nt2-l3-m-000-21-00005 rev. c

48
/ PECC2 DOCUMENT STATUS : For Reference A 10 Aug 09 ISSUE FOR REFERENCE SA-ARD O. KRIT K. SUMETH Y. Rev. Date Description Prepd. Chkd. Appd. Project : Owner : Consultant: EPC Contractor: Consultant: Subcontractor : Document Title : Method Statement for Installation of Main Cooling Water Piping Project No : NT 2 Format : A4 Total Pages : Designed by : Torishima Consortium Checked by : Function Name Sign Date Function Name Sign Date Approved Sumeth Y. SM Checked Krit K. ME Prepared Sa-ard O. QA/QC Document No : NT2-L3-M-000-21-00005 Date: 10 Mar 10 Rev. C NHON TRACH 2 - 750MW COMBINED CYCLE POWER PLANT PROJECT PETRO VIETNAM NHON TRACH 2 POWER JOINT STOCK COMPANY LILAMA PVC CONSORTIUM FICHTNER GmbH & Co.KG CONNELL WAGNER (AURECON) TORISHIMA - AFCOLENCO - LILAMA 18 JSC.

Upload: huynhthanhtamptsc

Post on 13-May-2017

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NT2-L3-M-000-21-00005 Rev. C

/ PECC2

DOCUMENT STATUS : For Reference

A 10 Aug 09 ISSUE FOR REFERENCE SA-ARD O. KRIT K. SUMETH Y.

Rev. Date Description Prepd. Chkd. Appd.

Project :

Owner : Consultant:

EPC Contractor:

Consultant:

Subcontractor :

Document Title : Method Statement for Installation of Main Cooling Water Piping

Project No : NT 2 Format :A4

Total Pages :

Designed by : Torishima Consortium Checked by :

Function Name Sign Date Function Name Sign Date

Approved Sumeth Y. SM

Checked Krit K. ME

Prepared Sa-ard O. QA/QC

Document No : NT2-L3-M-000-21-00005Date:

10 Mar 10Rev. C

NHON TRACH 2 - 750MW COMBINED CYCLE POWER PLANT PROJECT

PETRO VIETNAMNHON TRACH 2 POWERJOINT STOCK COMPANY

LILAMA – PVC CONSORTIUM

FICHTNER GmbH & Co.KG CONNELL WAGNER (AURECON)

TORISHIMA - AFCOLENCO - LILAMA 18 JSC.

Administrator
Typewritten Text
Administrator
Typewritten Text
Administrator
Typewritten Text
B 28 Jan 10 REVISED AS PER COMMENTS SA-ARD O. KRIT K. SUMETH Y.
Administrator
Typewritten Text
Administrator
Typewritten Text
C
Administrator
Typewritten Text
Administrator
Typewritten Text
Administrator
Typewritten Text
10 Mar 10
Administrator
Typewritten Text
Administrator
Typewritten Text
FINAL ISSUE FOR REFERENCE
Administrator
Typewritten Text
SA-ARD O.
Administrator
Typewritten Text
Administrator
Typewritten Text
KRIT K.
Administrator
Typewritten Text
SUMETH Y.
Administrator
Typewritten Text
Page 2: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 2

Torishima-AF Colenco-Lilma 18 JSC

Nhon Trach 2-750MW CCPP/ Lot 3 Balance of Plant

Page 3: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 3

CONTENTS

No. Description Page

1.0 Purpose ……………………………………………………… ….. 4 2.0 Scope …………………………………………………………….. 4

3.0 Definitions………………………………………………………... 4

4.0 Procedure...…………………………………………………….... 5 4.1 General Instruction………………………………………………...5 4.2 Pipe Installation…….……………………………………………...6 4.3 Test and Inspection………………………………………………...9 5.0 Cleaning of Main Cooling Water Piping …………………….....9

6.0 Reference Codes and Standard ………………………………....10

7.0 Reference Drawings ………………………………………….....10

8.0 Exhibits…………………………………………………………....11

8.1 Exhibit A...………………………………………………………...12

8.2 Exhibits B……………………………………………………….....13

8.3 Exhibits C……………………………………………………….....15

8.4 Exhibits D……………………………………………………….....17 8.5 Exhibits E ………………………………………………………...20

8.6 Exhibits F ………………………………………………………...26

8.7 Exhibits G ………………………………………………………...45

Page 4: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 4

1.0 Purpose

This procedure covers the detail of work to be carried out for installation of main cooling water pipe supply line and discharge line which it is in a part of Balance of Plant System for Nhon Trach 2 – 750 MW Combined Cycle Power Plant Project.

The purpose of this procedure is to identify the sequence of activities required to successfully install the equipment ensuring these tasks are properly coordinated and executed to the satisfaction to the contract specification requirement.

2.0 Scope This procedure covers the installation method for the construction of the large diameter

pipelines which consists as follows.

- Main cooling water pipe supply line from main cooling water pumping station to terminal point TP4a & TB4b between Lot 3 and Lot 1.

- Main cooling water pipe discharge line from terminal point TP5a & TP5b between Lot 3 and Lot 1 to discharge seal weir pit.

3.0 Definitions

“Unit” a term used in some sections of this statement and refers to pumps equipment.

“Reliability of unit operation” means the pump assembly itself. This terminology should not be constructed as the plant unit.

“Allowance” means the tolerance prescribed by the pump manufacturer and as per the tolerances defines in reference doc. no. NT2-L3-G-000-63-00001 Tolerance List for Mechanical Work.

“Bevel” the angle formed between the prepared edge of a pipe end and a plane perpendicular to the longitudinal axis of the pipe. Bevels are generally used for butt welding of pipe end.

“Butt Joint” a pipe joint in which the two pipe ends are in the same plane and do not overlap. This joint configuration is commonly beveled.

“Pipe bedding” the earthen material immediately under the pipeline and by which the pipeline is supported.

“Pipe Zone” the area of excavation within which the pipeline will be placed.

Page 5: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 5

4.0 Procedure 4.1 General Instruction

4.1.1 Equipment Handling and Protection From inland transportation, particular attention shall be paid to the following points:-

a) Checking the equipment and accessories

Inspect the goods and confirm all components and parts listed in the shipping manifest are all available. Report immediately any missing or damage parts/components during transportation.

b) Care should be exercised when unloading and handling the pipe. Main cooling water pipes are generally manufactured in length of 6.0 m which use of a two lifting for proper and safe handling.

Coated pipe shall be handled, stored and delivered in a manner that will prevent damage to the coating. If the coating is damaged, it shall be repaired with original coating per the applicable specification.

All pipes, fittings and accessories should be carefully loaded and unloaded by lifting equipment in order to avoid impact or damage.

c) Protection and care in storage yard.

If the goods are received some days or weeks prior to installation, store the unit in a dry place and keep the internal and external parts free from dirt and grit.

If the equipment is stored outside, exposed parts shall be coated with grease oil or spray type rust preventive coat and it should be covered with a weather proof sheet to protect from moisture. Usually, these are kept in packed condition if not stored for long period. Unpacking will only be done prior to installation.

In principle no turning and checking of lube oil condition will be necessary if the equipment has been in stored for a short period. Torishima’s supervisor, however, will use his judgments to determine if the unit will be stored for quite some time, then turning and lube oil inspection shall be scheduled.

4.1.2 Risk Assessment and Safe Work Method

Prior the installation work, supervisor and foreman in-charge shall perform the risk assessment to ensure the job is executed safely but not limited to the following:

Page 6: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 6

a) Check lifting equipment position is stable.

b) Check lifting devices and tools such as wire ropes, shackles, pulleys, chain blocks, etc. are free from any defect.

c) The vicinity of the installation where the lifting of parts to be carried out shall

be cordoned off to prevent workers from passing under the overhead work.

d) Supervisor or foreman shall be present at site during the work.

e) Softeners and woodblock are available to protect sling cables in contact with steel structure edges when used for rigging anchor.

f) Scaffolding when use as work platform is confirmed “Tagged for Use” by

authorized person. Safety harness/safety belts used by personnel working on high-elevated platform.

g) Extra care shall be taken to prevent bodily parts from being caught between

live load and structure.

h) Suitable fire extinguishers are available in the area where burning and welding works are performed. Suitable methods and facilities are available to contain burning and welding sparks/spatters.

i) Adequate lighting fixtures are installed in area of installation where illumination is inadequate.

j) Protective devices appropriate for the type of work for this installation are

available for personnel use.

4.2 Pipe Installation

4.2.1 Piping Route Surveying and Marking for Excavation

An area to be excavated of pipe trench shall be surveyed in respect of pipe routing based on the reference points marked on site.

4.2.2 Trenching

Excavation has to be carried out by an excavator and/ or equivalent equipment at specified width and depth. a) Depth

Trench shall be excavated to grade as shown in the drawing. Trench bottom shall provide uniform support for the full length of the pipes. The bedding shall be prepared to avoid damage to the pipe.

Page 7: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 7

b) Width

The sides of the trench will afford reasonable side support. The minimum trench width at the bottom of pipe should be plus 1.0 meter at each side.

c) Bottom Preparation

Flat-bottom trenches should be excavated to a depth of a minimum of 100 mm. below the established grade line of the outside bottom of pipe.

The excess excavation should then be filled with loose material from which all stones and hard limps have been removed.

The loose sub-grade material such as sand or suitable material should be filled and graded uniformly to the established grade line for the full length of pipe. A minimum requirement of trench bedding compaction at the level of standard proctor 90% is required. Welding pit 1.0m width x 1.0m depth approximately at every field welding joints shall be provided at adequate space for convenient in welding.

4.2.3 Pipe Laying a) Care shall be observed during installation of the pipe in the trench.

b) Pipe shall be laid to the lines and grades shown on the drawings.

c) While handling and placing pipe in the trench, fabric sling shall be used. The

pipe should not be dragged along the bottom of the trench. Rolling of coated pipe should be avoided which shall only be permitted for joint ends.

d) Touch-up of any visible damaged to the coating shall be repaired before

setting the pipes.

e) Pipe shall not be set on rigid blocks on the trench bottom that would cause concentration of the load on small areas of pipe. The elevation of pipe shall be adjusted by using sand bag.

4.2.4 Assembly of Pipe

a) Before lining-up, the weld ends shall be cleaned 20mm approximately to remove all foreign particles.

b) Alignment and fit up, temporary internal line up clamps of appropriate material shall be used.

c) Alignment shall be made which centerline of the pipe sections shall be maintained in a proper alignment.

Page 8: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 8

d) After checking includes edge preparation, offset and gap, tack welding shall

be performed by the qualified welder.

e) All welding works shall be completed in accordance with the applicable welding procedure specification (WPS). For pipe larger than 24 in. in diameter, two welders shall carry out on the opposite side of the pipe.

f) After welding has been finished, inspection of every welding joint shall be

performed as described in this method statement clause 4.3.

4.2.5 Field Coating of Joints

a) After inspection of field weld joint have been finished, the exterior and interior joint shall be completed with coatings that are compatible with the original coating system and in accordance with the applicable specification.

b) Acceptable procedure for coating of field welding joints is described in Doc. No. NT2-L3-M-000-21-00013 Method Statement for Site Painting Work.

4.2.6 Pipe Bedding and Backfilling

a) All backfill material in the pipe zone shall be free from vegetable, organic material, rocks or stones, and other unsuitable materials.

b) Care must be taken not to damage coatings during compaction. Equipment with suitably shaped tamping feet for compaction the material will generally ensure that the specified materials density is obtained under the lower quadrant of the pipe.

c) At the time of placement, the backfill material should contain the optimum moisture content required for compaction.

d) The moisture content should be uniform throughout each layer.

e) Backfill should be placed in layer of not more than 150 mm. in thickness after

compaction.

f) Unless otherwise specified, the dry density of compacted of bedding and backfill should not be less than 90% standard proctor.

g) Prior to bedding and backfilling, anode of cathodic protection system shall be

installation completed.

h) Care shall be taken to assure that the pipe is not floated of displaced before backfilling is complete.

Page 9: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 9

4.3 Test and Inspection

4.3.1 Nondestructive Examinations of Field Welded Joints

a) All field welded joints of main cooling piping shall be performed and passed the nondestructive examinations.

b) Nondestructive examinations shall be performed in accordance with ASME

Section V.

c) The requirement for examination of welds of main cooling water piping is as follow:-

c.1) Butt joint welds

- Visual inspection (VI) 100% - Ultrasonic test (UT) 100%

c.2) Fillet joint welds

- Magnetic particle test (MT) 100% c.3) T-joint welds

- Radiographic test (RT) 100%

4.3.2 Pressure Test

a) According to AWWA C206-03 field welding of steel water pipe, in lieu of the pressure test the non-destructive examination can be approved as alternative tests of field welded joints.

b) In additional, based on per described in Clause 137.7.1 of ASME B31.1 Power Piping, the pressure test for main cooling water piping are not practical. Thus, during commissioning of main cooling water system, service test for examination the leakage of all connections of main cooling water piping system shall be performed in accordance with Clause 137.7.2 of ASME B31.1 Power Piping.

4.3.3 Inspection of Field Coating of Joints

a) Inspection procedure of field coating of joints including acceptance criteria is

described in Doc. No. NT2-L3-M-000-21-00013 Method Statement for Site Painting Work.

b) Paint dry film thickness shall be measured by magnetic film thickness meter.

5. 0 Cleaning of Main Cooling Water Piping

In order to achieve/ensure the required internal cleanliness of the main cooling water piping and to avoid difficulties during commissioning and operation, main cooling water piping must be cleaned before commissioning.

Page 10: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 10

All pipe spools shall be delivered to site for installation in clean condition.

The major cleaning efforts are done by broom cleaning and only minimum wet cleaning is required to achieve the target cleanliness.

After termination of install and before commissioning, the internal main cooling water piping shall be broom cleaned and inspected for major contamination, lost tools, plastic or metal parts, etc. if cleanliness is not met by broom cleaning, wet cleaning shall be applied.

The evaluation of cleanliness with results from broom cleaning and wet cleaning shall be performed by the responsible parties.

6. 0 Reference Codes and Standards

AWS D1.1 Structural Welding Code-Steel

AWWA C200 Steel Water Pipe – 6 In. (150mm) and larger

AWWA C206 Field Welding of Steel Water Pipe

AWWA M11 Steel Pipe – A Guide for Design and Installation

ASME Sec. V Nondestructive Examination

ASME Sec. IX Steel Water Pipe – 6 In. (150mm) and larger

ASME B31.1 Power Piping

7. 0 Reference Drawings.

NT2-L3-M-PA-52-00001 Cooling Water System – P&I Diagram

NT2-L3-M-PAB-59-00001-001 to 003 Cooling Water Pipeline – Layout Plan

NT2-L3-M-PAB-59-00002-001 to 005 Cooling Water Pipeline – Longitudinal Profile

NT2-L3-C-PAB-55-00003 Cooling Water Pipeline – Manhole Plan View and Section

NT2-L3-M-PAB-63-00001-001 to 008 Main Cooling Water Pipe, Pipe Spool details

Page 11: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 11

8. 0 Exhibits

8.1 Exhibit A - Sequence of Work and QA/QC Inspection Test Point 8.2 Exhibit B - Unloading and Laying of Pipe Spool 8.3 Exhibit C – Installation Equipments, Tools and materials 8.4 Exhibit D – Extracted Standard

- Section 5.2 Testing of AWWA C206-03

- Clause 137.7.1 of ASME B31.1

8.5 Main Cooling Water Pipe Detail 8.6 Main Cooling Water Pipe Installation Schedule 8.7 Main Cooling Water Pipe Installation Plan

Administrator
Rectangle
Page 12: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 12

8.1 Exhibit A

SEQUENCE of WORK and QA/QC INSPECTION TEST POINT

SURFACE PREPARATION

CHECK (LOCATION, ELEVATION, ALIGNMENT,

OFFSET & GAP)

WELDING WORK

PIPE LAYING

WELDING INSPECTION (Refer to Clause 4.3.1

WORK COMPLETENESS

MATERIAL DELIVERY AT SITE

VISUAL CHECK

MATERIAL CONTROL STORAGE TRENCHING (BY OTHER)

FIELD JOINTS COATING

CLEANING OF INTERNAL

SURVEY & MARKING OF PIPE ROUTING

PIPE INSTALLATION / SETTING

ASSEMBLY & FIT-UP

YESNO

REMEDIAL WORK

YES

NOREMEDIAL WORK

YES

NO

REMEDIAL WORK

YES

NO

REMEDIAL WORK

Page 13: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 13

8.2 Exhibit B

Unloading and Laying of Pipe Spool

1. The parking position of the crane for lifting and laying the pipe spool shall be

ensuring there is no settlement.

2. The slings and shackles are previously used for unloading of pipe spool but making sure that the length is enough for keeping 60 degrees angle at the hook.

3. Pipe spool shall be protected in which damaging of external coating and internal

coating shall be avoided.

4. Lifting and lifting equipment for pipe laying and installation is planed per shown in fig. 1

Page 14: NT2-L3-M-000-21-00005 Rev. C
Administrator
Text Box
Fig. 1
Administrator
Typewritten Text
Page 14
Administrator
Typewritten Text
Page 15: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 15

8.3 Exhibit C

Installation Equipment, Tools and Material

Equipments, tools and materials for installation of main cooling water pipe shall be prepared but not limited to the following:- 1. Equipments

1.1 Air Compressor: 1 unit 1.2 SMAW Welding Machine and Accessories: 1 lot 1.3 TIG Welding machine and Accessories: 1 lot 1.4 Grinding Machine: 1 lot 1.5 Gas Torch Cutting Equipment and Accessories: 1 lot 1.6 Painting Equipment and Accessories: 1 lot

2. Tools

2.1 Chain block: 1 lot 2.2 Shackles: 1 lot 2.3 Sling wire: 1 lot 2.4 Hammer: 1 lot 2.5 Measuring tape: 1 lot 2.6 Engineering level (Spirit level): 1 set 2.7 Theodolite/ transit: 1 set 2.8 Plumb bob: 1 set 2.9 Spanner: 1 lot

2.10 Hydraulic jack: 1 set 2.11 Scaffolding: 1 lot 3. Materials

3.1 Mats/ straw mats or rags: 1 lot 3.2 Oil stone: 1 lot 3.3 Wood block/ grout stopper: 1 lot 3.4 Grouting Materials: 1 lot 3.5 Packer plate: 1 lot 3.6 Taper liner plate: 1 lot

Page 16: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 16

8.4 Exhibit D – Section 5.2 Testing of AWWA C206-03

Page 17: NT2-L3-M-000-21-00005 Rev. C

10 AWWA C206-03

determine the character of materials used, the ptogres:; and conditions of the work,

La £ S MII.$ auUS.4Z Jil; Ildche"TeSU.lts'obtained~<·< , 5.1.3 Weld inspection. When requested by the purchaser, a full-time weld­ •

109 inspector shall be present whenever there is welding to be performed. The

welding inspector shall have prior pipe-welding experience and shall be a certified

welding inspector (CWI) in accordance with the provisions of AWS QC I.

Sec.5.2 Testing

Testing for joint leaks shall be performed unless otherwise specified by the

purchaser. All welds shall be visually inspected in accordance with ANSIIAWS 01.1,

Table 6.1, Visual Inspection Acceptance Criteria table for statically loaded nontubu­

lar connections.

5.2.1 Hydrostatic test. Tests for leaks in all types of welded joint pipelines

shall be made by hydrostatically testing the entire pipeline, unless the procedures,

frequency of tests. and standards for acceptance or rejection of an alternative

nondestructive method are approved by the purchaser. If leakage exceeds the amount

allowed in the purchaser's specifications. leaks shall be located and repaired in

conformance with Sec. 4.7.

5.2.2 Alternative tests. In lieu of the hydrostatic test, the purchaser shall

approve nondestructive testing of welded joints. • 5.2.2.1 Ultrasonic testing with backing rings. Field-bun joints with a

backing ring may be tested by 100 percent ultrasonic testing of 10 percent of the

joints, using methods and acceptance criteria in ANSIIASME Sec. VIII.

5.2.2.2 Ultrasonic testing without backing rings. Field-butt joints without a

backing ring shall be tested by 100 percent ultrasonic testing of 10 percent of the

joints. using methods and acceptance criteria in ANSIIASME Sec. VIII or 100

percent radiograph of 10 percent of the joints, using methods and acceptance criteria

in API Standard 1104.

5.2.2.3 Lap joints. Radiographic testing of lap joints shall not be utilized

because of the difficulty inherent in interpreting the results.

Single-welded lap joints may be tested using magnetic particle testing

procedures and acceptance criteria as stated in ANSI/AWS 0.1.1 Table 6.1, Visual

Inspection Acceptance Criteria table.

Double-welded lap joints can be tested by shop drilling and tapping for 1/8-1/4-in.

(3.2-6.4-mm) national pipe thread in the spigot or bell end of the pipe. Apply 40 psi • 27 • * %')' ,

Administrator
Typewritten Text
Page 17
Administrator
Typewritten Text
Page 18: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 18

8.4 Exhibit D – Clause 137.7.1 of ASME B31.1

Page 19: NT2-L3-M-000-21-00005 Rev. C
Administrator
Typewritten Text
Administrator
Typewritten Text
Page 19
Administrator
Typewritten Text
Administrator
Rectangle
Page 20: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THIXUAN,HAI BA TRUNG DISTRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 20

8.5 Exhibit E – Main Cooling Water Pipe Detail

Page 21: NT2-L3-M-000-21-00005 Rev. C

Owner: PVN - PETRO VIETNAMClient: LILAMA - PVC CONSORTIUMProject: Nhon Trach 2 Combined Cycle Power Plant ProjectProject Package: LOT3-Balance of Plant

10PAB Main Cooling Water Pipe1 11-001 Reducer DN 2100 x 1950 - 19 1000 CS-08 CS-01 1,097.9 0.0 0.0 0.0 0.0 1,097.9 1,098 0.100% Stage5

2 12-001 Reducer DN 2100 x 1950 - 19 1000 CS-08 CS-01 1,098.8 0.0 0.0 0.0 0.0 1,098.8 1,099 0.100% Stage5

3 11-002 Straight Pipe 2100 19 2515 CS-08 CS-01 2,452.4 0.0 0.0 0.0 0.0 2,452.4 2,452 0.223% Stage5

4 12-002 Straight Pipe 2100 19 2515 CS-08 CS-01 2,452.4 0.0 0.0 0.0 0.0 2,452.4 2,452 0.223% Stage5

5 11-003Straight Pipe; /w 800 mm. MH, DN 300mm Tee & Puddle Flg. 2100 19 3800 CS-08 CS-01&07 3,705.4 0.0 904.7 229.3 0.0 4,839.4 4,839 0.440% Stage5

6 12-003Straight Pipe; /w 800 mm. MH, DN 300mm Tee & Puddle Flg. 2100 19 3800 CS-08 CS-01&07 3,705.4 0.0 904.7 229.5 0.0 4,839.5 4,840 0.440% Stage5

7 11-004 Straight Pipe 2100 19 3400 CS-08 CS-07 3,315.3 0.0 0.0 0.0 0.0 3,315.3 3,315 0.301% Stage5

7 12-004 Straight Pipe 2100 19 3400 CS-08 CS-07 3,315.3 0.0 0.0 0.0 0.0 3,315.3 3,315 0.301% Stage5

9 11-005 Elbow DN 2100, 35 deg 2100 19 6000 CS-08 CS-07 5,850.6 0.0 0.0 0.0 0.0 5,850.6 5,851 0.532% Stage5

10 12-005 Elbow DN 2100, 35 deg 2100 19 6000 CS-08 CS-07 5,850.6 0.0 0.0 0.0 0.0 5,850.6 5,851 0.532% Stage5

11 11-006 Straight pipe 2100 19 966 CS-08 CS-07 941.9 0.0 0.0 0.0 0.0 941.9 942 0.086% Stage5

12 12-006 Straight pipe 2100 19 966 CS-08 CS-07 941.9 0.0 0.0 0.0 0.0 941.9 942 0.086% Stage5

13 11-007 Elbow DN 2100, 35 deg 2100 19 6000 CS-08 CS-07 5,850.6 0.0 0.0 0.0 0.0 5,850.6 5,851 0.532% Stage5

14 12-007 Elbow DN 2100, 35 deg 2100 19 6000 CS-08 CS-07 5,904.0 0.0 0.0 0.0 0.0 5,904.0 5,904 0.537% Stage5

15 11-008 Reducer DN 2850 x 2100 - 19 3600 CS-08 CS-07 1,318.4 0.0 0.0 0.0 0.0 1,318.4 1,318 0.120% Stage5

16 12-008 Elbow DN 2100, 45 deg 2100 19 4600 CS-08 CS-07 4,485.4 0.0 0.0 0.0 0.0 4,485.4 4,485 0.408% Stage5

17 12-009 Straight Pipe 2100 19 3800 CS-08 CS-07 3,705.4 0.0 0.0 0.0 0.0 3,705.4 3,705 0.337% Stage5

18 30-001s Lateral DN 2850xDN 2100, 45 deg 2850 19 7160 CS-08 CS-07 9,497.9 0.0 0.0 0.0 0.0 9,497.9 9,498 0.863% Stage5

19 30-002s Straight Pipe 2850 19 5500 CS-08 CS-07 7,295.9 0.0 0.0 0.0 0.0 7,295.9 7,296 0.663% Stage5

20 30-003s Elbow DN 2850, 45 deg 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage5

21 30-004s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage5

22 30-005s Straight Pipe with manhole DN 1100mm 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 347.7 8,306.9 8,307 0.755% Stage5

23 30-006s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage5

24 30-007s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage5

25 30-008s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage5

26 30-009s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage5

27 30-010s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage5

28 30-011s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage5

29 30-012s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage5

30 30-013s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

RemarkPuddle

Work Percentage

per Pipe Spool

Manhole. DN 1100

Pipe Weight (kgs)

Pipe Body Flange

TORISHIMA NHON TRACH 2 PROJECT- LOT3 BALANCE OF PLANT

Main Cooling Water Pipe Schedule

Pipe DescriptionNo. Pipe Spool No. Coat-ing Type

Pipe Size (mm.)

Manhole. DN 800

Adjusted Weight (kgs)

Sub-Total

OD. t L

Lining Type

Page 21

Page 22: NT2-L3-M-000-21-00005 Rev. C

Owner: PVN - PETRO VIETNAMClient: LILAMA - PVC CONSORTIUMProject: Nhon Trach 2 Combined Cycle Power Plant ProjectProject Package: LOT3-Balance of Plant

RemarkPuddle

Work Percentage

per Pipe Spool

Manhole. DN 1100

Pipe Weight (kgs)

Pipe Body Flange

TORISHIMA NHON TRACH 2 PROJECT- LOT3 BALANCE OF PLANT

Main Cooling Water Pipe Schedule

Pipe DescriptionNo. Pipe Spool No. Coat-ing Type

Pipe Size (mm.)

Manhole. DN 800

Adjusted Weight (kgs)

Sub-Total

OD. t L

Lining Type

31 30-014s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

32 30-015s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

33 30-016s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

34 30-017s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

35 30-018s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

36 30-019s Straight Pipe with manhole DN 1100mm 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 347.7 8,306.9 8,307 0.755% Stage4

37 30-020s Straight Pipe 2850 19 4600 CS-08 CS-07 6,102.0 0.0 0.0 0.0 0.0 6,102.0 6,102 0.555% Stage4

38 30-021s Elbow DN 2850, 45 deg 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

39 30-022s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

40 30-023s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

41 30-024s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

42 30-025s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

49 30-026s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

50 30-027s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

51 30-028s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

52 30-029s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

53 30-030s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

54 30-031s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

55 30-032s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage4

56 30-033s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

57 30-034s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

58 30-035s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

59 30-036s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

60 30-037s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

61 30-038s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

62 30-039s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

63 30-040s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

64 30-041s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

65 30-042s Straight Pipe with manhole DN 1100mm 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 347.7 8,306.9 8,307 0.755% Stage2

66 30-043s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

67 30-044s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

68 30-045s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

Page 22

Page 23: NT2-L3-M-000-21-00005 Rev. C

Owner: PVN - PETRO VIETNAMClient: LILAMA - PVC CONSORTIUMProject: Nhon Trach 2 Combined Cycle Power Plant ProjectProject Package: LOT3-Balance of Plant

RemarkPuddle

Work Percentage

per Pipe Spool

Manhole. DN 1100

Pipe Weight (kgs)

Pipe Body Flange

TORISHIMA NHON TRACH 2 PROJECT- LOT3 BALANCE OF PLANT

Main Cooling Water Pipe Schedule

Pipe DescriptionNo. Pipe Spool No. Coat-ing Type

Pipe Size (mm.)

Manhole. DN 800

Adjusted Weight (kgs)

Sub-Total

OD. t L

Lining Type

69 30-046s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

70 30-047s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

71 30-048s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

72 30-049s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

73 30-050s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

74 30-051s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage2

75 30-052s Straight Pipe 2850 19 2292 CS-08 CS-07 3,040.4 0.0 0.0 0.0 0.0 3,040.4 3,040 0.276% Stage2

76 30-053s Elbow DN 2850, 45 deg 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

77 30-054s Straight Pipe 2850 19 2556 CS-08 CS-07 3,390.6 0.0 0.0 0.0 0.0 3,390.6 3,391 0.308% Stage1

78 30-055s Elbow DN 2850, 45 deg 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

79 30-056s Straight Pipe 2850 19 2572 CS-08 CS-07 3,411.8 0.0 0.0 0.0 0.0 3,411.8 3,412 0.310% Stage1

80 30-057s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

81 30-058s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

82 30-059s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

83 30-060s Straight Pipe with manhole DN 1100mm 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 347.7 8,306.9 8,307 0.755% Stage1

84 30-061s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

85 30-062s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

86 30-063s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

87 30-064s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

88 30-065s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

89 30-066s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

90 30-067s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

91 30-068s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

92 30-069s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

93 30-070s Straight Pipe with manhole DN 1100mm 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 347.7 8,306.9 8,307 0.755% Stage1

94 30-071s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

95 30-072s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

96 30-073s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

97 30-074s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

98 30-075s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

99 30-076s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

100 30-077s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

Page 23

Page 24: NT2-L3-M-000-21-00005 Rev. C

Owner: PVN - PETRO VIETNAMClient: LILAMA - PVC CONSORTIUMProject: Nhon Trach 2 Combined Cycle Power Plant ProjectProject Package: LOT3-Balance of Plant

RemarkPuddle

Work Percentage

per Pipe Spool

Manhole. DN 1100

Pipe Weight (kgs)

Pipe Body Flange

TORISHIMA NHON TRACH 2 PROJECT- LOT3 BALANCE OF PLANT

Main Cooling Water Pipe Schedule

Pipe DescriptionNo. Pipe Spool No. Coat-ing Type

Pipe Size (mm.)

Manhole. DN 800

Adjusted Weight (kgs)

Sub-Total

OD. t L

Lining Type

101 30-078s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

102 30-079s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

103 30-080s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

104 30-081s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

105 30-082s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

106 30-083s Straight Pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

107 30-084s Straight pipe with tee DN 300mm 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

108 30-085s Straight Pipe with manhole DN 1100mm 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 347.7 8,306.9 8,307 0.755% Stage3

109 30-086s Straight Pipe 2850 19 4871 CS-08 CS-07 6,461.5 0.0 0.0 0.0 0.0 6,461.5 6,461 0.587% Stage3

110 30-087s Straight Pipe 2850 19 5000 CS-08 CS-07 6,632.6 0.0 0.0 0.0 0.0 6,632.6 6,633 0.603% Stage3

111 31-001s Reducer DN 2850 x 1950 2850 19 4200 CS-08 CS-07 1,754.0 0.0 0.0 0.0 0.0 1,754.0 1,754 0.159% Stage3

112 31-002s Straight Pipe 1950 19 6000 CS-08 CS-07 5,428.8 0.0 0.0 0.0 0.0 5,428.8 5,429 0.493% Stage3

113 31-003s Straight Pipe 1950 19 6000 CS-08 CS-07 5,428.8 0.0 0.0 0.0 0.0 5,428.8 5,429 0.493% Stage3

114 31-004s Straight Pipe 1950 19 3600 CS-08 CS-07 3,257.3 0.0 0.0 0.0 0.0 3,257.3 3,257 0.296% Stage3

115 31-005s Straight Pipe 1950 19 5150 CS-08 CS-07 4,659.8 0.0 0.0 0.0 0.0 4,659.8 4,660 0.424% Stage3

116 31-004R Straight Pipe 1950 19 5150 CS-08 CS-07 4,659.8 0.0 0.0 0.0 0.0 4,659.8 4,660 0.424% Stage3

117 31-003R Straight Pipe 1950 19 3300 CS-08 CS-07 2,985.9 0.0 0.0 0.0 0.0 2,985.9 2,986 0.271% Stage3

118 31-002R Straight Pipe 1950 19 6000 CS-08 CS-07 5,428.8 0.0 0.0 0.0 0.0 5,428.8 5,429 0.493% Stage3

119 31-001R Reducer DN 2850 x 1950 1950 19 4200 CS-08 CS-07 1,754.0 0.0 0.0 0.0 0.0 1,754.0 1,754 0.159% Stage3

120 30-001R Straight pipe 2850 19 5500 CS-08 CS-07 7,295.9 0.0 0.0 0.0 0.0 7,295.9 7,296 0.663% Stage3

121 30-002R Straight pipe with tee DN 300mm 2850 19 5115 CS-08 CS-07 6,785.2 0.0 0.0 0.0 0.0 6,785.2 6,785 0.617% Stage3

122 30-003R Straight pipe 2850 19 2900 CS-08 CS-07 3,846.9 0.0 0.0 0.0 0.0 3,846.9 3,847 0.350% Stage3

123 30-004R Straight Pipe with manhole DN 1100mm 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 347.7 8,306.9 8,307 0.755% Stage3

124 30-005R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

125 30-006R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

126 30-007R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

127 30-008R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

128 30-009R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

129 30-010R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

130 30-011R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

131 30-012R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

132 30-013R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage3

Page 24

Page 25: NT2-L3-M-000-21-00005 Rev. C

Owner: PVN - PETRO VIETNAMClient: LILAMA - PVC CONSORTIUMProject: Nhon Trach 2 Combined Cycle Power Plant ProjectProject Package: LOT3-Balance of Plant

RemarkPuddle

Work Percentage

per Pipe Spool

Manhole. DN 1100

Pipe Weight (kgs)

Pipe Body Flange

TORISHIMA NHON TRACH 2 PROJECT- LOT3 BALANCE OF PLANT

Main Cooling Water Pipe Schedule

Pipe DescriptionNo. Pipe Spool No. Coat-ing Type

Pipe Size (mm.)

Manhole. DN 800

Adjusted Weight (kgs)

Sub-Total

OD. t L

Lining Type

133 30-014R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

134 30-015R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

135 30-016R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

136 30-017R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

137 30-018R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

138 30-019R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

139 30-020R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

140 30-021R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

141 30-022R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

142 30-023R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

143 30-024R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

144 30-025R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

145 30-026R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

146 30-027R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

147 30-028R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

148 30-029R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

149 30-030R Straight Pipe with manhole DN 1100mm 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 347.7 8,306.9 8,307 0.755% Stage1

150 30-031R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

151 30-032R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

152 30-033R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

153 30-034R Elbow DN 2850, 22.5 deg 2850 19 2100 CS-08 CS-07 2,785.7 0.0 0.0 0.0 0.0 2,785.7 2,786 0.253% Stage1

154 30-035R Straight pipe 2850 19 785 CS-08 CS-07 1,041.3 0.0 0.0 0.0 0.0 1,041.3 1,041 0.095% Stage1

155 30-036R Elbow DN 2850, 22.5 deg 2850 19 2100 CS-08 CS-07 2,785.7 0.0 0.0 0.0 0.0 2,785.7 2,786 0.253% Stage1

156 30-037R Straight pipe 2850 19 6000 CS-08 CS-07 7,959.1 0.0 0.0 0.0 0.0 7,959.1 7,959 0.723% Stage1

157 30-038R Straight pipe with Puddle Flange 2850 19 4252 CS-08 CS-07 5,640.4 0.0 1,851.7 0.0 0.0 7,492.1 7,492 0.681% Stage1

158 30-039R Elbow DN 2850, 45 deg 2850 19 2000 CS-08 CS-07 2,653.0 0.0 0.0 0.0 0.0 2,653.0 2,653 0.241% Stage1

Total 1,100,176 100.000%

Page 25

Page 26: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THIXUAN,HAI BA TRUNG DISTRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 26

8.6 Exhibit F – Main Cooling Water Pipe Installation Schedule

Page 27: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

1 Main Cooling Water Pipe Spool Piece Installation 152 days Thu 4/15/10 Wed 9/15/10

2 Zone #1 56 days Thu 4/15/10 Wed 6/9/10

378 Zone #2 29 days Tue 6/8/10 Tue 7/6/10

539 Zone #3 43 days Mon 6/28/10 Mon 8/9/10

812 Zone #4 29 days Fri 7/9/10 Fri 8/6/10

973 Zone #5 38 days Sat 8/7/10 Wed 9/15/10

4/15 9/150%

4/15 6/9

6/8 7/6

6/28 8/9

7/9 8/6

8/7 9/15

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 1

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 28: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

1 Main Cooling Water Pipe Spool Piece Installation 152 days Thu 4/15/10 Wed 9/15/10

2 Zone #1 56 days Thu 4/15/10 Wed 6/9/10

3 Spool Piece No 30-038R+30-037R 10 days Thu 4/15/10 Sat 4/24/10

11 Spool Piece No 30-037R+30-036R 10 days Fri 4/16/10 Sun 4/25/10

19 Spool Piece No 30-036R+30-035R 10 days Sat 4/17/10 Mon 4/26/10

27 Spool Piece No 30-035R+30-034R 10 days Sun 4/18/10 Tue 4/27/10

35 Spool Piece No 30-034R+30-033R 10 days Mon 4/19/10 Wed 4/28/10

43 Spool Piece No 30-033R+30-032R 10 days Tue 4/20/10 Thu 4/29/10

51 Spool Piece No 30-032R+30-031R 10 days Wed 4/21/10 Fri 4/30/10

59 Spool Piece No 30-031R+30-030R 10 days Thu 4/22/10 Sat 5/1/10

67 Spool Piece No 30-030R+30-029R 10 days Fri 4/23/10 Sun 5/2/10

75 Spool Piece No 30-029R+30-028R 10 days Sat 4/24/10 Mon 5/3/10

83 Spool Piece No 30-028R+30-027R 10 days Sun 4/25/10 Tue 5/4/10

91 Spool Piece No 30-027R+30-026R 10 days Mon 4/26/10 Wed 5/5/10

99 Spool Piece No 30-026R+30-025R 10 days Tue 4/27/10 Thu 5/6/10

107 Spool Piece No 30-025R+30-024R 10 days Wed 4/28/10 Fri 5/7/10

115 Spool Piece No 30-024R+30-023R 10 days Thu 4/29/10 Sat 5/8/10

123 Spool Piece No 30-023R+30-022R 10 days Fri 4/30/10 Sun 5/9/10

131 Spool Piece No 30-022R+30-021R 10 days Sat 5/1/10 Mon 5/10/10

139 Spool Piece No 30-021R+30-020R 10 days Sun 5/2/10 Tue 5/11/10

147 Spool Piece No 30-020R+30-019R 10 days Mon 5/3/10 Wed 5/12/10

155 Spool Piece No 30-019R+30-018R 10 days Tue 5/4/10 Thu 5/13/10

163 Spool Piece No 30-018R+30-017R 10 days Wed 5/5/10 Fri 5/14/10

171 Spool Piece No 30-017R+30-016R 10 days Thu 5/6/10 Sat 5/15/10

179 Spool Piece No 30-016R+30-015R 10 days Fri 5/7/10 Sun 5/16/10

187 Spool Piece No 30-015R+30-014R 10 days Sat 5/8/10 Mon 5/17/10

195 Spool Piece No 30-038R+30-039R 10 days Sun 5/9/10 Tue 5/18/10

202 Spool Piece No 30-053S+30-054S 10 days Mon 5/10/10 Wed 5/19/10

210 Spool Piece No 30-054S+30-055S 10 days Tue 5/11/10 Thu 5/20/10

218 Spool Piece No 30-055S+30-056S 10 days Wed 5/12/10 Fri 5/21/10

226 Spool Piece No 30-056S+30-057S 10 days Thu 5/13/10 Sat 5/22/10

234 Spool Piece No 30-057S+30-058S 10 days Fri 5/14/10 Sun 5/23/10

242 Spool Piece No 30-058S+30-059S 10 days Sat 5/15/10 Mon 5/24/10

250 Spool Piece No 30-059S+30-060S 10 days Sun 5/16/10 Tue 5/25/10

258 Spool Piece No 30-060S+30-061S 10 days Mon 5/17/10 Wed 5/26/10

266 Spool Piece No 30-061S+30-062S 10 days Tue 5/18/10 Thu 5/27/10

274 Spool Piece No 30-062S+30-063S 10 days Wed 5/19/10 Fri 5/28/10

282 Spool Piece No 30-063S+30-064S 10 days Thu 5/20/10 Sat 5/29/10

290 Spool Piece No 30-064S+30-065S 10 days Fri 5/21/10 Sun 5/30/10

298 Spool Piece No 30-065S+30-066S 10 days Sat 5/22/10 Mon 5/31/10

306 Spool Piece No 30-066S+30-067S 10 days Sun 5/23/10 Tue 6/1/10

314 Spool Piece No 30-067S+30-068S 10 days Mon 5/24/10 Wed 6/2/10

322 Spool Piece No 30-068S+30-069S 10 days Tue 5/25/10 Thu 6/3/10

330 Spool Piece No 30-069S+30-070S 10 days Wed 5/26/10 Fri 6/4/10

338 Spool Piece No 30-070S+30-071S 10 days Thu 5/27/10 Sat 6/5/10

346 Spool Piece No 30-071S+30-072S 10 days Fri 5/28/10 Sun 6/6/10

354 Spool Piece No 30-072S+30-073S 10 days Sat 5/29/10 Mon 6/7/10

362 Spool Piece No 30-073S+30-074S 10 days Sun 5/30/10 Tue 6/8/10

370 Spool Piece No 30-074S+30-075S 10 days Mon 5/31/10 Wed 6/9/10

378 Zone #2 29 days Tue 6/8/10 Tue 7/6/10

379 Spool Piece No 30-033S+30-034S 10 days Tue 6/8/10 Thu 6/17/10

387 Spool Piece No 30-034S+30-035S 10 days Wed 6/9/10 Fri 6/18/10

395 Spool Piece No 30-035S+30-036S 10 days Thu 6/10/10 Sat 6/19/10

403 Spool Piece No 30-036S+30-037S 10 days Fri 6/11/10 Sun 6/20/10

411 Spool Piece No 30-037S+30-038S 10 days Sat 6/12/10 Mon 6/21/10

419 Spool Piece No 30-038S+30-039S 10 days Sun 6/13/10 Tue 6/22/10

427 Spool Piece No 30-039S+30-040S 10 days Mon 6/14/10 Wed 6/23/10

435 Spool Piece No 30-040S+30-041S 10 days Tue 6/15/10 Thu 6/24/10

443 Spool Piece No 30-041S+30-042S 10 days Wed 6/16/10 Fri 6/25/10

451 Spool Piece No 30-042S+30-043S 10 days Thu 6/17/10 Sat 6/26/10

459 Spool Piece No 30-043S+30-044S 10 days Fri 6/18/10 Sun 6/27/10

467 Spool Piece No 30-044S+30-045S 10 days Sat 6/19/10 Mon 6/28/10

475 Spool Piece No 30-045S+30-046S 10 days Sun 6/20/10 Tue 6/29/10

483 Spool Piece No 30-046S+30-047S 10 days Mon 6/21/10 Wed 6/30/10

491 Spool Piece No 30-047S+30-048S 10 days Tue 6/22/10 Thu 7/1/10

499 Spool Piece No 30-048S+30-049S 10 days Wed 6/23/10 Fri 7/2/10

507 Spool Piece No 30-049S+30-050S 10 days Thu 6/24/10 Sat 7/3/10

515 Spool Piece No 30-050S+30-051S 10 days Fri 6/25/10 Sun 7/4/10

523 Spool Piece No 30-051S+30-052S 10 days Sat 6/26/10 Mon 7/5/10

531 Spool Piece No 30-052S+30-053S 10 days Sun 6/27/10 Tue 7/6/10

539 Zone #3 43 days Mon 6/28/10 Mon 8/9/10

540 Spool Piece No 30-014R+30-013R 10 days Mon 6/28/10 Wed 7/7/10

548 Spool Piece No 30-013R+30-012R 10 days Tue 6/29/10 Thu 7/8/10

556 Spool Piece No 30-012R+30-011R 10 days Wed 6/30/10 Fri 7/9/10

564 Spool Piece No 30-011R+30-010R 10 days Thu 7/1/10 Sat 7/10/10

572 Spool Piece No 30-010R+30-009R 10 days Fri 7/2/10 Sun 7/11/10

580 Spool Piece No 30-009R+30-008R 10 days Sat 7/3/10 Mon 7/12/10

588 Spool Piece No 30-008R+30-007R 10 days Sun 7/4/10 Tue 7/13/10

596 Spool Piece No 30-007R+30-006R 10 days Mon 7/5/10 Wed 7/14/10

604 Spool Piece No 30-006R+30-005R 10 days Tue 7/6/10 Thu 7/15/10

612 Spool Piece No 30-005R+30-004R 10 days Wed 7/7/10 Fri 7/16/10

620 Spool Piece No 30-004R+30-003R 10 days Thu 7/8/10 Sat 7/17/10

4/15 9/150%

4/15 6/9

4/15 4/24

4/16 4/25

4/17 4/26

4/18 4/27

4/19 4/28

4/20 4/29

4/21 4/30

4/22 5/1

4/23 5/2

4/24 5/3

4/25 5/4

4/26 5/5

4/27 5/6

4/28 5/7

4/29 5/8

4/30 5/9

5/1 5/10

5/2 5/11

5/3 5/12

5/4 5/13

5/5 5/14

5/6 5/15

5/7 5/16

5/8 5/17

5/9 5/18

5/10 5/19

5/11 5/20

5/12 5/21

5/13 5/22

5/14 5/23

5/15 5/24

5/16 5/25

5/17 5/26

5/18 5/27

5/19 5/28

5/20 5/29

5/21 5/30

5/22 5/31

5/23 6/1

5/24 6/2

5/25 6/3

5/26 6/4

5/27 6/5

5/28 6/6

5/29 6/7

5/30 6/8

5/31 6/9

6/8 7/6

6/8 6/17

6/9 6/18

6/10 6/19

6/11 6/20

6/12 6/21

6/13 6/22

6/14 6/23

6/15 6/24

6/16 6/25

6/17 6/26

6/18 6/27

6/19 6/28

6/20 6/29

6/21 6/30

6/22 7/1

6/23 7/2

6/24 7/3

6/25 7/4

6/26 7/5

6/27 7/6

6/28 8/9

6/28 7/7

6/29 7/8

6/30 7/9

7/1 7/10

7/2 7/11

7/3 7/12

7/4 7/13

7/5 7/14

7/6 7/15

7/7 7/16

7/8 7/17

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 1

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 29: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

628 Spool Piece No 30-003R+30-002R 10 days Fri 7/9/10 Sun 7/18/10

636 Spool Piece No 30-002R+30-001R 10 days Sat 7/10/10 Mon 7/19/10

644 Spool Piece No 30-001R+31-001R 10 days Sun 7/11/10 Tue 7/20/10

652 Spool Piece No 31-001R+31-002R 10 days Mon 7/12/10 Wed 7/21/10

660 Spool Piece No 31-002R+31-003R 10 days Tue 7/13/10 Thu 7/22/10

668 Spool Piece No 31-003R+31-004R 10 days Wed 7/14/10 Fri 7/23/10

676 Spool Piece No 30-076S+30-075S 10 days Thu 7/15/10 Sat 7/24/10

684 Spool Piece No 30-077S+30-076S 10 days Fri 7/16/10 Sun 7/25/10

692 Spool Piece No 30-078S+30-077S 10 days Sat 7/17/10 Mon 7/26/10

700 Spool Piece No 30-079S+30-078S 10 days Sun 7/18/10 Tue 7/27/10

708 Spool Piece No 30-080S+30-079S 10 days Mon 7/19/10 Wed 7/28/10

716 Spool Piece No 30-081S+30-080S 10 days Tue 7/20/10 Thu 7/29/10

724 Spool Piece No 30-082S+30-081S 10 days Wed 7/21/10 Fri 7/30/10

732 Spool Piece No 30-083S+30-082S 10 days Thu 7/22/10 Sat 7/31/10

740 Spool Piece No 30-084S+30-083S 10 days Fri 7/23/10 Sun 8/1/10

748 Spool Piece No 30-085S+30-084S 10 days Sat 7/24/10 Mon 8/2/10

756 Spool Piece No 30-086S+30-085S 10 days Sun 7/25/10 Tue 8/3/10

764 Spool Piece No 30-087S+30-086S 10 days Mon 7/26/10 Wed 8/4/10

772 Spool Piece No 31-001S+30-087S 10 days Tue 7/27/10 Thu 8/5/10

780 Spool Piece No 31-002S+31-001S 10 days Wed 7/28/10 Fri 8/6/10

788 Spool Piece No 31-003S+31-002S 10 days Thu 7/29/10 Sat 8/7/10

796 Spool Piece No 31-004S+31-003S 10 days Fri 7/30/10 Sun 8/8/10

804 Spool Piece No 31-005S+31-004S 10 days Sat 7/31/10 Mon 8/9/10

812 Zone #4 29 days Fri 7/9/10 Fri 8/6/10

813 Spool Piece No 30-013S+30-014S 10 days Fri 7/9/10 Sun 7/18/10

821 Spool Piece No 30-014S+30-015S 10 days Sat 7/10/10 Mon 7/19/10

829 Spool Piece No 30-015S+30-016S 10 days Sun 7/11/10 Tue 7/20/10

837 Spool Piece No 30-016S+30-017S 10 days Mon 7/12/10 Wed 7/21/10

845 Spool Piece No 30-017S+30-018S 10 days Tue 7/13/10 Thu 7/22/10

853 Spool Piece No 30-018S+30-019S 10 days Wed 7/14/10 Fri 7/23/10

861 Spool Piece No 30-019S+30-020S 10 days Thu 7/15/10 Sat 7/24/10

869 Spool Piece No 30-020S+30-021S 10 days Fri 7/16/10 Sun 7/25/10

877 Spool Piece No 30-021S+30-022S 10 days Sat 7/17/10 Mon 7/26/10

885 Spool Piece No 30-022S+30-023S 10 days Sun 7/18/10 Tue 7/27/10

893 Spool Piece No 30-023S+30-024S 10 days Mon 7/19/10 Wed 7/28/10

901 Spool Piece No 30-024S+30-025S 10 days Tue 7/20/10 Thu 7/29/10

909 Spool Piece No 30-025S+30-026S 10 days Wed 7/21/10 Fri 7/30/10

917 Spool Piece No 30-026S+30-027S 10 days Thu 7/22/10 Sat 7/31/10

925 Spool Piece No 30-027S+30-028S 10 days Fri 7/23/10 Sun 8/1/10

933 Spool Piece No 30-028S+30-029S 10 days Sat 7/24/10 Mon 8/2/10

941 Spool Piece No 30-029S+30-030S 10 days Sun 7/25/10 Tue 8/3/10

949 Spool Piece No 30-030S+30-031S 10 days Mon 7/26/10 Wed 8/4/10

957 Spool Piece No 30-031S+30-032S 10 days Tue 7/27/10 Thu 8/5/10

965 Spool Piece No 30-032S+30-033S 10 days Wed 7/28/10 Fri 8/6/10

973 Zone #5 38 days Sat 8/7/10 Wed 9/15/10

974 Spool Piece No 30-012S+30-013S 10 days Sat 8/7/10 Mon 8/16/10

982 Spool Piece No 30-011S+30-012S 10 days Sun 8/8/10 Tue 8/17/10

990 Spool Piece No 30-010S+30-011S 10 days Mon 8/9/10 Wed 8/18/10

998 Spool Piece No 30-009S+30-010S 10 days Tue 8/10/10 Thu 8/19/10

1006 Spool Piece No 30-008S+30-009S 10 days Wed 8/11/10 Fri 8/20/10

1014 Spool Piece No 30-007S+30-008S 10 days Thu 8/12/10 Sat 8/21/10

1022 Spool Piece No 30-006S+30-007S 10 days Fri 8/13/10 Sun 8/22/10

1030 Spool Piece No 30-005S+30-006S 10 days Sat 8/14/10 Mon 8/23/10

1038 Spool Piece No 30-004S+30-005S 10 days Sun 8/15/10 Tue 8/24/10

1046 Spool Piece No 30-003S+30-004S 10 days Mon 8/16/10 Wed 8/25/10

1054 Spool Piece No 30-002S+30-003S 10 days Tue 8/17/10 Thu 8/26/10

1062 Spool Piece No 30-001S+30-002S 10 days Wed 8/18/10 Fri 8/27/10

1070 Spool Piece No 11-008S+30-001S 10 days Thu 8/19/10 Sat 8/28/10

1078 Spool Piece No 11-007+11-008 10 days Fri 8/20/10 Sun 8/29/10

1086 Spool Piece No 11-006+11-007 10 days Sat 8/21/10 Mon 8/30/10

1094 Spool Piece No 11-005+11-006 10 days Sun 8/22/10 Tue 8/31/10

1102 Spool Piece No 11-004+11-005 10 days Mon 8/23/10 Wed 9/1/10

1110 Spool Piece No 11-003+11-004 10 days Tue 8/24/10 Thu 9/2/10

1118 Spool Piece No 11-002+11-003 10 days Wed 8/25/10 Fri 9/3/10

1125 Spool Piece No 11-001+11-002 10 days Thu 8/26/10 Sat 9/4/10

1132 Spool Piece No 30-001S+12-009 10 days Fri 8/27/10 Sun 9/5/10

1140 Spool Piece No 12-009+12-008 10 days Sat 8/28/10 Mon 9/6/10

1148 Spool Piece No 12-008+12-007 10 days Sun 8/29/10 Tue 9/7/10

1156 Spool Piece No 12-007+12-006 10 days Mon 8/30/10 Wed 9/8/10

1164 Spool Piece No 12-006+12-005 10 days Tue 8/31/10 Thu 9/9/10

1172 Spool Piece No 12-005+12-004 10 days Wed 9/1/10 Fri 9/10/10

1180 Spool Piece No 12-004+12-003 10 days Thu 9/2/10 Mon 9/13/10

1188 Spool Piece No 12-003+12-002 10 days Fri 9/3/10 Tue 9/14/10

1195 Spool Piece No 12-002+12-001 10 days Sat 9/4/10 Wed 9/15/10

7/9 7/18

7/10 7/19

7/11 7/20

7/12 7/21

7/13 7/22

7/14 7/23

7/15 7/24

7/16 7/25

7/17 7/26

7/18 7/27

7/19 7/28

7/20 7/29

7/21 7/30

7/22 7/31

7/23 8/1

7/24 8/2

7/25 8/3

7/26 8/4

7/27 8/5

7/28 8/6

7/29 8/7

7/30 8/8

7/31 8/9

7/9 8/6

7/9 7/18

7/10 7/19

7/11 7/20

7/12 7/21

7/13 7/22

7/14 7/23

7/15 7/24

7/16 7/25

7/17 7/26

7/18 7/27

7/19 7/28

7/20 7/29

7/21 7/30

7/22 7/31

7/23 8/1

7/24 8/2

7/25 8/3

7/26 8/4

7/27 8/5

7/28 8/6

8/7 9/15

8/7 8/16

8/8 8/17

8/9 8/18

8/10 8/19

8/11 8/20

8/12 8/21

8/13 8/22

8/14 8/23

8/15 8/24

8/16 8/25

8/17 8/26

8/18 8/27

8/19 8/28

8/20 8/29

8/21 8/30

8/22 8/31

8/23 9/1

8/24 9/2

8/25 9/3

8/26 9/4

8/27 9/5

8/28 9/6

8/29 9/7

8/30 9/8

8/31 9/9

9/1 9/10

9/2 9/13

9/3 9/14

9/4 9/15

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 2

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 30: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

1 Main Cooling Water Pipe Spool Piece Installation 152 days Thu 4/15/10 Wed 9/15/10

2 Zone #1 56 days Thu 4/15/10 Wed 6/9/10

3 Spool Piece No 30-038R+30-037R 10 days Thu 4/15/10 Sat 4/24/10

4 Check and Confirm Trenching work and Pipe Laying 1 day Thu 4/15/10 Thu 4/15/10

5 Fit-up and Alignment Including Inspection 1 day Fri 4/16/10 Fri 4/16/10

6 Welding 4 days Sat 4/17/10 Tue 4/20/10

7 Welding Inspection (NDE) 1 day Wed 4/21/10 Wed 4/21/10

8 Field Joint Painting and Touch-up Paint 2 days Thu 4/22/10 Fri 4/23/10

9 Painting Inspection 1 day Sat 4/24/10 Sat 4/24/10

10 Release Backfilling 0 days Sat 4/24/10 Sat 4/24/10

11 Spool Piece No 30-037R+30-036R 10 days Fri 4/16/10 Sun 4/25/10

12 Check and Confirm Trenching work and Pipe Laying 1 day Fri 4/16/10 Fri 4/16/10

13 Fit-up and Alignment Including Inspection 1 day Sat 4/17/10 Sat 4/17/10

14 Welding 4 days Sun 4/18/10 Wed 4/21/10

15 Welding Inspection (NDE) 1 day Thu 4/22/10 Thu 4/22/10

16 Field Joint Painting and Touch-up Paint 2 days Fri 4/23/10 Sat 4/24/10

17 Painting Inspection 1 day Sun 4/25/10 Sun 4/25/10

18 Release Backfilling 0 days Sun 4/25/10 Sun 4/25/10

19 Spool Piece No 30-036R+30-035R 10 days Sat 4/17/10 Mon 4/26/10

20 Check and Confirm Trenching work and Pipe Laying 1 day Sat 4/17/10 Sat 4/17/10

21 Fit-up and Alignment Including Inspection 1 day Sun 4/18/10 Sun 4/18/10

22 Welding 4 days Mon 4/19/10 Thu 4/22/10

23 Welding Inspection (NDE) 1 day Fri 4/23/10 Fri 4/23/10

24 Field Joint Painting and Touch-up Paint 2 days Sat 4/24/10 Sun 4/25/10

25 Painting Inspection 1 day Mon 4/26/10 Mon 4/26/10

26 Release Backfilling 0 days Mon 4/26/10 Mon 4/26/10

27 Spool Piece No 30-035R+30-034R 10 days Sun 4/18/10 Tue 4/27/10

28 Check and Confirm Trenching work and Pipe Laying 1 day Sun 4/18/10 Sun 4/18/10

29 Fit-up and Alignment Including Inspection 1 day Mon 4/19/10 Mon 4/19/10

30 Welding 4 days Tue 4/20/10 Fri 4/23/10

31 Welding Inspection (NDE) 1 day Sat 4/24/10 Sat 4/24/10

32 Field Joint Painting and Touch-up Paint 2 days Sun 4/25/10 Mon 4/26/10

33 Painting Inspection 1 day Tue 4/27/10 Tue 4/27/10

34 Release Backfilling 0 days Tue 4/27/10 Tue 4/27/10

35 Spool Piece No 30-034R+30-033R 10 days Mon 4/19/10 Wed 4/28/10

36 Check and Confirm Trenching work and Pipe Laying 1 day Mon 4/19/10 Mon 4/19/10

37 Fit-up and Alignment Including Inspection 1 day Tue 4/20/10 Tue 4/20/10

38 Welding 4 days Wed 4/21/10 Sat 4/24/10

39 Welding Inspection (NDE) 1 day Sun 4/25/10 Sun 4/25/10

40 Field Joint Painting and Touch-up Paint 2 days Mon 4/26/10 Tue 4/27/10

41 Painting Inspection 1 day Wed 4/28/10 Wed 4/28/10

42 Release Backfilling 0 days Wed 4/28/10 Wed 4/28/10

43 Spool Piece No 30-033R+30-032R 10 days Tue 4/20/10 Thu 4/29/10

44 Check and Confirm Trenching work and Pipe Laying 1 day Tue 4/20/10 Tue 4/20/10

45 Fit-up and Alignment Including Inspection 1 day Wed 4/21/10 Wed 4/21/10

46 Welding 4 days Thu 4/22/10 Sun 4/25/10

47 Welding Inspection (NDE) 1 day Mon 4/26/10 Mon 4/26/10

48 Field Joint Painting and Touch-up Paint 2 days Tue 4/27/10 Wed 4/28/10

49 Painting Inspection 1 day Thu 4/29/10 Thu 4/29/10

50 Release Backfilling 0 days Thu 4/29/10 Thu 4/29/10

51 Spool Piece No 30-032R+30-031R 10 days Wed 4/21/10 Fri 4/30/10

52 Check and Confirm Trenching work and Pipe Laying 1 day Wed 4/21/10 Wed 4/21/10

53 Fit-up and Alignment Including Inspection 1 day Thu 4/22/10 Thu 4/22/10

54 Welding 4 days Fri 4/23/10 Mon 4/26/10

55 Welding Inspection (NDE) 1 day Tue 4/27/10 Tue 4/27/10

56 Field Joint Painting and Touch-up Paint 2 days Wed 4/28/10 Thu 4/29/10

57 Painting Inspection 1 day Fri 4/30/10 Fri 4/30/10

58 Release Backfilling 0 days Fri 4/30/10 Fri 4/30/10

59 Spool Piece No 30-031R+30-030R 10 days Thu 4/22/10 Sat 5/1/10

60 Check and Confirm Trenching work and Pipe Laying 1 day Thu 4/22/10 Thu 4/22/10

61 Fit-up and Alignment Including Inspection 1 day Fri 4/23/10 Fri 4/23/10

62 Welding 4 days Sat 4/24/10 Tue 4/27/10

63 Welding Inspection (NDE) 1 day Wed 4/28/10 Wed 4/28/10

64 Field Joint Painting and Touch-up Paint 2 days Thu 4/29/10 Fri 4/30/10

65 Painting Inspection 1 day Sat 5/1/10 Sat 5/1/10

66 Release Backfilling 0 days Sat 5/1/10 Sat 5/1/10

67 Spool Piece No 30-030R+30-029R 10 days Fri 4/23/10 Sun 5/2/10

68 Check and Confirm Trenching work and Pipe Laying 1 day Fri 4/23/10 Fri 4/23/10

69 Fit-up and Alignment Including Inspection 1 day Sat 4/24/10 Sat 4/24/10

70 Welding 4 days Sun 4/25/10 Wed 4/28/10

71 Welding Inspection (NDE) 1 day Thu 4/29/10 Thu 4/29/10

72 Field Joint Painting and Touch-up Paint 2 days Fri 4/30/10 Sat 5/1/10

73 Painting Inspection 1 day Sun 5/2/10 Sun 5/2/10

74 Release Backfilling 0 days Sun 5/2/10 Sun 5/2/10

75 Spool Piece No 30-029R+30-028R 10 days Sat 4/24/10 Mon 5/3/10

76 Check and Confirm Trenching work and Pipe Laying 1 day Sat 4/24/10 Sat 4/24/10

77 Fit-up and Alignment Including Inspection 1 day Sun 4/25/10 Sun 4/25/10

78 Welding 4 days Mon 4/26/10 Thu 4/29/10

79 Welding Inspection (NDE) 1 day Fri 4/30/10 Fri 4/30/10

80 Field Joint Painting and Touch-up Paint 2 days Sat 5/1/10 Sun 5/2/10

81 Painting Inspection 1 day Mon 5/3/10 Mon 5/3/10

82 Release Backfilling 0 days Mon 5/3/10 Mon 5/3/10

4/15 9/150%

4/15 6/9

4/15 4/24

4/15

4/24

4/16 4/25

4/16

4/25

4/17 4/26

4/17

4/26

4/18 4/27

4/18

4/27

4/19 4/28

4/19

4/28

4/20 4/29

4/20

4/29

4/21 4/30

4/21

4/30

4/22 5/1

4/22

5/1

4/23 5/2

4/23

5/2

4/24 5/3

4/24

5/3

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 1

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 31: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

83 Spool Piece No 30-028R+30-027R 10 days Sun 4/25/10 Tue 5/4/10

84 Check and Confirm Trenching work and Pipe Laying 1 day Sun 4/25/10 Sun 4/25/10

85 Fit-up and Alignment Including Inspection 1 day Mon 4/26/10 Mon 4/26/10

86 Welding 4 days Tue 4/27/10 Fri 4/30/10

87 Welding Inspection (NDE) 1 day Sat 5/1/10 Sat 5/1/10

88 Field Joint Painting and Touch-up Paint 2 days Sun 5/2/10 Mon 5/3/10

89 Painting Inspection 1 day Tue 5/4/10 Tue 5/4/10

90 Release Backfilling 0 days Tue 5/4/10 Tue 5/4/10

91 Spool Piece No 30-027R+30-026R 10 days Mon 4/26/10 Wed 5/5/10

92 Check and Confirm Trenching work and Pipe Laying 1 day Mon 4/26/10 Mon 4/26/10

93 Fit-up and Alignment Including Inspection 1 day Tue 4/27/10 Tue 4/27/10

94 Welding 4 days Wed 4/28/10 Sat 5/1/10

95 Welding Inspection (NDE) 1 day Sun 5/2/10 Sun 5/2/10

96 Field Joint Painting and Touch-up Paint 2 days Mon 5/3/10 Tue 5/4/10

97 Painting Inspection 1 day Wed 5/5/10 Wed 5/5/10

98 Release Backfilling 0 days Wed 5/5/10 Wed 5/5/10

99 Spool Piece No 30-026R+30-025R 10 days Tue 4/27/10 Thu 5/6/10

100 Check and Confirm Trenching work and Pipe Laying 1 day Tue 4/27/10 Tue 4/27/10

101 Fit-up and Alignment Including Inspection 1 day Wed 4/28/10 Wed 4/28/10

102 Welding 4 days Thu 4/29/10 Sun 5/2/10

103 Welding Inspection (NDE) 1 day Mon 5/3/10 Mon 5/3/10

104 Field Joint Painting and Touch-up Paint 2 days Tue 5/4/10 Wed 5/5/10

105 Painting Inspection 1 day Thu 5/6/10 Thu 5/6/10

106 Release Backfilling 0 days Thu 5/6/10 Thu 5/6/10

107 Spool Piece No 30-025R+30-024R 10 days Wed 4/28/10 Fri 5/7/10

108 Check and Confirm Trenching work and Pipe Laying 1 day Wed 4/28/10 Wed 4/28/10

109 Fit-up and Alignment Including Inspection 1 day Thu 4/29/10 Thu 4/29/10

110 Welding 4 days Fri 4/30/10 Mon 5/3/10

111 Welding Inspection (NDE) 1 day Tue 5/4/10 Tue 5/4/10

112 Field Joint Painting and Touch-up Paint 2 days Wed 5/5/10 Thu 5/6/10

113 Painting Inspection 1 day Fri 5/7/10 Fri 5/7/10

114 Release Backfilling 0 days Fri 5/7/10 Fri 5/7/10

115 Spool Piece No 30-024R+30-023R 10 days Thu 4/29/10 Sat 5/8/10

116 Check and Confirm Trenching work and Pipe Laying 1 day Thu 4/29/10 Thu 4/29/10

117 Fit-up and Alignment Including Inspection 1 day Fri 4/30/10 Fri 4/30/10

118 Welding 4 days Sat 5/1/10 Tue 5/4/10

119 Welding Inspection (NDE) 1 day Wed 5/5/10 Wed 5/5/10

120 Field Joint Painting and Touch-up Paint 2 days Thu 5/6/10 Fri 5/7/10

121 Painting Inspection 1 day Sat 5/8/10 Sat 5/8/10

122 Release Backfilling 0 days Sat 5/8/10 Sat 5/8/10

123 Spool Piece No 30-023R+30-022R 10 days Fri 4/30/10 Sun 5/9/10

124 Check and Confirm Trenching work and Pipe Laying 1 day Fri 4/30/10 Fri 4/30/10

125 Fit-up and Alignment Including Inspection 1 day Sat 5/1/10 Sat 5/1/10

126 Welding 4 days Sun 5/2/10 Wed 5/5/10

127 Welding Inspection (NDE) 1 day Thu 5/6/10 Thu 5/6/10

128 Field Joint Painting and Touch-up Paint 2 days Fri 5/7/10 Sat 5/8/10

129 Painting Inspection 1 day Sun 5/9/10 Sun 5/9/10

130 Release Backfilling 0 days Sun 5/9/10 Sun 5/9/10

131 Spool Piece No 30-022R+30-021R 10 days Sat 5/1/10 Mon 5/10/10

132 Check and Confirm Trenching work and Pipe Laying 1 day Sat 5/1/10 Sat 5/1/10

133 Fit-up and Alignment Including Inspection 1 day Sun 5/2/10 Sun 5/2/10

134 Welding 4 days Mon 5/3/10 Thu 5/6/10

135 Welding Inspection (NDE) 1 day Fri 5/7/10 Fri 5/7/10

136 Field Joint Painting and Touch-up Paint 2 days Sat 5/8/10 Sun 5/9/10

137 Painting Inspection 1 day Mon 5/10/10 Mon 5/10/10

138 Release Backfilling 0 days Mon 5/10/10 Mon 5/10/10

139 Spool Piece No 30-021R+30-020R 10 days Sun 5/2/10 Tue 5/11/10

140 Check and Confirm Trenching work and Pipe Laying 1 day Sun 5/2/10 Sun 5/2/10

141 Fit-up and Alignment Including Inspection 1 day Mon 5/3/10 Mon 5/3/10

142 Welding 4 days Tue 5/4/10 Fri 5/7/10

143 Welding Inspection (NDE) 1 day Sat 5/8/10 Sat 5/8/10

144 Field Joint Painting and Touch-up Paint 2 days Sun 5/9/10 Mon 5/10/10

145 Painting Inspection 1 day Tue 5/11/10 Tue 5/11/10

146 Release Backfilling 0 days Tue 5/11/10 Tue 5/11/10

147 Spool Piece No 30-020R+30-019R 10 days Mon 5/3/10 Wed 5/12/10

148 Check and Confirm Trenching work and Pipe Laying 1 day Mon 5/3/10 Mon 5/3/10

149 Fit-up and Alignment Including Inspection 1 day Tue 5/4/10 Tue 5/4/10

150 Welding 4 days Wed 5/5/10 Sat 5/8/10

151 Welding Inspection (NDE) 1 day Sun 5/9/10 Sun 5/9/10

152 Field Joint Painting and Touch-up Paint 2 days Mon 5/10/10 Tue 5/11/10

153 Painting Inspection 1 day Wed 5/12/10 Wed 5/12/10

154 Release Backfilling 0 days Wed 5/12/10 Wed 5/12/10

155 Spool Piece No 30-019R+30-018R 10 days Tue 5/4/10 Thu 5/13/10

156 Check and Confirm Trenching work and Pipe Laying 1 day Tue 5/4/10 Tue 5/4/10

157 Fit-up and Alignment Including Inspection 1 day Wed 5/5/10 Wed 5/5/10

158 Welding 4 days Thu 5/6/10 Sun 5/9/10

159 Welding Inspection (NDE) 1 day Mon 5/10/10 Mon 5/10/10

160 Field Joint Painting and Touch-up Paint 2 days Tue 5/11/10 Wed 5/12/10

161 Painting Inspection 1 day Thu 5/13/10 Thu 5/13/10

162 Release Backfilling 0 days Thu 5/13/10 Thu 5/13/10

163 Spool Piece No 30-018R+30-017R 10 days Wed 5/5/10 Fri 5/14/10

164 Check and Confirm Trenching work and Pipe Laying 1 day Wed 5/5/10 Wed 5/5/10

4/25 5/4

4/25

5/4

4/26 5/5

4/26

5/5

4/27 5/6

4/27

5/6

4/28 5/7

4/28

5/7

4/29 5/8

4/29

5/8

4/30 5/9

4/30

5/9

5/1 5/10

5/1

5/10

5/2 5/11

5/2

5/11

5/3 5/12

5/3

5/12

5/4 5/13

5/4

5/13

5/5 5/14

5/5

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 2

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 32: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

165 Fit-up and Alignment Including Inspection 1 day Thu 5/6/10 Thu 5/6/10

166 Welding 4 days Fri 5/7/10 Mon 5/10/10

167 Welding Inspection (NDE) 1 day Tue 5/11/10 Tue 5/11/10

168 Field Joint Painting and Touch-up Paint 2 days Wed 5/12/10 Thu 5/13/10

169 Painting Inspection 1 day Fri 5/14/10 Fri 5/14/10

170 Release Backfilling 0 days Fri 5/14/10 Fri 5/14/10

171 Spool Piece No 30-017R+30-016R 10 days Thu 5/6/10 Sat 5/15/10

172 Check and Confirm Trenching work and Pipe Laying 1 day Thu 5/6/10 Thu 5/6/10

173 Fit-up and Alignment Including Inspection 1 day Fri 5/7/10 Fri 5/7/10

174 Welding 4 days Sat 5/8/10 Tue 5/11/10

175 Welding Inspection (NDE) 1 day Wed 5/12/10 Wed 5/12/10

176 Field Joint Painting and Touch-up Paint 2 days Thu 5/13/10 Fri 5/14/10

177 Painting Inspection 1 day Sat 5/15/10 Sat 5/15/10

178 Release Backfilling 0 days Sat 5/15/10 Sat 5/15/10

179 Spool Piece No 30-016R+30-015R 10 days Fri 5/7/10 Sun 5/16/10

180 Check and Confirm Trenching work and Pipe Laying 1 day Fri 5/7/10 Fri 5/7/10

181 Fit-up and Alignment Including Inspection 1 day Sat 5/8/10 Sat 5/8/10

182 Welding 4 days Sun 5/9/10 Wed 5/12/10

183 Welding Inspection (NDE) 1 day Thu 5/13/10 Thu 5/13/10

184 Field Joint Painting and Touch-up Paint 2 days Fri 5/14/10 Sat 5/15/10

185 Painting Inspection 1 day Sun 5/16/10 Sun 5/16/10

186 Release Backfilling 0 days Sun 5/16/10 Sun 5/16/10

187 Spool Piece No 30-015R+30-014R 10 days Sat 5/8/10 Mon 5/17/10

188 Check and Confirm Trenching work and Pipe Laying 1 day Sat 5/8/10 Sat 5/8/10

189 Fit-up and Alignment Including Inspection 1 day Sun 5/9/10 Sun 5/9/10

190 Welding 4 days Mon 5/10/10 Thu 5/13/10

191 Welding Inspection (NDE) 1 day Fri 5/14/10 Fri 5/14/10

192 Field Joint Painting and Touch-up Paint 2 days Sat 5/15/10 Sun 5/16/10

193 Painting Inspection 1 day Mon 5/17/10 Mon 5/17/10

194 Release Backfilling 0 days Mon 5/17/10 Mon 5/17/10

195 Spool Piece No 30-038R+30-039R 10 days Sun 5/9/10 Tue 5/18/10

196 Check and Confirm Trenching work and Pipe Laying 1 day Sun 5/9/10 Sun 5/9/10

197 Fit-up and Alignment Including Inspection 1 day Mon 5/10/10 Mon 5/10/10

198 Welding 4 days Tue 5/11/10 Fri 5/14/10

199 Welding Inspection (NDE) 1 day Sat 5/15/10 Sat 5/15/10

200 Field Joint Painting and Touch-up Paint 2 days Sun 5/16/10 Mon 5/17/10

201 1 day Tue 5/18/10 Tue 5/18/10

202 Spool Piece No 30-053S+30-054S 10 days Mon 5/10/10 Wed 5/19/10

203 Check and Confirm Trenching work and Pipe Laying 1 day Mon 5/10/10 Mon 5/10/10

204 Fit-up and Alignment Including Inspection 1 day Tue 5/11/10 Tue 5/11/10

205 Welding 4 days Wed 5/12/10 Sat 5/15/10

206 Welding Inspection (NDE) 1 day Sun 5/16/10 Sun 5/16/10

207 Field Joint Painting and Touch-up Paint 2 days Mon 5/17/10 Tue 5/18/10

208 Painting Inspection 1 day Wed 5/19/10 Wed 5/19/10

209 Release Backfilling 0 days Wed 5/19/10 Wed 5/19/10

210 Spool Piece No 30-054S+30-055S 10 days Tue 5/11/10 Thu 5/20/10

211 Check and Confirm Trenching work and Pipe Laying 1 day Tue 5/11/10 Tue 5/11/10

212 Fit-up and Alignment Including Inspection 1 day Wed 5/12/10 Wed 5/12/10

213 Welding 4 days Thu 5/13/10 Sun 5/16/10

214 Welding Inspection (NDE) 1 day Mon 5/17/10 Mon 5/17/10

215 Field Joint Painting and Touch-up Paint 2 days Tue 5/18/10 Wed 5/19/10

216 Painting Inspection 1 day Thu 5/20/10 Thu 5/20/10

217 Release Backfilling 0 days Thu 5/20/10 Thu 5/20/10

218 Spool Piece No 30-055S+30-056S 10 days Wed 5/12/10 Fri 5/21/10

219 Check and Confirm Trenching work and Pipe Laying 1 day Wed 5/12/10 Wed 5/12/10

220 Fit-up and Alignment Including Inspection 1 day Thu 5/13/10 Thu 5/13/10

221 Welding 4 days Fri 5/14/10 Mon 5/17/10

222 Welding Inspection (NDE) 1 day Tue 5/18/10 Tue 5/18/10

223 Field Joint Painting and Touch-up Paint 2 days Wed 5/19/10 Thu 5/20/10

224 Painting Inspection 1 day Fri 5/21/10 Fri 5/21/10

225 Release Backfilling 0 days Fri 5/21/10 Fri 5/21/10

226 Spool Piece No 30-056S+30-057S 10 days Thu 5/13/10 Sat 5/22/10

227 Check and Confirm Trenching work and Pipe Laying 1 day Thu 5/13/10 Thu 5/13/10

228 Fit-up and Alignment Including Inspection 1 day Fri 5/14/10 Fri 5/14/10

229 Welding 4 days Sat 5/15/10 Tue 5/18/10

230 Welding Inspection (NDE) 1 day Wed 5/19/10 Wed 5/19/10

231 Field Joint Painting and Touch-up Paint 2 days Thu 5/20/10 Fri 5/21/10

232 Painting Inspection 1 day Sat 5/22/10 Sat 5/22/10

233 Release Backfilling 0 days Sat 5/22/10 Sat 5/22/10

234 Spool Piece No 30-057S+30-058S 10 days Fri 5/14/10 Sun 5/23/10

235 Check and Confirm Trenching work and Pipe Laying 1 day Fri 5/14/10 Fri 5/14/10

236 Fit-up and Alignment Including Inspection 1 day Sat 5/15/10 Sat 5/15/10

237 Welding 4 days Sun 5/16/10 Wed 5/19/10

238 Welding Inspection (NDE) 1 day Thu 5/20/10 Thu 5/20/10

239 Field Joint Painting and Touch-up Paint 2 days Fri 5/21/10 Sat 5/22/10

240 Painting Inspection 1 day Sun 5/23/10 Sun 5/23/10

241 Release Backfilling 0 days Sun 5/23/10 Sun 5/23/10

242 Spool Piece No 30-058S+30-059S 10 days Sat 5/15/10 Mon 5/24/10

243 Check and Confirm Trenching work and Pipe Laying 1 day Sat 5/15/10 Sat 5/15/10

244 Fit-up and Alignment Including Inspection 1 day Sun 5/16/10 Sun 5/16/10

245 Welding 4 days Mon 5/17/10 Thu 5/20/10

246 Welding Inspection (NDE) 1 day Fri 5/21/10 Fri 5/21/10

5/14

5/6 5/15

5/6

5/15

5/7 5/16

5/7

5/16

5/8 5/17

5/8

5/17

5/9 5/18

0

Painting Inspection

5/10 5/19

5/10

5/19

5/11 5/20

5/11

5/20

5/12 5/21

5/12

5/21

5/13 5/22

5/13

5/22

5/14 5/23

5/14

5/23

5/15 5/24

5/15

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 3

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 33: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

247 Field Joint Painting and Touch-up Paint 2 days Sat 5/22/10 Sun 5/23/10

248 Painting Inspection 1 day Mon 5/24/10 Mon 5/24/10

249 Release Backfilling 0 days Mon 5/24/10 Mon 5/24/10

250 Spool Piece No 30-059S+30-060S 10 days Sun 5/16/10 Tue 5/25/10

251 Check and Confirm Trenching work and Pipe Laying 1 day Sun 5/16/10 Sun 5/16/10

252 Fit-up and Alignment Including Inspection 1 day Mon 5/17/10 Mon 5/17/10

253 Welding 4 days Tue 5/18/10 Fri 5/21/10

254 Welding Inspection (NDE) 1 day Sat 5/22/10 Sat 5/22/10

255 Field Joint Painting and Touch-up Paint 2 days Sun 5/23/10 Mon 5/24/10

256 Painting Inspection 1 day Tue 5/25/10 Tue 5/25/10

257 Release Backfilling 0 days Tue 5/25/10 Tue 5/25/10

258 Spool Piece No 30-060S+30-061S 10 days Mon 5/17/10 Wed 5/26/10

259 Check and Confirm Trenching work and Pipe Laying 1 day Mon 5/17/10 Mon 5/17/10

260 Fit-up and Alignment Including Inspection 1 day Tue 5/18/10 Tue 5/18/10

261 Welding 4 days Wed 5/19/10 Sat 5/22/10

262 Welding Inspection (NDE) 1 day Sun 5/23/10 Sun 5/23/10

263 Field Joint Painting and Touch-up Paint 2 days Mon 5/24/10 Tue 5/25/10

264 Painting Inspection 1 day Wed 5/26/10 Wed 5/26/10

265 Release Backfilling 0 days Wed 5/26/10 Wed 5/26/10

266 Spool Piece No 30-061S+30-062S 10 days Tue 5/18/10 Thu 5/27/10

267 Check and Confirm Trenching work and Pipe Laying 1 day Tue 5/18/10 Tue 5/18/10

268 Fit-up and Alignment Including Inspection 1 day Wed 5/19/10 Wed 5/19/10

269 Welding 4 days Thu 5/20/10 Sun 5/23/10

270 Welding Inspection (NDE) 1 day Mon 5/24/10 Mon 5/24/10

271 Field Joint Painting and Touch-up Paint 2 days Tue 5/25/10 Wed 5/26/10

272 Painting Inspection 1 day Thu 5/27/10 Thu 5/27/10

273 Release Backfilling 0 days Thu 5/27/10 Thu 5/27/10

274 Spool Piece No 30-062S+30-063S 10 days Wed 5/19/10 Fri 5/28/10

275 Check and Confirm Trenching work and Pipe Laying 1 day Wed 5/19/10 Wed 5/19/10

276 Fit-up and Alignment Including Inspection 1 day Thu 5/20/10 Thu 5/20/10

277 Welding 4 days Fri 5/21/10 Mon 5/24/10

278 Welding Inspection (NDE) 1 day Tue 5/25/10 Tue 5/25/10

279 Field Joint Painting and Touch-up Paint 2 days Wed 5/26/10 Thu 5/27/10

280 Painting Inspection 1 day Fri 5/28/10 Fri 5/28/10

281 Release Backfilling 0 days Fri 5/28/10 Fri 5/28/10

282 Spool Piece No 30-063S+30-064S 10 days Thu 5/20/10 Sat 5/29/10

283 Check and Confirm Trenching work and Pipe Laying 1 day Thu 5/20/10 Thu 5/20/10

284 Fit-up and Alignment Including Inspection 1 day Fri 5/21/10 Fri 5/21/10

285 Welding 4 days Sat 5/22/10 Tue 5/25/10

286 Welding Inspection (NDE) 1 day Wed 5/26/10 Wed 5/26/10

287 Field Joint Painting and Touch-up Paint 2 days Thu 5/27/10 Fri 5/28/10

288 Painting Inspection 1 day Sat 5/29/10 Sat 5/29/10

289 Release Backfilling 0 days Sat 5/29/10 Sat 5/29/10

290 Spool Piece No 30-064S+30-065S 10 days Fri 5/21/10 Sun 5/30/10

291 Check and Confirm Trenching work and Pipe Laying 1 day Fri 5/21/10 Fri 5/21/10

292 Fit-up and Alignment Including Inspection 1 day Sat 5/22/10 Sat 5/22/10

293 Welding 4 days Sun 5/23/10 Wed 5/26/10

294 Welding Inspection (NDE) 1 day Thu 5/27/10 Thu 5/27/10

295 Field Joint Painting and Touch-up Paint 2 days Fri 5/28/10 Sat 5/29/10

296 Painting Inspection 1 day Sun 5/30/10 Sun 5/30/10

297 Release Backfilling 0 days Sun 5/30/10 Sun 5/30/10

298 Spool Piece No 30-065S+30-066S 10 days Sat 5/22/10 Mon 5/31/10

299 Check and Confirm Trenching work and Pipe Laying 1 day Sat 5/22/10 Sat 5/22/10

300 Fit-up and Alignment Including Inspection 1 day Sun 5/23/10 Sun 5/23/10

301 Welding 4 days Mon 5/24/10 Thu 5/27/10

302 Welding Inspection (NDE) 1 day Fri 5/28/10 Fri 5/28/10

303 Field Joint Painting and Touch-up Paint 2 days Sat 5/29/10 Sun 5/30/10

304 Painting Inspection 1 day Mon 5/31/10 Mon 5/31/10

305 Release Backfilling 0 days Mon 5/31/10 Mon 5/31/10

306 Spool Piece No 30-066S+30-067S 10 days Sun 5/23/10 Tue 6/1/10

307 Check and Confirm Trenching work and Pipe Laying 1 day Sun 5/23/10 Sun 5/23/10

308 Fit-up and Alignment Including Inspection 1 day Mon 5/24/10 Mon 5/24/10

309 Welding 4 days Tue 5/25/10 Fri 5/28/10

310 Welding Inspection (NDE) 1 day Sat 5/29/10 Sat 5/29/10

311 Field Joint Painting and Touch-up Paint 2 days Sun 5/30/10 Mon 5/31/10

312 Painting Inspection 1 day Tue 6/1/10 Tue 6/1/10

313 Release Backfilling 0 days Tue 6/1/10 Tue 6/1/10

314 Spool Piece No 30-067S+30-068S 10 days Mon 5/24/10 Wed 6/2/10

315 Check and Confirm Trenching work and Pipe Laying 1 day Mon 5/24/10 Mon 5/24/10

316 Fit-up and Alignment Including Inspection 1 day Tue 5/25/10 Tue 5/25/10

317 Welding 4 days Wed 5/26/10 Sat 5/29/10

318 Welding Inspection (NDE) 1 day Sun 5/30/10 Sun 5/30/10

319 Field Joint Painting and Touch-up Paint 2 days Mon 5/31/10 Tue 6/1/10

320 Painting Inspection 1 day Wed 6/2/10 Wed 6/2/10

321 Release Backfilling 0 days Wed 6/2/10 Wed 6/2/10

322 Spool Piece No 30-068S+30-069S 10 days Tue 5/25/10 Thu 6/3/10

323 Check and Confirm Trenching work and Pipe Laying 1 day Tue 5/25/10 Tue 5/25/10

324 Fit-up and Alignment Including Inspection 1 day Wed 5/26/10 Wed 5/26/10

325 Welding 4 days Thu 5/27/10 Sun 5/30/10

326 Welding Inspection (NDE) 1 day Mon 5/31/10 Mon 5/31/10

327 Field Joint Painting and Touch-up Paint 2 days Tue 6/1/10 Wed 6/2/10

328 Painting Inspection 1 day Thu 6/3/10 Thu 6/3/10

5/24

5/16 5/25

5/16

5/25

5/17 5/26

5/17

5/26

5/18 5/27

5/18

5/27

5/19 5/28

5/19

5/28

5/20 5/29

5/20

5/29

5/21 5/30

5/21

5/30

5/22 5/31

5/22

5/31

5/23 6/1

5/23

6/1

5/24 6/2

5/24

6/2

5/25 6/3

5/25

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 4

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 34: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

329 Release Backfilling 0 days Thu 6/3/10 Thu 6/3/10

330 Spool Piece No 30-069S+30-070S 10 days Wed 5/26/10 Fri 6/4/10

331 Check and Confirm Trenching work and Pipe Laying 1 day Wed 5/26/10 Wed 5/26/10

332 Fit-up and Alignment Including Inspection 1 day Thu 5/27/10 Thu 5/27/10

333 Welding 4 days Fri 5/28/10 Mon 5/31/10

334 Welding Inspection (NDE) 1 day Tue 6/1/10 Tue 6/1/10

335 Field Joint Painting and Touch-up Paint 2 days Wed 6/2/10 Thu 6/3/10

336 Painting Inspection 1 day Fri 6/4/10 Fri 6/4/10

337 Release Backfilling 0 days Fri 6/4/10 Fri 6/4/10

338 Spool Piece No 30-070S+30-071S 10 days Thu 5/27/10 Sat 6/5/10

339 Check and Confirm Trenching work and Pipe Laying 1 day Thu 5/27/10 Thu 5/27/10

340 Fit-up and Alignment Including Inspection 1 day Fri 5/28/10 Fri 5/28/10

341 Welding 4 days Sat 5/29/10 Tue 6/1/10

342 Welding Inspection (NDE) 1 day Wed 6/2/10 Wed 6/2/10

343 Field Joint Painting and Touch-up Paint 2 days Thu 6/3/10 Fri 6/4/10

344 Painting Inspection 1 day Sat 6/5/10 Sat 6/5/10

345 Release Backfilling 0 days Sat 6/5/10 Sat 6/5/10

346 Spool Piece No 30-071S+30-072S 10 days Fri 5/28/10 Sun 6/6/10

347 Check and Confirm Trenching work and Pipe Laying 1 day Fri 5/28/10 Fri 5/28/10

348 Fit-up and Alignment Including Inspection 1 day Sat 5/29/10 Sat 5/29/10

349 Welding 4 days Sun 5/30/10 Wed 6/2/10

350 Welding Inspection (NDE) 1 day Thu 6/3/10 Thu 6/3/10

351 Field Joint Painting and Touch-up Paint 2 days Fri 6/4/10 Sat 6/5/10

352 Painting Inspection 1 day Sun 6/6/10 Sun 6/6/10

353 Release Backfilling 0 days Sun 6/6/10 Sun 6/6/10

354 Spool Piece No 30-072S+30-073S 10 days Sat 5/29/10 Mon 6/7/10

355 Check and Confirm Trenching work and Pipe Laying 1 day Sat 5/29/10 Sat 5/29/10

356 Fit-up and Alignment Including Inspection 1 day Sun 5/30/10 Sun 5/30/10

357 Welding 4 days Mon 5/31/10 Thu 6/3/10

358 Welding Inspection (NDE) 1 day Fri 6/4/10 Fri 6/4/10

359 Field Joint Painting and Touch-up Paint 2 days Sat 6/5/10 Sun 6/6/10

360 Painting Inspection 1 day Mon 6/7/10 Mon 6/7/10

361 Release Backfilling 0 days Mon 6/7/10 Mon 6/7/10

362 Spool Piece No 30-073S+30-074S 10 days Sun 5/30/10 Tue 6/8/10

363 Check and Confirm Trenching work and Pipe Laying 1 day Sun 5/30/10 Sun 5/30/10

364 Fit-up and Alignment Including Inspection 1 day Mon 5/31/10 Mon 5/31/10

365 Welding 4 days Tue 6/1/10 Fri 6/4/10

366 Welding Inspection (NDE) 1 day Sat 6/5/10 Sat 6/5/10

367 Field Joint Painting and Touch-up Paint 2 days Sun 6/6/10 Mon 6/7/10

368 Painting Inspection 1 day Tue 6/8/10 Tue 6/8/10

369 Release Backfilling 0 days Tue 6/8/10 Tue 6/8/10

370 Spool Piece No 30-074S+30-075S 10 days Mon 5/31/10 Wed 6/9/10

371 Check and Confirm Trenching work and Pipe Laying 1 day Mon 5/31/10 Mon 5/31/10

372 Fit-up and Alignment Including Inspection 1 day Tue 6/1/10 Tue 6/1/10

373 Welding 4 days Wed 6/2/10 Sat 6/5/10

374 Welding Inspection (NDE) 1 day Sun 6/6/10 Sun 6/6/10

375 Field Joint Painting and Touch-up Paint 2 days Mon 6/7/10 Tue 6/8/10

376 Painting Inspection 1 day Wed 6/9/10 Wed 6/9/10

377 Release Backfilling 0 days Wed 6/9/10 Wed 6/9/10

378 Zone #2 29 days Tue 6/8/10 Tue 7/6/10

379 Spool Piece No 30-033S+30-034S 10 days Tue 6/8/10 Thu 6/17/10

380 Check and Confirm Trenching work and Pipe Laying 1 day Tue 6/8/10 Tue 6/8/10

381 Fit-up and Alignment Including Inspection 1 day Wed 6/9/10 Wed 6/9/10

382 Welding 4 days Thu 6/10/10 Sun 6/13/10

383 Welding Inspection (NDE) 1 day Mon 6/14/10 Mon 6/14/10

384 Field Joint Painting and Touch-up Paint 2 days Tue 6/15/10 Wed 6/16/10

385 Painting Inspection 1 day Thu 6/17/10 Thu 6/17/10

386 Release Backfilling 0 days Thu 6/17/10 Thu 6/17/10

387 Spool Piece No 30-034S+30-035S 10 days Wed 6/9/10 Fri 6/18/10

388 Check and Confirm Trenching work and Pipe Laying 1 day Wed 6/9/10 Wed 6/9/10

389 Fit-up and Alignment Including Inspection 1 day Thu 6/10/10 Thu 6/10/10

390 Welding 4 days Fri 6/11/10 Mon 6/14/10

391 Welding Inspection (NDE) 1 day Tue 6/15/10 Tue 6/15/10

392 Field Joint Painting and Touch-up Paint 2 days Wed 6/16/10 Thu 6/17/10

393 Painting Inspection 1 day Fri 6/18/10 Fri 6/18/10

394 Release Backfilling 0 days Fri 6/18/10 Fri 6/18/10

395 Spool Piece No 30-035S+30-036S 10 days Thu 6/10/10 Sat 6/19/10

396 Check and Confirm Trenching work and Pipe Laying 1 day Thu 6/10/10 Thu 6/10/10

397 Fit-up and Alignment Including Inspection 1 day Fri 6/11/10 Fri 6/11/10

398 Welding 4 days Sat 6/12/10 Tue 6/15/10

399 Welding Inspection (NDE) 1 day Wed 6/16/10 Wed 6/16/10

400 Field Joint Painting and Touch-up Paint 2 days Thu 6/17/10 Fri 6/18/10

401 Painting Inspection 1 day Sat 6/19/10 Sat 6/19/10

402 Release Backfilling 0 days Sat 6/19/10 Sat 6/19/10

403 Spool Piece No 30-036S+30-037S 10 days Fri 6/11/10 Sun 6/20/10

404 Check and Confirm Trenching work and Pipe Laying 1 day Fri 6/11/10 Fri 6/11/10

405 Fit-up and Alignment Including Inspection 1 day Sat 6/12/10 Sat 6/12/10

406 Welding 4 days Sun 6/13/10 Wed 6/16/10

407 Welding Inspection (NDE) 1 day Thu 6/17/10 Thu 6/17/10

408 Field Joint Painting and Touch-up Paint 2 days Fri 6/18/10 Sat 6/19/10

409 Painting Inspection 1 day Sun 6/20/10 Sun 6/20/10

410 Release Backfilling 0 days Sun 6/20/10 Sun 6/20/10

6/3

5/26 6/4

5/26

6/4

5/27 6/5

5/27

6/5

5/28 6/6

5/28

6/6

5/29 6/7

5/29

6/7

5/30 6/8

5/30

6/8

5/31 6/9

5/31

6/9

6/8 7/6

6/8 6/17

6/8

6/17

6/9 6/18

6/9

6/18

6/10 6/19

6/10

6/19

6/11 6/20

6/11

6/20

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 5

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 35: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

411 Spool Piece No 30-037S+30-038S 10 days Sat 6/12/10 Mon 6/21/10

412 Check and Confirm Trenching work and Pipe Laying 1 day Sat 6/12/10 Sat 6/12/10

413 Fit-up and Alignment Including Inspection 1 day Sun 6/13/10 Sun 6/13/10

414 Welding 4 days Mon 6/14/10 Thu 6/17/10

415 Welding Inspection (NDE) 1 day Fri 6/18/10 Fri 6/18/10

416 Field Joint Painting and Touch-up Paint 2 days Sat 6/19/10 Sun 6/20/10

417 Painting Inspection 1 day Mon 6/21/10 Mon 6/21/10

418 Release Backfilling 0 days Mon 6/21/10 Mon 6/21/10

419 Spool Piece No 30-038S+30-039S 10 days Sun 6/13/10 Tue 6/22/10

420 Check and Confirm Trenching work and Pipe Laying 1 day Sun 6/13/10 Sun 6/13/10

421 Fit-up and Alignment Including Inspection 1 day Mon 6/14/10 Mon 6/14/10

422 Welding 4 days Tue 6/15/10 Fri 6/18/10

423 Welding Inspection (NDE) 1 day Sat 6/19/10 Sat 6/19/10

424 Field Joint Painting and Touch-up Paint 2 days Sun 6/20/10 Mon 6/21/10

425 Painting Inspection 1 day Tue 6/22/10 Tue 6/22/10

426 Release Backfilling 0 days Tue 6/22/10 Tue 6/22/10

427 Spool Piece No 30-039S+30-040S 10 days Mon 6/14/10 Wed 6/23/10

428 Check and Confirm Trenching work and Pipe Laying 1 day Mon 6/14/10 Mon 6/14/10

429 Fit-up and Alignment Including Inspection 1 day Tue 6/15/10 Tue 6/15/10

430 Welding 4 days Wed 6/16/10 Sat 6/19/10

431 Welding Inspection (NDE) 1 day Sun 6/20/10 Sun 6/20/10

432 Field Joint Painting and Touch-up Paint 2 days Mon 6/21/10 Tue 6/22/10

433 Painting Inspection 1 day Wed 6/23/10 Wed 6/23/10

434 Release Backfilling 0 days Wed 6/23/10 Wed 6/23/10

435 Spool Piece No 30-040S+30-041S 10 days Tue 6/15/10 Thu 6/24/10

436 Check and Confirm Trenching work and Pipe Laying 1 day Tue 6/15/10 Tue 6/15/10

437 Fit-up and Alignment Including Inspection 1 day Wed 6/16/10 Wed 6/16/10

438 Welding 4 days Thu 6/17/10 Sun 6/20/10

439 Welding Inspection (NDE) 1 day Mon 6/21/10 Mon 6/21/10

440 Field Joint Painting and Touch-up Paint 2 days Tue 6/22/10 Wed 6/23/10

441 Painting Inspection 1 day Thu 6/24/10 Thu 6/24/10

442 Release Backfilling 0 days Thu 6/24/10 Thu 6/24/10

443 Spool Piece No 30-041S+30-042S 10 days Wed 6/16/10 Fri 6/25/10

444 Check and Confirm Trenching work and Pipe Laying 1 day Wed 6/16/10 Wed 6/16/10

445 Fit-up and Alignment Including Inspection 1 day Thu 6/17/10 Thu 6/17/10

446 Welding 4 days Fri 6/18/10 Mon 6/21/10

447 Welding Inspection (NDE) 1 day Tue 6/22/10 Tue 6/22/10

448 Field Joint Painting and Touch-up Paint 2 days Wed 6/23/10 Thu 6/24/10

449 Painting Inspection 1 day Fri 6/25/10 Fri 6/25/10

450 Release Backfilling 0 days Fri 6/25/10 Fri 6/25/10

451 Spool Piece No 30-042S+30-043S 10 days Thu 6/17/10 Sat 6/26/10

452 Check and Confirm Trenching work and Pipe Laying 1 day Thu 6/17/10 Thu 6/17/10

453 Fit-up and Alignment Including Inspection 1 day Fri 6/18/10 Fri 6/18/10

454 Welding 4 days Sat 6/19/10 Tue 6/22/10

455 Welding Inspection (NDE) 1 day Wed 6/23/10 Wed 6/23/10

456 Field Joint Painting and Touch-up Paint 2 days Thu 6/24/10 Fri 6/25/10

457 Painting Inspection 1 day Sat 6/26/10 Sat 6/26/10

458 Release Backfilling 0 days Sat 6/26/10 Sat 6/26/10

459 Spool Piece No 30-043S+30-044S 10 days Fri 6/18/10 Sun 6/27/10

460 Check and Confirm Trenching work and Pipe Laying 1 day Fri 6/18/10 Fri 6/18/10

461 Fit-up and Alignment Including Inspection 1 day Sat 6/19/10 Sat 6/19/10

462 Welding 4 days Sun 6/20/10 Wed 6/23/10

463 Welding Inspection (NDE) 1 day Thu 6/24/10 Thu 6/24/10

464 Field Joint Painting and Touch-up Paint 2 days Fri 6/25/10 Sat 6/26/10

465 Painting Inspection 1 day Sun 6/27/10 Sun 6/27/10

466 Release Backfilling 0 days Sun 6/27/10 Sun 6/27/10

467 Spool Piece No 30-044S+30-045S 10 days Sat 6/19/10 Mon 6/28/10

468 Check and Confirm Trenching work and Pipe Laying 1 day Sat 6/19/10 Sat 6/19/10

469 Fit-up and Alignment Including Inspection 1 day Sun 6/20/10 Sun 6/20/10

470 Welding 4 days Mon 6/21/10 Thu 6/24/10

471 Welding Inspection (NDE) 1 day Fri 6/25/10 Fri 6/25/10

472 Field Joint Painting and Touch-up Paint 2 days Sat 6/26/10 Sun 6/27/10

473 Painting Inspection 1 day Mon 6/28/10 Mon 6/28/10

474 Release Backfilling 0 days Mon 6/28/10 Mon 6/28/10

475 Spool Piece No 30-045S+30-046S 10 days Sun 6/20/10 Tue 6/29/10

476 Check and Confirm Trenching work and Pipe Laying 1 day Sun 6/20/10 Sun 6/20/10

477 Fit-up and Alignment Including Inspection 1 day Mon 6/21/10 Mon 6/21/10

478 Welding 4 days Tue 6/22/10 Fri 6/25/10

479 Welding Inspection (NDE) 1 day Sat 6/26/10 Sat 6/26/10

480 Field Joint Painting and Touch-up Paint 2 days Sun 6/27/10 Mon 6/28/10

481 Painting Inspection 1 day Tue 6/29/10 Tue 6/29/10

482 Release Backfilling 0 days Tue 6/29/10 Tue 6/29/10

483 Spool Piece No 30-046S+30-047S 10 days Mon 6/21/10 Wed 6/30/10

484 Check and Confirm Trenching work and Pipe Laying 1 day Mon 6/21/10 Mon 6/21/10

485 Fit-up and Alignment Including Inspection 1 day Tue 6/22/10 Tue 6/22/10

486 Welding 4 days Wed 6/23/10 Sat 6/26/10

487 Welding Inspection (NDE) 1 day Sun 6/27/10 Sun 6/27/10

488 Field Joint Painting and Touch-up Paint 2 days Mon 6/28/10 Tue 6/29/10

489 Painting Inspection 1 day Wed 6/30/10 Wed 6/30/10

490 Release Backfilling 0 days Wed 6/30/10 Wed 6/30/10

491 Spool Piece No 30-047S+30-048S 10 days Tue 6/22/10 Thu 7/1/10

492 Check and Confirm Trenching work and Pipe Laying 1 day Tue 6/22/10 Tue 6/22/10

6/12 6/21

6/12

6/21

6/13 6/22

6/13

6/22

6/14 6/23

6/14

6/23

6/15 6/24

6/15

6/24

6/16 6/25

6/16

6/25

6/17 6/26

6/17

6/26

6/18 6/27

6/18

6/27

6/19 6/28

6/19

6/28

6/20 6/29

6/20

6/29

6/21 6/30

6/21

6/30

6/22 7/1

6/22

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 6

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 36: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

493 Fit-up and Alignment Including Inspection 1 day Wed 6/23/10 Wed 6/23/10

494 Welding 4 days Thu 6/24/10 Sun 6/27/10

495 Welding Inspection (NDE) 1 day Mon 6/28/10 Mon 6/28/10

496 Field Joint Painting and Touch-up Paint 2 days Tue 6/29/10 Wed 6/30/10

497 Painting Inspection 1 day Thu 7/1/10 Thu 7/1/10

498 Release Backfilling 0 days Thu 7/1/10 Thu 7/1/10

499 Spool Piece No 30-048S+30-049S 10 days Wed 6/23/10 Fri 7/2/10

500 Check and Confirm Trenching work and Pipe Laying 1 day Wed 6/23/10 Wed 6/23/10

501 Fit-up and Alignment Including Inspection 1 day Thu 6/24/10 Thu 6/24/10

502 Welding 4 days Fri 6/25/10 Mon 6/28/10

503 Welding Inspection (NDE) 1 day Tue 6/29/10 Tue 6/29/10

504 Field Joint Painting and Touch-up Paint 2 days Wed 6/30/10 Thu 7/1/10

505 Painting Inspection 1 day Fri 7/2/10 Fri 7/2/10

506 Release Backfilling 0 days Fri 7/2/10 Fri 7/2/10

507 Spool Piece No 30-049S+30-050S 10 days Thu 6/24/10 Sat 7/3/10

508 Check and Confirm Trenching work and Pipe Laying 1 day Thu 6/24/10 Thu 6/24/10

509 Fit-up and Alignment Including Inspection 1 day Fri 6/25/10 Fri 6/25/10

510 Welding 4 days Sat 6/26/10 Tue 6/29/10

511 Welding Inspection (NDE) 1 day Wed 6/30/10 Wed 6/30/10

512 Field Joint Painting and Touch-up Paint 2 days Thu 7/1/10 Fri 7/2/10

513 Painting Inspection 1 day Sat 7/3/10 Sat 7/3/10

514 Release Backfilling 0 days Sat 7/3/10 Sat 7/3/10

515 Spool Piece No 30-050S+30-051S 10 days Fri 6/25/10 Sun 7/4/10

516 Check and Confirm Trenching work and Pipe Laying 1 day Fri 6/25/10 Fri 6/25/10

517 Fit-up and Alignment Including Inspection 1 day Sat 6/26/10 Sat 6/26/10

518 Welding 4 days Sun 6/27/10 Wed 6/30/10

519 Welding Inspection (NDE) 1 day Thu 7/1/10 Thu 7/1/10

520 Field Joint Painting and Touch-up Paint 2 days Fri 7/2/10 Sat 7/3/10

521 Painting Inspection 1 day Sun 7/4/10 Sun 7/4/10

522 Release Backfilling 0 days Sun 7/4/10 Sun 7/4/10

523 Spool Piece No 30-051S+30-052S 10 days Sat 6/26/10 Mon 7/5/10

524 Check and Confirm Trenching work and Pipe Laying 1 day Sat 6/26/10 Sat 6/26/10

525 Fit-up and Alignment Including Inspection 1 day Sun 6/27/10 Sun 6/27/10

526 Welding 4 days Mon 6/28/10 Thu 7/1/10

527 Welding Inspection (NDE) 1 day Fri 7/2/10 Fri 7/2/10

528 Field Joint Painting and Touch-up Paint 2 days Sat 7/3/10 Sun 7/4/10

529 Painting Inspection 1 day Mon 7/5/10 Mon 7/5/10

530 Release Backfilling 0 days Mon 7/5/10 Mon 7/5/10

531 Spool Piece No 30-052S+30-053S 10 days Sun 6/27/10 Tue 7/6/10

532 Check and Confirm Trenching work and Pipe Laying 1 day Sun 6/27/10 Sun 6/27/10

533 Fit-up and Alignment Including Inspection 1 day Mon 6/28/10 Mon 6/28/10

534 Welding 4 days Tue 6/29/10 Fri 7/2/10

535 Welding Inspection (NDE) 1 day Sat 7/3/10 Sat 7/3/10

536 Field Joint Painting and Touch-up Paint 2 days Sun 7/4/10 Mon 7/5/10

537 Painting Inspection 1 day Tue 7/6/10 Tue 7/6/10

538 Release Backfilling 0 days Tue 7/6/10 Tue 7/6/10

539 Zone #3 43 days Mon 6/28/10 Mon 8/9/10

540 Spool Piece No 30-014R+30-013R 10 days Mon 6/28/10 Wed 7/7/10

541 Check and Confirm Trenching work and Pipe Laying 1 day Mon 6/28/10 Mon 6/28/10

542 Fit-up and Alignment Including Inspection 1 day Tue 6/29/10 Tue 6/29/10

543 Welding 4 days Wed 6/30/10 Sat 7/3/10

544 Welding Inspection (NDE) 1 day Sun 7/4/10 Sun 7/4/10

545 Field Joint Painting and Touch-up Paint 2 days Mon 7/5/10 Tue 7/6/10

546 Painting Inspection 1 day Wed 7/7/10 Wed 7/7/10

547 Release Backfilling 0 days Wed 7/7/10 Wed 7/7/10

548 Spool Piece No 30-013R+30-012R 10 days Tue 6/29/10 Thu 7/8/10

549 Check and Confirm Trenching work and Pipe Laying 1 day Tue 6/29/10 Tue 6/29/10

550 Fit-up and Alignment Including Inspection 1 day Wed 6/30/10 Wed 6/30/10

551 Welding 4 days Thu 7/1/10 Sun 7/4/10

552 Welding Inspection (NDE) 1 day Mon 7/5/10 Mon 7/5/10

553 Field Joint Painting and Touch-up Paint 2 days Tue 7/6/10 Wed 7/7/10

554 Painting Inspection 1 day Thu 7/8/10 Thu 7/8/10

555 Release Backfilling 0 days Thu 7/8/10 Thu 7/8/10

556 Spool Piece No 30-012R+30-011R 10 days Wed 6/30/10 Fri 7/9/10

557 Check and Confirm Trenching work and Pipe Laying 1 day Wed 6/30/10 Wed 6/30/10

558 Fit-up and Alignment Including Inspection 1 day Thu 7/1/10 Thu 7/1/10

559 Welding 4 days Fri 7/2/10 Mon 7/5/10

560 Welding Inspection (NDE) 1 day Tue 7/6/10 Tue 7/6/10

561 Field Joint Painting and Touch-up Paint 2 days Wed 7/7/10 Thu 7/8/10

562 Painting Inspection 1 day Fri 7/9/10 Fri 7/9/10

563 Release Backfilling 0 days Fri 7/9/10 Fri 7/9/10

564 Spool Piece No 30-011R+30-010R 10 days Thu 7/1/10 Sat 7/10/10

565 Check and Confirm Trenching work and Pipe Laying 1 day Thu 7/1/10 Thu 7/1/10

566 Fit-up and Alignment Including Inspection 1 day Fri 7/2/10 Fri 7/2/10

567 Welding 4 days Sat 7/3/10 Tue 7/6/10

568 Welding Inspection (NDE) 1 day Wed 7/7/10 Wed 7/7/10

569 Field Joint Painting and Touch-up Paint 2 days Thu 7/8/10 Fri 7/9/10

570 Painting Inspection 1 day Sat 7/10/10 Sat 7/10/10

571 Release Backfilling 0 days Sat 7/10/10 Sat 7/10/10

572 Spool Piece No 30-010R+30-009R 10 days Fri 7/2/10 Sun 7/11/10

573 Check and Confirm Trenching work and Pipe Laying 1 day Fri 7/2/10 Fri 7/2/10

574 Fit-up and Alignment Including Inspection 1 day Sat 7/3/10 Sat 7/3/10

7/1

6/23 7/2

6/23

7/2

6/24 7/3

6/24

7/3

6/25 7/4

6/25

7/4

6/26 7/5

6/26

7/5

6/27 7/6

6/27

7/6

6/28 8/9

6/28 7/7

6/28

7/7

6/29 7/8

6/29

7/8

6/30 7/9

6/30

7/9

7/1 7/10

7/1

7/10

7/2 7/11

7/2

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 7

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 37: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

575 Welding 4 days Sun 7/4/10 Wed 7/7/10

576 Welding Inspection (NDE) 1 day Thu 7/8/10 Thu 7/8/10

577 Field Joint Painting and Touch-up Paint 2 days Fri 7/9/10 Sat 7/10/10

578 Painting Inspection 1 day Sun 7/11/10 Sun 7/11/10

579 Release Backfilling 0 days Sun 7/11/10 Sun 7/11/10

580 Spool Piece No 30-009R+30-008R 10 days Sat 7/3/10 Mon 7/12/10

581 Check and Confirm Trenching work and Pipe Laying 1 day Sat 7/3/10 Sat 7/3/10

582 Fit-up and Alignment Including Inspection 1 day Sun 7/4/10 Sun 7/4/10

583 Welding 4 days Mon 7/5/10 Thu 7/8/10

584 Welding Inspection (NDE) 1 day Fri 7/9/10 Fri 7/9/10

585 Field Joint Painting and Touch-up Paint 2 days Sat 7/10/10 Sun 7/11/10

586 Painting Inspection 1 day Mon 7/12/10 Mon 7/12/10

587 Release Backfilling 0 days Mon 7/12/10 Mon 7/12/10

588 Spool Piece No 30-008R+30-007R 10 days Sun 7/4/10 Tue 7/13/10

589 Check and Confirm Trenching work and Pipe Laying 1 day Sun 7/4/10 Sun 7/4/10

590 Fit-up and Alignment Including Inspection 1 day Mon 7/5/10 Mon 7/5/10

591 Welding 4 days Tue 7/6/10 Fri 7/9/10

592 Welding Inspection (NDE) 1 day Sat 7/10/10 Sat 7/10/10

593 Field Joint Painting and Touch-up Paint 2 days Sun 7/11/10 Mon 7/12/10

594 Painting Inspection 1 day Tue 7/13/10 Tue 7/13/10

595 Release Backfilling 0 days Tue 7/13/10 Tue 7/13/10

596 Spool Piece No 30-007R+30-006R 10 days Mon 7/5/10 Wed 7/14/10

597 Check and Confirm Trenching work and Pipe Laying 1 day Mon 7/5/10 Mon 7/5/10

598 Fit-up and Alignment Including Inspection 1 day Tue 7/6/10 Tue 7/6/10

599 Welding 4 days Wed 7/7/10 Sat 7/10/10

600 Welding Inspection (NDE) 1 day Sun 7/11/10 Sun 7/11/10

601 Field Joint Painting and Touch-up Paint 2 days Mon 7/12/10 Tue 7/13/10

602 Painting Inspection 1 day Wed 7/14/10 Wed 7/14/10

603 Release Backfilling 0 days Wed 7/14/10 Wed 7/14/10

604 Spool Piece No 30-006R+30-005R 10 days Tue 7/6/10 Thu 7/15/10

605 Check and Confirm Trenching work and Pipe Laying 1 day Tue 7/6/10 Tue 7/6/10

606 Fit-up and Alignment Including Inspection 1 day Wed 7/7/10 Wed 7/7/10

607 Welding 4 days Thu 7/8/10 Sun 7/11/10

608 Welding Inspection (NDE) 1 day Mon 7/12/10 Mon 7/12/10

609 Field Joint Painting and Touch-up Paint 2 days Tue 7/13/10 Wed 7/14/10

610 Painting Inspection 1 day Thu 7/15/10 Thu 7/15/10

611 Release Backfilling 0 days Thu 7/15/10 Thu 7/15/10

612 Spool Piece No 30-005R+30-004R 10 days Wed 7/7/10 Fri 7/16/10

613 Check and Confirm Trenching work and Pipe Laying 1 day Wed 7/7/10 Wed 7/7/10

614 Fit-up and Alignment Including Inspection 1 day Thu 7/8/10 Thu 7/8/10

615 Welding 4 days Fri 7/9/10 Mon 7/12/10

616 Welding Inspection (NDE) 1 day Tue 7/13/10 Tue 7/13/10

617 Field Joint Painting and Touch-up Paint 2 days Wed 7/14/10 Thu 7/15/10

618 Painting Inspection 1 day Fri 7/16/10 Fri 7/16/10

619 Release Backfilling 0 days Fri 7/16/10 Fri 7/16/10

620 Spool Piece No 30-004R+30-003R 10 days Thu 7/8/10 Sat 7/17/10

621 Check and Confirm Trenching work and Pipe Laying 1 day Thu 7/8/10 Thu 7/8/10

622 Fit-up and Alignment Including Inspection 1 day Fri 7/9/10 Fri 7/9/10

623 Welding 4 days Sat 7/10/10 Tue 7/13/10

624 Welding Inspection (NDE) 1 day Wed 7/14/10 Wed 7/14/10

625 Field Joint Painting and Touch-up Paint 2 days Thu 7/15/10 Fri 7/16/10

626 Painting Inspection 1 day Sat 7/17/10 Sat 7/17/10

627 Release Backfilling 0 days Sat 7/17/10 Sat 7/17/10

628 Spool Piece No 30-003R+30-002R 10 days Fri 7/9/10 Sun 7/18/10

629 Check and Confirm Trenching work and Pipe Laying 1 day Fri 7/9/10 Fri 7/9/10

630 Fit-up and Alignment Including Inspection 1 day Sat 7/10/10 Sat 7/10/10

631 Welding 4 days Sun 7/11/10 Wed 7/14/10

632 Welding Inspection (NDE) 1 day Thu 7/15/10 Thu 7/15/10

633 Field Joint Painting and Touch-up Paint 2 days Fri 7/16/10 Sat 7/17/10

634 Painting Inspection 1 day Sun 7/18/10 Sun 7/18/10

635 Release Backfilling 0 days Sun 7/18/10 Sun 7/18/10

636 Spool Piece No 30-002R+30-001R 10 days Sat 7/10/10 Mon 7/19/10

637 Check and Confirm Trenching work and Pipe Laying 1 day Sat 7/10/10 Sat 7/10/10

638 Fit-up and Alignment Including Inspection 1 day Sun 7/11/10 Sun 7/11/10

639 Welding 4 days Mon 7/12/10 Thu 7/15/10

640 Welding Inspection (NDE) 1 day Fri 7/16/10 Fri 7/16/10

641 Field Joint Painting and Touch-up Paint 2 days Sat 7/17/10 Sun 7/18/10

642 Painting Inspection 1 day Mon 7/19/10 Mon 7/19/10

643 Release Backfilling 0 days Mon 7/19/10 Mon 7/19/10

644 Spool Piece No 30-001R+31-001R 10 days Sun 7/11/10 Tue 7/20/10

645 Check and Confirm Trenching work and Pipe Laying 1 day Sun 7/11/10 Sun 7/11/10

646 Fit-up and Alignment Including Inspection 1 day Mon 7/12/10 Mon 7/12/10

647 Welding 4 days Tue 7/13/10 Fri 7/16/10

648 Welding Inspection (NDE) 1 day Sat 7/17/10 Sat 7/17/10

649 Field Joint Painting and Touch-up Paint 2 days Sun 7/18/10 Mon 7/19/10

650 Painting Inspection 1 day Tue 7/20/10 Tue 7/20/10

651 Release Backfilling 0 days Tue 7/20/10 Tue 7/20/10

652 Spool Piece No 31-001R+31-002R 10 days Mon 7/12/10 Wed 7/21/10

653 Check and Confirm Trenching work and Pipe Laying 1 day Mon 7/12/10 Mon 7/12/10

654 Fit-up and Alignment Including Inspection 1 day Tue 7/13/10 Tue 7/13/10

655 Welding 4 days Wed 7/14/10 Sat 7/17/10

656 Welding Inspection (NDE) 1 day Sun 7/18/10 Sun 7/18/10

7/11

7/3 7/12

7/3

7/12

7/4 7/13

7/4

7/13

7/5 7/14

7/5

7/14

7/6 7/15

7/6

7/15

7/7 7/16

7/7

7/16

7/8 7/17

7/8

7/17

7/9 7/18

7/9

7/18

7/10 7/19

7/10

7/19

7/11 7/20

7/11

7/20

7/12 7/21

7/12

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 8

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 38: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

657 Field Joint Painting and Touch-up Paint 2 days Mon 7/19/10 Tue 7/20/10

658 Painting Inspection 1 day Wed 7/21/10 Wed 7/21/10

659 Release Backfilling 0 days Wed 7/21/10 Wed 7/21/10

660 Spool Piece No 31-002R+31-003R 10 days Tue 7/13/10 Thu 7/22/10

661 Check and Confirm Trenching work and Pipe Laying 1 day Tue 7/13/10 Tue 7/13/10

662 Fit-up and Alignment Including Inspection 1 day Wed 7/14/10 Wed 7/14/10

663 Welding 4 days Thu 7/15/10 Sun 7/18/10

664 Welding Inspection (NDE) 1 day Mon 7/19/10 Mon 7/19/10

665 Field Joint Painting and Touch-up Paint 2 days Tue 7/20/10 Wed 7/21/10

666 Painting Inspection 1 day Thu 7/22/10 Thu 7/22/10

667 Release Backfilling 0 days Thu 7/22/10 Thu 7/22/10

668 Spool Piece No 31-003R+31-004R 10 days Wed 7/14/10 Fri 7/23/10

669 Check and Confirm Trenching work and Pipe Laying 1 day Wed 7/14/10 Wed 7/14/10

670 Fit-up and Alignment Including Inspection 1 day Thu 7/15/10 Thu 7/15/10

671 Welding 4 days Fri 7/16/10 Mon 7/19/10

672 Welding Inspection (NDE) 1 day Tue 7/20/10 Tue 7/20/10

673 Field Joint Painting and Touch-up Paint 2 days Wed 7/21/10 Thu 7/22/10

674 Painting Inspection 1 day Fri 7/23/10 Fri 7/23/10

675 Release Backfilling 0 days Fri 7/23/10 Fri 7/23/10

676 Spool Piece No 30-076S+30-075S 10 days Thu 7/15/10 Sat 7/24/10

677 Check and Confirm Trenching work and Pipe Laying 1 day Thu 7/15/10 Thu 7/15/10

678 Fit-up and Alignment Including Inspection 1 day Fri 7/16/10 Fri 7/16/10

679 Welding 4 days Sat 7/17/10 Tue 7/20/10

680 Welding Inspection (NDE) 1 day Wed 7/21/10 Wed 7/21/10

681 Field Joint Painting and Touch-up Paint 2 days Thu 7/22/10 Fri 7/23/10

682 Painting Inspection 1 day Sat 7/24/10 Sat 7/24/10

683 Release Backfilling 0 days Sat 7/24/10 Sat 7/24/10

684 Spool Piece No 30-077S+30-076S 10 days Fri 7/16/10 Sun 7/25/10

685 Check and Confirm Trenching work and Pipe Laying 1 day Fri 7/16/10 Fri 7/16/10

686 Fit-up and Alignment Including Inspection 1 day Sat 7/17/10 Sat 7/17/10

687 Welding 4 days Sun 7/18/10 Wed 7/21/10

688 Welding Inspection (NDE) 1 day Thu 7/22/10 Thu 7/22/10

689 Field Joint Painting and Touch-up Paint 2 days Fri 7/23/10 Sat 7/24/10

690 Painting Inspection 1 day Sun 7/25/10 Sun 7/25/10

691 Release Backfilling 0 days Sun 7/25/10 Sun 7/25/10

692 Spool Piece No 30-078S+30-077S 10 days Sat 7/17/10 Mon 7/26/10

693 Check and Confirm Trenching work and Pipe Laying 1 day Sat 7/17/10 Sat 7/17/10

694 Fit-up and Alignment Including Inspection 1 day Sun 7/18/10 Sun 7/18/10

695 Welding 4 days Mon 7/19/10 Thu 7/22/10

696 Welding Inspection (NDE) 1 day Fri 7/23/10 Fri 7/23/10

697 Field Joint Painting and Touch-up Paint 2 days Sat 7/24/10 Sun 7/25/10

698 Painting Inspection 1 day Mon 7/26/10 Mon 7/26/10

699 Release Backfilling 0 days Mon 7/26/10 Mon 7/26/10

700 Spool Piece No 30-079S+30-078S 10 days Sun 7/18/10 Tue 7/27/10

701 Check and Confirm Trenching work and Pipe Laying 1 day Sun 7/18/10 Sun 7/18/10

702 Fit-up and Alignment Including Inspection 1 day Mon 7/19/10 Mon 7/19/10

703 Welding 4 days Tue 7/20/10 Fri 7/23/10

704 Welding Inspection (NDE) 1 day Sat 7/24/10 Sat 7/24/10

705 Field Joint Painting and Touch-up Paint 2 days Sun 7/25/10 Mon 7/26/10

706 Painting Inspection 1 day Tue 7/27/10 Tue 7/27/10

707 Release Backfilling 0 days Tue 7/27/10 Tue 7/27/10

708 Spool Piece No 30-080S+30-079S 10 days Mon 7/19/10 Wed 7/28/10

709 Check and Confirm Trenching work and Pipe Laying 1 day Mon 7/19/10 Mon 7/19/10

710 Fit-up and Alignment Including Inspection 1 day Tue 7/20/10 Tue 7/20/10

711 Welding 4 days Wed 7/21/10 Sat 7/24/10

712 Welding Inspection (NDE) 1 day Sun 7/25/10 Sun 7/25/10

713 Field Joint Painting and Touch-up Paint 2 days Mon 7/26/10 Tue 7/27/10

714 Painting Inspection 1 day Wed 7/28/10 Wed 7/28/10

715 Release Backfilling 0 days Wed 7/28/10 Wed 7/28/10

716 Spool Piece No 30-081S+30-080S 10 days Tue 7/20/10 Thu 7/29/10

717 Check and Confirm Trenching work and Pipe Laying 1 day Tue 7/20/10 Tue 7/20/10

718 Fit-up and Alignment Including Inspection 1 day Wed 7/21/10 Wed 7/21/10

719 Welding 4 days Thu 7/22/10 Sun 7/25/10

720 Welding Inspection (NDE) 1 day Mon 7/26/10 Mon 7/26/10

721 Field Joint Painting and Touch-up Paint 2 days Tue 7/27/10 Wed 7/28/10

722 Painting Inspection 1 day Thu 7/29/10 Thu 7/29/10

723 Release Backfilling 0 days Thu 7/29/10 Thu 7/29/10

724 Spool Piece No 30-082S+30-081S 10 days Wed 7/21/10 Fri 7/30/10

725 Check and Confirm Trenching work and Pipe Laying 1 day Wed 7/21/10 Wed 7/21/10

726 Fit-up and Alignment Including Inspection 1 day Thu 7/22/10 Thu 7/22/10

727 Welding 4 days Fri 7/23/10 Mon 7/26/10

728 Welding Inspection (NDE) 1 day Tue 7/27/10 Tue 7/27/10

729 Field Joint Painting and Touch-up Paint 2 days Wed 7/28/10 Thu 7/29/10

730 Painting Inspection 1 day Fri 7/30/10 Fri 7/30/10

731 Release Backfilling 0 days Fri 7/30/10 Fri 7/30/10

732 Spool Piece No 30-083S+30-082S 10 days Thu 7/22/10 Sat 7/31/10

733 Check and Confirm Trenching work and Pipe Laying 1 day Thu 7/22/10 Thu 7/22/10

734 Fit-up and Alignment Including Inspection 1 day Fri 7/23/10 Fri 7/23/10

735 Welding 4 days Sat 7/24/10 Tue 7/27/10

736 Welding Inspection (NDE) 1 day Wed 7/28/10 Wed 7/28/10

737 Field Joint Painting and Touch-up Paint 2 days Thu 7/29/10 Fri 7/30/10

738 Painting Inspection 1 day Sat 7/31/10 Sat 7/31/10

7/21

7/13 7/22

7/13

7/22

7/14 7/23

7/14

7/23

7/15 7/24

7/15

7/24

7/16 7/25

7/16

7/25

7/17 7/26

7/17

7/26

7/18 7/27

7/18

7/27

7/19 7/28

7/19

7/28

7/20 7/29

7/20

7/29

7/21 7/30

7/21

7/30

7/22 7/31

7/22

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 9

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 39: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

739 Release Backfilling 0 days Sat 7/31/10 Sat 7/31/10

740 Spool Piece No 30-084S+30-083S 10 days Fri 7/23/10 Sun 8/1/10

741 Check and Confirm Trenching work and Pipe Laying 1 day Fri 7/23/10 Fri 7/23/10

742 Fit-up and Alignment Including Inspection 1 day Sat 7/24/10 Sat 7/24/10

743 Welding 4 days Sun 7/25/10 Wed 7/28/10

744 Welding Inspection (NDE) 1 day Thu 7/29/10 Thu 7/29/10

745 Field Joint Painting and Touch-up Paint 2 days Fri 7/30/10 Sat 7/31/10

746 Painting Inspection 1 day Sun 8/1/10 Sun 8/1/10

747 Release Backfilling 0 days Sun 8/1/10 Sun 8/1/10

748 Spool Piece No 30-085S+30-084S 10 days Sat 7/24/10 Mon 8/2/10

749 Check and Confirm Trenching work and Pipe Laying 1 day Sat 7/24/10 Sat 7/24/10

750 Fit-up and Alignment Including Inspection 1 day Sun 7/25/10 Sun 7/25/10

751 Welding 4 days Mon 7/26/10 Thu 7/29/10

752 Welding Inspection (NDE) 1 day Fri 7/30/10 Fri 7/30/10

753 Field Joint Painting and Touch-up Paint 2 days Sat 7/31/10 Sun 8/1/10

754 Painting Inspection 1 day Mon 8/2/10 Mon 8/2/10

755 Release Backfilling 0 days Mon 8/2/10 Mon 8/2/10

756 Spool Piece No 30-086S+30-085S 10 days Sun 7/25/10 Tue 8/3/10

757 Check and Confirm Trenching work and Pipe Laying 1 day Sun 7/25/10 Sun 7/25/10

758 Fit-up and Alignment Including Inspection 1 day Mon 7/26/10 Mon 7/26/10

759 Welding 4 days Tue 7/27/10 Fri 7/30/10

760 Welding Inspection (NDE) 1 day Sat 7/31/10 Sat 7/31/10

761 Field Joint Painting and Touch-up Paint 2 days Sun 8/1/10 Mon 8/2/10

762 Painting Inspection 1 day Tue 8/3/10 Tue 8/3/10

763 Release Backfilling 0 days Tue 8/3/10 Tue 8/3/10

764 Spool Piece No 30-087S+30-086S 10 days Mon 7/26/10 Wed 8/4/10

765 Check and Confirm Trenching work and Pipe Laying 1 day Mon 7/26/10 Mon 7/26/10

766 Fit-up and Alignment Including Inspection 1 day Tue 7/27/10 Tue 7/27/10

767 Welding 4 days Wed 7/28/10 Sat 7/31/10

768 Welding Inspection (NDE) 1 day Sun 8/1/10 Sun 8/1/10

769 Field Joint Painting and Touch-up Paint 2 days Mon 8/2/10 Tue 8/3/10

770 Painting Inspection 1 day Wed 8/4/10 Wed 8/4/10

771 Release Backfilling 0 days Wed 8/4/10 Wed 8/4/10

772 Spool Piece No 31-001S+30-087S 10 days Tue 7/27/10 Thu 8/5/10

773 Check and Confirm Trenching work and Pipe Laying 1 day Tue 7/27/10 Tue 7/27/10

774 Fit-up and Alignment Including Inspection 1 day Wed 7/28/10 Wed 7/28/10

775 Welding 4 days Thu 7/29/10 Sun 8/1/10

776 Welding Inspection (NDE) 1 day Mon 8/2/10 Mon 8/2/10

777 Field Joint Painting and Touch-up Paint 2 days Tue 8/3/10 Wed 8/4/10

778 Painting Inspection 1 day Thu 8/5/10 Thu 8/5/10

779 Release Backfilling 0 days Thu 8/5/10 Thu 8/5/10

780 Spool Piece No 31-002S+31-001S 10 days Wed 7/28/10 Fri 8/6/10

781 Check and Confirm Trenching work and Pipe Laying 1 day Wed 7/28/10 Wed 7/28/10

782 Fit-up and Alignment Including Inspection 1 day Thu 7/29/10 Thu 7/29/10

783 Welding 4 days Fri 7/30/10 Mon 8/2/10

784 Welding Inspection (NDE) 1 day Tue 8/3/10 Tue 8/3/10

785 Field Joint Painting and Touch-up Paint 2 days Wed 8/4/10 Thu 8/5/10

786 Painting Inspection 1 day Fri 8/6/10 Fri 8/6/10

787 Release Backfilling 0 days Fri 8/6/10 Fri 8/6/10

788 Spool Piece No 31-003S+31-002S 10 days Thu 7/29/10 Sat 8/7/10

789 Check and Confirm Trenching work and Pipe Laying 1 day Thu 7/29/10 Thu 7/29/10

790 Fit-up and Alignment Including Inspection 1 day Fri 7/30/10 Fri 7/30/10

791 Welding 4 days Sat 7/31/10 Tue 8/3/10

792 Welding Inspection (NDE) 1 day Wed 8/4/10 Wed 8/4/10

793 Field Joint Painting and Touch-up Paint 2 days Thu 8/5/10 Fri 8/6/10

794 Painting Inspection 1 day Sat 8/7/10 Sat 8/7/10

795 Release Backfilling 0 days Sat 8/7/10 Sat 8/7/10

796 Spool Piece No 31-004S+31-003S 10 days Fri 7/30/10 Sun 8/8/10

797 Check and Confirm Trenching work and Pipe Laying 1 day Fri 7/30/10 Fri 7/30/10

798 Fit-up and Alignment Including Inspection 1 day Sat 7/31/10 Sat 7/31/10

799 Welding 4 days Sun 8/1/10 Wed 8/4/10

800 Welding Inspection (NDE) 1 day Thu 8/5/10 Thu 8/5/10

801 Field Joint Painting and Touch-up Paint 2 days Fri 8/6/10 Sat 8/7/10

802 Painting Inspection 1 day Sun 8/8/10 Sun 8/8/10

803 Release Backfilling 0 days Sun 8/8/10 Sun 8/8/10

804 Spool Piece No 31-005S+31-004S 10 days Sat 7/31/10 Mon 8/9/10

805 Check and Confirm Trenching work and Pipe Laying 1 day Sat 7/31/10 Sat 7/31/10

806 Fit-up and Alignment Including Inspection 1 day Sun 8/1/10 Sun 8/1/10

807 Welding 4 days Mon 8/2/10 Thu 8/5/10

808 Welding Inspection (NDE) 1 day Fri 8/6/10 Fri 8/6/10

809 Field Joint Painting and Touch-up Paint 2 days Sat 8/7/10 Sun 8/8/10

810 Painting Inspection 1 day Mon 8/9/10 Mon 8/9/10

811 Release Backfilling 0 days Mon 8/9/10 Mon 8/9/10

812 Zone #4 29 days Fri 7/9/10 Fri 8/6/10

813 Spool Piece No 30-013S+30-014S 10 days Fri 7/9/10 Sun 7/18/10

814 Check and Confirm Trenching work and Pipe Laying 1 day Fri 7/9/10 Fri 7/9/10

815 Fit-up and Alignment Including Inspection 1 day Sat 7/10/10 Sat 7/10/10

816 Welding 4 days Sun 7/11/10 Wed 7/14/10

817 Welding Inspection (NDE) 1 day Thu 7/15/10 Thu 7/15/10

818 Field Joint Painting and Touch-up Paint 2 days Fri 7/16/10 Sat 7/17/10

819 Painting Inspection 1 day Sun 7/18/10 Sun 7/18/10

820 Release Backfilling 0 days Sun 7/18/10 Sun 7/18/10

7/31

7/23 8/1

7/23

8/1

7/24 8/2

7/24

8/2

7/25 8/3

7/25

8/3

7/26 8/4

7/26

8/4

7/27 8/5

7/27

8/5

7/28 8/6

7/28

8/6

7/29 8/7

7/29

8/7

7/30 8/8

7/30

8/8

7/31 8/9

7/31

8/9

7/9 8/6

7/9 7/18

7/9

7/18

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 10

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 40: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

821 Spool Piece No 30-014S+30-015S 10 days Sat 7/10/10 Mon 7/19/10

822 Check and Confirm Trenching work and Pipe Laying 1 day Sat 7/10/10 Sat 7/10/10

823 Fit-up and Alignment Including Inspection 1 day Sun 7/11/10 Sun 7/11/10

824 Welding 4 days Mon 7/12/10 Thu 7/15/10

825 Welding Inspection (NDE) 1 day Fri 7/16/10 Fri 7/16/10

826 Field Joint Painting and Touch-up Paint 2 days Sat 7/17/10 Sun 7/18/10

827 Painting Inspection 1 day Mon 7/19/10 Mon 7/19/10

828 Release Backfilling 0 days Mon 7/19/10 Mon 7/19/10

829 Spool Piece No 30-015S+30-016S 10 days Sun 7/11/10 Tue 7/20/10

830 Check and Confirm Trenching work and Pipe Laying 1 day Sun 7/11/10 Sun 7/11/10

831 Fit-up and Alignment Including Inspection 1 day Mon 7/12/10 Mon 7/12/10

832 Welding 4 days Tue 7/13/10 Fri 7/16/10

833 Welding Inspection (NDE) 1 day Sat 7/17/10 Sat 7/17/10

834 Field Joint Painting and Touch-up Paint 2 days Sun 7/18/10 Mon 7/19/10

835 Painting Inspection 1 day Tue 7/20/10 Tue 7/20/10

836 Release Backfilling 0 days Tue 7/20/10 Tue 7/20/10

837 Spool Piece No 30-016S+30-017S 10 days Mon 7/12/10 Wed 7/21/10

838 Check and Confirm Trenching work and Pipe Laying 1 day Mon 7/12/10 Mon 7/12/10

839 Fit-up and Alignment Including Inspection 1 day Tue 7/13/10 Tue 7/13/10

840 Welding 4 days Wed 7/14/10 Sat 7/17/10

841 Welding Inspection (NDE) 1 day Sun 7/18/10 Sun 7/18/10

842 Field Joint Painting and Touch-up Paint 2 days Mon 7/19/10 Tue 7/20/10

843 Painting Inspection 1 day Wed 7/21/10 Wed 7/21/10

844 Release Backfilling 0 days Wed 7/21/10 Wed 7/21/10

845 Spool Piece No 30-017S+30-018S 10 days Tue 7/13/10 Thu 7/22/10

846 Check and Confirm Trenching work and Pipe Laying 1 day Tue 7/13/10 Tue 7/13/10

847 Fit-up and Alignment Including Inspection 1 day Wed 7/14/10 Wed 7/14/10

848 Welding 4 days Thu 7/15/10 Sun 7/18/10

849 Welding Inspection (NDE) 1 day Mon 7/19/10 Mon 7/19/10

850 Field Joint Painting and Touch-up Paint 2 days Tue 7/20/10 Wed 7/21/10

851 Painting Inspection 1 day Thu 7/22/10 Thu 7/22/10

852 Release Backfilling 0 days Thu 7/22/10 Thu 7/22/10

853 Spool Piece No 30-018S+30-019S 10 days Wed 7/14/10 Fri 7/23/10

854 Check and Confirm Trenching work and Pipe Laying 1 day Wed 7/14/10 Wed 7/14/10

855 Fit-up and Alignment Including Inspection 1 day Thu 7/15/10 Thu 7/15/10

856 Welding 4 days Fri 7/16/10 Mon 7/19/10

857 Welding Inspection (NDE) 1 day Tue 7/20/10 Tue 7/20/10

858 Field Joint Painting and Touch-up Paint 2 days Wed 7/21/10 Thu 7/22/10

859 Painting Inspection 1 day Fri 7/23/10 Fri 7/23/10

860 Release Backfilling 0 days Fri 7/23/10 Fri 7/23/10

861 Spool Piece No 30-019S+30-020S 10 days Thu 7/15/10 Sat 7/24/10

862 Check and Confirm Trenching work and Pipe Laying 1 day Thu 7/15/10 Thu 7/15/10

863 Fit-up and Alignment Including Inspection 1 day Fri 7/16/10 Fri 7/16/10

864 Welding 4 days Sat 7/17/10 Tue 7/20/10

865 Welding Inspection (NDE) 1 day Wed 7/21/10 Wed 7/21/10

866 Field Joint Painting and Touch-up Paint 2 days Thu 7/22/10 Fri 7/23/10

867 Painting Inspection 1 day Sat 7/24/10 Sat 7/24/10

868 Release Backfilling 0 days Sat 7/24/10 Sat 7/24/10

869 Spool Piece No 30-020S+30-021S 10 days Fri 7/16/10 Sun 7/25/10

870 Check and Confirm Trenching work and Pipe Laying 1 day Fri 7/16/10 Fri 7/16/10

871 Fit-up and Alignment Including Inspection 1 day Sat 7/17/10 Sat 7/17/10

872 Welding 4 days Sun 7/18/10 Wed 7/21/10

873 Welding Inspection (NDE) 1 day Thu 7/22/10 Thu 7/22/10

874 Field Joint Painting and Touch-up Paint 2 days Fri 7/23/10 Sat 7/24/10

875 Painting Inspection 1 day Sun 7/25/10 Sun 7/25/10

876 Release Backfilling 0 days Sun 7/25/10 Sun 7/25/10

877 Spool Piece No 30-021S+30-022S 10 days Sat 7/17/10 Mon 7/26/10

878 Check and Confirm Trenching work and Pipe Laying 1 day Sat 7/17/10 Sat 7/17/10

879 Fit-up and Alignment Including Inspection 1 day Sun 7/18/10 Sun 7/18/10

880 Welding 4 days Mon 7/19/10 Thu 7/22/10

881 Welding Inspection (NDE) 1 day Fri 7/23/10 Fri 7/23/10

882 Field Joint Painting and Touch-up Paint 2 days Sat 7/24/10 Sun 7/25/10

883 Painting Inspection 1 day Mon 7/26/10 Mon 7/26/10

884 Release Backfilling 0 days Mon 7/26/10 Mon 7/26/10

885 Spool Piece No 30-022S+30-023S 10 days Sun 7/18/10 Tue 7/27/10

886 Check and Confirm Trenching work and Pipe Laying 1 day Sun 7/18/10 Sun 7/18/10

887 Fit-up and Alignment Including Inspection 1 day Mon 7/19/10 Mon 7/19/10

888 Welding 4 days Tue 7/20/10 Fri 7/23/10

889 Welding Inspection (NDE) 1 day Sat 7/24/10 Sat 7/24/10

890 Field Joint Painting and Touch-up Paint 2 days Sun 7/25/10 Mon 7/26/10

891 Painting Inspection 1 day Tue 7/27/10 Tue 7/27/10

892 Release Backfilling 0 days Tue 7/27/10 Tue 7/27/10

893 Spool Piece No 30-023S+30-024S 10 days Mon 7/19/10 Wed 7/28/10

894 Check and Confirm Trenching work and Pipe Laying 1 day Mon 7/19/10 Mon 7/19/10

895 Fit-up and Alignment Including Inspection 1 day Tue 7/20/10 Tue 7/20/10

896 Welding 4 days Wed 7/21/10 Sat 7/24/10

897 Welding Inspection (NDE) 1 day Sun 7/25/10 Sun 7/25/10

898 Field Joint Painting and Touch-up Paint 2 days Mon 7/26/10 Tue 7/27/10

899 Painting Inspection 1 day Wed 7/28/10 Wed 7/28/10

900 Release Backfilling 0 days Wed 7/28/10 Wed 7/28/10

901 Spool Piece No 30-024S+30-025S 10 days Tue 7/20/10 Thu 7/29/10

902 Check and Confirm Trenching work and Pipe Laying 1 day Tue 7/20/10 Tue 7/20/10

7/10 7/19

7/10

7/19

7/11 7/20

7/11

7/20

7/12 7/21

7/12

7/21

7/13 7/22

7/13

7/22

7/14 7/23

7/14

7/23

7/15 7/24

7/15

7/24

7/16 7/25

7/16

7/25

7/17 7/26

7/17

7/26

7/18 7/27

7/18

7/27

7/19 7/28

7/19

7/28

7/20 7/29

7/20

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 11

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 41: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

903 Fit-up and Alignment Including Inspection 1 day Wed 7/21/10 Wed 7/21/10

904 Welding 4 days Thu 7/22/10 Sun 7/25/10

905 Welding Inspection (NDE) 1 day Mon 7/26/10 Mon 7/26/10

906 Field Joint Painting and Touch-up Paint 2 days Tue 7/27/10 Wed 7/28/10

907 Painting Inspection 1 day Thu 7/29/10 Thu 7/29/10

908 Release Backfilling 0 days Thu 7/29/10 Thu 7/29/10

909 Spool Piece No 30-025S+30-026S 10 days Wed 7/21/10 Fri 7/30/10

910 Check and Confirm Trenching work and Pipe Laying 1 day Wed 7/21/10 Wed 7/21/10

911 Fit-up and Alignment Including Inspection 1 day Thu 7/22/10 Thu 7/22/10

912 Welding 4 days Fri 7/23/10 Mon 7/26/10

913 Welding Inspection (NDE) 1 day Tue 7/27/10 Tue 7/27/10

914 Field Joint Painting and Touch-up Paint 2 days Wed 7/28/10 Thu 7/29/10

915 Painting Inspection 1 day Fri 7/30/10 Fri 7/30/10

916 Release Backfilling 0 days Fri 7/30/10 Fri 7/30/10

917 Spool Piece No 30-026S+30-027S 10 days Thu 7/22/10 Sat 7/31/10

918 Check and Confirm Trenching work and Pipe Laying 1 day Thu 7/22/10 Thu 7/22/10

919 Fit-up and Alignment Including Inspection 1 day Fri 7/23/10 Fri 7/23/10

920 Welding 4 days Sat 7/24/10 Tue 7/27/10

921 Welding Inspection (NDE) 1 day Wed 7/28/10 Wed 7/28/10

922 Field Joint Painting and Touch-up Paint 2 days Thu 7/29/10 Fri 7/30/10

923 Painting Inspection 1 day Sat 7/31/10 Sat 7/31/10

924 Release Backfilling 0 days Sat 7/31/10 Sat 7/31/10

925 Spool Piece No 30-027S+30-028S 10 days Fri 7/23/10 Sun 8/1/10

926 Check and Confirm Trenching work and Pipe Laying 1 day Fri 7/23/10 Fri 7/23/10

927 Fit-up and Alignment Including Inspection 1 day Sat 7/24/10 Sat 7/24/10

928 Welding 4 days Sun 7/25/10 Wed 7/28/10

929 Welding Inspection (NDE) 1 day Thu 7/29/10 Thu 7/29/10

930 Field Joint Painting and Touch-up Paint 2 days Fri 7/30/10 Sat 7/31/10

931 Painting Inspection 1 day Sun 8/1/10 Sun 8/1/10

932 Release Backfilling 0 days Sun 8/1/10 Sun 8/1/10

933 Spool Piece No 30-028S+30-029S 10 days Sat 7/24/10 Mon 8/2/10

934 Check and Confirm Trenching work and Pipe Laying 1 day Sat 7/24/10 Sat 7/24/10

935 Fit-up and Alignment Including Inspection 1 day Sun 7/25/10 Sun 7/25/10

936 Welding 4 days Mon 7/26/10 Thu 7/29/10

937 Welding Inspection (NDE) 1 day Fri 7/30/10 Fri 7/30/10

938 Field Joint Painting and Touch-up Paint 2 days Sat 7/31/10 Sun 8/1/10

939 Painting Inspection 1 day Mon 8/2/10 Mon 8/2/10

940 Release Backfilling 0 days Mon 8/2/10 Mon 8/2/10

941 Spool Piece No 30-029S+30-030S 10 days Sun 7/25/10 Tue 8/3/10

942 Check and Confirm Trenching work and Pipe Laying 1 day Sun 7/25/10 Sun 7/25/10

943 Fit-up and Alignment Including Inspection 1 day Mon 7/26/10 Mon 7/26/10

944 Welding 4 days Tue 7/27/10 Fri 7/30/10

945 Welding Inspection (NDE) 1 day Sat 7/31/10 Sat 7/31/10

946 Field Joint Painting and Touch-up Paint 2 days Sun 8/1/10 Mon 8/2/10

947 Painting Inspection 1 day Tue 8/3/10 Tue 8/3/10

948 Release Backfilling 0 days Tue 8/3/10 Tue 8/3/10

949 Spool Piece No 30-030S+30-031S 10 days Mon 7/26/10 Wed 8/4/10

950 Check and Confirm Trenching work and Pipe Laying 1 day Mon 7/26/10 Mon 7/26/10

951 Fit-up and Alignment Including Inspection 1 day Tue 7/27/10 Tue 7/27/10

952 Welding 4 days Wed 7/28/10 Sat 7/31/10

953 Welding Inspection (NDE) 1 day Sun 8/1/10 Sun 8/1/10

954 Field Joint Painting and Touch-up Paint 2 days Mon 8/2/10 Tue 8/3/10

955 Painting Inspection 1 day Wed 8/4/10 Wed 8/4/10

956 Release Backfilling 0 days Wed 8/4/10 Wed 8/4/10

957 Spool Piece No 30-031S+30-032S 10 days Tue 7/27/10 Thu 8/5/10

958 Check and Confirm Trenching work and Pipe Laying 1 day Tue 7/27/10 Tue 7/27/10

959 Fit-up and Alignment Including Inspection 1 day Wed 7/28/10 Wed 7/28/10

960 Welding 4 days Thu 7/29/10 Sun 8/1/10

961 Welding Inspection (NDE) 1 day Mon 8/2/10 Mon 8/2/10

962 Field Joint Painting and Touch-up Paint 2 days Tue 8/3/10 Wed 8/4/10

963 Painting Inspection 1 day Thu 8/5/10 Thu 8/5/10

964 Release Backfilling 0 days Thu 8/5/10 Thu 8/5/10

965 Spool Piece No 30-032S+30-033S 10 days Wed 7/28/10 Fri 8/6/10

966 Check and Confirm Trenching work and Pipe Laying 1 day Wed 7/28/10 Wed 7/28/10

967 Fit-up and Alignment Including Inspection 1 day Thu 7/29/10 Thu 7/29/10

968 Welding 4 days Fri 7/30/10 Mon 8/2/10

969 Welding Inspection (NDE) 1 day Tue 8/3/10 Tue 8/3/10

970 Field Joint Painting and Touch-up Paint 2 days Wed 8/4/10 Thu 8/5/10

971 Painting Inspection 1 day Fri 8/6/10 Fri 8/6/10

972 Release Backfilling 0 days Fri 8/6/10 Fri 8/6/10

973 Zone #5 38 days Sat 8/7/10 Wed 9/15/10

974 Spool Piece No 30-012S+30-013S 10 days Sat 8/7/10 Mon 8/16/10

975 Check and Confirm Trenching work and Pipe Laying 1 day Sat 8/7/10 Sat 8/7/10

976 Fit-up and Alignment Including Inspection 1 day Sun 8/8/10 Sun 8/8/10

977 Welding 4 days Mon 8/9/10 Thu 8/12/10

978 Welding Inspection (NDE) 1 day Fri 8/13/10 Fri 8/13/10

979 Field Joint Painting and Touch-up Paint 2 days Sat 8/14/10 Sun 8/15/10

980 Painting Inspection 1 day Mon 8/16/10 Mon 8/16/10

981 Release Backfilling 0 days Mon 8/16/10 Mon 8/16/10

982 Spool Piece No 30-011S+30-012S 10 days Sun 8/8/10 Tue 8/17/10

983 Check and Confirm Trenching work and Pipe Laying 1 day Sun 8/8/10 Sun 8/8/10

984 Fit-up and Alignment Including Inspection 1 day Mon 8/9/10 Mon 8/9/10

7/29

7/21 7/30

7/21

7/30

7/22 7/31

7/22

7/31

7/23 8/1

7/23

8/1

7/24 8/2

7/24

8/2

7/25 8/3

7/25

8/3

7/26 8/4

7/26

8/4

7/27 8/5

7/27

8/5

7/28 8/6

7/28

8/6

8/7 9/15

8/7 8/16

8/7

8/16

8/8 8/17

8/8

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 12

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 42: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

985 Welding 4 days Tue 8/10/10 Fri 8/13/10

986 Welding Inspection (NDE) 1 day Sat 8/14/10 Sat 8/14/10

987 Field Joint Painting and Touch-up Paint 2 days Sun 8/15/10 Mon 8/16/10

988 Painting Inspection 1 day Tue 8/17/10 Tue 8/17/10

989 Release Backfilling 0 days Tue 8/17/10 Tue 8/17/10

990 Spool Piece No 30-010S+30-011S 10 days Mon 8/9/10 Wed 8/18/10

991 Check and Confirm Trenching work and Pipe Laying 1 day Mon 8/9/10 Mon 8/9/10

992 Fit-up and Alignment Including Inspection 1 day Tue 8/10/10 Tue 8/10/10

993 Welding 4 days Wed 8/11/10 Sat 8/14/10

994 Welding Inspection (NDE) 1 day Sun 8/15/10 Sun 8/15/10

995 Field Joint Painting and Touch-up Paint 2 days Mon 8/16/10 Tue 8/17/10

996 Painting Inspection 1 day Wed 8/18/10 Wed 8/18/10

997 Release Backfilling 0 days Wed 8/18/10 Wed 8/18/10

998 Spool Piece No 30-009S+30-010S 10 days Tue 8/10/10 Thu 8/19/10

999 Check and Confirm Trenching work and Pipe Laying 1 day Tue 8/10/10 Tue 8/10/10

1000 Fit-up and Alignment Including Inspection 1 day Wed 8/11/10 Wed 8/11/10

1001 Welding 4 days Thu 8/12/10 Sun 8/15/10

1002 Welding Inspection (NDE) 1 day Mon 8/16/10 Mon 8/16/10

1003 Field Joint Painting and Touch-up Paint 2 days Tue 8/17/10 Wed 8/18/10

1004 Painting Inspection 1 day Thu 8/19/10 Thu 8/19/10

1005 Release Backfilling 0 days Thu 8/19/10 Thu 8/19/10

1006 Spool Piece No 30-008S+30-009S 10 days Wed 8/11/10 Fri 8/20/10

1007 Check and Confirm Trenching work and Pipe Laying 1 day Wed 8/11/10 Wed 8/11/10

1008 Fit-up and Alignment Including Inspection 1 day Thu 8/12/10 Thu 8/12/10

1009 Welding 4 days Fri 8/13/10 Mon 8/16/10

1010 Welding Inspection (NDE) 1 day Tue 8/17/10 Tue 8/17/10

1011 Field Joint Painting and Touch-up Paint 2 days Wed 8/18/10 Thu 8/19/10

1012 Painting Inspection 1 day Fri 8/20/10 Fri 8/20/10

1013 Release Backfilling 0 days Fri 8/20/10 Fri 8/20/10

1014 Spool Piece No 30-007S+30-008S 10 days Thu 8/12/10 Sat 8/21/10

1015 Check and Confirm Trenching work and Pipe Laying 1 day Thu 8/12/10 Thu 8/12/10

1016 Fit-up and Alignment Including Inspection 1 day Fri 8/13/10 Fri 8/13/10

1017 Welding 4 days Sat 8/14/10 Tue 8/17/10

1018 Welding Inspection (NDE) 1 day Wed 8/18/10 Wed 8/18/10

1019 Field Joint Painting and Touch-up Paint 2 days Thu 8/19/10 Fri 8/20/10

1020 Painting Inspection 1 day Sat 8/21/10 Sat 8/21/10

1021 Release Backfilling 0 days Sat 8/21/10 Sat 8/21/10

1022 Spool Piece No 30-006S+30-007S 10 days Fri 8/13/10 Sun 8/22/10

1023 Check and Confirm Trenching work and Pipe Laying 1 day Fri 8/13/10 Fri 8/13/10

1024 Fit-up and Alignment Including Inspection 1 day Sat 8/14/10 Sat 8/14/10

1025 Welding 4 days Sun 8/15/10 Wed 8/18/10

1026 Welding Inspection (NDE) 1 day Thu 8/19/10 Thu 8/19/10

1027 Field Joint Painting and Touch-up Paint 2 days Fri 8/20/10 Sat 8/21/10

1028 Painting Inspection 1 day Sun 8/22/10 Sun 8/22/10

1029 Release Backfilling 0 days Sun 8/22/10 Sun 8/22/10

1030 Spool Piece No 30-005S+30-006S 10 days Sat 8/14/10 Mon 8/23/10

1031 Check and Confirm Trenching work and Pipe Laying 1 day Sat 8/14/10 Sat 8/14/10

1032 Fit-up and Alignment Including Inspection 1 day Sun 8/15/10 Sun 8/15/10

1033 Welding 4 days Mon 8/16/10 Thu 8/19/10

1034 Welding Inspection (NDE) 1 day Fri 8/20/10 Fri 8/20/10

1035 Field Joint Painting and Touch-up Paint 2 days Sat 8/21/10 Sun 8/22/10

1036 Painting Inspection 1 day Mon 8/23/10 Mon 8/23/10

1037 Release Backfilling 0 days Mon 8/23/10 Mon 8/23/10

1038 Spool Piece No 30-004S+30-005S 10 days Sun 8/15/10 Tue 8/24/10

1039 Check and Confirm Trenching work and Pipe Laying 1 day Sun 8/15/10 Sun 8/15/10

1040 Fit-up and Alignment Including Inspection 1 day Mon 8/16/10 Mon 8/16/10

1041 Welding 4 days Tue 8/17/10 Fri 8/20/10

1042 Welding Inspection (NDE) 1 day Sat 8/21/10 Sat 8/21/10

1043 Field Joint Painting and Touch-up Paint 2 days Sun 8/22/10 Mon 8/23/10

1044 Painting Inspection 1 day Tue 8/24/10 Tue 8/24/10

1045 Release Backfilling 0 days Tue 8/24/10 Tue 8/24/10

1046 Spool Piece No 30-003S+30-004S 10 days Mon 8/16/10 Wed 8/25/10

1047 Check and Confirm Trenching work and Pipe Laying 1 day Mon 8/16/10 Mon 8/16/10

1048 Fit-up and Alignment Including Inspection 1 day Tue 8/17/10 Tue 8/17/10

1049 Welding 4 days Wed 8/18/10 Sat 8/21/10

1050 Welding Inspection (NDE) 1 day Sun 8/22/10 Sun 8/22/10

1051 Field Joint Painting and Touch-up Paint 2 days Mon 8/23/10 Tue 8/24/10

1052 Painting Inspection 1 day Wed 8/25/10 Wed 8/25/10

1053 Release Backfilling 0 days Wed 8/25/10 Wed 8/25/10

1054 Spool Piece No 30-002S+30-003S 10 days Tue 8/17/10 Thu 8/26/10

1055 Check and Confirm Trenching work and Pipe Laying 1 day Tue 8/17/10 Tue 8/17/10

1056 Fit-up and Alignment Including Inspection 1 day Wed 8/18/10 Wed 8/18/10

1057 Welding 4 days Thu 8/19/10 Sun 8/22/10

1058 Welding Inspection (NDE) 1 day Mon 8/23/10 Mon 8/23/10

1059 Field Joint Painting and Touch-up Paint 2 days Tue 8/24/10 Wed 8/25/10

1060 Painting Inspection 1 day Thu 8/26/10 Thu 8/26/10

1061 Release Backfilling 0 days Thu 8/26/10 Thu 8/26/10

1062 Spool Piece No 30-001S+30-002S 10 days Wed 8/18/10 Fri 8/27/10

1063 Check and Confirm Trenching work and Pipe Laying 1 day Wed 8/18/10 Wed 8/18/10

1064 Fit-up and Alignment Including Inspection 1 day Thu 8/19/10 Thu 8/19/10

1065 Welding 4 days Fri 8/20/10 Mon 8/23/10

1066 Welding Inspection (NDE) 1 day Tue 8/24/10 Tue 8/24/10

8/17

8/9 8/18

8/9

8/18

8/10 8/19

8/10

8/19

8/11 8/20

8/11

8/20

8/12 8/21

8/12

8/21

8/13 8/22

8/13

8/22

8/14 8/23

8/14

8/23

8/15 8/24

8/15

8/24

8/16 8/25

8/16

8/25

8/17 8/26

8/17

8/26

8/18 8/27

8/18

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 13

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 43: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

1067 Field Joint Painting and Touch-up Paint 2 days Wed 8/25/10 Thu 8/26/10

1068 Painting Inspection 1 day Fri 8/27/10 Fri 8/27/10

1069 Release Backfilling 0 days Fri 8/27/10 Fri 8/27/10

1070 Spool Piece No 11-008S+30-001S 10 days Thu 8/19/10 Sat 8/28/10

1071 Check and Confirm Trenching work and Pipe Laying 1 day Thu 8/19/10 Thu 8/19/10

1072 Fit-up and Alignment Including Inspection 1 day Fri 8/20/10 Fri 8/20/10

1073 Welding 4 days Sat 8/21/10 Tue 8/24/10

1074 Welding Inspection (NDE) 1 day Wed 8/25/10 Wed 8/25/10

1075 Field Joint Painting and Touch-up Paint 2 days Thu 8/26/10 Fri 8/27/10

1076 Painting Inspection 1 day Sat 8/28/10 Sat 8/28/10

1077 Release Backfilling 0 days Sat 8/28/10 Sat 8/28/10

1078 Spool Piece No 11-007+11-008 10 days Fri 8/20/10 Sun 8/29/10

1079 Check and Confirm Trenching work and Pipe Laying 1 day Fri 8/20/10 Fri 8/20/10

1080 Fit-up and Alignment Including Inspection 1 day Sat 8/21/10 Sat 8/21/10

1081 Welding 4 days Sun 8/22/10 Wed 8/25/10

1082 Welding Inspection (NDE) 1 day Thu 8/26/10 Thu 8/26/10

1083 Field Joint Painting and Touch-up Paint 2 days Fri 8/27/10 Sat 8/28/10

1084 Painting Inspection 1 day Sun 8/29/10 Sun 8/29/10

1085 Release Backfilling 0 days Sun 8/29/10 Sun 8/29/10

1086 Spool Piece No 11-006+11-007 10 days Sat 8/21/10 Mon 8/30/10

1087 Check and Confirm Trenching work and Pipe Laying 1 day Sat 8/21/10 Sat 8/21/10

1088 Fit-up and Alignment Including Inspection 1 day Sun 8/22/10 Sun 8/22/10

1089 Welding 4 days Mon 8/23/10 Thu 8/26/10

1090 Welding Inspection (NDE) 1 day Fri 8/27/10 Fri 8/27/10

1091 Field Joint Painting and Touch-up Paint 2 days Sat 8/28/10 Sun 8/29/10

1092 Painting Inspection 1 day Mon 8/30/10 Mon 8/30/10

1093 Release Backfilling 0 days Mon 8/30/10 Mon 8/30/10

1094 Spool Piece No 11-005+11-006 10 days Sun 8/22/10 Tue 8/31/10

1095 Check and Confirm Trenching work and Pipe Laying 1 day Sun 8/22/10 Sun 8/22/10

1096 Fit-up and Alignment Including Inspection 1 day Mon 8/23/10 Mon 8/23/10

1097 Welding 4 days Tue 8/24/10 Fri 8/27/10

1098 Welding Inspection (NDE) 1 day Sat 8/28/10 Sat 8/28/10

1099 Field Joint Painting and Touch-up Paint 2 days Sun 8/29/10 Mon 8/30/10

1100 Painting Inspection 1 day Tue 8/31/10 Tue 8/31/10

1101 Release Backfilling 0 days Tue 8/31/10 Tue 8/31/10

1102 Spool Piece No 11-004+11-005 10 days Mon 8/23/10 Wed 9/1/10

1103 Check and Confirm Trenching work and Pipe Laying 1 day Mon 8/23/10 Mon 8/23/10

1104 Fit-up and Alignment Including Inspection 1 day Tue 8/24/10 Tue 8/24/10

1105 Welding 4 days Wed 8/25/10 Sat 8/28/10

1106 Welding Inspection (NDE) 1 day Sun 8/29/10 Sun 8/29/10

1107 Field Joint Painting and Touch-up Paint 2 days Mon 8/30/10 Tue 8/31/10

1108 Painting Inspection 1 day Wed 9/1/10 Wed 9/1/10

1109 Release Backfilling 0 days Wed 9/1/10 Wed 9/1/10

1110 Spool Piece No 11-003+11-004 10 days Tue 8/24/10 Thu 9/2/10

1111 Check and Confirm Trenching work and Pipe Laying 1 day Tue 8/24/10 Tue 8/24/10

1112 Fit-up and Alignment Including Inspection 1 day Wed 8/25/10 Wed 8/25/10

1113 Welding 4 days Thu 8/26/10 Sun 8/29/10

1114 Welding Inspection (NDE) 1 day Mon 8/30/10 Mon 8/30/10

1115 Field Joint Painting and Touch-up Paint 2 days Tue 8/31/10 Wed 9/1/10

1116 Painting Inspection 1 day Thu 9/2/10 Thu 9/2/10

1117 Release Backfilling 0 days Thu 9/2/10 Thu 9/2/10

1118 Spool Piece No 11-002+11-003 10 days Wed 8/25/10 Fri 9/3/10

1119 Check and Confirm Trenching work and Pipe Laying 1 day Wed 8/25/10 Wed 8/25/10

1120 Fit-up and Alignment Including Inspection 1 day Thu 8/26/10 Thu 8/26/10

1121 Welding 4 days Fri 8/27/10 Mon 8/30/10

1122 Welding Inspection (NDE) 1 day Tue 8/31/10 Tue 8/31/10

1123 Field Joint Painting and Touch-up Paint 2 days Wed 9/1/10 Thu 9/2/10

1124 Painting Inspection 1 day Fri 9/3/10 Fri 9/3/10

1125 Spool Piece No 11-001+11-002 10 days Thu 8/26/10 Sat 9/4/10

1126 Check and Confirm Trenching work and Pipe Laying 1 day Thu 8/26/10 Thu 8/26/10

1127 Fit-up and Alignment Including Inspection 1 day Fri 8/27/10 Fri 8/27/10

1128 Welding 4 days Sat 8/28/10 Tue 8/31/10

1129 Welding Inspection (NDE) 1 day Wed 9/1/10 Wed 9/1/10

1130 Field Joint Painting and Touch-up Paint 2 days Thu 9/2/10 Fri 9/3/10

1131 Painting Inspection 1 day Sat 9/4/10 Sat 9/4/10

1132 Spool Piece No 30-001S+12-009 10 days Fri 8/27/10 Sun 9/5/10

1133 Check and Confirm Trenching work and Pipe Laying 1 day Fri 8/27/10 Fri 8/27/10

1134 Fit-up and Alignment Including Inspection 1 day Sat 8/28/10 Sat 8/28/10

1135 Welding 4 days Sun 8/29/10 Wed 9/1/10

1136 Welding Inspection (NDE) 1 day Thu 9/2/10 Thu 9/2/10

1137 Field Joint Painting and Touch-up Paint 2 days Fri 9/3/10 Sat 9/4/10

1138 Painting Inspection 1 day Sun 9/5/10 Sun 9/5/10

1139 Release Backfilling 0 days Sun 9/5/10 Sun 9/5/10

1140 Spool Piece No 12-009+12-008 10 days Sat 8/28/10 Mon 9/6/10

1141 Check and Confirm Trenching work and Pipe Laying 1 day Sat 8/28/10 Sat 8/28/10

1142 Fit-up and Alignment Including Inspection 1 day Sun 8/29/10 Sun 8/29/10

1143 Welding 4 days Mon 8/30/10 Thu 9/2/10

1144 Welding Inspection (NDE) 1 day Fri 9/3/10 Fri 9/3/10

1145 Field Joint Painting and Touch-up Paint 2 days Sat 9/4/10 Sun 9/5/10

1146 Painting Inspection 1 day Mon 9/6/10 Mon 9/6/10

1147 Release Backfilling 0 days Mon 9/6/10 Mon 9/6/10

1148 Spool Piece No 12-008+12-007 10 days Sun 8/29/10 Tue 9/7/10

8/27

8/19 8/28

8/19

8/28

8/20 8/29

8/20

8/29

8/21 8/30

8/21

8/30

8/22 8/31

8/22

8/31

8/23 9/1

8/23

9/1

8/24 9/2

8/24

9/2

8/25 9/3

8/25

9/3

8/26 9/4

8/26

9/4

8/27 9/5

8/27

9/5

8/28 9/6

8/28

9/6

8/29 9/7

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 14

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 44: NT2-L3-M-000-21-00005 Rev. C

ID Task Name Duration Start Finish

1149 Check and Confirm Trenching work and Pipe Laying 1 day Sun 8/29/10 Sun 8/29/10

1150 Fit-up and Alignment Including Inspection 1 day Mon 8/30/10 Mon 8/30/10

1151 Welding 4 days Tue 8/31/10 Fri 9/3/10

1152 Welding Inspection (NDE) 1 day Sat 9/4/10 Sat 9/4/10

1153 Field Joint Painting and Touch-up Paint 2 days Sun 9/5/10 Mon 9/6/10

1154 Painting Inspection 1 day Tue 9/7/10 Tue 9/7/10

1155 Release Backfilling 0 days Tue 9/7/10 Tue 9/7/10

1156 Spool Piece No 12-007+12-006 10 days Mon 8/30/10 Wed 9/8/10

1157 Check and Confirm Trenching work and Pipe Laying 1 day Mon 8/30/10 Mon 8/30/10

1158 Fit-up and Alignment Including Inspection 1 day Tue 8/31/10 Tue 8/31/10

1159 Welding 4 days Wed 9/1/10 Sat 9/4/10

1160 Welding Inspection (NDE) 1 day Sun 9/5/10 Sun 9/5/10

1161 Field Joint Painting and Touch-up Paint 2 days Mon 9/6/10 Tue 9/7/10

1162 Painting Inspection 1 day Wed 9/8/10 Wed 9/8/10

1163 Release Backfilling 0 days Wed 9/8/10 Wed 9/8/10

1164 Spool Piece No 12-006+12-005 10 days Tue 8/31/10 Thu 9/9/10

1165 Check and Confirm Trenching work and Pipe Laying 1 day Tue 8/31/10 Tue 8/31/10

1166 Fit-up and Alignment Including Inspection 1 day Wed 9/1/10 Wed 9/1/10

1167 Welding 4 days Thu 9/2/10 Sun 9/5/10

1168 Welding Inspection (NDE) 1 day Mon 9/6/10 Mon 9/6/10

1169 Field Joint Painting and Touch-up Paint 2 days Tue 9/7/10 Wed 9/8/10

1170 Painting Inspection 1 day Thu 9/9/10 Thu 9/9/10

1171 Release Backfilling 0 days Thu 9/9/10 Thu 9/9/10

1172 Spool Piece No 12-005+12-004 10 days Wed 9/1/10 Fri 9/10/10

1173 Check and Confirm Trenching work and Pipe Laying 1 day Wed 9/1/10 Wed 9/1/10

1174 Fit-up and Alignment Including Inspection 1 day Thu 9/2/10 Thu 9/2/10

1175 Welding 4 days Fri 9/3/10 Mon 9/6/10

1176 Welding Inspection (NDE) 1 day Tue 9/7/10 Tue 9/7/10

1177 Field Joint Painting and Touch-up Paint 2 days Wed 9/8/10 Thu 9/9/10

1178 Painting Inspection 1 day Fri 9/10/10 Fri 9/10/10

1179 Release Backfilling 0 days Fri 9/10/10 Fri 9/10/10

1180 Spool Piece No 12-004+12-003 10 days Thu 9/2/10 Mon 9/13/10

1181 Check and Confirm Trenching work and Pipe Laying 1 day Thu 9/2/10 Thu 9/2/10

1182 Fit-up and Alignment Including Inspection 1 day Fri 9/3/10 Fri 9/3/10

1183 Welding 4 days Sat 9/4/10 Tue 9/7/10

1184 Welding Inspection (NDE) 1 day Wed 9/8/10 Wed 9/8/10

1185 Field Joint Painting and Touch-up Paint 2 days Thu 9/9/10 Fri 9/10/10

1186 Painting Inspection 1 day Mon 9/13/10 Mon 9/13/10

1187 Release Backfilling 0 days Mon 9/13/10 Mon 9/13/10

1188 Spool Piece No 12-003+12-002 10 days Fri 9/3/10 Tue 9/14/10

1189 Check and Confirm Trenching work and Pipe Laying 1 day Fri 9/3/10 Fri 9/3/10

1190 Fit-up and Alignment Including Inspection 1 day Sat 9/4/10 Sat 9/4/10

1191 Welding 4 days Sun 9/5/10 Wed 9/8/10

1192 Welding Inspection (NDE) 1 day Thu 9/9/10 Thu 9/9/10

1193 Field Joint Painting and Touch-up Paint 2 days Fri 9/10/10 Mon 9/13/10

1194 Painting Inspection 1 day Tue 9/14/10 Tue 9/14/10

1195 Spool Piece No 12-002+12-001 10 days Sat 9/4/10 Wed 9/15/10

1196 Check and Confirm Trenching work and Pipe Laying 1 day Sat 9/4/10 Sat 9/4/10

1197 Fit-up and Alignment Including Inspection 1 day Sun 9/5/10 Sun 9/5/10

1198 Welding 4 days Mon 9/6/10 Thu 9/9/10

1199 Welding Inspection (NDE) 1 day Fri 9/10/10 Fri 9/10/10

1200 Field Joint Painting and Touch-up Paint 2 days Mon 9/13/10 Tue 9/14/10

1201 Painting Inspection 1 day Wed 9/15/10 Wed 9/15/10

8/29

9/7

8/30 9/8

8/30

9/8

8/31 9/9

8/31

9/9

9/1 9/10

9/1

9/10

9/2 9/13

9/2

9/13

9/3 9/14

9/3

9/14

9/4 9/15

9/4

9/15

Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23April May June July August September

2010

Task

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

Rolled Up Milestone

Baseline Summary

Rolled Up Baseline

Rolled Up Baseline Milestone

Rolled Up ProgTask

Progress

Baseline

Milestone

Baseline Milestone

Summary

Rolled Up Task

TORISHIMA CONSORTIUM

Page 15

Project: NHON TRACH 2 - 750MW CCPPInstallation of Spool Pieces for MCW PipeDate: Wed 3/10/10

Page 45: NT2-L3-M-000-21-00005 Rev. C

TORISHIMA –AF COLENCO-LILAMA 18 JSC

76BUI THI XUAN,HAI BA TRUNG DI STRICT, Tel : 84-4-943 7880 HANOI, VIETNAM Fax : 84-4-943 7875/7876

Page 45

8.7 Exhibit G – Main Cooling Water Pipe Installation Plan

Page 46: NT2-L3-M-000-21-00005 Rev. C
Page 47: NT2-L3-M-000-21-00005 Rev. C
Page 48: NT2-L3-M-000-21-00005 Rev. C