NATIONAL HIGHWAYS AUTHORITY OF INDIA (MINISTRY OF SHIPPING, ROAD TRANSPORT & HIGHWAYS ) GOVERNMENT OF INDIA QUARTERLY PROGRESS REPORT NO: 03 JULY TO SEPTEMBER 2016 Consulting Services As Independent Engineer During Operation & Maintenance Of 4 Laning of Devihalli - Hassan Section From Km 110+000 to Km 189+500 Of NH-48/75 Including A New 2-lane With Paved Shoulder By pass For Channarayapatna Town And Widening Of Existing Hassan By pass To 2-Lane With Paved Shoulder On DBFOT Basis. DEVIHALLI – HASSAN SECTION OF NH 75 BY INDEPENDENT ENGINEER

Upload: truongxuyen

Post on 24-Mar-2018

268 views

Category:

Documents


11 download

TRANSCRIPT

NATIONAL HIGHWAYS AUTHORITY OF INDIA(MINISTRY OF SHIPPING, ROAD TRANSPORT & HIGHWAYS )

GOVERNMENT OF INDIA

QUARTERLY PROGRESS REPORT NO: 03 JULY TO SEPTEMBER 2016

Consulting Services As Independent Engineer During Operation & Maintenance Of 4 Laning of Devihalli - Hassan Section From Km 110+000 to Km 189+500 Of NH-48/75 Including A New 2-lane With Paved Shoulder By pass For Channarayapatna Town And Widening Of Existing Hassan By pass To 2-Lane With Paved Shoulder On DBFOT Basis.

DEVIHALLI – HASSAN SECTION OF NH 75

BY INDEPENDENT ENGINEERM/S MSV INTERNATIONAL, INC

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

CLIENT INDEPENDENT ENGINEER CONCESSIONAIRETABLE OF CONTENTS

SL.No Description of Work Page No1 Introduction & Executive Summary 4-4

1.1 Introduction & General 5-51.2 Executive Summary 6-7

2 The Project 8-82.1 Background 9-92.2 Project Brief 9-92.3 Salient Feature 10-102.4 Responsible Parties 11-112.5 The Office of the NHAI, Independent Engineer & Concessionaire 11-122.6 Scope of Work 12-122.7 Location Map 13-132.8 Village Inventory 14-152.9 Major Junction 15-152.10 Minor Junction 15-152.11 Organization Chart 16-162.11.1 Organization Set-up Authority 17-172.11.2 Table shows Independent Engineer Deployment Status 17-182.12 Concessionaire 18-182.12.1 Organization Chart – Concessionaire 18-182.12.2 Organization Chart – O&M 19-19

3 Progress of the Work 20-203.1 Toll Plaza-1 Building Details (116+790) 21-213.2 Toll Plaza-2 Building Details (165+170) 22-223.3 Status of Service Road Work 22-22

4 Punch List Status 23-265 Quality Assurance Control 27-27

5.1 Quality Certification 28-285.2 Quality Assurance / Control & Certification 28-29

6 O&M Inspection Report 30-306.1 O&M Inspection Report 31-316.2 Present Status of Unauthorised Median ; As Existing Today 31-316.3 Team Leader Inspection for the month of July-2016. 32-336.4 Team Leader Inspection for the month of August-2016. 34-346.5 Team Leader Inspection for the month of September-2016. 35-366.6 Team Leader Night Inspection for the month of July-2016. 37-376.7 Team Leader Night Inspection for the month of August-2016. 38-386.8 Team Leader Night Inspection for the month of September-2016. 38-386.9 Deficiency Observed During July-2016. 39-396.10 Deficiency Observed During August-2016. 40-406.11 Deficiency Observed During September-2016. 40-406.12 Compliance /Non Compliance During July-2016. 41-416.13 Compliance /Non Compliance During August-2016. 41-426.14 Compliance /Non Compliance During September-2016. 42-426.15 Status of Plantation 43-446.16 Safety Issues 45-466.17 Encroachment Details 47-486.18 Construction of Public Facilities as Reported By Concessionaire 49-49

7 Traffic & Safety Measures 50-507.1 Traffic & Safety Measures 51-51

MSV International Inc. Page 2

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

7.2 Status of Traffic Safety Measure 51-517.3 Accident Report / Incident Report 51-60

8 Plant & Machineries 61-618.1 Plant & Machineries 62-62

9 Hindrances/ Land Acquisition Status 63-639.1 Hindrances / Land Acquisition Status / Utility Shifting 64-649.2 List of Hindrances 64-65

10 Correspondence 66-8811 Photographs 89-9412 Toll Collection Report 95-101

Conclusion 102-102Annexure-A :

MSV International Inc. Page 3

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

MSV International Inc. Page 4

Chapter-1Introduction & Executive Summary

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

1.1 INTRODUCTION AND GENERAL

The axis Devihalli to Hassan encompasses the road along NH-75 (Old NH-48) which is a 4 lane road except for the bypasses Hassan and Channarayapatna which are two lanes. The road traverses plain terrain generally with a traffic intensity which is moderate except at nodes/town junctions where movement is denser. Some of the townships like Udayapura (Km.155) and Shantigrama (Km.167) encountered in transit besides Devihalli and Channarayapatna are Hirisave (Km.123) and Gulsinda (Km.146). The density of population in the townships is not very heavy. The people form a mix of rural inhabitants and urban dwellers with the forte in occupation being principally agrarian. The language spoken is Kannada with a dialect in villages. Town dwellers are engaged in government pursuits with townships fairly well provisioned with educational institutions. Most of the village/town nodes are supplied with electricity and restricted water supply though at no time is water really in deficit. Devihalli is a sleepy village on the way to becoming a township in due course whereas Hassan is a developed town. Power cuts are limited. Generally water is in adequate supply to inhabitants and no grave shortage is recorded. The temperature is in the range of 400C during summer months and pleasant at nights whereas winter months are cool (170C at night). Day temperatures hover around 250C to 300C ambience on sunny days. Hassan is a gateway to mountainous stretches, beyond it towards Mangalore. The altitude of Hassan is 934 Meters above MSL (Mean Sea Level) whereas Devihalli is 778 meters above MSL (Mean Sea Level). Hassan is not industrialized. It also is not a cantonment. The administration provides a satisfactory facility for commutation by buses within town and around to outskirts and back. The Road has no zig though some expansive horizontal curves exit. The townships of Channarayapatna (which is fairly dense) and Hassan are slated to have 4 lane paved bypasses respectively on upgradation from the present 2 lane on sanction during pendency of this project. This is expected to start in November 2016. Accidents on the road are prompted basically by the carelessness of the drivers by over speeding or drunkenness which with more slogans besides the road furniture extant is expected to provide marginal relief. We are also exhorting the Concessionaire to expand/ improve the number and quality of signages. They have to be catchier. Some locales worth visiting around Hassan are Chickamangalur, Bellur and Hallebidu. Shravanabelagola (a famous Jain Pilgrimage centre) is situated on a lateral 30 Kms from Devihalli and it is easier to go from Channarayapatna. The 4 laning of Devihalli to Hassan except bypasses was almost completed during October end 2015 but Plaza works which are incomplete and a few civil works (Law and order problem) are being hastened. TP1 is under a penalty and for 2 months work is stopped. TP2 is proceeding at a snail’s pace and also under penalty. We had recommended penalty to be levied Vide our letter No 1004/MSV/D-H/IE/TL/Tech/(Plaza)/19:date:02-May-2016 . The Concessionaire must rise up to the occasion and finish the pending works earliest to avoid complications.

The Mahamastabhisheka of Gomateshwara (Eldest son of the first Jain Tirthankara Rishaba) at Shravanabelagola on a lateral 18 Kms off Channarayapatna is scheduled in 2018 (once in 12 years) inviting a huge surge of pilgrims, other state visitors and foreigners. This is performed with great austerity. The roads shall have to be top class with drainage in proper form. Efforts towards this end are at hand. Signages should be self revealing and catchy.

.

MSV International Inc. Page 5

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

1.2 EXECUTIVE SUMMARY

The Devihalli-Hassan project road traverses from Km 110+000 to Km 189+500 between Devihalli to Hassan on NH-48/75 in the state of Karnataka. The project was awarded to M/s L&T Devihalli-Hassan Toll Way Ltd. on 30 April 2010 under DBFOT pattern. The project construction period is 30 months and the concession period is 30 years. The project commenced on 14 December 2010.

As of now about 69 months have elapsed. The cumulative physical progress for the month of September 2016 is 68.48% (80.52% for TP1 and 56.35% for TP2) including Plaza compound walls and environment works (excluding PCOD) Financial progress 2.28 Crores (out off 3.7 Crores). The reported cumulative overall physical progress (Plazas and Civil works) including environmental Work by the end of September 2016 was 99.53%.

In respect of timelines to be met by the Concessionaire, Project Milestone-I, II & III have been achieved within stipulated time frame in the project. Schedule two/four laning date had been due by 10 June 2013 (910th day from the appointed date).EOT-1 has been approved by the Authority up to 31/12/2013. The Concessionaire had also applied for EOT-2 for completion of COS-II works which has been reviewed and recommended by the IE up to 31/10/2014. The NHAI had approved the EOT-2 up to 31/10/2014.The Concessionaire had also applied for EOT-3 up to 30/09/2015 for completion of COS-II works which has been reviewed and recommended by the IE up to 31/07/2015 and extended up to Feb 14 -2016 (EOT-4). This has lapsed. He has again applied for (EOT-5) till September 2016 and IE has recommended EOT-5 (for Plaza 2) up to June 30, 2016 with the provision; it takes effect on the performance. If he fails to perform he invites liquidated damages. This extension was later kept under suspension and now cancelled for no progress. A penalty on Plaza 2 has been recommended for levy vide our letter No 1004/MSV/D-H/IE/TL/Tech/(Plaza)/19:date:2-May-2016. It may be recalled the previous IE had already levied a penalty on Plaza-1.

Provisional Completion Certificate-I had been issued for 59.7 Km on 14/11/2013. Provisional Completion Certificate-II had been issued for 14.652 Km on 05/12/2014. Provisional Completion Certificate-III has been issued for 2.876 Km on 06/10/2015 by the IE. The total Project Highway of 77.228 Km (100%) has been completed except some line drains and service roads hindered by law and Order problems attempted to be surmounted and lingering for long. Toll collection is in progress at Toll Plazas 1 & 2. Toll building construction is under progress. The balance of civil works PCOD and Plazas including the Drain, Service Road and Metal Beam Crash Barrier amounts is 3.45 in Crores.

No extension is currently in vogue after the last expiry on Feb 14, 2016.Routine site inspection is carried out by Independent Engineer’s site staff on day to

day basis for ongoing works. Tests on material are conducted by the Independent Engineer if found warranted. Besides, pursuant to Schedule-Q of TOR, site inspection had been conducted by Team Leader on September 30, 2016 for the entire stretch of the project road. Inspections are carried out jointly by the team of Independent Engineer headed by The Team Leader, Key personnel and Concessionaire’s representative besides exclusive IE’s inspection Please see Annexure-A . The inspection starts at Km 110+000 and proceeds towards the end chainage up to Hassan. In general all site activities have been observed; however, close site inspection has been made at representative locations and remarks given. Monthly inspection summary carried out during the month of September 2016 is enclosed.

All design issues in the project such as revised pavement design, revised plan profile drawings, typical drawings of project facilities and design drawings of structures had already been completed and necessary concurrence for them accorded. Changes of Scope Notice for

MSV International Inc. Page 6

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

additional structures/supplementary work when issued were executed and completed integrating the same to the original contract.

Construction of major structures in the project such as Minor Bridges, Box Culverts and Pipe Culverts had already been completed. All 66 pipe culverts 26 additional pipe culverts completed, 14 of Box culverts and 21 of Minor Bridges have been completed.

Recommendation along with Design, Drawings & Cost Estimate for COS I, II, III & IV were submitted to NHAI for issue of Change of Scope Order. NHAI have issued the Change of Scope Order vide letter No.NHAI/22015/1/10/PIU-BNG/1588 Date/08/07/2014 for an amount of Rs 17.75 Crores. As on date the payment made is Rs 16.28 Crores. Design and Supervision charges have not been admitted as not permissible.

Road Signages require to be reinforced as these had been inadequately provided. In the interest of commuters and for wholesomeness we are in the process of recommending additions under Change of Scope.

The riding surface is in general good. Where cracks were discernible at the tail end an overlay has been laid. The surface shows distress again towards the end see appendix ‘A’ and action is contemplated to smoothen the riding surface. We feel the latter traverse of riding surface of this Project (4-Lane prior to Hassan Bypass) is qualitatively inferior compared to the rest of the Project which is satisfactory. We are investigating. Rectification are in Progress.

MSV International Inc. Page 7

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

MSV International Inc. Page 8

Chapter-2The Project

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

2.1 BackgroundThe Government of India has entrusted to the National Highways Authority of India (NHAI),

under Ministry of Shipping, Road Transport and Highways (MORTH) for the development of highways under National Highways Development Program (NHDP). The projects contemplate enhancing the traffic capacity and safety on the selected heavily trafficked high density stretches/corridors of National highways for efficient transportation of public and goods.

The Project Corridor under consideration falls under NHDP Phase III A program of 2/4 laning to be undertaken on Design, Built, Finance, Operate and Transfer (DBFOT) basis.

The Development of Project consists of four laning of Devihalli-Hassan Section of NH-48/75 from Km 110.000 to Km 189.500 including 2-lane with Paved Shoulders Bye pass for Channarayapatna Town and widening of existing Hassan Bye pass to 2 lanes with Paved Shoulder in the State of Karnataka.

2.2 Project BriefThe highway project described in this report runs from Km 110.000 to Km 189.500 between

Devihalli to Hassan on NH 48/75 in the state of Karnataka.The project was awarded to Concessionaire M/s L&T Devihalli Hassan Toll way Ltd and

LOA issued on 30th April, 2010. The Concession Agreement was signed between National Highways Authority of India & M/s L&T Devihalli Hassan Toll way Ltd .on June17, 2010.

The appointment date is December 14, 2010 and completion date is June 10, 2013. Extended completion Date is Dec 31, 2013.PCOD III final date is Oct 06, 2015 which has lapsed.

LEA Associates South Asia Pvt Ltd. had been appointed as Independent Engineer (IE) of the project. Independent Engineer mobilized since May 09, 2011. The IE had established their office at Channarayapatna town which is located about middle of the project highway and all of the key professionals & sub professionals staff had been mobilized.

MSV International, INC. has been appointed as Independent Engineer (IE) of the project and mobilized on 20th OCT 2015.The new IE for O & M and construction of 2 Lane bypasses is based at Hassan with full strength presently. Key staffs have been mobilized.

Progress of Road Work on 31Oct 2015 (Including EOT) - Last Extended Date

Percentage Time Re-maining (NIl beyond 1200 Days)

Percentage Time Elapsed (910 days) 100%

MSV International Inc. Page 9

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

2.3 Salient Features

Letter of Award 30th April 2010

Date of Concession Agreement 17th June 2010

Appointment Date (AD) 14th Dec, 2010

Schedule Project Completion Date (SPCD) 10thJune 2013(910 Days from AD)

First EOT 12th -Dec-2013

Second EOT 31st -Oct-2014

Third EOT 30th -July-2015

Fourth EOT 14th -Feb-2016

Estimated Project cost Rs 453 Crores

Total Expenditure Cost (31-1-2016) Rs 554 Crores

Concession Period 30 years .(Inclusive of Construction period)

MSV International, Inc. Mobilized on 20 Oct 2015

Project Length 77.228 Km

4 Lane 58.366 Km

2 Lane (Bypass) 18.862 Km

Design Speed 100 KMPH

No. of Major Bridges Nil

No of Minor Bridges 21 Numbers

No of Grade Separators Nil

No of Toll Plazas 02 No’s (Km 116+790 & Km 165+170)

No of Box/Slab Culverts 14 Numbers

No of Pipe Culverts 66 Numbers

No of Truck Lay Bye 6 Numbers

No of Bus Bays 56 Numbers

No of Major Junctions 11 Numbers

No of Minor Junctions 19 Numbers

New Median Openings 09 Numbers

No of Existing ROBs 02 Numbers

Illegal Median Openings 24 Numbers

PCOD-I 14-11-2013 (59.70 Km)

PCOD-II 05-12-2014 (14.652 Km)

PCOD-III 06-10-2015 (2.876 Km)

2.4 Responsible Parties

Project : Construction Operation and Maintenance for

MSV International Inc. Page 10

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Four Laning of Devihalli –Hassan Section of NH-48 from KM 110.000 to KM 189.50 in state of Karnataka on DBFOT Pattern under NHDP Phase III –A

Client / Employee : National Highways Authority of IndiaG 5&6 Sector-10, Dwaraka,New Delhi-110075

Independent Engineer : MSV INTERNATIONAL INC.

Concessionaire : L & T Devihalli-Hassan Toll Way LtdEPC Contractor : Larsen & Toubro Ltd

Design Consultant : Scott Wilson India Pvt Ltd., New DelhiFeasibility study of the project

carried by: SECON

Safety consultant : HAKS

2.5 The offices of the NHAI, Independent Engineer & Concessionaire are as follow:

Address of NHAI

Head Office PIU Office Regional Office

National Highways Authority of India(NHAI)G 5&6 Sector-10, Dwaraka,New Delhi-110075India.

Project Director (NHAI)Haasanambha Nilaya, b/w 3rd & 4th cross, Indira nagar( Near Varasidhi Vinayaka temple) Satyamangala Layout, HASSAN -573201E-mail:[email protected] No: 08172-24251

Chief General Manager (T)Sy No. 13 14th Km, Near Deepak Bus Stop,Nagasandra, M S Ramiaha Enclave,Tumkur Road (NH-4) Bengaluru-560073 [email protected]@gmail.com

Address of Independent Engineer (IE)Head Office Site Office

Project Executive DirectorMSV International , Inc.USAD-7, South City-1,Gurgaon-122002, Haryana, IndiaTel: 0091-124-4002603,04Fax: 0091-124-4002605Email: [email protected]

Team LeaderMSV International, Inc.Door No. 21, Ground Floor,Bommalingeshwara Nilaya,2nd Cross, SBM Colony,Near RTO office,Hassan-573201.KarnatakaTel: 08172-240242Email: [email protected]

Address of Concessionaire

MSV International Inc. Page 11

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Head Office: Site Office:

Cluster HeadRegistered Office,Mount Poonamallee Road,Manapakkam, P.B. No. 979,Channai-600089, India.Tel: +91 44 22526000/22528000E-mail: [email protected]

T Sunil Kumar ReddyL&T Devihalli Hassan Toll Way LimitedNo.3009, Near Water tank, Bannimantapa Road,Channarayapattana-573116, Karnataka, India.Tel: +91 8176 254222www.lntidpl.com

2.6 Scope of Work

The design specification for the Devihalli-Hassan Section is as follows:-

Four laning from Km 110.00 to Km 189.50, provided that in the following stretches, the width of the carriageway shall be Two lane with paved shoulder without a median for Channarayapatna bypass(New) from Km 139.677 to Km 148.824 and Hassan bypass from Km 175.163 to Km 184.912.

1. 21numbers of Minor Bridges, 14 numbers of Box culverts and 66 numbers of Pipe culverts on main carriage way are have been widened /reconstruct as per Schedule B of Concession Agreement.

2. There is 1 Box Culvert and 8 Pipe Culverts which are not available at site and these were proposed under negative Change of Scope and deleted.

3. Change of Scope notice for 3 VUPs, 1 Minor Bridge, 6 Box Culverts and 26 Pipe Culverts and service road has been issued by the Authority and work executed.

4. ROB/RUB, Grade separators, Pedestrian/Cattle Underpasses& Service Road have NOT been proposed for the project highway. Service Road came under Change of Scope.

5. Traffic Management and Safety of workers and the Public shall be maintained at all times in accordance with the relevant IRC/IS Codes as stipulated in the Concession Agreement without any deviations.The scope of the work for the Operation & Maintenance of Project Highway:-

Road side furniture Pedestrian Facilities Highway Lighting Systems Junctions(Major & Minor) Tree plantation and landscaping Truck Lay byes & Bus bays with bus shelters Four laning of Channarayapatna and Hassan Bypasses.

Except for the last point as above rest stands almost completed with the Operation and Maintenance Phase now on.

2.7 Location Map

MSV International Inc. Page 12

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

2.8 VILLAGE INVENTORY:SL.NO VILLAGE NAME CHAINAGE ( Km)

MSV International Inc. Page 13

Site Office

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

1 KASTURALLI 174+4402 KENCHATAHALLI 174+1003 POLICE TRAINING SCHOOL 170+3004 SHANTIGRAMA POLICE STATION 168+6005 SHANTIGRAMA 167+8006 SHANTIGRAMA 165+2007 MALALI CROSS 164+8008 BYDARAHALLI 164+1009 H.HALADAHALLI 162+80010 AGRICULTURAL COLLEGE 161+20011 AGRICULTURAL COLLEGE 160+20012 BSCPL CAMP CROSS 159+50013 JODIGHATTA 156+00014 JODIGHATTA 156+30015 ANNENAHALLI/APPENAHALLI 155+80016 UDAYAPURA 155+00017 UPPENAHALLI CROSS 154+60018 LAXMI TEMPLE 153+50019 KATRI GHATTA 152+50020 B CHOWDANE HALLI 151+30021 BARAGUR CROSS 150+40022 ARASIKRE JUNCTION 149+20023 GULSINDHA 147+40024 CHIKKAGUNDANA HALLI 144+10025 NUGGE HALLI JUNCTION 142+10026 SHATTIHALLI JUNCTION 140+60027 NANDIPURA 139+60028 BEDAGANA HALLI 138+40029 BEDAGANA HALLI 138+20030 NUGGE HALLI 136+10031 GOUDAGERI 135+00032 KODIBELAGOLA 133+80033 GULIHONNANA HALLI 132+90034 MATTANAVILE 131+40035 RAJAPURA 128+90036 DODDERI KAVALU 128+40037 BUKANAHALLI 126+90038 HEGGADE HALLI 125+80039 BAGURU 123+80040 YELLANA HALLI(HIRISEVA) 121+20041 YELLANA HALLI(HIRISEVA) 121+80042 METIKERE 121+40043 BYDARAHALLI 120+00044 BALAGANCHE 118+20045 KIRISEVA 116+20046 KADABA HALLI CROSS 115+20047 CHIKKANAHALLIPURA 114+900

MSV International Inc. Page 14

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

48 BELLUR CROSS 113+200

2.9 MAJOR JUNCTION

Sl. No MAJOR JUNCTION CHAINAGE ( Km)

1 KADABALLI 115+8002 HIRISAVE 123+0003 SHETTIHALLI 140+6004 NUGGEHALLI/(TIPTUR) 142+1005 ARSIKERE/(BARGOOR) 149+1006 BUSTENAHALLI 176+2007 MYSORE 179+9908 GORUR 181+5459 HASSAN (ENDING POINT) 185+200

2.10 MINOR JUNCTION

Sl. No MINOR JUNCTION CHAINAGE( Km)

1 DEVIHALLI 108+600

2 CHAKENAHALLI 109+500

3 ANAGATHIHALLI/KUCHIHALLI 113+000

4 CHOLENAHALLI 115+200

5 METIKERE 121+200

6 HIRISAVE 122+050

7 MATTANAVILE 131+1008 HONNENAHALLI 132+800

9 GOWDAGERE 135+000

10 BARAGURU 150+40011 AADDIHALLI 164+900

12 SHANTHIGRAMA RAILWAY STATION 168+500

13 KENCHATAHALLI 174+200

14 SHETTIHALLI/(HALUBAVILU CROSS) 183+100

MSV International Inc. Page 15

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

2.11 Organization Chart

Organization Chart

Team Leder cum Highway Engineer

Lt. Col. Rajkumar Titus

Intermitted Staff Regular Staff

Laboratory Asst.RaviKiran

Pavement Specialist Col R N Malhona

HME-IMr. Raghava Reddy

HME-IIMr. Challasreenivasa RaoToll Expert

Bharat Goel

Traffic and Transportation Expert

N.Murali KrishnaAHME-II

Nabeel Ahmad

Road Safety Expert G.V Ravi

Technical Supervisor-I Krushna.Naikar

Technical Supervisor-II Shridhara

Technical Supervisor-III Janardhan Kalal

Quqlity cum Material Expert Sushil Jhala

MSV International Inc. Page 16

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

2.11.1 Organization Set-up Authority

In terms of Concession Agreement, National Highways Authority of India is working as Authority. Project Implementation Unit at Bangalore is headed by Project Director with Manager Technical. Regional Office is headed by Chief General Manager.

Independent Engineer

Independent Engineer took charge of duty on 20th OCT, 2015. The team at site is headed by The Team Leader. All key staff members have been mobilized. Part Time/ Intermittent staffs are on as is required basis. Reviewing Design, Drawings and submitting a assessments to NHAI offices as relevant is on the instructions of Team Leader. In addition to above, Team leader as the functional Head, coordinates with his Team & relays and instructs necessary inputs of a corrective nature to Concessionaire. He keeps Project Director informed as an implementation advisor. Table 2.11.2 shows the deployment of IE.

Table 2.11.2 shows Independent Engineer Deployment Status

Sl No Position Name Date of Mobilization

Key ProfessionalsA1 Team Leader Cum Highway Engineer Lt .Col. Rajkumar Titus 20-10-2015A2 Highway Maintenance Engineer I Mr. M.Raghava Reddy 30-10-2015A3 Highway Maintenance Engineer II Mr. Challa Sreenivasa Rao 16-11-2015A4 Quality cum Material Expert Mr. Sushil JhalA5 Road Safety Expert Mr. Venkat Ravi .GA6 Bridge/Structural Expert Mr. Ajay KumarA7 Pavement Specialist Col .R.N .MalhotraA8 Traffic & Transportation Expert Mr.Meluchur Murali

KrishnaA9 HTM/Toll Expert Mr. Bharat Goel

Sub-ProfessionalsB1 Survey Engineer Being Positioned

B2 Assistant Highway Maintenance Engineer I

Suthan S S 13-06-2016

B3 Assistant Highway Maintenance Engineer II

Nabeel Ahmad 29-12-2015

B4 CAD Expert Being PositionedB5 Electrical Engineer S.ThirumuruthyB6 Horticultural Expert Being PositionedB7 Quantity Surveyor Mohd Adil 26-04-2016Support StaffC1 Technical Supervisor I Krushna Naikar 30-11-2015C2 Technical Supervisor II Janardhan Kalal 02-11-2015C3 Technical Supervisor III SridharaC4 Technical Supervisor IV SpurgeonC5 Laboratory Assistant Ravikiran Surpur 22-01-2016C6 Office Manager Kripesh kumar 06-04-2016C7 Accountant cum cashier Shwetha H D 10-05-2016

MSV International Inc. Page 17

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

C8 Steno cum Computer Operator I Kishan H.P 12-3-2016C9 Steno cum Computer Operator II UshaC10 Cad/Drafts Man Sudeep H D 22-01-2016C11 Office Boy I ManjulaC12 Office Boy II Sonali

2.12 Concessionaire

The Organization of Concessionaire is headed by its Project Manager, Mr. T. Sunil Kumar Reddy for balance implementation. The position is responsible for day to day activities conducted by Concessionaire and also is the source of information of daily progress to IE/Client.

O&M Works are done by the Project Manager (O&M) who is also the Logistics head of the Project.

2.12.1 ORGANIZATION CHART – CONCESSSIONAIRE

MSV International Inc. Page 18

T. Sunil Kumar ReddyProject Manager

(Implementation)

LohitAssistant

RGR & SB-Finance & Accounts at HQ

P. Ranjan ManagerConstruction

M. RameshDy. ManagerPlanning &

Construction

Krishna PrabhakarManager Acct.&Admin

Sri HarshaProject Acct. Admin

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

2.12.2 ORGANIZATION CHART O&M

MSV International Inc. Page 19

Subhasish KunduProject Manager

O & M

Kiran KumarMaintenance

Manager

Krishna PrabhakarAccounts manager

Vinod BhaskarPlaza Manager

Kadabahalli

NingarajPlaza ManagerShantigrama

Assistant ManagerRoute Operation

AnantRoute

EquipmentManager

D SureshElectrical Engineer

HarshaExecutive Accounts

Shift in charge-4 and Cashier-4

Shift in charge-4 and Cashier-4

CRO/RPO/RPDContractual Equipment

Executive

Contractual Staff

Contractual Staff

Toll collector/LaneAssistant/Admin on contract

Contractual StaffToll collector/LaneAssistant/Admin on contract

SubbiahSr. Engineer

Project

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

MSV International Inc. Page 20

Chapter-3Progress of the Work

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

3.1 Toll Plaza 1 Building Details (Km 116+790)

Toll Plaza-1 (Km 116+790)Progress over the past 3 months in Toll Plaza-1

Sl.no Month Progress of work in % Total cumulative in %

1 July-16 76.00 02 Aug-16 80.52 4.523 Sep-16 80.52 0

Jul-16 Aug-16 Sep-1673.00

74.00

75.00

76.00

77.00

78.00

79.00

80.00

81.00

76

80.52 80.52

Progress of work in %

Time in Months

Prog

ress

of W

ork

in %

Overall Physical Completion (%) = 80.52

Financial Report toll Plaza-1

Month Total Cost of TP-1 in Rs.

Balance Amount In Rs.

Amount of work done in Rs.

July to Sept-2016

2,00,65,949.00 51,60,000.00 1,49,05,949.00

MSV International Inc. Page 21

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

3.2 Toll Plaza 2 Building Details ( Km 165+170)

Toll Plaza-2 (Km 165+170)Progress over the past 3 months in Toll Plaza-2

Sl.no Month Progress of work in % Total cumulative in %1 July-16 39.71 11.332 Aug-16 52.35 12.643 Sep-16 56.35 4.00

Jul-16 Aug-16 Sep-160

10

20

30

40

50

60

39.71

52.3556.35

Progress of work in %

Time in Months

Prog

ress

of w

ork

in %

Overall Physical Completion (%) =56.35

Financial Report toll Plaza-2Month Total Cost of TP-

2 in Rs.Balance Amount In

Rs.Amount of work

done in Rs.

July to Sept-2016 1,70,33,570.55 68,20,000.00 1,02,13,570.60

3.3 Status of Service Road Works:

a) Hirisave - 200 m – RHS – Building Demolition Work Completed but the Road Work is yet to Start.

b) Shantigrama - 190 m-LHS-Service Road and Line Drain Work Started but not in Progress.

MSV International Inc. Page 22

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

PUNCH LISTMSV International Inc. Page 23

Chapter-4Punch List Status

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

The punch list progress as of date is enclosed the next page:

1. Annexure I –Summary of plaza progress.

2. Annexure II –PCOD I (Provisional Commercial Operation Date -I): 14-11-2013 (59.70Km)

3. Annexure III –PCOD II (Provisional Commercial Operation Date –II): 05-12-2014 (14.652Km)

4. Annexure IV-PCOD III (Provisional Commercial Operation Date –III): 06-10-2015 (2.876 Km)

Annexure-I

MSV International Inc. Page 24

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Summary of Toll Plaza Progress

DEVIHALLI TO HASSAN Km 110.000 TO Km 189.590 OF NH - 48(75)DESCRIPTION OF

WORK TOLL PLAZA 1 TOLL PLAZA 2

Admin/Maintenance Building

Finishing Work like Dado, Electrical, Water Supply & Sanitary fixtures etc. No provision

Control Building Finishing Work like Dado, Electrical, Water Supply & Sanitary fixtures etc.

Sub structure Completed, Super Structure Work is Under Progress.

Service Block Finishing work balance. Electrical Work & Minor Civil Work balance.

Traffic Aid and Medical Aid Post Block

Finishing Work like external painting & Sanitary Work Balance.

Painting, Door, Electrical Work & Sanitary Work Balance.

Maintenance Store As per drawing land not available at site Painting & Electrical Work Balance

PCOD Stretches: Present Position (Annexure-II)PCOD –I LIST B ( Km 107.684 to121.300,Km122.700 to 165.700, and Km167.176 to 170.260): (59.70 Km)

MSV International Inc. Page 25

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Issued Date: 14-11-2013Sl No ITEM

DESCRIPTION. UNIT TOTAL COMPLETED BALANCE STATUS REMARK

1CD works for Cross Road at

Minor JunctionsKm 2 1 1 Land is not available. 166+806 Shantigrama VUP

Junction Location.

2Unauthorized

Median Openings

Nos. 20 7 13 Law & Order Issues (PCOD I of list B item) Public protesting for Median Openings

3 Lined Drain Km 0.479 0.306 0.173 Law & Order Issues (PCOD I of list B item) Public protest Law & Order.

4 Unlined Drain Km 2.06 0 2.06 Law & Order Issues (PCOD I of list B item) Public protest Law & Order.

Annexure-IIIPCOD -II LIST B- (Km 170.260 to Km 184.912): (14.652 Km) Issued Date: 5-12-2014Sl No ITEM

DESCRIPTION. UNIT TOTAL COMPLETED BALANCE STATUS REMARK

1 Metal beam Crash Barrier Km 0.326 0.116 0.210 Law & Order Issues

Law & Order Issue, since Local Public are not allowing to install the MBCB for want of access to their shop in 5 Gaps (50 m) &

further in 160 m there is no land availability for MBCB.

2Unauthorized

Median Openings

Nos. 3 2 1 Law & Order IssuesThese unauthorized median

openings closed several times and reopened by the public

PCOD III List B (121.300 to 122.700 and Km 165.700 to 167.176):( Km 2.876) Issued Date :6-10-2015Sl No

ITEM DESCRIPTION. UNIT TOTAL COMPLETED BALANCE STATUS REMARK

1 Lined Drain Km 1.530 0.441 1.089 Law & Order Issues & EB Problem

2 Service Road Construction Km 0.540 0.150 0.390 Law & Order Issues & Court Issue

Shantigrama Service Road Construction Work

Stopped.

3 SDBC & Road Marking Km 1.240 0.850 0.390 Law & Order Issues & Court Issue

4 Median Plantation M 40.000 0.000 40.000 Law & Order Issues

5 Kerb Laying Km 0.040 0.000 0.040 Law & Order Issues

6 Bus bay Lighting Nos 2.000 0.000 2.000 Law & Order Issues

7 Illegal Median Opening MCW Nos 2.000 0.000 2.000 Law & Order Issues

8 Major Junction Nos 2.000 1.000 1.000 Land Issues 166+806 balance due to land not available.

Annexure-IV

MSV International Inc. Page 26

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

MSV International Inc. Page 27

Chapter-5Quality Assurance/Control

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

5.1 Quality Certification

As per the provision of Schedule-Q of CA to check adherence to quality and confirmation to specification and standard laid down in the Concession Agreement, Independent Engineer shall require the Concessionaire to carry out or cause to be carried out tests on sample basis. The sample size of the tests to be specified by the IE shall comprise 10% of the total quantity or no. of tests prescribed for each category.

The Independent Engineer had been adopting the above guideline and performing tests and inspections in the project is found necessary. However, the remaining number of tests and inspections are carried out by the QA/QC cell of the Concessionaire. Based upon the test results, inspections and other items in the check-list, approval of works performed during the month is accorded. If any road stretch or any part of the works fails to comply with the requirements of density, levels, cube strengths etc., then such stretch of road or part of the work stands disapproved and NCR was issued. For such instances, remedial actions are taken and new RFIs are raised for inspection in the case where remedial action cannot rectify the deficiencies then such works are removed from the project site.

Further, we would like to state that, part of the works completed during the month which have been approved vide respective RFIs with supporting documents are certified for adherence to quality and compliance to project technical specification, and standards.

Quality Assurance: A detailed project Quality Plan has been prepared with detailed construction

activities methodology and Assurance Plane with Acceptance Criteria. IRC: SP 57-2000 and IRC: SP 47-1998 have been followed for Quality assurance of Q3 standards. Pertaining to IRC: SP 84-2009 of CA,QAM covering quality system and QAP are implemented in project work.

5.2 QUALITY ASSURANCE/CONTROL& CERTIFICATION RECORDS

Sl No Description of Materials Approved

Samples Remarks

01 Burrow Area of Embankment and Sub grade 32 Numbers

02 GSB 4 Numbers @ Km 136 , 166 Crushers, @ Km 136 & 166 (Shoulder), @ Km 136 & 166 (RAM)

03 WMM 2 Numbers @ Km 136 & 166 Crushers04 STEEL 4 Numbers RINL, SAIL, TATA, JSW

05 Cement Grade-53 8 Numbers Penna, Birla, Dalmia, Ramco, Chettinad, Zuari, JSW, Maha Gold

06 Bitumen 3 Numbers MRPL, HPCL & MRP07 Admixture 2 Numbers BASF(RHEO PLUS 71EI), SIKA

08 Aggregate Quarry 4 Numbers Balaji crusher at Km 75, Oriental Granite, Km 133 & Km 159

09 Sand 1 Numbers Hemavathi river10 Water 2 Numbers Camp at Km 129 & 16211 Hume Pipe 1 Numbers M/s Hemavathi Spun Pipes, Hassan

MSV International Inc. Page 28

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

12 Concrete Mix Design (PCC) 13 Numbers M 15, M 15 &M2013 Concrete Mix Design (RCC) 21 Numbers M25,M30,M35,M4014 Concrete Mix Design (DLC) 2 Numbers DLC15 Concrete Mix Design (PQC) 1 Numbers M45

16 DBM & DBM Grade with RAP (Reclaimed Asphalt Pavement ) 5 Numbers DBM mix design(Grade-I / Grade-II

(Open Graded)17 Filter Media 2 Numbers18 Bearings 1 Numbers Kanta Rubber Pvt. Ltd.

19 Asphaltoseal 3 Numbers Tiki Tar Industries & STP, Tiki Tar (Water Proofing for Toll Plaza Tunnel )

20 Bitumen Emulsion 4 Numbers Mathoos HINCOL, BSCPLP &Tiki Tar21 Curing Compound 1 Numbers SIKA Antisol (EW)22 Expansion Joint 1 Numbers Kanta Rubber Pvt. Ltd.23 Road signage’s 1 Numbers M/s Trade Vision India Pvt Ltd

24 Thermoplastic Road Marking and Reflecting Glass beads 2 Numbers

1) Kataline Infra Structure Ltd, Nagpur2) Automark Industries(I) Pvt. Ltd.,

Nagpur25 Geo Sewa 1 Numbers Geo Sewa Pvt. Ltd., Hyderabad26 Metal Beam Crash Barrier 1 Numbers VK Engineers, Bombay27 Briefen Wire Rope Safety fence 1 Numbers VK Engineers, Bombay28 Bituminous Joint filler board 1 Numbers M/s Tiki tar industries

29 SDBC 1 Numbers SDBC Mix Design with Km 136 Quarry/Crusher Aggregate

Note: All the above were during Construction Period now during O&M Laboratory is maintained on minimum requirement and random tests are carried out. Some equipment is yet to come to ensure minimum functionability. A time limit till 12-10-2016 has been laid out before initiating penal action for inadequacies in terms of the Contract.

MSV International Inc. Page 29

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

6.1 O&M Inspection Report

MSV International Inc. Page 30

Chapter-6O&M Inspection Report

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

The inspection started from the start chainage Km 110+000 and proceeded towards the end chainage Km 189+500. In general all site activities have been observed .However, close site inspection has been made for O&M works of PCOD- I, II & III stretch of 77.228 Kms. Observation are made as below:

6.2 Present Status of unauthorized Median: As Existing Today

Unauthorized median openings

Sl. No Chainage (Km) Remarks

1 110+600 Local people are not allowing to close2 111+300 Local people are not allowing to close3 115+200 Local people are not allowing to close4 116+300 Local people are not allowing to close5 116+700 Local people are not allowing to close6 120+000 Local people are not allowing to close7 130+000 Closed and Reopened 8 132+100 Closed and Reopened9 132+300 Closed and Reopened

10 134+000 Local people are not allowing to close11 135+950 Local people are not allowing to close12 137+100 Local people are not allowing to close13 137+700 Local people are not allowing to close14 139+000 Local people are not allowing to close15 154+780 Local people are not allowing to close16 157+200 Closed and Reopened17 160+200 Local people are not allowing to close18 161+800 Local people are not allowing to close19 163+900 Local people are not allowing to close20 167+600 Local people are not allowing to close21 173+400 Local people are not allowing to close22 173+800 Local people are not allowing to close23 175+600 Local people are not allowing to close24 116+800 Newly opened

Total 24

6.3 TL’s Inspection on dated 12-7-2016 along with Highway Maintenance Engineers.

MSV International Inc. Page 31

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Team Leader accompanied by both Highway Maintenance Engineers inspected the Sector and the following composite observations are recorded.a) Pothole which has appeared at Km 181+200 (RHS) should be repaired as per norms without delay leading to aggravation.

b) MBCBs which are dented and damaged at various locations need to be under a scheduled programme be replaced. (The MBCB Sections are slotted with a release cushion (gap) for elastic resistance on impact. While repairing sections shall be replaced as such retaining the cushioning rather than ruining the cushion effect by short term undesirable methods as welding which due to metallurgical differential expansion could strain and distort the elements besides introducing rigidity which will keep the elements of the MBCB in severe tension and liable to impact breakage). A new damage is observed at km 179+150, Km 165+150 and Km 142+800 (RHS).

c) There should be a lined drain cleaning scheme to be published. Line drains are getting blocked. Cleaning and desiltation for part of premonsoon and post monsoon activity and should be regularly attended to. One time cleaning will not do. Line drain water stagnation at Km 171+350 (RHS) and Km 128+700 (RHS) shall among others be attended.d) A programme shall be instituted and intimated to us for the removal of ROW encroached boards. A new board has come up at Km 165+800(RHS) of Vishwas Restaurant and at Km 123+600(LHS). These shall be removed.

e) A geometrically wrong sign board at Km 120+830 (LHS) shall be removed.

f) The Hospital Sign Board at Km 123+600 (RHS) shall be properly fixed.g) Wrong figurative board shown for speed breaker at Km 123+000 LHS and shall be appropriately replaced. h) The arches of the stones at Km 131, 151, 152, 153, 171 and 172 are not painted in Golden Yellow. The rise of some these stones at these above locations need to be corrected while painting.i) Erect the Delineator which has fallen down at Km 157+970(LHS).j) All Median Blinkers not functioning shall be repaired including the recent one at Nuggehalli junction.k) All lanes of Plazas must be rendered open at all times unless on repair.l) In earlier observations, we desired replacement of defective studs in site; this has not been done including the latest ones at Km 162+900 (RHS) and at Km 164+050 (RHS). The non-repair and replacement have a bearing on safety.m) The apparent structural disturbance of the direct piers resting beams on sheet bearing on the Rail Cum Road Bridge at Km 179+100 shall be monitored from underneath when heavy vehicles pass. Any deterioration further or increase in vibrational noise shall be reported. Railway Engineer has been contacted for a joint visit and repairs as needed. The transverse cracks on approaches and along bituminous wearing course on deck transversely at expansion joint sections caused by movement vibrations shall be investigated and repaired after a joint visit. The parapets of the approach Return have sunk, which shall have to be investigated and corrective action of consolidation done. n) Head walls of culverts and parapets of bridges if broken shall be repaired.

MSV International Inc. Page 32

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

o) The Hassan Byepass Road Marking with correct Thermoplastic Paint should resume in fair weather. We had stopped the work which was being done with wrong material.p) Avenue planting is not seen.q) Fill the gaps of median plants especially at Km 125+400, Km 160 to 163, Km 158, Km 151, Km 139 to Km 140, Km 130 to Km 131 and Km 153+580. r) 50% of High Mast lighting on TP2 is not working still. TP1 is working presently. s) Repair damaged bus stops at Annenahalli (Km 156+400) LHS.t) Pitching slope joints of Hirisave VUP on both sides are overgrown with small trees and bushes which if not uprooted and cleaned will displace the stones.u) At Km 151+800 an unauthorised opening is closed but finishing shall be soon done. So also at Km 135+800, Km 137+100, Km 137+700 and km 164. v) At major accident site at Km 177, your Ambulance driver was moving among crowds without an uniform. This is improper. People should be in uniform.w) Patrolling vehicles must be more effective in reporting incidents.x) Acrylic Enamel shall be used at Kerbs henceforth. Poor quality paint is peeling off / getting faded at many places as Km 164 RHS, Km 162 RHS, Km 160 RHS, Km 156 RHS, Km 127 RHS and Km 152 RHS.

These locations shall be specially attended.y) Rumbler painting must start forthwith to avoid accidents.

6.4 Team Leader’s Joint Inspection (31.08.2016).

MSV International Inc. Page 33

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

The following were present during Team Leader’s Inspection:-Independent Engineer:-Team LeaderHME- IHME-IIAHE-IITechnical Supervisor- III

Concessionaire:-Mr. Durai Raj – Project Co-ordinatorMr. T. Sunil Kumar Reddy – Project Manager (Implementation)Mr. Subhasish Kundu – Project Head (O&M)Mr. Kiran Kumar – Maintenance Manager Mr. Subbaiah – Senior Engineer Maintenance

The Team Leader noticed the following points in special:-a) Encroachments are on the rise. Due priority does not appear to be accorded. The

concerned officer to monitor this aspect is also offitiating as TP1 Manager and should at the earliest be shifted to his earlier post to do justice. TP1 Manager must be selected soon. Encroachments must be nipped in the bud.

b) The stretch km 176+000 to Km 175+000 (RHS) has alligator and longitudinal cracks greater than 3 mm and shall be raked out and an overlay provided. Failure of the wearing coat observed here is premature and must be investigated.

c) Road and Kerb markings are not made with approved paint. Frequent fadings cause redoing of the work resulting in waste of effort and expenditure. We recommend Acrylic Enamel for kerbs to last longer. Manufacturing Test Reports of Thermo Plastic Paint prior to use must be invariably handed over to Independent Engineer.

d) Stagnation of water on carriageway should not normally happen. One reason is spill over from jammed drains. A regular pre-monsoon / monsoon clearance of drains must be scheduled in the interest of unhindered movement. Berms should follow the one side camber of the carriageway to exit the runoff.

e) Essential and few Horizontal curve / S curve boards have still not been installed. This shall be done forthwith.

f) The 2 Railway Bridges are not in very good shape. Joint inspection shall at the earliest be arranged.

We have to impress upon the urgency to the Railway Officials. Cut roads regradation must commence earliest.

Composite points viz. Appendix A to B shall be attended to before the next inspection.

Please adhere to the timings in Appendix-1 as assured.

Note: See Our Letter No 1004/MSV/D-H/IE/TL/Tech/ (Inspection)/ 105 Dated: Sept 2, 2016 for Appendix.

6.5 Team Leader’s Joint Inspection (30.09.2016).

The following were present during Team Leader’s Inspection:-

MSV International Inc. Page 34

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Independent Engineer:-Team Leader- Lt. Col. Rajkumar Titus.HME-I- M.Raghava Reddy.HME-II- Challa Sreenivasa RaoAHE-II- Nabeel AhmadTechnical Supervisor- III- Janardhan Kalal

Concessionaire:- OperationsMr. T. Sunil Kumar Reddy – Project Manager (Implementation) Mr. M. Ramesh – Dy Manager Planning & ConstructionMr. Subhasish Kundu – Project Head (O&M)Mr. Kiran Kumar – Maintenance Manager Concessionaire (O & M)Mr. Subbaiah – Senior Engineer Maintenance

The Team Leader observed the following points in special and an assurance was given by the Concessionaire that rectifications will be effected:

1. Lane marking with Thermoplastic painting- By NOV 1st week, work must start.

2. Kerb painting with acrylic enamel paint - By NOV 1st week, work must start.

3. Junction marking is not visible at chainages at Km 182+250 (Gorur Junction) and Km

180+000 (Mysore Junction) By NOV 1st week, work must proceed to clear this.

4. All Rumble strips painting- By NOV 1st week, work must start.

5. Contact Numbers on Ambulance- Noted for compliance by Concessionaire.

6. BC overlay warranted at km 175+000 to 174+000 (RHS)- Noted for compliance by

Concessionaire.

7. Encroachments: Hotel name board of Adyar Bhavan, Nisagara at km 153+800 LHS) and

Rajat Daba at km 175+100 (RHS)- The details to Authority in prescribed form with lodged

FIR reports shall be sent and effort shall be made to remove the boards with police support as

needed.

8. At km 166+200 (Shanthigrama Service Road), work stopped after earth work. Concessionaire

averred that as payment was pending the owner Mr. Krishna was obstructing the line drain work-

Team Leader advised the Concessionaire to check up with the dependent Tahsildar and SLAO

for their action as relevant. Team Leader shall be present when they come to site to sort out this

issue.

9. At km 167+200 (Santhigrama), RHS pipe line shifting work is in progress.

10. Silted and damaged wall repairs of Rain Harvesting structures should be attended

immediately.

11. Lighting at Bus bays, Truck Laybyes and Median Blinkers shall improve.

MSV International Inc. Page 35

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

12. Rectification of Cracks not as per standard emulsion treatment. Cracks more than 3mm have

reflective cracks perceived after emulsion treatment. The affected stretches shall be redone /

scarified and overlaid. If cracks are extensive for 3 mm and below and incase cracks are reflected

on capped emulsion. That stretch shall be relaid then.

Cracks if visible even if capped with emulsion shall be redone interms of Clause Schedule ‘K’

of the Contract and Clause Chapter 3 (Pavement) of the O&M Manual, at km 108+800 to

108+600.

13. Lodged complaints at Channarayapatna byepass at KM 144+450 shall be reported to

Authority in prescribed format. IE shall be informed.

14. At km 123+100 Land acquisition at Hirisave (RHS) of Sakamma is now in court. Service

Road construction is affected.

15. At km 168+000 to 169+00, the median plant soil should be replaced as plants are not

flowering. Mere manuring does not help.

16. At both Toll Plazas as centre line marking is faded; painting should be done with the

thermoplastic paint as per specification.

17. At km 131+000, truncated hazard marker should be replaced with new hazard marker.

18. At some locations earthen shoulders are eroded. The correct profile should be restored and

consolidated.

19. At both Toll Plazas Civil work is stopped due to Kaveri dispute. It is time work starts. Please

peruse my letter No. 1004/MSV/D-H/IE/TL/Tech(WORK)/61 dated 24-09-2016.(copy attached)

20. At Barguru junction High mast crown light is tilted. Needs to be straightened in position to

be plumb.

6.6 Night Inspection on date 18-07-2016Lighting Status.

MSV International Inc. Page 36

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Sl.No Description of ItemTotal number of

Lights in Provision/Scope

No of Lights Working

(18-07-2016)

No of Lights Not Working(18-07-2016)

Remarks.

1 BUS BAYS 94 94 0 100% Working

2 MEDIAN LIGHTS 91 91 0 100% Working

3 SERVICE ROAD LIGHTS 99 99 0 100% Working

4 TRUCK LAY BYE LIGHTS 102 102 0 100% Working

Sl.No Description Of ItemTotal number of High-Masts in

Provision/Scope

No of high Masts Working

No of high Masts Not Working.

Remarks.

1 JUNCTION(High-Mast) 10 High – Masts 10 0 100% Working

2 TOLL PLAZA (High-Mast) 12 High-Masts 12 0 100% Working

6.7 Night Inspection on date 24-08-2016

Lighting Status.

Sl.No Description of Item Total number of No of Lights No of Lights Remarks.

MSV International Inc. Page 37

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Lights in Provision/Scope

Working(24-08-2016)

Not Working(24-08-2016)

1 BUS BAYS 94 92 2

2 MEDIAN LIGHTS 91 91 0

3 SERVICE ROAD LIGHTS 158 150 9

4 TRUCK LAY BYE LIGHTS 102 84 18

Sl.No Description Of ItemTotal number of High-Masts in

Provision/Scope

No of high Masts Working

No of high Masts Not Working.

Remarks.

1 JUNCTION(High-Mast) 10 High – Masts 10 0

2 TOLL PLAZA (High-Mast) 12 High-Masts 11 1

6.8 Night Inspection on date 24-09-2016

Lighting Status.Sl No Description of

Item

Total number of Lights in

Provision/Scope

No of Lights Working

(24-09-2016)

No of Lights Not Working

(24-09-2016)Remarks.

1 BUS BAYS 94 68 26

2 MEDIAN LIGHTS 91 90 1

3 SERVICE ROAD LIGHTS 158 147 11

4 TRUCK LAY BYE LIGHTS 102 90 12

Sl No Description of ItemTotal number of High-Masts in

Provision/Scope

No of high Masts Working

No of high Masts Not Working.

Remarks.

1 JUNCTION(High-Mast) 10 High – Masts 10 0

2 TOLL PLAZA (High-Mast) 12 High-Masts 11 1

Note: From a drastic improvement two months back there is a slide. We are Monitoring and advised the Concessionaire to tone up and reach earlier standards.6.9 Deficiencies Observed During July 2016:

Sl.No. Chainage (Km) Side Remark

1 176+200,135+000,161+250,131+000 LHS/RHS Median Blinker Not Working Properly

MSV International Inc. Page 38

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

2 182+300, LHS/RHS Delineator Bent

3 140+600 Junction Junction Ahead Symbol Missing

4 171+600,171+600,158+900,136+000 LHS/RHS Stagnation of line drain Water

5 159+800,164+400,164+800 LHS/RHS Rain Water Harvesting Structure Damaged

6 179+100 LHS/RHS Minor Bridge Expansion Joint.

7 183+250 RHS Pot hole on Main Carriageway

8164+000 ,151+800 142+300 ,115+900, 125+750 ,131+050 ,132+900, 135+000

150+500 ,151+400 ,154+950 ,154+900 ,161+500 ,163+800 ,164+800,

RHS/LHS

Studs to be replace

9

185+300 ,185+200 ,181+600181+500 ,179+000 ,172+700 ,172+250 ,1

69+500 ,160+050 ,155+250 ,148+300146+800 ,140+700,

124+800 ,119+000 ,110+400,118+800 ,126+050

LHS/RHS/Junction

Locations f Hazard Markers Not As Per IRC 67-2001

See our letter No:(

1004/MSV/D-H/IE/TL/Tech/(Inspection)/71 )

10

185+000 to 185+200,168+800 to 169+600 ,185+200 , 181+545 ,

184+000 to 185+000,183+000 to 184+000,181+000 to 182+000,

180+000 to 181+000,179+000 to 180+000,176+200 to 177+000 ,

177+000 to 179+000

LHS/RHS/Junction

Thermoplastic paint /Road Marking Faded Locations

See our letter No:(1004/MSV/D-H/IE/TL/Tech/

(Inspection)/68)

11167+400 to 168+600,123+200 to

124+000,163+000 to 165+400,168+800 to 170+000,174+200 to 175+600

MedianFaded Median Kerb Locations

See our letter No:(1004/MSV/D-H/IE/TL/Tech/

(Inspection)/66)

12 175+800, 122+100,132+900 LHS/RHS/ Junction

Object Markers are Not as Per IRC 67-2001See our letter No:

1004/MSV/D-H/IE/TL/Tech/(Inspection)/71& 1004/MSV/DH/IE/TL/Tech/(Inspection)/66

13

172+100,163+600,161+500155+600,151+500,144+220,

144+400 LHS/RHS

Locations of Curve sign Boards Not ProvidedSee our letter No:

1004/MSV/D-H/IE/TL/Tech/(Inspection)/71&

1004/MSV/D-H/IE/TL/Tech/(Inspection)/66

6.10 Deficiencies Observed During August 2016:

Sl.No Description of work Chainage (Km) Side

MSV International Inc. Page 39

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

1 Pot hole on Main Carriageway 116+250,130+800,162+900,162+950,168+100,180+900,183+150,183+250 LHS/RHS

2 Hazard Marker Sticker Faded/Damaged 154+950,181+050, 144+350 and 117+250. LHS/RHS

3 Junction Ahead Symbol Missing 140+600 Junction

5 Rain Water Harvesting Structure Damaged 159+800 LHS/RHS

6 Median Blinker Not Working Properly 176+200 LHS/RHS

6.11 Deficiencies Observed During September 2016:

Sl No Description of work Chainage (Km) Side

1 MBCB Damaged at following Chainages

144+380(RHS), 182+100(LHS), 181+100(LHS), 178+100(RHS), 165+100(RHS), 159+700(RHS),

144+600(RHS).LHS/RHS

2 Bent Delineator should be fixed properly

134+630(RHS), 169+100(RHS), 185+300(RHS), 177+960(RHS), 163+700(RHS). LHS/RHS

3 KM Stone should be fixed properly 111+000 RHS

4 Hectometer Stone should be fix properly 159+200 RHS

5 Earthen shoulder Eroded 170+500 RHS

6 Destination Board is not as per IRC 139+950, 140+400

7 Following are the chain ages in which KM Stone is Behind the MBCB

180+000(LHS), 168+000(BHS), 167+000(BHS), 157+000(BHS), 155+000(BHS) and

176+000(LHS).

8 Median Solar Blinkers Not Working in following Locations

112+800, 128+400, 131+000, 135+000, 140+200, 168+600, 171+000

Towards Bangalore

129+200, 131+000, 135+000, 142+200, 176+200

Towards Hassan

6.12 Compliance /Non Compliance report July 2016:

Sl.No Description of work Chainage (Km) Side Remarks

MSV International Inc. Page 40

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

1 Destination description missing 139+000 RHS Not Done

2 Bus stop name Missing 133 LHS Not provided

3 Wire rope caps missed to be provide for proper functioning 125+400 to 126+800 LHS Not provided

4 Lane Marking Not Visible 169+00, 171+000 to 172+000 RHS Not Done

5 KM Stone should be fix properly 113+000 RHS Not Fixed

6 KM Stone damaged 133+000 RHS Not done

7 Wrong Hazard Marker Provided 158+500,181+545 Junction/LHS Not done

8 Kerb Edge Side Thermoplastic paintfaded 168+800 to 171.000 LHS/RHS

Not doneProperly

9Curve Indication Sign Board should

be Wrongly provided 176+200 Junction Not done

6.13 Compliance /Non Compliance report August 2016:

Sl.No

Description of work Chainage (Km) Side Remarks

1 Bus stop name Missing 133 LHS Not provided

2 Wire rope caps missed to be provide for proper functioning 125+400 to 126+800 LHS Not provided

3 KM Stone should be fix properly 113+000 RHS Not Fixed

4 Wrong Hazard Marker Provided 158+500 Junction/LHS Not done

5 Studs to be replace

164+000 ,151+800 142+300 ,115+900,

125+750 ,131+050 ,132+900, 135+000

150+500 ,151+400 ,154+950 ,154+900 ,161+500 ,163+800 ,164+80

0,

RHS/LHS Not done

6Locations f Hazard Markers Not Provided

And Also Not As Per IRC 67-2001

185+300 ,185+200 ,181+500 ,172+250 ,169+500 ,160+050,140+7

00, 124+800 ,119+000 ,110+400,118

+800 ,126+050

LHS/RHS/Junction Not done

7

Thermoplastic paint /Road Marking Faded 185+000 to 185+200,168+800

to169+600 ,184+000 to

LHS/RHS/Junction

Not done

MSV International Inc. Page 41

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Locations185+000,181+000

to182+000,180+000 to181+000,179+000to180+000,17

6+200 to 177+000 ,177+000 to 179+000

8 Faded Median Kerb Painting Locations 123+200 to 124+000,174+200 to 175+600 Median Not done

9 Object Markers are Not as Per IRC 67-2001 132+900 LHS/RHS Not done

10Locations of Curve sign Boards Not

Provided

172+100,163+600,161+500155+600,151+500,144+220,

144+400 LHS/RHS Not Provided

6.14 Compliance /Non Compliance report of September 2016:

Sl. No

Description of work Chainage (Km) Side Remarks

1 Pot hole on Main Carriageway

116+250,130+800,162+900,162+950,168+100,

180+900,183+150,183+250

LHS/RHS Done

2Hazard Marker Sticker Faded/Damaged 154+950,181+050, 144+350 and

117+250. LHS/RHS Done

3 Junction Ahead Symbol Missing 140+600 Junction Not Done

4 Median Blinker Not Working Properly 176+200 LHS/RHS Working

6.15 Status of Plantation:

MSV International Inc. Page 42

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Median Plantation

Sl No Date

Chainage Side Numbers of

Plants RemarksFrom To

1 6-Sep-16 111.000 111.800 Median 40  

2 12-Sep-16 160.400 160.900 Median 30  

3 15-Sep-16 150.500 150.800 Median 40  

4   159.800 160.100 Median 30  

5 17-Sep-16 158.600 159.000 Median 40  

6 21-Sep-16 134.000 134.800 Median 30  

7 22-Sep-16 134.800 135.200 Median 30  

8 28-Sep-16 174.500 174.800 Median 60  

      

Total 300  

Avenue Plantation

MSV International Inc. Page 43

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Sl No DateChainage

Side Number of Plants RemarksFrom To

1 1-Sep-16 119.000 120.000 LHS 70

2 3-Sep-16 120.000 120.300 RHS 25

3 162.400 162.600 RHS 15

4 7-Sep-16 110.000 110.600 RHS 30

5 10-Sep-16 117.800 118.600 LHS 40

6 12-Sep-16 109.600 110.000 LHS 20

7 13-Sep-16 133.000 133.800 RHS 45

8 14-Sep-16 127.200 128.000 LHS 40

9 15-Sep-16 169.400 169.600 RHS 15

10 17-Sep-16 128.400 129.600 RHS 50

11 20-Sep-16 129.000 129.800 LHS 40

12 21-Sep-16 134.000 134.800 RHS 30

13 22-Sep-16 133.800 134.000 RHS 10

14 134.000 134.600 LHS 25

15 23-Sep-16 127.000 128.000 RHS 50

16 24-Sep-16 165.000 165.600 RHS 20

17 26-Sep-16 152.100 152.600 LHS 25

18 27-Sep-16 136.200 136.500 LHS 20

19 152.200 152.700 RHS 25

20 28-Sep-16 164.000 164.800 LHS 40

21 29-Sep-16 124.600 125.200 RHS 35

670

MSV International Inc. Page 44

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

6.16 Safety IssuesNATIONAL HIGHWAYS AUTHORITY OF INDIAKARNATAKA REGION,REGIONAL OFFICE BANGALOREReport on safety issues on National Highways in the State of Karnataka  Name of Work: Four Laning of Devihalli-Hassan in NH75Name of Concessionaire: L&T Devihalli Hassan Toll way Limited     Name of IE: MSV INTERNATIONAL.INC  

 

Sl.No Safety issue Location as on Action taken for closing / removal / attended/replaced

Locations action pending with reason

Issue raised with enforcing agency

Penal action by IE due to delay / no action

1 Unauthorized median openings

23 Chainage No:109.795,111.300,114.372, 115.511, 119.965,123.100,135.151,136.310,136.930,138.350, 150.962,154.600,159.330, 163.800,167.700,173.500,173.800,175.150

4 closed

23 Chainage No:109.795,114.372,115.511,119.965,124.655,126.097,128.133,130.563133.208,134.452134.786,135.151,136.310,150.962,156.955, 159.330,163.205

Yes

Letters written to DC & SP, Mandya & Hassan vide Nos. 2817 & 2819 dt. 07.10.2014

Nil

2 Liquor shops adjacent to highway

Kadabahalli 1 Liquor shops RHS Km115.200,Herisave 4 liquor shops RHS and LHS km 123.200,Udayapura 1 liquor shop at KM 155.500 , Shantigrama 1 liquor shop Km166.100

Kadabahalli 115.200 RHS Liquor shop was shifted inside the village.

Hirisave 4 liquor shops RHS and LHS km 123.200,Udayapura 1 liquor shop at Km 155.500 , Shantigrama 1 liquor shop KM 166.100

YesLetters written to DC & SP, Mandya and Hassan vide Nos. 2798 & 2797 dt. 01.10.2014 and vide No. 1267 dt. 04.07.2013 & Letter No.22/2014 Dated.17.11.2014

Nil

3Black spots (10 accidents & more in a year at any spot causing fatalities)

Km 164+900 & Tiptur Junction

MSV International Inc. Page 45

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

4

Major / Minor junctions Transverse bar marking, rumble strips, speed breakers on X-road, Signage’s etc. Speed restriction signage’s as per enforcing agency requirement

ShettyHalli junction at Km 140.100,Nuggehalli Junction At Km 142.200 and Arsikere Junction at Km 149.800, Kadabahalli Junction at Km 115.750

Insisted by local police

ShettyHalli junction at KM140.100,Nuggehalli Junction AT KM142.200 and Arsikere Junction at KM149.800, Kadabahalli Junction at 115.750

NA Nil

5 Encroachment within ROW

Details enclosed at Annexure-I This office vide letter dated 30.01.2015 requested DC, Mandya & Hassan to direct the concern Officials to remove encroachments from NH Right of Way so as to achieve safe movement of traffic along NHs.

Notice issued dated 14.10.2015 for illegal access and name boards made by hotels & Restaurant at following Chainages :-109.200LHS, 115.300LHS, 120.800LHS, 132.800LHS, 147.200LHS,177.100 RHS, 174.500 RHS

- - Nil

6 Dumped/Surplus waste material

NIL

7 Damaged / deficient signage’s as per codal / CA provisions

NIL

8 Public demand/VIP ref. for VUP/ PUP /FOB etc.,

(1) Shri Cheluraya Swamy, Hon'ble MLA, Nagamangala has requested to construct VUP at Kadabahalli at Km 115/200. (2) Shri H.D.DeveGowda, Hon'ble Former PM of India and ShriBala Krishna, Hon'ble MLA Shravanabelagola has requested to construct VUP at ArsikereJuncion @ Km 149/800 &Nuggehalli Junction at Km 142/200. The estimate for overpass has been submitted by Concessionaire and is under scrutiny at IE level.

Public are demanding service Roads in all built up areas in project corridor.

9Any other unauthorized /illegal/unsafe activities on/ along project highway

Over speeding vehicles: In this regard, Concessionaire office vide letter Nos. 2742 & 2741 dt.29.09.2014 have requested DC, Mandya & Hassan to direct all the concerned for enforcing the speed limit of vehicle moving on NHs in order to avoid accident.

10 Cut Road sign board Letter No: 1004/MSV/D-H/IE/Tech/Deficiency/58 Dated: 08.03.2016

MSV International Inc. Page 46

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

6.17 ENCROACHMENTS DETAILS

Sl No Chainage (Km) Nature of Encroachment Efforts made for removal of encroachment

Target date for removal of encroachment Remarks

1 114.650 (LHS) Hotel BoardYes efforts were made to remove Land dispute and

payment issue15-Jun-16 Not Removed

2 135.000 (LHS) Building PillersYes efforts were made to

remove pressure from locals and polities

15-Jun-16 Not Removed

3 122.150 (LHS) Hotel Board Yes efforts were made to remove local politics pressure 15-Jun-16 Not Removed

4 141.900 (LHS) Dhaba Board Yes efforts were made to remove local politics pressure 15-Jun-16 Not Removed

05 153.600 (LHS) A2B Board Yes efforts were made to remove local politics pressure 15-Jun-16 Not Removed

6 166.400 (LHS) Petty Shop Yes efforts were made to remove local politics pressure 15-Jun-16 Not Removed

7 166.100 (LHS) Building Yes efforts were made to remove local politics pressure 15-Jun-16 Not Removed

8 153.800 (RHS) Nisarga Dhaba Board Yes efforts were made to remove local politics pressure 15-Jun-16 Not Removed

9 157.200 (RHS) College Board Yes efforts were made to remove local politics pressure 15-Jun-16 Not Removed

10 175.400 (RHS) Hotel BoardYes efforts were made to

remove local Villagers and politics pressure

15-Jun-16 Not Removed

MSV International Inc. Page 47

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Observed Encroachment DetailsSl No Chainage Side Description

1 184+800 RHS SKB Hotel board2 184+200 RHS Red Fort Restaurant board3 184+050 RHS HMS Auto diesel works name board4 184+000 RHS MK Family board5 183+950 RHS Star Hotel name board6 183+860 LHS Banaras Transport name board7 183+100 RHS New HMG Auto diesel works board8 183+060 LHS Vishwas Ginger Trading name board and Compound Wall9 183+050 LHS St.Josephs College board10 183+050 LHS Parivarthana Vyasana Mukthi Kendra name board11 182+700 LHS High Voltage Power Transmitting Truss12 182+200 RHS Kenchamba Hotel board13 182+200 RHS Swamy Fuel board14 182+170 RHS Petty Shop15 182+030 RHS A.P Car care building16 181+600 RHS Highway punture shop board17 181+300 LHS Rajarajeshwary lorry service station board18 180+350 RHS Nandi weigh bridge board19 180+570 LHS Jagadesh Engineering works board20 180+800 LHS Pavanputra Resort board21 178+100 RHS MR Hotel board22 175+150 RHS Hotel Likith, Hotel Vismaya board & building23 118+400 LHS Prajwal Family Restaurant board24 123+600 LHS Ganesh hotel board25 123+600 LHS Kaveri Gramina Bank board26 123+630 LHS Keralapura Hindu Miltry Hotel board

6.18 Construction of Public Facilities as Reported By Concessionaire

MSV International Inc. Page 48

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Toll Plaza equipped with All Project Facitilies

SL. No. Name of PIU Name of Project Date of COD

Toll plaza Project Facilities In case of default action taken

Remarks

Name

Tolling Stretch Chainage Traffic Aid post Medical Aid post Toilet Facilities

From To

1 Bangalore

116.790 107.684 147.424 Yes Yes 66 Sqm Yes Yes Nil - NA

165.170 147.424 184.912 Yes Yes 132 Sqm Yes Yes Nil - NA

Whether Proper display board

installed for public informatio

nLocation Chainage

Delay in Construction (in

days)

Reason for delay

Damages recoveredArea of Building

Constructed

Whether Operation

al

Area of Building Constructed

Whether Operation

al

Whether Operational

Whether Maintained

Properly

Devihalli to Hassan By pass end section of NH 75 From Km 107.684 to 184.912 in

the state of Karnataka

14.11.2013 for 77.3% (PCOD I) , 05.12.2014 for

96.276% (PCOD II) & 06.10.2015 FOR 100% (PCOD III)

Kadhaballi Toll Plaza

constructed

(Work in Progress)

constructed(work in

progress)

We have provided Porta toilets at plazas as building is yet to be constucted. The toilets

will be constructed alond with the building

there are 2 truck lay bye (LHS & Rhs) in this

chainage where in public toilets are

available

Shanthigrama Toll Plaza

constructed

(Work in Progress)

constructed(work in

progress)

We have provided Porta toilets at plazas as building is yet to be constucted. The toilets

will be constructed alond with the building

there are 4 truck lay bye (LHS & Rhs) in this

chainage where in public toilets are

available

MSV International Inc. Page 49

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

MSV International Inc. Page 50

Chapter-7Traffic & Safety Measures

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

7.1 TRAFFIC & SAFETY MEASURES

1. Traffic control & safety devices viz., Signs, Delineators, Blinkers, Barriers, etc., at the work sites as per relevant standards viz. NHAI-Technical Specification, IRC: SP-55-2014 & IRC: SP: 84-2014 have not been provided by the Concessionaire in full.

2. All Working Zones must be provided with adequate lateral & longitudinal buffer clearances as per IRC: SP: 55-2014.

3. Lapses observed at site in providing necessary PPE viz. Safety Shoe, Gloves, Jackets, to the workers. Necessary safety jackets, gloves, shall be provided to all workers at site by the Concessionaire.

4. The Concessionaire has been asked to comply whenever the deficiencies observed in the traffic safety measures have been pointed out. Full compliance awaited.

7.2 Status of Traffic Safety Measures

1) HSMU not established - ad hoc now

2) Traffic Aid Post not established.

3) Cautionary/Warning signs to be increased - See Letter Number/Inspection-108 Date: 28.09.2016

7.3 Accident Report /Incident Report

1.) Details of Accident Report

2.) Details of Incident Report

Abstract for Accident Report :-

Sl.No Type of Accident July-16 August-16 September-16 Total1 Fatal 10 5 5 202 Major 26 18 25 693 Non-Injury 16 11 12 394 Minor 37 29 14 80

Total 208

MSV International Inc. Page 51

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

MSV International Inc. Page 52

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

MSV International Inc. Page 53

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

MSV International Inc. Page 54

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Details of Accident Report:September-2016

ACCIDENT INCIDENT REPORTREPORT FOR THE MONTH: September-2016

SPV NAME: L&T DHTLADDRESS: Toll Plaza KM 116+792 NH-75 , Kadaballi Village,D

S.No Date Response Location Accident Services Nature Of Injury Damage FIR Cause of Time Chainage MCW/PR LHS/RHS Details Provided Minor Major Fatal NonInjury to Assets Lodged Accident Action

1 02-09-2016 20:01 00:00 175.200 Km MCW LHS RPV,,Ambulance - Y - - N N Vehicle lost control

2 03-09-2016 02:41 00:00 142.200 Km MCW RHS RPV - - - Y N N Vehicle lost control

3 03-09-2016 13:54 00:00 115.700 Km MCW LHS RPV,Ambulance - Y - - N N Vehicle lost control

4 05-09-2016 12:08 00:00 163.900 Km MCW LHS RPV - - - Y N N Vehicle lost control

5 06-09-2016 13:59 00:00 115.200 Km MCW LHS RPV,Ambulance Y Y - - N N Vehicle lost control

6 06-09-2016 14:30 00:00 126.800 Km OTH LHS RPV,Ambulance - Y - - N N Vehicle lost control

7 07-09-2016 07:17 00:00 142.700 Km OTH LHS RPV Y - - - N N Vehicle lost control

8 07-09-2016 10:52 00:00 162.050 Km MCW RHS RPV - - - - N N Animals in road

9 08-09-2016 05:15 00:00 112.000 Km MCW RHS - Y - - N N Drunken driving

10 08-09-2016 07:44 00:00 124.200 Km MCW RHS RPV - - - Y N N Overspeed

11 08-09-2016 14:22 00:00 145.600 Km OTH LHS RPV - - Y - N N Pedestrian related

12 08-09-2016 16:40 00:00 111.500 Km MCW RHS RPV - - - Y N N Vehicle lost control

13 08-09-2016 19:11 00:00 125.000 Km MCW LHS RPV - - - Y N N Vehicle lost control

14 10-09-2016 17:37 00:00 130.800 Km OTH LHS Y - - - N N Overspeed

15 11-09-2016 11:51 00:00 148.800 Km MCW RHS RPV,Ambulance Y Y - - N N Vehicle lost control

16 12-09-2016 15:04 00:00 171.000 Km MCW RHS RPV Y - - - N N Overspeed

17 12-09-2016 17:53 00:00 171.100 Km OTH LHS RPV,Tow Truck - - - Y N N Vehicle lost control

18 17-09-2016 12:00 00:00 154.200 Km MCW RHS RPV - - Y - N N Driver negligency Driver negligence.

19 17-09-2016 18:17 00:00 131.800 Km OTH LHS RPV - - - Y N N Overspeed

20 17-09-2016 20:20 00:00 145.600 Km OTH LHS RPV - - - Y N N Overspeed

Time [24 hrs]

Proposed Remedial

A car hit to gantry board due to driver lost the control.

A Car hit to Car due to driver lost control,Head & tail collision.

A car hit to bike due to driver lost the control,Head & tail collision.

A Bus hit to car due to driver lost the control,Hit & run.

A Car hit to Car due to driver lost the control,Head & tail collision.

A Car hit to Bike due to driver lost the control,Head on collision.A Car upside due to over speed.A bus hit to cow, accident due to animal.A car upside due to drunk & drive.

RPV,Ambulance,Tow Truck

A Car upside due to over speed.A Car hit to pedestrian due to driver lost the control,Hit & run

A MAV hit to car due to driver lost the control,Head & tail collision.A car upside due to over speed.

A CJV upside due to over speed.

RPV,Ambulance,Tow Truck

A Car hit to Car due to driver lost the control,Head on collision.

A bike upside due to over speed.

A truck hit to car due to driver lost the control,Head on collision.

A bike hit to pedestrian due to driver negligence,

A Bike upside due to over speed.

A tractor upside due to over speed.

MSV International Inc. Page 55

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

ACCIDENT INCIDENT REPORTREPORT FOR THE MONTH: September-2016

SPV NAME: L&T DHTLADDRESS: Toll Plaza KM 116+792 NH-75 , Kadaballi Village,D

S.No Date Response Location Accident Services Nature Of Injury Damage FIR Cause of Time Chainage MCW/PR LHS/RHS Details Provided Minor Major Fatal NonInjury to Assets Lodged Accident Action

1 02-09-2016 20:01 00:00 175.200 Km MCW LHS RPV,,Ambulance - Y - - N N Vehicle lost control

2 03-09-2016 02:41 00:00 142.200 Km MCW RHS RPV - - - Y N N Vehicle lost control

3 03-09-2016 13:54 00:00 115.700 Km MCW LHS RPV,Ambulance - Y - - N N Vehicle lost control

4 05-09-2016 12:08 00:00 163.900 Km MCW LHS RPV - - - Y N N Vehicle lost control

5 06-09-2016 13:59 00:00 115.200 Km MCW LHS RPV,Ambulance Y Y - - N N Vehicle lost control

6 06-09-2016 14:30 00:00 126.800 Km OTH LHS RPV,Ambulance - Y - - N N Vehicle lost control

7 07-09-2016 07:17 00:00 142.700 Km OTH LHS RPV Y - - - N N Vehicle lost control

8 07-09-2016 10:52 00:00 162.050 Km MCW RHS RPV - - - - N N Animals in road

9 08-09-2016 05:15 00:00 112.000 Km MCW RHS - Y - - N N Drunken driving

10 08-09-2016 07:44 00:00 124.200 Km MCW RHS RPV - - - Y N N Overspeed

11 08-09-2016 14:22 00:00 145.600 Km OTH LHS RPV - - Y - N N Pedestrian related

12 08-09-2016 16:40 00:00 111.500 Km MCW RHS RPV - - - Y N N Vehicle lost control

13 08-09-2016 19:11 00:00 125.000 Km MCW LHS RPV - - - Y N N Vehicle lost control

14 10-09-2016 17:37 00:00 130.800 Km OTH LHS Y - - - N N Overspeed

15 11-09-2016 11:51 00:00 148.800 Km MCW RHS RPV,Ambulance Y Y - - N N Vehicle lost control

16 12-09-2016 15:04 00:00 171.000 Km MCW RHS RPV Y - - - N N Overspeed

17 12-09-2016 17:53 00:00 171.100 Km OTH LHS RPV,Tow Truck - - - Y N N Vehicle lost control

18 17-09-2016 12:00 00:00 154.200 Km MCW RHS RPV - - Y - N N Driver negligency Driver negligence.

19 17-09-2016 18:17 00:00 131.800 Km OTH LHS RPV - - - Y N N Overspeed

20 17-09-2016 20:20 00:00 145.600 Km OTH LHS RPV - - - Y N N Overspeed

Time [24 hrs]

Proposed Remedial

A car hit to gantry board due to driver lost the control.

A Car hit to Car due to driver lost control,Head & tail collision.

A car hit to bike due to driver lost the control,Head & tail collision.

A Bus hit to car due to driver lost the control,Hit & run.

A Car hit to Car due to driver lost the control,Head & tail collision.

A Car hit to Bike due to driver lost the control,Head on collision.A Car upside due to over speed.A bus hit to cow, accident due to animal.A car upside due to drunk & drive.

RPV,Ambulance,Tow Truck

A Car upside due to over speed.A Car hit to pedestrian due to driver lost the control,Hit & run

A MAV hit to car due to driver lost the control,Head & tail collision.A car upside due to over speed.

A CJV upside due to over speed.

RPV,Ambulance,Tow Truck

A Car hit to Car due to driver lost the control,Head on collision.

A bike upside due to over speed.

A truck hit to car due to driver lost the control,Head on collision.

A bike hit to pedestrian due to driver negligence,

A Bike upside due to over speed.

A tractor upside due to over speed.

MSV International Inc. Page 56

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Details of Incident Management Report: July-2016 SAMPLE SHEET FOR RO

SUMMARY REPORT- STATEWISE Karnataka

Incident Management Data

July 1 to july 31 2016

Reference is made to NHAI HQ letter No. NHAI/CM/Inc.Man/2011 dated 24.05.2011 RO: BengaluruSECTION OF DEVIHALLI HASSAN FROM 108.450 to 184.912

Ambulance Tow Away Crane

1 Total No. of vehicles 2 2 2

2 Total number of accidents reported 49

3 Number of accident cases attended 49 22 7

4 Number of injured shifted to hospital 18

5 371 0 0

6 7

7 2 2 2

8 2 2 2

9 2 2 2

10 2 2 2

11 No. of vehicles fitted with GPS/VTS 2 2 2

12 20

13 Total no. of Toll Plazas 2

14 2

15 2

Genaral Information

Route Patrol

Vehicle Remarks/ reasons for non-

compliance

Number of other help provided by Route Patrol (other than accidents)

Number of help provided by Tow Away Vehicle (other than accidents)

No. of vehicles painted in stripes as per approved colour scheme

No. of vehicles with requisite T & P and accessories as per contract

No. of vehicles as per approved illuminated boards on top

No. of vehicles with Requisite man power as per contract

No. of reflective signages showing emergency contact no.

No. of plazas where emergency contact details boards are installed

No. of plaza where information is being printed on back of toll tickets

MSV International Inc. Page 57

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Details of Incident Management Report: August-2016

Details of Incident Management Report: September-2016

MSV International Inc. Page 58

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

INCIDENT MANAGEMENT DATA

    General Information

Route Patrol Vehicle

Ambulance Tow away crane

Remarks/ Reasons for non-compliance

1 Total Number Of Vehicles 6 2 2 2

Nil

2 Total Number Of accidents reported 38 38 16 63 Number of accident cases attended 38 38 16 64 Number of injured shifted to hospital 16 0 16 05 Number of other help provided by Route Patrol (other than accidents) 0 297 0 0

6 Number of help provided by Tow Away Vehicle (other than accidents) 0 0 0 6

7 Number of vehicles painted in stripes as per approved color scheme 6 2 2 28 Number of vehicles with requisite T & P and accessories as per contract 6 2 2 29 Number of vehicles as per approved illuminated boards on top 2 2 2 210 Number of vehicles with Requisite man power as per contract 6 2 2 211 Number of vehicles fitted with GPS/VTS 6 2 2 212 Number of reflective signages showing emergency contact No. 28 - - -13 Total Number of Toll Plazas 2 - - -

14 Number of Plaza where emergency contact details boards are installed 2 - - -

15 Number of Plaza where information is being printed on back of toll tickets

2 - - -

16 Date of last inspection by PD/RO to verify compliance of HQ instructions   - - -  

MSV International Inc. Page 59

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

MSV International Inc. Page 60

Chapter-8Plant and Machineries

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

8.1 PLANT & MACHINERIES

Status of Major Plant & Machinery

Sl No Type of Machinery Capacity Model Total

1 Excavator 1.1 Cum PC 200 L&T Komatsu, JCB 210 22 Grader GD 511 A L&T Komatsu 13 Soil Compactors L&T 1107D+ BW 212AD, EC 5250 PD 24 Tandem Roller IR IDD 90 1

5 Pneumatic Tyre Roller(PTR) IR 220 1

6 Pavers 400 TPH BITELLI, APOLLO 27 Bitumen Tanker 5 KL Comet Leyland 1

8 Water Tankers 20 KL15 KL 2516 Leyland, HMT Tractor 3

9 Taurus 10 Cum Leyland 2516 510 Tipper 4 Cum Leyland Comet 211 Tractors 2 Cum HMT, MAHENDRA 212 Wheel Loaders 3 Cum (5 T) Changing ZL50H 113 Hydra Crane 12 T, 10T ACT 12 XW 1

14 RMC Batching Plant 30 Cum/hr CP30, Setter 1

15 WMM Plants 100 TPH, 250 TPH APPOLLO 1

16 H M Plant 200 TPH DMI Corporation, D&G 1

17 Generator sets 500 kva, 400 kva, 380 kva, 62+5 kva, 50 kva, 15 kva, 10 kva, 5 kva 6

18 Compressors 165 PSI IR HP 400, Tractor Compressor 1

19 Light Vehicles Bolero Camper, Sumo, Tavera, Xylo, Omni, Indica 3

20 Motor Bikes Hero Honda, TVS 321 Hydraulic Broomer 122 Transit Mixers 6 Cum 2516 Leyland 123 Trailer 40 Tons Leyland 1

24 Milling Machine 1

25 JCB 1

26 Diesel Tanker 8 KL 1

27 Weigh Bridge 100T, 80T,60T 1

MSV International Inc. Page 61

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

9.1 HINDRANCE/LAND ACQUISITION STATUS/UTILITY SHIFTING

MSV International Inc. Page 62

Chapter-9Hindrances/ Land Acquisition Status

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Narrative Report

Pre-construction activities includes land acquisition, encroachment removal, relocation of religious structures, utilities shifting, shifting of tank bund and cutting trees from right of way.

Attention has been paid for removal of hindrances. Recently some more areas have been cleared with the help of NHAI representative and SLAO. Now the hindrance affected length at end of Sep 2015 has reduced on both LHS and RHS of the Project Highway

1. 100% of land was handed over to the Concessionaire by NHAI.2. 98% of Electrical lines shifting works has been completed.2% of electrical shifting is yet

to be completed in Mandya district and Hassan district.3. 99% of Water line shifting works has been completed.1% of water line shifting is yet to

be completed in Mandya district and Hassan district.4. Additional land for Toll Plaza 1& 2 handed over to the Concessionaire by the Authority.

9.2 List of Hindrances

There is no hindrances observed for the month of May 2016 for main carriageway are as follows:-

Obstruction in Shantigrama (Law and Order)

Sl no.Chainage

Side Owner Sy. No RemarkFrom To

1 166.7 166.74 LHS

Obstruction for taking up

DORE SWAMY S/O VEERBHADRIAH

Gramatana in between 443/4 & 447 /4

Owner need clarity on the extent for lands aquiereds. SLAO needs to clarity.

obstructing Service Road & MCW WORK & utillity shifting

Obstruction in Toll plaza -1

Sl no.Chainage

Side Owner Sy. No RemarkFrom To

1 116+850 116+850 TP-1 Land owners

Obstruction for taking up

Land owner wants way to their fields Compound wall

Toll Plaza -1

MSV International Inc. Page 63

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Obstruction in Shantigrama-RHS

Sl no.Chainage

Side Owner Sy. No RemarkFrom To

1 166.36 166.38 RHS Manjegowda Gramatana

2 166.38 166.4 RHS Gramatana

3 166.74 166.78 RHS Manjunath Gramatana

Obstruction for taking up

Payment pending for the building (Additional

valuation)Service road and

drain

Sarojamma ramachandra

Party demanding for payment

Service road and drain

Owner needs clarity on the extent land acquired. SLAO needs to clarify & finalise the same.

Service road and drain

Obstruction in Hirisave (Law and Order)

Sl no.Chainage

Side Owner Sy. No RemarkFrom To

1 123+100 123+200 RHS Sakamma Sy. No 20/1

Obstruction for taking up

Owner need clarity on the extent for lands aquiereds. SLAO needs to clarity.Now this dispute in Court.

obstructing Service Road & MCW WORK & utillity shifting

MSV International Inc. Page 64

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

INCOMMING LETTER FROM NHAI- JULY-2016

MSV International Inc. Page 65

Chapter-10Correspondence

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Sl.No LETTER NO. DATED ON SUBJECT

1 NHAI/22015/01/10/PIU-BNG/1347 1-July-2016 Marking of unpainted stretches especially Hassan Byepass.

2 NHAI/22015/01/10/PIU-BNG/1349 1-July-2016 Lighting defects: Recurrent-reg.

3 NHAI/22015/01/10/PIU-BNG/1350 1- July -2016 Update of the Toll Plazas-compliance Due.

4 NHAI/22015/01/15/PIU-BNG/1351 1- July -2016 Near stoppage of works in Plaza No.1

5 NHAI/22015/01/15/PIU-BNG/1391 5- July 2016 Request for Information under Right to Information Act, 2005

6 NHAI/22015/01/15/PIU-BNG/1315 5 July -2016

Design Engineering, Construction, Development, Finance, Operation & Maintenance of Devihalli to Hassan

NH-48 from Km 110.00 to km 189.500 in the SOK under NHDP Phase-IIIA on

DBFOT basis – reg.

7 NHAI/22012/1/10/PIU-BNG/1370 5- July -2016Requesting for construction of service road, rumble strip and solar lights at

Mattanavile village.

8 NHAI/22015/1/10/PIU-BNG/1372 5- July -2016 Pending works and proposed resolutions – reg.

9 NHAI/22015/1/10/PIU-BNG/1371 5- July -2016 Lighting defects: Recurrent – reg.

10 NHAI/22015/1/10/PIU-BNG/1375 5-july-2016Providing police protection for

demolition of acquired Building at Hirisave.

11 NHAI/22032/1/10/PIU-BNG/1361 12- July -2016 Regarding meeting on 15/7/2016 (postponed).

12 NHAI/22032/1/15/PIU-BNG/1440 11- July -2016 Settlement.

13 NHAI/22015/1/15/PIU-BNG/1398 11- July -2016Inspection XVI on zone 23rd of site by

team leader.

14 NHAI/22015/1/15/PIU-BNG/1405 11- July -2016 Toll expert

15 NHAI/22015/1/10/PIU-BNG/1402 11- July -2016Marking of unpainted stretches

especially Hassan Byepass- Inferior of Unacceptable road marking- reg.

16 NHAI/22015/1/10/PIU-BNG/1403 11 July -2016 Avenue plants: pre notice.

17 NHAI/22032/1/15/PIU-BNG/1404 11- July -2016 Notice: Non operationalisation of ETC lane and static weigh bridge.

18 NHAI/22012/1/10/PIU-BNG/1406 11- July -2016

Notice: Requirement of Non- Interrupted Supply of Light for 24 hours in the highway corridor- regarding Non-

Compliance.

MSV International Inc. Page 66

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

19 NHAI/22032/1/15/PIU-BNG/1439 11- July -2016 Karnataka Legislative Assembly Petitions Committee meeting on 23-06-2016- regarding furnishing information

for application No. 120/2015.

20 NHAI/22015/1/10/PIU-BNG/03 18- July -2016Providing police protection during

acquisition of land/ structure at Hirisave.

21 NHAI/22015/1/10/PIU-BNG/1498 15- July -2016 Vanamahotsava Programme conducted from 2nd July to 10th July 2016.

22 NHAI/22015/1/10/PIU-HSN/24 19- July -2016 Avenue Plants: Pre Notice Caution I- reg.

23 NHAI/22015/1/10/PIU-HSN/25 19- July -2016 Toll Expert – reg.

24 NHAI/22015/1/10/PIU-HSN/26 19- July -2016 Settlement.

25 NHAI/22015/1/10/PIU-BNG/27 19 July -2016 Submission of Monthly Progress Report for the month of June- 2016- reg.

26 NHAI/22015/1/10/PIU-HSN/28 19- July -2016 Parking of Vehicles near Plazas.

27 NHAI/17021/PIU-BNG/RTI/-P10/16-14/1562 21- July -2016 Request for Information Under Right to

Information Act 2005.reg

28 NHAI/22015/1/10/PIU-BNG/34 22- July -2016Requesting for Construction of Median opening and Bus stop at Madenur Gate, Shantigrama Hobli, Hassan Taluk-reg.

29 NHAI/22015/01/10/PIU-HSN/44 22- July -2016 Team Leader Inspection on 12.07.2016-reg

30 NHAI/RO-BNG/11028/MOM/11022/2016/1514 23- July -2016 Minutes of Meeting.

31 NHAI/22015/01/10/PIU-HSN/60 25- July -2016 Consolidated Claim-reg.

32 NHAI/22015/01/10/PIU-HSN/58 25- July -2016 Issuance of FASTAGS (RFID Tags) to Monthly pass holders-reg.

33 NHAI/22015/01/10/PIU-HSN/56 25- July -2016 Monthly Progress report for the Month of February 2016-Comments-reg.

34 NHAI/22015/01/10/PIU-HSN/54 25- July -2016 Lighting Defects :Recurrent-reg.

35 NHAI/22015/01/10/PIU-HSN/51 25- July -2016

Requesting for Construction of Median opening and Bus Stop at Madenur Gate, Shantigrama Hobli, Hassan

Taluk-reg36 NHAI/22015/01/10/PIU-HSN/52 25- July -2016 Deficiencies-reg.

37 NHAI/22015/01/10/PIU-HSN/49 25- July -2016

Acquisition of Portion of land bearing survey No.340/2 of shantigrama Village Hassan taluk & district for the purpose of Construction of Toll Plaza Without Providing a proper access to enter into

the land by partially blocking the entrance-request to affect not my

easementary right and to give access-reg.

38 NHAI/22015/01/10/PIU-HSN/48 25- July -2016 Identification of Encroachments and Illegal Access on National Highways –

Request for Removal and Report Compliance-reg..

39 NHAI/22015/01/15/PIU-HSN/80A 28- July -2016 Placement of Sub-professional Staff.

MSV International Inc. Page 67

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

40 NHAI/22015/01/15/PIU-HSN/75 28- July -2016 Avenue plants : Pre Notice : Caution I

INCOMMING LETTER FROM NHAI- AUGUST-2016Sl.N

o LETTER NO. DATED ON SUBJECT

1 NHAI/22015/01/10/PIU-HSN/104 2-Aug-2016 Marking of unpainted stretches especially Hassan Byepass.

2 NHAI/22015/01/10/PIU-HSN/105 2-Aug-2016 Lighting Defects: Recurrent.

3 NHAI/22015/01/15/PIU-HSN/107 2-Aug-2016 Consolidated Claim.

4 NHAI/14014/01/06/PIU-HSN/114 2-Aug-2016

Request for way leave permission to Lay OFC cable from Km 122+000 to

135+400 (Hirisave to Gowdagere) and 1No of Road crossing at km 122+000.

5 NHAI/14014/01/10/PIU-HSN/113 2-Aug-2016Estimate for Shifting of water supply pipe line (both side) at Shantigrama

Village .Hassan Taluk.

6 NHAI/(RO-BNG/11022/23/2016/1700 2-Aug-2016 Inferior of Unpainted Road Marking.

7 NHAI/25011/01/10/PIU-HSN/125 3-Aug-2016 Furnishing information under RTI Act.

8 NHAI/22015/01/10/PIU-HSN/116A 5-Aug-2016 Meeting Notice.9 NHAI/22015/01/10/PIU-HSN/120 9-Aug-2016 Corrections.

10 NHAI/22032/01/15/PIU-HSN/137 12-Aug-2016

Shiridi Ghat from 02.01.2015 to 08.08.2015-consequent Traffic

Diversions and material Adverse effect –Compensation for loss of Revenue and cost during the period from 02.01.2015

to 08.08.2015-reg11 NHAI/22032/01/15/PIU-HSN/138 12-Aug-2016 Penalty for WIMS.

12 NHAI/22032/01/10/PIU-HSN/142 12-Aug-2016Request Letter received from sub

inspector of Police, Hirisave regarding Providing Two CCTV at Toll Plazas.

13 NHAI/22032/01/10/PIU-HSN/144 12-Aug-2016 Construction of foot Over Bridge Planned for future.

14 NHAI/22032/01/15/PIU-BNG/148 16-Aug-2016

Granting Permission for laying ORC to connect Network along NH-48 (New

NH-75) from Devihalli Km 110.000 to Hassan Km 189.000 on LHS for a total length of 79kms and one Road crossing

at Km 189.000 in the State of Karnataka.

15 NHAI/22032/01/10/PIU-HSN/175 18-Aug-2016

Widening of Channarayapatna and Hassan Bypasses from 2-lane to 4-lane

construction of grade separated structures and seismic Road-COS

16 NHAI/22032/01/10/PIU-HSN/167 19-Aug-2016Guideline /Instruction for providing toilets, Hoarding and dustbins at toll plazas under swachh Bharat Mission.

MSV International Inc. Page 68

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

17 NHAI/22032/01/10/PIU-HSN/169 19-Aug-2016 Inspection of Bridges and Structures.

INCOMMING LETTER FROM NHAI–SEPTEMBER 2016

Sl No LETTER NO. DATED ON SUBJECT

1 NHAI/14024/01/07/PIU-HSN/206 10-Sep-2016

Request letter received from Police Sub-Inspector Shantigrama for

Construction of Service Road & Sky Wall.

2 NHAI/14024/01/07/PIU-HSN/207 10-Sep-2016 Regarding Exemption of Toll Fee for Vehicle used by Physically Disabled.

3 NHAI/22032/01/15/PIU-HSN/224 20-Sep-2016 Submission of RA Bill No: 13.

4 NHAI/17021/01/2005/PIU-HSN/235 23-Sep-2016

RFI Applications received from Soumya regarding Information of Toilet Facilities Along National Highways (2

Numbers)

5 NHAI/22015/01/15/PIU-HSN/250 24-Sep-2016 About CC TV Cameras at Toll Plaza.

6 NHAI/22015/01/10/PIU-HSN/242 26-Sep-2016 Accidents

7 NHAI/22015/01/10/PIU-HSN/243 26-Sep-2016

Representation from Shri.N.Cheluvanarayanaswamy, Honble

MLA Nagamangala Constituency, Mandya District.

8 NHAI/22015/01/10/PIU-HSN/245 26-Sep-2016 Road Marking/Signboards : ( Action I – Pre-notice )

9 NHAI/22015/01/10/PIU-HSN/246 26-Sep-2016

Status Report on compliance of Requirement-Provision of lease line

connectivity at Toll Plazas of NHAI and Control Centre.

10 NHAI/22015/01/15/PIU-HSN/247 26-Sep-2016 Inferior Of Unacceptable Road marking.

11 NHAI/22015/01/15/PIU-HSN/248 26-Sep-2016 Installation of WIM.

12 NHAI/22015/01/15/PIU-HSN/249 26-Sep-2016 Penalty for Name Boards & Lane.

13 NHAI/22015/01/15/PIU-HSN/251 26-Sep-2016 Back Pulling at Hemagangothri College on NH-75 Km 173+000

14 NHAI/22015/01/15/PIU-HSN/252 26-Sep-2016 Very Slow Progress of Works at Toll Plaza-01

15 NHAI/22015/01/15/PIU-HSN/253 26-Sep-2016 Avenue Plants Pre Notice Caution-I

16 NHAI/22015/01/15/PIU-HSN/254 26-Sep-2016 About CC TV Cameras at Toll Plaza.

MSV International Inc. Page 69

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

INCOMMING LETTER FROM L&T- JULY-2016

Sl.No LETTER NO. DATED ON SUBJECT

1 DHTL/CRP/IE/2016/1567 1-July-16 Incident Management of National Highway as on 30-06-2016.

2 DHTL/CRP/PD/2016/788 1-July-16 Stagnation of Water @ Km 155+400-reg.

3 DHTL/CRP/PD/2016/787 1-July-16 Marking of Unpainted Stretches especially Hassan Byepass-reg.

4 DHTL/CRP/PD/2016/791 4-July-16 Monthly Progress Report For the Month Of February -2016 Comments.

5 DHTL/CRP/IE/2016/1568 4-July-16 Submission of Schedule N & M for the month of June 2016.

6 DHTL/CRP/IE/2016/1569 4-July-16

Compliance Report for Observations during site visit for the period from 27.06.2016 to 03.07.2016 in COD

length-reg.

7 DHTL/CRP/IE/2016/1570 4-July-16

Observations during site visit for the period from 04.07.2016 to 10.07.2016

in CODS length-reg.

8 DHTL/CRP/PD/2016/1571 4-July-16 Avenue Plantation: Pre Notice Caution I.

9 DHTL/CRP/PD/2016/1572 5-July-16Submission of Maintenance bills for

Highway Lighting.

10 DHTL/CRP/PD/2016/1573 5-July-16 Settlement-reg.

11 DHTL/CRP/PD/2016/1574 6-July-16 Lighting Defects Recurrent –reg.

12 DHTL/CRP/PD/2016/1577 6-July-16

Identification of Encroachments and Illegal Access on National Highways –

Request for Removal and Report Compliance

13 DHTL/CRP/IE/2016/1575 6-July-16Requesting for Construction of

Connecting Bridge.

14 DHTL/CRP/IE/2016/1576 7-July-16 Laboratory: Insufficiency-reg.

15 DH/CRP/PD/2016/793 7-July-16 Lighting Defects Recurrent –reg.

16 DH/CRP/PD/2016/794 7-July-16 Pending Work and Proposal resolutions-reg.

MSV International Inc. Page 70

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

17 L&T DHTL/O&M/2016-17/07. 6-July-16Request for supply of power 24hrs basis High Mast lights @ various Junctions.

18 DH/PD/CRP/2016/792 6-July-16

Requesting for Permission for drawing overhead 11 Kv line along right side of

ROW on NH-75( Bangalore –Mangalore section ) from Km 171.000

to Km 173.000-reg.

19 DH/CRP/PD/2016/795 7-July-16Monthly Progress Report ending June -

2016 -reg.

20 DHTL/CRP/IE/2016/1578 8-July-16 NHAI Land Encroachment for Medical Store Ch.166.400 LHS.

21 DH/CRP/PD/2016/796 7-July-16Development of wayside Amenities

along the National Highway-reg.

22 DH/CRP/PD/2016/797 6-July-16 Requesting for information under Right to information Act,2005-reg.

23 DHTL/PD/CRP/2016/798 7-July-16 Parking of Vehicle near Plazas-reg.

24 DHTL/CRP/IE/2016/1579 8-July-16

Submission of Maintenance bills for Highway Lighting at COS locations-

reg.

25 DHTL/CRP/IE/2016/1580 12-July-16

Compliance Report for Observations during site visit for the period from 04.07.2016 to 10.07.2016 in COD

length-reg.

26 DHTL/CRP/IE/2016/1581 12-July-16

Observations during site visit for the period from 11.07.2016 to 17.07.2016

in COD length27 DHTL/CRP/IE/2016/1582 13-July-16 Repair of Cut Road Maintenance-reg.

28 DHTL/CRP/IE/2016/1583 13-July-16 Progress of the Work @ Site-reg.

29 DHTL/CRP/IE/2016/1584 14-July-16

Implementation of interoperable ETC system on Pan India Basis at Toll Plazas

–Issuance of Change of Scope order requested for Kerb Construction-reg.

30 DHTL/CRP/IE/2016/1586 16-July-16 Laboratory: Insufficiency.

31 DH/CRP/PD/2016/801 13-July-16 Settlement.

32 DH/CRP/PD/2016/799 13-July-16 Avenue Plants : Pre Notice Caution I.

33 DH/CRP/PD/2016/802 13-July-16 Toll Expert.

34 DHTL/PD/CRP/2016/803 14-July-16 Issuances of FasTags (RFID Tags) to Monthly pass Workers.

35 DH/CRP/PD/2016/804 16-July-16 Building Demolition at Km 122.300 RHS.

36 DHTL/CRP/IE/2016/1588 19-July-16

Compliance Report for Observations during site visit for the period from 11.07.2016 to 17.07.2016 in COD

length-19-July-16 Observations during site visit for the

MSV International Inc. Page 71

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

37 DHTL/CRP/IE/2016/1589 period from 18.07.2016 to 24.07.2016 in COD length

38 DHTL/PD/CRP/2016/807 20-July-16 Highway Lighting -reg.39 DHTL/PD/CRP/2016/806 19-July-16 Avenue Plantation:Pre Notice caution I.

40 DHTL/CRP/IE/2016/1587 20-July-16

Implementation of interoperable ETC system on Pan India Basis at Toll Plazas

–Issuance of Change of Scope order-Payment request.

41 DHTL/PD/CRP/2016/805 19-July-16

Karnataka legislative assembly petitions committee meeting on 23.06.2016-

regarding furnishing information for application No.120/2015

42 DHTL/CRP/IE/2016/1590 25-July-16 Toll Expert-reg.

43 DH/CRP/PD/2016/809 25-July-16 Hirisave Land loses representation.

44 DH/CRP/PD/2016/810 25-July-16

Cost estimation for construction of service roads, highway lighting and sky

wall at Shantigrama and Hirisave – change of scope notice.

45 DH/CRP/IE/2016/1592 25-July-16

Observations during site visit for the period from 25.07.2016 to 31.07.2016

in COD length

46 DH/CRP/PD/2016/1591 25-July-16

Compliance Report for Observations during site visit for the period from 18.07.2016 to 24.07.2016 in COD

length-

47 DH/CRP/PD/2016/811 27-July-16

Requesting for Construction of Median opening and Bus Stop at Madenur Gate, Shantigrama Hobli, Hassan

Taluk-reg

48 DH/CRP/PD/2016/813 27-July-16 Now Penalty for WIMS.

49 DH/CRP/IE/2016/1593 27-July-16 Punch List –B Works-reg..

50 DH/CRP/IE/2016/1594 28-July-16

Closure of Shiridi Ghat from 02.01.2015 to 08.08.2015-consequent

Traffic Diversions and material Adverse effect –Compensation for loss of

Revenue and cost during the period from 02.01.2015 to 08.08.2015-reg.

INCOMMING LETTER FROM L&T- AUGUST-2016

Sl.No LETTER NO. DATED ON SUBJECT

1 DHTL/CRP/CESCOM/2016/16 1-Aug-2016 Request for Estimate for Shifting of Electrical Line-reg.

MSV International Inc. Page 72

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

2 DHTL/CRP/IE/2016/1595 2-Aug-2016 Submission of RA Bill No.13 for Cos-II works.

3 DHTL/CRP/IE/2016/1596 2-Aug-2016 Incident Management of National highways as on 31.07.2016-reg.

4 DHTL/CRP/IE/2016/1599 3-Aug-2016 Submission of Schedule N & M for the Month of July 2016-reg.

5 DHTL/CRP/IE/2016/1598 2-Aug-2016 Team Leader’s Inspection of July 12.2016

6 DHTL/PD/CRP/2016/814 3-Aug-2016 Annual Plants : Pre Notice Caution I.

7 DHTL/CRP/IE/2016/1597 2-Aug-2016 Deficiencies. 8 DHTL/CRP/IE/2016/1600 3-Aug-2016 Submission of Maintenance bills for

Highway Lighting.

9 DHTL/PD/CRP/2016/815 3-Aug-2016Identification of Encroachments and illegal access on National Highways Request for Removal and report Compliance.

10 DHTL/PD/CRP/2016/819 5-Aug-2016Submission of Cost Estimate for widening of Channarayapatna Bypass from 2 to 4 Lane construction grade separated structures and service Road.

11 DHTL/CRP/IE/2016/1601 5-Aug-2016 Toll experts Comments/ state of Toll Plaza Apparatus.

12 DHTL/CRP/IE/2016/1604 5-Aug-2016Cost estimate for Construction of service Road, Highway lighting and Sky walk at Shantigrama and hirisave –COS notice.

13 DHTL/CRP/IE/2016/1602 5-Aug-2016

Acquisition of Portion of land bearing survey no: 340/02 of Shantigrama

without proper access to enter into the Land.

14 DHTL/CRP/IE/2016/1603 5-Aug-2016 Hirisave Land Loser Representation.

15 DHTL/CRP/PD/2016/821 6-Aug-2016 MPR Ending July 2016.

16 DHTL/CRP/IE/2016/1605 8-Aug-2016 Deficiencies of Service: Notice.

17 DHTL/CRP/IE/2016/1606 8-Aug-2016 Monsoon Planning.

18 DHTL/CRP/PD/2016/822 8-Aug-2016

Hassan Construction of new By line Exemption for road vehicles used by

Central Govt Officials

19 DHTL/CRP/PD/2016/823 9-Aug-2016 Quarterly Progress Report for the Month of April ,May & June-2016

MSV International Inc. Page 73

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

20 DHTL/CRP/IE/2016/1607 9-Aug-2016 Deficiencies.

21 DHTL/CRP/IE/2016/1608 9-Aug-2016 Corrections.

22 DHTL/CRP/IE/2016/1609 9-Aug-2016Marking of Unpainted Stretches

Especially Hassan Bypass.

23 DHTL/CRP/IE/2016/1610 10-Aug-2016

Closure of Shiridi Ghat from 02.01.2015 to 08.08.2015- Consequent

Traffic Diversions and Adverse Financial Impact compensation for loss

of revenue during the period from 02.01.2015 to 08.08.2015.

24 DHTL/CRP/IE/2016/1611 12-Aug-2016 Punch List- B Works.25 DHTL/CRP/IE/2016/1615 16-Aug-2016 Water Blocks.26 DHTL/CRP/PD/2016/824 16-Aug-2016 Corrections.

27 DHTL/CRP/PD/2016/825 16-Aug-2016Notice for lack of Display

Boards/Marking and Signages at TP1 &TP2.

28 DHTL/CRP/PD/2016/826 16-Aug-2016 Lighting Defects: Recurrent.

29 DHTL/CRP/PD/2016/827 16-Aug-2016 Monthly Progress Report of June-2016.

30 DHTL/CRP/PD/2016/828 16-Aug-2016 Furnishing information under RTI Act-2005.

31 DHTL/CRP/IE/2016/1612 16-Aug-2016 Expansion Joints.

32 DHTL/CRP/IE/2016/1613 16-Aug-2016 Dumping of Earth.

33 DHTL/CRP/IE/2016/1614 16-Aug-2016 Plaza Accessory :TP234 DHTL/CRP/PD/2016/829 18-Aug-2016 Additional Safety requirements.

35 DHTL/CRP/PD/2016/831 19-Aug-2016

Request letter received from Sub Inspector of police, Hirisave requesting Providing two CCTV Cameras at Toll

Plaza.

36 DHTL/CRP/IE/2016/1617 19-Aug-2016

Reimbursement of Lighting maintenance Charges in the Project

Highway.

37 DHTL/CRP/PD/2016/830 19-Aug-2016

Permission for laying underground OFC cable along Row of NH-75 (Devihalli-

Hassan) Section from Devihalli Km 110.000 to Hassan Km 189.000 on LHS for a total length of 79kms and one road crossing at Km 189.000 in the state of

Karnataka –Request for permission from m/s Reliance Jio.

38 DHTL/CRP/IE/2016/1618 22-Aug-2016 Road Marking.

39 DHTL/CRP/IE/2016/1619 22-Aug-2016 Submission of RA Bill No: 13 for COS-II Works.

40 DHTL/CRP/PD/2016/832 24-Aug-2016 Construction of foot Over Bridge Planned for future.

41 DHTL/CRP/PD/2016/833 24-Aug-2016 Now Penalty for Name Boards and Lane.

MSV International Inc. Page 74

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

42 DHTL/CRP/IE/2016/1622 23-Aug-2016 Deficiency.43 DHTL/CRP/IE/2016/1621 23-Aug-2016 Deficiency.44 DHTL/CRP/IE/2016/1620 23-Aug-2016 Deficiency.45 DHTL/CRP/IE/2016/1623 30-Aug-2016 Installation of WIM.

46 DHTL/CRP/PD/2016/834 30-Aug-2016 Construction of foot Over Bridge Planned for future.

47 DHTL/CRP/IE/2016/1624 30-Aug-2016

Closure of Shiridi Ghat from 02.01.2015 to 08.08.2015- Consequent

Traffic Diversions and Adverse Financial Impact compensation for loss

of revenue during the period from 02.01.2015 to 08.08.2015.

INCOMMING LETTER FROM L&T–SEPTEMBER 2016

Sl No LETTER NO. DATED ON SUBJECT

1 DHTL/CRP/IE/2016/1625 1-Sep-2016

Incident Management of National

Highways as on 31.08.2016.

2 DHTL/CRP/IE/2016/1626 3-Sep-2016 Submission of Schedule – N&M For the Month of August-2016.

3 DH/CRP/PD/2016/835 7-Sep-2016 Monthly Progress Report ending Aug-2016.

4 DHTL/CRP/IE/2016/1627 7-Sep-2016 Distress Of Riding Surface.

5 DHTL/CRP/IE/2016/1628 7-Sep-2016 FOB-GAD For Approval.

6 DHTL/CRP/IE/2016/1629 7-Sep-2016 Submission Of Maintenance Bills For Highway Lighting.

7 DHTL/CRP/IE/2016/1630 7-Sep-2016 Delineation of the ROW.

8 DH/CRP/PD/2016/836 8-Sep-2016 Request For Information Under Right to Information Act-2005.

9 DH/CRP/PD/2016/837 9-Sep-2016 Disruption Of Work.

10 DH/CRP/PD/2016/838 9-Sep-2016

Widening Of Channarayapatna and Hassan Bypasses From 2-Lane To 4-

Lane construction Of Grade Separated Structures and Service Road Change Of

Scope.

11 DHTL/CRP/IE/2016/1631 9-Sep-2016 Change Of Name – Certificate From ROC.

MSV International Inc. Page 75

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

12 DH/CRP/PD/2016/840 10-Sep-2016

Change In Law – Increase In Cost Due To Change In Rate Of Excise Duty and

VAT Notified- Notice Of Additional Expenses Incurred – Request For

Payment.

13 DHTL/CRP/IE/2016/1632 12-Sep-2016 Inspection Of Bridges and Structures.

14 DHTL/CRP/IE/2016/1633 12-Sep-2016 Deficiencies Not Attended.

15 DHTL/CRP/ IE/2016/1634 12-Sep-2016 Drainage Lapse.

16 PGCH/435/2016-2017 12-Sep-2016

Request to provide PUP at NH-75 chainage 173, Hemagangothri PG

Centre, Hassan.

17 DH/CRP/PD/2016/841 13-Sep-2016

Notice force Majeure Event (Indirect Political Event) Under Clause 34.3 w.e.f

09.09.2016.18 DHTL/CRP/IE/2016/1635 13-Sep-2016 Hectometer Stones.

19 DH/CRP/PD/2016/842 14-Sep-2016

Request for Way Leave permission to Lay OFC cable from Km 120+000 to

Km 135+400 (Hirisave to Gowdagere) & 1 no of road crossing at Km 122+000.

20 DHTL/CRP/IE/2016/1636 14-Sep-2016 Deficiencies to be Made Good: Km 185+450 to km 150+000.

21 DHTL/CRP/IE/2016/1637 15-Sep-2016

Permission of Laying underground OFC cable along ROW of NH-75 (Devihalli-

Hassan) section from Devihalli Km 110.000 to Hassan Km 189+000 as LHS for a total length of 79 km and one road crossing at Km 189+000 in the State of Karnataka Request for Permission from

M/S Reliance Jio.

22 DH/CRP/PD/2016/843 16-Sep-2016Representation from Aelelihalli

Villagers..

23 DHTL/CRP/IE/2016/1638 17-Sep-2016 Team Leader Joint Inspection 31.08.2016 .

24 DH/CRP/PD/2016/844 17-Sep-2016 Representation from Daneliganahalli Villagers.

25 DH/CRP/PD/2016/845 17-Sep-2016 Monthly Progress for the Month of February-2016 Comments.

26 DHTL/CRP/IE/2016/1639 19-Sep-2016 Requesting for Construction of Connecting Bridge

27 DH/CRP/PD/2016/846 21-Sep-2016 Stoppage of Works Due to Cauvery Issue-reg

28 DHTL/CRP/IE/2016/1640 22-Sep-2016

Minister of RT&H orders issued under Swatch Bharath Mission NHAI Notice

for Construction of Toilet Under Change of Scope Estimates-approval Change of

Scope order-reg.29 DHTL/CRP/IE/2016/1641 26-Sep-2016 FOB-GAD for Approval.

30 DH/CRP/PD/2016/852 28-Sep-2016Disruption of toll Plaza Work due to the Prevailing Cauvery dispute Request for

MSV International Inc. Page 76

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Police assistance-Reg31 DH/CRP/PD/2016/848 28-Sep-2016 Issuing of Measurement Books.

32 DH/CRP/PD/2016/849 28-Sep-2016

Representation from G.V.Doreswamy Sy.no.299/2-655 & 656 at Shantigrama,

Hassan (Talluk)-Reg.

33 DH/CRP/PD/2016/850 28-Sep-2016 Representation from Panchayath Karyalaya Shantigrama.

34 DH/CRP/PD/2016/851 28-Sep-2016

Representation from Madenuru, Sannachakanahalli, Gadenahalli,

Hampanahalli, Hoovinahalli and all Villagers in the Surroundings.

35 DHTL/CRP/IE/2016/1642 28-Sep-2016 Deficiencies.36 DH/CRP/CGM/2016/847 29-Sep-2016 Installation of WIM-Reg.

OUT GOING LETTER FROM MSV INTERNATIONAL, INC

OUT GOING LETTER TO NHAI –JULY 2016

Sl.No

LETTER NO DATED ON SUBJECT

1 1002/MSV/D-H/IE/TL/Adm/(Toll)/58

2-July-16 Toll Expert.

2 1002/MSV/D-H/IE/TL/Adm/(Correspondence)/18

2-July-16 Email Public Grievance.

3 1002/MSV/D-H/IE/TL/Adm/(Correspondence)/42

2-July-16 PMIS Certificate.

4 1002/MSV/D-H/IE/TL/Adm/(Toll)/62

2-July-16 Issuance of Fastags (RFID Tags) to Monthly pass holders.

5 1002/MSV/D-H/IE/TL/Adm/(Toll)/63

5-July-16Recovery of Damages Pursuant to Sub-clause 14.4.1 of CA for Not Completing

Balance Works of Toll Plaza At Shantigrama (Km 165.170).

6 1003/MSV/D-H/IE/TL/Tech/(Toll)/64

7-July-16 Reports: N& M.

7 1003/MSV/D-H/IE/TL/Adm/(Incident & Accident )/13

7-July-16 Incident and Accident Management of National Highway As on 30.06.2016.

8 1002/MSV/D-H/IE/TL/Tech/(Inspection)/88

7-July-16 Lighting Defects Recurrent.

9 1002/MSV/D-H/IE/TL/Tech/(Inspection)/90

7-July-16 Marking of Unpainted Stretches especially Hassan Byepass.

10 1002/MSV/D-H/IE/TL/Tech/(Miscellaneous)/44

7-July-16 Road Maintenance for Pilgrims.

11 1002/MSV/D-H/IE/TL/Tech/(Miscellaneous)/45

8-July-16Providing Police Protection for Demolition of Acquired Building at Hirisave.

12 1002/MSV/D-H/IE/TL/Tech/ 11-July-16 Requesting for Construction of Service

MSV International Inc. Page 77

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

(Estimate)/32 Road, Rumble Strips And solar lights at Mattanavile Village.

13 1002/MSV/D-H/IE/TL/Tech/(Misc)/49

11-July-16Letter Issued Regarding after survey of National Highway-48 Land is handed over and after Re-Verification, there is no records exist of possession of Land.

14 1002/MSV/D-H/IE/TL/Tech/(Planting)/15

16-July-16 Avenue Plants : Pre Notice caution I.

15 1002/MSV/D-H/IE/TL/Tech/(Inspection)/93

16-July-16 Settlement.

16 1002/MSV/D-H/IE/TL/Tech/(QPR)/03

16-July-16 Quarterly Progress Report O&M : II ( April- June) 2016.

17 1002/MSV/D-H/IE/TL/Tech/(Work)/47

18-July-16Identification of Encroachments and illegal Access on National Highway –Request for Removal and Report Compliance.

18 1004/MSV/D-H/IE/TL/Tech/(Inspection)/94

19-July-16 Lighting.

19 1002/MSV/D-H/IE/TL/Adm/(Staff)/38

19-July-16 Interview of AHE-I Replacement.

20 1002/MSV/D-H/IE/TL/Adm/(Toll)/67

20-July-16

Complete Closure of Shiridi Ghat from 2nd January 2015-Consequent Traffic diversions and Adverse Financial impact compensation for Period from 2.1.2015 to 31.08.2015 Claim from 1st month to 8th

month21 1002/MSV/D-H/IE/TL/Adm/(Toll)/

7021-July-16 Implementation of interoperable ETC

system on Pan India Basis at Toll Plazas –Issuance of Change of Scope order for Kerb Construction at both Toll Plaza.

22 1002/MSV/D-H/IE/TL/Tech/(Inspection)/95

22-July-16 Parking of Vehicle near Plazas-reg.

23 1002/MSV/D-H/IE/TL/Adm/(Toll)/69

22-July-16 Now Penalty for WIMS.

24 1002/MSV/D-H/IE/TL/Tech/(Planting)/16

22-July-16 Avenue Plants : Pre Notice caution I.

25 1004/MSV/D-H/IE/TL/Tech/(MPR)/25

22-July-16 Monthly Progress Report of May-2016

26 1002/MSV/D-H/IE/TL/Adm/(Toll)/71

25-July-16 Now Penalty for Name Boards and Lane.

27 1002/MSV/DH/IE/TL/Tech/(Miscellaneous)/54

27-July-16 Identification of Encroachments.

28 1002/MSV/D-H/IE/TL/Tech/(MPR)/26

29-July-16 General Progress.

29 1002/MSV/D-H/IE/TL/Tech/(Estimate)/36

29-July-16

Submission of Cost estimate for widening of Channarayapatna and Hassan Bypass from 2 to4 lanes, construction of Grade Separation Structures and service Road.

30 1003/MSV/D-H/IE/TL/Adm/(Incident & Accident )/14

30-July-16 Accidents.

MSV International Inc. Page 78

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

OUT GOING LETTER TO NHAI –AUGUST 2016

Sl.No LETTER NO DATED ON SUBJECT1 1002/MSV/D-H/IE/TL/Tech/

(Planting)/171-Aug-2016 Status of Avenue & Median Plantation.

2 1002/MSV/D-H/IE/TL/Adm/(Toll)/75

1-Aug-2016 Penalty for WIMS.

3 1002/MSV/D-H/IE/TL/Tech/(Planting)/18

1-Aug-2016 Avenue Plantation : Caution I

4 1002/MSV/D-H/IE/TL/Tech/(Misc)/57

1-Aug-2016 Requesting for Construction of Median Opening and Bus Stop At Madenur Gate,

Shantigrama hobli, Hassan Taluk.5 1002/MSV/D-H/IE/TL/Tech/

(Misc)/582-Aug-2016 PIMS certificate.

6 1002/MSV/D-H/IE/TL/Tech/(Estimate)/37

4-Aug-2016 Requesting for Handling Over of Measurement Books and Abstract Books

for COS-I & II 7 1003/MSV/D-H/IE/TL/Adm/

(Incident & Accident )/155-Aug-2016 Incident and Accident Management of

National Highway As on 31.07.2016.

8 1002/MSV/D-H/IE/TL/Adm/(Toll)/77

5-Aug-2016 N & M Report for the month of July-2016

9 1002/MSV/D-H/IE/TL/Tech/(Inspection)/100

6-Aug-2016 Lighting

10 1002/MSV/D-H/IE/TL/Tech/(Plaza)/34

6-Aug-2016 Status & functionary of ETC Lanes & Toll Equipment.

11 1002/MSV/D-H/IE/TL/Tech/(Plaza)/35

6-Aug-2016 Median Opening.

12 1002/MSV/D-H/IE/TL/Tech/(Estimate)/40

6-Aug-2016Submission of Cost Estimate for Widening of Channarayapatna and Hassan Bypass from 2 to 4 lanes Construction of grade separated statement and service Road.

13 1002/MSV/D-H/IE/TL/Tech/(Misc)/59

6-Aug-2016 Encroachments: Latest.

14 1002/MSV/D-H/IE/TL/Tech/(Estimate)/41

8-Aug-2016 Issues of New Measurement Book and Measurement Abstract Books for COS IX and II

15 1002/MSV/D-H/IE/TL/Adm/(Meeting)/08

8-Aug-2016 Agenda : Meeting 10.08.2016

16 1002/MSV/D-H/IE/TL/Tech/(Estimate)/42

9-Aug-2016 Consolidated Claim.

17 1002/MSV/D-H/IE/TL/Tech/(MPR)/28

11-Aug-2016 Monthly Progress Report No :09 July 2016

18 1002/MSV/D-H/IE/TL/Tech/(Misc)/60

12-Aug-2016 Overseas Trip: Africa & Kenya

Closure of Shiridi Ghat from 02.01.2015 to 08.08.2015-consequent Traffic

MSV International Inc. Page 79

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

191002/MSV/D-H/IE/TL/Tech/

(Estimate)/4413-Aug-2016 Diversions and material Adverse effect –

Compensation for loss of Revenue and cost during the period from 02.01.2015 to 08.08.2015-reg

20 1002/MSV/D-H/IE/TL/Tech/(Misc)/61

16-Aug-2016 Furnishing Information Check RTI-Act

21 Msv/PRJ/167/NHAI/IE/DEV-HASSAN/2015/22172-

10-Aug-2016 Reimbursement of Service Road.

22 1002/MSV/D-H/IE/TL/Tech/(Estimate)/45

19-Aug-2016 Requesting for Handling Over of Measurement Abstract Book for Cos-II

23 1001/MSV/D-H/IE/TL/Concessionaire/Running Account

Bill/10

31-Aug-2016 Change of Scope –IX , Running Account Bill-I

24 1002/MSV/D-H/IE/TL/Adm/(Toll)/82

30-Aug-2016Clarification of our Letter

No.1002/MSV/D-H/IE/TL/Adm/(Toll)/70 dt: 21.7.2016 (copy attached)

25 1001/MSV/D-H/IE/TL/Concessionaire/ Bill/09

30-Aug-2016 Certification of work done against running Account Bill No:13

26 1002/MSV/D-H/IE/TL/Tech/(Misc)/62

30-Aug-2016

Request for Permission for drawing Overhead 11kv line along right side of Row on NH-75(Bangalore- Mangalore)from Km 171.000 to 173.000 -reg

OUT GOING LETTER TO NHAI –SEPTEMBER 2016

Sl No LETTER NO DATED ON SUBJECT

1 1002/MSV/D-H/IE/TL/Tech/( Estimate)/46

2-Sep-2016

Clauses of Shiradi Ghat from 02.01.2015 to 08.08.2015 Consequent Traffic Diversions and Adverse Financial Impact Compensation for Loss of Revenue During The Period from 02.01.2015 to 08.08.2015 .

2 1002/MSV/D-H/IE/TL/Adm/(Misc)/63

2-Sep-2016 PMIS Certificate.

3 1002/MSV/D-H/IE/TL/Tech/(Toll)/85

3-Sep-2016 Installation of WIMS and levy of Additional Penalty for VIOLATION IN ETC Lanes.

4 Msv/PRJ/167/NHAI/IE/DEV-HASSAN/2015/F-11-22324

3-Sep-2016 Submission of Invoice No: Msv/PRJ/167/NHAI/IE/DEV-

HASSAN/2015/F-115 1004/MSV/D-H/IE/TL/(MPR)/30 6-Sep-2016 Monthly Progress Report No: 10 August-

2016..6 1002/MSV/D-H/IE/TL/(TOLL)/30 7-Sep-2016 Reports: N & M for the Month of

August.

MSV International Inc. Page 80

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

7 1003/MSV/D-H/IE/TL/(Incident & Accident )/16

7-Sep-2016 Incident and Accident Management of National Highway As on 31.08.2016.

8 1002/MSV/D-H/IE/TL/Adm/(Toll)/85 A

3-Sep-2016 Installation of WIMS and levy of Additional Penalty for VIOLATION IN

ETC Lanes.9 1002/MSV/D-H/IE/TL/Adm/

(Staff)/4213-Sep-2016 Sub Professional Approval of CV.

10 1002/MSV/D-H/IE/TL/Tech/(Estimate)/47

13-Sep-2016Widening of Channarayapatna & Hassan Bypass from 2-lane to 4-lane, Construction of Grade Separated Structure & Service Road Change of Scope.

11 Msv/PRJ/167/NHAI/IE/DEV-HASSAN/2015/22369

14-Sep-2016 Submission of Insurance Policy from 18.08.2016 to 17.08.2016.

12 MSV/D-H/IE/TL/Tech/(Inspection)/106

14-Sep-2016Request to Provide PUP at NH-75 Chainage 173+000 Hemagangothri P G Center, Hassan.

13 1002/MSV/D-H/IE/TL/Adm/(Misc)/66

16-Sep-2016 Identification of Land at Every 50 Km Along National Highway for Development of Way-side Amenities.

14 1002/MSV/D-H/IE/TL/Adm/(Toll)/87

17-Sep-2016 Discrepancies in Toll Collections at Devihalli Shantigrama Hassan

15 1002/MSV/D-H/IE/TL/Tech/(Misc)/67

17-Sep-2016 Regarding Exemption of Toll Fee for Vehicle used by Physically Disabled

16 1002/MSV/D-H/IE/TL/Tech/(Estimate)/49

19-Sep-2016 Requesting for handing over of Measurement Book (27, 28)

17 1002/MSV/D-H/IE/TL/Tech/(Correspondence)/19

19-Sep-2016 Corresponding with NHAI Direct

18 1002/MSV/D-H/IE/TL/Tech/(Correspondence)/20

19-Sep-2016 Corresponding with NHAI Direct

19 1002/MSV/D-H/IE/TL/Adm/(Misc)/69 19-Sep-2016

Permission of laying underground OFC cable along ROW of NH-75 (Devihalli-Hassan) section from Devihalli km 110.000 to Hassan km 189+000 as LHS for a total length of 79 km and one road crossing at km 189+000 in the state of Karnataka Request for Permission from M/S Reliance Jio.

20 1002/MSV/D-H/IE/TL/Tech/(Estimate)/50

20-Sep-2016 Submission of Measurement Book: COS IX and II

21 1002/MSV/D-H/IE/TL/Adm/(Misc)/71

20-Sep-2016 Representation from Adhihalli Villages.

22 1002/MSV/D-H/IE/TL/Adm/(Staff)/44

22-Sep-2016 New Staff Replacement

MSV International Inc. Page 81

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

23 1002/MSV/D-H/IE/TL/Tech/(Estimate)/51

22-Sep-2016 Swatch Bharath

24 1002/MSV/D-H/IE/TL/Tech/(Toll)/89

23-Sep-2016 Revised Kerb Estimate For ETC Lane

25 1002/MSV/D-H/IE/TL/Tech/(Estimate)/52

23-Sep-2016 Relaying of Design of Swatch Bharath Toilets as Prepared By Concessionaire

26 1002/MSV/D-H/IE/TL/Tech/(Concessionaire Bill )/09

26-Sep-2016 COS II, Running Account Bill-13

27 1002/MSV/D-H/IE/TL/Tech/(Concessionaire Bill )/10

26-Sep-2016 COS IX, Running Account Bill-1

28 1002/MSV/D-H/IE/TL/Adm/(Misc)/75

27-Sep-2016 Danger Zones

29 1002/MSV/D-H/IE/TL/Adm/(Misc)/77

27-Sep-2016 Advertising on the Site

30 1002/MSV/D-H/IE/TL/Adm/(Staff)/45

27-Sep-2016 New Staff-Replacement

OUT GOING LETTER TO L&T –JULY 2016

Sl.No LETTER NO. DATED ON SUBJECT

1 1002/MSV/D-H/IE/TL/Tech/(Inspection)/86

1-July-16Notice: Requirement of Non-Interrupted supply of Light for 24 Hours in the Highway corridor-Regarding Non-Compliance.

2 1002/MSV/D-H/IE/TL/Tech/(Inspection)/87

1-July-16 Settlement.

3 1002/MSV/D-H/IE/TL/Tech/(Planting)/13 1-July-16

Avenue Plantation: Pre Notice : Caution I

4 1002/MSV/D-H/IE/TL/Adm/(Toll)/57

2-July-16 Notice: Non operationalisation of ETC Lane and static weigh Bridge.

5 1002/MSV/D-H/IE/TL/Adm/(Toll)/59

2-July-16Notice: Non operationalisation of ETC Lane and static weigh Bridge.

6 1002/MSV/D-H/IE/TL/Adm/(Toll)/60

2-July-16 Notice: Non operationalisation of ETC Lane and static weigh Bridge.

7 1002/MSV/D-H/IE/TL/Adm/(Toll)/61

4-July-16 Issuance of FASTags (RFID Tags) on Monthly pass holders.

8 1002/MSV/D-H/IE/TL/Tech/(Miscellaneous)/43

4-July-16 NHAI Land Encroachments for Medical store, Ch: 166.400 LHS.

9 1004/MSV/D-H/IE/TL/Tech/(Deficiency)/88

5-July-16 Distress of Riding surface of the project: 60 Days Time for Remedial Action.

10 1004/MSV/D-H/IE/TL/Tech/(Deficiency)/89

7-July-16 Deficiency and Tests.

MSV International Inc. Page 82

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

11 1002/MSV/D-H/IE/TL/Tech/(Plaza)/31

7-July-16 Plaza-2

12 1002/MSV/D-H/IE/TL/Tech/(Planting)/14

7-July-16 Avenue Plantation : PreNoticeCautionI.

13 1002/MSV/D-H/IE/TL/Tech/(Concessionaire /Bill)07

8-July-16 Submission of Maintenance Bills for Highway.

14 1002/MSV/D-H/IE/TL/Tech/(Miscellaneous)/46

9-July-16 Laboratory: Insufficiency.

15 1004/MSV/D-H/IE/TL/Tech/(Inspection)/91

9-July-16 Lighting Defects : Recurrent.

16 1002/MSV/D-H/IE/TL/Tech/(Deficiency)/91

8-July-16 Cut Road survey: 26 Roads and of 30.

17 1002/MSV/D-H/IE/TL/Tech/( Misc)/48

11-July-16 Requesting for Construction of Connecting Bridge.

18 1004/MSV/D-H/IE/TL/Tech/( MPR)/23

12-July-16 Observation on Concessionaire’s June 2016, MPR

19 1002/MSV/D-H/IE/TL/Adm/(Toll)/65

13-July-16 Notice for Lack of Display Boards /Markings and Signages at TP 1 & TP2

20 1004/MSV/D-H/IE/TL/Tech/(Inspection)/92

14-July-16 Team Leader’s Inspection of July 12, 2016.

21 1004/MSV/D-H/IE/TL/Tech/(MPR)/24

16-July-16 Deficiencies: MPR.

22 1002/MSV/D-H/IE/TL/Adm/(Toll)/66

16-July-16 Toll Expert Notes.

23 1004/MSV/D-H/IE/TL/Tech/(QPR)/05

16-July-16 QPR O&M:-II(April – June 2016)

24 1002/MSV/D-H/IE/TL/Tech/(Deficiency)/92

18-July-16 Deficiencies.

25 1002/MSV/D-H/IE/TL/Tech/(Miscellaneous)/52

18-July-16 Karnataka Legislative Assembly Petitions Committee meeting on 23.06.2016-reg.

26 1002/MSV/D-H/IE/TL/Tech/(Estimate)/33

21-July-16 Estimate For Service Road and Consequent Lighting As Requested By Local Influential’s of Hirisave .

27 1002/MSV/D-H/IE/TL/Adm/(Toll)/68

21-July-16 WIMs for ETC Lanes.

28 1002//MSV/D-H/IE/TL/Tech/(Estimate)/34

21-July-16 Cost Estimate For Construction Of Service Road, Highway Lightings and Skywalks At Shantigrama and Hirisave-Change of Scope Notice.

29 1002/MSV/DH/IE/TL/Tech/(Deficiency)/94

27-July-16 Deficiencies.

30 1002//MSV/D-H/IE/TL/Tech/(Estimate)/35

27-July-16 Hirisave Land loses Representation.

31 1002/MSV/D-H/IE/TL/Adm/(Toll)/72

27-July-16 Toll Expert Comments/State of Toll plaza Apparatus.Acquisition of Portion of land bearing

MSV International Inc. Page 83

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

32 1002/MSV/DH/IE/TL/Tech/(Miscellaneous)/55

27-July-16

survey No.340/2 of shantigrama Village Hassan taluk & district for the purpose of Construction of Toll Plaza Without Providing a proper access to enter into the land by partially blocking the entrance-request to affect not my easementary right and to give access-reg.

33 1002/MSV/D-H/IE/TL/Adm/(Toll)/73

28-July-16 Implementation of interoperable ETC system on Pan India Basis at Toll Plazas –Issuance of Change of Scope order.

34 1004/MSV/D-H/IE/TL/Tech/(Inspection)/96

28-July-16 Static weigh Bridges.

35 1002/MSV/D-H/IE/TL/Tech/(Plaza)/32

28-July-16 Plaza Accessory: TP2

36 1002/MSV/D-H/IE/TL/Tech/(Plaza)/33

28-July-16 Reverse flow.

37 1002/MSV/DH/IE/TL/Tech/(Deficiency)/95

29-July-16 Corrections.

38 1004/MSV/DH/IE/TL/Tech/(MPR)/27

30-July-16 MPR for the Month of February -2016-Comments.

39 1002/MSV/DH/IE/TL/Tech/(Deficiency)/96

30-July-16 Expansion Joints.

40 1002/MSV/DH/IE/TL/Tech/(Deficiency)/97

30-July-16 Dumping of Earth.

OUT GOING LETTER TO L&T –AUGUST 2016

Sl.No LETTER NO. DATED ON SUBJECT

1 1002/MSV/D-H/IE/TL/Adm/(Toll)/74

1-Aug-16 WIMS for ETC Lanes.

2 1002/MSV/D-H/IE/TL/Adm/(Toll)/76

1-Aug-16

Closure of Shiridi Ghat from 02.01.2015 to 08.08.2015-consequent Traffic Diversions and material Adverse effect –Compensation for loss of Revenue and cost during the period from 02.01.2015 to 08.08.2015-reg

3 1002/MSV/D-H/IE/TL/Tech/(Deficiency)/99

1-Aug-16 Drainage Lapse.

4 1002/MSV/D-H/IE/TL/Tech/(Deficiency)/98

1-Aug-16 Deficiency of Service: Notice.

5 1004/MSV/D-H/IE/TL/Tech/(Inspection)/97

2-Aug-16 Safety Lapses.

MSV International Inc. Page 84

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

6 1002/MSV/D-H/IE/TL/Tech/(Work)/59

2-Aug-16 Punch List-B Works.

7 1004/MSV/D-H/IE/TL/Tech/(Inspection)/99

30-07-16 Road Markings/Signboards: Caution I: Pre-Notice.

8 1004/MSV/D-H/IE/TL/Tech/(Inspection)/98

4-Aug-16 Water Blocks.

9 1002/MSV/D-H/IE/TL/Tech/(Planting)/19

4-Aug-16 Avenue Plantation.

10 1004/MSV/D-H/IE/TL/Tech/(Deficiency)/100

5-Aug-16 Monsoon Planning.

11 1004/MSV/D-H/IE/TL/Tech/(Deficiency)/101

6-Aug-16 Distress of Riding Surface: latter Stretch of the Project 60 days time for remedial Action.

12 1004/MSV/D-H/IE/TL/Tech/(Inspection)/101

6-Aug-16 Marking of Unpainted Stretches Especially Hassan Byepass.

13 1002/MSV/D-H/IE/TL/Tech/(Estimate)/38

6-Aug-16 Cost estimate for Construction of Service Road, Highway lighting And Skywalk of Shantigrama And Hirisave-COS-Notice

14 1002/MSV/D-H/IE/TL/Tech/(Estimate)/39

6-Aug-16 Hirisave Land loser representation.

15 1002/MSV/D-H/IE/TL/Concessionaire/Bill/08

9-Aug-16 Submission of Maintenance bills for highway lighting.

16 1004/MSV/D-H/IE/TL/Tech/(Inspection)/102

9-Aug-16 Annual Plan for 2016-17 –Swachh Bharath Mission –VC Providing of Toilets AH Toll Plazas .

17 1004/MSV/D-H/IE/TL/Tech/( MPR)/29

9-Aug-16 Monthly Progress Report No: 09 July 2016

18 1004/MSV/D-H/IE/TL/Tech/(Deficiency)/103

13-Aug-16 Deficiency.

19 1004/MSV/D-H/IE/TL/Tech/(Inspection)/103

13-Aug-16Proposal of estimate and drawings at Toll plaza Both sides under Swachh bharath Annual Program 2016-17 at kadabahalli and Shantigrama.

20 1002/MSV/D-H/IE/TL/Adm/(Toll)/78 18-Aug-16

ETC at Toll plazas –Testing and integration of ICIC GST tags and IHMCL GST with Central Cleaning house(CCH)

21 1002/MSV/D-H/IE/TL/Adm/(Toll)/79 22-Aug-16 WIMS for ETC Lanes.

22 1002/MSV/D-H/IE/TL/Adm/(Toll)/80 30-Aug-16 Speed Breakers at Plazas.

23 1002/MSV/D-H/IE/TL/Adm/(Toll)/81 30-Aug-16 Now Penalty for Name Board and Lane

24 1002/MSV/DH/IE/TL/Tech/(Deficiency)/104 30-Aug-16 Deficiencies not Attended.

25 1004/MSV/D-H/IE/TL/Tech/(Inspection)/104

30-Aug-16Hectometer Stones.

MSV International Inc. Page 85

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

OUT GOING LETTER TO L&T –SEPTEMBER 2016

Sl No LETTER NO. DATED ON SUBJECT1 1002/MSV/D-H/IE/TL/Adm/(Toll)/

831-Sep-2016 Now Penalty for Name Boards & Lane.

21002/MSV/D-H/IE/TL/Tech/(Deficiency)/105

1-Sep-2016 Deficiency to be Made Good: Km 185+450 to Km 150+000

3 1002/MSV/D-H/IE/TL/Adm/(Toll)/84

2-Sep-2016 Toll Experts Comments/State of Toll Plaza Apparatus.

4 1004/MSV/D-H/IE/TL/Tech/(Inspection)/105

2-Sep-2016 Team Leader’s Joint Inspection.

5 1004/MSV/D-H/IE/TL/(MPR)/31 6-Sep-2016 Monthly Progress Report No: 10 August-2016.

6 1002/MSV/D-H/IE/TL/Tech/(Deficiency)/106

13-Sep-2016 Distress of Riding Surface.

7 1002/MSV/D-H/IE/TL/Adm/(Misc)/65

13-Sep-2016 FOB-GAD for Approval.

8 1002/MSV/D-H/IE/TL/Tech/(Deficiency)/107

16-Sep-2016 Deficiencies

9 1004/MSV/D-H/IE/TL/Tech/(Work)/60

17-Sep-2016 Swatch Bharath Toilet

10 1002/MSV/D-H/IE/TL/Tech/(Estimate)/48

17-Sep-2016 Request letter Received from Police Sub-Inspector, Shantigrama for Construction of Service Road & Sky Walls.

11 1002/MSV/D-H/IE/TL/Tech/(Correspondence)/20

19-Sep-2016 Corresponding with NHAI Direct

12 1002/MSV/D-H/IE/TL/Adm/(Misc)/70

19-Sep-2016 Construction of Lined Drain and Cover Slabs

13 1002/MSV/D-H/IE/TL/Tech/(Deficiency)/108

20-Sep-2016 Reconstruction of Hump.

14 1002/MSV/D-H/IE/TL/Tech/(Deficiency)/109

23-Sep-2016 O & M Deficiency’s

15 1002/MSV/D-H/IE/TL/Adm/(Misc)/73

23-Sep-2016 Laboratory Insufficiency’s

16 1004/MSV/D-H/IE/TL/Tech/(Work)/61

24-Sep-2016 Stoppage of Work

17 1004/MSV/D-H/IE/TL/Tech/(Inspection)/107

26-Sep-2016 Lighting

18 1002/MSV/D-H/IE/TL/Adm/(Misc)/74

26-Sep-2016 Danger Zones

MSV International Inc. Page 86

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

19 1002/MSV/D-H/IE/TL/Adm/(Misc)/76

27-Sep-2016 Danger Zones

20 1004/MSV/D-H/IE/TL/(Tech)/(Deficiency)/110

28-Sep-2016 Rain Water Harvesting Pits

21 1004/MSV/D-H/IE/TL/(Tech)/(Deficiency)/111

28-Sep-2016 Deficiency in Service/ Surface Cracks/ Quality Let Up

22 1004/MSV/D-H/IE/TL/(Tech)/(Inspection)/108

28-Sep-2016 Safety: Inadequacy of Signages

23 1004/MSV/D-H/IE/TL/(Tech)/(MPR)/32

28-Sep-2016 Monthly Progress Report August 2016 Comments

24 1004/MSV/D-H/IE/TL/(Tech)/(Work)/62

28-Sep-2016 Disruption of Toll Plaza Work due to the prevailing Cauvery dispute – Request for Police Assistance

25 1004/MSV/D-H/IE/TL/(Tech)/(Work)/63

29-Sep-2016 Progress of Work

26 1002/MSV/D-H/IE/TL/Adm/Tech/(Inspection)/109

29-Sep-2016 Lighting

MSV International Inc. Page 87

Chapter-12Photographs

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

DEFECTS OBSERVED IN THE MONTH OF JULY 2016

Stagnation of Line Drain Water @ Km :171+400 RHS Pot Hole @ Km: 183+250 RHS

Median Kerb Damaged @ Km 173+600 LHS

MSV International Inc. Page 88

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Line Drain Cover Slab Damaged @ Km 162+800 RHS

Minor Bridge.

Expansion Joint @ Km:179+100 Expansion Joint @ Km:179+100

Cracks on MCW

161+000 To 176+000(BHS)

142+100 To 159+320 (BHS)

MSV International Inc. Page 89

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

160+400 To161+000 (BHS) 140+600 To 140+700(BHS)

Note: Alligator Cracks on the increase. Cracks noticed from Km 174+600 to 174+800, Km 175+000 to 175+800, Km 184+300 to 184+500, Km 184+800 to 184+950, and Km 185+200 to 185+300.

DEFECTS OBSERVED IN THE MONTH OF AUGUST 2016

Hazard Marker Sticker Faded Hazard Marker Sticker Faded

MSV International Inc. Page 90

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Pothole on Main carriageway Pothole on Main carriageway

BT Waste Thrown on ROW @ Km 160+600 RHS Weeding Required @ Km 170+000 to 171+000

DEFECTS OBSERVED IN THE MONTH OF SEPTEMBER 2016

KM Stone Disturbed at Ch 111+000(RHS) Delineator Bent at Ch 169+100(RHS)

MSV International Inc. Page 91

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

KM Stone is Provided Behind the MBCB 157+000 (BHS)

MBCB Damaged at Ch 178+100(RHS)

Cracks At Km 163+600 BHS Cracks At Km 164+850 BHS

Work Progress Photos

At Km 123+000 (RHS) Land Dispute Building Demolition Work @ Hirisave.

MSV International Inc. Page 92

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Line Drain Work is Under Progress @ ShantigramaTP-2 Building work progress

TP-2 Building Work Progress Service Road Work @ Shantigrama

MSV International Inc. Page 93

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

L&T DEVIHALLI-HASSAN TOLLWAY LIMITED

STATEMENT OF TOLL COLLECTION-JULY 2016PLAZA-1 PLAZA-2 Grand

Total

DATE SHIFT-1 SHIFT-II SHIFT-IIIPOS Revenue TOTAL SHIFT-1 SHIFT-II SHIFT-III

POS Revenue TOTAL

01-Jul 168030 191550 173493 150510 683583 137741 174675 138925 20760 472101 1155684

02-Jul 199645 242285 194825 217735 854490 156315 196678 167192 79275 599460 1453950

03-Jul 182585 242880 245425 0 670890 155257 213442 177775 3405 549879 1220769

04-Jul 144680 152460 158330 0 455470 116992 137378 135325 3685 393380 848850

05-Jul 147025 167705 161475 1090 477295 127156 161336 132845 3165 424502 901797

06-Jul 154520 183105 167860 0 505485 127695 175290 135649 1100 439734 945219

07-Jul 145530 168085 167330 345 481290 126594 153425 140416 235 420670 901960

08-Jul 166720 202605 198695 105 568125 134455 192870 165265 492590 1060715

09-Jul 220740 277170 239655 0 737565 188955 242797 190948 155 622855 1360420

10-Jul 181095 259565 324255 0 764915 157810 229823 241601 210 629444 1394359

MSV International Inc. Page 94

Chapter-12Toll Collection

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

11-Jul 184305 154360 178420 0 517085 145810 149774 155969 295 451848 968933

12-Jul 162855 190455 165090 0 518400 141955 168442 138855 580 449832 968232

13-Jul 157825 179430 170385 0 507640 138035 174619 142229 105 454988 962628

14-Jul 172630 190030 177590 295 540545 143830 169580 141120 580 455110 995655

15-Jul 176435 193785 190920 0 561140 139694 171941 150690 285 462610 1023750

16-Jul 207800 254635 216835 0 679270 171020 218895 171505 561420 1240690

17-Jul 201375 236520 275570 0 713465 163415 212499 216296 592210 1305675

18-Jul 163030 161820 180075 50 504975 126135 150437 151380 335 428287 933262

19-Jul 179280 175760 174500 0 529540 141800 171222 139710 680 453412 982952

20-Jul 178130 176920 166020 0 521070 140345 158895 133545 1440 434225 955295

21-Jul 165350 182455 174985 0 522790 139400 161216 145477 446093 968883

22-Jul 171820 190160 201350 0 563330 138842 175327 153675 467844 1031174

23-Jul 218020 246110 224425 86200 774755 172215 217670 180340 44400 614625 1389380

24-Jul 197675 223909 272085 0 693669 156858 202435 214734 574027 1267696

25-Jul 148080 159000 165440 0 472520 116845 146232 144408 1860 409345 881865

26-Jul 149865 180935 167955 0 498755 124537 161174 137157 3700 426568 925323

27-Jul 144280 163875 166080 0 474235 120484 157278 134110 411872 886107

28-Jul 155515 183845 169365 0 508725 134040 164192 140525 438757 947482

29-Jul 161695 204195 194670 50 560610 136685 178902 152661 335 468583 1029193

30-Jul 214695 136240 180815 0 531750 170470 123056 145379 1045 439950 971700

31-Jul 165325 250330 278617 0 694272 141440 220662 208658 818030 1388790 2083062

TOTAL 5386555 6122179 6122535 456380 18087649 4432825 5532162 4924364 985660 15875011 33962660

L&T DEVIHALLI-HASSAN TOLLWAY LIMITEDTraffic Data for the Month of July -2016

Type of Vehicle

s as per

notification

CAR, JEEP, VAN OR LIGHT

MOTOR VEHICLE

LIGHT COMMERCIA

L VEHICLE, LIGHT

GOODS VEHICLE OR MINI BUS

TRUCK / BUS (TWO

AXLES)/MAV

THREE AXLE COMMERCIAL

VEHICLES

HEAVY CONSTRUCTION

MACHINERY (HCM) OR

EARTH MOVING EQUIPMENT

(EME) OR MULTI AXLE

VEHICLE (MAV) (FOUR TO SIX

AXLES)

OVERSIZED

VEHICLES (SEVEN

OR MORE AXLES)

Total

Nos. Nos. Nos. Nos. - - Nos.Toll 177834 24530 36664 20919 6 0 259953

MSV International Inc. Page 95

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Plaza 1Toll

Plaza 2 172044 23442 37514 20788 4 0 253792TOTAL 349878 47972 74178 41707 10 0 513745

L&T DEVIHALLI-HASSAN TOLLWAY LIMITEDSTATEMENT OF TOLL COLLECTION-AUGUST 16

PLAZA-1 PLAZA-2 Grand Total

DATE SHIFT-1 SHIFT-II SHIFT-IIIPOS

Revenue TOTAL SHIFT-1 SHIFT-II SHIFT-IIIPOS

Revenue TOTAL

1-Aug 165170 162260 162845 861050 135132512682

015353

613803

8 137895 556289 1907614

2-Aug 170530 165385 161280 227010 72420514298

515457

813204

5 7280 436888 1161093

3-Aug 152345 179715 163410 340 49581012521

516369

813475

0 2175 425838 921648

4-Aug 159900 195305 170295 0 52550013470

317186

013798

4 2410 446957 972457

5-Aug 155020 193020 203010 105 55115513607

217018

016593

3 2075 474260 1025415

6-Aug 195115 239180 216675 0 65097016749

020278

516507

0 1440 536785 1187755

7-Aug 169975 254365 256795 0 68113515188

020446

919100

1 235 547585 1228720

8-Aug 151635 160140 168805 0 48058012075

514704

314190

6 1050 410754 891334

9-Aug 168665 188620 174160 400 53184514492

517063

813564

9 285 451497 983342

MSV International Inc. Page 96

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

10-Aug 147380 167375 185365 295 50041511292

014485

016155

8 1335 420663 921078

11-Aug 173055 194580 195820 500 56395515546

216796

515326

0 570 477257 1041212

12-Aug 201915 226350 211305 0 63957016542

519859

117157

0 0 535586 1175156

13-Aug 266175 397175 306690 0 97004021592

533799

422934

8 530 783797 1753837

14-Aug 254545 344330 309340 0 90821522607

528867

823736

0 0 752113 1660328

15-Aug 179270 316780 460445 0 95649516638

025878

232930

0 1095 755557 1712052

16-Aug 213900 174615 192980 295 58179016737

516258

415801

0 530 488499 1070289

17-Aug 182860 196245 188940 0 56804515550

017996

414985

6 0 485320 1053365

18-Aug 177095 183845 178750 0 53969015071

416473

515147

0 0 466919 1006609

19-Aug 175290 195640 188830 0 55976014701

817688

215458

1 235 478716 1038476

20-Aug 211450 252280 238045 105 70188016989

021919

118179

2 0 570873 1272753

21-Aug 194500 278165 287215 0 75988016005

023282

822461

8 1860 619356 1379236

22-Aug 171295 181725 206580 0 55960012913

015744

517254

7 3700 462822 1022422

23-Aug 176530 188565 185005 86200 63630015010

417016

112643

5 44400 491100 1127400

24-Aug 158915 189685 181700 0 53030013863

517411

214825

5 0 461002 991302

25-Aug 168655 198880 176610 0 54414513884

517321

513880

0 155 451015 995160

26-Aug 179585 182640 203140 0 56536514566

417186

216017

8 235 477939 1043304

27-Aug 205145 256055 231970 0 69317016324

521029

218445

5 390 558382 1251552

28-Aug 202940 302440 279600 0 78498016843

024192

421483

5 0 625189 1410169

29-Aug 169480 187620 199610 0 55671013351

316573

916510

8 3060 467420 1024130

30-Aug 180700 197165 181390 0 55925515282

018076

314924

5 108440 591268 1150523

31-Aug 170480 197805 197045 734310 129964014149

218352

515988

4 644315 1129216 2428856

TOTAL 5649515 6747950 6663650 1910610 20971725 4705457 5900869 5264841 965695 16836862 37808587

L&T DEVIHALLI-HASSAN TOLLWAY LIMITEDTraffic Data for the Month of August -2016

MSV International Inc. Page 97

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

Type of Vehicles as

per notificatio

n

CAR, JEEP,

VAN OR LIGHT

MOTOR VEHICLE

LIGHT COMMERCIAL

VEHICLE, LIGHT GOODS VEHICLE OR

MINI BUS

TRUCK / BUS (TWO

AXLES)/MAV

THREE AXLE COMMERCIAL

VEHICLES

HEAVY CONSTRUCTION

MACHINERY (HCM) OR

EARTH MOVING EQUIPMENT

(EME) OR MULTI AXLE

VEHICLE (MAV) (FOUR TO SIX

AXLES)

OVERSIZED VEHICLES

(SEVEN OR MORE AXLES)

Total

Nos. Nos. Nos. Nos. - - Nos.

Toll Plaza 1 190030 26072 40294 22373 3 027877

2

Toll Plaza 2 176101 24536 40294 20788 4 026172

3

TOTAL 366131 50608 80588 43161 7 054049

5

L&T DEVIHALLI-HASSAN TOLLWAY LIMITED

MSV International Inc. Page 98

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

STATEMENT OF TOLL COLLECTION-SEPT 16PLAZA-1 PLAZA-2 Grand Total

DATE SHIFT-1 SHIFT-II SHIFT-IIIPOS Revenue TOTAL SHIFT-1 SHIFT-II SHIFT-III

POS Revenue TOTAL

01-Sep 181730 184839 200245 229335 796149 156965 166924 161527 119660 605076 1401225

02-Sep 222930 159850 207655 119315 709750 170187 135346 158904 80500 544937 1254687

03-Sep 207335 303865 301830 450 813480 165090 256829 215830 6490 644239 1457719

04-Sep 211110 237495 210285 295 659185 171345 202687 154200 1515 529747 1188932

05-Sep 121635 182385 308695 0 612715 99588 161037 192423 4275 457323 1070038

06-Sep 178365 210750 209885 285 599285 140865 171322 140228 1530 453945 1053230

07-Sep 207725 228760 219350 530 656365 155125 188580 162711 235 506651 1163016

08-Sep 217615 227225 246855 0 691695 156500 189262 177084 940 523786 1215481

09-Sep 213395 43860 176385 0 433640 167675 46817 130000 815 345307 778947

10-Sep 231650 318480 254940 0 805070 178570 255889 198850 0 633309 1438379

11-Sep 214220 313480 292015 0 819715 179535 228770 239431 400 648136 1467851

12-Sep 181380 181700 201875 0 564955 137815 161958 146980 1815 448568 1013523

13-Sep 122550 115185 143115 0 380850 95703 105585 103280 235 304803 685653

14-Sep 131320 155295 176790 0 463405 102620 143670 138757 0 385047 848452

15-Sep 175260 179745 164035 105 519145 146548 165298 108594 520 420960 940105

16-Sep 174385 177330 195390 0 547105 153547 159793 147540 0 460880 1007985

17-Sep 197015 209075 198720 105 604915 165375 245913 167693 235 579216 1184131

18-Sep 180385 225965 238425 0 644775 155115 202695 182359 235 540404 1185179

19-Sep 171485 160055 184740 4985 521265 124330 145497 149182 4640 423649 944914

20-Sep 156650 164475 148875 0 470000 128780 139298 114323 155 382556 852556

21-Sep 163560 167520 180475 0 511555 129371 149857 139104 0 418332 929887

22-Sep 166875 173700 187990 0 528565 131130 156995 146180 3700 438005 966570

23-Sep 183140 188205 196830 0 568175 140275 164887 147861 0 453023 1021198

24-Sep 202720 228205 201575 0 632500 160260 199804 162101 0 522165 1154665

25-Sep 187270 233725 250450 0 671445 150575 186317 187975 0 524867 1196312

26-Sep 157325 162470 184165 0 503960 123540 145187 141905 235 410867 914827

27-Sep 178730 183135 185775 0 547640 147150 154827 138885 44635 485497 1033137

28-Sep 171450 177435 190510 86200 625595 143563 153813 142740 207290 647406 1273001

29-Sep 179060 203480 235455 0 617995 145287 166558 176102 166970 654917 1272912

30-Sep 201535 228080 195980 885366 1510961 160127 181852 152850 593865 1088694 2599655

TOTAL548980

5592576

9628931

0132697

1 19031855 4382556 5133267 4725599 1240890 15482312 34514167

MSV International Inc. Page 99

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

L&T DEVIHALLI-HASSAN TOLLWAY LIMITEDTraffic Data for the Month of September -2016

Type of Vehicles

as per notifica

tion

CAR, JEEP, VAN OR LIGHT

MOTOR VEHICLE

LIGHT COMMERCIA

L VEHICLE, LIGHT

GOODS VEHICLE OR MINI BUS

TRUCK / BUS (TWO AXLES)/M

AV

THREE AXLE COMMERCIAL VEHICLES

HEAVY CONSTRUCTION

MACHINERY (HCM) OR

EARTH MOVING EQUIPMENT

(EME) OR MULTI AXLE

VEHICLE (MAV) (FOUR TO SIX

AXLES)

OVERSIZED VEHICLES

(SEVEN OR MORE AXLES)

Total

Nos. Nos. Nos. Nos. - - Nos.Toll

Plaza 1 173974 22634 38914 20903 7 0 256432

Toll Plaza 2 154395 20543 38420 20628 4 0 233990

TOTAL 328369 43177 77334 41531 11 0 490422

Abstract for Toll Collection Data:

Sl.No Month (2016) Plaza-1(Toll Collection) Plaza-I1(Toll Collection)

1 July 18,075,785.00

15,849,211.00

2 August 20,952,270.00

16,816,410.00

3 September 19,013,481.00 15,452,860.00

Conclusion

MSV International Inc. Page 100

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

The 3 months ending on Sept 30, 2016, have not given any encouraging sign. Progress is almost nil at Plazas and PCOD works especially 1 and 2 are nil. PCOD 3 has also grated to a haft. Work is yet to resume despite the Cauvery holdup having long since abated. We will watch this October and November and recommend any further action other than termination, and in consonance to the contract.

***********

MSV International Inc. Page 101

Quarterly Progress Report (Construction & O&M) No. 03 July to September 2016 Independent Engineer during O&M for 4 laning of Devihalli-Hassan Section of NH 48/75

ANNEXURE-A

MSV International Inc. Page 102