    LUMBINI SPORT COMPLEX

    Present by : Bandara K.A.J.M.

    RU/E/2008/014

    Department of Civil and Environmental EngineeringJanuary , 2012

  • 8/3/2019 Lumbini Sport Complex

    2/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TRAINING PLACEMENT

    Central Engineering Consultancy Bureau

    ~ CECB is the largest engineering consultancy & construction organization

    in Sri Lanka.

    ~ CECB is having about 10 regional base offices & 5 international base

    offices.

    ~ It consist of over 400 Engineers and 50 Architects and 600 Para Engineering

    staff.

    ~ It was established in 1973

  • 8/3/2019 Lumbini Sport Complex

    3/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    INTRODUCTION

    Contractor : Central Engineering Consulting Bureau.

    Structural design : CECB Design office

    Architectural design : CECB Design office

    Client : Ministry of Education

    Project cost : 87 million rupees

    Time for completion : 410 days.

    Project commencement date : 01/10/2010

    Schedule date for completion : 15/11/2011

    Source of fund : Source of funds is the Mahapola funds of

    government of Sri Lanka.

    Percentage of retention : 10% of initial contract price

  • 8/3/2019 Lumbini Sport Complex

    4/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    LOCATION

  • 8/3/2019 Lumbini Sport Complex

    5/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    PROJECT DETAILS

    39.3m

    26.8m

    12.5m

  • 8/3/2019 Lumbini Sport Complex

    6/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    PROJECT DETAILS

    Floor AreasGround Floor - 1063.66 sq. m

    First Floor - 517.64 sq. m

    Superstructure

    Superstructure consist of reinforced concrete 22 nos 300600 mm size columns,

    06 nos 300300 mm size columns and 11 nos 225225 mm size columns fromground level to roof. First floor slab thickness is 150 mm and seating area of first

    floor consist 150 mm thick slab strips and beam.

    Roof

    Zn/Al roofing materials rest on the steel trusses.

    Floor finishes

    Ground and First Floor - Cement rendered floor with approved colour

    cement floating.

    Play Area -Timber flooring

  • 8/3/2019 Lumbini Sport Complex

    7/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    PROJECT DETAILS

    Wall finishesInternal - Smooth wall finished by two coats of wall putty & painted with

    one coat of primer & two coats of emulsion paint.

    External - Semi rough plasters & painted with one coat of primer & two

    coats of weather shield paint.

    Soffit - Smooth finished with two coats of wall putty and painted with one primer

    coat & two coats of emulsion paint.

    Doors & Windows

    Natural anodized aluminum doors and windows.

    500 PEOPLE CAN SIT THE FIRST FLOOR SEATING AREAS.

  • 8/3/2019 Lumbini Sport Complex

    8/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCES

    COLUMN CONSTRUCTION

    ~ Over vibrating

    ~ Released concrete from more than 1.2m

    ~ Slump of concrete lower or higher than required value

    ~ Leakage of grout though the form work which is not fixed properly

  • 8/3/2019 Lumbini Sport Complex

    9/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCES

    6m>

    Chemical

    anchorage

  • 8/3/2019 Lumbini Sport Complex

    10/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCES

    Opening panel

    ~ Vehicle entry into building

    ~ Easy access material

  • 8/3/2019 Lumbini Sport Complex

    11/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCES

    75x75x8mm L angel

    60x60x6mm L angel

    ROOF CONSTRUCTION

    450x200x76mm

  • 8/3/2019 Lumbini Sport Complex

    12/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCESSTEEL PROTECTION

    ~ Galvanising[galvanized coating is

    expected to last 40 years]

    ~ Painting[10 years]

    InitialGalvanizing

  • 8/3/2019 Lumbini Sport Complex

    13/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCES

    Temporary bracing

    Connection point

  • 8/3/2019 Lumbini Sport Complex

    14/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCES

    Slag

    Anchor bolt

  • 8/3/2019 Lumbini Sport Complex

    15/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCES

    450x200x76mm I section

  • 8/3/2019 Lumbini Sport Complex

    16/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCES

    Wall connection

    BRACING SYSTEM

  • 8/3/2019 Lumbini Sport Complex

    17/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    TECHNICAL EXPERIENCES

    MC foil

    GS mesh

    JOINT

  • 8/3/2019 Lumbini Sport Complex

    18/18

    Department of Civil and Environmental EngineeringJanuary , 2012

    SAFETY

    Provide Safety Equipment's (helmets, safetyshoes, boots, goggles, gloves and safety belts)

    Safety Instruction Boards

    Cutting goggle

    Health protection