    Presentation to:

    Public Works Government Services Canada&

    Royal Architectural Institute of CanadaOttawa, ON

    GSAs National 3D-4D-BIM ProgramCharles Matta, FAIA

    Director, Federal Buildings & ModernizationsOffice of the Chief Architect & Capital Construction Programs

    February 15, 2008

  • 8/13/2019 Gsa Bim Program

    2/40

    Basic Facts about GSA / PBS

    Inventory of 340 million SF in 8,600 buildingsnationwide

    - Owned (approximately 51% of the inventory)- Leased - (approximately 49% of the inventory)

    - Serving over 1 million government workers in

    over 100 federal agenciesin 2,100 American communities

  • 8/13/2019 Gsa Bim Program

    3/40

    PBS Inventory/Construction Do General Purpose Buildings for the Executive and

    Judicial Branches

    Also Do Requested Transfer Projects

    We Dont Do

    Do General Purpose Buildings for the Executive andJudicial Branches

    Also Do Requested Transfer Projects

    We Dont Do

    Federal Buildings Courthouses

    Border Stations Warehouses

    Federal Buildings Courthouses

    Border Stations Warehouses

    Laboratories (FDA) Museums (Air & Space)

    Correctional (Bureau

    of Prisons)

    Education/Training

    (UDC)

    Laboratories (FDA) Museums (Air & Space)

    Correctional (Bureau

    of Prisons)

    Education/Training

    (UDC)

    Military Bases Civil Works

    Post Offices VA Hospitals

    NASA, DOE Facilities

    Legislative/AOC

    DOI Monuments/Parks Embassies

    Military Bases Civil Works

    Post Offices VA Hospitals

    NASA, DOE Facilities

    Legislative/AOC

    DOI Monuments/Parks Embassies

  • 8/13/2019 Gsa Bim Program

    4/40

    Federal Construction ProgramCapital and Minor ProjectsDesign, Construction, M&I Funding

    FY2003 FY2004 FY2005 FY2006 FY2007

    New $717M $721M $696M $792M $701M

    R&A $951M $964M $886M $861M $618M

    Total $1.66B $1.68B $1.57B $1.65B $1.31B

    Repairs and Alterations project dollars are likely to continue

    to outsize the New Construction program after DHS phase

  • 8/13/2019 Gsa Bim Program

    5/40

    GSAs Project Portfolio209 Active Major Projects, $12.425 Bill ion

  • 8/13/2019 Gsa Bim Program

    6/40

    Current Capital Program209 projects in 11 regions with a total value of

    approximately $12.425 B (as of November 19, 2007)71 are new construction projects

    26 of these projects are new courthouses or a newcourthouse annex.

    19 are new buildings or lab buildings.26 are new border stations

    94 are renovation projects (several are multi phase)89 are federal buildings modernizations (including space for

    judiciary).3 are federal courthouse modernizations2 are border station modernizations

    44 are lease projects

    42 are federal buildings2 are federal courthouses

  • 8/13/2019 Gsa Bim Program

    7/40

    Capital Program Delivery MethodsTypical - Based Upon Construction Cost

    30 - 40% - Construction Manager at Risk - (CMc) CM Works With Design Team to Optimize Design CM Guarantees Award, Typically at 75% Design

    5 - 10% - Design-Build (all Bridging) - (DB) Design Excellence A-E Develops Concept/DD DB Firm Selected Using Greatest Value Criteria DB Team Develops Construction Documents

    50 - 60% - Traditional (Design-Bid-Build) - (DBB) Design Excellence A-E Team Develops Concept A-E Team Develops Construction Documents

    Const. Award Based On Greatest Value Criteria

    Some Involve Design Competitions

  • 8/13/2019 Gsa Bim Program

    8/40

    Capital Program Objectives

    Meet customer needs

    Address building needs

    Consider market conditions

    Maintain stakeholder confidence

  • 8/13/2019 Gsa Bim Program

    9/40

    Business Challenges

    1. Human Capital

    2.Space Measurement

    3. Market Conditions

    4.Maintain Stakeholder Confidence

  • 8/13/2019 Gsa Bim Program

    10/40

    The Business CaseThe Business Case

  • 8/13/2019 Gsa Bim Program

    11/40

    PBS OCA 3D-4D-BIM ProgramGSAs National 3D-4D-BIM Program

    Strategy Overview

    1. Full Adoption FY2007

    Interoperability

    Foster competition

    Portfolio Planning Call

    Spatial Measurement Validation

    2. Venture Capital Board

    3D Laser Scanning

    3. Established Champions in Regions

    4. BIM Guide published

    5. Education and Public outreach

    6. Collaboration and Partnering with leading academic institutions

    GSAs National 3D-4D-BIM Program

  • 8/13/2019 Gsa Bim Program

    12/40

  • 8/13/2019 Gsa Bim Program

    13/40

    PBS OCA 3D-4D-BIM Program

    FedBizOpps:

    For all prospectus projects receiving design funding in FY2007 andbeyond, a spatial program Building Information Model will be the

    minimum requirement for all new and modernization projects that will

    be submitted to Commissioner of the Public Buildings Service forFinal

    Concept approvals.

    Scope of Work:

    check with OCA for latest template and advice on customization

    GSAs National 3D-4D-BIM Program

  • 8/13/2019 Gsa Bim Program

    14/40

    PBS OCA 3D-4D-BIM Program

    GSAs National 3D-4D-BIM Program

    From introduction,

    to pilots and technology/standard development,

    to policy and budget and guidance,

    to program and project deployment and supports

    60+ Projects To Date

    10+ pilots completed

    20+ projects underway

    35+ projects with Office of Chief Architect supports

  • 8/13/2019 Gsa Bim Program

    15/40

    The Value of 3D, 4D, and BIMThe Value of 3D, 4D, and BIM

  • 8/13/2019 Gsa Bim Program

    16/40

    PBS 3D-4D-BIM Program

    With respect to Industry Trends, Maturity, and Value

    The Many Facets and Applications of BIM:

    3D Visualization (Customer Communication/Mockup/Urban Study)

    3D Clash Detection and Coordination

    3D Production (Drawings and Fabrications)

    3D Laser Scanning

    4D Phasing (Tenants Move, Construction Sequence)

    Space/Program Validation

    Energy Simulation

    Circulation (occupants/vehicles), Egress, and Ingress Validation

    Acoustic Simulation

    Quantity Takeoff

    And more

  • 8/13/2019 Gsa Bim Program

    17/40

    PBS OCA 3D-4D-BIM Program

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    2 4 6 8 10 12 14 16 18 20 22 24

    pace: s

    3D Coordination BIMSpatial

    4D Phasing BIMEnergy 3D Laser Scanning

  • 8/13/2019 Gsa Bim Program

    18/40

    PBS OCA 3D-4D-BIM Program

    PrioritiesThe GSA BIM Guide Series

    01Overview

    02Spatial Program Validation

    033D Imaging

    044D Phasing

    05Energy Performance and Operation

    06Circulation and Security Validation07Building Elements

  • 8/13/2019 Gsa Bim Program

    19/40

    PBS OCA 3D-4D-BIM Program

    Space Measurement

    Gross Building Area

    Gross Design Area

    Usable Area

    Rentable Area

    Efficiency

    Volume

    Public/Private

    Ratio

    Fenestration

    RatioSkin to Floor

    Ratio

    Portfolio/Property

    Management

    STAR space type

    STAR space category

    Agency Bureau Code

    Business Question: How does PBS validate whether the design

    meets our program during concept phase?

  • 8/13/2019 Gsa Bim Program

    20/40

  • 8/13/2019 Gsa Bim Program

    21/40

    Basis for Spatial Program ValidaitonDuring Early Project Phases

    GSA Business Assignment Guide(2005)

    ANSI-BOMA Standard (1996)

    Regions SDM Formatting Standard

  • 8/13/2019 Gsa Bim Program

    22/40

    PBS OCA 3D-4D-BIM Program

    The Drive for Open Standard

    BIM-Authoring VendorsAutodesk & Inopso

    Architectural Desktop

    Autodesk RevitBentley Architecture

    Graphisoft ArchiCADOnuma Planning Stm.

    BIM-Viewing/AnalysisSolibri Model Checker

  • 8/13/2019 Gsa Bim Program

    23/40

    PBS 3D-4D-BIM Program

    Space ObjectSpace Name

    Space Number (ID)

    Occupant Org. Name

    Client Space Type

  • 8/13/2019 Gsa Bim Program

    24/40

    PBS OCA 3D-4D-BIM Program

    Our BIM-analysis tools incorporatedesign expertise in the analysis process

    We developed spatialprogram BIM analysistools that:

    Incorporate ANSI/BOMArules and spatialmeasurement expertise

    Automatically analyze thespatial program forefficiency ratios and area

    calculations Produce tenant stacking

    plans and reports

  • 8/13/2019 Gsa Bim Program

    25/40

    PBS OCA 3D-4D-BIM Program

    Automated Spatial BIM Report

    Floor

    Gross Building

    Area Gros s Measured Area Major Vertical Pen etration

    Floor Rentable

    Area

    Basement 118,823 111,039 3,020 108,020

    Ground Floor 107,954 101,020 3,437 97,583

    First Floor 153,767 94,678 2,936 91,742

    Second Floor 77,037 71,445 7,091 64,354

    Third Floor 74,512 70,497 2,328 68,169

    Fourth Floor 74,512 68,186 2,108 66,078

    Fifth Floor 74,512 65,419 2,221 63,199

    Sixth Floor 74,512 69,727 2,251 67,476

    Seventh Floor 59,239 51,591 1,676 49,915

    BUILDING 814,870 703,602 27,067 676,534

    Floor

    Floor Office

    Area USF/GSF

    Floor Building Common

    Area

    Floor Usable

    Area

    Basement 61,778 51.99% 26,395 88,176

    Ground Floor 71,380 66.12% 4,122 75,513

    First Floor 74,144 48.22% 3,473 79,020

    Second Floor 50,622 65.71% 3,565 55,847

    Third Floor 52,960 71.08% 2,801 55,764

    Fourth Floor 52,075 69.89% 2,538 54,613

    Fifth Floor 47,409 63.63% 2,579 50,363

    Sixth Floor 52,224 70.09% 1,484 53,718

    Seventh Floor 38,616 65.19% 3,795 42,462

    BUILDING 501,207 61.51% 50,752 555,477

    Usable Areas

    Floor Area Calculation s (in sf) Our BIM Report Contains:

    Floor Calculations Tenant Stacking Plans

    ANSI/BOMA Stacking Plans

    Basement

    INSERT STACKING FIGURE HERE

    O i 3D D B P j l d b OCA

  • 8/13/2019 Gsa Bim Program

    26/40

    PBS National 3D-4D-BIM ProgramOngoing 3D-4D-BIM Projects led by OCA:

    Spatial Program Validation

    Region 4 Tuttle Annex, GA

    Region 5 Dirksen Federal Building, IL (and laser as well)

    Region 6 Cedar Rapids Courthouse, IA

    Region 10 Edith Green Federal Office, OR

    R11/NCR 1800 F Street GSA Central Office, DC

    HCHB Dept of Commerce, DCSt. Elizabeths Campus, DC (candidate; led by NCR)

  • 8/13/2019 Gsa Bim Program

    27/40

  • 8/13/2019 Gsa Bim Program

    28/40

    Laser Scanning of 26 Federal Plaza

    2 days of scanning in parallel with 2.5 days of surveying

    covers plaza area, parking ramps, upper parking level, and exposed parking utilities

    5 weeks to convert points into 3D model (about 40 hours of actual modeling)

    accuracy from 3 feet to 150 feet

  • 8/13/2019 Gsa Bim Program

    29/40

    PBS 3D-4D-BIM Program

  • 8/13/2019 Gsa Bim Program

    30/40

    PBS 3D-4D-BIM Program

    St. Elizabeths Campus [NCR Portfolio]

    PBS 3D 4D BIM P

  • 8/13/2019 Gsa Bim Program

    31/40

    PBS 3D-4D-BIM Program

    St. Elizabeths Campus [NCR Portfolio]

    PBS 3D 4D BIM P

  • 8/13/2019 Gsa Bim Program

    32/40

    PBS 3D-4D-BIM Program

    HistoricBrooklyn GPO

    PBS 3D 4D BIM Program

  • 8/13/2019 Gsa Bim Program

    33/40

    PBS 3D-4D-BIM Program

    HistoricBrooklyn GPO

    PBS National 3D-4D-BIM Program Pilot Project

  • 8/13/2019 Gsa Bim Program

    34/40

    Salt Lake City Federal Courthouse, Utah

    Conventional vs. BIM

    0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    1000

    1 2 3 4 5 6 7 8 9 10 11 1 2

    ROOMS

    SPACES

    CORE

    PERIMITER

    ZONES

    PBS National 3D-4D-BIM Program Pilot Project

  • 8/13/2019 Gsa Bim Program

    35/40

    Salt Lake City Federal Courthouse, Utah

    Energy Use Breakdown

    0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    1000

    1 2 3 4 5 6 7 8 9 10 11 1 2

    VisualDOE Breakdown of

    Energy Use

    Riuska Breakdown of

    Energy Use

    Equipment

    8%

    Space Heating

    48%

    Space Cooling

    5%

    Lighting

    20%

    HVAC, other

    electricity (fans)

    9%

    DHW

    10%Equipment

    9%

    Space Heating

    44%

    Space Cooling

    7%

    Lighting

    11%

    HVAC, other

    electricity (fans)

    29%

    DHW

    0%

  • 8/13/2019 Gsa Bim Program

    36/40

    Sustaining a National ProgramSustaining a National Program

    PBS OCA 3D-4D-BIM Program

  • 8/13/2019 Gsa Bim Program

    37/40

    PBS OCA 3D 4D BIM Program

    GSAs One-Stop Center of Expertise

    Office of Chief ArchitectResources for 3D, 4D, BIM

    Strategy, Policy, and Tactics

    Program and Pilot Funding

    Development, Implementation, Standardization

    Solicitation and Scope of Work

    Internal Knowledge Portal (SOW, metrics, case studies)

    Training Opportunities (high-level, software trials, and

    tutorials)

    Public Outreach

    www.gsa.gov/bim: BIM Guides, GSA BIM Champions, Sign Up

    PBS OCA 3D-4D-BIM Program

    http://www.gsa.gov/bimhttp://www.gsa.gov/bim
  • 8/13/2019 Gsa Bim Program

    38/40

    PBS OCA 3D 4D BIM Program

    Improve Design

    Document as-built conditions

    Reduce Change orders due to errors and omissionsEnhance Design visualization, coordination and

    communication

    Improve project delivery

    Better address Facility Management

    BIM benefits to GSA

    http://www.gsa.gov/bim

    http://f/Recent%20GSA%20presentations/GSA%20PM%20Conf2005_Presentation/Pilot%2003=Central%20Office.ppthttp://f/Recent%20GSA%20presentations/GSA%20PM%20Conf2005_Presentation/Pilot%2003=Central%20Office.ppthttp://f/Recent%20GSA%20presentations/GSA%20PM%20Conf2005_Presentation/Pilot%2003=Central%20Office.ppthttp://f/Recent%20GSA%20presentations/GSA%20PM%20Conf2005_Presentation/Pilot%2003=Central%20Office.ppthttp://f/Recent%20GSA%20presentations/GSA%20PM%20Conf2005_Presentation/Pilot%2003=Central%20Office.ppthttp://f/Recent%20GSA%20presentations/GSA%20PM%20Conf2005_Presentation/Pilot%2003=Central%20Office.ppthttp://f/Recent%20GSA%20presentations/GSA%20PM%20Conf2005_Presentation/Pilot%2003=Central%20Office.ppthttp://f/Recent%20GSA%20presentations/GSA%20PM%20Conf2005_Presentation/Pilot%2003=Central%20Office.ppthttp://f/Recent%20GSA%20presentations/GSA%20PM%20Conf2005_Presentation/Pilot%2003=Central%20Office.ppt
  • 8/13/2019 Gsa Bim Program

    39/40

    p g g

  • 8/13/2019 Gsa Bim Program

    40/40

    Thank youCharles Matta, FAIA

    Director, Federal Buildings & Modernizations

    Office of the Chief Architect and Capital Construction Programs

    For more information visit: www.gsa.gov