    HYDROLOGIC &HYDRAULIC REPORT

    IH 610 W/ US 59 S INTERCHANGESOUTH DRAINAGE ELEMENTS

    CSJ: 0271-17-146

    HARRIS COUNTY, TEXAS

    Prepared for:

    &

    VOLUME 1

    H & H RESOURCES, INC. (F-3678)

    DECEMBER 2013

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    2/272

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    3/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    i

    TABLE OF CONTENTSVOLUME 1 OF 2

    EXECUTIVE SUMMARY .......................................................................................................... 1

    Table 1 Summary Cost Table ............................................................................................................................ 1

    1 INTRODUCTION .................................................................................................................. 2

    1.1 PROJECT DESCRIPTION AND LOCATION............................................................................ 2

    1.2 PURPOSE............................................................................................................................. 3

    1.3 SCOPE OF WORK................................................................................................................ 4

    1.4 DATA SOURCES................................................................................................................... 5

    1.5 OBSERVATIONS FROM AS-BUILT PLANS RESEARCH........................................................ 7

    1.5.1 US 59/METRO Plans ................................................................................................................................... 7

    1.5.2 Westpark Tollroad Detention Ponds ........................................................................................................... 8

    1.5.3 Westpark Culvert Plans ............................................................................................................................... 9

    1.5.4 Westpark Tollway Plans ............................................................................................................................ 10

    1.5.5 Westheimer Connector plans ..................................................................................................................... 14

    1.6 OBSERVATIONS FROM ANECDOTAL INFORMATION........................................................ 14

    2 METHODOLOGY ............................................................................................................... 15

    2.1 HYDROLOGIC APPROACH................................................................................................ 15

    2.2

    HYDRAULIC APPROACH................................................................................................... 17

    3 HYDROLOGIC SUMMARY ............................................................................................. 19

    3.1 OUTFALL IDENTIFICATION.............................................................................................. 19

    3.2 OUTFALL SUMMARY........................................................................................................ 19

    4 HYDRAULIC ANALYSIS .................................................................................................. 21

    4.1 EXISTING CONDITIONS WITH SILT.................................................................................. 22

    4.2 EXISTING CONDITIONS WITH NO SILT IN WESTPARK TRUNKLINE................................ 26

    4.3 EXISTING CONDITIONS WITH W129STAGE 3 ................................................................. 28

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    4/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    ii

    4.4 PROPOSED CONDITIONS WITH W129STAGE 3 ................................................................ 31

    4.4.1 Increase Detention Pond at W16........................................................................................................ 33

    4.4.2 Detention Pond at W18 ...................................................................................................................... 34

    4.4.3 Detention Pond at 4-H3 ...................................................................................................................... 34

    4.4.4 Oversized Storm Sewer at US 59 SBFR ............................................................................................. 35

    4.4.5 Trench Drain along IH 610 SB/US 59 SB Direct Connector ............................................................ 36

    4.4.6

    Increase Detention Storage at Ponds DB6-1 and DB6-2 .................................................................. 36

    4.4.7 Increase Height of Retaining Walls along IH 610 SBFR/Westpark Tollroad.................................. 37

    4.4.8 Pump Station Modifications ............................................................................................................... 37

    4.5 PROPOSED CONDITIONS WITH SILT................................................................................. 41

    4.6 PROPOSED CONDITIONS WITH NO SILT IN WESTPARK TRUNKLINE.............................. 44

    5 MITIGATION FOR THE IH 610 BRAYS BAYOU STORM SEWER ......................... 47

    6 ENTITY PARTICIPATION ............................................................................................... 49

    7

    CONCLUSIONS AND RECOMMENDATIONS ............................................................. 51

    Table 7 Summary Phase Table ........................................................................................................................ 52

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    5/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    iii

    APPENDICES

    APPENDIX A EXISTING CONDITIONS DRAINAGE AREA MAPS

    PROPOSED CONDITIONS DRAINAGE AREA MAPS

    APPENDIX B EXISTING HYDROLOGIC COMPUTATIONS

    PROPOSED HYDROLOGIC COMPUTATIONS

    APPENDIX C OVERALL EXISTING SWMM LAYOUT

    EXISTING SUMMARIES OF RESULTS

    VOLUME 2 OF 2

    APPENDIX D OVERALL PROPOSED SWMM LAYOUT

    PROPOSED SUMMARIES OF RESULTS

    APPENDIX E DETENTION POND LAYOUTS

    APPENDIX F BRAYS BAYOU STORM SEWER SYSTEM

    SMALL WATERSHED VOLUME CALCULATIONSSTORM SEWER VOLUME COMPUTATIONS

    APPENDIX G SEQUENCE OF CONSTRUCTION EXHIBITS

    APPENDIX H CD WITH ELECTRONIC FILES

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    6/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    1

    EXECUTIVE SUMMARY

    This is a comprehensive drainage study of IH 610 West at US 59 South interchange, in

    Harris County, Texas. The purpose of the study is to identify and recommend solutions

    for the existing drainage problems within the interchange and the US 59 corridor between

    Chimney Rock and Newcastle. This report also presents mitigation measures

    recommended to offset impacts due to proposed improvements.

    The following is a summary of the identified issues along with recommended solutions.

    These issues are located on Figure 1 in this section. The estimate of probable cost for

    each solution is discussed in Section 6: Entity Participation.

    Table 1 Summary of Recommended Solutions

    I.D. Report Ref Issue Solution

    A 1.5.1US 59 ML Ponding beneath METRO elevated

    lane and beneath IH 610 MLTrench drains

    B 1.5.3 Obs 2 Westpark storm sewer siltation Maintenance

    C 4.3.1

    Existing flooding of US 59 SBFR and adjacent

    properties, proposed additional impervious

    mitigation

    Increase W16 Detention

    D 4.3.2 Add W18 Detention

    E 4.3.3Existing flooding of IH 610 SBFR/Westpark

    Tollway

    Add H3 Detention, 24 flex valve, and related

    improvements

    F 4.3.3 Add flex valve at Pond DB-7G 4.3.4 Raise grade of US 59 SBFR

    H 4.3.4 Storm sewer and inlet improvements at US 59

    SBFR

    I 4.3.5 Increase Detention Storage at Ponds DB6-1 and

    DB6-2

    J 4.3.7 Adjust the pump timing for the IH 610 SBFR/

    Westpark Tollroad & IH 610 NBFR pump stations

    K 4.3.6 Increase wall height or add earthen berms at IH 610

    SBFR/Westpark Tollroad.

    L 1.5.4 Obs 5 Existing flooding of IH 610 NBFR Reroute storm sewer line (42 RCP)

    M 1.5.4 Obs 4 Regrade abandoned pavement near Chimney Rock

    Exit Ramp

    N1 5

    IH 610 Brays Bayou proposed additional

    impervious mitigationStorm sewer improvements at IH 610 SBFR, NBFR

    P1 1.5.3 Obs 2 Existing flooding of US 59 SBFR and Larchmont Complete Stage 3 of W129 channel improvements

    1. Related improvements, not included on Figure 1

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    7/272

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    8/272

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    9/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    2

    1 INTRODUCTION

    1.1 Project Description and Location

    This project consists of a comprehensive drainage study of IH 610 West at US 59 South

    interchange, in Harris County, Texas. The project is within the Cities of Houston and

    Bellaire. The study includes an analysis of the existing drainage system and flooding

    problems in and around the interchange, recommendations and analysis for the proposed

    conditions, and mitigation of any impacts due to proposed improvements. The study is

    being conducted as part of the reconstruction of the interchange, however, the study

    includes mitigation of the entire proposed interchange improvements, which include

    realignment of the direct connectors (DC), Post Oak Blvd, and the southbound (SB)

    frontage road (FR) between IH 610 and Chimney Rock, a new Chimney Rock Rd exitramp, and reconstruction of the IH 610 main lanes (ML). The proposed direct connectors

    constructed under CSJ 0271-17-145, -146, and -157 are Phase 1 of three phases.

    The project is within two watersheds, Buffalo Bayou and Brays Bayou (see overall

    drainage area maps in Appendix A). The boundary between the two is the old rail

    corridor along Westpark Dr. The majority of the interchange drains to the east to Harrris

    County Flood Control District (HCFCD) Ditch W129-00-00 through a large storm sewer

    line along Westpark Dr. A portion of the area along the northbound (NB) and SB FRs

    near Richmond Ave drains to the north through storm sewer along IH 610 to Buffalo

    Bayou (HCFCD Unit W100-00-00). Part of the IH 610 NB to US 59 SB DC is within the

    Brays Bayou watershed, as is the portion of IH 610 within the study area generally south

    of Westpark Dr.to just south of Fournace Place.

    This study and report is prepared by H & H Resources, Inc. (HHR), subconsultant to LJA

    Engineering, Inc. (LJA), the prime consultant under TxDOT Contract 33-212P5016,

    Work Authorization 1. HHRs role is to provide the drainage study as generally described

    above, and to oversee drainage study implementation and improvements for the IH 610 /

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    10/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    3

    US 59 interchange. Klotz Associates (Klotz), another subconsultant to LJA under the

    same TxDOT contract, is designing the IH 610 drainage system improvements south of

    Westpark, based on mitigation recommendations in this study. A concurrent drainage

    study and separate report is being prepared by AECOM, the prime consultant under a

    separate TxDOT contract, CSJ 0271-17-145. The AECOM study area includes drainage

    systems and contributing areas along IH 610 generally north of Richmond Ave., and

    along US 59 generally east of the IH 610 NBFR.

    As part of the overall interchange analysis, AECOM completed the W129-00-00 channel

    analysis and determined the downstream boundary (tailwater) conditions for use in this

    analysis for the Westpark storm sewer. Coordination with AECOM was also completed

    at several locations where the systems between the W129-00-00 watershed and the IH

    610N storm sewer are interconnected.

    Aguirre & Fields, LP (AFLP), the prime consultant under yet another current TxDOT

    contract (0271-17-157), is designing improvements for Phase 1 of the IH 610 / US 59

    interchange, including improvements to existing detention facilities in the SE quadrant of

    the interchange.

    1.2 Purpose

    The general purpose of this report is to identify the existing drainage problems within the

    interchange and the US 59 corridor between Chimney Rock and Newcastle, and

    recommend major drainage system improvements and mitigation. This study

    incorporates all of the major drainage elements associated with the existing and proposed

    roadway including the direct connectors and depressed sections. This report presents

    recommendations for mitigation measures that will be required to offset calculated

    impacts due to stated improvements.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    11/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    4

    1.3 Scope of Work

    The scope of work consists of performing an existing and proposed analysis that

    incorporates all of the representative elements. The intent of the existing conditions

    analysis is to establish a hydraulic baseline model for the existing storm sewer system

    and identify any drainage problems. For the proposed conditions, the analysis was

    completed to implement the proposed improvements due to the roadway construction,

    recommend solutions for existing drainage problems and mitigate any impacts due to the

    proposed changes. Additionally, the intent is to demonstrate that the proposed

    improvements will not adversely impact the abutting properties and receiving streams

    relative to the existing conditions. The drainage report includes hydrologic and hydraulic

    computer models such as HEC-HMS and SWMM, drainage area maps, drainage outfall

    descriptions, storm water storage requirements, and pump station recommendations.

    Mitigation measures to reduce flooding in problem areas will be evaluated, and solutions

    recommended. The report will present a comprehensive examination of the drainage

    issues for the project area and will address the following items in detail:

    Determine the existing drainage boundaries that contribute to the project area and

    develop peak flows using rational method. Use Small Watershed Method and

    Clark Unit Hydrograph method in HEC-HMS to develop hydrographs for import

    into the hydraulic model. Develop an existing conditions hydraulic model, using SWMM (XP-Storm

    Version 2012), from survey and as-built plans.

    Identify drainage problems as shown in the existing hydraulic model and compare

    to eyewitness information. Develop a list of the existing drainage problems

    determined from the analysis and from research of the as-built plans.

    Meet with TxDOT to discuss existing conditions analysis and existing problem

    areas.

    Determine proposed conditions drainage area boundaries based on proposed

    roadway improvements for the ultimate interchange configuration within the

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    12/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    5

    project area. Develop proposed hydrology using same methodology as the

    existing.

    Develop a proposed conditions hydraulic model and implement design changes to

    improve the existing drainage problems and mitigate potential impacts due to the

    proposed changes.

    Determine the impacts to the W129-00-00 and IH 610 South storm sewer system.

    (The outfalls to Buffalo Bayou have been analyzed by AECOM and will be

    discussed within their report.)

    Coordinate with AECOM regarding all interconnections of the storm sewer and

    tailwater conditions in the W129-00-00 channel.

    Coordinate with Aguirre & Fields, LP, (AFLP) on proposed work in Phase 1 and

    determine if any additional proposed work should be implemented with AFLPs

    construction.

    Limit the discharges to the receiving streams to existing capacity flows, as

    determined by study of the existing conditions.

    Provide a preliminary storm sewer trunk line design for the proposed conditions.

    Coordinate with roadway and storm sewer PS&E designers to implement

    proposed conditions as determined in the impact analysis.

    Prepare a report of preliminary findings.

    1.4 Data Sources

    The following sources of information are used to develop the hydrologic and hydraulic

    components: project topography/field surveys, aerial photography, as-built plans, City of

    Houston Geographic Information & Management System (GIMS), and LiDAR

    topography. All source data are either referenced to, or adjusted to the project vertical

    datum: NAVD 88 (2001 adjustment). This datum is the same as the Harris County

    benchmark network established by the Tropical Storm Allison Recovery Project

    (TSARP), which serves as the basis for Federal Emergency Management Agency

    (FEMA) Flood Insurance Rate Map (FIRM) effective flood study elevations.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    13/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    6

    The project topography is provided by TxDOT and updated through field survey for the

    project provided by RODS surveying. Subsurface utility survey is provided by RODS.

    Aerial photography dated 2008 was obtained from LJA.

    Several as-built plan sets were referenced for this study, dating back to the original

    construction plans for US 59 and IH 610 in 1961. Five of the plan sets are determined to

    be relevant for this study and are described below.

    1. TxDOT/METRO 0027-13-123 (1987) - US 59 Southwest Freeway FR

    relocation and freeway overlay widening from south of Westpark to east of IH610/US59 interchange.

    2. Harris County Toll Road Authority (HCTRA) (2001) Westpark Tollway

    from 0.1 mi west of Rice Ave. to 0.4 miles east of Rice Ave.

    3.

    Westpark Box Culverts (METRO) (1981) construction of Westpark

    trunkline from Chimney Rock to W129-00-00

    4. TxDOT 0271-17-138 (2001) - IH 610 depressed FRs and tollway connectorfrom Westpark Dr. to Richmond Ave.

    5. TxDOT 0271-17-125 (2002) IH 610 from south of Westpark Dr. to north of

    Richmond Ave, aka Westheimer Connectors.

    The numbering system for the as-built plans was utilized to label the drainage areas and

    nodes in the hydraulic model. The leading number refers to the plan set and the

    following letter/number refers to the label as shown in the corresponding plan set. For

    example, Node 1-F34 corresponds to MH-F34 as shown in Plan Set 1.

    City of Houston GIMS is used to obtain data related to storm sewer systems outside of

    the limits of the as-built plans. LiDAR is obtained from Harris County.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    14/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    7

    1.5 Observations From As-built Plans Research

    The following discussion is annotated to the plan source. Observations about existing

    conditions and the implications for new drainage calculations and modeling are

    described, as well as recommendations for constructed improvements if applicable.

    1.5.1 US 59/METRO Plans

    OBSERVATION 1

    US 59 ML inlets are located beneath the METRO elevated lane east of IH 610 and behind

    the slotted traffic rail. No inlet calculations for these inlets were found in the plan set.

    Several existing inlets were removed in this area when this project was completed.

    Contours indicate that the cross slope in this area is 0.2%. Plans show that the roadway is

    in a superelevation transition and is also near the sag in the vertical profile.

    Since inlet computations were not completed, the ponded width was not checked in this

    area. Instead of a 2% cross slope, the 0.2% cross causes significantly more ponding than

    expected or allowed. The superelevation transition occurs at sag in the profile which

    further exacerbates the flooding condition.

    Recommendation: Although the US 59 ML drainage system is outside the limits of the

    proposed construction for this project, it is recommended that trench drains are placed

    along the barrier on both sides of the roadway to reduce the ML flooding. (See Figure 1,

    Location A.) The existing inlets could be utilized to connect to the existing drainage

    system.

    OBSERVATION 2

    Another US 59 ML superelevation transition occurs beneath the IH 610 MLs. The

    longitudinal slope in this area is almost 0%. This flat slope contributes to the lack of

    conveyance.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    15/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    8

    Recommendation: With the placement of the proposed Chimney Rock exit ramp, it is

    recommended that trench drains are placed along the barrier between to reduce the ML

    flooding and convey the flow under the proposed ramp. (See Figure 1, Location A.)

    OBSERVATION 3

    The construction of the METRO HOV lane through the interchange created a small swale

    between the US 59 NBML and the HOV lane. The US 59 NBMLs prior to the HOV

    drained directly into the grassy area under the IH 610 ML bridges and away from the US

    59 NBML. Several columns for the existing direct connectors and IH 610 ML are within

    the swale. These columns restrict the area in which water would be conveyed to the

    inlets within the swale. Due to the restriction of the flow in the swale and the silting of

    the openings in the slotted rail, the US 59 NBML has more ponding than it otherwise

    would.

    Recommendation: With the proposed roadway improvements to the US 59/IH 610 direct

    connectors and the IH 610 MLs, several of the columns will be eliminated with the

    removal of the existing bridges. In Phase 1, the IH 610NB/US 59SB and IH 610SB/US

    59 NB direct connectors will be removed. For Phase 2 and 3, it is recommended that the

    bent locations be modified to remove columns from the swale area if possible. These

    changes should eliminate some of the ponding issues that are currently occurring. The

    slotted rail and swale should also be maintained regularly to eliminate silting and debris

    collection.

    1.5.2 Westpark Tollroad Detention Ponds

    OBSERVATION 1

    The detention pond outlets in the plans do not represent what is now in the field. The

    outlets were modified in the IH 610 FR and Westpark Tollroad depressed section plans

    (Plan Set 4). Due to this change, it appears that the detention ponds may not be

    functioning as originally designed.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    16/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    9

    Recommendation: Modeling in this study will analyze outlets per current field survey.

    1.5.3 Westpark Culvert Plans

    OBSERVATION 1

    The box culvert constructed in the early 1980s along the northern edge of Westpark

    Drive replaced an open channel. The box was placed virtually flat, with almost no

    longitudinal slope. West of Chimney Rock Road, the storm sewer is a single 10x5

    RCB. It transitions to a 12x6 RCB through the intersection, then to a 2-10x7 RCB,

    and finally to a 2-12x8 RCB. There are no junction boxes along this trunkline at

    Westpark Drive, only openings in the wall between the boxes in various locations. All

    of the trunklines from the north (those that drain US 59 and areas north of US 59)

    connect to the north box culvert. Flow can only enter the south box through theseopenings. These openings vary in size from 2x2 to 6x6. The openings smaller than 6

    in height are located 2 above the FL. The 6 openings match the FLs of the box culvert.

    Since all of the storm sewer systems only tie to the north box (this also includes the

    detention ponds along Westpark), the maximum capacity of the system may not be

    realized because the flow is not effectively conveyed to the south box culverts.

    Action item completed with modeling: The two storm sewer lines are modeled

    separately and connected with orifices sized and located as shown in the plans to

    determine the adequacy of the openings and operation of the system. The locations and

    sizes were also verified by the surveyors.

    OBSERVATION 2

    AECOM mentioned during a coordination meeting that during construction of the

    Westpark Tollroad, there were reports of the box culverts having a major silt problem

    with the boxes filled as much as 60%. The silt problem seems to occur due to the very

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    17/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    10

    flat longitudinal slope of the storm sewer system and the presence of sand in the W129-

    00-00 channel at the outfall of the Westpark System.

    Action item completed: Since there are no manholes located on the Westpark storm

    sewer line, the survey crew entered the storm sewer system and walked along the

    northern RCB. The surveyors note the presence of silt and the depth of the silt along the

    box culvert at each of the opening locations. Surveyors indicate that the silt depth

    appears to be equal in each of the boxes.

    Recommendation: The silt in the box culvert should be removed to allow for maximum

    conveyance in the system. It is recommended that maintenance of the boxes should be

    completed to keep the boxes clean of silt. Also, HCFCD completed a study to enclose

    the W129-00-00 channel with box culverts from the confluence with Buffalo Bayou to

    the Westpark storm sewer system. Construction of the HCFCD system was split into

    three stages, with Stage 3 being the most upstream portion located between Richmond

    and the Westpark system. The first two stages have been constructed with Stage 3

    lacking current construction funding. Construction of Stage 3 should help minimize the

    silting that occurs within the box and would allow for greater conveyance.

    Action item completed with modeling: The Westpark storm sewer system is analyzed

    with the silt in place in the existing and proposed condition to simulate the lost

    conveyance within the system. The system is also analyzed in the existing and proposed

    with the Phase 3 project in place and the silt removed from the Westpark storm sewer.

    1.5.4 Westpark Tollway Plans

    OBSERVATION 1

    A 24 RCP gravity line from Inlet H3 (located between US 59 SBMLs and Connector B

    (IH 610NB/US 59 SB) connects directly to detention pond DB-7; this line also connects

    to storm sewer line between the METRO HOV lane and US 59 MLs. The retaining wall

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    18/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    11

    plans for Wall W-2 for the depressed IH 610 SBFR show that the low point in the wall is

    at the corner of the US 59 SBML bridge and the separation area at elevation 56.20. Other

    significant elevations:

    The proposed pond design WSEL is shown as 57.00 with a flowline of 49.50.

    The top of grate elevation at Inlet H3 is 54.94 with a flowline of 50.37.

    The top of grate elevation at Inlet H2, located along the US 59 NB MLs, is 54.06

    with a flowline of 49.86.

    As the pond fills, the gravity line will fill with water and backup through the inlets. The

    water will then spread out over the US 59 MLs near the HOV lane. Near inlet 4-H3, the

    water will overflow the retaining wall and fall into the depressed IH 610 SBFR.

    Action item completed with modeling: Overflow of this wall has been observed during a

    flood event (See picture on following page). The elevations have been verified through

    field survey. The system is modeled in SWMM and the observation should be verified

    through the analysis.

    Water overflowing the wall near Inlet 4-H3 (January 2012)

    Photo Credit: Todd Thurber, LJA

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    19/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    12

    OBSERVATION 2

    Several field changes to the detention pond at DB-7 may have created hydraulic

    conditions different than intended by the design.

    The plans indicate the 48 RCP between Ponds DB-7 and DB6-1 was placed at a

    flatter slope than the original.

    The contours indicate less volume in Pond DB-7 than was shown in the plans.

    The capacity of the pipe is reduced from the as-built slope and requires more head to

    meet same flow capacity as the design. Less exit flow would create higher WSEL in the

    pond which could overflow into the depressed section.

    Action item completed with modeling: During the last flood event in January 2012,

    TxDOT personnel indicated that the wall was overtopped by water at this location and the

    depressed section was flooded. It was also noted that Pond DB-7 was full of water but

    Pond DB6-1 did not have water in it. The 48 outlet was blocked with debris and once

    cleared, Pond DB-7 began to release water. According to rainfall data collected from the

    Harris County Office of Emergency Management website, the rainfall recorded at the

    closest locations to the interchange would be classified as less than a 2 year event.

    Field survey has been completed and the elevations were utilized in the model. Although

    the failure of the existing system last occurred due to clogging of the outfall pipe, thesystem should be modeled to determine if overtopping of the wall can occur at or before

    the design event. The location is modeled in SWMM and the observation should be

    verified through the analysis.

    OBSERVATION 3

    Inlets on the depressed section were designed for 25-yr storm frequency design capacity.

    The elevation indicated for the maximum storage elevation in the proposed pump station

    plans is higher than the elevation at the low point in the Westpark Tollway profile with

    one lane ponded.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    20/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    13

    Action item completed with modeling: This location is modeled in SWMM with the

    pump station in place.

    OBSERVATION 4

    Water drains from the US 59 SBMLs through slotted traffic railing across an area of

    abandoned temporary pavement. When the depressed section for Westpark Tollway and

    IH 610 SBFR was built, the ditch along the pavement was not redesigned. The contours

    indicate that the water is directed towards the wall and then overflows to the depressed

    lanes below.

    Action item completed with modeling: This area is modeled in SWMM and the

    observation should be verified through the analysis. Regrading of this area will occur

    with the proposed Chimney Rock exit ramp being placed.

    OBSERVATION 5

    In the design plans, the drainage area maps for the depressed section do not include the

    overland flow from the direct connector side slopes. Also, overflow from the FRs along

    the NW, NE, and SW quadrants appears to be possible if the HGL in these adjacent areas

    becomes higher than the PGL entering into the depressions.

    As indicated in the Westpark Tollway report (Brown & Gay Engineers, Inc. report dated

    June 29, 2004) analyzing the flooding issues, the drainage areas to the pump stations are

    larger than indicated in the original report. The design for pump stations should be

    checked for the effect of the additional area. At the SE pump station, a large portion of

    the US 59 ML drainage is directed to the pump station. The FR near the Houston

    Chronicle building is also redirected to the pump station. The original plans connected

    the FR storm sewer directly to the Westpark box culverts.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    21/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    14

    At the NE quadrant, additional flow from the adjacent storm sewer systems can enter the

    IH 610 NBFR depressed section. The storm sewer system for this area is split into three

    segments. The north segment drains into the IH 610 north storm sewer system modeled

    in the AECOM study. The middle segment at the curve in the FR is connected to the

    depressed section system. The east segment is drained to W129-00-00 through a storm

    sewer which is also modeled in the AECOM study. The southernmost inlet in the north

    segment is an on-grade inlet that allows carryover to the middle segment, and this flow

    was not accounted for in the depressed section computations. From the east segment, an

    18 RCP was found in the field survey entering the middle segment storm sewer system.

    According to the as-built plans, this line should have been removed and no connections

    from the east should have occurred.

    Action item completed with modeling: These areas are modeled in SWMM and the

    observations should be verified through the analysis. Any changes to the pump station

    design and/or timing at the IH 610 NBFR location could be done as part of CSJ 0271-17-

    145, and the IH 610 SBFR station as part of Job 157 (Phase 1 construction plan sets).

    1.5.5 Westheimer Connector plans

    OBSERVATION 1

    In the design plans, the 6x6 RCB downstream of the concrete lined channel beneath the

    IH 610 MLs south of US 59 was realigned to avoid conflicts with the proposed

    foundations for the connectors. During a field visit, it was noted that a flex valve was

    present at the downstream end of the concrete lined channel. No field changes were

    found in the as-built plans.

    Action item completed with modeling: The flap gate is modeled in SWMM.

    1.6 Observations from Anecdotal Information

    TxDOT and the City of Houston have received several reports of flooding in the

    Larchmont Subdivision located north of US 59 between Chimney Rock and South Rice,

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    22/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    15

    and in the US 59 SBFR at South Rice. According to contour information, the Larchmont

    neighborhood, US 59 SBFR, and South Rice are significantly lower than the elevations at

    Chimney Rock and Westpark. The Westpark storm sewer plans indicate that the top of

    the box culvert is the pavement for Westpark Drive. Using the survey information

    provided, the inside top of the Westpark storm sewer lines are higher than the ground

    elevations along the US 59 FR and South Rice and within the Larchmont subdivision.

    Considering that all of the outfalls tie to the Westpark system, these areas can flood due

    to backwater from the Westpark boxes.

    2 METHODOLOGY

    The TxDOT Hydraulic Design Manual (HDM), October 2011, was utilized as the

    primary methodological source for hydrologic and hydraulic analyses in this study.

    Supporting methodologies were also obtained from the HCFCD Criteria Manual.

    2.1 Hydrologic Approach

    The Rational Method is used for peak flow calculations because the study area has small

    watersheds unaffected by complex hydrologic features. The existing drainage areas were

    delineated using the project topography, aerial photography, as-built plans, City of

    Houston GIMS, LiDAR, and project survey data. The proposed drainage areas were

    delineated based on the proposed roadway profiles and cross section data. The existing

    and proposed drainage area maps are included in Appendix A.

    Runoff coefficients (C-values) reflect the land use as indicated on the project aerial

    photography and onsite observations. A composite C-value was determined for each of

    the areas.

    To compute Time of Concentration (Tc), the flow path was determined using available

    topographic information. The travel time along the flow path was calculated using the

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    23/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    16

    following velocities: 0.5 fps for overland flow, 1.5 fps for gutter/channelized flow, and

    3.0 fps for storm sewer flow. Tc is limited to >/= 10 minutes.

    Rainfall data is taken from Recommendations for Rainfall Amounts in Harris County,

    (TSARP White Papers (2002). The following are the Region 2 duration-depths for the

    watersheds in this study:

    Return Period (by Probability)

    Duration 50% 10% 4% 1%

    5 min 0.7 0.9 1.0 1.2

    15 min 1.1 1.5 1.7 2.1

    30 min 1.5 2.1 2.4 3.0

    60 min 2.0 2.9 3.4 4.3

    2 hr 2.3 3.6 4.3 5.7

    3 hr 2.6 4.1 5.0 6.7

    6 hr 3.1 5.1 6.4 8.912 hr 3.7 6.2 7.8 10.8

    24 hr 4.4 7.6 9.6 13.2

    Since the Rational Method produces only peak flow, additional methods are required to

    develop hydrographs and runoff volume. Two methods are used, depending on the size

    and location of the sub-area: Clark Unit Hydrograph Method, and the Small Watershed

    Method.

    The Clark Unit Hydrograph Method uses hydrologic parameters time of concentration

    and Tc and R. Tc is computed as described above. The Storage Coefficient (R factor) is

    adjusted to calibrate hydrograph peak to that computed by Rational Method. Rainfall

    loss method is Green and Ampt which uses parameters Initial Loss, Moisture Deficit,

    Suction, and Conductivity taken from Recommendation for Replacing HEC-1

    Exponential Loss Function in HEC-HMS, (TSARP White Papers, 2002) as standard for

    Buffalo Bayou and Brays Bayou. The following values are used:

    Initial Loss = 0.1 inches

    Volume Moisture Deficit = 0.385 (unitless)

    Wetting Front Suction = 12.45 inchesHydraulic Conductivity = 0.024 in/hr

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    24/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    17

    The percent impervious ground cover is based on land use as indicated in project aerial

    photography and field investigations. The computations using this unit hydrograph

    method are made in HEC-HMS v3.5. For this study, the 2-, 10-, 25-, and 100-yr flows

    were computed.

    The (Malcom) Small Watershed Method is used for sub-areas BR-1 and BR-2 that drain

    to Brays Bayou. This method is used to develop a curvilinear design hydrograph for

    drainage areas < 640 acres, which peaks at a designated flow rate, and contains a runoff

    volume consistent with the design rainfall. For more details on this method, see the

    HCFCD Policy Criteria & Procedure Manual (2010), Section 3.6.

    The HCFCD TSARP 24-hour rainfall and loss methods are used to determine the direct

    runoff volume for the Small Watershed Method. Runoff volumes for the study event

    (100-yr) were computed using excess rainfall based on percent impervious ground cover

    and rainfall by frequency.

    The Rational Method, HEC-HMS output, and hydrograph and volumecomputations are

    included in Appendix B.

    2.2 Hydraulic Approach

    SWMM (XP-Storm 2012 V14.01) is used for hydraulic modeling because it accepts a

    variety of drainage system components, such as externally-developed inflow hydrographs

    for various frequency events, pipes, channels, culverts, weirs, inlets, and detention

    facilities. The SWMM model uses a series of nodes and links to represent the physical

    characteristics of the drainage system. The drainage system parameters are input into the

    model through the Hydraulic mode of SWMM. The SWMM program offers several

    methods for incorporating the runoff hydrographs into Hydraulic mode, including those

    developed using the HEC-HMS and Small Watershed Method (SWM) at specific nodal

    locations (Nodes) of the drainage network. The Hydraulic mode is a hydraulic flow

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    25/272

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    26/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    19

    3 HYDROLOGIC SUMMARY

    3.1 Outfall Identification

    The IH 610 / US 59 interchange ultimately drains to Buffalo Bayou and Brays Bayou

    through several storm sewer connections. The focus of this report is on the following

    outfalls.

    Watershed Existing Outfall DescriptionApproximate B/L

    Station

    Existing Outfall

    Structure

    Buffalo Westpark box culverts to W129-00-00Chimney Rock to3050 E of IH 610

    2/10x7 RCB/2-12x8 RCB

    Brays IH 610 South (connection to SBFR) IH 610 ML 195+80 30 RCP

    Brays IH 610 South (connection to NBFR) IH 610 ML 174+00 60 RCP

    As indicated previously, the FRs in the NE and NW quadrants drain to the IH 610 North

    storm sewer. This outfall as well as the hydraulic study of the outfall channel W129-00-

    00 is being completed by AECOM.

    3.2 Outfall Summary

    The major outfall for the US 59/ IH 610 interchange is the Westpark box culverts. All of

    the area between Westpark and IH 610 within the US 59 corridor drains to the Westpark

    storm sewer through various connecting storm sewer systems. For this study, the

    analysis of the Westpark storm sewer begins just west of the intersection with Chimney

    Rock. The contributing drainage area upstream of this location is combined into one

    drainage area and is applied at this location. Several storm sewer lines cross under US 59

    and connect to the Westpark storm sewer. Some of the outfalls include drainage areas

    with flow only from the US 59 corridor contributing; however, there are several

    connections that carry offsite flow from north of the US 59 corridor to the Westpark

    system. The lines carrying both on and offsite flow include a 48 RCP and 60 RCP at

    Chimney Rock (Systems F and G), a 48 RCP at Barrington (System J), a 5x4 RCB and

    48 RCP at Yorktown (System L), a 60 RCP at S. Rice (System M), and a 48 RCP at

    McCue (System Q). According to the COH GIMS information, each of these lines was

    built in the 1950s.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    27/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    20

    Between S Rice and the US 59/IH 610 interchange, three detention ponds are included

    with the construction of the Westpark Tollway and the depressed connection to Post Oak

    Blvd. The two ponds along Westpark, DB6-1 to the east and DB6-2 to the west, are

    directly connected to the Westpark storm sewer system with low flow orifice openings

    and high flow overflow outlets. Although a small portion of the new Westpark Tollroad

    storm sewer is connected to the detention ponds, these ponds act more as an offline

    storage area for the Westpark storm sewer. The new storm sewer line along the southside

    of the Westpark Tollroad is connected to the Westpark system near the outlet of Pond

    DB6-1. The third detention pond, DB-7, is the outfall for the IH 610 SBFR and

    Westpark Tollroad depressed section through the use of a pump station. The contributing

    flow is pumped into Pond DB-7, and then conveyed through a 48 RCP into DB6-1.

    Between the two depressed FRs, several changes have occurred since the original

    construction to alter the flow paths; however, the only connection between the areas north

    and south of the US 59 MLs has remained. Two 36 RCP (System W) convey flow from

    the north to the south. The pipes discharge into a concrete lined channel where various

    other storm sewer lines (part of System H and part of System S) also outfall. A 54 flex

    valve is located at the downstream end of the concrete lined channel. A detention pond,

    Node 1-W16, beneath the IH 610 MLs is also connected to the channel through 2-36

    RCP. This acts as an offline storage area for the attenuated flow created by the flex

    valve. Downstream of the flex valve, a 6x6 RCB outfalls into the Westpark storm

    sewer system.

    Another detention pond, DB-8, is located under the IH 610 MLs south of US 59. This is

    the outfall for the depressed IH 610 NBFR and the US 59 MLs (System S) east of the

    depressed section to approximately US 59 Station 191+00 along the northbound lanes

    and 188+00 along the southbound lanes. This area also includes the at-grade US 59

    NBFR east of the depressed section to station 189+00 and the contributing offsite area.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    28/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    21

    A pump station conveys the flow to Pond DB-8 which is discharged to a 5x4 RCB to

    the Westpark system.

    Along Westpark, the roadway and adjacent properties between US 59 and Westpark

    contribute directly to the Westpark storm sewer through roadway inlets and other storm

    sewer lines. The flow for this area was placed in the Westpark system at various

    locations within the hydraulic model.

    South of Westpark, two major storm sewer lines run along each of the FRs to Cypress

    Ditch (HCFCD T115-00-00) which outfalls into Brays Bayou. A 30 storm sewer line

    crosses beneath IH 610 (Station 195+80) from the IH 610 NBFR to the IH 610 SBFR

    storm sewer trunkline. The drainage area for the 30 line includes a portion of the IH 610

    NB MLs from station 194+50 to 204+75, the IH 610 NBFR, and a portion of the

    proposed IH 610 NB/ US 59 SB direct connector. Analysis of the IH 610 SBFR

    trunkline is not part of this scope and is being completed as part of the Phase 1

    construction, designed by AFLP. Mitigation (see Sect. 5) of the additional flow will be

    completed upstream of the 30 RCP crossing.

    South of the 30 RCP crossing, a large storm sewer system along the IH 610 NBFR

    begins. The IH 610 South trunkline is located within the separation between the MLs and

    NBFR. Due to the construction of the proposed direct connector, this storm sewer line

    will need to be relocated between Station 175+00 and 188+00. Mitigation (see Sect. 5)

    of additional flow due to the increase in impervious cover will be completed using inline

    detention within the project limits.

    4 HYDRAULIC ANALYSIS

    Six major analyses were completed as part of this study with all of the frequencies

    examined. The six analyses are Existing Conditions with silt, Existing Conditions with no

    silt in Westpark Trunkline, Existing Conditions with W129 Stage 3, Proposed Conditions

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    29/272

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    30/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    23

    occur at the other frequencies. The US 59 SBFR, the Larchmont subdivision, and the

    South Rice/ US 59 intersection are flooded in the 2-yr event. A summary of elevations

    along the US 59 SBFR is shown below in Table 4.1a.

    Table 4.1a Existing with Silt WSEL v Ground Elevations

    Ex

    Silt

    WSEL

    (ft)

    Flood

    Depth

    (+/-)

    Ex

    Silt

    WSEL

    (ft)

    Flood

    Depth

    (+/-)

    Ex

    Silt

    WSEL

    (ft)

    Flood

    Depth

    (+/-)

    Ex

    Silt

    WSEL

    (ft)

    Flood

    Depth

    (+/-)

    4-A29 24.94 19.19 -5.75 40.31 15.37 49.89 24.95 56.44 31.50

    4-J8 29.20 20.80 -8.40 40.93 11.73 49.94 20.74 56.46 27.26

    4-JB2 34.32 30.37 -3.95 36.47 2.15 37.67 3.35 40.00 5.68

    1-F34 55.00 56.17 1.17 57.35 2.35 57.66 2.66 58.00 3.00

    1-G23 55.25 56.16 0.91 57.00 1.75 57.27 2.02 57.61 2.36

    1-J8 53.78 55.60 1.82 56.56 2.78 56.99 3.21 57.49 3.71

    1-J5 54.41 55.65 1.24 56.60 2.19 57.01 2.60 57.50 3.09

    1-L14 53.60 55.88 2.28 56.97 3.37 57.44 3.84 57.95 4.35

    1-L9a 54.91 55.74 0.83 56.63 1.72 57.02 2.11 57.49 2.58

    1-L9 54.90 55.71 0.81 56.79 1.89 57.26 2.36 57.80 2.90

    1-L11 54.28 55.75 1.47 56.63 2.35 57.02 2.74 57.48 3.20

    1-M9 54.53 55.67 1.14 56.56 2.03 56.97 2.44 57.45 2.92

    1-M7 53.62 55.67 2.05 56.56 2.94 56.97 3.35 57.45 3.83

    1-M5 55.00 55.62 0.62 56.52 1.52 56.94 1.94 57.43 2.43

    1-M12 54.00 55.63 1.63 56.51 2.51 56.92 2.92 57.40 3.40

    1-M16 54.75 55.62 0.87 56.51 1.76 56.92 2.17 57.39 2.64

    1-M19 55.00 55.63 0.63 56.49 1.49 56.89 1.89 57.36 2.36

    1-Q5 54.52 55.65 1.13 56.46 1.94 56.85 2.33 57.32 2.80

    1-Q4 54.52 55.80 1.28 56.39 1.87 56.78 2.26 57.25 2.72

    1-Q3 54.00 55.83 1.83 56.38 2.38 56.77 2.77 57.23 3.23

    1-Q7 54.50 55.19 0.69 55.74 1.24 56.13 1.63 56.58 2.08

    4-B11 24.94 37.81 12.87 42.47 17.53 49.89 24.95 56.44 31.50

    4-H3 54.35 54.70 0.35 54.84 0.48 54.88 0.53 56.44 2.09

    1-W18 54.00 52.88 -1.12 54.71 0.71 55.14 1.14 56.36 2.36

    1-W16 54.35 52.88 -1.47 54.63 0.28 55.17 0.82 56.40 2.05

    Pond DB7 55.21 55.46 0.25 55.86 0.65 55.88 0.66 57.09 1.881-W14 55.00 52.88 -2.12 54.63 -0.37 55.17 0.17 56.44 1.44

    Node

    2-yr 10-yr 25-yr 100-yr

    Ground

    El

    (ft)

    The elevation at 1-L14 is the ground elevation in the adjacent street is 53.60. The flowline (FL) of the existing 2-5x2RCB is 51.68.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    31/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    24

    The depressed sections do not flood at the 2-yr frequency although water does overtop

    the retaining walls at 4-H3 and Pond DB-7. The retaining walls near 1-W18 and 1-W14

    begin to overtop in the 10-yr frequency. A summary of the retaining wall elevations and

    water surface elevations in this area is shown below.

    Table 4.1b Existing WSEL v Retaining Wall Elevations

    NodeRetaining

    Wall ID

    Retaining Wall

    Overtopping

    Elevation (ft)

    2-yr

    WSEL (ft)

    10-yr

    WSEL (ft)

    25-yr

    WSEL (ft)

    100-yr

    WSEL (ft)

    4-H3 W-2 54.35 54.70 54.84 54.88 56.44

    1-W18 W-4 54.00 52.88 54.71 55.14 56.36

    1-W14 W-4 55.28 52.88 54.63 55.17 56.44

    Pond DB7 W-2 55.21 55.46 55.86 55.88 57.09

    As for the flooding witnessed in January of 2012, a preliminary analysis was completed

    for the 2-yr frequency with the 48 RCP turned off in the model. The results indicate that

    the IH 610 SBFR (node 4-J8) and the Westpark Tollway (node 4-A29) would be flooded.

    The depth of water at node 4-A29 is 31.86 and 32.18 at 4-J8. The retaining walls near

    inlet 4-H3 and at Pond DB-7 are also overtopped. Water does fill Pond DB6-1 but only

    through backflow from the Westpark system. Pond DB6-1 empties as the tailwater on

    the Westpark system recedes; however, Pond DB-7 and the depressed section remain full

    of water throughout the duration of the analysis.

    The Westpark storm sewer system appears to be balancing between the two boxes

    through the openings along the length of the box. If the silt levels are greater than 2, the

    orifices are also reduced. For this analysis, only a few of the orifice areas were reduced

    by the silt. The flows and elevations within the two boxes are slightly different but not

    significant.

    For the 10-, 25-, and 100- yr frequencies, flooding in the IH 610 SBFR/ Westpark

    Tollway occurs. A significant amount of flow from the McCue drainage area can flow

    into the depressed section through overland flow. The high point in the gutter line

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    32/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    25

    between McCue and the depressed section is 54.79. The 10-, 25-, and 100- yr elevations

    near McCue (node 1-Q7) are 55.74, 56.13, and 56.58, respectively. Flow begins to

    overtop the high point in the gutter at STA 161+00 and drains to the low point in the US

    59 SBFR (node 4-B11). The storm sewer in this area is connected to the IH 610 SBFR/

    Westpark Tollway storm sewer system. Therefore, the additional flow is being conveyed

    to the depressed section through storm sewer, and once the water surface elevation in this

    portion of the US 59 SBFR exceeds 43.20, overland flow into the depressed section

    occurs. The elevations at Nodes 4-A29 and 4-J8 are shown below.

    Table 4.1c Existing WSEL v Ground Elevations in Depressed Sections

    NodeGround El

    (ft)

    10-yr

    WSEL (ft)

    Flood Depth

    (ft)

    25-yr

    WSEL (ft)

    Flood Depth

    (ft)

    100-yr

    WSEL (ft)

    Flood Depth

    (ft)

    4-A29 24.94 40.31 15.37 49.89 24.95 56.44 31.50

    4-J8 29.20 40.93 11.73 49.94 20.74 56.46 27.26

    4-JB2 34.32 36.47 2.15 37.67 3.35 40.00 5.68

    The IH 610 NBFR depressed section is flooded in the 10-, 25-, and 100-yr events.

    Additional flow from the IH 610 NBFR at grade FR and the US 59 SBFR east of IH 610

    drains toward the depressed section storm sewer system. Once the water surface

    elevation in this quadrant reaches 53.00, overland flow into the depressed section occurs.

    At the SE quadrant, additional overland flow from the east approaches the storm sewer

    system near the Houston Chronicle building. At an elevation of 51.50, overland flow

    into the depressed section occurs.

    The pump stations for each of the depressed sections do not meet the 25-yr design storm.

    For the west pump station, the adequacy of the pump station in the existing conditions

    cannot be determined with the additional flow that overtops the retaining walls and

    overland flow from the McCue area. The links representing the overtopping of theretaining walls and overland flow were turned off so the pump station could be more

    accurately analyzed, assuming that unintended overflows are not present. For the 25-yr

    event, the water surface elevation at node 4-A29 is 21.46, which is below the low point

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    33/272

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    34/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    27

    trunkline, and the box heights and orifices adjusted to as-built sizes. This analysis

    demonstrates the results that regular maintenance of the Westpark Trunkline would have

    on the overall system. A comparison between the existing with silt and existing without

    silt at some of the critical locations is shown in Table 4.2a.

    Table 4.2a Existing with Silt WSEL v Existing without Silt WSEL

    Ex

    Silt

    WSEL

    (ft)

    Ex

    No Silt

    WSEL

    (ft)

    (+/-)

    Ex

    Silt

    WSEL

    (ft)

    Ex

    No Silt

    WSEL

    (ft)

    (+/-)

    Ex

    Silt

    WSEL

    (ft)

    Ex

    No Silt

    WSEL

    (ft)

    (+/-)

    Ex

    Silt

    WSEL

    (ft)

    Ex

    No Silt

    WSEL

    (ft)

    (+/-)

    4-A29 19.19 18.72 -0.48 40.31 35.78 -4.53 49.89 42.65 -7.24 56.44 55.99 -0.45

    4-J8 20.80 20.63 -0.18 40.93 36.97 -3.96 49.94 42.68 -7.25 56.46 56.00 -0.46

    4-JB2 30.37 30.32 -0.06 36.47 36.23 -0.24 37.67 37.41 -0.27 40.00 39.87 -0.121-J5 55.65 55.13 -0.52 56.60 56.42 -0.18 57.01 56.74 -0.27 57.50 57.26 -0.24

    1-L9 55.71 55.11 -0.60 56.79 56.62 -0.17 57.26 56.97 -0.29 57.80 57.54 -0.26

    1-M5 55.62 55.22 -0.40 56.52 56.38 -0.14 56.94 56.68 -0.26 57.43 57.19 -0.24

    1-Q3 55.83 55.66 -0.17 56.38 56.21 -0.16 56.77 56.51 -0.26 57.23 57.00 -0.23

    4-B11 40.58 37.49 -3.09 42.47 41.78 -0.69 49.89 42.71 -7.17 56.44 55.99 -0.45

    4-H3 54.70 54.60 -0.10 54.84 54.81 -0.04 54.88 54.85 -0.03 56.44 55.99 -0.45

    Pond DB7 55.46 53.80 -1.66 55.86 55.84 -0.01 55.88 55.87 -0.01 57.09 56.39 -0.70

    1-W18 52.88 52.32 -0.56 54.71 54.31 -0.40 55.14 54.96 -0.17 56.36 55.89 -0.47

    Node

    2-yr 10-yr 25-yr 100-yr

    Maintenance of the Westpark trunkline does reduce water surface elevations within thestudy limits; however, it does not eliminate the flooding problems along the US 59 SBFR

    and adjacent properties or the flooding within the IH 610 SBFR/Westpark Tollway

    depressed section. The IH 610 NBFR system is not affected by the changes at W129-00-

    00. A comparison of the flood depths at some of the critical locations is shown in Table

    4.2b.

    Supplemental Tables 2.1 through 2.4 are available in Appendix C of the electronic file

    included on the CD of the report.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    35/272

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    36/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    29

    00-00 were provided by AECOM and include the HCFCD Stage 3 improvements to

    W129-00-00. (See AECOMs report Hydrologic & Hydraulic Analysis: IH 610 W/US

    59 S Interchange North Drainage Elements, CSJ: 0271-17-145 for details).

    The analysis shows the tailwater along the Westpark storm sewer line is reduced, and in

    turn, water surface elevations along the US 59 SBFR and in the IH 610 SBFR/Westpark

    Tollway depressed sections are also reduced. A comparison between the existing with

    silt and phase 3 at some of the critical locations is shown below.

    Table 4.3a Existing with Silt WSEL v Existing with Stage 3 WSEL

    Ex

    Silt

    WSEL(ft)

    Ex

    Stage 3

    WSEL(ft)

    (+/-)

    Ex

    Silt

    WSEL(ft)

    Ex

    Stage 3

    WSEL(ft)

    (+/-)

    Ex

    Silt

    WSEL(ft)

    Ex

    Stage 3

    WSEL(ft)

    (+/-)

    Ex

    Silt

    WSEL(ft)

    Ex

    Stage 3

    WSEL(ft) (+/-)

    4-A29 19.19 18.72 -0.48 40.31 29.82 -10.49 49.89 40.65 -9.24 56.44 55.92 -0.51

    4-J8 20.80 20.61 -0.18 40.93 30.15 -10.79 49.94 41.16 -8.78 56.46 56.03 -0.42

    4-JB2 30.37 29.93 -0.44 36.47 35.74 -0.73 37.67 37.00 -0.67 40.00 39.77 -0.23

    1-J5 55.65 54.67 -0.98 56.60 56.04 -0.56 57.01 56.57 -0.44 57.50 57.15 -0.35

    1-L9 55.71 54.68 -1.03 56.79 56.14 -0.64 57.26 56.78 -0.48 57.80 57.39 -0.41

    1-M5 55.62 54.92 -0.70 56.52 55.94 -0.58 56.94 56.51 -0.43 57.43 57.06 -0.37

    1-Q3 55.83 55.56 -0.27 56.38 56.07 -0.31 56.77 56.33 -0.44 57.23 56.86 -0.38

    4-B11 40.58 37.44 -3.14 42.47 39.54 -2.94 49.89 42.54 -7.35 56.44 55.92 -0.51

    4-H3 54.70 54.59 -0.11 54.84 54.79 -0.05 54.88 54.83 -0.05 56.44 56.04 -0.40

    Pond DB7 55.46 53.00 -2.46 55.86 55.74 -0.12 55.88 56.00 0.13 57.09 56.53 -0.56

    1-W18 52.88 51.99 -0.89 54.71 54.59 -0.12 55.14 55.44 0.30 56.36 56.44 0.08

    Node

    2-yr 10-yr 25-yr 100-yr

    Adding the Stage 3 improvements to W129-00-00 alone will not solve the flooding

    problems along the US 59 SBFR and adjacent properties or the flooding within the IH

    610 SBFR/Westpark Tollway depressed section. The IH 610 NBFR system is not

    affected by the changes at W129-00-00. A comparison of the flood depths at some of the

    critical locations is shown in Table 4.3b.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    37/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    30

    Table 4.3b Existing with Stage 3 WSEL v Ground Elevations

    Ex

    Stage 3

    WSEL

    (ft)

    (+/-)

    Ex

    Stage 3

    WSEL

    (ft)

    (+/-)

    Ex

    Stage 3

    WSEL

    (ft)

    (+/-)

    Ex

    Stage 3

    WSEL

    (ft)

    (+/-)

    4-A29 24.94 18.72 -6.23 29.82 4.88 40.65 15.71 55.92 30.98

    4-J8 29.20 20.61 -8.59 30.15 0.95 41.16 11.96 56.03 26.83

    4-JB2 34.32 29.93 -4.39 35.74 1.42 37.00 2.68 39.77 5.45

    1-F34 55.00 55.19 0.19 56.76 1.76 57.25 2.25 57.73 2.73

    1-G23 55.25 55.32 0.07 56.73 1.48 56.96 1.71 57.33 2.08

    1-J8 53.78 54.64 0.86 55.99 2.21 56.55 2.77 57.11 3.33

    1-J5 54.41 54.67 0.26 56.04 1.63 56.57 2.16 57.15 2.74

    1-L14 53.60 54.76 1.16 56.33 2.73 56.95 3.35 57.56 3.96

    1-L9a 54.91 54.66 -0.25 56.11 1.20 56.61 1.70 57.15 2.24

    1-L9 54.90 54.68 -0.22 56.14 1.24 56.78 1.88 57.39 2.49

    1-L11 54.28 54.77 0.49 56.10 1.82 56.60 2.32 57.15 2.87

    1-M9 54.53 54.94 0.41 55.97 1.44 56.53 2.00 57.09 2.56

    1-M7 53.62 54.94 1.32 55.97 2.35 56.53 2.91 57.09 3.47

    1-M5 55.00 54.92 -0.08 55.94 0.94 56.51 1.51 57.06 2.06

    1-M12 54.00 54.95 0.95 55.94 1.94 56.50 2.50 57.04 3.04

    1-M16 54.75 54.97 0.22 55.94 1.19 56.49 1.74 57.03 2.28

    1-M19 55.00 55.01 0.01 55.93 0.93 56.47 1.47 57.00 2.00

    1-Q5 54.52 55.50 0.98 55.92 1.40 56.43 1.91 56.95 2.43

    1-Q4 54.52 55.55 1.03 56.04 1.52 56.35 1.83 56.87 2.35

    1-Q3 54.00 55.56 1.56 56.07 2.07 56.33 2.33 56.86 2.86

    1-Q7 54.50 55.10 0.60 55.41 0.91 55.71 1.21 56.21 1.714-B11 24.94 37.44 12.50 39.54 14.60 42.54 17.60 55.92 30.98

    4-H3 54.35 54.59 0.24 54.79 0.44 54.83 0.48 56.04 1.69

    1-W18 54.00 51.99 -2.01 54.59 0.59 55.44 1.44 56.44 2.44

    1-W16 54.35 51.98 -2.37 54.59 0.24 55.43 1.08 55.95 1.60

    Pond DB7 55.21 53.00 -2.21 55.74 0.53 56.00 0.79 56.53 1.32

    1-W14 55.00 51.98 -3.02 54.59 -0.41 55.41 0.41 55.93 0.93

    Node

    2-yr 10-yr 25-yr 100-yr

    Ground

    El

    (ft)

    The elevation at 1-L14 is the ground elevation in the adjacent street is 53.60. The flowline (FL) of the existing 2-5x2RCB is 51.68.

    Summaries of the SWMM results are included in Appendix C Tables 3.1 through 3.4.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    38/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    31

    4.4 Proposed Conditions with W129 Stage 3

    The proposed conditions model with Stage 3 analysis includes the Westpark storm sewer

    system with the as-built box and orifice heights as well as the tailwater for the completed

    Stage 3 improvements to W129-00-00. It also contains several improvements within the

    TxDOT ROW to reduce the flooding within the corridor and the adjacent properties. It

    also mitigates the proposed increases in impervious cover for the ultimate US 59/IH 610

    interchange.

    As part of the realignment of the US 59 NB/IH 610 SB direct connector in Phase 1 Job

    157, AFLP has proposed the removal of the embankment and 48 restrictor between

    Ponds DB6-1 and DB-7. This change was implemented in this analysis prior to making

    any other proposed updates. The new detention pond reduces the water surface elevation

    in the vicinity of the retaining wall (wall elevation =55.21) for the 2-yr storm, but not

    enough to avoid overtopping the wall. The 10- and 25-yr elevations are higher than the

    existing elevations at Pond DB-7. This is due to the backwater from the Westpark storm

    sewer system filling the pond which will allow more water to overflow to the depressed

    section. A comparison of the elevations at existing Pond DB-7 and the AFLP proposed

    Pond DB6-1 is shown in Table 4.4a. A comparison of elevations within the depressed

    section at Node 4-A29 is also shown below in Table 4.4b. Supplemental Tables 4.1

    through 4.4 are available in Appendix D of the electronic file included on the CD of the

    report.

    Table 4.4a Existing WSEL v Existing with AFLP Pond DB6-1

    Location2-yr

    WSEL (ft)

    10-yr

    WSEL (ft)

    25-yr

    WSEL (ft)

    100-yr

    WSEL (ft)

    Existing Pond DB-7 55.46 55.86 55.88 57.09

    Existing Pond DB6-1 55.39 56.35 56.80 57.35

    Existing w/ AFLP Pond DB6-1 55.18 56.17 56.62 56.97

    DB-7 Change in WSEL (ft) -0.27 0.31 0.74 -0.12

    DB6-1 Change in WSEL (ft) -0.20 -0.18 -0.19 -0.38

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    39/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    32

    Table 4.4b Node 4-A29 Elevation Comparison

    Location2-yr

    WSEL (ft)

    10-yr

    WSEL (ft)

    25-yr

    WSEL (ft)

    100-yr

    WSEL (ft)

    Existing Node 4-A29 19.19 40.31 49.89 56.44

    Existing w/ AFLP Pond at Node 4-A29 18.90 41.13 50.95 56.24

    4-A29 Change in WSEL (ft) -0.30 0.81 1.07 -0.20

    It is recommended that the retaining wall adjacent to the existing Pond DB7 should be

    raised to elevation 57 to avoid overtopping during the Phase 1 Job 157 construction.

    Coordination with AFLP should be completed to determine the limits of the effected

    retaining wall and proposed detention pond limits and volume modeled within this report.

    At Node 4-H3, overflow of the adjacent retaining wall (wall elevation =54.35) will

    continue to occur. Without additional storage volume at 4-H3 and a flex valve on the

    existing 24 RCP outfall into Pond DB6-1 (see Section 4.4.3), the overtopping cannot be

    stopped without causing the US 59 MLs to flood. The construction of the detention pond

    as discussed below cannot be constructed until Phase 1 Job 146, which removes the

    existing IH 610 NB/ US 59 SB direct connector. It appears that some excavation at 4-H3

    could be completed during Phase 1 Job 157 construction without disturbing the

    embankment; however, the effect of those improvements have not been analyzed. A

    comparison of elevations at Node 4-H3 is shown in Table 4.4c.

    Table 4.4c Node 4-H3 Elevation Comparison

    Location2-yr

    WSEL (ft)

    10-yr

    WSEL (ft)

    25-yr

    WSEL (ft)

    100-yr

    WSEL (ft)

    Existing Node 4-H3 54.70 54.84 54.88 56.44

    Existing w/ AFLP Pond at Node 4-H3 54.68 54.82 54.87 56.24

    4-H3 Change in WSEL (ft) -0.02 -0.02 -0.01 -0.20

    Reduction of the tailwater is critical in reducing the flooding within the US 59 corridor

    and the adjacent properties. Two options were analyzed during the development of this

    report. First, an analysis was completed that would meet the 10-yr storm event along the

    US 59 SBFR. This option would require 2-10 x 10 RCB along the US 59 SB FR,

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    40/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    33

    modifications to the detention ponds DB6-1 and DB6-2 to include vertical walls and

    excavation to elevation 30.00, and the construction of a new pump station to de-water

    the ponds and storm sewer. This option is undesirable due to several reasons. First of all,

    the water table in the interchange is very high. Seepage through the walls in the

    depressed section has been noted. Therefore, excavation to an elevation approximately

    15 deeper than the existing detention pond would not likely be feasible. Without the

    possibility of deepening the detention pond, the large storm sewer boxes cannot be

    placed. The flowline of the box culverts would need to be significantly lower to place

    below the proposed pavement elevations. Another factor against this option is

    constructability near the Rice Blvd overpass. A single 10 x 10 RCB can be placed

    under the overpass; however, the depth of the RCB interferes with many utilities. Also,

    the proposed routing of the box along the US 59 NB MLs cannot be done at the depth

    needed. The width of the ROW is limited between a retaining wall and several

    businesses. Through coordination with LJA, it was determined that the integrity of the

    retaining wall could be compromised with the parallel placement of the 10 x 10 RCB.

    The limited ROW would not allow room for the storm sewer to be placed at a distance

    that would not have effects on the retaining wall.

    The second option would also require larger trunklines along the US 59 SB FR, but

    would maintain gravity drainage of detention ponds DB6-1 and DB6-2. Due to the slight

    slope of the terrain and the minimal depth of the existing storm sewer system, a 10-yr

    storm event cannot be obtained with this option. Therefore, a 2-yr storm sewer design for

    the US 59 SB FR was developed, with the proposed recommendations that follow.

    4.4.1 Increase Detention Pond at W16

    First of all, Pond 1-W16 is expanded to include Pond DB-8 and the additional area

    available due to the realignment of the IH 610 NB/ US 59 SB direct connector in Phase 1

    Job 146. Approximately 22.86 ac-ft of storage volume is available at this location.

    Additional volume could be realized by adding a retaining wall along the IH 610 NB/ US

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    41/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    34

    59 NB DC, however, the additional volume is not significant enough to have an impact

    on the water surface elevations within the US 59 corridor or the adjacent properties. The

    outlet from Pond 1-W16 will be the existing 5x4 RCB that currently serves as the outlet

    from Pond DB-8. The current outfall for Pond 1-W16, 2-36 RCP that enter the concrete

    lined channel, should be removed. This pond will now act as an offline storage area for

    the Westpark storm sewer system. A detention pond layout is provided in Appendix E.

    4.4.2 Detention Pond at W18

    A detention pond north of US 59 is also planned at Node 1-W18. The maximum water

    surface elevation of 55.00 is controlled by the existing US 59 MLs. The amount of

    drainage area that can be directed to this detention pond is restricted by the two depressed

    sections; therefore, additional flow from the south side of US 59 will be allowed to backup into the north pond through the existing 2-36 RCP. The outflow from the east pump

    station will be redirected to the concrete lined channel just downstream of the 2-36 RCP.

    A berm should be placed along the retaining wall on the west side so flow will not

    overtop the retaining wall. For this analysis, it is assumed that retaining walls can be

    placed along the DCs in the NE (Phase 2) and NW (Phase 1 Job 145) quadrants to

    maximize the size of the detention pond. Approximately 38.19 ac-ft of storage volume is

    available after Phase 2. This pond will also be utilized as mitigation volume for the

    AECOM part of the study. A layout for this detention pond is also included in Appendix

    E. An additional pond layout is also provided to show the limits of the detention pond

    that can be constructed as part of Phase 1 Job 145. This alternate layout provides

    approximately 28.68 ac-ft of detention.

    4.4.3 Detention Pond at 4-H3

    The gravity line between Inlet 4-H3 and the proposed Pond DB6-1 must remain in the

    proposed conditions. A flex valve should be placed at the downstream end of the gravityline to eliminate backflow through the system. A small detention pond is proposed in the

    separation between the US 59 MLs and the IH 610 SB/US 59 SB direct connector to

    create storage volume for the runoff to this area. The inlet 4-H3 should be removed and

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    42/272

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    43/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    36

    US 59 at South Rice. The trunkline will then turn toward the east, parallel the US 59 NB

    MLs, and discharge into Pond DB6-2.

    4.4.5 Trench Drain along IH 610 SB/US 59 SB Direct Connector

    Trench drain is proposed along the barrier of the IH 610 SB/US 59 SB direct connector to

    capture mainlane flow and direct it toward the detention pond at 4-H3. In the existing

    conditions, this area drains into a small concrete lined channel between the frontage road

    and the direct connector. During the 10-yr storm event, the water overflows into the

    depressed section along the US 59 SB FR and contributes to the flooding of the IH 610

    SB FR/Westpark Tollroad depressed section. With the adjustment to the frontage road

    profile, the edge of the direct connector cannot be drained to the concrete channel. The

    low point in the direct connector edge of pavement is approximately 53.90. Trenchdrain is proposed between Station 360+00 and 363+50. This line should outfall into the

    detention pond 4-H3. The results show that the water surface elevation in the 100-yr

    storm will be 54.45, which allows 1 lane of the direct connector to be passable.

    4.4.6 Increase Detention Storage at Ponds DB6-1 and DB6-2

    The detention ponds DB6-1 and DB6-2 should be regraded and reshaped within the

    available area to provide the maximum volume. The flowlines of Pond DB6-1 and DB6-

    2 are proposed at elevations 47.64 and 47.50, respectively. The ultimate configuration

    at Pond DB6-2 can be completed in Phase 1 Job 157. Pond DB6-1 will need to be phased

    with a majority of the pond completed during Phase 1 Job 157. During Phase 2 of the

    interchange reconstruction, Pond DB6-1 should excavated beyond the limits of the Phase

    1 Job 157 definition to the edge of the existing HOV lane. This step assumes that the US

    59 NB/ IH 610 NB DC can be reconfigured in the future construction to increase the

    length of the bridge. (AECOM is investigating this proposed change.) The ultimate

    storage available in each of the ponds is 49.26 ac-ft at Pond DB6-1 and 10.84 ac-ft atPond DB6-2. Pond layouts for Phase 1 Job 157 and Phase 2 conditions are included in

    Appendix E.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    44/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    37

    4.4.7 Increase Height of Retaining Walls along IH 610 SBFR/Westpark Tollroad

    To eliminate the overflows of the retaining walls, it is recommended that the wall heights

    are raised or protected by earthen berms. The wall along proposed Pond DB6-1 should

    be raised to approximately elevation 57 at all locations south of US 59. North of US 59

    adjacent to the proposed pond at 4-H3, the retaining wall should be protected up to

    elevation 55. Along the east side of the Westpark depressed lanes, the walls both north

    and south of US 59 should be raised or protected to elevation 56 as part of Job 146.

    These changes will keep water from overflowing the walls at all frequencies analyzed.

    4.4.8 Pump Station Modifications

    The pump station on/off elevations should be adjusted to allow the pumps to perform

    more effectively. With the overland flow and overtopping of the retaining walls

    eliminated, the IH 610 SBFR/ Westpark Tollroad is not flooded in the 25-yr storm

    frequency. A comparison of the on/off elevations for the existing and proposed

    conditions at Pump Station PS-4 is shown in Table 4.4d.

    Table 4.4d Pump Station PS-4 Existing V Proposed On/Off Elevations

    On El (ft) Off El (ft) On El (ft) Off El (ft)

    1 17.12 14.12 22.50 8.752 18.62 17.12 23.00 8.43

    Sump 5.69 3.04 5.69 3.04

    Existing ProposedPump

    For the IH 610 NBFR, several changes to the on/off elevations were made to reduce the

    flooding; however, the changes did not alleviate flooding in the 25-yr event. A change to

    the storm sewer routing is proposed to reduce the drainage area to the pump station. First

    of all, approximately 48% of the flow for P4-J42 will be redirected to a new storm sewer

    line as proposed in the AECOM (Job 145) study. This storm sewer line will drain to the

    east and directly into W129. This will eliminate several acres of offsite and US 59 ML

    and FR flow from being directed towards the pump station. Also, a proposed 42 storm

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    45/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    38

    sewer line is proposed to disconnect the existing trunkline along the US 59 NB MLs from

    the pump station system and reroute it directly to the Westpark trunkline. The routing of

    this line is shown in Appendix D. The line will need to pass under the METRO HOV

    lane and under the existing US 59 NB FR using jack and/or bore to avoid disruptions to

    traffic. Approximately 0.05 ac of ROW will be needed for construction of this line.

    With this adjustment, the depressed lanes will meet the 25-yr criteria. A comparison of

    the on/off elevations for the existing and proposed conditions at Pump Station PS-5 is

    shown in Table 4.4e.

    Table 4.4e Pump Station PS-5 Existing V Proposed On/Off Elevations

    On El (ft) Off El (ft) On El (ft) Off El (ft)1 22.45 20.70 27.50 18.75

    2 22.70 21.95 30.00 19.00

    3 24.70 22.95 32.00 18.65

    4 26.70 23.70 32.50 18.55

    Sump 16.64 15.64 16.64 15.64

    Existing ProposedPump

    A comparison of the water surface elevations to the ground levels within the depressed

    section are shown in Table 4.4f. Water surface elevations between the existing and

    proposed conditions are shown in Table 4.4g.

    Table 4.4f Proposed WSEL v Ground Elevations in Depressed Sections

    NodeGround El

    (ft)

    10-yr

    WSEL (ft)

    Flood

    Depth (ft)

    25-yr

    WSEL (ft)

    Flood

    Depth (ft)

    100-yr

    WSEL (ft)

    Flood

    Depth (ft)

    4-A29 24.94 24.68 -0.27 24.82 -0.12 37.91 12.97

    4-J8 29.20 24.87 -4.34 25.03 -4.17 38.04 8.84

    4-JB2 34.32 33.18 -1.14 33.50 -0.82 33.60 -0.73

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    46/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    39

    Table 4.4g Proposed WSEL v Existing WSEL in Depressed Sections

    Node

    10-yr

    EX

    WSEL

    (ft)

    10-yr

    PR

    WSEL

    (ft)

    Change

    in

    Depth

    (ft)

    25-yr

    EX

    WSEL

    (ft)

    25-yr

    PR

    WSEL

    (ft)

    Change

    in

    Depth

    (ft)

    100-yr

    EX

    WSEL

    (ft)

    100-yr

    PR

    WSEL

    (ft)

    Change

    in

    Depth

    (ft)

    4-A29 40.31 24.68 -15.64 49.89 24.82 -25.07 56.44 37.91 -18.53

    4-J8 40.93 24.87 -16.07 49.94 25.03 -24.91 56.46 38.04 -18.41

    4-JB2 36.47 33.18 -3.29 37.67 33.50 -4.17 40.00 33.60 -6.40

    With these proposed changes, water surface elevations within the project limits are

    greatly reduced when compared to existing conditions. Comparison of the Existing with

    Silt and the Proposed with Phase 3 is shown below in Table 4.4h. The proposed

    improvements also meet the 2-yr frequency for the frontage roads and the 25-yr in the

    depressed sections. The water surface elevations for the improvements compared to the

    ground elevations at critical locations are also shown below in Table 4.4i. Summaries of

    the SWMM results are included in Appendix D Tables 5.1 through 5.4.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    47/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    40

    Table 4.4h Existing with Silt WSEL v Proposed with Stage 3 WSEL

    Ex

    Silt

    WSEL(ft)

    Pr

    Stage 3

    WSEL(ft)

    (+/-)

    Ex

    Silt

    WSEL(ft)

    Pr

    Stage 3

    WSEL(ft)

    (+/-)

    Ex

    Silt

    WSEL(ft)

    Pr

    Stage 3

    WSEL(ft)

    (+/-)

    Ex

    Silt

    WSEL(ft)

    Pr

    Stage 3

    WSEL(ft)

    (+/-)

    4-A29 19.19 23.05 3.86 40.31 24.68 -15.64 49.89 24.82 -25.07 56.44 37.91 -18.53

    4-J8 20.80 23.13 2.33 40.93 24.87 -16.07 49.94 25.03 -24.91 56.46 38.04 -18.41

    4-JB2 30.37 30.98 0.61 36.47 33.18 -3.29 37.67 33.50 -4.17 40.00 33.60 -6.40

    1-J8 55.60 53.23 -2.37 56.56 55.61 -0.96 56.99 56.30 -0.70 57.49 57.06 -0.43

    1-J5 55.65 53.07 -2.58 56.60 55.64 -0.96 57.01 56.36 -0.65 57.50 57.05 -0.44

    1-L14 55.88 52.90 -2.99 56.97 55.82 -1.15 57.44 56.67 -0.77 57.95 57.38 -0.57

    1-L6 55.74 52.92 -2.82 56.64 55.68 -0.96 57.02 56.37 -0.65 57.49 57.05 -0.44

    1-L9 55.71 53.06 -2.65 56.79 55.72 -1.07 57.26 56.45 -0.81 57.80 57.12 -0.69

    1-M9 55.67 52.88 -2.79 56.56 55.63 -0.93 56.97 56.33 -0.64 57.45 57.04 -0.40

    1-M7 55.67 52.88 -2.79 56.56 55.60 -0.96 56.97 56.31 -0.66 57.45 57.04 -0.41

    1-M5 55.62 52.85 -2.77 56.52 55.59 -0.93 56.94 56.29 -0.66 57.43 57.04 -0.391-M12 55.63 52.84 -2.78 56.51 55.59 -0.92 56.92 56.29 -0.64 57.40 57.04 -0.37

    1-Q5 55.65 52.85 -2.80 56.46 55.57 -0.88 56.85 56.27 -0.58 57.32 57.02 -0.30

    1-Q3 55.83 52.85 -2.98 56.38 55.57 -0.80 56.77 56.27 -0.50 57.23 57.02 -0.22

    1-Q7 55.19 52.85 -2.34 55.74 55.57 -0.17 56.13 56.27 0.15 56.58 57.01 0.43

    4-B11 37.81 37.15 -0.66 42.47 37.39 -5.09 49.89 37.47 -12.42 56.44 42.18 -14.26

    4-H3 54.70 50.05 -4.65 54.84 51.72 -3.12 54.88 52.68 -2.20 56.44 54.36 -2.09

    1-W18 52.88 50.36 -2.53 54.71 51.62 -3.09 55.14 52.73 -2.41 56.36 55.41 -0.95

    1-W16 52.88 50.83 -2.05 54.63 51.92 -2.71 55.17 53.19 -1.98 56.40 55.55 -0.86

    Pond W16 52.88 52.42 -0.47 54.64 55.09 0.44 55.17 55.76 0.58 56.40 56.53 0.12

    Pond DB6-1 55.39 52.63 -2.76 56.35 55.31 -1.04 56.80 56.02 -0.79 57.35 56.80 -0.55

    1-W14 52.88 50.86 -2.02 54.63 51.93 -2.70 55.17 53.28 -1.89 56.44 55.53 -0.91

    Node

    2-yr 10-yr 25-yr 100-yr

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    48/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Elements, CSJ: 0271-17-146

    41

    Table 4.4i Proposed with Stage 3 WSEL V Ground Elevations

    Pr

    Stage 3

    WSEL

    (ft)

    Flood

    Depth

    (+/-)

    Pr

    Stage 3

    WSEL

    (ft)

    Flood

    Depth

    (+/-)

    Pr

    Stage 3

    WSEL

    (ft)

    Flood

    Depth

    (+/-)

    Pr

    Stage 3

    WSEL

    (ft)

    Flood

    Depth

    (+/-)

    4-A29 24.94 23.05 -1.89 24.68 -0.27 24.82 -0.12 37.91 12.97

    4-J8 29.20 23.13 -6.07 24.87 -4.34 25.03 -4.17 38.04 8.84

    4-JB2 34.32 30.98 -3.34 33.18 -1.14 33.50 -0.82 33.60 -0.73

    1-F34 55.00 55.14 0.13 56.45 1.45 57.05 2.05 57.66 2.66

    1-G23 55.25 54.95 -0.30 56.36 1.11 56.50 1.25 57.08 1.83

    1-J8 53.78 53.23 -0.55 55.61 1.83 56.30 2.52 57.06 3.28

    1-J5 54.11 53.07 -1.04 55.64 1.53 56.36 2.25 57.05 2.94

    1-L14 53.60 52.90 -0.70 55.82 2.22 56.67 3.07 57.38 3.78

    1-L6 54.19 52.92 -1.27 55.68 1.49 56.37 2.18 57.05 2.86

    1-L9 55.04 53.06 -1.98 55.72 0.68 56.45 1.41 57.12 2.08

    1-L11 56.04 52.90 -3.14 55.67 -0.37 56.36 0.32 57.05 1.01

    1-M9 54.77 52.88 -1.89 55.63 0.85 56.33 1.56 57.04 2.27

    1-M7 54.54 52.88 -1.66 55.60 1.06 56.31 1.77 57.04 2.50

    1-M5 54.94 52.85 -2.09 55.59 0.65 56.29 1.35 57.04 2.10

    1-M12 54.36 52.84 -1.52 55.59 1.23 56.29 1.93 57.04 2.68

    1-Q5 55.06 52.85 -2.21 55.57 0.51 56.27 1.21 57.02 1.96

    1-Q3 55.48 52.85 -2.63 55.57 0.09 56.27 0.79 57.02 1.54

    1-Q7 55.80 52.85 -2.95 55.57 -0.23 56.27 0.47 57.01 1.21

    4-B11 40.58 37.15 -3.43 37.39 -3.19 37.47 -3.11 42.18 1.60

    4-H3 55.00 50.05 -4.95 51.72 -3.28 52.68 -2.33 54.36 -0.64

    1-W18 55.00 50.36 -4.65 51.62 -3.38 52.73 -2.27 55.41 0.411-W16 55.00 50.83 -4.17 51.92 -3.08 53.19 -1.81 55.55 0.55

    Pond W16 58.00 52.42 -5.59 55.09 -2.92 55.76 -2.24 56.53 -1.47

    Pond DB6-1 58.00 52.63 -5.37 55.31 -2.69 56.02 -1.99 56.80 -1.20

    1-W14 57.00 50.86 -6.14 51.93 -5.07 53.28 -3.72 55.53 -1.47

    Node

    2-yr 10-yr 25-yr 100-yr

    Ground

    El

    (ft)

    The elevation at 1-L14 is the ground elevation in the adjacent street is 53.60. The flowline (FL) of the existing 2-5x2

    RCB is 51.68.

    4.5 Proposed Conditions with Silt

    The proposed conditions model with silt analysis includes all of the proposed drainage

    improvements discussed in the proposed conditions with Stage 3 analysis, but also

    includes the silt levels within the Westpark storm sewer line and the existing W129-00-

    00 conditions.

  • 7/26/2019 Hydrologic and Hydraulic Report TxDOT

    49/272

    Hydrologic & Hydraulic Analysis

    IH 610 W/ US 59 S Interchange South Drainage Element