Building the Future Current Activities this Week : Mass Excavation : Backfilling of foundations are ongoing in Area 3. Site Utilities : Tie in of domestic and fire line services are being tied in on the east side of France Family Drive. Foundations : Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork : Area 2 – Prep work for next slab pour is complete from Column Line 15 – 12. Structural Steel Erection : Area 2 – Main Canopy Truss Erection are set to Column Line 12. Precast Concrete : Area 3 – Precast erection is nearly complete to Column Line 1. Underground MEP : Area 3 - Deep underground Plumbing is ongoing. MEP Rough-in: Area 3 – Shallow electrical and plumbing rough-in is ongoing. Ductwork installation on Suite and Press Levels are ongoing. Plumbing rough-in is ongoing on Suite and To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 8.25.2010 Re: Wizards Stadium Project Update – Week of 8.23.2010 Area 3 – Connection of the domestic water and fire sprinkler service lines. Area 3 – Precast tread/riser erection is nearly complete. Field Level Area 4 – Excavation of North Field wall footing.

Upload: kansas-city-wizards

Post on 26-Jun-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Memo wizards 08-25-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of foundations are ongoing in Area 3.

Site Utilities:

Tie in of domestic and fire line services are being tied in

on the east side of France Family Drive.

Foundations:

Area 3 Field Level – Foundation installation continues on

the east side of the site.

Concrete Flatwork:

Area 2 – Prep work for next slab pour is complete from

Column Line 15 – 12.

Structural Steel Erection:

Area 2 – Main Canopy Truss Erection are set to Column

Line 12.

Precast Concrete:

Area 3 – Precast erection is nearly complete to Column

Line 1.

Underground MEP:

Area 3 - Deep underground Plumbing is ongoing.

MEP Rough-in:

Area 3 – Shallow electrical and plumbing rough-in is

ongoing. Ductwork installation on Suite and Press Levels

are ongoing. Plumbing rough-in is ongoing on Suite and

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 8.25.2010

Re: Wizards Stadium Project

Update – Week of

8.23.2010

Area 3 – Connection of the domestic water

and fire sprinkler service lines.

Area 3 – Precast tread/riser erection is

nearly complete.

Field Level Area 4 – Excavation of North

Field wall footing.

Page 2: Memo wizards 08-25-2010

Building the Future

Press Levels. Fire Protection rough-in is ongoing on

Suite and Press Levels.

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels are ongoing.

Masonry:

Area 1 Field Level – Masonry wall installation is ongoing

in Areas F, G and H.

Area 3 Concourse Level – Picture framing is ongoing

for south/east concourse buildings.

Projected Activities occurring next Week:

Site Utilities:

Gas Service installation will begin on France Family Drive.

Deep Underground MEP:

Deep Plumbing installation will continue in Area 3.

Foundations:

Area 4 Field Level – Foundation installation will continue

at north field walls.

Concrete Flatwork:

Area 2 Field Level – Concrete placement for Slab-on

Grade between Column Lines 15 - 12.

Area 1, 2 and 3 Field Level – Installation of on-grade seating

risers and intermediate stairs will continue.

Structural Steel Erection:

Area 2 – Canopy truss installation at South side of Stadium

Will continue. Area 3 – Canopy Truss installation will begin.

Underground MEP:

Deep underground plumbing will continue in Area 3.

Area 1 – Shot of the West Building from

Column Line 1 (Field Level).

Mezzanine Level Area 1 – Metal Stud

Framing has started at the VIP Area.

Area 2 – Canopy Truss erection is ongoing in

Sequence 2-2 (installation of Truss at 12-

Line shown).

Page 3: Memo wizards 08-25-2010

Building the Future

MEP Rough-in:

MEP Rough-in at Suite and Press Levels will continue.

Ductwork installation on Press Level will continue. Fire

Sprinkler installation will continue on Suite and Press Levels.

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels will continue.

Area 1 – Installation of curtainwall framing

at West Building is ongoing.

Roof Level Area 1 – West parapet wall

framing is ongoing.

Page 4: Memo wizards 08-25-2010

Building the Future

Additional Photos:

Field Level Area 1 – Concrete placement for

Stair 11 foundation walls.

Concourse Level Area 1 – Terrace Area

concrete placement is nearly complete.

Area 2 – Shot looking at south elevation of

Stadium.

Concourse Level Area 1 – South concourse

platform concrete being finished.

Concourse Level Area 3 – Masonry “picture

framing” at East Concourse Buildings.

Field Level Area 3 – Cast-in-place concrete

riser installation at east seating.