• CONDUCT A DETAILED PROGRAM ANALYSIS, AS IT RELATES TO DPI REQUIREMENTS & SPECIALIZED HAWLEY PROGRAM
• CREATE CONCEPT DESIGN APPROACH WITH “ADD ALTERNATES”
• PROVIDE PRELIMINARY “OPINION OF PROBABLE COST”
• PROVIDE A SCHEDULE FOR DESIGN AND CONSTRUCTION
PURPOSE OF CONCEPT DESIGN STUDY
A38,316 SF
B14,407 SF
19652005 RENOVATED
2005
1962 C10,241 SF
1965
1991
1991 A1
C D30,102 SF
EXISTING FLOOR PLAN
2005RENOVATED
D
PROPOSED AREAS FOR DEMOLITION
A38,316 SF
B14,407 SF
19652005 RENOVATED
2005
1962 C10,241 SF
1965
1991
1991 A1
C D30,102 SF
2005RENOVATED
D
EXISTING CONDITIONS – BUILDING B
NO AIR CONDITIONING IN GYM
STAGE UNDERSIZED AND NOT UTILIZED
PLUMBING ISSUES
EXISTING CONDITIONS – BUILDING B
FLOOR NEEDS REFINISHING WALLS NEED REPAINTING CEILING NEEDS REPAIR & PAINT
CAFETERIA IS IN GOOD CONDITION – BUILT IN 2005EXTERIOR OF BLDG “D” IN GOOD CONDITION
EXISTING CONDITIONS – BUILDING D
CLASSROOM WING RENOVATED IN 2005 – CENTRAL AIR CONDITIONING AND MINOR RENOVATIONS NEEDED
EXISTING CONDITIONS – BUILDING D
LEGEND
PROPOSED TEMPORARY CLASSROOMS
PROPOSED BUILDINGS TO BE DEMOLISHED
PROPOSED DESIGN APPROACH
4 LEASED MODULAR UNITS- IF STUDENTS REMAIN ON CAMPUS
PROPOSED DESIGN APPROACH OPTIONS
BASE DESIGN - LOW SLOPE ROOF CONCEPT
• ADD ALTERNATE A – SLOPING METAL ROOF
• ADD ALTERNATE B – NEW ENTRY APPROACH
• ADD ALTERNATE C – NEW AUDITORIUM
BASE DESIGN - SITE PLAN
EXISTINGCLASSROOMS
ADMIN
EXISTINGGYM
EXISTING DROP-OFF
MEDIA
COURTYARD
NEW PARKING
EXIS
TIN
G
PAR
KIN
G
MULTI-PURPOSE
EXISTINGCAFETERIA
MAINENTRANCE
6th GRADE 7th GRADEFINEARTS
BASE DESIGN - FLOOR PLAN
LEGENDADMIN
CIRCULATION
CLASSROOMS
MUSIC/ART
RESTROOMS
SUPPORT SERVICES
EXISTING8TH GRADE
MAINENTRY
6th GRADE 7th GRADE
ADMIN
ART
MUSIC
EXISTING GYM
MEDIA
EXISTING LOCKER ROOMS
EXISTING MULTI-PURPOSE
EXISTINGCAFETERIA
ASSUMPTIONS PRELIMINARY COST ESTIMATE BASE DESIGN
• ASSUMES BIDDING THE PROJECT SPRING 2021
• ADDITIONAL INFLATION/ESCALATION SHOULD BE CALCULATED3-5% PER YEAR BEYOND SPRING 2021
• RENOVATION COSTS INCLUDED FOR GYMNASIUM AND 8TH
GRADE BUILDING
• DISCUSS TEMPORARY HOUSING OPTIONS FOR STUDENT FOR ONE YEAR
PRELIMINARY COST ESTIMATE BASE DESIGN LOW SLOPE ROOF
CONSTRUCTION COSTS
• DEMOLITION OF EXISTING BUILDINGS $ 675,000
• NEW 64,000 S.F. BUILDING AND SITE WORK $16,640,000
• GYM RENOVATION: ADD AC, PLUMBING REPAIRS,FINISH UPGRADES, STAGE AND LOCKER ROOM RENOVATIONS $ 750,000
• 8th GRADE CLASSROOM BUILDING: ADD AC,MINOR RENOVATIONS $ 875,000
ESTIMATED CONSTRUCTION COST $18,940,000
PRELIMINARY COST ESTIMATE BASE DESIGN LOW SLOPE ROOF
ANCILLARY COSTS
• PROFESSIONAL SERVICES (DESIGN, GEO-TECH,SURVEYING, TESTING DURING CONSTRUCTION) $ 1,500,000
• NEW FURNITURE AND FIXTURES $ 560,000
• CONSTRUCTION CONTINGENCY (5%) $ 947,000
TOTAL ANCILLARY COSTS $ 3,007,000
TOTAL CONSTRUCTION COST $18,940,000
ESTIMATED PROJECT COST $21,947,000
TEMPORARY HOUSING OF STUDENTS
• TEMPORARY CLASSROOM RENTAL –4 LARGE MODULAR BUILDINGS $ 407,000
• TEMPORARY CLASSROOM SET-UP CONTRACTDELIVERY/RETURN $ 970,000
• TEMPORARY CANOPIES AND SIDEWALKS, UTILITIESTO TEMP CLASROOMS AND REMAINING BUILDINGS $ 188,000
TOTAL ESTIMATED COST $1,565,000
OTHER OPTIONS FOR TEMPORARY HOUSING FOR ONE SCHOOL YEAR?
PRELIMINARY COST ESTIMATE ALTERNATE A SLOPED STANDING SEAM METAL ROOF
• SLOPED, STANDING SEAM METAL ROOF $ 2,248,422
(INCLUDES ADDITIONAL ROOFING COST,EXTENDED STEEL STRUCTURE AND GABLE END WALLS,FASCIA AND SOFFIT)
ADD ALTERNATE B & C – SITE PLAN
6th GRADE 7th GRADE
EXISTINGCLASSROOMS
ADMIN
EXISTINGGYM
EXISTING DROP-OFF
MEDIA
COURTYARD
MULTI-PURPOSE
PARENT DROP-OFF
EXISTINGCAFETERIA
ADD ALT. BNEW
ENTRANCE
ADD ALT. CAUDITORIUM
LEGENDADMIN
CIRCULATION
CLASSROOMS
MUSIC/ART
RESTROOMS
SUPPORT SERVICES
6th GRADE 7th GRADE
ADMIN
ART
MUSICMEDIA
AUDITORIUM
ADD ALTERNATE B & C – FLOOR PLAN
EXISTING8TH GRADE
EXISTINGCAFETERIA
AUDITORIUM /GYM ENTRANCE
MAINENTRANCE
EXISTING GYM
EXISTING LOCKER ROOMS
EXISTING MULTI-PURPOSE
PRELIMINARY COST ESTIMATE ADD ALTERNATE B NEW ENTRANCE
• ADDITIONAL SITE COSTS $ 125,000
(TRAFFIC TURN AROUND, VISITOR ANDHANDICAP PARKING SPACES)
NEW TURN-AROUND
PRELIMINARY COST ESTIMATE ADD ALTERNATE C NEW AUDITORIUM
• CONSTRUCTION COSTSNEW 350 SEAT AUDITORIUM $ 3,200,000
• ADDITIONAL ANCILLARY COSTS(CONTINGENCY, PROFESSIONAL SERVICES, FFE) $ 400,000
ESTIMATED TOTAL COST AUDITORIUM $ 3,600,000
DESIGN AND CONSTRUCTION SCHEDULE - DURATIONS
• DESIGN DOCUMENTS 9 MONTHS
• APPROVALS AND BIDDING 4 MONTHS
• CONSTRUCTION 13 MONTHS
TOTAL PROJECT DURATION 26 MONTHS