Huckabee

GEORGETOWN ISD

2010 BOND PROGRAM UPDATE

J A N U A R Y 2 01 2

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 2

Huckabee

TABLE OF CONTENTS

East View High School Phase 2 Additions, Package 2 3

Georgetown High School Additions and Renovations 7

Completed Projects 10

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 3

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2Original: $25,574,000

CATE Addition – $2,121,338Baseball & Softball Turf - $880,000

Total - $28,575,338

Existing East View High School

A. New Athletic AdditionB. New Fine Arts AdditionC. New Academic AdditionD. New CTE BuildingE. New ROTC Addition (Alt.)F. New Tennis CourtsG. New Tennis Building H. New Baseball/Softball Fieldhouse,

Bleachers, Lighting & Pressbox I. New Practice FieldsJ. New Parking (1,070 spaces)

A

B

C

D

F

J

GH

B

J

J

J

J

Bid Package 1

E

Highway 29

CR

10

4

HH

I

I

Academic Wing

CTE Building

Softball Field House

First Floor

Second Floor

New Academic Addition

New Academic Addition

New Fine Arts Addition

New Athletic Addition

New CTE/ROTC Addition

General Contractor

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 4

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2

MILESTONE DATES

Schematic Design Presentation January 1, 2011

Architect Signs Documents March 8, 2011

Building Permit Application Submittal March 15, 2011

Site Plan Application Submittal March 17, 2011

Pre-Proposal Meeting March 22, 2011

Tour with General Contractors at East View Ninth Grade Center March 30, 2011

Proposal Part A Due April 7, 2011

Proposal Part B Due April 8, 2011

Proposal Evaluations April 11, 2011

Received City Building Dept. Plan Review Comments April 14, 2011

General Contractor Recommendation to School Board April 18, 2011

Received City Planning Dept. Plan Review Comments April 25, 2011

Construction Start Date May 19, 2011

First Owner/CO Meeting May 24, 2011

Building Permit Issued June 1, 2011

Owner, Architect and Contractor Meeting December 6, 2011

Owner, Architect and Contractor Meeting December 13, 2011

Owner, Architect and Contractor Meeting December 20, 2011

Owner, Architect and Contractor Meeting January 3, 2012

Owner, Architect and Contractor Meeting January 10, 2012

Substantial Completion June 27, 2012

ACADEMIC ADDITIONSteel structure placement and overhead MEP is ongoing.

CATE/ROTC

ATHLETIC ADDITION

FINE ARTS ADDITION – DRAMAOverhead MEP is ongoing.

FINE ARTS ADDITION – ORCHESTRA

Interior studs and sheetrock are complete.

BASEBALL, SOFTBALL, TENNIS AND SITE

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 5

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2

Academic Addition - Interior View Gymnasium Addition

Locker Room Addition Baseball Field

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 6

Huckabee

Aerial

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2

CATE/ROTC

Academic Addition

Athletic Addition

FIne Arts Addition

Courts

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 7

Huckabee

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS

Construction Manager

BAIRD WILLIAMS

CONSTRUCTION

Project Manager

CTE Wing

Science Labs

Academic

Special Education

Library

Cafeteria

Computer Labs

Athletics

Fine Arts

Academic

AuditoriumAthletics

Athletics

Athletics

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 8

Huckabee

June 30, 2011

Cost Review with Construction Manager July 19, 2011

Interiors Presentation July 25, 2011

Architect Signs Documents for Site Utility Package July 26, 2011

CD Coordination Meeting on Site with Architect, Owner and Construction Manager

July 27, 2011

July 27, 2011

City Comments Received for Site Utility package August 8, 2011

Site Utility Package Bid August 17, 2011

Guaranteed Maximum Price on Site Utility Package August 29, 2011

Architect Signs Documents September 1, 2011

Pre-Bid September 21, 2011

Pre-Bid (Technology) September 23, 2011

Bid October 4, 2011

Guaranteed Maximum Price Presented to School Board October 17, 2011

Construction Start Date October 18, 2011

Owner, Architect and Contractor Meeting December 8, 2011

Owner, Architect and Contractor Meeting December 15, 2011

Owner, Architect and Contractor Meeting December 22, 2011

Owner, Architect and Contractor Meeting December 29, 2011

Owner, Architect and Contractor Meeting January 5, 2012

Substantial Completion July 2013

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONSMILESTONE DATES

and Nurse

February 28, 2011

March 1, 2011

Initial Construction Phasing with Stakeholders March 3, 2011

March 4, 2011

March 10, 2011

Advertisement for Construction Manager at Risk RFQ March 12, 2011

Received Construction Manager at Risk Step 1 March 29, 2011

Evaluation Team Grades and Develops Recommended Short List March 30, 2011

Facility Assessment of ADA, Code and Existing Conditions March 29 - 30, 2011

School Board Receives Recommended Short List April 4, 2011

Step 2 of RFQ Submitted to Short Listed Contractors (Fees and General Conditions)

April 5, 2011

Fees and General Conditions due by 3 PM April 8, 2011

Board of Trustees Select Construction Manager at Risk April 18, 2011

First Meeting with District, Architect, Project Manager and Construction Manager

April 19, 2011

Site Logistics Survey with District, Architect, Project Manager and Construction Manager

April 29, 2011

Schematic Design Presentation June 6, 2011

June 14, 2011

Site Coordination Meeting with Architect, Owner and Construction Manager

June 16, 2011

MILESTONE DATES

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 9

Huckabee

PHASE I

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS

Locker Room Addition

Cafeteria Addition

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 10

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1

Contract Amount: $5,321,000Substantial Completion Date: August 19, 2011

General Contractor: Charter Builders

COMPLETED PROJECTS

Field House Locker Room

NEW WAREHOUSE FACILITY

Contract Amount: $641,000

Substantial Completion Date: November 9, 2011General Contractor: CSS, Inc.

Interior View of Warehouse

ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATION

Contract Amount: $229,000Substantial Completion Date: August 12, 2011

General Contractor: Saratoga

New HVAC Unit and Roofing

Field House Weight Room Storage Shed New Ceiling and Light Fixtures