NATIONAL HIGHWAYS AUTHORITY OF INDIA
(Ministry of Shipping, Road Transport & Highways)
NATIONAL HIGHWAY PROJECT PHASE – II
CONSULTANCY CONTRACT NO: IE
Independent Engineer Services for four Lining of Chenani to Nashri (New Alignment) of NH 1A including 9 KM Long Tunnel (2 Lane) with Parallel Escape Tunnel on BOT (Annuity) basis in the State of Jammu & Kashmir
(Package no. IE/NHDP-Phase-II/BOT/V/J&K)
QUARTERLY PROGRESS REPORT NO: 21
JUNE 2016 TO AUGUST 2016
Euroestudios S. L. Spain
in Association with
Segmental Consulting & Infrastructure Advisory (P) Ltd.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 1
TABLE OF CONTENTS
1. PROJECT OVERVIEW ...................................................................................................................................... 3
1.1. INTRODUCTION ...................................................................................................................................... 3
1.2. THE PROJECT ROAD ............................................................................................................................. 3
1.3. THE PROJECT ROAD CONSTRAINTS .................................................................................................. 3
1.4. PROPOSED PATNITOP TUNNEL ALIGNMENT .................................................................................... 4
1.5. PROJECT MAP ........................................................................................................................................ 5
2. PROJECT ASSIGNMENT .................................................................................................................................. 6
2.1. BACKGROUND ........................................................................................................................................ 6
3. MOBILIZATION OF AGENCIES ........................................................................................................................ 6
3.1. INDEPENDENT ENGINEER .................................................................................................................... 6
3.2. ROLE AND FUNCTIONS OF IE .............................................................................................................. 6
3.3. ORGANISATION CHART AND STAFF LIST........................................................................................... 7
3.4. DRAWL OF AGREEMENT WITH C0NCESSIONAIRE ........................................................................... 9
3.5. PIU............................................................................................................................................................ 9
4. PRE-CONSTRUCTION ACTIVITIES ................................................................................................................. 9
4.1. SHIFTING OF UTILITIES ......................................................................................................................... 9
4.2. UTILITIES SHIFTING & OTHER HINDRANCES ................................................................................... 10
4.2.1 STATUS OF UTILITY SHIFTING ........................................................................................................... 10
4.2.2 HINDRANCES ........................................................................................................................................ 10
5. CONSTRUCTION SCHEDULE ........................................................................................................................ 11
5.1. CONSTRUCTION SHEDULE AS PER MILESTONE TARGET ............................................................ 11
5.2. INAUGURATION .................................................................................................................................... 11
5.3. TUNNEL BREAKTHROUGH’S .............................................................................................................. 11
6. CONTRACTOR´S RESOURCES .................................................................................................................... 12
7. MEETINGS/SITE VISIT/REVIEW OF DOCUMENTS ...................................................................................... 13
7.1. MEETINGS ............................................................................................................................................. 13
7.2. SITE VISITS ........................................................................................................................................... 13
7.3. REVIEW OF DOCUMENTS/DRAWINGS ............................................................................................. 14
8. INVOICES PAYMENT & REIMBURSEMENT ................................................................................................. 20
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 2
9. EXECUTING AGENCIES AND CONTRACT DATA ....................................................................................... 20
9.1 AGENCIES ........................................................................................................................................ 20
9.2 CONTRACT DATA ............................................................................................................................ 20
9.2.1 PROJECT COST .............................................................................................................................. 20
9.2.2. CIVIL WORKS CONTRACT DETAILS ............................................................................................. 21
9.2.3 SCOPE OF WORK ........................................................................................................................... 21
10. WEATHER REPORT ....................................................................................................................................... 22
11. PROGRESS OF THE PROJECT ..................................................................................................................... 25
11.1 ESTIMATION OF PHYSICAL PROGRESS IN GLOBAILITY ........................................................... 25
11.2 TUNNEL WORKS MONITORING ..................................................................................................... 26
11.3 PHYSICAL PROGRESS CHART .................................................................................................... 28
12 QUALITY CONTROL AND TESTING OF MATERIALS ................................................................................ 34
12.1 UP TO DATE STATUS OF TEST ..................................................................................................... 34
12.2 TEST RESULT OF CONCRETE CORE & CUBES .......................................................................... 35
13 SAFETY REPORT ........................................................................................................................................... 67
14 MINUTES OF MONTHLY PROGRESS MEETING......................................................................................... 68
15 PHOTOGRAPHIC REPORT ............................................................................................................................ 69
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 3
1. PROJECT OVERVIEW
1.1. INTRODUCTION
The Ministry of Road Transport and Highway (MORT&H) has taken a strategic decision to develop the
North-South corridor connecting Srinagar (J&K) to Kanya Kumari (Tamilnadu). The National Highways
Authority of India (NHAI) has been appointed by MORT&H, to implement this development.
NHAI have appointed the Louis Berger Group, Inc., USA, in Joint Ventures with LRP Consultants,
India and in association with L&T Ramboll, India, and D2 Consultant for Tunnel as consultants to carry
out the detailed design, for the Patnitop Tunnel of the NH-1A, between Udhampur and Banihal (Km 66
to Km. 188) in the state of Jammu and Kashmir.
1.2. THE PROJECT ROAD
The NH-1A National Highway will be upgraded from its present two-lane layout, to a four-lane divided
carriageway configuration. The design of the road between Udhampur and Banihal, Km 67 to Km. 188
is being carried out in five separate packages. The project will require the construction of numerous
structures, including one approx. 9 Km. long Tunnel (Patnitop Tunnel) and six short Tunnels (Tunnels
with length below 1 km).
1.3. THE PROJECT ROAD CONSTRAINTS
The existing road alignment of the NH-1A between Km 67 and Km 188 is typified by sub-standard, and
often steep curves and gradients, in the horizontal and vertical planes. The proposed improvement will
entail widening towards the valley side along most of the road, which will also involve the construction
of many new structures, including viaducts, bridges, retaining walls and Tunnels.
The project road area is within a region that is prone to frequent earthquakes of sizeable magnitude.
Much of the rock in the area is well jointed and highly fragmented. Combining seismic activity, with the
extreme prevailing weather conditions, also means the area experiences constant landslides.
The Kashmir region, with its exceptional scenic landscapes, abundant wildlife, culture diversity and
profuse number of historic and religion building, is a ‘Mecca’ for tourists from every corner of the globe.
The NH-1A being the main route between the principal cities of Jammu and Srinagar carries most of
the tourist for the entire area. Tourism peaks during the summer months of July and August, but spring
and autumn, can also be busy.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 4
1.4. PROPOSED PATNITOP TUNNEL ALIGNMENT
In previous design stages different alternatives have been investigated for Tunnel, crossing of the
Patnitop range in approx. station Km 90 to Km 130 of the existing NH-1A. Five Tunnel alternatives
varying from 1.2 Km length have been assessed and presented in earlier design stages. As the
optimum alternative, the longest one, a base Tunnel at elevation of approx. 1220 m a.s.l. was
approved for further investigation and elaboration of the Tunnel civil tender design documents.
Concerned section Km. 67 to Km. 188 is being carried out in five separate packages 1 – 5.
Patnitop Tunnel is designed as a base Tunnel. Passing under the Patnitop mountain range with
overburden more than 1 Km and belongs to NHDP Phase- II. This contract package start at existing
road starts from Km 89 and ends at Km 130 of existing road. Tunnel mined portals are located at
approx. start of Km 90 (southern portal) close to village of Chenani and Km 130 (northern portal) close
to township of Batote of existing road at elevations 1230 m and 1210 m respectively. Tunnel profile
grade is of a roof character with 0.5 % longitudinal profile grade. Tunnel horizontal alignment starts
and ends with curves of 300 m radius, and the rest of mid-section is straight. Main Tunnel direction is
South to North. Travel distance will be reduced for more than 30 Km and climbing and descending of
approx. 1000 m shall be avoided. Tunnel shall be 2-lane, bidirectional tunnel with parallel escape
Tunnel and cross connections into escape Tunnel for emergency exit.
The Existing road (2-lane, bidirectional) will be utilized to accommodate the local traffic in the area as
well as over-sized and other vehicles non-suitable for tunnel operation. The existing carriageway will
be upgraded with minor improvement to both the horizontal and vertical alignment.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 5
1.5. PROJECT MAP
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 6
2. PROJECT ASSIGNMENT
2.1. BACKGROUND
NHAI have appointed the Louis Berger Group, Inc., USA, in Joint Venture with LRP Consultants, India
and in association with L&T Ramboll, India, as consultant to carry out the Feasibility Study and DPR
for 4-Laning of the section Udhampur to Banihal, Km. 66 to Km 188 of NH-1A in the State of Jammu
and Kashmir. The Complete project length is divided into 5 packages.
3. MOBILIZATION OF AGENCIES
3.1 INDEPENDENT ENGINEER
It was decided that Independent Engineer may be invited to participate for project management so as
to have proper management and quality assurance. Accordingly Bids were invited from pre-qualified
and shortly listed consultants and the work was allotted to M/s Euroestudios.S.L. In Association with
M/s Segmental Consulting and Infrastructure Advisory (Pvt.) Ltd. In an agreement for Independent
Engineer, services were entered into between National Highways Authority of India, Plot No. G-5 and
G-6, Sector No.10, Dwarka, New Delhi- 110045 and M/s M/S Euroestudios.S.L., Castelló 128, E-
28006 MADRID, ESPAÑA in Association with M/s Segmental Consulting and Infrastructure Advisory
(P) Ltd., Unit No. 419A-421, Spaze I Tech Park, Tower B-4.Sector 49, Sohna Road Gurgaon-122002–
India, by Letter No. NHAI/12015/GM (N-1)/CS-88-92/JK/2010/512 dated 05th April 2011 for
commencement of service and accordingly mobilization of Key/ Sub Key Personnel was done. M/S
Euroestudios, S.L. in Association with M/s Segmental Consulting and Infrastructure Advisory (P) Ltd.,
as Independent Engineer in accordance with the terms of the agreement in MOU, have deployed
personnel to look after the project.
Office Building for Team has been hired at Ekta Vihar, Near M.H. Hospital, Udhampur (J&K) and office
is fully operational.
3.2 ROLE AND FUNCTIONS of IE
The role of IE has been described in schedule “Q” of Concession Agreement between NHAI and CNTL
(SPV created by IL&FS) the main points are described below.
Review of Drawings & Documents.
Review, Inspection and Monitoring of construction work.
Conducting testing on completion of construction & issuing completion/ provisional certificate.
Review, Inspection & Monitoring of Divestment requirements.
Determining as required under the Agreement, the costs of any works or services and / or their
reasonableness.
Determining, as required under the Agreement, the period or any extension thereof, for
performing any duty or obligation.
Assisting the parties in resolution of disputes.
Undertaking all other duties and functions in accordance with Agreement.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 7
3.3 ORGANIZATION CHART AND STAFF LIST
Key Staff S.No Position Name Date of Joining Remarks
1 Team Leader cum Sr. Tunnel Expert Mr. Valentín Salcedo 25.05.2011
2 Tunnel Design Engineer 31.05.2011 Completed
3 Sr. Geologist 01.06.2011 Completed 4 Sr. Geotechnical Engineer Mr. Cesar Andia 11.08.2011 5 Sr. E & M Expert Mr. José Manuel Pineda 28.04.2012 6 Tunnel Safety Expert Mr. Sanjay Kr. Sharma 02.06.2011 7 Tunnel Ventilation Expert Mr. Ajit Kumar Swain 18.02.2015 8 9
10 11 12 13 14 15
Tunnel Excavation Expert Tunnel Lining Expert Tunnel Lighting Expert Senior Quality Cum Material Expert Bridge / Structural Engineer Financial Expert Legal Expert
Mr. Subash Chander Mr. Mihir Kumar Sahu Mr. Manish Kr. Sharma
01.06.2011 13.08.2015 30.06.2011 03.06.2011 03.06.2011 30.03.2016 28.06.2011
Completed
Completed Completed Completed
Tunnel Engineer-1 25.05.2011 Completed 16 Tunnel Engineer-2 Mr. Neeraj Singh Datta 01.06.2011
Sub-Professional Staff S.No Position Name Date of Joining Remarks
1 Tunnel Fire Fighting Expert Mr. Z.K. Khaishagi 04.04.2016
2 Environmental Expert 01.09.2011 Completed
3 4
Hydrologist/Drainage Expert Hydrologist/Drainage Expert
01.09.2011 15.09.2011
Completed Completed
5 Geologist 12.09.2011 Completed 6 Geo-technical Engineer 13.07.2011 Completed
7 Material Engineer 08.07.2011 Completed 8 9
10 11 12 13 14 15 16 17 18 19 20 21 22 23
Material Engineer Quantity Surveyor Highway Engineer Bridge Engineer Traffic & Transportation Expert Survey Engineer Survey Engineer Assist. Tunnel Excavation Expert Assist. Tunnel Excavation Expert Assist. Tunnel Lining Expert Assist. Tunnel Lining Expert Horticulturalist Lab. Technician Lab. Technician HTMS/Toll Expert CAD Expert
Mr. Vikas Gupta Mr. Rajesh Mishra Mr. Bharat Goel
03.10.2011 02.01.2012 01.10.2013 03.01.2014 15.07.2013 02.04.2012 01.08.2011 01.11.2014 13.06.2011 17.06.2011 20.06.2011 14.07.2014 01.01.2013 24.06.2011 21.09.2015 02.01.2012
Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed Completed
Completed
Support Staff S.No Position Name Date of Joining Remarks
1 Office Manager Ms. Akanksha Dubey 04.04.2016
2 Accountant Mr. Pankaj Gupta 01.10.2013
3 Cashier Mr. J.S. Jaswal 12.04.2012
4 Steno Mr. Akash Anand 01.08.2016
5 Computer Operator Mr. Sahil Gupta 01.08.2016
6 Photocopier Mr. Sanat Kr. Mishra 25.05.2011
7 Office Boy Mr. Subash Chander 01.07.2011
8 9
Security Guard Security Guard
Mr. Kewal Singh Mr. Jeevan Lal
01.02.2015 01.07.2016
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 8
ORGANISATION CHART
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 9
3.4 DRAWL OF AGREEMENT WITH CONCESSIONAIRE
Agreement was drawn by NATIONAL HIGHWAY AUTHORITY OF INDIA (NHAI) with Chenani
Nashri Tunnel way Limited. (CNTL) on 28th July 2010. For this project IL&FS Transportation
Networks Ltd has formed a Special Purpose Vehicle (SPV) by the name of Chenani Nashri Tunnel
way Limited (CNTL) (hereinafter referred as the “Concessionaire”).
3.5 PIU
PROJECT DIRECTOR.
National Highway Authority of India – PIU
315/1, 2nd
Floor, Channi Himmat
Jammu (J&K) 180015
4. PRE-CONSTRUCTION ACTIVITIES
4.1. SHIFTING OF UTILITIES
Km.89.00 to 90.20
(0.00-1.20)
Hilly Section
Revenue Land /Private Land
Km 00.00 to Km 00.300
Land Handed over, however
compensation for trees
pending payment by ADC.
Km 00.300 to 1.20
Compensation for Land,
Structures & Trees pending
payments by ADC.
Km. 90.20 to 130 Hilly Section
Forest Land
Km 1.20-10.70
Land Handed Over. Forest
Diversion Cost Deposited.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 10
4.2. UTILIES SHIFTING & OTHER HINDRANCES
4.2.1. STATUS OF UTILITY SHIFTING
North Portal
S. No. List of Utilities Chainage Unit Total Status
1 OFC Pillar 129.100-129.500 & 129.500- 130.00 Nos. 11 Completed
2 Electrical Pole 129.100-129.500 & 129.500-130.00 Nos. 41 Completed
3 Transformer 129.100-129.500 Nos. 2 Completed
4 Hand Pump 129.500- 130.00 Nos. 2 Completed
5 Shops 129.500- 130.00 Nos. 6 Completed
South Portal
S. No. List of Utilities Chainage Unit Total Status
1 OFC Pillar 89.000-90.000 Nos. 8 Completed
2 Electrical Pole 89.050-90.00 Nos. 15 Completed
3 Transformer 89.950 Nos. 1 Completed
4 33KVA ELECTRICAL POLE at Km 89.500 Nos. 18 Completed
5 HT Tower 89.680 Nos. 1 Completed
6 440 VA line near Toll Plaza 89+850 Completed
7 Electrical Pole Line 89.600-90.000 Nos. 5 Completed
8 Water Line 89.900-90.000 Nos. 2 Completed
9 House 89.650-89.700, 89.900-90.000 Nos. 6 Completed
10 Shops 89.000-89.300,89.350- 89.400,89.950-90.000
Nos. 17 Completed
11 Religious Structure 89.100,89.400,89.800 Nos. 3 Completed
12 Telephone Pole 89.050-89.200,89.750- 89.900,89.950-90.000
Nos. 7 Completed
13 Hand Pump 89.100 Nos. 1 Completed
14 PMGSY/Public Path Nos. 1 Completed
15 House beyond Km 89.0 Nos. 1 Completed
15 Telephone Tower 89.100 Nos. 1 Completed
4.2.2. HINDRANCES
NIL
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 11
5. CONSTRUCTION SCHEDULE
5.1 CONSTRUCTION SHEDULE AS PER MILESTONE TARGETS.
Milestone Financial Percentage
Date of Achievement of Milestone as envisaged
in Concession Agreement
Remarks
Appointed Date (As per Agreement)
0% 23-05-11 Appointed Date of the Project
Project Milestone 1 10% 23-11-11 Achieved
Project Milestone 2 20% 23-05-12 Achieved
Project Milestone 3 30% 23-11-12 Achieved
Project Milestone 4 40% 23-05-13 Achieved
Project Milestone 5 50% 23-11-13 Achieved
Project Milestone 6 60% 23-05-14 Achieved
Project Milestone 7 70% 23-11-14 Achieved
Project Milestone 8 80% 23-05-15 Achieved
Project Milestone 9 90% 23-11-15 Achieved
Project Milestone 10 100% 23-05-16
5.2 INAUGURATION
Escape Tunnel (South Portal) First blast taken on 8th
August 2011
Main Tunnel (South Portal) First blast taken on 18th
August 2011
Escape Tunnel (North Portal) First blast taken on 8th
October 2011
Main Tunnel (North Portal) First blast taken on 22nd
October 2011
5.3 TUNNEL´S BREAK THROUGHS
Escape Tunnel 2nd
June 2014
Main Tunnel 13th July 2015
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 12
6. CONTRACTOR´S RESOURCES
Description Model
Quantity
Brought From South Portal
North Portal
Boomer Drill E2C with Protection Roof(ROPS) 02 01 IMPORTED-SWEDEN
Boomer Drill XE3C with Protection Roof(ROPS) 02 01 IMPORTED-SWEDEN
Shotcrete Machine Aliva 263/Aliva 265 01/01 00/00 LOCAL-INDIA
Shotcrete Machine Spraymec 7110 / Spraymec 8100 00/01 02/00 IMPORTED-FINLAND
Shotcrete Machine Aliva 264 01 00 LOCAL-INDIA
Concrete Spraying Machine SIKA PM 500PC 01 01 LOCAL-INDIA
Plat Form Ashok Leyland 01 00 LOCAL-INDIA
Wheel Loader 2021Z 01 01 LOCAL-INDIA
Wheel Loader 500 Mega with 4.8 Bucket 00 01 IMPORTED
Wheel Loader 980H 01 01 IMPORTED
Tunnel Trucks 05 05 IMPORTED-GERMANY
Rock Header / Cutting Machine TC-E Hydraulic (140 KW max) 02 00 IMPORTED-USA
Crane-Truck Mounted HB120E3M 01 01 LOCAL-INDIA
Fuel Bowser Tanker 12000 Ltr. / 8000 Ltr/ 950 Ltr. 00/01/01 01/01/00 LOCAL-INDIA
Transit Mixers 13 00 LOCAL-INDIA
Air Compressor 05 07 LOCAL-INDIA
Generator Set 11 10 LOCAL-INDIA
Concrete Static Pump SP 1400 with Leaf Spring & 100 Mtr 01 01 LOCAL-INDIA
Batching Plant 03 03 LOCAL-INDIA
Main Tunnel Form-Gantry 02 02 LOCAL-INDIA
Main Tunnel Membrane Carrier Platform
02 02 LOCAL-INDIA
Main Tunnel Layby Form 01 01 LOCAL-INDIA
Main Tunnel Layby Membrane Carrier Platform
01 01 LOCAL-INDIA
Escape Tunnel Form-Gantry 01 01 LOCAL-INDIA
Escape Tunnel Membrane Carrier Platform
02 02 LOCAL-INDIA
Cross Passages Form-Gantry 01 01 LOCAL-INDIA
Cross Passage-Membrane Carrier Platform
02 02 LOCAL-INDIA
Ventilation Slab Platform 03 03 LOCAL-INDIA
Ventilation Slab Carrier 01 01 LOCAL-INDIA
Partion Walls Form Work 01 01 LOCAL-INDIA
LV Separation Walls Form Work 01 01 LOCAL-INDIA
LV Niches Form 01 01 LOCAL-INDIA
Niches Single 01 01 LOCAL-INDIA
Niches-Double 02 02 LOCAL-INDIA
Collar Form-ET 01 01 LOCAL-INDIA
Collar Form-MT 01 01 LOCAL-INDIA
Side Wall Member Form-MT 01 01 LOCAL-INDIA
Side Wall Panel-MT 01 01 LOCAL-INDIA
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 13
7. MEETINGS /SITE VISITS / REVIEW OF DOCUMENTS
7.1 MEETINGS
Team Leader attending meeting at South Portal Conference Hall on dated: 13.07.2016.
Acting Team Leader attending meeting at DC Office Udhampur on dated: 17.07.2016
Team Leader attending meeting with PD NHAI at PD office Jammu on dated: 22.08.2016
Team Leader attending meeting at Mada Office Chenani on dated 27.08.2016.
7.2 SITE VISITS
Team Leader visit South and North Portal on dated: 08.06.2016.
Team Leader visit South and North Portal on dated: 15.06.2016.
Team Leader visit South Portal on dated: 24.06.2016.
Team Leader visit North Portal on dated: 28.06.2016.
Team Leader visit SAR, Toll Plaza & Main Tunnel South Portal on dated: 01.07.2016.
Team Leader visit SAR and Main Tunnel South Portal dated: 13.07.2016.
Acting Team Leader visit South Portal on dated: 23.07.2016.
Acting Team Leader visit South Portal on dated: 27.07.2016.
Team Leader visit SAR Land Slide dated: 06.08.2016
Team Leader visit SAR Land Slide and Main Tunnel South Portal on dated: 10.08.2016.
Team Leader visit MT, North Dumping Area and North Toll Plaza Hill on dated: 12.08.2016.
Team Leader visit to SAR Landslide at Chainage 0+925 on dated: 16.08.2016.
Team Leader visit Main Tunnel South, Surface Drain on dated: 27.08.2016.
Team Leader visit Main Tunnel South and North, North Dumping Area and North Approach
Road on dated: 31.08.2016.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 14
7.3 REVIEW OF DOCUMENTS / DRAWINGS:
Concessionaire has submitted documents regarding rock mass drainage for final lining shotcrete
alternate solution in cross passage, Reminder for not compliance HSE shortcomings inside tunnel,
Fire Fighting System, Change of Scope Notice of resurfacing of Existing Highway for Km 89 to Km
130, Material being used in sub grade, Site Visits, Review of Monthly Environmental Monitoring Report
for the month of April, May & June 2016, Running of Vehicular Traffic construction works over PQC in
Escape Tunnel, Traffic Aid, First Aid and Vehicular Rescue Post, Tunnel Works Drainage System,
MEP Site Visits, Status of NCR’s, Mix Design, Drain for Culverts North Portal, Technical Submission of
ITCS Documents, Technical Submission of Toll Collection System, Submission of weekly report on the
status of Plantation on regular basis, RFI of 132 KV Transmission Tower Line, Rock Mass Drainage
for Final Lining Shotcrete Alternate solution in Cross Passage, Slide of berms from slope protection at
SAR, Site Inspection Report Main Tunnel dated 02.08.2016, Third Party testing of PVC Membrane,
Data Sheets of Sealant, Precast Kerb Stone for Project Highway Median, Failure of Gradation of
GSB, Regarding Fee Notification, FFS Technical Submission of Fire Pumps, Culvert at Km 104 on
Existing Highway, Intimation of Issuance of Provisional Completion Certificate, Status of NCR-02, etc.
Most of these documents have been reviewed and sent back to the Concessionaire after reviewing.
Below it can be found the documents which have been reviewed.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 15
Letter Date Subject
S-CO-TE.TW-3543 01.06.2016 Regarding Rock Mass Drainage for Final Lining Shotcrete alternate solution in Cross Passage
S-CO-TE.SF-3544 01.06.2016 Reminder for not Compliance HSE shortcomings inside tunnel.
S-CO-TE.EM-3546 03.06.2016 Submission of Updated Material Procurement Schedule & Shop Drawings Schedule.
S-CO-TE.TW-3547 03.06.2016 Regarding submission of pending documents of provide final recommendation for CP’s Final Lining Shotcrete Solution.
S-CO-TE.EM-3548 03.06.2016 Fire Fighting System in Tunnel
S-CO-TE.EM-3552 06.06.2016 FFS: Technical Submission of Stainless Steel Expansion Bellows
S-CO-TE.RO-3553 07.06.2016 Change of Scope Notice of Resurfacing of Existing Highway from Km 89 to Km 130.
S-CO-TE.PP-3554 08.06.2016 Regarding review of Project Progress and program of Balance activities.
S-CO-TE.QL-3555 08.06.2016 Material being used in subgrade
S-CO-TE.QL-3556 08.06.2016 Use of unapproved PVC waterproofing material.
S-CO-TE.TW-3557 09.06.2016 Running of Vehicular Traffic for construction works over PQC in Escape Tunnel.
S-CO-TE.EM-3558 10.06.2016 Joint Site Visit on 08.06.2016, regarding MEP Works.
S-CO-TE.BG-3561 10.06.2016 Drains for Culverts North Portal.
S-CO-TE.TW-3562 10.06.2016 Site Visit Main Tunnel, 28.01.2016
S-CO-TE.EM-3563 13.06.2016 Joint MEP Site Visit on 11.06.2016
S-CO-TE.VT-3564 13.06.2016 Slope Protection at Switchyard, South Portal.
S-CO-TE.EM-3568 14.06.2016 FFS-Arrangement of linear expansion and lateral movement of the firefighting piping
S-CO-TE.SP-3570 16.06.2016
Confiscation proceedings regarding seizure of 3 no. Tippers & 4 no. JCB (excavator) Machines at Nashri and Peerah under section-26 of J&K Forest Act 1987 for violation of Section-6 of the Said act & section-5 of J&K Forest Conservation Act, 1997.
S-CO-TE.TW-3571 17.06.2016 Site Visit South Portal and North Portal, 15.06.2016
S-CO-TE.SF-3572 17.06.2016 Review of Monthly Environmental monitoring report for the month of April 2016.
S-CO-TE.EM-3573 17.06.2016 Technical Submission of Fire Pumps for Fire Fighting System.
S-CO-TE.EM-3574 17.06.2016 FFS: Arrangement of linear expansion and lateral movement of the firefighting piping.
S-CO-TE.TW-3575 17.06.2016 Running of Vehicular Traffic for construction works over PQC in Escape Tunnel.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 16
Letter Date Subject
S-CO-TE.BG-3578 18.06.2016 Traffic Aid, First Aid and Vehicular Rescue Post.
S-CO-TE.SF-3580 20.06.2016 Review of Monthly Environmental monitoring report for the month of May 2016.
S-CO-TE.EW-3581 20.06.2016 List of mitigation & preparedness activities in view of impeding Monsoon season, and completion of all the preventive works required in Premonsoon.
S-CO-TE.TW-3582 21.06.2016 WMS for road PQC/ Surface Drainage works in Main Tunnel and PQC Trial.
S-CO-TE.TW-3583 21.06.2016 Tunnel Works: Drainage System.
S-CO-TE.TW-3584 22.06.2016 Physical Thickness report of Shotcrete Main Tunnel (TM 2900-4500) & Escape Tunnel (TM 2880-4500)
S-CO-TE.RO-3585 22.06.2016 Change of Scope Order for resurfacing Existing Highway from KM 89 to KM 130.
S-CO-TE.QL-3586 22.06.2016 Dry Lean concrete Mix design with Ultratech OPC 53 Grade of Cement.
S-CO-TE.QL-3587 22.06.2016 PQC Mix Design (M40) with Ultratech OPC 53 Grade of
Cement.
S-CO-TE.SF-3589 22.06.2016 Directions under section-5 of Environment (Protection) Act,
1986.
S-CO-TE.QL-3590 22.06.2016 Material being used in Subgrade.
S-CO-TE.SP-3591 22.06.2016
Reminder for submission of Justificative design and Drawings
of slope protection at South Switchyard platforms (S and N
Portal)
S-CO-TE.EM-3592 22.06.2016 PSS-Approval of Fire Fighting Rated Isolaters.
S-CO-TE.EM-3593 23.06.2016 FFS-Arrangement of linear expansion and lateral movement of the firefighting piping.
S-CO-TE.EM-3594 23.06.2016 MEP Site Visit- I on 25.04.2016
S-CO-TE.EM-3595 23.06.2016 PSS-Approval of Fire Rated Isolators.
S-CO-TE.QL-3596 24.06.2016 Dry Lean Concrete Mix Design with Ambuja OPC 53 Grade of Cement.
S-CO-TE.OT-3597 24.06.2016 Status of NCR’s issued to the Concessionaire by IE.
S-CO-TE.TW-3599 25.06.2016 Site Inspection Report for Main Tunnel during visit on 24.06.2016
S-CO-TE.QL-3602 30.06.2016 Dry Lean Concrete (DLC) Mix Design with Ambuja OPC 53 Grade of Cement.
S-CO-TE.TW-3604 30.06.2016 Regarding Clearing/Clearance of Cross Drainage Structure Before Coming Monsoon Season 2016.
S-CO-TE.DR-3605 01.07.2016 Drains for Culverts North Portal.
S-CO-TE.EM-3609 02.07.2016 MEP works Joint Site Visit on 11.06.2016.
S-CO-TE.TW-3610 02.07.2016 Regarding Rock Mass Drainage for Final Lining Shotcrete Alternate Solution in Cross Passage.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 17
Letter Date Subject
S-CO-TE.EW-3611 02.07.2016 Inspection Report for Visit to North Dumping Yard selected location on 28.06.2016.
S-CO-TE.EM-3616 05.07.2016 RFI of 132 KV Transmission Tower Line.
S-CO-TE.TW-3618 05.07.2016 WMS for Road PQC-Surface Drainage works in Main Tunnel and PQC Trial.
S-CO-LE.TW-3619 05.07.2016 Regarding final recommendation for CP’s Final Lining Shotcrete Solution.
S-CO-TE.EM-3620 05.07.2016 Site Visit of MEP & Civil Related works on Dated 01.07.2016
S-CO-TE.TW-3621 06.07.2016 Tunnel works Drainage System.
S-CO-TE.EM-3622 06.07.2016 Technical Submission of ITCS Documents.
S-CO-TE.EM-3623 06.07.2016 Technical Submission of ITCS Documents.
S-CO-TE.EM-3624 06.07.2016 Technical Submission of ITCS Documents.
S-CO-TE.TW-3625 06.07.2016 Inspection Report for visit to North Portal MT on 28.06.2016 and South Portal on 01.07.2016
S-CO-TE.EM-3626 07.07.2016 Technical Submission of Toll Collection System.
S-CO-TE.VT-3628 07.07.2016 SOS Niche Issue during site visit on dated 04.07.2016
S-CO-TE.SF-3629 08.07.2016 Submission of weekly report on the status of plantation on regular basis.
S-CO-TE.TW-3630 08.07.2016 Site Inspection Report- Main Tunnel
S-CO-AD-MC-3631 08.07.2016 Intimation from IE regarding overtake of completion dated with project works finalized
S-CO-TE.TU-3632 09.07.2016 Submission of Cross Section Drawing of road alignment.
S-CO-TE.QL-3634 12.07.2016 Test Report of material used in the subgrade
S-CO-TE.QL-3635 12.07.2016 Test Report of material used in the subgrade from source Chenab River.
S-CO-TE.RO-3636 12.07.2016 Change of Scope Order for Resurfacing of Existing Highway from KM 89 to KM 130.
S-CO-TE.EM-3638 15.07.2016 MEP Works Joint site visit on 08.06.2016
S-CO-TE.TW-3639 15.07.2016 Site regarding Clearing / Clearance of Cross Drainage structures Before Coming Monsoon season 2016.
S-CO-TE.EM-3643 16.07.2016 MEP works joint site visit on 08.06.2016 (Supplement to our letter ref. S-CO-TE.EM-3638 Dated: 15.07.2016)
S-CO-TE.VT-3645 21.07.2016 Data Sheet for 33 KV CRP North Portals.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 18
Letter Date Subject
S-CO-TE.EM-3646 21.07.2016 MEP Works 10 KVA & 20 KVA UPS.
S-CO-TE.TU-3647 21.07.2016 Physical Thickness report of shotcrete for Main Tunnel & Escape Tunnel and CP’s at South Portal
S-CO-TE.RO-3648 21.07.2016 Reply of CTEO’s/CVO’s Para 5.2.2, 5.2.6, 8.8.3, 9.1.2 and 10.1 as Annexure Q.
S-COT-E.EM-3649 22.07.2016 FFS Technical submission of Stainless Steel Expansion Bellow.
S-PD-TE.OT-3650 22.07.2016 Regarding Final Recommendation for CP Final Lining Shotcrete Solution.
S-CO-TE.EM-3652 25.07.2016 FFS Drawing and calculation report for Air Vessel.
S-CO-TE.SF-3654 26.07.2016 Review of Monthly Environmental Monitoring report for the Month of June 2016.
S-CO-TE.VT-3657 28.07.2016 Regarding Augmentation of 132 / 33 Kv Grid Station Batote.
S-CO-TE.EM-3659 28.07.2016 MEP Works 10 KVA & 20 KVA UPS.
S-CO-TE.SF-3660 28.07.2016
Minutes of the District Road Safety Committee meeting held on 28.06.2016 under the chairmanship of Sh. Niraj Kumar, IAS Deputy Commissioner, Udhampur (Chairman District Road Safety Committee)
S-CO-TE.TU-3661 29.07.2016 Regarding Flushing pipes in Concrete Lining – Main & Escape Tunnel
S-CO-TE.EM-3662 29.07.2016 Submission of ACS, EFS and ECS Drawings.
S-CO-TE.TU-3665 01.08.2016 Tunnel Works Drainage System.
S-CO-TE.SF-3669 01.08.2016 Slide of berms from slope protection at SAR
S-CO-TE.TU-3671 03.08.2016 Site Inspection report -Main tunnel, dated 02.08.2016 .
S-CO-TE.QL-3672 04.08.2016 PQC Mix Design (M 40) with Ambuja OPC 53 Grade of Cement .
S-CO-TE.VT-3673 04.08.2016 Use of EOT Crane at Ventilation Building, North Portal.
S-CO-TE.EM-3674 04.08.2016 Technical Submission of ITCS Documents.
S-CO-LE.TU-3675 06.08.2016 Tunnel Works Drainage System.
S-CO-TE.QL-3679
08.08.2016
Third Party testing of PVC Membrane
S-CO-TE.QL-3680
08.08.2016
Data Sheets of Sealent.
S-CO-TE.QL-3682
10.08.2016
Intensive Examination Conducted by CTEO (PARA 12.1 to 12.4).
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 19
Letter Date Subject
S-CO-TE.BG-3683 11.08.2016 Culvert at Km 104 on Existing Highway.
S-CO-TE.RW-3684 11.08.2016 Precast Kerb Stone for Project Highway median.
S-CO-TE.DR-3685 11.08.2016 Drain for Culverts North Portal.
S-CO-TE.EM-3687 13.08.2016 Accuracy of Measuring devices of Batching Plant.
S-CO-TE.VT-3690 13.08.2016 Failure of Gradation of GSB.
S-CO-FI.TP-3692 13.08.2016 Regarding Fee Notification.
S-CO-TE.SP-3693 16.08.2016 Slide of Berms from Slope protection at SAR.
S-CO-TE-TU-3696 16.08.2016 Tunnel Drainage Construction Methodology.
S-CO-TE.EM-3698
17.08.2016 FFS Technical Submission of Fire Pumps.
S-CO-TE.TW-3699
17.08.2016 Site Inspection on 12-08-2016 to Main Tunnel and Cross Passages, North Toll Plaza and Dumping Yard.
S-CO-TE.NCR-3700
17.08.2016
NCR regarding blockade of transverse PVC pipe outlet (right side) in Manhole P1- Main Tunnel and manhole P2 in CP and ET junction.
S-CO-TE.EM-3703 19.08.2016 Fire Fighting System Notes & Legends
S-CO-TE.EM-3704 19.08.2016 MEP Works Fire Fighting System Drawings
S-CO-TE.EM.3705 19.08.2016 ITCS-Speed Limit Variable message signs (SLVS)
S-CO-TE.QL-3706 23.08.2016 Intensive Examination conducted by CTEO (Para 12.1 to 12.4)
S-CO-TE.NCR-3709
23.08.2016
NCR regarding placing of PQC in 925mm wide edge (left side) not as per approved design in Main Tunnel. .
S-CO-TE.PC-3710 24.08.2016 Intimation for Issuance of Provisional Completion Certificate.
S-CO-TE.EM-3712 26.08.2016 Pending Compliances/Replies of our letters for MEP works.
S-CO-TE.QL-3714 29.08.216 Failure of Gradation of GSB.
S-CO-TE.TU-3715 29.08.2016 Site Inspection Report-South Portal (Night Shift), dated 26-08-2016.
S-CO-TE.VT-3719 29.08.2016 Site Inspection Report regarding surface finishing of Ventilation building at South Portal. .
S-CO-TE.TU-3721 30.08.2016 Status of NCR-02 (Regarding).
S-CO-TE.RO-3724 31.08.2016 Status of maintenance of existing road from km 89 to km 130.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 20
8. INVOICES PAYMENT & REIMBURSEMENT
Invoice for the month of June 2016 has been submitted to Project Director NHAI (PIU Jammu) on
01.07.2016.
Invoice for the month of July 2016 has been submitted to Project Director NHAI (PIU Jammu) on 01.08.2016.
Invoice for the month of August 2016 has been submitted to Project Director NHAI (PIU Jammu) on
01.09.2016
9. EXECUTING AGENCIES AND CONTRACT DATA
9.1 AGENCIES
9.1.1 Developer:
M/s IL & FS Transportation Networks Ltd is the Developer.
9.1.2 Concessionaire:
They have created SPV in the name of M/s CNTL for this Project. CNTL is the Concessionaire
for this project; they have mobilized staff and established its office C/o Lower Mada Village
Gujjard Tehsil Chenani Distt. Udhampur. M/s CNTL is represented by Mr. J.S. Rathore Project
Director.
9.1.3 EPC Contractor:
M/s ITNL has demobilized M/s Leighton and Project highway and tunnel activities is divided into
three section and contractor has deployed the separate construction for following sections.
Section 1: Excavation Works From North Portal-M/s AIMPL-BCC(JV).
Excavation Works From South Portal-M/s Nagyan Construction.
Section 2: Lining Works South Portal: M/s New India Infra Build tech Pvt. Ltd.
Lining Works North Portal: M/s Savronik- BCC (JV).
Section 3 Surface Works:
M/s Vinay Construction
M/s Chudhary Construction
M/s Kamlashi Construction.
9.2 CONTRACT DATA
9.2.1 PROJECT COST Project Cost (As per Concession Agreement) – Rs. 2519 Crore.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 21
9.2.2 CIVIL WORKS CONTRACT DETAILS
a) Concessionaire Chenani Nashri Tunnel way Ltd.
b) Contract Section Chenani to Nashri Section of NH 1A From Km. 89.00 to 130.00
c) Contract Length 10.800 Km
d) Agreement /MOU Date 28th July 2010
e) Agreement Amount Rs. 2519 Crs.
f) Commencement Date 23rd
May 2011
g) Intended date of Completion 20th May 2016
h) Performance Security Released
i) Mobilization Advance and Date of payment (s) Nil
j) Equipment Advance and Date of Payment (s) Nil
k) Net Material Advance Nil
l) Retention Money upto date Nil
m) Liquidated damages, if any -
n) Defect Liability Period Nil
9.2.3 SCOPE OF WORK
Main Tunnel: 9.00 km (As per CA)
Escape Tunnel: 9.00 Km
Cross Passage: 29 nos.
Rigid Pavement: 18.000 km (including Main Tunnel, Escape Tunnel and Bridges)
Flexible Pavement: 1.800 km (four lane)
Rotary Junction: 02 Nos.
Minor Bridge: 02 nos.
Culvert: 07 Nos. Box Culvert
Toll Plaza: 02 Nos.
Drainage pipe in Main Tunnel: 9.0 km (3 nos.)
Drainage pipe in Escape Tunnel: 9.0 km (2 nos.)
Drainage pipe in Cross passages: 29 Nos. (On both the ends)
Slope Protection works at Valley Side: 1520 m
Slope Protection works at Hill Side: 1750 m
Lay bays: 14 nos.
Firefighting Niches: 58 nos.
Vehicular emergency exit: 07 nos.
Ventilation Building: 02 nos.
Tunnel Control Centre (Building): 02 nos
Traffic, Medical Aid Post: (01 No. Per Side)
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 22
10. WEATHER REPORT
WEATHER REPORT FOR THE MONTH OF JUNE 2016
Max.
Temp.
(°C)
Min.
Temp.
(°C)
Max.
Humidity
(%)
Min.
Humidity
(%)
Rainfall
Max.
Temp.
(°C)
Min.
Temp.
(°C)
Max.
Humidity
(%)
Min.
Humidity
(%)
Rainfall
1 1/6/2016 24.2 21.6 72.0 45.0 NIL 36.0 15.2 71.0 35.0 NIL
2 2/6/2016 24.8 22.4 75.0 47.0 NIL 37.1 15.6 74.0 37.0 NIL
3 3/6/2016 25.6 23.2 70.0 41.0 NIL 36.9 15.7 76.0 32.0 NIL
4 4/6/2016 24.8 23.6 77.0 45.0 NIL 36.4 15.9 75.0 30.0 NIL
5 5/6/2016 22.4 20.8 72.0 43.0 NIL 37.1 15.1 79.0 35.0 NIL
6 6/6/2016 24.0 22.4 75.0 45.0 NIL 37.4 14.8 75.0 36.0 NIL
7 7/6/2016 26.1 24.2 78.0 48.0 NIL 35.8 15.6 68.0 35.0 NIL
8 8/6/2016 23.1 21.0 73.0 41.0 1.4 35.1 15.9 77.0 32.0 NIL
9 9/6/2016 24.0 22.0 76.0 46.0 NIL 36.4 16.2 79.0 50.0 NIL
10 10/6/2016 23.6 21.2 73.0 41.0 NIL 37.1 16.1 70.0 39.0 NIL
11 11/6/2016 24.4 23.0 78.0 46.0 NIL 37.4 15.8 79.0 44.0 NIL
12 12/6/2016 26.4 24.0 77.0 48.0 NIL 35.5 15.0 84.0 48.0 NIL
13 13/6/2016 24.0 23.6 74.0 45.0 NIL 36.7 14.8 79.0 39.0 19
14 14/6/2016 24.6 23.8 77.0 47.0 NIL 35.8 14.2 76.0 39.0 NIL
15 15/6/2016 23.8 22.8 74.0 41.0 NIL 36.3 15.4 77.0 36.0 NIL
16 16/6/2016 24.4 23.6 76.0 45.0 NIL 36.9 15.8 75.0 38.0 NIL
17 17/6/2016 23.8 22.0 73.0 41.0 NIL 36.5 15.6 77.0 37.0 NIL
18 18/6/2016 26.4 24.6 79.0 46.0 NIL 35.5 14.7 89.0 39.0 16
19 19/6/2016 25.4 23.8 81.0 48.0 NIL 36.4 15.2 78.0 36.0 NIL
20 20/6/2016 24.0 22.6 79.0 45.0 NIL 35.6 14.5 84.0 39.0 36
21 21/6/2016 20.0 18.6 75.0 41.0 3.5 35.8 14.6 82.0 40.0 18
22 22/6/2016 21.8 18.4 73.0 40.0 NIL 35.2 14.4 80.0 39.0 10
23 23/6/2016 23.2 17.8 75.0 43.0 2.4 36.4 15.3 76.0 37.0 NIL
24 24/6/2016 24.6 20.2 78.0 44.0 NIL 35.2 14.5 80.0 39.0 10
25 25/6/2016 27.6 23.4 80.0 42.0 NIL 36.4 15.4 76.0 37.0 NIL
26 26/6/2016 26.1 22.4 75.0 43.0 NIL 35.2 15.3 75.0 38.0 NIL
27 27/6/2016 26.8 23.1 78.0 45.0 NIL 35.6 15.2 78.0 39.0 NIL
28 28/6/2016 24.2 18.6 73.0 41.0 NIL 36.0 14.9 75.0 38.0 NIL
29 29/6/2016 23.6 17.8 75.0 43.0 NIL 35.8 15.1 77.0 37.0 NIL
30 30/6/2016 24.6 18.8 78.0 45.0 NIL 36.2 15.0 79.0 35.0 NIL
North Portal South Portal
DateSr.
No.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 23
WEATHER REPORT FOR THE MONTH OF JULY 2016
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 24
WEATHER REPORT FOR THE MONTH OF AUGUST 2016
Max.
Temp.
(°C)
Min.
Temp.
(°C)
Max.
Humidity
(%)
Min.
Humidity
(%)
Rainfall
Max.
Temp.
(°C)
Min.
Temp.
(°C)
Max.
Humidity
(%)
Min.
Humidity
(%)
Rainfall
1 1/8/2016 36.8 21.4 88.0 40.0 0 28.5 20.8 78.0 43.0 0
2 2/8/2016 36.9 20.6 83.0 39.0 18 28.7 21.5 79.0 45.0 0
3 3/8/2016 34.6 23.4 80.0 38.0 10 29.3 20.7 78.0 42.0 0
4 4/8/2016 37.1 24.0 82.0 40.0 0 28.9 22.6 80.0 41.0 0
5 5/8/2016 37.6 21.9 89.0 41.0 0 29.9 22.7 78.0 43.0 0
6 6/8/2016 35.5 20.4 88.0 44.0 8 27.5 22.1 75.0 42.0 66.8
7 7/8/2016 33.6 19.8 93.0 38.0 6 18.8 15.4 68.0 35.0 38.6
8 8/8/2016 32.4 22.0 86.0 37.0 88 23.5 20.3 56.0 40.0 0
9 9/8/2016 35.8 23.1 85.0 42.0 0 24.8 19.7 86.0 48.0 0
10 10/8/2016 35.9 22.8 92.0 41.0 0 23.9 20.2 99.0 88.0 3.92
11 11/8/2016 34.7 23.7 88.0 43.0 52 27.1 22.9 88.0 86.0 0.2
12 12/8/2016 35.1 23.9 87.0 42.0 8 32.6 21.3 88.0 53.0 0.2
13 13/8/2016 36.4 22.9 85.0 39.0 3 33.7 21.2 96.0 64.0 0
14 14/8/2016 35.2 23.8 81.0 40.0 0 34.2 21.7 97.0 43.0 0
15 15/8/2016 36.2 24 82.0 38.0 0 34.6 22.3 96.0 43.0 0
16 16/8/2016 36.3 23.8 80.0 37.0 0 34.3 22.1 92.0 43.0 0
17 17/8/2016 36.5 24.5 81.0 39.0 0 33.7 22.4 97.0 41.0 0
18 18/8/2016 37.4 26.2 83.0 38.0 0 31.6 22.1 92.0 51.0 0
19 19/8/2016 34.7 25.8 82.0 39.0 0 31.7 22.5 94.0 46.0 0
20 20/8/2016 35.8 26.5 85.0 42.0 0 30.6 21.1 87.0 43.0 0
21 21/8/2016 34.5 21.8 89.0 40.0 0 30.8 21.3 96.0 62.0 0
22 22/8/2016 32.5 25.4 88.0 41.0 6 29.8 20.9 91.0 56.0 0
23 23/8/2016 34.4 25.5 87.0 40.0 4 30.6 20.6 95.0 52.0 0
24 24/8/2016 35.2 24.7 89.0 41.0 4 24.7 20.4 99.0 71.0 8.8
25 25/8/2016 35.4 21.8 89.0 40.0 0 29.6 20.1 86.0 57.0 0
26 26/8/2016 32.5 21.0 84.0 43.0 0 29.8 19.9 92.0 62.0 0
27 27/8/2016 30.6 21.3 83.0 42.0 0 24.6 19.7 97.0 56.0 5.4
28 28/8/2016 31.5 22.0 86.0 41.0 0 29.7 19.9 87.0 53.0 0
29 29/8/2016 31.7 21.9 82.0 46.0 5 29.6 20.1 91.0 57.0 5.6
30 30/8/2016 31.5 21.5 80.0 45.0 4 30.5 20.3 92.0 61.0 3.6
31 31/8/2016 31 21.6 86.0 42.0 7 29.5 20.2 81.0 65.0 9.8
South Portal North Portal
DateSr.
No.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Page 25
11. PROGRESS OF THE PROJECT
11.1 ESTIMATION OF PHYSICAL PROGRESS IN GLOBALITY
Physical Progress has not to be taken as reference for financial progress, because it does not
include cost incurred (i) Construction of Labour camps, Batching plants and Labs (ii)
Procurement of machinery and advanced materials for construction.
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 26
11.2 Tunnel works monitoring
SOUTH PORTAL
Tunnel Excavation in Mtrs.
S.No. Location
Tunnel Meter Cumulative
Remarks
Initial Final Targets* Achieved % age
Progress
1 MT (Heading) 4403.5 4403.50 4403.50 4403.50 100.00 Completed
2 MT (Benching) 4403.0 4403.0 4403.00 4403.00 100.00 Completed
3 ET 4573.0 4573.00 4573.00 4573.00 100.00 Completed
4 Cross Passage 459.1 459.10 459.10 459.10 100.00 14 No’s completed
Final Lining:
Qtr
June-Aug
16
Qtr
June-Aug
16
Qtr
June-Aug
16
Target Achieved%
ProgressMTs Target Achieved % Progress MTs Target Achieved
%
ProgressMTs Target Achieved % Progress
1 MT 4506.00 4506.00 100 149.5 4773.50 4773.50 100.00 976.5 4800.00 4728.5 98.51 2000.5 4800.00 4475.50 93.24
2 ET 4573.00 4573.00 100 185 4485.00 4485.00 100.00
3 CP 459.05 459.05 100 32.25 459.05 425.75 92.75
Partion wall
Cumulative Cumulative CumulativeSno. Location
Ground Beam (M)
Cum
Final Linnig Ventilation slab
Tunnel Road Works:
TotalAchieved
% Progress Total Achieved % Progress
1 MT M 4479.00 1339.00 29.90 4479.00 0.00 0.00
2 ET M 4481.00 4050.00 90.38 4466.00 3747.00 83.90
3 CP Nos 15.00 10.00 66.67 15.00 10.00 66.67
Unit
Progress PCC/ DLC (cum) Progress PQC (cum)
Sno. Location
Tunnel Drainage Works
TotalAchieved
% Progress Total Achieved % Progress
1 MT M 4479.00 2400.00 53.58 4479.00 3900.00 87.07
Unit
Progress Surface Drain (cum) Progress Main Drain Collector (cum)
Sno. Location
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 27
NORTH PORTAL
Tunnel Excavation in Mtrs.
S.No Location
Tunnel Meter Cumulative Remarks
Initial Final Targets Achieved % age
Progress
1 MT (Heading) 4576.5 4576.5 4576.5 4576.5 100.0 Completed
2 MT
(Benching) 4576.0 4576.5 4576.5 4576.5 100.0 Completed
3 ET 4393.0 4393.0 4593.0 4593.0 100.0 Completed
4 Cross
Passage 486.40 486.4 486.4 486.40 100.0 15 No’s completed
Final Lining:
Qtr
June-Aug
16
Qtr
June-Aug
16
Qtr
June-Aug
16
Target Achieved%
ProgressMTs Target Achieved % Progress MTs Target Achieved
%
ProgressMTs Target Achieved % Progress
1 MT 4473.00 4473.00 100 162.8 4205.50 4205.50 100.00 1332 4179.00 4149 99.28 1523.5 4179.00 3761.00 90.00
2 ET 4393.00 4393.00 100 410 4481.00 4481.00 100.00
3 CP 486.33 486.33 100 211.9 486.33 471.33 96.92
Cumulative
Partion wall
Sno. Location
Ground Beam (M)
Cum
Final Linnig
Cumulative
Ventilation slab
Cumulative
Tunnel Road Works:
TotalAchieved
% Progress Total Achieved % Progress
1 MT M 4479.00 1339.00 29.90 4479.00 0.00 0.00
2 ET M 4481.00 4050.00 90.38 4466.00 3747.00 83.90
3 CP Nos 15.00 10.00 66.67 15.00 10.00 66.67
Unit
Progress PCC/ DLC (cum) Progress PQC (cum)
Sno. Location
Tunnel Drainage Works:
TotalAchieved
% Progress Total Achieved % Progress
1 MT M 4479.00 2400.00 53.58 4479.00 3900.00 87.07
Unit
Progress Surface Drain (cum) Progress Main Drain Collector (cum)
Sno. Location
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 28
11.3 PHYSICAL PROGRESS CHARTS
Main Tunnel
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 29
Escape Tunnel
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 30
Cross Passages
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 31
STRIP CHART
SOUTH PORTAL
PQC
DLC
GSB
Sub-Grade
Earthwork
-Other Hindrances
-Clearance Pending
-LA Pending
Workfront Available
Chainage (0+……) 14
0
20
0
25
0
30
0
35
0
40
0
45
0
50
0
55
0
60
0
65
0
70
0
75
0
80
0
85
0
90
0
95
0
10
00
10
50
11
00
11
50
12
00
12
50
13
00
13
50
14
00
14
82
workfront Available
Workfront Available
-LA Pending workfront Unavailable
-Clearance Pending
-Other Hindrances
Earthwork
Sub-Grade
GSB
DLC
PQC
Number of Structures SB
Type of Stuctures NB
Number of Structures NB
Status of Structures
LHS
-MC
W
Co
stru
ctio
n
(No
rth
Bo
un
d)
LHS
-MC
W
Wo
rkfr
on
t
(No
rth
Bo
un
d)
Type of Stuctures SB
Status of Structures
Bypass
RH
S-M
CW
Wo
rkfr
on
t
(So
uth
Bo
un
d)
RH
S-M
CW
Wo
rkfr
on
t
(So
uth
Bo
un
d)
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 32
MAIN TUNNEL
PQC
DLC
GSB
Sub-Grade
Earthwork
-Other Hindrances
-Clearance Pending
-LA Pending
Workfront Available
Chainage (0+……)
1482
1782
2082
2382
2682
2982
3582
3882
4182
4482
4782
5082
5382
5682
5982
6282
6582
6882
7182
7482
7782
8082
8382
8682
8982
9282
9582
9882
1018
2
1048
2
Number of Structures NB
Status of Structures
LHS-
MCW
Cost
ruct
ion
(Nor
th B
ound
)
LHS-
MCW
Wor
kfro
nt
(Nor
th
Boun
d)
3282
Type of Stuctures NB
ESCAPE TUNNEL
PQC
DLC/PCC
GSB
-Other Hindrances
-Clearance Pending
-LA Pending
Workfront Available
Chainage (0+……)
1482
1782
2082
2382
2682
2982
3582
3882
4182
4482
4782
5082
5382
5682
5982
6282
6582
6882
7182
7482
7782
8082
8382
8682
9282
9582
9882
1018
2
1048
2
8982
Type of Stuctures NB
Number of Structures NB
Status of Structures
LHS-
MCW
Cost
ruct
io
n
(Nor
th
Bou
nd)
3282
LHS-
MCW
Wor
kfro
nt
(Nor
th
Bou
nd)
CROSS PASSAGE
PQC
DLC/PCC
Cross Passage Nos. CP-01 CP-02 CP-03 CP-04 CP-05 CP-06 CP-07 CP-08 CP-09 CP-10 CP-11 CP-12 CP-13 CP-14 CP-15 CP-16 CP-17 CP-18 CP-19 CP-20 CP-21 CP-22 CP-23 CP-24 CP-25 CP-26 CP-27 CP-28 CP-29
LH
S-M
CW
Co
str
ucti
on
(No
rth
Bo
un
d)
Number of Structures NB
Status of Structures
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 33
NORTH PORTAL
PQC
DLC
GSB
Sub-Grade
Earthwork
-Other Hindrances
-Clearance Pending
-LA Pending
Workfront Available
Chainage (0+……)
10
48
2
10
53
2
10
58
2
10
63
2
10
68
2
10
73
2
10
78
2
10
83
2
10
88
2
10
93
2
10
98
2
11
03
2
workfront Available
Workfront Available
-LA Pending workfront Unavailable
-Clearance Pending
-Other Hindrances
Earthwork
Sub-Grade
GSB
DLC
PQC
Type of Stuctures SB
Type of Stuctures NB
Number of Structures SB
RH
S-M
CW
Wo
rkfr
on
t
(So
uth
Bo
un
d)
LHS-
MC
W
Wo
rkfr
on
t
(So
uth
Bo
un
d)
Bypass
Status of Structures
Number of Structures NB
Status of Structures
LHS-
MC
W
Co
stru
ctio
n
(No
rth
Bo
un
d)
LHS-
MC
W
Wo
rkfr
on
t
(No
rth
Bo
un
d)
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 34
12. QUALITY CONTROL AND TESTING OF MATERIALS.
12.1 UP TO DATE STATUS OF THE TESTS.
Total no.
of Tests
Required
No. of
Tests
Performed
No. of
Tests
Passed
No. of
Tests
Failed
Total no.
of Tests
Required
No. of
Tests
Passed
No. of
Tests
Failed
Action taken in case of
Failied Tests./Remarks
1
a 16 155 155 0 914 7648 34
b 8 21 21 0 472 961 0
c 8 17 17 0 478 677 0
d 0 0 0 0 13 13 0
e 120 240 240 0 7147 9963 0
g 4 8 8 0 236 449 0
h 4 8 8 0 249 469 0
2
a 16 88 88 0 1067 3372 68
b 120 240 240 0 7917 11755 0
c 0 0 0 0 10 10 0
3
a 4 4 4 0 169 169 0
b 4 4 4 0 169 169 0
c 4 4 4 0 169 169 0
d 4 4 4 0 169 169 0
4
a 9 9 9 0 477 477 0
b 9 9 9 0 483 483 0
c 3 3 3 0 489 489 0
5
0 0 0 0 2582 2582 0
6
07 Days 93 93 93 0 1644 1644 0
28 Days 129 129 129 0 4179 4179 0
b M10 DLC 07 Days 354 354 354 0 714 714 0
07 Days 126 126 126 0 7461 7461 0
28 Days 195 195 195 0 18150 18150 0
07 Days 3 3 3 0 327 327 0
28 Days 0 0 0 0 354 354 0
07 Days 0 0 0 0 87 87 0
28 Days 0 0 0 0 345 345 0
07 Days 393 393 393 0 14370 14370 0
28 Days 1479 1479 1479 0 60621 60621 0
07 Days 645 645 645 0 7593 7593 0
28 Days 792 792 792 0 13245 13245 0
07 Days 0 0 0 0 183 183 0
28 Days 0 0 0 0 1123 1123 0
07 Days 150 150 150 0 660 660 0
28 Days 162 162 162 0 570 570 0
07 Days Flexural
Strength150 150 150 0 660 660 0
28 Days Flexural
Strength162 162 162 0 570 570 0
07 Days 0 0 0 0 45 45 0
28 Days 0 0 0 0 111 111 0
7
3 3 3 0 5411 5411 0
M45
17.0 Up to Date Status of the Tests Up to August 2016
S.
No
For the month August 2016 Cumulative upto August 2016
Soundness
Specific gravity
Gradation
FI + EI
Moisture Content
Gradation
AIV
Log Angles
Crushing value
Fine Aggregate
M25
Cement Ambuja 53 Grade
Pullout Test for Rock Bolts at
North/South Portals
M15
Insitu Cores Compressive
Strengthat North/South
Portals
Insitu Cores Compressive Strength Test
a
h M40
f
k
c
M40 PQC
CUBE
UPTO DATE STATUS
Name of the Tests
Shortcrete / Concrete / Course Aggregate
IST & FST
Concrete Cube's Compressive Strength Test
07 days
Pullout Testing
28 days
Cement Cube Strength
Consistency
Moisture content
Specific Gravity
M10
M30
03 days
Fineness
M20
i
M40 PQC
BEAMj
M35
d
g
e
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 35
12.2 TEST RESULT OF CONCRETE CORES AND CUBES.
FOR THE MONTH OF JUNE 2016
DETAILS OF WSC CORES (M25) TESTED IN THE MONTH OF JUNE 2016.
SOUTH PORTAL
DATE
INSITU CORES PANEL CASTED
Remarks Pass Fail 1 days 7 days 28 days
01.06.2016 00 00 05 00 00
02.06.2016 00 00 05 00 00
03.06.2016 00 00 00 00 00
04.06.2016 00 00 00 00 00
05.06.2016 00 00 05 00 00
06.06.2016 00 00 00 00 00
07.06.2016 00 00 00 05 00
08.06.2016 00 00 00 05 00
09.06.2016 00 00 00 00 00
10.06.2016 00 00 00 00 00
11.06.2016 00 00 00 05 00
12.06.2016 00 00 00 00 00
13.06.2016 00 00 05 00 05
14.06.2016 00 00 00 00 00
15.06.2016 00 00 00 00 00
16.06.2016 00 00 00 00 00
17.06.2016 00 00 05 00 00
18.06.2016 00 00 00 00 00
19.06.2016 00 00 00 05 00
20.06.2016 00 00 00 00 00
21.06.2016 00 00 00 00 00
22.06.2016 00 00 00 00 00
23.06.2016 00 00 00 05 00
24.06.2016 00 00 05 00 00
25.06.2016 00 00 00 00 00
26.06.2016 00 00 00 00 00
27.06.2016 00 00 00 00 00
28.06.2016 00 00 00 00 05
29.06.2016 00 00 00 00 00
30.06.2016 00 00 00 05 00
Total 00 00 30 30 10
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 36
DETAILS OF WSC CORES (M25) TESTED IN THE MONTH OF JUNE 2016.
NORTH PORTAL
DATE
INSITU CORES PANEL CASTED
Remarks
Pass Fail 1 days 7 days 28 days
01.06.2016 00 00 00 00 00
02.06.2016 00 00 00 00 00
03.06.2016 00 00 00 00 00
04.06.2016 00 00 00 00 00
05.06.2016 00 00 00 00 00
06.06.2016 00 00 00 00 00
07.06.2016 00 00 00 00 00
08.06.2016 00 00 00 00 00
09.06.2016 00 00 00 00 00
10.06.2016 00 00 00 00 00
11.06.2016 00 00 00 00 00
12.06.2016 00 00 00 00 00
13.06.2016 00 00 00 00 00
14.06.2016 00 00 00 00 00
15.06.2016 00 00 00 00 00
16.06.2016 00 00 00 00 00
17.06.2016 00 00 00 00 00
18.06.2016 00 00 00 00 00
19.06.2016 00 00 00 00 00
20.06.2016 00 00 00 00 00
21.06.2016 00 00 00 00 00
22.06.2016 00 00 00 00 00
23.06.2016 00 00 00 00 00
24.06.2016 00 00 00 00 00
25.06.2016 00 00 00 00 00
26.06.2016 00 00 00 00 00
27.06.2016 00 00 00 00 00
28.06.2016 00 00 00 00 00
29.06.2016 00 00 00 00 00
30.06.2016 00 00 00 00 00
Total 00 00 00 00 00
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 37
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
SOUTH PORTAL
DATE Grout Cube Testing
Remarks
3 days 7 days 28 days
01.06.2016 00 05 00
02.06.2016 00 05 00
03.06.2016 00 05 05
04.06.2016 00 05 05
05.06.2016 00 05 00
06.06.2016 00 05 05
07.06.2016 00 05 05
08.06.2016 00 05 05
09.06.2016 00 05 05
10.06.2016 00 05 05
11.06.2016 00 05 00
12.06.2016 00 05 00
13.06.2016 00 05 00
14.06.2016 00 05 05
15.06.2016 00 05 05
16.06.2016 00 05 05
17.06.2016 00 05 05
18.06.2016 00 05 05
19.06.2016 00 05 05
20.06.2016 00 05 05
21.06.2016 00 05 00
22.06.2016 00 05 05
23.06.2016 00 00 05
24.06.2016 00 05 05
25.06.2016 00 05 05
26.06.2016 00 05 05
27.06.2016 00 00 05
28.06.2016 00 00 05
29.06.2016 00 00 05
30.06.2016 00 00 05
Total 00 125 115
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 38
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
NORTH PORTAL
DATE Grout Cube Testing
Remarks
3 days 7 days 28 days
01.06.2016 00 00 05
02.06.2016 00 00 00
03.06.2016 00 00 05
04.06.2016 00 00 05
05.06.2016 00 00 00
06.06.2016 00 00 00
07.06.2016 00 00 00
08.06.2016 00 00 00
09.06.2016 00 00 00
10.06.2016 00 00 00
11.06.2016 00 00 00
12.06.2016 00 00 05
13.06.2016 00 00 00
14.06.2016 00 00 00
15.06.2016 00 00 00
16.06.2016 00 00 00
17.06.2016 00 00 00
18.06.2016 00 00 00
19.06.2016 00 00 00
20.06.2016 00 00 00
21.06.2016 00 00 00
22.06.2016 00 00 00
23.06.2016 00 00 00
24.06.2016 00 00 00
25.06.2016 00 00 00
26.06.2016 00 00 00
27.06.2016 00 00 00
28.06.2016 00 00 00
29.06.2016 00 00 00
30.06.2016 00 00 00
Total 00 00 20
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 39
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
SOUTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M10 M10 DLC M15 M20 M25 M30
Remark 7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.06.2016 03 00 00 00 03 06 00 00 00 00 21 24
02.06.2016 00 00 09 00 03 09 00 00 00 00 03 51
03.06.2016 00 00 09 00 09 15 00 03 00 00 15 72
04.06.2016 00 00 00 00 09 00 00 03 00 00 12 69
05.06.2016 00 00 09 00 03 03 00 00 00 00 09 27
06.06.2016 03 00 00 00 00 03 00 03 00 00 18 66
07.06.2016 03 00 00 00 03 06 00 06 00 00 12 48
08.06.2016 00 00 00 00 06 00 00 03 00 00 06 39
09.06.2016 00 15 00 00 00 00 00 03 00 00 15 48
10.06.2016 00 06 09 00 00 09 00 03 00 00 03 21
11.06.2016 03 00 00 00 03 03 00 03 00 00 09 12
12.06.2016 00 00 00 00 03 00 00 03 00 00 06 48
13.06.2016 03 00 00 00 00 09 00 03 00 00 06 12
14.06.2016 00 00 00 00 00 00 00 03 00 00 15 72
15.06.2016 03 15 00 00 03 00 00 03 00 00 09 78
16.06.2016 03 09 09 00 03 15 00 03 00 00 06 39
17.06.2016 03 00 00 00 06 18 00 03 00 00 21 75
18.06.2016 03 00 18 00 00 15 00 03 00 00 06 45
19.06.2016 00 00 00 00 03 06 00 03 00 00 12 33
20.06.2016 03 00 00 00 03 00 00 03 00 00 00 69
21.06.2016 03 15 09 00 03 00 00 03 00 00 12 36
22.06.2016 03 06 00 00 03 06 00 00 00 00 03 99
23.06.2016 03 00 00 00 03 03 00 00 00 00 12 06
24.06.2016 03 00 09 00 06 15 00 00 00 00 09 90
25.06.2016 06 00 00 00 06 24 00 00 00 00 12 69
26.06.2016 03 00 00 00 03 09 00 00 00 00 12 60
27.06.2016 03 06 00 00 00 00 03 00 00 00 06 72
28.06.2016 00 03 09 00 00 15 00 00 00 00 12 66
29.06.2016 00 00 00 00 03 12 00 00 00 00 12 54
30.06.2016 03 00 00 00 03 00 00 00 00 00 09 69
Total 57 75 90 00 90 201 03 57 00 00 303 1569
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 40
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
SOUTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M10 M10 DLC M15 M20 M25 M30
Remark 7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.06.2016 03 00 00 00 03 06 00 00 00 00 21 24
02.06.2016 00 00 09 00 03 09 00 00 00 00 03 51
03.06.2016 00 00 09 00 09 15 00 03 00 00 15 72
04.06.2016 00 00 00 00 09 00 00 03 00 00 12 69
05.06.2016 00 00 09 00 03 03 00 00 00 00 09 27
06.06.2016 03 00 00 00 00 03 00 03 00 00 18 66
07.06.2016 03 00 00 00 03 06 00 06 00 00 12 48
08.06.2016 00 00 00 00 06 00 00 03 00 00 06 39
09.06.2016 00 15 00 00 00 00 00 03 00 00 15 48
10.06.2016 00 06 09 00 00 09 00 03 00 00 03 21
11.06.2016 03 00 00 00 03 03 00 03 00 00 09 12
12.06.2016 00 00 00 00 03 00 00 03 00 00 06 48
13.06.2016 03 00 00 00 00 09 00 03 00 00 06 12
14.06.2016 00 00 00 00 00 00 00 03 00 00 15 72
15.06.2016 03 15 00 00 03 00 00 03 00 00 09 78
16.06.2016 03 09 09 00 03 15 00 03 00 00 06 39
17.06.2016 03 00 00 00 06 18 00 03 00 00 21 75
18.06.2016 03 00 18 00 00 15 00 03 00 00 06 45
19.06.2016 00 00 00 00 03 06 00 03 00 00 12 33
20.06.2016 03 00 00 00 03 00 00 03 00 00 00 69
21.06.2016 03 15 09 00 03 00 00 03 00 00 12 36
22.06.2016 03 06 00 00 03 06 00 00 00 00 03 99
23.06.2016 03 00 00 00 03 03 00 00 00 00 12 06
24.06.2016 03 00 09 00 06 15 00 00 00 00 09 90
25.06.2016 06 00 00 00 06 24 00 00 00 00 12 69
26.06.2016 03 00 00 00 03 09 00 00 00 00 12 60
27.06.2016 03 06 00 00 00 00 03 00 00 00 06 72
28.06.2016 00 03 09 00 00 15 00 00 00 00 12 66
29.06.2016 00 00 00 00 03 12 00 00 00 00 12 54
30.06.2016 03 00 00 00 03 00 00 00 00 00 09 69
Total 57 75 90 00 90 201 03 57 00 00 303 1569
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 41
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
SOUTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M35 M40 M40
PQC
M40
PQC Flexural Strength
M45
Remarks
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.06.2016 15 00 00 00 03 03 03 03 00 00
02.06.2016 09 03 00 00 00 03 00 03 00 00
03.06.2016 21 18 00 00 00 03 00 03 00 00
04.06.2016 12 12 00 00 00 03 00 03 00 00
05.06.2016 09 15 00 00 03 03 03 03 00 00
06.06.2016 15 09 00 00 03 06 03 06 00 00
07.06.2016 12 15 00 15 03 03 03 03 00 00
08.06.2016 03 09 00 00 00 03 00 03 00 00
09.06.2016 15 15 03 00 03 03 03 03 00 00
10.06.2016 09 12 00 00 03 03 03 03 00 00
11.06.2016 03 15 00 00 00 00 00 00 00 00
12.06.2016 12 27 00 00 00 03 00 03 00 00
13.06.2016 06 06 00 03 00 00 00 00 00 00
14.06.2016 12 12 00 00 03 03 03 03 00 00
15.06.2016 12 12 00 00 03 03 03 03 00 00
16.06.2016 12 12 00 00 03 03 03 03 00 00
17.06.2016 18 18 00 00 00 03 00 03 00 00
18.06.2016 18 12 00 00 03 00 03 00 00 00
19.06.2016 12 12 00 00 03 00 03 00 00 00
20.06.2016 15 15 00 00 03 03 03 03 00 00
21.06.2016 21 09 00 15 06 00 06 00 00 00
22.06.2016 18 18 00 00 06 03 06 03 00 00
23.06.2016 06 09 00 00 03 00 03 00 00 00
24.06.2016 09 21 00 00 06 00 06 00 00 00
25.06.2016 12 12 00 00 03 00 03 00 00 00
26.06.2016 12 09 00 00 03 03 03 03 00 00
27.06.2016 12 15 00 00 03 03 03 03 00 00
28.06.2016 15 15 00 00 03 03 03 03 00 00
29.06.2016 06 03 00 00 06 00 06 00 00 00
30.06.2016 12 15 00 15 03 03 03 03 00 00
Total 363 375 03 48 78 66 78 66 00 00
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 42
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
NORTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M10 M10 DLC M15 M20 M25 M30
Remark 7 Day
s
28 Day
s
7 Day
S
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.06.2016 00 00 00 00 06 06 00 00 00 00 03 15
02.06.2016 00 09 00 00 00 00 00 00 00 00 09 36
03.06.2016 00 12 00 00 00 00 00 00 00 00 15 72
04.06.2016 00 09 00 00 00 15 00 00 00 00 09 21
05.06.2016 03 00 00 00 00 00 00 00 00 00 06 15
06.06.2016 03 00 00 00 00 00 00 00 00 00 12 27
07.06.2016 00 00 00 00 00 00 00 00 00 00 09 42
08.06.2016 00 06 00 00 03 00 00 00 00 00 06 15
09.06.2016 00 00 00 00 03 00 00 00 00 00 06 42
10.06.2016 00 06 00 00 03 06 00 00 00 00 06 24
11.06.2016 03 00 00 00 00 00 00 00 00 00 06 45
12.06.2016 00 06 00 00 00 00 00 00 00 00 03 36
13.06.2016 00 00 00 00 00 00 00 00 00 00 09 51
14.06.2016 00 00 00 00 03 00 00 00 00 00 09 33
15.06.2016 00 00 00 00 00 00 00 00 00 00 12 15
16.06.2016 03 06 00 00 00 00 00 00 00 00 03 66
17.06.2016 03 06 00 00 00 00 00 00 00 00 03 33
18.06.2016 00 00 00 00 00 03 00 00 00 00 09 42
19.06.2016 03 00 00 00 03 00 00 00 00 00 06 06
20.06.2016 03 00 00 00 00 09 00 00 00 00 00 36
21.06.2016 00 00 00 00 03 00 00 00 00 00 09 09
22.06.2016 00 00 00 00 00 12 00 00 00 00 06 42
23.06.2016 03 00 00 00 00 00 00 00 00 00 06 39
24.06.2016 03 00 00 00 00 00 00 00 00 00 06 78
25.06.2016 06 00 00 00 00 00 00 00 00 00 03 39
26.06.2016 00 06 00 00 00 00 00 00 00 00 03 36
27.06.2016 00 03 00 00 06 00 00 00 00 00 00 33
28.06.2016 03 00 00 00 00 00 00 00 00 00 09 66
29.06.2016 00 00 00 00 03 06 00 00 00 00 06 15
30.06.2016 00 00 00 00 00 09 00 00 00 00 09 30
Total 36 69 00 00 33 66 00 00 00 00 198 1059
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 43
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
00
NORTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M35 M40 M40
PQC
M40
PQC Flexural Strength
M45
Remarks
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.06.2016 00 00 00 00 03 00 03 00 00 00
02.06.2016 00 00 00 00 03 03 03 03 00 00
03.06.2016 00 00 00 00 03 00 03 00 00 00
04.06.2016 00 00 00 00 03 03 03 03 00 00
05.06.2016 00 00 00 00 03 00 03 00 00 00
06.06.2016 00 00 00 00 03 03 03 03 00 00
07.06.2016 00 00 00 00 03 00 03 00 00 00
08.06.2016 00 00 00 00 03 03 03 03 00 00
09.06.2016 00 00 00 00 03 00 03 00 00 00
10.06.2016 00 00 00 00 03 03 03 03 00 00
11.06.2016 00 00 00 00 03 03 03 03 00 00
12.06.2016 00 00 00 00 00 03 00 03 00 00
13.06.2016 00 00 00 00 00 03 00 03 00 00
14.06.2016 00 00 00 00 00 00 00 00 00 00
15.06.2016 00 00 00 00 03 03 03 03 00 00
16.06.2016 00 00 00 00 03 00 03 00 00 00
17.06.2016 00 00 00 00 03 03 03 03 00 00
18.06.2016 00 00 00 00 03 00 03 00 00 00
19.06.2016 00 00 00 00 03 00 03 00 00 00
20.06.2016 00 00 00 00 06 03 06 03 00 00
21.06.2016 00 00 00 00 09 03 09 03 00 00
22.06.2016 00 00 00 00 06 03 06 03 00 00
23.06.2016 00 00 00 00 06 03 06 03 00 00
24.06.2016 00 00 00 00 03 03 03 03 00 00
25.06.2016 00 00 00 00 03 03 03 03 00 00
26.06.2016 00 00 00 00 00 03 00 03 00 00
27.06.2016 00 00 00 00 00 03 00 03 00 00
28.06.2016 00 00 00 00 03 03 03 03 00 00
29.06.2016 00 00 00 00 06 03 06 03 00 00
30.06.2016 00 00 00 00 06 03 06 03 00 00
Total 00 00 00 00 96 63 96 63 00 00
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 44
FOR THE MONTH OF JULY 2016
DETAILS OF WSC CORES (M25) TESTED IN THE MONTH OF JULY 2016.
SOUTH PORTAL
DATE
INSITU CORES PANEL CASTED
Remarks Pass Fail 1 days 7 days 28 days
01.07.2016 00 00 05 00 00
02.07.2016 00 00 00 00 00
03.07.2016 00 00 00 00 00
04.07.2016 00 00 00 00 00
05.07.2016 00 00 00 00 00
06.07.2016 00 00 05 00 00
07.07.2016 00 00 00 05 00
08.07.2016 00 00 00 00 00
09.07.2016 00 00 00 00 00
10.07.2016 00 00 05 00 05
11.07.2016 00 00 00 00 00
12.07.2016 00 00 00 05 00
13.07.2016 00 00 05 00 00
14.07.2016 00 00 00 00 05
15.07.2016 00 00 00 00 00
16.07.2016 00 00 05 05 00
17.07.2016 00 00 00 00 00
18.07.2016 00 00 00 00 00
19.07.2016 00 00 00 05 00
20.07.2016 00 00 00 00 00
21.07.2016 00 00 05 00 05
22.07.2016 00 00 00 05 00
23.07.2016 00 00 05 00 00
24.07.2016 00 00 00 00 00
25.07.2016 00 00 05 00 00
26.07.2016 00 00 00 00 00
27.07.2016 00 00 05 05 00
28.07.2016 00 00 00 00 05
29.07.2016 00 00 00 05 00
30.07.2016 00 00 00 00 00
31.07.2016 00 00 00 00 00
Total 00 00 45 35 20
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 45
DETAILS OF WSC CORES (M25) TESTED IN THE MONTH OF JULY 2016.
NORTH PORTAL
DATE
INSITU CORES PANEL CASTED
Remarks
Pass Fail 1 days 7 days 28 days
01.07.2016 00 00 00 00 00
02.07.2016 00 00 00 00 00
03.07.2016 00 00 00 00 00
04.07.2016 00 00 00 00 00
05.07.2016 00 00 00 00 00
06.07.2016 00 00 00 00 00
07.07.2016 00 00 00 00 00
08.07.2016 00 00 00 00 00
09.07.2016 00 00 00 00 00
10.07.2016 00 00 00 00 00
11.07.2016 00 00 00 00 00
12.07.2016 00 00 00 00 00
13.07.2016 00 00 00 00 00
14.07.2016 00 00 00 00 00
15.07.2016 00 00 00 00 00
16.07.2016 00 00 00 00 00
17.07.2016 00 00 00 00 00
18.07.2016 00 00 00 00 00
19.07.2016 00 00 00 00 00
20.07.2016 00 00 00 00 00
21.07.2016 00 00 00 00 00
22.07.2016 00 00 00 00 00
23.07.2016 00 00 00 00 00
24.07.2016 00 00 00 00 00
25.07.2016 00 00 00 00 00
26.07.2016 00 00 00 00 00
27.07.2016 00 00 00 00 00
28.07.2016 00 00 00 00 00
29.07.2016 00 00 00 00 00
30.07.2016 00 00 00 00 00
31.07.2016 00 00 00 00 00
Total 00 00 00 00 00
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 46
DETAILS OF CUBES TESTED IN THE MONTH OF JULY 2016.
SOUTH PORTAL
DATE Grout Cube Testing
Remarks
3 days 7 days 28 days
01.07.2016 00 05 05
02.07.2016 00 05 05
03.07.2016 00 00 05
04.07.2016 00 00 05
05.07.2016 00 00 05
06.07.2016 00 05 05
07.07.2016 00 00 05
08.07.2016 00 05 05
09.07.2016 00 05 05
10.07.2016 00 05 05
11.07.2016 00 05 05
12.07.2016 00 00 05
13.07.2016 00 00 05
14.07.2016 00 00 00
15.07.2016 00 05 05
16.07.2016 00 05 05
17.07.2016 00 05 05
18.07.2016 00 05 05
19.07.2016 00 05 05
20.07.2016 00 05 05
21.07.2016 00 05 05
22.07.2016 00 05 05
23.07.2016 00 05 05
24.07.2016 00 05 00
25.07.2016 00 05 00
26.07.2016 00 05 00
27.07.2016 00 05 05
28.07.2016 00 05 00
29.07.2016 00 05 05
30.07.2016 00 00 05
31.07.2016 00 05 05
Total 00 115 130
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 47
DETAILS OF CUBES TESTED IN THE MONTH OF JULY 2016.
NORTH PORTAL
DATE Grout Cube Testing
Remarks
3 days 7 days 28 days
01.07.2016 05 00 00
02.07.2016 05 00 00
03.07.2016 05 00 00
04.07.2016 05 00 00
05.07.2016 00 05 00
06.07.2016 00 00 00
07.07.2016 00 05 00
08.07.2016 00 05 00
09.07.2016 00 00 00
10.07.2016 00 00 05
11.07.2016 00 00 00
12.07.2016 00 00 00
13.07.2016 00 00 05
14.07.2016 00 00 00
15.07.2016 00 00 05
16.07.2016 00 00 05
17.07.2016 00 00 05
18.07.2016 00 00 00
19.07.2016 00 00 00
20.07.2016 00 00 05
21.07.2016 00 00 05
22.07.2016 00 00 00
23.07.2016 00 00 00
24.07.2016 00 00 00
25.07.2016 00 00 00
26.07.2016 00 00 00
27.07.2016 00 00 05
28.07.2016 00 00 05
29.07.2016 00 00 05
30.07.2016 00 00 00
31.07.2016 00 00 00
Total 20 15 50
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 48
DETAILS OF CUBES TESTED IN THE MONTH OF JULY 2016.
SOUTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M10 M10 DLC M15 M20 M25 M30
Remark 7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.07.2016 00 15 09 00 06 00 00 00 00 00 21 45
02.07.2016 00 12 00 00 00 18 00 00 00 00 09 105
03.07.2016 00 00 00 00 00 15 00 00 00 00 00 18
04.07.2016 00 09 00 00 00 00 00 00 00 00 00 45
05.07.2016 03 00 00 00 00 00 00 00 00 00 12 66
06.07.2016 06 12 09 00 00 18 00 00 00 00 09 108
07.07.2016 03 12 00 00 03 12 00 00 00 00 18 72
08.07.2016 00 15 00 00 06 30 00 00 00 00 21 114
09.07.2016 00 39 09 00 06 00 00 00 00 00 30 42
10.07.2016 03 00 00 00 00 18 00 00 00 00 09 84
11.07.2016 06 00 00 00 03 06 00 00 00 00 12 21
12.07.2016 06 00 00 00 03 09 00 00 00 00 03 75
13.07.2016 00 06 00 00 00 03 00 00 00 00 00 15
14.07.2016 15 15 09 00 00 18 00 00 00 00 12 129
15.07.2016 00 06 09 00 00 15 00 00 00 00 18 12
16.07.2016 00 18 09 00 00 30 00 00 00 00 18 81
17.07.2016 00 12 00 00 03 21 00 00 00 00 15 51
18.07.2016 00 21 00 00 00 00 00 00 00 00 15 24
19.07.2016 00 09 18 00 03 00 00 00 00 00 09 78
20.07.2016 00 00 18 00 00 12 00 00 00 00 03 66
21.07.2016 00 15 09 00 00 06 00 00 00 00 15 51
22.07.2016 03 00 00 00 00 15 00 00 00 00 09 63
23.07.2016 00 00 09 00 00 00 00 00 00 00 15 45
24.07.2016 00 00 00 00 00 00 00 00 00 00 15 00
25.07.2016 00 00 09 00 03 00 00 00 00 00 09 00
26.07.2016 00 03 09 00 06 00 00 00 00 00 12 45
27.07.2016 00 06 09 00 00 00 03 00 00 00 18 30
28.07.2016 03 03 09 00 03 15 00 00 00 00 15 54
29.07.2016 00 00 00 00 00 06 00 00 00 00 06 54
30.07.2016 00 00 00 00 06 24 00 00 00 00 09 75
31.07.2016 00 15 09 00 03 00 00 00 00 00 15 33
Total 48 243 153 00 54 291 03 00 00 00 372 1701
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 49
DETAILS OF CUBES TESTED IN THE MONTH OF JULY 2016.
SOUTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M10 M10 DLC M15 M20 M25 M30
Remark 7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.07.2016 00 15 09 00 06 00 00 00 00 00 21 45
02.07.2016 00 12 00 00 00 18 00 00 00 00 09 105
03.07.2016 00 00 00 00 00 15 00 00 00 00 00 18
04.07.2016 00 09 00 00 00 00 00 00 00 00 00 45
05.07.2016 03 00 00 00 00 00 00 00 00 00 12 66
06.07.2016 06 12 09 00 00 18 00 00 00 00 09 108
07.07.2016 03 12 00 00 03 12 00 00 00 00 18 72
08.07.2016 00 15 00 00 06 30 00 00 00 00 21 114
09.07.2016 00 39 09 00 06 00 00 00 00 00 30 42
10.07.2016 03 00 00 00 00 18 00 00 00 00 09 84
11.07.2016 06 00 00 00 03 06 00 00 00 00 12 21
12.07.2016 06 00 00 00 03 09 00 00 00 00 03 75
13.07.2016 00 06 00 00 00 03 00 00 00 00 00 15
14.07.2016 15 15 09 00 00 18 00 00 00 00 12 129
15.07.2016 00 06 09 00 00 15 00 00 00 00 18 12
16.07.2016 00 18 09 00 00 30 00 00 00 00 18 81
17.07.2016 00 12 00 00 03 21 00 00 00 00 15 51
18.07.2016 00 21 00 00 00 00 00 00 00 00 15 24
19.07.2016 00 09 18 00 03 00 00 00 00 00 09 78
20.07.2016 00 00 18 00 00 12 00 00 00 00 03 66
21.07.2016 00 15 09 00 00 06 00 00 00 00 15 51
22.07.2016 03 00 00 00 00 15 00 00 00 00 09 63
23.07.2016 00 00 09 00 00 00 00 00 00 00 15 45
24.07.2016 00 00 00 00 00 00 00 00 00 00 15 00
25.07.2016 00 00 09 00 03 00 00 00 00 00 09 00
26.07.2016 00 03 09 00 06 00 00 00 00 00 12 45
27.07.2016 00 06 09 00 00 00 03 00 00 00 18 30
28.07.2016 03 03 09 00 03 15 00 00 00 00 15 54
29.07.2016 00 00 00 00 00 06 00 00 00 00 06 54
30.07.2016 00 00 00 00 06 24 00 00 00 00 09 75
31.07.2016 00 15 09 00 03 00 00 00 00 00 15 33
Total 48 243 153 00 54 291 03 00 00 00 372 1701
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 50
DETAILS OF CUBES TESTED IN THE MONTH OF JULY 2016.
SOUTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M35 M40 M40
PQC
M40
PQC Flexural Strength
M45
Remarks
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.07.2016 15 09 00 00 03 03 03 03 00 00
02.07.2016 12 03 00 00 00 00 00 00 00 00
03.07.2016 00 12 00 00 00 00 00 00 00 00
04.07.2016 00 06 00 00 00 00 00 00 00 00
05.07.2016 06 12 00 00 00 03 00 03 00 00
06.07.2016 15 12 00 00 06 03 06 03 00 00
07.07.2016 09 12 00 00 00 03 00 03 00 00
08.07.2016 18 21 00 00 03 00 03 00 00 00
09.07.2016 15 18 00 00 00 03 00 03 00 00
10.07.2016 12 12 00 00 03 03 03 03 00 00
11.07.2016 12 15 00 00 00 03 00 03 00 00
12.07.2016 18 24 00 00 06 03 06 03 00 00
13.07.2016 03 18 00 00 00 06 00 06 00 00
14.07.2016 15 09 00 00 00 03 00 03 00 00
15.07.2016 15 09 00 00 06 06 06 06 00 00
16.07.2016 21 125 00 00 06 03 06 03 00 00
17.07.2016 03 12 03 00 03 03 03 03 00 00
18.07.2016 18 12 00 00 00 03 00 03 00 00
19.07.2016 21 15 00 00 03 03 03 03 00 00
20.07.2016 18 06 03 00 03 03 03 03 00 00
21.07.2016 27 12 00 00 03 03 03 03 00 00
22.07.2016 21 18 06 00 03 03 03 03 00 00
23.07.2016 18 15 03 00 00 00 00 00 00 00
24.07.2016 21 00 00 00 00 00 00 00 00 00
25.07.2016 18 00 00 00 03 00 03 00 00 00
26.07.2016 18 06 03 00 03 00 03 00 00 00
27.07.2016 18 18 00 00 03 06 03 06 00 00
28.07.2016 21 09 00 00 03 00 03 00 00 00
29.07.2016 15 18 00 00 03 03 03 03 00 00
30.07.2016 15 21 00 00 03 00 03 00 00 00
31.07.2016 18 12 06 00 03 03 03 03 00 00
Total 456 378 24 00 69 72 69 72 00 00
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 51
DETAILS OF CUBES TESTED IN THE MONTH OF JULY 2016.
NORTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M10 M10 DLC M15 M20 M25 M30
Remark 7 Day
s
28 Day
s
7 Day
S
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.07.2016 00 00 00 00 03 03 00 00 00 00 06 27
02.07.2016 00 06 00 00 03 00 00 00 00 00 03 45
03.07.2016 00 00 00 00 03 00 00 00 00 00 03 00
04.07.2016 00 00 00 00 03 00 00 00 00 00 09 51
05.07.2016 00 00 00 00 06 06 00 00 00 00 06 33
06.07.2016 00 00 00 00 03 00 00 00 00 00 00 51
07.07.2016 00 06 00 00 00 00 00 00 00 00 09 30
08.07.2016 03 06 00 00 03 00 00 00 00 00 06 06
09.07.2016 00 00 00 00 00 00 00 00 00 00 06 33
10.07.2016 00 09 00 00 00 06 00 00 00 00 00 48
11.07.2016 00 12 00 00 00 00 00 00 00 00 09 00
12.07.2016 00 00 00 00 03 00 00 00 00 00 00 63
13.07.2016 00 00 00 00 03 00 00 00 00 00 00 18
14.07.2016 00 12 00 00 00 00 00 00 00 00 09 45
15.07.2016 00 12 00 00 00 00 00 00 00 00 03 21
16.07.2016 00 21 00 00 00 00 00 00 00 00 06 15
17.07.2016 00 00 00 00 03 00 00 00 00 00 06 21
18.07.2016 03 00 00 00 00 18 00 00 00 00 06 00
19.07.2016 03 06 00 00 00 00 00 00 00 00 03 69
20.07.2016 03 00 00 00 00 03 00 00 00 00 03 27
21.07.2016 00 00 00 00 00 00 00 00 00 00 09 48
22.07.2016 06 00 00 00 00 12 00 00 00 00 06 21
23.07.2016 00 00 00 00 00 15 00 00 00 00 03 06
24.07.2016 00 00 00 00 00 18 00 00 00 00 03 12
25.07.2016 00 00 00 00 00 18 00 00 00 00 09 30
26.07.2016 03 00 00 00 03 30 00 00 00 00 03 18
27.07.2016 06 00 00 00 06 18 00 00 00 00 12 00
28.07.2016 03 00 00 00 03 00 00 00 00 00 06 48
29.07.2016 03 06 00 00 09 03 00 00 00 00 09 18
30.07.2016 03 00 00 00 03 03 00 00 00 00 09 18
31.07.2016 03 00 00 00 00 00 00 00 00 00 03 18
Total 39 96 00 00 57 153 00 00 00 00 165 837
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 52
DETAILS OF CUBES TESTED IN THE MONTH OF JULY 2016.
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
00
NORTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M35 M40 M40
PQC
M40
PQC Flexural Strength
M45
Remarks
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.07.2016 06 06 00 00 03 03 03 03 00 00
02.07.2016 03 06 00 00 00 03 00 03 00 00
03.07.2016 03 06 00 00 00 00 00 00 00 00
04.07.2016 03 06 00 00 00 00 00 00 00 00
05.07.2016 06 06 00 00 00 00 00 00 00 00
06.07.2016 03 06 00 00 00 03 00 03 00 00
07.07.2016 03 06 00 00 03 03 03 03 00 00
08.07.2016 03 06 00 00 03 03 03 03 00 00
09.07.2016 03 06 00 00 03 03 03 03 00 00
10.07.2016 00 06 00 00 00 03 00 03 00 00
11.07.2016 03 06 00 00 03 06 03 06 00 00
12.07.2016 03 06 00 00 00 09 00 09 00 00
13.07.2016 00 06 00 00 00 06 00 06 00 00
14.07.2016 03 06 00 00 00 06 00 06 00 00
15.07.2016 03 06 00 00 03 03 03 03 00 00
16.07.2016 03 06 00 00 03 03 03 03 00 00
17.07.2016 06 06 00 00 00 00 00 00 00 00
18.07.2016 06 06 00 00 00 00 00 00 00 00
19.07.2016 06 06 00 00 03 03 03 03 00 00
20.07.2016 03 06 00 00 03 06 03 06 00 00
21.07.2016 06 06 00 00 03 03 03 03 00 00
22.07.2016 03 06 00 00 03 03 03 03 00 00
23.07.2016 03 06 00 00 00 00 00 00 00 00
24.07.2016 03 06 00 00 00 00 00 00 00 00
25.07.2016 03 06 00 00 03 00 03 00 00 00
26.07.2016 03 09 00 00 03 00 03 00 00 00
27.07.2016 03 09 00 00 00 00 00 00 00 00
28.07.2016 03 06 00 00 03 03 03 03 00 00
29.07.2016 09 06 00 00 03 03 03 03 00 00
30.07.2016 06 09 00 00 06 03 06 03 00 00
31.07.2016 03 00 00 00 03 00 03 00 00 00
Total 114 189 00 00 54 78 54 78 00 00
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 53
FOR THE MONTH OF AUGUST
DETAILS OF WSC CORES (M25) TESTED IN THE MONTH OF AUGUST 2016.
SOUTH PORTAL
DATE
INSITU CORES PANEL CASTED
Remarks Pass Fail 1 days 7 days 28 days
01.08.2016 00 00 00 05 00
02.08.2016 00 00 00 05 05
03.08.2016 00 00 00 00 00
04.08.2016 00 00 00 00 00
05.08.2016 00 00 00 00 00
06.08.2016 00 00 00 00 05
07.08.2016 00 00 00 00 00
08.08.2016 00 00 00 00 00
09.08.2016 00 00 00 00 05
10.08.2016 00 00 00 00 00
11.08.2016 00 00 00 00 00
12.08.2016 00 00 00 00 05
13.08.2016 00 00 00 00 00
14.08.2016 00 00 00 00 00
15.08.2016 00 00 00 00 00
16.08.2016 00 00 00 00 00
17.08.2016 00 00 00 00 05
18.08.2016 00 00 00 00 00
19.08.2016 00 00 00 00 05
20.08.2016 00 00 00 00 00
21.08.2016 00 00 00 00 00
22.08.2016 00 00 00 00 05
23.08.2016 00 00 00 00 05
24.08.2016 00 00 00 00 00
25.08.2016 00 00 00 00 00
26.08.2016 00 00 00 00 00
27.08.2016 00 00 00 00 00
28.08.2016 00 00 00 00 00
29.08.2016 00 00 00 00 00
30.08.2016 00 00 00 00 00
31.08.2016 00 00 00 00 00
Total 00 00 00 10 40
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 54
DETAILS OF WSC CORES (M25) TESTED IN THE MONTH OF AUGUST 2016.
NORTH PORTAL
DATE
INSITU CORES PANEL CASTED
Remarks
Pass Fail 1 days 7 days 28 days
01.08.2016 00 00 00 00 00
02.08.2016 00 00 05 00 00
03.08.2016 00 00 00 00 00
04.08.2016 00 00 00 00 00
05.08.2016 00 00 05 00 00
06.08.2016 00 00 05 00 00
07.08.2016 00 00 00 00 00
08.08.2016 00 00 00 05 00
09.08.2016 00 00 00 00 00
10.08.2016 00 00 00 00 00
11.08.2016 00 00 05 05 00
12.08.2016 00 00 00 05 00
13.08.2016 00 00 05 00 00
14.08.2016 00 00 00 00 00
15.08.2016 00 00 05 00 00
16.08.2016 00 00 00 00 00
17.08.2016 00 00 00 05 00
18.08.2016 00 00 05 00 00
19.08.2016 00 00 00 05 00
20.08.2016 00 00 05 00 00
21.08.2016 00 00 00 05 00
22.08.2016 00 00 05 00 00
23.08.2016 00 00 00 00 00
24.08.2016 00 00 05 05 00
25.08.2016 00 00 00 00 00
26.08.2016 00 00 05 05 00
27.08.2016 00 00 00 00 00
28.08.2016 00 00 00 05 00
29.08.2016 03 00 00 00 05
30.08.2016 00 00 00 05 00
31.08.2016 00 00 00 00 00
Total 03 00 55 50 05
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 55
DETAILS OF CUBES TESTED IN THE MONTH OF AUGUST 2016.
SOUTH PORTAL
DATE Contact Grout Cube Testing
Remarks
3 days 7 days 28 days
01.08.2016 00 00 05
02.08.2016 00 00 00
03.08.2016 00 00 00
04.08.2016 00 00 00
05.08.2016 00 00 05
06.08.2016 00 00 05
07.08.2016 00 00 05
08.08.2016 00 00 05
09.08.2016 00 00 05
10.08.2016 00 00 05
11.08.2016 00 05 05
12.08.2016 00 05 05
13.08.2016 00 05 05
14.08.2016 00 00 05
15.08.2016 00 00 00
16.08.2016 00 05 10
17.08.2016 00 10 05
18.08.2016 00 05 05
19.08.2016 00 05 05
20.08.2016 00 05 00
21.08.2016 00 05 05
22.08.2016 00 00 00
23.08.2016 00 05 00
24.08.2016 00 05 00
25.08.2016 00 05 00
26.08.2016 00 00 00
27.08.2016 00 00 00
28.08.2016 00 00 00
29.08.2016 00 00 00
30.08.2016 00 00 00
31.08.2016 00 00 00
Total 00 65 85
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 56
DETAILS OF CUBES TESTED IN THE MONTH OF AUGUST 2016.
NORTH PORTAL
DATE Grout Cube Testing
Remarks
3 days 7 days 28 days
01.08.2016 00 05 00
02.08.2016 00 05 00
03.08.2016 00 05 00
04.08.2016 00 00 00
05.08.2016 05 00 00
06.08.2016 05 00 00
07.08.2016 00 00 00
08.08.2016 00 00 00
09.08.2016 00 05 00
10.08.2016 00 05 00
11.08.2016 05 00 00
12.08.2016 00 00 00
13.08.2016 00 00 05
14.08.2016 00 00 05
15.08.2016 00 0 00
16.08.2016 00 05 10
17.08.2016 00 00 05
18.08.2016 00 00 05
19.08.2016 00 00 05
20.08.2016 00 00 05
21.08.2016 00 00 05
22.08.2016 00 00 05
23.08.2016 00 00 05
24.08.2016 00 00 05
25.08.2016 00 00 00
26.08.2016 00 00 00
27.08.2016 00 00 00
28.08.2016 00 00 00
29.08.2016 00 00 00
30.08.2016 00 00 05
31.08.2016 00 00 05
Total 15 30 70
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 57
DETAILS OF CUBES TESTED IN THE MONTH OF AUGUST 2016.
SOUTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M10 M10 DLC M15 M20 M25 M30
Remark 7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
3901.08.2016
00 12 09 00 03 09 00 00 00 00 09 12
02.08.2016 00 00 09 00 03 03 00 00 00 00 03 18
03.08.2016 03 00 09 00 00 00 00 00 00 00 03 09
04.08.2016 00 00 09 00 03 00 00 00 00 00 06 12
05.08.2016 00 00 09 00 03 00 00 00 00 00 09 18
06.08.2016 00 00 09 00 03 03 00 00 00 00 09 27
07.08.2016 00 00 09 00 03 00 00 00 00 00 12 27
08.08.2016 00 00 09 00 00 06 00 00 00 00 03 33
09.08.2016 00 00 00 00 03 00 00 00 00 00 09 39
10.08.2016 03 00 00 00 00 00 00 00 00 00 12 18
11.08.2016 03 00 09 00 00 00 00 00 00 00 03 33
12.08.2016 06 06 09 00 03 00 00 00 00 00 03 12
13.08.2016 06 00 09 00 03 00 00 00 00 00 03 18
14.08.2016 06 00 00 00 00 00 00 00 00 00 09 09
15.08.2016 00 00 00 00 00 00 00 00 00 00 00 00
16.08.2016 06 00 09 00 06 09 00 00 00 00 09 36
17.08.2016 06 00 00 00 00 00 00 00 00 00 06 18
18.08.2016 00 03 00 00 09 03 00 00 00 00 06 30
19.08.2016 03 00 09 00 03 00 00 00 00 00 06 27
20.08.2016 03 00 00 00 03 06 00 00 00 00 03 27
21.08.2016 00 00 00 00 03 00 00 00 00 00 09 24
22.08.2016 00 00 00 00 00 06 00 00 00 00 03 30
23.08.2016 03 00 00 00 06 03 00 00 00 00 03 30
24.08.2016 03 09 00 00 03 00 00 00 00 00 06 39
25.08.2016 03 00 00 00 06 06 00 00 00 00 09 33
26.08.2016 00 00 00 00 03 03 00 00 00 00 03 24
27.08.2016 00 00 09 00 00 06 00 00 00 00 12 12
28.08.2016 00 00 09 00 06 03 00 00 00 00 03 30
29.08.2016 03 00 09 00 09 00 00 00 00 00 03 30
30.08.2016 03 00 00 00 06 03 00 00 00 00 03 18
31.08.2016 03 06 09 00 06 00 00 00 00 00 06 24
Total 63 36 153 00 96 69 00 00 00 00 183 717
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 58
DETAILS OF CUBES TESTED IN THE MONTH OF AUGUST 2016.
SOUTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M35 M40 M40
PQC
M40
PQC Flexural Strength
M45
Remarks
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.08.2016 18 21 00 00 03 00 03 00 00 00
02.08.2016 12 15 00 00 00 06 00 06 00 00
03.08.2016 18 00 00 00 00 00 00 00 00 00
04.08.2016 15 12 00 00 03 00 03 00 00 00
05.08.2016 18 15 00 00 03 06 03 06 00 00
06.08.2016 15 18 00 00 03 06 03 06 00 00
07.08.2016 27 00 00 00 03 03 03 03 00 00
08.08.2016 12 27 00 00 03 00 03 00 00 00
09.08.2016 18 24 00 00 03 03 03 03 00 00
10.08.2016 21 15 00 00 03 03 03 03 00 00
11.08.2016 21 30 00 00 03 03 03 03 00 00
12.08.2016 21 18 00 00 03 03 03 03 00 00
13.08.2016 21 12 00 00 00 00 00 00 00 00
14.08.2016 06 21 00 00 00 00 00 00 00 00
15.08.2016 00 00 00 00 00 00 00 00 00 00
16.08.2016 39 30 00 00 06 06 06 06 00 00
17.08.2016 24 15 00 00 03 03 03 03 00 00
18.08.2016 24 21 00 00 03 03 03 03 00 00
19.08.2016 18 12 00 00 03 03 03 03 00 00
20.08.2016 15 12 00 00 03 03 03 03 00 00
21.08.2016 24 18 00 00 03 03 03 03 00 00
22.08.2016 00 15 00 00 03 03 03 03 00 00
23.08.2016 12 12 00 00 03 00 03 00 00 00
24.08.2016 24 18 00 00 03 00 03 00 00 00
25.08.2016 18 15 00 00 03 03 03 03 00 00
26.08.2016 21 18 00 00 03 03 03 03 00 00
27.08.2016 15 18 00 00 03 03 03 03 00 00
28.08.2016 09 27 00 00 03 06 03 06 00 00
29.08.2016 09 12 00 00 03 03 03 03 00 00
30.08.2016 24 18 00 00 03 03 03 03 00 00
31.08.2016 12 21 00 00 03 03 03 03 00 00
Total 531 510 00 00 81 81 81 81 00 00
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 59
DETAILS OF CUBES TESTED IN THE MONTH OF AUGUST 2016.
NORTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M10 M10 DLC M15 M20 M25 M30
Remark 7 Day
s
28 Day
s
7 Day
S
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.08.2016 03 00 00 00 03 00 00 00 00 00 09 60
02.08.2016 00 00 00 00 03 12 00 00 00 00 06 00
03.08.2016 00 00 00 00 00 00 00 00 00 00 09 00
04.08.2016 00 00 00 00 00 06 00 00 00 00 09 24
05.08.2016 00 00 00 00 00 00 00 00 00 00 12 03
06.08.2016 00 00 00 00 00 00 00 00 00 00 15 21
07.08.2016 00 00 00 00 00 15 00 00 00 00 09 57
08.08.2016 00 12 00 00 03 00 00 00 00 00 03 21
09.08.2016 03 06 00 00 00 00 00 00 00 00 06 09
10.08.2016 00 03 00 00 00 00 00 00 00 00 09 06
11.08.2016 03 00 00 00 00 00 00 00 00 00 09 57
12.08.2016 00 09 00 00 00 00 00 00 00 00 03 21
13.08.2016 00 00 00 00 00 00 00 00 00 00 06 27
14.08.2016 00 00 00 00 00 00 00 00 00 00 06 27
15.08.2016 00 00 00 00 00 00 00 00 00 00 00 30
16.08.2016 06 06 00 00 03 03 00 00 00 00 12 06
17.08.2016 03 21 00 00 00 21 00 00 00 00 06 39
18.08.2016 00 06 00 00 03 15 00 00 00 00 09 15
19.08.2016 00 06 00 00 00 30 00 00 00 00 09 24
20.08.2016 00 06 09 00 03 06 00 00 00 00 06 30
21.08.2016 00 06 00 00 00 00 00 00 00 00 06 06
22.08.2016 00 06 00 00 00 06 00 00 00 00 00 27
23.08.2016 03 00 00 00 00 06 00 00 00 00 06 18
24.08.2016 03 00 09 00 03 00 00 00 00 00 06 33
25.08.2016 00 00 09 00 03 00 00 00 00 00 09 33
26.08.2016 00 00 09 00 03 00 00 00 00 00 03 30
27.08.2016 03 00 09 00 00 00 00 00 00 00 06 33
28.08.2016 00 00 09 00 03 00 00 00 00 00 03 24
29.08.2016 00 00 00 00 00 06 00 00 00 00 06 12
30.08.2016 00 06 09 00 00 00 00 00 00 00 06 27
31.08.2016 03 00 09 00 00 00 00 00 00 00 06 42
Total 30 93 72 00 30 126 00 00 00 00 210 762
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 60
DETAILS OF CUBES TESTED IN THE MONTH OF AUGUST 2016.
DETAILS OF CUBES TESTED IN THE MONTH OF JUNE 2016.
00
NORTH PORTAL
DATE
Concrete Cube’s Compressive Strength
M35 M40 M40
PQC
M40
PQC Flexural Strength
M45
Remarks
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
7 Day
s
28 Day
s
01.08.2016 03 09 00 00 03 03 03 03 00 00
02.08.2016 06 06 00 00 03 00 03 00 00 00
03.08.2016 06 00 00 00 03 00 03 00 00 00
04.08.2016 06 06 00 00 06 00 06 00 00 00
05.08.2016 03 06 00 00 06 03 06 03 00 00
06.08.2016 09 09 00 00 06 03 06 03 00 00
07.08.2016 03 12 00 00 03 00 03 00 00 00
08.08.2016 06 12 00 00 03 00 03 00 00 00
09.08.2016 03 12 00 00 03 03 03 03 00 00
10.08.2016 03 06 00 00 03 03 03 03 00 00
11.08.2016 03 12 00 00 03 03 03 03 00 00
12.08.2016 03 09 00 00 03 03 03 03 00 00
13.08.2016 06 06 00 00 00 00 00 00 00 00
14.08.2016 03 06 00 00 03 00 03 00 00 00
15.08.2016 00 00 00 00 00 00 00 00 00 00
16.08.2016 09 12 00 00 03 06 03 06 00 00
17.08.2016 03 06 00 00 03 00 03 00 00 00
18.08.2016 03 06 00 00 00 03 00 03 00 00
19.08.2016 03 15 00 00 00 03 00 03 00 00
20.08.2016 03 12 00 00 00 06 00 06 00 00
21.08.2016 03 06 00 00 03 03 03 03 00 00
22.08.2016 00 06 00 00 00 03 00 03 00 00
23.08.2016 03 12 00 00 03 03 03 03 00 00
24.08.2016 03 09 00 00 00 03 00 03 00 00
25.08.2016 03 12 00 00 00 06 00 06 00 00
26.08.2016 03 06 00 00 00 06 00 06 00 00
27.08.2016 03 18 00 00 00 06 00 06 00 00
28.08.2016 03 06 00 00 00 03 00 03 00 00
29.08.2016 03 33 00 00 03 03 03 03 00 00
30.08.2016 03 06 00 00 03 03 03 03 00 00
31.08.2016 03 06 00 00 03 03 03 03 00 00
Total 114 282 00 00 69 81 69 81 00 00
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 61
12.3 DETAILS OF AGGREGATES TESTING
FOR THE MONTH OF JUNE
DETAILS OF TESTING IN THE MONTH OF JUNE 2016.
SOUTH PORTAL
MOISTURE CONTENT % GRADATION
DATE 10 & 20
mm Crusher
Dust Sand
10 mm
Crusher Dust
20 mm
Sand Combine
d F.I AIV
01.06.2016 04 02 02 01 01 01 01 01 00 00
02.06.2016 04 02 02 01 01 01 01 01 00 00
03.06.2016 04 02 02 01 01 01 01 01 00 00
04.06.2016 04 02 02 01 01 01 01 01 00 00
05.06.2016 04 02 02 01 01 01 01 01 00 00
06.06.2016 04 02 02 01 01 01 01 01 00 00
07.06.2016 04 02 02 01 01 01 01 01 00 00
08.06.2016 04 02 02 01 01 01 01 02 02 01
09.06.2016 04 02 02 01 01 01 01 01 00 00
10.06.2016 04 02 02 01 01 01 01 01 00 00
11.06.2016 04 02 02 01 01 01 01 01 00 00
12.06.2016 04 02 02 01 01 01 01 01 00 00
13.06.2016 04 02 02 01 01 01 01 01 00 00
14.06.2016 04 02 02 01 01 01 01 01 00 00
15.06.2016 04 02 02 01 01 01 01 02 02 01
16.06.2016 04 02 02 01 01 01 01 01 00 00
17.06.2016 04 02 02 01 01 01 01 01 00 00
18.06.2016 04 02 02 01 01 01 01 01 00 00
19.06.2016 04 02 02 01 01 01 01 01 00 00
20.06.2016 04 02 02 01 01 01 01 01 00 00
21.06.2016 04 02 02 01 01 01 01 02 02 01
22.06.2016 04 02 02 01 01 01 01 01 00 00
23.06.2016 04 02 02 01 01 01 01 01 00 00
24.06.2016 04 02 02 01 01 01 01 01 00 00
25.06.2016 04 02 02 01 01 01 01 01 00 00
26.06.2016 04 02 02 01 01 01 01 01 00 00
27.06.2016 04 02 02 01 01 01 01 01 00 00
28.06.2016 04 02 02 01 01 01 01 01 00 00
29.06.2016 04 02 02 01 01 01 01 02 02 01
30.06.2016 04 02 02 01 01 01 01 01 00 00
Total 120 60 60 30 30 30 30 34 08 04
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 62
DETAILS OF TESTING IN THE MONTH OF JUNE 2016.
NORTH PORTAL
MOISTURE CONTENT % GRADATION
DATE 10 & 20
mm Crusher
Dust Sand
10 mm
Crusher Dust
20 mm
Sand Combined F.I AIV
01.06.2016 04 02 02 00 00 00 00 00 00 00
02.06.2016 04 02 02 01 01 01 01 01 01 01
03.06.2016 04 02 02 00 00 00 00 00 00 00
04.06.2016 04 02 02 00 00 00 00 00 00 00
05.06.2016 04 02 02 00 00 00 00 00 00 00
06.06.2016 04 02 02 01 01 01 01 01 01 01
07.06.2016 04 02 02 00 00 00 00 00 00 00
08.06.2016 04 02 02 00 00 00 00 00 00 00
09.06.2016 04 02 02 01 01 01 01 01 01 01
10.06.2016 04 02 02 00 00 00 00 00 00 00
11.06.2016 04 02 02 00 00 00 00 00 00 00
12.06.2016 04 02 02 01 01 01 01 01 01 01
13.06.2016 04 02 02 00 00 00 00 00 00 00
14.06.2016 04 02 02 00 00 00 00 00 00 00
15.06.2016 04 02 02 01 01 01 01 01 01 01
16.06.2016 04 02 02 00 00 00 00 00 00 00
17.06.2016 04 02 02 00 00 00 00 00 00 00
18.06.2016 04 02 02 01 01 01 01 01 01 01
19.06.2016 04 02 02 00 00 00 00 00 00 00
20.06.2016 04 02 02 00 00 00 00 00 00 00
21.06.2016 04 02 02 01 01 01 01 01 01 01
22.06.2016 04 02 02 00 00 00 00 00 00 00
23.06.2016 04 02 02 01 01 01 01 01 01 01
24.06.2016 04 02 02 00 00 00 00 00 00 00
25.06.2016 04 02 02 00 00 00 00 00 00 00
26.06.2016 04 02 02 00 00 00 00 00 00 00
27.06.2016 04 02 02 01 01 01 01 01 01 01
28.06.2016 04 02 02 00 00 00 00 00 00 00
29.06.2016 04 02 02 00 00 00 00 00 00 00
30.06.2016 04 02 02 01 01 01 01 01 01 01
Total 120 60 60 10 10 10 10 10 10 10
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 63
FOR THE MONTH OF JULY 2016
DETAILS OF TESTING IN THE MONTH OF JULY 2016.
SOUTH PORTAL
MOISTURE CONTENT % GRADATION
DATE 10 & 20
mm Crusher
Dust Sand
10 mm
Crusher Dust
20 mm
Sand Combine
d F.I AIV
01.07.2016 04 02 02 02 02 02 02 01 00 00
02.07.2016 04 02 02 02 02 02 02 01 00 00
03.07.2016 04 02 02 02 02 02 02 01 00 00
04.07.2016 04 02 02 02 02 02 02 01 00 00
05.07.2016 04 02 02 02 02 02 02 01 00 00
06.07.2016 04 02 02 02 02 02 02 01 00 00
07.07.2016 04 02 02 02 02 02 02 01 00 00
08.07.2016 04 02 02 02 02 02 02 02 04 02
09.07.2016 04 02 02 02 02 02 02 01 00 00
10.07.2016 04 02 02 02 02 02 02 01 00 00
11.07.2016 04 02 02 02 02 02 02 01 00 00
12.07.2016 04 02 02 02 02 02 02 01 00 00
13.07.2016 04 02 02 02 02 02 02 01 00 00
14.07.2016 04 02 02 02 02 02 02 01 00 00
15.07.2016 04 02 02 02 02 02 02 02 04 02
16.07.2016 04 02 02 02 02 02 02 01 00 00
17.07.2016 04 02 02 02 02 02 02 01 00 00
18.07.2016 04 02 02 02 02 02 02 01 00 00
19.07.2016 04 02 02 02 02 02 02 01 00 00
20.07.2016 04 02 02 02 02 02 02 01 00 00
21.07.2016 04 02 02 02 02 02 02 01 00 00
22.07.2016 04 02 02 02 02 02 02 02 04 02
23.07.2016 04 02 02 02 02 02 02 01 00 00
24.07.2016 04 02 02 02 02 02 02 01 00 00
25.07.2016 04 02 02 02 02 02 02 01 00 00
26.07.2016 04 02 02 02 02 02 02 01 00 00
27.07.2016 04 02 02 02 02 02 02 01 00 00
28.07.2016 04 02 02 02 02 02 02 01 00 00
29.07.2016 04 02 02 02 02 02 02 01 00 00
30.07.2016 04 02 02 02 02 02 02 01 00 00
31.07.2016 04 02 02 02 02 02 02 02 04 02
Total 124 62 62 62 62 62 62 35 16 08
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 64
DETAILS OF TESTING IN THE MONTH OF JULY 2016.
NORTH PORTAL
MOISTURE CONTENT % GRADATION
DATE 10 & 20
mm Crusher
Dust Sand
10 mm
Crusher Dust
20 mm
Sand Combined F.I AIV
01.07.2016 04 02 02 00 00 00 00 01 00 00
02.07.2016 04 02 02 00 00 00 00 01 00 00
03.07.2016 04 02 02 01 01 01 01 01 01 01
04.07.2016 04 02 02 00 00 00 00 01 00 00
05.07.2016 04 02 02 00 00 00 00 00 00 00
06.07.2016 04 02 02 00 00 00 00 00 00 00
07.07.2016 04 02 02 00 00 00 00 00 00 00
08.07.2016 04 02 02 01 01 01 01 02 01 01
09.07.2016 04 02 02 00 00 00 00 01 00 00
10.07.2016 04 02 02 00 00 00 00 00 00 00
11.07.2016 04 02 02 01 01 01 01 01 01 01
12.07.2016 04 02 02 00 00 00 00 01 00 00
13.07.2016 04 02 02 00 00 00 00 01 00 00
14.07.2016 04 02 02 00 00 00 00 01 00 00
15.07.2016 04 02 02 01 01 01 01 01 01 01
16.07.2016 04 02 02 00 00 00 00 00 00 00
17.07.2016 04 02 02 00 00 00 00 00 00 00
18.07.2016 04 02 02 00 00 00 00 01 00 00
19.07.2016 04 02 02 00 00 00 00 02 00 00
20.07.2016 04 02 02 00 00 00 00 00 00 00
21.07.2016 04 02 02 01 01 01 01 02 01 01
22.07.2016 04 02 02 00 00 00 00 00 00 00
23.07.2016 04 02 02 00 00 00 00 00 00 00
24.07.2016 04 02 02 01 01 01 01 02 01 01
25.07.2016 04 02 02 00 00 00 00 01 00 00
26.07.2016 04 02 02 00 00 00 00 01 00 00
27.07.2016 04 02 02 01 01 01 01 02 01 01
28.07.2016 04 02 02 00 00 00 00 00 00 00
29.07.2016 04 02 02 00 00 00 00 01 00 00
30.07.2016 04 02 02 01 01 01 01 01 01 01
31.07.2016 04 02 02 00 00 00 00 00 00 00
Total 124 62 62 08 08 08 08 25 08 08
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 65
FOR THE MONTH OF AUGUST 2016
DETAILS OF TESTING IN THE MONTH OF AUGUST 2016.
SOUTH PORTAL
MOISTURE CONTENT % GRADATION
DATE 10 & 20
mm Crusher
Dust Sand
10 mm
Crusher Dust
20 mm
Sand Combine
d F.I AIV
01.08.2016 04 02 02 01 01 01 01 01 00 00
02.08.2016 04 02 02 01 01 01 01 01 00 00
03.08.2016 04 02 02 01 01 01 01 01 00 00
04.08.2016 04 02 02 01 01 01 01 01 00 00
05.08.2016 04 02 02 01 01 01 01 01 00 00
06.08.2016 04 02 02 01 01 01 01 02 02 01
07.08.2016 04 02 02 01 01 01 01 01 00 00
08.08.2016 04 02 02 01 01 01 01 01 00 00
09.08.2016 04 02 02 01 01 01 01 01 00 00
10.08.2016 04 02 02 01 01 01 01 01 00 00
11.08.2016 04 02 02 01 01 01 01 01 00 00
12.08.2016 04 02 02 01 01 01 01 01 00 00
13.08.2016 04 02 02 01 01 01 01 02 02 01
14.08.2016 04 02 02 01 01 01 01 01 00 00
15.08.2016 00 00 00 00 00 00 00 00 00 00
16.08.2016 04 02 02 01 01 01 01 01 00 00
17.08.2016 04 02 02 01 01 01 01 01 00 00
18.08.2016 04 02 02 01 01 01 01 01 00 00
19.08.2016 04 02 02 01 01 01 01 01 00 00
20.08.2016 04 02 02 01 01 01 01 01 00 00
21.08.2016 04 02 02 01 01 01 01 01 00 00
22.08.2016 04 02 02 01 01 01 01 02 02 01
23.08.2016 04 02 02 01 01 01 01 01 00 00
24.08.2016 04 02 02 01 01 01 01 01 00 00
25.08.2016 04 02 02 01 01 01 01 01 00 00
26.08.2016 04 02 02 01 01 01 01 01 00 00
27.08.2016 04 02 02 01 01 01 01 01 00 00
28.08.2016 04 02 02 01 01 01 01 01 00 00
29.08.2016 04 02 02 01 01 01 01 01 00 00
30.08.2016 04 02 02 01 01 01 01 01 00 00
31.08.2016 04 02 02 01 01 01 01 02 02 01
Total 120 60 60 30 30 30 30 34 08 04
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 66
DETAILS OF TESTING IN THE MONTH OF AUGUST 2016.
NORTH PORTAL
MOISTURE CONTENT % GRADATION
DATE 10 & 20
mm Crusher
Dust Sand
10 mm
Crusher Dust
20 mm
Sand Combined F.I AIV
01.08.2016 04 02 02 02 02 01 02 02 02 02
02.08.2016 04 02 02 00 00 00 00 01 00 00
03.08.2016 04 02 02 00 00 00 00 01 00 00
04.08.2016 04 02 02 00 00 00 00 01 00 00
05.08.2016 04 02 02 00 00 00 00 02 00 00
06.08.2016 04 02 02 01 01 01 01 02 01 01
07.08.2016 04 02 02 00 00 00 00 01 00 00
08.08.2016 04 02 02 00 00 00 00 00 00 00
09.08.2016 04 02 02 01 01 01 01 01 01 01
10.08.2016 04 02 02 00 00 00 00 01 00 00
11.08.2016 04 02 02 01 01 00 01 00 00 00
12.08.2016 04 02 02 01 01 01 01 02 01 01
13.08.2016 04 02 02 00 00 00 00 01 00 00
14.08.2016 04 02 02 00 00 00 00 00 00 00
15.08.2016 00 00 00 00 00 00 00 00 00 00
16.08.2016 04 02 02 01 01 01 01 02 01 01
17.08.2016 04 02 02 00 00 00 00 01 01 01
18.08.2016 04 02 02 00 00 00 00 01 00 00
19.08.2016 04 02 02 01 01 01 01 02 00 00
20.08.2016 04 02 02 00 00 00 00 01 00 00
21.08.2016 04 02 02 00 00 00 00 02 00 00
22.08.2016 04 02 02 02 02 01 02 02 02 02
23.08.2016 04 02 02 00 00 00 00 02 00 00
24.08.2016 04 02 02 00 00 00 00 02 00 00
25.08.2016 04 02 02 01 01 01 01 02 00 00
26.08.2016 04 02 02 00 00 00 00 01 01 01
27.08.2016 04 02 02 00 00 00 00 00 00 00
28.08.2016 04 02 02 01 01 01 01 01 01 01
29.08.2016 04 02 02 00 00 00 00 01 00 00
30.08.2016 04 02 02 00 00 00 00 00 00 00
31.08.2016 04 02 02 02 02 01 02 02 02 02
Total 120 60 60 14 14 10 14 37 13 13
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 67
13. SAFETY REPORT
S.no. Particulars Up to last Month Current Month Cumulative
1 Total Man-hours Worked 15,291,992 2,97,623 15,589,615
2 Average No of Employees 1,88,455 6,250 1,94,705
3 Incidents 17 0 17
4 Environment Incidents 0 0 0
5 Training (Man Hours) 4,77,841 87 4,77,928
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 68
14 MINUTES OF MONTHLY PROGRESS MEETING
No Meeting during Quarter (June 2016- August 2016)
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 69
15 PHOTOGRAPHIC REPORT
LAYING OF DLC AT SOUTH APPROACH ROAD
PQC AT SOUTH APPRAOCH ROAD
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 70
LAYING OF PQC AT SOUTH APPROACH ROAD
PQC AT TOLL PLAZA LOCATION SAR
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 71
PIPE CONDUCTOR FOR CABLES AT NORTH PORTAL TECHNOLOGY BUILDING
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 72
TECHNOLOGY BUILDING SOUTH PORTAL
VIEW OF NORTH PORTAL
Quarterly Progress Report June 2016 to August 2016
Euroestudios S. L. Spain in Association with Segmental Consulting & Infrastructure Advisory (P) Ltd Page 73
CHUTE DRAIN NEAR NORTH PORTAL
TOLL PLAZA AREA VIEW AT SOUTH PORTAL