IEM Daily Field Report Prepared By: Joseph Spinelli IEM Representative Page 1 of 4 Signed In Signed Out Southwest Brooklyn Marine Transfer Station 1824 Shore Parkway Brooklyn, New York 11214 Date: April 19, 2016 Inspector: Joseph Spinelli Location / Description: Project #: URLI1401 Site Time: 0650 to 1530 Assigned by: SPD Day Weather General Site Conditions Monday Thursday Clear Snow Warm Clear Tuesday Friday Overcast Windy Hot Muddy Wednesday Rain Cold Temperature Range: 61 ºF to 70 ºF General Contractor: Prismatic Development Corporation (PDC) Construction Manager: URS / LiRo G/C Name: Richard Tonnensen CM Name: Michael Balarezo / Michael Pokorny S/C&S/C Supervisor: NA CM Phone #: 917-983-5608 / 917-983-5616 Equipment and Machinery in Use (1) : Crane(s) Elevating Work Platform Forklift with extendable arm (Lull) (1) List of equipment and machinery is based on field observations and is not inclusive of every equipment and machinery that may have been present at the site. Personnel on Site (1) : Personnel Organization Personnel Organization Personnel PDC Mike Balarezo URS / LiRo Robert Amrhein Certified Safety Mike Pokorny URS / LiRo Nelson Mendez EnTech Nabil Saadi URS / LiRo Pavlos Kominakos Total Safety Consultant Roberto Vazquez URS / LiRo Personnel AEL, Presco, Stonebridge, Giaquinto, National Fireproofing Victor Bogatyrev URS / LiRo Andrew Port Louis Berger Tom Karas URS / LiRo Erdal Gurten Greeley and Hanson Smita Day H2M (1) List of personnel on site is based on field observations and is not inclusive of every personnel that may have been present at the site. Observations: Time Stamp Details Time On Site: 6:50 am 6:50 am Four air monitoring stations were set up at perimeter locations specified by the CM, forming a quadrangle around the anticipated work area. According to EnTech, air monitoring is occurring at the four air monitoring stations beginning at 6:25 am. The air monitoring station locations are depicted on the Sketch. 7:00 am to 3:15 pm GC installing rebar and wooden formwork for the construction of the elevated ramp in the eastern section of the site. 7:00 am to 3:15 pm GC removing scaffolding from underneath the ramp in the northeastern section of the site. 7:00 am to 3:00 pm Presco bending and installing rebar on the ramp in the eastern section of the site. A crane and forklift is utilized to move the rebar onto the elevated ramp.

Upload: buikhuong

Post on 05-Jul-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: IEM Daily Field Report · 2017-01-13 · National Fireproofing ... IEM Daily Field Report SKETCH ... Microsoft Word - 2016-04-19 IEM DFR.docx

IEM Daily Field Report

Prepared By: Joseph Spinelli IEM Representative

Page 1 of 4

Signed In Signed Out Southwest Brooklyn Marine Transfer Station

1824 Shore Parkway Brooklyn, New York 11214

Date: April 19, 2016 Inspector: Joseph Spinelli Location /

Description:

Project #: URLI1401 Site Time: 0650 to 1530 Assigned by: SPD

Day Weather General Site Conditions

Monday Thursday Clear Snow Warm Clear

Tuesday Friday Overcast Windy Hot Muddy

Wednesday Rain Cold Temperature Range: 61 ºF to 70 ºF

General Contractor: Prismatic Development Corporation (PDC) Construction Manager: URS / LiRo

G/C Name: Richard Tonnensen CM Name: Michael Balarezo / Michael Pokorny

S/C&S/C Supervisor: NA CM Phone #: 917-983-5608 / 917-983-5616

Equipment and Machinery in Use(1):

Crane(s)

Elevating Work Platform

Forklift with extendable arm (Lull) (1) List of equipment and machinery is based on field observations and is not inclusive of every equipment and machinery that may have been present at the site.

Personnel on Site(1):

Personnel Organization Personnel Organization

Personnel PDC Mike Balarezo URS / LiRo

Robert Amrhein Certified Safety Mike Pokorny URS / LiRo

Nelson Mendez EnTech Nabil Saadi URS / LiRo

Pavlos Kominakos Total Safety Consultant Roberto Vazquez URS / LiRo

Personnel AEL, Presco, Stonebridge, Giaquinto,

National Fireproofing Victor Bogatyrev URS / LiRo

Andrew Port Louis Berger Tom Karas URS / LiRo

Erdal Gurten Greeley and Hanson Smita Day H2M (1) List of personnel on site is based on field observations and is not inclusive of every personnel that may have been present at the site.

Observations:

Time Stamp Details

Time On Site: 6:50 am

6:50 am Four air monitoring stations were set up at perimeter locations specified by the CM, forming a quadrangle around the anticipated work area. According to EnTech, air monitoring is occurring at the four air monitoring stations beginning at 6:25 am. The air monitoring station locations are depicted on the Sketch.

7:00 am to 3:15 pm GC installing rebar and wooden formwork for the construction of the elevated ramp in the eastern section of the site.

7:00 am to 3:15 pm GC removing scaffolding from underneath the ramp in the northeastern section of the site.

7:00 am to 3:00 pm Presco bending and installing rebar on the ramp in the eastern section of the site. A crane and forklift is utilized to move the rebar onto the elevated ramp.

Page 2: IEM Daily Field Report · 2017-01-13 · National Fireproofing ... IEM Daily Field Report SKETCH ... Microsoft Word - 2016-04-19 IEM DFR.docx

Day / Date: Tuesday / April 19, 2016 Client: URS / LiRo H2M Project No.: URLI1401

Prepared By: Joseph Spinelli IEM Representative

Page 2 of 4

7:00 am to 2:30 pm National Fireproofing spraying fireproofing materials on the ceiling of the first floor of the main building on the concrete foundation slab.

7:00 am to 2:00 pm Stonebridge utilizing two cranes and elevating work platforms in the northern and southern sections of the site to install structural steel in the northwestern, eastern, and central sections of the concrete foundation slab. Stonebridge welding structural steel in the western section of the site.

7:00 am to 3:15 pm Giaquinto building interior cinder block walls for the main building in the northern section of the concrete foundation slab. Cement mixing and concrete block cutting in the northeastern section of the concrete foundation slab.

7:30 am

EnTech observed visible dust in the northwestern section of the site, near air monitoring station, B4. According to EnTech, a forklift that was transporting materials around the site kicked up dust in the vicinity of the air monitoring station. According to EnTech, the dust generated by the forklift dissipated within 2 feet of the forklift (and remained on site). EnTech reported the observation of visible dust to the CM (Nabil Saadi).

7:35 am to 8:20 am The GC is filling up the water tank truck with water from the fire hydrant located on Bay 41st Street.

8:20 am The GC implemented dust suppression by wetting down the ground surface in the northern section of the site with water from the water tank truck.

9:30 am to 10:00 am & 12:00 pm to 12:30 pm

Site work stops for a work break.

3:30 pm Site work stops for the day. EnTech removes air monitoring stations.

Time Off-Site: 3:30 pm

General Observations:

According to EnTech, particulate matter and total organic vapors were not detected at concentrations greater than the action levels.

The GC was observed implementing dust suppression at the site by wetting down the ground surface with water from the water tank truck at 8:20 am and 1:00 pm.

Issues discussed this date with Construction Manager: None.

Persons Contacted: N/A

Status: N/A

Notes: N/A

Page 3: IEM Daily Field Report · 2017-01-13 · National Fireproofing ... IEM Daily Field Report SKETCH ... Microsoft Word - 2016-04-19 IEM DFR.docx

IEM Daily Field Report

SKETCH

Prepared By: Joseph Spinelli IEM Representative

Page 3 of 4

`

Approximate Location of Air Monitoring Stations B3.

Approximate Location of Air Monitoring Stations B2.

Approximate Location of Air Monitoring Stations B1.

Approximate Location of Air Monitoring Stations B4.

Approximate location of interior cinder block wall installation

Approximate location of removal of scaffolding underneath the ramp

Approximate location of rebar and wooden formwork for ramp construction

Approximate location of structural steel installation

Page 4: IEM Daily Field Report · 2017-01-13 · National Fireproofing ... IEM Daily Field Report SKETCH ... Microsoft Word - 2016-04-19 IEM DFR.docx

IEM Daily Field Report

PHOTOGRAPH LOG

Prepared By: Joseph Spinelli IEM Representative

Page 4 of 4