METHODS OF SLOPE REMEDIAL(SOIL NAIL / SHOTCRETE / VEGETATION)
KEMENTERIAN KESEJAHTERAAN BANDAR,PERUMAHAN, DAN KERAJAAN TEMPATAN
PRESENTATION OUTLINE
1. INTRODUCTION2. HISTORY OF SLOPE FAILURES
3. PROBLEM STATEMENTS4. METHODS OF SLOPE REMEDIAL
i. SOIL NAILii. SHOTCRETEiii. VEGETATION
5. CASE STUDY OF SLOPE REMEDIAL :BUKIT NANAS
6. FACTOR OF SAFETY (FOS) GUIDELINEFOR SLOPE STABILITY
7. CONCLUSION
1.0 INTRODUCTION
1. The POPULATION OF MALAYSIA was estimatedto be 30 572 466 people. This is an INCREASE of1.51% compared to the previous year.
2. The escalating numbers of population leads to theHIGH DEMAND FOR RESIDENTIAL AREA.
3. LIMITED AVAILABILITY OF FLAT LAND causes thedevelopment to shift towards the hilly areas.
4. Rapid development on hilly areas affects SLOPESTABILITYand poses RISKS and DETERIORATIONto properties and human lives.
5. Thus, SUITABLE SLOPE REMEDIAL WORKS isNECESSARY to strengthen the slope and ensurethe slope is safe.
16/11/2016
2
HUMAN ERRORSINVOLVING SLOPE FAILURECauses oflandslides
No. of Causes Percentage (%)
Design Errors 29 60
Construction Errors 4 8
Design &Construction Errors
10 20
Geological Features 3 6
Maintenance 3 6
Total 49 100
Reference: Proceedings of the 3rd International conference onGeotechnical Engineering for Disaster Mitigation and Rehabilitation 2011
1.0 INTRODUCTION
Over 700 landslideswere reported on 2015
410 landslidesoccurred on
federal roads
290 happenedalong state
roads
According to the landslide forensic statistic data from year 2004 to2007 of Slope Engineering Branch under the Public Works ofDepartment Malaysia, 57% of landslides were due to human factors,whereas only 29% and 14% due to physical and geological factors,and most of the landslides occured at man-made slopes
16/11/2016
3
SLOPE FAILURE AT BUKIT ANTARABANGSA(2008)
• Occurred on 6TH December
2008
• Location : Bukit Antarabangsa,
Ulu Klang, Selangor
• 14 Bungalows at Taman Bukit
Mewah and Taman Bukit
Utama destroyed
• 1.5 km from Highland Tower.
• Fatalities : 4 persons
• Injuries :15 persons
SLOPE FAILURE ATBUKIT ANTARABANGSA
16/11/2016
4
SLOPE FAILURE AT SETIAWANGSA• Emergency Response on Setiawangsa Slope Failure (28th December 2012)• 1 house were badly damaged and houses evacuation were applied
BRIEFING TO PUBLIC & MEDIA ON SLOPE FAILUREAT SETIAWANGSA
Briefing To Public
Briefing At Site
Briefing To Media And Kuala LumpurMayor
Briefing To Media At SiteBriefing To Public
DTM SETIAWANGSA SLOPE FAILURE
16/11/2016
5
DTM SETIAWANGSA SLOPE FAILURE
AFTER SLOPE FAILURE
PROPOSED REMEDIALWORK
SLOPE FAILURE AT BUKIT NANAS
Wangsa Maju,2006
Taman Tasik Perdana,2011Bangsar, 2011
La View En Rose Restaurant,2014
Bukit Segar,2010
16/11/2016
6
Jalan Ampang, 2013
Jalan Semantan, 2008
Cheras, 2011
Wangsa Maju,2006
SLOPE FAILURE AT LEBUHRAYA MAHAMERU
TRAFFIC CONGESTION
16/11/2016
7
SLOPE FAILURE AT RUMAH ANAK-ANAK YATIM DAN KEBAJIKANMADRASAH AL-TAQWA, HULU LANGAT
• Occurred on 21st May 2011• Location : Rumah Anak-anak Yatim dan
Kebajikan Madrasah Al-Taqwa, FelcraSemungkis, Batu 14, Hulu Langat.
• The number of Victims : 25 persons• Fatalities : 16 persons• Injuries :9 persons
SLOPE FAILURE ATHULU LANGAT
LANDSLIDE AT KM52.4, KARAK HIGHWAY
16/11/2016
8
DEBRIS FLOWIN RAUB,PAHANG
SLOPEFAILURE INSG. BESI,KUALA
LUMPUR
As a reminder, repair works are very,
and the reactive measures taken would givesimpact towards
thus…………
Preventive is better than corrective,
16/11/2016
9
LIST OF REMEDIAL WORK FOR SLOPE FAILURES(2008-2014)
Location CameronHighland KM 55
Jalan KualaTerengganu -
Jabor
Tasik KenyirSeksyen 37
ChangkatPersekutuan Bukit Nenas
Date of Failure 2008 2009 2010 2013 2013
End ofConstruction 2009 2010 2013 2014 2015
Area of Failuresq.m(sq.ft) 65,110sq.ft 44,200sq.ft 94,2200sq.ft 12,880sq.ft 93,260sq.ft
Cost(RM) 5,400,000.00 1,300,000.00 5,300,000.00 4,300,000.00 15,300,000.00
Cost/Sq.ft RM82 RM30 RM6 RM333 RM164
Type Bungalow 1-Storey Terrace
Build Up Size 4000 sq.ft 1500 sq.ft
LandCost/Sq.ft(A)
RM 40 RM40
Land Cost /unit(B) RM 160,000.00 RM 60,000.00
ConstrcutionCost/sq.ft(C)
RM 150 RM 150
ConstrcutionCost/Unit(D)
RM 600,000.00 RM 225,000.00
Cost perUnit(B+D)
RM 760 000.00 RM 285 000
Cost persq.ft(A+C)
RM 190/sq.ft RM 190/sq.ft
COMPARISON COST OF A BUNGALOW AND 1 STOREY-TERRACE HOUSE
=
=@
( 12,880 sq.ft)
( 4000 sq.ft)
( 1500 sq.ft)
16/11/2016
10
COMPARISON COST of HOUSING DEVELOPMENT &SLOPE REMEDIAL
NO LOCATIONCOST OF
CONSTRUCTIONBUNGALOW4000 SQ.FT
@
TERRACE1500 SQ.FT
1 BukitNenas(93,260sq.ft)
RM15 300 000.00 20 53
2 Tasik Kenyir Seksyen36 (94,2200sq.ft)
RM 5 300 000.00 6 18
3 Cameron HiglandKM55 (65,110sq.ft)
RM 5 400 000.00 7 18
4ChangkatPersekutuan(12,880sq.ft)
RM 4 300 000.00 5 14
5Jalan KualaTerengganu –Jabor(44,200sq.ft)
RM 1 300 000.00 2 5
16/11/2016
11
TYPE OF SLOPE REMEDIAL
TYPE OF SLOPEREMEDIAL
RETAINING WALL SOILREINFORCEMENT
SURFACE EROSIONCONTROL
1. GRAVITY WALL2. CANTILEVER WALL3. PILING WALL4. MSE WALL
1. SOIL NAIL2. GROUND ANCHOR3. GEOTEXTILE
1. HYDROSEEDING2. TURFING3. PLANTATION4. SHORTCRETE
O ve rtu rn in g
R e s is t in g
M o m en t
H o r izo n ta lF o rce
M o m en t R e s is t in g Fo rce
S u rch a rg e S o il W a te r
16/11/2016
12
Soil nailing can prevent landslides by insertingsteel reinforcement bars into the soil and
anchoring them to the soil
Soil nailing is a technique used to bring soilstability in areas where landslides might
be a problem.
WHAT IS SOIL NAILING?
TERMINOLOGY OF SOIL NAIL
Soil Nail Head(400x400 mm)
Reinforcement BarDiameter = 25, 32 & 40 mm
Steel Bearing Plate(200x200 mm)
Subject to calculation
20°
Nail Inclination :150 -200
Critical Slip Circle
Sources : Soil Nail Design Malaysia Perspective(Chow Chee Meng & Tan Yean Chin)
16/11/2016
13
TERMINOLOGY OF SOIL NAIL
Vertical Spacing of nail:Typically 1.5m to 2.5m
Horizontal Spacing of nail:Typically 1.5m to 2.5m
Minimum plate width of 200mmMinimum plate thickness 19mm
Concrete cover typically 50-75mmthick
Sources : Soil Nail Design Malaysia Perspective(Chow Chee Meng & Tan Yean Chin)
TYPICAL DETAIL OF SOIL NAIL
SOIL NAILING ANIMATION
SITE IS CLEARED SLOPE IS CUT SOIL NAILING IS INSTALLED
Insert Bar andGrouting
Hole is drilled
Steel PlatesShortcrete
16/11/2016
14
STRUCTURAL CAPACITY OF SOIL NAIL
Ultimate structural capacity, P = 0.87 x fy x As
Where: fy = characteristic strength of steel barAs = reinforcement area
= πd²/4
Steel BarDiameter
(mm)
Cross-sectionalArea of Pile, Ac
(mm²)
25 490
32 804
40 1,256
* Normal Size Use in Malaysia
Ultimate structural capacity, P
P = 0.87 x fy x As= (0.87 x 460 N/mm² x 490 mm²) / 1000= 196 kN
*Structure Capacity (refer BS 8110: Clause 7.4.4.3.1)
Structural Capacity Soil Nail vs Steel Bar Size
*use FOS = 1.5 according to BS 8081: 1989
196
322
503
786
131
215
335
524
0
100
200
300
400
500
600
700
800
900
25 32 40 50
Stru
ctur
e Ca
paci
ty (
N/m
m2)
Diameter Steel (mm)
Structural Capacity Soil Nail vs Steel Bar Size
Ultimate Structure Capacity Allowable Structure Capacity
SENSITIVITY ANALYSIS
16/11/2016
15
Sand
Cement
Steel Casing, Nut & MS plate
T32 Galvanised Hot Rolled Steel
Excavator Cement Mixture
Drilling Machine Case 580 Super K
Hydraulic Screw Compressor
Air Compressor Grouting Pump
Guniting Spray
16/11/2016
16
SOIL NAILING WORK SEQUENCESSTEP 1Clearing , scaling and trimming
Clear and remove from site all obstacleover the areas for the construction
Trimming slope to perform proposedslope inclination
SOIL NAILING WORK SEQUENCESSTEP 2Survey & Paging soil nail point
Survey soil nail point to measure actualquantity of soil nail
SOIL NAILING WORKS SEQUENCESSTEP 3Preparation of Soil Nail Works
Installation of staging to perform soilnailing works
16/11/2016
17
SOIL NAILING WORK SEQUENCESSTEP 4Drilling soil for installation of soil nail
AirCompressor
Drilling soil nail point using drillingmachine
SOIL NAILING WORK SEQUENCESSTEP 5Installation of soil nail
Inserting reinforcement bar (size as perdesign) in the hole
Reinforcement bar
SOIL NAILING WORK SEQUENCESSTEP 6Grouting Process
Full grouting apply after installing thereinforcement bar in the hole ( cement
grout as per design )
Reinforcement bar
16/11/2016
18
SOIL NAILING WORKS SEQUENCESSTEP 7Locking Soil Nail
Install soil nail plate andlocking using bolt & nut
SOIL NAILING WORK SEQUENCESSTEP 8Testing – Pull Out Test
Perform pullout test to determine theperformance of soil nailing based on
design working load
Pull Out Test(According to BS 8081:1989)
• The pullout test on soil nail generally1.5 times the working load asspecified in BS 8081:1989.
• Load at this stage is called thepullout capacity.
• Tests are carried out to determine thestrength of soil nailed structures
16/11/2016
19
PROGRESS PICTURE
SETTING UP FOR PULL OUT TESTSETTING UP FOR PULL OUT TEST
GAUGE METER READING WHILE PULL OUT TESTGAUGE METER READING WHILE PULL OUT TEST PULL OUT TEST IN PROGRESSPULL OUT TEST IN PROGRESS
PULLOUT ON SITE
Production Rate
SPT VALUE LENGTH (m)TIMES REQUIRED
/ 1m LENGTH(minute)
TIMES REQUIRED/ 6m LENGTH
(minute)
TIMES REQUIRED/ 12m LENGTH
(minute)
10 1 2 12 24
20 1 6 36 70
30 1 7.5 45 90
40 - 50 1 10 60 120
SPT VALUEAVERAGE DAILY RATE FOR 6M
REINFORCEMENT
AVERAGE DAILY RATE FOR 12MREINFORCEMENT
10 40 20
20 14 7
30 11 6
40 - 50 8 4
EXAMPLES OF SOIL NAILING USINGMACHINERY
Excavator mounted drill rig
16/11/2016
20
VIDEO SOIL NAIL
DEFINITION OF SHOTCRETE
Shotcrete is a today an all-inclusive term thatdescribes spraying concrete or mortar with either adry or wet mix process through a hose and nozzle
onto a surface
16/11/2016
21
CLASSIFICATION OF SHOTCRETEDRY MIX1. Dry materials including cement,
aggregate, and ad-mixture are mixedtogether through a hose and then, atthe nozzle via a water ring, water isinjected evenly throughout the mix.
2. Dry mix usually uses for Slope protectionsurface (Shotcrete)
WET MIX1. Materials including cement, aggregate,
ad-mixture and water – are mixedtogether before being pumped through ahose.
2. Wet mix usually uses for Groutingprocess for Soil Nail Work
Application of Dry MIX
Application of Wet MIX
Gunite is trademarked name that isincorrectly used to describe the dry mix
shotcrete process
DEFINITION OF GUNITE
EXAMPLE APPLICATION OF SHOTCRETE
Shotcrete is used for slopesurface protection
16/11/2016
22
EXAMPLE APPLICATION OF SHOTCRETEShotcrete is used for concrete grouting of
soil nail (Wet Mix)
Grout
INGREDIENT OF SHOTCRETE
Sand Cement and Admixture
Cement Mixture Guniting Spray Grouting Pump
Material
Machinery
16/11/2016
23
SEQUENCE OF SHOTCRETE WORK ATTAMAN BUKIT SEGAR, CHERAS
SITE CLEARINGSITE CLEARING INSTALLATION OF BRCINSTALLATION OF BRC
SPRAY CONCRETESPRAY CONCRETESPRAY CONCRETESPRAY CONCRETEFINISH SHOTCRETEFINISH SHOTCRETE
VIDEO SHOTCRETE
16/11/2016
24
VEGETATION FOR SLOPE REMEDIAL1. Vegetation influences slope stability by:
• Providing cover for the impact of rain falling onslopes and prevent erosion on slope surface
• Providing root systems by transferring shear stressin soil to the tensile resistance in the root
2. Types of vegetation:• Hydroseeding• Turfing
HYDROSEEDING
HYDROSEEDING• Application of grass seed mixed with fertiliser and
nutrient by spraying method over the ground• The grass seed will grow eventually and the root
of the grass will act as an organic reinforced fiberand hold the surface soil.
16/11/2016
25
HYDROSEEDING WORKS
GRASS SEED, FERTILIZER ANDNUTRIENTS ARRIVED AT SITEGRASS SEED, FERTILIZER ANDNUTRIENTS ARRIVED AT SITE
EXAMPLE OF GRASS SEEDEXAMPLE OF GRASS SEED SPRAY GRASS SEEDSPRAY GRASS SEED
SPRAY GRASS SEEDSPRAY GRASS SEEDGRASS BEGIN TO GROWGRASS BEGIN TO GROWFINISH HYDROSEEDING WORKSFINISH HYDROSEEDING WORKS
VIDEO OF HYDROSEEDING
BEFORE AND AFTER HYDROSEEDING
BEFOREBEFORE
AFTERAFTER
16/11/2016
26
TURFING
TURFING
• Turfing is a direct application of grass withdeveloped roots on a slope surface
• The relatively matured grass will grow easierand extend its root into the soil to strengthenthe overall surface.
TURFING WORKS
BEFORE REMEDIAL
AFTER REMEDIAL
LIMBANG, SARAWAK
16/11/2016
27
TURFING WORKS1 2
3 4
1. SOIL NAIL2. HYDROSEEDING
Geotechnical Forensic Unit,3rd Floor, Block 5, Unipark Suria , Jalan Ikram-Uniten, 43000 Kajang, Selangor, Malaysia.Tel : (603) 87383388 Fax: (603) 89221134 www.ikram.com.my
16/11/2016
28
SATELLITE IMAGE OF FAILURE AREA
SMK StJohn
Convent BktNanas
SYABAS TreatmentTank
FailureLocation 1A
FailureLocation 2B
Jalan Ampang
Jalan SultanIsmail
Jalan P Ramlee
Jalan Raja Chulan
Jalan Bukit Nanas
FailureLocation 1B
FailureLocation 2A
LAYOUT PLAN OF LOCATION FAILURE 1
Location 1 A Location 1 A Location 1A
Location 1B
LAYOUT PLAN OF LOCATION FAILURE 2
Stone Pitching Moved Forward
Rubble Wall
20m
6m
6m
Location 2A
Location 2B
Panoramic View Of Location 2B
Staircase To Basement Parking
16/11/2016
29
REMEDIAL LAYOUT PLAN (LOCATION 1)
LOCATION 1B
LOCATION 1A
Anchored RCWall
Soil Nailing
REM
EDIA
L C
ROSS
SEC
TIO
N(L
OC
ATI
ON
1)
LOCATION 1B
LOCATION 1A
4m
12m18m
Anchored Retaining Wall
Soil Nailing
Remedial Item Location 1A Location 1B
RC Wall
Height (4m) 130m Length 35m Length
Tieback SoilNail(18m)
330 nos 80 nos
SlopeStrengtening
Soil Nail(12m length)
2700 nos 324 nos
SurfaceProtection
Enkamat 6000 m² 700 m²
FoundationMicropile
(6m length)55 nr 13 nr
SLOPE STABILITY ANALYSIS(LOCATION 1A)
1A
1A
Slope RemedialLength of Soil Nailing – 12m
Exposed Height Anchored RC Wall – 4m
Failure Area
Before
After
16/11/2016
30
SITE PHOTO BEFORE & AFTERREMEDIAL (LOCATION 1A)
SIDE VIEW
FRONT VIEW
JAN 2014JAN 2014 SEPTEMBER 2014SEPTEMBER 2014 NOVEMBER 2014NOVEMBER 2014
JAN 2014JAN 2014 SEPTEMBER 2014SEPTEMBER 2014 NOVEMBER 2014NOVEMBER 2014
DTM OFFAILURE AREA
(LOCATION1A)
Before
After
32mRL
95mRL
32mRL
95mRL
DTM VIDEO OF BUKIT NENAS
16/11/2016
31
GUIDELINE FOR SLOPE STABILITY(FACTOR OF SAFETY)
GUIDELINE
F.O.SNATURAL SLOPE
(GLOBAL/LOCAL)
F.O.SMAN MADE SLOPE
(GLOBAL/LOCAL
F.O.STEMPORARY SLOPE
(GLOBAL/LOCAL)
DBKL GUIDELINE
1.3 1.5 1.2PANDUAN REKABENTUK
CERUN (JKR)
GARIS PANDUAN PERANCANGANPEMBANGUNAN DI KAWASAN BUKIT DANCERUN BAGI WILAYAH PERSEKUTUAN KUALALUMPUR, 2010
16/11/2016
32
JKR GUIDELINE FOR SLOPE DESIGN
7.0 CONCLUSION
• Soil nail, vegetation and shotcrete are types ofremedial works for SLOPE STABILIZATION andPROTECTION of slope surface.
• Understanding the methods of remedial works iscrucial to ensure the works are ACCORDING tothe STANDARD SPECIFICATION andSEQUENCES.
• KuLSIS is an example of comprehensive slopeinformation system which acts as a tool for localauthorities to MANAGE SLOPE EFFICIENTLY.