pre – feasibility reportenvironmentclearance.nic.in/writereaddata/online/tor/14... · 2016. 6....
TRANSCRIPT
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 15
PRE – FEASIBILITY
REPORT
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 16
INDEX
1.0 EXECUTIVE SUMMARY ................................................................................................. 20
1.1 SALIENT FEATURES OF THE PROJECT .................................................................... 21
1.2 PROPOSED PLANNING ................................................................................................. 23
2.0 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION .................... 23
2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT ................................ 23
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT ............................................. 24
2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND OR
REGION ........................................................................................................................... 24
2.4 DEMAND - SUPPLY GAP............................................................................................... 25
2.5 IMPORTS VS. INDIGENOUS PRODUCTION ................................................................ 25
2.6 EXPORT POSSIBILITY ................................................................................................... 25
2.7 DOMESTIC/ EXPORT MARKETS .................................................................................. 25
2.8 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT 26
3.0 PROJECT DESCRIPTION .............................................................................................. 26
3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT
PROJECTS, IF ANY. ....................................................................................................... 26
3.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION, AND
PROJECT BOUNDARY AND PROJECT SITE LAYOUT) WITH COORDINATES ...... 26
3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF SELECTING
THE PROPOSED SITE, PARTICULARLY THE ENVIRONMENTAL
CONSIDERATIONS GIVEN INTO SHOULD BE HIGHLIGHTED. ................................ 27
3.4 SIZE OR MAGNITUDE OF OPERATION ....................................................................... 27
3.4.1 REGIONAL GEOLOGY .................................................................................................... 27
3.4.2 LOCAL GEOLOGY ........................................................................................................... 28
3.4.3 HYDROGEOLOGY ........................................................................................................... 29
3.4.4 MINERAL RESERVES ..................................................................................................... 29
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC DIAGRAM/
FLOW CHART SHOWING THE PROJECT LAYOUT, COMPONENTS OF THE
PROJECT ETC. SHOULD BE GIVEN)........................................................................... 29
3.5.1 YEAR WISE PRODUCTION DETAILS ............................................................................ 30
3.5.2 PROPOSED METHOD OF MINING ................................................................................ 30
3.5.3 EXTENT OF MECHANIZATION ....................................................................................... 31
3.5.4 CONCEPTUAL MINING PLAN ......................................................................................... 31
3.5.5 DRILLING .......................................................................................................................... 32
3.5.6 BLASTING ........................................................................................................................ 32
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 17
3.5.6.1 Broad Blasting Parameters ........................................................................................................ 32
3.5.6.2 Explosive Used ............................................................................................................................ 32
3.5.6.3 Powder Factor ............................................................................................................................. 32
3.5.6.4 Storage of Explosive ................................................................................................................... 32
3.5.7 MINERAL TRANSPORTATION ....................................................................................... 33
3.6 RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY
SOURCE, MARKETING AREA OF FINAL PRODUCT/S, MODE OF TRANSPORT OF
RAW MATERIAL AND FINISHED PRODUCT............................................................... 33
3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE
PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED .............................................. 33
3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY / POWER REQUIREMENT AND
SOURCE SHOULD BE GIVEN ....................................................................................... 33
3.8.1 WATER ............................................................................................................................. 33
3.8.2 POWER ............................................................................................................................. 34
3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND SCHEME
FOR THEIR MANAGEMENT/ DISPOSAL. .................................................................... 34
4.0 SITE ANALYSIS .............................................................................................................. 34
4.1 CONNECTIVITY .............................................................................................................. 34
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP ................................................... 35
4.2.1 LANDFORM ...................................................................................................................... 35
4.2.2 LAND USE ........................................................................................................................ 35
4.2.3 LAND OWNERSHIP ......................................................................................................... 35
4.3 TOPOGRAPHY (ALONG WITH MAP) ........................................................................... 35
4.4 EXISTING LAND USE PATTERN (AGRICULTURE, NON-AGRICULTURE, FOREST,
WATER BODIES (INCLUDING AREA UNDER CRZ)), SHORTEST DISTANCES FROM
THE PERIPHERY OF THE PROJECT TO PERIPHERY OF THE FORESTS,
NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE AREAS, WATER
BODIES (DISTANCE FROM THE HFL OF THE RIVER), CRZ. IN CASE OF NOTIFIED
INDUSTRIAL AREA, A COPY OF THE GAZETTE NOTIFICATION SHOULD BE
GIVEN. ............................................................................................................................. 35
4.5 EXISTING INFRASTRUCTURE ...................................................................................... 36
4.5.6 BASIC AMENITIES ........................................................................................................... 36
4.6 SOIL CLASSIFICATION ................................................................................................. 36
4.8 SOCIAL INFRASTRUCTURE AVAILABLE ................................................................... 37
5.0 PLANNING BRIEF .......................................................................................................... 37
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 18
5.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, TRANSPORTATION
ETC.) TOWN AND COUNTRY PLANNING/ DEVELOPMENT AUTHORITY
CLASSIFICATION. .......................................................................................................... 37
5.2 POPULATION PROJECTION ......................................................................................... 38
5.2 LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT ETC.) .................. 38
5.3 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL AND SOCIAL) ........ 39
5.4 AMENITIES/ FACILITIES ................................................................................................ 39
6.0 PROPOSED INFRASTRUCTURE .................................................................................. 39
6.1 INDUSTRIAL AREA (PROCESSING AREA) ................................................................. 39
6.2 RESIDENTIAL AREA (NON PROCESSING AREA) ..................................................... 39
6.3 GREEN BELT .................................................................................................................. 40
6.4 SOCIAL INFRASTRUCTURE ......................................................................................... 40
6.5 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL / METRO /
WATER WAYS ETC.) ..................................................................................................... 40
6.6 DRINKING WATER MANAGEMENT (SOURCE AND SUPPLY OF WATER) ............. 40
6.7 SEWERAGE SYSTEM .................................................................................................... 40
6.8 INDUSTRIAL WASTE MANAGEMENT ......................................................................... 40
6.9 SOLID WASTE MANAGEMENT .................................................................................... 40
6.10 POWER REQUIREMENT AND SUPPLY / SOURCE .................................................... 41
7.0 REHABILITATION AND RESETTLEMENT (R & R PLAN) ........................................... 41
7.1 POLICY TO BE ADOPTED (CENTRAL/ STATE) IN RESPECT OF THE PROJECT
AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND OUSTEES AND
LANDLESS LABOUR (A BRIEF OUTLINE TO BE GIVEN) ......................................... 41
8.0 PROJECT SCHEDULE AND COST ESTIMATES ......................................................... 41
8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF
COMPLETION (TIME SCHEDULE FOR THE PROJECT WILL BE GIVEN). ............... 41
8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC
VIABILITY OF THE PROJECT ....................................................................................... 41
9.0 ANALYSIS OF PROPOSAL ........................................................................................... 42
9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE
BENEFITS TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF ANY, IN
THE AREA ....................................................................................................................... 42
10.0 BASELINE ENVIRONMENT ............................................................................................ 43
10.2 AIR ENVIRONMENT ........................................................................................................ 44
10.3 WATER ENVIRONMENT ................................................................................................. 45
10.4 NOISE ENVIRONMENT ................................................................................................... 47
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 19
10.5 LAND ENVIRONMENT .................................................................................................... 49
10.6 BIOLOGICAL ENVIRONMENT ........................................................................................ 50
10.7 SOCIO-ECONOMIC ENVIRONMENT ............................................................................. 57
11.0 ENVIRONMENTAL MANAGEMENT PLAN ..................................................................... 71
12.0 CONCLUSION ................................................................................................................. 73
************
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 20
1.0 EXECUTIVE SUMMARY
Lime Stone Mine (Minor Mineral M.L. No. 169/2008) of lessee Sampoorna Exports (P)
Limited, is situated near Village – Kumbhkot, Tehsil – Ramganjmandi, District - Kota,
Rajasthan in an area of 4.0 ha.
Schedule 1 (a) Category - “B” as per MoEF EIA gazette Notification 14th Septmber 2006
and its subsequent amendement and in consistant with the MoEF Notifiaction dated
09.09.2013.
The Project Proponent has obtained a letter by Mining Engineer, along with map
showing the other mining leases falling within 500m from the periphery of the mine
Enclosed as Annexure - .
Details are as given below:-
S.
No.
Lease
No.
Name of the lease
holder
Name of the
Mineral
(Minor)
Total Area
(Ha.)
Area of the
mine falling in
500m
1. 04/ 2010 Status Impex (P) Limited
Kota
Lime stone /
(Building stone)
4.5058 4.0
2. 169/2008 Sampoorna Export (P)
Limited, Kota
Lime stone /
(Building stone)
4.0 4.0
3. 94/2008 ASI Kota Ltd. Lime stone /
(Building stone)
916.611 56.51
4. 05/ 2013 Sampoorna Export (P)
Limited, Kota
Lime stone /
(Building stone)
4.0 3.48
The mining lease was sanctioned in favour of Sampoorna Exports (P) Limited. The
Mining Plan has been approved by Superintending Mining Engineer, Kota Circle,
Annexure – .
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 21
The working will be carried out by opencast semi-mechanized method as per the
approved Mining Plan. The entire lease area is classified as Khatedari land & Sawaichak
Land (Govt. waste land). The proposed rate of production will be 1,97,819.55 TPA of
ROM (659 TPD). The estimated project cost is Rs. 2.0 Crore. The validity of lease will be
20 years (w.e.f. 05.09.2009 to 04.09.2029).
1.1 SALIENT FEATURES OF THE PROJECT
Particulars Details
Latitude (N) & Longitude (E)
Latitude (N) Longitude (E) Remark
240 37' 28.20'' 76
0 00' 02.00'' FRP/A
240 37' 35.20'' 75
0 59' 55.90'' B
240 37' 34.60'' 75
0 59' 53.10'' C
240 37' 28.50'' 75
0 59' 53.50'' D
240 37' 28.20'' 75
0 59' 50.80'' E
240 37' 25.70'' 75
0 59' 51.10'' F
240 37' 25.80'' 75
0 59' 58.40'' G
Toposheet No. 45P/14 and 45D/2.
Total Mine Lease area 4.0 ha.
Mineable Reserves 14,14,896 Tonnes
Production 1,97,819.555 TPA
Life of Mine 10 years
Estimated Project Cost Rs 2.0 Crore
Man Power 92 Persons
Elevation 332 MSL - Highest
330 MSL – Lowest
Land Use Sawaichak Land (Govt. Land): 0.4209 ha. and
Khatedari land (3.5791 ha.)
Nearest Habitation / Town Ramganjmandi ~ 7.5 km, WNW
Nearest Airport Jaipur International Airport ~ 243 km, N
Nearest Highway S. No. Name Distance (km) Direction
(From Lease Boundary)
1 RJ - SH - 9A 2.9 N
2 RJ - SH - 9B 6.87 W
3 NH - 12 5.47 E
Nearest Railway Station S. No. Name Distance (km) Direction
(From Lease Boundary)
1 Ramganjmandi 6.31 WNW
Power Supply 4 kw through JVVNL
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 22
Nearest Dispensary and
Govt. Hospital
S. No. Name Distance (km) Direction
(From Lease Boundary)
1 Govt. Manglam Cement
Hospital 4.68 WNW
2 Community Health
Care Center, Morak 9.9 N
3 Kota Stone Mariam
Hospital, Suket Road,
Ramganj Mandi
1.3 W
Educational Facility S. No. Name Distance (km) Direction
(From Lease Boundary)
1 Govt. Upper Primary
School, Kundayla 3.3 NW
2 Government Upper
Primary School,
Lakhariya
4.0 SSE
3 Government Girls
Upper Primary School
Suket
4.3 ENE
4 Government Sr. Sec.
School, Suket 4.8 ENE
5 Government Upper
Primary School Suket 4.5 ENE
6 Govt. Girls Senior
Secondary School,
Ramganj Mandi
5.94 WNW
7 New Happy School,
Ramganj Mandi 5.89 WNW
8 Govt. Senior Secondary
School, Lakhariya 4.9 SSE
9 Bright Technical PG
College, Ramganj
Mandi
5.46 W
Water Demand and Supply 10.0 KLD Water demand will be met from tanker supply.
Defense Installations None within the Study Area
Archeological Features None within the Study Area
Ecological Sensitive Zones None
Forest Name Distance (Km) Direction
Sahipur R.F. 7.5 E
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 23
Kheemach PF 7.92 NE
Mukunndgarh wild life hills 12.9 NE
Nearest Streams/ Rivers/
Water Bodies (From Mine
Boundary)
S. No. Name Distance (km) Direction
(From Lease Boundary)
1 Ahu River 5.95 E
Seismic Zone Zone-II, Low Damage Risk Zone as per BMTPC, Vulnerability Atlas Seismic
Zone of India IS: 1893-2002.
1.2 PROPOSED PLANNING
Mining Method: Semi-Mechanized Opencast Mine
Project Cost : Rs. 2.0 Crore
Production : 1,97,819 TPA of ROM
Table 1.2: Land Use of lease area
S. No. Land use Category Pre-operational
(Ha.)
Land-use after
5th
year (Ha.)
End of the life of mine
1 Pits -- 2.9328 3.7905*
2 Dump area -- -- --
3 Roads -- -- --
4 Infrastructure -- -- --
5 Mineral storage -- -- --
6 Top soil storage -- -- -
7 Plantation -- 0.2095 0.2095
8 Un-worked 4.0 0.8577 --
Total 4.0 4.0 4.0
*out of which 2.9209 ha. area will be backfilled and partially planted remaining area of 0.8696 ha. will be used as rain water storage.
2.0 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION
2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT
The mining lease was sanctioned in favour of M/s Sampoorna Exports (P) Limited. The
Mining Plan has been approved by Superintending Mining Engineer, Kota, vide letter no.
SME/ Kota/MP12-13/152 dated 27.02.2013 under RMMCR-1986.
The lease area is situated at village – Kumbhkot; Tehsil – Ramganjmandi, District- Kota,
Rajasthan in an area of 4.0 ha. The validity of the lease period is for 20 years. The lease
area is mix of Sawaichak land (Govt. Waste Land) and Khatedari Land. The targeted
production of mine will be 1,97,819.555 TPA of ROM with the estimated project cost as
2.0 crore. Life of the mine will be around 10 years.
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 24
The Project Proponent is a private company and engaged in mining. The main objective
to be pursued by the applicant is to carry the business of prospecting, exploring,
operating and working on mines. The main market for mineral is nationwide and will be
utilized as buildings stones.
Name and address of the Applicant M/s Sampoorna Exports (P) Limited
Bazar No. 1
Tehsil: Ramganjmandi;
District: Kota (Rajasthan)
Pin-code: 326-519
2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT
It has been proposed to excavate approximately 659 TPD (1,97,819 TPA of ROM) of
mineral by open cast semi-mechanized method. The lease area is 4.0 ha. Total minable
reserve available is 14,14,896.75 MT. The expected life of mine is 10 years. Total waste
generated during the plan period of the mine will be 9,07,049 m3.. The mineral will be
transported through trucks/ tippers.
At the conceptual stage, the total excavated area will be 3.7905 ha. Water requirement
will be 10.0 KLD for the project and will be met by water tanker supply. The ultimate pit
limit will be 270 MSL at conceptual stage. The water table is at 120 m below the general
ground level at 210 MSL (ground water fluctuates between 210 MSL in Pre-monsoon
and 213 MSL in Post – monsoon season). Thus, ground water table will not be
intersecting during working till life of mine.
2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY AND
OR REGION
Being a construction material, the mineral will be used in indigenous market. The
excavated mineral will be dressed and polished as finished good made ready for use.
The mining and associated activities in the mineral bearing areas will bring about gains
in gross domestic product, i.e. there is though a minor contribution by the project but will
add to the gains in G.D.P. (Gross Domestic Product). Sales in India have increased on
an over the past ten years, exceeding both regional and global averages. A rapidly
advancing economy and rising standards of living have helped increase overseas
investment in India, stimulating large amounts of industrialization and infrastructure-
related construction activity. However, Indian product demand (relative to construction
spending and on a per capita basis) is substantially below regional and world averages.
The mining project will provide employment to local people. Applicant will pay royalty for
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 25
the mineral produced from the mine, direct and indirect taxes will be paid thereby
contributing to the regional revenue. The public revenue so generated will further be put
for use in infrastructural development and other sectors like health, education and social
welfare. The applicant will spend 1% of profit for the development of the area i.e.
medical facilities, schools, temples and other social work.
2.4 DEMAND - SUPPLY GAP
Lime stone (building stone) is splittable used in construction activities as raw material. It
is available in the eastern part of the State near Kota and Jhalawar district. Most of the
lessees are from rural areas. Rajasthan in India is the largest producer of building stones
endowed with vast resources. The anticipated annual growth in consumption would be
around 15%. The entry in the target market is easy and there is a narrow gap in the
supply and demand, which is growing.
2.5 IMPORTS VS. INDIGENOUS PRODUCTION
The most commonly used product type is lime stone (building stone), is used for making
titles , Pattis, for flooring, table tops, cladding of walls and roof top coverings.. Limestone
(building stone) demand in India is expected to rise. Ongoing industrialization and
government plans to expand and upgrade the country's physical infrastructure will fuel
market growth.
2.6 EXPORT POSSIBILITY
Lime stone (building stone) production from the mine will cater to the needs of well
established domestic markets. There is a potential of the mineral for exporting after
meeting the indigenous requirements.
2.7 DOMESTIC/ EXPORT MARKETS
Domestic demand is one of the main reasons for the rapid growth of lime-stone (building
stone) business in India. Thus, domestic market for the stone as building stone is well
established.
The market scope for stone is found to be encouraging in local market with the
increased demand from construction fields
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 26
2.8 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE
PROJECT
The proposed project generates employment for around 92 people. Priority for
employment will be given to local persons. Following staff & workers are proposed to be
employed:-
Table 2.8: Provisional Number of Proposed Staff and Workers
S. No. Particulars Proposed
1. Managerial staff 05
2. Operating staff 42
3. Unskilled workers 25
4. Semi-skilled worker 10
5. Skilled 12
6. Total 92
3.0 PROJECT DESCRIPTION
3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INTERDEPENDENT
PROJECTS, IF ANY.
This will be a semi mechanized open cast limestone mining project. Mineral will be used
/ consumed as building stone.
3.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION,
AND PROJECT BOUNDARY AND PROJECT SITE LAYOUT) WITH
COORDINATES
The proposed Mine site is located at Khasara Nos. 41, 42, 43, 44, 45, 46, 47, 48, 63;
Village – Kumbhkot, Tehsil – Ramganjmandi, District – Kota, Rajasthan in an area of
4.0 hectare.
The geographical location with respect to boundary pillars of the proposed project are:-
Table 3.2: Geographical Position of the Boundary Pillars
Latitude (N) Longitude (E) Remark
240 37' 28.20'' 76
0 00' 02.00'' FRP/A
240 37' 35.20'' 75
0 59' 55.90'' B
240 37' 34.60'' 75
0 59' 53.10'' C
240 37' 28.50'' 75
0 59' 53.50'' D
240 37' 28.20'' 75
0 59' 50.80'' E
240 37' 25.70'' 75
0 59' 51.10'' F
240 37' 25.80'' 75
0 59' 58.40'' G
The map showing location of the lease area is enclosed as Annexure –.
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 27
3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF
SELECTING THE PROPOSED SITE, PARTICULARLY THE
ENVIRONMENTAL CONSIDERATIONS GIVEN INTO SHOULD BE
HIGHLIGHTED.
No alternate site was considered as mining project is a mineral specific activity.
3.4 SIZE OR MAGNITUDE OF OPERATION
Salient features of the project are as follows:-
Table 3.4: Size or Magnitude
S. No. Particulars Proposed
1. Lease Area 4.0 hectare
2. Mineable Reserves -Lime Stone (building stone) 14,14,896.75 tonnes
3. Production 659 TPD
4. Mine Waste 1675 TPD
5. Life of Mine 10
6. Period of the Lease 20 yrs.
7. Total Man Power (Nos.) 92
3.4.1 REGIONAL GEOLOGY
Most of the part of Kota district is occupied by rocks of Vindhyan Super Group which
forms the part of Great-Vindhyan basin, extending from Rohtas in Bihar to the
Chittorgarh area of Rajasthan. On the basis of different rock units the Vindhyan of the
area have been divided in to Semri, Kaimur, Rewa, and Bhander groups comprising
sandstones, shales and limestone. The Semri Group is separated from Kaimur by
conglomerate horizon which marks the break in sedimentation before the deposition of
Kaimur Group. The lime stone of Sirbu-Shale horizon; at places show the evidence of
algal life in the form of arch shaped structures known as Stomatolites. Occurrence of
Sandstone at different Stereographic horizons indicates fluctuation of the sea level due
to transgression and regression of the sea several times during the Vindhyan period.
The general Stratigraphic succession of rock types exposed in Kotah district is as under:
Geologically the district comprises rocks belonging to Vindhyan Super Group. The
generalized and modified litho stratigraphic sequence is as under:
Table 3.4.1: Regional Geology
Vindhyan Super
Group
Bhander Group Sandstone, Limestone & Shales
Rewa Group Shales & Sandstone
Delhi Super Group Kaimur Group Sandstone
Semri Group Sandstone Shale and Limestone
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 28
The rocks of the area belong to Vindhyan Super Group
3.4.2 LOCAL GEOLOGY
The rock formations occurring within mining lease area comprise of Semari Group
(Lower Vindhyan). Reconnaissance of Geological aspect was done in the area and
following geological sequence has been established.
Recent Soil
sub soil
Lower Vindhyan Limestone (upper layer & lower layer)
The limestone which is belonging to Suket Shale of Lower Vindhyan, occur near village
Suket, Ramganjmandi, Chechat & Morak area in tehsil- Ramganjmandi, District- Kota.
Figure 1: Geological Map(Source: GSI)
The surface geological plan of the lease area is enclosed as Annexure – .
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 29
3.4.3 HYDROGEOLOGY
The study area falls in Khairabad block of Kota district, which is under safe category
according to CGWB Publication “Dynamic Ground Water Resources of India – 2009”.
Rainfall plays a major role in groundwater availability of semi-arid region as it is the
major source available for groundwater recharge. The area is largely occupied by quartz
mica schist, phyllite along with granite & pegmatite intrusives as main aquifers.
Movement of groundwater in these hard rocks is controlled by size, continuity and
interconnectivity of weathered and fractured parts and due to other secondary porosities.
Groundwater occurs mainly under unconfined condition to semi-confined in saturated
zone of rock formation.
The water level in the study area varies from 210 MSL to 213 MSL as per
hydrogeological investigation. Seasonal fluctuation in the area is around -2 to 2 m as per
CGWA district groundwater brochure. (Source: CGWB Report)
3.4.4 MINERAL RESERVES
The mineral is already being worked in neighboring mine adjacent to the proposed
mining area under the supervision and control of the sister concern. The mineral is
exposed and similar in nature as per the investigations. The mineral reserves have been
estimated by plan area method. Based on the experience and the estimated reserves
have been classified in to proved, probable & possible reserves. The quantity of
reserves is arrived as per the details below:-
Table 3.4.4: Reserve Estimation according to UNFC Classification
S. No. Total Mineral Resources Code Reserves (Tonnes)
A. Mineral Reserves
1. Total Mineral (geological reserves) 111 16,62,000
2. Statutory Barrier 121 87,052.65
3. Reserve slope 211 1,60,050.6
4. Total mineable reserve in tonnes 111 16,62,000 – (87,052.65 –
1,60,050.6) = 14,14,896.75
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC
DIAGRAM/ FLOW CHART SHOWING THE PROJECT LAYOUT,
COMPONENTS OF THE PROJECT ETC. SHOULD BE GIVEN).
The proposed mining operations will be carried out by open cast semi-mechanized
method. The process flow diagram given below depicts the mining process:-
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
3.5.1 YEAR WISE PRODUCTION DETAILS
The details of year wise production for the first five years are given below:-
Table 3.5.1: Year wise production for the Five Years Period
Year Total ROM
in Tonne
85% lime Stone
(Tonne)
Waste 15
% m3
Soil M3 OB m3 Total OB
m3
1st year Nil Nil Nil 8,490 1,75,538 1,84,028
2nd
year Nil Nil Nil 0 43,610 43,610
3rd
year Nil Nil Nil 4,245 2,13,670 2,17,915
4th year 1,97,819.55 1,68,146.61 10,712 4,140 2,18,114 2,32,966
5th year 1,96,032.9 1,66,627.96 10,615 6,870 2,11,045 2,65,537
Total 393852.45 334774.57 21,327 23,745 8,61,977 9,07,049
The map showing working / composite plan is enclosed as Annexure –.
3.5.2 PROPOSED METHOD OF MINING
Mine will be developed by semi mechanized opencast mining method which includes
drilling, blasting, loading, transport and dispatch.
3.5.2.1 Open Cast Mining
The mining will be done by open cast semi-mechanized method of mining. The bench
height will be maintained at 7.0 m and width will not be less than the height. The face
slope will be 85°, whereas ultimate pit slope is proposed at 45°.
The drilling will be carried out by 110 mm rotary drill / Jack hammer pneumatically
operated. Waste /O.B will be loaded by excavators/loaders The mineral will be
transported through tipper/ tractor trolleys/ trucks
Removal of Top Soil/ Overburden
Excavation
Loading & Transportation
Stacking at Designated Areas
Dispatch
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 31
3.5.2.2 Salient Features of Mining Method
The proposed mining operations will be carried out by open cast semi-mechanized
method. The salient features of proposed mining method are:-
� The height and width of the bench will be maintained at 7.0 m.
� Face slope will be maintained 85°.
� Ultimate pit slope is proposed 45°
� Drilling will be done by Jack Hammer/110 mm drills.
3.5.3 EXTENT OF MECHANIZATION
The details of equipments proposed to be used in mining operation are listed below:-
Table 3.5.3: List of Machineries
3.5.4 CONCEPTUAL MINING PLAN
The applied area is having mineral throughout the lease area. The mineable reserves as
estimated are 14,14,896 MT. The annual production projected is estimated 1,97,819.555
TPA of ROM. Life of the mine therefore is around 10 years. Ultimate pit level will be 270
MSL.
3.5.4.1 Land Use Pattern
The land use for mining and allied purposes is given below:-
S. No. Land use Category Pre-operational
(Ha.)
Land-use after
5th
year (Ha.)
End of the life of
mine
1 Pits -- 2.9328 3.7905*
2 Dump area -- -- --
3 Roads -- -- --
4 Infrastructure -- -- --
5 Mineral storage -- -- --
6 Top soil storage -- -- -
7 Plantation -- 0.2095 0.2095
8 Un-worked 4.0 0.8577 --
Total 4.0 4.0 4.0
*out of which 2.9209 ha., area will be backfilled and planted remaining area of 0.8696 ha., will be used as rain water storage. The conceptual plan is enclosed as Annexure – .
S. No. Machine Type Capacity Nos.
1. Jhiri machine 30 hp 25
2. Transformer 210 kVA 1
3. Excavator 2.65 m3 range 1
4. Pneumatic drill 110 mm 1
5. Water tanker trolley mounted 10,000 liter 1
6. Dumper 35 tonne 4
7. Air compressor 450 cfm 1
8. Trucks 13 tonne 2
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 32
3.5.5 DRILLING
The hard strata (overburden) will be fragmented for ease in handling by drilling and
blasting as and when required. The material will be handled by loading equipments.
Mineral will be loaded manually into the trucks and sent to the stock yards / destination.
3.5.6 BLASTING
The blasting is needed to excavate the over burden. The controlled blasting is proposed
by adopting all the safety measures as per “M.M.R.1961” and with the permission of
DGMS.
3.5.6.1 Broad Blasting Parameters
Table 3.5.6.1: Broad Blasting Parameters
Deep Hole Blasting
Hole depth : 7m Effective Length
Burden : 3.5 m
Spacing : 4.0 m
Hole Diameter : 110 mm
volume 98 m3
Tonnage Yield (T) 98 x 2.7 = 264.6 Tonne
3.5.6.2 Explosive Used
Blasting will be done by ANFO along with booster and Slurry explosive viz. power
gel, Acquadyne, Superdyne etc.
3.5.6.3 Powder Factor
Charge per hole is 0.125 kg of booster, 6.0 kg/m of explosive and one detonator.
Table 3.5.6.3: Broad Blasting Parameters
S.No. Particulars Details
i Amount of charge per hole 17.5 kg
Booster – slurry explosive 3.5 kg
Column charge – ANFO (80%) 14 kg
ii Yield per hole 264.6 ton
iii expected powder factor yield / hole / charge / hole
= 15.12 / tone of explosive
3.5.6.4 Storage of Explosive
The explosive will be procured from authorized license supplier through their duly
licensed explosive vans.
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 33
3.5.7 MINERAL TRANSPORTATION
Mineral will be transported by trucks. However, 35 ton capacity dumper will be used
for OB / waste transportation.
Particulars Production
(TPD)
Vehicles Required
(Trips / day)
Mineral 659 33
Waste 1675 48
3.6 RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY
SOURCE, MARKETING AREA OF FINAL PRODUCT/S, MODE OF
TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT
No raw material will be required for production of lime stone (building stone). The final
product will be sent to consumer based on their demand. The mode of transportation of
raw material and finished product will be by road. Tippers/ trucks will be used for
transportation to the end users.
3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE
PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED
Mineral will be utilized and sent for use to different end users. The OB/ waste will be
used for the maintenance of roads and backfilling.
Rainwater harvesting will be done using excavated pit void. Water conservation will
thereby reduce exploitation of groundwater.
3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY / POWER REQUIREMENT
AND SOURCE SHOULD BE GIVEN
3.8.1 WATER
The total water requirement for the proposed will be 10.0 KLD. The detailed breakup of
the same is given below:-
Table 3.8.1: Water Demand
S. No. Particulars Proposed
1. Domestic 3
2. Dust Suppression
7 3. Plantation
Total 10.0
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 34
The drinking water demand will be met from tanker supply from company’s boreholes
and for plantation and dust suppression from sump / stored water in the old pit
Annexure –.
3.8.2 POWER
The total power requirement will be 4.0 kW which will be provided by Jaipur Vidhyut
Vitran Nigam Limited.
3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND
SCHEME FOR THEIR MANAGEMENT/ DISPOSAL.
About 9,07,049 m3 will be generated at the end of five years period. This waste will be
utilized in backfilling of the min pit. This waste will be used in maintenance of approach
roads from time to time.
The details as tabulated below:-
Table 3.9 - Waste Generation (Liquid and Solid)
Activity Quantity of waste Proposed Treatment /
Disposal
Mine Waste (TPD) 1675 backfilling
Municipal Solid
Waste
No. of mine workers 92
Municipality
sites
Total Waste Generation @ 0.15
kg/day approx
15
Biodegradable Waste (kg /day) 11
Non-biodegradable waste (kg /day) 4
Domestic
Wastewater
Wastewater Generation (KLD) 2.0 Septic tank followed
by soak pit
4.0 SITE ANALYSIS
4.1 CONNECTIVITY
Table 4.1 – Connectivity
Name Distance (Km) Direction
Ramganjmandi RS 6.31 WNW
SH - 9B 2.9 N
SH - 9A 6.87 W
NH - 12 5.47 E
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 35
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP
4.2.1 LANDFORM
The mining lease area comprises flat terrain with highest and lowest elevation 332 MSL
and 330 MSL. There is no water body or nallah within the lease area. However, the
drainage of the lease area is towards east.
4.2.2 LAND USE
The land use pattern is given in point no. 1.2.
4.2.3 LAND OWNERSHIP
The land as per revenue records is Sawaichak Land i.e. Govt. Waste Land (0.4209 ha.)
and Kharedari land (3.5791 ha.), the total lease are is 4.0 ha.. The map showing land
use of the lease area (Surface Plan) is enclosed as Annexure – .
4.3 TOPOGRAPHY (ALONG WITH MAP)
Topographically, the applied area comprises of flat land having gently sloping towards
east. The highest elevation of the lease area is 332 MSL.
4.4 EXISTING LAND USE PATTERN (AGRICULTURE, NON-AGRICULTURE,
FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ)), SHORTEST
DISTANCES FROM THE PERIPHERY OF THE PROJECT TO PERIPHERY OF
THE FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO
SENSITIVE AREAS, WATER BODIES (DISTANCE FROM THE HFL OF THE
RIVER), CRZ. IN CASE OF NOTIFIED INDUSTRIAL AREA, A COPY OF THE
GAZETTE NOTIFICATION SHOULD BE GIVEN.
Table 4.4: Land Use Pattern
S. No. Land use Category Pre-operational
(Ha.)
Land-use
after 5th
year
(Ha.)
End of the
life of mine
1 Pits -- 2.9328 3.7905*
2 Dump area -- -- --
3 Roads -- -- --
4 Infrastructure -- -- --
5 Mineral storage -- -- --
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 36
6 Top soil storage -- -- -
7 Plantation -- 0.2095 0.2095
8 Un-worked 4.0 0.8577 --
Total 4.0 4.0 4.0
4.5 EXISTING INFRASTRUCTURE
The same has been given in point no. 3.8 and 4.0.
4.5.6 BASIC AMENITIES
The details of basic amenities like schools, hospitals and community center located
nearby the mine site are mention below:-
Table 4.5.6: Basic Amenities
Name Distance (km) Direction
(From Lease Boundary)
Govt. Upper Primary School, Kundayla 3.3 NW
Government Upper Primary School, Lakhariya 4.0 SSE
Government Girls Upper Primary School Suket 4.3 ENE
Government Sr. Sec. School, Suket 4.8 ENE
Government Upper Primary School Suket 4.5 ENE
Govt. Girls Senior Secondary School, Ramganj Mandi 5.94 WNW
New Happy School, Ramganj Mandi 5.89 WNW
Govt. Senior Secondary School, Lakhariya 4.9 SSE
Bright Technical PG College, Ramganj Mandi 5.46 W
(Source: All distances are taken with respect to Google Earth)
4.6 SOIL CLASSIFICATION
According to the soil taxonomical classification, there are six categories of classification
i.e. i. Order (the broadest category) ii. Suborder, iii. Great group, iv. Subgroup, v. Family
and vi. Series (the most specific category). The soil of the Rajasthan state have been
grouped under five orders, namely, Aridosols, Alfisols, Entisols, Inceptisols and
Vertisols. Soils have further been subdivided at suborder and great group levels under
these five orders as shown below.
Table 4.6: Classification of Soils found in Rajasthan
S. No. Order Suborder Great group Occurrence
1. Aridisols Orthids a. Camborthids Parts of Jalore, Churu, Jodhpur, Pali, Barmer, Sikar and Jhunjhunu districts.
b. Calciorthids Parts of Jalore, Jodhpur, Pali, Barmer, Nagaur, Sikar, Churu, Sriganganagar and Jhunjhunu districts.
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 37
c. Salorthids Found scattered in Ghaggar floodplain in Sriganganagar; Near sambhar, Pachpadra, Deedwana lakes, little Rann of Kutch area in Jalore and in Barmer districts
d. Paleorthids Scattered and cover a small area in Jaisalmer, Barmer and Nagaur districts.
2. Alfisols Ustalfs a. Haplustalfs Eastern and south-eastern part of Rajasthan in Udaipur, Chittorgarh, Bhilwara, Ajmer and Jaipur districts.
3. Entisols Psamments a. Torripsamments Cover upto 80% of the area at many places in western Rajasthan. Also cover a part of Jaipur, Alwar and Ajmer districts.
b. Quartzipsamments Small part of Jaisalmer and barmer districts.
Fluvents c. Torrifluvents Occur in Ghaggar floodplain area of Sriganganagar district.
d. Ustifluvents Occur on the north-eastern and eastern portion of Rajasthan covering parts of Alwar and almost whole of Bharatpur districts.
4. Inceptisols Ochrepts a. Ustochrepts Occur along the foothill slopes and cover extensive areas in Bhilwara, Udaipur, north-eastern Sawaimadhopur and in parts of Sirohi, Pali, Jaipur and Chittorgarh districts.
5. Vertisols Usterts a. Chrom usterts Parts of Bundi, Kota & Jhalawar districts in south-eastern part of Rajasthan and to a lesser extent in Chittorgarh, Dungarpur, Banswara & Bharatpur districts.
b. Pellusterts Cover a large are of Bundi, Kota, Jhalawar, Chittorgarh, Dungarpur, Banaswara and Bharatpur districts.
4.8 SOCIAL INFRASTRUCTURE AVAILABLE
The well established social infrastructure like hospitals, educational facilities, temple,
community centre, roads, bridges, telecommunication and others similar are available/
existing within 15 km radius which is tabulated in point no. III of Form – 1.
5.0 PLANNING BRIEF
5.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES,
TRANSPORTATION ETC.) TOWN AND COUNTRY PLANNING/
DEVELOPMENT AUTHORITY CLASSIFICATION.
It is a mining industry in which open cast semi-mechanized method will be practiced.
The proposed mine will produce with the capacity of 1,97,819.55 TPA of ROM. It will be
used as building material. Mineral will be transported by trucks/ tippers to final
consumers.
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 38
POPULATION PROJECTION
The detail demographic profile of villages located in the study area is given in point no.
4.7.7.
5.2 LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT ETC.)
As per year wise afforestation programme, plantation is proposed. The main aim of the
green belt development is to improve the ecosystem to a maximum possible extent by
designing the green cover with the same native species. The year wise plantation
programme in five years is given below:-
Table 5.2:- Green Belt Development Programme (Inside the lease area)
The map showing greenbelt plan of the lease area is enclosed as Annexure – .
Table 5.2 i: Suggested Tree Species
TREE
S. No Species name Binomial name
1 Mahua Madhuca indica
2 Peepal Ficus religiosa
3 Sal Shorea robusta
4 Shesham Delbergia sissoo
5 Gulmohar Delonix regiosa
6 Siris Albizzia lebbek
7 Palas Butea monosperma
8 Satani Alstonia scholaris
9 Neem Azadirachta indica
10 Ashoka Ployalthia longifolia
11 Mahaneem Melia azadirachta
12 Khajoor Phoenix dactylifera
13 Kadam Anthosephalus cadamba
14 Bottle Brush Callistemon citrinus
15 Shoe babool Luceana leucopholea
16 Vilayati kikar Acacia farmesiana
Year Un-worked Area Waste Dump
(Outside)
Inside Dump
(Reclaimed Area)
Top Soil
Dumps
Total
Area
(Ha.)
No. of
Trees
Area
(Ha.)
No. of
Trees
Area
(Ha.)
No. of
Trees
Area
(Ha.)
No. of
Trees
Area
(Ha.)
No. of
Trees
I 0.0419 42 -- -- -- -- -- -- 0.0419 42
II 0.0419 42 -- -- -- -- -- -- 0.0419 42
III 0.0419 42 -- -- -- -- -- -- 0.0419 42
IV 0.0419 42 -- -- -- -- -- -- 0.0419 42
Vth year 0.0419 42 -- -- -- -- -- -- 0.0419 42
VIth yr. end -- -- -- -- 1.1105 1110 -- -- 1.1105 1110
Total 0.2095 210 -- -- 1.1105 1110 -- -- 1.32 1320
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 39
Table 5.2 ii. Suggested Shrub / Herb Species
S. No Species name Binomial name
1 Munja grass Saccharum munja
2 Vilayati Babool Prosopis juliflora
3 Kans grass Saccharum spontaneum
4 Arandi Ricinus cummunis
5 Kaner Nerium Indicum
6 Peeli Kaner Thevetia peruviana
7 "Red (Yellow, Wild) Sage" Lantana camara
8 Buffel Grass Cenchrus ciliaris
9 Sarphonka Tephrosia hamiltonii
10 Makara or crowfoot grass Dactyloctenium aegyptium
11 Bui Aerva tomentosa
5.3 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL AND SOCIAL)
On the basis of the preliminary site visit, the infrastructure demand in the nearby villages
will be assessed on the basis of need and priority. Job opportunities are limited and
newer avenues of skill development for income generation are required.
5.4 AMENITIES/ FACILITIES
Following facilities are provided for the smooth working of the mine:-
Table 5.4: Facilities provided to workers
S. No. Activities Capital Cost
*Rs In thousands
Recurring Cost
*Rs In thousands
1. Shelter 25.0 5.0
2. Health Facility 40.0 20.0
3. Drinking Water 10.0 10.0
4. Sanitation Facilities 25.0 10.0
5. Education 25.0 15.0
Total 125.0 60.0
6.0 PROPOSED INFRASTRUCTURE
6.1 INDUSTRIAL AREA (PROCESSING AREA)
The area is very well connected by road network to the mine, district headquarter etc.
The area is self sufficient to cater the needs of the project. Hence, no infrastructure is
proposed.
6.2 RESIDENTIAL AREA (NON PROCESSING AREA)
As the local person will be given employment, no residential area/ housing is proposed.
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
6.3 GREEN BELT
The same has been given in point 5.2.
6.4 SOCIAL INFRASTRUCTURE
Local population will be employed by the project proponent in the Mine. Further, indirect
means of earnings have been created in the area of contractual jobs, vehicle driving,
shops, construction etc. Therefore this project brought a positive impact on the adjoining
society. The proponent will spend 1% of profit for the development of the area i.e.
medical facilities, schools, temples and other social work. There is well developed social
infrastructure in the area detail has been tabulated in section – III of Form – 1.
6.5 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL / METRO /
WATER WAYS ETC.)
Given in point no. 4.0
6.6 DRINKING WATER MANAGEMENT (SOURCE AND SUPPLY OF WATER)
The drinking and other water demand will be sourced by the tanker supply.
The water demand is given below:-
6.7 SEWERAGE SYSTEM
Toilet facilities will be provided. The generated sewage will be channelized to septic tank
followed by soak pit.
6.8 INDUSTRIAL WASTE MANAGEMENT
There will be no industrial waste generation due to proposed project.
6.9 SOLID WASTE MANAGEMENT
The same has been given in point no. 3.9.
Daily Water Demand – 10.0 KLD
Domestic – 3.0 KLD Mining – 7.0 KLD
(Dust Suppression + Plantation)
Septic Tank followed by soak pit
2.0 KLD
Consumption – 1.0 KLD
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 41
6.10 POWER REQUIREMENT AND SUPPLY / SOURCE
The total power requirement for the proposed will be 4.0 kW. This is being provided by
Jaipur Vidhyut Vitran Nigam Limited.
7.0 REHABILITATION AND RESETTLEMENT (R & R PLAN)
7.1 POLICY TO BE ADOPTED (CENTRAL/ STATE) IN RESPECT OF THE
PROJECT AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND
OUSTEES AND LANDLESS LABOUR (A BRIEF OUTLINE TO BE GIVEN)
There is no habitation in the lease area, therefore rehabilitation & resettlement plan is
not required/ applicable.
8.0 PROJECT SCHEDULE AND COST ESTIMATES
8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF
COMPLETION (TIME SCHEDULE FOR THE PROJECT WILL BE GIVEN).
The project will commence once Environmental Clearance and other necessary
approvals will be obtained from the concern departments.
Table 8.1: Expected Time Schedule for the Project
S.
No.
Particulars Time Schedule
(in month)*
Remark If any
1st
2nd
3rd
4th
1. Environmental Clearance
2. Consent To Establish Project Establishment Period
3. Consent To Operate Production Start Period
*Time line may vary; subjected to rules & regulation / & other unforeseen circumstances
8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF
ECONOMIC VIABILITY OF THE PROJECT
The proposed project cost will be Rs. 2.0 crore.
Table 8.2 i: Estimated Project Cost and Economic Viability
S. No. Particulars Details
1. Estimated Project Cost (Fixed cost) 2.0 Cr. (including operational cost)
2. Operation cost Rs. 5 – 10 / sq.feet
3. Market cost Rs. 15 – 30 / sq.feet
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 42
Expenditure Proposed for Environmental protection activities:-
It is proposed to invest an amount of Rs. 1.0 Lac per annum towards environmental
action plan and the details of the same are given below:-
Table 8.2 ii: Expenditure Proposed for Environmental Protection Activities
S. No. Description of Item Recurring Cost (Rs)
1 Air Pollution Control - Water Sprinkling 20,000
2 Water Pollution Control 10,000
3 Environmental Monitoring and Management 50,000
4 Green Belt Development 20,000
Total 1,00,000/-
9.0 ANALYSIS OF PROPOSAL
9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE
BENEFITS TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF
ANY, IN THE AREA
No tribal population is residing in the study area. There will be social benefits from the
mining operations. The core benefit of the project is the availability of stone. The
underlying benefits through the proposed are:-
Table 9.1 i: Financial & Social Benefits
S. No. Activities
1. It aims to provide additional employment to the local population of the proposed study area.
Direct employment to locals: 92 Approx.
Indirect Employment to locals : 30 Approx.
2. The PP proposes to construct toilets and Rain Water Harvesting structures in the
Government schools of nearby villages
3. Health Camps will be organized for the local people.
The appropriate amount of CSR is proposed to be Rs. 2.0 lacs capital cost and Rs.10,000/- as
recurring cost till the life of the mine.
As a Corporate Social Responsibility, following activities along with budget provision are
proposed for improving the conditions in and around the project area.
Table 9.1 ii: Corporate Social Responsibility
S. No. Activity Capital Cost
(in Rs.)
Recurring Cost
(In Rs.)
1. Health Check Up Camps 25,000 2,500
2. Assistance to Local Schools, Scholarships to Students 60,000 3,000
3. Sanitations and Drinking Water Facilities 25,000 2,500
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 43
4. Vocational Training to Persons for Income Generation 30,000 1,000
5. Women Empowerment & Development Programme 60,000 1,000
Total 2,00,000 10,000
Table 9.1 iii: Action Plan
S.
No.
Action Plan Expenditure Cost (in Rs.) Recurring
Cost (in Rs.) Year I Year II Year III Year IV Year V
1. Health Check up camps 20,000 5,000 5,000 5,000 5,000 2,500
2. Assistance to local
schools, scholarships to
students
30,000 5,000 5,000 5,000 5,000 3,000
3. Sanitations and
drinking water facilities
20,000 5,000 5,000 5,000 5,000 2,500
4. Vocational training to
persons for income
generation
5,000 5,000 5,000 5,000 5,000 1,000
5. Women Empowerment
& Development
Programme
25,000 5,000 5,000 5,000 5,000 1,000
Total 1,00,000 25,000 25,000 25,000 25,000 10,000
Total 2,00,000
10.0 BASELINE ENVIRONMENT
The baseline environment quality represents the background environmental scenario of
various environmental components such as air, noise, land, ecological and socio-
economic status of the study area. Details of the sampling locations are given below:
Table 10.0 : Monitoring Locations
S.
No.
Location Latitude
Longitude
Distance –
(km)
Direction Core /
Buffer
Zone
Environmental
Components
From Lease Boundary
1 ML No. 05/
2013
24037’43.32”
75059’42.15”
-- -- Core Zone Air (A),
Water (GW),
Noise (N),
Soil (S)
2 Vill.
Satalkhei
24039’05.65”
75000’02.46”
1.7 NNE Buffer
Zone
3 Vill. Narli 24037’38.00”
75000’32.46”
1.6 SE Buffer
Zone
4 Vill.
Amerpura
24037’50.07”
75058’15.24”
2.2 WSW Buffer
Zone
5 Vill.
Kumbhkot
24037’00.03”
75000’08.99”
2.6 SSE Buffer
Zone
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 44
10.1 Climate
Kota has a semi arid climate with high temperatures throughout the year. Summers are
long, hot and dry, starting in late March and lasting till the end of June. The monsoon
season follows with comparatively lower temperatures, but higher humidity and frequent,
torrential downpours. The monsoons subside in October and temperatures rise again.
The brief, mild winter starts in late November and lasts until the last week of February.
Temperatures hover between 26.7 °C (max) to 12 °C (min).The average annual rainfall
in the Kota district is 660.6 mm. Most of the rainfall can be attributed to the southwest
monsoon which has its beginning around the last week of June and may last till mid-
September. Pre-monsoon showers begin towards the middle of June with post-monsoon
rains occasionally occurring in October. The winter is largely dry, although some rainfall
does occur as a result of the Western Disturbance passing over the region.
10.2 AIR ENVIRONMENT
The prime objective of the baseline air monitoring was to evaluate the existing air quality
of the area. This will also be useful for assessing the conformity to standards of the
ambient air quality during the operation of the proposed mine.
Field monitoring studies for 24 hourly frequencies was carried out to evaluate the base
line status of the project site.
Wind Rose Pattern
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 45
One day monitoring of environmental attributes was carried out. The monitored values
was used as a baseline data to identify, evaluate and predict the impacts due to
proposed mining activities in the surrounding areas for preparing the Environmental
Management Plan accordingly for the proposed activity.
Table 10.2 i: Ambient Air monitoring Instruments
Instrument Make Model
No.
Instrument
Identification No.
Range and Sensitivity
Respirable Dust
Sampler (RDS)
M/s
Envirotech
Instruments
Pvt. Ltd
APM-
450BL
SAL/RDS/01 0.40 – 1.5
m3/min
±0.02m3/min
(PM10)
0 – 3 LPM
± 0.2
LPM(gases)
Fine Particulate
Sampler (FPS)
APM
550
DTC-205 ±0.03 DGM m3
(PM2.5)
Table 10.2 ii: Testing Method to be followed for Ambient Air Quality
Particular Testing Method to be Followed
Ambient Air Monitoring Parameter
A PM10 IS-5182 (part – 23) 2006
B PM2.5 RTI (Research Triangle Institute) (Gravimetric Ana Revision-07 Aug14-
2003)
C SO2 (Sulfur Dioxide) IS 5182 (Part – II) 2001, with Improved West & Gaeke Method
D NO2 ( Oxides of
Nitrogen)
Modified Jacobs – Hochheiser Method / Arsenite Method (IS 5182 Part 6)
2011
E Carbon Monoxide NDIR Spectroscopy method
Table 10.2 iii: Ambient Air Quality Status
S. No. Parameters Units NAAQS 2009 A1 A2 A3 A4 A5
1. PM10 µg/m3 100 76.3 42.5 43.5 46.7 40.8
2. PM2.5 µg/m3 60 42.8 23.1 21.6 24.5 21.3
3. SO2 µg/m3 80 8.9 5.2 5.0 5.3 5.1
4. NO2 µg/m3 80 36.7 16.5 14.3 15.9 14.9
5. CO µg/m3 2000 892 423 512 431 436
Ambient air monitoring results were found within the standards (NAAQS).
10.3 WATER ENVIRONMENT
The purpose of this study is to:-
� Assess the water quality characteristics;
� Predict the likely impacts on water quality due to the project and related activities.
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 46
Table 10.3: Water Quality
S.
No
.
Parameter Drinking Water
Standard
(IS: 10500)
GW1 GW2 GW3 GW4 GW5
Desirable
Limits
Permissibl
e Limits
1 pH 6.5 – 8.5 NR 7.26 7.23 7.65 7.45 7.56
2 Color (Hazen) < 5 < 25
-
PROJECT : LIME STONE (BUILDING STONE)
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR
Baseline Water Quality: Ground water
The drinking quality of ground water in the study area
Standards, is given as below:
Inference:
S.No. Location Name
1. Mine site POOR
2. Vill. Satakheri POOR
3. Vill. Narli POOR
4. Vill. Amarpura POOR
5. Vill Kumbhkot POOR
WQI: Water Quality Index in range between; 101-200 hence POOR; *Ref. 1. Ramakrishnaiah, et. al., 2009; Data in parenthesis is percentage change
Anticipated Health risks associated due to ground water consumption
S.No. Contaminant
1. TH Scaling of skin and hair loss
2. TDS unpalatable taste
3 Sulphate Gastrointestinal distress / diarrhea
4 Chlorides Salty taste (impact on osmo
impaired fluid dynamics etc)
5. Fluoride Bone disease (pain and tenderness
bones); Children may get mottled teeth
Ref. USEPA; CPCB New Delhi
10.4 NOISE ENVIRONMENT
The main objective of noise monitoring in the study area is to establish the baseline noise
levels and assess the impact of the total noise expected to
operations in the project site.
0
20
40
60
80
100
120
140
160
180
Mine site Vill. Satakheri
water quality index
LIME STONE (BUILDING STONE) PRE -
M/s SAMPOORNA EXPORTS (P) LIMITED
EC/ MINE/ 2014
PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
Baseline Water Quality: Ground water
The drinking quality of ground water in the study area, in comparison to CPCB Desirable
WQI* Failed Parameters
POOR (TDS, Fluoride, TH, Biogenic salts)
POOR (TDS, Fluoride, TH, Biogenic salts) (+ 36 to + 264)
POOR (TDS, Fluoride, TH, Biogenic salts) (+ 10 to + 144)
POOR (TDS, Fluoride, TH, Biogenic salts) (+ 19 to + 161)
POOR (TDS, Fluoride, TH, Biogenic salts)
200 hence POOR; *Ref. 1. Ramakrishnaiah, et. al., 2009; Data in parenthesis is percentage change
Table
Anticipated Health risks associated due to ground water consumption & its mitigation
Health risks Mitigation Measure & Management
Scaling of skin and hair loss • Water pretreatment like filtration is
required before consumption
• Reverse Osmosis, activated
carbon filters
• Activated alumina, Nalgonda
• Reverse Osmosis, Ion exchange water softeners
unpalatable taste
Gastrointestinal distress / diarrhea
Salty taste (impact on osmo-regulation /
impaired fluid dynamics etc)
Bone disease (pain and tenderness of the
bones); Children may get mottled teeth
The main objective of noise monitoring in the study area is to establish the baseline noise
levels and assess the impact of the total noise expected to be generated during the project
operations in the project site.
Vill. Satakheri Vill. Narli Vill.
Amarpura
Vill Kumbhkot
water quality index
FEASIBILTY REPORT
AUTHORIZED SIGNATORY / PP
in comparison to CPCB Desirable
% change
(+ 6 to + 188)
(+ 36 to + 264)
(+ 10 to + 144)
(+ 19 to + 161)
(+ 3 to + 137)
& its mitigation
Mitigation Measure & Management
Water pretreatment like filtration is
required before consumption
Reverse Osmosis, activated
Activated alumina, Nalgonda
Reverse Osmosis, Ion exchange
The main objective of noise monitoring in the study area is to establish the baseline noise
be generated during the project
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 48
Instant sound level meter is used for the collection of data related to noise at an interval of
one hour per reading. Noise level for 24 hours was conducted in a day. The details of the
instrument used for the sampling are as given below:-
Table 10.4 i: Noise (Sound) Measuring Instrument
Instrument Make Model
No.
Instrument
Identification
Detection
Limit
Integrated Sound Level
Measurement Instrument
Standard Accessories
Lutron SL-4001 SAL/NOISE/INT/01 Lo 30-80dB
Hi 80-130dB
Table 10.4 ii: Testing Method to be followed
Particular Testing Method to be Followed
Noise Level Measurement
A Noise Level in dB (A) for continuous
24 hours at 1 hour interval
Operational Manual of Noise level Meter, Model No.
DT - 805 issued by Mextech
Table 10.4 iii: Noise Monitoring
Station Name N1 N2 N3 N4 N5
06.00 48.9 43.5 46.5 45.9 47.9
07.00 52.3 45.6 48.8 48.5 49.7
08.00 54.5 46.9 49.9 49.3 50.3
09.00 56.9 47.3 50.4 46.7 51.2
10.00 58.7 48.9 48.9 48.3 49.8
11.00 60.3 50.2 47.8 46.7 48.3
12.00 61.5 48.8 46.9 43.9 47.2
13.00 58.7 47.3 42.9 47.3 43.5
14.00 59.3 46.3 44.5 46.9 45.8
15.00 57.0 44.8 46.3 45.3 49.3
16.00 59.4 46.3 48.7 46.9 47.3
17.00 61.4 42.8 50.2 44.0 49.9
18.00 63.0 48.6 46.9 41.6 50.2
19.00 61.9 49.3 44.3 38.9 46.2
20.00 58.7 45.5 41.9 36.4 44.7
21.00 56.3 42.1 40.3 35.0 41.6
22.00 54.2 40.9 38.9 36.9 38.5
23.00 48.9 38.9 36.4 35.4 35.6
24.00 42.3 36.0 35.1 35.1 35.0
01.00 38.5 35.2 35.0 35.0 35.2
02.00 36.3 35.0 36.3 35.6 36.9
03.00 37.0 35.6 38.9 36.9 38.9
04.00 43.5 38.9 40.2 38.6 41.6
05.00 47.0 40.3 42.9 42.5 43.7
Leq day dB(A) 59.2 47.1 47.4 45.9 47.8
Leq Night dB(A) 47.5 38.2 38.8 37.8 38.8
Inference:
Noise levels were found within the prescribed standards.
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 49
10.5 LAND ENVIRONMENT
The objectives of the soil sampling are:-
� To determine the baseline soil characteristics of the study area;
� To determine the impact of existing as well as proposed activity on soil
characteristics and;
� To determine the impact on soil more importantly with agriculture production point of
view.
Table 10.5: Soil Analysis
S.No. Parameters Units S1 S2 S3 S4 S5
1 Texture - Sandy
Clay
Sandy
Clay
Sandy
Clay
Clay Sandy
2 Particle
size
Distribution
s
Sand % 52 50 36 22 50
Silt % 16 12 24 30 16
Clay % 32 38 40 48 34
3 Appearance (Color) -- Light
Brown
Light
Black
Light
Brown
Brown Brown
4 Sodium as Na mg/100g 1.23 1.26 1.13 1.14 1.09
5 pH (10% Slurry) - 7.42 7.39 7.23 7.51 7.39
6 Conductivity µS/cm 175 198 183 212 165
7 Bulk density g/cc 1.32 1.36 1.25 1.12 1.46
8 Porosity % v/v 20 26 31 42 12
9 Total Organic Matter % 0.74 0.81 0.89 0.94 0.53
10 Nitrogen as N mg/100g 165 204 215 264 132
11 Potassium as K mg/100g 56 72 88 112 34
12 Phosphorus as P mg/100g 29 59 72 68 22
13 Zinc as Zn mg/ kg 2.69 4.2 4.66 4.36 1.31
14 Cadmium as Cd mg/ kg 0.04 0.06 0.09 0.06 0.02
15 Chlorides as Cl mg/100g 1.23 1.26 1.06 1.68 0.68
16 Alkali Metals mg/ kg 0.26 0.23 0.22 0.36 0.2
17 Permeability cm/ h 7.3 7.3 5.4 4.6 7.3
18 Water Holding
Capacity
% 16.5 19.2 26.9 40 11.6
19 Copper as Cu mg/ kg 0.06 0.13 0.06 0.06 0.03
20 Iron as Fe mg/ kg 0.08 0.16 0.12 0.11 0.08
21 Lithium mg/ kg
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 50
10.6 BIOLOGICAL ENVIRONMENT
Natural flora and fauna are important features of environment. They are organized into
communities with mutual dependencies among their members and show various
responses and sensitivities to outside influences. Therefore, nature of development and
baseline characteristics of terrestrial flora and fauna around the site of existing/proposed
activities is required to be assessed.
The primary/ secondary study is to characterize the environmental components like flora
and fauna, to assess the biological diversity of the region. Flora and fauna can be used
for biological surveillance in assessing the environmental status.
Flora: Core Zone
Trees: Few trees were observed during the site visit in core zone.
S. No. Common Name Botanical Name Family Core/ Buffer Zone
1 Neem Azadirachta indica Meliaceae Core Zone
2 Kiker or Babool Acacia nilotica Leguminosae Core Zone
Shrubs
S. No. Common Name Botanical Name Family Core/ Buffer Zone
1 Kair Capparis decidua Capparaceae Core Zone
2 Aak Calotropis procera Asclepiadaceae Core Zone
3 Vilayati Babool Prosopis juliflora Fabaceae Core Zone
4 Ber Zizyphus nummularia Rhamnaceae Core Zone
5 Oontkateli Echinops echinatus Asteraceae Core Zone
6 Bui Aerva tomentosa Amaranthaceae Core Zone
Herbs
S. No. Common Name Botanical Name Family Core/ Buffer Zone
1 Kantakari Solanum xanthocarpum Solanaceae Core Zone
2 Makara or crowfoot grass
Dactyloctenium aegyptium Poaceae Core Zone
3 Sarphonka Tephrosia purpurea Fabaceae Core Zone
4 Bhurat Cenchrus biflorus Poaceae Core Zone
5 Bermuda Grass or Doob
Cynodon dactylon Poaceae Core Zone
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 51
FLORA : Buffer Zone
Trees
S. No. Common Name Botanical Name Family Core/ Buffer
Zone
1. Siris tree Albizia lebbeck Fabaceae Buffer Zone
2. Neem Azadirachta indica Meliaceae Buffer Zone
3. Gum Arabic tree Acacia senegal Fabaceae Buffer Zone
4. Khejri Prosopis cineraria Fabaceae Buffer Zone
5. Kiker or Babool Acacia nilotica Leguminosae Buffer Zone
6. Shisham Dalbergia sissoo Fabaceae Buffer Zone
7. Ardu Ailanthus excelsa Simaroubaceae Buffer Zone
8. Pipal Ficus relegiosa Moraceae Buffer Zone
9. Reonja or Safed babool Acacia leucophloea Fabaceae Buffer Zone
10. Bargad Ficus bengalenesis Moraceae. Buffer Zone
11. Kankera Maytinus emarginata Celastraceace Buffer Zone
12. Palash Butea monosperma Fabaceae Buffer Zone
13. Indian Elm Holoptelea integrifolia Ulmaceae Buffer Zone
14 Mahua Madhuca longifolia Sapotaceae Buffer Zone
15 Kassod Tree Cassia samia Caesalpiniaceae Buffer Zone
16 Safeeda Eucalyptus Myrtaceae Buffer Zone
Shrubs
S.
No.
Common Name Botanical Name Family Core/ Buffer
Zone
1. Ber Zyzipus nummularia Rhamnaceae Buffer Zone
2. Dandathor Euforbia caducifolia Euphorbiaceae Buffer Zone
3. Gajar grass Parthenium hysterophorus Asteraceae Buffer Zone
4. Vilayati Babool Prosopis juliflora Fabaceae Buffer Zone
5. Khimp Leptadenia pyrotechnica Apocynaceae Buffer Zone
6. Gokharu Tribulus terrestris Zygophyllaceae Buffer Zone
7. Damasa Tephrosia purpurea Fabaceae Buffer Zone
8. Kaner Nerium oleander Apocynaceae Buffer Zone
9. Arandi Ricinus cummunis Euphorbiaceae Buffer Zone
10. Kair Capparis decidua Capparaceae Buffer Zone
11. Aak Calotropis procera Asclepiadaceae Buffer Zone
12 Munja grass Saccharum munja Poaceae Buffer Zone
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR AUTHORIZED SIGNATORY / PP
SEPT’ 2014 52
Herbs
S.
No.
Common Name Botanical Name Family Core/ Buffer
Zone
1. Fiddler's spurge Euphorbia granulata Euphorbiaceae Buffer Zone
2. Bermuda Grass or
Doob
Cynodon dactylon Poaceae Buffer Zone
3. Bui Aerva tomentosa Amaranthaceae Buffer Zone
4. Satyanasi Argemone maxicana Papaveraceae Buffer Zone
5. Bhurat Cenchrus biflorus Poaceae Buffer Zone
6. Buffel Grass Cenchrus ciliaris Poaceae Buffer Zone
7. Bhurat Cenchrus biflorus Poaceae Buffer Zone
8. Crowfoot grass Dactyloctenium aegyptium Poaceae Buffer Zone
9. Kantakari Solanum xanthocarpum Solanaceae Buffer Zone
10. Ghamra Tridex procumbens Asteraceae Buffer Zone
11. Barrut grass Sorghum halepense Poaceae Buffer Zone
12. Motha Cyperus rotundus Cyperaceae Buffer Zone
13. Gokharu herb Tribulus terrestris Zygophyllaceae Buffer Zone
14. Sarphonka Tephrosia purpurea Fabaceae Buffer Zone
15 Crabgrass Digitaria sanguinalis Poaceae Buffer Zone
16 Chakvad Cassia Tora Fabaceae Buffer Zone
17 Cocklebur or chota
gokhuru Xanthium strumarium
Asteraceae Buffer Zone
FAUNA:
Core Zone
S.
No.
Common name Binomial name Family Schedule
IW(P)A/ IUCN
1 Pisces
No aquatic land observed at the site of study area during survey.
2 Amphibia
No amphibian observed during survey of site visit in core zone.
3. Reptilia
1 Garden Lizard Calotes versicolor Agamidae LC
4. Avis or Avifuana
1 Common Bulbul Pycnonotus barbatus Pycnonotidae IV
2 Rose-ringed Parakeet Psittacula krameri Psittacidae IV
3 House crow Corvus splendens Corvidae V
5. Mammalia
-
PROJECT : LIME STONE (BUILDING STONE) PRE - FEASIBILTY REPORT
APPLICANT : M/s SAMPOORNA EXPORTS (P) LIMITED
DOCUMENT NO.: EESPL/ SIPL-168/ 002/ 168-EC/ MINE/ 2014
ENKAY ENVIRO SERVICES PVT. LTD., JAIPUR