memo wizards 08-25-2010
TRANSCRIPT
Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of foundations are ongoing in Area 3.
Site Utilities:
Tie in of domestic and fire line services are being tied in
on the east side of France Family Drive.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site.
Concrete Flatwork:
Area 2 – Prep work for next slab pour is complete from
Column Line 15 – 12.
Structural Steel Erection:
Area 2 – Main Canopy Truss Erection are set to Column
Line 12.
Precast Concrete:
Area 3 – Precast erection is nearly complete to Column
Line 1.
Underground MEP:
Area 3 - Deep underground Plumbing is ongoing.
MEP Rough-in:
Area 3 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite and Press Levels
are ongoing. Plumbing rough-in is ongoing on Suite and
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 8.25.2010
Re: Wizards Stadium Project
Update – Week of
8.23.2010
Area 3 – Connection of the domestic water
and fire sprinkler service lines.
Area 3 – Precast tread/riser erection is
nearly complete.
Field Level Area 4 – Excavation of North
Field wall footing.
Building the Future
Press Levels. Fire Protection rough-in is ongoing on
Suite and Press Levels.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas F, G and H.
Area 3 Concourse Level – Picture framing is ongoing
for south/east concourse buildings.
Projected Activities occurring next Week:
Site Utilities:
Gas Service installation will begin on France Family Drive.
Deep Underground MEP:
Deep Plumbing installation will continue in Area 3.
Foundations:
Area 4 Field Level – Foundation installation will continue
at north field walls.
Concrete Flatwork:
Area 2 Field Level – Concrete placement for Slab-on
Grade between Column Lines 15 - 12.
Area 1, 2 and 3 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Structural Steel Erection:
Area 2 – Canopy truss installation at South side of Stadium
Will continue. Area 3 – Canopy Truss installation will begin.
Underground MEP:
Deep underground plumbing will continue in Area 3.
Area 1 – Shot of the West Building from
Column Line 1 (Field Level).
Mezzanine Level Area 1 – Metal Stud
Framing has started at the VIP Area.
Area 2 – Canopy Truss erection is ongoing in
Sequence 2-2 (installation of Truss at 12-
Line shown).
Building the Future
MEP Rough-in:
MEP Rough-in at Suite and Press Levels will continue.
Ductwork installation on Press Level will continue. Fire
Sprinkler installation will continue on Suite and Press Levels.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue.
Area 1 – Installation of curtainwall framing
at West Building is ongoing.
Roof Level Area 1 – West parapet wall
framing is ongoing.
Building the Future
Additional Photos:
Field Level Area 1 – Concrete placement for
Stair 11 foundation walls.
Concourse Level Area 1 – Terrace Area
concrete placement is nearly complete.
Area 2 – Shot looking at south elevation of
Stadium.
Concourse Level Area 1 – South concourse
platform concrete being finished.
Concourse Level Area 3 – Masonry “picture
framing” at East Concourse Buildings.
Field Level Area 3 – Cast-in-place concrete
riser installation at east seating.