JAGUAR LAND ROVER PURCHASING

Supplier Technical Assistance

PHASED PPAP REQUIREMENTS HANDBOOK

Edition 1.0 June 2010

-0-

Jaguar Land Rover Phased PPAP Requirements Handbook

Phased Production Part Approval Process

Phased PPAP Requirements Handbook

IMPORTANT This Jaguar Land Rover process is derived from the original Ford process used by Jaguar Land Rover prior to June 2008 but is unique to Jaguar Land Rover. Certain aspects of this process will appear similar to the process currently used by Ford and which was historically used by Jaguar Land Rover however the two processes are now distinct from each other and contain important differences. It is important to ensure that the Jaguar Land Rover version is always used for Jaguar Land Rover business; the Jaguar Land Rover and Ford versions are NOT interchangeable. For any queries regarding the Jaguar Land Rover process described in this document, please contact your Jaguar Land Rover STA Engineer.

Jaguar Land Rover Supplier Technical Assistance Edition 1.0 June 2010

-1-

June 2010

Jaguar Land Rover Phased PPAP Requirements Handbook

Table of ContentsPage

Phased PPAP Introduction Phased PPAP Overview Process Overview Definitions Process Map Phase 0 Runat-Rate Process Map Phase 1 Quality Verification Process Map Phase 2 Production Verification Process Map Phase 3 Capacity Verification Customer Approval of Phased PPAP Expectations Appendix A STA Roles & Responsibilities Appendix B Exception Management Process Appendix C Phased PPAP Submission Warrant Appendix D PPAP Requirements Appendix E Acronym List

3 4 5 6 7 8 9 10 11 12 13 14 - 18 19 20 21

-2-

June 2010

Jaguar Land Rover Phased PPAP Requirements Handbook

Phased PPAP IntroductionIn order to improve launch performance, Jaguar Land Rover have structured the Production Part Approval Process (PPAP) into a phased approach that will require an organisation to demonstrate manufacturing capability, product quality and production capacity prior to Job #1. Phased PPAP will provide Jaguar Land Rover and the Supplier with an improved understanding of Supplier manufacturing process and part readiness. Phased PPAP organises the Production Part Approval Process into four phases: Phase 0: 'Run-at-Rate' Phase 1: 'Quality Verification' Phase 2: Production Verification' Phase 3: Capacity Verification. Benefits of Phased PPAP Phased PPAP will benefit Jaguar Land Rover and its Suppliers by: Dividing PPAP activities into more manageable segments. Providing a structured approach aligned with manufacturing process development. Providing a Programme team with earlier and additional measures to forecast Programme/product readiness. Providing a consistent mechanism for a Supplier to demonstrate their ability to support Jaguar Land Rover production volume requirements/capacity. Teamwork Jaguar Land Rover and its Suppliers must work together to deliver a quality part, produced on-time, that meets all Jaguar Land Rover engineering requirements. To drive flawless execution in launching and delivering products that surpass customer expectations, Jaguar Land Rover and its Suppliers must place trust, integrity and accuracy above all else in the Production Part Approval Process.

What Phased PPAP Means to Jaguar Land Rover Successful completion of Phased PPAP: Confirms that all customer engineering design record and specification requirements are properly understood by the Supplier, and that ALL production streams have the potential to produce product consistently meeting these requirements during an actual production run at the quoted production rate. AND Verifies that the Supplier's production system can support the Daily Production Volume declared by the customer.

-3-

June 2010

Jaguar Land Rover Phased PPAP Requirements Handbook

Phased PPAP OverviewScope Phased PPAP must be completed for any of the situations already specified by the current edition AIAG PPAP Manual. In addition, any increase in the Daily Production Volume (DPV) declared by the customer above the verified declared DPV will require the Supplier to re-complete any affected Phased PPAP phases. Summary Phase 0: Run-at-Rate Objectives: To confirm that all production input requirements are available and understood, and can support a limited production run. To provide an early indicator that the design of the process/tool/facility has the potential to produce at rate the required number of acceptable parts as determined by the pre-launch control plan. Phase 0 is a limited run-at-rate of parts for at least one production stream, not a demonstration that all PPAP requirements have been met for that production stream. Phase 1: Quality Verification Utilises parts produced during Phase 0. Objectives: To confirm all customer design record and specification requirements are properly understood by the Supplier. To provide an early indicator that the design of the process/tool/facility has the potential to produce product consistently meeting these requirements during an actual production run at the quoted production rate by operating a minimum of one selected production stream. Phase 1 demonstrates that all PPAP requirements have been met for one production stream Phase 2: Production Verification Objectives: To confirm all customer engineering design record and specification requirements are properly understood by the Supplier, and that ALL production streams have the potential to produce product consistently meeting these requirements during an actual production run at the quoted production rate. Phase 2 demonstrates that all PPAP requirements are met for all production streams. Phase 3: Capacity Verification Objective: Verify the Supplier's production system can support customer declared volume requirements while meeting Phase 2 requirements.

-4-

June 2010

Jaguar Land Rover Phased PPAP Requirements Handbook

Process OverviewThis process flow (an extract from Jaguar Land Rover Internal Procedure PSP-011) is intended to link the activities in Phased PPAP to include 4-Panel Process Flow, Roles & Responsibilities Matrices & Exception Management Process with the AIAG PPAP Reference Manual and any related Jaguar Land Rover Internal procedures.GPDS TIMING Phase 0 Timing of Phase 0 is determined by longest lead activity that must be completed to meet Phase 1 Requirements Phase 1 TT MRD The process below is not to scale between timing points. Please refer to Phased PPAP Handbook for Timing Expectations by Phase Phase 2 PP MRD Phase 3 Job #1 MRD

LAUNCH TEAM c)

Refer to the Phased PPAP Exception Management Process in the Phased PPAP Handbook b)

SUPPLIER d) e)

Inputs Phased PPAP Promise dates into VPP/MPP per Phased PPAP Handbook

Completes Phased PPAP Requirements (Phase 0, 1, 2 or 3) and documentation defined for Phase below Phase 0 - Capacity Analysis Report Phase 1 - Warrant Phase 2 - Warrant Phase 3 - Warrant & Capacity Analysis Report

No Enters "R" (Rejected) in VPP/MPP within 24 hours Enters "A" (Approved) or "I" (Internim Accepted) in VPP/MPP within 24 hours

No

Were all requirements of the Phase met?

Yes

Enter "Y" code in VPP/MPP for Phase & submit documentation designated for Phase to STA

Are all Phases complete?

Yes

END

Reject With P.D., reviews and approves, accepts or rejects submission

STA ENGINEER a), d), e)

Assigns PPAP level to supplier Site (Per PSP-011), accounting for Priority status of Parts, working with Program STA

Warrant approved, accepted, or rejected

Approve or Accept

PRODUCT DEVELOPMENT (PD) ENGINEERING

With STA, reviews and approves, accepts or rejects submission

PD PROGRAM & STA PROGRAM MANAGER

Informs affected suppliers of Priority part status and designation of PPAP Submission Level

BUYER

Completes sourcing of supplier site per Purchasing Procedure 2.1 or local practice

START

NOTES

a) Refer to Roles and Responsibilities Matrices in the Phased PPAP Handbook to determine minimum expectations by submission level and phase. b) Product Development has the authority to authorize an Alert (or regional equivalent) where a deviation to specification exists, and Interim Acceptance is required. c) Launch team typically consists of STA, Purchasing, Product Development, New Model Launch and Material Planning & Logistics (MP&L) d) Data input into VPP/MPP may be conducted by an administration team defined by local procedure. If STA decision on Phased PPAP Warrant is entered by the supplier, STA may override supplier VPP/MPP entry at any time. This also applies in the cases of PPAP Submission Level 1 ("Supplier Self Certification"), where Approval is registered in VPP/MPP automatically when the supplier enters "Y" code. Once STA has entered the status, the supplier is no longer able to enter part status. e) Documentation is not limited to that defined in this Process Flowchart. The Ford Phased PPAP 4-Panel Process Map (see Phased PPAP Handbook) defines the documentation that is required to be completed at each Phase. Submission to the authorized customer representative (STA) is defined in the AIAG published PPAP Manual.

-5-

June 2010

Jaguar Land Rover Phased PPAP Requirements Handbook

Definitions:Production Stream A single production stream is a sequence of a minimum of one line, machine, tool, cavity, facility, equipment, gauge, operator and other required items at the intended location and with the intended layout that will be used to produce parts that meet Jaguar Land Rover specifications. All production streams must include any additional items not included in the single producti