Facility Condition Assessment Reports
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 1
Facility: \Administrative/Support\Central OfficeAddress: 1961 Midway, Shreveport, LA 71130
Attributes: ***None***
General Information: Function: Administration/Support Year Built:Gross Area: 142,935 S.F. Last Renovation:
Facility Description:
The Central Office campus consists of eight buildings located at 1961 Midway in Shreveport, Louisiana. The original campus was constructed in 1954. The Administrative Building was renovated and had an addition constructed in 1991; the ROTC Maintenance Repair Building had an addition in 1974; and the Teacher Resource Building was renovated in 1991. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report for each building or other facility on the campus.
Current Repair Cost: $7,567,823.00 Replacement Cost: $19,420,493.00 FCI: 38.97%
19-Apr-2010Central Office
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 2
Facility: \Administrative/Support\Central Office\Administrative BuildingAddress: 1961 Midway, Shreveport, LA 71130
Attributes: Number of Floors 2
General Information: Function: Administration/Support Year Built: 1954Gross Area: 68,346 S.F. Last Renovation: 1991
Facility Description:
The Administrative Building is a 2-story building located at 1961 Midway Street in Shreveport, Louisiana. There has been a 1-story addition and a renovation in 1991. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report.
Energy conservation opportunities for this building include: 1) Replacement of the dual duct system with a VAV design and a building automation system would allow programs to improve operation and reduce energy use; 2) Exterior windows are steel frame, operable clear glass design. Installation of fixed, double pane, low e, thermal windows with thermal breaks would improve energy use and improve comfort; 3) New low flow plumbing fixtures would reduce water use; and 4) A review of billing rate may justify addition of power factor correction capacitors.
ADA vertical access needs for this facility have been addressed with an elevator.
Current Repair Cost: $4,552,599.00 Replacement Cost: $10,076,394.00 FCI: 45.18%
19-Apr-2010West Elevation
19-Apr-2010South Elevation
19-Apr-2010East Elevation
19-Apr-2010North Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 3
Facility: \Administrative/Support\Central Office\Administrative Building (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $147.43 S.F. 68,346 106 $10,693,640 51 1972 1974 2010 44 $4,552,601 $10,076,392 45
Substructure $6.41 S.F. 68,346 100 $437,961 100 1954 $437,961
Foundations $6.41 S.F. 68,346 100 $437,961 100 1954 $437,961
Standard Foundations $2.93 S.F. 68,346 100 $200,117 100 1954 $200,117
Slab on Grade $3.48 S.F. 68,346 100 $237,844 100 1954 $237,844
Basement Construction 0 0 0
Basement Excavation 0 0 0 0
Basement Walls 0 0 0 0
Shell $50.21 S.F. 68,346 103 $3,537,808 75 1963 1992 $1,169,209 $3,431,516 34
Superstructure $16.46 S.F. 68,346 100 $1,125,249 100 1954 $1,125,249
Floor Construction $13.88 S.F. 68,346 100 $948,916 100 1954 $948,916
Roof Construction $2.58 S.F. 68,346 100 $176,333 100 1954 $176,333
Exterior Enclosure $23.94 S.F. 68,346 102 $1,675,488 82 1966 2002 $432,138 $1,636,203 26
Exterior Walls $18.19 S.F. 68,346 100 $1,243,350 100 1954 $1,243,350
Exterior Windows $4.66 S.F. 68,346 110 $350,041 30 1972 2002 $350,041 $318,219 110
Exterior Doors $1.09 S.F. 68,346 110 $82,097 30 1972 2002 $82,097 $74,634 110
Roofing $9.80 S.F. 68,346 110 $737,071 20 1972 1992 $737,071 $670,064 110
Roof Coverings - BUR $9.80 S.F. 68,346 110 $737,071 20 1972 1992 $737,071 $670,064 110
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Mettal
0 0 0 0
Roof Openings 0 0 0 0
Interiors $27.56 S.F. 68,346 104 $1,962,548 56 1964 1974 14 $667,868 $1,883,895 35
Interior Construction $11.26 S.F. 68,346 96 $736,496 65 1966 1992 5 $101,945 $769,303 13
Partitions $4.55 S.F. 68,346 110 $341,921 100 1954 $310,838
Interior Doors $5.35 S.F. 68,346 80 $292,630 40 1972 2012 5 $365,788
Fittings $1.36 S.F. 68,346 110 $101,945 20 1972 1992 $101,945 $92,677 110
Stairs $5.30 S.F. 68,346 110 $398,758 100 1954 $362,507
Stair Construction $5.30 S.F. 68,346 110 $398,758 100 1954 $362,507
Interior Finishes $11.00 S.F. 68,346 110 $827,294 28 1966 1974 24 $565,923 $752,085 75
Wall Finishes - Ceramic &
Glazed
$5.98 S.F. 6,834 110 $44,924 30 1972 2002 $44,924 $40,840 110
Wall Finishes - Paint $1.26 S.F. 61,512 110 $85,256 10 1972 1982 $85,256 $77,505 110
Floor Finishes - Carpet $2.88 S.F. 6,834 110 $21,650 8 1972 1980 $21,650 $19,682 110
Floor Finishes - Ceramic &
Quarry Tile
$10.57 S.F. 6,836 110 $79,497 50 1972 2022 24 $72,270
Floor Finishes - Terrazzo $6.05 S.F. 27,338 110 $181,874 50 1972 2022 24 $165,340
Floor Finishes - VCT $4.44 S.F. 27,338 110 $133,519 15 1972 1987 $133,519 $121,381 110
Floor Finishes - Wood 0 0 0 0
Ceiling Finishes $3.73 S.F. 68,346 110 $280,574 20 1954 1974 $280,574 $255,067 110
Services $61.57 S.F. 68,346 110 $4,629,020 26 1980 1984 2010 55 $2,715,524 $4,208,199 65
Conveying $12.12 S.F. 68,346 110 $911,189 30 2007 2037 90 $828,354
Elevators and Lifts $12.12 S.F. 68,346 110 $911,189 30 2007 2037 90 $828,354
Plumbing $5.22 S.F. 68,346 110 $392,444 30 1954 1984 $392,444 $356,766 110
Plumbing Fixtures $2.27 S.F. 68,346 110 $170,510 30 1954 1984 $170,510 $155,009 110
Domestic Water Distribution $0.71 S.F. 68,346 110 $53,228 30 1954 1984 $53,228 $48,389 110
Sanitary Waste $1.76 S.F. 68,346 110 $132,619 30 1954 1984 $132,619 $120,562 110
Rain Water Drainage 0 0 0 0
Other Plumbing Systems -
Natural Gas
$0.48 S.F. 68,346 110 $36,087 30 1954 1984 $36,087 $32,806 110
HVAC $25.21 S.F. 68,346 110 $1,895,453 26 1991 2006 2010 37 $1,634,727 $1,723,139 95
Heat Generating Systems $3.47 S.F. 68,346 110 $260,726 30 1991 2021 37 $237,024
Cooling Generating Systems $5.44 S.F. 68,346 110 $408,682 30 1991 2021 2010 $408,682 $371,529 110
Distribution Systems & Exhaust
Systems
$9.24 S.F. 68,346 110 $694,669 30 1991 2021 2010 $694,669 $631,517 110
Terminal & Package Units $4.82 S.F. 68,346 110 $362,671 15 1991 2006 $362,671 $329,701 110
Controls & Instrumentation $2.24 S.F. 68,346 110 $168,705 20 1991 2011 2010 $168,705 $153,368 110
Fire Protection 0 0 0
Sprinklers 0 0 0 0
Electrical $19.02 S.F. 68,346 110 $1,429,934 23 1984 1984 19 $688,353 $1,299,940 53
Electrical Service/Distribution $4.38 S.F. 68,346 110 $329,291 30 1991 2021 37 $299,355
Branch Wiring $5.48 S.F. 68,346 110 $412,290 30 1954 1984 $412,290 $374,809 110
Lighting $5.48 S.F. 68,346 110 $412,290 20 1991 2011 5 $374,809
Communications and Security -
Public Address & Clock System
0 0 0 0
Fire Alarm $2.45 S.F. 68,346 110 $184,042 10 1991 2001 $184,042 $167,311 110
Security & CCTV $1.22 S.F. 68,346 110 $92,021 10 1991 2001 $92,021 $83,656 110
Other Electrical Systems -
Emergency Generator
0 0 0 0
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 4
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Equipment & Furnishings $1.68 S.F. 68,346 110 $126,303 20 1991 2011 5 $114,821
Furnishings $1.68 S.F. 68,346 110 $126,303 20 1991 2011 5 $114,821
Fixed Furnishings $1.68 S.F. 68,346 110 $126,303 20 1991 2011 5 $114,821
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 5
Facility: \Administrative/Support\Central Office\Administrative Building (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $4,552,601 $554,752 $310,451 $27,426 $485,582
Substructure
Foundations
Standard Foundations
Slab on Grade
Basement Construction
Basement Excavation
Basement Walls
Shell $1,169,209
Superstructure
Floor Construction
Roof Construction
Exterior Enclosure $432,138
Exterior Walls
Exterior Windows $350,041
Exterior Doors $82,097
Roofing $737,071
Roof Coverings - BUR $737,071
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Mettal
Roof Openings
Interiors $667,868 $310,451 $27,426 $114,576
Interior Construction $101,945 $310,451
Partitions
Interior Doors $310,451
Fittings $101,945
Stairs
Stair Construction
Interior Finishes $565,923 $27,426 $114,576
Wall Finishes - Ceramic & Glazed $44,924
Wall Finishes - Paint $85,256 $114,576
Floor Finishes - Carpet $21,650 $27,426
Floor Finishes - Ceramic & Quarry
Tile
Floor Finishes - Terrazzo
Floor Finishes - VCT $133,519
Floor Finishes - Wood
Ceiling Finishes $280,574
Services $2,715,524 $424,659 $371,006
Conveying
Elevators and Lifts
Plumbing $392,444
Plumbing Fixtures $170,510
Domestic Water Distribution $53,228
Sanitary Waste $132,619
Rain Water Drainage
Other Plumbing Systems - Natural
Gas
$36,087
HVAC $1,634,727
Heat Generating Systems
Cooling Generating Systems $408,682
Distribution Systems & Exhaust
Systems
$694,669
Terminal & Package Units $362,671
Controls & Instrumentation $168,705
Fire Protection
Sprinklers
Electrical $688,353 $424,659 $371,006
Electrical Service/Distribution
Branch Wiring $412,290
Lighting $424,659
Communications and Security -
Public Address & Clock System
Fire Alarm $184,042 $247,337
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 6
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Security & CCTV $92,021 $123,669
Other Electrical Systems -
Emergency Generator
Equipment & Furnishings $130,093
Furnishings $130,093
Fixed Furnishings $130,093
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 7
Facility: \Administrative/Support\Central Office\Administrative Building (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B2020 System: Exterior Windows Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The exterior windows are beyond expected life and should be replaced.
Estimates:Raw Cost $291,700.73
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $291,700.73
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B2030 System: Exterior Doors Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The exterior doors are beyond expected life and should be replaced.
Estimates:Raw Cost $68,414.35
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $68,414.35
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 8
Facility: \Administrative/Support\Central Office\ Administrative Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B3010 System: Roof Coverings - BUR Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Roof covering is in poor condition and has been coated to extend its life, but should be replaced. Roof
replacement to include appropriate insulation for energy conservation.
Estimates:Raw Cost $614,225.50
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $614,225.50
Deficiency: Surveyor/Update: Somnath Das Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C1030 System: Fittings Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Fittings, such as chalk and tack boards, lockers, toilet and bath accessories, toilet partitions, and shelving, are
beyond expected life and should be replaced.
Estimates:Raw Cost $84,954.08
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $84,954.08
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 9
Facility: \Administrative/Support\Central Office\ Administrative Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Ceramic & Glazed Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The wall ceramic tiles are beyond expected life and should be replaced.
Estimates:Raw Cost $37,436.65
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $37,436.65
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Paint Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The painted wall finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $71,046.36
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $71,046.36
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 10
Facility: \Administrative/Support\Central Office\ Administrative Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: C3020 System: Floor Finishes - Carpet Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The carpet is stained, beyond expected life, and should be replaced.
Estimates:Raw Cost $18,041.76
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $18,041.76
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: C3020 System: Floor Finishes - VCT Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The VCT flooring is beyond expected life and should be replaced.
Estimates:Raw Cost $111,265.66
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $111,265.66
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 11
Facility: \Administrative/Support\Central Office\ Administrative Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3030 System: Ceiling Finishes Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The ceiling finishes are stained, beyond expected life, and should be replaced.
Estimates:Raw Cost $233,811.67
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $233,811.67
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2010 System: Plumbing Fixtures Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Plumbing fixtures are mostly original, beyond expected life, and should be replaced.
Estimates:Raw Cost $142,091.33
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $142,091.33
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 12
Facility: \Administrative/Support\Central Office\ Administrative Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2020 System: Domestic Water Distribution Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Domestic water system is mostly original, beyond expected life, and should be replaced.
Estimates:Raw Cost $44,356.55
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $44,356.55
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2030 System: Sanitary Waste Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Sanitary waste system is original, beyond expected life, and should be replaced.
Estimates:Raw Cost $110,515.48
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $110,515.48
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 13
Facility: \Administrative/Support\Central Office\ Administrative Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2090 System: Other Plumbing Systems - Natural Gas Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Natural gas system is original, beyond expected life, and should be replaced.
Estimates:Raw Cost $30,072.24
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $30,072.24
Deficiency: Surveyor/Update: Phil Trenbath Thu, 22-Apr-2010Priority: 3Quantity: 1
Assembly: D3030 System: Cooling Generating Systems Material: System Distress: Inadequate Category: Deferred Maintenance Correction: Renew System Note: Reciprocating chillers are obsolete, inefficient, and should be replaced.
Estimates:Raw Cost $340,568.12
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $340,568.12
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 14
Facility: \Administrative/Support\Central Office\ Administrative Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: D3040 System: Distribution Systems & Exhaust Systems Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Distribution is an inefficient dual duct system that is past expected life and should be replaced.
Estimates:Raw Cost $578,890.62
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $578,890.62
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D3050 System: Terminal & Package Units Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Air cooled chiller and distribution system is beyond expected life and should be replaced.
Estimates:Raw Cost $302,226.01
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $302,226.01
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 15
Facility: \Administrative/Support\Central Office\ Administrative Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: D3060 System: Controls & Instrumentation Material: System Distress: Inadequate Category: Deferred Maintenance Correction: Renew System Note: Pneumatic mixing boxes and control system is inefficient, past expected life, and should be replaced.
Estimates:Raw Cost $140,587.72
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $140,587.72
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5020 System: Branch Wiring Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Most of the wiring dates from original construction, is beyond expected life, and should be replaced.
Estimates:Raw Cost $343,575.34
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $343,575.34
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 16
Facility: \Administrative/Support\Central Office\ Administrative Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5030 System: Fire Alarm Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Fire alarm system are beyond expected life and should be replaced.
Estimates:Raw Cost $153,368.42
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $153,368.42
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: D5030 System: Security & CCTV Material: System Distress: Inadequate Category: Deferred Maintenance Correction: Renew System Note: CCTV system is reported to be inoperable, is past expected life, and should be replaced.
Estimates:Raw Cost $76,684.21
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $76,684.21
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 17
Facility: \Administrative/Support\Central Office\Carpenter ShopAddress: 1961 Midway, Shreveport, LA 71130
Attributes: Number of Floors 1
General Information: Function: Administration/Support Year Built: 1974Gross Area: 4,200 S.F. Last Renovation:
Facility Description:
The Carpenter Shop is a 1-story building located at 1961 Midway Street in Shreveport, Louisiana. There have been no additions and no renovations. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report.
Current Repair Cost: $177,075.00 Replacement Cost: $390,650.00 FCI: 45.33%
19-Apr-2010North Elevation
19-Apr-2010East Elevation
19-Apr-2010South Elevation
19-Apr-2010West Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 18
Facility: \Administrative/Support\Central Office\Carpenter Shop (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $93.01 S.F. 4,200 105 $410,437 67 1976 1994 10 $177,075 $390,650 45
Substructure $14.41 S.F. 4,200 100 $60,530 100 1974 $60,530
Foundations $14.41 S.F. 4,200 100 $60,530 100 1974 $60,530
Standard Foundations $8.88 S.F. 4,200 100 $37,296 100 1974 $37,296
Slab on Grade $5.53 S.F. 4,200 100 $23,234 100 1974 $23,234
Shell $48.38 S.F. 4,200 104 $212,199 65 1974 1994 $98,849 $203,214 49
Superstructure $12.30 S.F. 4,200 100 $51,660 100 1974 $51,660
Roof Construction $12.30 S.F. 4,200 100 $51,660 100 1974 $51,660
Exterior Enclosure $25.86 S.F. 4,200 104 $113,304 68 1974 2004 $51,614 $108,613 48
Exterior Walls $14.69 S.F. 4,200 100 $61,690 100 1974 $61,690
Exterior Windows $9.17 S.F. 4,200 110 $42,356 30 1974 2004 $42,356 $38,506 110
Exterior Doors $2.00 S.F. 4,200 110 $9,258 30 1974 2004 $9,258 $8,417 110
Roofing $10.22 S.F. 4,200 110 $47,235 20 1974 1994 $47,235 $42,941 110
Roof Coverings - BUR $10.22 S.F. 4,200 110 $47,235 20 1974 1994 $47,235 $42,941 110
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Metal
0 0 0 0
Roof Openings 0 0 0 0
Interiors $13.16 S.F. 4,200 107 $58,928 95 1974 2014 10 $55,289
Interior Construction $13.16 S.F. 4,200 107 $58,928 95 1974 2014 10 $55,289
Partitions $11.66 S.F. 4,200 110 $53,888 100 1974 $48,989
Interior Doors $1.50 S.F. 4,200 80 $5,040 40 1974 2014 10 $6,300
Fittings 0 0 0 0
Interior Finishes 0 0 0
Wall Finishes - Paint 0 0 0 0
Floor Finishes - Carpet 0 0 0 0
Floor Finishes - Ceramic &
Quarry Tile
0 0 0 0
Floor Finishes - VCT 0 0 0 0
Ceiling Finishes 0 0 0 0
Services $17.05 S.F. 4,200 110 $78,780 26 1978 1994 5 $78,226 $71,617 109
Plumbing $0.52 S.F. 4,200 110 $2,384 20 1974 1994 $2,384 $2,167 110
Plumbing Fixtures 0 0 0 0
Domestic Water Distribution 0 0 0 0
Sanitary Waste 0 0 0 0
Rain Water Drainage 0 0 0 0
Other Plumbing Systems -
Natural Gas
$0.52 S.F. 4,200 110 $2,384 20 1974 1994 $2,384 $2,167 110
HVAC $1.57 S.F. 4,200 110 $7,262 20 1985 2004 5 $6,708 $6,602 102
Distribution Systems & Exhaust
Systems
0 0 0 0
Terminal & Package Units $0.94 S.F. 4,200 110 $4,324 15 1991 2006 $4,324 $3,931 110
Controls & Instrumentation $0.12 S.F. 4,200 110 $554 20 1991 2011 5 $504
Other HVAC Systems/Equip -
Exhaust Hoods
$0.52 S.F. 4,200 110 $2,384 30 1974 2004 $2,384 $2,167 110
Fire Protection $3.85 S.F. 4,200 110 $17,796 30 1974 2004 $17,796 $16,178 110
Sprinklers $3.85 S.F. 4,200 110 $17,796 30 1974 2004 $17,796 $16,178 110
Electrical $11.11 S.F. 4,200 110 $51,338 26 1974 1994 $51,338 $46,670 110
Electrical Service/Distribution $3.70 S.F. 4,200 110 $17,076 30 1974 2004 $17,076 $15,523 110
Branch Wiring $3.48 S.F. 4,200 110 $16,078 30 1974 2004 $16,078 $14,616 110
Lighting $3.94 S.F. 4,200 110 $18,184 20 1974 1994 $18,184 $16,531 110
Communications and Security -
Fire Alarm
0 0 0 0
Communications and Security -
Security & CCTV
0 0 0 0
Equipment & Furnishings 0 0 0
Furnishings 0 0 0
Fixed Furnishings 0 0 0 0
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 19
Facility: \Administrative/Support\Central Office\Carpenter Shop (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $177,075 $571 $5,673
Substructure
Foundations
Standard Foundations
Slab on Grade
Shell $98,849
Superstructure
Roof Construction
Exterior Enclosure $51,614
Exterior Walls
Exterior Windows $42,356
Exterior Doors $9,258
Roofing $47,235
Roof Coverings - BUR $47,235
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Metal
Roof Openings
Interiors $5,673
Interior Construction $5,673
Partitions
Interior Doors $5,673
Fittings
Interior Finishes
Wall Finishes - Paint
Floor Finishes - Carpet
Floor Finishes - Ceramic & Quarry
Tile
Floor Finishes - VCT
Ceiling Finishes
Services $78,226 $571
Plumbing $2,384
Plumbing Fixtures
Domestic Water Distribution
Sanitary Waste
Rain Water Drainage
Other Plumbing Systems - Natural
Gas
$2,384
HVAC $6,708 $571
Distribution Systems & Exhaust
Systems
Terminal & Package Units $4,324
Controls & Instrumentation $571
Other HVAC Systems/Equip -
Exhaust Hoods
$2,384
Fire Protection $17,796
Sprinklers $17,796
Electrical $51,338
Electrical Service/Distribution $17,076
Branch Wiring $16,078
Lighting $18,184
Communications and Security - Fire
Alarm
Communications and Security -
Security & CCTV
Equipment & Furnishings
Furnishings
Fixed Furnishings
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 20
Facility: \Administrative/Support\Central Office\Carpenter Shop (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B2020 System: Exterior Windows Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The exterior windows are beyond expected life and should be replaced.
Estimates:Raw Cost $35,296.80
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $35,296.80
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: B2030 System: Exterior Doors Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The exterior doors are beyond expected life and should be replaced.
Estimates:Raw Cost $7,715.40
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $7,715.40
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 21
Facility: \Administrative/Support\Central Office\ Carpenter Shop (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B3010 System: Roof Coverings - BUR Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The roof covering is beyond expected life and should be replaced. Roof replacement to include appropriate
insulation for energy conservation
Estimates:Raw Cost $39,362.40
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $39,362.40
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2090 System: Other Plumbing Systems - Natural Gas Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Gas piping to unit heaters is beyond expected life and should be replaced.
Estimates:Raw Cost $1,986.60
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $1,986.60
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 22
Facility: \Administrative/Support\Central Office\ Carpenter Shop (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D3050 System: Terminal & Package Units Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Unit heaters are beyond expected life and should be replaced.
Estimates:Raw Cost $3,603.60
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $3,603.60
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D3090 System: Other HVAC Systems/Equip - Exhaust Hoods Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Exhaust system is beyond expected life and should be replaced.
Estimates:Raw Cost $1,986.60
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $1,986.60
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 23
Facility: \Administrative/Support\Central Office\ Carpenter Shop (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D4010 System: Sprinklers Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Sprinkler system is beyond expected life and should be replaced.
Estimates:Raw Cost $14,830.20
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $14,830.20
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5010 System: Electrical Service/Distribution Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Distribution system is beyond expected life and should be replaced.
Estimates:Raw Cost $14,229.60
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $14,229.60
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 24
Facility: \Administrative/Support\Central Office\ Carpenter Shop (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5020 System: Branch Wiring Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Wiring is beyond expected life and should be replaced.
Estimates:Raw Cost $13,398.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $13,398.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5020 System: Lighting Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Lighting system is beyond expected life and should be replaced.
Estimates:Raw Cost $15,153.60
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $15,153.60
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 25
Facility: \Administrative/Support\Central Office\Construction Capital Projects BuildingAddress: 1961 Midway, Shreveport, LA 71130
Attributes: Number of Floors 1
General Information: Function: Administration/Support Year Built: 2004Gross Area: 3,200 S.F. Last Renovation:
Facility Description:
The Construction and Capital Projects Building is a 1-story building located at 1961 Midway Street in Shreveport, Louisiana. There have been no additions and no renovations. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report.
Current Repair Cost: $0.00 Replacement Cost: $319,949.00 FCI: 0.00%
16-Apr-2010North Elevation
16-Apr-2010West Elevation
16-Apr-2010South Elevation
16-Apr-2010East Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 26
Facility: \Administrative/Support\Central Office\Construction Capital Projects Building (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $99.98 S.F. 3,200 107 $341,050 44 2004 2014 72 0 $319,950
Substructure $6.41 S.F. 3,200 100 $20,506 100 2004 $20,506
Foundations $6.41 S.F. 3,200 100 $20,506 100 2004 $20,506
Standard Foundations $2.93 S.F. 3,200 100 $9,370 100 2004 $9,370
Slab on Grade $3.48 S.F. 3,200 100 $11,136 100 2004 $11,136
Shell $27.13 S.F. 3,200 106 $91,799 75 2004 2034 88 $86,822
Superstructure $2.58 S.F. 3,200 100 $8,256 100 2004 $8,256
Roof Construction $2.58 S.F. 3,200 100 $8,256 100 2004 $8,256
Exterior Enclosure $14.75 S.F. 3,200 104 $49,033 71 2004 2034 80 $47,193
Exterior Walls $9.00 S.F. 3,200 100 $28,800 100 2004 $28,800
Exterior Windows $4.66 S.F. 3,200 110 $16,389 30 2004 2034 80 $14,899
Exterior Doors $1.09 S.F. 3,200 110 $3,844 30 2004 2034 80 $3,494
Roofing $9.80 S.F. 3,200 110 $34,510 75 2004 2079 92 $31,373
Roof Coverings - BUR 0 0 0 0
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Mettal
$9.80 S.F. 3,200 110 $34,510 75 2004 2079 92 $31,373
Roof Openings 0 0 0 0
Interiors $20.69 S.F. 3,200 102 $67,684 41 2004 2014 68 $66,201
Interior Construction $11.26 S.F. 3,200 96 $34,483 65 2004 2024 81 $36,019
Partitions $4.55 S.F. 3,200 110 $16,009 100 2004 $14,554
Interior Doors $5.35 S.F. 3,200 80 $13,701 40 2004 2044 85 $17,126
Fittings $1.36 S.F. 3,200 110 $4,773 20 2004 2024 70 $4,339
Interior Finishes $9.43 S.F. 3,200 110 $33,201 16 2004 2014 61 $30,182
Wall Finishes - Ceramic &
Glazed
0 0 0 0
Wall Finishes - Paint $1.26 S.F. 3,200 110 $4,435 10 2004 2014 40 $4,032
Floor Finishes - Carpet 0 0 8 2004
Floor Finishes - Ceramic &
Quarry Tile
0 0 50 2004
Floor Finishes - Terrazzo 0 0 0 0
Floor Finishes - VCT $4.44 S.F. 3,200 110 $15,629 15 2004 2019 60 $14,208
Floor Finishes - Wood 0 0 0 0
Ceiling Finishes $3.73 S.F. 3,200 110 $13,137 20 2004 2024 70 $11,942
Services $44.08 S.F. 3,200 110 $155,147 21 2004 2014 68 $141,045
Plumbing $4.74 S.F. 3,200 110 $16,684 30 2004 2034 80 $15,169
Plumbing Fixtures $2.27 S.F. 3,200 110 $7,983 30 2004 2034 80 $7,258
Domestic Water Distribution $0.71 S.F. 3,200 110 $2,492 30 2004 2034 80 $2,266
Sanitary Waste $1.76 S.F. 3,200 110 $6,209 30 2004 2034 80 $5,645
Rain Water Drainage 0 0 0 0
Other Plumbing Systems -
Natural Gas
0 0 0 0
HVAC $22.76 S.F. 3,200 110 $80,129 15 2004 2019 61 $72,845
Distribution Systems & Exhaust
Systems
0 0 0 0
Terminal & Package Units $20.52 S.F. 3,200 110 $72,230 15 2004 2019 60 $65,664
Controls & Instrumentation $2.24 S.F. 3,200 110 $7,899 20 2004 2024 70 $7,181
Fire Protection 0 0 0
Sprinklers 0 0 0 0
Electrical $16.57 S.F. 3,200 110 $58,334 25 2004 2014 74 $53,031
Electrical Service/Distribution $4.38 S.F. 3,200 110 $15,418 30 2004 2034 80 $14,016
Branch Wiring $5.48 S.F. 3,200 110 $19,304 30 2004 2034 80 $17,549
Lighting $5.48 S.F. 3,200 110 $19,304 20 2004 2024 70 $17,549
Fire Alarm 0 0 0 0
Security & CCTV $1.22 S.F. 3,200 110 $4,308 10 2004 2014 40 $3,917
Other Electrical Systems -
Emergency Generator
0 0 0 0
Equipment & Furnishings $1.68 S.F. 3,200 110 $5,914 20 2004 2024 70 $5,376
Furnishings $1.68 S.F. 3,200 110 $5,914 20 2004 2024 70 $5,376
Fixed Furnishings $1.68 S.F. 3,200 110 $5,914 20 2004 2024 70 $5,376
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 27
Facility: \Administrative/Support\Central Office\Construction Capital Projects Building (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $9,841 $114,636
Substructure
Foundations
Standard Foundations
Slab on Grade
Shell
Superstructure
Roof Construction
Exterior Enclosure
Exterior Walls
Exterior Windows
Exterior Doors
Roofing
Roof Coverings - BUR
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Mettal
Roof Openings
Interiors $4,992 $20,392
Interior Construction
Partitions
Interior Doors
Fittings
Interior Finishes $4,992 $20,392
Wall Finishes - Ceramic & Glazed
Wall Finishes - Paint $4,992
Floor Finishes - Carpet
Floor Finishes - Ceramic & Quarry
Tile
Floor Finishes - Terrazzo
Floor Finishes - VCT $20,392
Floor Finishes - Wood
Ceiling Finishes
Services $4,849 $94,244
Plumbing
Plumbing Fixtures
Domestic Water Distribution
Sanitary Waste
Rain Water Drainage
Other Plumbing Systems - Natural
Gas
HVAC $94,244
Distribution Systems & Exhaust
Systems
Terminal & Package Units $94,244
Controls & Instrumentation
Fire Protection
Sprinklers
Electrical $4,849
Electrical Service/Distribution
Branch Wiring
Lighting
Fire Alarm
Security & CCTV $4,849
Other Electrical Systems -
Emergency Generator
Equipment & Furnishings
Furnishings
Fixed Furnishings
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 28
Facility: \Administrative/Support\Central Office\Construction Capital Projects Building (continued)
Deficiency Sheet:
*** No Deficiencies Found ***
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 29
Facility: \Administrative/Support\Central Office\ROTC Maintenance Repair BuildilngAddress: 1961 Midway, Shreveport, LA 71130
Attributes: Number of Floors 1
General Information: Function: Administration/Support Year Built: 1950Gross Area: 35,000 S.F. Last Renovation: 1974
Facility Description:
The ROTC-Maintenance Building is a 1-story building located at 1961 Midway Street in Shreveport, Louisiana. There has been one addition of a partial slab and CMU building in 1974 and no renovations. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report.
Current Repair Cost: $598,063.00 Replacement Cost: $2,072,028.00 FCI: 28.86%
16-Apr-2010North Elevation
16-Apr-2010East Elevation
16-Apr-2010South Elevation
16-Apr-2010West Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 30
Facility: \Administrative/Support\Central Office\ROTC Maintenance Repair Buildilng (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $59.20 S.F. 35,000 105 $2,170,492 76 1966 1970 20 $598,062 $2,072,028 29
Substructure $11.09 S.F. 35,000 100 $388,248 100 1957 $18,000 $388,248 5
Foundations $11.09 S.F. 35,000 100 $388,248 100 1957 $18,000 $388,248 5
Standard Foundations $8.88 S.F. 35,000 100 $310,800 100 1950 $310,800
Slab on Grade $5.53 S.F. 14,000 100 $77,448 100 1974 $18,000 $77,448 23
Shell $32.87 S.F. 35,000 104 $1,201,805 82 1959 2004 20 $196,049 $1,150,380 17
Superstructure $12.30 S.F. 35,000 100 $430,500 100 1950 $430,500
Roof Construction $12.30 S.F. 35,000 100 $430,500 100 1950 $430,500
Exterior Enclosure $10.34 S.F. 35,000 104 $377,681 68 1974 2004 $196,049 $362,040 54
Exterior Walls $14.69 S.F. 14,000 100 $205,632 100 1974 $24,000 $205,632 12
Exterior Windows $9.17 S.F. 14,000 110 $141,187 30 1974 2004 $141,187 $128,352 110
Exterior Doors $2.00 S.F. 14,000 110 $30,862 30 1974 2004 $30,862 $28,056 110
Roofing $10.22 S.F. 35,000 110 $393,624 75 1950 2025 20 $357,840
Roof Coverings - BUR 0 0 0 0
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Metal
$10.22 S.F. 35,000 110 $393,624 75 1950 2025 20 $357,840
Roof Openings 0 0 0 0
Interiors $7.35 S.F. 35,000 108 $276,629 72 1974 1984 10 $80,203 $257,208 31
Interior Construction $5.27 S.F. 35,000 107 $196,426 95 1974 2014 10 $184,296
Partitions $11.66 S.F. 14,000 110 $179,626 100 1974 $163,296
Interior Doors $1.50 S.F. 14,000 80 $16,800 40 1974 2014 10 $21,000
Fittings 0 0 0 0
Interior Finishes $2.08 S.F. 35,000 110 $80,203 17 1974 1984 $80,203 $72,912 110
Wall Finishes - Paint $1.32 S.F. 14,000 110 $20,328 10 1974 1984 $20,328 $18,480 110
Floor Finishes - Carpet 0 0 0 0
Floor Finishes - Ceramic &
Quarry Tile
0 0 0 0
Floor Finishes Paint 0 0 0 0
Ceiling Finishes $3.89 S.F. 14,000 110 $59,875 20 1974 1994 $59,875 $54,432 110
Services $7.89 S.F. 35,000 110 $303,810 24 1972 1970 $303,810 $276,192 110
Plumbing $1.32 S.F. 35,000 110 $50,819 28 1974 1994 $50,819 $46,200 110
Plumbing Fixtures $0.24 S.F. 14,000 110 $3,696 30 1974 2004 $3,696 $3,360 110
Domestic Water Distribution $0.71 S.F. 14,000 110 $10,903 30 1974 2004 $10,903 $9,912 110
Sanitary Waste $1.84 S.F. 14,000 110 $28,274 30 1974 2004 $28,274 $25,704 110
Rain Water Drainage 0 0 0 0
Other Plumbing Systems -
Natural Gas
$0.52 S.F. 14,000 110 $7,946 20 1974 1994 $7,946 $7,224 110
HVAC $1.65 S.F. 35,000 110 $63,571 15 1962 1970 $63,571 $57,792 110
Distribution Systems & Exhaust
Systems
0 0 0 0
Terminal & Package Units $3.84 S.F. 14,000 110 $59,136 15 1974 1989 $59,136 $53,760 110
Controls & Instrumentation $0.29 S.F. 14,000 110 $4,435 20 1950 1970 $4,435 $4,032 110
Other HVAC Systems/Equip -
Exhaust Hoods
0 0 0 0
Fire Protection 0 0 0
Sprinklers 0 0 0 0
Electrical $4.92 S.F. 35,000 110 $189,420 25 1974 1984 $189,420 $172,200 110
Electrical Service/Distribution $3.70 S.F. 14,000 110 $56,918 30 1974 2004 $56,918 $51,744 110
Branch Wiring $3.71 S.F. 14,000 110 $57,103 30 1974 2004 $57,103 $51,912 110
Lighting $3.92 S.F. 14,000 110 $60,430 20 1974 1994 $60,430 $54,936 110
Communications and Security -
Fire Alarm
0 0 0 0
Communications and Security -
Security & CCTV
$0.97 S.F. 14,000 110 $14,969 10 1974 1984 $14,969 $13,608 110
Equipment & Furnishings 0 0 0
Furnishings 0 0 0
Fixed Furnishings 0 0 0 0
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 31
Facility: \Administrative/Support\Central Office\ROTC Maintenance Repair Buildilng (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $598,062 $18,909 $47,436
Substructure $18,000
Foundations $18,000
Standard Foundations
Slab on Grade $18,000
Shell $196,049
Superstructure
Roof Construction
Exterior Enclosure $196,049
Exterior Walls $24,000
Exterior Windows $141,187
Exterior Doors $30,862
Roofing
Roof Coverings - BUR
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Metal
Roof Openings
Interiors $80,203 $18,909 $27,319
Interior Construction $18,909
Partitions
Interior Doors $18,909
Fittings
Interior Finishes $80,203 $27,319
Wall Finishes - Paint $20,328 $27,319
Floor Finishes - Carpet
Floor Finishes - Ceramic & Quarry
Tile
Floor Finishes Paint
Ceiling Finishes $59,875
Services $303,810 $20,117
Plumbing $50,819
Plumbing Fixtures $3,696
Domestic Water Distribution $10,903
Sanitary Waste $28,274
Rain Water Drainage
Other Plumbing Systems - Natural
Gas
$7,946
HVAC $63,571
Distribution Systems & Exhaust
Systems
Terminal & Package Units $59,136
Controls & Instrumentation $4,435
Other HVAC Systems/Equip -
Exhaust Hoods
Fire Protection
Sprinklers
Electrical $189,420 $20,117
Electrical Service/Distribution $56,918
Branch Wiring $57,103
Lighting $60,430
Communications and Security - Fire
Alarm
Communications and Security -
Security & CCTV
$14,969 $20,117
Equipment & Furnishings
Furnishings
Fixed Furnishings
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 32
Facility: \Administrative/Support\Central Office\ROTC Maintenance Repair Buildilng (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Somnath Das Mon, 07-Jun-2010Priority: 2Quantity: 1
Assembly: A1030 System: Slab on Grade Material: Foundations Distress: Failing Category: Critical Repair Correction: Professional Service - Investigate Foundation Note: The foundation slab has observable cracks that should be studied by a professional structural engineer.
Estimates:Raw Cost $15,000.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $15,000.00
Deficiency: Surveyor/Update: Somnath Das Mon, 07-Jun-2010Priority: 2Quantity: 1
Assembly: B2010 System: Exterior Walls Material: Exterior Walls Distress: Failing Category: Critical Repair Correction: Professional Structural Engineer Note: The exterior have show observable cracks that should be studied by a professional structural engineer.
Estimates:Raw Cost $20,000.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $20,000.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 33
Facility: \Administrative/Support\Central Office\ ROTC Maintenance Repair Buildilng (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B2020 System: Exterior Windows Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The exterior windows are beyond expected life and should be replaced.
Estimates:Raw Cost $117,656.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $117,656.00
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B2030 System: Exterior Doors Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The exterior doors are beyond expected life and should be replaced.
Estimates:Raw Cost $25,718.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $25,718.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 34
Facility: \Administrative/Support\Central Office\ ROTC Maintenance Repair Buildilng (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Paint Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The painted wall finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $16,940.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $16,940.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3030 System: Ceiling Finishes Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The ceiling finishes are stained, beyond expected life, and should be replaced.
Estimates:Raw Cost $49,896.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $49,896.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 35
Facility: \Administrative/Support\Central Office\ ROTC Maintenance Repair Buildilng (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2010 System: Plumbing Fixtures Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Wash sink is beyond expected life and should be replaced. The building does not have restroom facilities.
Estimates:Raw Cost $3,080.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $3,080.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2020 System: Domestic Water Distribution Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Domestic water system is beyond expected life and should be replaced.
Estimates:Raw Cost $9,086.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $9,086.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 36
Facility: \Administrative/Support\Central Office\ ROTC Maintenance Repair Buildilng (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2030 System: Sanitary Waste Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Sanitary waste system is beyond expected life and should be replaced.
Estimates:Raw Cost $23,562.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $23,562.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2090 System: Other Plumbing Systems - Natural Gas Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Natural gas system is beyond expected life and should be replaced.
Estimates:Raw Cost $6,622.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $6,622.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 37
Facility: \Administrative/Support\Central Office\ ROTC Maintenance Repair Buildilng (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D3050 System: Terminal & Package Units Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: HVAC system is inadequate, beyond expected life, and should be replaced.
Estimates:Raw Cost $49,280.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $49,280.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D3060 System: Controls & Instrumentation Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Controls are obsolete, beyond expecte life, and should be replaced.
Estimates:Raw Cost $3,696.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $3,696.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 38
Facility: \Administrative/Support\Central Office\ ROTC Maintenance Repair Buildilng (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5010 System: Electrical Service/Distribution Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Electrical service is beyond expected life and should be replaced.
Estimates:Raw Cost $47,432.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $47,432.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5020 System: Branch Wiring Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Wiring is mostly original, beyond expected life, and should be replaced.
Estimates:Raw Cost $47,586.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $47,586.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 39
Facility: \Administrative/Support\Central Office\ ROTC Maintenance Repair Buildilng (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5020 System: Lighting Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Lighting system is beyond expected life and should be replaced.
Estimates:Raw Cost $50,358.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $50,358.00
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: D5030 System: Communications and Security - Security &
CCTV Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Building security is inadequate, past expected life, and should be replaced. For integrity of system, install wiring
in conduit.
Estimates:Raw Cost $12,474.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $12,474.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 40
Facility: \Administrative/Support\Central Office\SiteAddress: 1961 Midway, Shreveport, LA 71130
Attributes: Site Area (in Acres) 15.0
General Information: Function: Administration/Support Year Built: 1954Gross Area: 142,935 S.F. Last Renovation:
Facility Description:
The original site was constructed in 1954. There have been no additions, major renovations, or any additional improvements to the site. Campus site features include paved driveways and parking lots, pedestrian pavement, flag pole, landscaping, and fencing. Site mechanical and electrical features include water, sewer, natural gas, and site lighting. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report for each building.
Current Repair Cost: $1,387,613.00 Replacement Cost: $2,137,164.00 FCI: 64.93%
19-Apr-2010Aerial Image of Central Office
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 41
Facility: \Administrative/Support\Central Office\Site (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $14.95 S.F. 142,935 100 $2,137,163 33 1958 1974 2015 25 $1,387,612 $2,137,163 65
Building Sitework $14.95 S.F. 142,935 100 $2,137,163 33 1958 1974 2015 25 $1,387,612 $2,137,163 65
Site Improvements $8.50 S.F. 142,935 100 $1,214,376 28 1954 1974 2015 25 $481,977 $1,214,376 40
Roadways $1.38 S.F. 142,935 100 $197,250 50 1954 2004 $197,250 $197,250 100
Parking Lots $1.18 S.F. 142,935 100 $168,092 30 1954 1984 $168,092 $168,092 100
Pedestrian Paving $0.82 S.F. 142,935 100 $116,635 50 1954 2004 $116,635 $116,635 100
Site Development $3.86 S.F. 142,935 100 $552,301 20 1954 1974 2015 25 $552,301
Landscaping $1.26 S.F. 142,935 100 $180,098 10 1954 $180,098
Site Mechanical Utilities $4.86 S.F. 142,935 100 $694,663 44 1963 1984 37 $677,511 $694,663 98
Water Supply $0.82 S.F. 142,935 100 $116,635 30 1954 1984 $116,635 $116,635 100
Sanitary Sewer $0.41 S.F. 142,935 100 $58,317 30 1954 1984 $58,317 $58,317 100
Storm Sewer $3.52 S.F. 142,935 100 $502,559 50 1954 2004 $502,559 $502,559 100
Fuel Distribution $0.12 S.F. 142,935 100 $17,152 30 1991 2021 37 $17,152
Site Electrical Utilities $1.60 S.F. 142,935 100 $228,124 30 1954 1984 $228,124 $228,124 100
Site Lighting $1.60 S.F. 142,935 100 $228,124 30 1954 1984 $228,124 $228,124 100
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 42
Facility: \Administrative/Support\Central Office\Site (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $1,387,612 $640,268
Building Sitework $1,387,612 $640,268
Site Improvements $481,977 $640,268
Roadways $197,250
Parking Lots $168,092
Pedestrian Paving $116,635
Site Development $640,268
Landscaping
Site Mechanical Utilities $677,511
Water Supply $116,635
Sanitary Sewer $58,317
Storm Sewer $502,559
Fuel Distribution
Site Electrical Utilities $228,124
Site Lighting $228,124
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 43
Facility: \Administrative/Support\Central Office\Site (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Somnath Das Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: G2010 System: Roadways Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The roadways are beyond expected life and should be replaced.
Estimates:Raw Cost $164,375.25
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $164,375.25
Deficiency: Surveyor/Update: Somnath Das Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: G2020 System: Parking Lots Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The parking lots are beyond expected life and should be resurfaced and restriped.
Estimates:Raw Cost $140,076.30
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $140,076.30
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 44
Facility: \Administrative/Support\Central Office\ Site (continued)
Deficiency: Surveyor/Update: Somnath Das Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: G2030 System: Pedestrian Paving Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The pedestrian paving is cracked and should be replaced.
Estimates:Raw Cost $97,195.80
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $97,195.80
Deficiency: Surveyor/Update: Somnath Das Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: G3010 System: Water Supply Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Water supply system is beyond expected life and should be replaced.
Estimates:Raw Cost $97,195.80
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $97,195.80
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 45
Facility: \Administrative/Support\Central Office\ Site (continued)
Deficiency: Surveyor/Update: Somnath Das Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: G3020 System: Sanitary Sewer Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Sanitary sewer system is original, beyond expected life, and should be replaced.
Estimates:Raw Cost $48,597.90
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $48,597.90
Deficiency: Surveyor/Update: Somnath Das Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: G3030 System: Storm Sewer Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Storm sewer system is beyond expected life and should be replaced.
Estimates:Raw Cost $418,799.55
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $418,799.55
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 46
Facility: \Administrative/Support\Central Office\ Site (continued)
Deficiency: Surveyor/Update: Somnath Das Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: G4020 System: Site Lighting Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Site lighting is past expected life and should be replaced.
Estimates:Raw Cost $190,103.55
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $190,103.55
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 47
Facility: \Administrative/Support\Central Office\Teacher Resource BuildingAddress: 1961 Midway, Shreveport, LA 71130
Attributes: Number of Floors 1
General Information: Function: Administration/Support Year Built: 1974Gross Area: 19,784 S.F. Last Renovation: 1991
Facility Description:
The Teacher Resource Building is a 1-story building located at 1961 Midway Street in Shreveport, Louisiana. There have been no additions, but there was a renovation and conversion in 1991, and the building is currently undergoing upgrades to accommodate Information Services. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report.
Current Repair Cost: $697,549.00 Replacement Cost: $2,937,807.00 FCI: 23.74%
19-Apr-2010West Elevation
19-Apr-2010South Elevation
19-Apr-2010East Elevation
19-Apr-2010North Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 48
Facility: \Administrative/Support\Central Office\Teacher Resource Building (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $148.49 S.F. 19,784 107 $3,140,779 46 1989 1999 2010 28 $697,548 $2,937,809 24
Substructure $14.41 S.F. 19,784 100 $285,127 100 1974 $285,127
Foundations $14.41 S.F. 19,784 100 $285,127 100 1974 $285,127
Standard Foundations $8.88 S.F. 19,784 100 $175,682 100 1974 $175,682
Slab on Grade $5.53 S.F. 19,784 100 $109,445 100 1974 $109,445
Shell $48.38 S.F. 19,784 104 $999,559 65 1984 2011 22 $122,499 $957,229 13
Superstructure $12.30 S.F. 19,784 100 $243,343 100 1974 $243,343
Roof Construction $12.30 S.F. 19,784 100 $243,343 100 1974 $243,343
Exterior Enclosure $25.86 S.F. 19,784 104 $533,717 68 1985 2021 37 $122,499 $511,614 24
Exterior Walls $14.69 S.F. 19,784 100 $290,587 100 1974 $24,000 $290,587 8
Exterior Windows $9.17 S.F. 19,784 110 $199,518 30 1991 2021 37 $98,499 $181,380 54
Exterior Doors $2.00 S.F. 19,784 110 $43,612 30 1991 2021 37 $39,647
Roofing $10.22 S.F. 19,784 110 $222,499 20 1991 2011 5 $202,272
Roof Coverings - BUR $10.22 S.F. 19,784 110 $222,499 20 1991 2011 5 $202,272
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Metal
0 0 0 0
Roof Openings 0 0 0 0
Interiors $20.38 S.F. 19,784 108 $434,659 44 1988 1999 2010 12 $113,338 $403,239 28
Interior Construction $10.60 S.F. 19,784 106 $221,691 68 1985 2011 17 $209,631
Partitions $5.83 S.F. 19,784 110 $126,918 100 1974 $115,380
Interior Doors $1.50 S.F. 19,784 80 $23,741 40 1991 2031 52 $29,676
Fittings $3.26 S.F. 19,784 110 $71,032 20 1991 2011 5 $64,575
Interior Finishes $9.79 S.F. 19,784 110 $212,968 18 1991 1999 2010 8 $113,338 $193,608 59
Wall Finishes - Paint $1.32 S.F. 19,784 110 $28,726 10 1991 2001 $28,726 $26,115 110
Floor Finishes - Carpet $3.34 S.F. 1,500 110 $5,504 8 1991 1999 2015 62 $5,004
Floor Finishes - Ceramic &
Quarry Tile
0 0 0 0
Floor Finishes - VCT $4.68 S.F. 18,284 110 $94,126 20 1991 2011 5 $85,569
Ceiling Finishes $3.89 S.F. 19,784 110 $84,612 20 1991 2011 2010 $84,612 $76,920 110
Services $63.56 S.F. 19,784 110 $1,383,306 23 1993 2006 35 $461,711 $1,257,552 37
Plumbing $9.36 S.F. 19,784 110 $203,697 29 1991 2011 35 $185,179
Plumbing Fixtures $5.93 S.F. 19,784 110 $129,008 30 1991 2021 37 $117,280
Domestic Water Distribution $0.71 S.F. 19,784 110 $15,408 30 1991 2021 37 $14,007
Sanitary Waste $1.84 S.F. 19,784 110 $39,956 30 1991 2021 37 $36,323
Rain Water Drainage $0.37 S.F. 19,784 110 $8,096 30 1991 2021 37 $7,360
Other Plumbing Systems -
Natural Gas
$0.52 S.F. 19,784 110 $11,229 20 1991 2011 5 $10,209
HVAC $24.80 S.F. 19,784 110 $539,794 17 1991 2006 28 $440,558 $490,723 90
Distribution Systems & Exhaust
Systems
$2.76 S.F. 19,784 110 $60,064 30 1991 2021 37 $54,604
Terminal & Package Units $20.24 S.F. 19,784 110 $440,558 15 1991 2006 $440,558 $400,507 110
Controls & Instrumentation $1.28 S.F. 19,784 110 $27,943 20 1991 2011 5 $25,403
Other HVAC Systems/Equip -
Exhaust Hoods
$0.52 S.F. 19,784 110 $11,229 30 1991 2021 37 $10,209
Fire Protection $3.30 S.F. 19,784 110 $71,816 30 1991 2021 37 $65,287
Sprinklers $3.30 S.F. 19,784 110 $71,816 30 1991 2021 37 $65,287
Electrical $26.10 S.F. 19,784 110 $567,999 25 1998 2010 36 $21,153 $516,363 4
Electrical Service/Distribution $3.70 S.F. 19,784 110 $80,434 30 1991 2021 37 $73,122
Branch Wiring $7.50 S.F. 19,784 110 $163,218 30 1991 2021 37 $148,380
Lighting $7.50 S.F. 19,784 110 $163,218 20 1991 2011 5 $148,380
Communications and Security -
Fire Alarm
$2.27 S.F. 19,784 110 $49,357 10 2002 2012 20 $44,870
Communications and Security -
Security & CCTV
$0.97 S.F. 19,784 110 $21,153 10 2000 2010 $21,153 $19,230 110
Other Electrical Systems
Emergency Generators
$4.16 S.F. 19,784 110 $90,619 30 2010 2040 100 $82,381
Equipment & Furnishings $1.75 S.F. 19,784 110 $38,128 20 1991 2011 5 $34,662
Furnishings $1.75 S.F. 19,784 110 $38,128 20 1991 2011 5 $34,662
Fixed Furnishings $1.75 S.F. 19,784 110 $38,128 20 1991 2011 5 $34,662
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 49
Facility: \Administrative/Support\Central Office\Teacher Resource Building (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $697,548 $647,021 $52,363 $6,381 $67,034
Substructure
Foundations
Standard Foundations
Slab on Grade
Shell $122,499 $229,174
Superstructure
Roof Construction
Exterior Enclosure $122,499
Exterior Walls $24,000
Exterior Windows $98,499
Exterior Doors
Roofing $229,174
Roof Coverings - BUR $229,174
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Metal
Roof Openings
Interiors $113,338 $170,113 $6,381 $38,606
Interior Construction $73,163
Partitions
Interior Doors
Fittings $73,163
Interior Finishes $113,338 $96,950 $6,381 $38,606
Wall Finishes - Paint $28,726 $38,606
Floor Finishes - Carpet $6,381
Floor Finishes - Ceramic & Quarry
Tile
Floor Finishes - VCT $96,950
Ceiling Finishes $84,612
Services $461,711 $208,462 $52,363 $28,428
Plumbing $11,566
Plumbing Fixtures
Domestic Water Distribution
Sanitary Waste
Rain Water Drainage
Other Plumbing Systems - Natural
Gas
$11,566
HVAC $440,558 $28,781
Distribution Systems & Exhaust
Systems
Terminal & Package Units $440,558
Controls & Instrumentation $28,781
Other HVAC Systems/Equip -
Exhaust Hoods
Fire Protection
Sprinklers
Electrical $21,153 $168,115 $52,363 $28,428
Electrical Service/Distribution
Branch Wiring
Lighting $168,115
Communications and Security - Fire
Alarm
$52,363
Communications and Security -
Security & CCTV
$21,153 $28,428
Other Electrical Systems Emergency
Generators
Equipment & Furnishings $39,272
Furnishings $39,272
Fixed Furnishings $39,272
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 50
Facility: \Administrative/Support\Central Office\Teacher Resource Building (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Somnath Das Thu, 06-May-2010Priority: 2Quantity: 1
Assembly: B2010 System: Exterior Walls Material: Exterior Walls Distress: Failing Category: Critical Repair Correction: Professional Structural Engineer Note: The exterior walls show observable cracks that should be studied by a professional structural engineer.
Estimates:Raw Cost $20,000.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $20,000.00
Deficiency: Surveyor/Update: Somnath Das Thu, 06-May-2010Priority: 3Quantity: 50
Assembly: B2020 System: Exterior Windows Material: Exterior Windows Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Replace Double Hung Steel Window Note: The exterior windows on the north side of the building are beyond expected life and should be replaced.
Estimates:Raw Cost $82,082.50
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $82,082.50
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 51
Facility: \Administrative/Support\Central Office\ Teacher Resource Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Paint Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The painted wall finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $23,938.64
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $23,938.64
Deficiency: Surveyor/Update: Somnath Das Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3030 System: Ceiling Finishes Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The ceiling finishes are stained, beyond expected life, and should be replaced.
Estimates:Raw Cost $70,510.18
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $70,510.18
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 52
Facility: \Administrative/Support\Central Office\ Teacher Resource Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D3050 System: Terminal & Package Units Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Roof mounted air handler is beyond expected life and should be replaced.
Estimates:Raw Cost $367,131.69
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $367,131.69
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: D5030 System: Communications and Security - Security &
CCTV Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Security system is inoperable, past expected life, and should be replaced. For integrity of system, install wiring in
conduit.
Estimates:Raw Cost $17,627.54
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $17,627.54
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 53
Facility: \Administrative/Support\Central Office\Transportation BuildingAddress: 1961 Midway, Shreveport, LA 71130
Attributes: Number of Floors 1
General Information: Function: Administration/Support Year Built: 1994Gross Area: 10,000 S.F. Last Renovation:
Facility Description:
The Transportation Building is a 1-story building located at 1961 Midway Street in Shreveport, Louisiana. There have been no additions and no renovations. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report.
Current Repair Cost: $82,236.00 Replacement Cost: $1,308,360.00 FCI: 6.29%
19-Apr-2010North Elevation
19-Apr-2010West Elevation
19-Apr-2010South Elevation
19-Apr-2010East Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 54
Facility: \Administrative/Support\Central Office\Transportation Building (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $130.84 S.F. 10,000 106 $1,393,296 51 1994 2004 37 $82,236 $1,308,360 6
Substructure $14.41 S.F. 10,000 100 $144,120 100 1994 $144,120
Foundations $14.41 S.F. 10,000 100 $144,120 100 1994 $144,120
Standard Foundations $8.88 S.F. 10,000 100 $88,800 100 1994 $88,800
Slab on Grade $5.53 S.F. 10,000 100 $55,320 100 1994 $55,320
Shell $48.38 S.F. 10,000 104 $505,236 65 1994 2014 34 $483,840
Superstructure $12.30 S.F. 10,000 100 $123,000 100 1994 $123,000
Roof Construction $12.30 S.F. 10,000 100 $123,000 100 1994 $123,000
Exterior Enclosure $25.86 S.F. 10,000 104 $269,772 68 1994 2024 47 $258,600
Exterior Walls $14.69 S.F. 10,000 100 $146,880 100 1994 $146,880
Exterior Windows $9.17 S.F. 10,000 110 $100,848 30 1994 2024 47 $91,680
Exterior Doors $2.00 S.F. 10,000 110 $22,044 30 1994 2024 47 $20,040
Roofing $10.22 S.F. 10,000 110 $112,464 20 1994 2014 20 $102,240
Roof Coverings - BUR $10.22 S.F. 10,000 110 $112,464 20 1994 2014 20 $102,240
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Metal
0 0 0 0
Roof Openings 0 0 0 0
Interiors $15.54 S.F. 10,000 107 $166,440 52 1994 2004 25 $7,260 $155,400 5
Interior Construction $10.60 S.F. 10,000 106 $112,056 68 1994 2014 30 $105,960
Partitions $5.83 S.F. 10,000 110 $64,152 100 1994 $58,320
Interior Doors $1.50 S.F. 10,000 80 $12,000 40 1994 2034 60 $15,000
Fittings $3.26 S.F. 10,000 110 $35,904 20 1994 2014 20 $32,640
Interior Finishes $4.94 S.F. 10,000 110 $54,384 19 1994 2004 20 $7,260 $49,440 15
Wall Finishes - Paint $1.32 S.F. 5,000 110 $7,260 10 1994 2004 $7,260 $6,600 110
Floor Finishes - Carpet 0 0 0 0
Floor Finishes - Ceramic &
Quarry Tile
0 0 0 0
Floor Finishes - VCT $4.68 S.F. 5,000 110 $25,740 20 1994 2014 20 $23,400
Ceiling Finishes $3.89 S.F. 5,000 110 $21,384 20 1994 2014 20 $19,440
Services $50.75 S.F. 10,000 110 $558,228 26 1994 2004 41 $74,976 $507,480 15
Plumbing $9.36 S.F. 10,000 110 $102,960 29 1994 2014 46 $93,600
Plumbing Fixtures $5.93 S.F. 10,000 110 $65,208 30 1994 2024 47 $59,280
Domestic Water Distribution $0.71 S.F. 10,000 110 $7,788 30 1994 2024 47 $7,080
Sanitary Waste $1.84 S.F. 10,000 110 $20,196 30 1994 2024 47 $18,360
Rain Water Drainage $0.37 S.F. 10,000 110 $4,092 30 1994 2024 47 $3,720
Other Plumbing Systems -
Natural Gas
$0.52 S.F. 10,000 110 $5,676 20 1994 2014 20 $5,160
HVAC $18.42 S.F. 10,000 110 $202,620 24 1994 2009 42 $64,284 $184,200 35
Distribution Systems & Exhaust
Systems
$9.70 S.F. 10,000 110 $106,656 30 1994 2024 47 $96,960
Terminal & Package Units $5.84 S.F. 10,000 110 $64,284 15 1994 2009 $64,284 $58,440 110
Controls & Instrumentation $2.36 S.F. 10,000 110 $26,004 20 1994 2014 20 $23,640
Other HVAC Systems/Equip -
Exhaust Hoods
$0.52 S.F. 10,000 110 $5,676 30 1994 2024 47 $5,160
Fire Protection $3.30 S.F. 10,000 110 $36,300 30 1994 2024 47 $33,000
Sprinklers $3.30 S.F. 10,000 110 $36,300 30 1994 2024 47 $33,000
Electrical $19.67 S.F. 10,000 110 $216,348 25 1994 2004 36 $10,692 $196,680 5
Electrical Service/Distribution $3.70 S.F. 10,000 110 $40,656 30 1994 2024 47 $36,960
Branch Wiring $7.50 S.F. 10,000 110 $82,500 30 1994 2024 47 $75,000
Lighting $7.50 S.F. 10,000 110 $82,500 20 1994 2014 20 $75,000
Communications and Security -
Fire Alarm
0 0 0 0
Communications and Security -
Security & CCTV
$0.97 S.F. 10,000 110 $10,692 10 1994 2004 $10,692 $9,720 110
Equipment & Furnishings $1.75 S.F. 10,000 110 $19,272 20 1994 2014 20 $17,520
Furnishings $1.75 S.F. 10,000 110 $19,272 20 1994 2014 20 $17,520
Fixed Furnishings $1.75 S.F. 10,000 110 $19,272 20 1994 2014 20 $17,520
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 55
Facility: \Administrative/Support\Central Office\Transportation Building (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $82,236 $370,229 $24,126
Substructure
Foundations
Standard Foundations
Slab on Grade
Shell $126,579
Superstructure
Roof Construction
Exterior Enclosure
Exterior Walls
Exterior Windows
Exterior Doors
Roofing $126,579
Roof Coverings - BUR $126,579
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Metal
Roof Openings
Interiors $7,260 $93,449 $9,757
Interior Construction $40,410
Partitions
Interior Doors
Fittings $40,410
Interior Finishes $7,260 $53,039 $9,757
Wall Finishes - Paint $7,260 $9,757
Floor Finishes - Carpet
Floor Finishes - Ceramic & Quarry
Tile
Floor Finishes - VCT $28,971
Ceiling Finishes $24,068
Services $74,976 $128,510 $14,369
Plumbing $6,388
Plumbing Fixtures
Domestic Water Distribution
Sanitary Waste
Rain Water Drainage
Other Plumbing Systems - Natural
Gas
$6,388
HVAC $64,284 $29,268
Distribution Systems & Exhaust
Systems
Terminal & Package Units $64,284
Controls & Instrumentation $29,268
Other HVAC Systems/Equip -
Exhaust Hoods
Fire Protection
Sprinklers
Electrical $10,692 $92,854 $14,369
Electrical Service/Distribution
Branch Wiring
Lighting $92,854
Communications and Security - Fire
Alarm
Communications and Security -
Security & CCTV
$10,692 $14,369
Equipment & Furnishings $21,691
Furnishings $21,691
Fixed Furnishings $21,691
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 56
Facility: \Administrative/Support\Central Office\Transportation Building (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Paint Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The painted wall finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $6,050.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $6,050.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D3050 System: Terminal & Package Units Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The office has window units. The garage is heated, but not air conditioned. System is beyond expected life and
should be replaced.
Estimates:Raw Cost $53,570.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $53,570.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 57
Facility: \Administrative/Support\Central Office\ Transportation Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: D5030 System: Communications and Security - Security &
CCTV Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Security system is inadequate, past expected life, and should be replaced. For integrity of system, install wiring
in conduit.
Estimates:Raw Cost $8,910.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $8,910.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 58
Facility: \Administrative/Support\Central Office\Vehicle & Bus Wash BuildingAddress: 1961 Midway, Shreveport, LA 71130
Attributes: Number of Floors 1
General Information: Function: Administration/Support Year Built: 1995Gross Area: 1,055 S.F. Last Renovation:
Facility Description:
The Vehicle and Bus Wash Building is a 1-story building located at 1961 Midway Street in Shreveport, Louisiana. There have been no additions and no renovations. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report.
Current Repair Cost: $0.00 Replacement Cost: $52,121.00 FCI: 0.00%
19-Apr-2010North Elevation
19-Apr-2010West Elevation
19-Apr-2010South Elevation
19-Apr-2010East Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 59
Facility: \Administrative/Support\Central Office\Vehicle & Bus Wash Building (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $49.40 S.F. 1,055 104 $54,005 82 1995 2025 65 0 $52,122
Substructure $14.38 S.F. 1,055 100 $15,167 100 1995 $15,167
Foundations $14.38 S.F. 1,055 100 $15,167 100 1995 $15,167
Standard Foundations $8.26 S.F. 1,055 100 $8,710 100 1995 $8,710
Slab on Grade $6.12 S.F. 1,055 100 $6,457 100 1995 $6,457
Shell $26.38 S.F. 1,055 103 $28,798 91 1995 2070 80 $27,827
Superstructure $11.48 S.F. 1,055 100 $12,116 100 1995 $12,116
Roof Construction $11.48 S.F. 1,055 100 $12,116 100 1995 $12,116
Exterior Enclosure $5.69 S.F. 1,055 100 $6,001 100 1995 $6,001
Exterior Walls $5.69 S.F. 1,055 100 $6,001 100 1995 $6,001
Exterior Doors 0 0 0 0
Roofing $9.20 S.F. 1,055 110 $10,681 75 1995 2070 80 $9,710
Roof Coverings - Standing
Seam Metal
$9.20 S.F. 1,055 110 $10,681 75 1995 2070 80 $9,710
Interiors 0 0 0
Interior Construction 0 0 0
Fittings 0 0 0 0
Interior Finishes 0 0 0
Wall Finishes - Paint 0 0 0 0
Ceiling Finishes 0 0 0 0
Services $8.65 S.F. 1,055 110 $10,040 30 1995 2025 50 $9,128
Plumbing $7.09 S.F. 1,055 110 $8,230 30 1995 2025 50 $7,482
Wash Equipment $5.89 S.F. 1,055 110 $6,838 30 1995 2025 50 $6,216
Domestic Water Distribution $0.44 S.F. 1,055 110 $515 30 1995 2025 50 $468
Sanitary Waste $0.76 S.F. 1,055 110 $877 30 1995 2025 50 $798
HVAC 0 0 0
Terminal & Package Units 0 0 0 0
Controls & Instrumentation 0 0 0 0
Electrical $1.56 S.F. 1,055 110 $1,810 30 1995 2025 50 $1,646
Electrical Service/Distribution $1.56 S.F. 1,055 110 $1,810 30 1995 2025 50 $1,646
Branch Wiring 0 0 0 0
Lighting 0 0 0 0
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 60
Facility: \Administrative/Support\Central Office\Vehicle & Bus Wash Building (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total
Substructure
Foundations
Standard Foundations
Slab on Grade
Shell
Superstructure
Roof Construction
Exterior Enclosure
Exterior Walls
Exterior Doors
Roofing
Roof Coverings - Standing Seam
Metal
Interiors
Interior Construction
Fittings
Interior Finishes
Wall Finishes - Paint
Ceiling Finishes
Services
Plumbing
Wash Equipment
Domestic Water Distribution
Sanitary Waste
HVAC
Terminal & Package Units
Controls & Instrumentation
Electrical
Electrical Service/Distribution
Branch Wiring
Lighting
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 61
Facility: \Administrative/Support\Central Office\Vehicle & Bus Wash Building (continued)
Deficiency Sheet:
*** No Deficiencies Found ***
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 62
Facility: \Administrative/Support\Central Office\Welding ShopAddress: 1961 Midway, Shreveport, LA 71130
Attributes: Number of Floors 1
General Information: Function: Administration/Support Year Built: 1974Gross Area: 1,350 S.F. Last Renovation:
Facility Description:
The Welding Shop is a 1-story building located at 1961 Midway Street in Shreveport, Louisiana. There have been no additions and no renovations. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report.
Current Repair Cost: $72,688.00 Replacement Cost: $126,020.00 FCI: 57.68%
19-Apr-2010North Elevation
19-Apr-2010East Elevation
19-Apr-2010South Elevation
19-Apr-2010West Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 63
Facility: \Administrative/Support\Central Office\Welding Shop (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $93.35 S.F. 1,350 106 $133,034 57 1976 1984 17 $72,688 $126,020 58
Substructure $14.41 S.F. 1,350 100 $19,456 100 1974 $19,456
Foundations $14.41 S.F. 1,350 100 $19,456 100 1974 $19,456
Standard Foundations $8.88 S.F. 1,350 100 $11,988 100 1974 $11,988
Slab on Grade $5.53 S.F. 1,350 100 $7,468 100 1974 $7,468
Shell $48.38 S.F. 1,350 104 $68,207 65 1974 1994 $31,773 $65,318 49
Superstructure $12.30 S.F. 1,350 100 $16,605 100 1974 $16,605
Roof Construction $12.30 S.F. 1,350 100 $16,605 100 1974 $16,605
Exterior Enclosure $25.86 S.F. 1,350 104 $36,419 68 1974 2004 $16,590 $34,911 48
Exterior Walls $14.69 S.F. 1,350 100 $19,829 100 1974 $19,829
Exterior Windows $9.17 S.F. 1,350 110 $13,614 30 1974 2004 $13,614 $12,377 110
Exterior Doors $2.00 S.F. 1,350 110 $2,976 30 1974 2004 $2,976 $2,705 110
Roofing $10.22 S.F. 1,350 110 $15,183 20 1974 1994 $15,183 $13,802 110
Roof Coverings - BUR $10.22 S.F. 1,350 110 $15,183 20 1974 1994 $15,183 $13,802 110
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Metal
0 0 0 0
Roof Openings 0 0 0 0
Interiors $3.26 S.F. 1,350 110 $4,847 46 1974 1984 $3,029 $4,406 69
Interior Construction $1.22 S.F. 1,350 110 $1,818 100 1974 $1,652
Partitions $1.22 S.F. 1,350 110 $1,818 100 1974 $1,652
Interior Doors 0 0 0 0
Fittings 0 0 0 0
Interior Finishes $2.04 S.F. 1,350 110 $3,029 14 1974 1984 $3,029 $2,754 110
Wall Finishes - Paint $1.32 S.F. 1,350 110 $1,960 10 1974 1984 $1,960 $1,782 110
Floor Finishes - Carpet 0 0 0 0
Floor Finishes - Ceramic &
Quarry Tile
0 0 0 0
Floor Finishes -Paint $0.72 S.F. 1,350 110 $1,069 20 1974 1994 $1,069 $972 110
Ceiling Finishes 0 0 0 0
Services $27.29 S.F. 1,350 110 $40,524 25 1979 1989 17 $37,886 $36,840 103
Plumbing $2.29 S.F. 1,350 110 $3,404 28 1984 1994 17 $766 $3,095 25
Plumbing Fixtures $1.02 S.F. 1,350 110 $1,515 30 1981 2011 3 $1,377
Domestic Water Distribution $0.42 S.F. 1,350 110 $624 30 1991 2021 37 $567
Sanitary Waste $0.34 S.F. 1,350 110 $499 30 1991 2021 37 $454
Rain Water Drainage 0 0 0 0
Other Plumbing Systems -
Natural Gas
$0.52 S.F. 1,350 110 $766 20 1974 1994 $766 $697 110
HVAC $3.00 S.F. 1,350 110 $4,455 15 1974 1989 $4,455 $4,050 110
Distribution Systems & Exhaust
Systems
0 0 0 0
Terminal & Package Units $3.00 S.F. 1,350 110 $4,455 15 1974 1989 $4,455 $4,050 110
Controls & Instrumentation 0 0 0 0
Other HVAC Systems/Equip -
Exhaust Hoods
0 0 0 0
Fire Protection $3.30 S.F. 1,350 110 $4,900 30 1974 2004 $4,900 $4,455 110
Sprinklers $3.30 S.F. 1,350 110 $4,900 30 1974 2004 $4,900 $4,455 110
Electrical $18.70 S.F. 1,350 110 $27,765 26 1974 1994 $27,765 $25,240 110
Electrical Service/Distribution $3.70 S.F. 1,350 110 $5,489 30 1974 2004 $5,489 $4,990 110
Branch Wiring $7.50 S.F. 1,350 110 $11,138 30 1974 2004 $11,138 $10,125 110
Lighting $7.50 S.F. 1,350 110 $11,138 20 1974 1994 $11,138 $10,125 110
Communications and Security -
Fire Alarm
0 0 0 0
Communications and Security -
Security & CCTV
0 0 0 0
Equipment & Furnishings 0 0 0
Furnishings 0 0 0
Fixed Furnishings 0 0 0 0
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 64
Facility: \Administrative/Support\Central Office\Welding Shop (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $72,688 $1,560 $2,634
Substructure
Foundations
Standard Foundations
Slab on Grade
Shell $31,773
Superstructure
Roof Construction
Exterior Enclosure $16,590
Exterior Walls
Exterior Windows $13,614
Exterior Doors $2,976
Roofing $15,183
Roof Coverings - BUR $15,183
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Metal
Roof Openings
Interiors $3,029 $2,634
Interior Construction
Partitions
Interior Doors
Fittings
Interior Finishes $3,029 $2,634
Wall Finishes - Paint $1,960 $2,634
Floor Finishes - Carpet
Floor Finishes - Ceramic & Quarry
Tile
Floor Finishes -Paint $1,069
Ceiling Finishes
Services $37,886 $1,560
Plumbing $766 $1,560
Plumbing Fixtures $1,560
Domestic Water Distribution
Sanitary Waste
Rain Water Drainage
Other Plumbing Systems - Natural
Gas
$766
HVAC $4,455
Distribution Systems & Exhaust
Systems
Terminal & Package Units $4,455
Controls & Instrumentation
Other HVAC Systems/Equip -
Exhaust Hoods
Fire Protection $4,900
Sprinklers $4,900
Electrical $27,765
Electrical Service/Distribution $5,489
Branch Wiring $11,138
Lighting $11,138
Communications and Security - Fire
Alarm
Communications and Security -
Security & CCTV
Equipment & Furnishings
Furnishings
Fixed Furnishings
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 65
Facility: \Administrative/Support\Central Office\Welding Shop (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B2020 System: Exterior Windows Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The exterior windows are beyond expected life and should be replaced.
Estimates:Raw Cost $11,345.40
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $11,345.40
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B2030 System: Exterior Doors Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The exterior doors are beyond expected life and should be replaced.
Estimates:Raw Cost $2,479.95
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $2,479.95
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 66
Facility: \Administrative/Support\Central Office\ Welding Shop (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B3010 System: Roof Coverings - BUR Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The roof covering is beyond expected life and should be replaced. Roof replacement to include appropriate
insulation for energy conservation
Estimates:Raw Cost $12,652.20
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $12,652.20
Deficiency: Surveyor/Update: Somnath Das Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Paint Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The painted wall finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $1,633.50
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $1,633.50
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 67
Facility: \Administrative/Support\Central Office\ Welding Shop (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: C3020 System: Floor Finishes -Paint Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The painted floor finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $891.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $891.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2090 System: Other Plumbing Systems - Natural Gas Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Natural gas system is beyond expected life and should be replaced.
Estimates:Raw Cost $638.55
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $638.55
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 68
Facility: \Administrative/Support\Central Office\ Welding Shop (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D3050 System: Terminal & Package Units Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Unit heaters are beyond expected life and should be replaced.
Estimates:Raw Cost $3,712.50
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $3,712.50
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D4010 System: Sprinklers Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Sprinkler system is inadequate, beyond expected life, and should be replaced.
Estimates:Raw Cost $4,083.75
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $4,083.75
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 69
Facility: \Administrative/Support\Central Office\ Welding Shop (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5010 System: Electrical Service/Distribution Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Electrical service and distribution is beyond expected life and should be replaced.
Estimates:Raw Cost $4,573.80
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $4,573.80
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5020 System: Branch Wiring Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Wiring is beyond expected life and should be replaced.
Estimates:Raw Cost $9,281.25
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $9,281.25
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 70
Facility: \Administrative/Support\Central Office\ Welding Shop (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5020 System: Lighting Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Lighting system is beyond expected life and should be replaced.
Estimates:Raw Cost $9,281.25
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $9,281.25
COMET4 Caddo Parish
1961 Midway COMET4 Survey Report
Deficiency Detail ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 1
Facility
Name Assembly System Material Distress Correction Qty Unit Raw Cost
Additional
Cost Total Cost Priority Def. Cat. Location / Note
Caddo Parish School District $6,306,519 $1,261,304 $7,567,823 Administrative/Support $6,306,519 $1,261,304 $7,567,823 Central Office $6,306,519 $1,261,304 $7,567,823 Administrative Building $3,793,833 $758,767 $4,552,599 Building Systems $3,793,833 $758,767 $4,552,599
B2020 Exterior Windows
System Beyond Expected Life
Renew System 1 Ea. $291,701 $58,340 $350,041 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior windows are beyond expected life and should be replaced.
B2030 Exterior Doors System Beyond Expected Life
Renew System 1 Ea. $68,414 $13,683 $82,097 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior doors are beyond expected life and should be replaced.
B3010 Roof Coverings -BUR
System Beyond Expected Life
Renew System 1 Ea. $614,226 $122,845 $737,071 Necessary- 2-5 Yrs
Deferred Maintenance
Roof covering is in poor condition and has been coated to extend its life, but should be replaced. Roof replacement to include appropriate insulation for energy conservation.
C3010 Wall Finishes - Ceramic & Glazed
System Beyond Expected Life
Renew System 1 Ea. $37,437 $7,487 $44,924 Necessary- 2-5 Yrs
Deferred Maintenance
The wall ceramic tiles are beyond expected life and should be replaced.
C3010 Wall Finishes - Paint
System Beyond Expected Life
Renew System 1 Ea. $71,046 $14,209 $85,256 Necessary- 2-5 Yrs
Deferred Maintenance
The painted wall finishes are beyond expected life and should be replaced.
C3020 Floor Finishes - Carpet
System Beyond Expected Life
Renew System 1 Ea. $18,042 $3,608 $21,650 Necessary- 2-5 Yrs
Deferred Maintenance
The carpet is stained, beyond expected life, and should be replaced.
C3020 Floor Finishes - VCT
System Beyond Expected Life
Renew System 1 Ea. $111,266 $22,253 $133,519 Necessary- 2-5 Yrs
Deferred Maintenance
The VCT flooring is beyond expected life and should be replaced.
C3030 Ceiling Finishes System Beyond Expected Life
Renew System 1 Ea. $233,812 $46,762 $280,574 Necessary- 2-5 Yrs
Deferred Maintenance
The ceiling finishes are stained, beyond expected life, and should be replaced.
D2010 Plumbing Fixtures
System Beyond Expected Life
Renew System 1 Ea. $142,091 $28,418 $170,510 Necessary- 2-5 Yrs
Deferred Maintenance
Plumbing fixtures are mostly original, beyond expected life, and should be replaced.
D2020 Domestic Water Distribution
System Beyond Expected Life
Renew System 1 Ea. $44,357 $8,871 $53,228 Necessary- 2-5 Yrs
Deferred Maintenance
Domestic water system is mostly original, beyond expected life, and should be replaced.
D2030 Sanitary Waste System Beyond Expected Life
Renew System 1 Ea. $110,515 $22,103 $132,619 Necessary- 2-5 Yrs
Deferred Maintenance
Sanitary waste system is original, beyond expected life, and should be replaced.
D2090 Other Plumbing Systems - Natural Gas
System Beyond Expected Life
Renew System 1 Ea. $30,072 $6,014 $36,087 Necessary- 2-5 Yrs
Deferred Maintenance
Natural gas system is original, beyond expected life, and should be replaced.
D3040 Distribution Systems & Exhaust Systems
System Beyond Expected Life
Renew System 1 Ea. $578,891 $115,778 $694,669 Necessary- 2-5 Yrs
Deferred Maintenance
Distribution is an inefficient dual duct system that is past expected life and should be replaced.
D3050 Terminal & Package Units
System Beyond Expected Life
Renew System 1 Ea. $302,226 $60,445 $362,671 Necessary- 2-5 Yrs
Deferred Maintenance
Air cooled chiller and distribution system is beyond expected life and should be replaced.
D5020 Branch Wiring System Beyond Expected Life
Renew System 1 Ea. $343,575 $68,715 $412,290 Necessary- 2-5 Yrs
Deferred Maintenance
Most of the wiring dates from original construction, is beyond expected life, and should be replaced.
COMET4 Caddo Parish
1961 Midway COMET4 Survey Report
Deficiency Detail ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 2
Facility
Name Assembly System Material Distress Correction Qty Unit Raw Cost
Additional
Cost Total Cost Priority Def. Cat. Location / Note
D5030 Fire Alarm System Beyond Expected Life
Renew System 1 Ea. $153,368 $30,674 $184,042 Necessary- 2-5 Yrs
Deferred Maintenance
Fire alarm system are beyond expected life and should be replaced.
D5030 Security & CCTV System Inadequate Renew System 1 Ea. $76,684 $15,337 $92,021 Necessary- 2-5 Yrs
Deferred Maintenance
CCTV system is reported to be inoperable, is past expected life, and should be replaced.
D3030 Cooling Generating Systems
System Inadequate Renew System 1 Ea. $340,568 $68,114 $408,682 Necessary- 2-5 Yrs
Deferred Maintenance
Reciprocating chillers are obsolete, inefficient, and should be replaced.
C1030 Fittings System Beyond Expected Life
Renew System 1 Ea. $84,954 $16,991 $101,945 Necessary- 2-5 Yrs
Deferred Maintenance
Fittings, such as chalk and tack boards, lockers, toilet and bath accessories, toilet partitions, and shelving, are beyond expected life and should be replaced.
D3060 Controls & Instrumentation
System Inadequate Renew System 1 Ea. $140,588 $28,118 $168,705 Necessary- 2-5 Yrs
Deferred Maintenance
Pneumatic mixing boxes and control system is inefficient, past expected life, and should be replaced.
Carpenter Shop $147,563 $29,513 $177,075 Building Systems $147,563 $29,513 $177,075
B2020 Exterior Windows
System Beyond Expected Life
Renew System 1 Ea. $35,297 $7,059 $42,356 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior windows are beyond expected life and should be replaced.
B2030 Exterior Doors System Beyond Expected Life
Renew System 1 Ea. $7,715 $1,543 $9,258 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior doors are beyond expected life and should be replaced.
B3010 Roof Coverings -BUR
System Beyond Expected Life
Renew System 1 Ea. $39,362 $7,872 $47,235 Necessary- 2-5 Yrs
Deferred Maintenance
The roof covering is beyond expected life and should be replaced. Roof replacement to include appropriate insulation for energy conservation
D2090 Other Plumbing Systems - Natural Gas
System Beyond Expected Life
Renew System 1 Ea. $1,987 $397 $2,384 Necessary- 2-5 Yrs
Deferred Maintenance
Gas piping to unit heaters is beyond expected life and should be replaced.
D3090 Other HVAC Systems/Equip -Exhaust Hoods
System Beyond Expected Life
Renew System 1 Ea. $1,987 $397 $2,384 Necessary- 2-5 Yrs
Deferred Maintenance
Exhaust system is beyond expected life and should be replaced.
D5010 Electrical Service/Distribution
System Beyond Expected Life
Renew System 1 Ea. $14,230 $2,846 $17,076 Necessary- 2-5 Yrs
Deferred Maintenance
Distribution system is beyond expected life and should be replaced.
D5020 Branch Wiring System Beyond Expected Life
Renew System 1 Ea. $13,398 $2,680 $16,078 Necessary- 2-5 Yrs
Deferred Maintenance
Wiring is beyond expected life and should be replaced.
D5020 Lighting System Beyond Expected Life
Renew System 1 Ea. $15,154 $3,031 $18,184 Necessary- 2-5 Yrs
Deferred Maintenance
Lighting system is beyond expected life and should be replaced.
D4010 Sprinklers System Beyond Expected Life
Renew System 1 Ea. $14,830 $2,966 $17,796 Necessary- 2-5 Yrs
Deferred Maintenance
Sprinkler system is beyond expected life and should be replaced.
D3050 Terminal & Package Units
System Beyond Expected Life
Renew System 1 Ea. $3,604 $721 $4,324 Necessary- 2-5 Yrs
Deferred Maintenance
Unit heaters are beyond expected life and should be replaced.
COMET4 Caddo Parish
1961 Midway COMET4 Survey Report
Deficiency Detail ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 3
Facility
Name Assembly System Material Distress Correction Qty Unit Raw Cost
Additional
Cost Total Cost Priority Def. Cat. Location / Note
ROTC Maintenance Repair Buildilng $498,386 $99,677 $598,063 Building Systems $498,386 $99,677 $598,063
B2020 Exterior Windows
System Beyond Expected Life
Renew System 1 Ea. $117,656 $23,531 $141,187 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior windows are beyond expected life and should be replaced.
B2030 Exterior Doors System Beyond Expected Life
Renew System 1 Ea. $25,718 $5,144 $30,862 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior doors are beyond expected life and should be replaced.
C3010 Wall Finishes - Paint
System Beyond Expected Life
Renew System 1 Ea. $16,940 $3,388 $20,328 Necessary- 2-5 Yrs
Deferred Maintenance
The painted wall finishes are beyond expected life and should be replaced.
C3030 Ceiling Finishes System Beyond Expected Life
Renew System 1 Ea. $49,896 $9,979 $59,875 Necessary- 2-5 Yrs
Deferred Maintenance
The ceiling finishes are stained, beyond expected life, and should be replaced.
D2010 Plumbing Fixtures
System Beyond Expected Life
Renew System 1 Ea. $3,080 $616 $3,696 Necessary- 2-5 Yrs
Deferred Maintenance
Wash sink is beyond expected life and should be replaced. The building does not have restroom facilities.
D2020 Domestic Water Distribution
System Beyond Expected Life
Renew System 1 Ea. $9,086 $1,817 $10,903 Necessary- 2-5 Yrs
Deferred Maintenance
Domestic water system is beyond expected life and should be replaced.
D2030 Sanitary Waste System Beyond Expected Life
Renew System 1 Ea. $23,562 $4,712 $28,274 Necessary- 2-5 Yrs
Deferred Maintenance
Sanitary waste system is beyond expected life and should be replaced.
D2090 Other Plumbing Systems - Natural Gas
System Beyond Expected Life
Renew System 1 Ea. $6,622 $1,324 $7,946 Necessary- 2-5 Yrs
Deferred Maintenance
Natural gas system is beyond expected life and should be replaced.
D3050 Terminal & Package Units
System Beyond Expected Life
Renew System 1 Ea. $49,280 $9,856 $59,136 Necessary- 2-5 Yrs
Deferred Maintenance
HVAC system is inadequate, beyond expected life, and should be replaced.
D3060 Controls & Instrumentation
System Beyond Expected Life
Renew System 1 Ea. $3,696 $739 $4,435 Necessary- 2-5 Yrs
Deferred Maintenance
Controls are obsolete, beyond expecte life, and should be replaced.
D5010 Electrical Service/Distribution
System Beyond Expected Life
Renew System 1 Ea. $47,432 $9,486 $56,918 Necessary- 2-5 Yrs
Deferred Maintenance
Electrical service is beyond expected life and should be replaced.
D5020 Branch Wiring System Beyond Expected Life
Renew System 1 Ea. $47,586 $9,517 $57,103 Necessary- 2-5 Yrs
Deferred Maintenance
Wiring is mostly original, beyond expected life, and should be replaced.
D5020 Lighting System Beyond Expected Life
Renew System 1 Ea. $50,358 $10,072 $60,430 Necessary- 2-5 Yrs
Deferred Maintenance
Lighting system is beyond expected life and should be replaced.
D5030 Communications and Security - Security & CCTV
System Beyond Expected Life
Renew System 1 Ea. $12,474 $2,495 $14,969 Necessary- 2-5 Yrs
Deferred Maintenance
Building security is inadequate, past expected life, and should be replaced. For integrity of system, install wiring in conduit.
B2010 Exterior Walls Exterior Walls Failing Professional Structural Engineer
1 Ea. $20,000 $4,000 $24,000 Potentially Critical-12 months
Critical Repair
The exterior have show observable cracks that should be studied by a professional structural engineer.
A1030 Slab on Grade Foundations Failing Professional Service - Investigate Foundation
1 Ea. $15,000 $3,000 $18,000 Potentially Critical-12 months
Critical Repair
The foundation slab has observable cracks that should be studied by a professional structural engineer.
COMET4 Caddo Parish
1961 Midway COMET4 Survey Report
Deficiency Detail ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 4
Facility
Name Assembly System Material Distress Correction Qty Unit Raw Cost
Additional
Cost Total Cost Priority Def. Cat. Location / Note
Site $1,156,344 $231,269 $1,387,613 Building Systems $1,156,344 $231,269 $1,387,613
G2010 Roadways System Beyond Expected Life
Renew System 1 Ea. $164,375 $32,875 $197,250 Necessary- 2-5 Yrs
Deferred Maintenance
The roadways are beyond expected life and should be replaced.
G2020 Parking Lots System Beyond Expected Life
Renew System 1 Ea. $140,076 $28,015 $168,092 Necessary- 2-5 Yrs
Deferred Maintenance
The parking lots are beyond expected life and should be resurfaced and restriped.
G2030 Pedestrian Paving
System Beyond Expected Life
Renew System 1 Ea. $97,196 $19,439 $116,635 Necessary- 2-5 Yrs
Deferred Maintenance
The pedestrian paving is cracked and should be replaced.
G3010 Water Supply System Beyond Expected Life
Renew System 1 Ea. $97,196 $19,439 $116,635 Necessary- 2-5 Yrs
Deferred Maintenance
Water supply system is beyond expected life and should be replaced.
G3020 Sanitary Sewer System Beyond Expected Life
Renew System 1 Ea. $48,598 $9,720 $58,317 Necessary- 2-5 Yrs
Deferred Maintenance
Sanitary sewer system is original, beyond expected life, and should be replaced.
G3030 Storm Sewer System Beyond Expected Life
Renew System 1 Ea. $418,800 $83,760 $502,559 Necessary- 2-5 Yrs
Deferred Maintenance
Storm sewer system is beyond expected life and should be replaced.
G4020 Site Lighting System Beyond Expected Life
Renew System 1 Ea. $190,104 $38,021 $228,124 Necessary- 2-5 Yrs
Deferred Maintenance
Site lighting is past expected life and should be replaced.
Teacher Resource Building $581,291 $116,258 $697,549 Building Systems $581,291 $116,258 $697,549
C3010 Wall Finishes - Paint
System Beyond Expected Life
Renew System 1 Ea. $23,939 $4,788 $28,726 Necessary- 2-5 Yrs
Deferred Maintenance
The painted wall finishes are beyond expected life and should be replaced.
D3050 Terminal & Package Units
System Beyond Expected Life
Renew System 1 Ea. $367,132 $73,426 $440,558 Necessary- 2-5 Yrs
Deferred Maintenance
Roof mounted air handler is beyond expected life and should be replaced.
D5030 Communications and Security - Security & CCTV
System Beyond Expected Life
Renew System 1 Ea. $17,628 $3,526 $21,153 Necessary- 2-5 Yrs
Deferred Maintenance
Security system is inoperable, past expected life, and should be replaced. For integrity of system, install wiring in conduit.
C3030 Ceiling Finishes System Beyond Expected Life
Renew System 1 Ea. $70,510 $14,102 $84,612 Necessary- 2-5 Yrs
Deferred Maintenance
The ceiling finishes are stained, beyond expected life, and should be replaced.
B2020 Exterior Windows
Exterior Windows
Beyond Expected Life
Replace Double Hung Steel Window
50 Ea. $82,083 $16,417 $98,499 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior windows on the north side of the building are beyond expected life and should be replaced.
B2010 Exterior Walls Exterior Walls Failing Professional Structural Engineer
1 Ea. $20,000 $4,000 $24,000 Potentially Critical-12 months
Critical Repair
The exterior walls show observable cracks that should be studied by a professional structural engineer.
COMET4 Caddo Parish
1961 Midway COMET4 Survey Report
Deficiency Detail ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 5
Facility
Name Assembly System Material Distress Correction Qty Unit Raw Cost
Additional
Cost Total Cost Priority Def. Cat. Location / Note
Transportation Building $68,530 $13,706 $82,236 Building Systems $68,530 $13,706 $82,236
C3010 Wall Finishes - Paint
System Beyond Expected Life
Renew System 1 Ea. $6,050 $1,210 $7,260 Necessary- 2-5 Yrs
Deferred Maintenance
The painted wall finishes are beyond expected life and should be replaced.
D3050 Terminal & Package Units
System Beyond Expected Life
Renew System 1 Ea. $53,570 $10,714 $64,284 Necessary- 2-5 Yrs
Deferred Maintenance
The office has window units. The garage is heated, but not air conditioned. System is beyond expected life and should be replaced.
D5030 Communications and Security - Security & CCTV
System Beyond Expected Life
Renew System 1 Ea. $8,910 $1,782 $10,692 Necessary- 2-5 Yrs
Deferred Maintenance
Security system is inadequate, past expected life, and should be replaced. For integrity of system, install wiring in conduit.
Welding Shop $60,573 $12,115 $72,688 Building Systems $60,573 $12,115 $72,688
B2020 Exterior Windows
System Beyond Expected Life
Renew System 1 Ea. $11,345 $2,269 $13,614 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior windows are beyond expected life and should be replaced.
B2030 Exterior Doors System Beyond Expected Life
Renew System 1 Ea. $2,480 $496 $2,976 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior doors are beyond expected life and should be replaced.
B3010 Roof Coverings -BUR
System Beyond Expected Life
Renew System 1 Ea. $12,652 $2,530 $15,183 Necessary- 2-5 Yrs
Deferred Maintenance
The roof covering is beyond expected life and should be replaced. Roof replacement to include appropriate insulation for energy conservation
C3020 Floor Finishes -Paint
System Beyond Expected Life
Renew System 1 Ea. $891 $178 $1,069 Necessary- 2-5 Yrs
Deferred Maintenance
The painted floor finishes are beyond expected life and should be replaced.
D2090 Other Plumbing Systems - Natural Gas
System Beyond Expected Life
Renew System 1 Ea. $639 $128 $766 Necessary- 2-5 Yrs
Deferred Maintenance
Natural gas system is beyond expected life and should be replaced.
D3050 Terminal & Package Units
System Beyond Expected Life
Renew System 1 Ea. $3,713 $743 $4,455 Necessary- 2-5 Yrs
Deferred Maintenance
Unit heaters are beyond expected life and should be replaced.
D4010 Sprinklers System Beyond Expected Life
Renew System 1 Ea. $4,084 $817 $4,901 Necessary- 2-5 Yrs
Deferred Maintenance
Sprinkler system is inadequate, beyond expected life, and should be replaced.
D5010 Electrical Service/Distribution
System Beyond Expected Life
Renew System 1 Ea. $4,574 $915 $5,489 Necessary- 2-5 Yrs
Deferred Maintenance
Electrical service and distribution is beyond expected life and should be replaced.
D5020 Branch Wiring System Beyond Expected Life
Renew System 1 Ea. $9,281 $1,856 $11,138 Necessary- 2-5 Yrs
Deferred Maintenance
Wiring is beyond expected life and should be replaced.
D5020 Lighting System Beyond Expected Life
Renew System 1 Ea. $9,281 $1,856 $11,138 Necessary- 2-5 Yrs
Deferred Maintenance
Lighting system is beyond expected life and should be replaced.
C3010 Wall Finishes - Paint
System Beyond Expected Life
Renew System 1 Ea. $1,634 $327 $1,960 Necessary- 2-5 Yrs
Deferred Maintenance
The painted wall finishes are beyond expected life and should be replaced.
Future Facility and Site Assessment Report
FUTURE FACILITY AND SITE ASSESSMENT
School CENTRAL OFFICE 1961 Midway Lane Shreveport, LA 71108
Site Description 15.8 acre (approx.) site in central Shreveport south of the I-20 and Hearne intersection. The property faces Midway Avenue on the north, the eastern edge is Joplin Avenue, single-family residential borders the southern boundary, and the western edge is formed by a lumber yard and a small finger of land extends to the railroad right-of-way. The complex houses the main Administration Building and support facilities, primarily on the west side and the buildings along Midway, and also the major bus and vehicle maintenance facilities on the east side. The site is basically flat with a slight slope to the southwest (there is a 20 ft. storm drainage easement and collection ditch in the southwest corner). The main buildings sit along the Midway frontage which is also slightly higher ground. The facilities consist of the 2-story Administration Building (1972) and the adjacent 1-story Instructional Center, several warehouses and shops beginning in 1954 and added incrementally, the Teacher Resource Center added in 1991; other shops include Paint, Wash Rack, Garage, Carpenter, and the ROTC addition, and bus storage shed. There are six wooden modular buildings lined up north to south separating the west and east zones. Most buildings have flat roofs, some of the shops have low-slope metal roofs. The architectural styles are eclectic and simple, the only stand-out is the Administration building which is typical of its era. The exterior envelopes consist primarily of brick masonry for the offices and warehouse, the other shops and sheds are pre-engineered metal buildings. Site features include a bus fueling station near the Joplin driveway (with underground fuel tanks). The site is almost entirely paved: large concrete parking lots for the Administration functions; concrete, asphalt and gravel parking lots and drives for the shops zone; and gravel parking for the bus lot on the southeast. There are a few mature trees in the small yard around the main building and along the lumber yard border, also at the south edge by the Construction and Capital Projects building.
SUMMARY Topic Grade Comments
Site Adequacy Adequate
The site is basically full yet adequate for the current activities. Additional functions or population could strain the layout and cause redevelopment and increased density. SITE ASSESSMENT
Expansion Opportunities
Potential Constraint
The only uncovered parcels are the yards around the Administration Building and the Construction Services Building at the south end. The graphic shows possible building sites adjacent to these buildings and note a portion of the large parking lot that could be recaptured if a large facility is needed. The existing parking inventory appears adequate but reducing it by adding new facilities and population would impact capacity for large onsite events.
Usable Area Remaining
Potential Constraint
0.28 Acres – Administration; 0.61 Acres - Maintenance. Approximates the probable footprint locations. For the Administration zone, anticipates modest office additions to the existing structures. For the Maintenance zone, the two areas shown could be redeveloped with permanent, larger buildings that would make more efficient use of the ground and could be multi-story for greater density. No additional surfaces are available for paving or layout expansion.
• Flood Plain No Constraint
• Potable Water No Constraint Low pressure reported.
• Sanitary Sewer No Constraint
• Storm Drainage
No Constraint
There are localized ponding occurrences but no constraints from the city system to accept runoff. There is an open ditch in the southwest corner of the site within a 20 ft. easement. Due to the almost total impervious covering, there would be little if any additional runoff should buildings be added.
• Electricity No Constraint
• Natural Gas No Constraint
• Ground Water No Constraint See comments in HazMat/Soils
• Air Pollution No Constraint
• HazMat/Soils
No Constraint
No conflicts identified by DEQ. However, as a matter of due diligence because of the underground fuel tanks and vehicle servicing, continuing ground water monitoring and soil sampling is recommended to verify no contamination from the ongoing maintenance activities.
• Habitats No Constraint No conflicts identified by DEQ.
Ease of Access No Constraint
Design Compatibility
No Constraint
The administrative and maintenance facilities fits into the commercial neighborhood and has grown over the years; expansion would not be intrusive to the residential along the south due to precedence.
Compatibility of Structures
No Constraint
The simple, eclectic collection of contemporary styled buildings does not impose a style issue, although the Administration Building would need careful attention if expanded. Opportunities for upgrading to contemporary styles, energy conservation techniques, and general enhancement would be feasible. The original building envelopes may need thermal improvement.
CE
NT
RA
L O
FF
ICE
1961 M
idw
ay A
ve
Sh
revep
ort, L
A 7
1108
QUILEN ROAD
N
Pu
blis
he
d 0
5.0
5.1
0
N
MIDWAY AVE
JO
PL
IN A
VE
DE
VA
UG
HN
ST
RE
ET
CAROLINE STREET
20’ Drainage
Easement
New
Bldgs.
New Bldg.New Bus & Autos
Parking
ADMIN. ZONE
Primary 1A: 0.16 Ac
Secondary 1A: 0.22 Ac
Secondary 2A: 0.11 Ac
Total: 0.49 Ac
MAINT. ZONE
Primary 1M: 0. 29 Ac
Primary 2M: 0. 32 Ac
Total: 0.61 Ac
RE
SID
EN
TIA
L
LUMBER
YARD
RA
ILR
OA
D
RESIDENTIAL
NURSING
HOMECOMMERCIAL
+FH
+FH
Parking
Fuel
Station
Maint.
Maint. Shops
Bus Parking
Teachers Resource
Shops
Park
ing
Parking
Instruct.
Center
Admin.
HQ
Modular
Shed
T
E
E
E
E
E
Parking
Slight
Slope
Main
Entry
Long – Range
Expansion Zone
Second.
1APrim.1A
Second.
2A 3’+ Elev. Diff.Stor.Stor.
Prim.1M
Maint.
Bus
Wash
Prim.2M
T
Utility Data Incomplete
MAINTENANCEADMINISTRATION
Building Code Verification Report
Building Code Number COMPLYNOT
COMPLY
FCA
DEFICIENCY
NOT
KNOWN
SYSTEM
NOT
PRESENT
NA TO FCA
DATA
1Code of Federal Regulations 28 CFR Part
36, 1994 edition, Paragraph 4.1.2,
Paragraph 4.1.6
1 NPFA 101:15.2.3.2; IBC 1017.2
3 IBC 1005.2
5
a
b
c
d
6
a
b
1
2
4 IBC 1011.5.3
1 IBC 1007.3
2 IBC 1020.1
3
Hazardous storage?
Janitor’s closet?
Science labs?
IBC 1008.1.8.1
7
8
Boiler and furnace rooms?
Are corridor doors rated a minimum 20-minute rating?
Is glazing in rated doors above 20 minutes limited to 100 square inches?
NFPA 101:15.3.7
NFPA 101:15.3.2.1; IBC 508.2
Does every room or space greater than 250 SF and used for educational
purposes have not less than one outside window for emergency rescue
(exceptions: sprinklered building or room that has a door directly to the
outside)?
Do doors opening in the path of egress travel not reduce the required width to
less than 1/2 during the course of the swing?
When fully open, do corridor doors not project more than 7 inches into the
required corridor width?
Is the building subdivided into compartments by smoke partitions having not
less than a 1-hour fire rating? (Maximum area of compartment is 30,000 SF.
Length or width of building exceeds 300’ unless sprinklered.)
IBC 715.4.4.1
Is 1-hour rating or sprinkler protection provided for the following:
3
School Name: Central Office
IBC 1005.2
NFPA101:15.2.11.1.1
IBC 1017.1
G2030 Pedestrian Paving
B2020 Exterior Windows
4
BUILDING CODE COMPLIANCE REPORT
Code Provision
Is there a continuous path of entry/exit for handicap accessibility to all parts of
the building?
Do exit access corridors have not less than 6’ of clear width?
Are both 1-hour rating and sprinkler protection provided for the following:
2
Does all door hardware comply by not requiring tight grasping, tight pinching or
twisting to operate?
Maintenance shops?
C10 Interior Construction
C1010 Partitions
C1020 Interior Doors
1
Are corridors 1-hour rated (exceptions: building is sprinklered or each room for
instruction has at least one door directly to the exterior)?
Where there is a chiller, is it separated from a boiler or water heater by a 2-
hour assembly?IBC 508.2
Laundries? NFPA 101:15.3.2.1; IBC 508.2
NFPA 101:7.1.3.2.1; IBC 1020.1.2
C2010 Stair Construction
Are all means of egress illuminated at all times building is occupied?
Do exit stairways have a minimum 48” clearance width between handrails?
Are stairs separated by 1-hour fire resistance rating?
Are penetrations into stairs limited to doors, electrical conduit serving the
stairway, piping necessary for the heating or cooling of the exit enclosure,
sprinkler piping, standpipes and penetrations for fire alarm circuits?
Building Code Number COMPLYNOT
COMPLY
FCA
DEFICIENCY
NOT
KNOWN
SYSTEM
NOT
PRESENT
NA TO FCA
DATACode Provision
4
a NFPA 101:7.2.2.2.4.2; IBC 1012.4
b IBC 1012.5
c NFPA 101:7.2.2.4.4.6; IBC 1012.1
d NFPA 101:7.2.2.4.4.2; IBC 1012.2
5 IBC 1007.6
1
2
1 IBC 508.2
2 IBC 1203.1
3INTERNATIONAL MECHANICAL CODE
2000, 606.4
4 IBC 908.6
1 IBC 903.2
1 IBC 907.2
4
Is there a telephone or intercom communication in the cab?
Is there a fireman control panel at the ground floor controls?
Are handrails:
IBC 3006.2
IBC 3003.2
Continuously graspable?
Between 34” and 38” above the surface of the tread?
Between 1-1/4” and 2” in diameter?
Returning to wall, guard or walking surface?
3 IBC 907.11
IBC 907.2.12.2
Does the shaft have exhaust directly to the outside, an access ladder to the pit,
and battery backup lighting in the shaft/pit?
Are the mechanical rooms separated by fire rated partitions from remainder of
building?
Is there a standard and emergency ventilation system provided?
Are there automatic sprinkler systems provided in assembly spaces with more
than 300 occupants?
2
Is there a refrigerant detection and alarm system provided?
Are there emergency shut-offs provided?
Are the duct smoke detectors connected to the building’s fire alarm control
panel?
Is there a monitored fire alarm system provided?
Does the operation of fire detector, sprinkler device or manual fire alarm box
immediately sounds an alert tone followed by voice instructions giving
approved information and directions for an evacuation?
IBC 3004.1; IBC 3006.1
D30 HVAC Systems
D40 Fire Protection
D4010 Sprinklers
D50 Electrical
D5030 Communications and Security
D10 Conveying
D1010 Elevators
3Does the Elevator Machine Room have ventilation or air conditioning to protect
controls from overheating?
Is there an Area of Refuge in the stairwell or in a vestibule entering the stair? Is
there a communication device there?
Energy Conservation Opportunities Report
System Energy Conservation FCA Deficiency Replacement Cost
SCHOOL TYPEENERGY CONSERVATION OPPORTUNITIES
Central Office Admin
Admin Building Roof Covering Yes Yes $737,071.00
Exterior Windows Yes Yes $350,041.00
Interior Lighting No No
Bldg Controls & Instrumentation Yes Yes $168,705.00
Heating No No
Other HVAC Systems (Ventilation) Yes Yes $694,669.00
Terminal & Package Units Yes Yes $362,671.00
Cooling Yes Yes $408,682.00
Carpenter Shop Roof Covering Yes Yes $42,961.00
Exterior Windows Yes Yes $38,524.00
Interior Lighting Yes Yes $16,539.00
Bldg Controls & Instrumentation No No
Heating No No
Other HVAC Systems (Ventilation) Yes Yes $2,168.00
Terminal & Package Units Yes Yes $3,933.00
Cooling No No
Construction Capital Projects Building Roof Covering No No
Exterior Windows No No
Interior Lighting No No
Bldg Controls & Instrumentation No No
Heating No No
Other HVAC Systems (Ventilation) No No
Terminal & Package Units No No
Cooling No No
ROTC Maintenance Repair Building Roof Covering No No
Exterior Windows Yes Yes $141,187.00
Interior Lighting Yes Yes $60,430.00
Bldg Controls & Instrumentation Yes Yes $4,435.00
Heating No No
Other HVAC Systems (Ventilation) No No
Terminal & Package Units Yes Yes $59,136.00
Cooling No No
Teacher Resource Building Roof Covering No No
Exterior Windows Yes Yes $98,499.00
Interior Lighting No No
Bldg Controls & Instrumentation No No
Heating No No
Other HVAC Systems (Ventilation) No No
Terminal & Package Units Yes Yes $440,558.00
Cooling No No
Transportation Building Roof Covering No No
Exterior Windows No No
Interior Lighting No No
Bldg Controls & Instrumentation No No
Heating No No
Other HVAC Systems (Ventilation) No No
Terminal & Package Units Yes Yes $64,284.00
Cooling No No
Vehicle & Bus Wash Building Roof Covering No No
Exterior Windows No No
Interior Lighting No No
Bldg Controls & Instrumentation No No
Heating No No
Other HVAC Systems (Ventilation) No No
Terminal & Package Units No No
Cooling No No
Welding Shop Roof Covering Yes Yes $10,099.00
Exterior Windows Yes Yes $9,056.00
Interior Lighting Yes Yes $7,409.00
Bldg Controls & Instrumentation No No
Heating No No
Other HVAC Systems (Ventilation) No No
Terminal & Package Units Yes Yes $4,455.00
Cooling No No
Site Exterior Lighting Yes Yes $228,124.00
Facility Condition Assessment Reports
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 1
Facility: \Administrative/Support\Central WarehouseAddress: 7300 W. Bert Kouns Industrial Loop, Shreveport, LA 71129
Attributes: ***None***
General Information: Function: Administration/Support Year Built:Gross Area: 62,464 S.F. Last Renovation:
Facility Description:
The Central Warehouse campus was acquired by the CPSB in 1981 and consists of two buildings located at 7300 West Bert Kouns Industrial Loop in Shreveport, Louisiana. There have been no additions to the main buildings. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report for each building or other facility on the campus.
Current Repair Cost: $682,408.00 Replacement Cost: $5,554,915.00 FCI: 12.28%
20-Apr-2010Central Warehouse
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 2
Facility: \Administrative/Support\Central Warehouse\Office Warehouse BuildingAddress: 7300 W. Bert Kouns Industrial Loop, Shreveport, LA 71129
Attributes: Number of Floors 1
General Information: Function: Administration/Support Year Built: 1981Gross Area: 55,168 S.F. Last Renovation:
Facility Description:
The Central Warehouse Building is a 1-story building located at 7300 West Bert Kouns Industrial Loop in Shreveport, Louisiana. The building was acquired and renovated in 1981 and has had no additions or major renovations since that time. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report for each building.
Energy conservation opportunities for this building include: 1) Replacement of the dual duct system with a VAV design and a building automation system would allow programs to improve operation and reduce energy use; 2) A retrofit to higher efficiency (T8) lamps and corresponding electronic ballasts would, with proper maintenance, improve lighting effectiveness and reduce electrical energy consumption; and 3) A review of billing rate may justify addition of power factor correction capacitors.
ADA vertical access is not needed for this building.
Current Repair Cost: $580,236.00 Replacement Cost: $3,944,088.00 FCI: 14.71%
20-Apr-2010East Elevation
20-Apr-2010North Elevation
20-Apr-2010West Elevation
20-Apr-2010South Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 3
Facility: \Administrative/Support\Central Warehouse\Office Warehouse Building (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $71.49 S.F. 55,168 105 $4,132,169 68 1983 1989 33 $580,237 $3,944,087 15
Substructure $14.41 S.F. 55,168 100 $795,081 100 1981 $795,081
Foundations $14.41 S.F. 55,168 100 $795,081 100 1981 $795,081
Standard Foundations $8.88 S.F. 55,168 100 $489,892 100 1981 $489,892
Slab on Grade $5.53 S.F. 55,168 100 $305,189 100 1981 $305,189
Shell $31.31 S.F. 55,168 104 $1,791,547 88 1981 2011 54 $1,727,200
Superstructure $12.30 S.F. 55,168 100 $678,566 100 1981 $678,566
Roof Construction $12.30 S.F. 55,168 100 $678,566 100 1981 $678,566
Exterior Enclosure $8.78 S.F. 55,168 102 $492,540 88 1981 2011 3 $484,596
Exterior Walls $7.34 S.F. 55,168 100 $405,154 100 1981 $405,154
Exterior Windows $0.42 S.F. 55,168 110 $25,488 30 1981 2011 3 $23,171
Exterior Doors $1.02 S.F. 55,168 110 $61,898 30 1981 2011 3 $56,271
Roofing $10.22 S.F. 55,168 110 $620,441 75 1981 2056 61 $564,038
Roof Coverings - BUR 0 0 0 0
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Metal
$10.22 S.F. 55,168 110 $620,441 75 1981 2056 61 $564,038
Roof Openings 0 0 0 0
Interiors $6.58 S.F. 55,168 105 $381,120 36 1981 1989 28 $251,263 $363,242 69
Interior Construction $5.21 S.F. 55,168 105 $300,356 39 1981 2001 28 $198,075 $287,314 69
Partitions $1.00 S.F. 55,168 110 $60,442 100 1981 $54,947
Interior Doors $0.95 S.F. 55,168 80 $41,839 40 1981 2021 28 $52,299
Fittings $3.26 S.F. 55,168 110 $198,075 20 1981 2001 $198,075 $180,068 110
Interior Finishes $1.38 S.F. 55,168 106 $80,764 25 1981 1989 28 $53,188 $75,928 70
Wall Finishes - Paint $1.32 S.F. 2,760 110 $4,008 10 1981 1991 $4,008 $3,643 110
Wall Finishes - Wood Paneling $9.19 S.F. 3,000 100 $27,576 40 1981 2021 28 $27,576
Floor Finishes - Carpet $3.34 S.F. 2,760 110 $10,128 8 1981 1989 $10,128 $9,207 110
Floor Finishes - Ceramic &
Quarry Tile
0 0 0 0
Floor Finishes - VCT $4.68 S.F. 3,000 110 $15,444 20 1981 2001 $15,444 $14,040 110
Ceiling Finishes $3.89 S.F. 5,520 110 $23,608 20 1981 2001 $23,608 $21,462 110
Services $19.19 S.F. 55,168 110 $1,164,421 25 1985 1991 16 $328,974 $1,058,564 31
Plumbing $2.45 S.F. 55,168 110 $148,557 28 1981 2001 3 $31,313 $135,052 23
Plumbing Fixtures $0.80 S.F. 55,168 110 $48,791 30 1981 2011 3 $44,355
Domestic Water Distribution $0.71 S.F. 55,168 110 $42,965 30 1981 2011 3 $39,059
Sanitary Waste $0.42 S.F. 55,168 110 $25,488 30 1981 2011 3 $23,171
Rain Water Drainage 0 0 0 0
Other Plumbing Systems -
Natural Gas
$0.52 S.F. 55,168 110 $31,313 20 1981 2001 $31,313 $28,467 110
HVAC $2.84 S.F. 55,168 110 $172,588 16 1997 2011 65 $2,004 $156,898 1
Distribution Systems & Exhaust
Systems
$0.11 S.F. 55,168 110 $6,554 30 1981 2011 3 $5,958
Terminal & Package Units $2.65 S.F. 55,168 110 $160,936 15 2005 2020 67 $2,004 $146,306 1
Controls & Instrumentation $0.08 S.F. 55,168 110 $5,098 20 2005 2025 75 $4,634
Other HVAC Systems/Equip -
Exhaust Hoods
0 0 0 0
Fire Protection $3.30 S.F. 55,168 110 $200,260 30 1981 2011 3 $182,054
Sprinklers $3.30 S.F. 55,168 110 $200,260 30 1981 2011 3 $182,054
Electrical $10.60 S.F. 55,168 110 $643,016 24 1981 1991 3 $295,657 $584,560 51
Electrical Service/Distribution $2.28 S.F. 55,168 110 $138,361 30 1981 2011 3 $125,783
Branch Wiring $3.44 S.F. 55,168 110 $208,998 30 1981 2011 3 $189,999
Lighting $3.90 S.F. 55,168 110 $236,671 20 1981 2001 $236,671 $215,155 110
Communications and Security -
Fire Alarm
0 0 0 0
Communications and Security -
Security & CCTV
$0.97 S.F. 55,168 110 $58,986 10 1981 1991 $58,986 $53,623 110
Equipment & Furnishings 0 0 0
Furnishings 0 0 0
Fixed Furnishings 0 0 0 0
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 4
Facility: \Administrative/Support\Central Warehouse\Office Warehouse Building (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $580,237 $781,566 $12,830 $300,943
Substructure
Foundations
Standard Foundations
Slab on Grade
Shell $90,007
Superstructure
Roof Construction
Exterior Enclosure $90,007
Exterior Walls
Exterior Windows $26,252
Exterior Doors $63,755
Roofing
Roof Coverings - BUR
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Metal
Roof Openings
Interiors $251,263 $12,830 $5,386
Interior Construction $198,075
Partitions
Interior Doors
Fittings $198,075
Interior Finishes $53,188 $12,830 $5,386
Wall Finishes - Paint $4,008 $5,386
Wall Finishes - Wood Paneling
Floor Finishes - Carpet $10,128 $12,830
Floor Finishes - Ceramic & Quarry
Tile
Floor Finishes - VCT $15,444
Ceiling Finishes $23,608
Services $328,974 $691,559 $295,557
Plumbing $31,313 $120,760
Plumbing Fixtures $50,254
Domestic Water Distribution $44,254
Sanitary Waste $26,252
Rain Water Drainage
Other Plumbing Systems - Natural
Gas
$31,313
HVAC $2,004 $6,751 $216,285
Distribution Systems & Exhaust
Systems
$6,751
Terminal & Package Units $2,004 $216,285
Controls & Instrumentation
Other HVAC Systems/Equip -
Exhaust Hoods
Fire Protection $206,268
Sprinklers $206,268
Electrical $295,657 $357,780 $79,272
Electrical Service/Distribution $142,512
Branch Wiring $215,268
Lighting $236,671
Communications and Security - Fire
Alarm
Communications and Security -
Security & CCTV
$58,986 $79,272
Equipment & Furnishings
Furnishings
Fixed Furnishings
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 5
Facility: \Administrative/Support\Central Warehouse\Office Warehouse Building (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C1030 System: Fittings Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Fittings, such as lockers, toilet and bath accessories, toilet partitions, and shelving, are beyond expected life and
should be replaced.
Estimates:Raw Cost $165,062.66
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $165,062.66
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Paint Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The painted wall finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $3,339.60
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $3,339.60
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 6
Facility: \Administrative/Support\Central Warehouse\ Office Warehouse Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3020 System: Floor Finishes - Carpet Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The carpet is worn, beyond expected life, and should be replaced.
Estimates:Raw Cost $8,440.08
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $8,440.08
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: C3020 System: Floor Finishes - VCT Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The vinyl tiles are beyond expected life and should be replaced.
Estimates:Raw Cost $12,870.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $12,870.00
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 7
Facility: \Administrative/Support\Central Warehouse\ Office Warehouse Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3030 System: Ceiling Finishes Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The ceiling finishes are stained, beyond expected life, and should be replaced.
Estimates:Raw Cost $19,673.28
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $19,673.28
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2090 System: Other Plumbing Systems - Natural Gas Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Natural gas distribution system is beyond expected life and should be replaced.
Estimates:Raw Cost $26,094.46
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $26,094.46
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 8
Facility: \Administrative/Support\Central Warehouse\ Office Warehouse Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: D3050 System: Terminal & Package Units Material: Terminal and Package Units Distress: Inadequate Category: Capital Renewal Correction: Install CRCU Note: Computer server cabinet lacks sufficient individual cooling. Install computer cabinet cooling.
Estimates:Raw Cost $1,670.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $1,670.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5020 System: Lighting Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Lighting system is beyond expected life and should be replaced.
Estimates:Raw Cost $197,225.60
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $197,225.60
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 9
Facility: \Administrative/Support\Central Warehouse\ Office Warehouse Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5030 System: Communications and Security - Security &
CCTV Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Security system is inadequate, past expected life, and should be replaced. For integrity of system, install wiring
in conduit.
Estimates:Raw Cost $49,154.69
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $49,154.69
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 10
Facility: \Administrative/Support\Central Warehouse\SiteAddress: 7300 W. Bert Kouns Industrial Loop, Shreveport, LA 71129
Attributes: Site Area (in Acres) 12.1
General Information: Function: Administration/Support Year Built: 1981Gross Area: 62,464 S.F. Last Renovation:
Facility Description:
The site was acquired by CPSB in 1981 and there have been no additions to the site and no major renovations since that time. Campus site features include paved driveways and parking lots, pedestrian pavement, flag pole, landscaping, and fencing. Site mechanical and electrical features include water, sewer, natural gas, and site lighting. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report for the site features.
Current Repair Cost: $0.00 Replacement Cost: $933,962.00 FCI: 0.00%
20-Apr-2010Aerial Image of Central Warehouse
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 11
Facility: \Administrative/Support\Central Warehouse\Site (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $14.95 S.F. 62,464 100 $933,963 33 1981 2001 2020 33 0 $933,963
Building Sitework $14.95 S.F. 62,464 100 $933,963 33 1981 2001 2020 33 $933,963
Site Improvements $8.50 S.F. 62,464 100 $530,695 28 1981 2001 2020 40 $530,695
Roadways $1.38 S.F. 62,464 100 $86,200 50 1981 2031 42 $86,200
Parking Lots $1.18 S.F. 62,464 100 $73,458 30 1981 2011 3 $73,458
Pedestrian Paving $0.82 S.F. 62,464 100 $50,971 50 1981 2031 42 $50,971
Site Development $3.86 S.F. 62,464 100 $241,361 20 1981 2001 2020 50 $241,361
Landscaping $1.26 S.F. 62,464 100 $78,705 10 1981 $78,705
Site Mechanical Utilities $4.86 S.F. 62,464 100 $303,575 44 1981 2011 31 $303,575
Water Supply $0.82 S.F. 62,464 100 $50,971 30 1981 2011 3 $50,971
Sanitary Sewer $0.41 S.F. 62,464 100 $25,485 30 1981 2011 3 $25,485
Storm Sewer $3.52 S.F. 62,464 100 $219,623 50 1981 2031 42 $219,623
Fuel Distribution $0.12 S.F. 62,464 100 $7,496 30 1981 2011 3 $7,496
Site Electrical Utilities $1.60 S.F. 62,464 100 $99,693 30 1981 2011 3 $99,693
Site Lighting $1.60 S.F. 62,464 100 $99,693 30 1981 2011 3 $99,693
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 12
Facility: \Administrative/Support\Central Warehouse\Site (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $264,815 $324,369
Building Sitework $264,815 $324,369
Site Improvements $75,661 $324,369
Roadways
Parking Lots $75,661
Pedestrian Paving
Site Development $324,369
Landscaping
Site Mechanical Utilities $86,471
Water Supply $52,500
Sanitary Sewer $26,250
Storm Sewer
Fuel Distribution $7,721
Site Electrical Utilities $102,683
Site Lighting $102,683
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 13
Facility: \Administrative/Support\Central Warehouse\Site (continued)
Deficiency Sheet:
*** No Deficiencies Found ***
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 14
Facility: \Administrative/Support\Central Warehouse\Trade Shops BuildingAddress: 7300 W. Bert Kouns Industrial Loop, Shreveport, LA 71129
Attributes: Number of Floors 1
General Information: Function: Administration/Support Year Built: 1981Gross Area: 7,296 S.F. Last Renovation:
Facility Description:
The Trade Shop Building is a 1-story building located on the western side of the Warehouse Complex at 7300 West Bert Kouns Industrial Loop in Shreveport, Louisiana. The building was acquired and renovated in 1981 and has had no additions or major renovations since that time. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report for each building.
Energy conservation opportunities for this building include: 1) Replacement of the dual duct system with a VAV design and a building automation system would allow programs to improve operation and reduce energy use; 2) A retrofit to higher efficiency (T8) lamps and corresponding electronic ballasts would, with proper maintenance, improve lighting effectiveness and reduce electrical energy consumption; and 3) A review of billing rate may justify addition of power factor correction capacitors.
ADA vertical access is not needed for this building.
Current Repair Cost: $102,172.00 Replacement Cost: $676,865.00 FCI: 15.09%
20-Apr-2010East Elevation
20-Apr-2010South Elevation
20-Apr-2010West Elevation
20-Apr-2010North Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 15
Facility: \Administrative/Support\Central Warehouse\Trade Shops Building (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $92.77 S.F. 7,296 106 $716,421 67 1981 1991 20 $102,173 $676,864 15
Substructure $14.41 S.F. 7,296 100 $105,149 100 1981 $18,000 $105,149 17
Foundations $14.41 S.F. 7,296 100 $105,149 100 1981 $18,000 $105,149 17
Standard Foundations $8.88 S.F. 7,296 100 $64,788 100 1981 $64,788
Slab on Grade $5.53 S.F. 7,296 100 $40,361 100 1981 $18,000 $40,361 45
Shell $31.87 S.F. 7,296 104 $241,460 87 1981 2011 51 $232,538
Superstructure $12.30 S.F. 7,296 100 $89,741 100 1981 $89,741
Roof Construction $12.30 S.F. 7,296 100 $89,741 100 1981 $89,741
Exterior Enclosure $9.35 S.F. 7,296 102 $69,665 84 1981 2011 3 $68,203
Exterior Walls $7.34 S.F. 7,296 100 $53,582 100 1981 $53,582
Exterior Windows 0 0 0 0
Exterior Doors $2.00 S.F. 7,296 110 $16,083 30 1981 2011 3 $14,621
Roofing $10.22 S.F. 7,296 110 $82,054 75 1981 2056 61 $74,594
Roof Coverings - BUR 0 0 0 0
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Metal
$10.22 S.F. 7,296 110 $82,054 75 1981 2056 61 $74,594
Roof Openings 0 0 0 0
Interiors $14.48 S.F. 7,296 107 $112,960 87 1981 1991 28 $10,594 $105,676 10
Interior Construction $13.16 S.F. 7,296 107 $102,366 95 1981 2021 28 $96,045
Partitions $11.66 S.F. 7,296 110 $93,611 100 1981 $85,101
Interior Doors $1.50 S.F. 7,296 80 $8,755 40 1981 2021 28 $10,944
Fittings 0 0 0 0
Interior Finishes $1.32 S.F. 7,296 110 $10,594 10 1981 1991 $10,594 $9,631 110
Wall Finishes - Paint $1.32 S.F. 7,296 110 $10,594 10 1981 1991 $10,594 $9,631 110
Floor Finishes - Carpet 0 0 0 0
Floor Finishes - Ceramic &
Quarry Tile
0 0 0 0
Floor Finishes - VCT 0 0 0 0
Ceiling Finishes 0 0 0 0
Services $32.00 S.F. 7,296 110 $256,852 27 1981 1991 3 $73,579 $233,501 32
Plumbing $2.86 S.F. 7,296 110 $22,921 28 1981 2001 3 $4,141 $20,837 20
Plumbing Fixtures $1.44 S.F. 7,296 110 $11,557 30 1981 2011 3 $10,506
Domestic Water Distribution $0.48 S.F. 7,296 110 $3,852 30 1981 2011 3 $3,502
Sanitary Waste $0.42 S.F. 7,296 110 $3,371 30 1981 2011 3 $3,064
Rain Water Drainage 0 0 0 0
Other Plumbing Systems -
Natural Gas
$0.52 S.F. 7,296 110 $4,141 20 1981 2001 $4,141 $3,765 110
HVAC $6.18 S.F. 7,296 110 $49,599 30 1981 2001 3 $1,445 $45,089 3
Distribution Systems & Exhaust
Systems
0 0 0 0
Unit Heaters $4.56 S.F. 7,296 110 $36,597 30 1981 2011 3 $33,270
Controls & Instrumentation $0.18 S.F. 7,296 110 $1,445 20 1981 2001 $1,445 $1,313 110
Other HVAC Systems/Equip -
Exhaust Hoods
$1.44 S.F. 7,296 110 $11,557 30 1981 2011 3 $10,506
Fire Protection $3.30 S.F. 7,296 110 $26,484 30 1981 2011 3 $24,077
Sprinklers $3.30 S.F. 7,296 110 $26,484 30 1981 2011 3 $24,077
Electrical $19.67 S.F. 7,296 110 $157,848 25 1981 1991 3 $67,993 $143,498 47
Electrical Service/Distribution $3.70 S.F. 7,296 110 $29,663 30 1981 2011 3 $26,966
Branch Wiring $7.50 S.F. 7,296 110 $60,192 30 1981 2011 3 $54,720
Lighting $7.50 S.F. 7,296 110 $60,192 20 1981 2001 $60,192 $54,720 110
Communications and Security -
Fire Alarm
0 0 0 0
Communications and Security -
Security & CCTV
$0.97 S.F. 7,296 110 $7,801 10 1981 1991 $7,801 $7,092 110
Equipment & Furnishings 0 0 0
Furnishings 0 0 0
Fixed Furnishings 0 0 0 0
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 16
Facility: \Administrative/Support\Central Warehouse\Trade Shops Building (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $102,173 $205,338 $24,721
Substructure $18,000
Foundations $18,000
Standard Foundations
Slab on Grade $18,000
Shell $16,566
Superstructure
Roof Construction
Exterior Enclosure $16,566
Exterior Walls
Exterior Windows
Exterior Doors $16,566
Roofing
Roof Coverings - BUR
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Metal
Roof Openings
Interiors $10,594 $14,237
Interior Construction
Partitions
Interior Doors
Fittings
Interior Finishes $10,594 $14,237
Wall Finishes - Paint $10,594 $14,237
Floor Finishes - Carpet
Floor Finishes - Ceramic & Quarry
Tile
Floor Finishes - VCT
Ceiling Finishes
Services $73,579 $188,772 $10,484
Plumbing $4,141 $19,344
Plumbing Fixtures $11,904
Domestic Water Distribution $3,968
Sanitary Waste $3,472
Rain Water Drainage
Other Plumbing Systems - Natural
Gas
$4,141
HVAC $1,445 $49,599
Distribution Systems & Exhaust
Systems
Unit Heaters $37,695
Controls & Instrumentation $1,445
Other HVAC Systems/Equip -
Exhaust Hoods
$11,904
Fire Protection $27,279
Sprinklers $27,279
Electrical $67,993 $92,550 $10,484
Electrical Service/Distribution $30,552
Branch Wiring $61,998
Lighting $60,192
Communications and Security - Fire
Alarm
Communications and Security -
Security & CCTV
$7,801 $10,484
Equipment & Furnishings
Furnishings
Fixed Furnishings
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 17
Facility: \Administrative/Support\Central Warehouse\Trade Shops Building (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Somnath Das Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: A1030 System: Slab on Grade Material: Foundations Distress: Damaged Category: Safety Correction: Professional Service - Investigate Foundation Note: There is an observable crack on the concrete slab, which should be studied by a professional structural engineer.
Estimates:Raw Cost $15,000.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $15,000.00
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Paint Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The painted wall finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $8,828.16
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $8,828.16
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 18
Facility: \Administrative/Support\Central Warehouse\ Trade Shops Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2090 System: Other Plumbing Systems - Natural Gas Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Gas piping is beyond expected life and should be replaced.
Estimates:Raw Cost $3,451.01
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $3,451.01
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D3060 System: Controls & Instrumentation Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Manually set heating controls are beyond expected life and should be replaced.
Estimates:Raw Cost $1,203.84
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $1,203.84
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 19
Facility: \Administrative/Support\Central Warehouse\ Trade Shops Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5020 System: Lighting Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Lighting system are beyond expected life and should be replaced.
Estimates:Raw Cost $50,160.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $50,160.00
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: D5030 System: Communications and Security - Security &
CCTV Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Security system is inadequate, past expected life, and should be replaced. For integrity of system, install wiring
in conduit.
Estimates:Raw Cost $6,500.74
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $6,500.74
COMET4 Caddo Parish
1961 Midway COMET4 Survey Report
Deficiency Detail ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 1
Facility
Name Assembly System Material Distress Correction Qty Unit Raw Cost
Additional
Cost Total Cost Priority Def. Cat. Location / Note
Caddo Parish School District $568,674 $113,735 $682,409 Administrative/Support $568,674 $113,735 $682,409 Central Warehouse $568,674 $113,735 $682,409 Office Warehouse Building $483,530 $96,706 $580,236 Building Systems $483,530 $96,706 $580,236
C3030 Ceiling Finishes System Beyond Expected Life
Renew System 1 Ea. $19,673 $3,935 $23,608 Necessary- 2-5 Yrs
Deferred Maintenance
The ceiling finishes are stained, beyond expected life, and should be replaced.
D2090 Other Plumbing Systems - Natural Gas
System Beyond Expected Life
Renew System 1 Ea. $26,094 $5,219 $31,313 Necessary- 2-5 Yrs
Deferred Maintenance
Natural gas distribution system is beyond expected life and should be replaced.
D5020 Lighting System Beyond Expected Life
Renew System 1 Ea. $197,226 $39,445 $236,671 Necessary- 2-5 Yrs
Deferred Maintenance
Lighting system is beyond expected life and should be replaced.
D5030 Communications and Security - Security & CCTV
System Beyond Expected Life
Renew System 1 Ea. $49,155 $9,831 $58,986 Necessary- 2-5 Yrs
Deferred Maintenance
Security system is inadequate, past expected life, and should be replaced. For integrity of system, install wiring in conduit.
C1030 Fittings System Beyond Expected Life
Renew System 1 Ea. $165,063 $33,013 $198,075 Necessary- 2-5 Yrs
Deferred Maintenance
Fittings, such as lockers, toilet and bath accessories, toilet partitions, and shelving, are beyond expected life and should be replaced.
C3010 Wall Finishes - Paint
System Beyond Expected Life
Renew System 1 Ea. $3,340 $668 $4,008 Necessary- 2-5 Yrs
Deferred Maintenance
The painted wall finishes are beyond expected life and should be replaced.
C3020 Floor Finishes - Carpet
System Beyond Expected Life
Renew System 1 Ea. $8,440 $1,688 $10,128 Necessary- 2-5 Yrs
Deferred Maintenance
The carpet is worn, beyond expected life, and should be replaced.
C3020 Floor Finishes - VCT
System Beyond Expected Life
Renew System 1 Ea. $12,870 $2,574 $15,444 Necessary- 2-5 Yrs
Deferred Maintenance
The vinyl tiles are beyond expected life and should be replaced.
D3050 Terminal & Package Units
Terminal and Package Units
Inadequate Install CRCU 1 Each $1,670 $334 $2,004 Necessary- 2-5 Yrs
Capital Renewal
Computer server cabinet lacks sufficient individual cooling. Install computer cabinet cooling.
COMET4 Caddo Parish
1961 Midway COMET4 Survey Report
Deficiency Detail ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 2
Facility
Name Assembly System Material Distress Correction Qty Unit Raw Cost
Additional
Cost Total Cost Priority Def. Cat. Location / Note
Trade Shops Building $85,144 $17,029 $102,172 Building Systems $85,144 $17,029 $102,172
C3010 Wall Finishes - Paint
System Beyond Expected Life
Renew System 1 Ea. $8,828 $1,766 $10,594 Necessary- 2-5 Yrs
Deferred Maintenance
The painted wall finishes are beyond expected life and should be replaced.
D2090 Other Plumbing Systems - Natural Gas
System Beyond Expected Life
Renew System 1 Ea. $3,451 $690 $4,141 Necessary- 2-5 Yrs
Deferred Maintenance
Gas piping is beyond expected life and should be replaced.
D3060 Controls & Instrumentation
System Beyond Expected Life
Renew System 1 Ea. $1,204 $241 $1,445 Necessary- 2-5 Yrs
Deferred Maintenance
Manually set heating controls are beyond expected life and should be replaced.
D5020 Lighting System Beyond Expected Life
Renew System 1 Ea. $50,160 $10,032 $60,192 Necessary- 2-5 Yrs
Deferred Maintenance
Lighting system are beyond expected life and should be replaced.
D5030 Communications and Security - Security & CCTV
System Beyond Expected Life
Renew System 1 Ea. $6,501 $1,300 $7,801 Necessary- 2-5 Yrs
Deferred Maintenance
Security system is inadequate, past expected life, and should be replaced. For integrity of system, install wiring in conduit.
A1030 Slab on Grade Foundations Damaged Professional Service - Investigate Foundation
1 Ea. $15,000 $3,000 $18,000 Necessary- 2-5 Yrs
Safety There is an observable crack on the concrete slab, which should be studied by a professional structural engineer.
Future Facility and Site Assessment Report
FUTURE FACILITY AND SITE ASSESSMENT
School CENTRAL WAREHOUSE 7300 West Bert Kouns Industrial Loop Shreveport, LA 71129
Site Description 11.7 acre site in west Shreveport just south of the I-20 and the West Bert Kouns Industrial Loop intersection and touches a major railroad switching yard on the south. The site fronts onto Julie Frances Drive although the address is on Kouns which runs along the east boundary. The south and west boundaries abut a rail spur, a segment of which formerly served the warehouse building but has been removed (the servitude still sits over the south end of the site. The site is relatively flat with the main warehouse building on the north end with a small office wing on the east side; a long thin shop building lies along the west side of the large paved truck yard which forms the middle of the site; to the south is a grass and gravel lay down yard; and along the east boundary is a gravel access road along which employees park. There are trees along the Julie Frances front of the building and a few along the railroad spur on the south and west. The buildings are pre-engineered metal structures with typical corrugated metal siding and low-sloped metal roofs.
SUMMARY Topic Grade Comments
Site Adequacy Adequate
The site is adequate and suitable for the current functions and land for expansion of buildings and paving is plentiful and without inhibiting constraints. SITE ASSESSMENT
Expansion Opportunities Adequate
The grass and gravel lay down area to the south is available to almost double the warehouse capability or significantly expand the pavement for truck operations and parking.
Usable Area Remaining Adequate
2.4 Acres. A very rough approximation of the area available for a warehouse addition (scaled drawings were not available) is shown on the graphic.
• Flood Plain No Constraint
• Potable Water No Constraint Low pressure reported.
• Sanitary Sewer No Constraint
• Storm Drainage No Constraint
• Electricity No Constraint
• Natural Gas No Constraint
• Ground Water No Constraint
• Air Pollution No Constraint
• HazMat/Soils No Constraint
• Habitats No Constraint No conflicts identified by DEQ.
Ease of Access No Constraint
Ease of Traffic Flow No Constraint
Design Compatibility No Constraint
The facility fits into the commercial and light industrial neighborhood; expansion would not be intrusive.
Compatibility of Structures
No Constraint
CE
NT
RA
L W
AR
EH
OU
SE
7300 W
. Bert K
ou
ns
Ind
ustria
l Lp
Sh
revep
ort, L
A 7
1129
Pu
blis
he
d 0
5.0
5.1
0
WEST BERT KOUNS INDUSTRIAL LOOP HWY 526
JU
LIE
FR
AN
CE
S D
RIV
E
N
B.J
. MIL
LE
R D
RIV
E
RA
IL S
WIT
CH
YA
RD
FLOURNOY LUCAS RD
RAILROAD SPUR
SPUR
+FH
+FH
+FH
Parking Along Access Drive
Paved Truck
Yard
Former Spur Line
Rail Serv
itude
New Warehouse Zone
Grass/Gravel Lay Down Yard
Approximate: 2.40 AC
Building Code Verification Report
Building Code Number COMPLYNOT
COMPLY
FCA
DEFICIENCY
NOT
KNOWN
SYSTEM
NOT
PRESENT
NA TO FCA
DATA
1Code of Federal Regulations 28 CFR Part
36, 1994 edition, Paragraph 4.1.2,
Paragraph 4.1.6
1 NPFA 101:15.2.3.2; IBC 1017.2
3 IBC 1005.2
5
a
b
c
d
6
a
b
1
2
4 IBC 1011.5.3
1 IBC 1007.3
2 IBC 1020.1
NFPA 101:7.1.3.2.1; IBC 1020.1.2
C2010 Stair Construction
Are all means of egress illuminated at all times building is occupied?
Do exit stairways have a minimum 48” clearance width between handrails?
Are stairs separated by 1-hour fire resistance rating?
Are penetrations into stairs limited to doors, electrical conduit serving the
stairway, piping necessary for the heating or cooling of the exit enclosure,
sprinkler piping, standpipes and penetrations for fire alarm circuits?
Does all door hardware comply by not requiring tight grasping, tight pinching or
twisting to operate?
Maintenance shops?
C10 Interior Construction
C1010 Partitions
C1020 Interior Doors
1
Are corridors 1-hour rated (exceptions: building is sprinklered or each room for
instruction has at least one door directly to the exterior)?
Where there is a chiller, is it separated from a boiler or water heater by a 2-
hour assembly?IBC 508.2
Laundries? NFPA 101:15.3.2.1; IBC 508.2
School Name: Central Warehouse
IBC 1005.2
NFPA101:15.2.11.1.1
IBC 1017.1
G2030 Pedestrian Paving
B2020 Exterior Windows
4
BUILDING CODE COMPLIANCE REPORT
Code Provision
Is there a continuous path of entry/exit for handicap accessibility to all parts of
the building?
Do exit access corridors have not less than 6’ of clear width?
Are both 1-hour rating and sprinkler protection provided for the following:
2
IBC 1008.1.8.1
7
8
Boiler and furnace rooms?
Are corridor doors rated a minimum 20-minute rating?
Is glazing in rated doors above 20 minutes limited to 100 square inches?
NFPA 101:15.3.7
NFPA 101:15.3.2.1; IBC 508.2
Does every room or space greater than 250 SF and used for educational
purposes have not less than one outside window for emergency rescue
(exceptions: sprinklered building or room that has a door directly to the
outside)?
Do doors opening in the path of egress travel not reduce the required width to
less than 1/2 during the course of the swing?
When fully open, do corridor doors not project more than 7 inches into the
required corridor width?
Is the building subdivided into compartments by smoke partitions having not
less than a 1-hour fire rating? (Maximum area of compartment is 30,000 SF.
Length or width of building exceeds 300’ unless sprinklered.)
IBC 715.4.4.1
Is 1-hour rating or sprinkler protection provided for the following:
3
3
Hazardous storage?
Janitor’s closet?
Science labs?
Building Code Number COMPLYNOT
COMPLY
FCA
DEFICIENCY
NOT
KNOWN
SYSTEM
NOT
PRESENT
NA TO FCA
DATACode Provision
4
a NFPA 101:7.2.2.2.4.2; IBC 1012.4
b IBC 1012.5
c NFPA 101:7.2.2.4.4.6; IBC 1012.1
d NFPA 101:7.2.2.4.4.2; IBC 1012.2
5 IBC 1007.6
1
2
1 IBC 508.2
2 IBC 1203.1
3INTERNATIONAL MECHANICAL CODE
2000, 606.4
4 IBC 908.6
1 IBC 903.2
1 IBC 907.2
D10 Conveying
D1010 Elevators
3Does the Elevator Machine Room have ventilation or air conditioning to protect
controls from overheating?
Is there an Area of Refuge in the stairwell or in a vestibule entering the stair? Is
there a communication device there?
Continuously graspable?
Between 34” and 38” above the surface of the tread?
Between 1-1/4” and 2” in diameter?
Returning to wall, guard or walking surface?
3 IBC 907.11
IBC 907.2.12.2
Does the shaft have exhaust directly to the outside, an access ladder to the pit,
and battery backup lighting in the shaft/pit?
Are the mechanical rooms separated by fire rated partitions from remainder of
building?
Is there a standard and emergency ventilation system provided?
Are there automatic sprinkler systems provided in assembly spaces with more
than 300 occupants?
2
Is there a refrigerant detection and alarm system provided?
Are there emergency shut-offs provided?
Are the duct smoke detectors connected to the building’s fire alarm control
panel?
Is there a monitored fire alarm system provided?
Does the operation of fire detector, sprinkler device or manual fire alarm box
immediately sounds an alert tone followed by voice instructions giving
approved information and directions for an evacuation?
IBC 3004.1; IBC 3006.1
D30 HVAC Systems
D40 Fire Protection
D4010 Sprinklers
D50 Electrical
D5030 Communications and Security
4
Is there a telephone or intercom communication in the cab?
Is there a fireman control panel at the ground floor controls?
Are handrails:
IBC 3006.2
IBC 3003.2
Energy Conservation Opportunities Report
System Energy Conservation FCA Deficiency Replacement Cost
SCHOOL TYPEENERGY CONSERVATION OPPORTUNITIES
Central Warehouse Admin
Office Warehouse Building Roof Covering No No
Exterior Windows No No
Interior Lighting Yes Yes $236,671.00
Bldg Controls & Instrumentation No No
Heating No No
Other HVAC Systems (Ventilation) No No
Terminal & Package Units No Yes $2,004.00
Cooling No No
Trade Shops Building Roof Covering No No
Exterior Windows No No
Interior Lighting Yes Yes $60,192.00
Bldg Controls & Instrumentation Yes Yes $1,445.00
Heating No No
Other HVAC Systems (Ventilation) No No
Terminal & Package Units No No
Cooling No No
Site Exterior Lighting No No
Facility Condition Assessment Reports
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 1
Facility: \Administrative/Support\Building 6Address: 3004 Knight Street, Shreveport, LA 71105
Attributes: ***None***
General Information: Function: Administration/Support Year Built:Gross Area: 55,155 S.F. Last Renovation:
Facility Description:
The Building 6 campus consists of one main building located at 3004 Knight Street in Shreveport, Louisiana. The original campus was constructed in 1970. There have been no additions and no renovations. There are no ancillary buildings on campus. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report for each building or other facility on the campus.
Current Repair Cost: $3,662,370.00 Replacement Cost: $9,498,625.00 FCI: 38.56%
19-Apr-2010Building 6
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 2
Facility: \Administrative/Support\Building 6\Main BuildingAddress: 3004 Knight Street, Shreveport, LA 71105
Attributes: Number of Floors 2
General Information: Function: Administration/Support Year Built: 1970Gross Area: 55,155 S.F. Last Renovation:
Facility Description:
Building 6 is a 2-story commercial office building located at 3004 Knight Street in Shreveport, Louisiana. The building was constructed in 1970 and was acquired by the district in 2000. There have been no additions and no renovations. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report.
Energy conservation opportunities for this building include: 1) Addition of a building automation system would allow programs to improve operation and reduce energy use; 2) Exterior windows are steel frame, clear glass design. Installation of fixed, double pane, low e, thermal windows with thermal breaks would improve energy use and improve comfort; 3) New low flow plumbing fixtures would reduce water use; and 4) A review of billing rate may justify addition of power factor correction capacitors.
ADA vertical access needs for this building have been addressed with an elevator.
Current Repair Cost: $3,441,971.00 Replacement Cost: $8,680,566.00 FCI: 39.65%
19-Apr-2010North Elevation
19-Apr-2010Southeast Elevation
19-Apr-2010Northwest Elevation
19-Apr-2010Southwest Elevation
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 3
Facility: \Administrative/Support\Building 6\Main Building (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $157.38 S.F. 55,155 106 $9,233,577 47 1982 1978 2010 84 $3,441,971 $8,680,568 40
Substructure $6.41 S.F. 55,155 100 $353,433 100 1970 $353,433
Foundations $6.41 S.F. 55,155 100 $353,433 100 1970 $353,433
Standard Foundations $2.93 S.F. 55,155 100 $161,494 100 1970 $161,494
Slab on Grade $3.48 S.F. 55,155 100 $191,939 100 1970 $191,939
Basement Construction 0 0 0
Basement Excavation 0 0 0 0
Basement Walls 0 0 0 0
Shell $50.69 S.F. 55,155 103 $2,884,122 74 1974 1990 67 $906,418 $2,795,697 32
Superstructure $16.46 S.F. 55,155 100 $908,072 100 1970 $908,072
Floor Construction $13.88 S.F. 55,155 100 $765,772 100 1970 $765,772
Roof Construction $2.58 S.F. 55,155 100 $142,300 100 1970 $142,300
Exterior Enclosure $23.94 S.F. 55,155 102 $1,352,114 82 1980 2000 67 $282,482 $1,320,411 21
Exterior Walls $18.19 S.F. 55,155 100 $1,003,380 100 1970 $1,003,380
Exterior Windows $4.66 S.F. 55,155 110 $282,482 30 1970 2000 $282,482 $256,802 110
Exterior Doors $1.09 S.F. 55,155 110 $66,252 30 2000 2030 67 $60,229
Roofing $10.28 S.F. 55,155 110 $623,936 20 1970 1990 $623,936 $567,214 110
Roof Coverings - BUR $9.80 S.F. 55,155 110 $594,814 20 1970 1990 $594,814 $540,740 110
Roof Coverings - EPDM 0 0 0 0
Roof Coverings - Standing
Seam Mettal
0 0 0 0
Roof Openings $0.48 S.F. 55,155 110 $29,122 30 1970 2000 $29,122 $26,474 110
Interiors $25.98 S.F. 55,155 104 $1,487,961 55 1978 1978 37 $743,832 $1,433,200 52
Interior Construction $11.26 S.F. 55,155 96 $594,350 65 1980 2010 50 $236,152 $620,825 38
Partitions $4.55 S.F. 55,155 110 $275,929 100 1970 $250,845
Interior Doors $5.35 S.F. 55,155 80 $236,152 40 1970 2010 $236,152 $295,190 80
Fittings $1.36 S.F. 55,155 110 $82,269 20 2000 2020 50 $74,790
Stairs $5.30 S.F. 55,155 110 $321,796 100 1970 $292,542
Stair Construction $5.30 S.F. 55,155 110 $321,796 100 1970 $292,542
Interior Finishes $9.42 S.F. 55,155 110 $571,815 20 1979 1978 20 $507,680 $519,833 98
Wall Finishes - Ceramic &
Glazed
$5.98 S.F. 5,515 110 $36,253 30 1970 2000 $36,253 $32,958 110
Wall Finishes - Paint $1.26 S.F. 49,640 110 $68,801 10 2000 2010 $68,801 $62,546 110
Floor Finishes - Carpet $2.88 S.F. 38,600 110 $122,285 8 1970 1978 $122,285 $111,168 110
Floor Finishes - Ceramic &
Quarry Tile
$10.57 S.F. 5,515 110 $64,135 50 1970 2020 20 $58,305
Floor Finishes - Terrazzo 0 0 0 0
Floor Finishes - VCT $4.44 S.F. 11,040 110 $53,919 15 1970 1985 $53,919 $49,018 110
Floor Finishes - Wood 0 0 0 0
Ceiling Finishes $3.73 S.F. 55,155 110 $226,422 20 1970 1990 $226,422 $205,838 110
Services $72.62 S.F. 55,155 110 $4,406,135 24 1989 2000 2010 89 $1,791,721 $4,005,578 45
Conveying $12.12 S.F. 55,155 110 $735,326 30 1970 2000 $735,326 $668,479 110
Elevators and Lifts $12.12 S.F. 55,155 110 $735,326 30 1970 2000 $735,326 $668,479 110
Plumbing $5.09 S.F. 55,155 110 $308,692 30 1970 2000 $308,692 $280,629 110
Plumbing Fixtures $2.27 S.F. 55,155 110 $137,601 30 1970 2000 $137,601 $125,092 110
Domestic Water Distribution $0.71 S.F. 55,155 110 $42,955 30 1970 2000 $42,955 $39,050 110
Sanitary Waste $1.76 S.F. 55,155 110 $107,023 30 1970 2000 $107,023 $97,293 110
Rain Water Drainage $0.35 S.F. 55,155 110 $21,113 30 1970 2000 $21,113 $19,194 110
Other Plumbing Systems -
Natural Gas
0 0 0 0
HVAC $32.00 S.F. 55,155 110 $1,941,699 20 2010 2025 100 $1,765,181
Heat Generating Systems 0 0 0 0
Cooling Generating Systems 0 0 0 0
Distribution Systems & Exhaust
Systems
$9.24 S.F. 55,155 110 $560,595 30 2010 2040 100 $509,632
Terminal & Package Units $20.52 S.F. 55,155 110 $1,244,959 15 2010 2025 100 $1,131,781
Controls & Instrumentation $2.24 S.F. 55,155 110 $136,145 20 2010 2030 100 $123,768
Fire Protection $3.17 S.F. 55,155 110 $192,204 30 0 2010 $192,204 $174,731 110
Sprinklers $3.17 S.F. 55,155 110 $192,204 30 0 2010 $192,204 $174,731 110
Electrical $20.24 S.F. 55,155 110 $1,228,214 23 1995 2000 57 $555,499 $1,116,558 50
Electrical Service/Distribution $4.38 S.F. 55,155 110 $265,737 30 2000 2030 67 $241,579
Branch Wiring $5.48 S.F. 55,155 110 $332,717 30 1970 2000 $332,717 $302,470 110
Lighting $5.48 S.F. 55,155 110 $332,717 20 2000 2020 50 $302,470
Communications and Security -
Public Address & Clock System
$1.22 S.F. 55,155 110 $74,261 20 2000 2020 50 $67,510
Fire Alarm $2.45 S.F. 55,155 110 $148,521 10 2000 2010 $148,521 $135,019 110
Security & CCTV $1.22 S.F. 55,155 110 $74,261 10 2000 2010 $74,261 $67,510 110
Other Electrical Systems -
Emergency Generator
0 0 0 0
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 4
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Equipment & Furnishings $1.68 S.F. 55,155 110 $101,926 20 2000 2020 50 $92,660
Furnishings $1.68 S.F. 55,155 110 $101,926 20 2000 2020 50 $92,660
Fixed Furnishings $1.68 S.F. 55,155 110 $101,926 20 2000 2020 50 $92,660
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 5
Facility: \Administrative/Support\Building 6\Main Building (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $3,441,971 $154,907 $1,272,543
Substructure
Foundations
Standard Foundations
Slab on Grade
Basement Construction
Basement Excavation
Basement Walls
Shell $906,418
Superstructure
Floor Construction
Roof Construction
Exterior Enclosure $282,482
Exterior Walls
Exterior Windows $282,482
Exterior Doors
Roofing $623,936
Roof Coverings - BUR $594,814
Roof Coverings - EPDM
Roof Coverings - Standing Seam
Mettal
Roof Openings $29,122
Interiors $743,832 $154,907 $289,218
Interior Construction $236,152 $110,563
Partitions
Interior Doors $236,152
Fittings $110,563
Stairs
Stair Construction
Interior Finishes $507,680 $154,907 $178,655
Wall Finishes - Ceramic & Glazed $36,253
Wall Finishes - Paint $68,801 $92,463
Floor Finishes - Carpet $122,285 $154,907
Floor Finishes - Ceramic & Quarry
Tile
$86,192
Floor Finishes - Terrazzo
Floor Finishes - VCT $53,919
Floor Finishes - Wood
Ceiling Finishes $226,422
Services $1,791,721 $846,344
Conveying $735,326
Elevators and Lifts $735,326
Plumbing $308,692
Plumbing Fixtures $137,601
Domestic Water Distribution $42,955
Sanitary Waste $107,023
Rain Water Drainage $21,113
Other Plumbing Systems - Natural
Gas
HVAC
Heat Generating Systems
Cooling Generating Systems
Distribution Systems & Exhaust
Systems
Terminal & Package Units
Controls & Instrumentation
Fire Protection $192,204
Sprinklers $192,204
Electrical $555,499 $846,344
Electrical Service/Distribution
Branch Wiring $332,717
Lighting $447,144
Communications and Security -
Public Address & Clock System
$99,800
Fire Alarm $148,521 $199,600
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 6
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Security & CCTV $74,261 $99,800
Other Electrical Systems -
Emergency Generator
Equipment & Furnishings $136,981
Furnishings $136,981
Fixed Furnishings $136,981
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 7
Facility: \Administrative/Support\Building 6\Main Building (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B2020 System: Exterior Windows Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The exterior windows are beyond expected life and should be replaced.
Estimates:Raw Cost $235,401.54
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $235,401.54
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: B3010 System: Roof Coverings - BUR Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Roof covering system is past expected life and should be replaced. Roof replacement to include appropriate
insulation for energy conservation.
Estimates:Raw Cost $495,677.99
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $495,677.99
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 8
Facility: \Administrative/Support\Building 6\ Main Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: B3020 System: Roof Openings Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Roof hatch is beyond expected life, does not meet current OSHA requirements, and should be replaced.
Estimates:Raw Cost $24,268.20
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $24,268.20
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: C1020 System: Interior Doors Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The interior doors are beyond expected life and should be replaced.
Estimates:Raw Cost $196,793.04
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $196,793.04
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 9
Facility: \Administrative/Support\Building 6\ Main Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Ceramic & Glazed Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The ceramic wall finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $30,211.17
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $30,211.17
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3010 System: Wall Finishes - Paint Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The painted wall finishes are beyond expected life and should be replaced.
Estimates:Raw Cost $57,334.20
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $57,334.20
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 10
Facility: \Administrative/Support\Building 6\ Main Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3020 System: Floor Finishes - Carpet Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The carpet is worn, beyond expected life, and should be replaced.
Estimates:Raw Cost $101,904.00
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $101,904.00
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: C3020 System: Floor Finishes - VCT Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The vinyl tiles are beyond expected life and should be replaced.
Estimates:Raw Cost $44,932.80
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $44,932.80
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 11
Facility: \Administrative/Support\Building 6\ Main Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: C3030 System: Ceiling Finishes Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The ceiling finishes are stained, beyond expected life, and should be replaced.
Estimates:Raw Cost $188,685.26
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $188,685.26
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D1010 System: Elevators and Lifts Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Hydraulic elevator is beyond expected life, does not meet current codes, and should be replaced.
Estimates:Raw Cost $612,772.05
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $612,772.05
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 12
Facility: \Administrative/Support\Building 6\ Main Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2010 System: Plumbing Fixtures Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Plumbing fixtures are original, not low flow design, beyond expected life, and should be replaced.
Estimates:Raw Cost $114,667.25
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $114,667.25
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2020 System: Domestic Water Distribution Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Domestic water system is original, beyond expected life, and should be replaced.
Estimates:Raw Cost $35,795.60
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $35,795.60
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 13
Facility: \Administrative/Support\Building 6\ Main Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2030 System: Sanitary Waste Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The sanitary system is original, beyond expected life, and should be replaced.
Estimates:Raw Cost $89,185.64
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $89,185.64
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D2040 System: Rain Water Drainage Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Roof drain system is beyond expected life and should be replaced.
Estimates:Raw Cost $17,594.45
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $17,594.45
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 14
Facility: \Administrative/Support\Building 6\ Main Building (continued)
Deficiency: Surveyor/Update: Somnath Das Tue, 08-Jun-2010Priority: 3Quantity: 1
Assembly: D4010 System: Sprinklers Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note:
Estimates:Raw Cost $160,170.12
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $160,170.12
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: D5020 System: Branch Wiring Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Most wiring is original, past expected life, and should be replaced.
Estimates:Raw Cost $277,264.19
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $277,264.19
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 15
Facility: \Administrative/Support\Building 6\ Main Building (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5030 System: Fire Alarm Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Fire alarm system are beyond expected life and should be replaced.
Estimates:Raw Cost $123,767.82
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $123,767.82
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: D5030 System: Security & CCTV Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Security system is beyond expected life and should be replaced. For integrity of system, install wiring in conduit.
Estimates:Raw Cost $61,883.91
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $61,883.91
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 16
Facility: \Administrative/Support\Building 6\SiteAddress: 3004 Knight Street, Shreveport, LA 71105
Attributes: Site Area (in Acres) 2.55
General Information: Function: Administration/Support Year Built: 1970Gross Area: 55,155 S.F. Last Renovation:
Facility Description:
The original site was constructed in 1970. There have been no additions, major renovations, or additional improvements to the site. Campus site features include paved driveways and parking lots, pedestrian pavement, flag pole, landscaping, and fencing. Site mechanical and electrical features include water, sewer, natural gas, and site lighting. This report contains condition and adequacy data collected during the 2009/2010 Facility Condition Assessment (FCA). The detailed condition and deficiency statements are contained in this report for each building.
Current Repair Cost: $220,399.00 Replacement Cost: $818,059.00 FCI: 26.94%
19-Apr-2010Aerial Image of Building 6
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 17
Facility: \Administrative/Support\Building 6\Site (continued)
Building Condition:
System Unit Price$
Unit of
Meas Qty Renewal% Renewal$ Life Installed
Calc Next
Renewal
Next
Renewal CI% Deficiency$ Replacement Value FCI%
Total $14.83 S.F. 55,155 100 $818,057 33 1973 2000 32 $220,398 $818,057 27
Building Sitework $14.83 S.F. 55,155 100 $818,057 33 1973 2000 32 $220,398 $818,057 27
Site Improvements $8.50 S.F. 55,155 100 $468,596 28 1976 2000 39 $64,862 $468,596 14
Roadways $1.38 S.F. 55,155 100 $76,114 50 1970 2020 20 $76,114
Parking Lots $1.18 S.F. 55,155 100 $64,862 30 1970 2000 $64,862 $64,862 100
Pedestrian Paving $0.82 S.F. 55,155 100 $45,006 50 1970 2020 20 $45,006
Site Development $3.86 S.F. 55,155 100 $213,119 20 2000 2020 50 $213,119
Landscaping $1.26 S.F. 55,155 100 $69,495 10 1970 $69,495
Site Mechanical Utilities $4.74 S.F. 55,155 100 $261,434 45 1970 2000 20 $67,509 $261,434 26
Water Supply $0.82 S.F. 55,155 100 $45,006 30 1970 2000 $45,006 $45,006 100
Sanitary Sewer $0.41 S.F. 55,155 100 $22,503 30 1970 2000 $22,503 $22,503 100
Storm Sewer $3.52 S.F. 55,155 100 $193,925 50 1970 2020 20 $193,925
Fuel Distribution 0 0 0 0
Site Electrical Utilities $1.60 S.F. 55,155 100 $88,027 30 1970 2000 $88,027 $88,027 100
Site Lighting $1.60 S.F. 55,155 100 $88,027 30 1970 2000 $88,027 $88,027 100
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 18
Facility: \Administrative/Support\Building 6\Site (continued)
Renewal Schedule:
Systems 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Total $220,398 $709,809
Building Sitework $220,398 $709,809
Site Improvements $64,862 $449,190
Roadways $102,291
Parking Lots $64,862
Pedestrian Paving $60,485
Site Development $286,414
Landscaping
Site Mechanical Utilities $67,509 $260,619
Water Supply $45,006
Sanitary Sewer $22,503
Storm Sewer $260,619
Fuel Distribution
Site Electrical Utilities $88,027
Site Lighting $88,027
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 19
Facility: \Administrative/Support\Building 6\Site (continued)
Deficiency Sheet:
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: G2020 System: Parking Lots Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: The parking lots are beyond expected life and should be resurfaced and restriped.
Estimates:Raw Cost $54,051.90
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $54,051.90
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: G3010 System: Water Supply Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Water supply is original, beyond expected life, and should be replaced.
Estimates:Raw Cost $37,505.40
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $37,505.40
COMET4 Caddo Parish
1961 Midway COMET4 Facility Report
Facility Executive Summary ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 20
Facility: \Administrative/Support\Building 6\ Site (continued)
Deficiency: Surveyor/Update: Phil Trenbath Mon, 07-Jun-2010Priority: 3Quantity: 1
Assembly: G3020 System: Sanitary Sewer Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Sanitary sewer system includes a lift station that is beyond expected life and should be replaced.
Estimates:Raw Cost $18,752.70
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $18,752.70
Deficiency: Surveyor/Update: Phil Trenbath Thu, 06-May-2010Priority: 3Quantity: 1
Assembly: G4020 System: Site Lighting Material: System Distress: Beyond Expected Life Category: Deferred Maintenance Correction: Renew System Note: Exterior lighting is past expected life and should be replaced.
Estimates:Raw Cost $73,356.15
Plus or (Minus) Additional Cost $0.00Total Estimated Amount $73,356.15
COMET4 Caddo Parish
1961 Midway COMET4 Survey Report
Deficiency Detail ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 1
Facility
Name Assembly System Material Distress Correction Qty Unit Raw Cost
Additional
Cost Total Cost Priority Def. Cat. Location / Note
Caddo Parish School District $3,051,975 $610,395 $3,662,370 Administrative/Support $3,051,975 $610,395 $3,662,370 Building 6 $3,051,975 $610,395 $3,662,370 Main Building $2,868,309 $573,662 $3,441,971 Building Systems $2,868,309 $573,662 $3,441,971
D5020 Branch Wiring System Beyond Expected Life
Renew System 1 Ea. $277,264 $55,453 $332,717 Necessary- 2-5 Yrs
Deferred Maintenance
Most wiring is original, past expected life, and should be replaced.
D5030 Fire Alarm System Beyond Expected Life
Renew System 1 Ea. $123,768 $24,754 $148,521 Necessary- 2-5 Yrs
Deferred Maintenance
Fire alarm system are beyond expected life and should be replaced.
D5030 Security & CCTV System Beyond Expected Life
Renew System 1 Ea. $61,884 $12,377 $74,261 Necessary- 2-5 Yrs
Deferred Maintenance
Security system is beyond expected life and should be replaced. For integrity of system, install wiring in conduit.
B2020 Exterior Windows
System Beyond Expected Life
Renew System 1 Ea. $235,402 $47,080 $282,482 Necessary- 2-5 Yrs
Deferred Maintenance
The exterior windows are beyond expected life and should be replaced.
B3010 Roof Coverings -BUR
System Beyond Expected Life
Renew System 1 Ea. $495,678 $99,136 $594,814 Necessary- 2-5 Yrs
Deferred Maintenance
Roof covering system is past expected life and should be replaced. Roof replacement to include appropriate insulation for energy conservation.
B3020 Roof Openings System Beyond Expected Life
Renew System 1 Ea. $24,268 $4,854 $29,122 Necessary- 2-5 Yrs
Deferred Maintenance
Roof hatch is beyond expected life, does not meet current OSHA requirements, and should be replaced.
C1020 Interior Doors System Beyond Expected Life
Renew System 1 Ea. $196,793 $39,359 $236,152 Necessary- 2-5 Yrs
Deferred Maintenance
The interior doors are beyond expected life and should be replaced.
C3010 Wall Finishes - Ceramic & Glazed
System Beyond Expected Life
Renew System 1 Ea. $30,211 $6,042 $36,253 Necessary- 2-5 Yrs
Deferred Maintenance
The ceramic wall finishes are beyond expected life and should be replaced.
C3010 Wall Finishes - Paint
System Beyond Expected Life
Renew System 1 Ea. $57,334 $11,467 $68,801 Necessary- 2-5 Yrs
Deferred Maintenance
The painted wall finishes are beyond expected life and should be replaced.
C3020 Floor Finishes - Carpet
System Beyond Expected Life
Renew System 1 Ea. $101,904 $20,381 $122,285 Necessary- 2-5 Yrs
Deferred Maintenance
The carpet is worn, beyond expected life, and should be replaced.
C3020 Floor Finishes - VCT
System Beyond Expected Life
Renew System 1 Ea. $44,933 $8,987 $53,919 Necessary- 2-5 Yrs
Deferred Maintenance
The vinyl tiles are beyond expected life and should be replaced.
C3030 Ceiling Finishes System Beyond Expected Life
Renew System 1 Ea. $188,685 $37,737 $226,422 Necessary- 2-5 Yrs
Deferred Maintenance
The ceiling finishes are stained, beyond expected life, and should be replaced.
D1010 Elevators and Lifts
System Beyond Expected Life
Renew System 1 Ea. $612,772 $122,554 $735,326 Necessary- 2-5 Yrs
Deferred Maintenance
Hydraulic elevator is beyond expected life, does not meet current codes, and should be replaced.
D2010 Plumbing Fixtures
System Beyond Expected Life
Renew System 1 Ea. $114,667 $22,933 $137,601 Necessary- 2-5 Yrs
Deferred Maintenance
Plumbing fixtures are original, not low flow design, beyond expected life, and should be replaced.
D2020 Domestic Water Distribution
System Beyond Expected Life
Renew System 1 Ea. $35,796 $7,159 $42,955 Necessary- 2-5 Yrs
Deferred Maintenance
Domestic water system is original, beyond expected life, and should be replaced.
COMET4 Caddo Parish
1961 Midway COMET4 Survey Report
Deficiency Detail ReportShreveport, LA 71106 Report Date: 08 Jun 2010
Page 2
Facility
Name Assembly System Material Distress Correction Qty Unit Raw Cost
Additional
Cost Total Cost Priority Def. Cat. Location / Note
D2030 Sanitary Waste System Beyond Expected Life
Renew System 1 Ea. $89,186 $17,837 $107,023 Necessary- 2-5 Yrs
Deferred Maintenance
The sanitary system is original, beyond expected life, and should be replaced.
D2040 Rain Water Drainage
System Beyond Expected Life
Renew System 1 Ea. $17,594 $3,519 $21,113 Necessary- 2-5 Yrs
Deferred Maintenance
Roof drain system is beyond expected life and should be replaced.
D4010 Sprinklers System Beyond Expected Life
Renew System 1 Ea. $160,170 $32,034 $192,204 Necessary- 2-5 Yrs
Deferred Maintenance
Site $183,666 $36,733 $220,399 Building Systems $183,666 $36,733 $220,399
G2020 Parking Lots System Beyond Expected Life
Renew System 1 Ea. $54,052 $10,810 $64,862 Necessary- 2-5 Yrs
Deferred Maintenance
The parking lots are beyond expected life and should be resurfaced and restriped.
G3010 Water Supply System Beyond Expected Life
Renew System 1 Ea. $37,505 $7,501 $45,006 Necessary- 2-5 Yrs
Deferred Maintenance
Water supply is original, beyond expected life, and should be replaced.
G3020 Sanitary Sewer System Beyond Expected Life
Renew System 1 Ea. $18,753 $3,751 $22,503 Necessary- 2-5 Yrs
Deferred Maintenance
Sanitary sewer system includes a lift station that is beyond expected life and should be replaced.
G4020 Site Lighting System Beyond Expected Life
Renew System 1 Ea. $73,356 $14,671 $88,027 Necessary- 2-5 Yrs
Deferred Maintenance
Exterior lighting is past expected life and should be replaced.
Future Facility and Site Assessment Report
FUTURE FACILITY AND SITE ASSESSMENT
School BUILDING 6 3004 Knight Street Shreveport, LA 71105
Site Description 2.55 acre site in east Shreveport near the Red River adjacent to an oxbow cutoff of a former tributary and close to the Barksdale highway bridge over the Red River. The narrow, odd-shaped site is among a group of office buildings fronting on Knight Street. The building primarily houses administrative functions for the District but there are some small areas used for Special Education activities. The water area on the southwest edge is included in the 100-year flood plain and there is a culverted drainage easement passing under the building leading from the roadside ditch to the water. The T-shaped 2-story building and the surrounding parking lot fill the site. The adjacent building to the west shares a parking lot and the property line divides the paved area between them. There are trees along the bank of the watercourse. The office building is 2-story, T-shaped, with a decorative rough-finished stucco surface, and flat roof with a modest overhang. Site features include a footbridge across the west-side drainage ditch leading to the building to the west, paved parking lots and drives that surround the building, and the vegetated bank down to the water.
SUMMARY Topic Grade Comments
Site Adequacy Adequate
The site is adequate for the current functions but is entirely filled by the building and parking lots. SITE ASSESSMENT
Expansion Opportunities
None There is no space for expansion on the site without building on top of the existing parking.
Usable Area Remaining
None See note above.
• Flood Plain Potential
Constraint
The 100-year flood plain encroaches on the southwest side of the site and may penetrate northwards along the drainage easement that crosses underneath the building.
• Potable Water No Constraint Low pressure reported.
• Sanitary Sewer No Constraint
• Storm Drainage No Constraint
• Electricity No Constraint
• Natural Gas No Constraint
• Ground Water No Constraint
• Air Pollution No Constraint
• HazMat/Soils No Constraint
• Habitats No Constraint No conflicts identified by DEQ.
Ease of Access No Constraint
Ease of Traffic Flow No Constraint
Design Compatibility No Constraint
The facility fits into the commercial office and light industrial neighborhood.
Compatibility of Structures No Constraint
The simple but contemporary styling, building massing and layout, and materials used can be blended well with any new structure should a feasible way to add-on be devised.
BU
ILD
ING
63004 K
nig
ht S
treet
Sh
revep
ort, L
A 7
1105
Pu
blis
he
d 0
5.0
5.1
0
KNIGHT STREET
100 - YEAR
FLOOD PLAIN
(approximate)D
rain
age E
ase
ment +FH
COMMERCIAL
COMMERCIAL
COMMERCIAL
Parking
Park
ing
Footbridge
Open D
itch
Slight Slope
Bank
Slope
Culv
ert
Bank
Slope
Parking
Driveway
Ditch
West P
rop. Lin
e A
ppro
xim
ate
Utility Data Incomplete
RESIDENTIAL
N
Building Code Verification Report
Building Code Number COMPLYNOT
COMPLY
FCA
DEFICIENCY
NOT
KNOWN
SYSTEM
NOT
PRESENT
NA TO FCA
DATA
1Code of Federal Regulations 28 CFR Part
36, 1994 edition, Paragraph 4.1.2,
Paragraph 4.1.6
1 NPFA 101:15.2.3.2; IBC 1017.2
3 IBC 1005.2
5
a
b
c
d
6
a
b
1
2
4 IBC 1011.5.3
1 IBC 1007.3
2 IBC 1020.1
3
Hazardous storage?
Janitor’s closet?
Science labs?
IBC 1008.1.8.1
7
8
Boiler and furnace rooms?
Are corridor doors rated a minimum 20-minute rating?
Is glazing in rated doors above 20 minutes limited to 100 square inches?
NFPA 101:15.3.7
NFPA 101:15.3.2.1; IBC 508.2
Does every room or space greater than 250 SF and used for educational
purposes have not less than one outside window for emergency rescue
(exceptions: sprinklered building or room that has a door directly to the
outside)?
Do doors opening in the path of egress travel not reduce the required width to
less than 1/2 during the course of the swing?
When fully open, do corridor doors not project more than 7 inches into the
required corridor width?
Is the building subdivided into compartments by smoke partitions having not
less than a 1-hour fire rating? (Maximum area of compartment is 30,000 SF.
Length or width of building exceeds 300’ unless sprinklered.)
IBC 715.4.4.1
Is 1-hour rating or sprinkler protection provided for the following:
3
School Name: Building 6
IBC 1005.2
NFPA101:15.2.11.1.1
IBC 1017.1
G2030 Pedestrian Paving
B2020 Exterior Windows
4
BUILDING CODE COMPLIANCE REPORT
Code Provision
Is there a continuous path of entry/exit for handicap accessibility to all parts of
the building?
Do exit access corridors have not less than 6’ of clear width?
Are both 1-hour rating and sprinkler protection provided for the following:
2
Does all door hardware comply by not requiring tight grasping, tight pinching or
twisting to operate?
Maintenance shops?
C10 Interior Construction
C1010 Partitions
C1020 Interior Doors
1
Are corridors 1-hour rated (exceptions: building is sprinklered or each room for
instruction has at least one door directly to the exterior)?
Where there is a chiller, is it separated from a boiler or water heater by a 2-
hour assembly?IBC 508.2
Laundries? NFPA 101:15.3.2.1; IBC 508.2
NFPA 101:7.1.3.2.1; IBC 1020.1.2
C2010 Stair Construction
Are all means of egress illuminated at all times building is occupied?
Do exit stairways have a minimum 48” clearance width between handrails?
Are stairs separated by 1-hour fire resistance rating?
Are penetrations into stairs limited to doors, electrical conduit serving the
stairway, piping necessary for the heating or cooling of the exit enclosure,
sprinkler piping, standpipes and penetrations for fire alarm circuits?
Building Code Number COMPLYNOT
COMPLY
FCA
DEFICIENCY
NOT
KNOWN
SYSTEM
NOT
PRESENT
NA TO FCA
DATACode Provision
4
a NFPA 101:7.2.2.2.4.2; IBC 1012.4
b IBC 1012.5
c NFPA 101:7.2.2.4.4.6; IBC 1012.1
d NFPA 101:7.2.2.4.4.2; IBC 1012.2
5 IBC 1007.6
1
2
1 IBC 508.2
2 IBC 1203.1
3INTERNATIONAL MECHANICAL CODE
2000, 606.4
4 IBC 908.6
1 IBC 903.2
1 IBC 907.2
4
Is there a telephone or intercom communication in the cab?
Is there a fireman control panel at the ground floor controls?
Are handrails:
IBC 3006.2
IBC 3003.2
Continuously graspable?
Between 34” and 38” above the surface of the tread?
Between 1-1/4” and 2” in diameter?
Returning to wall, guard or walking surface?
3 IBC 907.11
IBC 907.2.12.2
Does the shaft have exhaust directly to the outside, an access ladder to the pit,
and battery backup lighting in the shaft/pit?
Are the mechanical rooms separated by fire rated partitions from remainder of
building?
Is there a standard and emergency ventilation system provided?
Are there automatic sprinkler systems provided in assembly spaces with more
than 300 occupants?
2
Is there a refrigerant detection and alarm system provided?
Are there emergency shut-offs provided?
Are the duct smoke detectors connected to the building’s fire alarm control
panel?
Is there a monitored fire alarm system provided?
Does the operation of fire detector, sprinkler device or manual fire alarm box
immediately sounds an alert tone followed by voice instructions giving
approved information and directions for an evacuation?
IBC 3004.1; IBC 3006.1
D30 HVAC Systems
D40 Fire Protection
D4010 Sprinklers
D50 Electrical
D5030 Communications and Security
D10 Conveying
D1010 Elevators
3Does the Elevator Machine Room have ventilation or air conditioning to protect
controls from overheating?
Is there an Area of Refuge in the stairwell or in a vestibule entering the stair? Is
there a communication device there?
Energy Conservation Opportunities Report
System Energy Conservation FCA Deficiency Replacement Cost
Building 6 Admin
Main Building Roof Covering Yes Yes $539,220.00
Exterior Windows Yes Yes $256,080.00
Interior Lighting No No
Bldg Controls & Instrumentation No No
Heating No No
Other HVAC Systems (Ventilation) No No
Terminal & Package Units No No
Cooling No No
Site Exterior Lighting Yes Yes $79,800.00
SCHOOL TYPEENERGY CONSERVATION OPPORTUNITIES