printable chetan1

Upload: piyush-sondarva

Post on 09-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Printable Chetan1

    1/26

    1

    Table of ContentsChapter I................................ ................................ ................................ ................................ ............ 3

    INTRODUCTION ................................ ................................ ................................ ............................. 3

    PERSONAL INFORMATION ABOUT PARTNERS ................................ ................................ ................ 4PRESENT STATUS & MARKET POTENTIAL................................ ................................ ........................ 5

    Brief about Leather Industry ................................ ................................ ................................ ...... 6

    Existing manufacturers of the product in our area and their annual production/sales turn over . 6

    Annual production and market need ................................ ................................ .......................... 7

    Expected customer and selected areas................................ ................................ ....................... 7

    Marketing strategy ................................ ................................ ................................ ..................... 7

    Scope of diversification ................................ ................................ ................................ .............. 7

    Risk factors ................................ ................................ ................................ ................................ 8

    Chapter II ................................ ................................ ................................ ................................ ........... 9

    COST OF THE PROJECT AND MEANS OF FINANCE ................................ ................................ ............... 9

    TYPE OF UNIT AND SITE SELECTION ................................ ................................ ............................ 9

    COST OF PROJECT ................................ ................................ ................................ ...................... 9MEANS OF FINANCE ................................ ................................ ................................ ................. 10

    Chapter III ................................ ................................ ................................ ................................ ........ 11

    PRODUCTION PROGRAMME AND PROCESS ................................ ................................ ................. 11

    PRODUCTION PROGRAMME ................................ ................................ ................................ .... 11

    PRODUCTION PROCESS ................................ ................................ ................................ ............ 11

    Chapter IV ................................ ................................ ................................ ................................ ....... 14

    FACILITIES AND UTILITIES ................................ ................................ ................................ ............. 14

    MANPOWER REQUIREMENTS ................................ ................................ ................................ .. 14

    INFRASTRUCTURE FACILITIES (100% Capacity utilisation) ................................ ......................... 15

    UTILITIES AND OVERHEAD COSTS: (at 100% capacity utilization) ................................ .............. 15

    ADMINISTRATIVE EXPENSES (at 100% capacity utilization) ................................ ....................... 15

    Chapter V ................................ ................................ ................................ ................................ ........ 16BREAK EVEN CALCULATION ................................ ................................ ................................ .......... 16

    ANALYSIS OF BREAK EVEN Analysis ................................ ................................ .......................... 16

    (Rs. In thousands) ................................ ................................ ................................ .................... 16

    Chapter VI ................................ ................................ ................................ ................................ ....... 17

    PROJECT IMPLEMENTATION SCHEDULE ................................ ................................ ....................... 17

    PROJECT IMPLEMENTATION SCHEDULE ................................ ................................ ................... 17

    Chapter VII ................................ ................................ ................................ ................................ ...... 18

    HR POLICIES ................................ ................................ ................................ ................................ . 18

    ANNEXURES ................................ ................................ ................................ ................................ ..... 19

    ANNEXURE-1 ................................ ................................ ................................ ............................... 19

    COST OF PLANT AND MACHINERY ................................ ................................ ............................ 19

    COST OF OTHER FIXED ASSETS ................................ ................................ ................................ . 19

    LAND AND BUILDING ................................ ................................ ................................ ............... 20

    PRE- OPERATIVE EXPENSES ................................ ................................ ................................ ...... 20

    NAME AND ADDRESSES OF THE MACHINERY SUPPLIERS ................................ .......................... 21

    ANNEXURE-2 ................................ ................................ ................................ ............................... 22

    RAW MATERIAL REQUIREMENT AND ITS COST ................................ ................................ ......... 22

    ANNEXURE-3 ................................ ................................ ................................ ............................... 23

    WORKING CAPITAL REQUIREMENTS (AT 100% UTILIZATION) ................................ ................... 23

    ANNEXURE-4 ................................ ................................ ................................ ............................... 23

  • 8/8/2019 Printable Chetan1

    2/26

    2

    DEPRECIATION CALCULATION ................................ ................................ ................................ .. 23

    ANNEXURE-5 ................................ ................................ ................................ ............................... 23

    INTEREST CALCULATION ................................ ................................ ................................ ........... 23

    ANNEXURE-6 ................................ ................................ ................................ ............................... 24

    COST OF PRODUCTION AND PROFITABILITY (AT 90% CAPACITY UTILIZATION) .......................... 24

    ANNEXURE-7 ................................ ................................ ................................ ............................... 25

    CASH FLOW STATEMENT ................................ ................................ ................................ .......... 25ANNEXURE-8 ................................ ................................ ................................ ............................... 26

    INTERNAL RATE OF RETURN (IRR) ................................ ................................ ............................. 26

  • 8/8/2019 Printable Chetan1

    3/26

    3

    Chapter I

    INTRODUCTION

    Bag is one of the convenient means used for carrying the belongings such as clothes, daily-use articles, books in case of students and other essentials during travelling from one place to

    other. Some other types of bags are also used for carrying important documents and office

    use equipments by the executives and high profile personnel. Although this product is

    manufactured from various types of materials such as textile, jute, coated fabrics, yet leather

    bag is having wider acceptance due to its superior strength, aesthetic look and up-man-ship

    among middle and high-income group people. A wide range of bags are in use for various

    purposes. The cost of the leather bags depend upon the type of leather nylon, space and/or

    style of it. This project aims at manufacturing various school bags and other variants.

    JVK bag will be a bag manufacturing unit located in Botad. The main idea behind starting

    this project is the potential opportunity that is untapped yet. We are going to manufacture

    bags as per the order and requirement of targeted customer. We will have a good scope of

    getting large quantity order from school bag retailers, wholesalers, government, various,

    tuition classes, and co operative societies. Looking into the trend, there is good scope in this

    particular segment because now days each and every coaching-classes and tuition classes

    institutions are giving a bag to the students. For e.g. PT education/Endeavour, CAT and other

    Entrance exams coaching classes, give bags to their students with their brand name on it.

    Companies give various type of bag to their employee like office bag, Tiffin bag, and

    equipment tool bag. We have a number of non profit making organizations which give a

    trolly bag, and other bags as gift. Thus there is a huge scope and potential for our venture to

    grow and create significant value.

    We will be producing the bags as per order and requirements of target audience. What type of

    bag they need? In what price they can afford? What type of raw material they want? These

    are the questions on the basis of which we will be judging particular requirements of

    customer regarding bag. The price of bag will be fixed according to the use of particular raw

    material in the bag. We will also negotiate with different parties in deciding the price of bag

    and in initial stages our aim will be customer satisfaction rather than profit maximization.

  • 8/8/2019 Printable Chetan1

    4/26

    4

    PERSONAL INFORMATION ABOUTPARTNERS

    JVK bag is a partnership firm which will be established by following partners mentioned

    below. We will come in to the partnership by contract between us about capital investment,

    profit sharing, and other activities. Each of us has a special skill in different field of the

    business.

    1) Name : Bijaya Laxmi ChoudharyAddress : Nepal

    Telephone number : 9909567756

    Date of birth : 01/10/1986

    Education qualification : MBA Marketing

    Family background : Service

    Your strength in this field : Marketing

    2) Name : Chetan G GohelAddress : Aveda Gate, Botad

    Telephone number : 9033318066

    Date of birth : 08/07/1988

    Education qualification : MBA Finance

    Family background : Business

    Your strength in this field : Experience in producing bag

    3) Name : Sondarva PiyushAddress : Police line, Maliya hatina

    Telephone number : 09228384443

    Date of birth : 30/04/1987

    Education qualification : MBA Marketing

    Family background : Service

    Your strength in this field : Marketing research

  • 8/8/2019 Printable Chetan1

    5/26

    5

    4) Name : Jignesh V KhadelaAddress : 302, Plot area, Chogath,Ta-Umrala,District-Bhavnagar

    Telephone number : M-9510785145

    Date of birth : 27/6/1989

    Education qualification : MBA (Finance)

    Family background : Agriculture

    Your strength in this field : Finance

    PRESENT STATUS & MARKETPOTENTIAL

    The leather and leather products industry is one of Indias oldest manufacturing industries

    that catered to the international market right from the middle of the nineteenth century. Since

    the beginning the demand for its products has been both domestic as well as international.

    About 46 per cent of the production in the sector is exported and it ranks eighth in the list of

    Indias top export earning industries and contributes roughly Rs. 10,000 crores per annum,

    i.e., about 4 per cent to export earnings. The sector accounts for 2.5 per cent of the global

    leather-related trade of Rs. 387,200 crores. An estimated 15 per cent of total purchase of

    leading global brands in footwear, garments, leather goods & accessories, in Europe, and 10

    percent of global supply is outsourced from India.

    The demand for bags is increasing day-by-day in tune with the growth of industrialization,

    educational institutions and coaching classes. The products with a price range of Rs. 200 to

    Rs.400 are commonly seen in the market which is felt quite acceptable with reasonable

    quality. Further, export worthiness of this product is quite substantial with qualitative and

    latest designs. A small manufacturer can have tie-up with any exporter merchant in the

    country for executing the order as per the specified design. There is an ample scope of

    students bags unit with ease and considerably cheaper availability of indigenous raw

    materials and skilled manpower.

  • 8/8/2019 Printable Chetan1

    6/26

    6

    Brief about Leather Industry

    The leather industry employs about 2.5 million people and has annual turnover of Rs. 25,000

    crores. The industry is also one with strong links with the social structure through caste and

    community. Thus a large number of people engaged in the industry (entrepreneurs as well asworkers) are even today, from traditional leather working castes (belonging to the lower

    castes in the caste hierarchy) and the Muslim community. Due to the age of the industry and

    its links with the social structure, the organisational structure that has emerged is a very

    complex one that contains within it elements of continuity with traditional structures as well

    as those that represent a break with them. In addition to these historical aspects of its

    evolution, the dynamics of the industry has been shaped, to a large extent, by export

    orientation from colonial times. The sector is dominated by small-scale firms although there

    are also a significant number of medium and large sized firms in all segments of the industry.

    The industry is concentrated in several leather clusters in four or five distinct locations in the

    country, with each cluster containing a wide variety of enterprise forms and organisational

    structure. To be more specific, the major production centres of leather and leather products

    are located at Chennai, Ambur, Ranipet, Vaniyambadi, Trichy, Dindigul in Tamil Nadu,

    Kolkata in West Bengal, Kanpur and Agra in U.P., Jallandhar in Punjab, Delhi, Hyderabad in

    Andhra Pradesh, Bangalore in Karnataka and Mumbai in Maharashtra. Tamil Nadu is the

    biggest leather exporter 40 percent of the country and its share in Indias output on leather

    products is 70 percent.

    Currently, Gujarat has around 300 small and medium plastic bag and school bags

    manufacturing units with a total industry size pegged at close to Rs 300 crore (Source:

    Gujarat State Plastic Manufacturers Association (GSPMA)).

    Existing manufacturers of the product in our area and their annual

    production/sales turn over

    Name Location Sales turnover

    Kisan bag Botad 150000

    Spirit bag Bhavnagar 200000

    Dharmesh bag Bhavnagar 300000

  • 8/8/2019 Printable Chetan1

    7/26

    7

    Annual production and market need

    The total annual production capacity of our plant will be 750000 units. As the numbers of the

    schools are increasing day by day so there is a great demand of these bags in prevailing

    market. We will try to capture complete market in nearby areas of Botad and complete orders

    far away places if it is according to our convenience and need. In the initial years, we will be

    able to fulfil the market need at 80 per cent capacity utilization and will be able to get good

    amount of profit.

    Expected customer and selected areas

    We are expecting all type of customers pertaining to the need of bags. The major customers

    will be coaching classes, retail marketers, large companies etc. We will first try to cover the

    areas which are nearby Botad and Bhavnagar side areas so that our distribution cost can be

    minimized. If we are able to meet the demand of nearby areas then we will try to look at the

    large cities like Ahmedabad, Rajkot, Vidyanagar, Baroda etc. Our prime objective will be

    customer satisfaction and meeting to their needs on time in all areas.

    Marketing strategy

    We will try to use different marketing strategy at different market looking at the need of the

    market and conditions prevailing in that market. The main strategy which will be used by us

    will be pricing strategy. We will be providing more discounts on bulk buying. Our initial

    strategy will be market penetration rather than profit maximization. When we are dealing

    with coaching classes we will try to see that we provide such a service that they become our

    regular customer. We will keep separate price for coaching class and retailer market. The

    bags will be distributed as per the demand of the market. We will be also making some

    special bags with extra strength if demanded and the price will be separate for such units.

    We will see to that there is no fixed price for any type of bags which are provided in bulks

    but we will be focusing on our negotiating skill. With proper negotiation with various dealers

    we will try to maximise our profit by customer satisfaction.

    Scope of diversification

    We will try to gain maximum from the existing business only but if needed or as per the

    demand of market we will try to look at the various diversification options available to our business. If possible we will try to diversify into manufacturing of travelling bags or

    manufacturing of leather shoes. We will also try to manufacture various other leather

    products if possible.

  • 8/8/2019 Printable Chetan1

    8/26

    8

    Risk factors

    There are various risk factors available with our project but we will try minimizing or

    nullifying those risk factors with our specialization and proper research and study of market.

    The various risk factors are:

    1. Inventory pile up: - If we are not able to study the demand of market properly then there

    are chances that our inventory will be piled up and resulting into a great loss arising out of

    inventory pile up.

    2. Competitors entry: - as it is an open market so there can be easy entry of competitors

    which can also have a great influence on the demand curve of our business.

  • 8/8/2019 Printable Chetan1

    9/26

    9

    Chapter II

    COST OF THE PROJECT AND MEANS OF FINANCE

    TYPE OF UNIT ANDSITESELECTIONName of unit : JVK Bag

    Address : JVK BAG

    Paliyad road,

    Botad-364710 Dist- Bhavnagar

    Type of unit : Small scale Industry

    Techno-economical reason for site selection : The main reasons behind selecting GIDC

    Botad are nearness to market and availability cheaper land and workforce. Besides, GIDC

    Botad provides following benefits:

    GIDC land is for industrial purpose. So no need to waste time on getting Non-Agricultural./ N.O.C.

    GIDC establishes its estates after verifying the viability and availability of water,power, linkages, communication, disposal of waste water etc. So the entrepreneur getsa really developed and planned area

    An entrepreneur can start the industry by paying only 30 % of the total cost as downpayment and can pay remaining amount in a period of 10 years.

    GIDC estate provides a unique opportunity to an entrepreneur to avail cluster benefitsrelated to raw material, market, technology, common services, linkages etc.

    Location of the factory & address : as mentioned above

    Requirement of land & building : 5000 sq metres

    COST OF PROJECT

    Land : 5000000

    Building : 800000

    Plant & machinery : 925600

    (Including installation, erection, electrification)

  • 8/8/2019 Printable Chetan1

    10/26

    10

    Other fixed asset : 215000

    Contingency and escalation : 50000

    Preliminary & preoperative expenses : 80000

    Working capital margin : 2505650

    Total Rs. 9576250(=9600000)

    MEANS OF FINANCE

    1. Promoters contribution : 40000002. Long term loan(@8% : 31000003. Working capital loan : 2500000

    Total 9600000

    PRELIMINARYANDPREOPERATIVEEXPENSES

    Pre-operativeExpenses (Rs.)

    1. Preparation of project report and consultancy 40000

    2. Administrative expenses 10000

    3. Travelling, Market development and tie-up 20,000

    4. Other formalities and expenses prior to production 10,000

    Total 80000

  • 8/8/2019 Printable Chetan1

    11/26

    11

    Chapter III

    PRODUCTIONPROGRAMMEAND PROCESS

    PRODUCTION PROGRAMME

    Annual installed capacity : 750000

    Utilization of capacity : first year we will utilize 80% of capacity install, next year

    90%, and thereafter 100% onwards we use our capacity

    Number of shift per day: 2 shifts per day

    Production detail per year

    Sr. No Name of the

    product

    At 80%

    utilization

    At 90%

    utilization

    At 100%

    utilization1 School Bag 160000 180000 200000

    2 Side bag 72000 81000 90000

    3 College bag 88000 99000 110000

    4 Kids bag 40000 50000 50000

    5 Cross belt bag 40000 50000 50000

    6 Haver shape bags 40000 50000 50000

    7 Teddybears bag 40000 50000 50000

    8 Equipment bag 120000 135000 150000

    PRODUCTION PROCESS

    Technical know-how availability

    The leather bags proposed to be manufactured in this project are mainly as per customer

    requirement. First of all the components are cut from suitable materials. The basic raw

    material is the finished nylon or leather, which is not uniform, irregular in shape and size,

    variation with grain structure and presence of defects on the surface. On the other hand, the

    components are generally regular or rectangular shape and the adjacent components should

    have similar shade and structure. Therefore, necessary care should be taken in cutting thecomponents. The cut components are then skived to the edges for ease of folding and/or

    stitching. The edges are then beaded and the zips and other fasteners attached as per the

    specification. The outer surface (leather), the inner surface (lining) and the re-enforcement

    materials if required so, are attached first with the adhesive and then by stitching. The linings

    and thread-ends are trimmed and sealed. The surface is cleaned and polished and made ready

    for packing

  • 8/8/2019 Printable Chetan1

    12/26

    12

    Step wise conversion process from raw material to finished product with the

    utilisation of per unit production

    Step 1: Cutting of a nylon or leather as per customer order with a bag making tool.

    Step 2: Giving priorities and order to each and every work, so that less time will require.Priority is given such a way that each of the nylon pieces stitch on skewing machine in order

    so that minimum time require to produce bag. It will also reduce free time time of worker.

    Step 3: As per order or priorities stitching work will given to worker.

    Step 4: After stitching, with bag making tool and other equipment the nylon, lock, handle,

    and nylon border will fit to the bag.

    Step 5: Bags will ready for packing and quality checking. Bags will pack in polythine bag.

    Raw material requirement per unit production

    The basic raw materials to produce one bag are nylon or leather, zip, chain, lock, handle,

    nylon border, etc. The quantity of raw material requirement will depend on the size of the

    bag. For example if we have to produce a single bag size of 18 inch the following raw

    material required.

    Nylon or leather 0.5 meter if length is 60

    Nylon border 3 meter

    Chain 3 meter

    Zip Depends on number of pocketLock 2 pcs

    Handle and other item As per requirement

    Quality control measures

    The quality of this product has to be maintained as per buyer's specification. However, the

    main criteria for quality control are selection of suitable materials, (especially the nylon with

    required thickness, shade, strength and softness) cutting components from suitable portions of

    nylon, uniform folding, fastener attachment, regular stitching with suitable thread with

    specified stitch length and finishing.

    We own a highly spacious manufacturing unit which is spread over a vast area and is

    equipped with all the essential facilities that ensure an uninterrupted production of variety of

    bags. To assist in creating unique designer bags, we are backed by an in-house design unit

  • 8/8/2019 Printable Chetan1

    13/26

    13

    which is managed by experienced designers and craftsmen. These personnel are engaged in

    developing bags in standard as well as customized options.

    Our manufacturing plant has various efficient machines that assist in producing a flawless

    range of designer bags without causing any material wastage, in the process.

  • 8/8/2019 Printable Chetan1

    14/26

    14

    Chapter IV

    FACILITIES AND UTILITIES

    MANPOWERREQUIREMENTS (at 90% capacity utilisation)

    Sr. No. Particulars Nos. Salary per

    month

    Monthly Rs. Yearly Rs.

    A)

    1

    2

    3

    4

    5

    6

    Factory staff

    Production manager

    Supervisor

    Skilled worker(s)

    Semi-skilled

    worker(s)

    Unskilled worker(s)

    Chowkidar

    2

    10

    100

    20

    5

    1

    20000

    5000

    3000

    2000

    1500

    1200

    40000

    50000

    300000

    40000

    7500

    1200

    480000

    600000

    3600000

    480000

    90000

    14400

    B)

    7

    8

    9

    Office Staff

    Clerk/Typist

    Accountant

    Peon

    1

    1

    1

    4000

    6000

    1200

    4000

    6000

    1200

    48000

    72000

    14400

    C)

    10

    11

    Sales staff

    Sales manager

    Field staff

    2

    10

    20000

    6000

    40000

    60000

    480000

    720000

    Subtotal:

    Add: Benefits@30%

    6598800

    1979640

    Total........ 8578440

  • 8/8/2019 Printable Chetan1

    15/26

    15

    INFRASTRUCTURE FACILITIES (100% Capacity utilisation)

    Electricity : 360000

    Fuel requirement/day (oil, gas, etc.) : 60000

    UTILITIESAND OVERHEAD COSTS: (at 100% capacity utilization)

    Sr. No. Particulars Monthly Rs. Yearly Rs.

    1 Electricity 30000 360000

    2 Fuel 5000 60000

    3 Repair and maintenance 200000

    TotalRs. 35000 620000

    ADMINISTRATIVEEXPENSES (at 100% capacity utilization)

    Sl.

    No.

    DescriptionAmount

    (Rs.)

    1. Other consumable 10000

    2. Insurance 20000

    3. Telephone, fax and other postal expenses 24000

    4. Stationery and printing 10000

    5. Other misc. expenditure 10000

    Total 274000

  • 8/8/2019 Printable Chetan1

    16/26

    16

    Chapter V

    BREAKEVEN CALCULATION

    ANALYSIS OF BREAKEVENAnalysis

    (Rs. In thousands)

    A.Sales realisation 108000B. Variable cost

    - Raw material 92500- Consumables 180- Power and fuel, water 480- Salaries and wages 8578- Interest on working capital loan 150- Selling, packing & distribution expenses 3500

    Total Variable Cost 105358

    Variable cost PerUnit Rs. (600000units) 176C.Fixed cost

    - Repair & Maintenance 200- Rent, Taxes, Insurance 150- Salary & wages 1200- Administrative 274- Interest on term loan 248- Depreciation 221

    Total Fixed Cost 2293

    D. Contribution 2642

    BEP=

    Revenue=Variable cost + Total cost

    180X=176X+2293

    X=573.250

    HenceBEPis 573250 units.

    (OnandAveragethesellingpriceofabagisassumedtobeRs.180)

  • 8/8/2019 Printable Chetan1

    17/26

    17

    Chapter VI

    PROJECT IMPLEMENTATION SCHEDULE

    PROJECT IMPLEMENTATIONSCHEDULE Days Date

    Auspicious beginning (On Auspicius day ofLabh Pancham) - Nov 10,2010

    1. Project selection and completion and market survey 15 Nov 25,20102. Project report preparation 5 Nov 30,20103. Site selection 5 Dec 5,20104. Loan application for Fixed asset and working capital 15 Dec 20,20105. Machinery order to be placed 3 Dec 20,20106. Building for factory to be ready(starting from Nov10) 180 May 10,20117. Installation of the machine 7 May 17,20118. Power connection 15 June 2,20119. Recruitment of manpower 7 June 9,201110.Electrification/ Erection 5 June 14,201111.Trial Production 15 June 29,201112.Sales Arrangements 7 July 6,201113.Commercial Production 30 Aug 6,2011

  • 8/8/2019 Printable Chetan1

    18/26

    18

    Chapter VII

    HR POLICIES

    We will be using following H.R .policies for carrying out our project in a successful manner.

    The different HR policies are:-

    Recruitment:-

    Our recruitment policy for workers will be not based on their qualification but how better

    they are able to deal with machine. We will try to conduct some test with stitching of bags

    and we will try to see how efficiently they are able to make the bags. In case of higher staff

    we will try to see various skills like technical know-how and selling and production

    knowledge of different persons in various departments. The salary will be provided to people

    at various levels as per their skills and experience.

    Compensation:-

    We will keep different type of compensation plans for various levels of people. We will try

    to compensate through some gifts or by providing bonus during various festivals or during

    birthday of that particular person. We will try to see that suitable compensation is available

    for right person.

    Training:-

    There will be certain programs available in order to increase the efficiency of the staff at

    various levels. At higher level we will be conducting training programs like attending

    seminars and various study circle related to our industry. For other staff we will be

    conducting programs to increase the speed and efficiency of stitching so that we can get a

    better output.

    Motivation:-

    There will be various motivational activities in order to make homely atmosphere. One type

    of motivation will be providing compensation to the workers. We will also try to give

    surprise birthday gifts to various workers in order to motivate them. We will also keep some

    special gifts of the day who stitch maximum bags in a day. We will try to make lively

    atmosphere by playing certain indoor games on some special occasion. We will try to see that

    essential need of the workers is being taken care of.

  • 8/8/2019 Printable Chetan1

    19/26

    19

    ANNEXURES

    ANNEXURE-1

    COST OF PLANT AND MACHINERY

    Sr.No Name/Particularof

    Machinerys with

    specification

    Nos.

    Required

    Costperm/c TotalValue

    1

    2

    3

    4

    Sewingmachine25 vaultmotor

    Standofsewingmachine

    Plywoodplate

    Total:

    Add: 30% towardstaxes,freight,insurance,

    installation,erection,

    electrificationetc

    40

    40

    40

    40

    15000

    1000

    1200

    600

    600000

    40000

    48000

    24000

    712000

    213600

    GrandTotal 925600

    COST OF OTHER FIXEDASSETS

    Sl.

    No.Description Qty.

    Rate

    (Rs.)

    Value

    (Rs.)

    1. Bag makers tool kit 3 sets 5000 15000

    2.Machine maintenance and

    electricians tool kit1set -

    5000

    3.Testing equipments-thickness

    gauge, measuring scales etc.- -

    5000

    4.Workshop working tables,

    racks etc.- -

    80000

    5.Office furniture and

    equipments- -

    100000

  • 8/8/2019 Printable Chetan1

    20/26

    20

    6. Misc. equipments - - 10000

    215000

    LANDANDBUILDING

    (i) LandandBuildingAmount

    (InRs.)

    (i) Land 5000 sq. ft. @ Rs. 1000 per sq. ft including

    registration 5000000

    (ii) Total built-up area 2000 sq. ft. @ Rs 400 per sq ft 800000

    Total civil cost= cost of land + building 5800000

    PRE- OPERATIVEEXPENSES

    Pre-operativeExpenses (Rs.)

    1. Preparation of project report and consultancy 40000

    2. Administrative expenses 10000

    3. Travelling, Market development and tie-up 20,000

    4. Other formalities and expenses prior to production 10,000

    Total 80000

  • 8/8/2019 Printable Chetan1

    21/26

    21

    NAMEANDADDRESSES OF THE MACHINERYSUPPLIERS

    1. NSIC Technical Service Centre

    Sector B-24, Guindy Indl. Estate,

    Ekkaduthangal,Chennai-32.

    2. M/s. Atlanta Trading (P) Ltd.

    Atur House,Worli Naka,

    Mumbai-18.

    3. M/s. Twin Star Engineering

    No. 98, Pammal Main Road,

    Pammal,

    Chennai-75.

    4. M/s. Raj Machine HomeOpp. New Jyoti Building,

    35/44, Karabala Road,Agra-5.

  • 8/8/2019 Printable Chetan1

    22/26

    22

    ANNEXURE-2

    RAW MATERIAL REQUIREMENT AND ITS COST

    REQUIREMENT PER YEAR (AT 90% CAPACITY UTILISATION)

    Sr. No Name/ Particular of raw materials

    required

    Qty per bag Value (in 000)

    1

    2

    3

    4

    56

    Nylon or leather

    Chain

    Runner

    Nylon border

    LockOther things like thread,lable

    printing

    0.5 mtr

    3 mtr

    5 pcs

    5 mtr

    2 pcsAs per

    requirement

    37500

    7500

    11250

    11250

    150007500

    90000

    NAMEANDADDRESSES OF RAWMATERIALSSUPPLIERS

    1. M/s. Alpha Global

    445/1,6th Cross, 7th Block,

    Jayanagar KPM Road,

    Baroda-560 082.

    2. M/s. Amjad Finished Leather Co.

    54, Maddox Street, Choolai,

    Rajkot-112.

    3. M/s. Arkay Leathers

    No. 3, Third Floor, Crown Court,

    34, Chathedral Road,

    Ahemdebad-86.

    4. M/s. Mow Chung Tannery Pvt. Ltd.

    47, South Tangra Road,

    Kolkata-46.

    5. M/s. Pidilite Industries Ltd.

    J.B. Marg, Nariman Point,

    Delhi

    (for adhesive)

    6. M/s. APL Poly Fab Pvt. Ltd.

    48 C, Matheswar Tala Road,

    bhavnagar-46

    (for lining)

  • 8/8/2019 Printable Chetan1

    23/26

    23

    ANNEXURE-3

    WORKING CAPITAL REQUIREMENTS (AT 100% UTILIZATION)

    a) Raw Material(15 days ) :3750000b) Stock in process(2 days) : 500000c) Finished goods stocks (1 month) :2500000d) Receivables :6250000e) Working expenses for one-month :772600

    (Salaries: Rs.714800 and Other

    Expenses:57800)

    Total: 13772600

    Less: Credit against purchases :3750000

    Net working capital :10022600

    Margin for working capital

    @25% of net working capital :2505650

    ANNEXURE-4

    DEPRECIATION CALCULATION

    Particular Percentage Yearly(Rs)

    Building 5 40000

    Machinery 15 138840

    Tools and furniture 20 43000

    Total 221840

    ANNEXURE-5

    INTEREST CALCULATION

    Particular Percentage Yearly (Rs)

    Interest on term loan 8 248000

    Interest on working capitalloan

    6 150000

    Total 398000

  • 8/8/2019 Printable Chetan1

    24/26

    24

    ANNEXURE-6

    COST OF PRODUCTIONAND PROFITABILITY (AT 90% CAPACITY

    UTILIZATION)

    Sr. No. Particulars Yearly ( Rs in crore)

    A) Cost of Production1 Raw Material 90000

    2 Utilities 730

    3 Consumables, Stores and Spare 180

    4 Repair and maintenance 200

    5 Rent, Tax and Insurance 290

    6 Salaries and Wages 8578

    7 Administration Expenses 274

    8 Selling, Distribution and Marketing

    Expenses

    5000

    9 Packaging Expenses 500

    10 Miscellaneous Expenses 100

    11 Interest on Term Loan 248

    Working capital Loan 150

    12 Depreciation 221

    Total Production Cost 106471

    B) Income

    1 Total Sales Income 108000

    2 Job Work Income 1200

    3 Scrap and Other 50

    Total Income 109250

    C) Gross Profit (B-A) 2729

    D) Income Tax(@30%) 818

    E)N

    et Profit (C-D) 1911

  • 8/8/2019 Printable Chetan1

    25/26

    25

    ANNEXURE-7

    CASH FLOW STATEMENT

    Sources of Fund Year of Production

    I II III IV V

    1. Term loan 3100 - - - -2. Promoters Contribution 4000 - - - -

    3. Gross profit(Percent increase over previous

    year)

    2729 2947

    (5%)

    3242

    (10%)

    3728

    (15%)

    4473

    (20)

    4. Working Capital Loan 2500 - - - -Capital Investment 6970 - - - -

    Increase in Net Working Capital 10000 100 150 180 180

    Repayment of Loan - 620 620 620 620

    Interest on term loan(@8% onoutstanding amount at the end of

    year)

    248 198 148 99 49

    Interest on Bank Loan(@6% on

    2500)

    150 150 150 150 150

    Opening Balance 3000 (2039) (160) 2014 4693

    Net Surplus (5039) 1879 2174 2679 3474

    Closing Balance (2039) (160) 2014 4693 8167

  • 8/8/2019 Printable Chetan1

    26/26

    ANNEXURE-8

    INTERNAL RATE OF RETURN (IRR)

    Internal Rate of Return (IRR) =

    CALCULATION OF IRR(Net cash flows RS in thousands)

    C0 NCI1 NCI2 NCI3 NCI4 NCI5 terminal value*

    Net Cash Inflows -9600 -5039 1879 2174 2679 3474 39372

    IRR 27%

    *Terminal value= 3473(1+Growth Rate)

    Ke-g

    (Where Ke=11%, g=2%)