installation at isolde (and costs)

19
Installation at Isolde (and costs) TSR at Isolde workshop CERN, 29/30 October 2012 TSR @ Isolde Erwin Siesling

Upload: darena

Post on 22-Feb-2016

92 views

Category:

Documents


0 download

DESCRIPTION

TSR @ Isolde. Installation at Isolde (and costs). TSR at Isolde workshop CERN, 29/30 October 2012. Erwin Siesling. TSR @ ISOLDE. TSR Max Planck Institute Heidelberg. TSR@ISOLDE LOI endorsed Jan 2011 TDR submitted Jan 2012 (K . Blaum , Y. Litvinov ) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Installation at Isolde (and costs)

Installation at Isolde (and costs)

TSR at Isolde workshop

CERN, 29/30 October 2012

TSR @ Isolde

Erwin Siesling

Page 2: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 2

TSR Max Planck Institute

Heidelberg

TSR @ ISOLDE

TSR@ISOLDELOI endorsed Jan 2011 TDR submitted Jan 2012 (K. Blaum, Y. Litvinov)CERN BE TSR Integration Study Mandate Aug 2012

Page 3: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 3

Layout

Jura

Saleve

Page 4: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 4

Building position

10m restriction

F/CH border

F

CH courtesy Didier Voulot

Page 5: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 5

Jura (west) side

24.6m23.3m

Proposed layout to fit the TSR and experiments at the west side

Page 6: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 6

Jura (west) sideTotal surface TSR floor: 24.6x23.3m=573m2 of which 20x20m (400m2) reserved for the ring (final position of the ring within the building to be defined)

Level of the center of beam at 1.77m above TSR floor

Total surface available basement: 12mx24.6m=295m2to house power-supplies and additional racks

Difficulties:Construction above the CERN service tunnel (which cannot be re-routed):TSR Floor approx. 4 m above the HIE Linac floor

Page 7: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 7

Proposed layout to fit the TSR and experiments at the east side

CH F

Saleve (east) side

21.8 m

33.6 m

11.8 m

28.2 m

Page 8: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 8

Saleve (east) side

Total surface TSR floor: 747m2 of which 20x20m (400m2) reserved for the ring (final position of the ring within the building to be defined) TSR floor at same level as the Hie Linac floor

Level of the center of beam at 1.77m above TSR floor 

Difficulties:Basement to add to house the necessary power-supplies and equipment Adaptation of existing buildings

Take in account the possible removal of the cold box, etc from building 199 and necessary access to the experimental hall: removal of the Cryo Modules, etc. Passages to be kept free

Requires construction (about 100m2) within the restricted area of 10m from the French border

22.6m

34.9 m

28.9m

Page 9: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 9

Proposed layout to fit the TSR:Installation above the CERN service-tunnelTilted beamline coming up from the machine.

Building cost & design study:Eliseo Perez-Duenas GS/SE

30m25m

4.1m above Isolde hall floor

final TSR building

Jura (west) side

10m (7m between floor and crane hook)

Page 10: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 10

TSR Building

Courtesy: Eliseo Perez-Duenas GS/SE

Page 11: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 11

Surface & WeightTotal surface TSR floor: 25x30m=750m2 of which 20x20m (400m2) reserved for the ring (final position of the ring within the building to be defined)

TSR floor 4.1m above Hie Linac floor

Level of the center of beam at 1.77m above TSR floor

TSR Building surface

Total surface available basement: 13.2mx30m=396m2 to house power-supplies and additional racks (total 29m length floor space for the TSR equipment and 7m for the e-target equipment + 10 standard 19’’ racks and ECOOL HV cage 4x4m2)Basement only under outer side of the service tunnel

 

Page 12: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 12

Surface & WeightWeight in each corner:Dipole: iron 12t + coil 0.8tQuadrupole: iron 1.9t + coil 0.36tSextupole: 0.65tConcrete bases 3.2t (to be verified, unknown)Each corner:2x12.8t + 5x2.26t + 3x0.65t + 2x3.2t= 45.25 ton Electron cooler:ECOOL magnet 6tECOOL supporting structure 4t (to be verified, unknown), total 10ton Total TSR floor weight:4x45.25ton=181ton1 Electron coolerTotal: 191 ton(Exclusive experiments, RF resonator and 19 standard 19’’ racks. Example: HELIOS magnet 12ton)

TSR floor weight

Page 13: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 13

Transfer lines

courtesy Fredrik Wenander / Didier Voulot

Standard HIE Isolde parts

Page 14: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 14

Control room

TSR Integration

TSR building

TSR cooling station

pit

TSR transformer

TSR integration: - TSR building, TSR cooling station & compressed air, TSR transformer

Page 15: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 15

TSR costsBuilding costs: Estimate 3.85 MChfThe civil engineering study is ongoing (Eliseo Perez-Duenas, CERN, GS/SE) 20t Overhead crane: not less than 300kChf (25 m wide, 20t, over 30m) (Caterina Bertone, CERN, EN/HE) Water station: 1MW 27C rough estimate 700kChf (Yannic Body, CERN, EN/CV)A few elements need 20C: some turbo pumps at inj and ej which could run at 27C and additional fan cooling, however, the cryo-compressors need 5kW of 20C water and the high power solenoid for the e-cooling as well Transfer Line: (Injection line 1385kChf, Ejection line 915kChf = 2.3MChf) - preliminaryWill be re-calculated in case of the use of standard HIE Isolde parts (HEBT lines)(Fredrik Wenander, CERN, BE/ABP) Infrastructure: ventilation, electricity – no numbers yet – inventory and requirements study ongoing (TSR Integration study group) FTE’s – no numbers yet.

Page 16: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling

Erwin Siesling

Emiliano Piselli

Fredrik Wenander

• Inventory equipment

• Initial estimates for infrastructure (not detailed)

• Brief study for each system in order to be integrated at

CERN

• Report ready by Q3 2013

In it's June meeting the CERN Research Board gave outline approval to the TSR@Isolde project. This outline approval requests that CERN undertakes an integration study to identify early the requirements for the initial installation together with the necessary modifications and upgrades needed to eventually be able to run the TSR as a standard CERN facility. A TSR Integration Study Working Group has been put in place to make an inventory of the actual components of the storage ring, its equipment and necessary infrastructure.

TSR integration study

Page 17: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling

TSR integration studyMagnet kickersSlow power suppliesBeam diagnosticsVacuumE-coolerAlignmentRPMagnetsSeptum and kickersAlignmentRFControls Application programmesInjection and extraction linesGeneral infrastructure Experimental lineGeneral layout at CERNConnection to HIE-ISOLDEDismantling, transport, reassembly

Page 18: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling

TSR integration study

Page 19: Installation at Isolde (and costs)

TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 19

Acknowledgement

• MPIK : KLAUS BLAUM, MANFRED GRIESER, YURI LITVINOV• GS/SE : DANIEL PARCHET, ELISEO PEREZ-DUENAS• EN/MEF : STEPHANE MARIDOR• BE/ABP : FREDERIK WENANDER • BE/OP : DIDIER VOULOT• PH/SME : YORICK BLUMENFELD, MARIA BORGE• BE/RF : MATTEO PASINI, MATTHEW FRASER• EN/CV : YANNIC BODY• EN/HE : CATERINA BERTONE• EN/EL : RENE NECCA