Social Monitoring Report
Bi-annual Social Monitoring Report July 2012
PAK: Power Distribution Enhancement Investment
Program, Tranche 2
Prepared by Islamabad Electric Supply Company (IESCO), Islamabad for the Asian
Development Bank.
NOTES
(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its agencies ends on 30 June.
(ii) In this report, "$" refers to US dollars.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
ADB Bi-annual Social Safeguards Monitoring Report
Project Number: 2727 — PK, Tranche — II {Jan — June, 2012}
Islamic Republic of Pakistan
Power Distribution Enhancement Investment Project (PDEIP) — Tranche — II Multi — Tranche Financing Facility (MFF)
Financed by the ASIAN DEVELOPMENT BANK
Prepared by
(Mr. Sher Afzal / Mr. Mohammad Yasin)
Environment & Social Safeguards Section —Management Unit
Office of the General Manager (Development)
ISLAMABAD ELECTRIC SUPPLY COMPANY (IESCO)
IESCO Head Office,
Street 40, G — 7 / 4, Islamabad, Pakistan.
For Islamabad Electric Supply Company (IESCO) Pakistan Electric Power Company (PEPCO)
This report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents.
Asian Development Bank
ABBREVIATIONS
ADB Asian Development Bank
ADB TA ADB Technical Assistance (Grant for Project preparation)
AHs Affected Households
AJK Azad Jammu & Kashmir
BPI British Power International
E&SS Environmental and Social Safeguard
EA Executing Agency
EIA Environmental Impact Assessment
EPA Environmental Protection Agency
EPD Environmental Protection Department
GMD General Manager Development
GOP Government of Pakistan
GRC Grievance Redress Committee
GS Grid Substation
HA Hector Area
IA Implementing Agency
IEE Initial Environmental Examination
IESCO Islamabad Electric Supply Company
Km Kilometer
KV Kilo - Volt
LARP Land Acquisition and Resettlement Plan
m2 Square meter
MOW&P Ministry of Water and Power
MEE Multi - Tranche Financing Facility
NOC No Objection certificate
PAPs Project Affected Persons
PDEIP Power Distribution Enhancement Investment Program
PEPA Pakistan Environmental Protection Act
PEPCO Pakistan Electric Power Company
PMU Project Management Unit
MU Management Unit
ROW Right of Way
TL Transmission Line
Bi Annual Social Safeguards Monitoring Report ADB (January -June 2012)
DEFINITION OF TERMS
Affected Persons (AP'S) All the people affected by the project through land acquisition, relocation, or loss of incomes and include any person, household (sometimes referred to as affected households (AH's) or project affected family), firms, or public or private institutions. AH's therefore include; i) persons affected directly by the safety corridor, right-of-way, tower or pole foundations or construction work area; (ii) persons whose agricultural land or other productive assets such as trees or crops are affected; (iii) persons whose businesses are affected and who might experi ce loss of income due to the project impact; (iv) persons who lose work employment as a result of project impact; and (v) people who los access to community resources/property as a result of the project.
Compensation Payment in cash or kind for an asset to be acquired or affected by a project at replacement cost at current market value.
Cut-off Date The date after which people will NOT be considered eligible for compensation i.e. they are not included in the li t of AHs as defined by the Census. Normally, the cut-off date is the last da of the Resettlement Field
Surveys (RFS).
Due diligence Report Projects which do not have any significant s• ial impacts hence do not involve/ require any land acquisition theref re; a brief due diligence report (DDR) is prepared for the documentary r uirements.
Environment Surroundings in which an organization oper. tes, Including air, water, land, natural resources, flora (Plants), fauna ( als), humans, and their
Interactions.
Environmental Aspect Element of an organization's activities or pro• ucts or services that can interact with the environment; environmental a • pects can be Significant or non-significant based on environment risk Assessment and a significant
aspect can have.
El A Detailed study based on environmental assessment (EA) to determine the type and level of effects an existing facility is having, or a proposed project would have, on its natural environment
Encroachers Those people who move into project area after the cut-off date and are therefore not eligible for compensation or other rehabilitation measures provided by the project.
Entitlement The range of measures comprising cash or kind compensation, relocation cost, income rehabilitation assistance, transfer assistance, income substitution, and relocation which are due to /business restoration which are due to AHs, depending on the type and degree nature of their losses, to restore their social and economic base.
GRC Grievance Redressal Committee
GRP Grievance Redressal Process/ Procedure
IEE A Preliminary attempt to evaluate environmental impacts in order to determine whether a full-scale environmental impact assessment is needed.
Land acquisition
E&SS - MU - IESCO
The process whereby a person is compelled by a public agency to alienate
Page 3 of 20
Bi Annual Social Safeguards Monitoring Report ADB (January -June 2012)
all or part of the land s/he owns or possesses, to the ownership and possession of that agency, for public purposes, in return for fair
compensation.
LARP Projects which do have significant socio-econo c impacts hence involve/ require land acquisition therefore; a deta 1 land acquisition and resettlement plan (LARP document) is prep d for the documentary requirements.
Non-Titled Those who have no recognizable rights or clai to the land that they are occupying and includes people using priva or state land without permission, permit or grant i.e. those people Ihout legal title to land and/or structures occupied or used by them. A B's policy explicitly states that such people cannot be denied compensatio
Replacement Cost The method of valuing assets to replace the lo s at current market value, or its nearest equivalent, and is the amount f cash or kind needed to replace an asset in its existing condition, witho t deduction of transaction
costs or for any material salvaged.
Resettlement Field Survey The detailed inventory of losses that is completed after detailed design and marking of project boundaries on the ground, socioeconomic data on the affected households/families, and stakehold r consultations.
Sharecropper The same as tenant cultivator or tenant far er, and is a person who cultivates land they do not own for an agreed proportion of the crop or harvest.
Significant Impact 200 People or more will experience major irnpac , which are defined as; (i) being physically displaced from housing, or (ii) osing ten per cent or more of their productive assets (income generating).
Social Impact Assessment Social Impact Assessment is analyzing, monitoring, and management of
social consequence of development interventio project infrastructure.
Vulnerable Any people who might suffer excessively marginalized from the effects of resettlement headed households with dependents; (ii) disa poor households (within the meaning given pr elderly households with no means of suppo security of tenure; (vii) ethnic minorities; and (v landholdings of five acres or less).
face the risk of being and includes; (i) female-led household heads; (iii) viously); (iv) landless; (v) (vi) households without
.i) marginal farmers (with
Resettlement Field Survey The detailed inventory of losses that is completed after detailed design and marking of project boundaries on the grou d, socioeconomic data on the affected households /families, and stakehol er consultations.
S-P Sub-project
Sharecropper The same as tenant cultivator or tenant far er, and is a person who cultivates land they do not own for an agreed proportion of the crop or harvest.
E&SS - MU - IESCO Page 4 of 20
ADB (January -June 2012)
Bi Annual Social Safeguards Monitoring Report
TABLE OF CONTENTS
2 3 6 6
ABBREVIATIONS DEFINITION OF TERMS 1: INTRODUCTION
1.1 IESCO
1.2 Power Distribution Enhancement Investment Program 6
1.3 Power Distribution Enhancement Investment Project (PDEIP) Tranche-II 6
1.4 Objective of the Project - PDEIP (Tranche-II) 7
1.5 Scope of the Work 8
1.6 Management Structure - Directorate of CE (Development) / M agement Unit 8
MANAGEMENT STRUCTURE OF E&SS - MU - IESCO 9
2. SOCIAL SAFEGUARD STATUS 10 2.1 Compliance Status with Statuary Requirements
10
2.2 Social Documentation & Disclosure
10
2.3 Present Status of the Project.
13
2.4 Grievance Redress Committee (GRC)
15
2.5 Social Awareness & Trainings 15
2.6 Internal Monitoring & Field Visits 15
2.7 Project Compliance Chart 16
ANNEX - A 18 IESCO JURISDICTION MAP 18
ANNEX - B 19 DETAIL SCOPE OF WORK OF TRANCHE - II SUBPROJECT 19
ANNEX - C 20 Figure 2: Organizational Structure of MU - IESCO 20
LIST OF TABLES 1. Program Basic Information
6
2. Project Compliance Chart 16
E&SS - MU - IESCO Page 5 of 20
Bi Annual Social Safeguards Monitoring Report
1: INTRODUCTION
ADB (January -June 2012)
IESCO Islamabad Electric Supply Company Ltd. (IESCO
company, having more than 02 Million consumers an
Nos. Northern Districts of the Punjab Province (Raw
and Chakwal); Capital Territory (Islamabad); and
Jammu & Kashmir (AJK). IESCO jurisdiction map is pl
a public utility
vides service to 04
di, Attock, Jhelum
em parts of Azad
d at Annex - A.
1.2 Power Distribution Enhancement Investment Program 2. Government of the Islamic Republic of Pakistan (GoP)
Water and Power (MOW&P) with assistance of Asian
(ADB) is implementing the Power Distribution Enhan
Program (PDEIP) under Multi Tranche Financing F
Program is part of the GoP long term energy securi
Electric Power Company (PEPCO) has been nominated b
and Power (MOW&P) to act as the Executing Agency (E
ough Ministry of
evelopment Bank
ement Investment
cility (MFF). This
strategy. Pakistan
Ministry of Water
) while Islamabad
Electric Supply Company (IESCO) is the Implementing Agency (IA) for
execution work in its service area.
1.3 Power Distribution Enhancement Investment Project (PDEIP)-Tranche-II 3. The Power Distribution Enhancement Investment Project (PDEIP) Tranche-II
is designed to provide grid-connected customers with adequate and reliable
supply of electricity. The rehabilitation, augmentation, and expansion of
power distribution infrastructure will increase the reliability of supply to
residential, agricultural, commercial, and industrial customers across
Pakistan. A reliable electricity supply will lead to s ial and economic
benefits and improved conditions for schools, hospitals, d social services,
among others. The main components of the program are ben as under:
■ Conversion / Up-gradation of Grid Stations
■ Extension of Power Transformers in existing Grid Stations
■ Augmentation of Power Transformers in existing Grid Stations
■ New Transmission Lines
■ Remodelling of Transmission Lines
E&SS - MU - IESCO Page 6 of 20
Bi Annual Social Safeguards Monitoring Report ADB (January -June 2012)
■ Installation of capacitors on 11 KV
■ Rehabilitation works
■ System Modernization
4. The projects basic information is provided in Table 1.
Table 1: Program Basic Information.
The Program Power Distribution Enhancement Investment Program (PDEIP). Multi - Tranche Financing Facility (MFF).
Subproject Tranche - II subproject.
Sponsoring Agency Government of Pakistan. Ministry of Water & Power (MoW&P).
Executing Agency Pakistan Electric Power Company (PEPCO).
Implement Agency Islamabad Electric Supply Company (IESCO).
Type of Financing Loan amount US $ 24.86 Million. Loan No. 2727 - PK ; Tranche - II Subproject. Loan No. 2728 - PK ; Support Project.
Loan Signing Date January 28, 2011.
Loan Effectiveness Date October 05, 2011.
Closing Date March 31, 2015.
Date of Last ADB Review Mission
March 05, 2012.
Focal Person General Manager (Development), Management Unit , Islamabad Electric Supply Company (IESCO).
Focal Person for Environment & Social Safeguards
Deputy Manager (E&SS), Project Management Unit, Islamabad Electric Supply Company (IESCO).
1.4 Objective of the Project - PDEIP (Tranche-II) 5. The main objectives of this Investment Program are; (i) improve power
distribution infrastructure through system rehabilitation, augmentation, and
expansion; and relieve the power system from distribution bottlenecks and
constraints; (ii) enable continued operation and mainte ce in accordance
E&SS - MU - IESCO
Page 7 of 20
Bi Annual Social Safeguards Monitoring Report ADB
(January -June 2012) with best international practices; and (iii) the system will be capable of
meeting peak demand, with electricity outages significantly reduced.
1.5 Scope of the Work 6. IESCO Tranche - II subproject includes 01 No. Co
Extension/ Augmentation, 02 Nos. Transmission Lin
Transmission Lines (Remodeling) & Capacitors &
Equipment. The detailed scope of work of Tram
attached at Annex - B.
versions, 09 Nos.
s (New), 01 No.
llaneous Electrical
- II subprojects is
1.6 Management Structure - Directorate of GM (Developm nt) / MU 7. To carry out and handle the investment projects I Sl 0 has established
Management Unit under the aciministr ti e control of
General Manager (Development). The MU comprises o four sections. The
main responsibilities of these sections are summarized be ow.
i. Planning Scheduling & Coordination: To take the responsibilities for
(i) identifying and proposing the subprojects to PEP O / Donor Agency
for approval and financing, (ii) Scheduling and Monitoring
(iii) preparing the necessary documentation in line with the statutory,
corporate and Donor policies including quarterly re its (iv) coordinate
with the consultants.
ii. Procurement: To take care of all responsibilities d tasks related to
procurement (goods, works and services) and for the activities related to
material planning, preparation of bidding docume is according to the
requirement of the Donors, getting the evaluation dine and for placing
the orders after approval of the Donors, inspection and then
transportation to the site. Arrange release of mat rial through Chief
Resident Representative (CRR) Karachi and final deli ery to the site.
iii. Project Finance: They are responsible for taking are of counterpart
financing, funds flow arrangements, paymen.., recording and
monitoring of both ADB & WB funds. Also, will es blish, monitor and
manage the imprest account and statement of expenditure (SOE)
procedures. Furthermore ensure timely preparati on of the annual
audited project accounts.
E&SS — MU — IESCO Page 8 of 20
Bi Annual Social Safeguards Monitoring Report ADB (January -June 2012)
iv. Environment & Social Safeguard: To take c• e of all the
responsibilities and tasks related to environmen land, and social
(including involuntary resettlement and indigenous u eople) and provide
oversight on occupational health, safety and env* o i ent safeguards in
the working environment. The Environmental Social Safeguard
(E&SS) Section of MU, IESCO provides an over • supervision and
advisory services during the Pre - Constructiotit hase, Construction
phase & Post - Construction phase of the project. e E&SS also assists
and advises GSC Directorate, Construction Directorate and other IESCO
departments on environmental and social matters. resently, the E&SS
Section has one Environmental and one Social Imp t expert under the
supervision of a Deputy Manager Environmental d Social Safeguard
(E&SS). The organizational structure of E&SS - IESCO is given
below in Figure-1
Figure-1: MANAGEMENT STRUCTURE OF E&SS - MU - IESCO
GM (Development)
M. Yousaf Awan
Dy. Manager (E&SS)
Mohammad Yasin
Asstt. Manager (Social Impact)
Sher Afza I
Asstt. Manager (Environment)
M. Imran Malak
E&SS - MU - IESCO Page 9 of 20
Bi Annual Social Safeguards Monitoring Report ADB (January -June 2012)
2. SOCIAL SAFEGUARD STATUS
2.1 Compliance Status with Statuary Requirements 8. The loan agreement of the project requires the Implementing Agency (IA) to
implement the project in compliance with s to / regulatory
requirements of the country and requirements of D Guidelines (May
2003). The detail of environmental & social compliance r garding statuary /
regulatory requirements in accordance to ADB & Natio al Law is tabulated
below.
No. Regulatory Requirements Status of Compli ce
1. Preparation of Land Acquisition &
Resettlement Plan (LARP).
Short LARPs pre ared.
2. Clearance from ADB. Clearance given by ADB.
3. Clearance/ obtaining No Objection
Certificate (NOC) from the
Environmental Protection Agency
(EPA).
Public hearing for
Left Bank to Rajja
Saiden Shah to N
Transmission line
30th April, 2012. P
132 KV Bagh _ H
line will be held after
date & venue by the
132 KV Mangla
and 132 KV Choa
or Pur Sathi
have been held on
blic hearing for
than Transmission
finalization of
AJ&K.-EPA.
2.2 Social Documentation & Disclosure
2.2.1 Short Land Acquisition & Resettlement Plans (LARPs)
9. The following Short Land Acquisition and Resettlement kris (LARPs) have
been prepared by M/S BPI for the project componen which have been
approved by ADB and IESCO. Their Urdu Version is vailable on IESCO
website for public information.
i. Short LARP of Bagh - Hattian 132 KV Transmission Line.
ii. Short LARP of Mangla Left Bank - Rajjar 132 KV ransmission Line.
E&SS - MU - IESCO Page 10 of 20
Bi Annual Social Safeguards Monitoring Report ADB (January -June 2012)
iii. Short LARP of Choa Saidan Shah - Noor Pur Sethi Grid Station &
132 KV Transmission Line.
I. Bea - Hattian 132 kV Transmission Line Subproject:
10. The Bagh - Hattian 132kV transmission line subproject has been proposed by
Islamabad Electric Supply Company (IESCO) to improve electric power
supply in Hattian area of Muzaffarabad district of Azad Jammu Kashmir
(AJK). The existing 66kV grid station at Hattian will be converted into 132kV
and connected to Bagh 132kV grid station by means of a new 25.22 km long
transmission line (TL). The new 132kV equipment Will be installed within
the bounds of the existing grid station, without acquiring any additional
land. The transmission line will traverse a government forest and five
villages, of which two villages are in Bagh district . a three villages in
Muzaffarabad district.
11. The grid station's conversion works will be carried out within the existing
boundary, and no additional land will be acquired for this purpose.
However, construction of the new transmission line will affect 12,420 m2 of
crops and 932 wood trees (918 forest trees and 14 private trees), thereby
affecting 6 farming households (AHs), with a population of 84 (APs). No
land will be acquired permanently for this subproject, nor it will affect built-
up structures or fruit trees. None of the six AHs will be displaced or lose
more than 10% of their productive assets.
IL Choa Saiden Shah to Noor Pur Sethi 132 kV Transmission Line
Subproject:
12. The Choa Saidan Shah to Noor Pur Sethi (CSS-NPS) 13 V transmission line
subproject has been proposed by IESCO to improve elec u is power supply in
Noor Pur Sethi area in Chakwal district of Punjab pr. wince. The existing
66kV grid station at Noor Poor Sethi will be convert d into 132kV and
connected to Choa Saidan Shah 132kV grid station by m-ans of a new 47.65
km long transmission line (TL).
E&SS — MU — IESCO Page 11 of 20
Bi Annual Social Safeguards Monitoring Report
ADB (January -June 2012)
13. The new 132kV equipment will be installed within e boundary of the
existing grid station without acquiring any additional 1 d, and therefore,
there will be no impacts of this component. The new 1 2kV double circuit
transmission line will pass through six villages of M akwal district and
temporarily affect a total of 55.15 HA of land with agric tural crops and 148
trees (79 fruit and 69 wood trees). The subproject will feet a total of 171
farming households (AHs) losing agricultural crops an• trees, with a total
population of 2,158 (APs). No built-up structures will e affected by this
subproject. None of the AHs are to be displaced or I s more than 10% of
their productive assets.
III. Man la Le Bank to Ra''ar 132 kV Transmission Line Sub ro ect:
14. The Mangla Left Bank to Rajjar 132kV transmission line .ubproject has been
proposed by IESCO to improve electric power supply in ajjar area in Gujrat
district of Punjab province. The existing 66kV grid station at Rajjar will be
converted into 132kV and connected to Mangla Left B• 132kV grid station
by means of a new 44.76 km long transmission line.
15. The new 132kV equipment will be installed within e boundary of the
existing grid station, without acquiring any ad• 'tional land. The
transmission line will pass through nine villages of Mirpur district of Azad
Jammu Kashmir (AJK) and Gujrat district of Punjab province. The
construction and stringing works of transmission line will affect 53.72 HA of
crops and 332 wood trees. Besides, some six built-up ctures (4 houses
and 2 boundary walls) are found falling in outer fringes of the transmission
line which are likely to be partially damaged during t e stringing activity
only. Altogether, the TL's execution works will affect 200 farming
losing agricultural
uffer from partial
walls of houses,
d). However, none
r compensated for
households (AHs), with a total population of 2,594 (APs)
crops and trees, and 5 AHs among them will also
damages to their structures (4 houses and 2 boun
one AH will have both house and boundary wall affect
of these structures will be removed and relocated, rath
E&SS - MU - IESCO Page 12 of 20
Bi Annual Social Safeguards Monitoring Report ADB (January -June 2012)
repairing the partial damages. As none of the Ahs will be displaced or lose
more than 10% of their productive assets.
2.3 Present Status of the Project.
16. The civil works of Tranche - II Subprojects have been
works awarded is as below:
awarded, the detail of
No. Package Lot No. Description of Work
Length of T/L (KM)
Nos. of Locations
Awarded to Contract
Signed Date
1 ICB-
11/TR- II/ADB
I
Procurement of Plan t, Design , Supply, Installation, Testing, Commissioning, & Civil Works of 132 KV Noor Pur Sethi (AIS) Grid Station District Chakwal on Turn Key Basis.
- 1
M/s Siemens (Pakistan) Engineering Co. Ltd. Islamabad.
May 15, 2012.
2 ICB-
11/TR- II/ADB
II
Procurement of Transmission Line Material , Construction Survey, Tower Sticking , Construction of Tower / Pile Foundation, Erection, Stringing, Testing & Commissioning of 132 KV T/ L from Hattian to Bagh (AJ&K) For Bagh Grid Station.
25.23 - M/s Pingaoo -Potential (JV), Lahore
Apri116, 2012.
3 ICB-
11/TR- II/ADB
III
Procurement of Transmission Line Material , Construction Survey, Tower Sticking , Construction of Tower / Pile Foundation, Erection, Stringing, Testing & Commissioning of 132 KV SDT T/L from Mangla Power House to Rajjar Grid Station on ACSR Rail Conductor.
49.2 - M/s Pingaoo - Potential (JV), Lahore
May 24, 2012.
4 ICB-
11/TR- II/ADB
4 IV
Procurement of Transmission Line Material, Construction Survey, Tower Sticking, Construction of Tower / Pile
Erection, Stringing,
. ,.., . ,, stinging, iesting or Commissioning of 132 KV T/L from Noor Pur Sethi to Choa Saiden Shah for Noor Pur Sethi Grid Station.
47 65 - M/s Pingaoo -Potential (JV), Lahore
April 16, 2012.
E&SS - MU - IESCO Page 13 of 20
Bi Annual Social Safeguards Monitoring Report
ADB (January -June 2012)
17. Orientation / pre - construction meeting were arranged •y E&SS section for
the contractors and they have been made aware of the responsibilities as
per the EMP.
18. Being in Federal Capital, the EIA report along with shot LARP report was
submitted to Pak - EPA on January 01, 2011 for issuance of NOC after the
approval of CEO, IESCO. Pak - EPA further processed e reports to Punjab
EPA & AJ&K EPA. The inspector of Punjab EPA visite•the project sites in
March - April 2011.
19. The comments of Pak - EPA, Punjab EPA & AJ&K EPA have been received
and their replies have been submitted vide Letter No. P U/E&SS/ADB-Tr
11/2702-03 dated 14.06.2011 & Letter No. PMU/E&SS/ADB-Tr II/4311-13
dated 21.09.2011.
20. Public Hearing session was held for the 132 KV Mangla Left Bank to Rajjar
and 132 KV Choa Saiden Shah to Noor Pur Sethi Tans sion Lines on 30th
April, 2012 at 66 KV Grid Station Noor Pur Sethi. The Pak EPA has been
requested to issuance of NOC in this regard.
21. The Public Hearing session for the 132 KV Bagh to Hatti•Transmission
Line will be held after finalization of date & venue b AJ&K - EPA.
IESCO is perusing the matter on priority basis.
22. The EIA/LARP Reports for sub projects under Tran e - II have been
approved by CEO IESCO & are available o IESCO website
(www.iesco.com.pk).
23. The demarcation of Transmission Lines is yet to be done by the GSC
Directorate; hence the up-dation of entitlement matrix as delayed. Several
meetings have been held between GSC Directorate • Social Safeguard
section for carrying out the demarcation & updating of entitlement matrix.
E&SS - MU - IESCO Page 14 of 20
Bi Annual Social Safeguards Monitoring Report ADB (January -June 2012)
2.4 Grievance Redress Committee (GRC) 24. To address and resolve the complaints & issues of Proj t Affected Persons
(PAPs) related to the components of Tranche - II s b projects, IESCO
constituted Grievance Redressal Committee (GRC) on 11 07 - 2009 inline of
the ADB Social Safeguard Policy. The committee member are as follow:
i. Project Director (GSC/ C&O)
ii. Deputy Manager (E&SS)
iii. Assistant Manager (Social Impact)
iv. Environment and Social Inspector
v. Contractor Representative
vi. Community Representative
C. vener
Member
M mber
Member
Member
Member.
25. To facilitate Project Affects Person (PAPs) and Stakehol • ers for registering
their complaints for immediate and amicable resolution complaint register
has been placed at the Office of General Manager (Develo •went).
2.5 Social Awareness & Trainings 26. An Awareness campaign regarding Communicable iseases has been
initiated to educate the workers regarding communicabl diseases especially
HIV/ AIDS, Hepatitis, Tuberculosis (TB) and Drugs. Pam hlets / Leaflets for
awareness regarding TB, HIV/ AIDS, Hepatitis and Drugs have been
prepared, printed and distributed to IESCO's GSC Directorate.
27. A number of trainings of have also been conducted for IESCO staff on
environmental and social aspects.
2.6 Internal Monitoring & Field Visits 28. Internal monitoring of the projects will be carried out by Environmental and
Social Safeguard (E&SS) section MU, IESCO during the xecution phase for
the smooth and effective implantation of Resettle ent Plan (RP) &
Environmental Monitoring Plan (EMP) under monitor' g indicators set by
ADB. To fulfill the requirements meetings were held wi Contractors.
E&SS - MU - IESCO Page 15 of 20
Bi Annual Social Safeguards Monitoring Report (January -Tune 2012)
Description of Indicator. Remarks.
Construction activities and Project Progress during previous 6 months.
Presently the documentation component of phase. The civil works Subprojects have contractors.
project
project is in phase and no
is in execution
of Tranche - II been awarded to
Changes in project organization and Environmental Management Team.
No change.
Relationships with Contractors, Owner, Lender, etc.
A meeting with Engineering Co. been held on June to 132 KV Noor Station District
A meeting with (JV), Lahore has 2012 with respect Hattian to Bagh T/L from Mangla Rajjar Grid Station Noor Pur Sethi to
M/s
M/s
(
Chakwal.
been
Choa
Siemens (Pakistan) Ltd. Islamabad has 19, 2012 with respect Pur Sethi (AIS) Grid
Pingaoo - Potential held on July 12,
to 132 KV T/L from A.J&K), 132 KV SDT
Power House to & 132 KV T/L from
Saiden Shah.
ADB
E& SS - Mlt - IESCO Page 16 of 20
Bi Annual Social Safeguards Monitoring Report ADB
anuary -June 2012) 2.7 Project Compliance Chart
29. The compliance status of Tranche - II Subprojects is
Table - 2.1.
Table 2.1: Compliance Status with Statuary & Regulatory equirements.
enlisted below in
No. Description Status of Compliance
1. Establishment of MU in IESCO. Yes.
2. Induction of Social Safeguard Staff in MU. Yes.
3. Preparation of Short Land Acquisition &
Resettlement Plan / Reports (LARP Reports). Yes.
4. Clearance & approval of IEE / EIA and LARP
Reports from ADB. Yes.
5. Approval of IEE / EIA and LARP Reports from
CEO, IESCO. Yes.
6. Urdu Translation of Short Land Acquisition &
Resettlement Plan / Reports (LARPs) Yes.
7. Uploading of EIA and LARPs Reports on IESCO
website. Yes.
8. Submission to Concerned EPA / EPD. Yes.
9. Public Hearing. Public hearing for 132 KV Mangla
Left Bank to Rajjar and 132 KV Choa
Saiden Shah to Noor Pur Sathi
Transmission Lines have been held on
30th April, 2012. Public hearing for
132 KV Bagh - Hattian Transmission
line will be held on finalization of
date & venue by the AJ&K.-EPA.
10. Clearance/ obtaining No Objection Certificate
(NOC) from the EPA / EPD. In process, Matter being followed up.
11. Constitution of Grievance Redressal Committee Yes.
12. Complaint Register available. Yes.
13. Awareness regarding communicable diseases. Yes.
14. Training on Environment & Social Issues. Yes.
15. Internal Monitoring & Field Visit. After the initiation of construction
phase.
16. Project present Status. No physical work initiated.
E&SS — MU — IESCO Page 17 of 20
Page 18 of 20
Bi Annual Social Safeguards Monitoring Report ADB (January -June 2012)
ANNEX - A
IESCO JURISDICTION MAP
AREA OF RESPONSIBILITY (DISTRICT WISE)
RAWALPINDI
E&SS - MU - IESCO
ADB (January -June 2012)
ANNEX - B
Bi Annual Social Safeguards Monitoring Report
DETAIL SCOPE OF WORK OF TRANCHE - II SUBPROJECT
Cost & Scope of Tranche-II Projects
Sr. No.
Project Component Amount (Us $ Mill)
01 Conversions 01 No.
2.32 i. Conversion of NPS Grid Station on Turnkey Basis
02
Extension / Augmentation 09 Nos.
6.00
i. Mangla Right Bank (R. B. Mangla) ii. Satellite Town iii. H-11 Islamabad iv. Pindi Gheb v. Hajeera vi. Minhasa vii. Mangla Left Bank (L.B.Mangla) viii. E-8 Islamabad ix. Line Bay Extensions
03
Transmission Lines (New) 02 No. 6.27
i. Hattian to Bagh Transmission Line
ii. Choa Saiden Shah - Noorpur Sethi Transmission Line
04 Transmission Lines (Remodelling) 01 No.
3.66 i. Mangla - Left Bank Magla - Rajjar Transmission Lines
05 Capacitors & Miscellaneous Equipment 5.50 Total 23.75