retains  responsibility  for  financing  investments. A  third  option  is  the  concession contract in which the private company is responsible for investments as well operations. 

There was  some  confusion  as  to whether EDM’s management  contract was  a  first  step toward an eventual lease or concession or as sufficient in itself. Some of the donors clearly saw it as  preparation  for  a  concession, while  some  of  the Malian’s working  in  EDM  viewed  it  as  a temporary device  to establish a more modern and professional approach to management. In any event, an international competition for the contract was won by a French‐Canadian consortium led by Saur and  including Hydro Québec and EdF. The consortium  included  firms  from all  the key donor countries and each member was assigned responsibility for different aspects of EDM, such as billing and collections, human relations, and electricity and water production and distribution. 

The management contract was for four years, beginning in January 1995. For the first two years the consortium would be compensated on a person‐month basis for the expatriate managers in  residence. At  the end of  two years, and once better  information  systems were  in place,  there would be a technical review to assess how well the managers were doing and to set performance standards for the following two years. Compensation in the final two‐year period would be based on  person‐months,  plus  or  minus  15  percent  depending  on  improvements  in  bill  collections, technical losses, and other performance measures. 

The  contract went well  for  the  first  year  or  two,  after which  relationships  between  the foreign managers and the Malian board of directors deteriorated rapidly.13 The foreign managers were  credited with  improving  customer  relations,  conducting  lots of  training and making  some badly  needed  investments.  But  they  made  little  headway  in  improving  the  reliability  of  the generators or in straightening out EDM’s accounting system. These shortcomings were made more obvious  in  the  summer  of  1996 when  the  combination of growing demand  and  a drought  that reduced Sélingué’s output  led  to many months of  serious blackouts. There were disagreements about  priorities  both within  the management  consortium  and  between  the  consortium  and  the board of directors. The board had to approve the budget, and used this leverage over both major and  symbolic  issues,  such  as  the purchase  of vehicles  for  the  senior  staff. The  chairman  of  the board of directors, who had held very senior posts in OERHN and EDM previously, exploited the differences within the consortium skillfully. In March 1998, with almost a year still remaining, the board finally cancelled the contract. 

The  cancellation provoked  another April meeting  of  the donors  in Paris,  at which  they pressed  the  government  for  a  commitment  to move  to  a  full  concession  in which  the  private concessionaire would  control  the board  as well  as  the management. This more  radical measure became more  acceptable  in  the  following  year,  as  the  performance  of EDM deteriorated  again. Sélingué was being rehabilitated, which meant that the turbines had to be taken out of service one 

                                                           13 Alain Henry, “La résiliation de la DGG á EDM”, Département des Politiques et Etudes, AFD, about 1999.

Page 9: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

at  a  time.  In  addition,  another drought  further  reduced output  and  some of  the  thermal plants broke down as well. At one point in 1999 EDM had only 8 MW of generating capacity on line. 

The Concession Begins (2000‐2002) 

With the help of  international consultants funded by the donors, the Malian government designed  a  20‐year  concession. The  concession  contract  specified  in detail  the  increases  in new connections and  investments,  reductions  in  technical  losses, and  the  tariffs  required.  In  the  first five years,  for example, EDM had  to  increase  the number of electricity customers  from 80,000  to 143,000 and the number of water customers from 60,000 to 80,000. By the end of the concession (in 2020) EDM was to have 300,000 electricity customers and 195,000 water customers. EDM was also to increase the number of urban centers provided with electricity from 34 to 97 by 2020. To achieve these goals, the contract anticipated that EDM would make investments of 180 billion CFA francs in the first five years, although this target was not to be binding if the firm met its targets for new customers. The contract also specified a formula by which tariffs would be adjusted every calendar year  for  the  first  ten  years.  For  example,  the  electricity  tariff  adjustment  formula,  which  is described in an appendix to this case, was based on a weighted index of the changes in the prices of  imported  spare  parts,  diesel  fuel,  power  purchased  from  independent  generators  and  the average  salaries of government  functionaries. For  the  final  ten years prices were be  to  set be  a regulator following the British price‐cap approach.14

Presumably with the final ten years in mind, the government also established an electricity and water regulator, CREE15, with a mandate to protect consumers, to promote competition where possible and  to serve as an arbitrator  in disputes between  the government and any electricity or water concessionaires. CREE had to approve any tariff increases proposed by a concessionaire, and was  authorized  to  suggest  alternative  tariffs.  Tariffs  had  to  “cover  all  expenses  and  charges justified  by  operating  needs”  and  “include  a  proper  rate  of  return  that  allows  the  operator  to attract and fairly reward the  invested capital.”16 CREE was designed to be  independent from the government  in  that CREE’s  five  commissioners were  appointed  to  staggered  5‐year  terms  and removable  only  for  “serious”  cause  and CREE’s  budget was  financed  by  a  small  surcharge  on electricity and water bills. The commissioners had to be an electrical engineer, a water engineer, a lawyer, and economist specialized in tariff setting, and a financial analyst. The five commissioners would elect one of them to serve as president of the commission. 

                                                           14 The electricity contract specified that the formula would apply for only the first ten years but the water contract did

not. For an account of this and many other inconsistencies in the contracts and authorizing legislation see Richard Schlirf Rapti, “The Privatization of EDM S.A. in Mali: Doomed by Design”, photocopied draft, MacroConsulting, May 30, 2005.

15 Commission de Régulation de l’Electricté et de l’Eau. 16 From article 42 of the 2000 law reorganizing the electricity sector (ordinance 00-019). The law did not specify a

body to which CREE decisions could be appealed, but presumably they could be appealed to the courts.

Page 10: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

The Ministry of Mines, Energy and Water retained responsibility for technical supervision of EDM. Within the ministry there was an agency for electricity, the DNE, and one for water, the DNH.17 Most senior ministry, DNE and DNH officials had worked in the management of EDM at some point in their careers. 

An international competition was held with the concession awarded to the highest bidder for 60 percent of the stock in EDM (the government would keep the rest). Three consortiums led by Saur,  the  U.S.  electricity  company  AES  and  the  French  water  company  Vivendi  participated, although the Vivendi bid was disqualified.18 Saur offered 13.2 billion CFA francs (approximately $17.6 million19),  six  times more  than  the AES bid of 2.2 billion CFA  francs. The  concession was signed in November 2000 and went into effect in December 2000. The government also called for open applications  to be CREE commissioners, but  that process was started  late and  took  long so that  the  five  commissioners  were  not  in  place  until  September  2001,  ten  months  after  the concession had started. 

Relations  between  EDM  and  the  government were  fairly  cordial  at  first.  The delivered price  of  diesel  in Mali  had more  than  doubled  during  2000,  so  that,  applying  the  adjustment formula in the contract, EDM calculated that electricity and water tariffs be increased by 28.7 and 16.1 percent, respectively, for 2001. Since CREE was not yet in place, the Ministry of Mines, Energy and Water  reviewed  the  proposal  and  EDM  and  the  ministry  agreed  on  a  small  downward revision  based  on  using  a  slightly  different  diesel  price  index.  Later  that  year  the  government decided the price increase was too large and controversial, and EDM and the government agreed to reduce the price increases to 5 percent for electricity and 10 percent for water for the second half of  the year, with  the government paying EDM 10.6 billion CFA  francs  in  compensation  for  lost revenue. 

During  the year, EDM won high marks  for  its  efforts  to  reduce blackouts  and  improve customer relations. The blackouts would be eliminated only when Manantali came on line but, in the meantime, EDM improved the reliability and efficiency of the existing thermal plants and even brought in a 10 MW diesel generator temporarily to help get through the summer months of 2001. EDM’s approach to bill collection was now firmer, as might be expected, but also more polite. 

Problems Develop (2002‐2004) 

The  start up of Manantali  in  2002  exposed  serious problems  in  the  concession  contract. Manantali, located on the Senegal River, was a multi‐national project with a capacity of 200 MW. 

                                                           17 Direction Nationale de l’Electricité and Direction Nationale de l’Hydraulique 18 A fourth consortium led by SNC Lavalin and Eskom qualified but did not bid. Saur’s consortium included IPS

West Africa, a part of the Aga Kahn Group. 19 Converted at 750 CFA francs to the dollar.

10 

Page 11: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Mali had the rights to 52 percent of Manantali’s output while Senegal had rights to 33 percent and Mauritania to 15 percent. Manantali was overseen by a special multi‐national agency that, after an international competition, awarded the contract to operate and maintain the plant to Eskom, South Africa’s government‐owned electricity company. 

When  the  first  of Manantali’s  five  40 MW  turbines  started  to  produce  power  in  late January  2002,  the people of Mali  expected  a dramatic  reduction  in  electricity prices. EDM paid only 27 CFA francs per kilowatt‐hour (kWh) for the power it bought from the new dam, while it cost  the  company  roughly  140  CFA  francs  to  generate  a  kWh  by  burning  diesel. When  EDM applied the formula in the contract, however, it calculated that electricity and water prices should go  up  by  4.87  and  13.19  percent,  respectively,  in  2002  even  assuming  that Manantali  would gradually  increase output  that year. To  the public  it  seemed bizarre  that  another price  increase would be needed now that Manantali was finally producing. 

To make matters worse, 2002 was an election year. Konaré had decided not  to run  for a third term, and General ATT, the hero of the 1991 coup, had thrown his hat in the ring. Given that the government had increased prices in 1999 to help prepare EDM for privatization, the public had seen electricity prices rise by nearly 30 percent and water prices by nearly 40 percent between 1999 and 2002. Not surprisingly, all of  the candidates,  including ATT, campaigned against the energy and water price increases. ATT won the July election and assumed office shortly after. 

It took most of 2002, and the help of several consultants, to figure out the problems in the tariff adjustment  formula. At a  first glance  the  formula  looked sensible. But  the  formula applied the diesel price  index  to all of  the electricity  that EDM produced,  ignoring  the  fact  that  roughly half of EDM’s production was  from  the Sotuba and Sélingué dams. Worse and more subtle,  the formula  weighted  the  electricity  EDM  produced  and  the  electricity  it  purchased  (e.g.  from Manantali)  in a way  that gave no credit for shifting to cheaper purchased energy unless the unit price of  the purchased  energy  also declined.  In  short,  consumers did not get  the  full benefit of EDM’s hydro resources. (For a more detailed explanation see the appendix to this case.) 

But  if  the  formula didn’t make sense,  it was still a part of  the contract and  there was no agreement  about  what  to  replace  it  with.  EDM  was  particularly  unhappy  to  abandon  the protection of the contract by opening it to renegotiation. The new administration of President ATT asked EDM to rollback some of the 2002 price  increases for the  last two months of the year, and EDM and the government agreed on compensation of 12 million CFA francs for EDM. Soon after, EDM, using the formula, called for another 16 percent increase in electricity prices to go into effect in 2003. CREE, using some different assumptions but the same formula, calculated that only a 7.6 percent increase was needed for 2003. But the new government wanted electricity and water prices to go down by 9.6 and 10.0 percent, respectively. EDM complied, but it took most of the year for the firm and the government to agree on compensation of 7.2 billion CFA francs. 

11 

Page 12: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Early in 2003, during the discussion of that year’s tariff increase, the government removed the president of the CREE for “serious offenses”. The government didn’t provide any explanation, but the removed CREE president didn’t offer a public defense either. Some observers believe that the  first  CREE  president  had  been  corrupted  by  EDM—it  was  rumored  that  he  drove  a  car supplied by EDM, for example, and that he dined often with EDM’s managing director. But others say  that he was not corrupt but was removed because he  insisted  that  the government honor  its contract  with  EDM,  even  if  it  had  defects.  That  summer  the  commissioners  elected  another member  to be CREE’s  second president. The new president had  joined CREE only  in  July 2002, having replaced a commissioner who had resigned. The new president was an electrical engineer and former EDM employee who had risen to be EDM’s managing director approximately 15 years earlier but had then left the firm for another post in government. 

During 2003, the AFD and the World Bank sought ways to help CREE and EDM develop a more constructive relationship, including paying for consultants to help the two agencies develop a shared  financial model  to evaluate  the  implications of changes  in  tariffs or other circumstance. The idea was that a common model would make it easier to negotiate over tariff compensation and related  issues. But under  its new president, CREE became gradually more aggressive with EDM. Some observers credit the change to the recruitment of two senior EDM managers to  join CREE’s senior  staff.  One man, who  became  the  executive  director  of  CREE,  had  been  EDM’s  deputy director of investments in electricity, while the other had held a similarly senior post on the water side of EDM. The two were alleged to have brought to CREE valuable  information about EDM’s performance and where costs could be cut. But CREE’s president blamed EDM’s unconstructive attitude and reluctance to share data. Bouygues’ managers had a reputation in certain quarters for protecting their companies aggressively. And, given the conflict underway, EDM was particularly concerned that any data it supplied to build the shared financial model might be misused against it. The model‐building exercise soon had to be suspended. 

Matters came to a head in the beginning of 2004, when CREE proposed that electricity and water prices  should be  reduced  that year by  8.6  and  1.1 percent,  respectively, and without any compensation  to EDM. CREE had discarded  the  contract’s  tariff  formula as  too unfair, and had instead based  the  tariffs on  its own analysis of EDM’s costs. Over the next year CREE and EDM would debate, sometimes in the Bamako press, about whether EDM’s costs were high or not. EDM was criticized for the size of its expatriate staff and the management fees that it paid to Saur and other members of the consortium of investors. In its first three years EDM had an average of 12 to 13 expatriate managers on the payroll at an annual cost of between 1.5 and 1.9 billion CFA francs, an amount equal to roughly one quarter of the salaries of the over 5000 Malian’s who worked for the  company.  In  addition, EDM paid Saur  and others management  fees of between  1.2  and  1.7 billion CFA  francs  per  year.  It was  also  alleged  that EDM  hid  its  profits  by  keeping  excessive maintenance  reserves,  for  example, or providing  cellular  telephones  for all  the  senior managers and their families. 

12 

Page 13: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

To the public, the most telling evidence that something was wrong was the fact, reported by CREE, that Mali’s electricity rates were the highest in West Africa by a substantial margin. Most Malian electricity was sold at 140 to 180 CFA francs per kWh while other countries, including the land‐locked  Burkina  Faso,  charged  80  to  100 CFA  francs  per  kWh  (Exhibit  7).20 And  this was despite the increase in the proportion of Malian electricity generated by hydro from 52 percent in 2001  to  73  percent  in  2002  and  83  percent  in  2003. An  internal  study  by AFD  argued  that  the comparison was unfair because some West African countries (including Burkina Faso) subsidized their  electricity  sectors  and  because  EDM  suffered  from  the  small  scale  of  its  systems.  EDM produced  only  one‐third  the  electricity  of  neighboring  Senegal  and  one‐tenth  that  of  the  Ivory Coast  ,  for example, and roughly 20 of  the 34 cities or  localities  it served were  isolated  from  the national grid21 and depended on small and costly diesel generators. EDM was required to charge the same tariffs nationwide, so the very high costs of the isolated systems were averaged in with the cheaper cost of the main grid.  

While  the  critics  charged  that  EDM’s  operating  costs  were  too  high,  they  were  also concerned  that  its  investments were  too  low.  In 2001 EDM engaged Propraco, a branch of AFD responsible  for  promoting  private  investment,  to  help  raise  capital.  But  EDM  and  Propraco abandoned this effort within two years on the grounds that the constant controversies about tariffs made  it  impossible  to attract private  investors. As a private company, EDM was not eligible  for concessional  loans  or  grants  from  the World Bank, AFD  or most  other donors—those were  for government agencies only. EDM still might finance some investments through cash flow, but not nearly as much as everyone had hoped for. Things were not so bad on the electricity side for now: Manantali was coming on line (financed by the donors), although EDM still needed to continue to invest in extending the grid and improving access. On the water side, however, Bamako was fast running out of drinking water  treatment  capacity and new  treatment plants were needed  soon. And water pressure was often low because of lack of capacity in the distribution system. 

The Negotiations (2004‐2005) 

By mid 2004 it was clear to all parties that the concession contract had to be changed, and in October  the  government  and  EDM  signed  a  protocol  to  negotiate with  the  assistance  of  an international mediator  funded  by  the World  Bank.  The  protocol  called  for  negotiations  to  be completed by mid February 2005, but that deadline was later extended to March 2005 and then to July  2005.  There  had  been  a  series  of  three  formal  negotiating  sessions—in  Washington  in November, in Paris in January, and in Bamako in March—plus a number of technical meetings in‐between. However, progress was slow: at one session the government had agreed in principle to a 

                                                           20 Mali had a social tariff of 80 CFA francs for customers who consumed less than 50 kWh per month. Data from

CREE as summarized in Ibrahim Togola, Tom Burrell and Youssouf Sanogo, “Case Study Report: Mali, West Africa”, photocopied July 2004, p. 9.

21 Two other localities were served by electricity imported from the Ivory Coast.

13 

Page 14: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

lease  or  affermage  contract  and  at  another  EDM  had  dropped  its  demand  that  adequate compensation for 2004 be a condition for any broader agreement. 

Negotiations did not improve relations between EDM and CREE. In September 2004,  just before the protocol was signed, the new CREE executive director who had come from EDM died suddenly. An autopsy  confirmed poison was  the cause, which provoked  completely unfounded speculation  in the press that EDM might have played a role. Then  in the first formal negotiating meeting in November, EDM insisted that CREE should not participate but only observe. CREE was not a formal party to the contract, EDM argued, and was supposed to remain neutral in the event of disputes. Excluding CREE did not quiet it, however. In January, the same month as the second formal negotiating session, CREE announced that EDM was due no compensation for 2004. EDM had claimed a  loss of 7 billion CFA  francs but CREE argued  that EDM had earned a profit of 1 billion  CFA  francs  once  padded  expenses  were  excluded.  And  in  February  CREE  upped  its estimate of EDM’s profit to 3 billion, leaving a 10 billion franc difference between it and EDM. 

The negotiations  raised many  issues,  including whether EDM  should  remain  in private hands. Opinion seemed divided within the various offices and agencies of the Ministry of Mines, Energy and Water. Most officials agreed that EDM had made progress:  it was well on its way to meeting targets for increasing customers, for example, and productivity per employee was way up (see Exhibits 8 and 9). But the new water connections had been partially subsidized by some donor grants left over from when EDM was a public agency. And the concession had been sold to Mali as a means  of  attracting  private  investment, which  had  not  happened. Moreover,  some ministry officials thought that “any fool” could do as well as the new EDM managers given the substantial tariff increases they had been granted and the fact that the government agencies were now, for the most  part,  paying  their  electricity  bills.  Others  were  less  sure  that  tariffs  would  have  been increased or bills paid if the company were still in public hands.  

Another  basic  issue was whether  converting  from  a  concession  to  a  lease  or  affermage contract would  improve matters. Under affermage,  two companies would be established: an asset holding company owned by  the government and a private operating company  that would  lease the assets from the government.22 The tariff would consist of distinct components, such as:  

                                                           22 In the negotiations the government insisted on two separate EDM operating companies: one for electricity and one

for water. EDM thought two operating companies would increase overhead but had agreed.

14 

Page 15: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Tariff = R1 + R2 + R3 +R4 + R5, 

where R1 was the operating cost paid to the operating company, R2 a fuel cost pass‐through, R3 any  taxes  the government chose  to  levy on  the operating company, R4 a development charge  to help  finance new  investment and R5 a charge  to pay off  the asset holding company’s debt. The operating company would collect the tariff and pass on R3 to the government and R4 plus R5 to the asset holding company. The  lease contract would  include a  formula  for R1 and R2, with R1 depending in part on performance. The government would set R4 and R5 to cover the investments it thought consumers needed and could afford.  

EDM and its owners at Bouygues believed that affermage was more practical than either a management  contract  or  a  concession.  Affermage  avoided  the  problems  created  under  a management contract because the managers and the board of directors of the operating company were responsible to different shareholders. And affermage avoided the difficulties that concessions had  experienced  in  attracting  private  capital,  especially  in  sub‐Saharan Africa.  In  fact  affermage would reduce  the cost of capital because  the asset holding company, owned by  the government, would be eligible to receive concessional loans from donors. A concessional loan from the World Bank carried an interest rate of only two to three percentage points, for example, roughly one fifth the cost of private capital.  In addition, affermage would remove a source of friction between the government  and  EDM  by  giving  the  government  the  flexibility  to  decide  when  and  where investments were  needed.  Affermage  supporters  recognized  that  it was  impossible  to  keep  the operator completely out of  investment decisions, however,  in as much as the  level of  investment determined  the  level  of  operating  costs  and  performance.  Indeed,  EDM  proposed  that  the operator’s  budget  include  an  investment  allowance  so  that  it  could  make  small  investments without having to secure approval from the asset holding company. 

Finally,  there was  the  issue of what  role,  if  any,  a  regulatory  agency  should play  in  an affermage system. Some critics argued  that Mali’s problems stemmed  in part  from combining  the Anglo‐Saxon  and  the  Francophone  approaches  to  regulation.  The  Anglo‐Saxon  concept  of  an independent  regulator  with  substantial  discretion  was  at  odds,  they  claimed,  with  the Francophone notion of a contract.   But others claimed that it had been useful to have a regulator with discretion when the contract had proven so flawed. 

The last formal negotiating session was scheduled for July 11 in Washington.  

15 

Page 16: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 1 Characteristics of Developing Countries by Region   

Region 

 GDP 2004  

(US$ millions) 

 Population 2004 (thousands) 

GDP per capita 2004 

(US$) 

 Percent urban 

2003 Sub‐Saharan Africa  719,022  543,990  760  33 East Asia and Pacific  2,367,508  1,870,228  1,270  39 Europe and Central Asia  1,768,088  472,073  3,750  64 Latin America and the Caribbean  2,018,715  542,322  3,730  77 Middle East and North Africa  600,256  293,994  2,040  59 South Asia  878,785  1,447,673  610  39 World (including developed)  40,887,837  6,345,127  6,440  49 Sources: GDP and population for low and middle income countries in 2004 as reported by World Bank Group at http://www.worldbank.org/data/quickreference/quickref.html. Percent urban for low and idle income countries as reported by World Bank, World Development Indicators 2005, World Bank, table 3.10 at http://www.worldbank.org/data/wdi2005/wditext/Tables3.htm.  

Exhibit 2 Access to Electricity in Developing Countries by Region, 1996 and 2002 

   All households 

 Rural households 

Urban households 

Region  1996  2002  1996  2002  1996  2002 Sub‐Saharan Africa  n.a.  15%  7%  8%  47%  54% East Asia/Pacific  n.a.  54%  n.a.  52%  n.a.  88% East Europe/Central Asia  n.a.  99%  n.a.  96%  n.a.  100% Latin America and the Caribbean  n.a.  79%  40%  45%  92%  93% Middle East/North Africa  n.a.  88%  47%  41%  92%  96% South Asia  n.a.  31%  26%  29%  83%  86% Note: “n.a.” means not available. Source: The figures are from countries in the regions for which detailed access data are available; Antonio Estache, “What do We Know about Sub-Saharan Africa’s Infrastructure and the Impact of its 1990s Reforms?”, World Bank draft working paper, May 24 2005.

16 

Page 17: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 3 Access to Improved Water Sources in Developing Countries 

by Region, 1996 and 2002    

All households  

Rural households Urban 

households Region  1996  2002  1996  2002  1996  2002 

Sub‐Saharan Africa  53%  64%  44%  54%  79%  83% East Asia/Pacific  75%  75%  69%  70%  90%  88% East Europe/Central Asia  92%  87%  86%  79%  97%  97% Latin America and the Caribbean  82%  90%  66%  80%  94%  96% Middle East/North Africa  80%  85%  70%  75%  86%  91% South Asia  76%  72%  73%  68%  92%  84% Source: The figures are from countries in the regions for which detailed access data are available; Antonio Estache, “What do We Know about Sub-Saharan Africa’s Infrastructure and the Impact of its 1990s Reforms?”, World Bank draft working paper, May 24 2005.  

Exhibit 4 Access to Telecommunications in Developing Countries 

by Region, 1996 and 2002   Telephone 

subscribers per 1000 people 

Mainline subscribers per 1000 people 

Cellular subscribers per 1000 people 

Region  1996  2002  1996  2002  1996  2002 Sub‐Saharan Africa  22  90  20  30  2  59 East Asia/Pacific  62  140  53  72  9  69 East Europe/Central Asia  180  475  173  219  7  257 Latin America and the Caribbean  157  378  145  193  12  188 Middle East/North Africa  98  257  90  123  8  132 South Asia  17  61  16  33  1  29 Source: The figures are from countries in the regions for which detailed access data are available; Antonio Estache, “What do We Know about Sub-Saharan Africa’s Infrastructure and the Impact of its 1990s Reforms?”, World Bank draft working paper, May 24 2005.  

17 

Page 18: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 5 Map of Africa with Countries with 

Electricity Concessions or Management Contracts, 2005  

  

Source: Anton Eberhard, “Regulation of Electricity Services in Africa: An Assessment of Current Challenges and an Exploration of New Regulatory Models”, paper presented at the conference Towards Growth and Poverty Reduction: Lessons from Private Participation in Infrastructure in Sub-Saharan Africa”, Cape Town, June 6-7, 2005, p. 5.

18 

Page 19: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 6 Status of Water and Electric Power PPIs in Sub‐Saharan Africa, 2005 

   

Country 

Popula‐tion (000), 2002 

GDP in US$ capita, 2002 

   

PPI 

  

Years in force 

   

Type 

   

Notes Central Africa 

           

Cameroon  15,729  702  Power  2001‐present 

Concession  In crisis 

Central African Republic 

3,819  332  Water  Lease  1991‐present (?) 

Saur withdraws in 2000.  Not sure if others continue. 

Chad  8,348  232  Power  n.a.  n.a.  Recently terminated Congo  3,633  705         Democratic Republic of Congo 

51,201  91  IPP  n.a.     

Equatorial Guinea 

481  2,448  Power  n.a.  n.a.   

Gabon  1,306  4,353  Water and power 

1997‐present 

Concession  Considered successful 

Sao Tome and Principe 

157  349         

Eastern Africa 

           

Burundi  6,602  153  IPP  n.a.     Djibouti  693  764         Eritrea  3,991  172         Ethiopia  68,961  121         Kenya  31,540  320  IPP  n.a.           Water  n.a.  n.a.  Contract terminated as 

a result of irregularities Rwanda  8,272  291  Power  n.a.  Management   Somalia  9,480  n.a.  IPP  n.a.     Uganda  25,004  353  Water 

(Kam‐pala) 

2002‐2003  Management  Ondeo did not exercise option to extend contract 

      Power  2005‐present 

Concession  With the South African electricity company (Eskom) 

Note: “n.a.” means not available; “IPP” is an independent power producer. Sources: see p. 23.

19 

Page 20: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 6 (continued)  

   

Country 

Popula‐tion (000), 2002 

GDP in US$ capita, 2002 

   

PPI 

  

Years in force 

   

Type 

   

Notes Southern Africa 

           

Angola  13,184  621         Botswana  1,770  3,968         Lesotho  1,800  640  Power  n.a.  Management   Malawi  11,871  142  Power  2001‐2003  Management  Initially successful, 

later controversial Mozambique  18,537  222  Water 

(Mapu‐to) 

1999‐present 

Lease  Saur withdrew from consortium in 2001 but local investors stayed 

      Power  n.a. ‐2001  Management  Saur withdraws Namibia  1,961  2,230         Saint Helena  5  n.a.         South Africa  44,759  4,072  IPP  n.a.           Water 

(Dolphin Coast) 

1999‐present 

Concession  Investment program renegotiated in 2001; Saur withdrew but others remain 

Swaziland  1,069  1,580  IPP  n.a.     Tanzania  36,276  201  IPP  n.a.           Power  2002‐2004  Management  Considered successful       Water 

(Dar‐es‐Salam) 

n.a.  n.a.  Biwater contract terminated 

Zambia  10,698  404  IPP  n.a.     Zimbabwe  12,835  528  IPP  n.a.           Water  n.a.  n.a.  Biwater withdraws for 

financial reasons Note: “n.a.” means not available; “IPP” is an independent power producer. Sources: see p. 23.

20 

Page 21: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 6 (continued)  

   

Country 

Popula‐tion (000), 2002 

GDP in US$ capita, 2002 

   

PPI 

  

Years in force 

   

Type 

   

Notes Western Africa 

           

Benin  6,558  442         Burkina Faso  12,624  263         Cape Verde  454  1,599         Ivory Coast  16,365  783  Water  1960‐

present Concession (1960‐1967, 1988‐present) and lease (1967‐1988) 

Saur. The longest lived PPI in Sub‐Saharan Africa.  Still in operation despite civil unrest since 1999. 

      Power  1990‐present 

Lease  Saur. The reference privatization in electricity.  Still in operation despite civil unrest since 1999. 

Gambia  1,388  356  Water and power 

1992‐1993   Lease  Contract unilaterally terminated  after military coup 

Ghana  20,471  424  IPP  n.a.           Water  n.a.    World Bank withdraws 

support due to lack of transparency in selection process 

Guinea  8,359  586  Water (Con‐kary) 

1989‐2000  Lease  Contract renewal negotiations with Saur failed over disagreements on tariffs 

      Power  1994‐2004  Concession  Saur.  Not renewed? Guinea‐Bissau 

1,449  161  IPP  n.a.     

Liberia  3,239  200         Note: “n.a.” means not available; “IPP” is an independent power producer. Sources: see p. 23.

21 

Page 22: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 6 (continued)  

   

Country 

Popula‐tion (000), 2002 

GDP in US$ capita, 2002 

   

PPI 

  

Years in force 

   

Type 

   

Notes Western Africa, continued 

           

Mali  12,623  278  Water and power 

1995‐98, 2000‐present 

Management (1995‐98),  concession (2000‐ present 

In crisis 

      IPP  n.a.    Manantali dam Mauritania  2,807  499  Power  (attempt 

2001‐2002) 

  Privatization suspended due to insufficient bidders 

Niger  11,544  207  Water  n.a.  n.a.   Nigeria  120, 911  273  IPP  n.a.     Senegal  9,856  628  Water  1996‐

present Lease  Considered successful, 

although government has failed to pay bills from 2002. Contract up for renewal in 2006 

      Power  1998‐2000  Concession  Concession cancelled for lack of investment.  Concession offered a second time but negotiations with short‐listed bidders fail. 

Sierra Leone  4,764  181         Togo  4,801  318  Power  2000‐2002  Concession  World Bank withdrew 

support because of disputes between government and concessionaire 

Note: “n.a.” means not available; “IPP” is an independent power producer. Sources: see p. 23.

22 

Page 23: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 6 (continued)  

   

Country 

Popula‐tion (000), 2002 

GDP in US$ capita, 2002 

   

PPI 

  

Years in force 

   

Type 

   

Notes Western Indian Ocean 

           

Comoros  747  342         Glorioso Islands 

n.a.  n.a.         

Juan de Nova Islands 

n.a.  n.a.         

Madagascar  16,916  209  IPP  n.a.     Mauritius  1,210  4,547  IPP  n.a.     Reunion  745  n.a.         Seychelles  80  8,443         

Note: “n.a.” means not available; “IPP” is an independent power producer. Sources: This list almost surely contains inaccuracies. It was compiled primarily from World Bank data bases; Castalia Strategic Advisors, “Experience with Private Participation Initiatives in sub-Saharan Africa: What are the Lessons for Future Policy?”, paper presented at the conference Towards Growth and Poverty Reduction: Lessons from Private Participation in Infrastructure in Sub-Saharan Africa”, Cape Town, June 6-7, 2005 ; Anton Eberhard, “Regulation of Electricity Services in Africa: An Assessment of Current Challenges and an Exploration of New Regulatory Models”, paper presented at the conference Towards Growth and Poverty Reduction: Lessons from Private Participation in Infrastructure in Sub-Saharan Africa”, Cape Town, June 6-7, 2005; Plane ; Richard Schlirf Rapti, “The Privatization of EDM S.A. in Mali: Doomed by Design”, photocopied draft, MacroConsulting, May 30, 2005; and Jean Claude Berthelemy et al., Privatization in Sub-Saharan Africa: Where do We Stand?, OECD Development Center Studies (Paris: OECD, 2004), esp. pp. 59-62, 75-79, and 102-107.

23 

Page 24: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 7 Electricity Tariffs in West Africa in CFA Francs per kWh, 2002 

  

Figure 3: Electricity Tariffs in West Africa (CFA/kWh)

-

20

40

60

80

100

120

140

160

180

Benin BurkinaFaso

Côted'Ivoire

Gambia Ghana Mali Niger Nigeria

Pric

e pe

r kW

h (F

CFA

)

Special tariff(<10kWh/month -1 kW)

Domestic use singlephase (<200kWh/month -2 kW)

Domestic use three phase(<600kWh/month - 6 kW)

Commercial use threephase (<1800kWh/month -12 kW)

Semi-industrial(<2500kWh/month -20kW)

Industrial (<3500kWh/month -250kW)

                     Source: Presentation of CREE at the conference Energy Week 2003, Bamako, October 2003 as reported in Ibrahim Togola, Tom Burrell and Youssouf Sango, “Case Study Report: Mali, West Africa”, photocopied, July 2004, p. 9.  

24 

Page 25: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 8 Technical Performance of EDM, 1990‐2003 

    1990  1995  1999  2000  2001  2002  2003 Electricity                 Localities served  14  16  28  31  32  32  32   Capacity (MW)                     Thermal  34.8  34.8  34.8  71  92.7  92.7  132.7       Hydro  50  50  50  50  92.62  92.62  91.01       Total  84.8  84.8  84.8  121  185.32  185.32  223.63   Production (GWh)  233.5  312.7  399.7  470.2  521.4  590.2  631.0   Consumption 

(GWh)  176.3  242.6  306.3  349.0  

386.5  

429.6  464.0.   Technical losses  n.a.  n.a.  n.a.  25.8%  25.8%  27.2%  26.5%   Clients  41,062  66,174  75,279  81,323  86,117  118,806  131,029   Households with 

electricity  6.0%  7.1%  9.4%  9.1%  9.3%  12.0%  13%   Employees per 1000 

clients  n.a.  n.a.  n.a.  12.83  12.26  8.53  8.24   Network                     Kilometers  n.a.  n.a.  n.a.  2,920.0  2,980.2  3,336.9  3,589.4       Meters/client  n.a.  n.a.  n.a.  36.2  34.9  28.3  27.6   Investment (mil. Of 

CFA francs)  n.a.  n.a.  n.a.  n.a.  9,774  10,410.3  9,027.7 Water                 Capacity (000 m3)  n.a.  n.a.  n.a.  n.a.  71,100  72,300  72,300   Production (000 m3)  n.a.  n.a.  n.a.  n.a.  49,778  54,311  56,994   Sales (000 m3)  n.a.  n.a.  n.a.  n.a.  30,668  34,769  38,679   Technical losses  n.a.  n.a.  n.a.  35.4%  38.4%  36.0%  32.2%   Clients  n.a.  n.a.  n.a.  56,034  62,222  77,705  82,755   Employees per 1000 

clients  n.a.  n.a.  n.a.  8.29  7.56  5.82  5.83   Network                     Kilometers  n.a.  n.a.  n.a.  1,949.4  2,050.3  2,138  2,193.2       Meters/client  n.a.  n.a.  n.a.  34.8  33.0  27.5  26.5   Investment (mil. Of 

CFA francs)  n.a.  n.a.  n.a.  n.a.  4,013.8  5,585.7  3,615.2 Source: Monistere des Mines, de l’Energie et de l’Eau, Direction Nationale de L’Energie, Resultats et Previsions de Developpement du Secteur de l’Electricite au Mali, Année 2003 (Bamako: 2004); Ibrahim Togola, Tom Burrell and Youssouf Sango, “Case Study Report: Mali, West Africa”, photocopied, July 2004, pp. 48-49; and Richard Schlirf Rapti, “The Privatization of EDM S.A. in Mali: Doomed by Design”, photocopied draft, MacroConsulting, May 30, 2005, pp. 19-20; Stone and Webster Consultants, “Mali Case Study”, draft report for KfW, April 2005, pp. 16-17.

25 

Page 26: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Exhibit 9 Financial Performance of EDM, 1996‐2003 

(millions of CFA francs)    1996  1997  1998  1999  2000  2001  2002  2003 Electricity sales  18,521  20,216  23,474  25,327  33,024  37,622  45,441  43,904 Water sales  4,969  5,049  5,701  7,074  7,747  9,226  11,542  11,159 Direct transfers from government 

0  0  0  0  0  10,647  0  7,200 

Other sales and outputs (1) 

2,175  920  4,652  3,351  4,756  7,667  12,743  7,806 

Total operating revenue 

25,665  29,443  33,009  34,961  45,527  65,162  69,725  70,069 

Operating expense  ‐19,694  ‐22,603  ‐28,414  ‐31,484  ‐44,152  ‐54,945  ‐52,976  ‐53,095 EBITDA  5,971  6,840  4,595  3,477  1,375  10,217  16,749  16,974 Depreciation  ‐7,854  ‐8,735  ‐11,346  ‐13,100  ‐11,290  ‐9,686  ‐8,161  ‐16,463 EBIT  ‐1,883  ‐1,895  ‐6,751  ‐9623  ‐9,915  531  8,588  511 Financial income  ‐1,752  ‐2,559  ‐2,930  ‐3,489  ‐2,986  ‐1,602  ‐3,240  ‐3,749 Other income  n.a.  n.a.  n.a.  n.a.  4,762  ‐32  877  3,740 EBT  ‐3,635  ‐4,454  ‐9.681  ‐13,112  8,139  ‐1,103  6,225  502 Taxes  n.a.  n.a.  n.a.  n.a.  ‐349  ‐380  ‐479  ‐509 Net income  n.a.  n.a.  n.a.  n.a.  ‐8,488  ‐1,483  5,746  ‐8 

Notes: ‘n.a.’ means note available. (1) Rent for meters and transfers from international financial institutions.

Sources: 1996-1999 from EDM annual reports; 2000-2003 from Richard Schlirf Rapti, “The Privatization of EDM S.A. in Mali: Doomed by Design”, photocopied draft, MacroConsulting, May 30, 2005, pp. 19-20.  

26 

Page 27: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

Appendix Tariff Adjustment Formula for Electricity 

The Formula 

The  average  tariff  on  January  1  in  a  future  year  t,  Pt,  is  calculated  by multiplying  the average tariff on January 1, 2000, P0, times an index, Indext:  

Pt =  Indext  x  P0  

The index is the sum of four components: 

Indext  =   k1  +  k2 (Gt/G0) (Et/E0)   + k3 (St/S0)   + k4 [I1 (Dt/D0) + I2 (At/A0)] 

where    k2  ,  k3  and  k4    are  the  weights  attached  to  replacement  parts,  salaries,  and  fuel  and purchased electricity respectively, and where 

k1   = 1 ‐  k2  ‐ k3 ‐ k4   

Efficiency incentive.  The first component of the index, k1 , provides an efficiency incentive because as long as k1 is positive tariffs will increase less than proportionally with inflation. 

Spare parts.  The second component of the index adjusts for changes in spare parts costs. G is an OECD index of spare parts prices and E is the exchange rate of the CFA franc for the euro. 

Salaries.   In the third component S is an index of the average salaries of civil servants in Mali. 

Fuel  and  purchased  electricity.  In  the  last  component  I1  and  I2  are,  respectively,  the proportion  of  EDM’s  electricity  that  it  produces  its  self  and  the  proportion  that  it  buys  from independent producers  (e.g.  from Manantali and,  for  two  isolated communities near  the border, from  the Ivory Coast).   D  is an  index of diesel fuel prices  in Bamako  in CFA francs and A  is the average price in CFA francs that EDM pays for purchased electricity. 

Problems 

When  the  Manantali  power  station  came  on  line  it  revealed  two  problems  with  the treatment  of  fuel  and  purchased  electricity.    First,  the  diesel  fuel  price  is weighted  by  I1,  the proportion of energy produced by EDM, even though roughly half of the energy EDM generates is by hydro.   Second,  the mix of generated  and purchased  electricity do not necessarily  affect  the price  index because both generated and purchased electricity are weighted by the proportions of 

27 

Page 28: Energie du Mali

EDM (Energie du Mali) ______________________________________________________ CR14‐05‐1811.0 

electricity from the two sources (I1 and  I2) rather than by the proportions times the relative costs of the  two  sources.    For  example,  if EDM  shifts  from  its  own  costly diesel  generation  to  cheaper Manantali electricity, the index will not decline as long as the prices of diesel and purchased power do not change (that is if  Dt/D0 and At/A0 are zero). 

The consultants also found other problems with the formula.  For example, using k1  as the efficiency incentive means that the incentive to become more efficient increases with inflation and there is no incentive if there is no inflation.  There is no reason to believe that the opportunities for efficiency gains increase proportionately with inflation.  

28