NEW ELEMENTARY SCHOOL REED SITE, ARLINGTON PUBLIC SCHOOLS SCHEMATIC DESIGN SCHOOL BOARD INFORMATION ITEM JULY 17, 2018

Upload: others

Post on 14-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

NEW ELEMENTARY SCHOOLREED SITE, ARLINGTON PUBLIC SCHOOLS SCHEMATIC DESIGNSCHOOL BOARD INFORMATION ITEM JULY 17, 2018

Page 2: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 2

PROJECT PARAMETERS

1. Create a new neighborhood elementary school with an attendance zone

2. Support APS Strategic Plan Goals, specifically Goal #4 – Provide Optimal

Learning Environments

3. Address capacity by providing at least 725 seats

4. Open by start of school 2021

5. Spend a maximum project cost of $55 million, with strong direction to find

opportunities to reduce costs.

CORE MISSION

Page 3: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 3

GMP

OVERALL PROJECT TIMELINE

Apr 2018

Concept Design SB Approval

CONCEPT DESIGN SCHEMATIC DESIGN

DESIGN DEVELOPMENT

Aug 2018

Schematic Design SB Approval

Oct2018

Design Development Submission

Sep 2019

Final Design + GMP

SBApproval

CONSTRUCTION DOCUMENTATION

Sep 2021

SchoolOpens

CONSTRUCTION

UsePermit

Approval

NOV 2018

May2019

ConstructionDocumentSubmission

BuildingPermit

Approval

AUG 2019

Page 4: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 4 Concept / Schematic Design Timeline

21Mar

29Nov

Concept Design

ApprovalCommunity

Forum

24Jan

JointPFRCBLPC

25Oct

JointPFRCBLPC

15Nov

JointPFRCBLPC

13Dec

10Jan

JointPFRCBLPC

SBInfo

22Mar

JointPFRCBLPC

15May

14Jun

17July

Jan 17

Schematic Design

Approval

Community Forum

May 16

CONCEPT DESIGN SCHEMATIC DESIGN

SiteTour

Dec 10

JointPFRCBLPC

JointPFRCBLPC

21Feb

JointPFRCBLPC

JointPFRCBLPC

JointPFRCBLPC

Apr 5

SBInfo

Aug 2

Building & Site Design MeetingsTransportation

Meetings

JointPFRCBLPC

Mar 14Cost Meeting

Page 5: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 5

PATH TO USE PERMIT APPROVAL

• September 2018 – Use Permit submission

• September to November 2018 – ACG/APS staff collaborate on submission

review

• Fall 2018 – County commission meetings

• Fall 2018 – Joint BLPC/PFRC meeting to review updated design and

likely more detail on construction phasing)

• November 17, 2018 – County Board meeting

Page 6: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 6 Final Schematic Design

FINALSCHEMATICDESIGN

On-site parking:

133 spaces (9 over min)

Space for 7 buses to

load/unload at suggested

location

Space for a total of 30

cars to queue on-site in

two rows

Interior Class 1 bike

storage with 2 showers

Exterior bike racks

Exhibit A

Page 7: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 7 Final Schematic Design

ImperviousAreas (sf)

Building:

Play Courts:

Other Paving:

Parking:

Total:

% of site:

52,744

16,272

46,741

26,476

142,233

39%

Existing

Final Schematic Design

Building:

Play Courts:

Other Paving:

Parking:

Total:

% of site:

58,875

8,574

50,165

46,982

164,596

45%

Page 8: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 8 Capacity Summary

Program Classrooms Factor Capacity

Pre-K 2 16.00 32.00

Kindergarten 5 23.33 116.65

First Grade 5 23.33 116.65

Second Grade 5 23.33 116.65

Third Grade 5 23.33 116.65

Fourth Grade 5 23.33 116.65

Fifth Grade 5 23.33 116.65

Total 32 732

Exhibit B

Page 9: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 9 Floor Plans – Level 1

CLASSROOM

RESOURCE ROOM

SHARED/PUBLIC (Dining, Library)

PHYSICAL EDUCATION

CORRIDOR / COMMONS

SUPPORT

ADMINISTRATION

ARTS

Exhibit C

Page 10: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 10 Floor Plans – Level 2

CLASSROOM

RESOURCE ROOM

SHARED/PUBLIC (Dining, Library)

PHYSICAL EDUCATION

CORRIDOR / COMMONS

SUPPORT

ADMINISTRATION

ARTS

Exhibit D

Page 11: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 11 Floor 3 & 4. Grade level learning community: Adaptable Rooms/Agile Furniture

CLASSROOM

RESOURCE ROOM

SHARED/PUBLIC (Dining, Library)

PHYSICAL EDUCATION

CORRIDOR / COMMONS

SUPPORT

ADMINISTRATION

ARTS

Exhibit E

Page 12: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 12 Adaptable design: 2 future classrooms

CLASSROOM

RESOURCE ROOM

SHARED/PUBLIC (Dining, Library)

PHYSICAL EDUCATION

CORRIDOR / COMMONS

SUPPORT

ADMINISTRATION

ARTS

Page 13: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 13 Adaptable design: 5 enclosed classrooms with open collaboration space

CLASSROOM

RESOURCE ROOM

SHARED/PUBLIC (Dining, Library)

PHYSICAL EDUCATION

CORRIDOR / COMMONS

SUPPORT

ADMINISTRATION

ARTS

Page 14: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 14 Final East Elevation – along 18th Street

Page 15: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 15 View from intersection of McKinley & Washington, Final SD

Page 16: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 16 View at entry plaza, Final SD

Page 17: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 17 Aerial view of entry courtyard, Final SD

Page 18: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 18 View from north approach on 18th Street, Final SD

Page 19: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 19 Aerial View from north approach on 18th Street, Final SD

Page 20: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 20 View from softball outfield, Final SD

Page 21: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 21 Aerial View of play areas, Final SD

Page 22: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 22 Final Schematic Design

Page 23: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 23 Items explored to manage cost

1. Wood construction in lieu of steel

Steel and concrete deck for now

2. Joist v/s beam roof framing & fireproofing issues

Beam framing at roof

3. Stacking K & 1 over Gym for repetitive structure

Marginal savings, so not worth it

4. Exploring prefabrication & different wall systems

May use structurally insulated panels

5. Reduced renovation scope

No new construction south of fire wall

6. Met with Instructional staff to find reductions in

program

Continue to reduce where possible

7. Re-use existing classrooms where possible without

renovation

Create break-out space to meet program

Cost control measures

Not adding a second floor in this area to save $

Example of extended learning space outside PreK rooms

Page 24: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 24 Items explored to manage cost

1. Energy efficient design to avoid

having to bring in a new electrical

service or new gas service

Right sized systems

2. Avoided tearing up all existing asphalt

or moving any public utility lines

Triggers more storm water

treatment measures

3. Preliminary discussions with Arlington

County staff on likely Use Permit

conditions

Manage scope and reduce

likelihood of surprises

Cost control measures

Page 25: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 25

SCHEMATIC DESIGN PHASE COST ESTIMATES

• To ensure that School Board action is based on the most complete and up-to-date

information, final total project cost estimates are prepared at the end of each

project phase by both the Architect / Engineering team (A/E) and Construction

Manager at-Risk (CMR).

• Process for developing the final estimates:

• A/E and CMR complete independent estimates

• A/E and CMR meet to review draft estimates and reconcile and clarify scope

• A/E and CMR provide revised estimates incorporating reconciliation efforts

• Estimates influenced by both historic cost databases and current market

conditions.

• Input from market activity reports and subcontractors confirm that the DC region

remains very busy and that material costs for some trades continue to experience

above average increases. Estimates include 5% per annum in escalation.

Page 26: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 26 Project Funding and Estimated Cost

Exhibit F

Maximum Project Funding (Millions)1

Major Construction Bonds $ 44.25

Capital Reserve $ 4.00

Other (Operating)2 $ 1.25

Subtotal $ 49.50

ACG/APS Jointly Funded Items

APS Funding $ 2.75

ACG Funding $ 2.75

Subtotal $ 5.50

Grand Total $ 55.00

Notes:

1. FY 2019-2028 CIP, Adopted by the School Board on June 21, 2018.

2. Furniture and equipment that cannot be bond funded.

Estimated Cost (Millions)1

A/E CMR

GMP (Construction Costs) $ 41.87 $ 42.71

Owner (Soft) Costs2 $ 12.24 $ 12.28

Total $ 54.11 $ 54.99

Note:

1. Based on final reconciled total project cost estimates.

2. Owner costs include design, project management, and other professional

services fees, utility/permitting fees, furniture, equipment, and project

contingencies.

Page 27: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 27

COST CONTROL IN DESIGN DEVELOPMENT PHASE

• Design development phase will provide additional opportunities to manage cost

as the design becomes more detailed and more information about the project is

known.

• Pursue various options for cost savings measures including:

• Right-size architectural design elements (wall and roofing systems) to work in

conjunction with engineering systems (HVAC, plumbing, electrical, etc.).

• Engage subcontractor community for design options that reduce costs.

• Develop a series of design alternatives which could be accepted to mitigate

unexpected cost increases, including options for building materials.

• Refinements to owner costs as more project information is known.

• Review accepted value engineering (VE) items from recent projects.

Page 28: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 28

COST CONTROL IN DESIGN DEVELOPMENT PHASE

• Produce cost analysis on various design elements to create the best value for APS:

• Balancing exterior sunshades/enclosures and mechanical systems

• Millwork

• Roofing, exterior materials, and window systems

• Ceiling and floor types

• Emergency electrical systems

• Site amenities

• Building volume

• Alternatives for extent of existing building renovations

• Complete final total project cost estimates at the conclusion of the design

development phase and share with the School Board as a monitoring item in Fall

2018.

Page 29: NEW ELEMENTARY SCHOOL · 2020. 6. 5. · 07.17.2018 School Board Info 2 PROJECT PARAMETERS 1. Create a new neighborhood elementary school with an attendance zone 2. Support APS Strategic

07.17.2018

School Board Info 29

RECOMMENDATIONS

• Reaffirm project criteria for a new neighborhood elementary school with an

attendance zone, a minimum capacity of 725 seats, and a project completion in

time for start of school September 2021;

• Approve the proposed schematic design as generally described in Exhibits A

through E;

• Approve the proposed project funding as described in Exhibit F;

• Direct staff to proceed to the design development phase, including preparation of

the Use Permit application;

• Direct staff to begin discussions with Arlington County on quantifying APS/AGC

jointly funded items; and

• Charge staff to continue to pursue cost savings measures to complete the project

as close to the original $49 million available funding as possible.