fail over test

Upload: menuselect

Post on 06-Apr-2018

221 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/3/2019 Fail Over Test

    1/379

    # Question Res onse

    M1Is this an Infrastructure or an Application Change?

    Application

    M2

    Is this change subject to a Change Management Approved agreement - i.e. CAMRequest - which specifies that a cut down version or non standard version of the

    RFC Tem late can be used

    No

    M3

    Is Business outage required? No

    M3a If a Business outa e what is the outa e duration? 3 hoursM3b If a Business outa e is it scheduled outside normal Business workin eriods? YesM4 Is the chan e window art of a WCC eriod? NoM5 Is this chan e window art of a Ke Event i.e. Stabilit Period Turnaround ? No

    I1Is this a Shared Infrastructure Change? No

    M6 What Se ments/Functions does this chan e im act Functions

    M7a Risk & Im act clarification 1 NoM7b Risk & Im act clarification 2M7c Risk & Im act clarification 3 No

    A1

    Is there a change to the Access Controls setup of the system? No

    A2

    Is there a change to the Data Classification within the application? No

    A3 Are an external links or FireWall chan es included in this chan e? NoM8 Does this chan e amend the Su ort Model in an wa ? NoM9 Does this chan e include a Version U rade? NoM10 Does this Chan e relate to a Ma or Pro ect? No

    M11Does this change include any Decommissioning activities No

    # Question Res onse

    Mp1 Are Business Communications re uired to su ort this chan e?Yes

    Mp2 Are Technical Communications re uired to su ort this chan e?

    Yes

    Mp3

    Have all teams who need to be involved in, or aware of the change been engaged

    with?Yes

    Mp4 What environment is this chan e bein made in Production

    Mp5

    Does this change follow a pre-defined Test Plan that has been formally reviewed

    and a roved and is ublishedNo

    N

    This Worksheet MUST be completed for all changes - your responses will provide g

    review

    If some detail is missing or not all results are sh

    General Guidelines and

    RFC Reference: CRQ000000049324

  • 8/3/2019 Fail Over Test

    2/379

  • 8/3/2019 Fail Over Test

    3/379

    Guidelines

    1. Testing Tables

    2. Engagement Meetings

    3. Communications

    4. External Resources and Engineers

    Is testing complete at the time of attaching this RFC Templa

    Test Case

    1. This implementation would be only on production systems,

    to make sure the availablity of cluster, in case of any major

    incident or failure of some service

    Is testing complete at the time of attaching this RFC Templa

    System Testing

  • 8/3/2019 Fail Over Test

    4/379

    Meeting Title/Purpose

    List External Resource / Engineer

    Provide det

    Provide details of Communicati

    Provide details of External

  • 8/3/2019 Fail Over Test

    5/379

  • 8/3/2019 Fail Over Test

    6/379

  • 8/3/2019 Fail Over Test

    7/379

  • 8/3/2019 Fail Over Test

    8/379

  • 8/3/2019 Fail Over Test

    9/379

  • 8/3/2019 Fail Over Test

    10/379

  • 8/3/2019 Fail Over Test

    11/379

  • 8/3/2019 Fail Over Test

    12/379

  • 8/3/2019 Fail Over Test

    13/379

  • 8/3/2019 Fail Over Test

    14/379

    NO Testing completion Date

    enter date whether

    completed or not

    Tester Pre-Change Test Stat Comment

    NO Testing completion Date

    enter date whether

    completed or not

    Tester Pre-Change Test Stat Comment

    environment(s) testing performed in >

    This tab must list all activities that need to be completed in preparation for the

    final implementation to ensure that all possible Risk Mitigation is in place

    our change ticket will not pass validation & you will not gain approval for this

    change

    -Testing plan

    -Pre-Testing Log

    Detail test plans, testers and test results - if referring to other documents these

    must be accessible by all reviewers of the RFC, with the location of the document

    provided below - if attached to the RFC state which Work Info Record they areIt is the responsibility of the Change Assignee to ensure all impacted parties are

    engaged with in preparation for the change activity. Details of these engagements

    Ensure these are considered as part of the Prior Preparation and Planning

    activities and are clearly documented in Tab 7 Communications Plan

    If it is necessary to secure any external resource for the change activity details

    must be provided - typically this will be an engineer. In the context of Rig, Tanker

    or similar changes where transportation etc is critical, therefore timing for

    external resources has a significant implication on the success/failure of the

  • 8/3/2019 Fail Over Test

    15/379

    Attendees Attendee Role & Org

    Comment (was

    objective met?)

    yes

    Justification for using

    external

    resource/engineer

    na a e can e

    booked to meet

    planned

    implementation

    window? To be booked by?

    ils of Engagement Meetings

    ns activities - Go to Tab 7 Communications Plan

    Resources and/or Engineers to be booked

  • 8/3/2019 Fail Over Test

    16/379

  • 8/3/2019 Fail Over Test

    17/379

  • 8/3/2019 Fail Over Test

    18/379

  • 8/3/2019 Fail Over Test

    19/379

  • 8/3/2019 Fail Over Test

    20/379

  • 8/3/2019 Fail Over Test

    21/379

  • 8/3/2019 Fail Over Test

    22/379

  • 8/3/2019 Fail Over Test

    23/379

  • 8/3/2019 Fail Over Test

    24/379

  • 8/3/2019 Fail Over Test

    25/379

  • 8/3/2019 Fail Over Test

    26/379

  • 8/3/2019 Fail Over Test

    27/379

  • 8/3/2019 Fail Over Test

    28/379

  • 8/3/2019 Fail Over Test

    29/379

  • 8/3/2019 Fail Over Test

    30/379

  • 8/3/2019 Fail Over Test

    31/379

  • 8/3/2019 Fail Over Test

    32/379

  • 8/3/2019 Fail Over Test

    33/379

  • 8/3/2019 Fail Over Test

    34/379

  • 8/3/2019 Fail Over Test

    35/379

  • 8/3/2019 Fail Over Test

    36/379

  • 8/3/2019 Fail Over Test

    37/379

  • 8/3/2019 Fail Over Test

    38/379

  • 8/3/2019 Fail Over Test

    39/379

  • 8/3/2019 Fail Over Test

    40/379

  • 8/3/2019 Fail Over Test

    41/379

  • 8/3/2019 Fail Over Test

    42/379

  • 8/3/2019 Fail Over Test

    43/379

  • 8/3/2019 Fail Over Test

    44/379

  • 8/3/2019 Fail Over Test

    45/379

  • 8/3/2019 Fail Over Test

    46/379

  • 8/3/2019 Fail Over Test

    47/379

  • 8/3/2019 Fail Over Test

    48/379

  • 8/3/2019 Fail Over Test

    49/379

  • 8/3/2019 Fail Over Test

    50/379

  • 8/3/2019 Fail Over Test

    51/379

  • 8/3/2019 Fail Over Test

    52/379

  • 8/3/2019 Fail Over Test

    53/379

  • 8/3/2019 Fail Over Test

    54/379

  • 8/3/2019 Fail Over Test

    55/379

  • 8/3/2019 Fail Over Test

    56/379

  • 8/3/2019 Fail Over Test

    57/379

  • 8/3/2019 Fail Over Test

    58/379

  • 8/3/2019 Fail Over Test

    59/379

  • 8/3/2019 Fail Over Test

    60/379

  • 8/3/2019 Fail Over Test

    61/379

  • 8/3/2019 Fail Over Test

    62/379

  • 8/3/2019 Fail Over Test

    63/379

  • 8/3/2019 Fail Over Test

    64/379

  • 8/3/2019 Fail Over Test

    65/379

  • 8/3/2019 Fail Over Test

    66/379

  • 8/3/2019 Fail Over Test

    67/379

  • 8/3/2019 Fail Over Test

    68/379

  • 8/3/2019 Fail Over Test

    69/379

  • 8/3/2019 Fail Over Test

    70/379

  • 8/3/2019 Fail Over Test

    71/379

  • 8/3/2019 Fail Over Test

    72/379

  • 8/3/2019 Fail Over Test

    73/379

  • 8/3/2019 Fail Over Test

    74/379

  • 8/3/2019 Fail Over Test

    75/379

  • 8/3/2019 Fail Over Test

    76/379

  • 8/3/2019 Fail Over Test

    77/379

  • 8/3/2019 Fail Over Test

    78/379

  • 8/3/2019 Fail Over Test

    79/379

  • 8/3/2019 Fail Over Test

    80/379

  • 8/3/2019 Fail Over Test

    81/379

  • 8/3/2019 Fail Over Test

    82/379

  • 8/3/2019 Fail Over Test

    83/379

  • 8/3/2019 Fail Over Test

    84/379

  • 8/3/2019 Fail Over Test

    85/379

  • 8/3/2019 Fail Over Test

    86/379

  • 8/3/2019 Fail Over Test

    87/379

  • 8/3/2019 Fail Over Test

    88/379

  • 8/3/2019 Fail Over Test

    89/379

  • 8/3/2019 Fail Over Test

    90/379

  • 8/3/2019 Fail Over Test

    91/379

  • 8/3/2019 Fail Over Test

    92/379

  • 8/3/2019 Fail Over Test

    93/379

  • 8/3/2019 Fail Over Test

    94/379

  • 8/3/2019 Fail Over Test

    95/379

  • 8/3/2019 Fail Over Test

    96/379

  • 8/3/2019 Fail Over Test

    97/379

  • 8/3/2019 Fail Over Test

    98/379

  • 8/3/2019 Fail Over Test

    99/379

  • 8/3/2019 Fail Over Test

    100/379

  • 8/3/2019 Fail Over Test

    101/379

  • 8/3/2019 Fail Over Test

    102/379

  • 8/3/2019 Fail Over Test

    103/379

  • 8/3/2019 Fail Over Test

    104/379

  • 8/3/2019 Fail Over Test

    105/379

  • 8/3/2019 Fail Over Test

    106/379

  • 8/3/2019 Fail Over Test

    107/379

  • 8/3/2019 Fail Over Test

    108/379

  • 8/3/2019 Fail Over Test

    109/379

  • 8/3/2019 Fail Over Test

    110/379

  • 8/3/2019 Fail Over Test

    111/379

  • 8/3/2019 Fail Over Test

    112/379

  • 8/3/2019 Fail Over Test

    113/379

  • 8/3/2019 Fail Over Test

    114/379

  • 8/3/2019 Fail Over Test

    115/379

  • 8/3/2019 Fail Over Test

    116/379

  • 8/3/2019 Fail Over Test

    117/379

  • 8/3/2019 Fail Over Test

    118/379

  • 8/3/2019 Fail Over Test

    119/379

  • 8/3/2019 Fail Over Test

    120/379

  • 8/3/2019 Fail Over Test

    121/379

  • 8/3/2019 Fail Over Test

    122/379

  • 8/3/2019 Fail Over Test

    123/379

  • 8/3/2019 Fail Over Test

    124/379

  • 8/3/2019 Fail Over Test

    125/379

  • 8/3/2019 Fail Over Test

    126/379

  • 8/3/2019 Fail Over Test

    127/379

  • 8/3/2019 Fail Over Test

    128/379

  • 8/3/2019 Fail Over Test

    129/379

  • 8/3/2019 Fail Over Test

    130/379

  • 8/3/2019 Fail Over Test

    131/379

  • 8/3/2019 Fail Over Test

    132/379

  • 8/3/2019 Fail Over Test

    133/379

  • 8/3/2019 Fail Over Test

    134/379

  • 8/3/2019 Fail Over Test

    135/379

  • 8/3/2019 Fail Over Test

    136/379

  • 8/3/2019 Fail Over Test

    137/379

  • 8/3/2019 Fail Over Test

    138/379

  • 8/3/2019 Fail Over Test

    139/379

  • 8/3/2019 Fail Over Test

    140/379

  • 8/3/2019 Fail Over Test

    141/379

  • 8/3/2019 Fail Over Test

    142/379

  • 8/3/2019 Fail Over Test

    143/379

  • 8/3/2019 Fail Over Test

    144/379

  • 8/3/2019 Fail Over Test

    145/379

  • 8/3/2019 Fail Over Test

    146/379

  • 8/3/2019 Fail Over Test

    147/379

  • 8/3/2019 Fail Over Test

    148/379

  • 8/3/2019 Fail Over Test

    149/379

  • 8/3/2019 Fail Over Test

    150/379

  • 8/3/2019 Fail Over Test

    151/379

  • 8/3/2019 Fail Over Test

    152/379

  • 8/3/2019 Fail Over Test

    153/379

  • 8/3/2019 Fail Over Test

    154/379

  • 8/3/2019 Fail Over Test

    155/379

  • 8/3/2019 Fail Over Test

    156/379

  • 8/3/2019 Fail Over Test

    157/379

  • 8/3/2019 Fail Over Test

    158/379

  • 8/3/2019 Fail Over Test

    159/379

  • 8/3/2019 Fail Over Test

    160/379

  • 8/3/2019 Fail Over Test

    161/379

  • 8/3/2019 Fail Over Test

    162/379

  • 8/3/2019 Fail Over Test

    163/379

  • 8/3/2019 Fail Over Test

    164/379

  • 8/3/2019 Fail Over Test

    165/379

  • 8/3/2019 Fail Over Test

    166/379

  • 8/3/2019 Fail Over Test

    167/379

  • 8/3/2019 Fail Over Test

    168/379

  • 8/3/2019 Fail Over Test

    169/379

  • 8/3/2019 Fail Over Test

    170/379

  • 8/3/2019 Fail Over Test

    171/379

  • 8/3/2019 Fail Over Test

    172/379

  • 8/3/2019 Fail Over Test

    173/379

  • 8/3/2019 Fail Over Test

    174/379

  • 8/3/2019 Fail Over Test

    175/379

  • 8/3/2019 Fail Over Test

    176/379

  • 8/3/2019 Fail Over Test

    177/379

  • 8/3/2019 Fail Over Test

    178/379

  • 8/3/2019 Fail Over Test

    179/379

  • 8/3/2019 Fail Over Test

    180/379

  • 8/3/2019 Fail Over Test

    181/379

  • 8/3/2019 Fail Over Test

    182/379

  • 8/3/2019 Fail Over Test

    183/379

  • 8/3/2019 Fail Over Test

    184/379

  • 8/3/2019 Fail Over Test

    185/379

  • 8/3/2019 Fail Over Test

    186/379

  • 8/3/2019 Fail Over Test

    187/379

  • 8/3/2019 Fail Over Test

    188/379

  • 8/3/2019 Fail Over Test

    189/379

  • 8/3/2019 Fail Over Test

    190/379

  • 8/3/2019 Fail Over Test

    191/379

  • 8/3/2019 Fail Over Test

    192/379

  • 8/3/2019 Fail Over Test

    193/379

  • 8/3/2019 Fail Over Test

    194/379

  • 8/3/2019 Fail Over Test

    195/379

  • 8/3/2019 Fail Over Test

    196/379

  • 8/3/2019 Fail Over Test

    197/379

  • 8/3/2019 Fail Over Test

    198/379

  • 8/3/2019 Fail Over Test

    199/379

  • 8/3/2019 Fail Over Test

    200/379

  • 8/3/2019 Fail Over Test

    201/379

  • 8/3/2019 Fail Over Test

    202/379

  • 8/3/2019 Fail Over Test

    203/379

  • 8/3/2019 Fail Over Test

    204/379

  • 8/3/2019 Fail Over Test

    205/379

  • 8/3/2019 Fail Over Test

    206/379

  • 8/3/2019 Fail Over Test

    207/379

  • 8/3/2019 Fail Over Test

    208/379

  • 8/3/2019 Fail Over Test

    209/379

  • 8/3/2019 Fail Over Test

    210/379

  • 8/3/2019 Fail Over Test

    211/379

  • 8/3/2019 Fail Over Test

    212/379

  • 8/3/2019 Fail Over Test

    213/379

  • 8/3/2019 Fail Over Test

    214/379

  • 8/3/2019 Fail Over Test

    215/379

  • 8/3/2019 Fail Over Test

    216/379

  • 8/3/2019 Fail Over Test

    217/379

  • 8/3/2019 Fail Over Test

    218/379

  • 8/3/2019 Fail Over Test

    219/379

  • 8/3/2019 Fail Over Test

    220/379

  • 8/3/2019 Fail Over Test

    221/379

  • 8/3/2019 Fail Over Test

    222/379

  • 8/3/2019 Fail Over Test

    223/379

  • 8/3/2019 Fail Over Test

    224/379

  • 8/3/2019 Fail Over Test

    225/379

  • 8/3/2019 Fail Over Test

    226/379

  • 8/3/2019 Fail Over Test

    227/379

  • 8/3/2019 Fail Over Test

    228/379

  • 8/3/2019 Fail Over Test

    229/379

  • 8/3/2019 Fail Over Test

    230/379

  • 8/3/2019 Fail Over Test

    231/379

  • 8/3/2019 Fail Over Test

    232/379

  • 8/3/2019 Fail Over Test

    233/379

  • 8/3/2019 Fail Over Test

    234/379

  • 8/3/2019 Fail Over Test

    235/379

  • 8/3/2019 Fail Over Test

    236/379

  • 8/3/2019 Fail Over Test

    237/379

  • 8/3/2019 Fail Over Test

    238/379

  • 8/3/2019 Fail Over Test

    239/379

  • 8/3/2019 Fail Over Test

    240/379

  • 8/3/2019 Fail Over Test

    241/379

  • 8/3/2019 Fail Over Test

    242/379

  • 8/3/2019 Fail Over Test

    243/379

  • 8/3/2019 Fail Over Test

    244/379

  • 8/3/2019 Fail Over Test

    245/379

  • 8/3/2019 Fail Over Test

    246/379

  • 8/3/2019 Fail Over Test

    247/379

  • 8/3/2019 Fail Over Test

    248/379

  • 8/3/2019 Fail Over Test

    249/379

  • 8/3/2019 Fail Over Test

    250/379

  • 8/3/2019 Fail Over Test

    251/379

  • 8/3/2019 Fail Over Test

    252/379

  • 8/3/2019 Fail Over Test

    253/379

  • 8/3/2019 Fail Over Test

    254/379

  • 8/3/2019 Fail Over Test

    255/379

  • 8/3/2019 Fail Over Test

    256/379

  • 8/3/2019 Fail Over Test

    257/379

  • 8/3/2019 Fail Over Test

    258/379

  • 8/3/2019 Fail Over Test

    259/379

  • 8/3/2019 Fail Over Test

    260/379

  • 8/3/2019 Fail Over Test

    261/379

  • 8/3/2019 Fail Over Test

    262/379

  • 8/3/2019 Fail Over Test

    263/379

  • 8/3/2019 Fail Over Test

    264/379

  • 8/3/2019 Fail Over Test

    265/379

  • 8/3/2019 Fail Over Test

    266/379

  • 8/3/2019 Fail Over Test

    267/379

  • 8/3/2019 Fail Over Test

    268/379

  • 8/3/2019 Fail Over Test

    269/379

  • 8/3/2019 Fail Over Test

    270/379

  • 8/3/2019 Fail Over Test

    271/379

  • 8/3/2019 Fail Over Test

    272/379

  • 8/3/2019 Fail Over Test

    273/379

  • 8/3/2019 Fail Over Test

    274/379

  • 8/3/2019 Fail Over Test

    275/379

  • 8/3/2019 Fail Over Test

    276/379

  • 8/3/2019 Fail Over Test

    277/379

  • 8/3/2019 Fail Over Test

    278/379

  • 8/3/2019 Fail Over Test

    279/379

  • 8/3/2019 Fail Over Test

    280/379

  • 8/3/2019 Fail Over Test

    281/379

  • 8/3/2019 Fail Over Test

    282/379

  • 8/3/2019 Fail Over Test

    283/379

  • 8/3/2019 Fail Over Test

    284/379

  • 8/3/2019 Fail Over Test

    285/379

  • 8/3/2019 Fail Over Test

    286/379

  • 8/3/2019 Fail Over Test

    287/379

  • 8/3/2019 Fail Over Test

    288/379

  • 8/3/2019 Fail Over Test

    289/379

  • 8/3/2019 Fail Over Test

    290/379

  • 8/3/2019 Fail Over Test

    291/379

  • 8/3/2019 Fail Over Test

    292/379

  • 8/3/2019 Fail Over Test

    293/379

  • 8/3/2019 Fail Over Test

    294/379

  • 8/3/2019 Fail Over Test

    295/379

  • 8/3/2019 Fail Over Test

    296/379

  • 8/3/2019 Fail Over Test

    297/379

  • 8/3/2019 Fail Over Test

    298/379

  • 8/3/2019 Fail Over Test

    299/379

  • 8/3/2019 Fail Over Test

    300/379

  • 8/3/2019 Fail Over Test

    301/379

    Guidelines

    Pre-implementation check

    Make sure that, are able to login to OS level and cluster level

    Pre-requisites1. Get the confirmation from the unix team before

    implementation, that every thing fine to implement

    Check-

    If some detail is missing or not all results are showing,

    If Pre-implementation r

    Pre-implemen

    -Pre-im

    -Pre

  • 8/3/2019 Fail Over Test

    302/379

  • 8/3/2019 Fail Over Test

    303/379

  • 8/3/2019 Fail Over Test

    304/379

  • 8/3/2019 Fail Over Test

    305/379

  • 8/3/2019 Fail Over Test

    306/379

  • 8/3/2019 Fail Over Test

    307/379

  • 8/3/2019 Fail Over Test

    308/379

  • 8/3/2019 Fail Over Test

    309/379

  • 8/3/2019 Fail Over Test

    310/379

  • 8/3/2019 Fail Over Test

    311/379

    Checked by

    Verified By

    Point Go\No Go decission

    our change ticket will not pass validation & you will not gain approval for this

    change

    Comments

    eceives a no go do not proceed further

    This tab must list all non-intrusive checks that must be performed before the

    Implementation activity is started - i.e.

    a) Confirm any testing that was not finished when the RFC template was finalisedhas been successfully completed

    b) Confirm all hardware, CDs, cables, external resources etc are in place and

    working

    c) Confirm site access is available

    d) Check that the RFC is fully approved and scheduled

    e) Check that all pre-Implementation Comms have been issued and no

    outstanding concerns have been raised

    f For com lex chan es check all teams are available and read

    tation checks & Pre-requisites

    plementation checks/steps

    Comments

    -requisites checks/steps

    Praveen Pothula

    Srinivas kalluri

  • 8/3/2019 Fail Over Test

    312/379

  • 8/3/2019 Fail Over Test

    313/379

  • 8/3/2019 Fail Over Test

    314/379

  • 8/3/2019 Fail Over Test

    315/379

  • 8/3/2019 Fail Over Test

    316/379

  • 8/3/2019 Fail Over Test

    317/379

  • 8/3/2019 Fail Over Test

    318/379

  • 8/3/2019 Fail Over Test

    319/379

  • 8/3/2019 Fail Over Test

    320/379

  • 8/3/2019 Fail Over Test

    321/379

  • 8/3/2019 Fail Over Test

    322/379

  • 8/3/2019 Fail Over Test

    323/379

  • 8/3/2019 Fail Over Test

    324/379

  • 8/3/2019 Fail Over Test

    325/379

  • 8/3/2019 Fail Over Test

    326/379

  • 8/3/2019 Fail Over Test

    327/379

  • 8/3/2019 Fail Over Test

    328/379

  • 8/3/2019 Fail Over Test

    329/379

  • 8/3/2019 Fail Over Test

    330/379

  • 8/3/2019 Fail Over Test

    331/379

  • 8/3/2019 Fail Over Test

    332/379

    Guidelines

    Description

    Check tabs 2 and 3 have been completed

    Description

    Stop the batch jobs using Btctrns1 report

    Logon to CI Os level

    Login to Verital cluster in operating system level

    Bring the system online to other node

    Check, whether all the services are shifted or not

    Login to the Sap system and check,able to login SAP or not through the gui

    Switch back to the original node

    Execute the btctrns2

    TIME ZONE

    If above

  • 8/3/2019 Fail Over Test

    333/379

    System outage details

    Description

    For Trouble Shooting Ongoing Support will be pro

    If above receives a no go do n

    Implement

    If above receives a no go

  • 8/3/2019 Fail Over Test

    334/379

  • 8/3/2019 Fail Over Test

    335/379

    10-Dec-11 8:30 AM IST 11:30 AM IST3 hours praveen

    pothula

    Date Start Time End Time Duration

    [Minutes]

    Owner Contacts

    See contact

    list

    ONGOING SUPPORT

    heck-Point Go\No Go decision

    ided during change window, please dial into the Telecom Bridge in order to arrange proble

    heck-Point Go\No Go decision

    t proceed further and invoke Backout plan detailed on Tab 5

    tion tests & Post Implementation results

    do not proceed further and request further information

  • 8/3/2019 Fail Over Test

    336/379

    Comment Telecom

    Bridge

    Comment Telecom

    Bridge

    lan 1st step

    ange

    a result in GMT bein

    eir tasks.

    vide details including the

    vided in this tab

    e RFC Change Window

    e provided or

    es, once per server>

    t gain approval

  • 8/3/2019 Fail Over Test

    337/379

    Comment Telecom

    Bridge

    solving.

  • 8/3/2019 Fail Over Test

    338/379

    Start Time

    Date Start Time

    Logon to CI Os level10-Dec-11 12:30 PM IST

    Login to Verital cluster in operating system level10-Dec-11

    1:00 PM IST

    Bring back the system to original node

    10-Dec-11

    3:00 PM IST

    Date Start

    Time

    End Time

    Implementation

    time

    This plan needs to document the timing at which the Remediation Plan should be invok

    The plan also needs to include who can authorise the implementation of the remediatio

    Remediation Tasks (Describe type and tasks involved, break down into logical steps useReference any external documentation already completed.

    Include any system dependencies etc.

    If external resources required add check points by their tasks.

  • 8/3/2019 Fail Over Test

    339/379

  • 8/3/2019 Fail Over Test

    340/379

    Post App Remediation

    Testing Testing Point

    End Time Duration

    [Minutes]

    Owner Contacts Comment

    1:00 PM IST :30 MinPraveen

    Pothula

    3:00 PM IST 2 hours Praveen

    Pothula

    3:30 PM IST :30 Min

    Praveen

    Pothula

    Duration

    Minutes

    Owner Contacts Comment Telecom

    Brid e

    d i.e. at what stage is the Change implementation considered unsuccessful.

    plan.

    1 row per step)

  • 8/3/2019 Fail Over Test

    341/379

  • 8/3/2019 Fail Over Test

    342/379

    Change

    End

    Telecom

    Bridge2. Ensure your Remediation plan

    addresses all of the possibilities

    identified above.3. Provide steps in detail for

    implementing the plan.4. Estimate t e ina reme iation point

    - the lastest time that a Remediation

    plan can be started and service stilled

    returned to the users within the

    Change Window.implemenation of the Remediation6. What tests will be carried out to

    ensure the remediation has been

    successful?

  • 8/3/2019 Fail Over Test

    343/379

    Guidelines

    Description1. Perform the sanity checks

    Post

    If some detail is missing or not all re

    validation & you w

    Post

  • 8/3/2019 Fail Over Test

    344/379

  • 8/3/2019 Fail Over Test

    345/379

  • 8/3/2019 Fail Over Test

    346/379

  • 8/3/2019 Fail Over Test

    347/379

  • 8/3/2019 Fail Over Test

    348/379

  • 8/3/2019 Fail Over Test

    349/379

  • 8/3/2019 Fail Over Test

    350/379

  • 8/3/2019 Fail Over Test

    351/379

  • 8/3/2019 Fail Over Test

    352/379

  • 8/3/2019 Fail Over Test

    353/379

    Owner Post Implementation Status Comment

    Praveen Pothula

    Implementation Steps

    ults are showing, your change ticket will not pass

    ill not gain approval for this change

    Implementation Steps

    This tab must list all the post-testing (note included as part of the

    Implementation/Remediation checks/tests) or steps to be performed after

    implementing in production include application and infrastructure (whereapplicable), with results, and should include links to the necessary documents that

    show how this post testing or steps will be done and expected results.

    After every change remember to update the CMDB, if required, as appropriate for

    the activities carried out durin the chan e - other exam les rovided delete if

  • 8/3/2019 Fail Over Test

    354/379

  • 8/3/2019 Fail Over Test

    355/379

  • 8/3/2019 Fail Over Test

    356/379

  • 8/3/2019 Fail Over Test

    357/379

  • 8/3/2019 Fail Over Test

    358/379

  • 8/3/2019 Fail Over Test

    359/379

  • 8/3/2019 Fail Over Test

    360/379

  • 8/3/2019 Fail Over Test

    361/379

  • 8/3/2019 Fail Over Test

    362/379

  • 8/3/2019 Fail Over Test

    363/379

  • 8/3/2019 Fail Over Test

    364/379

  • 8/3/2019 Fail Over Test

    365/379

  • 8/3/2019 Fail Over Test

    366/379

  • 8/3/2019 Fail Over Test

    367/379

  • 8/3/2019 Fail Over Test

    368/379

  • 8/3/2019 Fail Over Test

    369/379

  • 8/3/2019 Fail Over Test

    370/379

  • 8/3/2019 Fail Over Test

    371/379

  • 8/3/2019 Fail Over Test

    372/379

  • 8/3/2019 Fail Over Test

    373/379

  • 8/3/2019 Fail Over Test

    374/379

    Guidelines

    Date Time Owner

    1-Dec-11 11:00:00 AM ISTPraveen

    Pothula

    Date Time Owner

    9-Dec-11 1:00 AM ISTSrinivas

    kalluri

    9-Dec-11 1:00 AM ISTSrinivas

    kalluri

    Date Time Owner

    Imple

    Description

    Infor unix team on this activity and

    ask their support for this activity

    Pre-Impl

    Inform functional team about the

    activity

    Description

    Description

    If some detail is missing or not all results are showing, your chang

    This tab must list the communications plan steps in deep

    include any links to the necessary documents that will facil

    process.

    Reference any external documentation already completedInclude any system or tasks dependencies etc. If external

    The plan should explain what activities will be undertaken

    Who is going to manage the communications

    Who will be communicated to, why and when

    What communications have already been completed as

    Key communication milestones (planning, before, during

    Any dependencies.

    Prior Preparati

    Inform security team for the

    required access

  • 8/3/2019 Fail Over Test

    375/379

    Date Time Owner

    Post Impl

    Description

  • 8/3/2019 Fail Over Test

    376/379

    Comms

    To

    Security

    team

    Comms

    To

    FI team

    and

    Securiety

    team

    Unix team

    Comms

    To

    entation Stage

    Summary of Communications

    mentation StageSummary of Communications

    Summary of Communications

    ticket will not pass validation & you will not gain approval for this change

    etail, use one row for each step,

    litate or be used in the communications

    .resources required add check points by their tasks.

    to deliver the communications including:

    part of the preparation of the change

    and post implementation)

    on and Planning Stage

  • 8/3/2019 Fail Over Test

    377/379

    Comms

    To

    ementation Stage

    Summary of Communications

  • 8/3/2019 Fail Over Test

    378/379

    Is a Conference Bridge Available? As Needed Start Time: Add Details in End Time:

    Bridge Telecom 281-892-7000Participant

    Passcode:5705755

    Role First Name Last Name Organization Work Phone Mobile Phone

    Change Owner Praveen Pothula +91 9663014555

    Change Assignee Bhupesh Chimanlal IBM Basis 080-41956186 +91 9740205513

    Backup Change Assignee Praveen Pothula IBM Basis 080-41956186 09663014555

    Change Implementer Syed Ahmed IBM Basis 080-41956186

    Backup Change Implementer Lingaraj Nadagoudar IBM Basis 080-41956186 09972311330

    Change Coordinator Bhupesh Chimanlal IBM Basis 080-41956186 +91 97402 05513

    Backup Change Coordinator ronald IBM Basis 080-41956186

    Conference Bridge Owner kishore IBM Basis +1 630-836-5582

    Infrastructure Contacts

    Production Basis Llead Bhupesh Chimanlal IBM Basis +91 80 4195 6186 +91 97402 05513

    Unix Team Support Dilip Janbhale Unix Team 91-9881476390 91-9881476390

    Application Contacts

    PR9 App Mgr Oswin Fernando BS&S +44 (0) 2031 078341

    Business / Other Contacts

    RRO App Mgr Oswin Frenando B&SS +44 (0) 2031 078341

    PR9 App Mgr Oswin Fernando BS&S +44 (0) 2031 078341

    Infrastructure & Cutover Manager

    RRO App Mgr

    PRO App Mgr

    Infrastructure & Cutover Manager

    Remediation (Backout) Plan Key Decision Makers - if fully documented above it is acceptable to just

    Go/No Go Key Decision Makers - if fully documented above it is acceptable to just include t

    If some detail is missing or not all results are showing, your change ticket will not pass validation

    Contact and Telecom details will be required for all MAJOR changes. For normal changes contact and tele

    Contact and Telecom details

    CommunicationsIf Business and/or Technical Communications are planned these should be documented in Section

    Please list any contacts required as part of the change implementation and remediation

    CH1 O5 - Contact list

    Created on 5/3/2012 9:49 PM

  • 8/3/2019 Fail Over Test

    379/379

    V1.8 Dave Ray

    V1.9

    Kay

    Thomas

    Version

    Number

    Author Approver(s)