FITOUT SPACE-COMPARITIVE STUDY
Sl.# Factors Notes
1 Age of the Building Pretty New Old
As it is a new building relatively, all necessary
documents for statutory processes are available
As-built documents[existing], Existing DEWA
Approved Load Schedule are not be available
and hence affects the satutory procedures
2Electrical-Load
ProvisionPossible availability of additonal load provision No additional Load provision
3 DEWA ProcessesConsidering Above two parameters, DEWA's
Process might be quicker.
Considering Above two parameters, DEWA's
Process might take a more time.
4 Work PermitsUnder Dubai Minicipality and it takes 1-2 Week
to get work permit
Under Dubai Minicipality and it takes 1-2
Week to get work permit
5 Building NOC 7-10 Days 7-10 Days
6 Security Deposit Nil AED 25,000
7 Project Management
As the plan with Awards Building is two
floors[2nd & 3rd], project managing will be
easier than city towers
As the plan with City Towers is three
floors[2nd, 6th & 7th], project management
requires additional overheads than Awards
Building.
Has Cost Implications.
Program Attached for a
typical floor.
INTERIOR FIT OUT & MEP WORKS FOR CH2M HILL OFFICE
Building 1 Building II
![Page 2: Fit Out Space Comparision Report R1](https://reader038.vdocument.in/reader038/viewer/2022100722/577cc9a71a28aba711a44cd1/html5/thumbnails/2.jpg)
FITOUT SPACE-COMPARITIVE STUDY
Sl.# Factors Notes
INTERIOR FIT OUT & MEP WORKS FOR CH2M HILL OFFICE
Building 1 Building II
8 Fit out Duration 100-125 Days 150-175 Days Approximate Only
9 Cost Per Sqft 168 180 Approximate Only
10Work time
Restrictions
Normal Work Time possible & extended work
hours possible on request.
Has worktime restriction, such as only night
shifts possible, material logistics contraints
and lift access issues etc.,
Has Cost & Time Implications
11 Clear Work Frond
As the space is shell & core and has clear works
space, the site activities can be kick-started &
accelerated easily.
As it requires demolition, dismantling Cartway
activities, which takes some time to clear the
area to fit-out
12 Fit Factor
Flexible for space planning as it has a larger
area per floor [20,000 Sqft] than City
towers[11,000-14,000 Sqft].
Fits fewer workstations as it has a smaller
perfloor area than Awards Building [11,000-
14,000 Sqft].
13 Services IntegrityIntegrating of Services with Building's existing
system can be done at ease.
As the building is old, there will be issues
related to the integration of service to the
Building utility system
14 Natural Light
As the building is east facing, it is exposed to
more natural light, which can reduce the energy
cost and contribute to LEED ratings [If a
planned]
Relatively lesser exposure to natural light.
15 AccousticsExposed to lesser external noise , compared to
City Tower.
Exposed to higher external noise level due to
the presence of SZR Traffic and hence
requires more accoustical insulations all
around.
![Page 3: Fit Out Space Comparision Report R1](https://reader038.vdocument.in/reader038/viewer/2022100722/577cc9a71a28aba711a44cd1/html5/thumbnails/3.jpg)
5
10
15
20
25
30
35
40