jarman stephens - abb

43
21 FEBRUARY 2017 Innovations in Light Rail DC Traction Networks Light Rail 2017 Jarman Stephens - Area Rail Segment Specialist (AU-NZ) / Transportation Product Manager

Upload: informa-australia

Post on 20-Mar-2017

178 views

Category:

Business


0 download

TRANSCRIPT

Page 1: Jarman Stephens - ABB

21 FEBRUARY 2017

Innovations in Light Rail DC Traction NetworksLight Rail 2017Jarman Stephens - Area Rail Segment Specialist (AU-NZ) / Transportation Product Manager

Page 2: Jarman Stephens - ABB

1. Introduction

2. Integrated Transformer Rectifier

3. Energy Management Solutions

Energy Recuperation System

Energy Storage System

DC Traction Network Modelling

Case Studies

21 February 2017 Slide 2

Agenda

Page 3: Jarman Stephens - ABB

21 February 2017 Slide 3

Introduction

Light rail network operators must regularly develop their wayside power system to economically ensure a safe and reliable service.

Common Industry Challenges:

• Complicated and expensive land acquisition.

• Financial and corporate responsibility to decrease total network electricity use (kWh).

• Financial motivation to decrease electricity demand charge (kW).

Page 4: Jarman Stephens - ABB

1. Introduction

2. Integrated Transformer Rectifier

3. Energy Management Solutions

Energy Recuperation System

Energy Storage System

DC Traction Network Modelling

Case Studies

21 February 2017 Slide 4

Agenda

Page 5: Jarman Stephens - ABB

21 February 2017 Slide 5

Integrated Transformer Rectifier

Traction Rectifiers

DC Switchgear

Rectifier Transformers

AC MV Switchgear

MV/HV Network

DC +

AC ~

DC -

Page 6: Jarman Stephens - ABB

21 February 2017 Slide 6

Integrated Transformer Rectifier

Traction Rectifiers

DC Switchgear

Rectifier Transformers

AC MV Switchgear

MV/HV Network

DC +

AC ~

DC -

Page 7: Jarman Stephens - ABB

21 February 2017 Slide 7

Integrated Transformer Rectifier

Rectifier Transformer

Traction Diode Rectifier

Page 8: Jarman Stephens - ABB

21 February 2017 Slide 8

Integrated Transformer Rectifier

Benefits

- Volume reduction.

- No space required between units.

- Cabling reduction.

- Combined procurement, testing, documentation, shipping, installation and commissioning.

Page 9: Jarman Stephens - ABB

1. Introduction

2. Integrated Transformer Rectifier

3. Energy Management Solutions

Energy Recuperation System

Energy Storage System

DC Traction Network Modelling

Case Studies

21 February 2017 Slide 9

Agenda

Page 10: Jarman Stephens - ABB

21 February 2017 Slide 10

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

Acceleration

Constant

speed

Coasting

Braking

Traction

Power

Time

Page 11: Jarman Stephens - ABB

21 February 2017 Slide 11

Energy Management Solutions

Typical Light Rail Network

• Nominal Network Voltage: 750 VDC

• Line Resistance: 60 mΩ/km

• Tram Size: 40 tonne

• Stop Spacing: 500m – 1000m

• Headways: 5 min-30 min depending on common weekday/weekend scheduling.

• Speed Limit: 60 km/h

• Acceleration/Deceleration: 1 m/s2

• Electricity Price: 0.1 $AUD/kWh

Page 12: Jarman Stephens - ABB

21 February 2017 Slide 12

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

Page 13: Jarman Stephens - ABB

21 February 2017 Slide 13

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

750 VDC 720 VDC 730 VDC 750 VDC

Page 14: Jarman Stephens - ABB

21 February 2017 Slide 14

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

750 VDC

600 VDC

750 VDC

Page 15: Jarman Stephens - ABB

21 February 2017 Slide 15

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

Page 16: Jarman Stephens - ABB

21 February 2017 Slide 16

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

750 VDC 730 VDC 820 VDC 820 VDC

Page 17: Jarman Stephens - ABB

21 February 2017 Slide 17

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

Page 18: Jarman Stephens - ABB

21 February 2017 Slide 18

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

850 VDC 850 VDC 850 VDC 850 VDC

Page 19: Jarman Stephens - ABB

21 February 2017 Slide 19

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

850 VDC 850 VDC 850 VDC 850 VDC

Single Braking Event

Time ≈ 16 secondsEnergy ≈ 1 kWh

Value ≈ $0.10 AUDEmissions ≈ 1 kg of CO2-e

Australian Government Department of the Environment, “National Greenhouse Accounts Factors ,” July 2014.

Yearly Braking Events

Energy -> 000’s MWh

Value ≈ $000,000’s AUDEmissions ≈ 000’s tonnes of CO2-e

Page 20: Jarman Stephens - ABB

21 February 2017 Slide 20

Energy Management Solutions

Introduction MV/HV Network AC ~

DC +

DC -

• Voltage distribution on the traction network.

• Regenerative braking functionality.

• Utilisation of regenerative braking energy.

Page 21: Jarman Stephens - ABB

21 February 2017 Slide 21

Energy Management Solutions

Overview of SolutionsMV/HV Network AC ~

DC +

DC -

ERS TDR TDR

ESS

Energy Recuperation System (ERS)

Energy Storage System (ESS)

Page 22: Jarman Stephens - ABB

1. Introduction

2. Integrated Transformer Rectifier

3. Energy Management Solutions

Energy Recuperation System

Energy Storage System

DC Traction Network Modelling

Case Studies

21 February 2017 Slide 22

Agenda

Page 23: Jarman Stephens - ABB

21 February 2017 Slide 23

Energy Management Solutions

Energy Recuperation SystemMV/HV Network AC ~

DC +

DC -

ERS TDR

Energy Recuperation System (ERS)

Page 24: Jarman Stephens - ABB

21 February 2017 Slide 24

Energy Management Solutions

Energy Recuperation SystemMV/HV Network AC ~

DC +

DC -

ERS TDR

Energy Recuperation System (ERS) Benefits

• Energy savings• Provide rectification boost.

Page 25: Jarman Stephens - ABB

1. Introduction

2. Integrated Transformer Rectifier

3. Energy Management Solutions

Energy Recuperation System

Energy Storage System

DC Traction Network Modelling

Case Studies

21 February 2017 Slide 25

Agenda

Page 26: Jarman Stephens - ABB

21 February 2017 Slide 26

Energy Management Solutions

Energy Storage SystemMV/HV Network AC ~

DC +

DC -

TDR

ESS

Energy Storage System (ESS)

Page 27: Jarman Stephens - ABB

21 February 2017 Slide 27

Energy Management Solutions

Energy Storage SystemMV/HV Network AC ~

DC +

DC -

TDR

ESS

Energy Storage System (ESS)

(-)

(+)

Page 28: Jarman Stephens - ABB

21 February 2017 Slide 28

Energy Management Solutions

Energy Storage System - Benefits

• Energy savings

• Increased utilization of traction power substations and reduced peak demand charges.

• Avoid AC connection.

• Frequency Control Ancillary Service (FCAS) revenue.

Page 29: Jarman Stephens - ABB

21 February 2017 Slide 29

Energy Management Solutions

Energy Storage System - Benefits

• Energy savings

• Increased utilization of traction power substations and reduced peak demand charges.

• Avoid AC connection.

• Frequency Control Ancillary Service (FCAS) revenue.

Time (sec)

Po

wer

(W)

Vehicle Loading

Page 30: Jarman Stephens - ABB

21 February 2017 Slide 30

Energy Management Solutions

Energy Storage System - Benefits

• Energy savings

• Increased utilization of traction power substations and reduced peak demand charges.

• Avoid AC connection.

• Frequency Control Ancillary Service (FCAS) revenue.

Time (sec)

Po

wer

(W)

ESS Supply

Rectifier Supply

Vehicle Loading

Page 31: Jarman Stephens - ABB

21 February 2017 Slide 31

Energy Management Solutions

Energy Storage System - Benefits

• Energy savings

• Increased utilization of traction power substations and reduced peak demand charges.

• Avoid AC connection.

• Frequency Control Ancillary Service (FCAS) revenue.

Page 32: Jarman Stephens - ABB

21 February 2017 Slide 32

Energy Management Solutions

Energy Storage System - Benefits

• Energy savings

• Increased utilization of traction power substations and reduced peak demand charges.

• Avoid AC connection.

• Frequency Control Ancillary Service (FCAS) revenue.

Generation > Load Generation < Load

Frequency Frequency

Page 33: Jarman Stephens - ABB

21 February 2017 Slide 33

Energy Management Solutions

Overview of SolutionsMV/HV Network AC ~

DC +

DC -

Energy Recuperation System (ERS)

Energy Storage System (ESS)• Where should the unit be

installed?

• What size unit should be installed?

• What is the payback period?

Page 34: Jarman Stephens - ABB

1. Introduction

2. Integrated Transformer Rectifier

3. Energy Management Solutions

Energy Recuperation System

Energy Storage System

DC Traction Network Modelling

Case Studies

21 February 2017 Slide 34

Agenda

Page 35: Jarman Stephens - ABB

21 February 2017 Slide 35

Energy Management Solutions

DC Traction Network Modelling

- Position on the network.

- Vehicle characteristics and driving patterns.

- Timetabling and headways.

Page 36: Jarman Stephens - ABB

21 February 2017 Slide 36

Energy Management Solutions

DC Traction Network Modelling

- Position on the network.

- Vehicle characteristics and driving patterns.

- Timetabling and headways.

Page 37: Jarman Stephens - ABB

21 February 2017 Slide 37

Energy Management Solutions

DC Traction Network Modelling

- Position on the network.

- Vehicle characteristics and driving patterns.

- Timetabling and headways.

Page 38: Jarman Stephens - ABB

21 February 2017 Slide 38

Energy Management Solutions

DC Traction Network Modelling

- Position on the network.

- Vehicle characteristics and driving patterns.

- Timetabling and headways.

P. W. Zhongbei Tian, "Energy evaluation of the power network of a DC railway system with regenerating trains," Research Gate, Birmingham, 2015.

Timetable Optimisation ≈ Δ 25% network energy savings

Page 39: Jarman Stephens - ABB

1. Introduction

2. Integrated Transformer Rectifier

3. Energy Management Solutions

Energy Recuperation System

Energy Storage System

DC Traction Network Modelling

Case Studies

21 February 2017 Slide 39

Agenda

Page 40: Jarman Stephens - ABB

21 February 2017 Slide 40

Energy Management Solutions

Case Studies

Global ERS 750 Installations – 6 units globally.

Global ESS 750 Installations – 11 units globally.

Page 41: Jarman Stephens - ABB

21 February 2017 Slide 41

Energy Management Solutions

Case Study – SEPTA Project

Energy Savings:

• 2MWh reduction per day.

• 70kW demand reduction.

• $80 kUSD/year.

Energy Market Revenues:

• $200 kUSD/year.

Environmental Benefits

• 1000 tonnes/year CO2.

• 5 tonnes/year SO2

Page 42: Jarman Stephens - ABB

21 February 2017 Slide 42

Innovations in Light Rail DC Traction Networks

Summary

Integrated Transformer Rectifier

Energy Management Solutions

Energy Recuperation System

Energy Storage System

DC Traction Network Modelling

Case Studies

Page 43: Jarman Stephens - ABB