river user update - parks.vic.gov.au
TRANSCRIPT
River User UPDATE
Edition 2 – September
2021
Lower Yarra River Maintenance Dredging Program
Dredging Campaign 2021/22 Maintenance dredging is conducted in the Lower Yarra River to ensure safe boating navigation and
access. The second year of dredging under the current four-year Maintenance Dredging Program,
to commence in mid-October 2021 and run for about six months, will target sites between Botanic
Gardens Landing and Burnley Harbour.
Where will dredging occur during this campaign?
Dredging will commence at the upstream end of
the project area and progress in a downstream
direction. The 2021/22 Dredging Campaign will
therefore target dredging sites upstream of the
CBD area. Sites will be dredged in the following
order:
A) Herring Island Landing & Como Landing
B) Burnley southern bank- navigational
channel
C) Burnley Harbour
D) Botanic Gardens Landing & Morell Bridge
southern arch
See attached map for location of dredging sites.
When will dredging occur?
Dredging is scheduled to start in mid-October and
be completed in March 2022. A detailed dredging
schedule will be included in the Notice to River
Users for the Yarra River and available on the
Parks Victoria website.
Will the dredging impact river traffic and river access?
During the dredging of Herring Island Landing and
Como Landing, Herring Island Meander will be
closed. This is expected to be for around 5 weeks.
For all other dredging sites, the river will remain
open for traffic during dredging operations.
However, river traffic may be restricted to one-
lane traffic past the dredging operations.
There will be no access to dredging sites during
the dredging works and exclusion zones, clearly
marked with stringline buoys, will be established.
For current river traffic conditions refer to the latest Notice to River Users or the Change of Conditions for the Yarra River on the Parks Victoria website: https://www.parks.vic.gov.au/places-to-see/parks/yarra-river.
How much sediment will be removed?
In total, around 10 000 m3 of river sediment will
be removed from the four sites. The sediment will
be pumped via a pipeline to placement areas
downstream of the dredging sites. See attached
map for location of placement areas.
Once the sites have been dredged, the water
depth at the dredging sites will be around 2
metres during low tide.
Why does the river need to be dredged?
The gradual, natural build-up of sediment in the
lower Yarra River has reduced the water depth for
some parts of the river, restricting safe navigation
and access to facilities. The Victorian Government
has invested significantly to improve commercial
and recreational access along the lower Yarra
River through dredging.
What is the Lower Yarra River Maintenance Dredging Program?
Parks Victoria conducts maintenance dredging to
ensure safer navigation and reduce the amount of
sediment in key locations, ensuring the river is
accessible for public use into the future.
The first year of dredging under the Lower Yarra
River Maintenance Dredging Program was
completed in August 2020 and mitigated the most
urgent dredging needs in the river. A total of
4,500 m3 of sediment was removed from the
Victorian Rowing Association Landing and from
underneath the floating sections of the Main
Yarra Trail.
The 2021/22 dredge campaign is the second year
of dredging under the program.
The third dredge campaign will be carried out in
the Winter months of 2022 and target dredging
sites within the CBD area.
Dredging sites to be included in the fourth and
final dredge campaign in 2023 will be determined
based on needs at the time.
Environmental Management
The maintenance dredging program is managed
under an Environmental Management and
Monitoring Plan developed for the project. The
Environmental Management and Monitoring Plan
will ensure that environmental risks are actively
managed and mitigated and that the dredging is
carried out with minimal environmental impact.
More information
If you would like more information about the
Lower Yarra River Maintenance Dredging
Program, please call 13 1963 or email
Figure 1. Dredging and disposal sites for 2021 Dredge Campaign. Dredging sites shown in red A) Herring Island Landing and Como Landing, B) Burnley
southern bank – navigational channel, C) Burnley Harbour D) Botanic Gardens Landing and Morell Bridge southern arch. Placement areas 1 and 2 shown in
yellow. Placement area 2 is used for dredging at dredging site D) Botanic Gardens Landing and Morell Bridge southern arch. Placement area 1 is used for
remaining dredging sites A), B) and C).