Report-3 Proposals Approved by State Investment Promotion Board (SIPB) Sl. No. Name of the Company Proposal Proposed Investment (In Crores Rs.) Direct Employ -ment SIPB Approval date CM/ Cabinet approval date 1 M/S Netarhat Alumni Educational Trust (Vidya Vihar Educational Trust), Purnea. Proposal for Establishment of Engineering College in Purnea 6.74 27.2.06 13.06.06 2 M/S Indian Tractors & Components Pvt. Ltd., New Delhi. (Canceling the earlier name M/S International Tractors Ltd., new name as M/S Indian Tractors & Components Pvt. Ltd. has been approved) Proposal for production of Tractors and Commercial Vehicle at Industrial Area, Fatuha 150.00 27-2-06 29.09.08 29.09.07 27.01.09 3 M/s Gangotri Iron & Steel Co Ltd., Exhibition Road, Patna. Fax: 0612- 2685959 Phone: 2665456 E-mail: [email protected] Proposal for capacity expansion of the Unit and TMT and M.S. Twisted Bars production 33.8 29-3-06 22.10.06 4 M/s Century Ply Wood Ltd., Kolkata. Cement Manufacturing Company Ltd., Sajjan Bhajanka, Chairman, 281 Deepali Pitampura, New Delhi- 110034 Proposal for establishment of one Million Ton/Year Cement Grinding Plant at Kahalgaon 119.00 300 17-4-06 08.09.06 5 Dr. Ashok Kumar ,Medical World 4U Ltd., Sussex. U.K Establishment of Medical College and Super Specialty Hospital at Patna. 148.87 2-5-06 08.09.06 6 Sri Vinod Kumar Chaudhry ,M/s Ambedkar Medical &Technical Educational Development Trust, Lohiya Nagar , Patna. Establishment of Medical and Dental College at Arrah (Bhojpur) 35.076 2-5-06 31.07.06 7 Dr. Rajeshwar Thakur , Patna. (i) Proposal for Multi Super Specialty Hospital in the Jay Prabha Hospital Complex K.Bagh, Patna. (ii) Establishment of Medical College (with training) of National repute. 500.00 300.00 2-5-06 8 M/s Raj Laxmi Udyog, C/O Jain Paper Agency , Rajan Complex, Naya Tola , Patna. Off-Set Paper Printing and Paper Conversion (Place has been changed form Hajipur Industrial Area to Industrial Area Fatuha in SIPB meeting on 19.05.08) 1.645 70 19-6-06 19.05.08 25.07.08 9 M/s Lord Buddha Shiksha Prathisthan, Saharsa. Medical College Hospital 100.00 24-7-06 10 M/s Bharat Sugar Mills, Singhwalia, Gopalganj. Expansion of Sugar Mill from 2500 TCD to 5000 TCD and 15 M.W Co- generation Plant 137.00 1-8-06 15.09.06 11 M/S Ramco Industries Ltd, Chennai (Canceling the earlier approval given by SIPB in its meeting held on 16.12.08 on the proposal for establishment of Asbestos Cement Sheet Plant, Water Storage Plant and Cement Grinding Plant ; approval for establishment of Proposal for establishment of 1,20,000 MT/Annum Capacity of Asbestos Cement Sheet Plant and 2 Lakh MT/Annum Capacity of Cement Grinding Plant at Industrial Area, Bihiya, Bhojpur. 60.20 200 23.11.09 16.12.08

Upload: sm-shadab

Post on 01-Dec-2015

263 views

Category:

Documents


0 download

DESCRIPTION

sipb

TRANSCRIPT

Report-3

Proposals Approved by State Investment Promotion Board (SIPB)

Sl. No.

Name of the Company Proposal Proposed Investment (In Crores Rs.)

Direct Employ -ment

SIPB Approval

date

CM/ Cabinet

approval date

1 M/S Netarhat Alumni Educational Trust (Vidya Vihar Educational Trust), Purnea.

Proposal for Establishment of Engineering College in Purnea

6.74 27.2.06 13.06.06

2 M/S Indian Tractors & Components Pvt. Ltd., New Delhi. (Canceling the earlier name M/S International Tractors Ltd., new name as M/S Indian Tractors & Components Pvt. Ltd. has been approved)

Proposal for production of Tractors and Commercial Vehicle at Industrial Area, Fatuha

150.00 27-2-06 29.09.08

29.09.07 27.01.09

3 M/s Gangotri Iron & Steel Co Ltd., Exhibition Road, Patna. Fax: 0612-2685959 Phone: 2665456 E-mail: [email protected]

Proposal for capacity expansion of the Unit and TMT and M.S. Twisted Bars production

33.8 29-3-06 22.10.06

4 M/s Century Ply Wood Ltd., Kolkata. Cement Manufacturing Company Ltd., Sajjan Bhajanka, Chairman, 281 Deepali Pitampura, New Delhi-110034

Proposal for establishment of one Million Ton/Year Cement Grinding Plant at Kahalgaon

119.00 300 17-4-06 08.09.06

5 Dr. Ashok Kumar ,Medical World 4U Ltd., Sussex. U.K

Establishment of Medical College and Super Specialty Hospital at Patna.

148.87 2-5-06 08.09.06

6 Sri Vinod Kumar Chaudhry ,M/s Ambedkar Medical &Technical Educational Development Trust, Lohiya Nagar , Patna.

Establishment of Medical and Dental College at Arrah (Bhojpur)

35.076 2-5-06 31.07.06

7 Dr. Rajeshwar Thakur , Patna.

(i) Proposal for Multi Super Specialty Hospital in the Jay Prabha Hospital Complex K.Bagh, Patna. (ii) Establishment of Medical College (with training) of National repute.

500.00 300.00

2-5-06

8 M/s Raj Laxmi Udyog, C/O Jain Paper Agency , Rajan Complex, Naya Tola , Patna.

Off-Set Paper Printing and Paper Conversion (Place has been changed form Hajipur Industrial Area to Industrial Area Fatuha in SIPB meeting on 19.05.08)

1.645 70 19-6-06 19.05.08

25.07.08

9 M/s Lord Buddha Shiksha Prathisthan, Saharsa.

Medical College Hospital 100.00 24-7-06

10 M/s Bharat Sugar Mills, Singhwalia, Gopalganj.

Expansion of Sugar Mill from 2500 TCD to 5000 TCD and 15 M.W Co-generation Plant

137.00 1-8-06 15.09.06

11 M/S Ramco Industries Ltd, Chennai (Canceling the earlier approval given by SIPB in its meeting held on 16.12.08 on the proposal for establishment of Asbestos Cement Sheet Plant, Water Storage Plant and Cement Grinding Plant ; approval for establishment of

Proposal for establishment of 1,20,000 MT/Annum Capacity of Asbestos Cement Sheet Plant and 2 Lakh MT/Annum Capacity of Cement Grinding Plant at Industrial Area, Bihiya, Bhojpur.

60.20

200

23.11.09 16.12.08

Report-3

2

1,20,000 MT/Annum Capacity of Asbestos Cement Sheet Plant and 2 Lakh MT/Annum Capacity of Cement Grinding Plant at Industrial Area, Bihiya, Bhojpur has been given by SIPB in its meeting held on 23.11.09)

12 M/S Shakti Sudha Industries, Boring Road,Patna.

Establishment of Makhana Processing Unit & with Backward/ Forward linkage

70.00 14-8-06

13 M/S Balmukund Lease -Fin(P) Ltd., Exhibition Road, Patna.

5000 TCD Sugar Mill 60 KLPD Alcohol Plant & 26 M.W. Power Plant at Nariar, Baruraj, Muzaffarpur.

202.65 1500

14-8-06

10.10.06

14 M/S Riga Sugar Co. Ltd.,Netajee Subash Road, 2nd Floor, Kolkata. (Consent has been given on proposal of extension of period till 31.03.2011 for capacity expansion of existing Sugar Mill to 5000 TCD in SIPB meeting held on 25.02.11)

Expansion of Sugar Mill from 3500 TCD to 5000 TCD, 7.7 Megawatt Co-generation Plant and 50 KLPD Distillery at Sitamadhi

37.98 739 14-8-06 25.02.11

07.11.06

15 M/S Harinagar Sugar Mills Ltd. West Champaran.

Capacity expansion of Sugar Mill from 8500 TCD to 10000 TCD

39.96 2112 14-8-06 07.09.06

16

M/S New Swadeshi Sugar Mills, Narkatiaganj (Proposal for capacity expansion of Distillery Plant in two phases form 30 KLPD to 60 KLPD and 60 KLPD to 100 KLPD has been approved in SIPB Meeting on 18.05.09)

Capacity expansion of Sugar Mill from 5000 TCD to 7500 TCD, capacity expansion of Distillery Plant from 30 KLPD to 60 KLPD and 60 KLPD to 100 KLPD(in two phases) and 5 M.W. Co-generation Plant.

107.40 728

21-8-06 18.05.09

30.11.06

17 M/s Patna Notre Dame Sister's Society, Patliputra, Patna.

Establishment of Media arts and Communication.

3.32 21-8-06

18 M/S Ambuja Cements Ltd. at P.O- Ambuja Nagar, Taluka- Kodinar, Dist.- Junagadh, Gujarat-362715

Establishment of Cement Grinding Plant of 1.5 Million Ton Capacity and 15 MW Co-generation Plant at Barh

380.00 150 21-8-06 19.02.07 22.05.07

11.09.07

19 M/s Balmukund Concast Ltd., Patna.

Capacity expansion of MS Rod and Steel Production from 28350 MTA to 52350 MTA in the Bihta (Mahadeopur,Fulari)Unit.

13.96 175 06-9-06 22.10.06

20 M/s Harinagar Sugar Mills Ltd., Harinagar, W. Champaran. (Proposal has been rectified from 45 KLPD Distillery Plant to Distillery Plant for production of 45 KLPD Ethanol/50 KLPD Total Spirit)

Establishment of Distillery Plant for production of 45 KLPD Ethanol/50 KLPD Total Spirit.

45.00 89 06-9-06 29.09.08

22.10.06

21 M/s Vishnu Sugar Mills Ltd., Gopalganj.

Capacity expansion of Sugar Mill from 5000 TCD to 7500 TCD.

41.00 26-9-06 02.12.06

22 M/s Protech Feed Pvt. Ltd.)., Hajipur.

26-9-06

06.01.07

Report-3

3

(Name has been changed from M/S Protech Bio-System to M/S Protech Biosciences Pvt. Ltd.) (Company’s proposal approved by SIPB on 02.01.08 for production of LVP in the name of M/S Protech Biosciences Pvt. Ltd has been amended and consent has been given for establishment of 48,000 MT per year capacity Cattle and Poultry Feed unit at E.P.I.P, Hajipur in the name of M/S Protech Feed Pvt. Ltd.)

Establishment of 48,000 MT per year capacity Cattle and Poultry Feed unit at E.P.I.P, Hajipur

14.70

60

02.01.08 27.08.10

19.03.11

23 M/s M.P. Chini Industries Ltd. , Majahaulia, West Champaran. (Consent has been given for proposal of extension of period till 31.12.2011 for 2

nd

phase capacity expansion of Sugar Mill from 4300 TCD to 5000 TCD in SIPB meeting held on 08.03.10)

Capacity expansion of Sugar Mill from 3500TCD to 5000 TCD.

24.35 565 9.10.06 08.03.10

15.12.06

24 M/S Hasanpur Sugar Mills, Hasanpur Road, Samastipur.

Expansion of Sugar Mill First phase - 1750 TCD to 3000 TCD.(Investment-Rs99.094 Crores) Second phase- 3000 TCD to 5000 TCD.(Investment-Rs 50.956 Crores)

150.050 532 23.10.06 05.01.07

25 M/S Poorvanchal Urja Pvt. Ltd., R.Z.-1/57, Tuglakabad Extension, New Delhi-110019

Establishment of 1 MW Renewable Energy Power Plant (Biomass Based Power Plant in Buxar Industrial Area)

4.00 22 23.10.06 (Consent in principle with condition)

26 M/s Riga Sugar Co. Ltd., Kolkata. E-mail: dhanukas @cal2.vsnl.net.in

2500 TCD to 5000 TCD Expandable (within three years) Sugar Mill and 15 Megawatts Co-generation Plant at Nayagaon, Darbhanga

161.46 400 06.09.06 06.11.06

09.01.07

27 M/S Vishnu Sugar Mills Ltd., Gopalganj.

Proposal for establishment of 45 KLPD Distillery Plant and 15 MW Co-generation Plant in factory situated at Gopalganj

94.06 400 13.11.06 26.12.06

28 M/S J.H.V Distilleries & Sugar Mills Limited, Marhowrah, Saran(Chapra)

Establishment of 6000 TCD Sugar Mill , 25 MW Co-generation Plant at Marhowrah, Dist.- Saran (Chapra)

172.54 450 04.12.06 06.02.07

29 M/S P & M Infrastructure Pvt. Ltd., 47/B , Shri Krishna Puri, Patna.

Establishment of 3500 TCD Sugar Mill and 12 MW Co-generation Plant at Vill.- Sitanabad, Block- Simri Bakhtiyarpur, Dist.- Saharsa.

108.68 200 04.12.06 06.02.07

30 M/S Winsome International Ltd., Unit:-Rameshwara Jute Mills, 301,Viashno Chambers(3rd.Floor) 6,Brabourne Road, Kolkata-1

Proposal for establishment of new Jute Mill of 100 MT/day at Purnea/Kishanganj in Bihar

61.00 3121 15.01.07 (Consent in principle)

31 M/S Braj Industries Pvt. Ltd., P.O- Sadanandpur, Dist.- Begusarai-851211

Proposal for manufacturing of 190 Kilo Litter per Day Ethanol from Sugarcane Juice at Purnea

82.00 120 15.01.07

32 M/S Braj Industries Pvt. Ltd., P.O- Sadanandpur, Dist.- Begusarai-851211

Proposal for manufacturing of 190 Kilo Litter per Day Ethanol from Sugarcane Juice at Sahpur-Kamal(Dist.-Begusarai)

82.00 120 15.01.07 21.05.07

33 M/S Patwari Steels Pvt. Ltd. , Proposal for expansion of production 5.08 15.01.07

Report-3

4

6-M, Rajendra Nagar, Patna-16,

capacity of Steel Ingot, M.S. Bar and Rod and production of Cast Grinding Media Ball.

Proposal noted

34 M/S Rego Chemicals (P) Limited, 187, Rabindra Sarani, Kolkata-700007

Proposal for establishment of new Jute Mill of 30 T.P.D. with 2.5 MW Captive Power Plant at Samastipur

29.65 1250 01.02.07 (Consent in principle)

21.05.07

35 M/S Madina Educational Welfare Trust, Swarnim, East Boring Canal Road, Patna.

Establishment of Engineering College at Darbhanga(Simri, P.O.-Birdipur, Dist.-Darbhanga)

12.50 57 01.02.07 (Consent in principle)

10.05.08

36 M/s Association of Management Studies, 17, Mall Road , Meerut Cant(U.P).

Establishment of Engineering/ Management/ Medical College at Chapra and Patna.

17.50 - 01.02.07 (Consent in principle)

37 M/S Rakesh Eatables and General Products Pvt. Ltd., B-4, Industrial Area, Hajipur, Vaishali,-844101 (Canceling earlier name of the company M/S Rakesh Masala Pvt. Ltd, the new name as " M/S Rakesh Eatables and General Products Pvt. Ltd." has been approved in SIPB meeting on 14.08.08")

Setting up a Food Processing Unit at Hajipur Industrial Area/Export Zone

1.37 16 19.02.07 (Consent in principle) 14.08.08

38 M/S Siddivinayak Trust for Nature, Education and Health, 101, Shanti Kunj Apartment, T.N. Benerjee Road, Chhajjubagh, Patna-1. E-mail: lallsanjeev @yahoo.com

Setting up of Dental College and Hospital at Patna

15.10 19.02.07 (Consent in principle)

39 M/S Classicon Ventures Limited, Pro.-Sri Deepak Kumar Sinha/ Sri Rajiv Ranjan, 190/A , Boring Road, Patna, Email:-sksinha_ritco @yahoo.co.in

Establishment of 500 TCD Sugar Mill with Co-generation Power Plant at Kaabh/Ayan Khan, Dist.-Patna.

13.266 132 26.02.07 (Consent in principle)

21.05.07

40 M/S Jas Infrastructure and Power Ltd, Mahabir Tower, Main Road, Ranchi (Amending the earlier proposal approved on 11.07.08 and approval has been given on change of company’s name from M/S Jas Infrastructure Capital Pvt. Ltd. to Jas Infrastructure and Power Ltd for the same project on 26.05.11)

Establishment of 2640 MW coal based Thermal Power Plant in two phases (each phase 2x660 MW) at Banka. (Proposal for 2640 MW Thermal Power Plant in place of 1215(9x135MW) MW Thermal Power Plant)

11120.00

5000 12.03.07 (Consent in principle) 12.04.07 11.07.08 26.05.11

11.03.08

41 M/S Vikash Metal & Power Ltd., Kolkata

Establishment of 2x250 MW Power Plant at Begusarai

1350.00 1000 12.03.07 (Consent in principle)

42 M/S Nandi Soaps Private Ltd., Raxaul

Establishment of soap manufacturing plant at Raxual

6.414 142 19.03.07 21.05.07

43 M/S Saran Renewable Energy Pvt. Ltd., Chapra

Generation of 240 K.W Electricity from Biomass based Gasification System at Garkha, Saran.

1.45 14 19.03.07

Report-3

5

44 M/S Prachin Bharat Tourism, , Kalptaru Apartment, Bangalore E-mail: [email protected]

Establishment of Integrated Tourist Park at Nepura, Silao, Nalanda

5.00 100 19.03.07 (Consent in principle on concept of proposal) 08.10.07 (Consent )

14.11.07

45 M/S S.S. Infrastructure Pvt. Ltd., Darbhanga.

Establishment of Ethanol Plant from 2500 TCD Sugarcane Juice at Sukhait, Block- Jhanjharpur, Dist.- Madhubani.

95.04 120 19.03.07 21.05.07

46 M/S Braj Industries Pvt. Ltd., P.O- Sadanandpur, Dist.- Begusarai-851211

Proposal for establishment of 180 Kilo Litter Per Day Ethanol Production Plant from Sugarcane Juice at Supaul.

82.00 120 26.03.07

47 M/s Cement Manufacturing Co. Ltd., Kolkata.

Proposal for establishment of 2x250 MW Thermal Power Plant at Kahalgaon

1650.00 225 26.03.07

48 M/S Pinax Steel Industries Pvt. Ltd., VII/ 1&2 Industrial Estate, Patliputra, Patna-13

Manufacturing of M.S Ingot by setting of Induction Furnace at Devkuli , Bihta

8.67 69 07.05.07(Consent in principle)

10.05.08

49 M/S M J & Sons Distillery & Breweries Private Ltd., Jankivilla, Near Pushpanjali Plaza , Vasant Vihar Colony, Boring Rd., Patna-1

Setting up of Extra Neutral Alcohol Plant based on food grains at Amarpur, Banka.

36.70 375 07.05.07(Consent in principle)

09.10.07

50 M/S Vikramsheela Textile Park Ltd., 10 R.N. Mukherjee Road, Kolkata- 700001

Establishment of Textile Park at Bhagalpur

120.00 65 28.05.07 06.11.07

51 M/S Birla Corporation Ltd., Birla Building,9/1,RN Mukharji Road, Kolkata,-700001

Setting up of 1 Million TPA Cement grinding Unit at Barh, Patna.

155.00 350 25.06.07(Consent in principle)

17.06.08

52 M/S B. K. Group of Companies, Park Street. Kolkata.

Establishment of 1.5 Million TPA Cement manufacturing Plant near Barauni Thermal Power Station.

137.60 150 16.07.07 (Consent in principle)

53 M/S Angpradesh Handloom Park Pvt. Ltd., Bhagalpur.

Establishment of Handloom Park under Cluster Business Plan at Bhagalpur.

27.5 5000 16.07.07 (Consent in principle)

54 M/S Maurya Sugar Pvt. Ltd., 47/B Sahadeo Mahato Marg, Sri Krishna Puri, Patna- 800001

Setting up of 2500 TCD Sugar Mill & 15 MW Co-generation Power Plant at Chorma, East Champaran.

157.93 330 13.08.07

05.02.08

55 M/S Saran Renewable Energy Pvt. Ltd., Chapra

Generation of 10 MW Electricity from Biomass based Gasification System at Garkha, Saran.

50.80 20 24.09.07 (Consent in principle)

56 M/S Vaishali Kisan Uday Sugar Mills Pvt. Ltd., Patna. (Consent has been given for establishment of 1400 TCD Gur Khandsari unit at Tarwa, Majhaulia, Chochahi Chapra Panchayat, Anchal-Paru, Muzaffarpur in SIPB meeting held on 11.08.10)

Proposal for establishment of 5000 TCD Sugar Mill, 72 KLPD Ethanol Plant and 26 MW Captive Power Plant at Vill.- Chochahi-Chapra, Anchal- Paru, Muzaffarpur. (Proposal for starting of 500 TCD Mini Sugar Mill at Jita Chapra Block-Pakri Basrat has been approved with condition on 17.08.09) (Proposal for establishment of 1400 TCD Gur Khandsari unit at Tarwa,

155.18

440

24.09.07 (Consent in principle)

17.08.09

13.05.08

Report-3

6

Majhaulia, Chochahi Chapra Panchayat, Anchal-Paru, Muzaffarpur.)

22.5917

150

11.08.10

57 M/S Munger Medical College Trust, Munger

Establishment of Medical College at Munger

22.00 300 24.09.07 (Consent in principle)

58 M/S Sai Iron India Ltd., Didarganj, Patna

Establishment of second Rolling Mill in the Campus of existing Rolling Mill at Sabalpur, Didarganj, Patna.

42.39 367 24.09.07 (Consent in principle)

15.02.08

59 M/S Maurya Sugar Pvt. Ltd., 47/B Sahadeo Mahato Marg, Sri Krishna Puri, Patna- 800001

Setting up of 3500 TCD Sugar Mill, 120 KLPD Distillery Plant & 16 MW Co-generation Power Plant at Vill- Gurwalia Bishwash, Anchal- Chanpatia, Dist.- W. Champaran.

241.95 330 24.09.07 (Consent in principle)

23.09.08

60 M/S Steel Authority of India Ltd., Bokaro Steel Plant, Bokaro

Establishment of 1.55 Lakh Ton Steel Processing Unit at Kumarbagh, Bettiah.

160.63 293 24.09.07 (Consent in principle)

11.03.08

61 M/s Gangotri Iron & Steel Co Ltd., 307 Ashiana Tower, Exhibition Road, Patna. E-mail: [email protected]

Establishment of 15 MTx 2 Nos. Induction Furnace, Concast unit, Oxygen Plant , Wire Rod Plant & A Rerolling Mill of 300 TPD to manufacture Thermax TMT Bars Plant at Bihta, Patna

50.00 570 08.10.07 (Consent in principle)

31.01.08

62 M/S Steel Authority of India Ltd., Bokaro Steel Plant, Bokaro

Establishment of 1.07 Lakh TPA Steel Processing Unit at Sahdei, Vaishali

318.75 250 08.10.07 (Consent in principle)

21.02.08

63 M/S Prachin Bharat Tourism, Kalptaru Apartment, Bangalore

Establishment of Multi Media Museum at Nalanda

0.20 20 22.10.07 (Consent in

principle)

64

M/S Globe Sugar Refinery Ltd, Berger House, 5th Floor, 129, Park Street, Kolkata (Change of name of the company from M/S Kamlapur Sugar Refinery Limited to M/S Globe Sugar Refinery Ltd has been approved in SIPB meeting on 18.05.09)

Establishment of 8000 TCD Sugar Mill, 120 KLPD Ethanol Plant and 26 MW Co-generation Plant at Sariatpur-Chakia, East Champaran

248.80 106.10 132.90

450 60 30

29.10.07 (Consent in principle) 18.05.09

04.03.08

65 M/S Jagdamba Ispat (P) Ltd., Nasriganj, Danapur, Patna.

Capacity expansion of 5400 MT/Year MS Ingot at present established unit at Danapur

1.675 15 29.10.07 (Consent in principle)

66 M/S Babu Cold Storage, Pilkhan Road, Chura Patti, Kishanganj

Establishment of 5200 MT/Year capacity Cold Storage for Vegetable and Food Preservation at Chura Patti, Kishanganj

1.81 07 29.10.07 (Consent in principle)

67 M/S Laxmivinayak Ventures Pvt. Ltd., Malsalami, Patna City

Establishment of one Lakh Ton /Year Detergent Powder production Plant at Hajipur. (Place has been changed from Bihta to Hajipur)

20.00 20 29.10.07 (Consent in principle) 21.4.08

14.06.08

68 M/S P. M. R. Educational Trust, 2036, 15 th Main Road, Anna Nagar, West Chennai-600040

Setting up of Engineering College in Bihar

35.00 02.01.08

30.03.08

69 M/S Ganga Power & Natural Resources Ltd., 14 th Netaji Subhas Road, 2nd Floor, Kolkata-700001 (Name has been changed form M/S Neepaz Thermal Energy Ltd to Adhunik Power

Proposal for establishment of 2640 MW Coal based Thermal Power Plant in two phases at Pirpainti, Bhagalpur (Approval has been given for establishment of 1320 MW in place of 1000 MW in SIPB meeting held on

15079 1450 02.01.08 09.06.08

23.09.08

Report-3

7

& Natural Resources Ltd.) (Company’s proposal approved by SIPB on 01.02.10 for establishment of 1320 MW Thermal Power Plant at Kahalgaon, Bhagalpur in the name of M/S Adhunik Power & Natural Resources Ltd has been amended and consent has been given to establish that project at Pirpainti Block, Bhagalpur in the new name as M/S Ganga Power & Natural Resources Ltd in SIPB Meeting held on 29.06.10)

1.2.10) (Company’s proposal approved on 29.06.10 for establishment of 1320 MW Thermal Power Plant at Pirpainti Block, Bhagalpur has been amended and approval has been given for establishment of 2640 MW Coal based Thermal Power Plant in two phases at Pirpainti, Bhagalpur in SIPB meeting held on 12.01.11)

01.02.10 29.06.10 12.01.11

70 M/S Subhas Projects and Marketing Ltd., 22 Camac Street, Block-A, 3rd Floor, Kolkata-700016

Setting up of 1200 MW Thermal Power Plant at Rampur, Dist.- Lakhisarai, Bihar

5000.00 400 02.01.08

71 M/S India Power Corporation Ltd., Vishwakarma, 86 C, Topsia Road(South), Kolkata-700046 (Company's proposal approved by SIPB on 02.01.08 for establishment of 1650 MW Coal Based Thermal Power Plant in Bihar has been amended and consent has been given for establishment of 1320 (2x660) MW Coal Based Thermal Power Plant at Indragachi, Sangrampur(Areraj), East Champaran in SIPB meeting held on 21.07.10)

Establishment of 1320 (2x660) MW Coal Based Thermal Power Plant at Indragachi, Sangrampur (Areraj), East Champaran

7280.00 650 02.01.08 21.07.10

05.04.11

72 M/S P & M Infrastructure Pvt. Ltd., 47/B, Sahdeo Mahto Marg, Sri Krishna Puri, Patna-1

Setting up of Bodh Gaya Resort at Bodh Gaya

18.41 250 02.01.08 (Consent in principle)

73 M/S Maurya Sugar Pvt. Ltd., Sri Krishna Puri, Patna-1

Setting up of 3500 TCD expendable up to 6000 TCD Sugar Complex at Kharkatwa, Dhonar Devli, Ramgarhwa,EastChamparan

171.96 330 02.01.08

11.03.08

74 M/S Nalanda Power Company Limited, R.P.G. Group, C.E.S.C House, Chaurangi Square, Kolkata- 700001 (Name has been changed form M/S C.E.S.C. Limited to M/S Nalanda Power Company Limited)

Setting up of 1800 MW Coal based Thermal Power Plant at Pirpainti or other suitable place.

7290.00 02.01.08 09.06.08

26.03.08 12.08.08

75 M/S Neutral Publishing House Ltd.(Prabhat Khabar), Old By Pass Road, Kankarbagh, Patna- 20

Proposal for establishment of Printing, Publishing of News Papers and Publishing of Periodical at Patna, Bhagalpur and Muzaffarpur

38.62 502 25.02.08 25.07.08

76 M/S Amrapali Foods Ltd., Ujjawal, 2nd Floor, Opposite Planetarium, Bailey Road, Patna

Proposal for establishment of Food Park at Muzaffarpur, Vaishali (Hajipur).

125.00 25.02.08

77 M/S Bihar Agro Projects Ltd, Proposal for establishment of Food 75.00 25.02.08

Report-3

8

19, R.N. Mukherjee Road, Kolkata-1

Park at Bhagalpur

78 M/S Amit Oil Ltd., Allahabad Proposal for establishment of Solvent Extraction Plant at Kaimur

7.50 57 25.02.08 25.07.08

79 M/S I.L. & F.S, 4 B, 1st Floor, S.K. Puri, Patna

Proposal for establishment of 500 MW Power Plant in Muzaffarpur District

2223.40 500 25.02.08 (with condition)

80 M/S Amrapali Agro Foods Pvt. Ltd., Ujjawal, 2nd Floor, Bailey Road, Patna

Proposal for establishment of Fresh Fruits and Vegetable Unit at Muzaffarpur

2.253 228 25.02.08 (Consent in principle)

04.06.09

81 M/S Reliance Industries Ltd. Establishment of 5 MW Solar Power Plant at Patna

25.02.08 (Consent inprinciple)

82 M/S Medical World 4U Ltd., M.D- Dr. Ashok Kumar, 49 Truman Drive, High Beech, Saint Leonards-on-Sea, East Sussex, TN- 377 TH , U.K.

Company's proposal for establishment of Dental College and Para Medical College in the name of Lord Buddha International Institute of Medical Science

148.87 25.02.08

83 M/S Titagarh Biotech Pvt. Ltd., Kolkata

Establishment of Jatropha based Bio-diesel Plant at Banka

51.00 40 25.02.08

84 M/S Punrasar Jute Park Limited, 404, Vaishno Chamber, 6, Brabourne Road, Kolkta.

Establishment of Jute Hessian Cloth/Sacking Bags, Jute Yarn and Jute Twine industry at Moranga Industrial Area, Purnea (Canceling the above proposal, consent has been given for Jute Park at Moranga Industrial Estate in SIPB meeting on 19.05.08)

40.00 10000 17.03.08 (Consent in principle) 19.05.08

03.08.08

85 M/S M. D International , NS-9 Industrial Area, Fatuha

Establishment of Mineral Powder Production Plant at Industrial Area, Fatuha

1.8666 22 17.03.08 (Consent in principle)

86 M/S Tiger Warehousing Cold Chain Pvt. Ltd., 508, Dalamal House, Nariman Point, J.B. Road, Mumbai, Maharastra (Company's name has been changed form M/S Central Warehousing Cold Chain Pvt. Ltd to M/S Tiger Warehousing Cold Chain Pvt. Ltd on 09.02.09,)

Establishment of Warehousing, Container Freight and Cold Storage at Hajipur

49.75 105 09.02.09 17.03.08 (Consent in principle)

04.06.09

87 M/S Era Agritech(I) Pvt. Ltd., 153 Okhla Industrial Area, Phase-III, New Delhi.

Establishment of Agro Business Centre and Primary Processing Centre in Bihar

84.70 300 17.03.08 (Consent in principle)

88 M/S PTC Bermaco Green Energy Systems Ltd., D 73/1 TTC, Industrial Area , Navi Mumbai (Company’s name has been changed from M/S Bermaco Energy Systems Ltd to M/S PTC Bermaco Green Energy Systems Ltd on 29.06.09)

Establishment of 12 MW Biomass Power Plant at Sasaram- Rohtas.

56.7988 92 17.03.08 29.06.09 28.09.11

89 M/S Navran Advanced Nano Products Development International Pvt. Ltd., 109, M.I.G, Kankarbagh Colony, Patna.

Proposal for Production Polymerised Toner for Business Network Laser Printer

32.00 17.03.08

90 M/S Amrapali Foods Limited, Ujjwal, II Floor, Opposite Planetarium, Bailey Road,

Proposal for expansion and Modernisation of Fruits and Vegetable Processing Unit at Hajipur

2.28 15 17.03.08 31.05.08

Report-3

9

Patna Industrial Area.

91 M/S Maurya-Patna, Bihar Hotels Ltd, South Gandhi Maidan, Patna

Proposal for establishment of New Maurya Hotel Tower and expansion of existing Hotel

35.74 180 17.03.08 (Consent with condition)

92 M/S Krishak Bharti Cooperative Ltd., A-10, Sector-1, Noida-201301, Dist. Gautambudh Nagar(U.P.)

Proposal for establishment of 1320 MW coal based Power Project at Bihta/ Lakhisarai/Banka/Dehri

6200.00 800 17.03.08 (Consent in principle)

93 M/S Apollo Hospitals Enterprise Limited, Ali Tower, 55, Greams Road, Chennai

Establishment of state-of- art hospital, accommodation, educational and training infrastructure under Health Care Infrastructure.

40.00 376 21.04.08 (Consent in principle)

25.07.08

94 M/S Maharshi DAV Educational Trust, Haryana

Establishment of College for Engineering & Diploma Course at Muzaffarpur

4.06 30 19.05.08 ) (with condition)

25.07.08

95 M/S R.N.Dwivedi Foundation, Patna

Establishment of Composite Educational Complex at Patliputra Industrial Estate

10.08 227 19.05.08 (Consent in principle with condition)

96 M/S Triton Energy Limited, "Indiabulls House" 448-451, Udyog Vihar, Phase-V, Gurgaon-122001

Establishment of 1320 MW coal based mega thermal power plant at vill Kochar, Tehsil-Barun, Dist.-Aurangabad. (Change of place from Navinagar, Aurangabad to vill- Kochar, Tehsil-Barun, Dist.-Aurangabad has been approved in SIPB meeting on 19.10.09)

6573.50 400 09.06.08 (Consent in principle) 19.10.09

29.12.09

97 M/S Essar Steel Limited, 11 K K Road, Mahalaxmi, Mumbai-400034

Proposal for establishment of call center at Bhagalpur and Patna

250.00 2000 09.06.08

98 M/S Jhunjhunwala Vanspati Ltd., Jhunjhunwala Bhawan, Nati Imli, Varanasi(U.P)

Establishment of 225000 MT/A Refined Edible Oil Plant at Dehri (Rohtas)

95.00 171 11.07.08 14.08.08

99 M/S Jay Shri Ram Annapurna Rice Mill Pvt. Ltd, Rohtas

Establishment of Rice Mill at Kailani, Rohtas

1.7325 10 11.07.08 14.08.08

100 M/S India Greenfuel Pvt. Ltd., 241, Okhla Industrial Estate, Phase- III, New Delhi- 110020

Establishment of 5000 TCD Sugar Mill, 175 KLPD Distillery Plant and 25 MW Bagasse based Co-generation Plant at Khajooriya, Areraj, East Champaran

240.00 325 11.07.08 (Consent in principle)

101 M/S Licchavi Foundation, Hajipur( Vaishali)

Establishment of B.Ed. Teacher's Training Institute at Hajipur, Vaishali.

1.61 19 11.07.08 (Consent with condition)

08.09.08

102 M/S ITC Limited, Indian Tobacco Division, P.O- Basdeopur Munger(Bihar)-811202

Establishment of Milk Processing Plant at Sitakund, Munger

100.90 140 14.08.08

103 M/S Ramadhar Singh Cold Storage Pvt. Ltd., Bharhopur, Ganjpar, Ekma, Saran-841208

Establishment of Multi Purpose and Multi Chambered Cold Storage at Ganjpar, Ekma, Saran.

3.58 26 14.08.08 15.11.08

104 M/S Essar Power (Jharkhand) Limited, Next to Tirath Mansion, Near

Establishment of Thermal Power Plant of 3x600 MW capacity at Pirpainti, Bhagalpur.

8130.00 2200 29.09.08 (Consent with

Report-3

10

Over Bridge, Main Road, Ranchi

condition)

105 M/S Jain Agro Distilleries Pvt Ltd., 306, Akash Deep Building, 26-A, Barakhamba Road, New Delhi-110001

Establishment of 45 KLPD Distillery Plant at Bighaijaghish, Tehsil-Hathua(Mirganj, Gopalganj (Cancelling earlier approved place which was at Chitauli, Siwan and new place as Bighaijaghish, Tehsil-Hathua(Mirganj), Gopalganj has been approved on 09.2.09)

29.69 100 09.02.09 29.09.08

11.02.10

106 M/S Astonfield Renewable Resources Pvt. Ltd., 28, Naresh Mitra Sarani, Kolkata.

Establishment of 100 MW (10x10 MW) Biomass based Power Plant in 10 district clusters in Bihar

598.00 45 29.09.08

107 M/S All India Asian Educational Foundation, 3&4, Industrial Area, Jasola (Sarita Vihar), New Delhi-110025

Proposal for opening of Technical Institute at Patna.

51.00 19 29.09.08

108 M/S Birsa Institute of Technology, Ratu Road, Ranchi

Establishment of Engineering College in Bihar.

29.09.08

109 M/S Narayan Chikitsalay, Rohtas

Establishment of Medical College at Sasaram Road, Jamuar, Rohtas.

29.09.08 (Consent with condition)

110 M/S Malti Holy health & Welfare Society, Arrah, Pakri, Bhojpur.

Establishment of Medical College and Hospital at Arrah, Bhojpur.

29.09.08 (Consent with condition)

111 M/S Sona Auto Agriculture Pvt. Ltd., Abhishek Plaza, 2nd Floor, Exhibition Rd. Patna.

Proposal for manufacturing of Agriculture Implements unit at Fatuha Industrial Area.

12.70 59 29.09.08

112 M/S East West Power Generation Company Ltd., Maharastra

Proposal for establishment of 1000 MW coal based Thermal Power Plant at Kahalgaon/Aurangabad

5000.00 700 18.11.08 (Consent in-principle with condition)

113 M/S Sri Durga Agro Energy Ltd, Station Road, Buxar.

Proposal for establishment of Rice Mill, Solvent Extraction Plant and 15 MW Co-generation Plant at Bhagra Kudra, Kaimur.

141.00 265 18.11.08 (Consent in-principle with condition)

114 M/S Emergent Ventures India Pvt. Ltd, Gurgaon, Haryana (On request of M/S Emergent Ventures India Pvt. Ltd for its Gaya project, approval has been given to its new subsidiary company namely M/S Tathagata Bio Energy Pvt. Ltd for establishment of 12 MW Biomass based Power Plant at vill- Churi, Dist.-Gaya and for its Kaimur project also approval has been given to new SPV company namely M/S Mundeshwari Bio Energy Pvt. Ltd for establishment of 12 MW Biomass based Power Plant at Kaimur, Bhabhua in SIPB meeting held on 12.01.11) (On request of M/S Emergent

Proposal for establishment of 12 MW biomass based Power Plant in each district namely Nalanda, Nawada, Jehanabad, Arwal, Bhojpur, Patna and Banka.

358.00 90 18.11.08 (Consent in-principle with condition) 12.01.11 26.05.11

Report-3

11

Ventures India Pvt. Ltd for its Rohtas project newly formed subsidiary company M/S Sanmati Bio Energy Pvt. Ltd for 12 MW Biomass based Power Plant at Songwa, Rohtas and for its Aurangabad project newly formed subsidiary company M/S Harit Bio Energy Pvt. Ltd for 12 MW Biomass based Power Plant at Barwa, Aurangabad have been approve on 26.05.11.)

115 M/S Shahi Foundation, Gannipur, Muzaffarpur

Proposal for establishment of Engineering College at Dighra, Mushari, Muzaffarpur.

6.99 38 18.11.08 (Consent with condition)

116 M/S ESVEEGEE STARCH AND CHEMICALS PVT. LTD., Ahmedabad.

Proposal for establishment of Maize Processing Unit at Imadpur Raghunathpur, Block- Bhagwanpur, Dist.- Vaishali

90.00 250 18.11.08 22.12.08

117 M/S Siddhashram Rice Mills Cluster Pvt. Ltd., Rambag, Buxar.

Proposal for establishment of Rice Mill and 2 MW Rice Husk based Power Plant at Chausa, Buxar

14.30 250 18.11.08 (Consent with condition)

04.06.09

118 M/S Manju Makhana Enterprises Pvt. Ltd, Madhubani. (Unit's proposal approved by SIPB on 18.11.08 for establishment of Makhana Storage Godown and Mechanised Packaging Facilities in the name of M/S Manju Udyog, has been amended and consent has been given for establishment of Makhana Processing and 200 MT Warehouse at Sapta, Rahika, Madhubani in the name of M/S Manju Makhana Enterprises Pvt. Ltd. in SIPB meeting held on 11.08.10)

Proposal for establishment of Makhana Processing and 200 MT Warehouse at Sapta, Rahika, Madhubani.

0.80 15 18.11.08 11.08.10

04.06.09

119 M/S Institute of Chartered Accountant of India, Frazer Road, Patna.

Proposal for establishment of a Branch of Chartered Accountant of India at Patna

18.11.08 (Consent with condition)

120 M/S Prachin Bharat Tourism, Bangalore.

Establishment of following proposals based on outsourcing:- (a) Management of Tourist

Information Centre using new technology.

(b) Development and management of Website of Bihar State Tourism Development Corporation(BSTDC) using 2.0 Technology.

18.11.08 (Consent with condition)

121 M/S Bihar Starch Ltd, Khagaria.

Proposal for establishment of Maize Processing Unit at Kothia, Kashimpur, Khagaria.

17.11 91 18.11.08 (Consent in-principle)

28.12.08

122 M/S Jaiprakash Associates Ltd., New Delhi.

Proposal for establishment of capacity of 1 Million Ton Flyash

18.11.08 (Consent in-

Report-3

12

based Cement Grinding Plant at Motipur, Muzaffarpur

principle with condition)

123 M/S Archi Breweries Pvt Ltd, Birchand Patel Marg, R Block, Patna

Proposal for establishment of Beer Plant with capacity of 1 lakh HLPA at Parew, Bihta, Patna.

9.63 45 16.12.08

124 M/S PTC Bermaco Green Energy Systems Ltd, Navi Mumbai, Maharastra (Earlier, in the SIPB's 63

rd

meeting held on 16.12.08 consent was given for establishment of Biomass based Power Plant for 300 MW(12x25 number) at 25 different places and in the SIPB's 66

th meeting on

29.06.09 consent was given for 12 MW Biomass based Power Plant at Rohtas. Again on company's request, consent has been given on 28.09.11 for establishment of 312 MW(26x12) Biomass based Power Plant at 26 different places, Bikramganj-Rohtas, Dinara-Rohtas, Durgawati-Kaimur, Kudra-Kaimur, Dumraon-Buxar, Jagdishpur-Bhojpur, Gaunaha-West Champaran, Bettiah-West Champaran, Motihari-East Champaran and Sasaram-Rohtas, Purnea, Samastipur, Bihta-Patna, Belaganj-Gaya, Aurangabad, Marhaura-Saran, Siwan, Katihar, Saharsa, Banka, Udakishanganj-Madhepura, Rafiganj-Aurangabad, Rahika-Madhubani, Forbesganj-Araria, Gopalganj and Supaul.)

Proposal for establishment of 300 MW Biomass Power Plant in 25 different places ( 12 MW in each place) - Bikramganj-Rohtas, Dinara-Rohtas, Durgawati-Kaimur, Kudra-Kaimur, Dumraon-Buxar, Jagdishpur-Bhojpur, Gaunaha-West Champaran, Bettiah-West Champaran, Motihari-East Champaran, Purnea, Samastipur, Bihta-Patna, Belaganj-Gaya, Aurangabad, Marhaura-Saran, Siwan, Katihar, Saharsa, Banka, Udakishanganj-Madhepura, Rafiganj-Aurangabad, Rahika-Madhubani, Forbesganj-Araria, Gopalganj and Supaul.)

1254.25 2300 16.12.08 (Consent with condition) 28.09.11

125 M/S Geneva Software Technologies Ltd, Bangalore

Proposal for working in the field of Disaster Information Management and Enterprise Solution at Patna.

16.12.08

126 M/S Meera Comtrade Pvt Ltd, Exhibition Road, Patna (Change of name of the company from M/S Meera Enterprises to M/S Meera Comtrade Pvt Ltd has been approved in SIPB meeting on 18.05.09)

Proposal for establishment of Cold Storage with proposed capacity of 40 MT, Agri Marketing Yard and Dry Warehouse with proposed capacity of 400 MT under Rural Agri Business Centre at Narkatiabazar, East Champaran.

3.861 100 16.12.08 18.05.09

11.07.09

127 M/S Bhartiya Agro Products Pvt Ltd, Bettiah

Proposal for establishment of Cold Storage with proposed capacity of 6150 MT, Dry Warehouse with proposed capacity of 5000 MT, Agri Input Marketing and Agri Output Marketing Project at Bettiah

9.319 280 16.12.08

128 M/S Jai Kisan Food Products Pvt Ltd, Sasaram

Proposal for establishment of Modern Rice Mill with proposed capacity of 4 MT per hour, Warehousing with proposed capacity of 5000 MT and Packaging

5.3851 150 16.12.08 04.06.09

Report-3

13

project with proposed capacity of 4 MT per hour at Chandwa, Rohtas.

129 M/S Vindhyabasini Rice Mills Cluster Pvt Ltd, Nokha, Rohtas (Change of name of the company from M/S Sunil Kumar Singh to M/S Vindhyabasini Rice Mills Cluster Pvt Ltd has been approved in SIPB meeting on 18.05.09)

Proposal for establishment of Modern Rice Mill with proposed capacity of 7 MT per hour, Warehouse with proposed capacity of 10,000 MT and Packaging Project with proposed capacity of 4 MT per hour at Nokha, Rohtas.

10.38 200 16.12.08 18.05.09

11.07.09

130 M/S Shivjee Modern Rice Mill Pvt Ltd, Konar, Sasaram

Proposal for establishment of Modern Rice Mill with proposed capacity of 4 MT per hour, Warehouse with proposed capacity of 5000 MT and Packaging Project with proposed capacity of 4 MT per hour at Konar, Shiv Sagar, Rohtas.

4.715 150 16.12.08 04.06.09

131 M/S Indsolar Renewables Pvt. Ltd., Harihar Singh Road, Morabadi, Ranchi. (Canceling the company's earlier approved proposal to set up 5 MW Solar Thermal Power Project with earlier name(Indsolar India) and approval has been given for establishment of 2 MW Power Plant based on Solar Photo Voltaic Technology and 3 MW Solar Thermal Power Generation Plant with it's new name as Indsolar Renewables Pvt. Ltd. in SIPB meeting on 19.10.09)

Establishment of 2 MW Power Plant based on Solar Photo Voltaic Technology and 3 MW Solar Thermal Power Generation Plant at Aurangabad

26.74 20 09.02.09 (Consent in-principle) 19.10.09

132 M/S Nalanda Biscuit Company Ltd, Khagaul Road, Nayatola, Phulwarisharif, Patna

Proposal for capacity expansion of existing Biscuit manufacturing unit at Phulwarisharif from 10,750 MT per year to 16,750 MT per year.

3.38 269 09.02.09

133 Prachin Bharat Tourism, Bangalore

Establishment of Multimedia Museum at Bodh Gaya

0.2471 09.02.09

134 M/S All India Asian Educational Foundation, 3&4, Industrial Area, Jasola (Sarita Vihar), New Delhi-110025

Establishment of Institute of Medical Sciences, Dental Sciences and Nursing Sciences at Patna

150.00 09.02.09 (Consent with condition)

135 M/S SREI Infrastructure Finance Limited, 'Vishwakarma' 86 C, Topsia Road(South), Kolkata.

Establishment of 5 MW Grid Interactive Solar Power Plant at Jamalpur

116.00 30 09.02.09 (Consent with condition)

136 M/S Taj Trading Company, Chhatia, Bhatgama, Purnea East, Purnea

Establishment of Warehousing and Packaging Facility for Makhana at Purnea.

0.936 55 09.02.09

137 M/S Employees' State Insurance Corporation, Patna

Establishment of Medical College and Hospital at Patna

201.00 500 09.02.09

138 M/S Lakhisarai Bijlee Company Pvt. Ltd., New Delhi

Establishment of 1320(660x2) MW Coal based Thermal Power Project at Kajra, Lakhisarai

6810.00 600 09.02.09 10.05.11

139 M/S Buxar Bijlee Company Pvt. Ltd., New Delhi

Establishment of 1320 MW Coal based Thermal Power Project at Chausa, Buxar

6795.00 600 09.02.09 10.05.11

Report-3

14

140 M/S Shristi Infrastructure Development Corporation Ltd. Kolkata

Establishment of Five Star Hotel in Patna and International Tourist Resort at Bodh Gaya in PPP mode and Golf Course

18.05.09 (Consent with condition)

141 M/S Steel Authority of India Ltd., Bokaro Steel Plant, Bokaro

Establishment of Steel Processing Unit of TMT Bar with the capacity of one lakh Ton per year at Gaya

88.76 179 18.05.09 07.08.09

142 M/S Chaitanya Gurukul Trust, Gopalganj.

Establishment of Educational Institution as- Model School from class 1 to 12, Degree Engineering College and Research and Development at Chamanpura, Gopalganj

30.00 200 18.05.09 (Consent in-principle)

143 M/S Tirupati Balajee Nutrition Pvt. Ltd., Patna

Establishment of Flour Mill with the capacity of 45,000 MT per year at Khedalpura, Bihta, Patna.

5.56 103 18.05.09 07.08.09

144 M/S Royal Engineering and Cold Storage Pvt. Ltd., Siwan.

Establishment of Cold Storage with the Capacity of 5000 MT at Pakwaliya, Dhrundha, Siwan.

1.5 15 18.05.09 16.09.09

145 M/S Hindustan Petroleum Corporation Ltd, Mumbai.

Establishment of 3500 TCD Capacity of Sugar Mill, 60 KLPD Capacity of Ethanol Plant and 20 MW Co-generation Plant at Lauriya, West Champaran.

304.39 375 29.06.09 (Consent with condition)

146 M/S Hindustan Petroleum Corporation Ltd, Mumbai.

Establishment of 3500 TCD Capacity of Integrated Sugar Mill, 60 KLPD Capacity of Ethanol Plant and 20 MW Co-generation Plant at Sugauli, East Champaran.

309.15 375 29.06.09 (Consent with condition)

147 M/S Nibhi Industries Pvt. Ltd, Mylapore, Chennai

Establishment of 1,00,000 (One Lakh) MT Capacity Asbestos Fiber Cement Corrugated Sheet, Flat Sheet and Accessories and Light Weight Fly Ash Block Plant at Industrial Growth Centre, Giddha, Ara (Change of place from Dariapur, Chapra to Industrial Growth Centre, Giddha, Ara has been approved in SIPB meeting on 19.10.09)

31.00 125 29.06.09 (Consent with condition) 19.10.09

148 M/S Parijat Next Gen Energy Pvt. Ltd, Bangalore.

Establishment of 15 MW (2x7.5 MW) Biomass based Power Plant at Bihiya, Bhojpur.

73.00 30 29.06.09 (Consent with condition)

149 M/S Bajaj Buildcon Pvt. Ltd, Patna.

Establishment of Resort, Water Park and Educational Development at Patna.

285.00 29.06.09 (Consent with condition)

150 M/S Kanika Buildcon Pvt. Ltd, Patna

Establishment of Mall-cum- Multiplex, Health and Medical, Educational Development and Residential Complex at Patna.

365.00 29.06.09 (Consent with condition)

151 M/S Sukhjit Starch & Chemicals Limited, Phagwara, Punjab.

Establishment of two Warehouse with the capacity of 5000-5000 MT at Naugachia(Bhagalpur) and Gulzarbagh (Purnea).

12.62 50 29.06.09 (Consent with condition)

13.12.09

152 M/S Sahu Agro Business Pvt. Ltd, Bhagalpur.

Establishment of Cold Storage with capacity of 3000 MT, Warehouse with capacity of 1100 MT and Pack House with the capacity of 200 MT under R.A.B.C at Naugachia, Bhagalpur.

4.21 64 29.06.09

13.12.09

Report-3

15

153 M/S Radhe Shyam Cold Storage & Foods Pvt. Ltd, Gajipur, Uttar Pradesh.

Establishment of Fruit Pulp and Juice Plant with annual capacity of 17,500 MT at Industrial Area, Pandaul, Madhubani.

9.61 148 29.06.09

13.12.09

154 M/S Usha Martin Ltd, New Delhi.

Establishment of 1200-1320 MW Coal based Thermal Power Plant at Kahalgaon/ Pirpainti, Bhagalpur.

6000.00 500 29.06.09

155 M/S Amrapali Foundation, New Delhi. (Approval has been given for change of place from Motihari to Kumarbagh(Bettiah) in SIPB meeting held on 20.07.09)

Establishment of Engineering College at Foundation’s Campus- Begusarai, Jamalpur and Kumarbagh(Bettiah)and Management Institute at Motipur.

18.952 247 29.06.09 (Consent with condition)

156 M/S Advantage Educational Society, New Delhi.

Establishment of Advantage Media Academy at off Bailey Road, Patna.

7.00 30 29.06.09 (Consent with condition)

157 M/S Suman Agritech Pvt. Ltd, Indore

Establishment of Vegetable Refined Oil and Inter-esterification unit and Bakery fat at Kulaharia, Ara

120.00 250 20.07.09 29.12.09

158 M/S Amit metaliks Ltd, Durgapur, West Bengal.

Establishment of Five Star Hotel at Patna Town

168.18 309 20.07.09 (Consent with condition)

159 M/S Uttam Cycle Pvt. Ltd, Patna

Establishment of Cycle Manufacturing Industry at Gaya-Patna Road

50.00 75 20.07.09

160 M/S Ganapati Biscuits Pvt. Ltd, Patna City

Establishment of Biscuit Manufacturing Unit at Bankaghat, Patna City

14.85 300 20.07.09 13.12.09

161 M/S Sarvottam Infrastructure Pvt. Ltd, Kolkata.

Establishment of 540 MW coal based Thermal Power Plant at Kahalgaon

2250.00 610 17.08.09

162 M/S I L & FS Renewable Energy Ltd, Mumbai

Establishment of 12 MW biomass based Power Project at Banka.

50.17 92 17.08.09

163 M/S Tarouna Cold Storage Pvt Ltd, Purnea

Establishment of Cold Storage with the capacity of 11,400 MT under R.A.B.C. at Jalalgarh, Purnea.

7.29 60 17.08.09 13.12.09

164 M/S Ambo Agro Products Ltd, Kolkata

Establishment of 200 TPD Refined Edible Oil, 2.5 MW Captive Power Plant, 200 TPD Rice Mill and 150 TPD Flour Mill at Bhagalpur / Patna/ Begusarai

84.00 200 17.08.09

165 M/S Ashwini Jhunjhunwala, Tilkamanjhi, Bhagalpur.

Establishment of 100 MT Cold Room, 500 MT Pack House, Processing Hall, 1000 MT Agri Input Warehouse and 5600 MT Grain Storage Warehouse under R.A.B.C at Tilkamanjhi, Bhagalpur.

5.9091 31 17.08.09

166 M/S Hira Bharti Agro Pvt. Ltd, Bhagalpur. (Unit's proposal approved by SIPB on 17.08.09 for establishment of 3000 MT Cold Storage, 2800 MT Warehouse for grains and 600 MT Pack House and Cold Room under R.A.B.C. at Shivnarayanpur, Kahalgaon, Bhaglapur in the name of M/S Amit Sinha, has been amended and consent has

Establishment of 3000 MT Cold Storage, 2800 MT Warehouse for grains and 600 MT Pack House and Cold Room under R.A.B.C. at Shivnarayanpur, Kahalgaon Bhagalpur.

4.77 38 17.08.09 08.06.10

Report-3

16

been given for establishment of that project in the name of M/S Hira Bharti Agro Pvt. Ltd in SIPB meeting held on 08.06.10.)

167 M/S Unique Foods, Muzaffarpur

Establishment of I. Q. F. Plant-2 MT per hour Frozen / Aseptic line 10 MT per hour, Canning Line 15 MT per day, Cold Room 500 MT and Modern Cold Chain at Muzaffarpur.

16.64 35 17.08.09 13.12.09

168 M/S Ruchi Soya Industries Ltd, Mumbai (Company’s revised proposal for establishment of Bran/ Seed De-oiled Cake -1,20,000 MTA, Vanaspati / Bakery Fats/ Interestified -90,000 MTA, Packaged Blended / Refined Oils-1,26,000 MTA , Expeller Oil- 18000 MTA, Textured Soya Protein- 15,000 MTA , Packaged Grains- 22,500 MTA, Co-generation Power – 4.5 MW has been approved in SIPB meeting on 15.02.10.) (Again on company’s request consent has been given for 4.5 MW Biomass based Captive generation Plant and 1.5 MW Solar PV Power Plant in place of 4.5 MW co-generation Plant in the SIPB meeting held on 28.09.11.)

Establishment of Bran/ Seed De-oiled Cake -1,20,000 MTA, Vanaspati / Bakery Fats/ Interestified -90,000 MTA, Packaged Blended / Refined Oils-1,26,000 MTA , Expeller Oil- 18000 MTA, Textured Soya Protein- 15,000 MTA , Packaged Grains- 22,500 MTA, 4.5 MW Biomass based Captive generation Plant and 1.5 MW Solar PV Power Plant at Durgawati, Kaimur, Dist.- Bhabhua.

215.00 530 17.08.09 15.02.10 28.09.11

19.04.11

169 M/S Bhagwan Agro Pvt Ltd, Rohtas

Establishment of 4 MT per hour Modern Rice Mill and 2000 MT Capacity Warehouse at Nokha,Rohtas.

3.46 90 17.08.09 13.12.09

170 M/S Shanti Modern Rice Mill, Sasaram

Establishment of 4 MT per hour Modern Rice Mill and 1000 MT capacity Warehouse at Kaua Dehri, Block-Shivsagar, Rohtas.

1.45 40 17.08.09 13.12.09

171 M/S Shree Hanumanjee Modern Rice Mill Pvt Ltd, Sasaram. (Company's proposal approved by SIPB on 17.08.09 for establishment of 4 MT per hour Modern Rice Mill and 4000 MT Capacity Warehouse at Vaijala, Sasaram in the name of M/S Hanumanjee Modern Rice Mill Pvt Ltd and 5 MT per hour capacity Rice Mill and 3000 MT capacity Warehouse at Baijala, Sasaram in the name of M/S Hanuman Food Products. As per company's request, amending the approvals given on both proposals, consent has been given for one company as M/S Shree Hanumanjee Modern Rice Mill Pvt. Ltd, Rohtas for establishment of 12 MT per hour Modern Rice Mill and 3000 MT Warehouse at Baijala, Mokar, Rohtas in SIPB meeting held on 21.07.10.)

Establishment of 12 MT per hour Modern Rice Mill and 3000 MT Warehouse at Baijala, Mokar, Rohtas

9.75 50 17.08.09 21.07.10

13.12.09 21.12.10

172 M/S Dumraon Textiles Ltd, Dumraon

Establishment of 10 MT per hour capacity Modern Rice Mill and 2 MW Captive Power Plant at Dumraon, Buxar.

19.68 175 17.08.09

Report-3

17

173 M/S Sushila Cold Storage Pvt Ltd, Ara (Cancelling the earlier proposal approved on 17.8.09, present proposal as establishment of 7000 MT capacity Cold Storage (5000 MT capacity of Potato storage and 2000 MT capacity of Fruit and Vegetable storage), 2000 MT capacity Onion storage and Primary Processing and Packaging unit of Fruits and Vegetable under RABC at Giddha Industrial Area has been approved on 21.12.09)

Establishment of 7000 MT capacity Cold Storage (5000 MT capacity of Potato storage and 2000 MT capacity of Fruit and Vegetable storage), 2000 MT capacity Onion storage and Primary Processing and Packaging unit of Fruits and Vegetable under RABC at Giddha Industrial Area

7.05 85 17.08.09 21.12.09

11.03.10

174 M/S Om Shivam Modern Rice Mill Pvt Ltd, Sasaram.

Establishment of 11 MT per hour capacity Modern Rice Mill and 5000 MT capacity Warehouse at Konar, Shivsagar, Rohtas

5.79 55 17.08.09 13.12.09

175 M/S Fox Petroleum Ltd, New Delhi

Establishment of 30 MW Power Generation Plant based on dual fuel (gas & alternative fuel) technology in each 38 districts of Bihar.

7899.83 695 19.10.09 (Consent with condition)

176 M/S Gajanana Agronomy Pvt. Ltd, Bettiah.

Establishment of Multipurpose Cold Storage with the capacity of 6860 MTA at Chhawani, Mehdia Bari, West Champaran.

4.49 13 19.10.09 01.02.10

177 M/S Aasma Foods & Beverages Pvt. Ltd., Patna.

Establishment of Fruit & Vegetable Processing unit with the capacity of 2500 MTA at EPIP, Hajipur.

1.10 72 19.10.09 11.02.10

178 M/S Maa Jaemangla Dairy Clusters Ltd., Kolkata. (Earlier, in the SIPB meeting held on 19.10.09 consent was given in the name of M/S Prashant Jalan & Associates, Kolkata for establishment of 100 MT per day capacity of Skimmed Milk Powder, Poly Pack Milk, Ice-cream, Ghee and Curd production unit at Begusarai/ Kahalgaon, Bhagalpur. Again, in SIPB meeting held on 28.09.11 consent has been given in the name of newly formed company M/S Maa Jaemangla Dairy Clusters Ltd for establishment of 44,000 MT per year capacity Ghee, Skimmed Milk Powder, Concentrated Milk, Pasteurized Poly Pack Milk, Curd/Yoghurt production unit at Mohanpur, Begusarai.

Proposal for establishment of 44,000 MT per year capacity Ghee, Skimmed Milk Powder, Concentrated Milk, Pasteurized Poly Pack Milk, Curd/Yoghurt at Mohanpur, Begusarai.

38.61 47 19.10.09 28.09.11

25.09.12

179 M/S Shiv Shakti Modern Flour Mills Pvt. Ltd., Raxaul, East Champaran.

Establishment of Flour Mill with the capacity of 120 MT per day at Raghunathpur, Ramgharwa, Raxaul, E.Champaran.

6.144 78 19.10.09 11.02.10

180 M/S Om Shri Establishment of Modern Rice Mill 13.62 101 19.10.09 11.02.10

Report-3

18

LaxminarayanWarehouse Shoppers Ltd, Patna.

with the capacity of 24 MT per hour at Nasriganj, Danapur, Patna.

181 M/S Thakur Nikunj Cold Storage Pvt. Ltd., Samastipur.

Establishment of Multipurpose Cold Storage with the capacity of 6000 MT at Mathurapur, Samastipur.

3.59 130 19.10.09 11.02.10

182 M/S Auro Sundram International Pvt. Ltd., Roorkee, Dist.- Haridwar(Uttarakhand) (Company’s earlier proposal approved by SIPB on 19.10.09 to set up 150 TPD capacity Maize Processing unit for production of Maize Starch and Liquid Glucose and 3 MW Captive Power Plant at Industrial Area, Forbesganj, Araria has been amended by SIPB on 19.04.10 for establishment of 200 MT per day capacity Maize Processing unit for production of Maize Starch and Liquid Glucose and 2.5 MW Captive power Plant at the same place.)

(Earlier, in the SIPB's 83rd

meeting held on 19.04.10 consent was given for establishment of 200 MT per day capacity Maize Processing unit for production of Maize Starch and Liquid Glucose and 2.5 MW Captive Power Plant.. Again on request of the company amending the above proposal consent has been given for establishment of 300 TPD capacity Maize Processing unit for production of Maize Starch and Liquid Glucose and 03 MW in place of 2.5 MW Captive Power Plant in SIPB meeting held on 28.09.11)

Establishment of 300 TDP capacity Maize Processing unit for production of Maize Starch and Liquid Glucose and 03 MW in place of 2.5 MW Captive Power Plant at Industrial Area, Forbesganj, Araria.

110.00 140 19.10.09 19.04.10 28.09.11

24.06.10

183 M/S Vikramshila Educational and Welfare Society, Patna.

Establishment of Management Institute in the name of Indian School of Management at Vill- Sarai, Khagaul, Patna.

15.13 44 19.10.09 01.02.10

184 M/S Yugal Green Urja Solutions Pvt. Ltd., New Delhi.

Establishment of 750 KW Biomass based Power Plant at Goriakothi, Siwan.

3.55 20 19.10.09

185 M/S Eco Cements Ltd., Varanasi.

Establishment of grinding unit of Portland Cement, Portland Pozzolana Cement and Portland Slag Cement with the capacity of 3000 TPD and 5 MVA Captive Power

100.00 150 19.10.09 23.08.12

Report-3

19

Plant at Karamnasa, Bhabhua.

186 M/S Simri Cold Storage Pvt Ltd, Simri, Samastipur.

Establishment of 6000 MT Capacity Cold Storage, 3 MT per hour Sorting /Grading Unit under R.A.B.C Scheme at Simri, Samastipur.

4.5055 8 09.11.09 01.02.10

187 M/S Mohan Cold Storage Pvt Ltd, Samastipur

Establishment of 10,600 MT Capacity Cold Storage under R.A.B.C. Scheme at Tajpur, Samastipur.

7.44 09.11.09 11.02.10

188 M/S Lichchhwi Foods India Pvt Ltd, Hajipur (Vaishali).

Establishment of 7000 MT per year Capacity Multi Commodity Cold Storage, 2000 MT per year Capacity Deep Freezer and 2 MT per hour I.Q.F Line Freezer at Dighi Kala, Industrial Estate Hajipur

8.72 7 09.11.09 11.02.10

189 M/S Aqua Tech Industries, Keshrinagar, Patna

Establishment of 60 Lakh Liter per year Capacity Packaged Drinking Water Unit at Rajiv Nagar, Patna

1.66 18 09.11.09 (Consent with condition)

190 M/S Sityog Educational & Welfare Society, Patna

Establishment of Engineering and Management College at Aurangabad.

3.20 56 16.11.09

191 M/S Protech Cold Storage Pvt. Ltd, Muzaffarpur.

Establishment of 10,000 MT per year capacity Cold Storage at Paroo, Muzaffarpur.

4.82 26 16.11.09 11.02.10

192 M/S Kamla Agro Pvt. Ltd, Banka

Establishment of 6 MT per hour capacity Rice Mill, Husk Based Power Plant and 5000 MT capacity Warehouse at Amarpur, Banka.

11.47 100 16.11.09 11.02.10

193 M/S Ambo Exports Ltd, Kolkata (Company's proposal approved by SIPB on 16.11.09 for establishment of 100 MT per day capacity Rice Bran Oil Extraction Plant at Aurangabad Industrial Area has been amended and consent has been given with condition for establishment of 500 MT per day capacity Rice Bran Oil Extraction Plant at Kahalgaon Industrial Area, Bhagalpur on 03.05.10.)

Establishment of 500 MT per day capacity Rice Bran Oil Extraction Plant at Kahalgaon Industrial Area, Bhagalpur

25.00 114 16.11.09 03.05.10

194 M/S Bihar College of Education, Promoter- Nav Bharti Trust, Patna

Establishment of Training College in the name and style of Bihar College of Education at Giddha Industrial Area, Ara.

1.0704 17 16.11.09 (Consent with condition)

195 M/S Ashok Cattle and Poultry Feeds Pvt. Ltd, Darbhanga

Establishment of 9600 MT per year capacity Cattle and Poultry Feed Unit at New Industrial Estate Bela, Darbhanga.

0.8922 18 16.11.09 11.02.10

196 M/S D.K. Agro Products, Turki, Muzaffarpur.

Establishment of 60 Lakh Liter per year capacity Milk Processing Plant at Turki, Muzaffarpur.

2.15 80 16.11.09 (Consent with condition)

197 M/S Mirzanagar Gramodyog Sahyog Samiti Ltd, Hajipur.

Establishment of Honey Processing and Packaging Plant at Mahua, Hajipur.

1.166 14 23.11.09 25.05.10

198 M/S Ram Pukar Cold Storage Pvt. Ltd, Samastipur

Establishment of 6500 MT capacity Cold Storage at Mohiuddin Nagar,

5.2288 23 23.11.09 11.02.10

Report-3

20

Samastipur

199 M/S Hrideshwari Jee Modern Rice Mill, Rohtas

Establishment of 2 MT Per hour capacity Modern Rice Mill at Saleya, Akori Gola, Rohtas.

2.1283 15 23.11.09 11.02.10

200 M/S Maurya Foods Pvt. Ltd, East Champaran

Establishment of 8134 MT Capacity Cold Storage under Rural Agri Business Centre at Mehsi, East Champaran.

5.93 37 23.11.09

201 M/S Shree Kalu Cold Storage Pvt. Ltd, Purnea.

Establishment of 11000 MT Capacity Cold Storage under Rural Agri Business Centre at Moranga Growth Centre, Purnea.

6.0430 51 23.11.09 23.04.10

202 M/S Vaidyanath Sugar Mills Pvt. Ltd, East Chamaran

Establishment of 3500 TCD Sugar Mill and 12 MW Electric Co-generation Plant at Chakia,East Champaran.

175.00 277 23.11.09 (Consent with condition)

203 M/S Xavier’s Girls School, Muzaffarpur

Establishment of 10+2 Level Xavier’s Girls School at Industrial Area, Bela, Muzaffarpur.

2.20 46 30.11.09

204 M/S Balajee Mini Steels & Rerolling Pvt. Ltd, Patna

Establishment of 63000 MTA capacity Re-rolling Mill at Bihta-Maner Road, Patna

17.66 78 30.11.09 01.02.10

205 M/S Sivaani Agribusiness Pvt. Ltd, Gaya

Establishment of 30 MT per day capacity Dal Mill at Dhanua, Dovi Road, Gaya.

3.00 20 30.11.09 01.02.13

206 M/S Sadafal Dev Agro Mills Pvt. Ltd, Dehri, Sasaram

Establishment of 96 MT per day capacity Rice Mill at Kauwa, Dehri, Sasaram.

3.9618 45 30.11.09 11.03.10

207 M/S Gaurav Foods and Cool Connections Pvt. Ltd, Patna

Establishment of 45000 MTA capacity Roller Flour Mill at Didarganj, Patna City

4.8781 103 30.11.09 01.02.10

208 M/S SVJ Enterprises Pvt. Ltd, Donar, Darbhanga.

Establishment of 1(one) MT per day capacity Honey Processing unit at Donar, Dist.-Darbhanga

1.236 22 30.11.09 21.12.10

209 M/S Jagran Institute of Management & Mass Communication, Patna.

Proposal for establishment of Jagaran Institute of Management & Mass Communication at Bihta, Patna of M/S Shri Puran Chandra Gupta Smarak Trust, Kanpur

30.11.09

210 M/S Astonfield Renewable Resources Ltd, New Delhi

Establishment of 300 MW Solar Power Plant(5-25 MW size) in first phase at Dist.-Gaya, Sasaram, etc and in second phase at Dist.-Muzaffarpur, Madhubani, West Champaran, Bhojpur and Patna, etc

4500.00 5000 30.11.09

211 M/S Ambo Exports Ltd, Kolkata

Establishment of 1(one) Lakh MT per year capacity Maize Primary Processing, Drying, Sorting and Packaging unit at Kahalgaon Industrial Area, Bhagalpur.

17.00 27 07.12.09

212 M/S Great Value Foods, New Delhi

Establishment of 60,000 MT per year capacity RTE(Ready to eat) Supplementary Nutrition Fortified Food unit in Bihar.

16.2903 179 07.12.09

213 M/S Om Shri Gramin Fodder Food Process Ltd, Patna (Company’s proposal approved on 07.12.09 for establishment of 1,53,600 MT per year capacity Modern

Establishment of 1,53,600 MT per year capacity Modern Rice Mill at Danapur, Patna.

10.14 101 07.12.09 12.01.11 (Consent with

Report-3

21

Rice Mill at Phulwarisharif, Patna has been amended and approval has been given for the same project at Danapur, Patna in SIPB meeting held on 12.01.11)

condition)

214 M/S Okpet Construction & Services Pvt. Ltd, Patna.

Establishment of 600 MT/Kilo Litre per year Fruit Pulp and Juice Processing unit at Simri, Darbhanga

1.1291 21 07.12.09

215 M/S Shree Shree Dwarikaji Foods Pvt. Ltd, Patna City.

Proposal for capacity expansion from 24000 MT per year to 60000 MT per year in the existing Flour Mill at Karmali Chak, Bypass Road, Patna City.

3.77 50 21.12.09 06.01.11

216 M/S Sano Foods Pvt. Ltd, Mumbai.

Proposal for establishment of 3434 MT capacity production unit of Vermicelli and Macroni at Danapur, Patna.

13.39 28 21.12.09

217 M/S Golden Dairy Products Pvt. Ltd, Patna.

Proposal for establishment of Ice-cream and Dairy Products unit at Industrial Area, Hajipur.

1.96 37 21.12.09

218 M/S Balmukund Cement & Roofings Ltd, Kolkata

Proposal for establishment of 1.5 Lakh MT capacity production unit of Asbestos Fiber Cement Sheet (Corrugated/Flat) and Accessories at Kanti, Muzaffarpur.

31.00 45 21.12.09

219 M/S Bhagwan Veer Hanuman Cold Storage Pvt. Ltd, Samastipur

Proposal for establishment of 5000 MT capacity Cold Storage, 2 MT per hour capacity Rice Mill and Warehouse under RABC at Industrial Area, Harpur Alloth, Samastipur.

4.17 4 21.12.09 11.07.11

220 M/S Hamara Industries, Boring Road, Patna

Proposal for establishment of 700 MT per year capacity Glucose-D Processing and Packaging unit from Dextrose Monohydrate (100% Maize product) at Industrial Area, Giddha.

2.55 50 21.12.09 27.02.11

221 M/S Bansal Biscuits Pvt. Ltd, Kolkata (Amending the proposal approved on 21.12.09 for establishment of 12,600 MT per year capacity Biscuits production unit at EPIP, Hajipur, approval has been given for manufacturing of 36,000 MT per year capacity Biscuit manufacturing unit at EPIP, Hajipur on 26.05.11)

Proposal for establishment of 36000 MT per year capacity Biscuit production unit at EPIP, Hajipur Industrial Area.

50.57 328 21.12.09 26.05.11

25.05.10

222 M/S Shyama Agro Foods & Exports Pvt. Ltd, Muzaffarpur. (Cancelling the earlier proposal approved on 04.01.10 for establishment of Ultra Modern Fruit and Vegetable Processing unit at Industrial Area, Bela, Muzaffarpur, approval has been given for establishment of 36,000 MT per year capacity Modern Flour Mill unit at Industrial Area, Bela, Muzaffarpur in SIPB meeting held on

Establishment of 36,000 MT per year capacity Modern Flour Mill unit at Industrial Area, Bela, Muzaffarpur.

5.5500 36 04.01.10 11.06.12

20.02.11

Report-3

22

11.06.12.)

223 M/S Raghunandan Teachers Training College, Promoter-Baba Educational Trust, Danapur, Patna.

Establishment of B.Ed. Teachers Training College at Mathiyapur(Kali Asthan), Danapur, Patna.

1.00 30 04.01.10

224 M/S Glatt Solutions Pvt. Ltd, Kolkata. (Approval was given on 11.01.10 in SIPB meeting for establishment of 03 MW Grid connected Solar Photo Voltaic Power Project at Muzaffarpur/Purnea. Again on request of the company approval has been given for same project at Nawada in place of Muzaffarpur/Purnea in SIPB meeting on 26.05.11)

Establishment of 3 MW Grid Connected Solar Photo Voltaic Power Project at Nawada

57.00 22 11.01.10 26.05.11

225 M/S Gokul Sericulture Production and Training Centre, Gokul, Pilkhi, Muzaffarpur

Establishment of Sericulture Production and Training Centre at Gokul, Pilkhi, Muzaffarpur in the name of M/S Gokul Sericulture Production and Training Centre by M/S Maha Lakshmi Kripa Social and Educational Welfare Society, Muzaffarpur

2.53 65 11.01.10

226 M/S Abacus Holdings Pvt. Ltd, Kolkata.

Establishment of 05-05 MW Grid Connected Solar Photo Voltaic Power Project at Muzaffarpur, Gaya, Bhagalpur and Purnea.

392.48 96 11.01.10

227 M/S Adhunik Metaliks Ltd, Kolkata (Company's proposal approved by SIPB on 01.02.10 for establishment of 2.2 MTA Integrated Steel Plant at Industrial Growth Centre, Bhagalpur has been amended and consent has been given for establishment of 2.2 MTPA Integrated Steel Plant at Kahalgaon, Pirpainti Block, Bhagalpur.)

Establishment of 2.2 MT PA capacity Integrated Steel Plant at Kahalgaon, Pirpainti Block, Bhagalpur.

5668.29 2187 01.02.10 03.05.10

228 M/S Bhojpur Rice Mill Pvt. Ltd, Bhojpur

Establishment of 9600 MT per year capacity Rice Mill at Baradparva, District.- Bhojpur

1.54 30 01.02.10 06.04.10

229 M/S Maa Durga Rice Mill, Madhubani.

Establishment of 2400 MT per year capacity Rice Mill at Industrial Area, Pandaul, Madhubani.

0.4731 7 01.02.10 08.06.10

230 M/S Raj Agrochem Products Pvt. Ltd, Muzaffarpur.

Establishment of 45000 MT per year capacity Poultry Feed and Cattle Feed Unit at Bochahan, Muzaffarpur.

5.39 41 01.02.10 16.04.10

231 M/S Maa Shitla Rice Mill Pvt. Ltd, Purnea.

Establishment of 14,400 MT per year capacity Rice Mill at Growth Centre, Moranga, Purnea.

1.206 26 01.02.10 06.01.11

232 M/S Bihar Hotels Ltd, Patna. (Company’s earlier proposal approved by SIPB on 01.02.10 for establishment of Budget Hotel at Dehri-on-Sone has been amended and consent has been given with condition for establishment of 2-Star Hotel at Dehri-on-

Establishment of 2-Star Hotel at Dehri-on-Sone.

4.79 49 01.02.10 19.04.10 (Consent with condition)

Report-3

23

Sone on 19.04.10)

233 M/S Prakash Udyog, Patna. Establishment of 1200 Kiloliter Fruit Drink, 12000 Kiloliter Packaged Drinking Water and 2400 Kiloliter Soda Water Production Plant at Industrial Area, Patliputra, Patna.

2.52 25 01.02.10

234 M/S UAL Industries Ltd, Kolkata. (Company's proposal approved by SIPB on 01.02.10 for establishment of 1,20,000 MT per year capacity Asbestos Cement and corrugated Sheets Plant at Bakhtiyarpur has been amended and consent has been given for establishment of 2,33,000 MT per year capacity Asbestos Cement Sheet, Corrugated Sheets Plant in two phases at Goraul, Vaishali in the name of UAL-Bihar in SIPB meeting held on 21.07.10)

Establishment of 2,33,000 MT per year capacity Asbestos Cement Sheet and Corrugated Sheets Plant in two phases at Goraul, Vaishali in the name of UAL-Bihar

54.67 210 01.02.10 21.07.10

235 M/S Oriental Group of Institutes, Bhopal

Establishment of Engineering College at Patna

59.84 300 01.02.10 (Consent with condition)

236 M/S Shobhnath Rice Mill Pvt. Ltd, Bhabhua.

Establishment of 2 MT per hour capacity Rice Mill and 1000 MT capacity Warehouse at Kulhariya, Kaimur, Dist.-Bhabhua.

1.15 16 01.02.10 28.03.10

237 M/S G. C. Foods Pvt. Ltd, Muzaffarpur.

Establishment of 960 MT per year capacity Puff and Fried Snacks Food unit at Industrial Estate, Bela, Muzaffarpur.

1.91 23 01.02.10

238 M/S Satbhani Agro Pvt. Ltd, Aurangabad.

Establishment of 10 MT per hour capacity Modern Rice Mill, 4 MT per hour capacity Sortex and Packaging unit, 7000 MT capacity Warehouse and 1.2 MW Husk based Power Plant at Aurangabad.

10.77 36 01.02.10

239 M/S Kaimur Kohinur Rice Mill Pvt. Ltd, Kaimur.

Establishment of 9600 MT per year capacity Rice Mill at Chand, Dist.- Kaimur.

1.53 14 01.02.10 23.04.10

240 M/S Shrawasthi Agrotech Pvt. Ltd, Lucknow.

Establishment of 4500 MT capacity Poultry Feed unit at Giddha Growth Centre, Ara(Bhojpur).

6.18 30 01.02.10 04.02.11

241 M/S Milsha Agro Exports Pvt. Ltd, Kolkata.

Establishment of 500 MT capacity Multi Purpose Cold Storage, 10 MT Pre-cooling Room, 5 MT Pulp Processing Unit in Phase-1 and 1 MT Individual Quick Freezer in Phase-2 at Hajipur Industrial Estate.

5.60 41 15.02.10

242 M/S Badrinarayanji Agromills Pvt. Ltd, Sasaram.

Establishment of 7 MT per hour capacity Modern Rice Mill, 3000 MT capacity Warehouse at Usrawan, Cochas, Rohtas.

4.50 40 15.02.10 12.05.10

243 M/S Keshri Cold Storage Agro Products and Construction Pvt. Ltd, Rohtas.

Establishment of 7000 MT (5000 MT Potato and 2000 MT Onion) capacity Cold Storage, 2 MT per hour Potato sorting/grading line, 2 MT per hour

7.17 11 15.02.10 23.04.10

Report-3

24

capacity Modern Rice Mill and 4000 MT capacity Warehouse under R.A.B.C at Dhoudhad, Sasaram

244 M/S Gayatri Soya Food Products, Patna.

Proposal for establishment of Production unit of 960 Liter per day capacity Soya Milk and Paneer at Phulwarisharif, Patna

0.51 17 15.02.10 02.12.11

245 M/S Nilkanth Chawal Mills Pvt. Ltd, Kolkata. (Approval was given for Modernisation of the existing Rice Mill with the capacity of 10,692 MT per year at Conch, Gaya. Again on request of the company, approval has been given for capacity expansion from 54 MT per day to 90 MT per day in the existing Rice Mill at Conch, Gaya on 26.05.11)

Proposal for Modernisation of the existing unit of Rice Mill of 10,692 MT per year capacity at Ahiyapur, Konch, Gaya. Proposal for capacity expansion from 54 MT per day to 90 MT per day in the existing Rice Mill at Conch, Gaya.

3.3634 1.2047

19 19

15.02.10 26.05.11

25.05.10

246 M/S Comprehensive Consultancy Pvt. Ltd, Kolkata.

Establishment of 5 MT per hour capacity Rice Mill, 3 MT per hour capacity Sorting/ Packaging, Warehouse of 4500 MT and Husk Processing Gasifier unit at Banka, Bhagalpur.

6.10 14 22.02.10 23.07.10

247 M/S Sita Flour Mills Pvt. Ltd, Darbhanga

Proposal for capacity expansion of existing Flour Mill from 100 MT per hour to 200 MT per hour at Donar Industrial Area, Darbhanga.

1.45 7 22.02.10 04.02.11

248 M/S Shivsagar Rice Mill Pvt. Ltd, Nalanda

Establishment of 14400 MT per year capacity Rice Mill at Deep Nagar, Maniyama Road, Nalanda.

2.05 33 22.02.10 08.06.10

249 M/S Champaran Agricon Pvt. Ltd, East Champaran (Motihari)

Establishment of 64 MT per day capacity Rice Mill at Chandrahiya, Motihari.

2.29 45 22.02.10

250 M/S Auto Matrix Pvt. Ltd, Patna.

Proposal for capacity expansion and Modernization of existing unit of Service Centre and Auto Parts at Patliputra Industrial Estate.

2.76 22 08.03.10 (Consent with condition)

251 M/S Kumar Tech Bio Products Pvt. Ltd, Bangalore. (Company’s proposal for establishment of 30 MW Rice Husk based Power Plant at Bodh Gaya, Gaya which was approved in SIPB meeting on 8.03.10, has been amended and approval has been given for same project at Kizarsarai Road, Gaya in SIPB meeting held on 29.11.10)

Establishment of 30 MW Rice Husk based Power Plant at Kizarsarai Road, Gaya.

306.00 300 08.03.10 (Consent with condition) 29.11.10 (Consent with condition)

20.12.11

252 M/S Leela Anand Fertilizer & Chemicals Pvt. Ltd, Patna

Establishment of 60,000 MT per year capacity N.P.K. Fertilizer unit at Ahiyapur, Turki, Muzaffarpur.

7.90 67 08.03.10

253 M/S Gokul Steels Pvt. Ltd, Patna.

Establishment of Steel Re-rolling Mill for production of 28,800 MT per year capacity Steel Bar and Rod at Khusrupur, Patna.

9.20 46 08.03.10

254 M/S Shree Vishnu Vishal Paper Mills Pvt. Ltd, Patna

Establishment of 33,000 MT per year capacity Craft Paper and Paper Board and 3 MW Captive Power

32.11 182 08.03.10

Report-3

25

Plant at Industrial Area Growth Centre, Giddha

255 M/S Amrapali Biotech India Pvt. Ltd, Gaziabad, U.P. (Company's proposal approved by SIPB on 08.03.10 for establishment of 2779 MT per year capacity Pickles and Corn Flakes unit at Industrial Area, Bela, Muzaffarpur has been amended and consent has been given for establishment of 8825 MT per year capacity Tomato Ketchup, Pickles, Jam and Jelly and Corn Flakes unit at Chabilapur, Rajgir in SIPB meeting held on 21.07.10)

Establishment of 8825 MT per year capacity Tomato Ketchup, Pickles, Jam and Jelly and Corn Flakes unit at Chabilapur, Rajgir

17.37 119 08.03.10 21.07.10

04.02.11

256 M/S Amrit Cement Pvt. Ltd, Kolkata.

Establishment of Cement Grinding unit of 6.60 Lakh MT per year capacity at Kahalgaon, Bhagalpur.

111.28 140 08.03.10

257 M/S Natraj Agro and Herbs Pvt. Ltd, Nawada

Establishment of 4 MT per hour capacity Modern Rice Mill and 1200 MT Warehouse at Konchgaon, Warsaliganj, Nawada.

1.48 20 08.03.10 (Consent with condition)

25.05.10

258 M/S Binod Cold Storage Pvt. Ltd, Begusarai

Establishment of 7000 MT capacity Cold Storage, Sorting/Grading of Potato and Agri Input Store under R.A.B.C. at Tilrath Devnath Industrial Area, Barauni, Begusarai.

5.48 20 08.03.10 (Consent with condition)

06.01.11

259 M/S Rozy Food Processing Pvt. Ltd, Begusarai

Proposal for capacity expansion of existing production unit of Spice Powder from 500 Kg per day to 1500 Kg per day at Tilrath Industrial Area, Barauni, Begusarai.

0.9423 15 08.03.10 (Consent with condition)

260 M/S Sri Moti Pvt. Ltd., Chapra

Proposal for establishment of 6500 MT capacity Cold Storage, 2 MT per hour Potato Grading Line, Weighing Line-1, 500 MT Agri Input Godown and 600 MT capacity Warehouse unit under R.A.B.C at Khalpura, Motinagar, Chapra.

5.61 20 23.03.10

261 M/S Uttri Bihar Milk Food Company Pvt. Ltd., Begusarai (Amending the earlier proposal approved in SIPB meeting on 23.03.10 for the production of 30,140 MT per year capacity Pasteurized Milk, Chhena, Curd, Paneer, Milk Cake and Khoa at Industrial Area, Begusarai, approval has been given for the production of 30,000 MT capacity Pasteurized Milk, Chhena, Curd, Paneer, Milk Cake and Khoa at Ajnul, Dalsingsarai, Samastipur on 26.05.11)

Proposal for production of 30,000 MT capacity Pasteurized Milk, Chhena, Curd, Paneer, Milk Cake and Khoa at Ajnul, Dalsingsarai, Samastipur.

1.0918 102 23.03.10 26.05.11

16.08.11

262 M/S Ambo Exports Ltd, Kolkata

Proposal for establishment of 35 MT per day capacity Biscuit production unit at Kahalgaon Industrial Area, Bhagalpur.

17.50 204 23.03.10

263 M/S Yashoda Enterprises Proposal for establishment of 3000 Liters 1.00 24 23.03.10

Report-3

26

Pvt. Ltd, Fatuha, Patna. per hour capacity Packaged Drinking Water unit at Fatuha Industrial Area, Patna.

(Consent with condition)

264 M/S Maa Mundeshwari Agro Mills Pvt. Ltd., Aurangabad.

Proposal for establishment of 4 MT per hour capacity Modern Rice Mill and 1000 MT Warehouse at Growth Centre, Aurangabad.

2.59 30 23.03.10 02.01.12

265 M/S Hindustan Coca-Cola Beverages Pvt. Ltd., Haryana

Proposal for establishment of Coca Cola Green Field Project for the production of Aerated Drinks, Soft Drinks, other Non-alcoholic Beverage, Fruit Juice/ Fruit Based Drinks and Packaged Drinking Water at Industrial Area, Bihta, Patna.

100.00 100 23.03.10 (Consent with condition)

266 M/S Mega Rice Mill Pvt. Ltd, Jehanabad

Proposal for establishment of 3 MT per hour capacity Rice Mill at Algana, Jehanabad.

1.17 10 23.03.10 02.01.12

267 M/S Rainbow Products Pvt. Ltd, Patna. (Company’s proposal approved by SIPB on 19.04.10 for establishment of 28,800 MT per year capacity Rice Mill at Mahuli Road, Karmalichak, Patna City, Patna has been amended and consent has been given for establishment of 14,400 MT per year capacity Rice Mill at the same place.)

Proposal for establishment of 14,400 MT per year Capacity Rice Mill Unit at Mahuli Road, Karmalichak, Patna City.

3.11 23 19.04.10 27.08.10

04.02.11

268 M/S Gulshan Polyols Ltd, Delhi (Cancelling the earlier proposal approved on 19.04.10, approval has been given for establishment of

Maize Processing unit for the production capacity of Sorbitol-10,000 MT per year, Dextrose Monohydrate - 20,000 MT per year and Lysine- 30,000 MT per year capacity from Maize and in addition to this project establishment of 63,200 Kiloliter per year capacity grain based Distillery for E.N.A. unit, 6.5 lac HLA capacity Brewery Plant and 13.5 lac Cases per month capacity I.M.F.L Bottling Plant unit at Industrial Growth Centre, Kahalgaon, Bhagalpur in SIPB meeting held on 09.04.12).

Proposal for establishment of Maize Processing unit for the production capacity of Sorbitol-10,000 MT per year, Dextrose Monohydrate - 20,000 MT per year and Lysine- 30,000 MT per year capacity from Maize and in addition to this project establishment of 63,200 Kiloliter per year capacity grain based Distillery for E.N.A. unit, 6.5 lac HLA capacity Brewery Plant and 13.5 lac Cases per month capacity I.M.F.L Bottling Plant unit at Industrial Growth Centre, Kahalgaon, Bhagalpur.

583.05

531

19.04.10 09.04.12

269 M/S Aditya Food Products, Ara(Bhojpur)

Proposal for establishment of 21,600 MT per year capacity Flour Mill in partnership at Giddha, Ara.

1.43 36 19.04.10

270 M/S Harinagar Sugar Mills Ltd, Harinagar.

Proposal for establishment of 14.5 MW new Power Project at Bagaha, Harinagar.

77.50 29 19.04.10 (Consent with condition)

10.04.11

271 M/S Terai Ispat Ltd, Siliguri. Proposal for establishment of two Induction Furnace of 15 MT,(Steel Melting Shop 1,05,000 MT per year) 99684 MT per year capacity Re-rolling

149.88 697 19.04.10 (Consent with condition)

Report-3

27

Mill and 12 MW Captive Power Plant at Banka

272 M/S Durga Agronomy Pvt. Ltd, Darbhanga.

Proposal for establishment of 8 MT per hour capacity Rice Mill and 2000 MT capacity Warehouse at Donar Industrial Area, Darbhanga.

3.87 30 19.04.10

273 M/S Shree Shyam Kutir Udyog, Muzaffarpur.

Proposal for establishment of 480 MT per year capacity Spice Powder and Besan Udyog at Industrial Estate, Bela, Muzaffarpur in proprietorship.

0.3273 15 19.04.10

274 M/S Kunwar Apiary Pvt. Ltd, Gaya.

Proposal for establishment of 10 MT per day capacity Honey Processing unit at Janakpur, Buniyadganj.

1.41 20 19.04.10 06.01.11

275 M/S Shiv Shakti Agriproducts and Rice Industries Pvt. Ltd, East Champaran.

Proposal for establishment of 05 MT per hour capacity Modern Rice Mill at Gamaharia, Raxaul.

2.81 52 19.04.10 21.12.10

276 M/S Kumar Industries, Darbhanga

Proposal for establishment of 150 MT per year capacity Noodle Production unit at Industrial Area, Bela, Darbhanga in proprietorship.

0.1681 10 19.04.10

277 M/S Moti Babu Institute of Technology, New Delhi.

Proposal for establishment of Engineering College at Forbesganj, Araria.

14.66 65 19.04.10 (Consent with condition)

278 M/S Ambe Kamakhya Agronomy Pvt. Ltd, Begusarai

Proposal for establishment of 5000 MT per year capacity Cold Storage under Rural Agri Business Centre at Bakhri Bazar, Begusarai.

3.91 20 19.04.10 (Consent with condition)

06.01.11

279 M/S Britannia Industries Ltd, Bangalore(Karnataka)

Proposal for establishment of 50,000 MT per year capacity Bakery Product and production of Biscuit at E.P.I.P., Hajipur.

55.00 330 19.04.10 27.02.11

280 M/S Hyderabad Industries Ltd, Hyderabad.

Proposal for establishment of 2,50,000 MT per year capacity Asbestos Cement Sheeting Plant in two Phases at Kumarbagh Industrial Area, West Champaran.

80.00 600 19.04.10

281 M/S Sonamoti Agrotech Pvt. Ltd, Patna. (Earlier, in the SIPB meeting held on 03.05.10 consent was given for establishment of 28,800 MT per year capacity Rice Mill at Karmalichak, Patna City. Again on request of company, amending the above proposal consent has been given for establishment of 62592 MT per year capacity Modern Rice Mill in place of 28,800 MT per year capacity in SIPB meeting held on 28.09.11)

Proposal for establishment of 62592 MT per year capacity Modern Rice Mill in place of 28,800 MT per year capacity at, Karmalichak, Patna City. Patna.

22.4394 103 03.05.10 28.09.11

04.02.11 22.12.12

282 M/S Creation Agro Processing Industries, Bhagalpur.

Proposal for establishment of 1500 MT per year capacity Chura(Pressed Rice) Mill at Barari Industrial Area, Bhagalpur in proprietorship.

0.46 12 03.05.10

283 M/S Radhika Flour Mills Pvt. Ltd, Patna.

Proposal for establishment of 36,000 MT capacity Flour Mill for production of Maida, Atta, Suzi and Chokar at Sikandarpur, Bihta.

5.84 55 03.05.10 10.04.11

Report-3

28

284 M/S Khilani Agro Foods Pvt. Ltd, Hajipur.

Proposal for establishment of 12.73 Crore pieces per year capacity Preform Pet Bottle's unit at E.P.I.P. Hajipur.

15.77 25 03.05.10

285 M/S Jaya Nutritions Pvt. Ltd, Deedarganj Patna City.

Proposal for establishment of 80 MT per day capacity Roller Flour Mill at Deedarganj, Patna City.

5.65 42 03.05.10 23.07.10

286 M/S Riya Chakraborty Food Processing Pvt. Ltd, Bhagalpur.

Proposal for establishment of 01 MT per hour capacity Fruit Processing Unit and Tomato Juice Plant at Industrial Area, Barari, Bhagalpur.

0.99 20 03.05.10 (Consent with condition)

287 M/S Arisson Power Ltd, Kolkata

Proposal for establishment of 1320 MW Coal Based Thermal Power Plant at Prabhawati Nagar, Banka.

7260.00 145 24.05.10 11.09.12

288 M/S Pashupati Roller Flour Mill Pvt. Ltd, East Champaran.

Proposal for establishment of 100 MT per day capacity Roller Flour Mill at Bela Industrial Area, Muzaffarpur.

5.60 30 24.05.10 02.12.11

289 M/S Shimla Horticulture Pvt. Ltd, Kolkata.

Proposal for establishment of 1000 MT per year capacity Multipurpose Cold Storage at EPIP, Hajipur.

15.66 400 24.05.10

290 M/S Aarna Foods Pvt. Ltd, Patna City.

Proposal for capacity expansion from 4500 MT to 9600 MT per year capacity in the existing Rice Mill at Deedarganj, Patna City.

2.95 7 24.05.10 04.02.11

291 M/S Sunasi Food and Beverages Pvt. Ltd, Patna.

Proposal for production of 60 Lac Liters per year capacity Fruit Juice at Industrial Area, Giddha, Ara.

2.00 70 24.05.10

292 M/S Green Valliey Industries Ltd, Shillong

Proposal for establishment of 1 Million Ton per year capacity Cement Grinding unit at Industrial Growth Centre, Kahalgaon, Bhagalpur.

120.00 200 24.05.10

293 M/S Sandeep Sijol Infrastructure Pvt. Ltd, Mumbai

Proposal for Generation of Electricity from 3 MW Solar Photo Voltaic Modules at Madhubani / Samastipur / Vaishali.

57.00 23 24.05.10

294 M/S A Infrastructure Ltd, Rajasthan (Company’s proposal for change of place from Industrial Area, Kumarbagh, Bettiah to Pandaul Industrial Area, Madhubani has been approved in SIPB meeting held on 07.09.10)

Proposal for establishment of 1,25,000 MT per year capacity A.C. Sheet and 1,00,000 MT per year capacity A.C. Pressure Pipe at Pandaul Industrial Area, Madhubani.

91.65 352 24.05.10 07.09.10

10.04.12

295 M/S Ruby Rahul Rice Mills Pvt. Ltd, Patna City.

Proposal for establishment of 3 MT per hour capacity Rice Mill and 1000 MT capacity Warehouse at Giddha Industrial Area, Ara.

0.72 9 24.05.10

296 M/S Kisan Food Processing Udyog, Darbhanga.

Proposal for establishment of 2 MT per hour capacity Modern Rice Mill, 01 MT per hour capacity Rice Flakes and 0.5 MT per hour capacity Corn Flakes unit in proprietorship at New Industrial Area, Bela, Darbhanga.

0.9089 30 24.05.10 30.09.11

297 M/S Maa Tara Water Products, Patna.

Proposal for establishment of 120 Lac Liters per year capacity Packaged Drinking Water unit in partnership at Dashratha, Patna.

0.8522 24 24.05.10

298 M/S Aquadolphin Solutions Pvt. Ltd, Patna.

Proposal for establishment of 72 Lac Liters per year capacity Packaged Drinking Water unit at Babhanpura,

1.0161 13 24.05.10

Report-3

29

Phulwarisharif, Patna.

299 M/S Patliputra Educational and Welfare Foundation, Patna.

Proposal for establishment of Educational Institute of Engineering and Polytechnic College in two phases at Islampur, Nalanda.

30.00 150 24.05.10

300 M/S City Rolling Mills Pvt. Ltd, Patna. (Company’s proposal approved by SIPB on 24.05.10 for establishment of 3000 MT per year capacity Rolling Mill at Bihta, Patna has been amended and consent has been given for establishment of 30,000 MT per year capacity Rolling Mill at Bihta, Patna in SIPB meeting held on 29.06.10)

Proposal for establishment of 30,000 MT per year capacity Rolling Mill at Bihta, Patna.

7.72 44 24.05.10 29.06.10

301 M/S Ganga Dairy Ltd, Begusarai

Proposal for Capacity Expansion from 10 MT per day to 40 MT per day in the existing Milk Processing unit at Begusarai.

10.30 65 08.06.10 21.05.11

302 M/S Royal Manucon Pvt Ltd, Hajipur(Vaishali). (Earlier on 08.06.10 approval was given for establishment of 120 Lac Liters per year capacity Packaged Drinking Water unit at Industrial Area, Hajipur. Again on company's request, amending above, approval has been given for 120 Lac Liters per year capacity Packaged Drinking Water, 5 Lakh Cartoons per year Soda Water (24x600 ml. in one Cartoon) and 2,16,000 Pieces per year capacity Pet Jar production unit at Industrial Area, Hajipur in SIPB held on 26.03.12.)

Proposal for establishment of 120 Lac Liters per year capacity Packaged Drinking Water, 5 Lakh Cartoons per year Soda Water (24x600 ml. in one Cartoon) and 2,16,000 Pieces per year capacity Pet Jar production unit at Industrial Area, Hajipur

1.5480 51 08.06.10 26.03.12

303 M/S Diwakar Solar Projects Pvt. Ltd, Hyderabad.

Proposal for establishment of 15 MW Solar Photo Voltaic Power Plant at Kumarbagh Industrial Estate, Bettiah.

253.50 15 08.06.10

304 M/S Howrah Mills Company Ltd., Howrah

Proposal for establishment of 05 MW Rice Husk Based Power Plant at Barsoni, Purnea.

28.50 25 08.06.10

305 M/S Mohini Oil Mills, Nalanda.

Proposal for establishment of 15 Lac Liters per year capacity Mustard Oil Extraction Plant at Hilsa, Nalanda in Partnership.

0.48 14 08.06.10

306 M/S Maruti Nandan Food Products Pvt. Ltd, Ara

Proposal for establishment of 250 MT per day capacity Roller Flour Mill at Giddha Industrial Area, Ara.

12.38 60 08.06.10 26.07.10

307 M/S Global Powmin Ltd., Kolkata (Amending the proposal approved on 08.06.10 for establishment of 2640 MW coal based Therma Power Plant at Sirdala(Nawada), approval has been given for

Proposal for establishment of 2640(4x660) MW Coal Based Thermal Power Plant at Sirdala (Nawada)-Fatehpur(Gaya).

14908.40 400 08.06.10 26.05.11

Report-3

30

establishment of 2640 MW coal based Thermal Power Plant at Sirdala(Nawada)- Fatehpur(Gaya) on 26.05.11.)

308 M/S Vishwanath Agro Foods Pvt. Ltd, Muzaffarpur.

Proposal for establishment of 60 MT per day capacity Modern Maize Mill at Kudhani, Muzaffarpur

4.60 35 29.06.10 04.02.11

309 M/S Lavanya Finvest Pvt Ltd, Muzaffarpur.

Proposal for establishment of 36,000 MT per year capacity Pale-G and Pare Namkin Biscuit production unit at Industrial Area, Bela, Muzaffarpur.

22.70 434 29.06.10 27.02.11

310 M/S Kanishka Agro Foods Pvt Ltd, Begusarai.

Proposal for establishment of 40,000 MT per year capacity Cattle and Poultry Feed unit at Industrial Area, Barauni.

4.70 36 29.06.10

311 M/S Himalayan Vegefruit Ltd, Chandigarh.

Proposal for establishment of 2000 MT per year capacity Fruit Processing unit at Industrial Estate, Muzaffarpur.

18.00 150 29.06.10

312 M/S Akanksha Foods Pvt Ltd, Patna City, Patna. (Cancelling the earlier proposal approved on 29.06.10 for establishment of 21,600 MT per year capacity Flour and Bran production unit at E.P.I.P. , Hajipur, approval has been given for establishment of 21,600 MT per year capacity Flour and Bran production unit at Simli, Didarganj, Patna in SIPB meeting held on 13.08.12.) (Approval has been given for change of capacity of Flour and Bran production unit at Simli, Didarganj, Patna as 29,400 MT per year capacity in place of 21,600 MT per year capacity in SIPB meeting held on 13.03.13. )

Proposal for establishment of 29,400 MT per year capacity Flour and Bran production unit at Simli, Didarganj, Patna.

6.10

67

29.06.10 13.08.12 13.03.13

313 M/S J. K. Aqua Industries, Muzaffarpur.

Proposal for establishment of 120 Lac Liters per year capacity Packaged Drinking Water unit at Banaras Bank Chowk, Muzaffarpur in proprietorship.

0.98 10 29.06.10

314 M/S Peerage Buildtech Pvt. Ltd, New Delhi.

Proposal for establishment of 8400 MT per year capacity Noodle production unit at Industrial Area, Hajipur.

6.16 62 29.06.10

315 M/S Paras Agro Foods, Muzaffarpur.

Proposal for establishment of 54000 MT per year capacity Makhana Processing and Packaging unit at Bela Industrial Estate, Muzaffarpur in proprietorship.

0.2676 12 29.06.10 02.01.12

316 M/S Siddhi Refoils & Industries Pvt. Ltd, Kolkata. (Earlier on 29.06.10 approval was given for establishment of 75,000 MT per year capacity Edible Oil Refinery Plant and 1 MW Captive

Proposal for establishment of 75,000 MT per year capacity Edible Oil Refinery Plant and 2 MW Captive Power Plant at Akbar Malahi, Lalganj, Vaishali.

58.1000 130 29.06.10 23.02.12

18.12.11

Report-3

31

Power Plant at Akbar Malahi, Lalganj, Vaishali. Again on company's request, amending partly approval has been given for 75,000 MT per year capacity Edible Oil Refinery Plant and 2 MW Captive Power Plant at Akbar Malahi, Lalganj, Vaishali in SIPB held on 23.02.12.)

317 M/S Nawneet Raj Rice Mills Pvt. Ltd, Ara.

Proposal for establishment of 2.5 MT per hour capacity Rice Mill and 1000 MT Warehouse at Ariaon, Dumraon, Buxar.

1.54 20 29.06.10

318 M/S Oriental Crafts Manufacturing Company Pvt. Ltd , Guwahati, Assam.

Proposal for establishment of 40,000 MT per year capacity Maize based Cattle Feed and Poultry Feed production unit at Bela Industrial Area, Muzaffarpur.

4.45 36 21.07.10

319 M/S Ambo Exports Ltd, Kolkata

Proposal for establishment of 200 MT per day capacity Modern Rice Mill unit at Kahalgaon Industrial Area, Bhagalpur.

17.50 114 21.07.10

320 M/S Ambo Exports Ltd, Kolkata

Proposal for establishment of 18,000 MT per year capacity Maize Starch Production Unit at Kahalgaon Industrial Area, Bhagalpur.

16.12 114 21.07.10

321 M/S Anmol Feeds Pvt. Ltd, Muzaffarpur

Proposal for capacity expansion from 36000 MT per year capacity to 81000 MT per year capacity in the existing unit of Cattle and Poultry Feed at Bela Industrial Area, Muzaffarpur.

3.39 55 21.07.10 16.02.12

322 M/S Shree Saibaba Plasto Products Pvt. Ltd, Kolkata.

Proposal for establishment of 1914 MT per year capacity Plastic Molded unit at E.P.I.P. , Hajipur.

5.62 40 21.07.10

323 M/S Kumar Infratrade Enterprises Pvt. Ltd, Patna. (Approval has been given for 135 rooms Five Star Hotel in place of 84 rooms in SIPB meeting held on 25.02.11)

Proposal for establishment of 135 rooms Five Star Hotel at Exhibition Road, Patna.

48.34 50 21.07.10 25.02.11

17.09.11

324 M/S Keventer Food Park Infra Ltd, Kolkata.

Proposal for establishment of Food Park at Kahalgaon Industrial Area, Bhagalpur.

75.33 425 21.07.10

325 M/S Maa Sarswati Modern Rice Mill Pvt. Ltd, Patna.

Proposal for establishment of 6 MT per hour capacity Rice Mill and 1000 MT Warehouse at Bhagwatipur More, Bihta, Patna.

01.55 45 21.07.10 06.01.11

326 M/S AKS Fashion News Pvt. Ltd, Patna.

Proposal for establishment of 900 MT per year capacity Banana & Bamboo Fiber Yarns unit at Hajipur.

2.06 120 21.07.10

327 M/S Dharti Agro Food Products, Muzaffarpur.

Proposal for establishment of 24 MT per day capacity Flour Mill at Bela Industrial Area, Muzaffarpur in Partnership.

0.8748 32 21.07.10

328 M/S Mirach Power Ltd, Gurgaon, Haryana. (Amending the earlier proposal approved on 11.08.10, approval has been given on change of company’s name from M/S Mirach Power Pvt. Ltd. to M/S

Proposal for establishment of 1320 MW (2x660MW) coal based Thermal Power Plant at Lakhisarai.

7359.60 600 11.08.10 (Consent in-principle) 27.07.11

Report-3

32

Mirach Power Ltd for the same project on 27.07.11)

329 M/S Mars Mountain Securities and Trade Pvt. Ltd, Fatuha

Proposal for establishment of 75 lac liters per year capacity Packaged Drinking Water unit at Fatuha Industrial Area.

2.08 25 11.08.10

330 M/S S.S.K. Enterprises, Muzaffarpur.

Proposal for establishment of 2000 Liters per hour Packaged Drinking Water at Shyambabu Road, Andigola, Muzaffarpur in proprietorship.

0.9177 22 11.08.10

331 M/S Pawan Rice Industries, Gopalganj

Proposal for establishment of 6 MT per hour Modern Rice Mill and 1000 MT Warehouse at Madhomath, Kuchaikot, Gopalganj in partnership.

0.9892 21 11.08.10 04.02.11

332 M/S Vindhya Steel Pvt. Ltd, Patna

Proposal for establishment of 6000 MT per year capacity Clod Briquetted Iron production unit at Giddha Growth Centre, Ara.

5.00 100 11.08.10

333 M/S Netaji Subhas Institute of Technology, Patna.

Proposal for establishment of new syllabus for M.Tech., M.B.A. in Netaji Subhas Institute of Technology, Amhara, Bihta, Patna.

25.12 11.08.10

334 M/S Lakhan Aqua Enterprises Pvt. Ltd, Patna.

Proposal for establishment of 120 lac liters per year capacity Packaged Drinking Water unit at Khusrupur, Patna.

0.8546 15 11.08.10 04.02.11

335 M/S Aqua Honey Industries, Darbhanga.

Proposal for establishment of 72 lac liters per year capacity Packaged Drinking Water unit at Donar Industrial Area, Dharbhanga in partnership.

0.6896 24 11.08.10

336 M/S Bihar Ma Durga Agro Industries Pvt. Ltd, Patna.

Proposal for establishment of 8 MT per hour Modern Rice Mill unit at Pandaul Industrial Area, Madhubani.

5.00 30 11.08.10

337 M/S AES Patliputra Energy Pvt. Ltd, Gurgaon, Haryana. (Approved proposal of M/S AES India Pvt. Ltd on 11.08.10 for establishment of 1320 MW (2x660 MW) coal based Thermal Power Plant at Jagdishpur, Bhagalpur has been approved in the name of M/S AES Patliputra Energy Pvt. Ltd in SIPB meeting held on 25.02.11)

Proposal for establishment of 1320 MW (2x660 MW) coal based Thermal Power Plant at Jagdishpur, Bhagalpur.

8120.00 300 11.08.10 (Consent in-principle) 25.02.11

338 M/S Champaran Agri Park Pvt. Ltd, Kolkata.

Proposal for establishment of Food Park at Bairia, Motihari.

132.14 1140 11.08.10

339 M/S Cruinne Edulac Consultancy Services Pvt. Ltd, Patna.

Proposal for establishment of Kautilya International Business School in Bihta Industrial Mega Park, Patna.

130.60 290 11.08.10 (Consent with condition)

340 M/S Sona Biscuits Ltd, Kolkata

Proposal for establishment of 15000 MT per year capacity Biscuit production unit at E.P.I.P., Hajipur.

26.51 219 13.08.10 05.09.12

341 M/S PI Systems Pvt. Ltd, Patna.

Proposal for establishment of Information Technology unit at Patliputra.

1.02 12 13.08.10

Report-3

33

342 M/S S.K. Gupta Rice Mill, Banka.

Proposal for establishment of 3 MT pre hour Rice Mill, 500 MT Warehouse, Husk Based Gasifier D.G. Set at Rajbandh, Dhoraiya, Banka in partnership.

0.73 5 13.08.10

343 M/S Sai Sachidanand Agrotech Pvt. Ltd, Jamshedpur.

Proposal for establishment of 3 MT per hour Rice Mill at Khera, Darbhanga.

2.71 20 13.08.10

344 M/S Sushila Food Product, Gaya.

Proposal for establishment of 900 MT per year capacity Vermicelli, Chowmien, Gold Finger and Fryums industry at Bhagwanpur, Baiju Bigaha, Gaya in partnership.

1.04 15 13.08.10

345 M/S Aarcee Foods, Aurangabad.

Proposal for establishment of 300 MT per year capacity Spices Grinding, Spice Blending and Packaging unit at Industrial Area, Aurangabad in proprietorship.

0.7569 25 13.08.10

346 M/S Mcore Foods Pvt. Ltd, Purnea.

Proposal for establishment of 3000 MT per year capacity Rice Mill, 4000 MT per year capacity Colour Sorting, Grading and Packing and 950 MT per year capacity Grinding and packing unit at Growth Centre, Moranga, Purnea.

1.60 50 13.08.10

347 M/S Blue Heavens Agro Industries Ltd, Patna.

Proposal for establishment of 1,20,000,00 Liters per year capacity Packaged Drinking Water at Chhotki Chanda, Koilwar, Bhojpur.

1.0087 17 13.08.10

348 M/S Alok Harsh Rice Mill Pvt. Ltd, Danapur, Patna.

Proposal for establishment of 4 MT per hour Modern Rice Mill at Giddha Industrial Area, Koilwar, Ara.

2.0970 42 13.08.10

349 M/S Tirupati Sugars Ltd, West Champaran.

Proposal for modernisation and capacity expansion from 2500 TCD to 5000 TCD in the existing Sugar Mill at Bagaha, West Champaran.

144.90 451 13.08.10 (Consent in-principle)

24.03.11

350 M/S Narayani Packaging Pvt. Ltd, Patna City, Patna. (Amending the proposal approved on 13.08.10 for 2400 MT per year capacity corrugated Boxes production unit at E.P.I.P., Hajipur, approval has been given for 9000 MT per year capacity instead of 2400 MT per year capacity Corrugated Boxes production unit at E.P.I.P., Hajipur in SIPB meeting held on 23.02.12.).

Proposal for establishment of 9000 MT per year capacity Corrugated Boxes production unit at E.P.I.P., Hajipur.

7.1483 40 13.08.10 23.02.12

351 M/S Prince Masala Company, Muzaffarpur.

Proposal for establishment of 450 MT per year capacity Spices and Spice Blends Manufacturing and Packaging unit at Muzaffarpur in proprietorship.

0.1249 25 13.08.10

352 M/S Skand Agri Power Pvt. Ltd, Patna.

Proposal for establishment of Biomass Based Power Plant of 7.5 MW each at Dehri, Rohtas and Industrial Area, Kahalgaon, Bhagalpur.

92.63 60 27.08.10

353 M/S Avant Garde Re-Energy Ltd, Kolkata.

Proposal for establishment of 10 MW Solar PV Power Plant unit at

160.00 31 27.08.10

Report-3

34

Bhojpur/Saran/Bhabhua.

354 M/S Pransukhka Cold Storage Pvt. Ltd, Purnea.

Proposal for establishment of 6000 MT Modern Multi Products Cold Storage unit under R.A.B.C. at Gulab Bagh, Purnea.

6.73 138 27.08.10

355 M/S Krishna Rice & Polisher Mills, Kaimur.

Proposal for Modernisation after establishment of 3 MT per hour capacity Modern Rice Mill in proprietorship in place of existing 1 MT per hour capacity Rice Mill at Bhopatpur, Mohania, Kaimur.

1.15 20 27.08.10 19.04.12

356 M/S Minakshi Rural Agri Business Pvt. Ltd, Patna.

Proposal for establishment of 10,000 MT Modern Multi Purpose Cold Storage at Chandpur, Baligaon, Patepur, Vaishali.

9.56 40 27.08.10 20.02.11

357 M/S Vijay Laxmi Dal Mill, Purnea.

Proposal for establishment of 1 MT per hour Dal Mill unit in proprietorship at Industrial Growth Centre, Purnea.

97.38 16 27.08.10

358 M/S Prasad Refrigeration and Agro Industries Pvt. Ltd, East Champaran.

Proposal for establishment of 2500 TCD (expandable up to 5000 TCD) Sugar Mill and 5 MW Co-generation Plant at Sataha, Nauadih, Paharpur, East Champaran.

129.33 205 27.08.10

359 M/S Jhunjhunwala Oil Mills Ltd, Varanasi.

Proposal for establishment of 8 MT per hour capacity Rice Mill at Bangra, Kudra, Kaimur, Bhabhua.

19.00 125 27.08.10 04.02.11

360 M/S Bluestar Cement Ltd, Varanasi.

Proposal for production of 3,00,000 MT per year capacity Portland Pozzolana Cement unit at Karamnasha, Kaimur, Bhabhua.

27.75 42 27.08.10

361 M/S Ripuraj Agro Pvt. Ltd, Raxaul, East Champaran.

Proposal for establishment of 04 MT per hour Modern Rice Mill and 1000 MT Warehouse unit at Amodei, Ramgadhwa, East Champaran.

2.20 19 27.08.10 10.04.11

362 M/S Mangal Deep Rice Mill Pvt. Ltd, Motihari, East Champaran.

Proposal for establishment of 3 MT per hour capacity Rice Mill, 1000 MT Warehouse at Ekdari, Chaura Dano, East Champaran.

1.3782 44 27.08.10 11.07.11

363 M/S Lumbini Beverages Pvt. Ltd, Hajipur.

Proposal for capacity expansion from 39971250 Liters per year capacity to 67971250 Liters per year capacity and Modernisation in the existing unit of manufacturing of PET Bottle, Aerated Water and Juice Based Drinks at E.P.I.P, Hajipur.

31.89 220 27.08.10 07.10.11

364 M/S Shree Tel Fab Industries Pvt. Ltd, Hajipur.

Proposal for capacity expansion from 5000 MT per year capacity to 10,616 MT per year capacity in the existing unit of P.V.C. Pipe and P.V.C. Filter at Industrial Area, Vaishali, Hajipur.

1.35 53 27.08.10

365 M/S Orange Powergen Pvt. Ltd, New Delhi. (Earlier, in the meeting of SIPB held on 29.11.10 consent was given for establishment of Biomass based Power Plant of 7.5 MW in Rohtas district, 7.5 MW in Nalanda district, 10 MW in Vaishali district, 7.5 MW in Aurangabad district and 10 MW in Begusarai district in the name of

Proposal for establishment of Biomass based Power Plant of 10 MW in Rohtas district in the name of new SPV company M/S Rohtas Biomass Pvt. Ltd., 10 MW in Nalanda district in the name of new SPV company M/S Nalanda Biomass Pvt. Ltd., 10 MW in Vaishali district in the name of new SPV company M/S Vaishali Biomass Pvt. Ltd., 10 MW in

225.00 125 29.11.10 (Consent with condition) 28.09.11

Report-3

35

Green Horsepower Pvt. Ltd. Again on request of the company, consent has been given on 28.09.11 for change of name of holding company from M/S Green Horsepower Pvt. Ltd to M/S Orange Powergen Pvt. Ltd and also for formation of five new SPV company as follows:- (1) Consent has been given for 10 MW Biomass based Power Plant in place of 7.5 MW in the name of new SPV company M/S Rohtas Biomass Pvt. Ltd. in Rohtas district. (2) Consent has been given for 10 MW in place of 7.5 MW Biomass based Power Plant in the name of new SPV company M/S Nalanda Biomass Pvt. Ltd. in Nalanda district. (3) Consent has been given for 10 MW Biomass based Power Plant in the name of new SPV company M/S Vaishali Biomass Pvt. Ltd. in Vaishali district. (4) Consent has been given for 10 MW Biomass based Power Plant in the name of new SPV company M/S Aurangabad Biomass Pvt. Ltd. in Aurangabad district. (5) Consent has been given for 10 MW Biomass based Power Plant in the name of new SPV company M/S Begusarai Biomass Pvt. Ltd. in Begusarai district.)

Aurangabad district in the name of new SPV company M/S Aurangabad Biomass Pvt. Ltd and 10 MW in Begusarai district in the name of new SPV company M/S Begusarai Biomass Pvt. Ltd.

366 M/S Raunak Trade & Agencies Pvt. Ltd, Farbisganj, Araria.

Proposal for production of 600 MT per year capacity PVC Rigid Pipe, 567.54 MT per year capacity Ice-Cream Cone, Wafer Biscuit and 6000 MT per year capacity Laundry and Toilet Soap at Industrial Area, Farbisganj, Araria.

7.9576 141 29.11.10

367 M/S Godrej Agrovet Ltd, Mumbai.

Proposal for production of 84000 MT per year capacity of Cattle and Poultry Feed at EPIP, Hajipur, Vaishali.

17.05 220 29.11.10

368 M/S Om Shree Gramodyog Food Process Co-operative Society Ltd, Patna.

Proposal for establishment of 24 MT per hour capacity Modern Rice Mill at Danapur Biscuit Factory Road, Nasriganj, Patna.

7.54 101 29.11.10

369 M/S MMMJ Food Processing Industry, Madhubani.

Proposal for establishment of 12 MT per year capacity Makhana Processing unit in proprietorship at Mahtoregoth, Mahadeomath, Madhubani.

0.20 16 29.11.10

370 M/S Bihar Spices & Foods, Muzaffarpur.

Proposal for establishment of 40 MT per year capacity Spice Processing and Packaging unit in proprietorship at Bela Industrial Area, Muzaffarpur.

0.25 8 29.11.10

371 M/S Devlok Agro and Beverages Pvt. Ltd, Patna.

Proposal for establishment of 96 Lac Liters per year capacity Packaged Drinking Water unit at Hajipur.

1.58 32 29.11.10

372 M/S Aroma Feeds Pvt. Ltd, Proposal for establishment of 12000 1.1937 22 29.11.10

Report-3

36

Muzaffarpur. MT per year capacity Cattle Feed unit at Kanti, Muzaffarpur.

373 M/S Kumar Sunil Enterprises Pvt. Ltd, Bettiah.

Proposal for establishment of 40 Lac Liters per year capacity Fruit based Beverage Juice, 120 Lac Liters per year capacity Beverage Packaged Drinking Water and 10 Lac Liters per year capacity Soda Water unit at Bettiah.

3.93 40 29.11.10

374 M/S Gauri Mangla Cold Storage Pvt. Ltd, Kaimur, Bhabhua.

Proposal for establishment of 6000 MT Cold Storage at Mukhrao, Kuchila, Kaimur, Bhabhua.

3.60 13 29.11.10 16.08.11

375 M/S Saumya Industries, Darbhanga.

Proposal for establishment of 45 Lac Liters per year capacity Packaged Drinking Water/Mineral Water unit in proprietorship at Bela Industrial Area, Darbhanga.

1.0028 25 29.11.10

376 M/S Mishti Raj Foods Pvt. Ltd, Muzaffarpur.

Proposal for establishment of 2600 Kilo Liter per year capacity Packaged Drinking Water unit at Industrial Area, Bela, Muzaffarpur.

1.3227 19 29.11.10

377 M/S Elegance Power and Infrastructure Pvt. Ltd, Patna.

Proposal for establishment of 05 MW Biomass based Power Plant at Pandaul Industrial Area, Madhubani.

20.00 10 29.11.10

378 M/S Elegance Power and Infrastructure Pvt. Ltd, Patna.

Proposal for production of 60 Lac CFL Bulb and LED Lights at Giddha Industrial Area, Ara.

08.00 48 29.11.10

379 M/S Star Flour Mills Pvt. Ltd, Patna.

Proposal for establishment of 150 MT per day capacity Flour Mill at Pandaul Industrial Area, Madhubani.

9.3375 72 29.11.10 17.09.11

380 M/S Samras Products Pvt. Ltd, Sitamarhi

Proposal for establishment of 37 Thousand Liters per day capacity Edible Oil Packing unit at Industrial Area, Sitamarhi.

4.35 10 29.11.10 25.04.12

381 M/S Agro Industries, Muzaffarpur.

Proposal for establishment of 55,200 MT per year capacity Poultry Feed unit in proprietorship at Industrial Estate, Bela, Muzaffarpur.

7.0727 123 29.11.10 28.06.12

382 M/S Vina Paras Modern Rice Mill Pvt. Ltd, Kaimur, Bhabhua.

Proposal for establishment of 12 MT per hour capacity Modern Rice Mill unit at Bhabhua, Kaimur.

14.2378 83 29.11.10 18.07.11

383 M/S Gangotri Holy Products Pvt. Ltd, Muzaffarpur.

Proposal for establishment of 72 Thousand MT per year capacity Cattle Feed unit at Industrial Estate, Bela, Muzaffarpur.

5.9690 41 29.11.10

384 M/S Ambey Rice Mill, Bettiah. Proposal for establishment of 3 MT per hour capacity Modern Rice Mill unit in proprietorship at Industrial Area, Kumarbagh, Bettiah.

0.8725 30 29.11.10

385 M/S Chanakya Foods India Pvt. Ltd, Patna.

Proposal for establishment of 9000 MT per year capacity Turmeric & Ginger Processing unit, Ginger Garlic Paste Manufacturing unit, Spice Grinding and Packing unit, 10 Thousand MT capacity of Multi Purpose Cold Storage and 6000 MT capacity Modified Packing of Fresh Fruits and Vegetable unit at Khokshaha, Bibhutipur, Dist.-Samastipur.

8.45 60 29.11.10 10.04.12

386 M/S Sri Dewanjee Rice Mill Pvt. Ltd, Rohtas.

Proposal for establishment of 4 MT per hour capacity Modern Rice Mill at Nokha, Rohtas.

1.4697 20 29.11.10

387 M/S Bhojpur High Tech Agro Products Pvt. Ltd,

Proposal for establishment of 05 MT per hour capacity Modern Rice Mill,

1.2155 30 29.11.10

Report-3

37

Ara. 1000 MT capacity Warehouse and 200 KW Gasifier unit at Sakhua, Udwantnagar, Ara.

388

M/S Shirdi Foods Pvt. Ltd, Muzaffarpur.

Proposal for establishment of 1650 MT per year capacity Sugar Candy Manufacturing and Packing unit at Bela Industrial Estate, Muzaffarpur.

1.1965 17 29.11.10

05.02.12

389 M/S Nutan Bhabya Rural Agro Solution Pvt. Ltd, Patna.

Proposal for establishment of 3000 MT Warehouse, 01 MT per hour Multi Grading Line and Packing unit under R.A.B.C at Industrial Area, Fatuha, Patna.

1.0057 20 29.11.10 (Consent with condition)

01.02.13

390 M/S Green Earth Fertilizer Pvt. Ltd, Sitamarhi.

Proposal for establishment of 03 MT per hour capacity Modern Rice Mill unit at Industrial Area, Sitamarhi.

1.19 25 12.01.11 11.07.11

391 M/S Bhaskar Rice Mill Pvt. Ltd, Aurangabad.

Proposal for establishment of 04 MT per hour capacity Rice Mill, 1000 MT Warehouse and 125 KVA Gasifier at Biratpur, Malitola, Aurangabad.

1.5392 35 12.01.11

392 M/S Tathagata Bio Energy Pvt. Ltd, Gurgaon, Haryana. (On request of M/S Emergent Ventures India Pvt. Ltd for its Gaya project approval has been given to its new subsidiary company namely M/S Tathagata Bio Energy Pvt. Ltd for establishment of 12 MW Biomass based Power Plant at Vill-Churi, Dist.-Gaya in SIPB meeting held on 12.01.11)

Proposal for establishment of 12 MW Biomass based Power Plant at Churi, Dist.- Gaya.

52.00 50 12.01.11

393 M/S Jira Devi Cold Storage Pvt. Ltd, Patna.

Proposal for establishment of 6000 MT capacity Cold Storage at Balipakar, Paliganj, Patna.

4.6121 40 12.01.11 (Consent with condition)

11.07.11

394 M/S Anubhav Agro Processing Pvt. Ltd, Patna.

Proposal for establishment of 500 MT per year capacity Fruit and Vegetable Processing unit at Baghikariho, Supaul.

0.5117 15 12.01.11

395 M/S KKK Biomass Power Pvt. Ltd, Faridabad, Haryana.

Proposal for establishment of 02 MW Biomass based Power Plant at Industrial Area, Purnea.

11.00 50 12.01.11 (Consent with condition)

396 M/S Satyam Agrofood Industries Pvt. Ltd, West Bengal.

Proposal for establishment of 02 MT per hour capacity Rice Mill at Bulachak, Kalyanpur, East Champaran.

3.5933 59 12.01.11 10.04.11

397 M/S M.B. Tiles & Constructions Pvt. Ltd, Bhubneshwar.

Proposal for establishment of 22,50,000 number Pavers, Designers and Wall Tiles production unit at Industrial Growth Centre, Purnea.

1.2516 31 12.01.11

398 M/S Swastik Refinery Pvt. Ltd, Kolkata.

Proposal for establishment of 31000 MT per year capacity Oil and Banaspati (Hydrogenated) and Vegetable Oil and Fats(other than Hydrogenated) production unit at Kahalgaon Industrial Area, Bhagalpur.

30.00 114 12.01.11

399 M/S Krishna & Fula Industries, Bettiah, West Champaran.

Proposal for establishment of 15,000 MT per year capacity Poultry Feed/Cattle Feed unit at Kumarbagh, Bettiah in Partnership.

0.8477 26 12.01.11

400 M/S Anand Feeds Pvt. Ltd, Proposal for establishment of 15,000 1.5424 60 12.01.11 10.04.11

Report-3

38

Patna. MT per year capacity Poultry Feed unit at Industrial Area, Fatuha, Patna.

401 M/S Plant Insecticides Industries, Patna.

Proposal for establishment of 1200 MT per year capacity Insecticides and Pesticides production unit at Industrial Area, Fatuha, Patna in partnership.

1.5355 31 12.01.11

402 M/S Maruti Nandan PU Foams Pvt. Ltd, Patna.

Proposal for establishment of 300 MT per year capacity PU Foam (Polyurethane Foam) production unit at Industrial Area, Fatuha, Patna.

1.4797 25 12.01.11

403 M/S Jaikrishna Steel Pvt. Ltd, Rajendra Nagar, Patna.

Proposal for establishment of 22,500 MT per year capacity Rolling Mill at Industrial Area, Fatuha, Patna.

5.00 60 12.01.11

404 M/S Mahadeva Feeds Industries, Raxual, East Champaran.

Proposal for establishment of 3600 MT per year capacity Poultry Feed unit at Industrial Area, Raxaul in proprietorship.

1.1448 21 12.01.11

405 M/S Khushi Polypack Pvt. Ltd, Muzaffarpur.

Proposal for establishment of 672 MT per year capacity Disposable Glasses and Cup unit at Industrial Area, Muzaffarpur.

3.1372 44 12.01.11

406 M/S Maa Shyama Rice Mills, Darbhanga.

Proposal for establishment of 01 MT per hour capacity Rice Mill unit at Industrial Area, Bela, Darbhanga in proprietorship.

0.508 10 12.01.11

407 M/S M.B. Organics Pvt. Ltd, Purnea.

Proposal for establishment of 2400 MT per year capacity Soya Bari and Finger Strip Bari production unit at Industrial Area, Purnea.

0.9628 30 12.01.11 (Consent with condition)

408 M/S Supermax Foods Pvt. Ltd, Dwarka, New Delhi.

Proposal for establishment of 2.34 MT per year capacity Fruit and Vegetable Processing unit at Radhanagar, Mushari, Muzaffarpur.

0.297 20 12.01.11 08.01.12

409 M/S Shubham Consumer Product, Sabour, Bhagalpur.

:Proposal for establishment of 72 Lacs Liters per year capacity Drinking Mineral Water unit at Industrial Area, Barari, Sabour, Bhagalpur in proprietorship.

0.73 12 12.01.11 (Consent with condition)

410 M/S Mundeshwari Bio Energy Pvt. Ltd, Gurgaon, Haryana. (On request of M/S Emergent Ventures India Pvt. Ltd for its Kaimur project approval has been given to new SPV company namely M/S Mundeshwari Bio Energy Pvt. Ltd for establishment of 12 MW Biomass based Power Plant at Kaimur, Bhabhua in SIPB meeting held on 12.01.11)

Proposal for establishment of 12 MW Biomass Based Power Plant at Kaimur, Bhabhua.

52.00 40 12.01.11

411 M/S Hitachi Refrigeration, Begusarai.

Proposal for establishment of 48,000 Liters per year capacity Ice Cream unit at Industrial Area, Barauni, Begusarai in proprietorship.

0.6592 23 12.01.11

412 M/S Krrish Rice Mills Pvt. Ltd, Patna.

Proposal for establishment of 08 MT per hour capacity Modern Rice Mill at Industrial Area, Fatuha, Patna.

10.3269 50 12.01.11 11.07.11

413 M/S Casecade Power Ltd, Lakhisarai.

Proposal for establishment of 1320 (2x660) MW coal based Thermal Power Plant at Lakhisarai District in Bihar.

8343.50 400 25.02.11

414 M/S Bettiah Industries Pvt. Ltd,

Proposal for establishment of 08 MT per hour capacity Modern Rice Mill and 1.2 M

21.2081 178 25.02.11

Report-3

39

Kumarbagh, Bettiah. W Captive Power Plant at Kumarbagh Industrial Area, Chanpatiya, West Champaran.

415 M/S Lama Bear Organic Extract Ltd, Kaimur, Bhabhua

Proposal for establishment of 55.33 MT per year capacity Spice Oils and Oleoresin unit at Mathura, Durgawati, Kaimur, Bhabhua.

16.1535 25 25.02.11 16.08.11

416 M/S Deepak Vegpro(P) Ltd., Bhabhua. (Cancelling the earlier proposal approved on 25.02.11 for establishment of 18,000 MT per year capacity Mustard Oil, 24,000 MT per year capacity RBD Palm Oil, 6000 MT per year capacity Soya Refined Oil unit at Durgawati, Kaimur, Bhabhua, approval has been given for expansion/diversification of 24000 MT per year capacity Banaspati Ghee, 30000 MT per year capacity RBD Palm/Palmolien Oil and 8400 MT per year capacity Soya Refined Oil in the existing unit of 30000 MT per year capacity Banaspati Ghee at Durgawati, Kaimur, Bhabhua in SIPB meeting held on 23.02.12.).

Proposal for expansion/diversification of 24000 MT per year capacity Banaspati Ghee, 30000 MT per year capacity RBD Palm/Palmolien Oil and 8400 MT per year capacity Soya Refined Oil in the existing unit of 30000 MT per year capacity Banaspati Ghee at Durgawati, Kaimur, Bhabhua.

18.02 65 25.02.11 23.02.12

22.12.12

417 M/S The West Coast Paper Mills Ltd, Karnataka.

Proposal for establishment of one Lakh MT per year capacity Duplex Board unit in first phase at Dalmia Nagar, Rohtas.

350.00 500 25.02.11

418 M/S Era Infra Engineering Ltd, New Delhi.

Proposal for establishment of 2640(4x660) MW coal based Thermal Power Plant at Rajauli, Nawada and 1320(2x660) MW coal based Thermal Power Plant at Pirpainti, Bhagalpur.

14800.00 7374.00

700 350

25.02.11

419 M/S SCI India Ltd, Bhagalpur.

Proposal for establishment of grain based Alcohol Plant in place of Molasses based Distillery Plant and Modernization of existing effluent treatment Plant to get zero pollution in existing unit and generation of 1.6 MW Power from industrial waste.

30.2316 25.02.11

420 M/S Mahalaxmi Industries, Bettiah. (Correction has been made from proprietorship to partnership vide letter no. 1125 dated 23.07.12 )

Proposal for establishment of 3200 MT per year capacity Modern Rice Mill at Industrial Area, Bettiah in partnership.

0.3629 06 25.02.11 19.04.12

421 M/S Winsome International Ltd, Samastipur ( Unit of M/S Rameshwara Jute Mills)

Proposal for establishment of 35 MT per day capacity Jute Processing Unit, 40 MT per day capacity Corn Flakes manufacturing unit and establishment of Marketing Complex at Dharmpur, Samastipur.

160.00 155 25.02.11

422 M/S Dalmia Power Ltd, New Delhi. (Amending the proposal approved on 25.02.11 for establishment of 1320(2x660) MW coal based Thermal

Proposal for establishment of 2640 (4x660) MW Coal based Thermal Power Plant at Dona, Banka

14600.0000 1500 25.02.11 23.02.12

Report-3

40

Power Plant at Dona, Banka, approval has been given for establishment of 2640(4x660) MW coal based Thermal Power Plant at Dona, Banka in SIPB meeting held on 23.02.12.).

423 M/S Sravanthi Rohtas Energy Pvt. Ltd, New Delhi. (Earlier, in the SIPB's 95

th

meeting held on 25.02.11 consent was given in the name of M/S Sravanthi Infratech Pvt. Ltd, Gurgaon, Haryana for establishment of 450 MW gas based Power Plant at Dehri-On-Sone, Rohtas. Again on request of the company consent has been given for establishment 450 MW gas based Power Plant at Dehri-on-Sone, Rohtas. in the name of newly formed SPV company M/S Sravanthi Rohtas Energy Pvt. Ltd. New Delhi in SIPB meeting held on 28.09.11.)

Proposal for establishment of 450 MW gas based Power Plant at Dehri-On-Sone, Rohtas.

1620.00 90 25.02.11 28.09.11

424 M/S Adhish Enterprises Pvt. Ltd, Bettiah(West Champaran).

Proposal for establishment of 20 rooms Hotel and Motel at Ujjain Tola, Bettiah, West Champaran.

1.7752 07 25.02.11 18.07.11

425 M/S Ishwar Raj Beverages Pvt. Ltd, Patna.

Proposal for establishment of 120 Lac Crates capacity Soft Drinks and Packaged Drinking Water unit at Jethuli, Fatuha, Patna.

15.2854 88 25.02.11 11.09.11

426 M/S Patwari Steels Pvt. Ltd, Fatuha, Patna.

Proposal for establishment of 30,000 MT per year capacity Poultry Feed and Cattle Feed unit at Industrial Area, Fatuha, Patna.

6.1210 20 25.02.11 30.07.11

427 M/S T I Cycles of India (M/S Tube Investments of India Ltd.), Chennai, Tamil Nadu.

Proposal for establishment 20 Lac pieces per year capacity Cycle, Cycle Parts and Accessories manufacturing unit at E.P.I.P, Hajipur.

45.10 500 25.02.11

428 M/S Sanmati Bio Energy Pvt. Ltd, (Prom.- M/S Emergent Ventures India Pvt. Ltd), Gurgaon, Haryana (Approval was given in principle on 18.11.08 in SIPB meeting for establishment of 12 MW Biomass based Power Plant at Rohtas in the name of M/S Emergent Ventures India Pvt. Ltd. Again on company’s request amending the earlier approved proposal and approval has been given to the newly formed subsidiary company M/S Sanmati Bio Energy Pvt. Ltd for establishment of 12 MW Biomass based Power Plant at Songwa, Rohtas on 26.05.11)

Proposal for establishment of 12 MW Biomass based Power Plant at Songwa, Rohtas.

52.00 40 26.05.11

429 M/S National Plastic Proposal for production of 5100 MT 5.75 100 26.05.11

Report-3

41

Industries Ltd, Mumbai. per year capacity Plastic Furniture, Plastic Mat and other Plastic Products at Fatuha Industrial Area, Patna.

430 M/S Tota Rai Food Products, Patna.

Proposal for establishment of 4.5 MT per day capacity Flour Mill in proprietorship at Industrial Area, Fatuha, Patna

0.9754 26 26.05.11

431 M/S Vishwa Laghu Udyog, Muzaffarpur.

Proposal for establishment of 1.80 MTPA Spice and 1.50 MTPA Besan and Sattu unit in proprietorship at Bela Industrial Area, Muzaffarpur.

0.316 11 26.05.11

432 M/S Kesho Food and Beverage Pvt. Ltd, Patna

Proposal for production of 11,500 MT per year capacity Noodles, Sauce, Ketchup and Pickles at Parsa Bazar, Patna.

2.9445 60 26.05.11 05.02.12

433 M/S Harit Bio Energy Pvt. Ltd, (Prom.- M/S Emergent Ventures India Pvt. Ltd), Gurgaon, Haryana (Approval was given on 18.11.08 in SIPB meeting for establishment of 12 MW Biomass based Power Plant at Aurangabad in the name of M/S Emergent Ventures India Pvt. Ltd, again on request of the company approval has been given to newly formed subsidiary company M/S Harit Bio Energy Pvt. Ltd. for the production of 12 MW Biomass based Power Plant at Barwa, Aurangabad on 26.05.11.)

Proposal for establishment of 12 MW Biomass based Power Plant at Vill-Barwa, Aurangabad.

52.00 40 26.05.11

434 M/S Pristine Magadh Infrastructure Pvt. Ltd, New Delhi

Proposal for establishment of Rail Linked Logistic-cum- Industrial Park at Bihta, Patna.

48.26 100 26.05.11

435 M/S Anuj Dairy Pvt. Ltd, Patna

Proposal for production of 5475 MT per year capacity Milk Powder and 255.5 MT per year capacity Butter or 164.25 MT per year capacity Ghee at Industrial Area, Hajipur.

10.00 80 26.05.11 05.04.13

436 M/S Janardhan Ramjhari Enterprises Pvt. Ltd, Madhubani

Proposal for establishment of 18000 MT per year capacity Flour Mill at Pandaul Industrial Area, Madhubani.

1.6458 34 26.05.11 10.04.12

437 M/S Asra Agro Industries, Patna

Proposal for establishment of 7200 MT per year capacity Rice Polishing and Milling unit in proprietorship at Industrial Area, Fatuha, Patna.

2.3743 25 26.05.11

438 M/S Ranjan Foods Products, Darbhanga

Proposal for establishment of 72 MT per year capacity Spices manufacturing unit and 120 MT per year capacity Besan and Sattu production unit in proprietorship at Industrial Area, Donar, Darbhanga.

0.2735 10 26.05.11

439 M/S Avyn Enterprises Pvt. Ltd, Prunea

Proposal for establishment of 08 MT per hour Grain and Rice sorting and 03 MT per hour Rice Grading and 20,000 MT Dry Warehouse under R.A.B.C at Ghourdaur, Haveli, Purnea.

12.94 70 26.05.11

440 M/S Shyam Industries, Gaziabad

Proposal for establishment of 2400 MT per year capacity Washing Powder unit in proprietorship at Industrial Area, Fatuha, Patna.

1.2063 25 26.05.11

Report-3

42

441 M/S Vinayak Food Industries, Saharsa

Proposal for establishment of 1440 MT per year capacity Sattu, Besan, Atta production unit in proprietorship at Industrial Area, Saharsa.

0.6725 09 26.05.11

442 M/S Shree Ganpati Enterprises, Patna

Proposal for establishment of Offset Printing, Binding and Stitching unit in proprietorship at Industrial Area, Fatuha, Patna.

2.3541 36 26.05.11

443 M/S Jagdamba Bhawani Enterprises Pvt. Ltd, East Champaran.

Proposal for establishment of 03 MT per hour capacity Modern Rice Mill, two Warehouse of 3225 sq ft and 150 KVA Gasifier unit at Adapur, East Champaran.

1.5750 30 26.05.11 17.09.11

444 M/S Moser Baer Power and Infrastructures Ltd, New Delhi. (Earlier on 26.05.11 approval was given by SIPB for establishment of 1980 MW Coal based Thermal Power Plant at Morma, Lakhisarai. Again on company’s request, amending the above proposal consent has been given for change of place from Morma, Lakhisarai to Banka in SIPB meeting held on 18.09.12.)

Proposal for establishment of 1980 MW Coal based Thermal Power Plant at Banka.

11000.00 2000 26.05.11 18.09.12

445 M/S Kritika Rice Mill Pvt. Ltd, Samastipur

Proposal for establishment of 14400 MT per year capacity Modern Rice Mill and Warehouse at Basudeopur, Kalyanpur, Samastipur.

4.48 35 26.05.11 02.12.11

446 M/S Premier Cryogenics Ltd, Guwahati.

Proposal for establishment of Liquid Oxygen- 10800000 Cubic Meter per year capacity, Oxygen Gas- 2160000 Cubic Meter per year capacity, Liquid Nitrogen- 2880000 Cubic Meter per year capacity, Nitrogen Gas-720000 Cubic Meter per year capacity, Compressed Air-360000 Cubic Meter per year capacity at Fatuha, Patna.

27.00 50 26.05.11

447 M/S Ananya Agro Tech Pvt. Ltd, Patna

Proposal for establishment of 2.5 MT per hour Modern Rice Mill and 1000 MT Warehouse at Giddha Growth Centre, Ara(Bhojpur).

2.3275 60 26.05.11 16.08.12

448 M/S Bihar Distillers & Bottlers Pvt. Ltd., Chandigarh. (Earlier on 26.05.11 approval was given for establishment of 330 KLPD capacity of Distillery Plant for production of ENA, RS, IMFL, Country Liquor, Industrial Alcohol, Absolute Alcohol, DNS, Ethanol in the name of M/S Chandigarh Distillers and Bottlers Ltd. at Patna/Vaishali. Again on company's request, Cancelling the above proposal, approval has been given for establishment of 660 KLPD capacity of Distillery Plant for production of ENA, RS, IMFL, Country

Proposal for establishment of 660 KLPD capacity of Distillery Plant for production of ENA, RS, IMFL, Country Liquor, Industrial Alcohol, Absolute Alcohol at Bhojpur.

230.00 140 26.05.11 16.04.12

Report-3

43

Liquor, Industrial Alcohol, Absolute Alcohol in the name of newly formed SPV company M/S Bihar Distillers and Bottlers Pvt. Ltd. at Bhojpur in SIPB meeting held on 16.04.12.)

449 M/S Maa Mundeshwari Cycle Udyog Pvt. Ltd., Aurangabad. . (Earlier, in the SIPB's 96

th

meeting held on 26.05.11 consent was given for establishment of 30,000 nos. of Bicycle Assembling & Bicycle parts production unit at Aurangabad. Again on promoter’s request amending the above proposal consent has been given for establishment of Bicycle manufacturing and assembling unit for 1000 Bicycle per day capacity in SIPB held on 28.09.11.) (Cancelling the earlier proposal approved on 28.09.11 in the name of M/S Maa Mundeshwari Cycle Udyog for establishment of 1000 pieces per day capacity Bicycle manufacturing and assembling unit at Aurangabad, approval has been given for newly formed company M/S Maa Mundeshwari Cycle Udyog Pvt. Ltd for establishment of 1000 pieces per day capacity Bicycle manufacturing and assembling unit at Aurangabad in SIPB meeting held on 23.02.12.).

Proposal for establishment of 1000 pieces per day capacity Bicycle manufacturing and assembling unit at Aurangabad.

6.6870 77 26.05.11 28.09.11 23.02.12

450 M/S Maa Urmila Agro Pvt. Ltd, Rohtas

Proposal for establishment of 05 MT per hour Modern Rice Mill unit at Bikramganj, Rohtas.

4.2367 35 26.05.11 02.12.11

451 M/S United Breweries Ltd, Bangalore, Karnataka (U B Group)

Proposal for establishment of 10 lac Hecto Liter per year capacity Beer production unit at Kopakala, Naubatpur, Patna.

200.00 294 26.05.11

452 M/S Mahajan Rice Mills Pvt. Ltd, Patna.

Proposal for capacity expansion of existing Rice Mill from 02 MT per hour capacity to 07 MT per hour capacity and modernization at Nokha, Rohtas.

7.63 35 26.05.11 02.12.11

453 M/S Prasad Udyog, Purnea Proposal for establishment of 2400 MT per year capacity Dal Mill unit in proprietorship at Industrial Area, Maranga, Purnea.

1.5552 17 27.07.11

454 M/S Guptaji Brothers Rice Mills Pvt. Ltd, Rohtas.

Proposal for establishment of 12 MT per hour capacity Modern Rice Mill at Dalmia Nagar, Rohtas

14.2378 83 27.07.11 16.08.12

455 M/S Sri Hari Rice Mills Pvt. Ltd,

Proposal for establishment of 03 MT per hour capacity Modern Rice Mill at

1.5661 42 27.07.11

Report-3

44

Kaimur, Bhabhua. Dadava, Mohania, Kaimur, Bhabhua.

456 M/S Kudra Rice Mill Pvt. Ltd, Kaimur, Bhabhua.

Proposal for establishment of 19,200 MT per year capacity Modern Rice Mill and 150 KVA Gasifier unit at Kudra, Kaimur, Bhabhua.

1.8871 44 27.07.11

457 M/S Muzaffarpur Modern Rice Mill, New Delhi.

Proposal for establishment of 144 MT per day capacity Modern Rice Mill unit in partnership at Chajan, Harishnagar, Turki, Muzaffarpur.

2.1664 38 27.07.11 25.04.12

458 M/S Pack Care Industries, Patna.

Proposal for establishment of 1200 MT per year capacity Corrugated Paper and Boxes unit in proprietorship at Industrial Area, Fatuha, Patna.

1.2154 23 27.07.11

459 M/S Shree Hanumanjee Modern Rice Mill Pvt. Ltd, Sasaram.

Proposal for establishment of 10 MT per hour Modern Rice Mill unit at Godwar, Shivsagar, Sasaram, Dist.-Rohtas.

10.0288 150 27.07.11 18.12.11

460 M/S Narayan Poly Tube, Siwan.

Proposal for establishment of 360 MT per year capacity PVC Rigid Pipe production unit in partnership at Industrial Area, Fatuha, Patna.

2.0869 21 27.07.11

461 M/S Nandita Poultry Integrators Pvt. Ltd, Ranchi.

Proposal for 30,000 MT per year capacity expansion in the existing unit of 18,000 MT per year capacity of Poultry Feed and Cattle Feed at Industrial Area, Hajipur.

5.4853 21 27.07.11

462 M/S Hari Om Narar Rice Mill Pvt. Ltd, Madhubani.

Proposal for establishment of 03 MT per hour Modern Rice Mill, 5000 MT Warehouse and Gasifier unit at Kaluahi, Madhubani.

1.2585 20 27.07.11

463 M/S Vaishali Fresh Fruits and Vegetables Pvt. Ltd, Patna.

Proposal for capacity expansion from 2500 MT per year capacity to 7500 MT per year capacity in the existing unit of Fresh Fruits and Vegetable Processing at Industrial Area, Hajipur.

0.7517 28 27.07.11

464 M/S Responce Renewable Energy Ltd, Kolkata. (Earlier on 27.07.11 approval was given for establishment of Power Generation unit with the help of 25 MW Solar PV Modules at Madhubani, Buxar or Chapra. Again on company's request, amending above, approval has been given for establishment of the same proposal at Nawada in the name of M/S Responce Renewable Energy Ltd., Kolkata in SIPB meeting held on 26.03.12)

Proposal for establishment of Power Generation unit with the help of 25 MW Solar PV Modules at Nawada.

425.00 150 27.07.11 26.03.12

465 M/S Shree Shree Dwarikaji Agro Pvt. Ltd, Patna City, Patna.

Proposal for establishment of 60,000 MT per year capacity Soya Oil and Soya Nugget production unit at Nagla, Malsalami, Patna City.

25.80 157 27.07.11

466 M/S Pandoul Flour Mills Pvt. Ltd, Darbhanga.

Proposal for establishment of 59, 100 MT per year capacity Folur Mill unit at Industrial Area, Pandaul,

8.6761 40 27.07.11

Report-3

45

Madhubani.

467 M/S Jai Kisan Food Products Pvt. Ltd, Sasaram, Rohtas.

Proposal for establishment of 15,360 MT per year capacity Grain Sorting and Grading unit and 6000 MT Warehouse under R.A.B.C. at Chandwa, Rohtas.

4.2977 30 27.07.11

468 M/S Good Health Dairy Products Pvt. Ltd, Kolkata.

Proposal for establishment of 3,65,00000 Liters per year capacity Milk Chilling Plant at Industrial Area, Samastipur.

0.80 25 27.07.11

469 M/S Phular Cold Storage Pvt. Ltd, Vaishali.

Proposal for establishment of 11,000 MT Multipurpose Cold Storage, Multiproduct Grading Line and Agri Mall Warehouse under R.A.B.C. at Mansoorpur, Kanti, Muzaffarpur.

8.5450 40 27.07.11 30.09.11

470 M/S Unique Food Industries, Aurangabad.

Proposal for establishment of 05 MT per hour Rice Mill, 2000 MT Warehouse and 250 KVA Gasifier unit in proprietorship at Aurangabad Industrial Area, Aurangabad.

1.3862 35 27.07.11 16.02.12

471 M/S Om Shakti Sitaram Rice Mill Pvt. Ltd, Rohtas.

Proposal for establishment of 04 MT per hour Rice Mill unit and 4000 MT Warehouse at Ghausiankala, Bikramganj, Rohtas.

5.6961 44 27.07.11 27.02.12

472 M/S Maa Mundeshwari Agro Mills Pvt. Ltd, Aurangabad.

Proposal for establishment of 12000 MT per year capacity Roller Flour Mill unit at Industrial Area, Aurangabad.

3.7519 30 27.07.11

473 M/S Lal Kesra Rice Mill Pvt. Ltd, Sasaram, Rohtas.

Proposal for establishment of 14400 MT per year capacity Rice Mill unit and 3000 MT Warehouse at Karhgar, Rohtas.

4.4640 36 27.07.11

474 M/S Maa Bhagwati Kalyanpur Cold Storage Pvt. Ltd, Samastipur.

Proposal for establishment of 6000 MT Multipurpose Cold Storage under R.A.B.C at Kalyanpur, Bibhutipur, Samastipur.

8.5450 100 27.07.11 30.09.11

475 M/S Laxmi Narayan Enterprises Pvt. Ltd, Patna.

Proposal for establishment of 08 MT per hour Modern Rice Mill, 1000 MT Warehouse at Rani, Bhojpur.

9.1260 68 27.07.11 19.04.12

476 M/S Narmedeshwar Rice Mills Pvt. Ltd, Howrah, West Bengal.

Proposal for establishment of 08 MT per hour Modern Rice Mill unit and 4 Warehouse of 5000 Square Feet at Industrial Growth Centre, Aurangabad.

9.6290 60 27.07.11 08.01.12

477 M/S Ganesh Edibles LLP, Muzaffapur.

Proposal for establishment of 60,000 MT per year capacity Refined and Hydrogenated Oil production unit at Baijnathpur, Ahiyapur, Muzaffarpur.

26.63 150 27.07.11

478 M/S L V Commercial Pvt. Ltd, Patna.

Proposal for establishment of 49,500 MT per year capacity Roller Flour Mill at E.P.I.P, Hajipur.

11.1410 69 27.07.11

479 M/S Nalanda Biscuit Company Ltd, Patna.

Proposal for establishment of 75,000 MT per year capacity Flour Mill unit at E.P.I.P, Hajipur.

14.6753 40 27.07.11

480 M/S Sai Dairy, Purnea. Proposal for establishment of 8,64,000 Liters per year capacity Pasteurized Milk and Toned/Double Toned Milk and 74,520 Kg per year capacity Ghee and Milk Cream unit in proprietorship at Industrial Growth Centre, Purnea.

0.4790 18 27.07.11

481 M/S Meena Binay Nishant Proposal for establishment of 9000 9.3253 14 27.07.11 01.02.12

Report-3

46

Bhawani Cold Storage Pvt. Ltd. (M.B.N.B. Cold Storage Pvt. Ltd,), Patna.

MT capacity Cold Storage under R.A.B.C. at Teghra, Begusarai.

482 M/S Vaishali Enterprises and Cold Storage Pvt. Ltd, Patna.

Proposal for establishment of 11,000 MT Cold Storage unit under R.A.B.C. at Giddha Industrial Growth Centre, Ara, Bhojpur.

10.00 70 27.07.11 02.12.11

483 M/S Suman Grih Food Products Pvt. Ltd, Bhagalpur.

Proposal for establishment of 300 MT per year capacity production unit of different types of Papad at Sultanganj Bazar, Bhagalpur.

0.9441 15 27.07.11

484 M/S Claro Energy Pvt. Ltd, New Delhi.

Proposal for establishment of 2x5 MW Solar PV Power Project at Gopalganj and Khagaria.

160.00 500 27.07.11

485 M/S Bihar Milk Products Pvt. Ltd, Bhojpur.

Proposal for establishment of 4 Lakh Liter per day capacity Milk Processing unit at Industrial Area, Bihiya, Bhojpur.

21.35 77 27.07.11

486 M/S River Valley Flour Mills Pvt. Ltd, Hajipur, Vaishali.

Proposal for capacity expansion from 49,500 MT per year capacity to 75,000 MT per year capacity in the existing unit of Flour Mill at Industrial Area, Hajipur.

6.20 17 27.07.11 19.04.12

487 M/S Ganesh Laxmi Rice Mills Pvt. Ltd, Rajauli, Nawada.

Proposal for establishment of 1,20,000 MT per year capacity Rice Mill at Chautha, Nawada.

2.0203 24 27.07.11 26.04.13

488 M/S Buddha Packaging Industry, Patna. (Earlier, in the SIPB meeting held on 27.07.11 consent was given in the name of M/S Buddha Corrugated Industry for establishment of 120 MT per year capacity Corrugated Paper, Board and Boxes production unit in proprietorship at Industrial Area, Fatuha, Patna. Again on request of promoter consent has been given for establishment of 120 MT per year capacity Corrugated Paper, Board and Boxes production unit in proprietorship in the name of M/S Buddha Packaging Industry at Industrial Area, Fatuha, Patna.)

Proposal for establishment of 120 MT per year capacity Corrugated Paper, Board and Boxes production unit in proprietorship at Industrial Area, Fatuha, Patna.

1.00 23 27.07.11 28.09.11

489 M/S Girja Devi Polytechnic College(Promoter- M/S Suchit Singh Memorial Educational Trust), Patna.

Proposal for establishment of Polytechnic Institute in the name of Girja Devi Polytechnic College by the Trust at Bihiya, Bhojpur.

1.3593 52 27.07.11

490 M/S Shree Cement Ltd., New Delhi. (Cancelling the earlier proposal approved on 27.07.11 for establishment of

10 Lakh MT per year capacity Cement Plant and Captive Power Generation at Aurangabad, approval has been given for establishment of 10 Lakh MT capacity Cement Plant and 12 MW Biomass based Captive Power Plant at Aurangabad in SIPB meeting held on

Proposal for establishment of 20 Lakh MT per year capacity Cement Plant and 12 MW Biomass based Captive Power Plant unit at Aurangabad.

337.00 300 27.07.11 09.04.12 08.02.13

Report-3

47

09.04.12.) ( Approval has been given for establishment of 20 Lakh MT per year capacity Cement Plant and 12 MW Biomass based Captive Power Plant at Aurangabad in place of 10 MT per year capacity Cement Plant and 12 MW Biomass based Captive Power Generation Plant at Aurangabad in SIPB meeting held on 08.02.13.)

491 M/S Mithila Rice Mills Pvt. Ltd, Darbhanga.

Proposal for establishment of 06 MT per hour Modern Rice Mill, 2000 MT Warehouse and 400 KW Biomass Gasifier unit at Darbhanga.

4.3720 50 27.07.11

492 M/S B K Industries Ltd, Patna.

Proposal for establishment of 12000 MT Cold Storage and 6000 MT Warehouse under R.A.B.C. at Ilmas Nagar, Samastipur.

14.93 50 27.07.11 18.12.11

493 M/S Tirhut Industries Ltd, New Delhi.

Proposal for establishment of 5000 TCD capacity Integrated Sugar Mill, 60 KLPD Distillery Plant and 28 MW Co-generation Power Plant at Ryam, Keoti, Darbhanga.

313.40 526 27.07.11

494 M/S Mor Mukat Marketing Pvt. Ltd, New Delhi.

Proposal for establishment of 150 BPM capacity RTS Juice Plant unit at Nasriganj, Danapur, Patna.

7.2990 40 27.07.11 30.09.11

495 M/S Chaucer Capital, London.

Proposal for establishment of 20 MW Solar Power Project unit at Dobhi, Barachatti, Gaya.

328.50 125 27.07.11

496 M/S Om Shri Laxminarayan Education Foundation Ltd., Patna

Proposal for establishment of 120 lakh Litres per year capacity of Packaged Drinking Water, 10 Lakh Litres per year capacity of Soda Water and 40 Lakh Litres per year capacity of Fruit based Beverage unit at Industrial Area, Patliputra, Patna.

15.8000 100 28.09.11

497 M/S Om Sai Cold Storage Pvt. Ltd., Samastipur.

Proposal for establishment of 6000 MT per year capacity Multipurpose Cold Storage under R.A.B.C. at Lohagir, Ujiarpur, Samastipur.

7.1500

70 28.09.11

498 M/S Kundan Food Industries, Saharsa

Proposal for establishment of 1200 MT per year capacity of Dal Mill unit in proprietorship at Industrial Area, Saharsa.

0.7083 16 28.09.11

499 M/S Swadist Udyog, Bhagalpur.

Proposal for establishment of production unit of 804 MT per year capacity of Masala, Vermicelli and Papad in proprietorship at Industrial Area, Barari, Bhagalpur.

0.6656 23 28.09.11

500 M/S Mahabali Water Products, Biharsharif

Proposal for establishment of 7200 Kilo Litre per year capacity Packaged Drinking Water and Soda Water unit in Partnership at Sosarai, Nalanda.

1.6359 21 28.09.11

501 M/S Ma Shitla Onion Storage Pvt. Ltd., Nalanda.

Proposal for establishment of 4200 MT per year capacity Onion Storage unit at Noorsarai, Nalanda.

1.4756 14 28.09.11

502 M/S Rambriksha Food and Beverage Pvt. Ltd., Patna

Proposal for establishment of 97.92 Lakh Litres per year capacity of Packaged Drinking Water and Soft

0.6830 66 28.09.11

Report-3

48

Drink unit at Pahari, Transport Nagar, Patna.

503 M/S Om Sai Ram Beverages and Food Pvt. Ltd, Patna.

Proposal for establishment of production unit of 72 Lakh Litres per year capacity Packaged Drinking Water at Nandlal Chapra, Patna.

0.7000 21 28.09.11

504 M/S Aahar Feeds and Agro Products Pvt. Ltd., Patna

Proposal for establishment of 33,000 MT per year capacity Poultry Feed unit at Fatuha Industrial Area, Fatuha, Patna.

10.3375 21 28.09.11

505 M/S Anjali Rice Mill Pvt. Ltd, Patna.

Proposal for expansion of 3 MT per hour capacity of Modern Rice Mill, 14000 Sq. Ft. Warehouse and Gasifier unit in the existing unit at Sadallichak, Patna.

2.6624 49 28.09.11

506 M/S Kalpana Foods Pvt. Ltd, Patna.

Proposal for establishment of 3 MT per hour capacity Modern Rice Mill and 1000 MT Warehouse unit at Fatuha Industrial Area, Fatuha.

2.2548 12 28.09.11

507 M/S Sunasi Food and Beverages Pvt. Ltd., Patna.

Proposal for establishment of production unit of 150 MT per year capacity Ethnic and Extruded Foods(Ready to eat Namkin Extruded Snacks, Packaged Food, Spices & Paste of Spices, Indian Sweets, Potato Chips and Wafer) at Industrial Growth Centre, Giddha.

1.6200 14 28.09.11

508 M/S Bhilwara Energy Ltd, Noida, Uttar Pradesh.

Proposal for establishment of 10 MW Solar Energy Power Generation Plant at Muzaffarpur.

169.0000 20 28.09.11 (Consent with condition)

509 M/S Carlsberg India Pvt. Ltd., Gurgaon,Haryana. (Cancelling the earlier proposal approved on 28.09.11 for establishment of 10 Lakh Hecto Litre per year capacity of Beer production unit at Koilwar, Bhojpur, approval has been given for establishment of 10 Lakh Hecto Litre per year capacity of Beer production unit at Bikram, Patna in SIPB meeting held on 11.06.12.)

Proposal for establishment of 10 Lakh Hecto Litre per year capacity of Beer production unit at Bikram, Patna.

140.00 600 28.09.11 11.06.12

510 M/S Thakur Modern Cold Storage Pvt. Ltd., East Champaran.

Proposal for establishment of 6000 MT per year capacity Cold Storage unit under R.A.B.C at Mathiyavrit, Chhouradano, East Champaran.

5.8021 40 28.09.11

511 M/S Recon, Patna. Proposal for establishment of I.T. Park and Five-Star Hotel-cum-Shopping Complex in proprietorship at Industrial Area, Patliputra, Patna.

190.0300 161 28.09.11 (Consent with condition)

512 M/S A 2 Z Powercom Ltd., Gurgaon, Haryana.

Proposal for establishment of 05-05 MT per hour capacity of Modern Rice Mill and 02-02 MW Biomass Based Power Plant in each district of Buxar and East Champaran.

37.8400 150 28.09.11

513 M/S Mansi Bijlee & Rice Mills Pvt. Ltd., Gurgaon, Haryana.

Proposal for establishment of 05-05 MT per hour capacity of Modern Rice Mill and 02-02 MW Biomass Based Power Plant in each district of Bhojpur, Rohtas and Kaimur.

56.7600 225 28.09.11

Report-3

49

514 M/S IPL Sugar & Allied Industries Ltd., New Delhi.

Proposal for modernization and capacity expansion from 1219 TCD capacity to 3500 TCD capacity, 46 KLPD Distillery Plant and 20 MW Co-generation Plant in the existing Sugar Mill at Motipur, Muzaffarpur.

257.0000 413 28.09.11

515 M/S Usher Agro Ltd., Buxar Proposal for additional capacity expansion of 100,000 MT per year and 01 MW Rice Husk based Power Plant in the existing Rice Mill of 47,600 MT per year capacity.

48.8800 100 28.09.11

516 M/S Ganesh Steel Impex Ltd., Muzaffarpur.

Proposal for establishment of 21,900 MT per year capacity of Aluminum Profiles and Lead Ingot unit at Thuhwa, Kuddhani, Muzaffarpur.

8.9000 150 28.09.11

517 M/S Shivam Vincom Pvt. Ltd., Muzaffarpur.

Proposal for establishment of production unit of 42,000 MT per year capacity of Lead Ingot and Lead Plate at Baidhyanathpur, Muzaffarpur.

12.0000 150 28.09.11

518 M/S Sri Sri Cold Storage, Purnea.

Proposal for capacity expansion from 7000 MT to 14,000 MT in the existing Multipurpose Cold Storage unit in proprietorship at Industrial Growth Centre, Maranga, Purnea.

9.9500 60 28.09.11

519 M/S Tulsyan Cans & Cardboards Pvt. Ltd., Kolkata.

Proposal for establishment of production unit of 15000 MT per year capacity of Automatic Corrugated Cardboard Boxes at Bihiya, Bhojpur.

11.5500 260 28.09.11

520 M/S Sitamarhi Flour Mill Pvt. Ltd., Sitamarhi.

Proposal for establishment of 125 MT per day capacity of Roller Flour Mill unit at Banchauri, Dumra, Sitamarhi.

9.4800 45 28.09.11

521 M/S Alok Harsh Rice Mill Pvt. Ltd., Danapur, Patna.

Proposal for establishment of 70 MT per day capacity of Modern Para Boiled Rice Mill unit at Giddha Industrial Growth Centre, Ara.

7.3600 42 28.09.11 27.02.12

522 M/S Achyut Shanti Foods Pvt. Ltd., Patna.

Proposal for establishment of production unit of 18,000 MT per year capacity of Besan, Sattu and Daliya at Industrial Area, Fatuha, Patna.

1.1100 25 28.09.11

523 M/S Mrigendra Cold Storage Pvt. Ltd., Begusarai.

Proposal for establishment of 50,000 Litre per day capacity of Milk Processing unit at Rajwara, Begusarai.

2.8730 30 28.09.11

524 M/S Danapur Flour Mills Ltd., Patna.

Proposal for modernization and capacity expansion from 33,000 MT per year capacity to 58,500 MT per year capacity in the existing Flour Mill at Nasriganj, Danapur, Patna.

5.0875 17 28.09.11 07.06.12

525 M/S Shri Sai Nath Enterprises, Muzaffarpur.

Proposal for establishment of production unit of 480 MT per year capacity of Vermicelli, Noodles, Disco Chips and Finger Chips in proprietorship at Industrial Area, Bela, Muzaffarpur.

0.8235 9 28.09.11

526 M/S Vaishali Flour Mills, Patna

Proposal for capacity expansion from 100 MT per day to 172 MT per day capacity in the existing unit of Flour Mill in proprietorship at Nasriganj, Digha, Patna.

1.8825 40 28.09.11

527 M/S Mithla Flour Mills, Proposal for capacity expansion from 3.1207 40 28.09.11

Report-3

50

Darbhanga. 200 MT per day to 310 MT per day capacity in the existing Roller Flour Mill unit in proprietorship at Gangwara, Makhwara, Darbhanga.

(Consent with condition)

528 M/S Jass Agri Products Pvt. Ltd., New Delhi.

Proposal for establishment of 5 MT per hour capacity Modern Rice Mill and 4000 MT Warehouse unit at Jhumma, Rooni Saidpur, Sitamarhi.

4.9941 50 28.09.11

529 M/S Arihant Naturecrop Pvt. Ltd., Vadodara, Gujarat.

Proposal for establishment of 2500 MT/Kilo Litre per year capacity of Bio Fertilizer and Bio Pesticides unit at Lodipur, Rajgir, Nalanda.

2.3649 46 28.09.11

530 M/S Bhagwati Cylinders Pvt. Ltd., Samastipur.

Proposal for establishment of manufacturing unit of 3,00,000 piece per year capacity of LPG Cylinder at Rajajan, Mohiuddin Nagar, Samastipur.

8.3400 108 28.09.11 28.06.12

531 M/S Sona Sati Organics Pvt. Ltd., Patna. (Cancelling the earlier proposal approved on 28.09.11 for establishment of 60 KLPD Molasses Based Distillery and 1.5 MW Co-generation Power Plant at Rajpatti Kothi, Rajpatti, Gopalganj,approval has been given for establishment of 60

KLPD Distillery Plant (Grain/Molasses Based) and 3 MW Co-generation Power Plant at Rajpatti Kothi, Rajpatti, Gopalganj in SIPB meeting held on 13.08.12.)

Proposal for establishment of 60 KLPD Distillery Plant(Grain/Molasses Based) and 3 MW Co-generation Power Plant at Rajpatti Kothi, Rajpatti, Gopalganj.

86.37

49

28.09.11 13.08.12

18.12.11

532 M/S Rameshwaram Rice Mills Pvt. Ltd., Patna.

Proposal for establishment of 4 MT per hour capacity of Boiled Rice Mill unit at Kaimur, Bhabhua.

7.6236 40 28.09.11 23.08.12

533 M/s Harinagar Sugar Mills Ltd., Harinagar, W. Champaran.

Proposal for diversification of existing 13,500 Kilo Litre per year capacity of Distillery Plant for Extra Neutral Alcohol production unit of its same capacity at Harinagar, Bagha, East Champaran.

12.0000 87 28.09.11

534 M/S Pawapuri Rice Mills, Nalanda.

Proposal for establishment of 4 MT per hour capacity of Para Boiled Rice Mill unit in proprietorship at Chausa, Pokharpur, Pawapuri, Nalanda.

4.7887 31 28.09.11

535 M/S ABG Cement Ltd., Mumbai.

Proposal for establishment of 1.5 MTPA (Million Ton per year) Cement Grinding Plant and 12 MW Coal Based Captive Power Plant at Pandarak, Barh.

548.6460 230 28.09.11

536 M/S Keshav Madhav Agro Enterprises Pvt. Ltd., Patna.

Proposal for establishment of 150 MT per day capacity of Roller Flour Mill unit at Fatehpur, Nawada.

10.4975 50 28.09.11 16.02.12

537 M/S Takshila Seas & Resorts Pvt. Ltd., Mumbai.

Proposal for establishment of Water Park and Pool Restaurant unit at Sona Gopalpur, Patna.

6.3000 102 28.09.11 (Consent with condition)

538 M/S Avon Cycles Ltd., Ludhiana, Punjab.

Proposal for establishment of production unit of 03 Lakh piece per year capacity of Bicycle and Cycle Parts at Patna or Vaishali.

8.0000 500 28.09.11

Report-3

51

539 M/S Standard Properties Pvt. Ltd., Patna.

Proposal for establishment of Hotel and Business Centre at Kidwaipuri, Patna.

32.5000 35 28.09.11 (Consent with condition)

540 M/S Mithla Dairy Pvt. Ltd., Mumbai.

Proposal for establishment of 35,000 Litres per day capacity of Milk Processing unit at Industrial Area, Pandaul, Madhubani.

5.0100 50 28.09.11

541 M/S Modern Amrit Feed Company Pvt. Ltd., Samastipur.

Proposal for establishment of 12,000 MT per year capacity Poultry Feed and Cattle Feed unit at Mohanpur, Samastipur.

3.9277 31 28.09.11 15.12.12

542 M/S Jai Shree Balaji Fats & Oils Pvt. Ltd., Kolkata.

Proposal for establishment of 250 TPD Edible Oil Refinery, 100 TDP Banaspati Oil Plant, 50 TPD Rice Bran Oil/ Sun Flower Oil / Solvent Oil and 01 MW Captive Power Plant at Akbar Malahi, Lalganj, Vaishali.

65.5000 130 28.09.11

543 M/S JRN Enterprises Pvt. Ltd., New Delhi.

Proposal for establishment of 360 MT per year capacity of Pickles manufacturing unit and 16,500 MT per year capacity of Besan manufacturing unit at Industrial Area, Fatuha, Patna.

1.7754 24 28.09.11 27.02.12

544 M/S Ultra Tech Cement Ltd., Mumbai.

Proposal for establishment of 02 Million Ton per year capacity of Cement Grinding unit at Fatuha, Patna.

326.1000 246 28.09.11 14.02.12

545 M/S Dumraon Textiles Ltd., Dumraon, Buxar.

Proposal for capacity expansion from 17,160 spindles per year to 17992 spindles per year capacity in the existing unit of cotton yarn at Dumraon.

6.7782 707 28.09.11

546 M/S Skill Foods Pvt. Ltd., Patna.

Proposal for establishment of 1000 MT Multi Purpose Cold Storage and 5000 MT Dry Warehouse unit at Siljori, Chandan, Banka.

1.1700 30 28.09.11

547 M/S Nandan Biomatrix Ltd., Hyderabad.

Proposal for establishment of production unit of 45,000 MT per year capacity of Crude Jatropha oil under Public Private Panchayat Partnership Model at Jhajaha and Jamui.

200.0000 4576 28.09.11 (Consent with condition)

548 M/S Amar Roller Flour Mills Pvt. Ltd., Chapra.

Proposal for establishment of 100 MT per day capacity of Flour Mill unit at Chapra(Saran).

5.1700 39 28.09.11 01.02.13

549 M/S R.K. Poultry Feed Industries, Hajipur(Vaishali). (Earlier on 28.09.11 approval was given for capacity expansion from 6,000 MT per year capacity to 30,000 MT per year capacity in the existing Poultry Feed unit in partnership at Industrial Area, Hajipur in the name of M/S R.K. Feed Industries. Again request for adding the word 'Poultry' in the company's name, approval has been given for capacity expansion from 6,000 MT per year capacity to 30,000 MT per year capacity in the

Proposal for capacity expansion from 6,000 MT per year capacity to 30,000 MT per year capacity in the existing Poultry Feed unit in partnership at Industrial Area, Hajipur.

2.6365 21 28.09.11 23.02.12

Report-3

52

existing Poultry Feed unit in partnership at Industrial Area, Hajipur in the name of M/S R.K. Poultry Feed Industries in SIPB held on 23.02.12.)

550 M/S Tirupati Commodities Pvt. Ltd., Kolkata.

Proposal for establishment of 4870 MT per year capacity of Jute goods unit at Purnea.

9.6008 660 28.09.11

551 M/S R.M. Industries, Ara, Bhojpur.

Proposal for establishment of manufacturing unit of 600 MT per year capacity of Brass utensils in proprietorship at Industrial Area, Growth Centre, Giddha.

1.3293 29 28.09.11

552 M/S Parmeshwari Aqua Pvt. Ltd., Madhubani.

Proposal for establishment of 96 Lakh Litres per year capacity of Packaged Juice, Areated Fruit Drinks, Drinking Water and Soda Water unit at Industrial Area, Pandaul, Madhubani.

1.0381 21 28.09.11

553 M/S Unibell Polyplast Pvt. Ltd., Patna.

Proposal for establishment of production unit of 2220 MT per year capacity of PVC Rigid Pipe and Fittings at Bhaghakole, Bikram, Patna.

3.0315 25 28.09.11 31.10.12

554 M/S LV Enterprises Pvt. Ltd., Patna.

Proposal for establishment of 250 MT per day capacity of Roller Flour Mill unit at Hajipur(Vaishali).

15.3000 69 28.09.11 05.09.12

555 M/S Laxmivinayak Ventures Pvt. Ltd., Patna.

Proposal for capacity expansion from 01 Lakh MT per year capacity to 1.5 Lakh MT per year capacity in the existing unit of Detergent powder at Hajipur(Vaishali).

16.9400 150 28.09.11

556 M/S Krrish Engicon Pvt. Ltd., Patna.

Proposal for establishment of Multiplex-cum-Shopping Mall and Hotel at Sudarshan Path, Patna City, Patna.

37.4800 72 28.09.11 (Consent with condition)

557 M/S Gandiv Builder and Engineers Pvt. Ltd., Patna.

Proposal for establishment of Hotel in the name of Hotel Gargee Grand in two stages at Exhibition Road, Patna.

14.1000 49 28.09.11 (Consent with condition)

10.04.12

558 M/S Rohit Surfactants Pvt. Ltd., Kanpur

Proposal for establishment of 2,50,000 MT per year capacity Detergent Cake, Detergent powder, LABSA (Linear Alkaline Benzene Sulforation, Acid Slurry for Soaps) unit at Fatuha Industrial Area, Patna.

79.0000 77 28.09.11

559 M/S Pearl Processing Industries, Patna.

Proposal for establishment of 4125 MT per year capacity of Sugar Cube and Candy production unit in partnership at Mohali Road, Karmalichak, Agamkuan, Patna City, Patna.

2.3800 16 28.09.11 01.02.13

560 M/S Meridian Budha Hotels Pvt. Ltd., Patna.

Proposal for establishment of Five Star Hotel of 90 Rooms at Budh Marg, Patna.

8.8100 160 28.09.11 (Consent with condition)

561 M/S Hotel Windsor, Patna (Unit of M/S Patliputra Fashion Pvt. Ltd.)

Proposal for capacity expansion from 51 Rooms to 79 Rooms in the existing Hotel at Umang Palace, Exhibition Road, Patna.

3.5500 71 28.09.11 (Consent with condition)

562 M/S Yatri Bihar Hospitality Pvt. Ltd., Patna.

Proposal for establishment of Three Star Hotel -cum- Resort of 80 Rooms at Bodh Gaya.

34.3000 135 28.09.11 (Consent with condition)

563 M/S La'-Elixier Ashiyan Proposal for establishment of 3-4 Star Hotel, 18.8200 400 28.09.11

Report-3

53

Estate Developers Pvt. Ltd., Bhagalpur.

Marketing Complex and Amusement Park at Barari Industrial Area, Bhagalpur.

(Consent with condition)

564 M/S Muskan Event Management and Caterers Pvt. Ltd., Patna.

Proposal for establishment of Resort-cum-Restaurant in the name of Ghar Aangan at Industrial Estate Road, Patliputra Colony, Patna.

1.2500 53 28.09.11 (Consent with condition)

565 M/S MV Hotels & Projects Pvt. Ltd., Patna.

Proposal for establishment of Five Star Hotel of 124 Rooms at Patliputra, Patna.

83.0900 70 28.09.11 (Consent with condition)

566 M/S Schanti Partners LLC, New York.

Proposal for establishment of 10 MW Solar Energy generation unit at Kaimur.

153.0000 210 28.09.11

567 M/S Adani Power Ltd., Ahmedabad, Gujarat.

Proposal for establishment of 1320 MW coal based Super Critical Thermal Power Plant at Lakhisarai.

7707.5700 600 28.09.11 (Consent with condition)

568 M/S Moser Baer Clean Energy Ltd., New Delhi.

Proposal for establishment of Solar Power Project of 25 MW at Chakia, East Champaran, 20 MW at Ramnagar, East Champaran and 40 MW at Katoria, Banka.

1318.0000 4200 28.09.11 (Consent with condition)

569 M/S Hemkund Industries, Patna.

Proposal for establishment of production unit of 63.24 Lakh pieces per year capacity of Fly Ash Bricks, Pavers Block and Tiles in proprietorship at Industrial Area, Fatuha, Patna.

1.6927 23 28.09.11

570 M/S Khushi Beverages Pvt. Ltd., Gaya.

Proposal for establishment of 80 Lakh Liters per year capacity Fruit based Beverage and Carbonated Fruit Juice unit at Manpur, Buniyadganj, Gaya

2.3878 33 23.02.12 28.06.12

571 M/S Aditya Food Products, Patna.

Proposal for establishment of 420 MT per year capacity Noodles production unit in proprietorship at Kurji, Patna.

0.5000 21 23.02.12

572 M/S Shankar Agrotech and Food Pvt. Ltd., Patna.

Proposal for establishment of 18,000 MT per year capacity Roller Flour Mill unit at Chhitnama, Maner, Patna.

2.5200 21 23.02.12 16.10.12

573 M/S Shahabad Agro Pvt. Ltd., Bhojpur, Ara.

Proposal for establishment of 04 MT per hour capacity Modern Para Boiled Rice Mill, 2000 MT Warehouse and Captive Power Plant at Bihta, Bhojpur.

6.7095 50 23.02.12 07.06.12

574 M/S Mahavir Grih Udyog, Patna.

Proposal for establishment of 180 MT per year capacity Vermicelli production unit in partnership at New Harnichak (Tej Pratap Nagar), Anisabad, Patna.

4.6800 6 23.02.12

575 M/S G.M. Exim Pvt. Ltd., Patna.

Proposal for establishment of 2400 MT per year capacity Packing Materials and Corrugated Boxes production unit at Hajipur (Vaishali).

4.5200 51 23.02.12

576 M/S Hotel U.S. Residency, Aurangabad.

Proposal for establishment of 29 Rooms Hotel Project in proprietorship at Aurangabad.

4.6300 40 23.02.12

577 M/S Wave Distilleries and Breweries Ltd., New Delhi.

Proposal for establishment of 5 Lakh HLPA(Hecto Litre per day) capacity Beer production unit in Bihar.

121.1400 375 23.02.12 (Consent with condition)

Report-3

54

578 M/S A FP Manufacturing Company Pvt. Ltd, New Delhi.

Proposal for establishment of production unit of 20,000 MT per year capacity Namkin, Bakery and Extruded Snacks in unit-1 and unit-2 at E.P.I. P., Hajipur.

33.0430 142 23.02.12 05.05.13

579 M/S Rathi Feeds India Pvt. Ltd., Haryana.

Proposal for establishment of 36000 MT per year capacity Poultry Feed production unit at Maranga, Purnea.

10.3050 50 23.02.12

580 M/S Skylark Feeds Pvt. Ltd., Haryana.

Proposal for establishment of 200 MT per day capacity Poultry Feed Production unit at Maranga Industrial Area, Purnea

4.4282 22 23.02.12

581 M/S Inspiring Agro Ltd., West Bengal

Proposal for establishment of 100800 Eggs per day capacity Fully Automation Commercial Egg production unit and 80 KWH Power Plant at Mahuabari, Jiradei, Siwan.

17.9506 50 23.02.12

582 M/S Reshma Cold Storage Pvt. Ltd., Vaishali.

Proposal for establishment of 9000 MT Multi Purpose Cold Storage unit under R.A.B.C. at Fulwaria, Mahua, Vaishali.

10.6225 50 23.02.12 16.08.12

583 M/S Om Corrugated Pack Pvt. Ltd., Patna. (Earlier on 23.02.12 approval was given by SIPB for establishment of 7200 MT per year capacity Corrugated Card Board Boxes production unit at E.P.I.P., Hajipur. Again on company’s request, amending the above proposal consent has been given for change of place from E.P.I.P., Hajipur to Mauza-Painal, Bihta, Patna in SIPB meeting held on 18.09.12.)

Proposal for establishment of 7200 MT per year capacity Corrugated Card Board Boxes production unit at Mauza-Painal, Bihta, Patna.

8.5576 36 23.02.12 18.09.12

584 M/S Protech Feed Pvt. Ltd., Patna

Proposal for establishment of 2000 MT capacity Frozen Cold Storage at E.P.I.P., Hajipur.

17.4900 15 23.02.12

585 M/S Protech Feed Pvt. Ltd., Patna

Proposal for establishment of 6000 MT capacity Cold Storage under R.A.B.C., at E.P.I.P., Hajipur.

10.4800 15 23.02.12

586 M/S Panna Agrotech Coldstorage Pvt. Ltd., Purnea.

Proposal for establishment of 5000 MT capacity Multi Purpose Cold Storage under R.A.B.C. at Gangoli, K. Nagar, Purnea.

2.1848 20 23.02.12 16.08.12

587 M/S Veer Hanuman Foods Processing Pvt. Ltd., Kaimur, Bihar.

Proposal for establishment of 05-05 MT per hour capacity Modern Para Boiled Rice Mill and Modern Raw Rice Mill unit at Raziabandh, Mohania, Kaimur.

6.1300 30 23.02.12 27.07.12

588 M/S Millenium Infrastructures Pvt. Ltd., Delhi.

Proposal for establishment of 10 MW Waste to Energy Project(Build Own, Operate Basis) at Patna.

80.0000 50 23.02.12 (Consent with condition)

589 M/S MPOT Energy Ventures Pvt. Ltd., Hyderabad.

Proposal for establishment of 500 MW Natural Gas Based Combined Cycle Duel Fuel Thermal Power Plant at Rupauli, Ujiarpur, Samastipur.

2250.0000 240 23.02.12

590 M/S Balmukund Cement & Roofings Ltd., Patna.

Proposal for establishment of 3,00,000 MT per year capacity

81.0000 147 23.02.12

Report-3

55

Asbestos Fibres Cement Corrugated Flat Sheets and Accessories Plant in two phases at Industrial Develpoment Area, Kahalgaon, Bhagalpur.

591 M/S Jagat Bakers, Katihar. Proposal for establishment of 90,000 Loaves, 1,06,200 Buns, 90,000 Rusk and 468600 Biscuits/Cookies per year capacity Bakery Plant in proprietorship at Industrial Area, Katihar.

0.4680 31 23.02.12

592 M/S Sri Avantika Contractors (I) Ltd., Hyderabad.

Proposal for establishment of 05 MW Grid Connected Solar PV Power Project at Rampurwa, Gaunaha, West Champaran.

76.9000 31 23.02.12

593 M/S Hotel Galaxy Intercontinental Pvt. Ltd., Bodh Gaya, Gaya.

Proposal for establishment of Hotel and Restaurant at Mastipur, Bodh Gaya, Gaya

4.9392 43 23.02.12 28.06.12

594 M/S Okpet Bicycles Pvt. Ltd., Patna.

Proposal for establishment of 2,40,000 pieces of Bicycles production unit at Simri, Darbhanga.

4.5203 73 23.02.12 28.06.12

595 M/S Mother's Society for Education and Child Development, Delhi.

Proposal for establishment of Engineering and Management Institute by the Society at Industrial Park, Bihta.

13.7300 82 23.02.12

596 M/S Iceland Beverages Pvt. Ltd., Patna. (Cancelling the earlier proposal approved on 23.02.12 for establishment of 30 Lacs Litres per year capacity IMFL production unit at Industrial Area, Giddha, Bhojpur, approval has been given for establishment of 30 Lacs Litres per year capacity IMFL Plant at Bisanpura, Mahua, Vaishali in SIPB meeting held on 11.06.12.)

Proposal for establishment of 30 Lacs Litres per year capacity IMFL Plant at Bisanpura, Mahua, Vaishali.

2.5226 37 23.02.12 11.06.12

597 M/S Kisan Seva Cold Storage Pvt. Ltd., Samastipur.

Proposal for establishment of 10000 MT Multi Purpose Cold Storage Unit under R.A.B.C. at Lakhnipur, Maheshpatti, Samastipur.

8.3000 50 23.02.12 16.08.12

598 M/S Vidyadaan, New Delhi. Proposal for establishment of Engineering College in the name of ''Vidyadaan Institute of Technology and Management'' at Ariaon, Dumraon, Buxar.

11.3295 165 23.02.12

599 M/S Kisan Hi-Tech Agro Foods Pvt. Ltd, Kochas, Rohtas.

Proposal for establishment of 05-05 MT per hour capacity Modern Para Boiled Rice Mill and Raw Rice Mill unit at Kochs, Rohtas.

10.2800 40 23.02.12

600 M/S Hari Narayan Singh Agro Pvt. Ltd., Rohtas.

Proposal for establishment of 08-08 MT per hour capacity Modern Para Boiled Rice Mill and Raw Rice Mill unit at Tilain, Nokha, Rohtas.

8.0057 38 23.02.12

601 M/S Nutrilite Agro Products Pvt. Ltd., Delhi.

Proposal for establishment of 08 MT per hour capacity Modern Para Boiled Rice Mill and 1 MW Husk Based Power Generation unit at Sinduria, Barun, Aurangabad.

18.5500 160 23.02.12

Report-3

56

602 M/S ATN Agro Products Ltd., Patna.

Proposal for establishment of 2000 MW Thermal Power Plant at Babura, Bhojpur.

11500.0000 160 23.02.12

603 M/S Prabhakar Organics & Agro Foods Pvt. Ltd., Patna.

Proposal for establishment of 903 MT per year capacity Sauce, Jam, Jelly, Pickles, Custard, Baking Powder and Food Grade Colour Production unit at Industrial Area, Fatuha, Patna.

1.3165 57 23.02.12

604 M/S Sri Laxmi Food Industries, Raxaul, East Champaran.

Proposal for establishment of 16,200 MT per year capacity Dal Mill unit in Partnership at Raxaul.

1.2338 47 23.02.12

605 M/S Triveni Smelters Pvt. Ltd., Patna.

Proposal for 39,600 MT per year capacity Mild Steel Ingot unit at Raipura, Fatuha, Patna.

9.6932 36 23.02.12

606 M/S Pinax Steel Industries Pvt. Ltd., Patna.

Proposal for expansion/diversification of 18,000 MT per year capacity Electroforged Grating in the existing Rerolling Mill unit of 15,000 MT per year capacity at Devkuli, Bihta.

7.7200 36 23.02.12

607 M/S Vindhyawasini Agro Tech Pvt. Ltd., Patna.

Proposal for establishment of 15,000 MT per year capacity Poultry Feed unit at Chhapiya, Baniyapur, Saran.

1.3824 36 23.02.12

608 M/S Gupta and Sons Traders Pvt. Ltd., Araria

Proposal for establishment of 5,300 MT capacity Multi Purpose Cold Storage at Industrial Area, Forbesganj, Araria.

3.4830 49 23.02.12

609 M/S Vindhyawasini Rice Mill, Samastipur.

Proposal for establishment of 2 MT per hour capacity Rice Mill unit in proprietorship at Bargaon, Hasanpur, Samastipur.

0.9550 11 23.02.12

610 M/S Baba Baidhnath Agro Cold Storage Pvt. Ltd., Vaishali.

Proposal for establishment of 10,000 MT capacity Multi Purpose Cold Storage under R.A.B.C. at Vaishali.

9.9312 50 23.02.12 07.06.12

611 M/S Takshak Engineering Pvt. Ltd., Patna.

Proposal for establishment of 600 MT per year capacity PVC Rigid Pipe and Pipe Fittings production unit at Industrial Growth Centre, Giddha, Bhojpur.

2.6009 21 23.02.12

612 M/S Shakshi Industries, Bhagalpur.

Proposal for establishment of 900 MT per year capacity Noodles and Vermicelli production unit in Proprietorship at Bhagalpur.

0.4013 20 23.02.12

613 M/S Sharda Duro Plastics Pvt. Ltd., Patna.

Proposal for establishment of 511000 pieces per year capacity Moulded Plastic Furniture unit at Hajipur Industrial Area, Vaishali.

5.1606 34 23.02.12

614 M/S Piyush and Associates Pvt. Ltd., Patna.

Proposal for establishment of 22,500 MT per year capacity Rerolling Mill unit at Mahuli Road, Patna City, Patna.

5.0000 24 23.02.12

615 M/S Sanwara Pet Industies, Patna.

Proposal for establishment of 480 MT per year capacity Pet Preform and Plastic Goods production unit in proprietorship at Simli Murarpur, Kotia, Malsalami, Patna City, Patna.

1.3562 6 23.02.12

616 M/S Mani Cold Storage Pvt. Ltd., Samastipur.

Proposal for establishment of 15000 MT capacity Multi Purpose Cold Storage under R.A.B.C. at Nigopur, Saraisa, Sakra, Muzaffarpur.

16.5012 50 23.02.12 23.08.12

617 M/S Shashibhushan Cold Proposal for establishment of 9000 10.1412 50 23.02.12 07.06.12

Report-3

57

Storage pvt. Ltd., Chhapra. MT Cold Storage unit under R.A.B.C. at Bhakura Bhitti, Sahabuddin, Chhapra.

618 M/S Laheji Freezing House, Siwan.

Proposal for establishment of 6000 MT capacity Multi Purpose Cold Storage unit under R.A.B.C. at Laheji, Siwan.

9.6412 85 23.02.12

619 M/S Symbiosis Electronics Pvt. Ltd., Patna.

Proposal for establishment of 1,50,000 Hecto Litre per year capacity Beer Plant at Amjhour, Old PPCL, Dehri-on-Sone, Rohtas.

63.6425 82 23.02.12

620 M/S Jai Prakash Hotels and Resorts Pvt. Ltd., Gaya.

Proposal for establishment of 49 Rooms Hotel at Rajgir.

7.5220 30 23.02.12

621 M/S Shiva Laboratories Pvt. Ltd., Patna.

Proposal for establishment of 3000 MT per year capacity Ethyl Acetate unit at Shakin-Kharuara, Harnaut, Nalanda.

2.5740 46 23.02.12 28.06.12

622 M/S Keshiha Services Enterprises pvt. Ltd., Bettiah.

Proposal for establishment of 20000 MT Modern Dry Warehouse under R.A.B.C. at Fursatpur, Motihari.

12.6302 165 23.02.12 16.08.12

623 M/S Hestia & Hermes Realestate Pvt. Ltd., Kolkata.

Proposal for establishment of 10,000 MT Dry Warehouse under R.A.B.C. at Dalan, Katihar.

7.1830 30 23.02.12

624 M/S Malhotra Poly Plast, Patna.

Proposal for establishment of 1440 MT per year capacity PVC Pipe production unit in partnership at Industrial Area, Patliputra, Patna.

1.1195 24 23.02.12

625 M/S Madhuraj Enterpries Pvt. Ltd., Patna.

Proposal for establishment of 6000 MT Multi Purpose Cold Storage unit under R.A.B.C. at Mathbanwari, Chakia, East Champaran.

10.9812 50 23.02.12 16.08.12

626 M/S Ritnand Balved Education Foundation, New Delhi.

Proposal for establishment of University in the name of Amity University Bihar at Patna.

83.1800 23.02.12 (Consent in principle)

627 M/S Electronic Equipment Company Pvt. Ltd., Kolkata.

Proposal for establishment of 03 MW Grid connected Solar PV Power Project at Gaya/Buxar or Chhapra.

57.0000 50 23.02.12

628 M/S Jai Jawan Food Processing Pvt. Ltd., Bokaro.

Proposal for establishment of 03 MT per hour Para Boiled Rice Mill unit at Chowk Kharwan, Dulhin Bazar, Danapur, Patna.

3.3550 25 23.02.12

629 M/S Mithila Food Processing, Darbhanga.

Proposal for Capacity expansion and Modernization of the existing Sattu production unit from 2400 MT per year to 6000 MT per year in proprietorship at Laxmi Nagar, Darbhanga.

0.3000 5 23.02.12 (Consent with condition)

630 M/S Balaji Udyog, Rohtas. Proposal for establishment of 03 MT per hour Rice Mill unit in proprietorship at Industrial Area, Dehri, Rohtas.

1.0205 16 23.02.12 27.07.12

631 M/S Shri Sita Rice Mill, Buxar.

Proposal for capacity expansion of the existing Rice Mill from 2 MT per hour to 06 MT per hour in partnership at Mohanpurwa, Chausa, Buxar.

1.5984 40 23.02.12 28.06.12

632 M/S Aparna Cold Storage Pvt. Ltd., Samastipur.

Proposal for capacity expansion of the existing Cold Storage from 3250 MT to 6500 MT under R.A.B.C. at Patori, Samastipur.

3.2336 30 23.02.12 16.08.12

633 M/S Hariom Feeds Pvt. Ltd., Gopalganj.

Proposal for establishment of 30,000 MT per year capacity Cattle Feed

5.6288 37 23.02.12 28.06.12

Report-3

58

and Poultry Feed unit at Gopalganj Birtitola, Manjhagarh, Gopalganj.

634 M/S Shiv Shakti Industries Pvt. Ltd., Raxaul.

Proposal for establishment of 10 MT per hour Poultry Feed unit at Majharia, Ramgarhwa, East Champaran.

15.1777 70 23.02.12 17.07.12

635 M/S Hotel Rohit International, Rohtas.

Proposal for establishment of Hotel in partnership at G.T. Road, Sasaram.

1.5744 61 23.02.12

636 M/S Dina Metals Ltd., Patna. Proposal for capacity expansion of the existing unit of Mild Steel Ingot from 200 MT per day capacity to 350 MT per day capacity at Abdul Rahmanpur Road, Deedarganj, Patna City, Patna.

42.8400 200 23.02.12

637 M/S Gayan Buddha Regency Pvt. Ltd., Patna.

Proposal for establishment of 50 Rooms Hotel at Bodh Gaya, Gaya.

6.3976 30 23.02.12

638 M/S Sunayana Cold Storage Pvt. Ltd., Begusarai.

Proposal for establishment of 6000 MT Cold Storage unit under R.A.B.C. at Fatehpur, Begusarai.

4.0903 25 23.02.12 16.10.12

639 M/S Amrapali Biotech India Pvt. Ltd., Gaziabad(U.P.).

Proposal for establishment of 6000 MT per year capacity Fruit and Vegetable Processing and Canning unit at Maranga Industrial Area, Purnea.

17.0712 120 23.02.12

640 M/S Swastik Agro Industries(Promoter Company M/S Swastik Hotels and inns Pvt. Ltd.,), Vaishali.

Proposal for establishment of 05 MT per hour capacity Cattle Feed and Poultry Feed unit in the name of M/S Swastik Agro Industries at Industrial Area, Hajipur.

3.3021 47 23.02.12 28.06.12

641 M/S Jagadamba Bhawani Agro Pvt. Ltd., Raxaul (East Champaran)

Proposal for establishment of 150 MT per day capacity Roller Flour Mill unit at Raxaul, East Champarn.

9.3942 100 23.02.12

642 M/S Kumud Foods and Beverage Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 06 MT per hour Modern Rice Mill (Raw and Para Boiled) unit at Kanti, Muzaffarpur.

7.1075 60 23.02.12 01.12.12

643 M/S Celebrity Liquors Pvt. Ltd., Patna.

Proposal for establishment of 5 Lakh (expandable up to 10 Lakh) Hecto Litre per year capacity Beer production unit at Bhagwanpur, Vaishali.

135.1200 170 23.02.12

644 M/S Jagat Jagdamba Flour Pvt. Ltd., Hajipur(Vaishali).

Proposal for establishment of 300 MT per day capacity Roller Flour Mill unit at Kisanpura, Balukaram, Dist.-Vaishali.

12.0000 33 23.02.12 07.06.12

645 M/S Aasma Foods and Beverages Pvt. Ltd., Hajipur(Vaishali).

Proposal for establishment of 11442 MT per year capacity Milk Processing unit at E.P.I.P., Hajipur(Vaishali).

12.2162 107 23.02.12

646 M/S Minerva Power Corporation Ltd., Secundrabad (A.P.)

Proposal for establishment of 15 MW Biomass Based Power Plant at Gautholi, Barun, Aurangabad.

70.2200 52 23.02.12

647 M/S Pasupati Rice Mills Pvt. Ltd., Rohtas.

( Approval has also been given for establishment of 600 Kilowatt Captive Power Project with earlier approved proposal for establishment of 04 MT per hour capacity Boiled

Proposal for establishment of 04 MT per hour capacity Boiled Rice Mill

unit with 600 Kilowatt Captive Power Project at Majhiaon,

Paruhar, Darihat, Rohtas.

7.4500 43 23.02.12 28.11.12 &29.11.12

Report-3

59

Rice Mill unit at Majhiaon, Paruhar, Darihat, Rohtas in SIPB meeting held on 28.11.12 & 29.11.12)

648 M/S Stef Medical Care India Pvt. Ltd., New Delhi.

Proposal for establishment of 01 MT per hour capacity Fruit and Vegetables Processing unit at Industrial Area, Maranga, Purnea.

2.4561 23 23.02.12

649 M/S Saroj Ranjan Foods Pvt. Ltd., Kaimur, Bhabhua.

Proposal for establishment of 64 MT per day capacity Rice Mill unit at Salthua, Kaimur, Bhabhua.

6.9588 38 23.02.12

650 M/S Sampurnam Agro Foods Pvt. Ltd., Patna.

Proposal for establishment of 2400 MT per year capacity Cattle Feed unit at Industrial Area, Bihiya, Bhojpur.

1.4001 22 23.02.12

651 M/S Lakho Agriculture and Food Products Pvt. Ltd., Bhojpur.

Proposal for establishment of 04 MT per hour capacity Boiled Rice Mill unit at Raghunathpur, Brahampur, Buxar.

7.7850 42 23.02.12 28.06.12

652 M/S Unique Foods, Promoter- R.K. Agri Biz, LLP, Muzaffarpur

Proposal for capacity expansion of existing unit of Frozen / Aseptic Products, Ready to Drink and Processed Fruits from 4958 MT per year capacity to 9108 MT per year capacity at Rewa Road, Patahi, Muzaffarpur.

14.2506 70 23.02.12

653 M/S White Ocean Foods Pvt. Ltd., Patna Sadar, Patna.

Proposal for establishment of 120 Lakh Litre per year capacity Packaged Drinking Water at Jakariyapur, Zero Mile, Pahari, Patna.

1.0000 18 23.02.12

654 M/S Raushan Agro Pvt. Ltd., Nokha, Rohtas.

Proposal for establishment of 04 MT per hour capacity Boiled Modern Rice Mill unit at Kusumtola, Baraon, Nokha, Rohtas.

6.2793 38 23.02.12

655 M/S Urmila Rice Mill Pvt. Ltd., Patna.

Proposal for establishment of 04 MT per hour capacity Boiled Modern Rice Mill unit at Pararia, Dinara, Rohtas.

5.4720 40 23.02.12 03.08.12

656 M/S Radhika Rice Mills, Silao, Nalanda.

Proposal for establishment of 03 MT per hour capacity Modern Rice Mill in partnership at Nirpur, Silao, Nalanda.

0.7871 15 23.02.12

657 M/S Pragana Danwar Food Processor Pvt. Ltd., Patna.

Proposal for establishment of 04 MT per hour capacity Modern Rice Mill unit at Danwar, Rohtas.

5.8949 30 23.02.12 28.06.12

658 M/S Danara Agro and Packaging Pvt. Ltd., Patna.

Proposal for establishment of 06 MT per hour capacity Modern Rice Mill unit at Danara, Bikram, Patna.

3.7406 25 23.02.12 12.12.12

659 M/S Vaishali Thread Mills, Patna City, Patna.

Proposal for establishment of 100 MT per year capacity Sewing Thread production unit in partnership at Industrial Area, Donar, Darbhanga.

1.2670 18 23.02.12

660 M/S Jest Liquors Pvt. Ltd., Patna.

Proposal for establishment of 6000 MT capacity Cold Storage unit at Nasriganj, Danapur, Patna.

6.6908 8 23.02.12 05.09.12

661 M/S Jagrity Motors Pvt. Ltd., Patna.

Proposal for establishment of 1200 pieces per year capacity Three Wheeler and Components, Chassis of Three Wheeler, Gear Box and Differential Box production unit at Bhusaula, Phulwarisharif, Patna.

2.6907 27 23.02.12

Report-3

60

662 M/S Aneja Food Products India Pvt. Ltd., Patna.

Proposal for establishment of 05 Lakh Litre per day capacity Milk Powder, Pasteurized Milk, Butter, Ghee and Curd production unit at Parmanandpur, Lalganj, Vaishali.

17.2345 400 23.02.12

663 M/S Kamakhya Kaushlya Construction Pvt. Ltd., Sitamarhi.

Proposal for establishment of 25920 MT per year capacity Modern Rice Mill unit at Punauradham, Sitamarhi.

4.8467 30 23.02.12 30.08.12

664 M/S Ambey Mata Agro Industries Pvt. Ltd., Samastipur.

Proposal for establishment of 05 MT per hour capacity Modern Rice Mill unit at Dadhiya Belar, Karpurigram, Samastipur.

3.2468 22 23.02.12

665 M/S Bhusari Cold Storage Pvt. Ltd., Begusarai.

Proposal for establishment of 7200 MT Cold Storage unit under R.A.B.C. at Korjana, Cheria Bariyarpur, Begusarai.

5.3843 15 23.02.12 17.06.12

666 M/S Bhabishya Rice Mill Ltd., Howrah. ( Approval for change of place has been given in earlier approved proposal for establishment of 08 MT per hour capacity Para Boiled Modern Rice Mill unit at Kishanpura, Vaishali to Visheshwar Patli, Saraiya, Muzaffarpur in SIPB meeting held on 13.03.13.)

Proposal for establishment of 08 MT per hour capacity Para Boiled Modern Rice Mill unit at Visheshwar Patli, Saraiya, Muzaffarpur

29.4650 28 23.02.12 13.03.13

19.08.12

667 M/S N.V.S. Industries, Patna. Proposal for establishment of 70 pieces per year capacity Plant -Machinery and Equipment production unit for Dairy and Food Processing Industries in proprietorship at E.P.I.P., Hajipur (Vaishali).

0.9232 17 23.02.12

668 M/S Parasnath Engicon Pvt. Ltd., Patna.

Proposal for establishment of 120 Rooms Hotel at Digha Road, Kurji, Patna.

41.0400 119 23.02.12

669 M/S Shrawasthi Agrotech Pvt. Ltd., Lucknow.

Proposal for capacity expansion of existing unit of Cattle Feed from 45000 MT per year capacity to 90,000 MT per year capacity at Giddha Industrial Growth centre, Ara.

5.1886 45 23.02.12

670 M/S Trimurti Flour Mill Pvt. Ltd., Deedarganj, Patna City, Patna.

Proposal for establishment of 100 MT per day capacity Roller and Chakki Flour Mill unit at Deedarganj, Patna City, Patna.

5.5505 30 23.02.12

671 M/S Naturals Dairy Pvt. Ltd., Patna.

Proposal for establishment of 75000 Litres per year capacity Milk Processing and Packaging unit at Patliputra Industrial Area, Patliputra.

5.0327 35 23.02.12

672 M/S Riga Sugar Company Ltd, Kolkata.

Proposal for capacity expansion from 5000 TCD to 6000 TCD in the existing Sugar Mill at Riga, Sitamarhi.

17.00 628 26.03.12

673 M/S Dumraon Agro Industries Pvt. Ltd., Buxar.

Proposal for establishment of 6 MT per hour Modern Rice Mill unit at Garatha Khurd, Buxar.

11.8609 86 26.03.12

674 M/S Dev Rice Mills Pvt. Ltd., Siwan.

Proposal for establishment of 04 MT per hour capacity Modern Rice Mill unit at Siswa Kala, Siwan.

4.6960 12 26.03.12

675 M/S Kolhaura Rice Mill Pvt. Ltd., Gaya.

Proposal for establishment of 48 MT per day capacity Modern Arwa Rice

2.6300 41 26.03.12

Report-3

61

Mill unit at Kolhaura, Bodh Gaya.

676 M/S Sai Plastic Industries, Patna.

Proposal for establishment of 40 Pieces per day capacity Plastic Overhead Tank production unit in Proprietorship at Gaganpura, Patna.

1.4235 47 26.03.12

677 M/S Chaman Rice Mill Pvt. Ltd., Shekhpura.

Proposal for establishment of 70 MT per day capacity Modern Rice Mill unit at Andauli , Chewara, Shekhpura.

2.5633 41 26.03.12

678 M/S Shushila Shankar Cold Storage Pvt. Ltd., Samastipur.

Proposal for establishment of 8000 MT Cold Storage unit under R.A.B.C. at Hasan Sarai, Belgaon, Patepur, Vaishali.

9.8683 15 26.03.12 28.06.12

679 M/S Bhagwati Metalloys Pvt. Ltd., Patna.

Proposal for establishment of 2700 MT per year capacity Lead Ingot and Plates production unit at Fatuha, Patna.

2.5205 34 26.03.12

680 M/S Srishyam Agro Pvt. Ltd., Patna.

Proposal for capacity expansion from 100 MT per day capacity to 150 MT per day capacity in the existing Poultry and Cattle Feed unit at Industrial Area, Hajipur.

0.7701 8 26.03.12

681 M/S Jamuna Nursing Home Pvt. Ltd., Vaishali.

Proposal for capacity Expansion and Modernization from 5200 MT to 7900 MT in the existing unit of Cold Storage under R.A.B.C at Jandaha, Vaishali.

7.3750 17 26.03.12

682 M/S Mums Mega Food Park Pvt. Ltd., Delhi.

Proposal for establishment of Food Park (Central Processing Centre, Common Facilities Cold Warehouse, Dry Warehouse, C.A. Storage, Sorting Grading Washing) unit at Nawa Nagar, Buxar.

75.3354 100 26.03.12

683 M/S Sakaldeep Cold Storage Pvt. Ltd., Bhojpur.

Proposal for establishment of 5000 MT Multi Purpose Cold Storage unit at Industrial Area, Bihiya.

4.1061 9 26.03.12

684 M/S Parwati Beverages and Foods Pvt. Ltd., Siwan.

Proposal for establishment of 9720000 Liters per year capacity Packaged Drinking Water unit at Orma Mukund, Mufasil Siwan.

1.1890 15 26.03.12

685 M/S Ashiana Heritage Hotels Pvt. Ltd., Patna.

Proposal for establishment of Hotel at Fraser Road, Patna.

3.1800 45 26.03.12

686 M/S Vaibhavaa Communication and Assets Pvt. Ltd., Patna.

Proposal for establishment of total 55 Safe Drinking Water(Piao) in 42 different places of Patna.

2.8875 55 26.03.12

687 M/S Magadh Institute of Higher Education, Patna

Proposal for establishment of B.Ed. Degree College at Dehri on Sone, Rohtas.

1.00 20 26.03.12 (Consent with condition)

688 M/S Ram Rati Devi Memorial Trust, Digha, Patna.

Proposal for establishment of B.Ed. Training College in the name of Magadh Teacher Training Centre at Industrial Area, Muzaffarpur.

1.00 20 26.03.12 (Consent with condition)

689 M/S Bhagwati Rice Mill, Katihar

Proposal for establishment of 3 MT per hour Para Boiled Modern Rice Mill unit at Bhorabari, Katihar.

4.2662 12 26.03.12

690 M/S National Plasto Products Pvt. Ltd., Kolkata.

Proposal for establishment of 4443 MT per year capacity Plastic Moulded Items production unit at E.P.I.P., Hajipur.

14.3890 41 26.03.12

691 M/S Sristhi Feeds Pvt. Ltd., Proposal for establishment of 9600 0.9939 35 09.04.12

Report-3

62

Patna MT per year capacity Cattle and Poultry Feed unit at Industrial Area, Growth Centre, Giddha.

692 M/S Maruti Meditech Pvt. Ltd., Patna.

Proposal for establishment of 1560 MT per year capacity Disposable Syringe and I.V. Set production unit at Mirchi Bhavania, Chowkkalan, Patna.

10.26 25 09.04.12

693 M/S Hargauri Recycling Plant Pvt. Ltd., Siliguri, Darjeeling, West Bengal.

Proposal for establishment of Recycling unit for production of Carbon Black, Furnace Oil and Steel Wire from Waste Tuyre at Kurlicot, Kiashanganj.

2.0663 13 09.04.12

694 M/S Excel Paper Packaging Pvt. Ltd., Patna.

Proposal for establishment of 10,200 MT per year capacity Corrugated Boxes production unit at Hajipur Industrial Area, Vaishali.

12.05 86 09.04.12

695 M/S Swastika Bakers, Gaya. Proposal for establishment of production unit of Bakery Product in proprietorship at Dubhal, Gaya.

0.9184 2 09.04.12

696 M/S Alex Green Energy Pvt. Ltd., Kolkata.

Proposal for establishment of 50 MW Solar Energy Power Plant at Katoria, Banka.

640.00 3750 09.04.12

697 M/S Maa Vindhyabasini Agro Product Pvt. Ltd., Rohtas.

Proposal for establishment of 04 MT per hour capacity Rice Mill at Khairahin, Bahuara, Dawath, Rohtas.

9.6154 25 09.04.12

698 M/S Maharshi Badri Pharmaceuticals, Jaipur.

Proposal for establishment of Awala based Food Products and Ayurvedic Medicine (Murabba, Squash syrup) production unit under proprietorship at Industrial Area, Giddha, Bhojpur.

1.4660 41 09.04.12

699 M/S Kakan Rice Mill Pvt. Ltd., Patna.

Proposal for establishment of 8 MT per hour capacity Para Boiled and Raw Rice Mill unit at Giddha, Ara, Bhojpur.

14.8213 12 09.04.12 08.09.12

700 M/S Gyani Distributors, Patna Proposal for establishment of Awala based Food Products and Ayurvedic Medicine (Murabba, Squash syrup, etc.) production unit at Industrial Growth Centre, Giddha, Bhojpur.

1.4275 41 09.04.12

701 M/S Gallantt Udyog Ltd., Gorakhpur.

Proposal for establishment of 400 MT per day capacity Roller Flour Mill unit at Durgawati, Chipali, Karamnasa, Bhabhua.

25.00 100 09.04.12

702 M/S Nawneet Raj Rice Mill Pvt. Ltd., Ara.

Proposal for establishment of 04 MT per hour capacity Rice Mill at Baligaon, Garhani, Bhojpur.

4.0951 15 09.04.12

22.12.12

703 M/S Jay Mata Rani Food and Grains Pvt. Ltd., Aurangabad.

Proposal for establishment of 08 MT per hour Para Boiled and Raw Rice Mill at Kaithi Siro, Goh, Aurangabad.

7.2634 25 09.04.12

704 M/S Vishnu Food Products, East Champaran.

Proposal for establishment of 108 MT per year capacity Oil Mill and 7200 MT Rice Polishing unit under proprietorship at Nakched Tola, Ward No.- 4, Motihari.

1.4634 34 09.04.12

705 M/S Bihar Agrochem Pvt. Ltd., Patna.

Proposal for establishment of 06 Lakh pieces per year capacity HDPE Pipe(High Density Polyethylene Pipe) and Sprinkler System production unit at Nariyar, Panapur, Minapur, Muzaffarpur.

3.4920 34 09.04.12

Report-3

63

706 M/S Captain Ramesh Rice Mills Pvt. Ltd., Ara.

Proposal for establishment of 04 MT per hour capacity Boiled Rice Mill at Demha, Bagwa, Udwantnagar, Bhojpur.

6.4260 38 09.04.12 01.02.13

707 M/S Mahesh Engineering Works, Muzaffarpur.

Proposal for establishment of 900 MT per yea capacity Lead Ingot production unit under proprietorship at Bela Industrial Area, Bela, Muzaffarpur.

1.3799 19 09.04.12

708 M/S Stef Energy India Pvt. Ltd., New Delhi. (Earlier on 09.04.12 approval was given by SIPB for establishment of 03 MW Solar Photo Voltaic Power Project unit at Udakishanganj, Madhepura. Again on company’s request, amending the above proposal consent has been given for change of place from Udakishanganj, Madhepura to Baunsi, Banka in SIPB meeting held on 18.09.12, but Tariff will be decided on the basis of competitive bidding.)

Proposal for establishment of 03 MW Solar Photo Voltaic Power Project unit at Baunsi, Banka.

50.70 40 09.04.12 18.09.12

(Consent with condition)

709 M/S Parwati Hatcheries, Vaishali.

Proposal for capacity expansion from 96000 pieces per year capacity to 28,80,000 pieces per year capacity in the existing Egg Hatchery unit under proprietorship at Industrial Area, Hajipur, Vaishali.

0.7955 7 09.04.12

710 M/S Inspiring Agro Ltd., Kolkata.

Proposal for establishment of 50 Lakh Eggs per day capacity, 50 Lakh Chicks per year capacity, 800 TDP capacity Poultry Feed unit, 20 MW Biomass Based Power Plant and 1500 Ton Pisces Culture unit in two phases at Sonahula, Guthni, Siwan.

1176.00 2100 09.04.12

711 M/S Alex Green Energy Pvt. Ltd., Kolkata.

Proposal for establishment of 25 MW Solar Energy Power Plant at Goryakothi, Siwan.

312.50 1875 09.04.12

712 M/S Kaushalya Infrastructure Development Corporation Ltd. Kolkata.

Proposal for establishment of 25 MW Solar PV Power Plant unit at Khulasa, Siwan.

312.00 09.04.12

713 M/S Nand Gopal Agro Industries Pvt. Ltd., Darbhanga.

Proposal for establishment of 04 MT per hour capacity Modern Rice Mill unit at Chandanpatti, Sara, Mohanpur, Darbhanga.

4.7299 30 16.04.12 26.04.13

714 M/S Nand R.A.B.C. Cold Storage, Darbhanga.

Proposal for establishment of 500 MT Multipurpose cold storage unit in proprietorship under R.A.B.C. at Katsaha, Bharwara, Singhwara, Darbhanga.

3.1450 130 16.04.12

715 M/S Vishnujee Oil Mill, Darbhanga.

Proposal for establishment of Mustard Oil Mill unit in proprietorship at Bela Industrial Area, Darbhanga.

0.6631 10 16.04.12

716 M/S Hariom Modern Rice Mill, Darbhanga.

Proposal for establishment of 15000 MT per year capacity Rice Mill unit in proprietorship at Katsa, Bharwara, Darbhanga.

2.3250 12 16.04.12

717 M/S Shivam Modern Rice Proposal for establishment of 36,000 8.4034 19 16.04.12 16.08.12

Report-3

64

Industries Pvt. Ltd., Raxaul. MT per year capacity Rice Mill unit at Kaurihar, Raxaul.

718 M/S Shashibhushan Agro Pvt. Ltd., Patna.

Proposal for establishment of Food Processing unit for production of 3000 MT per year capacity of Fruit, Jam, Jelly, Tomato Ketchup, Pickles, Ginger, Garlic Paste, RTS Beverage, Squash, Candy/Murabba etc. at Industrial Area, Bela, Muzaffarpur.

1.9275 15 16.04.12

719 M/S Iceberg Industries Ltd., Patna.

Proposal for capacity expansion in the existing unit from 168000 Hectoliter to 326000 Hectoliter for production of Beer in phase-1 and phase-2 at Bihta, Patna.

40.05 70 16.04.12 26.08.12

720 M/S Sharda Bhawani Cold Storage and Ware Housing Pvt. Ltd., Supaul.

Proposal for establishment of 6000 MT Multipurpose Cold Storage unit under R.A.B.C. at Sukhanagar, Pratapganj, Supaul.

5.7557 10 16.04.12

721 M/S P & R Infraprojects Ltd., Chandigarh, Punjab.

Proposal for establishment of 10 MW PV Solar Power Plant at Muzaffarpur.

130.00 100 16.04.12

722 M/S Nalanda Paper Mills Ltd., New Delhi.

Proposal for establishment of 66,000 MT per year capacity Craft Paper Production unit at Bhawnathpur, Sultanganj, Bhagalpur.

204.00 83 11.06.12

723 M/S Maa Shyama Ganga Agronomy Pvt. Ltd., Darbhanga.

Proposal for establishment of 21,600 MT per year capacity Flour Mill unit at New Industrial State, Bela, Darbhanga.

4.3310 67 11.06.12

724 M/S Indica Overseas Pvt. Ltd., Noida, U.P.

Proposal for establishment of 9600 MT per year capacity Rice Mill unit at Industrial Area, Maranga, Purnea.

3.3796 36 11.06.12

725 M/S Lakshmi Wheat Products Pvt. Ltd., Samastipur.

Proposal for capacity expansion in the existing Flour Mill unit from 15000 MT per year capacity to 54000 MT per year capacity at Samastipur.

3.4200 28 11.06.12

726 M/S Mahashakti Industries, Varanasi.

Proposal for establishment of 66,000 MT per year capacity Poultry Feed unit in partnership at Industrial area, Pandaul,Madhubani.

9.3162 40 11.06.12

727 M/S Sri Hari Educational & Welfare Trust, Patna.

Proposal for expansion of Industrial Training Centre established by the trust in the name of Sri Hari Industrial Training Centre at Haridaspur, Khagaul Nahar Road,Rupaspur, Patna.

0.8700 17 11.06.12

728 M/S Green Mark Health Care System & Solution, Darbhanga.

Proposal for establishment of 4800 MT per year capacity Roasted Gram, Maize and Corn Flakes unit in proprietorship at Industrial Area, Donar, Darbhanga.

1.2575 24 11.06.12

729 M/S Krishna Food & Beverage Industries, Noida, U.P.

Proposal for establishment of 1200 MT per year capacity Fruits Vegetables and Cereals Processing and Health Drinks production unit in proprietorship at Industrial Area, Giddha, Bhojpur.

1.3197 28 11.06.12

730 M/S Baba lokenath Agrotech Industries Pvt. Ltd., Patna.

Proposal for establishment of 2541 MT per year capacity HDPE Pipe production unit in the name of Mahashakti Pipe Industries at Saidpur Tola, Karauta, Bakhtiyarpur,

5.4798 20 11.06.12 26.04.13

Report-3

65

Patna.

731 M/S Darbhanga Agro Pvt. Ltd., Darbhanga.

Proposal for establishment of 5500 MT capacity Cold Storage unit under RABC at Chanpatti, Saramohanpur, Darbhanga.

4.7443 20 11.06.12

732 M/S Globus Spirits Ltd., New Delhi. (Earlier on 11.06.12 approval was given by SIPB for establishment of grain based 120 K.L.P.D. Distillery Plant, Country Liquor and I.M.F.L. production unit at Andhrabar Chowk, Panapur, Vaishali. Again on company’s request, amending the above proposal consent has been given for establishment of grain based 120 K.L.P.D. Distillery Plant, Country Liquor and I.M.F.L. production unit from grain as well as from molasses at Andhrabar Chowk, Panapur, Vaishali in SIPB meeting held on 18.09.12.)

Proposal for establishment of grain based 120 K.L.P.D. Distillery Plant, Country Liquor and I.M.F.L. production unit from grain as well as from molasses at Andhrabar Chowk, Panapur, Vaishali.

160.0000 88 11.06.12 18.09.12

733 M/S Shree Hari Jee Agro Products Pvt. Ltd., Rohtas.

Proposal for establishment of 10 MT per hour Modern Para Boiled and Raw Rice Mill unit at Bairi Karmaini Kala, Bikramganj, Rohtas.

11.7418 30 11.06.12

734 M/S Jas Global Agriculture and Power Pvt. Ltd., Motihari.

Proposal for establishment of 08 MT per hour Para Boiled and Raw Rice Mill and 02 MW Co-generation Plant unit at Chintawanpur, Chakiya, Pipra, East Champaran.

18.9888 96 11.06.12

735 M/S Vaishali Industrial Products, Hajipur (Vaishali).

Proposal for establishment of 100 pieces Modular Furniture, 100 pieces Hospital Furniture/Equipment and 100 pieces Office Furniture per month production unit in partnership at Hajipur Industrial Area, Vaishali.

1.0010 16 11.06.12

736 M/S Shree Balajee Industries, Patna.

Proposal for establishment of 15,000 MT per year capacity Cement Plant unit in proprietorship at Industrial Area, Fatuha, Patna.

2.3845 35 11.06.12

737 M/S Tara Health Foods Ltd., Ludhiana, Punjab.

Proposal for establishment of 250 MT per day capacity Cattle Feed production unit at Industrial Area, Barauni, Begusarai.

14.8000 185 11.06.12

738 M/S JAK Hotel & Arcade LLP, Bettiah.

Proposal for establishment of Hotel and Restaurant Services unit at Nauranga Garden, Bettiah.

16.8952 37 11.06.12

739 M/S Dumraon Power Pvt. Ltd., Dumraon.

Proposal for establishment of Biomass based 02 MW Captive Power Plant at Gurahatha Khurd, Buxar.

14.9386 55 11.06.12

740 M/S Sumedha Agro Products Pvt. Ltd., Sasaram.

Proposal for establishment of 18000 MT per year capacity Modern Rice Mill unit at Hurka Tillauthu, Dehri-on-Sone, Rohtas.

8.8314 30 11.06.12

741 M/S Shivshakti Hatchery Pvt. Ltd., Samastipur.

Proposal for establishment of 9600 MT per year capacity Poultry Feed unit at Hansa, Warisnagar, Samastipur.

0.9972 56 11.06.12

Report-3

66

742 M/S Ocean Elevator Pvt. Ltd., Patna.

Proposal for establishment of 96 pieces per year capacity Elevator/Lift production and Fabrication unit at Industrial area, Fatuha, Patna.

0.9037 22 11.06.12

743 M/S Maa Durga Industries, Vaishali.

Proposal for establishment of 3000 MT per year capacity Maize Flour, Corn Flakes production unit in proprietorship at EPIP, Hajipur.

1.0971 16 11.06.12

744 M/S J. K. Lakshmi Cement Ltd., New Delhi.

Proposal for establishment of 05 lakh MT per year capacity Cement Plant at Industrial Area, Aurangabad.

120.4000 130 11.06.12

745 M/S J. K. Lakshmi Cement Ltd., New Delhi.

Proposal for establishment of 10 lakh MT per year capacity Cement Plant at Industrial Area, Kishanganj.

260.0000 175 11.06.12

746 M/S Parwati Buildtech Pvt. Ltd., Gaya.

Proposal for establishment of 7500 MT per year capacity Pack House for Fruits and Vegetable under R.A.B.C. at Sadar Gaya, Chandauli.

2.4175 15 11.06.12 07.03.13

747 M/S Suresh Kumar and Company, Khagaria.

Proposal for establishment of 12000 pieces per year capacity Diesel Engine Pumpset Assembling unit in proprietorship at Khagaria.

1.0442 15 11.06.12

748 M/S JKM Beverages Ltd., New Delhi.

Proposal for establishment of 2.5 lakh Hectoliters per year capacity Beer Plant at Jagdishpur, Bhojpur.

61.9500 88 11.06.12

749 M/S Kumar Commodity and Food Management Pvt. Ltd., Beguasarai.

Proposal for establishment of 04 MT per hour Rice Mill unit at Deona Industrial Area, Barauni.

2.6500 81 11.06.12

750 M/S Astha Confectioneries Pvt. Ltd., Patna.

Proposal for establishment of 10,71,900 Kg. per year capacity Slice Bread and Cake production unit at Industrial Area, Fatuha, Patna.

1.1464 25 11.06.12

751 M/S Loma Rice Mills(Proprietorship unit of M/S Blue Bird e Solutions Pvt. Ltd.), Kolkata.

Proposal for establishment of 43,200 MT per year capacity Para Boiled and Plain Rice Mill unit in proprietorship at Loma, Jandaha, Vaishali.

8.0359 38 11.06.12

752 M/S Sai Sharan Foods, Patna.

Proposal for establishment of 6720 Loaves per day, 2520 Rusk per day and 336 Kg. Biscuit/Cookies per day capacity production unit in partnership at Dariyapur, Neura, Patna.

0.9954 41 11.06.12

753 M/S Kandla Energy and Chemicals Ltd., Ahmedabad, Gujarat.

Proposal for establishment of 2 X 250 MW coal based Thermal Power Plant in two phase at Sahebpur Kamal, Begusarai.

2750.0000 250 11.06.12

754 M/S Hentech Agrovet Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 45,000 MT per year capacity Cattle Feed, Poultry Feed, Fish Feed and Pig Feed production unit at Industrial Area, Muzaffarpur.

3.4025 55 11.06.12

755 M/S J K M Infra Projects Ltd., New Delhi.

Proposal for establishment of 4 Star Hotel at Bodh Gaya, Gaya.

29.3000 150 11.06.12

756 M/S Mother Teresa Nursing School,(Pro.- M/S Gandhi Educational Trust), Katihar.

Proposal for establishment of Nursing Training Institute in the name of Mother Teresa Nursing School at Mongra Fatak, Dalan, Katihar.

5.2560 29 11.06.12

757 M/S Natural Thermo Pvt. Ltd., Gorakhpur, U.P.

Proposal for establishment of 576 MT per year capacity Plastic

3.5566 39 11.06.12

Report-3

67

Disposable Glasses and Cups production unit at E.P.I.P., Hajipur.

758 M/S Sone Ojas Ltd.(Pro.- M/S Kalyanpur Cements Ltd.), Patna.

Proposal for establishment of 15 MW Co-generation Captive Power Plant (based on Coal and Waste Heat of Cement Plant) at Banjari, Kalyanpur, Rohtas.

100.0000 54 11.06.12

759 M/S Shrenuj & Co. Ltd.,Mumbai.

Proposal for establishment of 2,88,000 Crates per year capacity Diamond Manufacturing- Cutting and Polishing unit at Industrial Area, Patliputra, Patna.

47.8100 1395 11.06.12

760 M/S Lal Chinta Rice Mills Pvt. Ltd., Ara(Bhojpur).

Proposal for establishment of 05 MT per hour Para Boiled and Raw Rice Mill unit at Industrial Growth Centre, Giddha, Bhojpur.

5.2853 12 11.06.12

761 M/S Angel Farms, Haryana. Proposal for establishment of 192000,00 pieces per year capacity Egg Hatchery unit in partnership at Industrial Area, Fatuha, Patna.

2.6793 68 11.06.12

762 M/S Laxman Agro Enterprises Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 03 MT per hour capacity Modern Rice Mill unit at Industrial Area, Bela, Muzaffarpur

1.0584 25 11.06.12

763 M/S Technocrates, Forbesganj, Araria.

Proposal for establishment of 9000 MT per year capacity Cattle Feed and Poultry Feed unit in proprietorship at Industrial Area, Forbesganj.

2.5110 117 11.06.12

764 M/S Claro Energy Pvt. Ltd, New Delhi.

Proposal for establishment of 20 MW Solar Power Plant at Sahjadpur, Sarairanjan, Samastipur.

240.0000 100 11.06.12

765 M/S Jaimatadi Incorporation Pvt. Ltd., Patna.

Proposal for establishment of 72 Room Hotel in the name of J.M.D International at Industrial Area, Patliputra, Patna.

20.2158 119 11.06.12

766 M/S Kanodia Infratech Ltd., Varanasi.

Proposal for establishment of 06 lakh MT per year capacity Cement Plant unit at Growth Centre , Industrial Area, Aurangabad.

78.5500 74 11.06.12

767 M/S Aroma Beauty & Health Care Pvt. Ltd., Patna.

Proposal for establishment of 192 MT per year capacity Spice Powder unit in the name of Aroma Spices at Fatuha, Patna.

1.0260 10 13.08.12

768 M/S Champaran Rice Mill Pvt. Ltd., Patna.

Proposal for establishment of 48 MT per day capacity Arwa Rice Mill unit at Mathiyavrit, Chauradano, East Champaran.

2.9647 26 13.08.12

769 M/S Bhimseria Agro Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 10 MT per hour Para Boiled Rice Mill and Plain Rice Mill unit at Industrial Estate, Bela, Mizaffarpur.

10.4663 36 13.08.12

770 M/S Jai Maa Kali Cold Storage Pvt . Ltd. Lakhisarai.

Proposal for establishment of 6000 MT Multipurpose Cold Storage under R.A. B.C. at Mohanpur, Lakhisarai.

9.9352 30 13.08.12

771 M/S Jyoti Moulders Pvt. Ltd., Patna.

Proposal for 200 MT per year capacity expansion in the existing Plastic Chair and Furniture unit at Mahuli Road, Karmalichak, Patna City, Patna.

3.4300 8 13.08.12

Report-3

68

772 M/S Girdhari Murari Agro Food Products Pvt. Ltd., Rohtas.

Proposal for establishment of 15,000 MT per year capacity Modern Rice Mill unit at Noonsarai, Nokha, Sasaram.

2.00 21 13.08.12

773 M/S Shri Ji Enterprises, Bhabhua.

Proposal for establishment of 3 MT per hour Modern Rice Mill unit in partnership at Ratwar, Bhabhua.

3.4766 15 13.08.12

774 M/S Keventer Food Park Infra Ltd., Bhagalpur.

Proposal for establishment of 20 MW coal based Captive Power Plant unit at Kahalgaon Industrial Area, Bhagalpur.

130.00 100 13.08.12

775 M/S Om Shanti Rice Mill Pvt. Ltd., Kaimur, Bhabhua. (Earlier on 13.08.12 SIPB meeting, approval was given for establishment of 05 MT per hour Modern Para Boiled and Raw Rice Mill unit at Usri, Mohania, Kaimur. Again, approval has been given for change of project site from Usri, Mohania, Kaimur to Mauza-Sahpur, Mohania, Kaimur in SIPB meeting held on 18.04.13.)

Proposal for establishment of 05 MT per hour Modern Para Boiled and Raw Rice Mill unit at Mauza-Sahpur, Mohania, Kaimur.

7.4281 35 13.08.12 18.04.13

776 M/S G.C. Consumer Products Pvt. Ltd,. Muzaffarpur.

Proposal for establishment of 80 MT per day capacity Whole Mill Atta production unit at Bela Industrial Area, Muzaffarpur.

2.6824 28 13.08.12

777 M/S Manju Cold Storage Pvt. Ltd., Nalanda.

Proposal for establishment of 10,000 MT Cold Storage unit under R.A.B.C. at Karampur-Dharampur, Pawapuri, Nalanda.

12.8912 50 13.08.12

778 M/S Kusum Agro Endeavor Pvt. Ltd., Patna

Proposal for establishment of 04 MT per hour Modern Rice Mill unit at Simra, Parsa Bazar, Phulwarisharif, Patna.

5.3145 48 13.08.12

779 M/S Patil Steel Wires Pvt. Ltd., Hyderabad

Proposal for establishment of 10,800 MT per year capacity High Tension Steel Wire production unit at Sabalpur, Patna City, Patna.

8.7913 65 13.08.12

780 M/S Ram Vilash Cold Storage Pvt. Ltd., Samastipur.

Proposal for capacity expansion from 3000 MT capacity to 7000 MT capacity under R.A.B.C. in the existing Cold Storage unit at Kushar, Nijhma, Mahua,Vaishali.

2.8487 105 13.08.12

781 M/S J K Hitech Rice Mill Pvt. Ltd., Patna.

Proposal for establishment of 8 MT per hour Modern Para Boiled Rice Mill unit at Raghunathpur, Ramgharwa, Raxaul, East Champaran.

13.800 75 13.08.12

782 M/S Om Shri Dhanushdhari Foods Ltd., Patna.

Proposal for establishment of 100 MT per day capacity Roller Flour Mill and 50 MT per day capacity Atta Chakki unit at Hajipur(Vaishali).

9.8442 100 13.08.12

783 M/S Shrinivas (G) Educational & Research Institute of Medical Sciences, Patna.

Proposal for establishment of Super Speciality Hospital and Higher Educational Institute- Medical College at Garkha, Chapra.

143.00 200 13.08.12

784 M/S Khatu Shyam Foods Pvt. Ltd., Patna

Proposal for establishment of 08 MT per hour Modern Rice Mill unit at Mohiuddinpur, Fatuha, Patna.

15.8586 57 13.08.12

Report-3

69

785 M/S A.R. Mills, Patna. Proposal for establishment of 9600 MT per year capacity Rice Mill and Dal Mill unit in proprietorship at Fatuha, Patna.

1.7647 38 13.08.12

786 M/S Om Shri Laxminarain Warehouse Shoppers Ltd., Patna

Proposal for establishment of 8 MT per hour Boiled Rice Mill unit at Hajipur.

18.6678 60 13.08.12

787 M/S Kalyanpur Building Materials Pvt. Ltd., Patna.

(Amending the approval given on proposal for establishment of 30,000 Cubic Meter per year capacity Autoclaved Aerated Concrete Blocks in two phases at Aurangabad in SIPB meeting held on 13.08.12, approval has been given for establishment of 3,00,000 Cubic Meter per year capacity Autoclaved Aerated Concrete(AAC) Blocks production unit in two phases at Aurangabad in SIPB meeting held on 28.11.12 & 29.11.12.)

Proposal for establishment of 3,00,000 Cubic Meter per year capacity Autoclaved Aerated Concrete(AAC) Blocks production unit in two phases at Aurangabad.

78.1700 64 13.08.12

28.11.12 &29.11.12

788 M/S Kusum Rice Mill Pvt. Ltd., Buxar.

Proposal for establishment of 04 MT per hour Modern Arwa Rice Mill unit at Tiyara, Manoharpur, Buxar.

3.5440 12 13.08.12

789 M/S Sri Rani Sati Agri Feeds Pvt. Ltd., Darbhanga.

Proposal for establishment of 9600 MT per year capacity Poultry Feed and Cattle Feed unit at Industrial Area, Donar, Darbhanga.

1.3973 5 13.08.12 09.04.13

790 M/S SSF Industries Ltd., Hajipur(Vaishali).

Proposal for establishment of 600 MT per year capacity Flexible Polyurethane Foam production unit at E.P.I.P., Hajipur.

10.4387 39 13.08.12

791 M/S Anagha Energy and Infrastructure Pvt. Ltd., Patna.

Proposal for establishment of 1000 pieces per year capacity of 100 KVA Transformer production unit at Fatuha/Hajipur.

1.5000 33 13.08.12

792 M/S Parashmani Food & Chem Pvt. Ltd., Patna.

Proposal for establishment of 120 MT per year capacity Snacks and Puffs production unit at Danapur Cantt, Patna.

1.00 13 13.08.12

793 M/S Sony Air Gases Industries, Begusarai

Proposal for establishment of 900 Cubic Meter per year capacity Medical and Industrial Oxygen, Liquid Nitrogen and Nitrogen Gas production unit in partnership at Industrial Area, Barauni, Begusarai.

3.1146 38 13.08.12

794 M/S Bohra Sales & Services Ltd., Ranchi.

Proposal for establishment of 900 MT per year capacity Vermicelli and Noodles unit at Fatuha, Patna.

1.2856 18 13.08.12

795 M/S Mithila Feed, Darbhanga.

Proposal for establishment of 2400 MT per year capacity Poultry Feed and Cattle Feed unit in proprietorship at Darbhanga.

1.1239 27 13.08.12

796 M/S Mahua Co-operative Proposal for establishment of 1 MT 24.00 13.08.12

Report-3

70

Cold Storage Ltd., Mahua, Vaishali.

per hour Frozen Item-Fruits and Vegetable units at Kariho, Mirjanagar, Mahua, Vaishali.

797 M/S Shri Ashutosh Securities Pvt. Ltd., Patna.

Proposal for establishment of Multiplex and Food Court unit in the name of Rendezvous at Arya Kumar Road, Rajendra Nagar, Patna.

8.00 65 13.08.12

798 M/S Shakaldeep Cold Storage Pvt. Ltd., Bhojpur.

Proposal for establishment of 10,000 MT Multipurpose Cold Storage unit under R.A.B.C. at Industrial Area Bihiya, Bhojpur.

12.2123 60 13.08.12

799 M/S Kaveri Food Industry, Buxar.

Proposal for establishment of 5222 MT per year capacity Modern Rice Mill(Arwa) unit in proprietorship at Ahirauli, Buxar.

1.0300 15 13.08.12

800 M/S Pashupatinath Distributors Pvt. Ltd., Patna.

Proposal for establishment of 12,000 Kiloliter per year capacity Packaged Drinking Water and 276 MT per year capacity PET Bottle unit at Fatuha, Patna.

3.0323 55 13.08.12

801 M/S Savitri Horticulture Pvt. Ltd., Samastipur.

Proposal for establishment of 8500 MT Cold Storage unit under R.A.B.C. at Donar Industrial Area, Darbhanga.

8.3600 10 13.08.12

802 M/S AL Sameer Exports Pvt. Ltd., Meerut.

Proposal for establishment of 46,350 MT per year capacity Meat Processing unit at Araria/Kishanganj or Bhagalpur.

26.6235 426 13.08.12 26.04.13

803 M/S Mahaganpati Food and Agro Products Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 14,880 MT per year capacity Modern Para Boiled Rice Mill unit at Muzaffarpur.

6.9267 18 13.08.12

804 M/S Kavish Infrastructure Pvt. Ltd., Kolkata.

Proposal for establishment of 240 Lakh pieces per year capacity Fly Ash Bricks production unit at Barauni, Begusarai.

4.80 10 13.08.12

805 M/S Unique Properties Pvt. Ltd., Guwahati.

Proposal for establishment of Five Star Hotel at Patna.

92.0000 18.09.12

806 M/S D.R. Polymer, Patna. Proposal for establishment of 900 MT per year capacity Agarbatti stick production unit in proprietorship at Industrial Area, Hajipur, Vaishali.

1.0582 27

18.09.12 (Consent

with condition)

807 M/S Green Concretex Cements Pvt. Ltd., Kolkata.

Proposal for establishment of 01 million MT per year capacity cement plant unit at Kahalgaon.

137.6000 153 18.09.12

808 M/S Chandrika Infra Pvt. Ltd., New Delhi.

Proposal for establishment of 02 MW Solar P.V. Power Plant unit at Fatehli, Deepnagar, Nalanda.

20.0000 12

18.09.12 (Consent

with condition)

809 M/S Sureka Industries Pvt. Ltd., Darbhanga.

Proposal for establishment of 250 MT per year capacity spice production unit at Industrial Area, Donar, Darbhanga.

1.3250 12

18.09.12 (Consent

with condition)

810 M/S Om Sai Brick Industries, Purnea.

Proposal for establishment of 108 lakh pieces per year capacity Fly Ash Bricks production unit in partnership at Industrial Area, Maranga, Purnea.

1.0890 24

18.09.12 (Consent

with condition)

811 M/S Tegh Bahadur Carbons Pvt. Ltd., Begusarai.

Proposal for establishment of 19,800 MT per year capacity Calcined Petroleum Coke production unit at Barauni Industrial Area, Begusarai.

4.8000 31

18.09.12 (Consent

with condition)

812 M/S Dayal Products Pvt. Ltd., Proposal for establishment of 105.60 1.2421 11 18.09.12

Report-3

71

Hajipur, Vaishali. lakh litres per year capacity Packaged Drinking Water unit at Industrial Area, Hajipur, Vaishali.

(Consent with

condition)

813 M/S Technoculture Building Centre Pvt. Ltd., Patna.

Proposal for establishment of 3.5 MW Rice Husk Based Power Plant unit at Hajipur, Vaishali.

9.5200 25

18.09.12 (Consent

with condition)

814 M/S Thirteen Bulls Infra Pvt. Ltd., Purnea.

Proposal for establishment of Hotel and Restaurant and Resort unit at Industrial Growth Centre, Purnea.

9.0000 89

18.09.12 (Consent

with condition)

815 M/S Birla Urja Ltd., Mumbai. Proposal for establishment of 10 MW Solar Photo Voltaic Solar Power Plant unit at Darbhanga / Bhagalpur / Munger / Gaya / Muzaffarpur.

114.3100 250

18.09.12 (Consent

with condition)

816 M/S Acme Tele Power Ltd, Gurgaon, Haryana.

Proposal for establishment of 30 MW Solar Photo Voltaic Power Plant unit at Gaya.

350.0000 280

18.09.12 (Consent

with condition)

817 M/S Jhunjhunwala Oil Mills Ltd., Varanasi.

Proposal for capacity expansion from 28,800 MT per year capacity to 72,000 MT per year capacity in the existing Modern Rice Mill unit at Bangra, Kudra, Mohania, Kaimur, Bhabhua.

21.0000 180 18.09.12

818 M/S Vaishnavi Industries, Darbhanga.

Proposal for establishment of 5520 MT per year capacity Rice Mill and Dal Mill production unit in proprietorship at Industrial Area, Donar, Dabhanga.

1.9413 34

18.09.12 (Consent

with condition)

819 M/S Shree Shashwatraj Agro Pvt. Ltd., Aurangabad.

Proposal for establishment of 3528 MT per year capacity Flour Mill unit at Industrial Growth Centre, Aurangabad.

1.0297 29

18.09.12 (Consent

with condition)

820 M/S Vishnu Industries, Gaya. Proposal for establishment of 4800 MT per year capacity Dal Mill unit in partnership at Industrial Area, Gaya.

1.7030 34

18.09.12 (Consent

with condition)

821 M/S Srinivash Food Industries, Patna.

Proposal for establishment of 3120 MT per year capacity Maize Poha, Rice Poha and Chilli Powders production unit in proprietorship at Fatuha Industrial Area, Fatuha, Patna.

1.2870 30

18.09.12 (Consent

with condition)

822 M/S Indo Gulf Fertilizers, Uttar Pradesh.

Proposal for establishment of 19,800 MT per year capacity Fertilizer and 4,15,800 pieces per year capacity bags production unit at Bela Industrial Area, Muzaffarpur.

15.5000 33

18.09.12 (Consent

with condition)

823 M/S Rozario Beverages Pvt. Ltd., West Bengal.

Proposal for establishment of 60,000 litre per day capacity Distillery unit at Bhagwanpur, Vaishali.

89.6770 18.09.12

824 M/S Aryan Agro Industries, Aurangabad.

Proposal for establishment of 10,000 MT Cold Storage unit in partnership at Industrial Growth Centre, Jasoiya, Aurangabad.

6.2944 7

18.09.12 (Consent

with condition)

825 M/S Moolchand Healthcare Pvt. Ltd., New Delhi.

Proposal for establishment of Multi Speciality Tertiary Care Hospital and Diagnostic Centre at E.P.I.P., Hajipur.

503.5000 2150

18.09.12 (Consent

with condition)

826 M/S Kisan Rice Industries Pvt. Ltd., Nalanda.

Proposal for establishment of 15,000 MT per year capacity Modern Rice

3.9020 24 18.09.12 (Consent

Report-3

72

Mill unit at Narsanda, Chandi, Nalanda.

with condition)

827 M/S Pratik Industries, Muzaffarpur.

Proposal for establishment of 8760 MT per year capacity Ice-Cream, Ice-Cream Block, Sorting and Packaging of Fruits and Vegetable unit in proprietorship at Industrial Area, Bela, Muzaffarpur.

3.9322 170

18.09.12 (Consent

with condition)

26.04.13

828 M/S Hotel Pushkar, Aurangabad.

Proposal for establishment of Three-Star Hotel in proprietorship at Industrial Growth Centre, Jasoiya, Aurangabad.

1.3050 16

18.09.12 (Consent

with condition)

829 M/S Rajhans Cold Storage Pvt. Ltd., Begusarai.

Proposal for capacity expansion from 7690 MT to 11,890 MT under R.A.B.C. in existing Cold Storage at Teghra, Begusarai.

2.7509 5 18.09.12

830 M/S Om Aastha Indo Energy Pvt. Ltd., Sasaram.

Proposal for establishment of 16,000 MT per year capacity Modern Rice Mill Unit at Belaon, Kharonda, Kaimur.

5.1759 40 18.09.12

831 M/S Mahabir Petroleum Products, Begusarai.

Proposal for establishment of 100 MT per day Calcined Petroleum Coke production unit in proprietorship at Barauni Industrial Area, Barauni.

3.0500 31

18.09.12 (Consent

with condition)

832 M/S Pragati Food Products, Hajipur, Vaishali.

Proposal for establishment of 3960 MT per year capacity Ice-Cream and Ice-Cream Block production unit in partnership at E.P.I.P., Hajipur, Vaishali.

2.4426 33

18.09.12 (Consent

with condition)

833 M/S Frostberg Agritech Pvt. Ltd., Saharsa.

Proposal for establishment of 5000 MT Cold Storage under R.A.B.C. at Patuaha, Kahra, Saharsa.

3.2574 15 18.09.12

834 M/S Manokamna Enterprises Pvt. Ltd., Patna.

Proposal for establishment of 30,000 MT per year capacity M.S. Steel Bar and Structural Products production unit at Fatuha Industrial Area, Patna.

7.4800 47

18.09.12 (Consent

with condition)

835 M/S Vivek Vinayak Foods Pvt. Ltd., Hajipur.

Proposal for establishment of 97,20,000 litres per year capacity Packaged Drinking Water unit at Hajipur, Vaishali.

1.0016 15 18.09.12

836 M/S K.D. Liquor & Fertilizer Pvt. Ltd., Patna.

Proposal for establishment of 750 lakh pieces per year capacity Pet Bottles production unit at Fatuha Industrial Area, Fatuha, Patna.

4.9373 23

18.09.12 (Consent

with condition)

837 M/S Susheela Agro Industries, Patna.

Proposal for establishment of 9000 MT per year capacity Cattle Feed and Poultry Feed unit in proprietorship at Industrial Area, Fatuha, Patna.

1.2891 32

18.09.12 (Consent

with condition)

838 M/S Bansal Industries, Begusarai.

Proposal for establishment of 24000 MT per year capacity Whole Wheat Ata Chakki Plant (Flour Mill) unit in proprietorship at Barauni Industrial Area, Deona, Begusarai.

2.1436 25

18.09.12 (Consent

with condition)

839 M/S Dynamic Tarang Pvt. Ltd., Ranchi.

Proposal for establishment of 10 MT per year capacity Jaggery and allied Food Product unit at Industrial Area, Barari, Bhagalpur.

1.8723 20

18.09.12 (Consent

with condition)

840 M/S Emami Cement Ltd., Kokata.

Proposal for establishment of 1.5 MT per year capacity Cement Grinding unit and 10 MW Captive Power

418.0000 166 18.09.12

Report-3

73

Plant1unit at Shivnarayanpur, Kahalgaon, Bhagalpur.

841 M/S New Patliputra Gas Manufacturers, Ramgarh(Jharkhand).

Proposal for establishment of Industrial and Medical Oxygen, Carbondioxide Gas, Nitrogen Gas, Argon Gas, Dry Ice Mixed Gas production unit in partnership at Barari Industrial Area, Bhagalpur.

5.1185 40

18.09.12 (Consent

with condition)

842 M/S Lal Bhai Construction Equipments Pvt. Ltd., Patna.

Proposal for establishment of 580 pieces per year capacity Reversible Mixer, Batching Plant, Disaster and Safety Equipment and Machineries (Building Construction Equipment) production unit at Industrial Area, Fatuha, Patna.

8.7460 129

18.09.12 (Consent

with condition)

843 M/S Lal Bhai Construction Equipments Pvt. Ltd., Patna.

Proposal for establishment of 1500 pieces per year capacity Building Construction Tools production unit at Industrial Area, Fatuha, Patna.

2.0087 46

18.09.12 (Consent

with condition)

844 M/S K.K. Rice Mill, Aurangabad.

Proposal for establishment of 03 MT per hour Modern Rice Mill (Arwa And Usna) unit in proprietorship at Industrial Growth Centre, Aurangabad.

2.3560 15

18.09.12 (Consent

with condition)

845 M/S Shakambhari Agro Foods Industries, Patna City, Patna.

Proposal for establishment of 1200 MT per year capacity Fryums and Soya Bari production unit in partnership at Bharatpur Simli, Patna City, Patna.

2.0327 34 18.09.12

846 M/S Tanya Enterprises, Aurangabad.

Proposal for establishment of Air Separation unit for production of 150 Cubic Newton Meter per hour capacity Oxygen/Nitrogen Gas in proprietorship at Aurangabad.

3.2995 14 18.09.12

847 M/S Rikon Pharmaceuticals Pvt. Ltd., Patna.

Proposal for establishment of Allopathic medicine (Tablets, Capsule, Liquid Syrup, Eye Drop, Ointment, Injection Ampoule and Food Supplement) production unit at Industrial Area, Fatuha, Patna.

4.7160 55

18.09.12 (Consent

with condition)

848 M/S B.R. Irrigation System, Katihar.

Proposal for establishment of 1.20 Lakh pieces per year capacity H.D.P.E. Pipe (High Density Polyethylene Pipe) production unit in partnership at Industrial Growth Centre Maranga, Purnea.

1.7370 39

18.09.12 (Consent

with condition)

849 M/S Ayush Rice Mill, Aurangabad.

Proposal for establishment of 36000 MT per year capacity Arwa Rice Mill and Boiled rice Mill unit in proprietorship at Industrial Growth Centre, Jasoiya More, Aurangabad.

2.7100 9

18.09.12 (Consent

with condition)

850 M/S Protech Packaging Pvt. Ltd., Patna.

Proposal for establishment of 1200 Lakh pieces per year capacity Aluminium Bottle Cap production unit at Industrial Area, Fatuha, Patna.

1.3167 20

18.09.12 (Consent

with condition)

851 M/S Sri Shivam Rice Mill, Bhojpur.

Proposal for establishment of 7200 MT per year capacity Modern Rice Mill unit in partnership at Giddha Industrial Area, Giddha, Bhojpur.

1.5300 26

18.09.12 (Consent

with condition)

852 M/S M J & Sons Distillery & Breweries Pvt. Ltd., Banka.

Proposal for establishment of 150000 H.L.P.A. capacity Brewery Plant unit at Raghunathpur, Banka.

54.5200 75 18.09.12

Report-3

74

853 M/S BMW Ventures Ltd., Patna.

Proposal for establishment of 25,000 MT per year capacity M.S.T.M.T.(Thermo Mechanically Twisted) and Sheet Cutting Processing unit at Industrial Area, Fatuha, Patna.

38.7000 300

18.09.12 (Consent

with condition)

854 M/S Swastik Poly Plast, Patna.

Proposal for establishment of 450 K.G. per hour Plastic Granules production unit in proprietorship at Industrial Area, Fatuha, Patna.

1.3680 28

18.09.12 (Consent

with condition)

855 M/S I.P. Threads, Dumraon, Buxar.

Proposal for establishment of 144 MT per year capacity twisted yarn unit in proprietorship at Dumraon Textiles Residential Colony, Dumraon.

1.1386 40 18.09.12

856 M/S Ankur Business Pvt. Ltd., Kolkata.

Proposal for establishment of 30,000 MT per year capacity Packaging of Iodised Salt unit at Fatuha Industrial Area, Fatuha, Patna.

2.5750 141

18.09.12 (Consent

with condition)

857 M/S Imperial Agrotech Pvt. Ltd., Patna.

Proposal for establishment of 36,000 MT per year capacity Modern Rice Mill unit at Industrial Growth Centre, Aurangabad.

2.9316 9

18.09.12 (Consent

with condition)

858 M/S S.K. Plast, Chapra. Proposal for establishment of 4,32,000 pieces per year capacity Pet Jar production unit in proprietorship at Industrial Area, E.P.I.P., Hajipur.

1.0800 25

18.09.12 (Consent

with condition)

859 M/S Ram Janki Cold Storage Pvt. Ltd., Bhojpur.

Proposal for establishment of 6000 MT Cold Storage unit at Karisath, Bhojpur.

4.0000 13 18.09.12

860 M/S Anupam Dispo Cons, Muzaffarpur.

Proposal for establishment of 440 MT per year capacity PP Glass and 318 Lakh pieces per year capacity Paper Cup production unit in proprietorship at Industrial Area, Bela, Muzaffarpur.

2.5168 17

18.09.12 (Consent

with condition)

861 M/S Jindal Moulded Furniture Pvt. Ltd., Aligarh.

Proposal for establishment of 450000 pieces per year capacity Moulded Plastic Chair production unit at Industrial Area, Fatuha, Patna.

2.1780 27

18.09.12 (Consent

with condition)

862 M/S Siddhi Vinayak Petro Chemicals, Begusarai.

Proposal for establishment of Cationic Bitumen Emulsion (15,600 MT per year capacity) production unit in proprietorship at Industrial Area, Barauni, Begusarai.

5.3900 15

18.09.12 (Consent

with condition)

863 M/S Ugraya Suppliers Pvt. Ltd., New Delhi.

Proposal for establishment of 1.20 Lakh MT per year capacity Poultry Feed unit at Industrial Estate, Bela, Muzaffarpur.

14.7663 43

18.09.12 (Consent

with condition)

864 M/S Mohit Polytech Pvt. Ltd., Jaipur, Rajasthan.

Proposal for establishment of 06 Lakh pieces per year capacity HDPE Pipes(High Density Polyethylene Pipes) and Sprinkler System Production unit at Industrial Growth Centre, Giddha, Ara.

11.9700 86

18.09.12 (Consent

with condition)

865 M/S L.K. Rice Mill, Patna. Proposal for establishment of 96 MT per day capacity Arwa Rice Mill unit in proprietorship at Industrial Area, Fatuha, Patna.

1.4391 39 18.09.12

866 M/S Shikha Breeding Farm & Hatchery, Muzaffarpur.

Proposal for establishment of 48 Lakh pieces per year capacity Day-

1.4938 23 18.09.12 (Consent

Report-3

75

Old Chicks(Hatchery) unit in proprietorship at Industrial Area, Donar, Darbhanga.

with condition)

867 M/S Shalimar Pellet Feeds Ltd., Kolkata.

Proposal for establishment of 60,000 MT per year capacity Poultry Feed unit at Industrial Area, Muzaffarpur.

10.7070 60

18.09.12 (Consent

with condition)

868 M/S Shilpee Educational Trust, Patna.

Proposal for establishment of Nurses Training College at Maranga Industrial Area, Maranga, Purnea.

1.7187 23

18.09.12 (Consent

with condition)

869 M/S Swadeshi Rice Mills Pvt. Ltd., Vaishali.

Proposal for establishment of 64,000 MT per year capacity Rice Mill unit at E.P.I.P., Hajipur.

21.0311 72

18.09.12 (Consent

with condition)

870 M/S Siddhi Bricks, Buxar. Proposal for capacity expansion from 75000 pieces per year capacity to 3,93,75,000 pieces per year capacity in the existing Mechanised Bricks unit in partnership at Navanagar, Buxar.

1.1478 21 18.09.12

871 M/S Lord Buddha Food Products Pvt. Ltd., Patna.

Proposal for establishment of 600 MT per year capacity Plastic Granules production unit at Industrial Area, Hajipur.

1.4355 21

18.09.12 (Consent

with condition)

872 M/S Mukesh Rice & Flour Mill, Madhepura.

Proposal for establishment of 7200 MT per year capacity Rice Mill and 14400 MT per year capacity Roller Flour Mill unit in proprietorship at Udakishanganj Industrial Area, Madhepura.

3.0037 36

18.09.12 (Consent

with condition)

873 M/S Shree Balajee Cement Industries Pvt. Ltd., Patna.

Proposal for establishment of 15,000 MT per year Capacity Cement Plant unit at Industrial Area, Fatuha, Patna.

2.3845 35

18.09.12 (Consent

with condition)

874 M/S Swastik Rice Mill, Aurangabad.

Proposal for establishment of 19200 MT per year capacity Arwa Rice Mill unit in proprietorship at Industrial Area, Barun, Aurangabad.

1.9260 51

18.09.12 (Consent

with condition)

875 M/S Rameshwar Sinha Poly Industries, Patna.

Proposal for establishment of 792 MT per year capacity P.V.C. Rigid Pipe production unit in proprietorship at Industrial Area, Fatuha, Patna.

1.2780 27

18.09.12 (Consent

with condition)

876 M/S Maa Mundeshwari Automobiles, Aurangabad.

Proposal for establishment of Tractor Servicing and Repairing unit in partnership at Aurangabad.

1.0526 25

18.09.12 (Consent

with condition)

877 M/S Shree Bajrang Foam, Patna.

Proposal for establishment of 300 MT per year capacity Polyurethane Foam unit in proprietorship at Industrial Area, Hajipur, Vaishali.

2.0592 12

18.09.12 (Consent

with condition)

878 M/S Sahu Industries, Darbhanga.

Proposal for establishment of 9600 MT per year capacity Poultry Feed and Cattle Feed unit in partnership at Industrial Area, Donar, Darbhanga.

3.4057 63

18.09.12 (Consent

with condition)

879 M/S Ashoka Cattle and Poultry Feeds Pvt. Ltd., Darbhanga.

Proposal for establishment of 30,000 MT per year capacity Cattle and Poultry Feed unit at Industrial Area, Donar, Darbhanga.

4.0110 36

18.09.12 (Consent

with condition)

880 M/S Berger Colours (India) Pvt. Ltd., Patna.

Proposal for establishment of Oxide Pigment-300 MT per year, Cement Paint-240 MT per year and Wall

1.0260 16 18.09.12 (Consent

with

Report-3

76

Putty -150 MT per year capacity production unit at Industrial Area, Fatuha, Patna.

condition)

881 M/S Marps Organics, Patna. Proposal for establishment of Formaldehyde Plant unit in proprietorship at Fatuha Industrial Area, Fatuha, Patna.

3.0000 40

18.09.12 (Consent

with condition)

882 M/S Simplex Infrastructures Ltd., Kolkata.

Proposal for establishment of 25 MW Solar Power Project unit at Mahuli, Guraru, Gaya.

276.6027 1200

18.09.12 (Consent

with condition)

883 M/S Simplex Infrastructures Ltd., Kolkata.

Proposal for establishment of 25 MW Solar Power Project unit at Khaira, Suryagadha, Lakhisarai.

276.6027 1200

18.09.12 (Consent

with condition)

884 M/S Vaishali Enterprises Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 40320 MT per year capacity Para Boiled Rice Mill unit at Bela Industrial Area, Muzaffarpur.

7.5477 34 18.09.12

885 M/S Dayal Industries Ltd., New Delhi.

Proposal for establishment of 45,000 MT per year capacity Cattle Feed Unit at Industrial Area, Muzaffarpur.

6.7176 67

18.09.12 (Consent

with condition)

886 M/S Progressive Emulsion Bitumen Manufacturer(India) Pvt. Ltd., Patna.

Proposal for establishment of 96,000 MT per year capacity Bitumen Emulsion, Crum Rubber Modified Bitumen and Polymer Modified Bitumen unit at Sarsu, Atri, Gaya.

1.4850 50 18.09.12

887 M/S Jai Maa Sharda Rice Mill, Danapur Cantt., Patna.

Proposal for establishment of 14,400 MT per year capacity Modern Rice Mill unit in proprietorship at Giddha Industrial Area, Bhojpur.

2.0970 7

18.09.12 (Consent

with condition)

888 M/S Udhyam Vihar Industrial Infrastructure Corporation Ltd., Patna.

Proposal for establishment of 3500 KW Biomass Based (Rice Husk) Power Plant unit in the name of Technoculture Building Centre Pvt. Ltd. at Sonpur, Chapra.

9.5219 25 18.09.12

889 M/S Anamika Hitech Agro Industries Pvt. Ltd., Kaimur, Bhabhua.

Proposal for establishment of 19,200 MT per year capacity Modern Rice Mill unit at Kaimur, Bhabhua.

5.7518 12 18.09.12

890 M/S Kanti Nagendra Rice Mill Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 17280 MT per year capacity Rice Mill unit at Jarang Tekuna, Muzaffarpur.

8.3604 42 18.09.12

891 M/S Prabha Enterprises, Motihari.

Proposal for establishment of 10,500 MT per year capacity Rice Mill (Arwa) unit in proprietorship at Industrial Area, Bettiah, West Champaran.

1.1883 21

18.09.12 (Consent

with condition)

892 M/S Hentech Agrovet Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 42,240 MT per year capacity Para Boiled Rice and Plain Rice Mill unit at Bela Industrial Area, Muzaffarpur.

10.4645 47

18.09.12 (Consent

with condition)

893 M/S Patna Iron Pvt. Ltd., Patna.

Proposal for establishment of 1224 MT per year capacity M.S. Flat, M.S. Round, M.S. Square and M.S. Angle, E.R.W Pipe unit at Phase -3, Industrial Area, Fatuha, Patna.

11.1083 130 18.09.12

894 M/S Orion Solar Products Pvt. Ltd., Promoter-Lanco Group, Gurgaon, Haryana.

Proposal for establishment of 15 MW P.V. Solar Power Project unit each at three places in Phulli Dumar Block, Banka.

450.0000 60

18.09.12 (Consent

with condition)

895 M/S Maurya Co-operative Proposal for establishment of 9.9 400.0000 10000 18.09.12

Report-3

77

Agro Industries Ltd., Madhepura.

lakh ton per year capacity Maize Processing (Corn Starch Gluten Germ Husk, Corn Oil, Steep Liquor) unit at Kalasan, Chausa Block, Madhepura.

896 M/S Radha Krishna Hi-Tech Agro Industries Pvt. Ltd., Patna.

Proposal for establishment of 19200 MT per year capacity Rice Mill unit at Mahadevpur, Phulari, Bihta.

5.4956 12 18.09.12

897 M/S Balajee Flour Mills, Begusarai.

Proposal for establishment of 24,000 MT per year capacity Ata Chakki Mill unit in partnership at Phulwaria, Begusarai.

2.1184 25 18.09.12

898 M/S Natraj Rice Mills Pvt. Ltd., Lakhisarai.

Proposal for establishment of 96,000 MT per year capacity Rice Mill and 1.2 MW Captive Power Plant unit at Dakra, Lakhisarai.

34.6938 68 18.09.12

899 M/S Claro Energy Pvt. Ltd., New Delhi.

Proposal for establishment of 60 MW Solar Power Plant unit at Basantpur, Supaul.

660.0000 170

18.09.12 (Consent

with condition)

900 M/S Sone Ganga Feeds Pvt. Ltd., Rohtas.

Proposal for establishment of Poultry Feed unit at Bharatkasba, Karakat, Rohtas.

5.0000 25 18.09.12

901 M/S Kushaan Energy Services Pvt. Ltd., Gurgaon, Haryana.

Proposals for establishment of Biomass Based Power Projects at 04 places- 1-12 MW Biomass Based Power Project at Durgawati Block, Kaimur

2-12 MW Biomass Based Power Project at Kochas Block, Rohtas

3-12 MW Biomass Based Power Project at Dinara Block, Rohtas

4-12 MW Biomass Based Power Project at Ramgarh Block, Kaimur.

72.0602

72.0602

72.0602

72.0602

57

57

57

57

18.09.12 (Consent

with condition)

902 M/S Intech Infrastructure Pvt. Ltd., Gurgaon, Haryana.

Proposal for establishment of 25 MW Solar Plant unit at Bihiya, Ara.

312.5000 18.09.12 (Consent

with condition)

903 M/S Ganga Live Feed Pvt. Ltd., Begusarai.

Proposal for establishment of 30,000 MT per year capacity Cattle Feed unit at Ramjanpur, Begusarai.

5.3783 33 18.09.12

904 M/S Maa Padmawati Agro Foods Pvt. Ltd., Aurangabad.

Proposal for establishment of 76800 MT Rice Mill unit at Vill.- Radhua, Post-Siris, Dist.-Aurangabad.

17.4476 48 18.09.12

905 M/S Genial Polymers Pvt. Ltd., Vaishali.

Proposal for establishment of 750 MT per year capacity Pet Preform production unit at Hajipur Industrial Area, Vaishali.

1.1891 8

18.09.12

906 M/S Sone Ganga Modern Rice Mill Pvt. Ltd., Patna.

Proposal for establishment of 64 MT per day capacity Modern Arwa Rice Mill unit at Berkup, Darihat, Dehri-on-Sone, Rohtas

4.5864 41 28.11.12 &29.11.12

907 M/S Saphir Warehousing Services Pvt. Ltd., Uttar Pradesh.

Proposal for establishment of 160 MT per day capacity Energy Food production unit at Industrial Growth

5.0850 71 28.11.12 &29.11.12

Report-3

78

Centre, Giddha, Bhojpur.

908 M/S Sundram Cold Storage Pvt. Ltd., Saran.

Proposal for establishment of 4200 MT capacity Cold Storage unit under R.A.B.C. at Bhatoura, Gawandri, Marhaura, Saran.

5.3438 15 28.11.12 &29.11.12

909 M/S Sri Pawansut Food Industries Pvt. Ltd., Rohtas.

Proposal for establishment of 4 MT per hour Modern Rice Mill unit at Nokha, Rohtas.

7.4100 35 28.11.12 &29.11.12

910 M/S Mehta Feeds India Pvt. Ltd., Hazaribagh.

Proposal for establishment of 19,200 MT per year capacity Poultry Feed unit at Bela Industrial Area, Muzaffarpur.

5.9614 32 28.11.12 &29.11.12

911 M/S Shalimar Pellet Feeds Pvt. Ltd., Kolkata.

Proposal for establishment of 133.12 Lac pieces per year capacity Day-old Chicks production unit at Pandaul Industrial Area, Madhubani.

4.6600 24 28.11.12 &29.11.12

912 M/S Vikash Verma Agrotech Pvt. Ltd., Ara(Bhojpur).

Proposal for establishment of 15000 MT per year capacity Cattle Feed and Poultry Feed unit at Khajuata, Udwantnagar, Bhojpur.

1.9557 25 28.11.12 &29.11.12

913 M/S Ishan Industries, Muzaffarpur.

Proposal for establishment of 1200 MT per year capacity Corn Flakes, Potato Wafers and Fryum production unit in proprietorship at Industrial Area, Bela, Muzaffarpur.

1.4400 35 28.11.12 &29.11.12

914 M/S Guru Mahima Polytech Pvt. Ltd., Buxar.

Proposal for establishment of 72 Lac liters per year capacity Water Storage Tank and Plastic Container production unit at Industrial Area, Buxar.

1.0000 25 28.11.12 &29.11.12

915 M/S Shanti Cotton Industries, Muzaffarpur.

Proposal for establishment of 1,23,000 Kg. per year capacity Surgical Cotton, Bandage and Gauze production unit in proprietorship at Industrial Area, Bela, Muzaffarpur.

1.0942 22 28.11.12 &29.11.12

916 M/S Laheji Freezing House Pvt. Ltd., Siwan.

Proposal for establishment of 9600 MT Fruit Pulp processing unit under R.A.B.C. at Laheji, Daraunda, Siwan.

13.4312 55 28.11.12 &29.11.12

917 M/S Jai Durga Print & Packaging, New Delhi.

Proposal for establishment of 900 MT per year capacity Printed Cotton Box production unit in proprietorship at Bela Industrial Area, Muzaffarpur.

1.3116 16 28.11.12 &29.11.12

918 M/S Jain Cotton Industries, Bhagalpur.

Proposal for establishment of 1200 MT per year capacity of "B" Grade Cotton and Cotton Layer Sheet production unit in proprietorship at Industrial Area, Barari, Bhagalpur.

1.0440 30 28.11.12 &29.11.12

919 M/S Maya Foods and Drinks Pvt. Ltd., Patna.

Proposal for establishment of 18000 MT per year capacity Whole Wheat Plant(Atta Chakki) at Industrial Area, Gaya.

2.6262 21 28.11.12 &29.11.12

920 M/S J. P. Polyplasts, Patna. Proposal for establishment of 1920 MT per year capacity Plastic Granules and 1440 MT per year capacity Poly White Compound production unit in partnership at Banstal, Patna City, Patna.

1.9003 32 28.11.12 &29.11.12

921 M/S Maa Yakshini Food Processing Pvt. Ltd., Dinara, Rohtas.

Proposal for establishment of 30,000 MT per year capacity Modern Rice Mill unit at Dinara, Rohtas.

6.0000 21 28.11.12 &29.11.12

922 M/S Aricon Polymers, Proposal for establishment of 36000 1.1600 9 28.11.12

Report-3

79

Forbesganj, Araria. (Earlier, approval was given for establishment of 36000 pieces per year capacity Water Storage Tank production unit in proprietorship at Mohammadpur Jalla, Patna City, Patna in SIPB meeting held on 28.11.12 &29.11.12. Again, approval has been given for change of place as Alampur, Katchi Dargah, Patna City, Patna in the proposal for establishment of 36000 pieces per year capacity Water Storage Tank production unit in proprietorship in SIPB meeting held on 18.04.13. )

pieces per year capacity Water Storage Tank production unit in proprietorship at Alampur, Katchi Dargah, Patna City, Patna.

&29.11.12 18.04.13

923 M/S Budh Bihar Rice Mill Pvt. Ltd., Nalanda.

Proposal for establishment of 19,200 MT per year capacity Arwa Rice Mill unit at Deep Nagar, Nalanda.

3.8520 32 28.11.12 &29.11.12

924 M/S Ma Vindhya Devi Rice Mills Pvt. Ltd., Buxar.

Proposal for establishment of 38400 MT per year capacity Modern Rice Mill unit at Bharkhara, Rajpur, Buxar.

11.5128 12 28.11.12 &29.11.12

925 M/S Mangal Deep Rice Mill Pvt. Ltd, Chhauradano, East Champaran.

Proposal for establishment of 8 MT per hour Modern Para Boiled Rice Mill unit at Chhauradano, East Champaran.

18.0892 15 28.11.12 &29.11.12

926 M/S Aastha Fine Packaging Pvt. Ltd., Patna.

Proposal for establishment of 60 Lac pieces per year capacity Laminated Packaging Bags unit at Gosai Tola, Patliputra, Patna.

1.0891 20 28.11.12 &29.11.12

927 M/S Gopal & Company, Muzaffarpur.

Proposal for establishment of 600 MTPA capacity Sattu, 600 MTPA capacity Besan, 90 MTPA capacity Spice production unit in proprietorship at Industrial Area, Bela, Muzaffarpur.

1.5032 7 28.11.12 &29.11.12

928 M/S Tirupati Iron Foundry, Lakhisarai.

Proposal for establishment of 1224 MT per year capacity RPVC Pipes(Rigid PVC Pipes) production unit in proprietorship in the existing unit of Agriculture Implement at Industrial Estate, Lakhisarai.

1.5659 15 28.11.12 &29.11.12

929 M/S Shipra Agrotech Pvt. Ltd., Patna.

Proposal for establishment of 3000 MT per year capacity Organic Fertilizer, Bio Fertilizer, Bio Pesticide, Tissue Culture Plant at Nariar, Panapur, Minapur, Muzaffarpur.

1.1398 12 28.11.12 &29.11.12

930 M/S Bapuji Educational & Development Trust, Saran.

Proposal for establishment of Teacher Training College(B.Ed. College) in the name of "Ramadhar Singh Teacher Training College" at Amdhari, Ekma, Saran.

2.3780 16 28.11.12 &29.11.12 (Consent with condition)

931 M/S Laheji Freezing House Pvt. Ltd., Siwan.

Proposal for establishment of 200 MTPD capacity Roller Flour Mill unit in the name of M/S Laheji Roller Flour Mill at Laheji, Siwan.

20.2455 125 28.11.12 &29.11.12

932 M/S Om Suryay Namah, Chapra.

Proposal for establishment of 6000 MT Multi Purpose Cold Storage unit under R.A.B.C. in partnership at

9.9312 25 28.11.12 &29.11.12

Report-3

80

Mohammadpur, Garkha, Chapra.

933 M/S Ocean Filtration Pvt. Ltd., Delhi.

Proposal for establishment of 5000 pieces per year capacity Water Purifier and R.O. System production unit at Industrial Area, Muzaffarpur.

2.5635 25 28.11.12 &29.11.12

934 M/S Peerage Buildtech Pvt. Ltd., Delhi.

Proposal for establishment of 1200 MT per year capacity Extruded Cereal based Nutri Food unit at Industrial Area, Hajipur.

1.6685 20 28.11.12 &29.11.12

935 M/S Sri Ram Praikshan Cold Storage Pvt. Ltd., Jandaha, Vaishali.

Proposal for establishment of 8000 MT Multi Purpose Cold Storage unit under R.A.B.C. at Jandaha, Vaishali.

10.8305 50 28.11.12 &29.11.12

936 M/S Gajanan Siddhi Vinayak Foods Pvt. Ltd., Hajipur.

Proposal for establishment of 16 MT per hour Modern Rice Mill unit at Ibrahimpur, Padri, Chanari, Rohtas.

30.6523 50 28.11.12 &29.11.12

937 M/S Sri Radhakrishna Rice Mill, Buxar.

Proposal for establishment of 3 MT per hour Modern Rice Mill unit in proprietorship at Sarenja, Rajpur, Buxar.

1.0355 22 28.11.12 &29.11.12

938 M/S Ramond Ltd., Mumbai. Proposal for establishment of 1,30,200 pieces per year capacity Customised Garment production unit in two phases at Industrial Area, Bihta, Patna

5.2814 188 28.11.12 &29.11.12

939 M/S Alaknanda International Educational Society, Dehradun.

Proposal for establishment of Engineering College at Sahpur, Bhojpur.

16.8000 55 28.11.12 &29.11.12

940 M/S Nu Creations, New Delhi.

Proposal for establishment of 200 MT per year capacity Makhana Processing unit in proprietorship at Forbesganj Industrial Area, Araria.

1.0000 15 28.11.12 &29.11.12

941 M/S Raj Mani Agro Pvt. Ltd., Daudnagar, Aurangabad.

Proposal for establishment 05 MT per hour Modern Rice Mill unit under R.A.B.C. at Daudnagar, Aurangabad.

9.6913 50 28.11.12 &29.11.12

942 M/S SRS Multispeciality Hospital, Aurangabad.

Proposal for establishment of 100 bed Super Multi Speciality Hospital in proprietorship at Jaosiya, Aurangabad.

14.8043 60 28.11.12 &29.11.12

943 M/S Jay Maa Laxmijee Rice Mill, Bhojpur.

Proposal for establishment of 3 MT per hour Modern Rice Mill unit in proprietorship at Piro, Bhojpur.

1.0584 25 28.11.12 &29.11.12

944 M/S Parampuri Rice Mills Pvt. Ltd., Raipurchor, Sasaram.

Proposal for establishment of 5 MT per hour Modern Rice Mill unit at Raipurchor, Sasaram.

4.8350 69 28.11.12 &29.11.12

945 M/S Laxmi Food and Agro Pvt. Ltd., Samastipur.

Proposal for establishment of 8 MT per hour Modern Rice Mill unit at Growth Centre, Maranga, Purnea.

16.6481 20 28.11.12 &29.11.12

946 M/S Swastik Plast, Bhagalpur.

Proposal for establishment of 9000 pieces per year capacity Rigid PVC Pipes and Roto Moulded Plastic Storage Tank production unit in proprietorship at Barari Industrial Area, Bhagalpur.

2.4840 60 28.11.12 &29.11.12

947 M/S Tirhut Industries Ltd., Pandaul, Madhubani.

Proposal for establishment of 2.5 Lac Hecto Liter per year capacity Brewery Plant unit at Sakri, Pandaul, Madhubani.

110.7405 80 28.11.12 &29.11.12

948 M/S Ashok Raj Preserve Pvt. Ltd., Samastipur.

Proposal for establishment of 10000 MT Multi Purpose Cold Storage unit under R.A.B.C. at Sadipur, Tajpur, Samastipur.

14.1212 30 28.11.12 &29.11.12

Report-3

81

949 M/S Sinha Beverages and Eatables Pvt. Ltd., Patna.

Proposal for establishment of 120 Lac Liters per year capacity Packaged Drinking Water unit at Jalalpur, Rupaspur, Patna.

1.5000 18 28.11.12 &29.11.12

950 M/S Shubh Laxmi Flour Mills, Muzaffarpur.

Proposal for establishment of 24000 MT per year capacity Whole Wheat Atta Chakki unit in partnership at Patiyasa, Bochaha, Muzaffarpur.

2.8273 25 28.11.12 &29.11.12

951 M/S Manjusha Mini Rice Plant, Kaimur, Bhabhua.

Proposal for capacity expansion of 4 MT per hour of existing Rice Mill of 1 MT per hour in proprietorship at Sakri, Kudra.

1.6500 13 28.11.12 &29.11.12

952 M/S Lavanya Pure Food Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 45000 MT per year capacity Roller Flour Mill unit at Industrial Area, Bela, Muzaffarpur.

16.1100 50 28.11.12 &29.11.12

953 M/S Maa Vaishno Roller Flour Mill, Sasaram.

Proposal for establishment of 100 Ton per day capacity Roller Flour Mill unit in partnership at Industrial Area, Dehri, Rohtas.

6.1074 100 28.11.12 &29.11.12

954 M/S Shristi Rice Mill Pvt. Ltd., Patna.

Proposal for establishment of 4 MT per hour Rice Mill unit at Dumraitha, Kaimur, Bhabhua.

3.6250 42 28.11.12 &29.11.12

955 M/S Reliance Marts Pvt. Ltd., Gaya.

Proposal for establishment of 1200 MT per year capacity Fruits, Vegetable Processing and Preservation unit at Industrial Area, Bodhgaya, Gaya.

3.7312 42 28.11.12 &29.11.12

956 M/S Sarvoday Rice Mill Pvt. Ltd., Vaishali.

Proposal for establishment of 48000 MT per year capacity Modern Para Boiled Rice Mill unit at Balnathpur, Kudi, Patepur, Mahua, Vaishali.

20.0570 75 28.11.12 &29.11.12

957 M/S Satya Enterprises Pvt. Ltd., Patna.

Proposal for establishment of 840 MT per year capacity Fuel Oil production in the existing unit at Industrial Area, Patliputra, Patna.

1.0716 9 28.11.12 &29.11.12

958 M/S Kanchan Jangha Food Products Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 19,200 MT per year capacity Raw Rice Mill unit at Industrial Area, Bela, Muzaffarpur.

4.2570 20 28.11.12 &29.11.12

959 M/S Shree Singhal Flyash Products, Patna.

Proposal for establishment of 63.24 Lac pieces per year capacity Flyash Bricks, Pavers Blocks and Tiles production unit in proprietorship at Industrial Area, Fatuha, Patna.

3.6937 34 28.11.12 &29.11.12

960 M/S Akash Agro Developers Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 36000 MT per year capacity Para Boiled Modern Rice Mill unit at Silaut, Baijnath, Kudhani, Muzaffarpur.

11.4287 54 28.11.12 &29.11.12

961 M/S Amrapali Biotech India Pvt. Ltd., Gaziabad. Uttar Pradesh.

Proposal for establishment of 32000 MT per year capacity Corn Grit, Rice Grit and Wheat Grit production unit at Navanagar, Dumaraon, Buxar.

18.3493 175 28.11.12 &29.11.12

962 M/S Sarojani & Sarojani Cold Storage Pvt. Ltd., Jahanabad.

Proposal for establishment of 6000 MT Multi Purpose Cold Storage unit under R.A.B.C. at Neuru, Jahanabad.

9.7912 50 28.11.12 &29.11.12

963 M/S Neogenetics Foods Pvt. Ltd., Bangalore.

Proposal for establishment of 50000 MT per year capacity Maize based Poultry Feed unit at Muzaffarpur.

4.0260 58 28.11.12 &29.11.12

964 M/S Amrapali Biotech India Proposal for establishment of 5000 18.5643 120 28.11.12

Report-3

82

Pvt. Ltd., Gaziabad, Uttar Pradesh.

MT per year capacity Corn Flakes and Wheat Flakes production unit at Navanagar, Dumraon, Buxar.

&29.11.12

965 M/S Nand Rice Mill Pvt. Ltd., Patna.

Proposal for establishment of 38400 MT per year capacity Arwa Rice Mill unit at Babhinav, Jagdihspur, Bhojpur.

7.4493 47 28.11.12 &29.11.12

966 M/S Maa Bhawani Super Agro Products Pvt. Ltd., Rohtas.

Proposal for establishment of 19,200 MT per year capacity Rice Mill unit at Paduhar, Darihat, Rohtas.

5.9577 12 28.11.12 &29.11.12

967 M/S Aaryapoorna Food Processing Pvt. Ltd., Navi Mumbai, Maharastra.

Proposal for establishment of 6375 MT per year capacity Dal Mill unit at Selgarh, Saidabad, Bikram, Patna.

3.4818 17 28.11.12 &29.11.12

968 M/S Riga Sugar Company Ltd., Kolkata.

Proposal for establishment of 03 MW New Co-generation Power Plant in addition to the existing 8 MW Co-generation Power Plant in Sugar Mill at Riga, Sitamarhi.

3.5000 666 28.11.12 &29.11.12

969 M/S J.K. Plast, Patna. Proposal for establishment of 480 MT per year capacity PVC Rigid Pipes production unit in partnership at Industrial Area, Fatuha.

2.9247 22 28.11.12 &29.11.12

970 M/S Shiv Shakti Rice Mill, Dinara, Rohtas.

Proposal for establishment of 7200 MT per year capacity Arwa Rice Mill unit in proprietorship at Chorpokhar English, Dinara, Rohtas.

1.0500 30 28.11.12 &29.11.12

971 M/S Dadiji Steels Ltd., Patna. Proposal for capacity expansion of 28800 MT in the existing 62400 MT per year capacity of MS Billet/Ingot unit and 30000 MT per year capacity expansion in the existing 90000 MT per year capacity of TMT Tour(Re-rolling Mill) at Sabalpur, Patna City, Patna.

14.6903 6 28.11.12 &29.11.12

972 M/S Tridev Rice Mill, East Champaran.

Proposal for establishment of 9600 MT per year capacity Arwa Rice Mill Unit in proprietorship at Mathkolasi,Chiraiya, East Champaran.

1.1835 26 28.11.12 &29.11.12

973 M/S Sai Kamal Agro Pvt. Ltd., Patna.

Proposal for establishment of 14,400 MT per year capacity Arwa Rice Mill unit at Nagwa, Naubatpur,Patna.

2.8170 30 28.11.12 &29.11.12

974 M/S Neel Kanth Agrofood Products Pvt. Ltd., Patna.

Proposal for establishment of 150 MT per day capacity Roller Flour Mill unit at Mahuli, Parsabazar, Patna.

11.2095 115 28.11.12 &29.11.12

26.04.13

975 M/S Chanakya Agro Products Pvt. Ltd., Patna.

Proposal for establishment of 10 lac Kg per year capacity CTC-Tea production unit at Pothiya, Kishanganj.

4.7994 62 28.11.12 &29.11.12 (Consent with condition)

976 M/S Maa Mundeshwari Automobiles, Aurangabad.

Proposal for establishment of 1400 pieces per year capacity Agriculture Equipment manufacturing unit and Mahindra Tractor Workshop unit in proprietorship at Industrial Growth Centre, Aurangabad.

3.5975 28.11.12 &29.11.12

977 M/S Sunil Singh Hatchery(India) Pvt. Ltd., Hajipur(Vaishali).

Proposal for establishment of 4800 MT per year capacity Poultry Feed unit at Industrial Area, Hajipur, Vaishali.

1.0261 9 28.11.12 &29.11.12

978 M/S Maa Durgeshwari Metal Products Pvt. Ltd., Patna.

Proposal for expansion/diversification of 3000 MTA capacity MS Wire and

1.0998 26 28.11.12 &29.11.12

Report-3

83

360 MTPA capacity of Wire Nails in existing unit of 85 MTPA capacity Wire Nails at Industrial Area, Fatuha, Patna.

979 M/S Maa Agro Food Industries Pvt. Ltd., Patna.

Proposal for establishment of 19200 MT per year capacity Para Boiled Rice Mill unit at Majhion, Hasanbazar, Piro, Bhojpur.

8.5140 43 28.11.12 &29.11.12

980 M/S Pankaj International, Purnea.

Proposal for establishment of 216 MT per year capacity Button Mushroom Processing, Packaging and Canning unit in proprietorship at Maranga Growth Centre, Purnea.

2.6000 50 28.11.12 &29.11.12

981 M/S Sumitra Sahu and Sons Agro Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 24000 MT per year capacity Roller Flour Mill unit at Bela Industrial Area, Muzaffarpur.

3.5323 20 28.11.12 &29.11.12

982 M/S Jacksons Homeo, Patna.

Proposal for establishment of 48,000 Litres per year capacity Homeopathic Medicine unit in proprietorship at Industrial Area, E.P.I.P, Hajipur.

1.0035 18 02.01.13 (consent with condition)

983 M/S Maa Flour Mill, Paduhar, Darihat, Rohtas.

Proposal for establishment of 24,000 MT per year capacity Flour Mill unit in proprietorship at Darihat, Rohtas.

2.4158 15 02.01.13

984 M/S Upendra Prasad Singh Hi-Tech Constructions Pvt. Ltd., Begusarai.

Proposal for establishment of production unit of 3,000 MT per year capacity Fabricated Steel Product at Industrial Area, Barauni.

6.5831 281 02.01.13

985 M/S Eco Pavers and Bricks Pvt. Ltd., Patna.

Proposal for establishment of 72 Lac pieces per year capacity of Fly Ash Bricks unit at Badipur, Naubatpur, Patna.

1.0411 22 02.01.13

986 M/S Pashupati Modern Rice Mill Pvt. Ltd., Rohtas.

Proposal for establishment of 19,200 MT per year capacity Rice Mill unit at Sagarpur, Ghordihan, Kargahar, ,Rohtas.

4.2726 20 02.01.13

987 M/S Anirudhjee Modern Rice Mill Pvt. Ltd., Sasaram.

Proposal for establishment of 06 MT per hour Para Boiled Rice Mill unit at Sukulpur, Barki Mahuli, Kargahar, Rohtas.

8.9987 17 02.01.13

988 M/S Hero Cycles Ltd., Punjab.

Proposal for establishment of 09 Lac pieces per year capacity Cycle and Cycle Parts production unit at Bihta.

22.00 300 02.01.13

989 M/S Shiv Shakti Hatchery Pvt. Ltd., Vaishali.

Proposal for establishment of 19,200 MT per year capacity Poultry Feed unit at Industrial Area, Donar, Darbhanga.

1.9437 12 02.01.13 (consent with condition)

990 M/S Shiv Shakti Hatchery Pvt. Ltd., Vaishali.

Proposal for establishment of 25,71,400 pieces per year(Birds) capacity Hatchery unit at Industrial Estate, Samastipur.

1.0511 10 02.01.13 (consent with condition)

991 M/S Panna Lal Agro Products Pvt . Ltd., Hajipur.

Proposal for establishment of 18,000 MT per year capacity Dal Mill unit at Industrial Area, Hajipur.

2.6434 40 02.01.13 (Consent with condition)

992 M/S Shree Sai Polymers, Muzaffarpur.

Proposal for establishment of 300 MT per year capacity Laminated Multi Colour Pouch unit in Proprietorship at Industrial Area Muzaffarpur.

1.4968 14 02.01.13 (consent with condition)

993 M/S Shree Milk and Food Proposal for establishment of 6200 28.93 120 02.01.13

Report-3

84

Industries Ltd., Kolkata. MT per year capacity Milk Processing unit at Bankat, Motihari.

994 M/S Simanchal Dairy Pvt. Ltd., Kishanganj.

Proposal for establishment of 3,60,000 Litres per year capacity Milk Processing unit at Dharmganj, Kishanganj.

1.413 37 02.01.13

995 M/S Purnea Dairy, Darjeeling, West Bengal.

Proposal for establishment of 3420 Kilo Litre per year capacity Milk, Curd and Lassi unit in proprietorship at Moria Sadar, Purnea.

1.2019 25 02.01.13

996 M/S Renew Power Ventures Pvt . Ltd.,Gurgaon, Haryana

Proposal for establishment of 10 MW Solar Photo Voltaic Plant Unit at Banka/Lakhisarai/East Champaran.

100.00 08.02.13 (consent with condition)

997 M/S Renew Power Ventures Pvt Ltd, Gurgaon, Haryana.

Proposal for establishment of 50 MW Solar Voltaic Plant unit at Banka/Lakhisarai/East Champaran.

500.00 08.02.13 (consent with condition)

998 M/S Roha Dye Chem Pvt. Ltd., Mumbai.

Proposal for establishment of 25 MW Solar Photo Voltaic Power Plant Unit at Patna/Jahanabad/Nalanda.

225.00 50 08.02.13 (consent with condition)

999 M/S Welspun Renewables Energy Ltd., Delhi.

Proposal for establishment of 100 MW Solar Power Project unit at Nawada.

1000.00 200 08.02.13 consent with condition)

1000 M/S Solar Field Energy Four Pvt. Ltd. and L & T, Mumbai.

Proposal for establishment of 100 MW Solar Power Project Unit at Gaya/Hajipur.

1050.00 2875 08.02.13 (consent with condition)

1001 M/S Dayal Products Pvt. Ltd., Hajipur.

Proposal for establishment of 18000 MT per year capacity Dal Mill unit at Industrial Area, Hajipur, Vaishali.

2.4380 40 08.02.13 (Consent with condition)

1002 M/S GSR Agro Mills Pvt. Ltd., Aurangabad.

Proposal for establishment of 4.5 MT per hour capacity Modern Rice Mill Unit at Growth Center, Aurangabad.

6.045 48 08.02.13

1003 M/S Shiv Shakti Mini Rice Mill, Kaimur.

Proposal for 2 MT per day capacity expansion of existing Rice Mill unit in proprietorship at Chakiya, Durgawati , Kaimur.

1.32 9 08.02.13

1004 M/S Shri Hanuman Mini Rice Mill, Kaimur.

Proposal for 2 MT per hour capacity expansion of existing Rice Mill in proprietorship.

1.3800 9 08.02.13 (Consent with condition)

1005 M/S Golden Flour Mill Pvt. .Ltd., Kaimur.

Proposal for establishment of 9000 MT per year capacity Flour Mill unit for production of Maida, Atta, Suzi at Bharkhar, Kaimur.

8.00 35 08.02.13

1006 M/S Jai Mata Rani Rice Mill, Mohania, Kaimur.

Proposal for establishment of 02 MT per hour capacity Arwa Rice Mill Unit in proprietorship at Bharkhar, Mohania, Kaimur.

1.38 8 08.02.13

1007 M/S Pushpanjali Mini Rice Mill, Kaimur.

Proposal for capacity expansion of 02 MT per hour in the existing Arwa Rice Mill unit in proprietorship at Bharkhar, Patelnagar, Mohania, Kaimur.

1.25 9 08.02.13

1008 M/S Jhandu Mini Rice Mill, Kaimur.

Proposal for capacity expansion of 02 MT per hour in the existing Rice

1.25 9 08.02.13

Report-3

85

Mill unit in proprietorship at Bharkhar, Mohania, Kaimur.

1009 M/S Maa Mundeshwari Flour Mill Pvt. Ltd., Mohania, Kaimur.

Proposal for establishment of 10,800 MT per year capacity Flour Mill unit for Atta, Maida , Suzi at Mohania, Kaimur.

8.50 23 08.02.13

1010 M/S Malahi Cold Storage Pvt. Ltd., East Champaran.

Proposal for 6000 MT capacity expansion and modernization of existing 4000 MT capacity Cold Storage under R.A.B.C. at Malahahi, Areraj, East Champaran.

11.6912 15 08.02.13

1011 M/S Maa Ambika Bhawani Industries, Patna.

Proposal for establishment of 6000 MT per year capacity Modern Rice Mill unit in partnership at Industrial Area, Fatuha, Patna.

2.4074 24 08.02.13 (consent with condition)

1012 M/S Bodhi Hotel and Resorts Pvt. Ltd., Haryana.

Proposal for establishment of Three Star Hotel at Bodhgaya, Gaya.

32.50 70 08.02.13 (consent with condition)

1013 M/S Nasco Metals Pvt. Ltd., Patna City, Patna.

Proposal for establishment of 600 MT per year capacity Hinges and Wire Nails production unit at Didarganj, Patna City, Patna.

1.0762 16 08.02.13 (consent with condition)

1014 M/S Shiv Sai Metal Products Pvt. Ltd., Patna.

Proposal for establishment of 1.5 MT per day capacity Aluminium Wire Products production unit at Maner, Patna.

1.7826 31 08.02.13

1015 M/S Devi Prasad Bhimseria Hospital Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 112 bed Hospital and Diagnostics Facility at Purani Gudri, Muzaffarpur.

8.3568 97 08.02.13

1016 M/S Nath Consumer Products Pvt. Ltd., Hajipur.

Proposal for capacity expansion of 3600 MT per year capacity in the existing Fruit and Vegetable Processing unit at Industrial Area, Hajipur.

3.0429 23 08.02.13

1017 M/S Meceka Graphite Pvt. Ltd., Maharashtra.

Proposal for establishment 75,000 pieces per year capacity Graphite Products- Crucible, Dies and Mould production unit at Jamalpur Industrial Area, Munger.

1.32 31 08.02.13

1018 M/S Raveena Rice Mills India Pvt. Ltd., Buxar.

Proposal for establishment of 19,200 MT per year capacity Modern Rice Mill unit at Dehariya, Basudhar, Buxar.

6.8487 15 08.02.13

1019 M/S Sona Biscuits Ltd., Kolkata.

Proposal for capacity expansion of 8000 MT per year capacity expansion in the existing Biscuit unit of 15000 MT per year capacity at Industrial Area, Hajipur.

20.2019 35 08.02.13

1020 M/S Arena Food and Agro Industries Pvt. Ltd., Sheikhpura.

Proposal for establishment of 14,400 MT per year capacity Arwa Rice Mill unit at Maharath, Sheikhpura.

1.5090 21 08.02.13

1021 M/S Abhyodya Agro and Infrastructure Pvt .Ltd., Kaimur, Bhabhua.

Proposal for establishment of 12,000 MT per year capacity Seeds Processing unit-cum-Seed Research Centre at Araiya, Chand, Kaimur.

2.0305 8 08.02.13

1022 M/S Pristine Mega Food Park Pvt. Ltd., New Delhi.

Proposal for establishment of Mega Food Park at Mansi, Khagaria.

146.00 10790 08.02.13

1023 M/S Neelkamal Steels Pvt. Ltd., Patna.

Proposal for capacity expansion of 30,000 MT per year M.S. Billet and 30,000 MT per year T.M.T. Tor in

20.0300 21 08.02.13

Report-3

86

the existing unit of M.S. Ingot and T.M.T. Tor at Sabalpur, Patna.

1024 M/S Kalpshrijan Rice Mill Pvt. Ltd., Kaimur, Bhabhua.

Proposal for establishment of 24,000 MT per year capacity Modern Rice Mill unit at Rewra, Mohania, Kaimur, Bhabhua.

5.2907 58 08.02.13

1025 M/S Bihar Trade Tower(Joint Venture of M.V. Hotels and Projects Pvt. Ltd. And Ashwarya Foundation), Patna.

Proposal for establishment of I.T. Park in the name of M/S Bihar Trade Tower in a joint venture by M/S M.V. Hotels and Projects Pvt. Ltd. And M/S Ashwarya Foundation at Patliputra Industrial Area, Patna.

98.78 15 08.02.13 (consent with condition)

1026 M/S Sunny Star Hotels Pvt. Ltd., Patna.

Proposal for establishment of 4 Star Hotel and restaurant at South Gandhi Maidan, Patna.

31.6768 33 08.02.13 (consent with condition)

1027 M/S Prakash Roller Flour Mills Pvt. Ltd., Gaya.

Proposal for establishment of Three Star Hotel at Bodhgaya, Gaya.

40.80 350 08.02.13 (consent with condition)

1028 M/S Pankaj Nirala Steel Pvt. Ltd., Purnea.

Proposal for establishment of 55.92 T.P.D capacity Iron Ingot unit at Kathpul Chowk, Kasba, Purnea.

4.1888 30 08.02.13

1029 M/S Patliputra Infotech Park Pvt. Ltd., Patna.

Proposal for establishment of I.T Services, I.T. Enabled Services and I.T. Industries at Patliputra Colony, Patna.

9.79 1000 08.02.13 (consent with condition)

1030 M/S Uno Digital Pvt. Ltd., Patna.

Proposal for capacity expansion of Software, I.T. Park at Industrial Area, Patna.

20.2370 582 08.02.13

1031 M/S Foot Steps of Buddha Hotels Pvt. Ltd., Mumbai.

Proposal for establishment of International Convention Centre and Star Category Hotel at Bodhgaya, Gaya.

112.10 150 08.02.13 (consent with condition)

1032 M/S Mithila Polymers Pvt. Ltd., Darbhanga.

Proposal for establishment of unit for production of 480 MT per year capacity P.V.C. Rigid Pipes at the New Industrial Estate, Bela, Muzaffarpur.

1.9306 20 08.02.13 (consent with condition)

1033 M/S Sitwanto Devi Mahila Kalyan Sansthan, Jamshedpur.

Proposal for establishment of Medical College and Hospital in the name of Netaji Subhash Medical College at Dumri, Bihta, Patna.

53.50 150 08.02.13

1034 M/S Ayesha Export Pvt. Ltd., Kolkata.

Proposal for establishment of 7.66 Lac Kg Made-Tea per year capacity production unit at Bagalbari, Pothia, Kishanganj.

4.9039 22 08.02.13 (consent with condition)

1035 M/S Dhiraj Herbs Pvt. Ltd., Patna.

Proposal for establishment of 7,200 MT per year capacity Processed Fruits, Vegetables and Ayurvedic Medicine (Herbal Products) production unit at Industrial Area, Bihiya, Bhojpur.

10.3798 79 08.02.13

1036 M/S Universal Agro Corporation Ltd., Begusarai.

Proposal for establishment of 38,400 MT per year capacity Rice Mill unit at Bagrahadih, Barauni, Begusarai.

17.7941 18 08.02.13

1037 M/S V N Udyog Pvt. Ltd., Bhagalpur.

Proposal for establishment of 15,360 MT per year capacity Rice Mill unit at Barari Industrial Area, Bhagalpur.

3.9609 48 08.02.13

1038 M/S Arya Agrofoods Pvt. Ltd., Sasaram.

Proposal for establishment of 28,800 MT per year capacity Modern Rice

5.9257 54 08.02.13

Report-3

87

Mill unit at Adampur, Sasaram, Rohtas.

1039 M/S Shivnandni Agro Pvt. Ltd, East Champaran.

Proposal for establishment of 24,000 MT per year capacity Rice Mill unit at Adapur, East Champaran.

4.4404 54 08.02.13

1040 M/S Shree Riddhi Siddhi Agriproducts Pvt . Ltd., Bettiah.

Proposal for establishment of 03 MT per hour Rice Mill and Pulse unit at Kumarbagh, Industrial Area, Bettiah.

1.4752 35 08.02.13

1041 M/S Gauri Shankar Agriproducts Pvt . Ltd., West Champaran.

Proposal for establishment of 12,600 MT per year capacity Modern Rice Mill unit at Satahi, Chanpatia, West Champaran.

1.5835 35 08.02.13

1042 M/S Kalawati Manas Rice Mill Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 30,240 MT per year capacity Para Boiled Rice Mill unit at Chandua Tola, Barkurwa, Kurhani, Turki, Muzaffarpur.

5.8850 29 08.02.13

1043 M/S Jai Mata Di Industries, Vaishali.

(1) Proposal for establishment of 5,49,120 pieces per year capacity Plastic Moulded Chair production unit in partnership at Industrial Area, Kumarbagh, Bettiah.

(2) Proposal for establishment of 5,49,120 pieces per year capacity Plastic Moulded Chair production unit in partnership at Industrial Area, Samastipur.

3.5942 3.2862

27 27

08.02.13 (consent with condition)

1044 M/S Hindustan Medicines Pvt. Ltd., Kolkata.

Proposal for establishment of 95,730 Litres per year capacity Drugs and Pharmaceuticals Formulation unit at Fulwaria, Barauni, Begusarai.

3.3500 27 08.02.13

1045 M/S Laxmi Mini Rice Mill, Rohtas.

Proposal for establishment of 6400 MT per year capacity Arwa Rice Mill unit in proprietorship at Bilaspur, Kargahar, Rohtas.

1.3624 9 08.02.13

1046 M/S Indian Potash Ltd., Chennai.

Proposal for establishment of 60,000 MT per year capacity Sulphuric Acid production unit at Industrial Area, Muzaffarpur.

29.0701 50 08.02.13 (consent with condition)

1047 M/S Santosh Kumar Gupta Rice Mill Pvt. Ltd., Fatuha, Patna.

Proposal for establishment of 4 Ton per hour Rice Mill unit at Industrial Area, Fatuha, Patna.

4.8361 12 08.02.13 (consent with condition)

1048 M/S Swastik Rice and Chura Mill, Purnea.

Proposal for establishment of 19,200 MT per year capacity Rice Mill and 21.6 MT per day capacity Chura Mill unit in partnership at Industrial Growth Centre, Maranga, Purnea.

3.3000 54 08.02.13 (consent with condition)

1049 M/S Lali Atta Mill L.L.P, Gopalganj.

Proposal for establishment of 18,000 MT per year capacity Whole wheat Atta Mill unit in partnership.

4.1180 34 08.02.13

1050 M/S Rupam Manufacturing and Trading Pvt. Ltd., Katihar.

Proposal for establishment of 30,000 MT per year capacity Cattle Feed and Poultry Feed unit at Industrial Growth centre, Maranga, Purnea.

3.4740 36 08.02.13

1051 M/S Maharashtra Feeds Pvt. Ltd., Delhi.

Proposal for establishment of 38,400 MT per year capacity Cattle feed and

6.31 39 08.02.13

Report-3

88

Poultry Feed unit at Industrial Area, Bela, Muzaffarpur.

1052 M/S Harsh Fresh Agro Foods Pvt. Ltd., Patna.

Proposal for establishment of 14,400 MT per year capacity Rice Mill Unit at Lakhna Balipur, Patna.

2.3348 12 08.02.13

1053 M/S Jai Malikaarjun Rice Mill Pvt. Ltd., Kaimur, Bhabhua.

Proposal for establishment of 15,360 MT per year capacity Rice Mill unit at Bhundi, Tekari, Mohania, Kaimur.

5.0337 12 08.02.13

1054 M/S Shiv Vijay Udyog, Araria. Proposal for capacity expansion of 7,600 MT in the existing Rice Mill of 7,600 MT in partnership at Forbesganj, Araria.

2.3457 30 08.02.13

1055 M/S Sinha Rice and Agro Pvt. Ltd., Patna.

Proposal for establishment of 19,200 MT per year capacity Rice Mill unit at Verni, Masaurhi, Patna.

2.7438 12 08.02.13

1056 M/S Rajkishori Flour & Rice Mills Pvt. Ltd., Buxar.

Proposal for establishment of 19,200 MT Rice Mill unit at Chhotka Naun, Buxar.

4.3813 12 08.02.13

1057 M/S A.B.Z. Agro Foods Pvt. Ltd., New Delhi.

Proposal for establishment of 23000 MT per year capacity Buffalo Meat Production and Processing unit at Raipur and Lodhabari, Pothia, Kishanganj.

17.30 175 08.02.13 (consent with condition)

1058 M/S A.B.Z. Agro Foods Pvt. Ltd., New Delhi.

Proposal for establishment of 27,000 MT per year capacity Blast Freezer Storage and Processing unit at Lodhabari and Raipur, Surajpur, Pothia, Kishanganj.

12.30 175 08.02.13 (consent with condition)

1059 M/S Shri Janki Food Grains Pvt. Ltd., Varanasi

Proposal for establishment of 72000 MT per year capacity Rice Bran Solvent Extraction Plant at Kudra, Kaimur.

16.8367 20 13.03.13

1060 M/S Lord Buddha Food Products Pvt. Ltd., Hajipur.

Proposal for establishment of 5.49 Lac pieces per year capacity Moulded Plastic Chair Production unit at Industrial Area, Hajipur, Vaishali.

3.3092 43 13.03.13

1061 M/S Annapurna Industries, Muzaffarpur.

Proposal for establishment of 4320 MT per year capacity Biomass Briquette production unit in partnership at Industrial Area, Bela , Muzaffarpur.

1.2608 16 13.03.13 (consent with condition)

1062 M/S Classic Hotel, Purnea. Proposal for establishment of two Star Hotel in partnership at Industrial Growth Centre, Purnea.

4.9500 60 13.03.13 (consent with condition)

1063 M/S Dev Shiva Agro Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 10,000 MT capacity Cold Storage under R.A.B.C. at Chandrahatti, Kurhani, Muzaffarpur.

15.8412 20 13.03.13

1064 M/S J.G. Foundry Ltd., Patna City, Patna.

Proposal for capacity expansion of 21,600 MT per year capacity in the existing unit of M.S. Ingot at Chimochak, Kothia, Didarganj, Patna City, Patna.

7.6912 12 13.03.13

1065 M/S Agritech Engineering Pvt. Ltd., Bangalore.

Proposal for establishment of 05 MW Solar Power Plant at Muzaffarpur

69.9715 10 13.03.13 (consent with condition)

1066 M/S Ruchi Soya Industries Ltd, Kaimur, Bhabhua.

Proposal for establishment of 10 MW Solar Power Plant at Karnpura,

85.24 10 13.03.13 consent

Report-3

89

Durgawati, Kaimur. with condition)

1067 M/S Rajput Agro Food Products, Mohania, Kaimur, Bhabhua.

Proposal for establishment of 02 MT per hour Rice Mill unit in proprietorship at Piparia, Mohania, Kaimur.

1.3843 15 13.03.13

1068 M/S Goenka Bricks Pvt. Ltd., Patna.

Proposal for establishment of 57.60 Lac pieces per year capacity Fly Ash Bricks production unit at Mahajpura, Bikaram, Patna.

2.5700 45 13.03.13

1069 M/S Chandan Agro Foods Pvt. Ltd., Patna.

Proposal for establishment of 10 MT per hour Modern Rice Mill (Para Boiled and Arwa) unit at Kanti, Muzaffarpur.

13.5900 69 13.03.13

1070 M/S Sone Ganga Seeds, Rohtas.

Proposal for establishment of 10,800 MT per year capacity Seed Processing unit at in partnership at Industrial Area, Bikramganj, Rohtas.

1.2000 30 13.03.13

1071 M/S N N Sang Biotech Pvt. Ltd., Patna.

Proposal for establishment of 86.40 Lac pieces per year capacity Fly Ash Bricks production unit at Sadatpur, Kanti, Muzaffarpur.

1.8500 15 13.03.13

1072 M/S P.S. Oil Industries Pvt. Ltd., Darbhanga.

Proposal for establishment of 12000 MT per year capacity Mustard Oil unit at Brahampur, Singhwara, Darbhanga.

8.0183 77 13.03.13

1073 M/S Manju Modern Rice Mills Pvt. Ltd., Patna.

Proposal for establishment of 6000 MT per year capacity Modern Rice Mill at Lalbagh, Dhanarua, Patna.

1.7805 21 13.03.13

1074 M/S Rathi Hatcheries Pvt. Ltd., Haryana.

Proposal for establishment of 252 Lac pieces per year capacity Chicks Production unit at Maranga Industrial Area, Purnea.

4.1247 30 13.03.13 (consent with condition)

1075 M/S Pentagon Maritime Training and Research Institute, Navi Mumbai.

Proposal for establishment of Maritime Institute nearby Patna.

15.0000 80 13.03.13 (consent with condition)

1076 M/S Harsh Tejas Packaging Pvt. Ltd., Patna.

Proposal for establishment of 7,60,800 Kg. per year capacity woven fabric bags production unit at East Pahari, New Bypass Road, Patna.

1.5818 16 13.03.13

1077 M/S Shahi Fresh Food India Pvt. Ltd., Patna.

Proposal for establishment of 10,000 MT Cold Chain, Pack House, Ripening Chamber and Logistic at Nayanagar, Hasanpur, Samastipur.

5.3987 30 13.03.13

1078 M/S Sharma Rice Mill, Sheikhpura.

Proposal for establishment of 14,400 MT per year capacity Rice Mill unit in proprietorship at Mafo, Ghatkushumbha, Barbhigha, Sheikhpura.

2.3550 30 13.03.13

1079 M/S Trikut Cement Works, Bhagalpur.

Proposal for establishment of 34,500 MT per year capacity Portland Cement, Fly Ash Bricks and Pavers Blocks and Tiles Production unit in partnership at Anadipur, Kahalgaon, Bhagalpur.

5.0662 79 13.03.13

1080 M/S Gauri Shankar Rice Mill, Kaimur, Bhabhua.

Proposal for establishment of 9600 MT per year capacity Rice Mill in proprietorship at Jagariya, Chainpur, Kaimur.

1.9669 23 13.03.13

Report-3

90

1081 M/S Savitri Memorial Trust, Aurangabad.

Proposal for establishment of Para Medical College in the name of M/S Surendra-Savitri Memorial Institute of Para Medical and Allied Sciences at Industrial Growth Centre, Aurangabad.

1.9432 21 13.03.13

1082 M/S Shiv Shakti Udyog, Kumarbagh, West Champaran.

Proposal for establishment of 03 MT per hour Arwa Rice Mill production unit in proprietorship at Industrial Area, Kumarbagh, West Champaran.

1.4818 12 13.03.13

1083 M/S Chintamaniaditya International Pvt. Ltd., Ramgarh, Mohania, Kaimur.

Proposal for establishment of 15,300 MT per year capacity Rice Mill unit at Sahuka, Ramghar, Kaimur, Mohania.

6.3000 10 13.03.13

1084 M/S Yog Badri Pharmaceuticals, Panapur, Patna.

Proposal for establishment of 1,15,000 Kg. per year capacity Amla based Food Products and Ayurvedic Medicine Production unit in proprietorship at Industrial Growth Centre, Giddha, Bhojpur.

2.6550 39 13.03.13

1085 M/S Nampa Electricals Pvt. Ltd., Howrah.

Proposal for capacity expansion of 30,000 MT per year capacity in the existing unit of Fabricated Structural Products of Iron and Steel at Patna.

30.0000 120 13.03.13

1086 M/S Sone Valley International Pvt. Ltd., Ramgarh, Kaimur, Bhabhua.

Proposal for establishment of 45,300 MT per year capacity Rice Mill unit at Sahuka, Ramgarh, Kaimur.

8.0000 15 13.03.13

1087 M/S Veena Edibles Pvt. Ltd., Begusarai.

Proposal for establishment of 14,400 MT per year capacity Arwa Rice Mill at Daulatpur Kothi, Khodawandpur, Begusarai.

2.5110 28 13.03.13

1088 M/S Samrat Laboratories, Unit-2, Samastipur.

Proposal for establishment of unit-2 for production of 16,500 Ton per year capacity Formaldehyde at Harpur Alloth, Industrial Area, Samastipur.

3.3800 49 13.03.13

1089 M/S Baba Baijnath Agro Pvt. Ltd., Aurangabad.

Proposal for establishment of 12,000 MT per year capacity Rice Mill unit at Tengra Barun, Aurangabad.

8.2283 20 13.03.13

1090 M/S Maa Chhinmastika Enterprises Pvt. Ltd., Samastipur.

Proposal for establishment of 28,800 MT per year capacity Rice Mill unit at Industrial Area, Samastipur.

9.0756 40 13.03.13

1091 M/S Shri Sita Ram Jee Modern Rice Mill Pvt. Ltd., Rohtas.

Proposal for establishment of 19,200 MT per year capacity Rice Mill unit at Karup, Bhabhani, Kargahar, Rohtas.

5.6765 20 13.03.13

1092 M/S Maa Kali Super Agro Products Pvt. Ltd., Dehri-on-sone, Rohtas.

Proposal for establishment of 19,200 MT per year capacity Rice Mill unit at Akorigola, Rajapur Road, Rohtas.

8.3535 18 13.03.13

1093 M/S Social Welfare Organization of India, Patna.

Proposal for establishment of Food Technology Entrepreneurship and Testing Laboratory at Mega Industrial Park, Bihta, Patna.

10.6900 53 13.03.13 (consent with condition)

1094 M/S Kanhaiya Jee Rice Mill Pvt. Ltd., Aurngabad.

Proposal for establishment of 06 MT per hour Modern Rice Mill unit at Industrial Growth Centre, Aurangabad.

3.9030 128 13.03.13

1095 M/S Srijagannath Cold Storage Pvt. Ltd., Samastipur.

Proposal for establishment of 10,000 MT capacity Multi Purpose Cold Storage under R.A.B.C. at Wajidpur, Samastipur.

12.6912 65 13.03.13

1096 M/S Maa Parvati Agotech & Proposal for establishment of 9,600 2.5000 30 13.03.13

Report-3

91

Food Pvt. Ltd., Natwar, Rohtas.

MT per year capacity Arwa Rice Mill at Natwar, Rohtas.

(consent with condition)

1097 M/S Babajee Rice Mill, Bhojpur.

Proposal for capacity expansion of 02 MT per hour in the existing Rice Mill in partnership at Besiyan, Jamua, Bhojpur.

3.7980 44 13.03.13

1098 M/S SAR Capital Pvt. Ltd., New Delhi.

Proposal for establishment of 10 MW Solar Photo Voltaic Power Plant unit at Sangrampur Block, Indragachi, East Champaran.

100.000 120 13.03.13 (consent with condition)

1099 M/S Telesolar Solutions Pvt. Ltd., Chennai.

Proposal for establishment of 1200 KW Solar Power Generation unit at 200 different places in addition to the existing Solar Power unit of 120 KW capacity at 20 different places in Bihar for Telecom Tower.

20.00 40 13.03.13

1100 M/S S.S. Agro Projects Pvt. Ltd., Bhojpur.

Proposal for establishment of 14,400 MT per year capacity Rice Mill unit at Gyanpura, Bhojpur.

3.8592 17 13.03.13

1101 M/S Sai Feeds Pvt. Ltd., Darbhanga.

Proposal for establishment of 05 MT per hour Poultry Feed unit at Industrial Area, Donar, Darbhanga.

1.9835 31 13.03.13

1102 M/S Kumar Food Product, Madhubani.

Proposal for establishment of 05 MT per hour Roller Flour Mill unit in partnership at Industrial Area, Jhanjharpur, Madhubani.

1.0600 11 13.03.13

1103 M/S Kisan Rice & Dal Mill, Darbhanga.

Proposal for establishment of 15,000 MT per year capacity Rice and Dal Mill unit in proprietorship at New Industrial Estate, Bela, Darbhanga.

1.7883 27 13.03.13 (consent with condition)

1104 M/S B.K. Polytech, Danapur, Digha, Patna.

Proposal for establishment of 300 Lac pieces per year capacity HDPE/PP Bags production unit in partnership at Industrial Area, Bihiya, Bhojpur.

8.8191 54 13.03.13 (consent with condition)

1105 M/S Vaishali Rice Mill Pvt. Ltd., Hajipur.

Proposal for establishment of 24,000 MT per year capacity Modern Rice Mill unit at Industrial Area, Hajipur.

5.0000 15 13.03.13

1106 M/S SNSR Infra Ventures Pvt. Ltd., Araria.

Proposal for establishment of 5000 MT capacity Grain Storage Unit under R.A.B.C. Rajganj, Narpatganj, Araria.

7.9312 15 13.03.13

1107 M/S Bihari Soya Foods Processing Pvt. Ltd., Gaya.

Proposal for establishment of 1680 MT per year capacity Soya Bari unit at Hariharpur, Bodhgaya, Gaya.

1.3704 12 13.03.13

1108 M/S Litchica Products Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 14400 MT per year capacity Fruits and Vegetable Processing unit at Industrial Area, Bela, Muzaffarpur.

5.1329 35 18.04.13

1109 M/S Zafar Industries Pvt. Ltd., Gaya.

Proposal for establishment of 4800 MT per year capacity Iron Wire and Nails production unit at Baijubigha, Bodh Gaya, Gaya.

4.1083 36 18.04.13

1110 M/S Maa Kali Rice Mill, Mohania, Kaimur.

Proposal for establishment of 04 MT per hour Arwa Rice Mill in proprietorship at Bharkhar, Mohania, Kaimur.

3.0919 20 18.04.13

1111 M/S Astha Mini Rice Mill, Kaimur.

Proposal for establishment of 03 MT per hour Arwa Rice Mill in proprietorship at Dohra, Mohania,

1.3407 19 18.04.13

Report-3

92

Kaimur.

1112 M/S New Shanti Rice Mill, Mohania.

Proposal for establishment of 03 MT per hour Arwa Rice Mill in proprietorship at Akodhi, Mohania, Kaimur.

1.4246 17 18.04.13

1113 M/S Akshay Rice Mill, Mohania, Kaimur.

Proposal for establishment of 03 MT per hour Arwa Rice Mill in proprietorship at Duhra, Mohania, Kaimur.

1.3490 18 18.04.13

1114 M/S Shivam Rice Mill, Mohania, Kaimur.

Proposal for establishment of 04 MT per hour Arwa Rice Mill in proprietorship at Bharkhar, Mohania, Kaimur.

2.2093 20 18.04.13

1115 M/S Sarojini Rice Mill, Kaimur, Bhabhua.

Proposal for establishment of 04 MT per hour Arwa Rice Mill in proprietorship at Harnathpur, Bhabhua, Kaimur.

2.3757 18 18.04.13

1116 M/S Shobhnathji Rice Mill, Kaimur, Bhabhua.

Proposal for establishment of 03 MT per hour Arwa Rice Mill in proprietorship at Nibi, Chand, Kaimur.

1.2871 21 18.04.13

1117 M/S Puja Rice Mill, Rohtas

Proposal for establishment of 04 MT per hour Rice Mill in proprietorship at Beda More, Sarai, Shivsagar, Rohtas.

2.6756 20 18.04.13

1118 M/S Dharti Agro Food Products, Muzaffarpur.

Proposal for establishment of 60 MT per day capacity Whole Wheat Flour Mill in partnership at Bela Industrial Area, Muzaffarpur.

2.1186 25 18.04.13

1119 M/S Jai Bajrang Agro Farm Pvt. Ltd., Rohtas.

Proposal for establishment of 38400 MT per year capacity Rice Mill at Harnathpur, Kochas, Rohtas.

11.1000 40 18.04.13

1120 M/S Kisan Rice Industries, Gopalganj.

Proposal for establishment of 04 MT per hour Modern Rice Mill in partnership at Chanpatti, Gopalganj.

4.5691 25 18.04.13

1121 M/S Maharshi Badri Ayurved, Patna.

Proposal for establishment of 115 MT per year capacity Awala based Food Product and Ayurvedic Medicine production unit in proprietorship at Industrial Growth Centre, Giddha, Ara, Bhojpur.

2.6550 39 18.04.13

1122 M/S Aditi Deva Mills Pvt. Ltd., Patna.

Proposal for establishment of 06 MT per hour Boiled Rice Mill at Barun, Aurangabad.

7.6284 40 18.04.13

1123 M/S C G Foods India Pvt. Ltd., Delhi.

Proposal for establishment of 6000 MT per year capacity Noodles production unit at Industrial Estate, Maranga, Purnea.

22.7500 450 18.04.13 (consent with condition)

1124 M/S Shree Sai Organic Foods Pvt. Ltd., Bettiah.

Proposal for establishment of 38400 MT per year capacity Rice Mill at Bettiah, West Champaran.

21.0500 87 18.04.13 (consent with condition)

1125 M/S Shanta Nursing Institute, Aurangabad.

Proposal for establishment of ANM Nurses Training Institute by Trust at Industrial Growth Centre, Aurangabad.

1.0116 27 18.04.13

1126 M/S Amar Jyoti Industries Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 38400 MT per year capacity Para Boiled Rice Mill at Jamlabad, Mushari, Minapur, Muzaffarpur.

18.3316 20 18.04.13

1127 M/S Pawandeo Rice Mill, Proposal for establishment of 19200 3.2804 12 18.04.13

Report-3

93

Kaimur. MT per year capacity Rice Mill in proprietorship at Pachpokhari, Kudra, Kaimur.

1128 M/S Hotel Simna International, Muzaffarpur.

Proposal for establishment of Hotel in the name of Hotel Simna International in partnership at Maripur, Muzaffarpur.

4.5665 41 18.04.13

1129 M/S Reliance Marts Pvt. Ltd., Gaya.

Proposal for establishment of 3360 MT per year capacity Soya Nuggets and Vermicelli at Bodh Gaya, Gaya.

2.0338 48 18.04.13

1130 M/S Prakash Udyog, Patna. Proposal for capacity expansion from 27 Lakh Bottles per year capacity to 82.80 Lakh Bottles in the existing units of Packaged Drinking Water production unit in partnership at Industrial Estate, Patna.

1.3500 16 18.04.13 (consent with condition)

1131 M/S Jamuna Nursing Home Pvt. Ltd., Vaishali.

Proposal for establishment of 50-55 Ton per day capacity Flour Mill at Chakmadhin, Jandaha, Vaishali

8.5829 18.04.13 (consent with condition)

1132 M/S Wayss Food Products Pvt. Ltd., Hajipur, Vaishali.

Proposal for establishment of 2640 MT per year capacity Ice-cream production unit at Hajipur, Vaishali

2.4309 30 18.04.13 (consent with condition)

1133 M/S Vishwakarma Rice Mill, Rohtas.

Proposal for establishment of 15000 MT per year capacity Rice Mill unit in partnership at Industrial Area, Barun, Aurangabad.

2.3354 24 18.04.13 (consent with condition)

1134 M/S Madhan Foods and Bakers Pvt. Ltd., Patna.

Proposal for establishment of 2.5 MT per day capacity Mechanised Bakery Products, Bread Rusk, Baked Biscuit Production unit at Patliputra Industrial Area, Patna.

1.5882 15 18.04.13

1135 M/S Nilnikhil Cement Manufacturing (India) Pvt. Ltd., Lakhisarai.

Proposal for establishment of 30,000 MT per year capacity Cement Plant unit at Khemtarini Asthan, Suryagarha, Lakhisarai.

1.6482 27 18.04.13 (consent with condition)

1136 M/S Angel Papers Pvt. Ltd., Bettiah.

Proposal for establishment of 12000 MT per year capacity Craft Paper Production unit at Industrial Area, Bettiah.

8.1497 41 18.04.13 (consent with condition)

1137 M/S Jai Bajrang Modern Agro Products Pvt. Ltd., Rohtas.

Proposal for establishment of 19200 MT per year capacity Rice Mill unit at Pahari, Babhani, Kargahar, Rohtas.

9.5635 18 18.04.13

1138 M/S Raghubash International Pvt. Ltd., Kaimur.

Proposal for establishment of 04 MT per hour Rice Mill unit at Devhaliya, Ramgarh, Kaimur, Mohania.

9.5800 20 18.04.13

1139 M/S Maa Ambey Anshika International Pvt. Ltd., Mohania, Kaimur.

Proposal for establishment of 04 MT per hour Rice Mill unit at Kavilaspur, Durgawati, Kaimur.

9.5100 20 18.04.13

1140 M/S Maa Mundeshwari Mini Rice Mill, Rohtas.

Proposal for capacity expansion from 02 MT per hour to 06 MT per hour in the existing Rice Mill unit in proprietorship at Barhari, Kargahar, Rohtas.

3.4500 8 18.04.13

1141 M/S Anvi Food & Beverages Pvt. Ltd., New Delhi.

Proposal for establishment of 04 MT per hour Rice Mill unit at Industrial Growth Centre, Maranga, Purnea.

6.7179 18 18.04.13 (consent with condition)

1142 M/S Vinayak Binod Agro Proposal for establishment of 04 MT 5.8210 10 18.04.13

Report-3

94

Product Pvt. Ltd., Kaimur. per hour Rice Mill unit at Sultanpur, Ramgarh, Kaimur.

1143 M/S Janhvi and Shrishti Agro Product Pvt. Ltd., Kaimur.

Proposal for establishment of 04 MT per hour Rice Mill unit at Sahuka, Ramgarh, Kaimur.

9.9400 20 18.04.13

1144 M/S Kisan Food Processing Udyog, Darbhanga.

Proposal for establishment of 13000 MT per year capacity Para Boiled Rice Mill unit in partnership at New Industrial Estate, Bela, Darbhanga.

5.4652 24 18.04.13

1145 M/S Vikash Agro Industries Pvt. Ltd., Nalanda.

Proposal for establishment of 04 MT per hour Para Boiled Rice Mill unit at Sartha, Chandi, Nalanda.

7.9745 18 18.04.13

1146 M/S Chandra Palace, Muzaffarpur.

Proposal for establishment of Hotel Project unit in proprietorship at Maripur, Muzaffarpur.

3.1674 35 18.04.13

1147 M/S Skyfisher Airways Ltd., New Delhi

Proposal for Air Connectivity at JPNI Airport, Patna and its vicinity.

46.5000 370 18.04.13

1148 M/S Tara Proteins Pvt. Ltd., Kolkata.

Proposal for establishment of 25200 MT per year capacity Biscuit production unit at Bihta Industrial Estate, Patna.

41.0129 275 18.04.13 (consent with condition)

1149 M/S Osard, Patna. Proposal for establishment of Educational/Technical Institute in the name of "Centre for Leadership Development" at Mega Industrial Park, Bihta, Patna.

9.0974 27 18.04.13 (consent with condition)

1150 M/S Inspira Enterprise India Pvt. Ltd., Mumbai.

Proposal for establishment of 60 MW Solar Photo Voltaic Power Plant at Khulsa, Jamo Bazar, Goriakothi, Siwan.

660.0000 140 18.04.13 (consent with condition)

1151 M/S Sanwara Pet Industries, Patna.

Proposal for capacity expansion from 480 MT per year capacity to 960 MT per year capacity in the existing unit of Pet Preform in proprietorship at Simli Morarpur, Devi Asthan, Kotia, Patna City.

1.1277 6 18.04.13

1152 M/S Herbal Remedies India Pvt. Ltd., Patna.

Proposal for establishment of Ayurvedic Medicine Production and Super Specialist Ayurvedic Hospital and Research Centre at Anandichak, Navhatta, Rohtas.

1.2500 210 18.04.13

1153 M/S Life Plus Food, New Delhi.

Proposal for establishment of Corn Flakes/Cereals, Soya Milk and Paneer, Kefir, Fruit Juice and Fruit Purees/Crushed, Dehydrated Fruits and Vegetables production unit in two phases in proprietorship at Industrial Area, Bhagalpur.

1.9823 31 18.04.13 (consent with condition)

1154 M/S ARG (Groups), Hajipur. Proposal for establishment of (i) PVC Pipes(ii) PVC Fittings (iii) Casing and Capping (iv) PVC Electrical Boards (v) Electrical Fans (vi) Lighting Systems (vii) Sewing Machine (viii) Electrical Transformer in partnership at E.P.I.P., Hajipur.

13.0300 112 18.04.13 (consent with condition)

1155 M/S PMB Industries, Patna City, Patna.

Proposal for establishment of 672 MT per year capacity Disposable Glasses and Cups production unit in partnership at Industrial Area, Fatuha, Patna.

3.3933 44 18.04.13 (consent with condition)

1156 M/S Super Aadarsh Private ITI, Promoter- Super Aadarsh

Proposal for establishment of ITI in the name of Super Aadarsh Private

1.6608 14 18.04.13 (consent

Report-3

95

ITC, Aurangabad ITI in proprietorship at Growth, Jasoiya, Aurangabad.

with condition)

1157 M/S Budha Caprient, Patna. Proposal for establishment of 3135 MT per year capacity Edible Oil production unit in partnership at Industrial Area, Fatuha, Patna.

3.1663 40 18.04.13 (consent with condition)

1158 M/S Pramila Enterprises, Purnea.

Proposal for establishment of 24000 Litres per day capacity Packaged Drinking Water unit in proprietorship at Growth Centre, Maranga, Purnea.

1.0827 23 18.04.13 (consent with condition)

1159 M/S Sita Agrofoods Industries Pvt. Ltd., Patna.

Proposal for establishment of 19200 MT per year capacity Rice Mill at Maranga Industrial Area, Purnea.

6.0352 26 18.04.13 (consent with condition)

1160 M/S T & P Agro Multifood Pvt. Ltd., Darbhanga.

Proposal for establishment of 50 MT per day capacity Roller Flour Mill unit at Singhwara, Darbhanga.

6.7001 15 18.04.13 (consent with condition)

1161 M/S Jai Aryan Agro Pvt. Ltd., Motihari

Proposal for establishment of 06 MT per hour capacity Rice Mill at Kesaria, Motihari.

9.6792 46 18.04.13 (consent with condition)

1162 M/S Dhanlaxmi Vastu Pvt. Ltd., Kolkata.

Proposal for establishment of 72000 MT per year capacity Rice Mill at Aurangabad Industrial Area, Aurangabad.

22.5469 61 18.04.13 (consent with condition)

1163 M/S Ashwini Polymers, Raipur, Rajasthan.

Proposal for establishment of 960 MT per year capacity Rigid PVC Pipe production unit in proprietorship at Growth Centre, Aurangabad.

1.2839 25 18.04.13 (consent with condition)

1164 M/S Om Prakash Roller Flour Mill Pvt. Ltd., Nalanda.

Proposal for establishment of 80 Ton per day capacity Roller Flour Mill and 40 Ton per day capacity Whole Wheat (Atta Chakki) unit at Hasanpur, Rajgir, Nalanda.

7.9000 60 18.04.13 (consent with condition)

1165 M/S Shri Ganpati Rice Mill and Rice Bran Industries Pvt. Ltd., Muzaffarpur.

Proposal for establishment of 400 MT per year capacity Rice Bran based Solvent Extraction unit at Gaighat, Muzaffarpur.

27.6500 20 18.04.13 (consent with condition)