    NOVEMBER 2012

    FARRELL DESIGN STUDIO

    Pennyfeathers Development

    Isle of Wight

    Environmental statement: Non-technical summary

    110405

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    2/23

    Pennyfeathers Development: Non-technical summary i

    Contents

    INTRODUCTION.....................................................................................................................................1The project team...........................................................................................................................1SITE DESCRIPTION...............................................................................................................................2Site and its surroundings ..............................................................................................................2Site landform, watercourses, geology and soil ................................................................................2Site cultural and archaeological heritage......................................................................................3Existing noise and air quality ........................................................................................................3

    CONSULTATION....................................................................................................................................6Background to the development...................................................................................................6Public consultation on the scheme...............................................................................................6

    NEED FOR THE DEVELOPMENT.........................................................................................................7PROJECT DESCRIPTION......................................................................................................................8

    Project alternatives .......................................................................................................................8APPROACH TO THE EIA ....................................................................................................................10EIA ISSUES AND FINDINGS...............................................................................................................12

    Construction and environmental management...........................................................................12Soils and geology .......................................................................................................................14Hydrology and flood risk .............................................................................................................14Archaeology................................................................................................................................14Ecology..15Landscape and visual aspects ...................................................................................................15Air quality ..16Noise and vibration.....................................................................................................................16Socio-economics ........................................................................................................................17Traffic.17Sustainability...............................................................................................................................19

    WHAT HAPPENS NEXT? ....................................................................................................................21CONTACT DETAILS ............................................................................................................................21

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    3/23

    Pennyfeathers Development: Non-technical summary 1

    INTRODUCTION

    This document is the non-technical

    summary (NTS) of the environmental

    statement (ES) for the Pennyfeathers

    Development, near Ryde on the Isle of

    Wight. It describes in non-technical

    language the proposed development and

    the potential impacts it may have on the

    physical and biological environment and on

    people. It also lists the measures that the

    developer will implement to avoid or reduce

    adverse impacts and to enhance potential

    social benefits, and describes howenvironmental issues will be managed

    during and after construction.

    The ES presents the complete findings of the

    environmental impact assessment (EIA), and

    is one of the documents accompanying the

    outline planning application submitted under

    the Town and Country Planning Act 1990.

    The primary purpose of the ES is to inform

    the planning and decision making process by

    reporting the results of the EIA, and inparticular any significant environmental

    effects. The authority determining the

    application is the Isle of Wight (IoW) Council.

    They have confirmed that the development

    requires an ES to be submitted alongside the

    planning application.

    If you have any questions or would like to

    comment on the application then you can

    find out how to do so at the end of this NTS.

    The project team

    The site developer is The Pennyfeathers

    Property Company Limited. The Project

    Team working on behalf of the developer on

    planning, design and environmental issues

    included:

    Farrell Design Studio who prepared themaster plan

    Hepburns Planning Consultancy Limitedwho is the planning consultant for thescheme

    RSK Environment Limited (RSK) whoundertook the EIA and prepared theenvironmental statement.

    RSK was responsible for undertaking and

    managing the EIA studies, using their in-

    house resources supplemented by the

    following specialist consultants:

    Glanville Consultants Ltd for the transportassessment

    Frankham Consultancy Group Ltd for allengineering and design issuesassociated with access and modificationsto the railway, stations/platforms.

    Box 1: Project overview

    The proposed development on around 53 ha of land will consist of a mainly residential scheme(904 dwellings) comprising a mix of housing types and supporting commercial areas (e.g. officesor local shops), landscaped open space and leisure/recreation areas, and a school, whilstretaining and enhancing features of the existing landscape and valued ecological habitats. Thedevelopment will need to be serviced by supporting infrastructure including sewerage anddrainage, electricity and gas supply, and telecommunications. District heating infrastructure(subject to ongoing feasibility work) will be developed on the site.

    Enhanced transport links will be provided. These will include provision for future access to theexisting railway station(s) adjacent to the site, as well as provision of local roads andimprovements to existing road junctions, and extensions of cycleways and footpaths through thedevelopment, which in turn will enhance linkages to the local and regional networks.

    Environmental factors were considered from the earliest stage of the proposals and so the

    planning and engineering design and layout has been developed in response to awareness of theenvironmental issues of the area. The layout design in the master plan has therefore alreadyincorporated a number of measures designed to avoid or reduce environmental impacts.

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    4/23

    Pennyfeathers Development: Non-technical summary 2

    SITE DESCRIPTION

    Site and its surroundingsLocated on the southern edge of Ryde, Isle

    of Wight (Figure 1), the Pennyfeathers site

    comprises mainly fields in agricultural use

    (currently used for pasture/grazing or

    hay/silage) classified as mostly (~70%)

    grade 3b (moderate quality) agricultural

    land. The site also comprises hedgerows,

    woodlands, a permanent stream

    (Monktonmead Brook) and some ephemeral

    spring-fed streams. Also included in the siteis a farm and associated agricultural

    buildings (Prestwood Grange), a pound

    store open to the public and a garage with

    car showroom. The cemetery and an

    adjacent existing electricity substation

    compound are not included within the

    scheme.

    For the purpose of the planning application,

    the site area is shown to include parts of

    Smallbrook Lane/Great PrestonRoad/Brading Road and the Westridge

    Cross junction (see Figure 2). This is to

    accommodate planned highways works (re-

    alignments and junction improvements)

    proposed to be implemented under the

    Pennyfeathers scheme as components to

    support the development.

    Similarly, the site area also spans across the

    existing Island Line Railway and steam

    railway at Smallbrook junction. This is toaccommodate connection of a cyclepath and

    footbridge from the Pennyfeathers

    development, ultimately connecting to both

    of the railway stations, and further on

    towards the Smallbrook stadium.

    The southern extension of the site area

    down to Harding Shute merges into the

    western edge of Whitefield Wood and in this

    portion is mostly plantation woodland. A

    footpath and cycle track will be formed in

    this area together with habitat

    enhancements including native tree planting.

    Land uses adjoining the site include some

    commercial areas along Brading Road to the

    east and residential areas of Ryde to the

    north. Land to the west is mostly agricultural

    holdings whereas the southern boundary

    comprises small woodlands.

    Site landform, watercourses,

    geology and soilThe Monktonmead Brook has sculpted the

    topography of the site, the course of the

    brook currently following the western site

    boundary before discharging into the Solent

    at Ryde, some two kilometres to the north.

    Ground levels across the site fall gently from

    around 48.5 m above Ordnance Datum

    (AOD) at Brading Road down to 9.9 m AOD

    along Monktonmead Brook. A spring line

    approximately follows the 40 m contouracross the site. The spring line roughly

    defines the near-surface outcrop of the

    geological boundary between the River

    Terrace Deposits found at the higher

    eastern side of the site (beside Brading

    Road) and the underlying Bembridge Marl

    Formation, which forms the remainder of the

    site geology.

    An agricultural land survey concluded that

    the topsoils are in grade 3a and 3b. Some12 ha of land located across the eastern

    flank of the site, was classified as grade 3a

    with typically permeable, loamy topsoil and

    the remainder of the existing pasture was

    found to comprise grade 3b land, where the

    topsoil is a heavy or medium loam and clay

    subsoil at shallow depth. There is some

    made ground in areas of previous

    development (the former farmyard and

    slurry pit).

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    5/23

    Pennyfeathers Development: Non-technical summary 3

    Top of site adjacent to Brading road (behind hedge on left of picture) looking south toward Busy Bee Garden Centre

    There is a shallow aquifer in the River

    Terrace Deposits across the eastern flank of

    site, which seems to feed the local line of

    springs. There is a deeper confined but

    unproductive aquifer in the deeper

    Bembridge Limestone that lies underneath

    the negligibly permeable Bembridge Marls.

    Site cultural and

    archaeological heritage

    Although there are no scheduled

    monuments, UNESCO World heritage sites,

    registered parks and gardens or registered

    battlefields within the study area, the Isle of

    Wight has known records of human

    settlements. From extensive desktop

    searches (e.g. archive records, maps, aerial

    photographs, etc.) it is considered that the

    development site has a moderate potential

    for the survival of previously unknown

    archaeological remains, particularly with

    respect to the Bronze Age, medieval and

    post medieval periods. These factors were

    taken into account in development of the

    master plan.

    Existing noise and air quality

    The edge of town location and semi-rural

    nature of the site means it is not affected by

    any large air or noise pollution apart from

    existing traffic on Brading Road and

    Smallbrook Lane at the site boundary. (The

    steam railway emissions are quite localised).

    The site has good conditions for dispersion

    of any emissions and air quality is thereforegood and concentrations of pollutants are

    well below levels of any concern;

    background noise levels are also very low.

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    6/23

    Pennyfeathers Development: Non-technical summary 4

    Figure 1: Site overview and key features of the locality

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    7/23

    Pennyfeathers Development: Non-technical summary 5

    Figure 2: Site redline area

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    8/23

    Pennyfeathers Development: Non-technical summary 6

    CONSULTATION

    Background to thedevelopment

    Parts of the site have been the subject of

    several previous smaller planning

    applications in relation to existing land uses.

    However, the consolidation of land holdings

    has allowed the formulation of a larger vision

    for the area.

    Conceptual plans were developed and two

    community consultation events were held in2006 and 2007 to generate local interest

    and create input to the development

    process. A preliminary master plan was

    formulated in 2008 and this was subject to

    an environmental appraisal (September

    2008) to identify important constraints and

    opportunities of the site for optimising the

    project design. A further public exhibition

    was held in 2009.

    The current scheme is of smaller scale thanthat promoted in 2008 (it no longer includes

    development to the north of Smallbrook

    Lane) and the scheme has been significantly

    modified to account for increased knowledge

    of the site, greater understanding of the

    extent of public interest and aspirations, and

    the evolving national/regional planning

    framework.

    Public consultation on thescheme

    In addition to the community consultation

    events held in 2006, 2007 and 2009 on an

    earlier version of the scheme, a public

    exhibition was held at a local hotel in Ryde,

    Isle of Wight on 10th September 2011.

    Attendance throughout the day was very

    good with about 440 people attending. Often

    very strongly held views were expressed

    with representatives of the developers team

    and the EIA team, and there was a large

    amount of informed and informative

    feedback received, which has been taken

    into account in further scheme development

    and the impact assessment process.

    A request for an EIA screening and scoping

    opinion was sent to the IoW Council on 7 th

    June 2011 and the accompanying scopingreport was circulated to a range of

    consultees/organisations including Natural

    England and the Environment Agency. The

    screening and scoping opinion was received

    from the IoW Council on 14th July 2011.

    Copies of the EIA screening and scoping

    opinion are contained in the ES Volume 2,

    Annex 5.2 and Annex 5.3, respectively. As a

    result of this process, it was formally agreed

    that the EIA would consider environmental

    impacts of the development (both

    construction and post-construction) on a

    range of topics.

    In addition to the formal EIA process, other

    correspondence and discussions took place

    with a range of organisations including local

    landowners, utilities and transport

    companies, and local groups.

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    9/23

    Pennyfeathers Development: Non-technical summary 7

    NEED FOR THE DEVELOPMENT

    The proposed development at the

    Pennyfeathers site seeks to satisfy the need

    to provide a substantial proportion of the

    housing supply of the Island. The Core

    Strategy of the Island Plan envisages

    provision of 8,320 dwellings over the 16

    years from 2011 to 2027 (520 units/year)

    including 2,100 in the Ryde area.

    Furthermore, a fundamental principle

    underpinning the policies within the Core

    Strategy is to maximise all opportunities

    within, close to or adjacent to the settlementboundaries with access to public transport,

    local shops and services to encourage

    sustainable patterns of development and

    sustainable communities. Ryde is a key

    regeneration area, and the Pennyfeathers

    scheme will satisfy the above stated

    sustainable development criteria.

    The scheme has high regard to the highly

    valued natural and historic environment,

    seeking to provide houses, jobs, services,

    and supporting infrastructure whilst

    conserving and enhancing the natural

    environment. The scheme also anticipates

    likely demographic change and in particular

    seeks to meet the needs of the Islands

    increasingly ageing population, as well as to

    address the shortage of supply of affordable

    housing for people on low incomes and first

    time buyers.

    Box 2: The main benefits of the development

    Significant contribution to meeting the housing supply targets of the region

    Provision of accessible open space Provision of leisure facilities including sports pitches

    Improved connectivity via extension of cycle routes and footpaths

    Improved transport links, in particular the provision of a link road from Smallbrook Lane toBrading Road that would relieve pressure on the junction at Westridge Cross fromeast/southbound traffic

    Improved road junctions including additional turning lanes at Westridge Cross to relieveforecast junction capacity problems

    Improved junction of Smallbrook Lane and Great Preston Road to improve safety

    Improved alignment of Smallbrook Lane over the existing railway bridge to improve safety,including separation of road from the existing cycle track

    Ultimately, if acceptable to the rail operators, contribute to sustainable transport objectivesby providing a link to the existing Island Line station at Smallbrook Junction, as well asenabling a connection between the Island Line and the Steam Railway

    Contribute to sustainable transport objectives by providing a park & ride facility withconnection to Smallbrook Junction

    Relocation of the existing garage from Westridge Cross to a more favourable location,and enabling any necessary land remediation

    Enhancing the landscape and habitat connectivity with benefits to areas of ecologicalvalue

    Climate change mitigation

    Sustainable building design

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    10/23

    Pennyfeathers Development: Non-technical summary 8

    PROJECT DESCRIPTION

    The area subject to the planning application

    (the site redline) is shown in Figure 2. This

    encloses an area of about 53 hectares,

    although only the central part of the site

    would be developed for housing. The overall

    site master plan, illustrated in Figure 3, sets

    out the main development areas and

    infrastructure such as roads and paths.

    The development will comprise mostly

    housing up to a maximum of three storeys

    high. The mix of housing types will be as in

    Table 1.

    The master plan comprises 121 assisted

    living units, included in the total of 904 units.

    The scheme will be a phased development,

    with construction occurring over several

    years between 2014 and 2027.

    Project alternatives

    There are limited areas on the Isle of Wight,and in or around Ryde in particular, of such

    a scale that can offer opportunities for a

    consolidated village style development,

    rather than piecemeal ad hoc

    developments such as are possible on

    smaller pockets of development land that

    may from time to time become available.

    The current location is favoured for its

    proximity to the town centre via sustainable

    means of travel.

    Alternative layouts were developed as part

    of the scheme design and the most

    favourable alternative, which respects the

    constraints of the site, has been selected.

    For instance, internal roads have been

    aligned so as not bisect valued ecological

    habit. In addition, some variation in the

    development mix has been considered

    although the aim has always been to

    develop a residential scheme. The objective

    of the design put forward is to optimise site

    use whilst minimising environmental

    impacts. For instance, relatively low-rise

    structures have been selected that can be

    accommodated within the landscape setting.

    Other types of development such as

    extensive commercial or industrial were

    ruled out due to various factors such as

    constraints to development at this location,

    the abundant commercial areas to the east

    of Brading Road and the proposed industrial

    development to the north of Smallbrook

    Lane. The do-nothing alternative (to leave

    the site undeveloped) would mean that

    opportunities to improve sustainable

    transport and other linkages in the area, and

    the opportunity to meet increasing housing

    demand, would be foregone.

    Table 1: Housing types

    Number of unitsUnit type

    Affordable Market Total

    Affordable (%)

    1-bed 118 8 126 93.7%

    2-bed 97 20 117 82.9%

    3-bed 94 475 569 16.5%

    4-bed 6 86 92 6.5%

    Totals 315 589 904 34.8%

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    11/23

    Pennyfeathers Development: Non-technical summary 9

    Figure 3: Overall site master plan

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    12/23

    Pennyfeathers Development: Non-technical summary 10

    APPROACH TO THE EIA

    Environmental impact assessment (EIA) is a

    systematic process established in European

    Law1

    to identify, predict and evaluate theenvironmental effects of proposed projects.

    The authority determining the planning

    application2 (the IoW Council) have

    confirmed that the development requires

    submission of an environmental statement3.

    The purpose of the EIA is to:

    Provide a baseline against which actualproject impacts will be assessed

    Identify and assess the anticipatednegative and positive environmental andsocial impacts of projects

    Determine measures designed to avoid,minimise or mitigate negative

    1Directive on the Assessment of the Effect of Certain

    Public and Private Projects on the Environment(85/337/EC), as amended by Directives 97/11/EC,2003/35/EC and COM/2009/03782

    Planning application submitted under the Town andCountry Planning Act 19903

    The project falls under Schedule 2, Part 10b, of the Townand Country Planning (Environmental Impact Assessment)Regulations 2011 (S.I. No. 1824), as an urbandevelopment project of more than 0.5 hectare.

    environmental or social impacts andoptimise potential positive impacts

    Use the results of that assessment toinform option selection and subsequentproject design

    Consult with and obtain feedback fromproject stakeholders.

    Figure 4 shows the main stages of the EIA

    that were followed.

    Baseline environmental conditions were

    identified from a range of sources and field

    surveys as identified in Box 4.

    The scheme master plan was developed

    iteratively to allow incorporation of

    knowledge of site constraints gained from

    the baseline evaluations and to allow impact

    avoidance and mitigation measures to be

    designed-in from the outset as illustrated by

    the examples in Box 5.

    Box 3: Components of the development

    Residential (904 units of 1 and 2 bed apartments, assisted living units, one, two, three andfour bed houses, including 35% affordable housing)

    Commercial (including local shops/ caf/ offices, etc.)

    Two form intake primary school (420 pupils)

    Community centre/polyclinic

    Two football pitches and changing facilities within local small community centre (to includecorner/coffee shop location)

    Combined heat and power (CHP) station

    Cycle ways (north to south and east to west)

    Footpath/cycleway bridge linking existing sports stadium to the west of the railway line tothe Pennyfeathers site, with provision for future connection to the railway station

    Road and junction improvements

    Waterways (ponds and swales) for drainage attenuation

    Enhanced landscaping, open space (around 5.7 ha) and play areas Park & ride car ark

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    13/23

    Pennyfeathers Development: Non-technical summary 11

    Box 4: Environmental baseline surveys

    Soil and land survey of site (agricultural land classification)

    Phase 1 ecological surveys of site

    Botanical (plants and flowers) surveys Mammal surveys (bats, badger, water vole, dormouse, red squirrel)

    Breeding bird surveys

    Reptile surveys (snakes and lizards)

    Invertebrates (such as insects and spiders)

    Survey of Great Crested Newt habitat potential

    Tree survey

    Geophysical survey to identify archaeological remains

    Box 5: Environmental design

    Ecological surveys guided the layout so as to avoid valued woodland and hedgerows nearMonktonmead Brook and to provide green corridors in landscape design to improveecological connectivity of the habitat.

    Layout design has avoided and/ or provided set-back from ecologically valued resourcesand flood risk areas around Monktonmead Brook.

    Sustainable drainage has been designed in to the scheme so as to avoid exacerbating(and hopefully to reduce) existing flooding in areas downstream and to provide additionalhabitat.

    Design of new/ improved highways junctions and internal road layouts so as to improvetraffic and pedestrian safety.

    Buildings will be designed using a terraced arrangement orientated to reduce impact onviews from both within and into the site. Building heights have been limited and aregenerally higher at the top parts of the site (near Brading Road) so as to reduce visualimpacts.

    Housing is not proposed alongside Brading Road, to minimise adverse effects of traffic.

    Various local community facilities including a primary school and local open space andsports facilities will discourage car use.

    Footpaths and cycleways are planned to maximise their usage both within the siteboundaries and also to connect to the surrounding areas, which should reduce the needfor car use.

    Roads, paths and tracks through the development will be designed to blend better into the

    landscaping by having a boulevard style design with general separation of roads frompaths and extensive use of landscaping.

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    14/23

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    15/23

    Pennyfeathers Development: Non-technical summary 13

    insulated pipework for the districtheating network

    creation of construction platforms andground re-profiling comprisingexcavation and temporary storage of

    excavated material for later fill, in orderto maintain a suitable cut & fill balanceon site and minimising off-site removal

    drainage works to provide sustainabledrainage systems (SUDS)

    highway and bridge works for roads,parking, cycle paths and footpaths

    railway works for upgrading ofSmallbrook Junction Railway Station

    foundation works for buildings and other

    structures superstructure works and internal

    building fitting out and associatedbuilding services works

    hard and soft landscaping worksincluding planting.

    It is anticipated that standard construction

    working hours would be adopted, subject to

    agreement with the local authority, for

    instance Monday to Friday 8 a.m. to 6 p.m.

    and Saturday mornings 8 a.m. to 1 p.m.There would be no work on Sundays or

    Public Holidays and working is not expected

    to take place at night.

    Construction activities in the absence of

    mitigation measures and controls have the

    potential to generate temporary, short term

    adverse impacts. Examples of such

    mitigation measures include watering to

    control dust, and use of noise attenuationplant, which will be under the control of the

    main contractor. The EIA has recommended

    a range of measures designed to mitigate

    and control potential impacts, as

    summarised in the above sections.

    Prior to the start of construction, a

    construction method statement (CMS) will

    be agreed with the relevant authorities. The

    CMS will define responsibilities and

    procedures for the management of thepotential impacts on the environment arising

    during demolition, site preparation,

    excavation and construction and will include,

    among other things, specific measures for

    the control of pollution. It is recommended

    that the main contractor be required to

    register the site under the considerate

    constructors scheme. A site waste

    management plan will also be prepared and

    submitted for approval as required by the

    Site Waste Management Plans Regulations

    2008.

    Box 6: Types of impact considered

    Direct impacts may occur when some aspect of the development, physically impinges upon avalued resource, for instance the proposed construction of a house may result in loss of ecologicalhabitat or an archaeological relic. Indirect impacts could occur in either time, or location, from the

    source for instance construction works on a slope could result in heavy rainfall washing exposedsoil into a nearby watercourse, which could smother aquatic life.

    Cumulative impacts are defined as:

    impacts that result from changes caused by the proposed development together withother past, present or future developments

    impact interactions that may arise from a combination of separate impacts on one or asmall number of receptors due to the same proposed development.

    Information on possible future developments was gathered through discussions with IoW Counciland research of relevant planning documentation. The possibility of cumulative impacts arisinghas been considered in each of the technical chapters of the ES. It was concluded there would beno risk of cumulative impacts arising.

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    16/23

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    17/23

    Pennyfeathers Development: Non-technical summary 15

    boundary but excavation of trial trenches

    confirmed there to be no finds of any merit.

    Two listed buildings (outside the site) could

    be visually affected by the proposals, but

    both are considered of low sensitivity tovisual impact.

    It is anticipated that residual impact from the

    scheme will be negligible.

    Ecology

    A desk-based ecological background data

    search was undertaken to highlight

    conservation areas and records of

    internationally, nationally and locallyimportant species.

    The following field surveys were carried out

    to identify ecological features and provide

    information to determine their value: phase 1

    habitat survey; detailed botanical survey;

    hedgerow surveys; survey of grasslands and

    woodlands; invasive plant survey; and

    animal surveys for: amphibians; reptiles,

    wintering birds; breeding birds; bats,

    badgers; red squirrels; dormice; terrestrialinvertebrates; otters, and water voles.

    Red squirrel, resident on the Isle of Wight

    Best practice measures will be included in a

    construction method statement and the

    development will include targeted measures

    such as translocation of notable plants to

    safeguarded receptor sites, as well as the

    creation of diverse new habitats includinggreen space, new ponds, landscaping and

    wildflower meadows.

    Various further surveys and monitoring will

    be undertaken, with a full specification

    included in an environmental management

    plan. Also, a five-year habitat management

    plan (HMP) will be produced for the site.

    These measures will result in an overall

    positive residual impact.

    Landscape and visual aspects

    The landscape character in this part of the

    IoW has a medium sensitivity in the wider

    setting and low sensitivity in the immediate

    setting, mainly due to its proximity to the

    urban area of Ryde. The development will

    have little effect since much of the existing

    landscape structure will be retained and a

    strong landscape framework to reinforce this

    structure is provided in the proposal.

    The development could be visible from

    locations close to the site or from the more

    elevated locations to the west but the

    screening effects of other nearby buildings

    or existing landscape structures mean that

    the most visible parts of the proposed

    development areas are the higher parts of

    the site, particularly the areas near Brading

    Road.

    Mitigation opportunities have been

    suggested in terms of internal site tree

    screening and ecological planting to

    strengthen the existing landscape

    framework and increase screening effects.

    The use of dark colour, non-reflective

    materials, especially for roofing material

    would reduce the anticipated impacts, and

    there will be no significant residual effects.

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    18/23

    Pennyfeathers Development: Non-technical summary 16

    Air quality

    Construction of the development has the

    potential to affect local air quality, principally

    in terms of nuisance dust. Impacts will be

    controlled and monitored by means of aconstruction environmental management

    plan or construction method statement,

    agreed with the local authority. As a

    consequence, construction phase impacts

    would be negligible.

    Detailed assessment of operational impacts

    used an atmospheric dispersion computer

    model, with assumptions that were designed

    to over-predict pollutant concentrations.

    Data input to the model included anticipatedchanges in traffic flows and design data for

    the energy centre. The primary pollutants

    assessed were carbon monoxide (CO),

    nitrogen dioxide (NO2) and fine dust

    particles4.

    Predicted air pollutant concentrations (up to

    2027), after adding background pollutant

    concentrations, were compared with

    relevant air quality objectives. Every

    modelled scenario predicted that therelevant short-term and long-term air quality

    objectives would be achieved. With

    reference to planning guidance provided by

    Environmental Protection UK, the results

    indicate that the overall air quality impact of

    the development would be negligible.

    Noise and vibration

    The existing noise levels measured at the

    site during both day and night are typical of

    semi-rural edge of town sites. Noise levels

    were also measured during a speedway

    event at Smallbrook stadium so this could

    be taken into account. Vibration was also

    measured during train operations on the

    nearby railway tracks.

    The assessment concluded that achieving

    suitable indoor noise levels (within habitable

    4Known as PM10 as the particles have an average

    size (mean aerodynamic diameter) of 10 microns

    rooms) in proposed residential properties,

    would need suitable mitigation to be

    provided at some dwellings. This is subject

    to detailed design but may include double

    glazing and trickle ventilation on some

    building facades.

    As well, to achieve suitable noise levels at

    outdoor living areas, 1.8m high fences will

    be provided at properties close to

    Smallbrook Lane.

    Construction noise will be controlled using

    standard procedures that will reduce the

    noise to acceptable levels.

    The cumulative vibration values at proposed

    residential units for both day and night time

    are at levels indicating a low probability of

    adverse comment; therefore the impact of

    ground-borne vibration is considered to be

    not significant.

    Future increase in traffic flows will generally

    be less than 20% and on some roads traffic

    will decrease. However, traffic flows on

    Carters Road, Smallbrook Lane and Brading

    Road could increase more than 20%. The

    resultant increase in road traffic noise would

    be less than 1.5 dB, which is not significant.

    It is therefore concluded that, provided the

    recommended mitigation measures are

    implemented, the site is suitable for the

    proposed development and will not result in

    significant impact.

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    19/23

    Pennyfeathers Development: Non-technical summary 17

    Socio-economics

    The development will create employment

    opportunities during the construction phase,

    which will last for 13 years. There will also

    be some new jobs created during theoperational phase.

    904 new homes will be created by the

    development, which will contribute towards

    the IoW Councils target of 2,100 new

    dwellings in the Ryde area by 2027.

    Affordable housing units will be included to

    meet the 35% target.

    It is expected that around 167 primary

    school age children and 171 secondaryschool age children would live in the

    completed development. The primary school

    children will be accommodated by a new 2-

    form entry junior mixed infant (JMI) school

    (ages 4 11) for 420 pupils, which will be

    built as part of the development. The

    secondary school age children would be

    accommodated by the Ryde Academy.

    As part of the proposed development, a

    polyclinic or doctors surgery will be providedwith at least one GP, which will

    accommodate the anticipated 1,800

    residents of the development.

    Two multi use sports pitches and changing

    facilities will be provided as well as a small

    community centre (to include corner/coffee

    shop location) and play equipment. The

    development will provide almost 6 ha of

    enhanced landscaping and public open

    space. In addition, enhanced transportlinkages such as new bus routes and future

    access to the existing railway station(s) and

    to the local public right of way network of

    footpaths and cycleways would be provided

    throughout the development.

    The provision of new homes, employment

    opportunities, leisure and health facilities, new

    school and public open space on-site and

    transport linkages on- and off-site are assessed

    to be beneficial for the new residents and theexisting neighbouring communities.

    Traffic

    The proposed development site has been

    designed so that it will be accessible by a

    range of non-car travel modes. This should

    encourage the use of existing public

    transport services in the area and reduce

    the impact of the development on existing

    road junctions.

    Footways will be provided alongside all

    roads within the site. This will ensure full

    inter-connectivity between all elements of

    the proposed development as well as

    between the proposed development and the

    surrounding areas. This should encourage

    residents to walk to places in the vicinity of

    the site and therefore reduce their

    dependence on the car. Controlled

    pedestrian crossing facilities will be installed

    at major road junctions in and adjacent to

    the development.

    Cycle routes and cycle parking provision will be

    provided within the site to encourage the use of

    bicycles rather than private cars. Brading Roadcurrently presents an unattractive environment

    for cycling so improvements to this link in the

    form of a tree-lined boulevard with separate

    cycle lane will be made to better cater for this

    mode of transport.

    A new footbridge will be provided across the

    railway to link the development and

    Smallbrook Stadium. As part of a future

    upgrade to Smallbrook Junction, the rail

    station could also be connected. This wouldreduce private car use.

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    20/23

    Pennyfeathers Development: Non-technical summary 18

    Vehicular access to the proposed

    development site will be provided from three

    points around the site connecting to the

    existing local road network. Smallbrook

    Lane will be re-directed, while a new

    junction (a 4-arm roundabout) will beprovided on Brading Road.

    The re-directed Smallbrook Lane will be

    configured as an attractive boulevard with

    landscaped central reservation, forming the

    principal route through the site. It would

    divert most existing traffic on Smallbrook

    Lane away from its junction with Great

    Preston Road and through the proposed

    development site to the new roundabout on

    Brading Road. This is likely to cause asignificant re-distribution of traffic towards

    junctions with better capacity and flow

    pattern.

    The transport assessment (TA) identified the

    baseline traffic conditions of the local road

    network of the site for 2011, using traffic

    counts at key junctions. It looked at the type

    of junctions that already exist in the vicinity

    of the proposed development site and their

    existing capacity (for 2011 traffic flows). The

    TA then used this information to consider

    the potential impacts that the proposed

    development might have on the traffic flows

    and junction capacities subsequent to the

    completion and occupation of the whole

    development in 2027, compared to asituation that would occur in 2027 without

    the proposed development.

    It is expected that by 2027, six of the nine

    existing junctions would operate under

    capacity and with little queuing for both the

    morning and evening peak periods, an

    improvement compared to the situation

    predicted in 2027 without the development

    (see Table 2). The development proposes to

    make modifications to the road network andso reduce the level of congestion at

    significant junctions. With the development,

    the predicted changes to traffic volume at

    the three junctions that would be over

    capacity in 2027 will be small and will not be

    significant, and two of the three junctions

    would be over capacity even without the

    development.

    Table 2: Predicted effect of the development on capacity of nearby road junctions

    Junctions studiedWithoutdevelopment

    Withdevelopment

    Nicholson Road/Great Preston Road

    Smallbrook Lane/Great Preston Road / Over-capacity

    Great Preston Road/Marlborough Road/Bullen Road/ Brading

    Road (Westridge Cross) Over-capacity

    A3055 Brading Road/Cothey Way

    A3055 Brading Road/Tesco access

    Hornsey Road/A3055 New Road/B3395 MarshcombeShute/A3055 Morton Road (Yar Cross)

    Over-capacity Over-capacity

    Stroudwood Road/Upton Road/Carters Road/Gatehouse Road

    Argyll Street/West Street/Green Street Over-capacity Over-capacity

    Carters Road/Ashey Road/Smallbrook Lane Over-capacity

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    21/23

    Pennyfeathers Development: Non-technical summary 19

    At the junction - Carters Road / Ashey Road

    / Smallbrook Lane - the development would

    increase the volume of traffic by 13% in the

    morning peak hour and 20% in the evening

    peak hour, but the changes would have very

    little significance at the junction. Thedevelopment would tip this junction just over

    capacity on only one arm of the roundabout

    with the other three arms remaining under

    capacity. To put this in context, this arm

    would be close to capacity in 2027 without

    development, with development traffic

    adding only a further two vehicles to the

    queuing.

    SustainabilityInteraction between the master plan

    designers and the EIA team ensured that

    sustainability concerns were embedded in

    the design from the earliest stage. In

    addition, a detailed sustainability

    assessment was completed for the scheme,

    including code for sustainable homes and

    BREEAM pre-assessments, district heating/

    CHP (combined heat and power) feasibility,

    and SAP modelling (energy and carbonperformance of new buildings).

    Site construction activities will be managed

    and monitored to ensure the potential for

    nuisance impacts to local receptors such as

    dust, noise and construction traffic/ plant is

    minimised. A range of protection measures

    will also be implemented to safeguard local

    environmental conditions in respect of

    ecology, air, ground and water. The

    minimisation, sorting and recycling/ re-use ofconstruction materials will form a key

    component of the developments

    construction-phase sustainability

    credentials, for which a site waste

    management plan with appropriate targets

    will be prepared.

    In addition to protecting local ecology during

    construction, the completed development

    will incorporate a range of ecological

    enhancement measures to benefit key

    species and habitats, such as those covered

    by biodiversity action plans (BAP).

    Clean and zero/low carbon energy

    technologies are proposed for the

    development, including district heating/ CHPand high efficiency gas boilers. Energy

    efficiency measures will ensure energy

    demand and associated carbon emissions

    are minimised. On-site renewable energy is

    also anticipated for phase 2 onwards in the

    form of roof-mounted photovoltaic (PV)

    panels in order to further reduce carbon

    emissions. The development will therefore

    make a substantial contribution to climate

    change mitigation, as well as to climate

    change adaptation in the form of floodprotection, surface water runoff attenuation,

    rainwater harvesting and potable water use

    efficiency.

    A high quality internal environment is

    anticipated for residents, including noise

    insulation above minimum building

    regulations standards, good levels of

    daylighting and access to private and public

    outdoor space, including a range of amenity

    and leisure/ play uses for residents andother users. The creation of quality open

    spaces promotes healthy living through

    providing places to walk, cycle and exercise,

    bringing people together and nurturing

    community spirit through shared spaces.

    In addition to applying the waste hierarchy

    during construction, the development will

    incorporate convenient and accessible

    waste reception and sorting facilities for

    residents that promote the separation andrecycling of relevant waste streams.

    The selection of construction and finishing

    materials will be informed by their

    environmental performance among other

    considerations, with reference made to the

    green guide for specification to optimise the

    specification of high scoring materials. All

    timber will be FSC certified. The use of

    innovative and low environmental impact

    construction materials will be explored anddeveloped during detailed design.

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    22/23

    Pennyfeathers Development: Non-technical summary 20

    Pennyfeathers therefore fulfils the

    sustainable development expectations of the

    national planning policy framework and Isle

    of Wight Core Strategy by supporting

    sustainable economic development through

    the delivery of high quality homes andcreating a thriving local place.

    Illustration of a typical low carbon CHP engine

  • 7/29/2019 Pennyfeathers Development Isle of Wight Environmental statement: Non-technical summary

    23/23

    WHAT HAPPENS NEXT?

    The planning authority (IoW Council) will

    consider the findings of the ES, of which this

    non-technical summary forms a part,

    together with other documents submitted as

    part of the planning application. There is a

    statutory period allowed for comments to be

    returned to the IoW Council.

    If the IoW Council were to grant planning

    permission (with or without conditions) then

    it is envisaged that the following would

    occur:

    developer completes purchase of thesite

    detailed design of (each phase of the)development (taking into account anyplanning conditions that may have beenimposed)

    contractor tendering and appointment

    site investigations

    discharge of planning conditions

    construction including site preparationand foundations and infrastructure

    construction including buildingsuperstructures

    building fit-out and completion.

    CONTACT DETAILS

    The person to contact for further information

    on the project is:

    Mr Glen Hepburn

    Hepburns Planning Consultancy Ltd

    Cheeks Farm, Merstone Lane

    Merstone

    Isle of Wight, PO30 3DE

    Tel: (01983) 522100

    Email: [email protected]

    If you would like to comment on any aspect

    of the ES or non-technical summary or you

    would like to make an appointment to view

    the documents, then please contact Ms

    Sarah Wilkinson, principal planning officer,

    at the following address:

    Planning Services

    Isle of Wight Council

    Seaclose Offices

    Fairlee Road

    Newport

    Isle of Wight, PO30 2QS

    Tel: (01983) 823552

    Email: [email protected]