Tutorial 2: Creating a Project Sched leCreating a Project Schedule

Microsoft Project 2010®Microsoft Project 2010

http://www.learningquotient.in

Page 2: Ms project 2010 tutorial   2

XPXPXPIn Tutorial Section 2.1 you will:you will:• Start a new project

h d l d f l• Examine scheduling defaults• Change a project and task calendar• Enter and edit tasks and durations• Enter and edit recurring tasks and milestonesEnter and edit recurring tasks and milestones• Enter lag and lead times

New Perspectives on Microsoft Project 2010 2http://www.learningquotient.in

Page 3: Ms project 2010 tutorial   2

XPXPXPIn Tutorial Section 2.2you will:you will:• Enter and edit task dependencies• View project statistics• Show the project summary• Review project statistics• Create and manipulate summary tasksCreate and manipulate summary tasks• Develop a work breakdown structure

New Perspectives on Microsoft Project 2010 3http://www.learningquotient.in

Page 4: Ms project 2010 tutorial   2

XPXPXP

• By default, the new project file is scheduled from a project Start dateproject Start date

• All tasks are scheduled to begin as soon as possible• Project 2010 calculates the project’s Finish date• Project 2010 calculates the project s Finish date based on the: – TasksTasks– Durations– Dependencies

New Perspectives on Microsoft Project 2010 4http://www.learningquotient.in

Page 5: Ms project 2010 tutorial   2

XPXPXPProject Information Dialog Box

New Perspectives on Microsoft Project 2010 5http://www.learningquotient.in

Page 6: Ms project 2010 tutorial   2

XPXPXPScheduling a Project from a Finish DateDate• When a project is scheduled from a Finish date, such as a conference all tasks are scheduled to begin asas a conference, all tasks are scheduled to begin as late as possible.

• Project 2010 calculates the project’s Start date basedProject 2010 calculates the project s Start date based on the tasks, durations and dependencies.

• The default is for all tasks and the project to start as p jlate as possible.

• To schedule from a Finish Date, you apply this setting y pp y gas soon as the project is created.

New Perspectives on Microsoft Project 2010 6http://www.learningquotient.in

Page 7: Ms project 2010 tutorial   2

XPXPXPProject Scheduled From Finish Date

New Perspectives on Microsoft Project 2010 7http://www.learningquotient.in

Page 8: Ms project 2010 tutorial   2

XPXPXPThe Task Information Dialog Box• The Task Information dialog box is a comprehensive collection of all of the information about each taskcollection of all of the information about each task organized into six categories:– General– Predecessors– Resources– Advanced– Notes

ld– Custom Fields

• The Task Information dialog box is another view by which you can examine and enter data about a taskwhich you can examine and enter data about a task.

New Perspectives on Microsoft Project 2010 8http://www.learningquotient.in

Page 9: Ms project 2010 tutorial   2

XPXPXPThe Task Information Dialog Box

New Perspectives on Microsoft Project 2010 9http://www.learningquotient.in

Page 10: Ms project 2010 tutorial   2

XPXPXPConstraints using Task Information• How the project is originally scheduled (from a Start date or from a Finish date) determines the initial )Constraint types (as soon as possible or as late as possible).h l h d• The initial Constraint type has a tremendous impact on the calculated start and finish dates for each task entered into the project.entered into the project.

• Always take the time to examine the Project Information dialog box before starting a new project.

New Perspectives on Microsoft Project 2010 10http://www.learningquotient.in

Page 11: Ms project 2010 tutorial   2

XPXPXPExamining Project Calendars• By default, the entire project, each task, and each 

resource is scheduled according to the Standard calendar.

• The Standard calendar specifies that Monday through Friday are working days with 8 hours of work completedFriday are working days with 8 hours of work completed each day.

• Saturday and Sunday are designated as nonworking days.• The Calendar can be modified to identify holidays or 

other nonworking days or times in which work should not be scheduledbe scheduled.  

• You can also create unique calendars for tasks and resources that do not follow the working and nonworking times specified by the Standard calendar.

New Perspectives on Microsoft Project 2010 11http://www.learningquotient.in

Page 12: Ms project 2010 tutorial   2

XPXPXPChange Time for a Work Week

New Perspectives on Microsoft Project 2010 12http://www.learningquotient.in

Page 13: Ms project 2010 tutorial   2

XPXPXPCreating a Task Calendar

• An individual task calendar can be created for anyAn individual task calendar can be created for any task that does not follow the working and nonworking times specified by the project calendar. 

• An individual resource calendar can be created for a resource that does not follow the working and nonworking times specified by the project calendarnonworking times specified by the project calendar. 

• By default, all tasks and resource assignments inherit the project calendar unless you specify something p j y p y gelse. 

New Perspectives on Microsoft Project 2010 13http://www.learningquotient.in

Page 14: Ms project 2010 tutorial   2

XPXPXPChanging the Calendar for a Task

New Perspectives on Microsoft Project 2010 14http://www.learningquotient.in

Page 15: Ms project 2010 tutorial   2

XPXPXPApplying a Task Calendar to a Task

New Perspectives on Microsoft Project 2010 15http://www.learningquotient.in

Page 16: Ms project 2010 tutorial   2

XPXPXPEntering Tasks and Durations in the Entry Tablein the Entry Table• Entering tasks and durations is probably the single most important effort in developing a useful project p p g p jfile.

• If tasks are omitted or durations underestimated, the l f h ’ h d l dvalue of the project’s scheduling and cost 

information is compromised and the success of the project might be jeopardized.project might be jeopardized.

• Often you will need to change an existing task or insert, delete, or move a task.

New Perspectives on Microsoft Project 2010 16http://www.learningquotient.in

Page 17: Ms project 2010 tutorial   2

XPXPXPEditing Tasks and Durations in the Entry Tablein the Entry Table• Project 2010 makes it very easy to edit an existing project.p j

• Many of the editing skills that you gained when editing a spreadsheet will apply to a project table.

• To change an existing entry, you first navigate to the cell.  Once there, you have several options:

R t th t– Retype the entry– Edit the entry directly in the cell– Edit an entry in the Entry bary y

New Perspectives on Microsoft Project 2010 17http://www.learningquotient.in

Page 18: Ms project 2010 tutorial   2

XPXPXPEntering and Editing Tasksin the Entry Tablein the Entry Table

New Perspectives on Microsoft Project 2010 18http://www.learningquotient.in

Page 19: Ms project 2010 tutorial   2

XPXPXPTo Delete a Task• If you want to delete an entire task row in Project 2010 you must select the entire row then press the2010, you must select the entire row, then press the Delete key.

• Project 2010 includes a Smart Tag to allow you toProject 2010 includes a Smart Tag to allow you to specify what you want to delete.

• A list arrow appears when you place the pointer over pp y p pthe Smart Tag.

New Perspectives on Microsoft Project 2010 19http://www.learningquotient.in

Page 20: Ms project 2010 tutorial   2

XPXPXPSmart Tag Selection for Task DeletionDeletion

New Perspectives on Microsoft Project 2010 20http://www.learningquotient.in

Page 21: Ms project 2010 tutorial   2

XPXPXPCopy, Paste and Move• Copying, pasting, and moving tasks are important task editing skillstask editing skills.  

• Project 2010 offers a variety of tools that you can use to accomplish these common tasks, including:to accomplish these common tasks, including:– Menu bar options– Toolbar buttons– Quick keystrokes– Right‐click shortcut menus

New Perspectives on Microsoft Project 2010 21http://www.learningquotient.in

Page 22: Ms project 2010 tutorial   2

XPXPXPFill Handle• If several task durations are the same, you can use either the copy and paste features to quickly entereither the copy and paste features to quickly enter the durations or the fill handle to populate cells.

• If you have used the fill handle in Excel or anotherIf you have used the fill handle in Excel or another spreadsheet program, you will find it a very similar process in Project 2010.

• The fill handle is a small square that appears in the lower corner of the selected cell.

• When you drag a fill handle, the contents of the active cell are copied.

• You can also use the fill handle to fill task names.New Perspectives on Microsoft Project 2010 22http://www.learningquotient.in

Page 23: Ms project 2010 tutorial   2

XPXPXPFill Handle

New Perspectives on Microsoft Project 2010 23http://www.learningquotient.in

Page 24: Ms project 2010 tutorial   2

XPXPXPWorking with Duration Units of MeasureMeasure• Entering and editing durations involves understanding the units of measure available forunderstanding the units of measure available for them.

• The default unit of measure is day, and thereforeThe default unit of measure is day, and therefore “day” does not need to be entered.

• To use any other unit, you must type the y , y ypabbreviation.

New Perspectives on Microsoft Project 2010 24http://www.learningquotient.in

Page 25: Ms project 2010 tutorial   2

XPXPXPUnits of Measure Abbreviations• Elapsed refers to clock time rather than working time.

• An example is the task “Allow paint to dry.” The paint will dry in exactly the same amount of time 

dl f h h d kdregardless of whether it dries on a workday, a weekend or holiday.  If it takes one day to dry, the duration should be entered as “1 ed” (for 1 elapsedduration should be entered as  1 ed  (for 1 elapsedday). 

New Perspectives on Microsoft Project 2010 25http://www.learningquotient.in

Page 26: Ms project 2010 tutorial   2

XPXPXPEditing Tasks and Durationsin Other Viewsin Other Views• Anything changed in one view is automatically changed in all the other viewschanged in all the other views.

• You can use the View Bar to quickly switch between viewsviews.

• The way data is displayed differs by view and often satisfies different communication and reportingsatisfies different communication and reporting needs as the project develops.

New Perspectives on Microsoft Project 2010 26http://www.learningquotient.in

Page 27: Ms project 2010 tutorial   2

XPXPXPEditing Tasks and Durations in Other Views Cont ’din Other Views Cont. d• Regardless of the view used, you can edit any task by double‐clicking it to open its Task Information dialogdouble clicking it to open its Task Information dialog box.

• As you work with Project 2010, you will becomeAs you work with Project 2010, you will become more familiar with each view and learn which is the best representation of the data for different purposes.

New Perspectives on Microsoft Project 2010 27http://www.learningquotient.in

Page 28: Ms project 2010 tutorial   2

XPXPXPEntering Recurring Tasks• A recurring task is a task that repeats at a regular interval.  

• A status meeting is a good example of a recurring task that needs to be scheduled for each week or h l l hother regular intervals in the project.

• In Project 2010, you can define a recurring task one time using the Recurring Task Information dialog boxtime using the Recurring Task Information dialog box.

• Project 2010 then handles the details of scheduling the task at specified interval for the entire project or p p jfor the time period you specify.

• You can also change the calendar used on the recurring task in the Calendar section.

New Perspectives on Microsoft Project 2010 28http://www.learningquotient.in

Page 29: Ms project 2010 tutorial   2

XPXPXPRecurring Task Information Dialog BoxBox

New Perspectives on Microsoft Project 2010 29http://www.learningquotient.in

Page 30: Ms project 2010 tutorial   2

XPXPXPEntering Milestones• A milestone is a task that marks a significant point in time or a progress checkpointtime or a progress checkpoint.

• It has a zero duration and is therefore a symbolic task that is used mainly to communicate progress or tothat is used mainly to communicate progress or to mark the end of a significant phase of the project.

• Examples include the signing of a contract or the p g gannouncement of a new product.

• Milestones can also be used to motivate project p jparticipants by recognizing accomplishments.

New Perspectives on Microsoft Project 2010 30http://www.learningquotient.in

Page 31: Ms project 2010 tutorial   2

XPXPXPMilestones

New Perspectives on Microsoft Project 2010 31http://www.learningquotient.in

Page 32: Ms project 2010 tutorial   2

XPXPXPUnderstanding Task Dependencies• Four task dependencies define the relationships between tasks in a projectbetween tasks in a project.

New Perspectives on Microsoft Project 2010 32http://www.learningquotient.in

Page 33: Ms project 2010 tutorial   2

XPXPXPUnderstanding Task Dependencies Cont ’dCont. d• By linking tasks in finish‐to‐start relationships, you establish the required sequence of tasksestablish the required sequence of tasks.

• Project 2010 uses these relationships to set start and finish dates for each task.finish dates for each task.

• Most dependencies are Finish‐to‐Start (FS), meaning a certain task (the predecessor) must finish before ( p )another task (the successor) can start.

• In order to use important project management p p j gtechniques such as critical path analysis, you must determine task dependencies.

New Perspectives on Microsoft Project 2010 33http://www.learningquotient.in

Page 34: Ms project 2010 tutorial   2

XPXPXPCreating Task Dependencies• Project 2010 makes it easy to create, and remove, FS relationships between tasks by providing the Link p y p gTasks and Unlink Tasks buttons on the Standard toolbar.

k d d l b bl h d h• Task dependencies also can be established in the graphical views.

New Perspectives on Microsoft Project 2010 34http://www.learningquotient.in

Page 35: Ms project 2010 tutorial   2

XPXPXPCreating Task Dependencies Cont.

New Perspectives on Microsoft Project 2010 35http://www.learningquotient.in

Page 36: Ms project 2010 tutorial   2

XPXPXPSlack Times• Total slack is the amount of time by which an activity may be delayed from its scheduled Start date withoutmay be delayed from its scheduled Start date without the delay setting back the entire project.

• Free slack is the amount of time by which an activityFree slack is the amount of time by which an activity may be delayed without delaying the early start of any immediately following tasks.

New Perspectives on Microsoft Project 2010 36http://www.learningquotient.in

Page 37: Ms project 2010 tutorial   2

XPXPXPCritical and Non‐Critical Tasks• In the Network Diagram view, the critical tasks—tasks that are on the critical path—are displayed p p ywithin a red border.

• A task that is not on the critical path is a non‐critical k h d ’ l htask, that is, it doesn’t necessarily have to start on its 

currently scheduled Start date in order for the overall project to be completed on time.project to be completed on time.

• The Network Diagram is used mainly to view and analyze the critical path.

New Perspectives on Microsoft Project 2010 37http://www.learningquotient.in

Page 38: Ms project 2010 tutorial   2

XPXPXPCreating Dependencies using the Network Diagram viewNetwork Diagram view

New Perspectives on Microsoft Project 2010 38http://www.learningquotient.in

Page 39: Ms project 2010 tutorial   2

XPXPXPEntering Lag and Lead Times• When a project is scheduled from a Start date, lag and lead times refer to an amount of time that the second task of a relationship is moved backward (lead) or forward (lag) in time.

d h d k b k d• Lead timemoves the second task backward in time so that the two tasks overlap.  

• Lag time is the opposite of lead time It moves the• Lag time is the opposite of lead time.  It moves the second task forward in time so that the tasks are further separated.  

New Perspectives on Microsoft Project 2010 39http://www.learningquotient.in

Page 40: Ms project 2010 tutorial   2

XPXPXPLag and Lead Time from Start Date

New Perspectives on Microsoft Project 2010 40http://www.learningquotient.in

Page 41: Ms project 2010 tutorial   2

XPXPXPEntering Lag and Lead Times Cont.’d• Project 2010 combines the concepts of lag and lead times into one term, lag time.  , g

• When a project is scheduled from a Start date, positive lag timemoves the second task forward in time.– Positive lag time is the traditional definition of lag time in general project management discussions.general project management discussions.

• Negative lag timemoves the second task backward in time so that the tasks overlap.  – Negative lag time is called lead time in general project management discussions.

New Perspectives on Microsoft Project 2010 41http://www.learningquotient.in

Page 42: Ms project 2010 tutorial   2

XPXPXPNegative and Positive Lag Time

New Perspectives on Microsoft Project 2010 42http://www.learningquotient.in

Page 43: Ms project 2010 tutorial   2

XPXPXPCheck for Lag Time Effects Cont.• Confusing negative and positive lag times is easy, especially when examining them for both a project p y g p jthat is scheduled from a Start date and one scheduled from a Finish date.

b• Remember:– Positive lag time always increases the amount of time between tasks.between tasks.

– Negative lag time always causes the tasks to overlap.– This rule holds true regardless of whether the project is 

h d l d f th St t d t th Fi i h d tscheduled from the Start date or the Finish date.

New Perspectives on Microsoft Project 2010 43http://www.learningquotient.in

Page 44: Ms project 2010 tutorial   2

XPXPXPCheck for Lag Time Effects• Once the tasks, durations, and relationships are entered you should check the Project Informationentered, you should check the Project Informationdialog box to verify the project’s calculated Finish date if the project is scheduled from a Start date, or p jcalculated Start date if the project is scheduled from a Finish date.

• When a project is scheduled from a Start date, applying negative lag time to task dependencies that 

th iti l th i t h tare on the critical path is a common way to shorten the critical path because it allows tasks to overlap.

New Perspectives on Microsoft Project 2010 44http://www.learningquotient.in

Page 45: Ms project 2010 tutorial   2

XPXPXPCheck for Lag Time Effects Cont.’d• When you apply negative lag time, the second task is allowed to start before the first task is completelyallowed to start before the first task is completely finished.

• When a project is scheduled from a Finish date, allWhen a project is scheduled from a Finish date, all tasks have as late as possible schedules and lag time affects the first task rather than the second.

New Perspectives on Microsoft Project 2010 45http://www.learningquotient.in

Page 46: Ms project 2010 tutorial   2

XPXPXPLag Time From a Finish Date

New Perspectives on Microsoft Project 2010 46http://www.learningquotient.in

Page 47: Ms project 2010 tutorial   2

XPXPXPCreating a Work Breakdown Structure with Summary Taskswith Summary Tasks• A very important strategy for managing projects well is to organize the work that needs to be done in a glogical manner.

• A work breakdown structure (WBS) is an outcome‐d l f h k l doriented analysis of the work involved in a project 

that defines the total scope of the project.– AWBS is a foundation document in project managementA WBS is a foundation document in project management because it provides the basis for planning and managing project schedules, costs, and changes.TheWBS provides a hierarchy similar to an organizational– The WBS provides a hierarchy, similar to an organizational chart, to group project work logically.

New Perspectives on Microsoft Project 2010 47http://www.learningquotient.in

Page 48: Ms project 2010 tutorial   2

XPXPXPCreating a Work Breakdown Structure with Summary Tasks Cont ’dwith Summary Tasks Cont. d• In order to use a WBS in Project 2010, you must organize tasks into summary tasks (groups of tasks g y (g pthat logically belong together).

• When developing a new, large project, some project f h b d fmanagers prefer to start with broad groupings of 

summary tasks and then break them down into smaller tasks.smaller tasks.

New Perspectives on Microsoft Project 2010 48http://www.learningquotient.in

Page 49: Ms project 2010 tutorial   2

XPXPXPCreating a Work Breakdown Structure with Summary Tasks Cont ’dwith Summary Tasks Cont. d• Planning a project by starting with broad categories of tasks is called the top‐down method of creating a p gWBS.

• Other project managers prefer to list all of the d d l k d h ll h l lindividual tasks, and then collect them into logical 

groupings using the bottom‐up method.• Once you have indentified your summary tasks you• Once you have indentified your summary tasks, you use Outdenting and Indenting in Project 2010 to create the summary tasks.

New Perspectives on Microsoft Project 2010 49http://www.learningquotient.in

Page 50: Ms project 2010 tutorial   2

XPXPXPOutdenting and Indenting Tasks• Use the Outdent button and the Indent button on the Formatting toolbar to create your WBSFormatting toolbar to create your WBS.

• Outdentingmoves a task to the left (a higher level in the WBS), and indentingmoves a task to the right (a ), g g (lower level in the WBS).

• Projects can have several levels in the WBS.• Many projects have at least three levels, and some large projects have more.

New Perspectives on Microsoft Project 2010 50http://www.learningquotient.in

Page 51: Ms project 2010 tutorial   2

XPXPXPCreating a Summary Task

New Perspectives on Microsoft Project 2010 51http://www.learningquotient.in

Page 52: Ms project 2010 tutorial   2

XPXPXPDisplaying Outline Numbers• Tasks and subtasks are organized in an outline, with tasks in a hierarchy when you have created summarytasks in a hierarchy, when you have created summary tasks.

• In Project 2010, you can view built‐in outlineIn Project 2010, you can view built in outline numbers, which will display in the Task name cells for all tasks.

New Perspectives on Microsoft Project 2010 52http://www.learningquotient.in

Page 53: Ms project 2010 tutorial   2

XPXPXPDisplaying Outline Numbers Cont ’dCont. d

New Perspectives on Microsoft Project 2010 53http://www.learningquotient.in

Page 54: Ms project 2010 tutorial   2

XPXPXPProject Summary Task• Many Project Managers like to create a Project Summary Task which allows them to see how theSummary Task which allows them to see how the start and finish dates change as they enter and edit tasks, durations, and dependencies.p

New Perspectives on Microsoft Project 2010 54http://www.learningquotient.in

Page 55: Ms project 2010 tutorial   2

XPXPXPProject Summary Task Cont.’d

New Perspectives on Microsoft Project 2010 55http://www.learningquotient.in

Page 56: Ms project 2010 tutorial   2

XPXPXPExpanding and Collapsing Tasks• Once your project has been organized into summary tasks you can easily expand (show) and collapsetasks, you can easily expand (show) and collapse(hide) the individual tasks within each phase.

New Perspectives on Microsoft Project 2010 56http://www.learningquotient.in

Page 57: Ms project 2010 tutorial   2

XPXPXPUsing WBS Codes• Many people like to number tasks in their WBS to show the logical groupings of workshow the logical groupings of work.

• Using outline numbers or special work breakdown structure (WBS) code is a way to use anstructure (WBS) code is a way to use an alphanumeric code to represent each task’s position within the hierarchical structure of the project.

• A WBS code helps identify and group project tasks for project communication, documentation, or accounting purposes.

New Perspectives on Microsoft Project 2010 57http://www.learningquotient.in

Page 58: Ms project 2010 tutorial   2

XPXPXPCreating WBS Codes

New Perspectives on Microsoft Project 2010 58http://www.learningquotient.in