monreal del campo calamocha appendix 4 a23...
TRANSCRIPT
March 2011 | Frontier Economics, Atkins, ITS 1
Appendix 4 – A23 Motorway in Spain
Appendix 4 – A23 Motorway in Spain
This chapter presents the results of the ex post analysis for the project covering
the construction of four sections of the A23 motorway in Spain.
4.1 Introduction
4.1.1 Project overview
Location
The Cohesion Fund contributions for the period 2000-2006 cover two sections
of the A23 motorway, between Teruel and Calamocha and between Huesca and
Nueno.
Figure 1. A23 Motorway. Sections funded by the Cohesion Fund 2000-06
Source: Openstreetmap.org
The A23 motorway in Spain (also called Autovía Mudéjar) is a high capacity road
connecting Sagunto, on the Mediterranean coast just north of Valencia, and the
Somport road tunnel. The tunnel connects Spain and France through the central
Pyrenees. It was opened in 2003. Although the A23 is not part of any TEN-T
corridor, it belongs to the European route E07 connecting Pau in France to
Zaragoza in Spain. Currently, the A23 motorway is completed between Sagunto
and Nueno. The remaining sections between Nueno and the Somport tunnel are
either under construction or in advanced planning stages. At this point, it is
Teruel
Huesca
Nueno
Monreal del Campo
Santa Eulalia
Calamocha
Teruel
Huesca
Nueno
Monreal del Campo
Santa Eulalia
Calamocha
Teruel
Huesca
Nueno
Monreal del Campo
Santa Eulalia
Calamocha
Teruel
Huesca
Nueno
Monreal del Campo
Santa Eulalia
Calamocha
2 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
unclear when the A23 motorway will be completed. Recent budget cuts
announced by the Spanish government in July 2010 are likely to cause delays.1
Description
The project under analysis comprises four subprojects, namely one 11.5 km-long
segment between Huesca and Nueno, and three adjacent segments between
Teruel Norte and Calamocha, for a total of 63.5 km. The two sections are 178
km apart. Table 1 summarises the subprojects considered in this evaluation,
indicating also their completion date and total cost (including the share provided
by the Cohesion Fund).
All four segments are located in Aragon, in north-east Spain, bordering with
France to the north, in the Pyrenees. The capital city of Aragón is Zaragoza, the
fifth largest Spanish city. Aragón has three provinces: Zaragoza, Huesca and
Teruel. The A23 sections considered in this analysis are located in the provinces
of Huesca and Terual. Both provinces cover a total extension of 30,000 km2
(about the size of Belgium) and have a total population of 370,000 people.
Table 1. Subprojects making up the project
Subprojects (province)
- code
Completion
date
Description of the
subproject
Cost
(% CF)
Huesca to Nueno (Huesca) -
1999ES16CPT002 December 2000
11.5 Km motorway including
a viaduct of 70 metres long
23 € million
(85%)
Monreal del Campo to
Calamocha (Teruel) -
1999ES16CPT003
July 2001 14.8 Km motorway 34 € million
(85%)
Santa Eulalia del Campo to
Monreal del Campo (Teruel) -
1999ES16CPT004
July 2001 21.9 Km motorway 78 € million
(85%)
Teruel (N) to Santa Eulalia del
Campo (Teruel) -
2003ES16CPT029
December 2005
26.8 Km motorway, with two
viaducts of 100 and 231
metres long
70 € million
(85%)
Source: Application forms
In the three subprojects with code 1999ES16CPT002, -003, -004, works started
between 1998 and 1999 and finished between the end of 2000 and mid 2001. In
the fourth subproject, 2003ES16CPT029, works started in 2002 and finished at
the end of 2005.
1 http://www.fomento.es/NR/rdonlyres/BD8EBB62-047D-42C2-8639-
8C79651C83BE/76288/Impactoajustepresupuestario.pdf
March 2011 | Frontier Economics, Atkins, ITS 3
Appendix 4 – A23 Motorway in Spain
4.1.2 Context
Socio-economic context
The project was developed during a period of high and sustained economic
growth in Spain. While we focus the description of the socio-economic context
on the provinces of Teruel and Huesca, to provide some perspective we also
refer to figures at the regional and the national for comparison. Regional and
national figures are useful because they also account for the impact of other
infrastructure projects being developed at the same time as the A23. For
example, the high-speed rail line between Madrid and Barcelona arrived to
Zaragoza at about the same time this project was completed.2
Figure 2 and Figure 3 show time series of GDP per capita and unemployment
in the provinces of Teruel and Huesca, in Aragón and in Spain. The charts show
the period of sustained growth that lasted until 2007. Figure 3 also shows the
effects of the economic crisis on unemployment from 2008 onwards. The
evolution of both series is similar in all the areas considered, although the levels
of unemployment in Aragon, and Teruel and Huesca, are lower that those for
Spain.
Figure 2. GDP - Evolution of GDP per capita.
Source: Instituto Nacional de Estadística (INE)
2 The some sections of the AVE Madrid – Barcelona that received Cohesion Funds during the period 2000-
2006 are also subject in the current exercise.
0
5,000
10,000
15,000
20,000
25,000
1996 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007
GD
P p
er
cap
ita
(E
UR
)
Huesca (province)
Teruel (province)
Aragon (region)
SPAIN
4 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
Figure 3. Unemployment - Evolution of unemployment rate.
Source: Encuesta de Población Activa (EPA) available at the Instituto Nacional de Estadística (INE)
Figure 4 shows the population growth in all four areas considered, before and
after the opening of three segments of the A23 under analysis. In the first period,
before the first three segments opened, the population in the provinces of
Huesca and Teruel was growing at much lower rates than in the rest of Spain
(Teruel even showed a negative rate). In the second period, both provinces
showed higher population growth rates, similar to those recorded for Spain as a
whole.
0%
5%
10%
15%
20%
25%
1996
TI
1996
TIII
1997
TI
1997
TIII
1998
TI
1998
TIII
1999
TI
1999
TIII
2000
TI
2000
TIII
2001
TI
2001
TIII
2002
TI
2002
TIII
2003
TI
2003
TIII
2004
TI
2004
TIII
2005
TI
2005
TIII
2006
TI
2006
TIII
2007
TI
2007
TIII
2008
TI
2008
TIII
2009
TI
2009
TIII
2010
TI
Un
em
plo
ye
me
nt
rate
Huesca (province)
Teruel (province)
Aragon (region)
SPAIN
March 2011 | Frontier Economics, Atkins, ITS 5
Appendix 4 – A23 Motorway in Spain
Figure 4. Population growth rate. Average of annual growth rates in period
Source: Instituto Nacional de Estadística
It is not possible to establish a causal link between the construction of four
sections on the A23 and the changes in population growth. Nonetheless, the new
motorway might have help to bring these peripheral areas closes to larger centres.
This probably turned them into more feasible locations to reside and work.
Strategic policy context
The A23 was one of the fifteen motorways identified by the National
Infrastructure Plan 1993-2007.3 This Plan was later updated into the
Infraestructure Plan 2000-2007.4
The main objective of the A23 was to transform the existing road axis Valencia-
Zaragoza-Somport (French border) into a motorway. This would facilitate the
freight traffic between the Levante (Eastern Spain) and Aragón, in Spain, as well
as France and the rest of Europe. The new was designed to become the natural
route through the central Pyrenees, replacing the existing wide road connections
between Spain and France in both extremes of the Pyrenees, Irun-Hendaya to
the West and La Jonquera to the East.
Additional strategic objectives have been identified in the Funding Applications
for each of the four subprojects.
3 Ministerio de Obras Públicas, Transportes y Medio Ambiente, “Plan Director de Infraestructuras 1994-
2007”, approved in 1994.
4 Ministerio de Fomento, “Plan de Infraestructuras 20000-2007”.
-0.25%
0.00%
0.25%
0.50%
0.75%
1.00%
1.25%
1.50%
1999-2001 2002-2008
Po
pu
lati
on
gro
wth
ra
te (
an
nu
al
av
era
ge
s i
n p
eri
od
)Teruel (province) Huesca (province)
Aragon (region) SPAIN
6 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
To complete the national motorway network as envisaged in the
Infrastructure Plan in the early 1990s. The A23 was identified as the
fifteenth and last corridor in the Spanish government’s analysis on missing
links in the Spanish motorway network.
To improve the communications with non-coastal areas of Spain, which
were located far from existing main road corridors. Before the project, the
links between Huesca and Teruel and the rest of Spain were slow and
congested, despite their central location.
To achieve significant time savings in a slow roads. In the four segments
under study average speeds were expected to increase.
To decrease the number of accidents and improve overall safety conditions
in the corridor.
The previous Cohesion Fund contributions (1994-1999) had already financed
some sections of the A23 motorway, namely Zaragoza to Huesca and Gilet to
Soneja, and the Somport tunnel.5
4.1.3 Sources
We have relied on a variety of different sources of information provided by DG
REGIO and by stakeholders in Spain. DG REGIO made available the Funding
Applications and Funding Decisions for each of the four subprojects. Each
application provided a detailed description of each subproject, its objectives and
the costs and benefits that it was expected to generate. DG REGIO also
provided additional supporting documentation, such as the initial overall cost-
benefit analysis and final reports for each of the four subprojects. In addition, the
Unidad de Carreteras de Teruel (part of the Dirección General de Carreteras, a
directorate within Ministerio de Fomento) have provided the initial study done
by the Spanish authorities regarding the segment Teruel – Zaragoza of the A23,
which contains three of the four projects under study.6
Table 2 provides the complete list of documents we have used for this
evaluation.
5 http://www.sifemurcia-
europa.com/2002/fondos/pdfs/programa_operativo_fondo_cohesion_feder_2007_2013.pdf
6 Ministerio de Obras Públicas, Transportes y Medio Ambiente, “Estudio Informativo de la Autovía Levante
Aragón, Tramo Teruel – Zaragoza”, Estudio de Rentabilidad, 28 Febrero 1994.
March 2011 | Frontier Economics, Atkins, ITS 7
Appendix 4 – A23 Motorway in Spain
Table 2. Summary of project-related documentation
Documents Obtained from
Funding Applications
All subprojects DG REGIO
Funding Decisions
All subprojects DG REGIO
Ex ante CBA (one for each subproject) DG REGIO
Estudio Informativo,
for the three subprojects in Teruel, segment Teruel - Zaragoza (February 1994)
for the subproject in Huesca, Villanueva de Gállego -Nueno (1992)
Ministerio de Fomento (Teruel, Zaragoza and
Huesca Units)
Methodology used in the economic analysis of the projects, “Recomendaciones para la Evaluación Económica de Estudios y Proyectos de Carreteras”, 1992.
Ministerio de Fomento
Studies on traffic in the A23 around Teruel Ministerio de Fomento
(Teruel, Unit)
Study on socio-economic effects caused by the motorway Somport – Sagunto, CREA, 1992
Government of Aragon
In order for us to carry out the ex post analysis of the project, the Dirección
General de Carreteras from the Ministerio de Fomento made available
significant amounts of data, including outturn costs (both investment and
maintenance), traffic data and journey times for each of the subprojects. We were
also provide with data on accidents and updated values for other parameters.
Table 3 lists the data we have received along with the source.
Table 3. Summary of Primary & Secondary Data Availability
Data Source
Traffic data
Ministerio de Fomento – Demarcacion de Carreteras de Aragón.
Website of MInisterio de Fomento
Infrastructure investment costs Ministerio de Fomento – Demarcacion de Carreteras de Aragón
Infrastructure maintenance costs Ministerio de Fomento
Value of time Ministerio de Fomento
Fuel costs and vehicle operating costs Ministerio de Fomento
Finally, we held meetings with members of the Demarcación de Carreteras del
Estado en Aragón (Ministerio de Fomento), one in Teruel regarding the three
8 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
subprojects of the A23 in Teruel and one in Zaragoza regarding the subproject in
Huesca. In both meetings we discussed the following key issues.
Our understanding of the calculations and assumptions underpinning the ex
ante CBA, and of the usefulness of the CBA and other analysis carried out in
the decision-making process leading to the approval of the project.
Our understanding of the post-opening data and the expected future
developments of such figures, such as traffic volumes.
The wider impacts that could be attributed to the A23, especially in the areas
surrounding the subprojects considered in this analysis.
Throughout the study, we have been in close contact with the Dirección General
de Carreteras (Ministerio de Fomento) in order to obtain supplementary
documents and updated parameter values to carry out our ex post CBA.. We
have also been in contact with the Regional Government of Aragón (various
departments) and the provincial administration in Teruel (Diputación de Teruel)
to better understand the impact of this infrastructure in the territory.
We understand that the Ministerio de Fomento is a stakeholder at national level.
Despite this, our experience and the dialogue established with its regional units
have proven successful to both to understand the technical aspects of the project
and also to identify its wider impacts.
4.1.4 Overall issue and challenges with the evaluation.
The project under study comprises four subprojects covering two non-adjacent
segments of the new A23. Individual ex ante CBAs exist for each of the four
subprojects. The first available profitability analyses of these segments were
included in two separate Estudios Informativos, one covering the segment
Teruel-Zaragoza and the other Villanueva de Gállego-Nueno. The latest ex ante
CBAs were prepared together with the applications for funding of each
subproject.
In addition to presenting the results of the ex ante CBA for each project
separately, we have also calculated aggregate economic indicators covering the
four subprojects. In the ex post CBA, we have calculated the costs and benefits
corresponding to each subproject and again we present them both separately and
as an aggregate.
4.2 Ex post cost-benefit analysis
We have carried an ex post CBA for each of the four funded in the period 2000-
2006. Traffic data differ for each segment, both in terms of volumes and timing
(the segments opened in different years). The ex post analysis compares the net
March 2011 | Frontier Economics, Atkins, ITS 9
Appendix 4 – A23 Motorway in Spain
benefits of the implemented subprojects with the counterfactual situation in
which only the old road exists.
While we have calculated the net economic benefits for each subproject, we
present the aggregate results for the project as a whole, using a common discount
rate and the same base year. For each subproject we consider, as in the ex ante
analysis, a 31-year lifetime, over which the net benefits are calculated from the
opening of the segment to traffic.
4.2.1 Headline results from the analysis:
This section contains the key results of the economic and financial analysis.
These results can be later compared with those obtained in the ex ante analysis.
Economic analysis
To carry out the ex post CBA for each of the four subprojects we have
considered a Low Case and a High Case. These scenarios use different
assumptions regarding the traffic growth on the four segments after 2008. The
High Case (optimistic scenario) assumes a constant traffic growth rate, equal to
the average of the long-run traffic growth on the four segments. This is about
5% per year. The Low Case (pessimistic scenario) assumes a constant 2.5%
traffic growth rate after 2008.
We have calculated single economic indicators (NPV, IRR and BCR) covering all
the four subprojects under study, using a 5.5% discount rate. To be consistent
with the ex ante analysis, we have used 1998 as the base year. Table 4
summarises the results of the ex post analysis under both scenarios. We note that
in the Low Case, the NPV of the project is negative.
Table 4. Summary of ex post economic analysis (2010 prices)
Low case High case
Net Present Value (€m) -27.7 27.6
Economic IRR (%) 4.6% 6.3%
Benefit-cost ratio 0.9 1.1
Source: Own calculation
Annexe I provides the detailed results of the cost benefit analysis for each option,
following the structure used in the 2008 EC Guide. The values in these figures
are non-discounted and are expressed in 2010 prices.
10 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
Financial analysis
The Funding Applications did not include any financial analysis for any of the
four subprojects under study. This is because the A23 is a toll free motorway and
therefore has no revenues.
Nonetheless, we have done an ex post financial analysis for the whole project,
calculating the annual cashflow. Table 5 summarises the results of the ex post
financial analysis. As the project cashflow is always negative, the IRR is non-
defined. Low Case and High Case yield the same financial NPVs. This is because
capital and maintenance costs are not traffic-related. Hence, they do not change
between scenarios. This assumption is based on the information provided by the
Ministerio de Fomento.
Table 5. Summary of ex post financial analysis (2010 prices)
Low / High case
Net Present Value – Investment (€m) -230
Financial IRR – Investment (%) Not available
Net Present Value – Capital (€m) -55
Financial IRR – Capital (%) Not available
Source: Own calculation
Annexe 1 provides the detailed results of the financial analysis.
Wider socio-economic impacts
The A23 represents a major step-change in the road network of the Aragón
region, and especially in the provinces of Teruel and Huesca. Discussing with
various stakeholders (such as regional and local authorities), we explored the
impact that the A23 has had so far on the territory.
We note that the subprojects under analysis in this evaluation are relatively minor
compared to the whole of the A23. It is therefore difficult to establish causality
links between these investments and any wider impact. Moreover, the A23 is one
of the many interventions that affected the region during the same period. For
example, the high-speed rail link between Madrid and Barcelona, reached
Zaragoza in 2005.
However, for the purpose of this evaluation, we managed to isolate the impacts
that are more specific to the segments considered.
In relation to the three subprojects located in the province of Teruel, we
obtained information about two new infrastructure projects (an industrial park
March 2011 | Frontier Economics, Atkins, ITS 11
Appendix 4 – A23 Motorway in Spain
and an airport) developed in the area since the opening of the first road
segments. In addition, two new road connections with the A23 are currently
under study or in advanced planning stages.
In relation to the subproject Huesca – Nueno, new infrastructures (an industrial
park, a technology centre, and new university buildings) have been developed
along the A23 near Huesca since the opening of the new road. We note however
that these developments are located alongside an older section of the A23 (built
in the previous funding period). Therefore, the causality link with the subproject
under analysis is more tenuous.
4.2.2 Costs
We have grouped costs into two different categories. One-off costs are the
capital investment costs incurred to build the infrastructures. On the other hand,
annual road maintenance is an ongoing cost. The same cost categories were used
in the ex ante analysis.
One-off costs
In general, actual total capital costs did not exceed the expected expenditure
(about €204m). While the subproject Huesco-Nueno was completed with lower
than expected capital costs, the subproject Teruel (N) – Santa Eulalia del Campo
generated some cost overruns. These effects almost offset each other.
Figure 5 shows the evolution of capital expenditure over time. Expenditure
peaked in 2000, when three of the four subprojects approached completion, and
then again in 2004 and 2005 for the completion of the last project.
12 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
Figure 5. Capital expenditure 1998 to 2005 (€, 2010 prices)
Source: Ministerio de Fomento
Unit cost calculation
The Ministerio de Fomento provided us with disaggregated cost information
(Level 2) regarding the subprojects Huesca (N) to Nueno and for the project
Teruel – Santa Eulalia. Table 6 provides the results of the Level 2 unit cost
calculation. Data disaggregated at Level 3 is not available.
0
10
20
30
40
50
60
70
80
1998 1999 2000 2001 2002 2003 2004 2005
EU
R (
Mil
lio
ns)
March 2011 | Frontier Economics, Atkins, ITS 13
Appendix 4 – A23 Motorway in Spain
Table 6. Summary of ex post unit costs (2010 prices)
Non-discounted NPV (@ 5.5%)
Level 1 „All-in‟ (€/km) 2.67 1.939
Level 2
Land (€m/ha) 0.233 Not available
Roadworks (€m/km) 0.621 Not available
Tunnels (€m/km) Not available Not available
Bridge (€m/km) 6.62 Not available
Source: Ministerio de Fomento
Ongoing costs
The methodology used in the ex ante analysis, which is still in use today to
evaluate new road projects in Spain, assumes that road maintenance costs in
Spain are independent of the volume of traffic. For consistency, we have
followed the same approach for the ex post analysis. In practice, while it
simplifies the analysis, this assumption is not material. Due to the actual absolute
volumes of traffic, maintenance costs are likely to be very similar under both the
Low Case and High Case scenario.
Ministerio de Fomento informed us that the annual maintenance costs of the
segments of the A23 in Teruel and the segment in Huesca are 18,036 €/km and
26,344 €/km respectively.
In addition to the ordinary maintenance costs, Ministerio de Fomento informed
us that in 2006 there some exceptional costs, just above €1m in the segment
Santa Eulália del Campo – Monreal del Campo.
4.2.3 Direct benefits
To calculate the project’s benefits, we have used the same approach
recommended by Ministerio de Fomento in its 1992 methodological document.
The same methodology was used to prepare the ex ante cost benefit analysis.
Ministerio de Fomento regularly updates the parameters it uses to estimate the
monetary value of time savings, vehicle operating costs and fuel costs. We used
the most updated available values.
Traffic volumes
Ministerio de Fomento provides, through its website, data on historic traffic for
the segments of the A23 under study and for the corresponding segments of the
old road. For the three segments between Teruel (N) and Calamocha, the old
14 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
road is the road N-234. For the segment Huesca – Nueno, the old road
corresponds to the N-330a.
We discussed about the appropriate use of this traffic data with Ministerio de
Fomento. They confirmed that the A23 motorway did not generate any induced
traffic or modal shift. We were also told that, contrary to what it had been
expected, between 2,000 to 2,500 vehicles (about 20% of total traffic) still use the
old road every day.
Using the historic data, we have calculated the average annual growth rate of
traffic in the segments covered by our study. The average growth rate of traffic
across the four segments considered was 5% between 1999 and 2008.
In order to carry out the ex post CBA for this project we have identified two
possible scenarios for traffic growth, a High Case and a Low Case. The scenarios
differ in the assumed level of traffic growth from 2010 onwards. We have
defined the two scenarios as follows:
High case: we assume that in each year after 2010 traffic on the A23
motorway grows at 5%. This is equal to the actual average annual
growth rate of traffic on the corridor of the A23 between 1999/2000
and 2008.
Low case: we assume a traffic growth rate in this case is 2.5%, equal to
half of the one assumed in the high case scenario.
Our analysis is based only on the traffic on the A23. This is because:
there has not been any new traffic (induced or modal shift) on the A23;
and,
the costs and benefits associated with the traffic that remains on the old
road are the same with or without the A23 being implemented.
Time savings
Most of the direct benefits of the project come from time savings. In the ex ante
cost-benefit analysis, the benefits related to the time savings more than
compensate the negative impact arising from the higher vehicle operating costs
and higher fuel consumption, which we address below.
Ministerio de Fomento provided us with data on average speeds on both the new
and on the old road. We have used this information to calculate the time savings
generated by the new road.
March 2011 | Frontier Economics, Atkins, ITS 15
Appendix 4 – A23 Motorway in Spain
Table 7. Time savings (minutes) generated by the new road
Subprojects Time savings (minutes)
Car and LGV HGV
Huesca to Nueno 0.6 4.7
Monreal del Campo to Calamocha 2.7 0.9
Santa Eulalia del Campo to Monreal del Campo 3.2 0.4
Teruel (N) to Santa Eulalia del Campo 6.5 3.3
Source: Frontier Economics
The Ministerio de Fomento also provided us with the parameter of the value of
time currently used in road projects in Spain. The value of time currently used in
Spain for road projects is 14.63 €/hour for cars and light-goods vehicles (LGVs)
and 25.08 €/hour for heavy-goods vehicles (HGVs). Table 8 summarises the
total value of the time spent travelling on the new road and the old road,
respectively. The difference between the two is the time saving generated by the
new road.
Table 8. Time benefits generated by the new road (2010 prices)
NPV of Cost of Time
(€m)
NPV of Time Benefits
(€m)
With new road 688.20
172.86
With old road (counterfactual) 861.06
Source: Frontier Economics
Vehicle operating costs
Vehicle operating costs are higher in the new A23 than in the old road. This is
due to the higher speeds that the A23 allows, resulting in higher fuel and oil
consumption and quicker deterioration of car components, mainly tyres, in the
new road. As the length of the two roads (old and new) is almost the same,
differences in speed translate proportionally in different VOC and fuel
consumptions. Because of the increase in VOC, the new road generates a loss
compared with the old one.
Ministerio de Fomento provided us with the parameter values for the cost of
fuel, oil and tyres currently used in road projects in Spain. These are summarised
in Table 9.
16 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
Table 9. Unit costs for fuel and tyres
Car and LGV HGV
Petrol (€/litre) 0.58
Diesel (€/litre) 0.59
Oil (€/litre) 4.21 4.71
Tyres(*)
386 5,285
Source: Frontier Economics (*)
4 tyres in cars and LGVs, 6 tyres in HGVs
Petrol and diesel consumption depends on speed. The ex ante analysis provides
value tables for petrol and diesel consumption, as a function of speed and the
characteristics of the road in the subsections under analysis. We have revised the
fuel consumption values using this information and the actual speeds provided
by Ministerio de Fomento. We have used a similar approach to quantify any
change in oil consumption. To calculate tyre consumption, we have used the
parameters provided by the ex ante analysis, which links tyre wearing to speed
and road conditions.
4.2.4 Externalities
Safety
Safety conditions on the A23 are significantly better than on the old road, for all
sections considered in this analysis.
Table 10 shows the annual average number of accidents on the new A23, with
the data for the old road, before the opening of the A23. The total number of
accidents on the A23 is less than half the number of accidents in the old road.
Fatalities have been reduced to zero, from 15 on the old road, while casualties
have fallen from around 120 in 1999 to 20 in 2009.
March 2011 | Frontier Economics, Atkins, ITS 17
Appendix 4 – A23 Motorway in Spain
Table 10. Number of fatalities and injuries
Segment Fatalities Injuries Vehicles/day Year
OLD
ROAD
Huesca to Nueno 4 38 7,773 1999
Teruel(N) to Calamocha 11 84 7,900 (average) 2000
NEW
ROAD
Huesca to Nueno 0 8 9,224 2009
Teruel(N) to Calamocha 0 12 9,450 (average) 2009
Source: Ministerio de Fomento
Note: Injuries includes severe and non-severe injuries
Ministerio de Fomento provided us with the parameter values related to the
monetary value attached to fatalities and casualties currently used in road project
appraisal in Spain.
Table 11. Monetary value for fatalities and casualties (€, 2010 prices)
Fatalities Casualty
Monetary value 258,342 34,100
Source: Ministerio de Fomento
Accident costs are calculated using the values shown in Table 11. Given the
historic information on accidents in the subsections, provided by the Ministerio
de Fomento, we have calculated the ratios for fatalities and casualties per
vehicle/day and held this ratio constant for all years in the analysis.
Environmental (noise, pollution, CO2)
The A23 has not generated any induced traffic or any modal shift. Therefore, in
the analysis we have assumed that that externalities related to changes in noise or
pollution levels, if any, are negligible and can be ignored. We understand that the
similar approach was used for the ex ante analysis.
4.2.5 Wider impacts
We have considered the wider impact of these projects in each province.
Teruel
Two new developments took place after the completion of the A23.
18 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
The first is a new logistic and industrial park, PLATEA, developed by the
Government of Aragón and managed by Platea Gestión S.A. The objective
of this park is to promote economic and social development in the southern
region of Aragón. It covers an area of around 2.5 million m2. Its location
was chosen thanks for the advantageous position of Teruel, half way
between the Mediterranean coast and the Ebro Valley.
The second is an industrial aeronautical platform, PLATA, offering space for
long-term parking, recycling and maintenance of aircrafts and other related
aeronautical sector activities. PLATA has been developed by the
Government of Aragón and the Teruel City Council. This aeronautical
platform is currently under construction (expected to be completed by late
2010) on the area of the previous Caudé aerodrome and covers an area of
around 2 million m2.
In addition to these developments, the Spanish Government is considering two
new road connections, providing links to the A23. The first and more advanced
project, from Alcolea to Monreal del Campo, is a direct link between the A2
(Madrid to Barcelona) and the A23 roads and will provide more capacity to the
Madrid-Levante corridor. The second, from Cuenca to Teruel, will allow the road
traffic on the axis South-West to North-East of Spain to avoid going through the
congested road around Madrid.
Huesca
Some developments also took place in the region following the completion of the
A23. However, we note that these are all located alongside a section of the
motorway developed prior to the one considered here. Even though we can not
relate these developments to the road segment under study, it is worth
mentioning them, given their proximity and significance. All have recently
opened in the outskirts of Huesca.
New industrial park, PLHUS. It covers an area of around 1.150.000 m2. It is
located near the city of Huesca, halfway between the Cantabrian and the
Mediterranean coastlines along the planned Pamplona - Huesca - Lleida dual
carriageway. The industrial park is located two kilometres southeast of the
city centre.
The technology park, WALQA. It is situated in the outskirts of Huesca, on
the dual carriageway Autovía Mudéjar that directly links to Madrid. It covers
an area of 529.000 m2. Since its opening in 2002 it has been devoted to bring
together technological companies. Its main objective is to become a centre
of interest to R&D innovation, especially in the fields of communications
technology, Internet and e-commerce, contributing to the economic
development of Huesca and consequently of the Aragón region.
March 2011 | Frontier Economics, Atkins, ITS 19
Appendix 4 – A23 Motorway in Spain
A business innovation centre, CEEI. The European Centre of Enterprises
and Innovation of Aragon, CEEIARAGON, is a business incubator with
the mission to support the creation of innovative industries or services that
generate wealth in Aragon. Its main objective is to help entrepren€ial
ventures to consolidate and develop during the first years of life.
In addition to these developments, two new high capacity roads are currently
under construction and will connect to the A23 motorway in Huesca. The A22
motorway will connect Huesca to Lleida. The A21 will connect Pamplona and
Huesca. These two new motorways form an East – West axis road to the south
of the Pyrennes and are a complement to the A23.
Environmental requirements
The four subprojects included in the project under study were covered by two
Estudios Informativos, Villanueva de Gállego to Nueno and Teruel – Zaragoza.
The Spanish Government approved the corresponding DIAs (Environmental
Impact Declaration) related to this two Estudios Informativos in published in the
official state gazette (BOE) on 2nd September 19927 and 26th April 19978,
respectively. Both documents established that the projects were environmentally
viable.
Utilisation rates
We have been informed by the Ministerio de Fomento (Demarcación de
Carreteras de Aragón) that the maximum capacity of the new road ranges from
7,478 vehicles/hour in the Huesca – Nueno section to 8,000 vehicles/hour for
the Teruel – Calamocha section.
We have calculated actual utilisation rates based on traffic demand data for 2008,
provided by the Ministerio de Fomento, and expected utilisation rates for 2036
based on our traffic growth assumptions. Table 12 presents the results.
7 http://www.boe.es/boe/dias/1992/09/02/pdfs/A30318-30323.pdf
8 http://www.boe.es/boe/dias/1997/04/26/pdfs/A13511-13517.pdf
20 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
Table 12. Utilisation rates
2008 2036 High case 2036 Low case
Huesca – Nueno 5.0% 19.6% 10.0%
Teruel - Calamocha 4.8% 18.8% 9.6%
Source: Frontier Economics
Other projects
Various high capacity roads are currently under construction/study and will be
linked to the A23 motorway on or close to the segments considered in this
analysis. The new A21 and A22 roads connecting Huesca to Pamplona and
Lleida are currently under construction. Two additional roads, connecting Teruel
to Cuenca and Alcolea (on the A2) to Monreal del Campo, are currently under
study. These new road infrastructures will establish additional links with the A23
motorway, enhancing its potential to achieve the stated objectives for these
projects.
Unintended effects
The ex ante cost-benefit analysis assumed that, after opening the A23, the old
road would only carry residual traffic (tráfico de agitación). In reality, the N-234 in
Teruel and the N-330 in Huesca still carry a significant volume of traffic,
currently between 2,000 and 2,500 vehicles a day.
4.2.6 Uncertainty and sensitivity analysis
The ex post analysis carried out for this project uses comprehensive historic data
on traffic until 2008. We have had make an assumption regarding the traffic
growth rate parameter when considering the two scenarios in the analysis.
Historic data and current impacts
Historic traffic data for this project is available through website of the Ministerio
de Fomento. We also received more data and guidance on how to use it during
the stakeholder meetings we had with members of the Ministerio de Fomento, in
Teruel and Zaragoza (this last regarding the segment Huesca). Apart from
receiving data we were informed that according to their analysis the A23 has not
generated new traffic, either induced or modal shift.
Forecast of impacts
In order to carry out the ex post CBA for this project we have identified two
possible scenarios, an optimistic and a pessimistic one. Both scenarios differ in
March 2011 | Frontier Economics, Atkins, ITS 21
Appendix 4 – A23 Motorway in Spain
the assumed level of traffic growth from 2010 onwards. To decide on the traffic
growth rate for each scenario, we have taken into account the actual traffic
growth rate in each segment since opening.
High case: we assume that in each year after 2010 traffic on the A23
motorway grows at 5%. This is equal to the actual average annual
growth rate of traffic on the corridor of the A23 between 1999/2000
and 2008.
Low case: we assume a traffic growth rate in this case is 2.5%, equal to
half of the one assumed in the high case scenario.
We note that we have not considered the possible network effects that the
construction of the Somport tunnel will have on the whole traffic demand,
especially for the Huesca – Nueno segment. This is because the tunnel is not
expected to be finalised in the near future.
4.3 Review ex ante cost-benefit analysis
The first assessments of the four subprojects included in this project were carried
out in 19929 and 1994.10 These were part of public information procedures
(Estudio Informativo) covering large segments of the A23 (Villanueva de Gállego –
Nueno and Teruel – Zaragoza). These assessments included a profitability
analysis for each of the subprojects under analysis. They also considered costs
and benefits of different alternatives for each subproject. Later, in 1999 and
2003, and before the submission of the application for subsidies were submitted
for each subproject, the Ministerio de Fomento prepared an ex ante CBA of the
main implementation option for each subproject. We have focused the review of
the ex ante CBA on these analyses. For all four of them, the methodology used
is the one recommended by the Spanish Public Works Ministry in 1992.11
Given that a unique ex ante CBA covering all four subprojects does not exist, we
present the results of the four individual ex ante CBA carried out at the time.
Note that the four ex ante CBA do not use the same base year and discount rates
to calculate the net present value and IRR indicators. We start reporting the
figures included in the original submissions and then present the same indicators
using a common base year and discount rate.
9 Ministerio de Obras Públicas, Transportes y Medio Ambiente, “Estudio Informativo de la Autovía
Levante Aragón, Tramo Villanueva de Gállego - Nueno”, Estudio de Rentabilidad, 1992.
10 Ministerio de Obras Públicas, Transportes y Medio Ambiente, “Estudio Informativo de la Autovía
Levante Aragón, Tramo Teruel – Zaragoza”, Estudio de Rentabilidad, 28 Febrero 1994.
11 Ministerio de Obras Públicas y Transportes – Dirección General de Carreteras, “Recomendaciones
para la Evaluación Económica de Estudios y Proyectos de Carreteras”, 1992.
22 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
4.3.1 Headline results from the analysis
Economic analysis
The ex ante CBAs prepared by Ministerio de Fomento, and used to prepare the
four applications for funding, considered just the option implemented. They
assessed it against the counterfactual of the old road being maintained. In all
four subprojects, the economic costs and benefits were calculated over a period
of 34 years. In the three 1999 submissions the net economic benefits were
calculated using a 6% discount rate. The only difference between these three
CBAs was the starting year in which the net benefits were calculated. In the
Huesca-Nueno subproject the base year was 1998, while in the other two
subprojects, in the Teruel province, the costs and benefits were discounted to
1999. In the 2003 submission, Teruel (N) to Santa Eulalia del Campo, the net
economic benefits were calculated using 2002 as a base year and a 5% discount
rate.
Table 13 shows the economic indicators for each of the four subprojects
included in the analysis, together with the underlying assumptions regarding the
base year and discount rate used in the calculations. In all four cases the
economic costs and benefits have been calculated over a period of 34 years,
assuming 3 years of constructions and 31 years of operations thereafter.
The subproject Teruel(N) to Santa Eulalia del Campo should significantly larger
economic benefits than the other the projects. We have not been able to pin
down the specific causes for this, although we believe that the reported NPV
does not include a significant amount of the initial capital costs.
Table 13. Results of ex ante cost benefit analysis
Subproject Discount
rate
Base
year
Net Present Value
(€ million)
Economic
IRR (%)
BCR
Huesca to Nueno 6% 1998 2.60 7.05 1.12
Monreal del Campo to
Calamocha 6% 1999 15.98 9.45 1.51
Santa Eulalia del Campo to
Monreal del Campo 6% 1999 1.57 6.15 1.02
Teruel(N) to Santa Eulalia
del Campo 5% 2002 90.80 16.65 2.93
Source: Ministerio de Fomento
We have re-calculated these economic indicators using common assumptions
regarding the base year and the discount rate. By doing so, we have been able to
calculate a unique NPV, IRR and BCR covering all four subprojects under study.
March 2011 | Frontier Economics, Atkins, ITS 23
Appendix 4 – A23 Motorway in Spain
We have assumed a discount rate equal to 5.5% (as used in the ex post CBA) and
used 1998 as base year. Overall, the whole project has a positive NPV and
satisfactory IRR and benefit-cost ratio.
Table 14. Results of ex ante cost benefit analysis – Revision
Net Present Value
(€ million, 1998 prices)
Economic IRR
(%)
BCR
Whole project 86.54 9.14 1.56
Source: Frontier Economics using data from Ministerio de Fomento
Financial analysis
The A23 motorway is a toll free road. The applications for funding submitted in
1999 and 2003 do not include any financial analysis for any of the subprojects
under study.
4.3.2 Key aspects of ex ante CBA
Demand analysis
The ex ante cost-benefit analysis assumed that the new segments in the A23 were
not going to generate any induced traffic. On the other hand, the assumed traffic
growth during the period under study ranged between 0.88%, for the last 25
years in the Teruel – Santa Eulalia del Campo subproject (with assumed 1.9% in
the first 5 years), and 3%, for the whole period in the 2 subprojects covering
Santa Eulalia del Campo to Calamocha. In the subproject Huesca to Nueno a
4% traffic growth was assumed throughout the considered period. Growth
assumptions are based on historical information for the 1987-1996 period. In
terms of percentages of heavy goods vehicles the ex ante analysis considered a
minimum of 12 in the Huesca to Nueno subproject, and 27 in the 2 subprojects
covering Santa Eulalia del Campo to Calamocha.
Direct benefits
One of the objectives of the A23, listed in the various applications for funding,
was to achieve significant time savings, thanks to the increase in speeds and the
lower traffic congestion in the new road compared to the old one. In the four
segments under study the speeds were expected to increase, from 63-90 Km/h to
120 Km/h for cars and light good vehicles, and from 51-73 Km/h to 90-97
Km/h for heavy good vehicles.
24 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
Table 15. Time savings (minutes) generated by the new road
Subprojects Time savings (minutes)
Car and LGV HGV
Huesca to Nueno 4.4 5.4
Monreal del Campo to Calamocha 5.9 7.3
Santa Eulalia del Campo to Monreal del Campo 9.7 11.8
Teruel Norte to Santa Eulalia del Campo 7.1 8.7
Source: Ministerio de Fomento
In all the four subproject-specific ex ante CBAs time savings appear to be the
main driver of economic benefits. For all four subprojects the benefits related to
the time savings more than compensate the costs arising from the increase in
vehicle operating costs and fuel consumption. VOC and fuel consumption are
higher in the new road due to higher speeds.
According to the ex ante analysis, operating costs and fuel consumption were
expected to increase, on average for the four subprojects, by 15% for cars and
LGV and by 26% for HGV, with the new road. On the contrary, costs related to
time consumption were expected to decrease by 39% for cars and LGV and 38%
for HGV.
In addition to the time savings, vehicle operating costs and fuel consumption, the
other relevant element included in the calculation of costs and benefits are the
benefits related to the accidents occurring in the road. In all four subprojects the
net benefits related to the reduction of accidents are always positive and
significant. Specifically, the average reduction of unitary costs related to accidents
for the four subprojects is 43% for cars and LGV and 46% for HGV.
Sensitivity analysis
A sensitivity analysis was carried out in each of the four ex ante CBAs. In all
cases two scenarios were tested, regarding the assumed traffic growth and the
value of time. Scenario 1 assumes a lower traffic growth rate in each of the four
subprojects. In Scenario 2, the value of time for cars and LGVs was reduced in
order to induce a 20% reduction in the series of net benefits.
March 2011 | Frontier Economics, Atkins, ITS 25
Appendix 4 – A23 Motorway in Spain
Table 16 shows the economic IRR indicators obtained in the sensitivity analysis
for each of the four subprojects.12 The sensitivity analysis shows a negative NPV
for the subproject Monreal del Campo to Calamocha under both alternative
hypothesis. Also, the subproject Huesca to Nueno shows a negative NPV when
a lower value of time is considered. In all other cases the sensitivity analysis does
not change the sign of the economic indicators. In addition to these two
hypothesis, an additional hypothesis assuming a higher traffic growth was
considered for the subproject Teruel(N) to Santa Eulalia del Campo, resulting in
a 24.75% economic IRR.
Table 16. Results of the sensitivity analysis
Subprojects
Economic IRR Discount
rate Original Scenario 1 Scenario 2
Huesca to Nueno 7.1% 6.4% 3.6% 6%
Monreal del Campo to
Calamocha 9.5% 8.5% 7.2% 6%
Santa Eulalia del Campo to
Monreal del Campo 6.2% 5.3% 4.2% 6%
Teruel Norte to Santa Eulalia
del Campo 16.7% 15.6% 14.0% 5%
Source: Ministerio de Fomento
4.3.3 Quality of ex ante CBA
Overall, the quality of the ex ante Cost Benefit Analysis of the four subprojects is
high. We have found that all of them follow a well established methodology
proposed by the Ministerio de Fomento. Another positive aspect of the ex ante
CBAs is that it is clearly stated the parameters used (i.e. unit costs, unit
consumptions, value of time, etc.) and their source.
As mentioned above, ex ante CBAs also included sensitivity analysis. Two
alternative scenarios were included regarding the assumed traffic growth and the
value of time.
12 The sign of the other indicators can be easily deducted from this. An IRR higher than the discount
rate results in a positive NPV and a BCR above one. An IRR lower than the discount rate results in
a negative NPV and a BCR below one.
26 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
On the other hand, the main drawback of the ex ante CBAs of the four
subprojects is related to the quality of the demand forecast. Based on the
documentation we have reviewed, the methodology used to estimated future
demand is unclear. Also, the assumption that the new infrastructure would not
generate induced traffic is questionable.
Finally, it should be mentioned that ex ante CBAs consider as counterfactual that
the old road would be closed, but actually it was maintained opened and it
currently a significant volume of traffic.
4.4 Differences between ex post and ex ante analysis
Table 17 compares the aggregate results of the ex ante economic analysis with
the results of the ex post CBA for all the four subprojects included in this study,
segments Teruel (N) to Calamocha and Huesca to Nueno.
Table 17. Comparison ex ante and ex post economic CBA (2010 prices)
Ex ante Ex post
Low case High case
Net Present Value (€m) 120.3 -27.7 27.6
Economic IRR (%) 9.14 4.6 6.3
Benefit-cost ratio 1.56 0.9 1.1
Source: Own elaboration with data from the Ministerio de Fomento
As mentioned in section 4.3.1, the ex ante economic indicators for the whole
project have been calculated using the series of net economic benefits
corresponding to the four subprojects. We have recalculated these series using a
common base year, 2010, and the discount factor suggested by the EC Guide to
Cost-Benefits Analysis (5.5%). The original ex ante economic analysis used
either 1998 or 2002 as the base year and a discount factor equal to 5% or 6%.
The economic IRR resulting from the ex ante analysis is 9.14%. This result is
above the range of the ex post CBA carried out in this exercise. However, the
high case scenario in the ex post analysis confirms that the economic benefits of
the project exceed its costs. We note the high case scenario assumes a long-run
growth rate of traffic equal to the growth observed in the corridor since the
completion of the first segments.
There main differences between the two analyses stem from the following areas:
parameters for the value of time and cost of fuel
March 2011 | Frontier Economics, Atkins, ITS 27
Appendix 4 – A23 Motorway in Spain
time savings
volume of traffic and percentage of HGV
safety conditions
Value of fuel and time
In both the ex ante and the ex post analyses, the higher driving speeds achieved
on the new road generate two opposite effects in terms of induced benefits. On
the one hand, higher speeds result in time savings that generate positive
economic benefits. On the other hand, these speeds cause high fuel
consumption and higher vehicle operating costs which result in negative
economic benefits.
Net economic benefits from time savings use parameters for the value of time
for cars, LGV and HGV that Ministerio de Fomento keeps regularly updated.
Ministerio de Fomento also updates regularly the parameters for the cost of fuel
parameters and vehicle operating costs.
Table 18. Parameters for value of time, fuel costs and VOC
Ex ante Ex post
Value of time (€/hour)
Car and LGV 9.3 14.63
HGV 16 25.08
Fuel and VOC
Petrol (€/litre) 0.28 0.58
Diesel (€/litre) 0.25 0.59
Oil (€/litre) 3.06 (3.42) 4.21 (4.71)
Tyres(*)
281 (3,845) 386 (5,285)
Source: Ministerio de Fomento (*)
4 tyres in cars and LGVs, 6 tyres in HGVs
Table 18 shows that fuel cost parameters have increase by more than 100% since
the ex ante analysis was carried out. In contrast, the value of time has increased
by approximately 50%. Time savings and fuel costs are the main drivers of the
net economic benefits induced by the project. The significant decrease of the
economic indicators in the ex post analysis is mainly the result of the change in
relative values of these two parameter sets.
28 Frontier Economics, Atkins, ITS | March 2011
Appendix 4 – A23 Motorway in Spain
Time savings
The ex ante analysis forecast a total amount of time savings along the four
segments considered equal to 27 and 33 minutes for cars/LGVs and HGVs
respectively. In the ex post analysis, and according to the speed data obtained
from the Ministerio de Fomento, actual time savings achieved through the four
segments are 13 and 9.3 minutes, significantly lower that what was originally
assumed.
Traffic volumes
The ex ante analysis forecast that traffic growth on the new A23 would be
around 3% annually. Historic traffic data shows that the long-run annual growth
rate of traffic has been around 5%. This 5% has been used as the traffic growth
rate after 2010 in the optimistic scenario of the ex post analysis.
Safety conditions
Information provided by the Ministerio de Fomento used in the ex post CBA
suggests that safety condition were undervalued in the ex ante analysis. The
average reduction of fatalities and injuries per km in the ex ante analysis was 53%
and 13% respectively. Ex post information considers an average reduction of
100% and 83% respectively.
4.5 Role of CBA in decision-making process
We have talked with Ministerio de Fomento - Unidad de Carreteras de la
Demarcación de Aragón regarding the role of CBA in the decision making
process. We have received confirmation that the decision to construct the A23
was mainly political. Despite this, the decision among different alternatives
regarding the exact configuration of the road was based on two economic
analyses undertaken by the Demarcación de Carreteras del Estado en Aragón.
For the three subprojects in the province of Teruel, they were included in a study
covering the segment “Teruel - Zaragoza”.13 The Huesca to Nueno was included
in a study covering the segment “Villanueva de Gállego – Nueno”.14
The methodology used in both economic analyses followed the
recommendations to evaluate road projects in Spain published by Ministerio de
Obras Publicas y Transportes at the time. The study covering the segment
“Teruel - Zaragoza” followed the methodology still used today and published in
13 Ministerio de Obras Públicas, Transportes y Medio Ambiente, “Estudio Informativo de la Autovía
Levante Aragón, Tramo Teruel – Zaragoza”, Estudio de Rentabilidad, 28 Febrero 1994.
14 Ministerio de Obras Públicas, Transportes y Medio Ambiente, “Estudio Informativo de la Autovía
Levante Aragón, Tramo Villanueva de Gállego - Nueno”, Estudio de Rentabilidad, 1992.
March 2011 | Frontier Economics, Atkins, ITS 29
Appendix 4 – A23 Motorway in Spain
1992.15 The study covering the segment “Villanueva de Gállego – Nueno” used
a previous methodology of 1990.
In both cases the methodology recommended by Ministerio de Fomento
proposes the use of a multi-criteria analysis to choose among different
alternatives for each of the sub-segments in which the overall project has been
previously determined. In the analysis reviewed the option to use the current
road is included among the alternatives considered.
Even though the decision to construct the A23 motorway was mainly political,
the choice of alternatives regarding the configuration of the new road appears to
have been based on a sound economic analysis.
15 Ministerio de Obras Públicas y Transportes – Dirección General de Carreteras, “Recomendaciones
para la Evaluación Económica de Estudios y Proyectos de Carreteras”, 1992.
March 2011 | Frontier Economics, Atkins, ITS 31
Annexe 1: Detailed results
Annexe 1: Detailed results
A23 Motorway in Spain
Figure 6. A23 Motorway – Spain. Economic analysis (€m, 2010 prices) – Low case
Source: Own calculations
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
BENEFITS
Consumers Surplus
Time Benefits 0.0 0.0 0.0 1.8 3.2 3.2 3.4 3.4 8.0 9.0 10.1 10.4 10.6
Vehicle Operating Costs 0.0 0.0 0.0 -1.3 -2.5 -2.7 -2.8 -2.8 -3.1 -3.4 -4.0 -4.1 -4.2
Environmental Benefits 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Accident Reduction 0.0 0.0 0.0 2.8 4.2 4.3 4.7 4.6 7.0 7.9 8.7 8.9 9.1
TOTAL BENEFITS 0.0 0.0 0.0 3.3 4.8 4.9 5.3 5.2 12.0 13.5 14.8 15.1 15.5
COSTS
Investment Costs
Land Purchase / Construction / …
Other
Total Investment costs 2.2 34.0 74.3 46.0 13.7 22.0 27.8 27.0 0.0 0.0
Maintanance Costs 0.0 0.0 0.0 0.6 1.0 1.0 1.0 1.0 2.6 1.5 1.5 1.5 1.5
TOTAL COSTS 2.2 34.0 74.3 46.6 14.7 22.9 28.8 28.0 2.6 1.5 1.5 1.5 1.5
NET BENEFITS -2.2 -34.0 -74.3 -43.3 -9.9 -18.1 -23.5 -22.9 9.4 12.0 13.3 13.7 14.0
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
BENEFITS
Consumers Surplus
Time Benefits 10.9 11.2 11.5 11.8 12.0 12.3 12.7 13.0 13.3 13.6 14.0 14.3 14.7
Vehicle Operating Costs -4.3 -4.4 -4.6 -4.7 -4.8 -4.9 -5.0 -5.2 -5.3 -5.4 -5.6 -5.7 -5.8
Environmental Benefits 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Accident Reduction 9.3 9.6 9.8 10.0 10.3 10.5 10.8 11.1 11.4 11.6 11.9 12.2 12.5
TOTAL BENEFITS 15.9 16.3 16.7 17.1 17.5 18.0 18.4 18.9 19.4 19.9 20.4 20.9 21.4
COSTS
Investment Costs
Land Purchase / Construction / …
Other
Total Investment costs
Maintanance Costs 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5
TOTAL COSTS 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5
NET BENEFITS 14.4 14.8 15.2 15.7 16.1 16.5 17.0 17.4 17.9 18.4 18.9 19.4 19.9
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
BENEFITS
Consumers Surplus
Time Benefits 15.0 15.4 15.8 16.2 16.6 17.0 17.4 17.9 16.7 9.9 10.1 10.4 10.6
Vehicle Operating Costs -6.0 -6.1 -6.3 -6.4 -6.6 -6.8 -6.9 -7.1 -6.4 0.3 0.3 0.3 0.3
Environmental Benefits 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Accident Reduction 12.9 13.2 13.5 13.8 14.2 14.5 14.9 15.3 11.3 4.4 4.5 4.6 4.8
TOTAL BENEFITS 21.9 22.5 23.0 23.6 24.2 24.8 25.4 26.1 21.5 14.5 14.9 15.3 15.6
COSTS
Investment Costs
Land Purchase / Construction / …
Other
Total Investment costs
Maintanance Costs 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.2 0.5 0.5 0.5 0.5
TOTAL COSTS 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.2 0.5 0.5 0.5 0.5
NET BENEFITS 20.4 21.0 21.6 22.1 22.7 23.3 23.9 24.6 20.4 14.0 14.4 14.8 15.1
Discount Rate 5.5%
ENPV -27.7
ERR 4.6%
B/C Ratio 0.9
No breakdown figures available
No breakdown figures available
No breakdown figures available
32 Frontier Economics, Atkins, ITS | March 2011
Annexe 1: Detailed results
Figure 7. A23 Motorway – Spain. Financial return on investment (€m, 2010 prices) –
Low case
Source: Own calculations
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENT COSTS 2,2 34,0 74,3 46,0 13,7 22,0 27,8 27,0 0,0 0,0 0,0 0,0 0,0
Maintenance 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
TOTAL OPERATING COSTS 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
TOTAL OUTFLOWS 2,2 34,0 74,3 46,6 14,7 22,9 28,8 28,0 2,6 1,5 1,5 1,5 1,5
CASH FLOW -2,2 -34,0 -74,3 -46,6 -14,7 -22,9 -28,8 -28,0 -2,6 -1,5 -1,5 -1,5 -1,5
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENT COSTS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
TOTAL OPERATING COSTS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
TOTAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENT COSTS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
TOTAL OPERATING COSTS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
TOTAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,2 -0,5 -0,5 -0,5 -0,5
Discount rate 5,0%
FNPV (C) -230
FRR (C) #DIV/0!
No breakdown figures available
No breakdown figures available
No breakdown figures available
March 2011 | Frontier Economics, Atkins, ITS 33
Annexe 1: Detailed results
Figure 8. A23 Motorway – Spain. Financial return on capital (€m, 2010 prices) – Low
case
Source: Own calculations
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
Revenues
Residual values
TOTAL FINANCIAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Local contribution
Regional contrintribution
National contribution 0.3 5.2 10.7 7.1 2.2 4.9 6.1 6.0
Total national public contribution 0.3 5.2 10.7 7.1 2.2 4.9 6.1 6.0 0.0 0.0 0.0 0.0 0.0
Maintenance 0.0 0.0 0.0 0.6 1.0 1.0 1.0 1.0 2.6 1.5 1.5 1.5 1.5
Total Operating Costs 0.0 0.0 0.0 0.6 1.0 1.0 1.0 1.0 2.6 1.5 1.5 1.5 1.5
TOTAL FINANCIAL OUTFLOWS 0.3 5.2 10.7 7.7 3.2 5.8 7.1 7.0 2.6 1.5 1.5 1.5 1.5
NET CASH FLOW -0.3 -5.2 -10.7 -7.7 -3.2 -5.8 -7.1 -7.0 -2.6 -1.5 -1.5 -1.5 -1.5
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
Revenues
Residual values
TOTAL FINANCIAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Local contribution
Regional contrintribution
National contribution
Total national public contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Maintenance 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5
Total Operating Costs 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5
TOTAL FINANCIAL OUTFLOWS 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5
NET CASH FLOW -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.5
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
Revenues
Residual values
TOTAL FINANCIAL INFLOWS 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Local contribution
Regional contrintribution
National contribution
Total national public contribution 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Maintenance 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.2 0.5 0.5 0.5 0.5
Total Operating Costs 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.2 0.5 0.5 0.5 0.5
TOTAL FINANCIAL OUTFLOWS 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.2 0.5 0.5 0.5 0.5
NET CASH FLOW -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.5 -1.2 -0.5 -0.5 -0.5 -0.5
Discount rate 5.0%
FNPV (K) -55
FRR (K) N/A
34 Frontier Economics, Atkins, ITS | March 2011
Annexe 1: Detailed results
Figure 9. A23 Motorway – Spain. Financial sustainability (€m, 2010 prices) – Low
case
Source: Own calculations
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
EU Grant 1,9 28,8 63,6 38,9 11,5 17,1 21,6 21,1
Local contribution
Regional contrintribution
National contribution 0,3 5,2 10,7 7,1
Total national public contribution 0,3 5,2 10,7 7,1 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Operating subsidies
FINANCIAL RESOURCES 2,2 34,0 74,3 46,0 11,5 17,1 21,6 21,1 0,0 0,0 0,0 0,0 0,0
Passenger vehicles
Goods vehicles
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
TOTAL INFLOWS 2,2 34,0 74,3 46,0 11,5 17,1 21,6 21,1 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENTS COSTS 2,2 34,0 74,3 46,0 13,7 22,0 27,8 27,0
Maintenance 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
TOTAL OPERATING COSTS 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
TOTAL OUTFLOWS 2,2 34,0 74,3 46,6 14,7 22,9 28,8 28,0 2,6 1,5 1,5 1,5 1,5
NET CASH FLOW 0,0 0,0 0,0 -0,6 -3,2 -5,8 -7,1 -7,0 -2,6 -1,5 -1,5 -1,5 -1,5
CUMULATED CASH FLOW 0,0 0,0 0,0 -0,6 -3,8 -9,6 -16,8 -23,7 -26,3 -27,8 -29,3 -30,7 -32,2
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
EU Grant
Local contribution
Regional contrintribution
National contribution
Total national public contribution 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Operating subsidies
FINANCIAL RESOURCES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Passenger vehicles
Goods vehicles
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
TOTAL INFLOWS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENTS COSTS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
TOTAL OPERATING COSTS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
TOTAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
NET CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5
CUMULATED CASH FLOW -33,7 -35,2 -36,6 -38,1 -39,6 -41,0 -42,5 -44,0 -45,4 -46,9 -48,4 -49,8 -51,3
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
EU Grant
Local contribution
Regional contrintribution
National contribution
Total national public contribution 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Operating subsidies
FINANCIAL RESOURCES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Passenger vehicles
Goods vehicles
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
TOTAL INFLOWS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENTS COSTS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
TOTAL OPERATING COSTS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
TOTAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
NET CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,2 -0,5 -0,5 -0,5 -0,5
CUMULATED CASH FLOW -52,8 -54,3 -55,7 -57,2 -58,7 -60,1 -61,6 -63,1 -64,2 -64,7 -65,2 -65,7 -66,2
No breakdown figures available
No breakdown figures available
No breakdown figures available
March 2011 | Frontier Economics, Atkins, ITS 35
Annexe 1: Detailed results
Figure 10. A23 Motorway – Spain. Economic analysis (€m, 2010 prices) – High case
Source: Own calculation
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
BENEFITS
Consumers Surplus
Time Benefits 0.0 0.0 0.0 1.8 3.2 3.2 3.4 3.4 8.0 9.0 10.1 10.6 11.2
Vehicle Operating Costs 0.0 0.0 0.0 -1.3 -2.5 -2.7 -2.8 -2.8 -3.1 -3.4 -4.0 -4.2 -4.4
Environmental Benefits 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Accident Reduction 0.0 0.0 0.0 2.8 4.2 4.3 4.7 4.6 7.0 7.9 8.7 9.1 9.6
TOTAL BENEFITS 0.0 0.0 0.0 3.3 4.8 4.9 5.3 5.2 12.0 13.5 14.8 15.5 16.3 17.1
COSTS
Investment Costs
Land Purchase / Construction / …
Other
Total Investment costs 2.2 34.0 74.3 46.0 13.7 22.0 27.8 27.0 0.0 0.0
Maintanance Costs 0.0 0.0 0.0 0.6 1.0 1.0 1.0 1.0 2.6 1.5 1.5 1.5 1.5
TOTAL COSTS 2.2 34.0 74.3 46.6 14.7 22.9 28.8 28.0 2.6 1.5 1.5 1.5 1.5 1.5
NET BENEFITS -2.2 -34.0 -74.3 -43.3 -9.9 -18.1 -23.5 -22.8 9.4 12.0 13.3 14.0 14.8 15.6
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
BENEFITS
Consumers Surplus
Time Benefits 11.7 12.3 12.9 13.6 14.3 15.0 15.7 16.5 17.3 18.2 19.1 20.1 21.1
Vehicle Operating Costs -4.7 -4.9 -5.1 -5.4 -5.7 -6.0 -6.2 -6.6 -6.9 -7.2 -7.6 -8.0 -8.4
Environmental Benefits 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Accident Reduction 10.0 10.5 11.1 11.6 12.2 12.8 13.5 14.1 14.8 15.6 16.4 17.2 18.0
TOTAL BENEFITS 17.1 18.0 18.9 19.8 20.8 21.8 22.9 24.1 25.3 26.5 27.9 29.3 30.7
COSTS
Investment Costs
Land Purchase / Construction / …
Other
Total Investment costs
Maintanance Costs 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5
TOTAL COSTS 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5
NET BENEFITS 15.6 16.5 17.4 18.3 19.3 20.4 21.5 22.6 23.8 25.1 26.4 27.8 29.3
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
BENEFITS
Consumers Surplus
Time Benefits 22.1 23.2 24.4 25.6 26.9 28.2 29.6 31.1 29.7 18.0 18.9 19.8 20.8
Vehicle Operating Costs -8.8 -9.2 -9.7 -10.2 -10.7 -11.2 -11.8 -12.4 -11.5 0.5 0.5 0.5 0.5
Environmental Benefits 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Accident Reduction 18.9 19.9 20.9 21.9 23.0 24.2 25.4 26.6 20.2 8.1 8.5 8.9 9.4
TOTAL BENEFITS 32.3 33.9 35.6 37.3 39.2 41.2 43.2 45.4 38.4 26.5 27.9 29.3 30.7
COSTS
Investment Costs
Land Purchase / Construction / …
Other
Total Investment costs
Maintanance Costs 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.2 0.5 0.5 0.5 0.5
TOTAL COSTS 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.5 1.2 0.5 0.5 0.5 0.5
NET BENEFITS 30.8 32.4 34.1 35.9 37.7 39.7 41.8 43.9 37.2 26.0 27.4 28.8 30.2
Discount Rate 5.5%
ENPV 27.6
ERR 6.3%
B/C Ratio 1.1
No breakdown figures available
No breakdown figures available
No breakdown figures available
36 Frontier Economics, Atkins, ITS | March 2011
Annexe 1: Detailed results
Figure 11. A23 Motorway – Spain. Financial return on investment (€m, 2010 prices)
– High case
Source: Own calculations
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENT COSTS 2,2 34,0 74,3 46,0 13,7 22,0 27,8 27,0 0,0 0,0 0,0 0,0 0,0
Maintenance 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
TOTAL OPERATING COSTS 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
TOTAL OUTFLOWS 2,2 34,0 74,3 46,6 14,7 22,9 28,8 28,0 2,6 1,5 1,5 1,5 1,5
CASH FLOW -2,2 -34,0 -74,3 -46,6 -14,7 -22,9 -28,8 -28,0 -2,6 -1,5 -1,5 -1,5 -1,5
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENT COSTS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
TOTAL OPERATING COSTS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
TOTAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENT COSTS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
TOTAL OPERATING COSTS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
TOTAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,2 -0,5 -0,5 -0,5 -0,5
Discount rate 5,0%
FNPV (C) -230
FRR (C) #DIV/0!
No breakdown figures available
No breakdown figures available
No breakdown figures available
March 2011 | Frontier Economics, Atkins, ITS 37
Annexe 1: Detailed results
Figure 12. A23 Motorway – Spain. Financial return on capital (€m, 2010 prices) –
High case
Source: Own calculations
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
Revenues
Residual values
TOTAL FINANCIAL INFLOWS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Local contribution
Regional contrintribution
National contribution 0,3 5,2 10,7 7,1
Total national public contribution 0,3 5,2 10,7 7,1 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
Total Operating Costs 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
TOTAL FINANCIAL OUTFLOWS 0,3 5,2 10,7 7,7 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
NET CASH FLOW -0,3 -5,2 -10,7 -7,7 -1,0 -1,0 -1,0 -1,0 -2,6 -1,5 -1,5 -1,5 -1,5
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
Revenues
Residual values
TOTAL FINANCIAL INFLOWS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Local contribution
Regional contrintribution
National contribution
Total national public contribution 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
Total Operating Costs 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
TOTAL FINANCIAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
NET CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
Revenues
Residual values
TOTAL FINANCIAL INFLOWS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Local contribution
Regional contrintribution
National contribution
Total national public contribution 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
Total Operating Costs 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
TOTAL FINANCIAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
NET CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,2 -0,5 -0,5 -0,5 -0,5
Discount rate 5,0%
FNPV (K) -41
FRR (K) #DIV/0!
38 Frontier Economics, Atkins, ITS | March 2011
Annexe 1: Detailed results
Figure 13. A23 Motorway – Spain. Financial sustainability (€m, 2010 prices) – High
case
Source: Own calculations
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
EU Grant 1,9 28,8 63,6 38,9 11,5 17,1 21,6 21,1
Local contribution
Regional contrintribution
National contribution 0,3 5,2 10,7 7,1
Total national public contribution 0,3 5,2 10,7 7,1 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Operating subsidies
FINANCIAL RESOURCES 2,2 34,0 74,3 46,0 11,5 17,1 21,6 21,1 0,0 0,0 0,0 0,0 0,0
Passenger vehicles
Goods vehicles
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
TOTAL INFLOWS 2,2 34,0 74,3 46,0 11,5 17,1 21,6 21,1 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENTS COSTS 2,2 34,0 74,3 46,0 13,7 22,0 27,8 27,0
Maintenance 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
TOTAL OPERATING COSTS 0,0 0,0 0,0 0,6 1,0 1,0 1,0 1,0 2,6 1,5 1,5 1,5 1,5
TOTAL OUTFLOWS 2,2 34,0 74,3 46,6 14,7 22,9 28,8 28,0 2,6 1,5 1,5 1,5 1,5
NET CASH FLOW 0,0 0,0 0,0 -0,6 -3,2 -5,8 -7,1 -7,0 -2,6 -1,5 -1,5 -1,5 -1,5
CUMULATED CASH FLOW 0,0 0,0 0,0 -0,6 -3,8 -9,6 -16,8 -23,7 -26,3 -27,8 -29,3 -30,7 -32,2
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
EU Grant
Local contribution
Regional contrintribution
National contribution
Total national public contribution 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Operating subsidies
FINANCIAL RESOURCES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Passenger vehicles
Goods vehicles
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
TOTAL INFLOWS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENTS COSTS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
TOTAL OPERATING COSTS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
TOTAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5
NET CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5
CUMULATED CASH FLOW -33,7 -35,2 -36,6 -38,1 -39,6 -41,0 -42,5 -44,0 -45,4 -46,9 -48,4 -49,8 -51,3
2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
EU Grant
Local contribution
Regional contrintribution
National contribution
Total national public contribution 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Operating subsidies
FINANCIAL RESOURCES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Passenger vehicles
Goods vehicles
TOTAL REVENUES 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
TOTAL INFLOWS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Land Purchase / Construction / …
Other
TOTAL INVESTMENTS COSTS 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0 0,0
Maintenance 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
TOTAL OPERATING COSTS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
TOTAL OUTFLOWS 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,5 1,2 0,5 0,5 0,5 0,5
NET CASH FLOW -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,5 -1,2 -0,5 -0,5 -0,5 -0,5
CUMULATED CASH FLOW -52,8 -54,3 -55,7 -57,2 -58,7 -60,1 -61,6 -63,1 -64,2 -64,7 -65,2 -65,7 -66,2
No breakdown figures available
No breakdown figures available
No breakdown figures available
March 2011 | Frontier Economics, Atkins, ITS 39
Annexe 1: Detailed results