environment management plan (emp)environmentclearance.nic.in/writereaddata/online/eds/0_0... ·...

41

Upload: others

Post on 01-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

  • Environment Management Plan (EMP)

    Proposed Development of All-Weather Greenfield Captive Jetty

    at Nandgaon, Taluka Palghar, Dist. Thane, Maharashtra

    Submitted to

    Ministry of Environment, Forest & Climate Change

    (MoEF&CC), New Delhi

    Infrastructure Limited, Mumbai

  • Environment Management Plan1

    Proposed Development of All-Weather Multi Cargo Captive Jetty in a Greenfield Site at Village Nandgaon, Taluk Palghar, Dist. Thane, Maharashtra

    Environmental

    Concern Objectives Environmental Management Plan- Mitigation Measures

    (MM) Suggested Responsibility for

    implementation of MM

    CONSTRUCTION PHASE

    1. Plan to control environmental and associated impacts - Orientation for the contractors and workers

    To ensure that the Contractor, subcontractors and workers understand and have the capacity to ensure that the environmental requirements for mitigation measures are implemented. To ensure physical safety of workers.

    1. On-site briefing/training for the contractors and workers on the environmental requirement of the project. Record attendance and achievement.

    2. Agreement on critical areas to be considered and necessary mitigation measures, among all parties who are involved in project activities.

    3. Periodic review sessions to be conducted every six months. 4. Providing adequate warning signs. 5. Providing every worker with hard hat and safety shoes. 6. Establish all relevant safety measures as required by law

    and good engineering practices. 7. Contractor shall instruct his workers in health and safety

    matters, and require the workers to use the provided safety equipment.

    Environmental Management Cell (EMC) of JSW Infrastructure Limited (JSW IL_ to observe the proper implementation of training and safety measures.

    2. Water quality

    To prevent adverse water quality impacts due to negligence and ensure unavoidable impacts are managed effectively.

    1. Proper construction measures, maintenance and management including training of operators and workers to avoid pollution of water bodies by the considerate operation of construction machinery and equipment and reporting and feedback by EMC.

    EMC of JSW IL to observe and periodically monitor the water environment

    1 Revised with reference to Minutes of MoEFCC’s EAC (Infrastructure Development, Coastal Regulation Zone, Building/Construction and Miscellaneous projects) meeting held on 24th – 26th June, 2015 (149th Meeting), Ahenda Item 3.21, page no, 41.

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 1

  • Environmental Concern Objectives

    Environmental Management Plan- Mitigation Measures (MM) Suggested

    Responsibility for implementation of MM

    2. Storage of lubricants and fuels away from the coastal water. 3. No stockpile next to water bodies. 4. Proper disposal of solid waste from construction activities

    and worker camps. 5. Provision of mobile STPs for disposal of sewage. Treated

    sewage will be utilized for irrigation of greenbelt. There shall be no discharge of untreated sewage in marine water.

    6. Provision of settling tank effluent from coal stockyard. 7. Emergency responders will be trained and equipped in

    accordance with OSHA (Occupational Safety and Health Administration) standards on emergency response.

    8. Periodic monitoring of coastal water quality. 9. Reclamation on the landward/port backup side of the an

    embankment bund to prevent back wash of dredged spoil in the sea water, thus control the water turbidity.

    10. Dredging to be carried out as per Dredging Plan given as Annex I. Dredging shall be completed in fair weather (i.e during October to March.

    3. Water Resources

    To ensure impacts on local water supply caused by construction activities are minimized.

    1. Availability of water will be assessed to evaluate the impact on community resources.

    2. Project water will be obtained from pipeline if available, or by tankers. There shall no withdrawal of ground water in CRZ area.

    3. Guidelines will be established to minimize the wastage of water during construction operations and at camp sites.

    EMC of JSW IL shall ensure to avoid impact on the water resources.

    4. Noise To minimize noise level and ground vibrations during construction operations.

    1. Install, maintain and monitor all requisite mitigation, as per contract. All noisy machinery shall be fitted with acoustic insulation. Installation of silencer and muffler on individual

    EMC of JSW IL shall ensure proper implementation and monitor periodically to avoid

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 2

  • Environmental Concern Objectives

    Environmental Management Plan- Mitigation Measures (MM) Suggested

    Responsibility for implementation of MM

    machines. 2. Installation and operation of DG sets shall comply with the

    guidelines of CPCB.. 3. All engines, winches and gear on the dredgers will be

    acoustically treated to minimize noise during dredging. 4. Workers operating in the high noise areas will be provided

    with earplugs. 5. Monitoring of noise levels will be conducted during

    construction phase of the project. 6. In case of exceeding of pre-determined acceptable noise

    levels by the machinery will require the contractor(s) to stop work and remedy the situation prior to continuing construction.

    7. Job rotation/automation, use of ear plugs, etc. to reduce the exposure to noise

    8. Noise levels in the construction phase will conform to the standards laid down by the competent authorities including the Central or State Pollution Control Board and under the Environment (Protection) Act, 1986.

    any noise pollution.

    5. Air quality

    To minimize effectively and avoid complaints due to the airborne particulate matter released to the atmosphere.

    1. Control all dusty materials at source. 2. Stockpiled soil and sand shall be adequately wetted before

    loading, particularly in windy conditions. 3. Vehicles transporting soil, sand and other construction

    materials shall be covered. 4. Vehicles and construction equipment will be compliant to the

    applicable emission regulations. 5. Construction equipment and vehicles will be turned off when

    not in use.

    EMC of JSW IL shall implement and monitor to avoid air pollution.

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 3

  • Environmental Concern Objectives

    Environmental Management Plan- Mitigation Measures (MM) Suggested

    Responsibility for implementation of MM

    6. Surface roads are black topped to avoid fugitive dust. 7. Regular spraying of water on the stacks of fine aggregate to

    minimize entrainment of fugitive emissions. 8. Greenbelt development for mitigation of Air Pollution.

    6. Land Environment

    To avoid soil contamination and change in land use pattern

    1. Contractors to instruct and train workforce in the storage and handling of materials that can potentially cause soil contamination.

    2. Segregation of organic and inorganic solid waste. 3. Provision for collection and conveyance of municipal wastes

    from labor hutments 4. Decomposable domestic solid wastes will be composted on-

    site in a composting pit. No solid waste will be discharged into the water/CRZ area.

    5. Port development on reclaimed land. 6. No acquisition of private/forest land. Hence, no displacement

    of local people. 7. Construction material will be sourced from approved local

    quarries.

    EMC of JSW IL shall ensure solid waste management plan is in place to avoid any impact on the land environment.

    7.Labour Camp Location and Operation

    To ensure that the operation of work camps does not adversely affect the surrounding environment and residents in the area.

    1. Labour camps shall be located outside the CRZ area. 2. Water and sanitary facilities shall be provided for workers

    and employees 3. Solid waste and sewage shall be managed according to the

    state PCB and local regulations. Decomposable Solid waste will be composted on-site in a composting pit and used in the greenbelt as manure

    4. After construction phase, all debris and waste shall be removed and appropriately disposed. All temporary structures, including shelters and toilets shall be removed.

    The EMC of JSW IL shall inspect and report that the camp has been vacated and restored to pre-project conditions as far as is reasonably practicable.

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 4

  • Environmental Concern Objectives

    Environmental Management Plan- Mitigation Measures (MM) Suggested

    Responsibility for implementation of MM

    5. Exposed areas shall be planted with suitable vegetation.

    8. Social Impacts To engage local workforce and community.

    1. Use local labour for the manual work. 2. Engage local educated people through proper training. 3. CSR activity plan for the socio-economic development of the

    local community. 4. The project affected people, if any due to the land

    acquisition will be rehabilitated or compensated as per the norms laid down by the concerned agency of State/Central Government.

    Port management to encourage the local support for the project.

    9. Mangroves To ensure no adverse impacts on the mangroves.

    1. Nearest mangroves are more than 5 km from the Port construction site. No activity is proposed near the mangrove stands. No possibility of damage/adverse impact of any kind is envisaged on the mangroves.

    EMC of JSW IL shall ensure that there are no adverse impacts on the mangroves in the vicinity of the construction site.

    10. Compliance reporting to MoEFCC RO

    To ensure six monthly reporting of compliance of EC conditions to the MoEFCC RO

    1. Six monthly reporting of compliance of EC conditions to the MoEFCC RO shall be submitted as per proviso of EIA Notification, 2006.

    2. Compliance of the conditions laid down in Consent to Establish from Maharashtra Pollution Control Board shall be reported as per prescribed frequency.

    3. EMP measures prescribed for the construction phase of the project in the EIA Report and by CWPRS, Pune will be complied with, and reported at prescribed frequency

    4. Budgetary provision for implementation of EMP is given in Annex II.

    EMC of JSW IL shall ensure compliance.

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 5

  • Environmental Concern Objectives

    Environmental Management Plan- Mitigation Measures (MM) Suggested

    Responsibility for implementation of MM

    OPERATIONAL PHASE

    1. Air Quality To minimize and monitor the air pollution.

    1. Coal and other dusty cargoes will be conveyed through closed conveyor and stored in closed/water sprinkled /covered stack yard.

    2. A windshield with a wire mesh fencing with fast growing creepers, or air conducting geotextile cladding up to a height of 14 m around the coal/other bulk stack yard shall be provided for control of wind generated dust.

    3. Continuously sprayed with water sprinkler to siege any fugitive emissions.

    4. Lose material will be conveyed through closed conveyors and bagged in a closed enclosure.

    5. Wagon loading shall be fitted with dust arresting/capturing devices to comply with applicable emissions standards

    6. All internal roads will be black topped/RCC/Paver block; hence no dust emission is envisaged.

    7. Non road areas will be paved using paver blocks 8. Continuous air monitoring will help in putting other measures

    in place for reducing the pollution levels in atmosphere, if any.

    9. Green belt development to control the fugitive emissions.

    EMC of JSW IL shall ensure the conveyor and storage facility of cargoes are in place and implemented. Continuous air monitoring system has to be in place to detect any change in the air quality to ensure the proper implementation of MM.

    2. Water Quality To minimise and monitor the water pollution.

    1. Effluent from the Stack Yards of the Solid Cargoes will be collected in garland canal and sand piping pit system and the decanted clear water will be used for dust suppression on the coal stockpiles.

    2. Dried coal sludge from the sand piping pit which will have significant fuel value which will be distributed among the villagers as domestic fuel.

    EMC of JSW IL shall ensure the proper implementation of the facilities to control any water pollution. Also, ensure the proper implementation of OSCP.

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 6

  • Environmental Concern Objectives

    Environmental Management Plan- Mitigation Measures (MM) Suggested

    Responsibility for implementation of MM

    3. Sewage generated will be treated in a system of distributed STPs. Treated water will be re-used after disinfection in horticulture.

    4. Effluent from the liquid storage and workshops shall be collected and treated in an oil skimmer. The oily sludge will be disposed in a TSDF. Clear water will be taken to a STP for treatment.

    5. Oil spill contingency plan (OSCP) to monitor and control oil pollution if any.

    6. Prevention of Marine pollution as per the guideline MARPOL, 1973, modified by 1978 (MARPOL, 73/78)

    7. No product other than permitted under the CRZ Notification, 2011 shall be stored in the CRZ area

    Continuous monitoring need to be carried out to detect any change in the water quality to ensure the proper implementation of MM.

    3. Water Resources

    To minimize the impacts on local water resources and supply

    1. Water requirement during the operation phase will be met from MIDC, through tankers or by Sea Water RO at the start of Operations phase

    2. Treated water shall be used for dust suppression on the stockpiles and green belt development

    3. Guidelines will be established to minimize the wastage of water during Port operations.

    EMC of JSW IL shall implement and take measures towards the restoration of water resources.

    4. Noise To minimize noise level increases and ground vibrations during construction operations.

    1. Install, maintain and monitor all requisite mitigation. 2. All machinery shall be fitted with acoustic insulation or will be

    acoustically treated. 3. Installation of silencer/dampner on individual machines. 4. Installation and operation of DG sets shall comply with the

    guidelines of CPCB.. 5. Job rotation/automation, use of ear plugs, etc. to reduce the

    exposure to noise

    EMC of JSW IL shall ensure proper implementation and monitor periodically to avoid any noise pollution.

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 7

  • Environmental Concern Objectives

    Environmental Management Plan- Mitigation Measures (MM) Suggested

    Responsibility for implementation of MM

    5. Ecology and Environment

    To minimize the adverse impact on its environment and ecology.

    1. Nearest mangroves are more than 5 km from the Port construction site. No activity is proposed near the mangrove stands. No possibility of damage/adverse impact of any kind is envisaged on the mangroves.

    2. No cutting of trees is envisaged. Aesthetic of the area will be ensured with the proper implementation of air pollution preventive measures at source.

    Port management shall ensure no such adverse impact on ecology and its environment.

    6. Navigation and Port operation

    To ensure no damage to the fishing boats, nets.

    1. The vessels calling on the Port will move in a well-defined channels marked with Marker Buoys to avoid any damage to the fishing nets

    2. If any instance of damage of nets comes to the knowledge of the Port, replacement of net/monitory compensation will be provided to the fishermen after necessary due diligence

    Port Officer shall ensure such operational activity

    7. Fishery Resources

    To ensure no adverse impact on the fishing activity due to operation of the Port.

    1. Bilge water and waste water from vessels shall not be release in around the port area

    2. Strict compliance of MARPOL, 73/78 guideline for prevention of marine pollution in the port area.

    3. A Detailed study has been commissioned to study impact assessment on fish production due to port development to the Central Marine Fishery Research Institute (CMFRI), Indian Council of Agricultural Research, Govt. of India. Its recommendations will be followed to ensure that no negative impact is exerted on the fishing activity in the area. Rapid Survey Report by CMFRI, June 2015 is given in Annex III.

    EMC and Port Officer of JSW IL shall ensure the proper implementation of the MM.

    8. Existing Infrastructure

    To ensure no such adverse impact on the existing infrastructure.

    1. Road will be developed without affecting the existing infrastructure.

    2. Present road will be strengthened and widened through Public Works Department (PWD).

    Port management ensures such functional activity

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 8

  • Environmental Concern Objectives

    Environmental Management Plan- Mitigation Measures (MM) Suggested

    Responsibility for implementation of MM

    3. Land requirement for such roads is much less and if any private land is involves shall be purchased from land owners with adequate compensation.

    9. Solid Waste Management

    Ensure adequate disposal options for solid waste.

    1. Solid waste management plan to identify locations for the storage and disposal.

    2. Segregation of organic and inorganic solid waste. Provision for collection and disposal of municipal solid wastes

    with the help of local authority. Decomposable Solid waste will be composted on-site in a composting pit and used in the greenbelt as manure.

    EMC of JSW IL to implement the plan

    10. Hazardous Waste Disposal

    To ensure proper disposal of hazardous waste in line with best practice.

    1. Waste management plan will be developed to identify, properly store, handle and transport the hazardous materials for disposal.

    2. Hazardous waste will be sent to Common Hazardous Waste Treatment Storage and Disposal Facility (CHWTSDF).

    EMC of JSW IL to implement the plan

    11. Financial and Social livelihood

    To ensure financial and social livelihood security of the local people.

    1. Adequate job opportunities (both direct and indirect) will be created for local youths through proper technical training.

    2. Financial and social livelihood security through adequate CSR (corporate social responsibility) plan is commitant; Education (free scholarship, mid-day meal, class

    room facility, etc.) Sports and cultural activity Water supply to local area villages Community health facilities Social livelihood of local people and farmers Empowerment of woman Infrastructure development (roads, sanitary facility,

    renovation of cultural places, tree plantation, etc)

    Port management shall ensures the implementation of CSR plan on priority

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 9

  • Environmental Concern Objectives

    Environmental Management Plan- Mitigation Measures (MM) Suggested

    Responsibility for implementation of MM

    Infrastructure development - Fisherman community (Ice factory, strengthen fish landing facility, common facility centre, fisherman education and empowerment)

    3. Budgetary provision made for CSR activities is given in Annex IV.

    12. Compliance reporting to MoEFCC RO

    To ensure six monthly reporting of compliance of EC conditions to the MoEFCC RO

    1. Six monthly reporting of compliance of EC conditions to the MoEFCC RO shall be submitted as per proviso of EIA Notification, 2006.

    2. Compliance of the conditions laid down in Consent to Operate from Maharashtra Pollution Control Board shall be reported as per prescribed frequency.

    3. EMP measures prescribed for operation phase of the project in the EIA Report and by CWPRS, Pune will be complied with, and reported at prescribed frequency

    4. Monitoring pf environmental parameters as given in the EIA Report and as prescribed by the MPCB will be reported to the respective authorities.

    5. Budgetary provision for implementation of EMP is given in Annex II.

    EMC of JSW IL shall ensure compliance.

    Environment Management Plan - All Weather Multi Cargo Captive Jetty at Nandgaon, Maharashtra 10

  • Annex I

    Dredging Plan sequence and schedule (Tentative)

    BD

    CSD

  • Dredging Methodology

    Plant and machinery required to dredge 10 million CBM in six months i.e. average 60,000 CBM

    per day will require deployment of following equipment.

    THSD with Hopper capacity of minimum 10,000 CBM and arrangement for rainbowing/pipeline

    discharge for reclamation – 02 nos. (for soft to medium clay)

    CSD with dredging reach of 22 m considering maximum height of tide 5.0 meters – 01 no (for

    medium clay to degradable decomposed rock)

    Backhoe Dredger with reach of 20 m with 6 CBM bucket/drum cutter arrangement – 01 no (for

    stiff clay to compact basalt)

    Self-propelled bottom open hopper barges to support Backhoe dredger for loading and

    disposal dredged material. – 02 nos

    Other required associated equipment to support the dredging work.

  • Annex II

    Cost for implementation of Environment Management Plan (EMP)

    S. No. Parameter Cost (Rs. In million)

    1. Sanitary facilities at labour camps 4.50

    2. Treatment of effluent from coal stack yard 3.00

    3. Solid waste Management 10.88

    4. Treatment of effluent from workshops 1.00

    5. Provision of free fuel 33.20

    Terrestrial Ecology 1.0

    7. Greenbelt development 0.400

    8. Purchase of noise meter 0.10

    9 Implementation of Environmental Monitoring Programme during construction phase

    6.65

    Total 59.73

    Cost for implementation of Environmental Monitoring Programme during construction phase

    S. No. Parameter Cost (Rs. In million)

    1. Marine Ecology 4.64

    2. Ambient air quality 2.01

    Total 6.65

  • 1

    Interim Survey report on

    “Assessment of Impacts on fish production due to

    development of the proposed All-Weather Captive Jetty”

    at village Nandgaon Maharashtra

    Submitted To

    JSW Infrastructure Limited

    JSW Centre, Bandra Kurla Complex, Bandra (East), Mumbai 400 051

    By

    Mumbai Research Centre of

    ICAR-Central Marine Fisheries Research Institute

    Second floor, CIFE old Campus, Fisheries University Road, Seven Bungalows, Versova, Andheri (West), Mumbai – 400 061.

    June 2015

    ajay.rayTypewritten Text

    ajay.rayTypewritten Text

    ajay.rayTypewritten TextAnnex III

  • 2

    CONTENTS

    Sl. No. Particulars Page No.

    1. Executive Summary 4

    2. Background 5

    3. Observations 6

    3.0 Project Area 6

    3.1 Sampling stations 8

    3.2 Collection of environment and fishery data 9

    4 Results 12

    4.1 Environmental and water parameters 12

    4.2 Biological 11

    4.3 Fishery 13

    5 Further studies 18

    6 CSR Plan of JSW 19

  • 3

    LIST OF TABLES

    Sl. No. Particulars Page No.

    1. Fisheries profile of villages near JSWIL all- weather

    captive jetty

    7

    2. Physico- chemical and biological parameters recorded

    at proposed project site

    14

    3. List of the species recorded in fish samples collected

    from project site

    15

    4. Budget for the CSR Plan 20

    5. CSR activities undertaken in the year 2014-15 21

    LIST OF PLATES

    1. Base camp image of the survey tour undertaken 8

    2. Google earth image of the survey tour undertaken 8

  • 4

    1. EXECUTIVE SUMMARY

    “Assessment of Impacts on fish production due to development of the proposed

    All Weather Captive Jetty” proposed at village Nandgaon Maharashtra required as a part

    of the Environmental Impact Assessment study has been undertaken by the Mumbai

    Research Centre of ICAR-Central Marine Fisheries Research Institute for JSW

    Infrastructure Limited, JSW Centre, Bandra Kurla Complex, Bandra (East), Mumbai 400

    051.

    This rapid report is formulated based on the data collected from primary and

    secondary resources in the month of April and May 2015. Water, sediment and fish

    samples were collected in situ from the three locations near proposed project site viz.

    Alewadi, Navapur and Nandgaon. Data of environmental parameters has also been

    collected and analysed further.

    Results & observations are presented in the form of figures and tables whenever

    required. Information on demographic profile of the fishing villages in the vicinity of the

    project area has been tabulated from the secondary source i.e., Marine Fisheries Census

    2010. Data of biological parameters of water and sediments are presented in tabular

    form. The fishery observations made at Alewadi & Navapur landing centre. Fish samples

    were collected from local fishers and fishing by using traditional shore seines & lift net

    namely Gholwa, Vedi and Magh. Single day dol net fishing samples were also collected

    from Navapur landing centre for further laboratory analysis. Fish samples were

    identified up to species level.

  • 5

    2. BACKGROUND

    JSW Group is one of the fastest growing business conglomerates with a strong

    presence in the core economic sector. This enterprise has grown from a steel rolling mill

    in 1982 to a multi business conglomerate within a short span of time.

    JSW Group has diversified interests in Steel, Energy, Minerals and Mining,

    Aluminum, Infrastructure, Cement and Information Technology.

    JSW Steel Limited (JSWSL) the flag ship company of JSW group is one of the

    largest steel producers of the Country. The company has manufacturing facilities

    located at Vijayanagar in Karnataka, Salem in Tamil Nadu Vasind, Tarapur and Dolvi,

    Kalmeshwar in Maharashtra and is in process of expanding further. The product range

    includes Pellets, Slabs, HRC, HR Plates / Sheets, CR Coils, GP/GC and Colour Coated

    Coils/Sheets, Bars, Rounds & Reinforcement bars.

    The JSW Infrastructure Ltd (JSWIL) is a JSW Group company which is presently

    into development of ports, rail/road and inland water connectivity, development of port

    based SEZ and other related infrastructure developments works along with terminal

    handling operations and port management.

    Presently the raw materials for the plants at Tarapur, Kamleshwar and Vasind,

    are being handled at various places on a make shift basis and therefore bringing in

    uncertainties in supply and increase in the cost. Hence, JSW is desirous of consolidating

    its group cargo and develop a jetty at village Nandgaon, district Palghar, Maharashtra

    for handling its group cargoes.

    JSW Infrastructure Limited approached ICAR-CMFRI to assess impacts on fish

    production due to the development of the proposed All weather captive jetty at

    Nandgaon, District Palghar.

    A study on assessment of impacts on fish production broadly covers following

    aspects;

  • 6

    - Demographic profile of the fishers in nearby fishing villages

    - Water quality

    - Sediment quality

    - Biological aspects (chlorophyll, plankton and benthos)

    - Fishing activities and fishery

    - Fish catch and resources

    The objective of the study is:

    To analyse the fishery potential of the area

    To assess fish ecology and fish diversity

    To identify the fish landing centres and the high economy yielding species

    To assess any impact in the fishing pattern/ potential due to the development

    To assess quantum of loss of income, if any

    To suggest a compensatory plan for the loss of livelihood, if any identified

    during the study

    To suggest a compensatory plan for loss or damage to the fishing nets and

    related accessories, if any.

  • 7

    3. OBSERVATIONS

    3.0 Project Area:

    Proposed all-weather captive jetty is located near Nandgaon village in Palghar

    district. Digitized locations collected during field visit are marked and shown below:

  • 8

    Table No. 1: Fisheries Profile of villages near JSWIL all-weather captive jetty:

    Village Alewadi Navapur Dandi Uccheli Murbe Kharekuran Satpati Village summary Fisherman

    families 75 900 1650 337 1333 177 2639

    Traditional fisherman families

    75 899 1643 337 1323 177 2492

    BPL families 11 120 123 39 205 16 234 Fisherfolk population

    291 3328 7006 2779 5305 776 12532

    Male population Adult 120 1348 2371 672 2034 305 4878 Children 30 349 1209 678 687 69 1428

    Female population

    Adult 103 1339 2476 710 1944 333 4886 Children 38 292 950 719 640 69 1340

    Active fishers Actual fishing 85 480 112 111 680 18 583 Fish seed collection

    0 17 7 0 1 0 551

    Fishing allied activities

    Marketing of fish

    43 697 63 88 452 182 1709

    Net making/ repairing

    0 0 22 4 89 2 289

    Curing/ processing

    0 0 2072 9 26 0 47

    Peeling 0 0 15 2 24 0 22 Labourer 0 117 1782 304 1462 0 1062 others 0 3 1 98 205 0 253

    Religion (no. of families)

    Hinduism 75 900 1615 337 1333 177 2622 Islam 0 0 35 0 0 0 17 SC/ST 0 57 1 56 13 2 197

    Membership in fisheries co-operatives

    Fisheries co-operatives

    0 504 336 0 1324 137 2104

    others 0 4 0 0 110 0 21 Craft owned by fisher folk

    Mechanized 0 7 57 6 24 0 110 Outboard 0 0 0 0 0 0 2 Non-motorized 3 0 0 5 12 0 11

    Fishing craft in the fishery

    Gill netters 8 0 8 0 148 Dol netters 0 6 23 0 19 Motorized 18 19 8 0 102 No motorised 7 5 8 0 26

    Source: Marine Fisheries Census 2010: Maharashtra (DAHDF, Ministry of Agriculture, Govt. Of

    India, New Delhi)

  • 9

    3.1 Sampling stations:

    Three sampling locations were considered for collection of water and sediment

    samples during rapid survey;

    Station 1.Navapur Landing Centre (19° 47’32.24” N & 72° 41’25.96” E) Station 2.Alewadi (19° 46’25.24” N & 72° 41’ 15.76” E)

    Station 3.Nandgaon (19° 46’04.90” N & 72° 41’ 15.28” E)

    Plate 1. Base camp image of the survey tour undertaken

    Plate 2. Google Earth image of the survey tour undertaken

  • 10

    3.2 Collection of environmental and fishery data:

    The samples has been collected in the month of April & May 2015 from pre-

    identified sampling stations to observe environmental data such as water quality

    parameters, nutrient profile of water and sediment samples. Water samples collected

    were analysed to study the species diversity of phytoplankton and productivity.

    Project Site Water & sediment sample collection

    Analysis of water quality parameters View of Navapur landing centre

    ‘Dol’ net landing at Navapur landing centre Fish sample collected in near shore waters

  • 11

    Analysis of fish samples in laboratory collected from project site:

    Sample analysis collected from near shore ‘Dol’ net sample analysis from Navapur

    Mugil cephalus Harpadon nehereus

    Juveniles of Pampus argenteus Sillago sihama

    Scylla tranquebarica Coilia dussumieri

  • 12

    Bregmaceros mcllelandi Tenulosa toli

    Caranx heberi Loliolus investigatoris

    Pellona ditchela Otolithoides biauritus

    Metapenaeus affinis Sepia aculeata

  • 13

    4. RESULTS

    4.1 Environmental and water parameters:

    Environmental and physico-chemical parameters were analysed in the

    laboratory and results tabulated in Table 2. The results showed that the pH range was

    from 7.94 to 8.35 found to be within optimum pH range. The Dissolved Oxygen level

    was found to be within the optimum limits from 2.4 to 4.0 ppm or mg/l. The salinity was

    fluctuating between 33.48-35.3 ppt; conductivity ranged between 52.4 to 54.87 ms/cm.

    Colour of the near shore water was black to brown with a strong stinking & chemical

    odour.

    Total dissolved solids and total suspended solids content in sea water samples

    ranged between 47.12 to 50.46 ppt and 0.22 to 0.56 ppt respectively. Sea water

    turbidity fluctuated between 28.6 to 45.7 NTU. Nutrients play a crucial role in the

    primary productivity of sea water. Nutrients such as phosphate, nitrate, nitrite, silicate

    were analysed from water samples and tabulated in Table 2.

    4.2 Biological:

    Chlorophyll content was estimated and found to be ranging between 8.57 to

    16.39 mg/m3. Escherichia coli, a faecal coliform bacteria was absent in the samples

    collected during rapid survey whereas Total Viable Count and Total Coliform Forming

    ranged between 103 to 106 and absent to 102 respectively.

    Phytoplankton diversity and abundance studies were undertaken for the

    collected water samples from selected locations. Laboratory analysis revealed the

    presence of 12 phytoplankton species in the sea water samples. Species recorded

    during rapid survey were Thalassioira decipiens, Navicula distans, Skeletonema

    costatum, Coscinodiscus granii, Scrippsiella trochoidea, Guinardia delicatula,

    Trichodesmium erythraeum, Odontella sinenis, Navicula clavata, Gonyaulax polygramma,

    Diploneis sp. and Amphora sp. Thalassiosira decipiens was major phytoplankton species

    recorded followed by Skeletonema costatum.

  • 14

    4.3 Fishery:

    Fish samples were collected by operating shore seine near project site and single

    day dol net landings at Navapur landing centre. Fish samples were further analysed in

    laboratory. Fish species richness (S) was 25 during rapid survey conducted in the

    proposed project location (Table 3).

    Fish samples represented by 12 species of finfishes, 11 species of crustaceans

    and two species of Mollusca.

  • 15

    Table No. 2: Physico-chemical and biological parameters recorded at proposed project site.

    Parameter April 2015 May 2015 Alewadi Navapur Nandgaon Alewadi Navapur Nandgaon

    Physico-Chemical 1. Atmospheric Temperature (°C) 35 34.5 34.5 35 34 33.8 2. Sea Surface Temperature(°C) 34.5 33.2 34 34.9 33.48 33 3. pH 8.15 7.94 8.3 8.31 8.28 8.35 4. Salinity x10-3 35.3 34.8 33.49 33.6 33.48 33.64 5. Conductivity (ms/cm) 52.51 52.4 52.95 52.91 54.87 53.18 6. Dissolved Oxygen (mg/l) 4.02 3.12 3.6 2.5 3.0 2.4 7. Dissolved Oxygen Saturation (%) 54.5 44.3 50.3 36.8 43.3 35.2 8. Total Dissolved Solids (ppt) 48.93 47.12 48.47 50.46 49.66 48.67 9. Total Suspended Solids (mg/l) 0.22 0.35 0.56 0.36 0.23 0.38

    10. Turbidity (NTU) 32.4 28.6 35.2 44.7 45.7 44.1 Nutrients 1. Phosphate (mg/l) 1.1 2.8 2.1 1.1 2.3 1.3 2. Nitrate(mg/l) 11.2 5.8 6.2 5.3 6.2 4.8 3. Nitrite(mg/l) 1.8 0.5 0.25 1.65 0.59 0.25 4. Silicate(mg/l) 1.12 4.31 6.42 1.37 2.56 1.87 5. Ammonia(mg/l) 0.30 0.98 0.76 0.10 0.82 0.54 Biological 1. Chlorophyll-a (mg/m3) 16.39 11.83 9.31 8.57 10.17 5.05 2. Total Viable Count (cfu/ml) 106 103 103 103 103 103 3. Total Coliform Forming (cfu/ml) Nil 102 Nil Nil 102 102

    4. Escherichia coli (cfu/ml) Nil Nil Nil Nil Nil Nil

  • 16

    Table No. 3: List of the species recorded in fish samples collected from project site

    Sl. No. Scientific Name Common English Name Marathi Name Finfishes

    1 Bregmaceros mcllelandi Unicorn Cod द ांडी

    2 Pampus argenteus Silver Pomfret प पलेट

    3 Megalaspis cordyla Horse Mackerel क ट ब ांगड

    4 Alepes djedaba Shrimp scad क करी ब ांगड

    5 Caranx heberi Blacktip trevally शितप

    6 Otolithoides biauritus Bronze croaker कोथ

    7 Harpadon nehereus Bombay duck बोंशबल

    8 Pellona ditchella Indian pellona क टी

    9 Coilia dussumieri Golden Anchovy म ांदेली

    10 Mugil cephalus Stripped grey mullet बोई म स

    11 Sillago sihama Lady fish रेणवी

    12. Tenulosa toli Toli shad श ांग

    Crustaceans

    13. Penaeus merguiensis Banana shrimp सफेद श ांग

    14. Metapenaeus affinis Jhinga shrimp चतैी

    15. Melicertus latisulcatus Western king shrimp कोळांबी

    16. Nematopalaemon tenuipes Spider shrimp अांब डी / कदी

    17. Acetes indicus Paste shrimp जवळ

    18. Parapenaeopsis sculptilis Rainbow shrimp पटे्टरी

    19. Solenocera crassicornis Coastal mud shrimp गोयन र

    20. Exhippolyasmata ensirostris Hunter shrimp गोबी

    21. Charybdis callianasa Crab खेकड

    22. Exopalaemon styliferus Shrimp अांब डी / कदी

    23. Scylla tranquebarica Green mud crab खेकड / शचांबोरी

    Molluscans

    24. Loliolus investigatoris Inshore squid म्ह कूळ

    25. Sepia aculeata Needle Cuttlefish म्ह कूळ

  • 17

    Qualitative analysis of phytoplankton samples collected from project site:

    Thalassiosira decipiens Skeletonema costatum

    Navicula distans Coscinodiscus granii

    Trichodesmium erythraeum Odontella sinensis

    Navicula clavata Amphora sp.

  • 18

    Scrippsiella trochoidea Guinardia delicatula

    Diploneis sp. Gonyaulax polygramma

  • 19

    5. FURTHER STUDIES

    The report enumerates the studies carried out for two months for collection of physico-

    chemical and biological of water and sediments. Experimental fishing was carried out

    around the project site. Further data collection and analysis is in the streamline. The

    proposed study is to be extended over a period of 12 months so as collect data for the

    entire fishing cycle.

    The present study can be considered as micro representation of the potential of the

    region. The landing majorly consists of fish belonging to Otolithes spp, Coilia dussumieri,

    and mix of small prawn and large prawn species and some clupeids.

    Further study is being carried out to identify the fishing pockets, fishing areas and

    landing centres.

    Methodology for sustainable development would be suggested such that there is no or

    minimal loss to the potential fishing grounds. CMFRI also proposes to submit a plan for

    the compensation to the fisher folk in a possibility of the loss or damage to the fishing

    gears and crafts due to port operation activities.

  • 20

    6. CSR PLAN OF JSW

    JSW is a responsible corporate and would integrate its environment, HR and ethical

    business policies with appropriate community engagement and gender equality. JSW

    Foundation works closely with the village communities and creates synergies with other

    verticals of the JSW group, to assimilate their intervention in a social development

    framework.

    The major activities of the JSW Foundation are in the areas of;

    Education

    Health

    Livelihood and Empowerment, especially for Women

    Sports

    Environment

    Arts, Culture and Heritage

    CSR Activity

    The JSW Foundation is facilitating the social activities in the following core areas with

    the help of Municipal Corporation, Education and Health Department of State

    Government, Local Community and Non-Governmental Organization as a part of the CSR

    activity. For the proposed Nandgaon Port project, the JSW Foundation has proposed to

    expand the CSR activities in the project influence area for the socio-economic benefit of

    the local people.

    The budget for the CSR activities is already been identified by JSW. The detail of the

    budget is given in Table 4 below.

    Table 4: Budget for the CSR plan (Figures in Lakhs)

    S. No.

    Activities Description CSR Activity Existing

    CSR Activity Planned

    1

    Education

    Education sector and development of Educational facilities like Digi- Class rooms (PEARSON-UK), etc.

    3.00

    100.0

  • 21

    S. No.

    Activities Description CSR Activity Existing

    CSR Activity Planned

    Services- In Schools

    ISCKON JSW Mid-Day Meal 60.00

    2 Water Supply Development of water supply system 5.00 200.00

    3 Community Health

    Provide health related facilities. Health Camps in consultation with

    the Smile Foundation. 50.00

    4 Sports & Culture

    Sports development & cultural activities

    25.00 50.00

    5 Livelihood & Empowerment

    Implementation of training programmes for woman empowerment, SHGs

    Training programme for educated unemployed youth

    100.00

    6 Infrastructure Development & Environment

    Development of internal roads, toilets, Playground, etc

    Beautification of “Hutatma Smarak”, reconstruction of fencing walls, and refurbishment of monuments.

    Renovation of Temples. Plantations along the roads.

    7.00 300.00

    7

    Infrastructure Development –Fisherman Community

    Ice factory Common facility centre Fishermen Empowerment Strengthen fish landing facility

    700.00

    Total 100.00 1500.00

    As a part of the pre- project activities JSW Infrastructure Limited has been in the fore

    front to implement the CSR activities. In the financial year 2014-15 about 75 lakhs has

    been utilised. The core activities undertaken under the various heads are depicted in

    table 5.

    Table 5: CSR Activities under taken in the year 2014-15

    Sr. no. Item Activity undertaken 1 Education Renovation of anganwadi centres at Murbe &

    Dandi Distribution of school stationery Upgradation of primary school , ITI Establishing libraries

    2 Health and hygiene Prenatal Care Center in village Dandi Training of adolescent girls in personal

    hygiene & sanitation 3 Community Welfare Bore well at Murbe

  • 22

    Promoting gender equality Visits to other projects

    4 Sports Development of playground Organizing football tournaments Organizing cricket tournament

    5 Infrastructure development

    Construction of Group Toilets at Murbe & Dandi Construction of platform for performances by

    Local artists 6 Infrastructure for

    Fisher folk Construction of jetty stands at Murbe and Dandi Distribution of fishing nets Distribution of ice boxes

  • 23

    CSR Activities undertaken around the project site

    Infrastructure Development for the fisher folks

    Distribution of fishing nets

    Strengthening of jetty platform

  • 24

    Establishment of Prenatal Care Centre

    Organizing Sports Tournaments

  • 25

    Education sector - anganwadis, workshops etc.

    Bore wells in the surrounding villages

  • Annex-IV

    Budgetary provision for CSR Activity plan

    S.

    No.

    Activities Description CSR

    Activity

    Existing

    CSR

    Activity

    Planned

    1 Education

    Services- In

    Schools

    Education sector and

    development of Educational

    facilities like Digi-Class rooms

    (PEARSON-UK), etc.

    ISCKON JSW Mid-Day Meal

    3.0

    60.0

    100.0

    2 Water Supply Development of water supply system 5.0 200.0

    3 Community

    Health

    Provide health related facilities.

    Health Camps in consultation with

    the Smile Foundation

    50.0

    4 Sports & Culture Sports development & cultural activities 25.0 50.0

    5 Livelihood &

    Empowerment

    Implementation of training

    programs for woman

    empowerment, SHGs

    Training program for educated

    unemployed youth

    100.0

    6 Infrastructure

    Development &

    Environment

    Development of internal roads,

    toilets, Playground, etc

    Beautification of “Hutatma

    Smarak”, reconstruction of fencing

    walls, and refurbishment of

    monuments.

    Renovation of Temples.

    Plantations along the roads.

    7.0 300.0

    7 Infrastructure

    Development –

    Fisherman

    Community

    Ice factory

    Common facility centre

    Fishermen Education and

    Empowerment

    Strengthen fish landing facility

    700.0

    Total 100.0 1500.0

    Cover ltr signed.pdfRevised EMP_Nandgaon Port.pdfNandgaon fornt page.pdfEMP Nandgaon Port Jetty Final 210715.pdfEnvironment Management Plan0FResponsibility for implementation of MMEnvironmental Management Plan- Mitigation Measures (MM) SuggestedEnvironmental ConcernObjectives

    Annex I.pdfAnnex II.pdfAnnex III_CMFRI_JSW_Rapid Survey18.7.15.pdfAnnex IV.pdf