[email protected] managing director endesa trading · investment in gas-fired generation juan j alba...

37
Investment in gas-fired generation Juan J Alba [email protected] Managing Director Endesa Trading March 25th, 2003 IEA/NEA Workshop on Power generation investment in liberalised electricity markets

Upload: others

Post on 01-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Investment in gas-fired generation

    Juan J [email protected] DirectorEndesa Trading

    March 25th, 2003IEA/NEA Workshop on Power generation investment in liberalised electricity markets

  • 2

    Contents

    • The CCGT: the response for generation capacity needs

    • Electricity: market, risks, regulation

    • Gas: the market environment

    • Are markets signals adequate for investment?

    • Some final thoughts

  • 3Source: Cambridge Energy Research Associates.* Dependable Capacity Margin calculated by subtracting Peak to Dependable Capacity, then dividing by peak demand. The calculation uses 50 percent of InstalledHydro Capacity with the exception of Finland, Luxembourg, Norway, and Sweden which are calculated using 90 percent of Hydro Capacity.20801-3

    Total Capacity MW

    Peak Demand MW

    Dependable Reserve Margin*%

    France

    111.2

    77.0

    28.8%

    Belgium14.8%

    12.915.6Germany

    105.8

    78.2

    20.1%

    Netherlands

    33.4%14.2

    19.4

    Luxembourg

    1.60.9 62.2%

    Portugal

    19.1%7.411.1

    Spain

    54.1

    Italy

    21.3%

    51.9

    75.8

    Greece

    -10.1%8.69.5

    Austria

    8.236.2%

    Switzerland9.6%

    9.717.3

    14.2%

    34.9

    16.8

    Sweden

    31.726.8

    11.4%Finland

    24%13.3

    16.8

    Norway

    9.0%

    23.027.9

    Denmark

    12.46.269.2%

    UnitedKingdom

    34.0%

    57.0

    78.8

    Ireland

    4.64.0 15.4%

    The reservemargin in

    Europeseems to be

    high

    The Capacity Situation in Western EuropeNo immediate needs for massive capacity additions

  • 4

    Reserve Margin140%

    134%

    126%

    120%

    114%

    101%

    105%

    106%

    1996 1997 1998 1999 2000 2001 2002 2003

    Peak Dem and 37.350 MW (14/01/03); 18:57 h)

    Capacity Insta lled Dependable

    Nuclear 7.888 7.092

    Coa l 11.565 9.851

    Fue l-Gas 7.594 5.024

    CCGT 3.032 1.518 * *

    Hydro (Conv) 13.918 8.100 *

    Hydro (Pum p) 2.788 1.940

    Eolic 4.830 175

    Others (cogen & renew ) 6.874 4.130

    T ota l 58.489 37.830

    Reserve Margin 1,3%

    (* ) Last 5 years average

    (* * ) Capacity reduced due to natura l gas

    constra ints

    Reserve M arg in in stress scenario

    The situation is not uniformReserve margin evolution in Spain

  • 5

    Hydro

    Classic

    Nuclear

    0

    20

    40

    60

    80

    100

    120

    140

    Hydro

    Classic

    Nuclear

    Hydro

    Classic

    Nuclear

    0

    20

    40

    60

    80

    100

    120

    140

    Hydro

    Classic

    Nuclear

    Hydro

    Classic

    Nuclear

    0

    20

    40

    60

    80

    100

    120

    140

    Hydro

    Classic

    Nuclear

    Hydro

    Classic

    Nuclear

    0

    20

    40

    60

    80

    100

    120

    140

    Hydro

    Classic

    Nuclear

    Installed capacity (GW)

    Expected French demand (2010)

    GW

    BASE (Nuclear, 7200 G

    WBASE (Nuclear, 7200

    GW

    BASE (Nuclear, 7200

    20

    40

    60

    80

    100

    GW

    BASE (Nuclear, 7200 G

    WBASE (Nuclear, 7200

    GW

    GW

    20

    40

    60

    80

    100

    GW

    GW

    GW

    GW

    20

    40

    60

    80

    100

    GW

    GW

    SEMI BASE (Coal, 4000)

    BASE (Nuclear, 7200

    PEAK (Hydro, 2000 hours)Potential NEEDS

    GW

    BASE (Nuclear, 7200 G

    WBASE (Nuclear, 7200

    GW

    BASE (Nuclear, 7200

    20

    40

    60

    80

    100

    GW

    BASE (Nuclear, 7200 G

    WBASE (Nuclear, 7200

    GW

    GW

    20

    40

    60

    80

    100

    GW

    GW

    GW

    GW

    20

    40

    60

    80

    100

    GW

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    8000

    GW

    SEMI BASE (Coal, 4000)

    BASE (Nuclear, 7200

    PEAK (Hydro, 2000 hours)Potential NEEDS

    hours

    But even France could need some capacity

  • 6

    Efficiency (%)

    30

    35

    40

    45

    50

    55

    60

    Gas turbine Coal CoalSuper-critical

    Gas-oil CCGT

    33-38

    30-43 40-44

    40-49

    48-60

    0

    500

    1000

    1500

    2000

    Hydro Nuclear Coal CCGT

    1500-1800

    1200-1500

    900-1100

    450-600

    CCGT is the most attractive technology becauseof economics...

    Investment(Eur/MWh)

  • 7

    00,20,4

    Kgr

    /tep

    Carb

    ón

    Petr

    oleo

    Gas

    Natu

    ral

    Particles

    0

    40

    80

    Kgr

    /tep

    Car

    bón

    Petr

    oleo

    Gas

    Nat

    ural

    SO2

    05

    10

    Kgr

    /tep

    Carb

    ón

    Petr

    oleo

    Gas

    Natu

    ral

    NOx

    025005000

    Kgr

    /tep

    Carb

    ón

    Petr

    oleo

    Gas

    Natu

    ral

    CO2

    ... and environmental impact

  • 8

    Scandinavia

    CentralEurope

    Britain

    IberiaItaly

    Electricity: market and regulatory environmentEurope has already moved from national toregional markets...

    • Two very mature and integratedmarkets in Britain andScandinavia

    • The largest market is in CentralEurope➔ Germany, France, Benelux,

    Switzerland, Austria ...➔ Size, location

    • Iberia and Italy are relativelyisolated➔ But this will change

  • 9

    Scandinavia

    CentralEurope

    Britain

    IberiaItaly

    Electricity: market and regulatory environment...with different market arrangements

    NordPool: power exchange + futuresStrong OTC

    Started with pool, now scrapedStrong OTC

    Power exchanges

    Fundamentally OTC, Most liquidity in GermanyPower exchanges in Germany, France,

    Netherlands, Austria

    PoolIberian market

    Bilateral activity scarce but increasing

    Will start with poolWhat next?

  • 10

    Electricity: market and regulatory environmentGermany and France are the core of thecontinental power markets

    Baseload Cal 02

    20.00

    20.50

    21.00

    21.50

    22.00

    22.50

    23.00

    23.50

    24.00

    24.50

    17/05

    /2001

    24/05

    /2001

    31/05

    /2001

    07/06

    /2001

    14/06

    /2001

    21/06

    /2001

    28/06

    /2001

    05/07

    /2001

    12/07

    /2001

    19/07

    /2001

    26/07

    /2001

    02/08

    /2001

    09/08

    /2001

    16/08

    /2001

    23/08

    /2001

    30/08

    /2001

    06/09

    /2001

    13/09

    /2001

    20/09

    /2001

    27/09

    /2001

    04/10

    /2001

    11/10

    /2001

    18/10

    /2001

    25/10

    /2001

    01/11

    /2001

    08/11

    /2001

    15/11

    /2001

    22/11

    /2001

    29/11

    /2001

    06/12

    /2001

    Eur/M

    Wh

    FranceGermany

    • Germany was the first bilateral wholesale market in continental Europe➔ Started in 1998, currently around 1500 TWh/year➔ Volumes stabilised or reduced since Enron’s collapse➔ Much speculative trading, but greatly reduced after the fall of American traders

    • The French bilateral market is growing rapidly➔ Started in 2001, now around 200 TWh/year➔ Has kept growing, a less speculative market, closer to the physical delivery

  • 11

    European Power Exchanges are growing fastNow, as spot markets, tomorrow as futures

    • LPX (Germany)➔ Accounts for 5% of

    German Demand➔ Averaged Hourly depth

    is 2500 MWh• EEX (Germany)

    ➔ 0,5% of GermanDemand; Depth of 260MWh

    • APX (Netherlands)➔ 12-15% of Dutch

    consumption.➔ Hourly depth of 1500

    MWh• PowerNext (France)

    ➔ Depth of 280 MWh➔ Accounts for less than

    0,5% of FrenchDemand

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500

    week

    25we

    ek 30

    week

    35we

    ek 40

    week

    45we

    ek 50

    week

    2we

    ek 7

    week

    12we

    ek 17

    week

    22we

    ek 27

    week

    32we

    ek 37

    week

    42we

    ek 47

    week

    52we

    ek 5

    week

    10we

    ek 15

    week

    20

    Agg

    rega

    ted

    Wee

    kly

    Vol

    ume,

    GW

    h

    LPX EEX APX PowerNext

    2002

  • 12

    7 €

    2 €

    European Power Exchanges are growing fastThe supply and demand curve in Powernext• Currently the profile of the offer curve of the peak hours is very steep.

    An small variation in the demand leads to high variations in price• The off-peak hours offer curve show a flatter profile

  • 13

    7,00

    27,00

    47,00

    67,00

    87,00

    107,00

    ene-

    98

    may

    -98

    sep-

    98

    ene-

    99

    may

    -99

    sep-

    99

    ene-

    00

    may

    -00

    sep-

    00

    ene-

    01

    may

    -01

    sep-

    01

    ene-

    02

    may

    -02

    sep-

    02

    ene-

    03

    euro

    / M

    Wh

    0

    1.000

    2.000

    3.000

    4.000

    5.000

    6.000

    7.000

    8.000

    9.000

    GW

    h

    Daily Weighted Average Price (E/MWh)

    Hydro Energy (GWh)

    There is also a strongcorrelation between

    hydro conditions, priceand volatility

    After all, hydroconditions are a short

    term distorsion ofreserve margin, withan underlying long

    term hydro availablecapacity

    Hydro conditions are a major driver of electricityprices, and therefore a risk factorSpanish pool price Price spikesnormal in the short term

    (electricity cannot be stored)

  • 14

    PRODUCCION HIDRAULICA DEL SISTEMA2000-2001-2002

    500

    1.500

    2.500

    3.500

    4.500

    5.500

    6.500

    ENER

    O

    FEBR

    ERO

    MARZ

    O

    ABRI

    L

    MAYO

    JUNI

    O

    JULIO

    AGOS

    TO

    SEPT

    IEMB

    RE

    OCTU

    BRE

    NOVI

    EMBR

    E

    DICI

    EMBR

    EEn

    ergí

    a(G

    Wh/

    mes

    )

    Año 2001: 36.503 GWh

    Año 2000: 24.883 GWh

    Año 2002: 18.572 GWh

    Hydro conditions are a major driver of electricityprices, and therefore a risk factorSpanish hydro production

  • 15

    Fuel- gas/hydro production & Spanish pool price

    0.000

    1.000

    2.000

    3.000

    4.000

    5.000

    6.000

    7.000

    0.0% 2.0% 4.0% 6.0% 8.0% 10.0% 12.0% 14.0%

    Participación del fuel en MD

    Prec

    io (c

    €/kW

    h)

    0.000

    1.000

    2.000

    3.000

    4.000

    5.000

    6.000

    7.000

    0.0% 5.0% 10.0% 15.0% 20.0% 25.0% 30.0% 35.0% 40.0%

    Participación del agua en la cobertura

    Prec

    ios

    (c€/

    kWh)

    There is a non-linear relation betweenthe share of fuel-oil production and

    pool price. The “discontinueties” arerelated with points at which fuel-oilstarts to be essential for demand

    coverage

    With high hydro productions,marginal price is set by stable coalprice. With decreasing hydro levels,

    the volatility of fuel price is perceived

  • 16

    Possible environmental impact in pool prices

    Investment

    Fixed costs

    Fuel Costs

    Other variable costs

    Emissions costs

    (Euros/tCO2)

    (Euros/MWh)

    (MWh/h)

    Ci

    (Euros/MWh)

    (MWh/h)

    Ci

    Cf

    Depending in the type of

    fuel and the efficiency of

    the plant, emission costs

    will have an impact as an

    additional variable cost

    and therefore on

    wholesale prices (?)

    +

  • 17

    1998 1999 2000 2001 2002

    Reserve MarginPool Price (98 base)Customer Price (98 base)

    But, does the wholesale price really matter?The example of Spain

    Pool price has adequatelyreflected the balance of supplyand demand forces:

    •Decreasing reserve margin•Changing hydro conditions•Fuel prices•Increasing LTMC

    However, this evolution of poolprice has had no effectwhatsoever on prices to finalcustomers

  • 18

    61,1 58,9 60,362,9

    67,5

    39,838,240,241,0 39,8

    1998 1999 2000 2001 2002

    Régimen Ordinario Régimen Especial

    10,5%

    -3,0%

    The effect of regulationRevenues of generation in Spain (eur/MWh)

  • 19

    7,8 7,5

    5,6

    4,6 4,5

    1998 1999 2000 2001 2002

    -42,3%

    The effect of regulationThe capacity payment in Spain (eur/MWh)

  • 20REE (83)

    CHAOS

    Elkraft (00)

    GRTN (00)

    Elia (01)

    RTE (00)

    REN (94)

    National Grid (90)

    EirGrid (99) Fingrid (96)Statnett (92)

    SVK (92)

    TenneT (98)

    Verbund (88)

    Electricity: market and regulatory environmentA variety of system operators...

  • 21Spanish Pool (OMEL) (98)

    EEX (00)

    APX (99)

    Italy: no yet

    Belgium: no yet

    Greece: no wayPortugal: no yet

    England & Wales Pool (90)now! NETA (01)

    Nordpool (93)

    Austria: EXAAPowerNext (01)

    Ireland: no yet

    Electricity: market and regulatory environment...power exchanges...

  • 22CNE (94)

    Germany: ??

    Dte (99)

    OFGEM (86)

    E-CONTROL (01)

    CRE (00)

    CREG (00)

    ERSE (97)

    AEEG (96)

    CER (99)

    Electricity: market and regulatory environment...and regulatory entities

  • 23

    25 - 35 €/MWh

    23 - 28 €/MWh

    28 - 35 €/MWh25 - 33 €/MWh

    23 - 28 €/MWh

    20 - 25 €/MWh

    20 - 25 €/MWh

    35 - 40 €/MWh

    23 - 28 €/MWh

    15 - 35 €/MWhNuclear

    GasFuel-Oil

    CoalHydro

    Electricity: market and regulatory environmentForward prices in Europe are too different

  • 24

    But these price differences are not reallyjustified considering the interconnections

    0%

    20%

    40%

    60%

    80%

    100%

    120%

    140%

    160%

    180%

    200%

    Germany Belgium Spain Portugal France Greece Italy The Netherlands Austria Switzerland UK

    Capacity in MW/peak demand

    Capacity in MWh/yearly demand in MWh

    The apparently small interconnectioncapacity is much larger than the

    market depth, and should beenough to make prices converge:there is no need to wait until new

    lines are built

    The apparently small interconnectioncapacity is much larger than the

    market depth, and should beenough to make prices converge:there is no need to wait until new

    lines are built

  • 25

    79,6Russia

    47,5

    Norway

    Gasoduct LNG

    34 22

    Algeria1,6

    Rest

    4,3

    Nigeria

    0,8Trinidad &Tobago

    Year 2000bcm

    0,15SE Asia

    Selfsupply187 bcm

    Gas: the market environmentA market dominated by a handful of suppliers

  • 26

    • Strategic point in thenetwork, with access tostorage capacity

    • Typical points of delivery forwholesale transactions

    • Prices of bilateraltransactions there becomereference

    • Developed by gastransporters/supppliers,less organised than powerexchanges

    Zelzate

    Potential Hubs

    Existing Hubs

    LNG Terminals

    Zeebrugge

    Bacton

    Aachen

    Laqc

    Emden

    Frankfurt an der OderÖresundregion

    WaidhausPo Valley

    Ukraine

    Baumgarten

    Fuente: Energy Markets Limited

    Gas: the market environmentDevelopment of trading hubs

  • 27

    Gas... and comparison with electricity• Oligopoly

    ➔ A handful of external suppliers➔ Typically one large distributor/supplier

    per country

    • Rigid➔ Long term contracts➔ Take or Pay➔ Small spot market➔ UK only significant traded market

    • Regional markets➔ Transport bottlenecks➔ Regulatory problems: network tariffs

    • More competition, suppliers in eachcountry

    ➔ More progress regarding independenceof transmission system operator

    • More wholesale/trading activity➔ Bilateral and exchanges➔ Germany, France, Netherlands

    • Regional markets➔ Transport bottlenecks➔ Regulatory problems: network tariffs

  • 28

    Gas: the market environmentDrivers of gas prices in Europe

    • Liquidity of wholesale markets➔ NBP➔ Zeebrugge (UK-Bel)➔ Emden/Bunde (Ger-Neth)➔ Zelzate (Neth-Bel)

    • LNG➔ Atlantic arbitrage➔ Ships➔ USD/EUR

    • Supply flexibility➔ Storage➔ North sea➔ Netherlands

    • Oil market➔ Indexations➔ Traders psichology➔ USD/EUR

    €/MWh

  • 29

    0

    25

    50

    75

    100

    125

    Euro

    /MW

    h

    1998 1999 2000 2001 2002

    25,7 26,731,9 31,5

    38,9

    Are markets signals adequate for investment?Even in a market with high wholesale prices, like Spain, prices donot provide adequate signals (until the last moment)

  • 30

    CCGT: 37.920 MWEólica: 21.825 MW

    Are markets signals adequate for investment?However, lots of projects have been announced or started

  • 31

    Expected electricity prices

    0

    10

    20

    30

    40

    50

    60

    2002 2004 2006 2008 2010 2012 2014 2016 2018 2020

    Base price (long term model results) Forward Base price (16/8/02)Peak price (long term model results) Forward Peak price (16/8/02)

    Precios de electricidad esperados

    0

    10

    20

    30

    40

    50

    60

    2002 2004 2006 2008 2010 2012 2014 2016 2018 2020

    Precio base modelo de largo plazo Precio forward base FranciaPrecio pico modelo de largo plazo Precio forward pico FranciaEscenario precio base considerado Escenario precio pico considerado

    Wholesale prices in France-GermanySignificant gap between forward curve & economic reality

    • Using a business dynamic long term model wecan conclude that:

    ➔ No clear trend in the expected Central Europeanelectricity prices

    ➔ Significant volatility can be expected due to theuncertainties of new capacity installed and thesensitivity of prices to small changes in capacity

    • Big gap between forward curve and resultsobtained from the model.

    ➔ Prices obtained from the model are consistentwith expected costs

    ➔ What does this say about the forward curve?• It seems reasonable to assume a increase in

    wholesale prices to adapt to the actual cost ofnew capacity

  • 32

    Wholesale prices in France-GermanySignificant gap between forward curve & economic reality

    20

    25

    30

    35

    40

    45

    50

    2002

    2003

    2004

    2005

    2006

    2007

    2008

    2009

    2010

    2011

    2012

    2013

    2014

    2015

    2016

    2017

    2018

    2019

    2020

    eur/M

    Wh

    base peak forward curve

    Long termequilibrium pricethat allowscompleterecovery ofCCGT costsThis price level iscompatible withcurrent retailprices (similar tothe embeddedprices in pricesto smallcustomers)

    Forward curve(market prices,not estimates)

    Current disparity between marketprices and prices “embedded” intariffs cannot continue muchbeyond the total liberalisation ofretail market

  • 33

    Are markets signals adequate for investment?Spikes are natural in the short term prices, but are they reasonablein the forward curve?

    1919,5

    2020,5

    2121,5

    2222,5

    2323,5

    2424,5

    2525,5

    2626,5

    2727,5

    2828,5

    2929,5

    30

    17-a

    br-0

    0

    17-m

    ay-0

    0

    17-ju

    n-00

    17-ju

    l-00

    17-a

    go-0

    0

    17-s

    ep-0

    0

    17-o

    ct-0

    0

    17-n

    ov-0

    0

    17-d

    ic-0

    0

    17-e

    ne-0

    1

    17-fe

    b-01

    17-m

    ar-0

    1

    17-a

    br-0

    1

    17-m

    ay-0

    1

    17-ju

    n-01

    17-ju

    l-01

    17-a

    go-0

    1

    17-s

    ep-0

    1

    17-o

    ct-0

    1

    17-n

    ov-0

    1

    17-d

    ic-0

    1

    17-e

    ne-0

    2

    17-fe

    b-02

    17-m

    ar-0

    2

    17-a

    br-0

    2

    17-m

    ay-0

    2

    17-ju

    n-02

    17-ju

    l-02

    17-a

    go-0

    2

    17-s

    ep-0

    2

    17-o

    ct-0

    2

    17-n

    ov-0

    2

    17-d

    ic-0

    2

    17-e

    ne-0

    3

    17-fe

    b-03

    17-m

    ar-0

    3

    CAL 2002 CAL 2003 CAL 2004

  • 34

    Final thoughtsAre markets signals adequate for investment?

    • An illiquid/non competitive market is not credible➔ Cannot be the basis for supply and generation activities in competition...

    • How can we increase liquidity/credibility of the market?➔ Divestitures (the English solution) would be a way of bringing competition

    and increasing liquidity✔ Bot no continental government seems to be seriously considering this...

    national champions are the preferred objective➔ New entrants will take years to make an impact

    ✔ And “real” new entrants are in very short supply these days...➔ Only the development of an integrated European electricity market would

    offer the possibility of a liquid market, with a sufficient number ofsignificant players

    ✔ Only the neighbours are bringing some real competition to the currentconcentrated markets

  • 35

    Final thoughtsThe key: fair access to electricity networks

    • The objective: an European market in electricity➔ Only this can bring sufficient competition and liquidity in a reasonable time

    frame➔ The place where that market is supposed to exist is the network

    • Fair access to the network is the key to the development of theEuropean market

    • The current level of network infrastructure allows for asignificant degree of integration of the markets➔ The barrier is not infrastructure, but long term contracts and regulation

    • Access to the network is not cross-border trading➔ No more multiple networks, but one single European network!

  • 36

    WHEN

    will prices raiseagain?

    • WHEN capacity reserve margins tightens up.➔ This tends to happen before everybody expects

    (though it can also reverse rapidly)

    • WHEN interconnections allow to “transmit” scarcityin certain areas to the rest of Europe➔ Spain, Norway, Italy, Portugal

    • WHEN neighbouring countries (Eastern Europe)stop exporting.➔ This could happen much more rapidly than expected

    • BUT MAINLY, WHEN prices to final customers andwholesale prices are representative of real marketforces and not only political/economic interests

    Final thoughtsWholesale prices will increase

  • 37

    Final thoughtsDealing with risks• A critical need to manage risk: flexibility

    ➔ In electricity & gas: balancing and flexible access to the network• Investment needs long term economic signals

    ➔ Even the most liquid markets provide forward curves for a limited time horizon• Regulatory measures have been tried

    ➔ Capacity payments (England, Spain, South America)➔ Capacity contracts (US)➔ But no clear solution➔ ...and beware regulatory interference with price spikes

    • The most important need is the development of a real market➔ liquid➔ competitive➔ ... a single European market

    • This is a regulatory/political issue: infrastructure is not the main barrier