ADCO Constructions Pty Limited A.B.N. 46 001 044 39123 Graham Street Milton QLD 4064 • PO Box 1167 Milton QLD 4064
Tel: (07) 3511 5555 • Fax: (07) 3511 5500 • [email protected] • www.adcoconstruct.com.au
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
Gladstone Entertainment Centre
and Office Development
Construction Report No. 8
April 2013
Copies: 2 copies - Gladstone Port Corporation 1 copy - John Outhwaite & Associates 1 copy - ADCO
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
Contents
1. Executive Summary
2. Programme 2.1 Milestones 2.2 Potential Delays 2.3 Current Status
3. Approvals / Inspections 3.1 Certifier 3.2 Consultants 3.3 QFRS 3.4 Authorities 3.5 Client Approvals
4. Site Management 4.1 Safety 4.2 Industrial Relations 4.3 Environment 4.4 Quality
5. Variations 5.1 Variations Requiring Immediate Advice
6. Risk Management
7. Completion 7.1 Authorities 7.2 Certifier 7.3 Warranties, As-Builts 7.4 Defects
8. Appendices • Variation Register • Local Participation - Opportunities Presented • Delay / Extension of Time Register • Photographs
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
1. Executive Summary
Project A
Project A is proceeding well with the final suspended slabs being poured within the month. Ergon has advised that their anticipated commencement date for the transformer installation is 20 May 2013. Services rough-in to the lower carpark levels is continuing with the main switchboards installed ready for commissioning with the Ergon Transformers. The fabrication of the structural steel is complete with an anticipated commencement date of 27 May 2013 for the erection on site. The setout and bracket installation has commenced for the L1 – L5 carpark screens. Lift installation is due to commence mid-May for lifts 1-3. Work is also scheduled to commence on the in-ground stormwater retention tank in the Yarroon Street Laneway.
Project B
Structural steel has commenced to the main function hall of Project B, with erection well underway. Footings and in-ground services have commenced to the Forecourt/Foyer area, as well as the lower ground holding area/scullery. Ground slabs to this level continue further towards the Oaka Lane frontage with suspended formwork over.
Off-site procurement of major components is also well underway, with items such as the numerous hoists within the facility, kitchen equipment, acoustic ceiling system, operable walls all in manufacture off-site.
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
2. Programme
2.1 Milestones
Milestones reached throughout the March 2013 - April 2013 period include:
Project A
• Completion of level 7 slabs.
• Commencement of concrete columns for roof and plant room steelwork.
• Commencement of stair and lift cores to roof level.
• Services rough in continuing to carpark levels.
• Carpark façade screen setout and installation commenced.
Project B
• Commencement of structural steel to main function rooms.
• Continuation of ground and suspended slabs to Kitchen/holding area zone.
• Commencement of in-ground services and continuation of Forecourt/Plaza retaining works & foundations.
2.2 Potential Delays
• Ergon – installation of new transformers including the disconnection of the existing transformer. This is a critical issue as it affects the construction progress of the Kitchen and Conference Room areas. We are continuing to liaise with Ergon for this work, however we have taken steps to mitigate the delay by re-designing and constructing the footings to the kitchen while the cables are still live to continue construction in this area. We have now been given a date of mid-May for transformer installation, with the subsequent demolition and removal of the existing transformer (by Ergon) yet to be confirmed.
• MSQ fitout – the base building services have been designed to an open plan with the view that the MSQ floor plan and services design will be issued to provide an integrated fit-out. A revised date of mid-May has been given by MSQ to release the fit-out drawings for tender and hence integration into the base building. We were instructed by the Superintendent to place a hold on manufacturing of ductwork to level 7 until we can incorporate the required tenancy layout into the base building works. This remains the case as of the end of the reporting period. All mechanical equipment have been ordered for the project and will need to be reviewed once tender documents are received.
• Water Supply – Gladstone City Council has approved the dual water supply to the site and we are continuing as per the original design intent. Discussions are on-going in relation to Council required water meters and location of water feeds from Council main. An inspection will be organized on site with the Council to review the water supply location and Council requirements.
• Wet weather – wet and windy weather conditions continue to delay the project.
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
2. Programme (cont’d)
2.3 Current Status
Project A
Original Completion Date 24 May 2013EOT’s Claimed 58 daysEOT’s Approved 56.5 daysCurrent Contract Completion Date 2 September 2013Current status against Programme On ProgrammeForecast Completion Date 2 September 2013
Project B
Original Completion Date 28 June 2013EOT’s Claimed 58 daysEOT’s Approved 56.5 daysCurrent Contract Completion Date 2 October 2013Current status against Programme 4 days behind current ProgrammeForecast Completion Date 2 October 2013
ID Task Name Duration Start Finish Predecessors
1 Construction 232.5 daysMon 3/09/12 Wed 2/10/13
2 Site Establishment 11 days Mon 3/09/12 Tue 18/09/12
7 Demolition 20 days Wed 12/09/12 Wed 10/10/12
13 Project A ‐ Car Park & Office 200.5 daysWed 19/09/12 Mon 2/09/13
14 Car Park Strenthening Works 42 days Wed 19/09/12 Tue 20/11/12
15 Ground to Level 1 32 days Wed 19/09/12 Fri 2/11/12
27 Level 1 to Level 2 42 days Wed 19/09/12 Tue 20/11/12
34 New Structure 103.5 daysWed 21/11/12 Wed 12/06/13
35 Level 3 18 days Wed 21/11/12 Wed 19/12/12
47 Level 4 82.5 days Tue 11/12/12 Wed 29/05/13
60 Level 5 17 days Tue 15/01/13 Mon 25/02/13
72 Level 6 17 days Mon 18/02/13 Wed 20/03/13
83 Level 7 17 days Thu 14/03/13 Mon 15/04/13
94 Roof 42.5 days Mon 8/04/13 Wed 12/06/13
95 FRP Stair Core Walls & Roof at Pour A 6 days Mon 8/04/13 Tue 16/04/13 88
96 FRP Stair / Lift Walls & Roofs at Pour B 8 days Mon 15/04/13 Fri 26/04/13 95SS+4 days,91
97 Erect Structural Steel Roof Frame Incl.Plant Room
15 days Tue 21/05/13 Wed 12/06/13 91,96
98 Scaffold, Hoists & Cranes 165 days Tue 9/10/12 Wed 31/07/13
107 Roofing 15 days Thu 13/06/13 Thu 4/07/13
111 Facades 47 days Tue 21/05/13 Wed 31/07/13
112 Car Park Screens Ground to Level 5 47 days Tue 21/05/13 Wed 31/07/13
113 Office Glazing/ Sun Shades Level 6 & 7 20 days Thu 13/06/13 Thu 11/07/13 97
114 Services & Finishes 101 days Sat 30/03/13 Mon 2/09/13
115 Car Park Levels 81 days Sat 30/03/13 Fri 2/08/13
116 Replace Existing Services at Ground andLevel 1
20 days Sat 30/03/13 Wed 1/05/13 65
117 Services & Finishes Ground 15 days Tue 4/06/13 Tue 25/06/13 116SS+10 days
118 Services & Finishes Level 1 10 days Fri 7/06/13 Fri 21/06/13 117SS+3 days
119 Services & Finishes Level 2 20 days Wed 12/06/13 Wed 10/07/13 117SS+5 days
120 Services & Finishes Level 3 20 days Wed 19/06/13 Wed 17/07/13 119SS+5 days,80
121 Services & Finishes Level 4 20 days Thu 27/06/13 Thu 25/07/13 120SS+6 days
122 Services & Finishes to Link at L4 15 days Thu 27/06/13 Thu 18/07/13 121SS,59
123 Services & Finishes Level 5 20 days Fri 5/07/13 Fri 2/08/13 121SS+5 days
124 Office Tower Levels 45 days Thu 13/06/13 Fri 16/08/13
125 Services & Finishes Level 6 (Base Build) 35 days Thu 13/06/13 Fri 2/08/13 97,113FF
126 Services & Finishes Level 7 (Base Build) 35 days Thu 27/06/13 Fri 16/08/13 125SS+5 days,108
127 Lift Installation 51 days Mon 13/05/13 Thu 25/07/13
128 Clear Lift Shaft 6 days Mon 13/05/13 Mon 20/05/13
129 Lift Installation & Commission 45 days Tue 21/05/13 Thu 25/07/13 128
130 Lifts Available for Car Park Levels 0 days Thu 25/07/13 Thu 25/07/13 129
131 Roof 40 days Thu 13/06/13 Fri 9/08/13
132 Load Out Roof Plant 2 days Thu 13/06/13 Fri 14/06/13 97
133 Plant Room Enclosure & Louvres 5 days Thu 27/06/13 Thu 4/07/13 110SS
C
Site Establishment
Demolition
Project A ‐ Car Park & Office
Car Park Strenthening Works
Ground to Level 1
Level 1 to Level 2
New Structure
Level 3
Level 4
Level 5
Level 6
Level 7
Roof
FRP Stair Core Walls & Roof at Pour A
FRP Stair / Lift Walls & Roofs at Pour B
Erect Structural Steel Roof Frame Incl. Plant Room
Scaffold, Hoists & Cranes
Roofing
Facades
Car Park Screens Ground to Level 5
Office Glazing/ Sun Shades Level 6 & 7
Services & Finishes
Car Park Levels
Replace Existing Services at Ground and Level 1
Services & Finishes Ground
Services & Finishes Level 1
Services & Finishes Level 2
Services & Finishes Level 3
Services & Finishes Level 4
Services & Finishes to Link at L4
Services & Finishes Level 5
Office Tower Levels
Services & Finishes Level 6 (Base Build)
Services & Finishes Level 7 (Base Build)
Lift Installation
Clear Lift Shaft
Lift Installation & Commission
25/07
Roof
Load Out Roof Plant
Plant Room Enclosure & Louvres
1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 1 4 7 10131619222528 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 2 5 8 11141720232629 2 5eptember 2012 October 2012 November 2012 December 2012 January 2013 February 2013 March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 September 2013 Octob
Task Critical Split Milestone Summary Project Summary External Tasks External Milestone Deadline Progress
GLADSTONE OFFICE & ENTERTAINMENT CENTRE EXPANSION
Page 1 Tue 14/05/13
Project: GLADSTONE OFFICE & ENDate: Tue 14/05/13
ID Task Name Duration Start Finish Predecessors
134 Plant Fit‐off & Pre‐Commissioining 30 days Thu 27/06/13 Fri 9/08/13 133SS,132
135 Commissioning 20 days Mon 5/08/13 Mon 2/09/13
136 Commission Building Services 20 days Mon 5/08/13 Mon 2/09/13 134FS‐5 days,126FS‐10
137 Completion 0 days Mon 2/09/13 Mon 2/09/13
138 Completion of Project A 0 days Mon 2/09/13 Mon 2/09/13 136FF
139 Project B ‐ Entertainment Centre 206.5 daysThu 11/10/12 Wed 2/10/13
140 Substructure 166 days Thu 11/10/12 Mon 5/08/13
141 Structure 108.5 daysThu 8/11/12 Wed 5/06/13
142 Facade Panels 33 days Thu 8/11/12 Thu 10/01/13
145 Suspended Level 1 (Leaving Area for CraneAccess)
17 days Fri 16/11/12 Wed 12/12/12
153 Suspended Level 1 (Balance of Area South ofGrid 7cc)
5 days Thu 21/02/13 Fri 1/03/13
157 Suspended Level 1 (Kitchen) 5 days Mon 13/05/13 Fri 17/05/13
158 Erect Formwork (180m2) 2 days Mon 13/05/13 Tue 14/05/13
159 Reo & Services 2 days Wed 15/05/13 Thu 16/05/13 158
160 Concrete Slab 1 day Fri 17/05/13 Fri 17/05/13 159
161 Office Mezzanine Level 10 days Mon 20/05/13 Fri 31/05/13
162 Frame Mezz Incl. Stairs 5 days Mon 20/05/13 Fri 24/05/13
163 Construct Mezz Floor 5 days Mon 27/05/13 Fri 31/05/13 162
164 Roof Structure 20 days Wed 8/05/13 Wed 5/06/13
165 Erect Structural Steel Trusses & Roof Frami15 days Wed 8/05/13 Tue 28/05/13
166 Low Level Framing over Kitchen &Conference Rooms
5 days Wed 29/05/13 Wed 5/06/13 165,160
167 Roofing 20 days Tue 4/06/13 Wed 3/07/13
168 High Level Roofing Over Function Room/ Foyer15 days Tue 4/06/13 Tue 25/06/13 165,184SS+3 days
169 Low Level Roofing Over Kitchen & ConferenceRooms
5 days Wed 26/06/13 Wed 3/07/13 168,166
170 Facades 25 days Tue 2/07/13 Tue 6/08/13
174 Services & Finishes 85 days Wed 29/05/13 Wed 2/10/13
175 Level B + Lower Stage 53 days Fri 21/06/13 Fri 6/09/13
176 Block Walls 8 days Fri 21/06/13 Wed 3/07/13 168
177 Services & Finishes ‐ New Amenities 30 days Fri 28/06/13 Mon 12/08/13 176SS+5 days
178 Builders Work to Plant Areas 10 days Thu 4/07/13 Wed 17/07/13 176
179 Plant Room Installation & Fit‐off 35 days Thu 18/07/13 Fri 6/09/13 176,178
180 Services & Finishes ‐ Lobby, PA Store & Lau45 days Thu 4/07/13 Fri 6/09/13 169,176
181 Services & Finishes ‐ Plant Storage Area 20 days Thu 11/07/13 Thu 8/08/13 180SS+5 days
182 Services & Finishes to Car Parking Area 20 days Thu 11/07/13 Thu 8/08/13 176,181FF
183 Level 1 Incl Mezz. 85 days Wed 29/05/13 Wed 2/10/13
184 Assemble & Erect Ceiling Panels 10 days Wed 29/05/13 Thu 13/06/13 165
185 Upgrade of Existing Areas 60 days Fri 14/06/13 Tue 10/09/13 186SS
186 Services & Finishes 65 days Fri 14/06/13 Tue 17/09/13 163FF+30 days,172FF+
187 Commission Services 20 days Wed 4/09/13 Wed 2/10/13 186FS‐10 days
188 External Works 40 days Wed 8/05/13 Fri 5/07/13
Plant Fit‐off & Pre‐Commissioining
Commissioning
Commission Building Services
2/09
2/09
P
Substructure
Structure
Suspended Level 1 (Kitchen)
Erect Formwork (180m2)
Reo & Services
Concrete Slab
Office Mezzanine Level
Frame Mezz Incl. Stairs
Construct Mezz Floor
Roof Structure
Erect Structural Steel Trusses & Roof Framing
Low Level Framing over Kitchen & Conference Rooms
Roofing
High Level Roofing Over Function Room/ Foyer
Low Level Roofing Over Kitchen & Conference Rooms
Facades
S
Level B + Lower Stage
Block Walls
Services & Finishes ‐ New Amenities
Builders Work to Plant Areas
Plant Room Insta
Services & Finish
Services & Finishes ‐ Plant Storage Area
Services & Finishes to Car Parking Area
L
Assemble & Erect Ceiling Panels
Upgrade of Exi
Services &
C
External Works
1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 1 4 7 10131619222528 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 2 5 8 11141720232629 2 5eptember 2012 October 2012 November 2012 December 2012 January 2013 February 2013 March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 September 2013 Octob
Task Critical Split Milestone Summary Project Summary External Tasks External Milestone Deadline Progress
GLADSTONE OFFICE & ENTERTAINMENT CENTRE EXPANSION
Page 2 Tue 14/05/13
Project: GLADSTONE OFFICE & ENDate: Tue 14/05/13
ID Task Name Duration Start Finish Predecessors
189 Excavation / Install RCP Tank in PedestrianLaneway
20 days Wed 8/05/13 Wed 5/06/13
190 Yarroon Laneway Pavement 20 days Thu 6/06/13 Fri 5/07/13 189
191 Entry Plaza 83.5 days Fri 26/04/13 Fri 30/08/13
192 Substructure 32.5 days Fri 26/04/13 Mon 17/06/13
193 Earthwork /Trim to Levels 5 days Fri 26/04/13 Thu 2/05/13
194 Detailed Excavation / FRP Footings 10 days Tue 14/05/13 Mon 27/05/13 193
195 Inground Services 6.5 days Wed 22/05/13 Thu 30/05/13 194
196 Prep./ FRP Slab on Ground/ Entry Steps 10 days Thu 30/05/13 Mon 17/06/13 195,194
197 Structure 12 days Mon 17/06/13 Thu 4/07/13
198 Blockwork 4 days Mon 17/06/13 Fri 21/06/13 196
199 Entry Structural Steel 8 days Fri 21/06/13 Thu 4/07/13 166,198,144
200 Roofing 29 days Thu 4/07/13 Thu 15/08/13
207 Services & Finishes 23 days Tue 23/07/13 Tue 27/08/13
211 External Works & Landscaping 39 days Thu 4/07/13 Fri 30/08/13
219 Completion 0 days Wed 2/10/13 Wed 2/10/13
220 Completion of Project B 0 days Wed 2/10/13 Wed 2/10/13 187,217,218,210,206,2
Excavation / Install RCP Tank in Pedestrian Laneway
Yarroon Laneway Pavement
Entry Plaza
Substructure
Earthwork /Trim to Levels
Detailed Excavation / FRP Footings
Inground Services
Prep./ FRP Slab on Ground/ Entry Steps
Structure
Blockwork
Entry Structural Steel
Roofing
Services & Finishes
External Works & Landscaping
2
2
1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 1 4 7 10131619222528 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11141720232629 1 4 7 10131619222528 1 4 7 1013161922252831 3 6 9 12151821242730 2 5 8 11141720232629 2 5eptember 2012 October 2012 November 2012 December 2012 January 2013 February 2013 March 2013 April 2013 May 2013 June 2013 July 2013 August 2013 September 2013 Octob
Task Critical Split Milestone Summary Project Summary External Tasks External Milestone Deadline Progress
GLADSTONE OFFICE & ENTERTAINMENT CENTRE EXPANSION
Page 3 Tue 14/05/13
Project: GLADSTONE OFFICE & ENDate: Tue 14/05/13
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
3. Approvals/Inspections
3.1 Certifier
Stage 2 Building Approval was received on 11 February 2013.
3.2 Consultants
Architect
Thomson Adsett have finalised the external finishes and preparing the required documents for submission to Council as part of the DA requirements.
Structural Engineer
OPUS is continuing to complete site inspections as required on site.
Civil/Hydraulics
No issues.
Electrical/Mechanical
No issues.
Acoustic Engineering
No issues..
Landscape Design
No issues.
Commercial Kitchen
No issues.
Green Star
The Round 1 Green Star review has been completed, with further information to be submitted by the design team back to the Green Building Council for the Round 2 review.
3.3 QFRS
No issues.
3.4 Authorities
Gladstone City Council has agreed to provide a dual water supply to the site. Discussions are on-going with
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
3. Approvals/Inspections (cont’d)
the Council in relation to the exact location and costs associated with the water connection from both Oaka Lane and Goondoon Street. ADCO will arrange for a meeting on site to discuss the location of the connection after which time the Council will prepare an estimate of costs to complete the connections. ADCO / Council are continuing discussions regarding the number of required Council meters for the site. The number of meters will be impacted when the tenancy fitout plans are received for Level 7, as the Council require individual Council meters for each tenancy. The design and location of these will be discussed with the team prior to finalising their location.
3.5 Client Approvals
No issues.
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
4. Site Management
4.1 Safety
There are no Workplace Health & Safety issues that have arisen throughout the reporting period.
4.2 Industrial Relations
ADCO closed the site over the Easter period due to RDO’s as requested by the various union bodies, and also closed the site for city-wide industrial action in Gladstone on 17 April 2013. ADCO continues to take a consultative approach with the trade unions to mitigate potential for delays to progress.
4.3 Environment
There are no Environmental issues that have arisen throughout the reporting period.
4.4 Quality
There are no Quality issues that have arisen throughout the reporting period.
4.5 Public Relations
ADCO is continuing to consult with Nicole on a weekly basis in relation to upcoming activities that may impact the neighbours. Nicole and Luke Broadhurst also met with a number of the neighbours to discuss the project and upcoming events.
ADCO Constructions Pty Ltd
23 Graham Street
MILTON QLD 4064
PO Box 1167
MILTON QLD 4064
Tel: (07) 3511 5555
Fax: (07) 3511 5500
A.B.N. 46 001 044 391
ADCO Constructions Pty Ltd
Level 2, 7 – 9 West Street
NORTH SYDNEY NSW 2060
PO Box 1982
NORTH SYDNEY NSW 2059
Tel: (02) 8437 5000
Fax: (02) 8437 5050
A.B.N. 46 001 044 391
ADCO Constructions (VIC) Pty Ltd
455 – 459 Auburn Road
HAWTHORN VIC 3122
PO Box 938
HAWTHORN VIC 3122
Tel: (03) 9832 1400
Fax: (03) 9832 1444
A.B.N. 15 094 531 272
PROJECT EHS MONTHLY REPORT
REPORT FOR THE MONTH OF: April 2013
PROJECT NAME Gladstone Entertainment Centre
LOCATION Goondoon Street, Gladstone
STATE Queensland
Corporate EHS Mgt System/EHS Monthly Report Page 2
INDEX
CONSTRUCTION OVERVIEW ..................................................................................................................... 3
PERSONNEL DATA ..................................................................................................................................... 4
INCIDENT SUMMARY.................................................................................................................................. 5
COMPLIANCE SUMMARY ........................................................................................................................... 5
Corporate EHS Mgt System/EHS Monthly Report Page 3
CONSTRUCTION OVERVIEW
During the past month, the following construction activities occurred on this project site:
Form for suspended slab Level7 of Carpark Tower completed and poured with columns for roof structure underway.
Concrete and formwork continues to be undertaken for the lift shaft and all 3 stairwells at various stages of build. Setting out for Ground Floor Slab and poring of areas of Ground Level of carpark is underway.
Some areas of Ground Level slab completed in Entertainment Centre and some of the block walls laid and core filled.
Air conditioning refurbishment is underway with some of the old unit removal and duct work installation in progress.
Plumbing continues to be installed in Entertainment Centre ground areas. Some fire water mains and water service mains have been installed in carpark.
Electrical work on carpark and Entertainment Centre building is ongoing. Lower Carpark Level conduits are being installed for
permanent lighting and cables have been installed in trays throughout various Levels. Switch Room installation is continuing to progress.
Block layers undertaking construction of walls and core fill.
Entertainment Centre deck has been poured and formwork removed with propping now in place for crane operation on deck for steel work erection for the roof structure.
Scaffold modifications have been undertaken to accommodate the roof structure currently being installed.
A small amount of water proofing and caulking has been undertaken on tilt panels and some backfilling has been completed.
Work has begun with footings and other in ground services in the forecourt area.
Excavating has been underway for the stormwater retention tank for the tower.
Corporate EHS Mgt System/EHS Monthly Report Page 4
PERSONNEL DATA
MONTHLY DATA
WEEK NO. 1 2 3 4 5
TOTAL a) Date range (Monday to
Sunday) 01-07.03.2013 08-14.04.2013 15-21.04.2013 22-28.04.2013 29-30.04.2013
b) No. of days worked 0 6 6 3 2 17
c) No. of Public Holidays 1 0 0 1 0 2
d) No. Inducted each week 0 19 10 3 6 38
e) No. subcontractors on site each week
0 288 283 153 96 820
f) Hours worked each week (e x 8)
0 2,304 2,264 1,224 768 6,560
g) No. ADCO on site each week
0 34 33 18 12 97
h) Hours worked (g x 8) 0 272 264 144 96 776
PROJECT ACCUMULATIVE DATA
Contractor ADCO TOTAL
i) No. Inducted to date (previous month + d) 398 9 407
j) Hours worked to date (sub = previous month +f TOTAL) and
ADCO = previous month +h TOTAL). Place accumulative figure in the TOTAL column.
49,220 6,352 55,572
Corporate EHS Mgt System/EHS Monthly Report Page 5
INCIDENT SUMMARY
OHS INCIDENTS
Type
Nature Mechanism
Fracture Dislocation
or sprain Cut Bruising Burn
Other unspecified
Contact with
equipment
Trip, slip, fall
Manual handling
Electrical Substance Other
unspecified
FATI
MTI
LTI
TOTAL 0 0 0 0 0 0 0 0 0 0 0
FATI - First Aid treatment MTI – Medical treatment LTI – Lost time injury
ENVIRONMENTAL INCIDENTS
Aspect Type
Air quality Water quality
Noise Fauna or
Flora
Cultural or
Heritage
Other non specific
Contamination Damage Spill Complaint Regulatory
breach
0 0 0 0 0 0 0 0 0 0 0
GENERAL INCIDENTS
Services affected Operational impact
Electrical Fire
service Mechanical Gas
Potable water
Stormwater Sewer Security Comms LO NLO NI
0 0 0 0 0 0 0 0 0 0 0 0
LO - Lost operational time NLO – non lost operational NI – Nil impact
COMPLIANCE SUMMARY
Regulatory Authority name
Date issued Type (i.e IN,
PIN) Description of issue
Nil issues
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
5. Variations
5.1 Variations Requiring Immediate Advice
There are no urgent Variations outstanding at this stage.
5.2 Client Variations
ADCO has commenced works on the G.P.C. transformer relocation (outside the head contract agreement) as a direct project to G.P.C.
ADCO has also commenced tendering of the Kullaroo House/Yarroon Street carpark works based on design documentation prepared to date. However, it is unclear whether this will become a head contract variation or a separate G.P.C. project at this stage.
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
6. Risk Management
There are no issues that have arisen throughout the reporting period.
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
7. Completion
7.1 Authorities
• Plumbing inspections are ongoing for both project A & B.
• Hiller & Associates have prepared for submission the Food Safety application. Hiller’s are awaiting G.E.C. input and information prior to finalizing the submission to Council.
7.2 Certifier
There are no completion issues that have arisen throughout the reporting period.
7.3 Warranties, As Builts
There are no completion issues that have arisen throughout the reporting period.
7.4 Defects
There are no completion issues that have arisen throughout the reporting period.
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
8. Appendices
Variation Register
PROJECT VARIATION REGISTER
GLADSTONE ENTERTAINMENT CENTRE
Draft
ADCO
VO #
CLIENT REF
#Variation Claim Description Status Date Submitted Est. cost
Amount
SubmittedAmount Approved Date Approved % Claimed Value Claimed
01 New operable wall layout - increase in block walls Approved 11-Jul-12 $ 0 20-Sep-12 0% $ -
02 Forecourt Retail Tenancy Alterations - Refer to VO 15 Approved 11-Jul-12 $ 0 31-Aug-12 0% $ -
03 Delete burnished slab to Entertainment Centre Approved 19-Sep-12 $ (11,198) 21-Sep-12 100% $ (11,198)
04 Event Management Office - Provision of Approved 11-Jul-12 $ 26,617 24-Aug-12 30% $ 7,985
05 Additional window to south elevation of Entertainment Centre Approved 11-Jul-12 $ 11,840 24-Aug-12 40% $ 4,736
06 Continuous formed basin shelf to M/F Entertainment Centre Amenities Approved 11-Jul-12 $ 3,700 24-Aug-12 0% $ -
07 Conference rooms AC upgrade Approved 11-Jul-12 $ 25,000 24-Aug-12 15% $ 3,750
08 Upgrade to exsting Entertainment Centre slabs to accomodate forklift with 2.5t lifting capacity Approved 05-Sep-12 $ 45,775 12-Sep-12 100% $ 45,775
09 Additional amenities to Level 6 & 7 Approved 10-Jan-13 $ 0 22-Jan-13 0% $ -
10 Structural modifications to VTS Room - Increased slab capacity Submitted 11-Jul-12 $ 18,444 0% $ -
11 Precast panel applied finish savings Approved 17-Jul-12 $ (17,060) 24-Aug-12 0% $ -
12 Acoustic screening to Project B chiller location Approved 13-Mar-13 $ 85,111 28-Mar-13 5% $ 4,256
13 Alternative carpark screening (L1 - L5 adjustment) Approved 09-Jan-13 $ (738,080) 11-Jan-13 0% $ -
14 Alternative office level screening (L6 & L7 adjustment) Approved 09-Jan-13 $ 58,625 14-Jan-13 0% $ -
15 Cafe & Forecourt Extensions & Additions Approved 30-Oct-12 $ 38,937 16-Nov-12 32% $ 12,460
16 Electrical/Gas early works (Ergon & APA Conduits) Approved 01-Aug-12 $ 102,079 12-Sep-12 100% $ 102,079
17 Provisional Sum adjustment - Alterations to adjoin owners fencing for temporary access purposes Approved 12-Nov-12 $ 6,671 16-Nov-12 100% $ 6,671
18Town Planning advice - additional to contract (10 Central Lane Carpark Extension (consultancy costs incurred to
30th October 2012)Draft 26-Nov-12 $ 7,510 100% $ 7,510
19 Town Planning advice - additional to contract (Post DA negotiations on clients behalf) Approved 26-Nov-13 $ 8,058 26-Feb-13 100% $ 8,058
20 Development Approval - additional associated costs outside contract scope Draft $ 80,000 0% $ -
21 Latent Condition - Removal of asbestos identified on existing buildings Approved 09-Jan-13 $ 22,912 11-Jan-13 100% $ 22,912
22Adjustment for reduction in insurance requirements under the General Conditions of Contract (Cost of Policy
Difference)Approved 28-Aug-12 $ (44,136) 21-Sep-12 75% $ (33,102)
23 Credit against tender for OPUS fees paid direct by client Approved 07-Sep-12 $ (30,000) 12-Sep-12 94% $ (28,200)
24 Additional fees associated with Building Certifier in line with client advice received 24.04.12 Approved 07-Sep-12 $ 8,030 21-Sep-12 100% $ 8,030
25 DJ Kebab Amenities Blocks Approved 09-Nov-12 $ 33,803 16-Nov-12 8% $ 2,704
26 Latent Condition - Obstructions encountered during demolition/civil works Approved 05-Feb-13 $ 10,551 26-Feb-13 100% $ 10,551
27 Upgrade of structure to accomodate the MSQ antenna tower Submitted 13-Mar-13 $ 13,255 0% $ -
28 Provision of 100mm communications conduit from ground level G.P.C. Office to tenancies Project A Approved 14-Mar-13 $ 17,512 28-Mar-13 70% $ 12,258
29Additional items in Entertainment Centre as requested by Troy Everitt (Refer to design meeting 08.10.12, see M.
Bedford email dated 19.10.12) - 'G.E.C. Shopping list'Approved 13-Mar-13 $ 32,597 28-Mar-13 36% $ 11,735
30 External Lighting - Provisional Sum adjustment Approved 05-Mar-13 $ 37,677 28-Mar-13 29% $ 10,926
31 Electrical Services - Provisional Sum adjustment Approved 18-Feb-13 $ 461,674 08-Apr-13 0% $ -
32 Ergon Enabling Works & works to Scotties Restaurant/G.P.C.L. Offices sub-mains Approved $ 83,838 05-Feb-13 100% $ 83,838
33Additional costs associated with the requirements of providing a volumetric title ownership structure of the
projectDraft tba 0% $ -
34Costs associated with relocation of GPCL transformer from within their current premises to the corner of Oaka
Lane and Yarroon StDraft $ 80,000 0% $ -
35 Design and approval fees associated with DJ Kebab Amenities block Draft $ 5,000 0% $ -
36 Deletion of painting to carpark soffits Approved 08-Apr-13 $ (70,940) 12-Apr-13 0% $ -
37 Additional sewer manhole as requested by Gladstone Regional Council Draft $ 5,000 0% $ -
38 Local Government/Authority Fees Draft $ 40,000 0% $ -
39 Provision of Security Services to Entertainment Centre (excl from tender allowance) Draft $ 100,000 0% $ -
40 Kitchen/Bar/Scullery - Provisional Sum Adjustment Approved 13-Mar-13 $ 786,858 08-Apr-13 0% $ -
41 Provision of Building Identification signage across Project A & Project B Draft $ 45,000 0% $ -
42 Design fees for Forecourt Cafe (Hiller & Associates) Approved 13-Mar-13 $ 3,850 15-Mar-13 100% $ 3,850
43 Supply & install CCTV to Project A (LG Carpark & Office Tower Lobby) Submitted 26-Apr-13 $ 15,736 0% $ -
44 Latent Condition - Raine & Horne building high-level footing treatment Draft $ 10,000 0% $ -
45 Replace exsiting roof to project B (above circulation areas) Draft tba 0% $ -
46 Additional link bridge gate on Level 4 to GPC office Submitted 29-Apr-13 $ 7,123 0% $ -
$ 372,510 $ 54,558 $ 1,000,301 $297,584.38
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
8. Appendices (cont’d)
Local Participation - Opportunities Presented
LOCAL PARTICIPATION - OPPORTUNITIES PRESENTED TO INDUSTRY
TRADE TENDERERS CONTACTED BUSINESS LOCATION STATE ENGAGED CONTRACTOR
Demolition Delta Group Eagle Farm QLD Delta Group (Eagle Farm, QLD)
A.M.P.E. (Sarl South Pacific) Eagle Farm QLD
HOSE Family Trust Rockhampton QLD
WMA Demolition Yeerongpilly QLD
Busby Demolition Rockhampton QLD
Rosenlund Group Banyo QLD
Caylamax Demolitions Brendale QLD
Abyss Demolitions Underwood QLD
Australian Demolition & Excavations Gumdale QLD
JAL Concrete Works & Demolitions Rockhampton QLD
JM Kelly Project Services North Rockhampton QLD
Cortis Civil & Demo Farleigh QLD
Kwiklift (QLD) Pty Ltd Bundaberg QLD
Concrete Supply Holcim Gladstone QLD Holcim (Gladstone, QLD)
Boral Gladstone QLD
Burro Group Gladstone QLD
Hanson Gladstone QLD
Foundation Early Works Bona's Concreteing Gladstone QLD Bona's Concreting (Gladstone, QLD)
Remo Concrete Constructions Yatala QLD
Mitchell Concrete Constructions Rockhampton QLD
Steel Supply One Steel Gladstone QLD One Steel (Gladstone, QLD)
Steel Supplies Gladstone QLD
Australian Reinforcing Company Rockhampton QLD
Blue Scope Steel Gladstone QLD
Form Direct Bundaberg QLD
Wagners Everton Park QLD
Surveying North Surveys Gladstone QLD North Surveys (Gladstone, QLD)
Fredriksen, Maclean & Associates Gladstone QLD
RPS Gladstone QLD
Capricorn Survey Group Gladstone QLD
Bored Piers Anora Foundations Goodna QLD Anora Foundations (Goodna, QLD)
Wagstaff Piling Ashgrove QLD
Giles Contractors Mackay QLD
Ezibore Rockhampton QLD
Operable Walls Dorma Movable Walls Coorparoo QLD Dorma (Coorparoo, QLD)
Hufcor Wacol QLD
Spacial Concepts Virginia QLD
Unifold Loganholme QLD
Passenger Lifts Kone Elevators Bowen Hills QLD Kone Elevators (Bowen Hills, QLD)
Otis South Brisbane QLD
Schindler Hamilton QLD
ThyssenKrupp East Brisbane QLD
Scissor Hoists Southwell Engineering Camden NSW Southwell Engineering (Camden, NSW)
Tieman Industries Banyo QLD
Total Lifting Solutions Sommerville VIC
Materials Handling Oxley QLD
Porter Equipment Karratha WA
TRADE TENDERERS CONTACTED BUSINESS LOCATION STATE ENGAGED CONTRACTOR
Stair Climber Platform Lift Company Coomera QLD Platform Lifts (Coomera, QLD)
Simplex Elevators Brendale QLD
Porter Equipment Karratha WA
Tilt Panels Morton Panels Woodford QLD Morton Panels (Woodford, QLD)
Barrier Reef Construction Mackay QLD
E4 Tilt Panels Mermaid Beach QLD
Tilt-Up (East Coast Group of
Companies)Acacia Ridge QLD
Bonas Concreting Gladstone QLD
ANH Holdings Rockhampton QLD
A J & D H Bourke Mackay QLD
Keppel Coast Concretors Yepoon QLD
PJ Walsh Townsville QLD
Mitchells Concrete Rockhampton QLD
Scaffolding Harsco Infrastructure (Gladstone) Gladstone QLD Harsco Infrastructure (Gladstone, QLD)
Waco Kwikform Brisbane QLD
Syphonic Drainage Syfon Systems Slacks Creek QLD Syfon Systems (Slacks Creek, QLD)
Fastflow Nundah QLD
Concrete, Formwork & Bona's Concreting Gladstone QLD Bona's Concreting (Gladstone, QLD)
Reinforcing Fix Remo Concrete & Constructions Brisbane QLD
Barrier Reef Construction Proserpine QLD
Mitchells Concretors Rockhampton QLD
CADA Formwork Rockhampton QLD
Oakdale Formwork Brisbane QLD
Formwork Services Brisbane QLD
Dino's Gladstone QLD
Manly Concrete Brisbane QLD
Structural Steel MC Engineering Narangba QLD MC Engineering (Narangba, QLD)
Caneland Engineering Bundaberg QLD
Widgee Widgee QLD
Brown Steel Charlton QLD
CQ Steel Rockhampton QLD
Pierce Engineering Rockhampton QLD
Statewide Industries Mackay QLD
Aestec Engineering Gladstone QLD
Team Engineering Mackay QLD
Gay Construction Brisbane QLD
Milfab Deception Bay QLD
Capalaba Engineering Brisbane QLD
AG Rigging Toowoomba QLD
Australian Site Management Capalaba QLD
Concrete Pumping Meales Concrete Pumping Gladstone Gladstone QLDMeales Concrete Pumping (Gladstone,
QLD)
Post Tensioning Southern Cross Prestressing Caboulture QLDSouthern Cross Prestresing (Caboolture,
QLD)
CR & SS Canberra NSW
Tensioned Concrete Brisbane QLD
Freyssinet Brisbane QLD
Team PT Narangba QLD
Kent Works Group Brisbane QLD
APS Brisbane QLD
Wagners Toowoomba QLD
TRADE TENDERERS CONTACTED BUSINESS LOCATION STATE ENGAGED CONTRACTOR
Hydraulic Services Bluewater Contracting Gladstone QLD Bluewater Contracting (Gladstone, QLD)
Gladstone Plumbing & Drainage Gladstone QLD
Harbour City Plumbing Gladstone QLD
EKV Plumbing Brisbane QLD
EB Plumbing Gladstone QLD
Aztec Plumbing Coromandel SA
Mark Maunder Plumbing Mackay QLD
Fairfield Plumbing Capalaba QLD
PHP Contractors Brisbane QLD
CQ Plumbing Rockhampton
Electrical Services Corfields Electrical Gladstone QLD Corfields Electrical (Gladstone, QLD)
Stowe Brisbane QLD
Eaton Electrical Brisbane QLD
Livingstone Low Electrical Bundaberg QLD
KLM Group Brisbane QLD
Diamond Electrics Rockhampton QLD
Direct Electrical Nambour QLD
Paul Gray Electrical Gladstone QLD
Central Electrics Rockhampton QLD
O'Donnell Griffin Rydalmere NSW
Stanke Electrical Rockhampton QLD
Pacific Services Group Brisbane QLD
Electrotech Systems Brisbane QLD
FIP Electrical Mortlake NSW
Toilet Partitions Realhome Brisbane QLD Realhome (Brisbane, QLD)
Project Hardware Townsville QLD
ABP Allboards Brisbane QLD
Kirkbuild Brisbane QLD
Hufcor Brisbane QLD
Durra Ceiling System Tyzac Constructions Sunshine Coast QLDTyzac Constructions (Sunshine Coast,
QLD)
Q-Clad Sunshine Coast QLD
Dowbury Brisbane QLD
Queensland Industrial Cladding Brisbane QLD
Northwest Commerical Interiors Gordonvale QLD
Arondale Brisbane QLD
Fire Detection & Alarms Firelec Gladstone QLD Firelec (Gladstone, QLD)
Grainger Contracting Rockhampton QLD
Fire Sure Group Gold Coast QLD
Blockwork Twidale Bricklaying Goondiwindi QLD Twidale Bricklaying (Goondiwindi, QLD)
PNP Blockwork Cairns QLD
Impact Blocklaying Gold Coast QLD
J & L Blocklaying Brisbane QLD
Fugen Nerang QLD
Pict Brick Gladstone QLD
Adbri Masonry Gladstone QLD
Oaka Constructions Gladstone QLD
Door & Frame Supply Metal Accessories Rockhampton QLD Metal Accessories (Rockhampton, QLD)
Fire Mex Brisbane QLD
Spence Doors Brisbane QLD
FDF Doors Gold Coast QLD
Aust Architectural Doors Brisbane QLD
TRADE TENDERERS CONTACTED BUSINESS LOCATION STATE ENGAGED CONTRACTOR
Mechanical Services BPM Cowlrick Rockhampton QLD BPM Cowlrick (Rockhampton, QLD)
Siganto & Stacey Brisbane QLD
ECMS Brisbane QLD
Isothermal Brisbane QLD
Haden Engineering Gladstone QLD
Global Airconditioning Brisbane QLD
MVO Services Townsville QLD
Genaire Darwin NT
Wahoo Airconditioning Brisbane QLd
Windows Breezeview Aluminium Brisbane QLD Breezeview Aluminium (Brisbane, QLD)
G James Brisbane QLD
Total Concept Group Brisbane QLD
A & G Fabrications Brisbane QLD
Abbey Aluminium Brisbane QLD
Bradnams Brisbane QLD
Queensland Windows Rockhampton QLD
Civic Glass Brisbane QLD
Roller Shutters Mirage Doors Rockhampton QLD Mirage Doors (Rockhampton, QLD)
Best Doors Gladstone QLD
Arco Doors Brisbane QLD
Easy Lift Garage Doors Rockhampton QLD
Kitchen Works Hiller & Associates Maroochydore QLD Hiller & Associates (Maroochydore, QLD)
Reward Project Management Brisbane QLD
Connoisseur Sunshine Coast QLD
Diamond Catering Solutions Brisbane QLD
Carpark Crash Barriers Hyforce Engineering Gold Coast QLD Hyforce Engineering (Goldcoast, QLD)
On-time Guardrail Gold Coast QLD
Ali, Glass & Stainless Bundaberg QLD
MC Engineering Brisbane QLD
Aluminium Screens & SunshadesA & G Fabrications Brisbane QLD A & G Fabrications ( Brisbane, QLD)
Lowline Brisbane QLD
Total Concept Group Gold Coast QLD
Shutterflex Brisbane QLD
Hi-light Industries Brisbane QLD
Skyline Commerical Louvres Brisbane QLD
Carpet & Vinyl Contract Floor Coverings Brisbane QLD Contract Floor Coverings (Brisbane, QLD)
Gladstone Carpet & Vinyl Gladstone QLD
Len Smith Carpet Court Gladstone QLD
Focus on Floors Mackay QLD
Fraser Coast Commerical Flooring Hervey Bay QLD
Gladstone Warehouse Flooring Gladstone QLD
Harbour City Tiles & Carpets Gladstone QLD
PK Flooring Gladstone QLD
Floor Zone Gladstone QLD
Master Kelwin Brisbane QLD
Aluminium Louvres A & G Fabrications Brisbane QLD A & G Fabrications (Brisbane, QLD)
Austral Monsoon Brisbane QLD
Shutterflex Brisbane QLD
Skyline Commerical Louvres Brisbane QLD
Roof Safety System Roofsafe T Systems Brisbane QLD Roofsafe T Systems (Brisbane, QLD)
Safemaster Brisbane QLD
Safetylyne Brisbane QLD
Aegis Safety Brisbane QLD
Bullivants Brisbane QLD
Waterproofing Wet-seal Gladstone QLD Wet-seal (Brisbane, QLD)
All State Gladstone QLD
Joinery Corona Cabinets Brisbane QLD Corona Cabinets (Brisbane, QLD)
Pro 1 Brisbane QLD
Bradco Brisbane QLD
CQ Construction Gladstone QLD
Furniture Concepts QLD Rocklea QLD
Oceanic Cabinets Gladstone QLD
KBL Brisbane QLD
All Kind Joinery Brisbane QLD
Custom Cabinetry Gladstone QLD
Centre Coast Cabinets Sunshine Coast QLD
Samways Brisbane QLD
Scan Mac Brisbane QLD
Sparkmans Gladstone QLD
Security Services Securcom Brisbane QLD Securcom (Brisbane, QLD)
Tiling Ceramic Solutions Melbourne VIC Cermaic Solutions (Melbourne, VIC)
Gemma Tiles Brisbane QLD
Dlink Tiles Gladstone QLD
C & K Tiling Gladstone QLD
CK Tiling Brisbane QLD
BAK Tiling Brisbane QLD
Brisbane Tiling Service Brisbane QLD
Concept Tiles Brisbane QLD
Harbour City Tiles & Carpets Gladstone QLD
Andersens Gladstone QLD
Mark Maker Tiling Rockhampton QLD
Project Tilers Brisbane QLD
Tile Smith Gladstone QLD
Top Notch Tiles Gladstone QLD
Tilerite Bundaberg QLD
Roofing Roof Technology Brisbane QLD Roof Technology (Brisbane, QLD)
McHugh Steel Bundaberg QLD
Qclad Noosa QLD
Dowbury Brisbane QLD
Chainwire Fencing Gladstone Fencing Gladstone QLD Gladstone Fencing (Gladstone, QLD)
Metal Accessories Rockhampton QLD
Soft Landscaping Glascott Landscapes Brisbane QLD Glascott Landscapes (Brisbane, QLD)
Penfold Projects Brisbane QLD
Plantability Rockhampton QLD
A Touch of Paradise Bundaberg QLD
Dig It Landscapes Brisbane QLD
Naturelink Nerang QLD
Handrails Sentaur Products Maryborough QLD Sentaur Products (Maryborough, QLD)
Metal Accessories Rockhampton QLD
Gladstone Machining & Fabrication Gladstone QLD
Global Manufacturing Group Maryborough QLD
United Group & Resources Mackay QLD
Extreme Engineering Gladstone QLD
Watson Engineering Gladstone QLD
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
8. Appendices (cont’d)
Delay / Extension of Time Register
GLADSTONE ENTERTAINMENT CENTRE
Notice of Delay/EOT Register
Claim
No.
Date
SubmittedDate Approved Comment
001 03-Sep-12 37 days 37 days 04-Sep-12
002 15-Jan-13 1.5 days 1.5 days 16-Jan-13
003 04-Feb-13 6.5 days 6.5 days 07-Feb-13
004 07-Feb-13 4 days 4 days 08-Feb-13
005 05-Mar-13 3 days 3 days 06-Mar-13
006 04-Apr-13 6 days 4.5 days 08-Apr-13
007
008
009
010
58 days 56.5 days
EOT Claim Summary
Inclement Weather - March
Contract Start Date:
Concrete supply
Delay Total:
Time Submitted
(Working Days)
Time Approved
(Working Days)
Inclement Weather - January
Inclement Weather - Febuary
Cause Of Delay
Posession of site
Inclement weather
2 July 2013
Project A - Seperable Portion 1 17 April 2013
Project A - Seperable Portion 2 24 May 2013
Project B 28 June 2013
Amended Completion Dates:
Project A - Seperable Portion 1 25 July 2013
Project A - Seperable Portion 2 2 September 2013
Project B 2 October 2013
Contract Start Date:
Contract Completion Dates:
16/05/2013
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
8. Appendices (cont’d)
Photographs
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
8. Appendices (cont’d)
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
8. Appendices (cont’d)
SYDNEY BRISBANE MELBOURNE GOLD COAST TOWNSVILLE CAIRNS NEWCASTLE
8. Appendices (cont’d)