installation at isolde (and costs)
DESCRIPTION
TSR @ Isolde. Installation at Isolde (and costs). TSR at Isolde workshop CERN, 29/30 October 2012. Erwin Siesling. TSR @ ISOLDE. TSR Max Planck Institute Heidelberg. TSR@ISOLDE LOI endorsed Jan 2011 TDR submitted Jan 2012 (K . Blaum , Y. Litvinov ) - PowerPoint PPT PresentationTRANSCRIPT
Installation at Isolde (and costs)
TSR at Isolde workshop
CERN, 29/30 October 2012
TSR @ Isolde
Erwin Siesling
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 2
TSR Max Planck Institute
Heidelberg
TSR @ ISOLDE
TSR@ISOLDELOI endorsed Jan 2011 TDR submitted Jan 2012 (K. Blaum, Y. Litvinov)CERN BE TSR Integration Study Mandate Aug 2012
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 3
Layout
Jura
Saleve
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 4
Building position
10m restriction
F/CH border
F
CH courtesy Didier Voulot
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 5
Jura (west) side
24.6m23.3m
Proposed layout to fit the TSR and experiments at the west side
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 6
Jura (west) sideTotal surface TSR floor: 24.6x23.3m=573m2 of which 20x20m (400m2) reserved for the ring (final position of the ring within the building to be defined)
Level of the center of beam at 1.77m above TSR floor
Total surface available basement: 12mx24.6m=295m2to house power-supplies and additional racks
Difficulties:Construction above the CERN service tunnel (which cannot be re-routed):TSR Floor approx. 4 m above the HIE Linac floor
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 7
Proposed layout to fit the TSR and experiments at the east side
CH F
Saleve (east) side
21.8 m
33.6 m
11.8 m
28.2 m
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 8
Saleve (east) side
Total surface TSR floor: 747m2 of which 20x20m (400m2) reserved for the ring (final position of the ring within the building to be defined) TSR floor at same level as the Hie Linac floor
Level of the center of beam at 1.77m above TSR floor
Difficulties:Basement to add to house the necessary power-supplies and equipment Adaptation of existing buildings
Take in account the possible removal of the cold box, etc from building 199 and necessary access to the experimental hall: removal of the Cryo Modules, etc. Passages to be kept free
Requires construction (about 100m2) within the restricted area of 10m from the French border
22.6m
34.9 m
28.9m
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 9
Proposed layout to fit the TSR:Installation above the CERN service-tunnelTilted beamline coming up from the machine.
Building cost & design study:Eliseo Perez-Duenas GS/SE
30m25m
4.1m above Isolde hall floor
final TSR building
Jura (west) side
10m (7m between floor and crane hook)
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 10
TSR Building
Courtesy: Eliseo Perez-Duenas GS/SE
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 11
Surface & WeightTotal surface TSR floor: 25x30m=750m2 of which 20x20m (400m2) reserved for the ring (final position of the ring within the building to be defined)
TSR floor 4.1m above Hie Linac floor
Level of the center of beam at 1.77m above TSR floor
TSR Building surface
Total surface available basement: 13.2mx30m=396m2 to house power-supplies and additional racks (total 29m length floor space for the TSR equipment and 7m for the e-target equipment + 10 standard 19’’ racks and ECOOL HV cage 4x4m2)Basement only under outer side of the service tunnel
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 12
Surface & WeightWeight in each corner:Dipole: iron 12t + coil 0.8tQuadrupole: iron 1.9t + coil 0.36tSextupole: 0.65tConcrete bases 3.2t (to be verified, unknown)Each corner:2x12.8t + 5x2.26t + 3x0.65t + 2x3.2t= 45.25 ton Electron cooler:ECOOL magnet 6tECOOL supporting structure 4t (to be verified, unknown), total 10ton Total TSR floor weight:4x45.25ton=181ton1 Electron coolerTotal: 191 ton(Exclusive experiments, RF resonator and 19 standard 19’’ racks. Example: HELIOS magnet 12ton)
TSR floor weight
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 13
Transfer lines
courtesy Fredrik Wenander / Didier Voulot
Standard HIE Isolde parts
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 14
Control room
TSR Integration
TSR building
TSR cooling station
pit
TSR transformer
TSR integration: - TSR building, TSR cooling station & compressed air, TSR transformer
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 15
TSR costsBuilding costs: Estimate 3.85 MChfThe civil engineering study is ongoing (Eliseo Perez-Duenas, CERN, GS/SE) 20t Overhead crane: not less than 300kChf (25 m wide, 20t, over 30m) (Caterina Bertone, CERN, EN/HE) Water station: 1MW 27C rough estimate 700kChf (Yannic Body, CERN, EN/CV)A few elements need 20C: some turbo pumps at inj and ej which could run at 27C and additional fan cooling, however, the cryo-compressors need 5kW of 20C water and the high power solenoid for the e-cooling as well Transfer Line: (Injection line 1385kChf, Ejection line 915kChf = 2.3MChf) - preliminaryWill be re-calculated in case of the use of standard HIE Isolde parts (HEBT lines)(Fredrik Wenander, CERN, BE/ABP) Infrastructure: ventilation, electricity – no numbers yet – inventory and requirements study ongoing (TSR Integration study group) FTE’s – no numbers yet.
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling
Erwin Siesling
Emiliano Piselli
Fredrik Wenander
• Inventory equipment
• Initial estimates for infrastructure (not detailed)
• Brief study for each system in order to be integrated at
CERN
• Report ready by Q3 2013
In it's June meeting the CERN Research Board gave outline approval to the TSR@Isolde project. This outline approval requests that CERN undertakes an integration study to identify early the requirements for the initial installation together with the necessary modifications and upgrades needed to eventually be able to run the TSR as a standard CERN facility. A TSR Integration Study Working Group has been put in place to make an inventory of the actual components of the storage ring, its equipment and necessary infrastructure.
TSR integration study
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling
TSR integration studyMagnet kickersSlow power suppliesBeam diagnosticsVacuumE-coolerAlignmentRPMagnetsSeptum and kickersAlignmentRFControls Application programmesInjection and extraction linesGeneral infrastructure Experimental lineGeneral layout at CERNConnection to HIE-ISOLDEDismantling, transport, reassembly
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling
TSR integration study
TSR@Isolde, CERN 29/30 Oct 2012 Erwin Siesling 19
Acknowledgement
• MPIK : KLAUS BLAUM, MANFRED GRIESER, YURI LITVINOV• GS/SE : DANIEL PARCHET, ELISEO PEREZ-DUENAS• EN/MEF : STEPHANE MARIDOR• BE/ABP : FREDERIK WENANDER • BE/OP : DIDIER VOULOT• PH/SME : YORICK BLUMENFELD, MARIA BORGE• BE/RF : MATTEO PASINI, MATTHEW FRASER• EN/CV : YANNIC BODY• EN/HE : CATERINA BERTONE• EN/EL : RENE NECCA