GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | i
Kempsey Shire Council
Kempsey Regional Saleyards
Financial Plan March 2016
APPENDIX C15MAR2016
Page 15ITEM 4
ii | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
Executive summary GHD were engaged by Kempsey Shire Council (the Council) to develop a financial plan for the
Kempsey Regional Saleyards (the Saleyards)
After reviewing previous reports, GHD visited the facilities to consider potential upgrades and
consult key stakeholders, including Council staff, agents and a selection of producers.
Potential improvements were identified, costed and prioritised (section 2.3) based on the
Council’s ability to finance future works.
Current financial position
Historically the Saleyards have typically returned an annual loss or small profit, which after
accounting for loan repayments has resulted in an annual operating deficit absorbed by Council.
However in recent years, the financial position of the Saleyards has been steadily improving, as
loans are repaid. Throughput and revenue has also increased since the second agent was
provided access to the facilities. 2014/15 saw an increase in revenue of over $90K, due to
increased throughput (28K to 36K head) and also an increase in yard dues.
Forward projections suggest the facility will continue to return modest annual profits. Without
additional borrowing, the facility will return its first annual operating surplus in 2017/18.
Year Source Revenue Expenses Profit/Loss Loan repayments
Operating Surplus/Deficit
2004/05 Historical $190,494 $170,824 $19,670 $70,943 -$51,273
2005/06 Historical $192,059 $240,603 -$48,544 $78,820 -$127,364
2006/07 Historical $220,992 $267,835 -$46,843 $105,909 -$152,752
2007/08 Historical $254,138 $240,409 $13,729 $126,492 -$112,763
2008/09 Historical $257,983 $306,536 -$48,553 $156,331 -$204,884
2009/10 Historical $278,933 $339,550 -$60,617 $183,521 -$244,138
2010/11 Historical $276,606 $260,214 $16,392 $193,355 -$176,963
2011/12 Historical $238,787 $249,947 -$11,160 $204,557 -$215,717
2012/13 Historical $215,941 $222,628 -$6,687 $182,207 -$188,894
2013/14 Historical $208,282 $252,469 -$44,187 $174,271 -$218,458
2014/15 Historical $300,796 $258,295 $42,501 $138,557 -$96,056
2015/16 Budget $297,285 $215,693 $81,592 $122,118 -$40,526
2016/17 Forecast $307,121 $243,271 $63,850 $93,626 -$29,776
2017/18 Forecast $330,035 $241,093 $88,942 $64,379 $24,563
2018/19 Forecast $354,728 $240,996 $113,732 $31,258 $82,474
2019/20 Forecast $381,339 $243,643 $137,696 0 $137,696
2020/21 Forecast $410,019 $247,795 $162,224 0 $162,224
The expiration of the current lease agreement in coming years will provide an opportunity for the
facility to increase throughput, by providing access to all agents, through the introduction of
multi-agent sales. To facilitate multi-agent sales, the facility would most likely need to introduce
pen selling (in addition to ring selling), to ensure operational efficiency.
APPENDIX C15MAR2016
Page 16ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | iii
Limit of Council subsidisation
The above projections suggest there will be some capacity for the facility to finance future loans
from annual profits, however any substantial borrowing will likely return the facility to deficit.
Council’s position is that the facility should be independently financially viable, without ongoing
Council subsidisation through annual deficits. While Council is prepared to cover occasional
deficits, ideally the facility would return a net surplus over the coming 5 years. Council is
committed to continuing to provide in kind staffing support for the facility, which does not appear
in the financial analysis.
Proposed Capital Works Schedule
The proposed capital works schedule (below) aims to implement high priority and less
expensive capital improvements in 2016/17 (CCTV, new scales and pneumatic gates, replace
water troughs) before moving onto longer term priorities in 2017/18 (new office building, raised
walkways, secondary effluent treatment). The construction of a roof over delivery yards
(discussed below) is delayed until 2018/19 to allow time for Council to monitor throughput and
financial performance and seek additional funding.
2016/17 2017/18 2018/19 2019/20 2020/21
CCTV
High (short term)
$8,000
Signage and safety $2,000
Fix bent gates $2,000
Scales and gates $26,500
Replace water trough and cover copper pipe
$17,000
WWTS maintenance works
$50,000
New office
High (long term)
$20,000
Raised walkways $62,000
Secondary effluent treatment System
$140,000
Roofing over delivery yards (initial)
$460,000
Roofing over delivery yards (final)
$460,000
Total capital cost $105,500 $82,000 $140,000 $460,000 $460,000
Construction of roof over delivery yards
The construction of a roof over the delivery yards is the major long-term investment decision for
the facilities. This investment will address a number of issues facing the facilities, by:
Reducing the amount of wastewater entering the wastewater treatment system (WWTS),
by allowing clean captured rainwater to be diverted either to tank storage or nearby
drainage;
Eliminating the need for town water top-up during warmer months;
Reducing animal welfare issues associated with excessive heat, including water trough
overheating;
Addressing OH&S and amenity issues associated with heat and rain;
Helping facilitate pen selling; and
APPENDIX C15MAR2016
Page 17ITEM 4
iv | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
Allow the introduction of sawdust flooring, to prevent hoof injuries and lameness.
Financial projections
The financial projections below assume annual operating cash surpluses (excluding
depreciation) will be held in a reserve fund and used for future capital improvements. The
funding shortfall (i.e. when the balance of the reserve fund falls below zero in 2019/20 and
2010/21 will be obtained from internal borrowings and rapidly repaid in the following year.
Modelling has been conducted using the following assumptions:
• Improvements lead to an increase in annual saleyard throughput of 3% per annum until
2020/21 after which throughput plateaus.
• Annual costs and fees increase with CPI.
APPENDIX C15MAR2016
Page 18ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | i
Projections 2015/2016 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 2022/2023 2023/2024
Throughput
(assuming 3% annual increase)
36,255 37,343 38,463 39,617 40,805 42,029 42,029 42,029 42,029
Revenue $297,285 $307,121 $330,035 $354,728 $381,339 $410,019 $421,499 $433,301 $445,434
Operating expenses (including interest)
$215,693 $243,271 $241,093 $240,996 $243,643 $247,795 $252,097 $256,556 $261,177
Annual operating profit (loss) $81,592 $63,850 $88,942 $113,732 $137,696 $162,224 $169,402 $176,745 $184,257
Existing loan repayments $122,118 $93,626 $64,379 $31,258 $- $- $- $- $-
Annual operating surplus (deficit) -$40,526 -$29,776 $24,563 $82,474 $137,696 $162,224 $169,402 $176,745 $184,257
Reserve Fund
Input
(Annual operating surplus excluding depreciation costs)
$68,149 $99,124 $147,737 $199,130 $246,960 $263,132 $269,527 $276,064 $282,747
Withdrawal
(Proposed capital works)
$- $105,500 $82,000 $140,000 $460,000 $460,000 $- $- $-
Balance $68,149 $61,773 $127,510 $186,640 -$26,400 -$223,268 $46,259 $322,323 $605,070
Internal borrowings $- $- $- $- $26,400 $223,268 $- $- $-
APPENDIX C15MAR2016
Page 19ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | i
Sensitivity analysis
The sensitivity analysis below shows how the total funding required from internal borrowings
(i.e. the funding shortfall) would vary, under changes to key assumptions around annual
throughput growth.
Annual increase in annual throughput
(20/21 throughput level)
Total funding required from internal borrowings (funding shortfall)
0% (36K) $486,313
1% (38K) $393,233
2% (40K) $299,930
3% (42K) $249,666
4% (44K) $198,515
5% (46K) $146,465
Conclusion
Having undergone previous capital works and repaid debt, the Kempsey Regional Saleyards
are expected to return operating surpluses in coming years, allowing Council to undertake
additional targeted capital improvements.
The capital works schedule proposed in this report aims to prepare the facility for servicing
multiple agents following the expiration of the current lease, without burdening Council with
unsustainable debt levels.
Failure to reinvest in the facility will most likely lead to a steady decline in operational efficiency
and increased scrutiny on animal welfare, environmental management and OH&S.
A summary of recommendation from this report is provided below.
Summary of recommendations
1. Implement the capital works program as outlined in this report, while monitoring annual
changes to throughput, revenue and expenses against projections.
2. Investigate opportunities to draw on the Environmental Levy or the NSRF to help fund the
construction of a roof over delivery yards.
3. Ensure all usage fees are regularly adjusted for CPI.
4. Revisit the business development actions outlined in the Saleyard Business Plan
including activities aimed at improving promotion, broaden the Saleyards supply area and
improving security/revenue collection.
5. Begin planning and preparations for beyond the current lease agreement. If Council is to
hold multi-agent sales, how will sales be managed? Will additional resources be
required?
6. If the Council is not fully committed to managing the facility to its full potential, including
the management of multi-agent sales, the Council should seek to outsource management
or sell the facility.
APPENDIX C15MAR2016
Page 20ITEM 4
ii | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
Table of contents
1. Introduction..................................................................................................................................... 1
1.1 Purpose of this report........................................................................................................... 1
1.2 Terms of reference ............................................................................................................... 1
1.3 Methodology ........................................................................................................................ 1
1.4 Scope and limitations ........................................................................................................... 2
2. Background .................................................................................................................................... 3
2.1 Previous analysis and reviews ............................................................................................. 4
2.2 Completed works ................................................................................................................. 6
2.3 Current financial position ..................................................................................................... 8
2.4 Limit of Council subsidisation .............................................................................................. 8
2.5 Potential sources of capital .................................................................................................. 8
3. Identified improvements ............................................................................................................... 10
3.1 Roofing over delivery yards ............................................................................................... 10
3.3 Roofing over holding pens ................................................................................................. 12
3.4 Shade membrane .............................................................................................................. 13
3.5 Raised walkway ................................................................................................................. 14
3.6 New office building ............................................................................................................. 14
3.7 New scales and pneumatic gates ...................................................................................... 15
3.8 Secondary effluent treatment system ................................................................................ 16
3.9 Scour cleaning system ....................................................................................................... 17
3.10 Replace water troughs and cover copper piping ............................................................... 19
3.12 WWTS maintenance works ............................................................................................... 20
3.13 Minor upgrades and general maintenance ........................................................................ 21
3.14 Summary of priority investments ....................................................................................... 22
5. Proposed capital works program ................................................................................................. 23
5.1 Capital improvements excluded from the program ............................................................ 25
6. Financial plan ............................................................................................................................... 26
6.1 Sensitivity analysis ............................................................................................................... 1
6.2 Low investment option ......................................................................................................... 1
7. Summary of findings and recommendations .................................................................................. 2
7.1 Summary of recommendations ............................................................................................ 2
8. References ..................................................................................................................................... 3
APPENDIX C15MAR2016
Page 21ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | iii
Table index
Table 1 Summary of identified projects (Huefner & Associates 2006) ............................................. 4
Table 2 Capital works program expenditure since 2004/05 ............................................................. 6
Table 3 Financial performance (historical, current budget and forecast) ......................................... 8
Table 4 Prioritisation rating system ................................................................................................. 10
Table 5 Improvement summary: Roofing over delivery yards ........................................................ 11
Table 6 Improvement summary: Roofing over holding pens .......................................................... 12
Table 7 Shade membrane options .................................................................................................. 13
Table 8 Improvement summary: Shade membrane ....................................................................... 13
Table 9 Improvement summary: Raised walkways ........................................................................ 14
Table 10 Improvement summary: New office building ...................................................................... 15
Table 11 Improvement summary: New scales and pneumatic gates ............................................... 16
Table 12 Improvement summary: Secondary Treatment System .................................................... 17
Table 13 Improvement summary: Scour cleaning system ................................................................ 18
Table 14 Improvement summary: Replace water troughs and cover copper piping ........................ 19
Table 15 Improvement summary: WWTS efficiency works .............................................................. 20
Table 16 Improvement summary: Minor upgrades and general maintenance ................................. 21
Table 17 Summary of capital improvements by priority .................................................................... 22
Table 18 Proposed capital works program ....................................................................................... 23
Table 19 Excluded capital improvements ......................................................................................... 25
Table 20 Capital works schedule ...................................................................................................... 26
Table 21 Financial projections ............................................................................................................ 1
Table 22 Sensitivity analysis: impact on net funding shortfall from changes in annual
throughput ............................................................................................................................ 1
Table 23 Description and assumptions for financial modelling items ................................................. 7
APPENDIX C15MAR2016
Page 22ITEM 4
iv | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
Figure index
Figure 1 Kempsey Regional Saleyards Site Plan .............................................................................. 3
Figure 2 Delivery pens ..................................................................................................................... 11
Figure 3 holding yards ...................................................................................................................... 12
Figure 4 Proposed location for new office ........................................................................................ 15
Figure 5 Scale and gates ................................................................................................................. 16
Figure 6 A Secondary effluent treatment system installed at the Braidwood Livestock
Truck Wash (For Earth Pty Ltd) ......................................................................................... 17
Figure 7 Delivery yards with solid waste build-up ............................................................................ 18
Appendices
Appendix A – Summary of recommended management options for WWTS (ERM 2011)
Appendix B Financial modelling
APPENDIX C15MAR2016
Page 23ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 1
1. Introduction
1.1 Purpose of this report
GHD has been engaged produce a Financial Plan and Capital Works Program for Kempsey
Regional Saleyards, which will help build the asset’s competitive advantages and ensure
compliance with current and future regulatory and animal welfare requirements.
Kempsey Shire Council’s (KSC’s) investment in the Kempsey Regional Saleyards is consistent
with the Council’s economic development focus which seeks to stimulate growth of higher value
and value-added agribusiness ventures.
1.2 Terms of reference
The terms of reference for the project are to:
1. Review the 2013 Kempsey Regional Saleyards business Plan and other support
documentation, including Kempsey Regional Saleyards, Market Analysis and Financial
Modelling (GHD Pty Ltd, 2013) and Kempsey Regional Saleyards Infrastructure Review
and Feasibility Study (Huefner & Associates Pty Ltd, 2006);
2. Conducting a site visit to the site and liaising with key industry stakeholders and Council
staff; and
3. Developing the Financial Plan, including future fee modelling and a five-year capital
works program.
1.3 Methodology
The financial plan has been completed over the period from November 2015 – February 2016.
Following are the activities completed in conducting the review:
a) Review of previous reports and financial data;
b) Site visit and consultation with Council employees, livestock agents, producers and
suppliers;
c) Identification, costing and prioritisation of potential capital improvements;
d) Financial planning; and
e) Reporting.
APPENDIX C15MAR2016
Page 24ITEM 4
2 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
1.4 Scope and limitations
This report: has been prepared by GHD for Kempsey Shire Council and may only be used and relied on by Kempsey Shire Council for the purpose agreed between GHD and the Kempsey Shire Council as set out in section 1.1 of this report.
GHD otherwise disclaims responsibility to any person other than Kempsey Shire Council arising in connection with this report. GHD also excludes implied warranties and conditions, to the extent legally permissible.
The services undertaken by GHD in connection with preparing this report were limited to those specifically detailed in the report and are subject to the scope limitations set out in the report.
The opinions, conclusions and any recommendations in this report are based on conditions encountered and information reviewed at the date of preparation of the report. GHD has no responsibility or obligation to update this report to account for events or changes occurring subsequent to the date that the report was prepared.
The opinions, conclusions and any recommendations in this report are based on assumptions made by GHD described in this report. GHD disclaims liability arising from any of the assumptions being incorrect.
GHD has prepared this report on the basis of information provided by Kempsey Shire Council and others who provided information to GHD (including Government authorities)], which GHD has not independently verified or checked beyond the agreed scope of work. GHD does not accept liability in connection with such unverified information, including errors and omissions in the report which were caused by errors or omissions in that information.
GHD has prepared the preliminary cost estimates set out in section 3 of this report using information reasonably available to the GHD employee(s) who prepared this report; and based on assumptions and judgments made by GHD.
The Cost Estimate has been prepared for the purpose of Kempsey Saleyard financial planning for and must not be used for any other purpose.
The Cost Estimate is a preliminary estimate only. Actual prices, costs and other variables may be different to those used to prepare the Cost Estimate and may change. Unless as otherwise specified in this report, no detailed quotation has been obtained for actions identified in this report. GHD does not represent, warrant or guarantee that the works can or will be undertaken at a cost which is the same or less than the Cost Estimate.
All cost estimates presented in the report exclude GST.
APPENDIX C15MAR2016
Page 25ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 3
2. Background
Kempsey Regional Saleyards is a community asset owned and maintained by Kempsey Shire
Council. With 66 sales held per annum, the Saleyards provide a regular venue for livestock
buyers and sellers across the region to generate income and undertake herd development
activities. The weekday markets are attended by an average of 150-300 buyers and sellers, with
this number increasing to over 3-400 at the Saturday markets.
Local Government has managed Saleyards in the Macleay Valley since the early 1900s and at
the current saleyard site since 1969. The Saleyards provide an essential service to beef and
dairy industry producers, operators and end users and is ideally located mid-way between
Saleyards at Taree and Grafton. Council owns the Kempsey Regional Saleyards facility and is
responsible for providing all infrastructure, ongoing upgrading and maintenance.
Under current leasing arrangements, livestock sales are a function of two agents, with Kempsey
Stock & Land (KSL) operating under a five-year lease which provides exclusive use on
Thursdays and Midcoast Rural having operating on Tuesdays. Other interested agents can
operate on other days.
Over the past 12 years, Kempsey Shire Council has invested $2M in upgrade and infrastructure
works to ensure the Saleyards comply with environmental standards, meet OH&S requirements
and offer ‘best practice’ facilities capable of processing more than 2000 head of cattle per day.
Loans associated with these upgrades expire in 2017/2018.
Council has long-term plans to upgrade the saleyard facility to address effluent disposal issues
and improve the selling yards (2014/15 Annual Report).
While Saleyards have historically formed an integral part of the economic and social fabric of
rural communities in Australia, it is acknowledged that improved technology, transportation and
regionalisation have driven a consolidation of Saleyards and the growth of alternative selling
methods, placing pressure on their financial management.
Figure 1 Kempsey Regional Saleyards Site Plan
APPENDIX C15MAR2016
Page 26ITEM 4
4 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
2.1 Previous analysis and reviews
This section provides a summary (in chronological order) of previous analysis and reporting on
the Kempsey Saleyards, including recommended capital improvements.
2.1.1 Kempsey Regional Saleyards Infrastructure Review and Feasibility
Study (Huefner & Associates Pty Ltd, 2006).
Huefner & Associates Pty Ltd conducted an infrastructure review and feasibility study in 2006.
The project included an inspection of the Saleyards, as well as stakeholder consultation with
staff, operators and vendors. The report highlighted the projects below as priorities, which
helped shape the capital works program in subsequent years (outlined in section 2.2).
Table 1 Summary of identified projects (Huefner & Associates 2006)
Identified projects Project description Estimated cost (2005)
Saleyard signage Provide additional signage at main roads (allowance) $4,000
Buffers Visual and noise buffers to be planted $6,000
Northern Yards Require complete replacement
1. New unloading ramps
2. New receival yards
3. New drafting facilities
4. New holding pens
5. New bull pens
6. New calf pens
7. New ring and ring seating
8. New delivery pens
$1,550,000
Kiosk and canteen Required to provide service $300,000
Calf building To be demolished Profit
Pavements Need some rehabilitation $60,000
Truck Wash New - Required Use existing funds
Lighting Requires additional open air lighting $40,000
Effluent treatment Review required Use existing funds
Soft flooring Trial required $10,000
2.1.1 Wastewater Treatment Report (ERM 2011)
In 2011 Environmental Resource Management Australia Pty Ltd (ERM) were engaged
undertake a site inspection of the saleyard wastewater treatment system (WWTS) and provide
recommendations for system improvements and ongoing management.
This study followed the previous WWTS Design Upgrade (ERM 2008) and Operation and
Maintenance Manual (ERM 2006).
The study found that improving the maintenance program for the WWTS was one of the most
cost-effective solutions for Council. Other cost effective solutions included the instillation of
baffle weirs, and the management of ponds as a constructed wetland. The study identified roof
construction as an effective long-term means of improving wastewater quality, however
requiring a higher capital outlay for Council. With this in mind, the study recommended a staged
approach to roofing. Other potential improvements were found to be more cost effective in the
short term. A summary of the recommended management options is provided in Appendix A.
APPENDIX C15MAR2016
Page 27ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 5
2.1.2 Kempsey Regional Saleyards, Market Analysis and Financial
Modelling (GHD Pty Ltd, 2013)
This 2013 report provides an analysis of factors impacting on the long term viability of the
Kempsey Regional Saleyards, including local cattle numbers, changing selling trends, operating
costs etc.
The report provided a review of local market conditions and the past financial performance of
the Saleyards, which was used to provide projections of future throughput and financial
performance under different investment scenarios.
The report anticipated an increase in throughput to around 35,000 head, largely due to a
second agent (Midcoast Rural) being provided access. Overall the report found the Saleyards
are well placed to deliver operating profits of between $12,000 and $72,000 per annum going
forward (depending on future capital improvements).
Projections from the report were used to inform the Saleyard Business Plan (below).
2.1.3 2013 Kempsey Regional Saleyards Business Plan
The Kempsey Regional Saleyards Business Plan highlights some major immediate challenges
currently faced by Kempsey Regional Saleyards, including:
acceleration of direct selling methods;
changes to the operating environment;
increasing regulations; and
ongoing competition from larger neighbouring Saleyards (e.g. Armadale, Grafton, Taree),
abattoirs and alternative sale methods.
The report detailed two investment scenarios (low and high investment). The high investment
scenario incorporates a range of potential upgrades and improvements to the saleyard facilities
which may be required into the future, and/or are likely to improve the facilities operations,
throughput and profitability. These upgrades and improvements are examined in more detail
below, including estimated costs and benefits.
Soft flooring: Approximately 5000 square meters of soft flooring would be required at a
cost $80 per square meter. The total cost of the flooring upgrade would be approximately
$400,000.
Roofing over delivery yards: The cost of roofing the delivery yards is estimated at
$445,000, based on the 2006 estimate1 adjusted for inflation.
Roofing over holding pens: The cost of roofing the holding pens is estimated at $635,000,
based on the 2006 estimate2 adjusted for inflation.
Raised walkway: The approximate cost for installing a catwalk around the pens would be
$89,000, based on the 2006 estimate3 adjusted for inflation.
Effluent disposal system: The cost of the effluent disposal system upgrade is estimated at
approximately $50,000. Revenue from manure sales is estimated at $5,000 per annum
(125 M2 sold annually, at market rate of $40/M
2).
Meat Standards Australia (MSA) Accreditation: For modelling purposes, and in the
absence of further analysis, this study has assumed MSA accreditation would increase
1 $350,000
2 $500,000
3 $70,000
APPENDIX C15MAR2016
Page 28ITEM 4
6 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
throughput by 1.5% per annum. This increase represents an additional 611 cattle per
annum, or 9 per sale.
European Union (EU) Accreditation: This analysis has assumed a cost of $2,000 per
annum for the facilities becoming accredited, with a resulting increase throughput of 0.5%
per annum.
2.2 Completed works
Between 2004 and 2010 Council implemented an extensive capital works program totalling
$1.66 million. The capital works program addressed a range of operational, animal welfare,
environmental and amenity issues.
Table 2 Capital works program expenditure since 2004/05
Year Works Amount ($)
Annual Total
2004/05
2004/05 Signage - saleyards 953
2004/05 Trees for saleyards 5,473
2004/05 Water supply to all yards 156
2004/05 Roofing of selling complex 1
2004/05 Plant & equipment 3,147
2004/05 Lighting improvements 834
2004/05 Weighbridge indicators 5,106
2004/05 Alteration to pens & lanes - stage 1 136,999
2004/05 NLIS equipment 51,078
2004/05 Project management 29,484
2004/05 North unloading area 19,324
2004/05 North holding pens 52,613
2004/05 South holding pens 20,973
2004/05 Saleyards - water trough 0
2004/05 Saleyards - annual capital works program 2,400
2004/05 EPA works 36,833
2004/05 Project management 4,131
2004/05 EPA works - effluent plumbing - spray lines & sprinklers 33,636
2004/05 EPA works - effluent ponds - excavation earthworks & construction
23,056
2004/05 Avdata truckwash 69
2004/05 EPA works - truck wash bay construction 53,055
2004/05 Feasibility study saleyards 18,820 498,139
2005/06
2005/06 Drafting yards 1,075
2005/06 Improvements to kiosk (saleyards) 18,716
2005/06 Plant & equipment 6,954
2005/06 Pa system - saleyards 3,182
2005/06 Alteration to pens & lanes - stage 1 128,575
2005/06 Project management 0
2005/06 North unloading area 55,162
2005/06 North holding pens 100,704
2005/06 South holding pens 2,571
2005/06 OH & S alterations 1,357
2005/06 Saleyards - water trough 0
2005/06 EPA works 164
APPENDIX C15MAR2016
Page 29ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 7
Year Works Amount ($)
Annual Total
2005/06 EPA works - effluent plumbing - spray lines & sprinklers 108
2005/06 EPA works - effluent ponds - excavation earthworks & construction
9,800
2005/06 EPA - security fencing 16,477
2005/06 Avdata truckwash 7,150
2005/06 EPA works - truck wash bay construction 7,063
2005/06 Demolish old truck wash 3,670
2005/06 Roadworks - design (saleyards) 178 362,906
2006/07
2006/07 North unloading area 195,952
2006/07 North holding pens 795
2006/07 Asphalt spectator area 7,050
2006/07 Roadworks - design (saleyards) 204
2006/07 Drainage & concrete yards - northern end 62,094 266,096
2007/08
2007/08 Alteration to pens & lanes - stage 1 5,455
2007/08 North holding pens 63,453
2007/08 Plant & equipment 2,087
2007/08 Saleyards - annual capital works program 377
2007/08 Saleyards - contract labour 60,868
2007/08 Saleyards - extra steel 18,594
2007/08 Saleyards - gate & panels 21,267
2007/08 Saleyards - materials 25,413
2007/08 Saleyards - plumbing 6,049
2007/08 Saleyards - sundries 26,089
2007/08 Saleyards - water trough 10,851
2007/08 South holding pens 13,394 253,897
2008/09
2008/09 Plant & equipment 12,511
2008/09 Roof & scanner - saleyards 5,427
2008/09 Saleyards - contract labour 38,603
2008/09 Saleyards - environmental works (env. Levy funded) effluent system
19,787
2008/09 Saleyards - extra steel 70,311
2008/09 Saleyards - gate & panels 11,159
2008/09 Saleyards - materials 5,785
2008/09 Saleyards - plumbing 8,402
2008/09 Saleyards - sundries 6,763
2008/09 Saleyards - water trough 29,083
2008/09 South holding pens 69,590 277,422
2009/10
2009/10 Saleyards - environmental works (env. Levy funded) 3,362 3,362
Total 1,661,822
APPENDIX C15MAR2016
Page 30ITEM 4
8 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
2.3 Current financial position
Historically the Saleyards have typically returned an annual loss or small profit, which after
accounting for loan repayments has resulted in an annual operating deficit which is absorbed by
Council.
However in recent years the financial position of the Saleyards has been steadily improving, as
loans are repaid. Throughput and revenue has also increased since the second agent was
provided access to the facilities. 2014/15 saw an increase in revenue of over $90K, due to
increased throughput (28K to 36K head) and also an increase in yard dues.
Forward projections suggest the facility will continue to return modest annual profits. Without
additional borrowing, the facility will return its first annual operating surplus in 2017/18.
Table 3 Financial performance (historical, current budget and forecast)
Year Source Revenue Expenses Profit/Loss Loan repayments
Operating Surplus/Deficit
2004/05 Historical $190,494 $170,824 $19,670 $70,943 -$51,273
2005/06 Historical $192,059 $240,603 -$48,544 $78,820 -$127,364
2006/07 Historical $220,992 $267,835 -$46,843 $105,909 -$152,752
2007/08 Historical $254,138 $240,409 $13,729 $126,492 -$112,763
2008/09 Historical $257,983 $306,536 -$48,553 $156,331 -$204,884
2009/10 Historical $278,933 $339,550 -$60,617 $183,521 -$244,138
2010/11 Historical $276,606 $260,214 $16,392 $193,355 -$176,963
2011/12 Historical $238,787 $249,947 -$11,160 $204,557 -$215,717
2012/13 Historical $215,941 $222,628 -$6,687 $182,207 -$188,894
2013/14 Historical $208,282 $252,469 -$44,187 $174,271 -$218,458
2014/15 Historical $300,796 $258,295 $42,501 $138,557 -$96,056
2015/16 Budget $297,285 $215,693 $81,592 $122,118 -$40,526
2016/17 Forecast $307,121 $243,271 $63,850 $93,626 -$29,776
2017/18 Forecast $330,035 $241,093 $88,942 $64,379 $24,563
2018/19 Forecast $354,728 $240,996 $113,732 $31,258 $82,474
2019/20 Forecast $381,339 $243,643 $137,696 0 $137,696
2020/21 Forecast $410,019 $247,795 $162,224 0 $162,224
2.4 Limit of Council subsidisation
The above projections suggest there will be some capacity for the facility to finance future loans
from annual profits, however any substantial borrowing will likely return the facility to deficit.
GHD met with the Kempsey Shire Council Financial Manager to clarify the extent to which the
Council is prepared to incur future operating deficits, should additional borrowings be required.
Council’s position is that the facility should be independently financially viable, without ongoing
Council subsidisation through annual deficits. While Council is prepared to cover occasional
deficits, ideally the facility would return a net surplus over the coming years. Council is
committed to continuing to provide staffing support for the facility, which does not appear in the
financial analysis.
2.5 Potential sources of capital
2.5.1 Reserve fund
Council has suggested the Saleyards could establish a reserve fund in which annual operating
cash surpluses can be held over and used to fund future capital works. Cash surpluses will
exclude non cash depreciation costs.
APPENDIX C15MAR2016
Page 31ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 9
2.5.2 Internal borrowings
Council has suggested that capital improvements not able to be funded via the reserve fund
could draw on internal borrowings for a short period. Internal borrowings would be repaid via the
reserve fund.
2.5.3 Environmental Levy
Some capital improvements to the Saleyards may qualify for funding under the Kempsey Shire
Council’s Environmental Levy. The levy has previously been used to fund capital improvements
at the Saleyards, including $400,000 to upgrade the WWTS. The levy is a flat annual fee of $50
per rate assessment. In 2016/17 the levy is expected to collect $731K. The current levy will
expire in 2018/19, after which time Council can reapply.
Given the WWTS remains ill-equipped to handle current and future water and nutrient loads,
capital improvements addressing this issue are likely to qualify for environmental levy funding.
Currently the WWTS is difficult to operate and results in regular occurrences of effluent runoff
into the nearby Christmas Creek, during heavy rain and flood events.
The construction of a roof over the delivery pens was recommended in the 2011 ERM
Wastewater Treatment Report (Section 2.1.1) as an effective long-term solution to wastewater
issues.
2.5.4 Sale of warehoused steel piping
Council is in the possession of a large stock of steel piping remaining from recent capital works,
which has a market value of $8,085 inc. GST (105 (8m) lengths @ $77 per length)
The steel piping could be sold or used in capital improvements to reduce costs.
2.5.5 National Stronger Regions Fund (NSRF)4
The NSRF commenced in 2015 and provides funding of $1 billion over 5 years to fund priority
infrastructure in regional communities, with grants between $20,000 and $10 million.
Round Three of the NSRF is currently open for application, and will close on Tuesday 15 March
2016.
Conditions include:
Grant funding must be matched in cash on at least a dollar for dollar basis. NSRF
funding will be provided for capital projects which involve the construction of new
infrastructure, or the upgrade or an extension of existing infrastructure.
The project must deliver an economic benefit to the region beyond the period of
construction. Projects should support disadvantaged regions or areas of disadvantage
within a region.
The NSRF funded component of the project must be completed on or before 31
December 2019.
2.5.6 Increase in fees
Council recently significantly increased yard dues, which had remained unchanged for many
years. Consultation suggests further increasing yard dues (beyond CPI) would likely result in
reduced throughput, with more local producers choosing to sell livestock at other saleyards,
direct to slaughter or via other selling options (e.g. AuctionsPlus).
4 http://investment.infrastructure.gov.au/funding/NSRF/
APPENDIX C15MAR2016
Page 32ITEM 4
10 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
3. Identified improvements
The following list of potential improvements were identified in previous reports (see Section 2.1)
and/or raised during the site visit and stakeholder consultation.
Potential improvements were prioritised according to the following criteria.
Table 4 Prioritisation rating system
Priority rating Criteria
High (short-term) Capital improvements which are:
Required in the short-term to improve operations and/or meet
regulatory standards for animal welfare, OH&S or environmental
management; and
Easily funded
High (long-term) Capital improvements which are:
Required in the long-term to improve operations and/or meet
regulatory standards for animal welfare, OH&S or environmental
management; and
More difficult to fund.
Medium Capital improvements which;
May be required in the long-term to improve operations and/or meet
regulatory standards for animal welfare, OH&S or environmental
management;
Low Capital improvements which are:
Not required in the long-term to improve operations and/or meet
regulatory standards for animal welfare, OH&S or environmental
management; or
Are not the preferred solution
3.1 Roofing over delivery yards
Constructing a roof over the delivery yards would address a number of issues facing the
facilities, by:
Reducing the amount of wastewater entering the WWTS, by allowing clean captured
rainwater to be diverted either to tank storage or nearby drains;
Eliminating the need for town water top-up during warmer months (assuming additional
tank storage is installed to manage increased water capture;
Reducing animal welfare issues by allowing the use of soft flooring (sawdust);
Reducing animal welfare issues associated with excessive heat, including water trough
overheating; and
Addressing OH&S and amenity issues associated with heat and rain.
APPENDIX C15MAR2016
Page 33ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 11
In addition to the above benefits, the construction of a roof over the delivery yards would help
enable the use of soft flooring and pen selling (discussed below).
Soft flooring
Saleyards across Australia are increasingly using sawdust over concrete flooring to reduce the
risk of lameness or stress on livestock. The use of sawdust is only appropriate if roofing is
provided.
Pen selling
Roofing would reduce exposure to heat and rain, thereby making pen selling more feasible
(following the construction of raised walkways, see section 3.5).
Table 5 Improvement summary: Roofing over delivery yards
Improvement Roofing over delivery yards
Requirement 80m x 37m gabled roof
3 X water holding tanks
Cost estimate $920,000 based on an indicative rate of $312 per m2
Source of cost
estimate
Estimate based on analysis of costs for similar saleyard roof design and
construction projects.
Estimated benefit Reduced water loading in WWTS
Improved animal welfare
Improved amenity and OH&S
Reduced cleaning costs
Priority High (long-term)
Figure 2 Delivery pens
APPENDIX C15MAR2016
Page 34ITEM 4
12 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
3.3 Roofing over holding pens
The construction of roofing over holding pens would provide shade for livestock after being sold.
Depending on the time of loading, livestock can remain in the holding pens for more than 24
hours after being sold. The holding yards have soft flooring (gravel) which somewhat reduces
the risk of lameness or stress on livestock.
It is not likely to be necessary to cover the entire holding pen area, instead coverage of half the
area would most likely provide sufficient coverage for livestock which are held for extended
periods.
Coverage over the holding pens is considered a lower priority than the delivery pens, as there
are minimal benefits from cleaning costs and reduced water loading into the WWTS.
Table 6 Improvement summary: Roofing over holding pens
Improvement Roofing over holding pens
Requirement 35m x 43m gabled roof (half holding pen area)
2 X water holding tanks
Cost estimate $470,000 based on an indicative rate of $312 per m2 (as above)
Source of cost
estimate
Estimate based on analysis of costs for similar saleyard roof design and
construction projects.
Estimated benefit Improved animal welfare
Priority Medium
Figure 3 holding yards
APPENDIX C15MAR2016
Page 35ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 13
3.4 Shade membrane
A potentially cheaper alternative to roof construction would be to install a shade membrane
structure which could be provided to both the delivery and loading pens. This would provide
shade for livestock and people, however would not provide additional benefits of a solid roof
including reduced WWTS water loads, reduced need for town water top-up and ability to install
soft flooring. While being a cheaper option, shade membranes will have a reduced effective life
(25 years) compared to a solid roof (50+ years). Some shade options and indicative prices are
provided below.
Table 7 Shade membrane options5
Shade
membrane
options
Description Unit
cost6
Example concept design
Permeable
shadecloth
“hypar”
design
Requires columns at approx.
15m distances and is typically
used for large open spaces
like shopping centre carparks
$140 M2
Permeable
shadecloth
supported
structure
Typically used to cover pools
or sporting complexes
$250 M2
Waterproof
tensile
membrane
supported
structure
Typically used to cover pools
or sporting complexes.
Reflect 80% of the sun’s heat,
whilst also allowing light
through (ie no lighting
needed), deadens the noise
and offers 100% UV protection
$420 M2
Table 8 Improvement summary: Shade membrane
Improvement Shade membrane structure
Requirement 80m x 37m shade membrane over delivery yards
Cost estimate From $140/m2 ($414,400)
Source of cost
estimate
Shade and Membrane Structures Australia
Estimated benefit Improved animal welfare
Improved amenity and OH&S
Priority Low (solid roof is preferable)
5 Provided by Shade and Membrane Structures Australia
6 Including design, engineering, fabrication, supply and complete installation
APPENDIX C15MAR2016
Page 36ITEM 4
14 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
3.5 Raised walkway
The establishment of a raised walkways along the delivery yards would allow pen selling to be
conducted at the facility, in addition to the current ring selling arrangements. Pen selling is
generally preferred to ring selling for its increased speed and improved labour efficiency. Under
current ring selling arrangements, sales can finish as late as 8pm, and up to 12 casual staff are
required to manage livestock movement. Pen selling would improve the efficiency of the
Saleyards, which would be particularly important should the facility begin operating multi-agent
sales after the conclusion of the current contract.
Despite its disadvantages, ring selling is supported by many local saleyard users who prefer the
convenience of having cattle presented along with the pre-sale weighing information.
Ideally, pen selling would be conducted undercover to avoid exposure to weather (rain and
sun). However many facilities operate open air pen selling.
Table 9 Improvement summary: Raised walkways
Improvement Raised walkways
Requirement 3 X 78m catwalks installed along delivery yards.
Cost estimate 2.75M long section 0.6m wide = $595 for materials comprising of
galvanised stanchions, expanded mesh, pipe handrails and angle for
support/kick-rail plus $130 per section to install = $725 per section.
Total cost for 3 X 78m catwalks = $62K
Source of cost
estimate
Proway Livestock Equipment
Estimated benefit Improved labour efficiency
Reduced sale time
Ability to facilitate multi-agent sales
Priority High (long-term)
3.6 New office building
The current office building is a solid brick construction and in good condition, however is proving
inefficient due to its size and location.
The office and the callers shed are situated on either side of the scales, requiring a PA system
to communicate during sales. This arrangement is proving inefficient. Furthermore the current
office building is considered too small to accommodate multiple agents at the same time.
Consultation suggests the room could be increased by 150% to accommodate multiple agents
(required for multi-agent sales).
A preferred solution would be to install a new portable office building in the central area
between the callers shed and the scales. Ideally the office building would be elevated by about
1 mitre to allow cattle in the scales to be viewed and counted. The office building would need to
be lockable and fitted out with additional furniture.
APPENDIX C15MAR2016
Page 37ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 15
Table 10 Improvement summary: New office building
Improvement New portable office building
Requirement Instillation and fitout of a new portable office building, on skid beams.
Approximately 18-20M2 with bench space and kitchenette.
Cost estimate 6mX3m portable office building delivered $15,0007
Foundations, connections and fitout: $5,000
Source of cost
estimate
ATCO structure and logistics, GHD estimate for foundations, connections
and fitout.
Estimated benefit Improved operating efficiency
Required to facilitate multiple agent sales
Priority High (long-term)
Figure 4 Proposed location for new office
3.7 New scales and pneumatic gates
The current scales are an older design with an underground pit which may pose an OH&S risk
for staff cleaning (confined space). Consultation also found the pneumatic gates on the scales
are not functioning well, and may also pose an OH&S risk. Council has previously been quoted
$14,000 to increase air tank capacity to address issues.
A preferred solution would be to install new raised platform, above ground scales, and to install
new pneumatic gates or increase air tank capacity to improve functionality of existing gates.
7 Indicative price for 12m X 3m office is $25K + GST
APPENDIX C15MAR2016
Page 38ITEM 4
16 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
Table 11 Improvement summary: New scales and pneumatic gates
Improvement New scales and pneumatic gates
Requirement Instillation of new raised platform pneumatic gates
Instillation of new pneumatic gates or increase air tank capacity to
improve functionality of existing gates.
Cost estimate New scales: $16,500
Instillation of two pneumatic guillotine gates for weigh bridge: $10,000
Source of cost
estimate
Proway Livestock Equipment and GHD estimate based on previous
saleyard project
Estimated benefit Improved operating efficiency
Improve OH&S
Priority High (short-term)
Figure 5 Scale and gates
3.8 Secondary effluent treatment system
One option for reducing WWTS loadings would be to install a secondary treatment system,
which are being used by other saleyards and truck washes to address similar issues.
These systems are typically installed following primary treatment (removal of solids) Screened
effluent water passes through three poly tanks in series which contain aeration and bacteria
dosing systems that treat the water and remove nutrients.
For Earth Pty Ltd has installed secondary treatment systems for the Roma Livestock Exchange,
Ballarat Saleyards, Harden Truchwash and Braidwood Livestock Truck Wash (Figure 6).
APPENDIX C15MAR2016
Page 39ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 17
Figure 6 A Secondary effluent treatment system installed at the Braidwood
Livestock Truck Wash (For Earth Pty Ltd)
GHD has not evaluated the suitability or effectiveness of the secondary treatment system,
however consider it may present a relatively low cost solution for the Kempsey saleyard WWTS.
Council would need to speak with suppliers and saleyards who have installed similar systems to
further investigate suitability.
Table 12 Improvement summary: Secondary Treatment System
Improvement Secondary Treatment System
Requirement Installation of a 3 tank secondary treatment system provided by For Earth
Pty Ltd or other similar provider.
Cost estimate $140,000
Source of cost
estimate
Commercial supplier, based on other installed systems.
Estimated benefit Reduced water loan on WWTS
Priority High
3.9 Scour cleaning system
Council has recently encountered difficulty keeping the delivery yards clean, within the available
budget. At present Council uses a bobcat to clean solid waste from the yards as required
(usually every 6 weeks), this costs approximately $1,600 each time.
One potential solution is to install a network of high pressure pipes and spray outlets, to scour
solid waste away from the yards. They system would use recycled wastewater from the WWTS,
providing increased opportunity for evaporation to reduce water loading. A similar system of
scour cleaning is currently being used at the Casino Saleyards.
APPENDIX C15MAR2016
Page 40ITEM 4
18 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
If the facilities were to install a roof over the delivery yards and move to soft flooring, a scouring
system would probably not be required.
Table 13 Improvement summary: Scour cleaning system
Improvement Scour cleaning system
Requirement Installation of a pumping station and sub-surface pipeline from the WWTS
to the delivery yards.
Installation of pipelines and spray outlets along each row of delivery yards
(7 x 40m).
Cost estimate Pump $50,000
Pipes, valves and outlets $60,000
Main pipe instillation $15,000
Chlorination dosing system $15,000
Pump shed $5,000
Power connection $5,000
Total $150,000
Source of cost
estimate
Commercial supplier
Estimated benefit Reduced cleaning costs (saving $1,600 every 6 weeks)
Reduced water loan on WWTS
Improved animal welfare and amenity
Priority Medium
Figure 7 Delivery yards with solid waste build-up
APPENDIX C15MAR2016
Page 41ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 19
3.10 Replace water troughs and cover copper piping
Many of the current metal stock water troughs are small in size leading to water overheating in
hot weather. To avoid overheating operators have been allowing troughs to overflow at a trickle
with the added benefit of cooling the concrete flooring below. Many troughs are possibly also
too high for very young calves to reach.
It is estimated that up to 70 troughs could be replaced, however in many cases increasing the
size of the troughs is difficult due to the need for troughs to fit between gate rails.
Overheating also occurs to the copper piping which runs along the delivery yards. This piping
could be covered or lined with plastic to avoid overheating.
Replacing water troughs and covering coper piping may not be necessary if a roof were to be
constructed over delivery yards, as shade would avoid overheating.
Table 14 Improvement summary: Replace water troughs and cover copper
piping
Improvement Replace water troughs and cover copper piping
Requirement Replacement of 70 water troughs with larger PVC troughs
Covering or lining of coper pipe with PVC
Cost estimate Replacement of water troughs: $14,000 ($200 each installed)
Cover coper pipe: $3,000
Source of cost
estimate
Commercial suppliers/GHD estimate
Estimated benefit Improved animal welfare and amenity
Priority High (short-term)
APPENDIX C15MAR2016
Page 42ITEM 4
20 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
3.12 WWTS maintenance works
$50,000 has been requested from the 2016/17 budget to implement a range of minor
improvements to the current WWTS and irrigated areas to improve efficiency. Improvements are
consistent with the recommendations of the Wastewater Treatment Report (ERM 2011),
discussed in 2.1.1 and Appendix A.
Table 15 Improvement summary: WWTS efficiency works
Improvement WWTS efficiency works
Requirement Improvements to bunding, irrigation systems and solid management
Cost estimate $50,000 requested in 2016/17 budget
Source of cost
estimate
Council
Estimated benefit Improved WWTS efficiency
Priority High (short-term)
APPENDIX C15MAR2016
Page 43ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 21
3.14 Minor upgrades and general maintenance
Consultation identified a range of opportunities for minor upgrades and improved general
maintenance, listed below.
Table 16 Improvement summary: Minor upgrades and general maintenance
Improvement Details Estimated
Cost
Source of cost
estimate
Estimated
Benefit
Priority
CCTV CCTV would
prevent stock theft,
vandalism or
unauthorised use
of the yards.
4 camera unit with
monitor
8,000
including
labour
(price estimate
from supplier)
Commercial
supplier and
Council estimate
Improved
security,
safety and
revenue
collection
High
(short-
term)
Additional
signage and
address
other safety
issues
identified in
Appendix A
The Council Safety
Officer has
developed a list of
safety non-
conformance
items, which
should be
addressed, in
particular the need
for improved
signage and other
capital
improvements.
$2,000
(GHD
estimate)
GHD estimate Improved
OH&S
High
(short-
term)
Fix/replace
bent gates
Small number of
gates are bent and
are difficult to close
$2,000
(GHD
estimate)
GHD estimate Improved
efficiency
High
(short-
term)
Additional
lighting
Additional lighting
required at certain
points of delivery
and loading yards
$1,500
(GHD
estimate)
GHD estimate Improved
OH&S and
efficiency
Medium
More
frequent
cleaning
Agents requesting
more frequent
cleaning with
bobcat (every 4
weeks).
$6,400 per
annum
(4 additional
cleans @
$1,600 each)
Council estimate
based on
current costs
Improved
animal
welfare,
OH&S and
amenity
High
(short-
term)
Add more
gravel to
loading yards
Loading yards
require additional
gravel from time to
time to avoid mud
forming
$1,000 per
year
GHD estimate Improved
animal
welfare,
OH&S and
amenity
High
(short-
term)
APPENDIX C15MAR2016
Page 44ITEM 4
22 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
3.15 Summary of priority investments
The table below summarises the high, medium and low priority improvements.
Table 17 Summary of capital improvements by priority
Priority Capital improvement Estimated cost
High (short term)
CCTV $8,000
Additional signage and other safety issues $2,000
Fix/replace bent gates $2,000
New scales and pneumatic gates $26,000
Replace water troughs and cover copper
piping
$17,000
WWTS maintenance works $50,000
More frequent cleaning (x 6 per year) $6,400 per annum
Add more gravel to loading yards $1,000 per annum
High (longer term)
New office building (scalers shed) $20,000
Raised walkway $150,000
Secondary effluent treatment system $140,000
Roofing over delivery yards $920,000
Medium
Scour cleaning system $100,000
Additional lighting $1,500
Roofing over holding pens $470,000
Low Shade membrane structure $414,400
APPENDIX C15MAR2016
Page 45ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 23
5. Proposed capital works program
The central investment decision for the Saleyards is whether to construct a roof over the
delivery pens and raised walkway to allow pen selling, which would require funds to be drawn
from the environmental levy or other sources (e.g. the National Stronger Regions Fund).
GHD consider the construction of a roof is a long term high priority for the Saleyards, however
there a number of short-term and less expensive improvements which could be made sooner to
help improve the operation of the facilities. The proposed capital works program outlined below,
seeks to address these short-term priority improvements, before committing to roof construction
in 2018/19.
This approach will allow the facility to continue to build throughput and address operational
issues, strengthening the case for roof construction. The construction of raised walkways and a
new office building in 2017/18 will enable pen selling to be introduced improving saleyard
efficiency and throughput.
Overall this proposed capital works program will prepare the facilities for a future beyond the
current lease agreement, which is likely to involve non-exclusive access and multi-agent sales.
Table 18 Proposed capital works program
Improvement Description Price estimate (excl. GST)
2016/17
CCTV 4 camera unit with monitor installed $8,000 installed
Additional signage and other safety issues
The Council Safety Officer has developed a list of safety non-conformance items, which should be addressed, in particular the need for improved signage and other capital improvements.
$2,000
Fix/replace bent gates
Small number of gates are bent and are difficult to close
$2,000
More frequent cleaning
Agents requesting more frequent cleaning with bobcat (every 4 weeks).
$6,400 per annum
(4 additional cleans @ $1,600 each)
Add more gravel to loading yards
Loading yards require additional gravel from time to time to avoid mud forming
$1,000 per annum
New scales and pneumatic gates
Instillation of new raised platform pneumatic gates
Instillation of new pneumatic gates or increase air tank capacity to improve functionality of existing gates.
New scales: $16,500
Instillation of two pneumatic guillotine gates for weigh bridge: $10,000
Replace water troughs and cover copper piping
Replacement of 70 water troughs with larger PVC troughs
Covering or lining of coper pipe with PVC
$17,000
Replacement of water troughs: $14,000 ($200 each installed)
Cover coper pipe: $3,000
WWTS maintenance works
Improvements to bunding, irrigation systems and solid management
$50,000 requested in 2016/17 budget
2017/18
New office building
Instillation and fitout of a new portable office building, on skid beams.
Approximately 18-20M2 with bench space and kitchenette.
Office building: $15,000 (indicative price provided by ATCO structure and logistics for a 6mX3m portable office delivered)
Foundations, connections and fitout:
APPENDIX C15MAR2016
Page 46ITEM 4
24 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
Improvement Description Price estimate (excl. GST)
$5,000
Raised walkway
3 X 78m catwalks installed along delivery yards.
2.75M long section 0.6m wide = $595 for materials comprising of galvanised stanchions, expanded mesh, pipe handrails and angle for support/kick-rail plus $130 per section to install = $725 per section.
Total cost for 3 X 78m catwalks = $62,000
2018/19
Secondary effluent treatment system
3 poly tank secondary treatment system installed
$140,000
2019/20
Roof over delivery yards
80m x 37m gabled roof
3 X water holding tanks and connections
$920,000 based on an indicative rate of $312 per m
2 (arrived at following
analysis of costs for similar saleyard roof design and construction projects)
A $400,000 contribution from the Environmental levy would reduce the outlay to $520,000
50% completed in 2018/19 = $460,000
2020/21
Roof completed Remaining 50% completed in 2018/19 = $460,000
APPENDIX C15MAR2016
Page 47ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 25
5.2 Capital improvements excluded from the program
The following capital improvements investigated in Section 2.3 above, were excluded from the
proposed capital works program.
Table 19 Excluded capital improvements
Excluded capital
improvement
Reason for exclusion
Roofing over the
holding yards
Roofing costs prohibit covering the both the delivery and holding yards.
Roofing over the delivery yards is a higher priority due to potential benefits
in waste water load reduction, animal welfare (ability to facilitate soft
flooring), and human amenity
Shade membrane Compared to a solid roof, a shade membrane structure will not facilitate
water collection to reduce waste water loadings, and will have a reduced
lifespan.
Costs for constructing shade cloth structure are not significantly lower than
constructing a solid roof
Scour cleaning
system
Construction of a roof over delivery yards would negate the need for scour
cleaning system.
If in the future a roof does not receive funding, a scour cleaning system
could be reconsidered.
Additional lighting Additional lighting would be installed with the construction of a roof over the
delivery yards (factored into price)
APPENDIX C15MAR2016
Page 48ITEM 4
26 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
6. Financial plan
Table 20 presents the proposed capital works schedule for the Saleyards. Capital improvements
have been spaced out, in order to reduce the need for additional borrowing.
Table 20 Capital works schedule
2016/17 2017/18 2018/19 2019/20 2020/21
CCTV $8,000
Signage and safety $2,000
Fix bent gates $2,000
Scales and gates $26,500
Replace water trough and cover copper pipe
$17,000
WWTS maintenance works
$50,000
New office $20,000
Raised walkways $62,000
Secondary effluent treatment system
$140,000
Roofing over delivery yards (initial)
$460,000
Roofing over delivery yards (final)
$460,000
Total capital cost $105,500 $82,000 $140,000 $460,000 $460,000
APPENDIX C15MAR2016
Page 49ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 1
Table 21 below presents the financial projections for the Saleyards. Annual operating cash surpluses (excluding depreciation) will be held in a reserve fund
and used for future capital improvements. The funding shortfall (i.e. when the balance of the reserve fund falls below zero in 2019/20 and 2010/21) will be
obtained from internal borrowings and rapidly repaid in the following year.
Modelling has been conducted using the following assumptions:
Improvements lead to an increase in annual saleyard throughput of 3% per annum until 2020/21 after which throughput plateaus.
Annual costs and fees increase with CPI.
Table 21 Financial projections
Projections 2015/2016 2016/2017 2017/2018 2018/2019 2019/2020 2020/2021 2021/2022 2022/2023 2023/2024
Throughput
(assuming 3% annual increase)
36,255 37,343 38,463 39,617 40,805 42,029 42,029 42,029 42,029
Revenue $297,285 $307,121 $330,035 $354,728 $381,339 $410,019 $421,499 $433,301 $445,434
Operating expenses (including interest)
$215,693 $243,271 $241,093 $240,996 $243,643 $247,795 $252,097 $256,556 $261,177
Annual operating profit (loss) $81,592 $63,850 $88,942 $113,732 $137,696 $162,224 $169,402 $176,745 $184,257
Existing loan repayments $122,118 $93,626 $64,379 $31,258 $- $- $- $- $-
Annual operating surplus (deficit) -$40,526 -$29,776 $24,563 $82,474 $137,696 $162,224 $169,402 $176,745 $184,257
Reserve Fund
Input
(Annual operating surplus excluding depreciation costs)
$68,149 $99,124 $147,737 $199,130 $246,960 $263,132 $269,527 $276,064 $282,747
Withdrawal
(Proposed capital works)
$- $105,500 $82,000 $140,000 $460,000 $460,000 $- $- $-
Balance $68,149 $61,773 $127,510 $186,640 -$26,400 -$223,268 $46,259 $322,323 $605,070
Internal borrowings $- $- $- $- $26,400 $223,268 $- $- $-
The full financial projection analysis, including all line items and assumptions is provided in Appendix B,
APPENDIX C15MAR2016
Page 50ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 1
6.1 Sensitivity analysis
Table 22 below shows how the total funding required from internal borrowings (i.e. the funding
shortfall) would vary, under changes to key assumptions around annual throughput growth.
Table 22 Sensitivity analysis: impact on net funding shortfall from changes
in annual throughput
Annual increase in annual throughput
(20/21 throughput level)
Total funding required from internal borrowings (funding shortfall)
0% (36K) $486,313
1% (38K) $393,233
2% (40K) $299,930
3% (42K) $249,666
4% (44K) $198,515
5% (46K) $146,465
6.2 Low investment option
If sufficient funding cannot be obtained to construct a roof structure, a lower investment option
would need to be considered. This option would include the establishment of shade cloth,
walkways and a scour cleaning system as well as other improvements.
APPENDIX C15MAR2016
Page 51ITEM 4
2 | GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
7. Summary of findings and
recommendations
Having undergone previous capital works and repaid debt, the Kempsey Regional Saleyards
are expected to return operating surpluses in coming years, allowing Council to undertake
additional targeted capital improvements.
The capital works schedule proposed in this report aims to prepare the facility for servicing
multiple agents following the expiration of the current lease, without burdening Council with
unsustainable debt levels.
Failure to reinvest in the facility will most likely lead to a steady decline in operational efficiency
and increased scrutiny on animal welfare, environmental management and OH&S.
A summary of recommendation from this report is provided below.
7.1 Summary of recommendations
1. Implement the capital works program as outlined in this report, while monitoring annual
changes to throughput, revenue and expenses against projections.
2. Investigate opportunities to draw on the Environmental Levy or the National Stronger
Regions Fund to help fund the construction of a roof over delivery yards.
3. Ensure all usage fees are regularly adjusted for CPI.
4. Revisit the business development actions outlined in the Saleyard Business Plan
including activities aimed at improving promotion, broaden the Saleyards supply area and
improving security/revenue collection.
5. Begin planning and preparations for beyond the current lease agreement. If Council is to
hold multi-agent sales, how will sales be managed? Will additional resources be
required?
6. If the Council is not fully committed to managing the facility to its full potential, including
the management of multi-agent sales, the Council should seek to outsource management
or sell the facility.
APPENDIX C15MAR2016
Page 52ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 3
8. References
ERM (2008) Kempsey Saleyard Wastewater Treatment System Design Upgrade, ERM May
2008.
ERM (2006) Kempsey Saleyard Effluent Treatment System Operation and Maintenance
Manual, ERM January 2006.
ERM (2011) Kempsey Saleyard Wastewater Treatment System Improvement Options, ERM
October 2011.
Kempsey Shire Council (2014) Kempsey Regional Saleyards Business Plan, Kempsey Shire
Council May 2014.
Kempsey Shire Council (2015) Annual Report 2014/15, Kempsey Shire Council 2015.
GHD (2013), Kempsey Regional Saleyards, Analysis and Financial Modelling, GHD May 2013.
Huefner & Associates (2005) Kempsey Regional Saleyards Infrastructure Review and
Feasibility Study, Huefner & Associates January 2005.
APPENDIX C15MAR2016
Page 53ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
Appendices
APPENDIX C15MAR2016
Page 54ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154 | 5
Appendix A – Summary of recommended management options for WWTS (ERM 2011)
Management Area Recommended Management Options Effectiveness Estimated Cost
1 - Saleyard
Roof entire saleyard area and direct clean water into holding tanks for reuse in truck-wash
1 $500,000 - $600,000
Remove current tank overflow from WWTS and divert clean water to nearest stormwater outlet or wetland
1 $3,000 - $5,000
2 – Truck-wash and Sludge Dewatering and Disposal Area
Improve maintenance program for Truck-wash
1 $500 - $1000 per sale event
Provide roofed dewatering bay 1 $20,000 - $40,000
3- WWTS Install baffle weirs 1 $1000 - $2000
Wetland treatment of Ponds 1 and 2 1 $3,000
Water quality monitoring program N/A $4,000 per year
4– Irrigation Areas Actively manage irrigation area (i.e. rotational resting, or tilling soils and plant improved pasture ect)
3 $500 - $1,000 per event
Fill in contour drains and create contour banks (not required if using for improved pasture)
2 $2,000 - $4,000
Re-alignment of existing and installation of additional sprinkler heads in southern holding paddock.
1 $3,000 - $5,000
Divert upstream catchment on-flow run-on.
1 $3,000 - $6,000
Investigate options for relocation / removal of headwall and pipe structure the Southern Irrigation Area
1 N/A
Undertake feasibility study for transfer to treated wastewater to sewer network
1 N/A
5 – Revegetation Areas
Further revegetate strip of vegetation along bund on western boundary of property
3 $3,000 plus planting and maintenance costs
Consider raising height of bund to retain more water for uptake by planted vegetation
3 $1,000
Initiate broader revegetation project for 1 ha parcel of land in the north western corner of the site.
3 $9,000 plus planting and maintenance costs
Effectiveness Ranking in Achieving Improved Water Quality:
1- Considered most effective based on minimising load and nutrient levels within wastewater 2- Considered 2
nd most effective based on reducing nutrient levels in wastewater
3- Considered 3rd
most effective based on final polishing of water quality.
APPENDIX C15MAR2016
Page 55ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
Appendix B Financial modelling
Year 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29
Estimate Actual Actual Actual Actual Budget Modelled Modelled Modelled Modelled Modelled Modelled Modelled Modelled Modelled Modelled Modelled Modelled Modelled
1 Throughput 30,179 25,304 27,725 36,255 36,255 38,068 39,971 41,970 44,068 46,272 46,272 46,272 46,272 46,272 46,272 46,272 46,272 46,272
Revenue
2 Agents Fees 273$ 13,636$ 409$ 714$ 1,000$ 300$ 308$ 317$ 326$ 335$ 344$ 354$ 364$ 374$ 385$ 395$ 406$ 418$
3 Yard Dues - Owners 172,783$ 160,174$ 148,539$ 219,626$ 208,953$ 229,000$ 247,183$ 266,809$ 287,994$ 310,860$ 319,564$ 328,512$ 337,710$ 347,166$ 356,887$ 366,880$ 377,152$ 387,713$
4 Selling Fees - Agents 34,841$ 28,222$ 23,919$ 42,994$ 46,540$ 41,400$ 44,687$ 48,235$ 52,065$ 56,199$ 57,773$ 59,390$ 61,053$ 62,763$ 64,520$ 66,327$ 68,184$ 70,093$
5 Agents Fees - Complex Hire 13,636$ - 19,346$ 26,885$ 20,000$ 23,000$ 23,644$ 24,306$ 24,987$ 25,686$ 26,405$ 27,145$ 27,905$ 28,686$ 29,489$ 30,315$ 31,164$ 32,037$
6 Rental - Kiosk 4,602$ 2,654$ 2,716$ 2,005$ 5,585$ 3,000$ 3,084$ 3,170$ 3,259$ 3,350$ 3,444$ 3,541$ 3,640$ 3,742$ 3,846$ 3,954$ 4,065$ 4,179$
7 Rental - Holding Paddocks 3,055$ - 4,623$ 2,285-$ 1,689$ 1,721$ 1,769$ 1,819$ 1,870$ 1,922$ 1,976$ 2,031$ 2,088$ 2,146$ 2,207$ 2,268$ 2,332$ 2,397$
8 Sponsorship Signage 2,273$ 591$ 2,955-$ 2,773$ 2,216$ 600$ 617$ 634$ 652$ 670$ 689$ 708$ 728$ 748$ 769$ 791$ 813$ 836$
9 Truck Wash Income 7,442$ 8,436$ 7,134$ 7,924$ 11,081$ 8,000$ 8,635$ 9,321$ 10,061$ 10,860$ 11,164$ 11,476$ 11,798$ 12,128$ 12,468$ 12,817$ 13,176$ 13,545$
10 Sundries 118-$ 2,228$ 4,551$ 160$ 221$ 100$ 108$ 117$ 126$ 136$ 140$ 143$ 147$ 152$ 156$ 160$ 165$ 169$
11 Total Operating Revenue 238,787$ 215,941$ 208,282$ 300,796$ 297,285$ 307,121$ 330,035$ 354,728$ 381,339$ 410,019$ 421,499$ 433,301$ 445,434$ 457,906$ 470,727$ 483,907$ 497,457$ 511,386$
Expenses
12 Operating Expenses 92,680$ 85,070$ 99,975$ 119,360$ 92,342$ 95,740$ 99,263$ 102,916$ 106,704$ 110,630$ 114,702$ 118,923$ 123,299$ 127,836$ 132,541$ 137,418$ 142,475$ 147,718$
13 Yard Cleaning -$ -$ -$ -$ -$ 6,400$ 6,579$ 6,763$ 6,953$ 7,147$ 7,348$ 7,553$ 7,765$ 7,982$ 8,206$ 8,436$ 8,672$ 8,915$
14 Gravel -$ -$ -$ -$ -$ 1,000$ 1,028$ 1,057$ 1,086$ 1,117$ 1,148$ 1,180$ 1,213$ 1,247$ 1,282$ 1,318$ 1,355$ 1,393$
15 Depreciation 98,073$ 90,939$ 117,505$ 115,900$ 108,675$ 128,900$ 128,900$ 128,900$ 128,900$ 128,900$ 128,900$ 128,900$ 128,900$ 128,900$ 128,900$ 128,900$ 128,900$ 128,900$
16 Interest on existing loan 59,194$ 46,619$ 34,989$ 23,035$ 14,676$ 11,231$ 5,322$ 1,360$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
17 Total Operating Expenses 249,947$ 222,628$ 252,469$ 258,295$ 215,693$ 243,271$ 241,093$ 240,996$ 243,643$ 247,795$ 252,097$ 256,556$ 261,177$ 265,966$ 270,929$ 276,072$ 281,402$ 286,926$
18 Operating Profit 11,160-$ 6,687-$ 44,187-$ 42,501$ 81,592$ 63,850$ 88,942$ 113,732$ 137,696$ 162,224$ 169,402$ 176,745$ 184,257$ 191,940$ 199,798$ 207,836$ 216,055$ 224,460$
19 Existing loan repayments 204,557$ 182,207$ 174,271$ 138,557$ 122,118$ 93,626$ 64,379$ 31,258$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
20 Operating surplus/(deficit) 215,717-$ 188,894-$ 218,458-$ 96,056-$ 40,526-$ 29,776-$ 24,563$ 82,473$ 137,696$ 162,224$ 169,402$ 176,745$ 184,257$ 191,940$ 199,798$ 207,836$ 216,055$ 224,460$
21 Reserve fund (input) 68,149$ 99,124$ 153,463$ 211,373$ 266,596$ 291,124$ 298,302$ 305,645$ 313,157$ 320,840$ 328,698$ -$ -$ -$
22 Reserve fund (withdrawal) -$ 105,500$ 82,000$ 140,000$ 460,000$ 460,000$ -$ -$ -$ -$ -$ -$ -$ -$
23 Reserve fund (balance) 68,149$ 61,773$ 133,237$ 204,610$ 11,205$ 157,671-$ 140,631$ 446,276$ 759,433$ 1,080,273$ -$ -$ -$ -$
24 Internal borrowings -$ -$ -$ -$ 26,399$ 223,267$ -$ -$ -$ -$ -$ -$ -$ -$
APPENDIX C15MAR2016
Page 56ITEM 4
GHD | Report for Kempsey Shire Council - Kempsey Regional Saleyards, 22/18154
Table 23 Description and assumptions for financial modelling items
Line Title Description and modelling assumptions
1 Throughput Annual cattle sold, 3% increase per annum following improvements, plateauing from 2020/21
2 Agents Fees Fees for service, Linked to CPI
3 Yard Dues - Owners Per head selling fees collected, Linked to CPI
4 Selling Fees - Agents Per head weighing fees collected, Linked to CPI
5 Agents Fees - Complex Hire Expected income linked to CPI
6 Rental - Kiosk Expected income linked to CPI
7 Rental - Holding Paddocks Expected income linked to CPI
8 Sponsorship Signage Expected income linked to CPI
9 Truck Wash Income Expected income linked to CPI
10 Sundries Expected income linked to CPI
11 Total Operating Revenue Total revenue collected
12 Operating expenses Expected operating expenses
13 Yard Cleaning Regular cleaning costs, linked to CPI
14 Gravel Additional gravel added to receival yards, $1000 per annum
15 Depreciation As per Council estimate
16 Interest on existing loan As per current loans
17 Total Operating Expenses Total operational costs (including interest)
18 Operating Profit Total Operating Revenue minus Expenses
19 Existing loan repayments Principal repayments from existing loans
20 Operating surplus/(deficit) Operating profit minus loan repayments
21 Reserve fund (input) Operating cash surplus (excluding non cash depreciation costs)
22 Reserve fund (withdrawal) Withdrawals to fund capital works
23 Reserve fund (balance) Remaining balance in reserve fund
24 Internal borrowings Funding shortfall (when capital works exceeds amount in reserve fund).
APPENDIX C15MAR2016
Page 57ITEM 4
GHD
133 Castlereagh St Sydney NSW 2000 - T: +61 2 9239 7100 F: +61 2 9239 7199 E: [email protected]
© GHD 2016
This document is and shall remain the property of GHD. The document may only be used for the purpose for which it was commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised use of this document in any form whatsoever is prohibited.
N:\AU\Sydney\Projects\22\18154\WP\Kempsey Regional Saleyards Financial Plan (Final Draft).docx
Document Status
Rev No.
Author Reviewer Approved for Issue
Name Signature Name Signature Date
1 S Hoban W Van Lindt S Keevil-Jones 29/01/2016
2 S Hoban W Van Lindt S Keevil-Jones 29/02/2016