heerema marine contractors - centre for international law...heerema marine contractors rigs-to-reefs...

20
Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Upload: others

Post on 12-Sep-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Heerema Marine Contractors

Rigs-to-Reefs

Presented by: Claudio Gentile

Date: 13 Nov 2013

Page 2: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Introduction

Offshore platforms are to be removed after life time cycle is finished if they represent an hazard to navigation

For North Sea platforms removal is mandatory

- Jackets to be removed up to 6ft below seabed

Derogation

- For concrete base platforms

- Jackets weighing > 10.000 mT and in a water depth > 100m can apply for Derogation: leaving the “Jacket

footings” in situ with a cut elevation at the top of the pile stick ups

Parties involved

- Government: Regulator

- Marine authority: MWS

- Client; Oil companies (Partners)

- Contractors

- Green party; NGO’s

- Other stakeholders e.g. fisherman

2

Page 3: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Project highlights

Removal is not a reverse installation

Removal is still relatively new in the industry

Procedures are not fully standardized

Platforms are not designed for removal

Structure might have been modified along the years or can be damaged

Safety standards at the time of installation are different from present (e.g. use of

hazardous substances)

3

Page 4: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

4

EPRD SoW

Firm Scope (Removal 2008 – 2013)

Optional Scope (Removal 2014 or earlier)

Page 5: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

5

Field/Platform

Topside

weight

(Tonnes)

Jacket

Weight

(tonnes)

No. of

leg Piles

Water

depth (m)

Norpipe 36/22 A

(UK Sector) 5580 4313 8 81

Norpipe 37/4 A

(UK Sector) 5962 4709 8 85

Albuskjell 1/6 A 10649 8902 12 70

Albuskjell 2/4 F 11418 7190 12 70

EPRD SoW

Page 6: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

6

Field/Platform

Topside

weight

(Tonnes)

Jacket

Weight

(tonnes)

No. of

leg

Piles

Water

depth

(m)

West Eko 2/4 D 3655 4146 8 70

EKO 2/4 R 4352

180 (Bridge) 6464 8 78

Edda 2/7C 10390 6155 12 70

Cod 7/11A 5167 5094 8 78

Ekofisk 2/4P 367 (2/4p deck)

93 (bridge supp.)

503 (bridge)

2061 2/4p

971 (tripod) 4+3 78

EPRD SoW

Page 7: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

7

Engineering Challenges

Verification of existing old and limited information (3500 drawings received)

Weight engineering including offshore visits for verification

Set-up of structural models

Structural integrity verification

Lift configurations including new lift points

Hook down engineering

- work packs structural

- work packs piping, electrical etc

Load-in engineering

Disposal engineering

Page 8: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

8

Topsides Removal Challenges

Modules originally designed for lifting

(Unknown) modifications during lifetime

Identify hook down scope

Potential hazardous substances (asbestos)

Page 9: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Jacket Removal Challenges

Most of jackets were originally designed as Launch Jackets

- Investigation of removal methods

Weight increase

Structural integrity verification

Subsea tools to be procured or developed and tested

Page 10: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

10

HMC approach

Scope definition for all phases

- Phase 1

- Platform surveys

- Topside

- Jacket (by ROV)

- Phase 2

- Make safe

- Phase 3

- Hook down and Topsides removal (and disposal)

- Jacket preparation

- Phase 4

- Jacket removal (and disposal)

Page 11: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Jacket inspection and preparation

11

2x UHD ROV + Subsea Tools

Inspection

- General visual inspection of the jacket

- Pre and post removal seabed survey

- Debris identification and removal

- Flooded members inspection

Preparation

- Marine growth removal

- Drill holes on jacket legs

- Seabed excavation

- Drill cutting relocation

- Removal of anodes, grout lines, risers

where required

Page 12: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

12

Jacket inspection and preparation

Subsea Inspection

Page 13: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

13

Jacket inspection and preparation

Subsea Tools

Page 14: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Jacket inspection and preparation

14

Drill cuttings relocation

Dredging seabed around jacket legs

To provide access to cutting tools

Page 15: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Jacket inspection and preparation

Cutting tools

- Water jet

- Shears

- Diamond wire

Page 16: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Jacket removal

16

Horizontal split

Page 17: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Jacket removal

17

Piecemeal lift

Page 18: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

Jacket removal

18

Single lift

Page 19: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

19

Conclusions

Removal of jackets and rigs to reef

- Experience and capability could be reused to create artificial reefs in a safe

manner

Page 20: Heerema Marine Contractors - Centre for International Law...Heerema Marine Contractors Rigs-to-Reefs Presented by: Claudio Gentile Date: 13 Nov 2013

20

Conclusions

Removal of jackets and rigs to reef

- Jacket left in place

- Jacket down-ended onto seabed

- Multiple jackets relocated in suitable place