neighbourhood and infrastructure plan for resettlement of ... · for wub consult staff this was a...
TRANSCRIPT
-
1
Neighbourhood and infrastructure plan for resettlement of persons from
the Core Zone of Lalibela
Ethiopian Sustainable Tourism Development Project
VOL. V
Submitted by Submitted to:
WUB Consult
Architectural & Development Planning
Consultant
P.O.Box 19974, Addis Ababa, Ethiopia
Tel.
E-mail: [email protected]
Ethiopian Sustainable Tourism Development
Project-ESTDP
P.O.Box 100953 Addis Ababa
Tel.25115 509540; Fax:
E-mail: [email protected]
April 2011
Addis Ababa
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
wb20439Typewritten TextRP775v5
-
2
Table of Contents Abbreviations .................................................................................................................................... 4
Preface Error! Bookmark not defined.
Executive summary ................................................................................. Error! Bookmark not defined.
PART I: NEIGHBOURHOOD PLANNING FOR RESETTLERS ...................................................................... 8
1.0 Existing situation assessment of the Core Zone localities .............................................................. 9
1.1 Location ................................................................................................................................................. 9
1.2 Settlement pattern .................................................................................................................................. 9
1.3 Housing and service condition ............................................................................................................ 10
1.4 Plot patterns in the three settlements ................................................................................................... 10
1.4 The decision to relocate the three settlements ..................................................................................... 10
2.0 The planning of the new resettlement site ................................................................................. 11
2.1 Location ............................................................................................................................................... 11
2.2 Existing land use of the selected sites ................................................................................................. 11
2.3 Proposed land use of Kurakur resettlement site in the new structure plan .......................................... 12
2.4 Existing facilities ................................................................................................................................. 12
2.5 Planning proposal ................................................................................................................................ 12
2.5.1 Resettlement style ..................................................................................................................... 12
2.5.2 Proposed plot sizes in the Kurakur resettlement area ............................................................... 13
2.5.3 Land use proposal of the new plan ........................................................................................... 14
PART II: Situational Assessment, Proposal and Cost Estimates of Infrastructure design for the new
Resettlement Area at Kurakur, ........................................................................................... 17
3.0 Infrastructures ........................................................................................................................... 18
3.1 Power /Electricity supply ........................................................................................................................ 18
3.2 Telecommunication Services .................................................................................................................. 24
3.3 Storm water drainage management ................................................................................................... 25
3.3.1 The natural drainage system ........................................................................................................... 25
-
3
3.3.2 The urban storm water drainage net-work ..................................................................................... 27
3.4 Water supply ....................................................................................................................................... 30
3.4.1 INTRODUCTION ............................................................................................................................... 30
3.4.2 History of Water Supply In Lalibela Town ....................................................................................... 31
3.4.3 Reliable Drinking Water Supply Resource in Lalibela ...................................................................... 31
3.4.4 Water supply at ‘Kurakur’ ............................................................................................................... 32
3.4.5 Cost estimate of the water supply infrastructure at ‘Kurakur’. ...................................................... 33
3.5 Road Design for the new neighbourhood .............................................................................................. 37
3.6 Implementation guide lines.................................................................................................................... 41
2.6.1 Road ................................................................................................................................................. 41
-
4
Abbreviations
ANRS Amhara National Regional State
BoCT Bureau of Culture and Tourism (Regional level)
BoQ Bill of Quantities
DLCA Debre Lalibela Churches Administration.
EOTC Ethiopian Orthodox Tewahdo Church
ESTDP Ethiopian Sustainable Tourism Development Project
GOE Government of Ethiopia
ESTDP-LSMU Ethiopian Sustainable Tourism Development Project-Lalibela Site Management
Unit
LMA Lalibela Municipal Administration
MoCT Ministry of Culture and Tourism
MSO Municipal Services Office
PASDEP Plan for Accelerated and Sustainable Development to End Poverty
PA Peasant Administrations
PAP Project Affected persons
RAP Resettlement Action Plan
RPF Resettlement Policy Framework
RPIU Resettlement project Implementation Unit
TNRS Tigray National Regional State
VC Valuation Committee
WB World Bank
CIS Corrugated Iron Sheet roofing
BoQ Bill of quantities
DPL Dry Pit Latrine
-
5
Preface
Resettlement projects displace persons from places where ones memories are deeply rooted. No
amount of compensation and replacement of one artefact by another can wash away the myriads
of valued relations to places and people. However, change is natural, human beings and their
social relations are after all parts of nature. The resettlement project in Lalibela is a project which,
in the view of those who came to be near the spiritual core of Lalibela, is displacement from their
perpetual abode. Such hard feelings have made the study a soul searching one. It needed the
participation of many people who believed the conservation of the historic and cultural heritage
sites of Lalibela are beneficial not only to them but also to those residents who, deep in their
heart, love the churches, the residents of the Core Zone.
For WUB Consult staff this was a very challenging project; but finally to see would-be relocated
persons contributing positively to the planning of the new resettlement sites is very encouraging.
First and foremost, I would like to thank the staff of ESTDP in Lalibela as well in Addis Ababa who
put unreserved efforts to keep the momentum of the RAP project. I would also like to thank the
Lalibela Town administration officials for their contribution in organising public forums. The
residents of the Core Zone in Adishade, Chifrgoch, Mikael Ghibi and Gebriel Sefer and farmers in
Kurakur area deserve special mention for their trust in our work. I deeply share their concerns,
frustrations and uncertainties surrounding resettlement projects. I sincerely hope the new
settlement, with its improved layout, will compensate the loss in proximity to the churches by
providing decent and honourable spaces in lieu of the crowded and privacy-less environs of the old
Core Zone.
I would also like to thank the professional team1 of WUB Consult for their dedication to the project
ideals and their understanding of the aspiration of the project affected persons while carrying out
their professional duties.
April 2011
Wubshet Berhanu (Dr.Ing)
General Manager
WUB Consult
1 Ato Assefa Hagos; Ato Abraham Workneh, Ato Elias Gashaw, Ato Dagnachew Adugna, Ato Yohannes Tadesse, Ato
Amha Tigabu, and Ato Desalegn Berhanu and Ato Ezra Teshome participated in different capacities in the project.
-
6
Executive summary
The Government of Ethiopia has identified tourism as one of the key sectors for economic growth. The
policy stresses the need to develop the historic and cultural sites in the country so as to make them
productive sources of jobs, incomes, and economic growth. To this end, the Ethiopian Sustainable Tourism
Development Programme (ESTDP) is conceived in support of this objective and the various initiatives
already taken by the Government of Ethiopia (GOE).
As part of the development of a strategy for the tourism sector, a series of studies were planned to analyse
the situation, identify key potentials in the sector, and to develop strategic integrated destination
development plans (IDDP). A Resettlement Policy Framework (RPF) was first prepared to guide the
development of resettlement issues that may arise as a result of the development of projects for historic
and cultural sites. A series of actions were carried out as part of the tourism development strategy of the
country. Some of the important initiatives taken by the GOE at national level include:
Upgrading the tourism portfolio from a Commission to a ministry level Establishment of a public-private forum known as the National Tourism Council, which is to be
replicated at regional level.
Commitment to rehabilitate the Tourism Training Institute Upgrading transport facilities, such as roads and airports, especially in the Northern Historic Route Adopting a tourism policy Approaching and showing commitment to work with the World Bank (WB) to develop a strategy
and implement an investment program for the tourism sector.
Conducting project studies and entering agreement with WB
This document, Resettlement Action Plan for Lalibela, presents an overview of the socio-economic profile of
persons affected by the ESTDP project, categories of persons according to entitlement for compensation,
methods of property valuation, modalities for managing allocation of compensation, review of legal
frameworks for resettlement project and other RAP components. This document is an action plan
documenting overall resettlement actions while reports dealing with specific components provide details in
separate volumes. The background documents which form part of the Resettlement Action Plan (RAP) are:
1. Vol.1: Resettlement Action Plan for Lalibela (this report) 2. Vol. 2: Socio-economic situation assessment of persons affected by tourism development projects in
Lalibela 3. Vol.3 Property valuation of private properties in the Core Zone of Lalibela 4. Vol.4: Livelihood restoration plan for persons affected by tourism development projects in Lalibela 5. Vol.5: Neighbourhood and infrastructure designs for resettlement of persons from the Core Zone of
Lalibela 6. Vol.6: Environmental Impact Assessment of the resettlement project in Lalibela 7. Vol. 7: Appendices of Evidences for the RAP studies of Lalibela
Volume One deals with the resettlement action plan proper (this report) where the major issues of the
resettlement project are assessed (legal, social, administrative, and financial), project activities including
their costs and time frame is provided; implementing institutions are identified and mechanisms for
monitoring and evaluation are suggested.
-
7
Volume Two assesses the socio-economic situation of households in the Core Zone (Adishade, Chifrgoch,
Gebriel Sefer, and Mikael ghibi) and the host community in Kurakur area. The residents of the Core Zone
live in very crowded localities. However, they have built social ties over long years of living in the localities.
The socio-economic survey revealed that the majority of households are women-headed. Out of a total of
2025 residents in the Core Zone, about 44% of the residents in Adishade and Chifrgoch live in kebele
houses. The overwhelming majority of residents are Orthodox Christians; a quarter of the residents are
below 14 years of age and less than 10% are 65 years and above. There are people with disability of
different kinds (1.5%) who need special support during the relocation. The unemployed, the elderly and
women are the vulnerable groups identified by the study.
Volume Three presents the methods of property valuation, the eligibility criteria, and challenges of the task.
All houses in the Core Zone were measured, their specifications and bill of quantities prepared based on the
unit rate provided by the Zone administration. The measurement was verified to be correct by property
owners and the Resettlement Committee. The estimated cost of compensation for private house owners in
the three Core Zone localities is about thirty five million Birr (about USD 2,187,850).The compensation for
loss of farmland is estimated to be about five million Birr (about USD 312,500).
Volume Four dealt with livelihood restoration plan for relocated households. Based on the socio-economic
situation assessment reported in Vol.2, possible engagement areas of beneficiaries were identified, and
possible businesses were identified based on the capacity of the local economy of Lalibela Town. A total of
about Birr 16 million is required to construct shades, for training, as seed capital to start businesses.
Volume Five presents the new neighbourhood plan of the resettlement areas. It dealt with site selection
criteria, standards for plots and social facilities, and approaches for the subdivision of blocks into parcels.
Two sites were selected in consultation with the Office of Muncipal Services and the persons affected by
the resettlement project. The resettlement sites are located in Kurakur on both sides of the asphalted road
leading from Neakutoleab to the town centre of Lalibela. Private house owners will be allocated plots
proportional to their former plot while tenants in Kebele houses will be allocated the minimum size plot. A
total of 713 plots are provided in the two sites; however not more than 450 plots will be required by the
displaced person. The neighbourhood plan presents infrastructure design with the estimated costs too.
Volume Six dealt with the environmental impact assessment of the resettlement project. The impact of
infrastructure developments is reviewed; the impacts of persons who will not be relocated from the Core
Zone (the church school and the monastery) and that of the residents in the new resettlement area is
presented in detail. The main impact on the Core Zone is from solid and liquid waste which requires proper
mitigation measures. The analysis indicated that there are no appreciable fauna and flora nor cultural
heritage artefacts which require conservation. The would-be relocated and the host community are
households of nearly similar culture and the displacement being not too far, the social impact was found to
be minimal; or Category C according to the WB Operations manual.
Volume Seven consists of appendices that are evidences for the RAP study and documents for
implementation. Attendance sheets for the different consultative meetings, lists of persons by category of
entitlement, and other documents used for the study are presented in this volume.
-
8
PART I: NEIGHBOURHOOD PLANNING FOR RESETTLERS
-
9
1.0 Existing situation assessment of the Core Zone localities
1.1 Location
Addish Ade: As we can see on diagram #1, Addish Ade is located North-East of the church
compound just on topographically elevated position. At the foot of this settlement is the church
compound. According to geological evidence, the settlement is sitting on the top of the same
rock formation from which the churches are hewed.
Chifrigoch: This is the settlement located west of the church compound and topographically, its
location is downstream.
Gebriel Sefer: Its location is within the church compound but to the South.
Figure#1: Location of the three settlements and the new resettlement site
1.2 Settlement pattern
The settlement pattern in all the three settlements can be defined as organic. The location of the
houses within a compound and in relation to other houses, the size and Streets, access patterns,
open spaces, etc have all evolved from the very needs of the residents themselves.
Regarding density, due to their location in close proximity to the main entrance to the church
and the weekly market respectively, Addish Ade and Chifrigoch are high density areas while the
third settlement is very low density.
-
10
1.3 Housing and service condition
The three settlements were the most deprived areas in the city for the last 20 years. The previous
master plan has identified these three settlements as “Conservation areas”. Misinterpreted by
local technicians as “no improvement zone”, residents were not allowed to maintain their
houses, build toilets, kitchens, or any other private or communal facilities.
Such planning decision had its toll on the churches as residents from these three settlements
were forced to use the church compound or the open spaces around for disposing their wastes
(including human).
1.4 Plot patterns in the three settlements
Table #1 presents plot sizes in the three settlements. As we can see in this table, 67.4% of the
residents occupy plots whose sizes is below the minimum provided by the city‟s land policy
which is 150m2.
Table 1. Number of Plots by category in the neighbourhood plan for persons to be
relocated from the Core Zone
S.No. Size category in m2
No. of plots in Size category Total by
category Adishade Chifrgoch Gabriel sefer
1 600 2 2 11 15
Total plots by locality-owners 174 78 49 301
Total kebele owned (tenants) 105 25 xxx 130
Total Number of plots needed for allocation (including 130 kebele tenants) 431
Source: Property survey by WUB Consult, August 2010
1.4 The decision to relocate the three settlements
One of the major components of the new Structure Plan of Lalibela was the redefinition of the
church compound which was made in close collaboration with the ministry of culture. Two
workshops were organized by the ministry where experts presented their views on how to
protect the churches. One of the major outcomes of such discussions was the decision to
-
11
redefine the old church boundary. Using UNIESC guidelines, the study team proposed two
boundaries, one for the core area where no intervention will be allowed and one for the buffer
zone where intervention will be controlled. The proposal was unanimously accepted by the
residents of the city.
This boundary definition among other things called for the relocation of all settlements that fall
within the core zone since this is the area where no intervention other than those related to the
church is allowed.
The relocation of the three settlements (Addish Ade, Chifrigoch and Gebriel Sefer) is thus the
result of this decision.
2.0 The planning of the new resettlement site
2.1 Location
As we can see in figure #2, Kurakur resettlement site is located south of the city towards
Nakotoleab. The site is divided into two parts by the main highway
Figure #2: The selected resettlement site at Kurakur
2.2 Existing land use of the selected sites
As can be seen in the diagram, Kurakur is currently a farm land partly occupied by scattered
farmer‟s villages and partly by recently resettled communities coming from the church compound.
-
12
A small part of the site is also reserved as “investment promotion area” of which part is already
developed by some investors.
Fig. # 3: Kurakur resettlement site
2.3 Proposed land use of Kurakur resettlement site in the new structure plan
According to the new structure plan of the city (prepared in 2009-2010), Kurakur site is proposed
for the expansion of residential and mixed activities.
2.4 Existing facilities
Kurakur site has its strength from service distribution point of view. Within a radius of less than
1km, there is one high school, one kinder garden and one elementary school. The main bus terminal
of the town is also near this site.
2.5 Planning proposal
2.5.1 Resettlement style
Group resettlement: One of the reasons for choosing a big site for relocation is to undertake a type
of “group resettlement” approach. By so doing, people residing in the same area for many years and
organized under different type of social and economic organization would be able to continue their
old way of life in an improved living environment.
Provision to the host farming community: The proposal does not only provide to the new comers
but also to the host community. Farmers‟ houses in the area are incorporated in the plan with the
-
13
maximum care taken not to demolish any of them. The only adjustment made is regarding the size
of the plots. With the new readjustment, every farmer in the area will be allowed to retain his house
and a maximum of 500 m2 for residence. As we can see in the final plan, the twisting and
narrowing of some of the roads in the area is due to this attempt to retain existing settlements intact.
2.5.2 Proposed plot sizes in the Kurakur resettlement area
From the data collected during the field survey in the three settlements, the total number of plots
needed to resettle the people coming from the Core Zone is 301 for private property owners and 130
for kebele tenants. What the new plan has provided is the following:
1. To accommodate the 301 residents, the plan has reserved a total of 524 plots which exceeds the original number by 223.
2. It has also reserved 189 plots of 120m2 size out of which 130 are to be used for Kebele tenants and the remaining to be kept for other unforeseen events.
The excess land in the project area in all size categories can be used to accommodate future growth
requirements of the city as proposed in the new structure plan. Part of it can also be leased to high
income groups to create a strong social mix in the area.
Table 2: Proposed plot sizes in Kurakur resettlement area
Plot sizes in the Core Zone
(in m2)
Total number of plots
Average plots sizes proposed
Total provided Excess
For kebele tenants None (130) 120 (8x15) 189 59 600 15
Total 298 (130) 713 226 (59) (a) 65 Mixed commercial plots (150m2 plot size) are provided along the main road. (b) 189 plots (120m2) are provided for allocation to kebele tenants (130 tenants)
Source: Neighbourhood plan by WUB Consult April 2011
-
14
2.5.3 Land use proposal of the new plan
Residential land use
Residential plots for resettlers: as we can see in the table, out of the total of 31.8 hectares, 52.5% is assigned for residential. Each resident will be given a plot of land between 150m2
and 500m2. This is depending on the size of the plots residents left behind in their old
neighborhoods.
Plots for the host community: As explained above, the plan has maintained most of the houses untouched. Plots of 500m2 are assigned to farmers whose residing in the area. For
the few houses that will be demolished as part of the provision of services and infrastructure
in the area, replacement plots are reserved just adjacent or nearby the original site.
Commercial land use
Mixed land use: This land use category includes plots ( a total of 65) facing the main road on both sides. Such plots are to be allocated for people who will combine residential with other
income generating activities as part of the livelihood program. The total area reserved for mixed
land use is 1.1 hectares.
Daily market: in addition to shortening the distance people have to travel to the main market in the city which is about one hour walking distance, the daily market is also important as a source
of employment for the poor people that move to the settlement area. The location of this market
is just under the big “Worka tree” (see the photo below) making it a shaded space for both the
customers and sellers. As the area where this market is located is investment area and many of
such investors have already built new hotels, the daily market has to be managed in such a way
that it contributes to the promotion of the tourist industry. In other words, the design of the
stalls, the provision of adequate sanitation services, and diversity of the goods on sale have to be
taken with this objective in mind.
-
15
Picture #--: The Warka tree in the site whose shade is proposed to be a market area
Commercial area: three sites with total area coverage of 3870m2 are reserved for commercial activities. This land use is exclusively for business.
Services
Besides residential plots, the plan has also considered the provision of other services that are needed
by the residents particularly in Kurakur area. Two of such services are:
• Health post: a small plot of land (1347m2) just by the road side is reserved for social services including a health post.
• Open spaces: due to scarcity of land in the town, the settlement is relatively dense. Yet, the plan has made provision for a variety of open spaces in the area. Some of these sites are
steep areas which if planted with ornamental trees will make the area beautiful and pleasing.
Other small open spaces are also reserved in the middle of the blocks for social encounters
and as children play grounds. The total size of such planned area is 2900 m2.
Green areas
• Formal green: this is green area design for specific purpose which in this case is to be used for social gatherings, economic activities and children play ground. The total of such land
amounts to 2900m2
• Informal green: this is green area to be developed in areas which are not habitable due to topographic reasons and proximity to gullies. Their purpose is more of protective and
decorative. Such areas account for 2.31 hectares.
Table 3: land use types and sizes in the project area
No Land use type Area coverage (in hectares) percentage
1 Residential area for new settlers and farmers 16.69 52.5
2 Mixed land use 1.1 3.46
3 Commercial land use 0.387 1.21
4 Daily market 0.44 1.38
6 Existing Elementary school 2.165 6.83
7 Health post 0.135 0.4
7 Formal green 0.29 0.91
8 Informal green 2.31 7.26
9 Circulation 8.273 26.01
Total project area 31.79 100
-
16
FINAL RESETTLEMENT PLAN FOR KURAKUR
-
17
PART II: Situational Assessment, Proposal and Cost Estimates of
Infrastructure design for the new Resettlement Area at Kurakur,
-
18
3.0 Infrastructures
Introduction
Infrastructure is engine to any economic development and is a must to ensure the well fare of
citizens. It includes Social infrastructures (housing, health facilities, rehabilitation centers, public
libraries and recreational facilities), public infrastructure (Roads, Bridges, public houses, water
supply and sanitation, electricity, telecommunication, storm water drainage, sewerage, rail ways,
water ways, sea ways, air ports, etc), green infrastructure (water ways, wetlands, woodlands,
wildlife habitats, green ways, parks and conservation lands, water resources etc), environmental
infrastructure (water supply, sanitation, hazardous and solid waste management).
Although the scope of infrastructure is broad, in this study infrastructure particularly means those
basic physical infrastructures and utilities which should be fulfilled to satisfy the minimum needs
of the relocated people. In this sense it includes water supply, Electricity, Road, storm water
drainage, telecommunication, and sanitation facilities (public latrines and solid waste management
facilities). Thus, the infrastructure study is, particularly, emphasized on the new settlement area, at
„Kurakur‟.
3.1 Power /Electricity supply
Introduction
power supply is one of the basic infrastructures to urban life. It is fundamental to meet the needs of
the community, particularly in areas like Lalibela where forest resources and other fuel sources are
minimal. In addition, the expansion and use of electricity in the new settlement areas will help to
prevent further deforestation on few available plant species.
There is a power supply line that passes near to the new settlement site and which can fulfill the
needs of the relocated people. The only required materials are one transformer which step-down
from 15,000kv to 400kv, standard wire to reach power from the feeder line to each residence/house
and meters for each users.
Three types of treated posts/poles will be required to carry the required electricity /power from the source to each individual‟s house. The three types of poles are:
11m height = 457.66 birr per pole 10 m height = 424.54 birr per pole 9m height = 389.90 birr per pole.
One Transformer is needed to transfer/divert electric power from the nearby line to the new settlement sites for the relocated community. This transformer will be a 200kv and has the
capacity to step-down from 15,000kv to 400kv which is appropriate to the new site.
The cost of the transformer is 119,845.50 birr (fully equipped with all necessary installed accessories) (Source: Lalibela power supply service).
-
19
Table-1: Distance between poles and cost of poles for different height poles. No Height
of pole
(m)
Cost per
pole (birr)
Use/function Distance between poles (meters) Depth of the pole
to be buried below
ground
1 11 457.66 higher voltage (15kv)
carrier
60-70
60m on plane surfaces. 70 on rugged/undulating
surfaces
1.20m to 1.70m
2 10 424.54 To carry transformer
(200kv)
Transformer (no need)
3 9 389.90 Low voltage carrier 30-40
30m on plane surfaces 40m on undulating
surfaces2.
Source: Lalibela Electric supply district (August 23, 2010)
Cost to install one transformer (labor cost (service charge)) is 2,106.72 birr. The cost of an electric meter (5-10A*220v) is 1,000 birr. Cost to install one electric meter is 91 birr (labor cost (service charge). To dig one hole (60-70cm depth) is 40birr per hole. (One man per day) + 35 Birr to erect/fix
the pole.
Required cables to the meter are: 2*4mm = 18 birr per linear meter. 2*6mm = 21 birr per linear meter. 2*2.5mm = 15 birr per linear meter.
AC-50 cable/wire is used to carry power both through the high and low tension lines which costs 8.41 birr per meter.
Electrification (electric power installation). Figure-1 shows the series of installation.
Fig.-1.Schematic presentation of the electric power source, Transformer, meter & users
Note: Cost of AC-cable = 8.41 birr per linear meter of cable.
Cos of ABC-cable = 63.45 birr per linear meter of cable.
All the expenses between the source and the meter is covered by the City
Administration (service) or municipality and between the meter and End-users by
the customer or individual users.
2 For the case of the Lalibela Rehabilitation Action Plan (RAP) the distance between poles adopted is 40m.
-
20
At this time it is not possible to install the electric power to the relocated people at „Kurakur‟ because:
All the necessary electrical materials which have mentioned above including the transformer are not at hand (no material) (source: Lalibela power service). But, the Lalibela Electric
customer service center told me that the transformer is at shipping (August, 2010).
The techniques of installing electric poles in relation to streets has displayed graphically here under:
Fig-2 Position of Road, Residences and Electric poles.
Source: Lalibela power supply district (Customer service center, Kedir Abdu, August, 2010).
The cost estimate of power supply for the new neighbourhood at Kurakur is provided in Table 2.
Table-2: Total cost estimation of power supply for the Kurakur resettlement area
No Activity/
item
Site power supply line Require
d poles
Unit Qt Unit price
(Birr)
Total price
(Birr) Code Length(m)
1 Treated
Electric pole
Kurakur P1-13 421
7
pcs
7
389.90 2729.3
2 Treated Electric pole
Kurakur P2-4 372 7
pcs 7
389.90 2729.3
3 Treated Electric pole
Kurakur P3-4 327 6
pcs 6
389.90 2339.4
4 Treated Electric pole
Kurakur P4-3 279 5
pcs 5
389.90 1949.5
5 Treated Electric pole
Kurakur P5-3 282 5
pcs 5
389.90 1949.5
6 Treated Electric pole
Kurakur P6-5 219 5
pcs 5
389.90 1949.5
7 Treated Electric pole
Kurakur P7-6 161 4
pcs 4
389.90 1559.6
3 P1-1 stands for power supply line No.1 on Road No.1, P2-4 = Power supply No.2 on Road N0.4 and the others
interpreted in such a fashion.
-
21
No Activity/
item
Site power supply line Require
d poles
Unit Qt Unit price
(Birr)
Total price
(Birr) Code Length(m)
8 Treated Electric pole
Kurakur P8-6 152 4
pcs 4
389.90 1559.6
9 Treated Electric pole
Kurakur P9-2 122 3
pcs 3
389.90 1169.7
10 Treated Electric pole
Kurakur P10-2 127 3
pcs 3
389.90 1169.7
11 Treated Electric pole
Kurakur P11-4 138 3
pcs 3
389.90 1169.7
12 Treated Electric pole
Kurakur P12-4 65 2
pcs 2
389.90 779.8
13 Treated Electric pole
Kurakur P13-11 192 4
pcs 4
389.90 1559.6
14 Treated Electric pole
Kurakur P14-11 177 3
pcs 3
389.90 1169.7
15 Treated Electric pole
Kurakur P15-10 94 3
pcs 3
389.90 1169.7
16 Treated Electric pole
Kurakur P16-10 88 3
pcs 3
389.90 1169.7
17 Treated Electric pole
Kurakur P17-8 206 4
pcs 4
389.90 1559.6
18 Treated Electric pole
Kurakur P18-8 210 4
pcs 4
389.90 1559.6
19 Treated Electric pole
Kurakur P19-28 170 4
pcs 4
389.90 1559.6
20 Treated Electric pole
Kurakur P20-7 214 4
pcs 4
389.90 1559.6
21 Treated Electric pole
Kurakur P21-7 214 4
pcs 4
389.90 1559.6
22 Treated Electric pole
Kurakur P22-19 120 3
pcs 3
389.90 1169.7
23 Treated Electric pole
Kurakur P23-19 123 3
pcs 3
389.90 1169.7
24 Treated Electric pole
Kurakur P24-18 40 2
pcs 2
389.90 779.8
25 Treated Electric pole
Kurakur P25-18 38 2
pcs 2
389.90 779.8
26 Treated Electric pole
Kurakur P26-23 214 4
pcs 4
389.90 1559.6
27 Treated Electric pole
Kurakur P27-33 403 7
pcs 7
389.90 2729.3
28 Treated Electric pole
Kurakur P28-33 291 6
pcs 6
389.90 2339.4
29 Treated Electric pole
Kurakur P29-22 35 2
pcs 2
389.90 779.8
30 Treated Electric pole
Kurakur P30-32 261 5
pcs 5
389.90 1949.5
31 Treated Electric pole
Kurakur P31-32 249 5
pcs 5
389.90 1949.5
32 Treated Electric pole
Kurakur P32-22 370 7
pcs 7
389.90 2729.3
33 Treated Electric pole
Kurakur P33-32 240 5
pcs 5
389.90 1949.5
34 Treated Electric pole
Kurakur P34-29 414 7
pcs 7
389.90 2729.3
-
22
No Activity/
item
Site power supply line Require
d poles
Unit Qt Unit price
(Birr)
Total price
(Birr) Code Length(m)
35 Treated Electric pole
Kurakur P35-29 371 7
pcs 7
389.90 2729.3
36 Treated Electric pole
Kurakur P36-30 383 7
pcs 7
389.90 2729.3
37 Treated Electric pole
Kurakur P37-31 202 4
pcs 4
389.90 1559.6
38 Treated Electric pole
Kurakur P38-35 550 9
pcs 9
389.90 3509.1
39 Treated Electric pole
Kurakur P39-35 555 9
pcs 9
389.90 3509.1
40 Treated Electric pole
Kurakur P40-57 193 4
pcs 4
389.90 1559.6
41 Treated Electric pole
Kurakur P41-57 188 4
pcs 4
389.90 1559.6
42 Treated Electric pole
Kurakur P4236 73 2
pcs 2
389.90 779.8
43 Treated Electric pole
Kurakur P43-36 78 3
pcs 3
389.90 1169.7
44 Treated Electric pole
Kurakur P44-37 83 3
pcs 3
389.90 1169.7
45 Treated Electric pole
Kurakur P45-37 82 3
pcs 3
389.90 1169.7
46 Treated Electric pole
Kurakur P46-41 268 5
pcs 5
389.90 1949.5
47 Treated Electric pole
Kurakur P47-41 263 5
pcs 5
389.90 1949.5
48 Treated Electric pole
Kurakur P48-38 79 3
pcs 3
389.90 1169.7
49 Treated Electric pole
Kurakur P49-38 80 3
pcs 3
389.90 1169.7
50 Treated Electric pole
Kurakur P50-42 192 4
pcs 4
389.90 1559.6
51 Treated Electric pole
Kurakur P51-42 143 3
pcs 3
389.90 1169.7
52 Treated Electric pole
kurakur P52-47 105 3
pcs 3
389.90 1169.7
53 Treated Electric pole
kurakur P53-47 105 3
pcs 3
389.90 1169.7
54 Treated Electric pole
kurakur P54-49 106 3
pcs 3
389.90 1169.7
55 Treated Electric pole
kurakur P55-43 79 3
pcs 3
389.90 1169.7
56 Treated Electric pole
kurakur P56-43 79 3
pcs 3
389.90 1169.7
57 Treated Electric pole
kurakur P57-44 86 3
pcs 3
389.90 1169.7
58 Treated Electric pole
kurakur P58-44 80 3
pcs 3
389.90 1169.7
59 Treated Electric pole
kurakur P59-46 308
6
pcs 6
389.90 2339.4
60 Treated Electric pole
kurakur P60-46 329 6
pcs 6
389.90 2339.4
61 Treated Electric pole
kurakur P61-39 73 2
pcs 2
389.90 779.8
-
23
No Activity/
item
Site power supply line Require
d poles
Unit Qt Unit price
(Birr)
Total price
(Birr) Code Length(m)
Sum-1 12,161 258 258 389.90 100,594.20
Labor + erecting (concreting) cost pcs 258 175 45,150.00
3 Wire cost (AC-50 cable) m 12,161
18.41
233,884
4 Transformer cost pcs 1 119,845.5 239,691
sum-2 518,725
5 Grand total (sum-1 + sum-2) 619,320
6 Contingency (15%) 92,898
7 Grand total (with contingency) 712,2184
Source: own computation from field survey and electric supply plan (March 2011)
Note: The distance between poles is chosen to be 70m, because the area is rolling.
Summary, from Table-2, above:
A total of 12,161m electric wire is required. A total of 258 treated electric poles are required. One step-down transformer is required at „Kurakur‟ For a complete electric/power supply installation a total of 712,218.00 Birr is estimated.
Fig-3: Power supply net-work plan of ‘Kurakur’
Ssource: own proposed plan March 2011
4 The grand total only includes the cost from source to house hold meter (the meter cost is not included, because the
cost from the electric meter to end users should be covered by the respective house hold/owner (client))
-
24
3.2 Telecommunication Services
Introduction:
Particularly these days with globalization and technological advancement telecommunication has a
vast contribution in economic and social development. In line with this the development/use of
telecom services in the new resettlement areas will help the relocated community to reinforce their
economic and social development. Specially, this will enable them to strengthen their social tie with
their previous neighbors and families.
Total population in Lalibela town = 15,873 (CSA, 2007). According to the Lalibela
Telecommunication service/office, customers having fixed telephone lines are 1,100 (6.93 %).
Whereas up to August 2010 there were no wireless (CDM) telephone users, but according to the
Lalibela telecommunication service this service will commence & be open for all who need to have
this service by September 2010, because the old telecommunication system was fully replaced by
the new CDM (wireless) system.
From the above data, we have ensured that there will no problem to install telephone lines in the
new settlement area. The telephone line is CDM (wireless) because the use of fixed telephone line
in Lalibela becomes outdated. On the other hand, those residents who need to install fixed line will
no longer get any service as the service in the town has shifted from fixed to CDM-wireless.
During field survey (at the time of collecting this data) it was observed that the Chinese were
transferring the fixed line to the new technology, CDM-wireless telephone (as evidence see Fig-4).
Fig-4: Transfer of old telephone system to the New (CDMA) system (August, 2010).
According to the Lalibela telephone service manager, Ato Debebe Mengistu, the process of
transferring from fixed to CDM-wireless has started by July, 2010 and is expected to be finalized
-
25
for final test by mid september 2010. That is, as per the residents‟ demand the service will be
installed for all who need to get telephone service including the relocated people at “Kurakur”
Cots/expenses to install CDM-wireless telephone (if it is from the tele office) are as follows:
Cost of CDM-wireless telecom service:
a. CDM-wireless apparatus for households and interested groups is governed by prepaid system
= 832 birr plus 217 birr for service charge (installation cost)-it has no antenna because as it is a
prepaid (card based) no need of taking a reading.
b. CDM-for institutions needs to install antenna because the payment is post paid. Thus, to take
reading it is must to know how much it counts with the help of the installed antenna.
o Ato Debebe added the following points about telephone service: Their office will give a greater attention/focus on the use of the new technology CDM-
wireless telephone system.
The process of transferring the fixed telephone line system to the new technology, CDM-wireless, is under way.
The service of fixed telephone line is dead or will be terminated besides; the question of installing fixed telephone lines from customer sides will not get service or will not be
treated.
o The new technology, CDM-wireless, works where there is net-work. In relation to this, in Lalibela, there is accessible net-work and it is possible to use up to „Nakuteleab‟ locality.
3.3 Storm water drainage management
Introduction:
It is part of urban infrastructure which is significant to safely remove the run-off or storm water
generated within an urban center or enters in to an urban center from external sources. Thus, storm
water drainage lines are abiding structures to keep or elongate the service life of other urban
utilities.
3.3.1 The natural drainage system
The area is surrounded by highly degraded and bare terrains and hills including Meskel Kebera,
Asheten and Ager ersha. These terrains and hills (mountains) (fig.-5) located at the upper catchment
of the new settlement area, „Kurakur‟. They are situated just to the above side of the Asphalt road
that runs from the Air port to Lalibela town. That is, the flood generated from these mountains will
enter into the new settlement area and will be an incidence of flooding unless sustainable flood
control techniques are put in to effective (practice). Flood control techniques include area closure to
let the site for rehabilitation and afforestaion of the hills, increasing the proportion of green spaces,
combining physical and biological conservation measures such as terracing with plantation.
-
26
Fig.-5: Degraded terrains located at the upper catchment of “Kurakur”.
Within the site there is one hill/terrain named „Kebo‟. This terrain, alike the others is highly
degraded. That is, along with urbanization the problem of flood generation will increase to a greater
amount. Thus, to sustainably reduce the problem of flooding this terrain shall be treated both with
biological and physical soil and water conservation measures such as vegetating with fast growing
and appropriate trees.
The municipality should give a greater attention to soil and water conservation measures. In the new
settlement site, urbanization along with its impervious layer (fig.-6) (due to soil degradation/erosion
the area is highly exposed resulting in bed rock layer, crop-out) the storm water will be maximum
because on-site infiltration is almost impossible.
The site is highly dissected by gullies and gorges (fig.-7). It is highly undulating and rugged. It is
sloppy to provide storm water drainage lines for the safe removal of flood to final receiving
systems- this will increase the speed and volume of flood. Thus, the
Fig.-6: Impervious layer within the resettlement area
(Source: Field survey, August 2010).
-
27
best remedial mechanism will be pre-controlling/prevention techniques. This is because the post
(after-problem) prevention is inappropriate rather it will intensify the problem. The pre-controlling
mechanisms (mitigation measures) include:
Roof rain water harvesting techniques-best before: prevention method. River bank rehabilitation methods. River buffering techniques. Terracing. Check dams and gabion retaining walls. Tree plantation on river banks and degraded hills. To sustainably alleviate the flood problem on down catchment residences and properties
the terrain „Kebo‟ should be planted with trees in association with other physical soil
and water conservation techniques.
Fig.-7: Dissected gullies within the new settlement area, Kurakur.
(Source: Field survey August, 2010).
The mountains: „Meskel Kebera‟ „Ashten‟ and „Ager ersha‟ should be vegetated with trees and other fast growing shrubs. Rehabilitating these terrains /mountains.
3.3.2 The urban storm water drainage net-work
Introduction: This is a net work of individual storm water drainage lines to remove the collected
storm water from each drain. The objective of net-worked drains is to safely remove the storm water
to final receiving systems by accepting one from the other. This is the remedial process. The pre-
medial process is encouraging on-site infiltration through porous structure like grassing or
greeneries.
a. Planning and Designing process:
It has planned and designed based on the proposed the Road net-work but as it has strictly
emphasized above, storm water drainage lines will not sustainably solve the problem rather
-
28
intensifying it. Thus, applying the above techniques will be appropriate and sustainable means. The
process/procedures of storm water drainage lines planning and design have presented in the
preceding pages.
As this is the case, the generation of storm water as a result of urbanization and imperviousness is
inevitable. Thus, the safe removal of the generated storm water in to final receiving system is a
must. To do this, the rainfall data of the surrounding area was the key input.
Table-3: Summary of storm water drainage lines.
No Site Drain code5 Length (m) Contour (m) Water shed area of each
drains
Initial terminal Code Area (m2)
1
„Kuraur‟
D16 386 2452 2425 WS1 11350
2 D3 320 2470 2452 WS3 16846
3 D4 361 2443 2426 WS4 19975
4 D7 212 2437 2425 WS7 10205
5 D8 212 2435 2428 WS8 9620
6 D15 346 2461 2450 WS15 23527
7 D22 148 2438 2432 WS22 6198
8 D23 199 2458 2450 WS23 9739
9 D27 210 2469 2452 WS27 17229
10 D29 99 2428 2425 WS29 4012
11 D35.1 187 2475 2468 WS35.1 10963
12 D35.2 190 2466 2457 WS35.2 7641
13 D41 123 2482 2462 WS41 2491
14 D52 545 2455 2440 WS52 29842
15 D55 171 2500 2468 4S55 5522
16 D63 180 2463 2452 WS63 6203
17 D6 52 2452 2451 WS6 1520
18 D61 135 2462 2452 WS61 5799
19 D2 117 2452 2443 WS2 4191
20 D64 111 2466 2460 WS64 4057
Sum 4,304m
~4.3Km
206,930m2
Source: WUB Consult March 2011: GIS analysis
5 The drain codes have assigned correspondingly to the code of Roads.
-
29
Based on the analysis, the storm water drainage is designed by considering the topographic feature,
vegetation cover, rainfall data (intensity) and catchment area of each drainage lines. This presented
in Table 4 below.
Table-4: Storm water drainage lines design sheet
Code
flow direction
elevation
channel
length
(m)
Q
(m3/s)
Dp
(m)
Rectangular
Ap
(m2)
V
(m/s)
from to initial terminal
B7
(m)
D 8(m)
D1 D1 outlet 2452 2425 386 1.55 0.31 0.39 0.35 0.07 3.89
D3 D3 D1 2470 2452 320 1.16 0.29 0.36 0.34 0.06 3.10
D4 D4 outlet 2443 2426 361 1.27 0.31 0.38 0.35 0.07 3.17
D7 D7 outlet 2437 2425 212 1.11 0.28 0.35 0.34 0.06 3.03
D8 D8 outlet 2435 2428 212 1.09 0.31 0.39 0.36 0.08 2.71
D15 D15 D1 2461 2450 346 1.18 0.32 0.40 0.36 0.08 2.82
D22 D22 outlet 2438 2432 148 1.07 0.30 0.37 0.35 0.07 2.78
D23 D23 D6 2458 2450 199 1.10 0.30 0.38 0.35 0.07 2.82
D27 D27 outlet 2469 2445 304 1.18 0.27 0.34 0.34 0.06 3.35
D29 D29 outlet 2428 2425 99 1.05 0.31 0.39 0.36 0.08 2.60
D35.1 D35.1 outlet 2475 2468 187 1.11 0.31 0.38 0.35 0.07 2.81
D35.2 D35.2 outlet 2466 2457 190 1.08 0.29 0.36 0.34 0.07 2.88
D41 D41 outlet 2482 2462 123 1.04 0.23 0.28 0.31 0.04 3.55
D52 D52 outlet 2455 2440 545 1.18 0.33 0.41 0.37 0.09 2.75
D55 D55 outlet 2500 2468 171 1.09 0.22 0.28 0.31 0.04 3.74
D63 D63 D6 2463 2452 180 1.07 0.28 0.34 0.34 0.06 3.01
D6 D6 D2 2452 2451 52 1.02 0.34 0.42 0.37 0.09 2.35
D61 D61 D2 2462 2452 135 1.08 0.27 0.33 0.33 0.06 3.13
D2 D2 D4 2452 2443 117 1.17 0.27 0.34 0.34 0.06 3.32
D64 D64 outlet 2466 2460 111 1.06 0.28 0.35 0.34 0.06 2.91
Source: WUB Consult March 2011
Table -5: Cost estimate of the drainage lines provision/construction.
No Description/item unit Qt Unit price (Birr) Total price (Birr)
1 Total drainage line Km 4.304 213,745.00 919,959.00
2 Contingency (15%) 137,994.00
Total 1,057,952.00
Source: own computation from storm water drainage plan (March 2011).
7 “B” stands for Base of a rectangular drainage line.
8 “D” stands for depth/Height of a Rectangular drainage line.
-
30
Fig-8 Storm water drainage plan in ‘Kurakur’
Source: WUB Consult March 2011
3.4 Water supply
3.4.1 INTRODUCTION
Water is essential to sustain life, every community has the right to get safe and adequate water
supply. However, 1.1 billion People live without clean, safe and adequate water throughout the
world. About 4% of all deaths and almost 6% of the total global burden of disease are the result of
inadequate and unsafe water supply and sanitation facilities (WHO, 2003). Protection of water
supplies from contamination is the first line of defense with the focus on “access” to safe water,
there is concern about actual quality of drinking water. About 1.8 million people (90% are children
-
31
HIV/AIDS. Lalibela, which is one of the urban centers in Ethiopia, also faces the aforementioned
problems.
3.4.2 History of Water Supply In Lalibela Town
The first gravity water supply system in Lalibela was installed in 1955E.C by Le'elit Hirut Desta for
only 'sebat woira' hotel, (which is owned by Lalibela Churches), from 'Asheten' spring9 Although,
the water supply was not sufficient to meet the demand of the town's residents, the first pressurized
public spring water supply system which lasted from 1974E.C to 1986E.C (1982-1994), was
developed and distributed to Lalibela town from a specific locality called 'Medagie'. This source
was supplying the town until the emergence of 'Kenknit' spring in 1986E.C. (1994).
As interviews from different residents of Lalibela revealed that Lalibela has got a formal piped
water system since 1992(1986E.C) some 17years ago from a spring called "Kenkenit", which is
13km North of the town with a discharge rate of 5 liters per second and the supply was through
gravity system. The next pressurized (non-gravity) water supply system was dug in 2005 from a
bore hole about 12.5km South of the town with a discharge rate of 15 liters per second.
3.4.3 Reliable Drinking Water Supply Resource in Lalibela
As various studies and field surveys indicated that the reliable water resource for Lalibela town is
ground water. This reliable resource is located at "Shumshiha", which is about 22 kilometers south
of Lalibela town-near to the Airport. Within this area there is a potential ground water resource.
Currently there are four bore holes around Shumshiha which are dug and prepared for drinking
purposes, of which two of them are for the town of Lalibela, one for Lalibela Air port and one for
"Shumshiha" village itself. Their relative status and discharge rates are depicted in Table-6, below.
Table-6 Existing drinking water bore holes for Lalibela town and for its hinter land.
No. Name of bore
hole
Discharge
rate(lt/sec)
Distance
(km)
Status/condition Serves to Year of
establishment
1 Bore hole-I 15 12.5 functional Lalibela town 2005
2 Bore hole-II 20 12 functional Lalibela town 2008
3 Bore hole-III 3 22 functional Air port 12years ago
4 Bore hole-IV 3 21 Non-functional Shimshiha 20years ago
Source: Plan Ethiopia, 19May, 2009.
9 Source: Lalibela water supply service
-
32
Table-7: Style and period of water supply Shift basis system.
No. Moths
Water is distributed every From To
1 July October Day
2 November January Three days once
3 February March Four days once
4 April June Six days once
Source: field survey from the Town water supply service 16-18May, 2009.
From Table-7, it can be concluded that there is a serious water shortage problem in the Tourist town
Lalibela and this may be a barrier for tourism development in the town and above all the sanitation
and the health condition of the community is at risk, almost all of the latrines are pit. This has a
greater impact for diseases to be transferred from one person to another like diarrhea and others, on
the other hand the socio-economic status of the people are/will be affected. Thus, some permanent
water delivery/supply mechanisms should be devised to ensure the social and economic
sustainability at Kurakur, in particular and Lalibela town, in general.
3.4.4 Water supply at ‘Kurakur’
The new settlement area is located some distance south of Lalibela Town. It is reserved for the
relocated people from the Church compound. As a general truth water is basic necessity for living
things. In line with this, the town‟s water supply service has installed water supply lines to the new
settlement („Kurakur‟ site) for peoples displaced from Michael locality/„sefer‟. The sizes of the
installed water pipes are:
i. The main line = 2 and 3 inches. ii. The secondary (accessible) line = 1.5 inch.
These lines have the capacity to serve all the relocated people including those from the Core Zone‟.
„Shimshiha‟, which has started its function in October 2009, is the ultimate source of water supply
for the new settlement area. It will supply all the water demand for the relocated people.
The average water supply per head is 40-80 liters and 20 liters when the water supply is on shift
basis (once every three days). Currently, the bore hole which functional has a capacity of 6 liter per
second; while the other borehole which produces 13 liters per second was damaged and is non-
functional. If this bore hole is maintained the 40-80 liters per day per head will be
maintained/secured. The price/cost of one cubic meter of water in Lalibela town is 1 birr
(minimum) and the maximum is 2.50 birr.
-
33
3.4.5 Cost estimate of the water supply infrastructure at ‘Kurakur’.
i. Distribution lines
The total required supply lines will be estimated from the proposed Road net-work. That is, two
accessible lines will be installed on opposite edges of each road. Thus, on the basis of this the total
pipe lines along with their lengths will be estimated to get the total required cost.
Table-8: Water supply lines cost estimates No Site Pipe line Required
pipes
Distribution line
type
Material type
Code Length
1 Kurakur WS1-110 420 7011 tertiary GI pipe
2 Kurakur WS2-2 194 33 tertiary GI pipe
3 Kurakur WS3-2 127 22 tertiary GI pipe
4 Kurakur WS4-3 295 50 Secondary GI pipe
5 Kurakur WS5-3 293 49 tertiary GI pipe
6 Kurakur WS6-2 280 47 secondary GI pipe
7 Kurakur WS7-4 334 57 secondary GI pipe
8 Kurakur WS8-4 139 24 tertiary GI pipe
9 Kurakur WS9-5 71 12 tertiary GI pipe
10 Kurakur WS10-5 43 8 tertiary GI pipe
11 Kurakur WS11-5 117 20 tertiary GI pipe
12 Kurakur WS12-6 109 19 tertiary GI pipe
13 Kurakur WS13-6 51 9 tertiary GI pipe
14 Kurakur WS14-6 157 27 tertiary GI pipe
15 Kurakur WS15-7 215 36 Secondary GI pipe
16 Kurakur WS16-7 218 37 tertiary GI pipe
17 Kurakur WS17-8 214 36 tertiary GI pipe
18 Kurakur WS18-8 209 35 secondary GI pipe
19 Kurakur WS19-9 42 7 tertiary GI pipe
20 Kurakur WS20-10 202 34 tertiary GI pipe
21 Kurakur WS21-10 98 17 tertiary GI pipe
22 Kurakur WS22-11 129 22 tertiary GI pipe
23 Kurakur WS23-12 54 9 tertiary GI pipe
24 Kurakur WS24-12 47 8 tertiary GI pipe
25 Kurakur WS25-13 42 7 tertiary GI pipe
26 Kurakur WS26-28 129 22 tertiary GI pipe
27 Kurakur WS27-18 48 8 tertiary GI pipe
28 Kurakur WS28-18 48 8 tertiary GI pipe
29 Kurakur WS29-19 125 21 tertiary GI pipe
30 Kurakur WS30-19 125 21 tertiary GI pipe
31 Kurakur WS31-20 44 8 tertiary GI pipe
32 Kurakur WS32-20 46 8 tertiary GI pipe
33 Kurakur WS33-22 372 62 secondary GI pipe
10
WS1-1 stands for water supply line No.1 on Road No.1, WS11-5stands for water supply line No.11 on Road No.5. The others interpreted in a similar fashion.
11 The required pipes are obtained by dividing the length by six. Because one GI pipe is equivalent to 6m
-
34
No Site Pipe line Required
pipes
Distribution line
type
Material type
Code Length
34 Kurakur WS34-32 256 43 tertiary GI pipe
35 Kurakur WS35-22 502 84 secondary GI pipe
36 Kurakur WS36-23 291 49 tertiary GI pipe
37 Kurakur WS37-23 293 49 tertiary GI pipe
38 Kurakur WS38-32 264 44 tertiary GI pipe
39 Kurakur WS39-29 371 62 Secondary GI pipe
40 Kurakur WS40-29 416 70 secondary GI pipe
41 Kurakur WS41-31 210 35 tertiary GI pipe
42 Kurakur WS42-30 385 65 tertiary GI pipe
43 Kurakur WS43-23 121 22 tertiary GI pipe
44 Kurakur WS44-11 196 33 tertiary GI pipe
45 Kurakur WS45-49 110 19 tertiary GI pipe
46 Kurakur WS46-47 108 18 Secondary GI pipe
47 Kurakur WS47-47 109 19 Secondary GI pipe
48 Kurakur WS48-42 193 33 tertiary GI pipe
49 Kurakur WS49-42 143 24 tertiary GI pipe
50 Kurakur WS50-41 307 52 tertiary GI pipe
51 Kurakur WS51-41 271 46 tertiary GI pipe
52 Kurakur WS52-36 79 14 tertiary GI pipe
53 Kurakur WS53-36 79 14 tertiary GI pipe
54 Kurakur WS54-37 82 14 tertiary GI pipe
55 Kurakur WS55-37 84 14 tertiary GI pipe
56 Kurakur WS56-36 77 13 tertiary GI pipe
57 Kurakur WS57-38 77 13 tertiary GI pipe
58 Kurakur WS58-39 73 13 tertiary GI pipe
59 Kurakur WS59-46 72 12 tertiary GI pipe
60 Kurakur WS60 332 56 tertiary GI pipe
61 Kurakur WS61 241 41 tertiary GI pipe
62 Kurakur WS62-43 79 14 tertiary GI pipe
63 Kurakur WS63-43 80 14 tertiary GI pipe
64 Kurakur WS64-44 83 14 tertiary GI pipe
65 Kurakur WS65-44 94 16 tertiary GI pipe
66 Kurakur WS66-57 188 32 tertiary GI pipe
67 Kurakur WS67-57 192 32 tertiary GI pipe
68 Kurakur WS68-35 564 94 primary GI pipe
69 Kurakur WS69-35 562 94 primary GI pipe
Sum-1 12,621m 2,134
Source: Own computation from the water supply line plan (Jan., 2011)
-
35
Table-9, below, summarizes the total pipe lines and the cost estimate
No Description/item Unit quantity Unit price
(Birr)
Total cost
(Birr) Pcs Meter
1 Water supply pipe lines
3 inch Pcs 188 1,126 350 65,800 2 inch Pcs 540 3,211 250 135,000 1.5 inch Pcs 1,406 8,284 200 281,200 Sub-total-1 2,173 12,621 482,000.00
2 Fittings
Elbow 1,870 - 25 46,750.00 T-joint 40 - 35 1,400.00 Nipples 1,870 - 40 74,800.00 Sub-total-2 122,950.00
3 Labor cost
GI pipe installation (clearing, excavation, backfill)
Lm12
12,937 60 776,220.00
Sub-total-3 776,220.00
Total (sub-total (1+2+3)) 1,381,170.00
4 Contingency (15%) 207,176.00
Grand total 1,588,346.0013
Source: Own computation from water supply line plan (March 2011)
Note:The cost is the current market value collected from Lalibela Municipality.
ii. Reservoir
This is a large water container which reserves water for times other than the supply period. This is
to mean it will reserve and supply water for events when water interruption occurs due to
inconveniences. During field survey we have discussed and reached to consensus with the town‟s
water supply coordinator to construct/provide one reservoir with a capacity of 50m3 volume at
„Kurakur‟ which can meet the aforementioned purposes. The materials which will be used in the
construction of this reservoir include:
o Stone – this will be used for foundation and body construction. o Sand – this is used to construct the whole body of the reservoir. o Cement- this is also joker/sticking (cementing material) to all parts of the reservoir. o Gravel – these are for concrete.
12
LM = Linear meter 13
This cost does not include the cost of main supply line from the source. Because there is already an
available/accessible main supply line near to the resettlement area.
-
36
o Pipes – these are for inlet, outlet and over flow. o Gate valves – these are to let and close water to flow & not to flow respectively. o Fittings – including T-joints, elbows and nipples.
Accordingly, the following cost14
estimate has estimated and presented in Table-10 for the full
provision of one reservoir for the relocated people at „Kurakur‟.
Table-10: Cost estimate for one Reservoir construction.
No. Description/item Unit Quantity Unit price Total
1 Stone m3 40 900 36,000.00
2 Sand m3 40 700 28,000.00
3 Cement Qt 50 400 20, 000
4 Gravel m3 10 700 7,000.00
5 Pipes (over flow, inlet, outlet) pcs 5 140.00 700.00
6 Gate valves pcs 2 150.00 300.00
8 Fittings (elbow + nipples) pcs 10 45.00 450.00
9 Constructor (professional) - - 30,000.00 30,000.00
10 Daily laborer - - 10,000.00 10,000.00
11 Iron bar (reinforcing bar) mm 18 & 12 5,600.00 5,600.00
12 Water Lt - 1,000.00 1,000.00
Total 119,050.00
Contingency (15%) 17,858.00
Grand total 136,908.00
The expense (service charge) to install the required water supply line for a customer depends on the
size of the pipe line:
If the pipe size is from 1 inch to ½ inch = 205 birr. If the pipe size is 2 inch to ½ inch = 347 birr.
But, based on the Ethiopian government principle/regulation this installation cost will be covered by
the owner/house hold him/her self. Because all the expenses from the water meter to the end use is
covered by the owners themselves including water meter.
Remark: Constructing and providing a reservoir for the relocated community will ensure sustainable or
uninterrupted water supply.
14 This cost estimated on the current market value which is workable around Lalibela town.
-
37
Table-11: Summary of water supply cost estimates
No Description Cost estimate (Birr) Remark
1 Water supply line 1,588,345.00
2 Reservoir 136,908.00
Grand total 1,725,253.00
Source: Computation from own design
Fig -9: Water supply line plan of Kurakur
Source: Own proposed plan March 2011
3.5 Road Design for the new neighbourhood
The relocated people should be served with a better and accessible road infrastructure. Each
displaced people will have accessible roads. As per the road net-work plan, it will be checked that
whether the relocated individuals get better road than the previous one. Thus, to ensure such
services the following rough cost estimate has done for the gravel roads which will be constructed
in the new resettlement area, „Kurakur‟.
-
38
Table-12: Road code, width and length.
No Activity/item Site Road
Code Length (meter)
1 Road Kurakur R1 435
2 Road Kurakur R2 227
3 Road Kurakur R3 299
4 Road Kurakur R4 412
5 Road Kurakur R5 127
6 Road Kurakur R6 204
7 Road Kurakur R7 222
8 Road Kurakur R8 217
9 Road Kurakur R9 53
10 Road Kurakur R10 116
11 Road Kurakur R11 146
12 Road Kurakur R12 57
13 Road Kurakur R13 55
14 Road Kurakur R14 -
15 Road Kurakur R15 -
16 Road Kurakur R16 -
17 Road Kurakur R17 44
18 Road Kurakur R18 59
19 Road Kurakur R19 127
20 Road Kurakur R20 51
21 Road Kurakur R21 37
22 Road Kurakur R22 521
23 Road Kurakur R23 142
24 Road Kurakur R24 62
25 Road Kurakur R25 109
26 Road Kurakur R26 73
27 Road Kurakur R27 215
28 Road Kurakur R28 138
29 Road Kurakur R29 446
30 Road Kurakur R30 410
31 Road Kurakur R31 248
32 Road Kurakur R32 268
33 Road Kurakur R33 299
34 Road Kurakur R34 37
35 Road Kurakur R35 1,000
36 Road Kurakur R36 82
37 Road Kurakur R37 90
-
39
No Activity/item Site Road
Code Length (meter)
38 Road Kurakur R38 83
39 Road Kurakur R39 82
40 Road Kurakur R40 77
41 Road Kurakur R41 273
42 Road Kurakur R42 195
43 Road Kurakur R43 271
44 Road Kurakur R44 137
45 Road Kurakur R45 72
46 Road Kurakur R46 88
47 Road Kurakur R47 112
48 Road Kurakur R48 39
49 Road Kurakur R49 113
50 Road Kurakur R50 42
51 Road Kurakur R51 -
52 Road Kurakur R52 -
53 Road Kurakur R53 -
54 Road Kurakur R54 -
55 Road Kurakur R55 331
56 Road Kurakur R56 86
57 Road Kurakur R57 193
58 Road Kurakur R58 -
59 Road Kurakur R59 57
60 Road Kurakur R60 123
61 Road Kurakur R61 150
62 Road Kurakur R62 85
63 Road Kurakur R63 135
64 Road Kurakur R64 111
65 Road Kurakur R65 78
Grand Total 9,961m~9.96km
Source: Own computation from field survey (March 2011).
Note: R14, 15, 16, 51, 52, 53, 54 and R58 are blank because these are roads located in the investment area where the
cost estimate is not included
-
40
Table-13: Cost estimate summary (per kilometer of Gravel Road)
No. Description/activity Cost requirement (Birr/km) Remark
1 Clearing and Grubbing15
6,000.00
2 Earth work 422,260.00
3 Surfacing 151,610.00
Sub-total-1 579,870.00
4 Supervision & administration expense 47,987.00
Sub-total-2 627,857.00
5 Contingency (15%) 94,179.00
Grand total 722,036.0016
Source: own computation based on the current market value (March 2011)
Table -12: Cost estimates summary of Gravel Road construction by width type.
No
.
Site Width Number of
segments
Corresponding
length(km)
Estimated cost (Birr)17
Unit cost per
km
Total cost
per km
1 Kurakur 5 4 0.421 722,036.0018
303977.16
2 Kurakur 6 9 1.032 722,036.00 745,141.20
3 Kurakur 7 12 2.363 722,036.00 1706171.1
4 Kurakur 8 11 1.372 822,036.00 1127833.4
5 Kurakur 9 11 1.829 822,036.00 1503503.8
6 Kurakur 10 4 0.772 822,036.00 634,611.80
7 Kurakur 11 1 0.196 922,036.00 180719.06
8 Kurakur 12 4 1.149 922,036.00 1059419.4
9 Kurakur 14 1 0.397 1,022,036.00 405748.29
10 Kurakur 15 1 0.105 1,022,036.00 107313.78
11 Kurakur 16 1 0.325 1,022,036.00 332161.7
Total 65 9.96 8,106,601.00
Contingency (15%) - - - 1,215,990.00
Grand Total - - - 9,322,591.00
Source: Own computation from Road net-work plan (March 2011) & current estimate cost from Lalibela
town municipality.
A total cost of 9, 322,591.00 (Nine million three hundred twenty two thousand five hundred ninety
one) Birr estimated for Gravel Road construction at the new resettlement area at ‘Kurakur’
15
Cost of clearing and grubbing does not include demolition cost if any exists. 16
For every 3m road width increment this value raises by 100,000.00 (one hundred thousand) birr. 17
The cost is estimated for normal gravel road with the current cost estimate of the surrounding area. 18
The cost per kilometer of gravel road from 5-7m, 8-10m, 11-13m & 14-16m width is estimated to be 607,036.00 birr, 707,036.00 birr, 807,036.00 birr, and 907,036.00 Birr respectively.
-
41
Fig-10: Proposed Road network plan
WUB Consult March 2011
3.6 Implementation guide lines19
2.6.1 Road
Since the topography of the resettlement areas are steep/or undulating, the sites should be
rehabilitated/stabilized by vegetative structures. In addition to this, the upper catchment areas
should be reinforced by physical as well as biological conservation measures. The length and width
of each road along with their codes is provided in Table-12.
Storm water drainage
The urban storm water drainage infrastructure should be implemented as presented on the design
sheet in table-4. It should be implemented/ placed in between the pedestrian ways and carriage
19
Generally, to implement the infrastructure and utility lines it is strictly advised to refer the map of each respective infrastructure/utility lines presented in map forms and respective tables indicated in this main document. The maps and tables of the respective infrastructures are the prime inputs while implementing infrastructure plans.
-
42
ways. The drainage lines dimension, code and length have presented in Table-4. The drainage lines
should discharge like the way they are directed/indicated with the arrow. To reduce the intensified
storm water, roof rain water harvesting should be taken as a major strategy.
Water supply
In order to ensure safe and accessible water to the relocated people, the planned water supply lines
shall be implemented as per the plan. If there faces a financial problem, the lines shall be
implemented phase by phase. To ensure uninterrupted water supply, the provision of one reservoir
as per the proposed type is paramount. The full information/data is presented in Table-8. Thus,
during implementation refer to this table.
Power supply
To reduce electric shocks and unnecessary load on power supply lines, it is advisable to implement
as per the plan which is depicted/presented on the proposed power supply plan. The provision of
one transformer has also a very important function to control/balance the power supply fluctuation
problem.