Confidential © 2012 Aker Solutions Preferred partner
Preferred partner
Plugging and abandonment Tubing retrieval on wireline or coiled tubing
Bård Martin Tinnen
Confidential © 2012 Aker Solutions Preferred partner
P&A – main downhole scope (relating to this project)
19 June, 2013 Slide 4
2 barriers to be installed
between the reservoir
and the topside
May entail need to
fix poor annulus
cement
May entail need to
remove control
line
May entail need to pull
tubing
Typical barrier = cement
plug, 50m long
May entail need to
log annulus
cement
Confidential © 2012 Aker Solutions Preferred partner
Plugging and abandonment - operational challenge
19 June, 2013 Slide 5
■ Many current jobs performed using drilling rigs
■ For platforms without drilling equipment in place, tubing retrieval towers
represents lighter alternative
■ Depending on the operational scope, P&A is still characterised by
operational and logistical complexity ■ e.g. plugging & abandonment on platforms with no drilling equipment and where
the job require fixing of poor annulus cement
Mobilise wireline
Demobilise wireline
Mobilise tubing retrieval tower
Demobilise tubing retrieval tower
Mobilise coil tubing
Demobilise coil tubing
Confidential © 2012 Aker Solutions Preferred partner
Activities Fluid
systems
Cement
systems
Wireline Coil
Tubing
Heavy
lifting
High
torque
force
Swarf
Well head integrity check
Drift run
Integrity logging
Injection test / killing well
Cement squeeze perforations
Install deep set plug
Punch tubing
Circulate heavy fluid (tubing + annulus)
Cut tubing
Remove tree, install BOP
Pull tubing
Log cement
Typical steps of P&A operation (1)
19 June, 2013 Slide 6
Step 1
Step 2
Step 3
Step 4
Step 5
Step 6
Step 7
Step 8
Step 9
Step 10
Step 11
Step 12
Ph
as
e 1
P
has
e 2
Confidential © 2012 Aker Solutions Preferred partner
Status at the initiation of the down hole tubing retrieval process
19 June, 2013 Slide 14
Tubing,
cut in top
Confidential © 2012 Aker Solutions Preferred partner
Cut to define tubing segment to be retrieved
19 June, 2013 Slide 15
Tubing cutting
tool
Confidential © 2012 Aker Solutions Preferred partner
Set bottom plug with check valve
19 June, 2013 Slide 16
Bottom plug
Confidential © 2012 Aker Solutions Preferred partner
Engagement of top plug to tubing segment
19 June, 2013 Slide 17
Control
module
Seal and
anchor
Confidential © 2012 Aker Solutions Preferred partner
Injection of gas to generate buoyancy force
19 June, 2013 Slide 18
Gas displaces
fluid
Confidential © 2012 Aker Solutions Preferred partner
Potential weight reduction
19 June, 2013 Slide 19
2.5
1.2
0.3
2.2
Confidential © 2012 Aker Solutions Preferred partner
Potential length increase
19 June, 2013 Slide 20
2.2
700 180
hook load for 100m 5.5" tubing (17lb/ft) in water
100
2.2
Confidential © 2012 Aker Solutions Preferred partner
Tubing retrieval
19 June, 2013 Slide 21
Confidential © 2012 Aker Solutions Preferred partner
Tubing handling equipment
■ Mobile/portable overhead crane
that is mounted on skid beams is
planned used for this project
■ Modified Aker MH overhead crane
19 June, 2013 Slide 22
Confidential © 2012 Aker Solutions Preferred partner
Aker MH drillfloor / pipe handling equipment
19 June, 2013 Slide 23
Modified Aker MH pipe handling equipment is
planned used for this project
Confidential © 2012 Aker Solutions Preferred partner
Effect of pulling tubing on wireline (1)
19 June, 2013 Slide 29
4 x 10' tank containers
= ~1 well volume
3 x 20' x 10' containers
(= winch, BOP skid, tool cont.)
(This only represents parts of the
WL equipment package)
Mobilise wireline
Demobilise wireline
Mobilise tubing retrieval tower
Demobilise tubing retrieval tower
Mobilise coil tubing
Demobilise coil tubing
Confidential © 2012 Aker Solutions Preferred partner
Example – wireline operation equipment
19 June, 2013 Slide 30
Not shown in the picture:
■ Wireline winch
■ Large pressure control skid
■ Workshop container
■ Riser rack
■ Overhead crane
■ Pipe handling crane
■ Work platform with false rotary
■ 13-5/8 pressure control
equipment
■ Fluid tanks / pumps / valve
manifolds / pipe
■ Cementing equipment
Confidential © 2012 Aker Solutions Preferred partner
Activities Fluid
systems
Cement
systems
Wireline Coil
Tubing
Heavy
lifting
High
torque
force
Swarf
Well head integrity check
Drift run
Integrity logging
Injection test / killing well
Cement squeeze perforations
Install deep set plug
Punch tubing
Circulate heavy fluid (tubing + annulus)
Cut tubing
Remove tree, install BOP
Pull tubing
Log cement
Suspend well
PLANNING BREAK
Effect of pulling tubing on wireline (2)
19 June, 2013 Slide 31
Step 1
Step 2
Step 3
Step 4
Step 5
Step 6
Step 7
Step 8
Step 9
Step 10
Step 11
Step 12
Step 13
Ph
as
e 1
P
has
e 2
Confidential © 2012 Aker Solutions Preferred partner
Summary
19 June, 2013 Slide 33
■ P&A as a stand-alone market segment is rapidly emerging
■ As of current, most of the relevant down hole activities are conducted using
drilling rigs
■ For old platforms where the drilling equipment has been removed, tubing
retrieval towers represents a lighter alternative to rig mobilisation
■ Current methods represent relatively high cost as well as operational and
logistical challenges
■ An optimisation potential is envisaged
P&A using
drilling rigs
P&A using tubing
retrieval towers
P&A using
wireline ?
Confidential © 2012 Aker Solutions Preferred partner 19 June, 2013 Slide 34
THANK YOU
Confidential © 2012 Aker Solutions Preferred partner
Copyright and disclaimer
Copyright Copyright of all published material including photographs, drawings and images in this document remains vested in Aker Solutions and
third party contributors as appropriate. Accordingly, neither the whole nor any part of this document shall be reproduced in any form nor
used in any manner without express prior permission and applicable acknowledgements. No trademark, copyright or other notice shall
be altered or removed from any reproduction.
Disclaimer This Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and
uncertainties that could cause actual results to differ. These statements and this Presentation are based on current expectations,
estimates and projections about global economic conditions, the economic conditions of the regions and industries that are major
markets for Aker Solutions ASA and Aker Solutions ASA’s (including subsidiaries and affiliates) lines of business. These expectations,
estimates and projections are generally identifiable by statements containing words such as “expects”, “believes”, “estimates” or similar
expressions. Important factors that could cause actual results to differ materially from those expectations include, among others,
economic and market conditions in the geographic areas and industries that are or will be major markets for Aker Solutions’ businesses,
oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currency
exchange rates and such other factors as may be discussed from time to time in the Presentation. Although Aker Solutions ASA believes
that its expectations and the Presentation are based upon reasonable assumptions, it can give no assurance that those expectations will
be achieved or that the actual results will be as set out in the Presentation. Aker Solutions ASA is making no representation or warranty,
expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Aker Solutions ASA nor any of its
directors, officers or employees will have any liability to you or any other persons resulting from your use.
Aker Solutions consists of many legally independent entities, constituting their own separate identities. Aker Solutions is used as the
common brand or trade mark for most of these entities. In this presentation we may sometimes use “Aker Solutions”, “we” or “us” when
we refer to Aker Solutions companies in general or where no useful purpose is served by identifying any particular Aker Solutions
company.
Slide 39 19 June, 2013