surveying and civil engineering materials unit i basic...
TRANSCRIPT
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
1
SURVEYING Definition:
Surveying is the art of determining the relative position of points on, above or below the earth
surface by direct or indirect measurements of distance, direction and elevation.
Objectives:
The object of survey is to prepare the map or plan, so that it may represent the area on a
horizontal plane. A plane or map is the horizontal projection of an area and shows only horizontal
distances of the points. Vertical distances between the points are however shown by contour lines or
some other methods.
Purposes of surveying:
1. To produce up to date engineering plans of the areas in which work is going to be carried out
which would be helpful for the design purpose.
2. To determine the required areas and volumes 0f land materials needed during construction.
3. To ensure the construction takes place in the correct relative and absolute position on the
ground.
4. To record the final position of the construction including any design changes.
5. To provide permanent control points from which particularly important projects can be
surveyed.
Primary division of surveying:
Plane surveying:
In this type of surveying the mean surface of the earth is considered as a plane. All
triangles formed by survey lines are considered as plane triangles in which small portions of earth
surface are taken into account and spherical shape is neglected.
Geodetic surveying:
Survey is which the shape (curvature) of the earth surface is taken in the account a higher
degree of precision is exercised in linear and angular measurement is tanned as Geodetic Survey.
A line connecting two points is regarded as an arc. Such surveys extend over large areas.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
2
Principles of surveying:
Surveying is Location of a point by measurement from other points of reference and Working
from whole to part.
Classification of surveying:
1. Classification based on the field Survey
i. Land surveying:
a. Topographical survey:
The purpose is to gather survey data about the natural and man – made features of
the land.
b. Cadastral Survey:
This is carried out to mark the boundaries of a land located within the city
municipality, etc.
c. City survey:
This is made in connection with the construction of streets, water supply systems,
sewers and other works.
ii. Marine survey: It deals with bodies of water for purpose of navigation, harbor works.
iii. Astronomical Survey: This carried out to understand the nature and the behavior of the
heavily objects such as sun or any fixed star.
2. Classification based on object of survey
i. Engineering survey: to determination of quantities or to affords sufficient data for designing
of engineering works such as roads and reservoirs.
ii. Military survey: this is used for determining points of strategic importance.
iii. Mine survey: this is exploding the mineral wealth.
iv. Geological survey: This is used for determining the strata for earth’s crust.
v. Archeological survey: This is used for unearthing relics of antiquity.
3. Classification based on Instruments used
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
3
i. Chain surveying
ii. Theodolite surveying
iii. Plane table surveying
iv. Tachometric surveying
v. Arial surveying
vi. Photographic surveying.
4. Classification based on methods employed:
i. Traverse surveying
ii. Triangulation surveying.
MEASUREMENT OF DISTANCES:
The distance between two points on the surface of earth can be determined by two methods : i.
Direct method, ii. Computative method
i. Direct method: distances measured using tapes, chains etc.
ii. Computative method: Distance measured by using Tacheometry, Triangulation.
Chain surveying:
Linear measurements.
Principle:
To provide a skeleton of frame work consisting of a number of connected triangles. The
triangles are plotted from the length of its sides, measured in the field. The frame work
consists of equilateral triangles.
Terms used in Chain surveying:
Survey station:
It is the main point on the chain line. Which can be at the beginning or at the end? These
are called Main stations.
Subsidiary station:
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
4
These are the station points which can be selected anywhere on the chain line for running
the auxiliary line. It is also called as Tie station.
Survey lines:
The lines joining the main survey stations are called the survey lines. There are three types
of survey lines, Base line, Check line and Tie line.
LEVELLING
Levelling is a branch of surveying the object of which is :
(1) To find the elevations of given points with respect to a given or assumed datum,
(2) To establish points at a given elevation or at different elevations with respect to a given
or assumed datum.
PRINCIPLES OF LEVELLING
The principle of levell lies in furnishing a horizontal line of sight and finds the vertical distance of
the points above or below the line of site. A line of sight is provided with a level, and a graduated
leveling staff provides the vertical height of a station with reference to the level line.
INSTRUMENTS USED FOR LEVELLING
The instruments commonly used in direct levelling are:
(1) A level
(2) A leveling staff.
1. LEVEL
A Level consists of the following four parts:
1. A telescope to provide line of sight
2. A level tube to make the line of sight horizontal
3. A leveling head (tribrach and trivet stage) to bring the
4. Bubble in its centre of run
5. A tripod to support the instrument.
Types of levels
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
5
1. Dumpy level
2. Wye level
3. Reversible level
4. Tilting level
Dumpy level
1. The dumpy level consists of a telescope tube firmly secured in two collars fixed by screws to the
stage carried by the vertical spindle.
2. The modern form of dumpy level has the telescope tube and the vertical spindle cast in one piece
and a long bubble tube is attached to the top of the telescope. This form is known as solid dumpy.
Following are the parts of the dumpy level:
1. TELESCOPE, 2. EYE-PIECE, 3. RAY SHADE, 4. OBJECTIVE END,
5. LONGITUDINAL BUBBLE, 6. FOOT SCREWS, 7. UPPER PARALLEL PLATE,
8. DIAPHRAGM ADJUSTING SCREWS, 9. BUBBLE TUBE ADJUSTING SCREWS,
10. TRANSVERSE BUBBLE TUBE.
• In some of the instruments, a clamp Screw is provided to control the movement of the spindle
about the vertical axis.
• For small or precise movement, a slow motion screw (or tangent screw) is also provided.
• The leveling head generally con of two parallel plates with either three-foot screws.
• The upper plate is known as tri branch and the lower plate is known as trivet which can be
screwed on to a tripod.
The advantages of the dumpy level over the Wye level are:
(i) Simpler construction with fewer movable parts.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
6
(ii) Fewer adjustments to be made.
(iii) Longer Life of the adjustments
LEVELLING STAFF
• A levelling staff is a straight rectangular rod having graduations, the foot of the staff representing
zero reading.
• The purpose of a level is to establish a horizontal line of sight.
• The purpose of the levelling staff is to determine the amount by which the station is above or
below the line of sight.
• Levelling staves may be divided into two classes
(1) Self-reading staff, (2) Target staff.
SELF-READING STAFF
There are usually three forms of self-reading staff:
(a) Solid staff
(b) Folding staff
(c) Telescopic staff (Sop with pattern).
� Fig (a) and (b) show the patterns of a solid staff in English units while (c)
and (d ) show that in metric unit.
� In must common forms, the smallest division is of 0.01 ft. or
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
7
� The above fig. shows a sop with pattern staff arranged in three telescopic lengths.
� When fully extended, it is usually of 1.4 ft (or 5 m) length. The 14 ft. staff has solid top length of
4’ 6” sliding into the central box of 4’ 6” length.
� The central box, in turn, slides into lower box of 5’ length. In the 5 m staff, the three
corresponding lengths are usually 1.5m, 1.5 m and 2 m.
� The above fig shows a folding staff usually 10 ft long having a hinge at the middle of its length. When
not in use, the rod can be folded about the hinge so that it becomes convenient to carry it from one
place to the other.
� The hundredths of feet are indicated by alternate white and black spaces, the top of a black space
indicating odd hundredths and top of a white space indicating even hundredths.
Target Staff
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
8
� Fig. shows a target staff having a sliding target equipped with vernier. The rod consists of two
sliding lengths, the lower one of approx. 7 ft and the upper one of 6 ft.
� The rod is graduated in feet, tenths and hundredths, and the vernier of the target enables the
readings to be taken up to a thousandth part of a foot.
� For readings below 7 ft the target is slided to the lower part while for readings above that, the
target is fixed to the 7 ft mark of the upper length.
� For taking the reading, the level man directs the staff man to raise or lower the target till it is
bisected by the line of sight.
� The staff holder then clamps the target and takes the reading & the Upper part of the staff is
graduated from the top downwards.
�
PROCESS OF LEVELLING
(i) INSTRUMENT STATION:
A point where instrument is set up for observations is called instrument station.
(ii) HEIGHT OF INSTRUMENT (Hi)
The elevation of line of site with respect to assumed datum is known as height of instrument.
It does not mean the height of telescope above the ground level were the level is setup.
BACK SITE: (BS)
A first site taken on a level staff held at position of known elevation is called back site. It
ascertains the amount by which the line of sight is above or below the elevation of the point. Back site
enable the surveyor to obtain the height of instrument.
FORE SITE: (FS)
The site on a level staff held at a point of unknown elevation to ascertain by what extent the
point is above or below the line of site is called fore site. Fore site enables surveyor to obtain the
elevation of the point.
CHANGE POINT: (CP)
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
9
The point at which both a fore sight and back sight are taken during the operation of levelling is
called a change point. Sights are taken from two different instrument station a fore sight ascertains the
elevation of point to establish the height of instrument at the new instrument station. The change point
is always selected on a relatively permanent point.
INTERMEDIATE SIGHT: (IS)
The F.S taken on a level staff held at points between two turning points to determine the
elevation of points is known as intermediate sight. It may be noted that for one setting of the level there
will be only a back sight and fore sight but there can be a number of intermediate sights.
ERRORS IN LEVELLING:
Errors in leveling may be categorized into
1. Personal error
2. Errors due to natural factors
3. Instrumental error
PERSONAL ERROR:-
Personal error include the following
(i) Error in sighting:
This is caused when it is difficult to see the exact coincide of the crosshairs and the staff graduation. This
may be either due to long sights or due to poor focusing of the crosshair. Some times atmospheric air,
atmospheric condition also cause on error in sighting. This error is accidental and may be classified as
compensative.
(ii) Error in manipulation:-
This is due to careless setting up of the level neither the telescope nor the tripod should be
disturbed while taking readings. The instrument should be set up on a firm ground and carefully
leveled.
Take care that the bubble is centre when the readings are observed. If the bubble is not
centered a Horizontal axis telescope gets inclined affecting the staff readings. The error is more for
long sights & less for short sights. To avoid the error the observer should develop the habit of checking
the bubble before and after taking reading.
(iii) Non Vertically of staff :
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
10
If the staff is not held vertical during observation of the staff reading the observed value will
be higher than the actual value. The staff should be held vertical using a plumb bob.
Error is reading the staff:
These error generally committed are
(i) Reading the staff up side down.
(ii) Reading top or bottom hair instead of center hair.
(iii) Concentrating the attention on decimal part of reading and entering the whole value
wrongly.
(iv) Reading the inverted staff as a vertically held staff.
Error is recording & computation:
Common errors is recording are
(i) Entering the reading in the wrong column that is B.S reading in the I.S or F.S column.
(ii) Recording the reading with digits inters change.
(iii) Omitting on entry.
(iv) Adding the F.S reading instead of subtracting with and subtracting a B.S reading instead
of adding.
Errors due to natural causes:
(i) Errors due to curvature :-
The curvature of the earth surface lowers the elevation of the station and it is directly
proportional to the square of the horizontal distance between the staff position and the point of
observation. The correction of the curvature has to be subtracted from the observe staff reading to get
correct reading. In case of ordinary leveling error due to curvature in negligible that is only 0.003m for a
sight of 300 m length.
(ii) Error due to refraction :-
The effect of refraction on the observe readings is opposite to that of the curvature.
Refraction rise the elevation of the station on the error is also professional to the square of the
horizontal distance of the station from the level. This is negligible for short sites and it’s generally
ignored in ordinary leveling.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
11
(iii) Error due to wind & sun :-
Due to strong winds it is always difficult to hold the staffs vertical due to non verticality of
the staff the observed reading are higher. The wind is also responsible for small disturbance in the
instrument level. In strong winds it’s always advisable to suspend the work.
The sun causes a considerable trouble. It’s recommended to protect the objective by an
umbrella. The effect of sun in also cause’s elongation of the staff due to increased temperature but in
ordinary leveling the changing in length is negligible.
Instrumental error:
(i) Imperfect adjustment of level:- In a perfected adjusted level a line of collimation remains
horizontal when the bubble of the level tube occupies the central position. When adjustment is not
perfect the line of collimation is either inclined upwards or downwards or observed reading are either
more a less. Such error gets compensative. If the B.S & F.S distance are kept equal as in the case of the
leveling. But in the case of inter mediate site the distance reading are thrown into error by a different
amount. Incase of leveling a steep slopes.
(ii) Defecting level tube: If the bubble of level tube is sluggish. It will remain centre even if the
bubble axis is not horizontal or on the other hand if it’s two sensitive a reasonable time is spent to bring
a bubble centre. Irregularly of curvature of the tube is also a series defect.
The effect of deflective level tube also gets neutralized if the sights are of equal length.
CONSTRUCTION MATERIALS
STONES Definition: Stone is the naturally available material and is obtained from rocks. Classifications of Rock:
� Geological
� Physical
� Chemical
Geological: Igneous rock:
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
12
The rocks which are formed by cooling of magma are known as igneous rocks which are inside earth’s surface.
Sedimentary rocks: They are formed by deposition of products of weathering on the pre existing rocks. These products due to wind, rain, frost etc... E.g.: limestone, gypsum.
Metamorphic: When the preexisting rocks are subjected to great heat and pressure they are changed in
character and forms metamorphic rocks. E.g.: marble Physical:
� Stratified rocks
� Unstratified rocks
� Foliated
Stratified:
These rocks possess planes of stratification or cleavage and such rocks can be easily being split up along these planes. Unstratified:
These rocks do not have any definite planes.
Foliated: These rocks have a tendency to be split up into definite direction only. Chemical classifications:
� Siliceous � Argillaceous � Calcareous
Siliceous: In these silica predominates. It is hard and durable.
Argillaceous: In these clay predominates. These are hard and durable.
Calcareous: In these calcium predominates. The durability depends upon the constitutes present. Qualities:
� It should be homogeneous in structure. � It should be free from cracks. � It should be easily workable. � It must be fire resistant. � It should be easily obtainable.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
13
Quarrying: � By hand tool � By blasting �
By hand tools: They are executed by pick-axes hammer, chisels, etc... By blasting: In this process explosives are used.. Uses:
o Stones are used for pavements o Used for foundations o Ballast in railways o Used for bridges, dams, etc…
Characteristics of good building stone
The characteristics of good building stone are:
a) Uniform color and Appearance
b) Uniform grain Structure
c) High Strength
d) Moderate Weight
e) Hardness
f) Toughness
g) Low Porosity and absorption
h) Well Seasoned
i) Good Workability
A GOOD BUILDING STONE SHOULD HAVE THE FOLLOWING QUALITIES:
Appearance:
For face work it should have fine, compact texture. Light colored stone is preferred as it is more
durable.
Structure:
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
14
A broken stone should not be dull in appearance and should have uniform texture free from
cavities, cracks and patches of loose or soft material. Stratifications should not be visible to naked eye.
Strength:
A stone should be strong and durable to withstand the disintegrating action of weather.
Compressive strength of building stones in practice range between 60 to 200 N/mm2.
Weight:
It is an indication of the porosity and density. For stability of structures such as dams, retaining
walls etc. heavier stones are required, whereas for arches, vaults, domes etc. light stones are used.
Hardness:
This property is important for floors, pavements, aprons of bridges; etc. The hardness is
determined by the mohs scale.
Toughness:
The measure of impact that a stone can withstand is defined as toughness. The stone used should
be tough when vibratory or moving loads are anticipated.
Porosity and absorption:
Porosity depends on the mineral constituents, cooling time and structural formation. A porous stone
disintegrates as the absorbed rain water frezes, expands and causes cracking. Permissible water
absorption for some of the stoners is given in table.
Seasoning:
The stone should be will seasoned.
Weathering:
The resistance of stone against the wear and tear due to natural agencies should be high.
Workability:
Stone should be workable so that cutting, dressing and bringing it out in the required shape and
size may not be uneconomical.
Fire resistance:
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
15
Stones should be free from calcium carbonated, oxides of iron, and minerals having different
coefficients of thermal expansion. Limestone, however can withstand a little higher temperature ie Up
to 8000C after which they disintegrate.
Specific Gravity:
The specific Gravity of most of the stones lies between 2.3 to 2.5
Thermal Movement:
Thermal movements alone are usually not trouble some. However joints in coping and parapets
open out inletting the rain water causing trouble. An exposure of one side of marble slab to heat may
cause that side to expand and the slab warps. On cooling the slab does not go back to its original shape.
Crushing strength:
Minimum average value should be 3.5N/mm2. Strength of individual block should not fall below
the average value by more than 20 percent.
Water absorption:
It should not be more than 20 percent.
SANDS
Sand is formed by the decomposition of sand stones due to various effects of weather. Functions of sand: The sand is used in the concrete for the following purpose: Bulk: It does not increase the strength of the mortar but if bulk is increased the cost is reduced. Shrinkage: It prevents excessive shrinkage during drying Strength: It helps in the adjustment of strength by variation of its ratio with cement. Surface area: It sub divides the paste of binding material and increase the surface area. Classifications:
� Pit sand
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
16
� River sand � Sea sand
Pit sand: It is excavated from the depth of about 1m to 2m. It consists of sharp angular grains which are free from salts. River sand: It is obtained from bank of bed of river. It consist of fine rounded grain and available in clean condition. Sea sand: It is obtained from sea shores. It consists of fire randed grains and contains salt. These salts attract moisture from the Atmosphere and not used for engineering purpose. Classification:
� Fine sand � Coarse sand � Gravelly
Fine sand: The sand passing through a screen with clear opening 1.5875mm and used for plastering. Coarse sand: This sand passing through a screen with clear with clear openings 3.175mm and used for masonry. Gravelly sand: This sand passing through a screen with clear openings as 7.62mm and used for concrete work. BULKING OF SAND: The presence of moisture in sand increases the volume of sand and it is known as bulking of sand. PROPERTIES:
1. It should be chemically inert 2. It should be clean. 3. It should not contain salts. 4. It should be well graded.
TESTS:
CLAY: 1. A glass of water is taken out and sand is placed. It is vigorously shaken and allowed to
settle. If clay is present its layer is formed on top of sand.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
17
2. The color of sand will indicate the purity. 3. Add sodium hydroxide to sand and stride. If the color of solution changes to brown and it indicates the presence of organic matter.
BRICKS
It is the oldest material and it is extensively used as leading building material because of its (a) durability
(b) strength
(c) low cost
(d) Availability.
COMPOSITION: (a) alumina (b) oxide of iron (c) silica (d) magnesia (e) lime Alumina:
A good brick contains about 20% to 30% alumina. Silica:
A good brick contains about 50% to 60% of silica. It prevents cracking. Lime:
A small quantity of lime not exceeding 5% is desirable. It prevents shrinkage. Oxide of iron:
A small quantity of oxide 5% to 6% is desirable. It also imports red color. Harmful ingredients: Lime & alkalis: The excess of lime and alkalis causes the brick to melt and lost its shape. Iron pyrites: If iron pyrites are present in brick they are disintegrated during burning. Organic matter: This organic matter in brick earth assists in burning. But if such matter is not completely burnt the bricks become porous. QUALITIES OF GOOD BRICK:
� It should be table moulded. � It should have uniform color � It should be free from cracks � It should have low thermal conductivity
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
18
� It should not break on hard ground when dropped from a height of 1m. � It should have min strength of 3.5N/mm2.
CLASSIFICATION:
(a) unburnt or sun dried bricks (b) burnt bricks
Unburnt bricks: They are dried with the help of heat received from the sun after the process of moulding.
Burnt bricks: They are classified into four categories:
1. first class 2. second class 3. third class 4. Fourth class.
First class: Used for superior works.
Second class: Used at places where brick work is to be provided with coat of plaster. Third class:
Used for temporary works and at places where rainfall is not heavy Fourth class:
They used as aggregates for concrete in foundations, floors.
Uses: I. It is used for construction of walls. II. It is used as refractory material III. It is used in construction of chimney IV. Bricks with cavities are known as hollow bricks used for front wall structures V. Sand-line bricks used for ornamental works
MOULDING OF BRICKS:
Hand moulding: It is done by rectangular box with open at top and bottom. it may be wood or steel.
Types: Ground moulding: Table moulding
GROUND MOULDING: First small portion of ground is cleared and leveled. Fine sand is sprinkled over it. Moulding is dipped in water and kept on ground and clay is pressed by hand so that all
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
19
corners are filled with clay sand excess is scraped by strikes. Process is repeated fill the ground is covered with bricks. After that bricks become dry, it is sent for next of drying.
TABLE MOULDING:
Instead of ground in table the table used is the size of 2mx1m.
TABLE MOULDING: When bricks are manufactured in huge quantity these are done by machines. The machine
containing the rectangular opening under pressure, it is cut into strips by wire fixed in frames.
DRYING OF BRICKS: This is done in drying yards. Bricks are stacked in 8 to 10 bricks in each row and they are dried for
5 to 12 days
BURNING: It imports hardness and strength of bricks. It must be done carefully because unburnt bricks remains soft and over burnt bricks become brittle and hence break easily. It is done in kilns.
HOLLOW BLOCKS:
Hollow blocks are manufactured from a thoroughly ground; lump free, well mixed clay mass of
medium plasticity to allow moulding. The process of manufacture is similar to that of stiff mud bricks.
These are used to reduce he dead weight of the masonry and for exterior as well as partition walls.
Types:
Type A – Blocks with both faces keyed for plastering or rendering.
Type B – Blocks with both faces smooth for use without plastering or rendering on either side.
Type C- Blocks with one face keyed and one face smooth.
Length Breadth Height (Cm) (Cm) (Cm) 19 19 9 29 9 9 29 14 9
REFRACTORY BRICKS:
Refractory bricks are made from fire clay. The process of manufacturing is similar to ordinary
brick, but burnt at very high temperatures in special kilns. Fire clay mortar is used to lay refractory
bricks.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
20
Properties:
1. The color is whitish yellow or light brown
2. The water absorption of fire clay bricks varies from 4-10%
3. The compressive strength ranges between 150 to 200 N/mm2.
Acid Refractory Bricks:
It consists of silica bricks and ganister bricks (Ganister- a hard colored sand stone containing 10
per cent clay and 2 percent of lime), used in lining furnaces having acidic slag, steel industry and coke
oven.
Basic refractory bricks:
It consists of magnesia bricks (magnesia minimum 85 percent calcium oxide maximum 25 percent
and silica maximum 5.5 percent) and bauxite bricks(minimum 85 percent aluminum oxide and maximum
20 percent clay).these are highly resistant to corrosion and are used for lining furnaces having basic
slag.
Natural refractory Bricks:
It consists of chromoite bricks (50 percent chrome and iron ore containing 30 percent iron oxide
and bauxite containing 15 percent aluminum and 5 percent silica) chrome magnesite bricks(Cr2o3 18
percent MgO 30 percent ) spinel and forsterite bricks. The neutral Refractory bricks are suitable at
places where acidic and basic linings are to be separated, e.g. for lining copper reverberatory furnace.
Bricks are classified on the basis of strength and durability as
First class Bricks
1. There are thoroughly burnt with deep red, cherzy or copper colours.
2. The surface should be smooth and rectangular, with parallel, sharp and straight edges and
square corners.
3. They should be free form flaws, cracks and stones.
4. They should have uniform lexhure.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
21
5. No impression should be left on brick when a scratch is made by a figer nail.
6. Later absorption should be 12.15% of its dry weight when immersed in cold water for 24 hours.
7. The fractured surface of the brick should not shour lumps of line.
8. The crushing strength of the brick should not be less then 10.5 N / mm2
Second class Bricks
i. Small cracks and distortions are permitted.
ii. A little higher woler absorption of about 16- 20% of its dry weight is allowed
iii. The crushing strength not is less than 7.0 N/mm2.
Third Class Bricks
1. These are under burnt bricks.
2. They are soft and light colored producing a dull sound when struck against each other. Water
absorption is about 25% of dry weight.
Fourth class Bricks
1. These are over burnt and badly distorted in shape and size and are brittle in nature.
2. It uses the bellas 1. of such bricks is used for foundation and floors in lime concrete and road
metal
II. On the Basis of Usage.
Common Brick
In a general multi-purpose unit manufactured economically without special reference to
appearance. These may vary greatly in strength and durability and are used for filling, backing
and in walls where appearance in of no consequence.
Facing Brick
Facing Brick are made primarily with a new to have good appearance, either of color or lexture or
both. These are durable under severe exposure and are used in founts of building walls for which
a pleasing appearance is desired.
III. On the Basis of finish.
Sand faced Brick
It has textured surface manufactured by sprinkling and or the inner surface of the mould.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
22
Rustic Brick
It has mechanically lextured finish, varying in pattern .On the basis of manufacture.
Hand made:
These bricks are hand moulded
Machine made
Depending upon mechanical arrangement, bricks are known as wire cut bricks – bricks cut from
clay extruded in a column and into brick sizes by wires.
IV. On the Basis of burning
Pale bricks: Pale bricks are under burnt
Body bricks: Body bricks are well burnt bricks occupying central portion of the kiln.
Arch Bricks: Arch Bricks are over burnt also known as clinker bricks.
Preparation of Brick Earth
1. Unsoiling
i. The soil used for making building bricks should be processed so that, it is free of gravel, coarse
sand, line and base bar particles, organic matter.
ii. About 20 cm of the top layer of the earth, normally containing stones, pebbles, gravel, tools
etc is removed after clearing the trees and vegetation.
ii. Digging:
After removing the top layer of the earth, proportions of additives such as fly ash, sandy
loom, rice husk ash, stone dust, etc. should be stored over the plane surface on volume basis. The
digging operation should be done before rains.
iii. Weathering:
Stones, gravel, pebble, roots etc are removed form the dug earth and the soil is heaped on
level ground in layer of 60 - 120 cm thickness. The soil is left in heaps and exposed to weather for
at least one month in cases where such weathering is considered necessary for the soil. This is
done to develop homogeneity in the mass of soil, particularly if they are from different sources
and also to eliminate the impurities. Soluble salts in the clay would also be eroded by rain to some
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
23
extent, which otherwise could have caused scumming at the time of burning of the bricks in the
kiln.
iv. Blending
The earth is then mixed with sandy earth and calcurious earth in suitable proportions to
modify the compositions of soil. Moderate amount of water is mixed so as to obtain the right
consistency for moulding. The mass is then mixed uniformly. Addition of water to the soil at the
damps is necessary with spacles. Addition of water to the soil at the dumps is necessary for easy
mixing and workability, but addition of water should be controlled in such a way that it may not
create a problem in moulding and drying.
V. Tempering
Tempering consists of kneeling the earth so as to make the mass shift and plasticise. It
should preferably be carried out by storing the soil in a cool place in layers of about 30 cm
thickness for not less than 36 hours. This will ensure homogeneity in the mass of clay for
subsequent process. For manufacturing good bricks, tempering is done in pug mills. And
operation is called pugging. Pug mill consists of a conical iron tube shown in figure. The mill is
sunk 60 cm it to earth. A vertical shaft with a number of horizontal arms filled with knives, is
provided at the center of tube. This central shaft is rotated. The knives cut and rough the clay and
break all the clogs or lumps when the shaft rotates.
Moulding
1. Hand moulding
a. Ground Moulding
In this process, the ground is leveled and sand in sprinkled on it. The clay is molded to the
shape with wooden moulds on the leveled surface. The molded bricks are left on the ground for
drying, such bricks don’t have frog and the lower brick surface becomes too rough. To overcome
these defects, moulding blocks or boards are used at the base of the mould. The process consists
of shaping in hands a lump of well-pugged earth, slightly more than that of the brick volume. The
molder then gives blows with his lists and process the earth properly in the corners of the mould
with his thumb. The surplus clay on the top surface is removed with a sharp edge metal plate
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
24
called strike.
b. Table Moulding
The bricks are molded on stock boards nailed on the moulding table. Stock boards have
the projection for forming the frog. The process of filling clay in the mould is the same as
explained above. After this thin band called pollet in placed over the mould. The mould
containing the brick is then smartly lifted along with the stock board and inverted so that the
molded clay along with the mould rests on the pallet.
II. Machine Moulding
a. Plastic Method.
The pugged, stiffer clay is forced through a rectangular opening of brick size by
means of layer clay out of the opening in the form of an bar. The bricks are cut from the
bar by a frame consisting of several wires at a distance of brick size. This is a quick and
economical process.
ii. Dry – press Method
The moist, powdered clay is fed into the mould on a mechanically operated press, where it
in subjected to high pressure, the clay in the mould takes the shape of bricks. Such pressured
bricks are more dense, smooth and uniform than ordinary bricks.
Process of Burning of Bricks
i. Dehydration (400 - 6500C)
This is also known as water smoking stage.
(1) The water which has been retained in the pores of the clay after drying is driven off
and the clay losses its plasticity.
2. Some of the carbon matter in the brick is burnt.
3. A portion of sulphur is distilled from pyrites.
4. Hydrous minerals like ferric hydroxide are dehydrated.
5. The carbonate minerals are also decarbonizes.
6. Two rapid heating causes cracking or bursting of the bricks, on the other hand, if alkali
is contained in the clay or sulphur is present in large amount in the coal quality of brick is
deteoriated.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
25
ii. Oxidation period (650-900oC)
During the oxidation period
1. Residues of carbon is eliminated.
2. The ferrous iron is oxidized to the ferric form.
3. The removal of sulphur is completed only after the carbon has been eliminated.
4. Sulphur on account of its affinity for oxygen, also holds back the oxidation of iron.
5. Sand is often added to the raw clay to produce a more open structure and thus provide
escape of gases generated in burning.
iii. Vitrification
To convert the mass in to glass like substance – the temperature ranges from 900 – 1100 oC
for low melting clay and 1000 – 1250o C for high melting clay. Virtrification period may further be
divided into a. In a pient vitrification, at which the clay has softened sufficiently to cause
adherence but not enough to close the pores or causes loss of space on cooling the material
cannot be scratched by the knife.
b. Complete vitrification, more or less will be marked by maximum shrinkage.
c. Viscous vitrification produced by a further increase in temperature which results in a soft
molten mass, a gradual loss in shape, and a glassy structure after cooling. Burning of bricks is
done in a clamp or Kiln. A clamp is a temporary structure whereas kiln is a permanent one
COMMON DEFECTS IN BRICK
a. Over burning of Bricks:
Bricks should be burned at temperatures at which complete and viscous vitrification
occur. However, if the bricks are over burnt a soft molten mass in produced and the brick loose
their shape.
b.Under – burning of Bricks:
When Bricks are to be burnt to cause complete vitrification, some layers are not softened
because of in sufficient heat and the pores are not closed. This results in higher degree of water
absorption and less compressive strength. These bricks are not used for construction works.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
26
c. Bloating
This defect is observed as spongy swollen mass over the surface of burnt bricks. It is
caused due to the presence of excess carbonaceous material and sulphur is brick – clay.
d. Black core:
When brick –clay contains bituminous matter or carbon and they are not completely
removed by oxidation the brick results in black core mainly because of improper burning.
e. Efflorscence:
This defect is caused because of alkalis present in bricks. When bricks come in contact
with moisture, water is absorbed and the alkalis crystalize. On drying grey or white powder
patches appear on the brick surface. This can be minimized by selecting proper clay materials for
brick manufacturing, preventing moisture to come in contact with the masonry, by providing
water proof coping and by using water repellent materials in mortar and by providing clamp
proof course.
f. Chuffs
The deformation of the shape of bricks cause by the rainwater falling on hollow
a brick is known as chuffs.
g. Checks or cracks:
This defect may be because of lumps of lime or excess of water. In case of the former,
when bricks come in contact with water, the absorbed water reacts with lime nodules causing
expansion and a consequent disintegration of bricks whereas shrinkage and burning crocks result
when exes of water is added during brick manufacturing.
h. Spots:
Iron sulphide, if present in the brick clay, results in clark surface spots on the brick
surfaces. Such bricks through not harmful are unsuitable for exposed masonry work.
i. Blisters:
Broken filters are generally caused on the surface of sewer pope and drain filters due to air
impressoned during their moulding.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
27
j. Laminations:
These are caused by the entrapped air in the voids of clay. Laminations produce thin
lamina on the brick faces which whether out on exposure such bricks are weak in structure.
CEMENT
Cement is a substance act as binding agent. Constituents:
1. Argillaceous 2. Calcareous
In argillaceous clay is the main ingredient and un calcareous calcium carbonate is the main ingredient. Setting Action: When water is added to cement, the ingredients of cement react chemically with water and forms various complicated chemical compounds which import strength to cement. This phenomenon is called as hardening.
Manufacture of cement
Following three district operations are involved in the manufacture of normal setting or ordinary
or Portland cement.
1. Mixing of raw materials
2. Burning
3. Grinding
Mixing of raw materials:
The raw materials such as limestone or chalk and shale or clay may be mixed either in dry
condition or is wet condition. The process is accordingly known as the dry process or the wet
process of mixing.
Dry process:
In this process, the raw materials are first reduced in size at about 25 mm in crushers. A
current of dry air is then passed over these dried materials. These dried materials are then
pulverized into fire powder in ball mills and tube mills. All these operations are done separately
for each raw material and they are stored in hoppers. They are then mixed in correct proportions
and made ready for the feed at rotary Kiln. This finely ground powder at raw materials is known
as the raw mix and it is stored in storage tank. Fig shows the flow diagram of mixing at raw
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
28
materials by dry process. The dry process has been modernized and it is widely used at present
because of the following reasons.
Competition:
At present, several dry process cement plants are vying or competing with each other.
The cement consumers in general and the practicing civil engineers in particular are greatly
benefited by such competition.
Power:
The blending of dry powders has now perfected and the wet process, which required
much higher consumption of power, can be replaced with confidence.
Quality of cement: It is found that the quality of the production no longer depended on the
skilled operators and workmen because temperature control and proportioning can be done
automatically through a centralized control room.
Technology:
There has been several advances is instrumentation. Computerization and quality control,
the application of the modern technology has made the production of cement by dry process
more economical and of superior quality. Following is the procedure of anufacture of cement by
the dry process using modern technology.
i) Most of the cement factories are located very close to the limestone quarries. The boulders up
to 1.2 m size are transported in huge dumpers up to 300 KN capacities and dumped into the
hopper of the crusher.
ii) The hammer mill crushers of single stage are now used for crushing as against the time
consuming two stage crushers used in earlier plants. The modern stacker – reclaimed system is
now in use in most of the modern plants. The stacker helps in spreading the crushed materials in
horizontal layers and the reclaimed restricts in the variation at calcium carbonate is crushed
limestone to less than 1% thereby minimizing quality variation is the materials.
iii) The argillaceous or clay materials found in the quarry are also dumped into the crusher and
stacked along with the limestone iv) The crushed materials are checked for calcium carbonate,
lime alumina, ferrous oxide and silica contents. In a similar way, if limestone is found to contain
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
29
less content of lime, the high grade limestone is crushed and stored separately in the raw material
hopper.
v) The additive material and crushed limestone are conveyed to the storage hopers. The raw
materials are fed to the raw mill by means of a conveyer and proportioned by use of weight
feeders which are adjusted as per the chemical analysis done on the raw materials taken from the
hoppers from time to tome.
vi) The materials are ground to the desired fineness in the raw mill. In some of the modern
plants, the high efficiency. Vertical grinding mills are installed The fine powder which energies
as a result of grinding in the raw mill is blown upwards, collected in cyclones and fed to the giant
sized continuous blending and storage silo by use of aeropole . The advantage of these silos is
that one stage of pumping is eliminated which has inevitable in the traditional pattern of different
silos for blending and storage.
vii) The material is dropped merely by gravity from the blending to the storage silo thereby
conserving
viii) The material is than once again, pumped using an aerosol onto he pre heater. The most
modern heater have five stage fro m 60 to 850 c has hard gas at temperature 1000 c is blown
against the falling gradient the material from the bottom of the pre heater is fed to the rotary kiln
due to the use of multi stage pre heater in the modern plant, the length of rotary kiln is
considerably reduced there by resulting in saving maintenance cost and power requirement
Wet process:
In the earlier part of the century from 1913 to 1960 the wee process was used for the
manufacture of cement. From 1913 onwards ‘cement industries under went a no of changes
mainly to suit the requirement of manufactures and government polishes till 1982.
All the cement plants setup of after 1980 use the dry process for the manufacture of cement. In
this process the calcareous materials such as lime stone are crushed and stored in silos for storage
tank now the crushed lime stone from silos and red clay from the basins are allowed fall in the
channel in correct propos ion this channel leads the material to grinding mills where they are
brought in to ultimate contact to form what is known as the slurry.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
30
The grinding is carried out either in ball mill or tube mill or both. The slurry is let, to correcting
basin where it is constantly stirred at the stage the chemical composition is adjusted as necessary.
The corrected slurry is stored in storage tanks and kept ready to serve as feed for rotary kiln in
this fig. show the flow diagram of mixing of raw materiel by the wet process. It is thus seen that is
case of mixing of raw materials by dry process the raw mix is formed and in case of mixing of raw
materials by wet process the slurry is formed the remaining two operation namely burning in
grinding are the same for both the process
Burning:
The burning is carried out in a rotary kiln as shown in fig the rotary kiln is formed of steel
tube is diameter varies from 90m to 120m. it is laid at a gradient of about 1in 25 to 1in 30 the kiln
supported at intervals by column of masonry or concrete the refractory lining is provided on the
in side surface of rotary kiln it is so arranged that the kiln rotates at about 1to 3 revolution per mint
about is longitudinal axis . The corrected slurry is injected at the upper end of the kiln in the fig
shows the rotary kiln for the wet process hot gases or planes or forced through the lawyer end of
the kiln. The portion of the kiln near its upper end is known as the dry zone and in this zone, the
slurry of evaporated as the slurry gradually descends there is raise in temperature and in the next
sections of kiln, the carbon dioxide from slurry is evaporated. These small pumps known as the
modulus are formed at the stage. This modulus then gradually roll down passing through zone of
rising temperature and altimetry reach to the burning zone when temperature is about 1400 c to
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
31
500 c In burning zone, the calcimined product is formed and modulus are converted into small
hard dark greenness blue balls which are known as clinkers. In the modern technology of dry
process, the coal brought from the coal fields is pulverized in vertical coal mill and it is stored in
silo it is pumped with required quantity of air through the burns. The preheated Raw material
rolled down kiln and gets heated to such on extent that the carbon dioxide is driven with
computation gases. The material is heated to temperature of nearly 1400 c to 1500 c when it gets
fused together. The fused product is known as the clinkers or raw cement. The size clinkers vary
from 3mm to 20mm. and they are very hot when n the come out of burning zone of kiln. the
clinker temperature at the outlet of kiln is nearly 1000c .A rotary kiln of small size is provide to
cool down the hot clinkers. It is laid in opposite directions as shown fig. and the cooled clinkers
having temperature of about 95 c are collected in containers of suitable size.
Grinding:
The clinkers as obtained from the rotary kiln are finally ground in ball mils and tube mills.
During grindings a small gentrify. About 3 to 4 percent of gypsum is added. The gypsum control
the initial setting time of cement. If gypsum is not added the cement. If gypsum is not added, the
cement would set as soon as water is added. The gypsum acts as retorted and its delays the
setting action of cement. It thus permits cement to the mixed with the aggregate and to be placed
in position.
The grinding of clingers is modern plants is carried out in the cement mill which contains
chromium steel balls of varies this balls with in the mill and grind the mixer which is collected in a
Hooper and taken in bucket elevator for storage in silos. The cement from silos is feet to the
pacer machines. Most of the modern plans have electric backing plant having provision to
account for the weight of empty bags of different types and to ensure a 50kg net weight of
cement bag with + or – 20g limits each bag of cement contains 50kg or 500N or about 0.035m3 of
cement this bag are automatically discharge from the bakers to the conveyer belts to different
loading are. They are carefully stored in a dry place.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
32
The properties of cement
i) It gives strength to the masonry
ii) It gives an excellent binding material
iii) It is easily workable
iv) It is posses a good plasticity
v) It is stiffness or hardness early
The functions of the ingredients of Portland cement
lumina content should not be less than 32% and ratio by weight of alumina to the lime should be
between 0.85 to 1.30. This cement is known by the trade names of cement Fondu in England and
Lumnite in America.
TYPES OF CEMENT:
Hydrophobic Cement:
This type of cement contains admixtures which decrease the wetting ability of cement grains.
The usual hydrophobic admixtures are acidol, napthenesoap, oxidized petroleum etc. When water is
added to hydrophobic cement, the absorption films are turn off the surface and they do not in any way,
prevent the normal hardening of cement. However, in initial stage, the gain in strength is less as
hydrophobic films on cement grains prevent the interaction with water. When hydrophobic cement is
used, the fine pores in concrete are uniformly distributed and thus the frost resistance and the water
resistance of such concrete are considerably increased.
Low heat cement:
The considerable heat is produced during the setting action of cement. In order to reduce the
amount of heat this type of cement is used. It contains lower percentage of dicalcium silicate C2 S of
about 46 % .
Pozzuolana Cement:
The pozzuolana is a volcanic powder. It is found in Italy near Vesuvius. It resembles surkhi which
is prepared by burning bricks made form ordinary soils. It can also be processed from Sholes and contain
types of clays. The percentage of pozzuolana material should be between 10 – 30.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
33
Quick setting cement:
This cement is produced by adding a small percentage of aluminium sulphate and by finely
grinding the cement. The percentage of gypsum or retarded setting action is also greatly reduced.
The addition of aluminum sulphate and fineness of grinding are responsible for acceleration the setting
action of cement the setting action of cement starts within five minutes after addition of water and it
becomes hard like stone in less than 30 minutes or so.
Rapid hardening cement:
The initial and final setting times of this cement are the same as those of ordinary cement. But it
attains high strength in early days. It contains high percentage of tricalcium silicate C3 S to the extent of
about 56%.
Sulphate resisting cement:
In this cement, the percentage of tricalcium aluminate C3 A is kept below 5% and it results in the
increase in resisting power against sulphates. This cement is used for structures which are likely to be
damaged by severe alkaline conditions such as canal linings, Culverts, siphons etc.
Physical tests available for cement
Fineness:
The degree of fineness of cement is the measure of the mean size of the grain it. There are
three methods for testing fineness.
a. Sieve Method
b. Air permeability test
c. Sedimentation Method.
CONCRETE
Concrete may be defined as building material obtained by mixing cement, fine and coarse aggregates, and water in suitable proportions.
Constituents: Cement: Selection of particular type depends on specific conditions. Aggregates: Coarse aggregates: Aggregates pass through 75mm mesh. Eg: Stone, broken brick.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
34
Fine aggregates: Aggregates pass through 4.75mm mesh. Eg: Sand. Water: Purpose of water:
1. To form the paste. 2. Enables the concrete mix to flow into moulds. 3.
Workability: Workability is defined as the ease with which it can be mixed, transported and placed. Wet concrete more workable than dry concrete. Batching: The measurement of materials for making concrete is known as Batching. Weight Batch -> cement. Weight Batch -> aggregates. MIXING: Mass becomes homogeneous and uniform. There are two types
1. Hand mixing. 2. Machine mixing. 3.
Transporting: Mortar pan, bucket and rope Belt conveyors are used.
Placing:
It should be placed in systematic manner to yield maximum result.
Compacting: It should be compared to eliminate air bubbles and obtain maximum density.
Curing: It should be wet at least for 7 days to promote continued hydration.
PURPOSE: 1. Increases durability. 2. Reduces shrinkage. 3. Increases wear resistance.
Types:
Plain Cement Concrete: It is mixture of cement, sand, crushed rock and water.
1. Free from corrosion. 2. High compressive strength. 3. It binds rapidly with steel.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
35
R.C.C: Plains concrete strong in compression but weak in tension. To increase the tensile strength steel bars are embedded in concrete known as R.C.C.
Pre Stressed Concrete: Here high tensile steel wires are used instead of mild steel bars. There are two types:
1. Pre tensioning 2. Post tensioning.
Pre Tensioning:
� The wires are initially stressed and concrete is cost. Post tensioning:
� The wires are placing inside the concrete and then stressed. It saves the concrete and steel 50 to 80% compared with R.C.C.
Pre-cast concrete:
� It is manufactured in factory and transmitted to site. Advantages:
1. They are finished with accuracy. 2. High quality. 3. It is completed in short time. 4. It can be dismantled when required and they are suitable used else where.
Sl.no. Grade of concrete
Cement, sand, & aggregates
Characteristic Compressive Strength in
N/mm2
Uses
1. M10 1 : 3 : 6 10 Culverts 2. M15 1 : 2 : 4 15 Bridges
3. M20 1 : 1.5 : 3 20 Light loaded
columns
4. M25 1:1:2 25 Heavy loaded
columns
Factors that affect workability of concrete
a) Water content
b) Micro proportions
c) Size of aggregates
d) Shape of aggregates
e) Surface textures of aggregate
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
36
Preparation of concrete
To prepare concrete, following steps are to be followed
a) Batching
b) Mixing
c) Transporting
d) Placing
e) Compacting
f) Curing
Methods employed to transport concrete
Concrete can be moved from one place to another using
a) Mortar pan
b) Wheel barrow, handcart
c) Crane, bucket and rope way
d) Truck mixer and dumper
e) Belt conveyers
f) Chute
g) Skip and hoist
h) Transit mixer
Methods adopted for curing
Methods employed for curing of mortar or concrete are
(a) Water curing
(b) Membrane curing
(c) Application of heat
(d) Miscellaneous
Short notes on water curing.
This is by far the best method of curing as it satisfies all the requirements of curing mainly,
completion of hydration, elimination of shrinkage and absorption of heat of hydration. It is
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
37
pointed out that even if the membrane method is adopted, it is desirable that a certain extent of
water curing is done before the concrete is covered with membrane. Water curing can be done
in the following ways:
(a) Immersion
(b) Ponding
(c) Spraying or fogging
(d) Wet covering
Explain the slump test
Slump test is the most commonly used method of measuring consistency of concrete. It
can be employed either in laboratory or at work site. It is not a suitable method for very wet or
very dry concrete. However, it can be used to check quality of concrete and gives an indication of
the uniformity of concrete from batch to batch. Additional information on workability and quality
of concrete can be obtained by observing the manner in which concrete slumps. Quality of
concrete can also be further assessed by giving a few tappings or blows with tamping rod to the
base plate and observing the flow. The apparatus far conducting the slump test, essentially
consists of a metallic in the form of a function of a cone having the internal dimensions as under
Bottom diameter: 20cm
Top diameter: 10cm
Height: 30cm
The thickness of the metallic sheet for the mould should not be thinner than 1.6mm. The internal
surface of the mould is thoroughly cleared and freed from super flow moisture. The mould is then filled
in four layers, each approximately (1/4) of the height of the mould. Each layer in tamped 25 times by the
tamping rod taking care to distribute the strokes evenly over the grease section. After the layer has been
rodded, the concrete is struck off level with a trowel and tampering rod. The mould is re mould from the
concrete immediately by raising it slowly and carefully in a vertical direction. This allows the concrete to
subside. This subsidence is referred as SLUMP of concrete. The difference in level between the height
of the mould and that of the highest paint of the subsided concrete is measured. This difference in
height in mm, is taken as slump of concrete. The pattern of slump is shown in fig. It indicates the
characteristics of concrete in addition to the slump value. If the concrete slumps evenly it is called the
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
38
normal slump. It one half of the cone slides down, It is called shear slump. In case of a shear slump, the
slump value is measured as the difference in height between the height of the mould and the average
value of the subsidence. Shear slump also indicates that the concrete is non-cohesive and shows the
characteristic of segregation. Despite many limitations, the slump test is very useful on site to check
day-to-day as hour-to-hour variation in the quality of mix. An increase of the aggregates may mean for
instance that the moisture content of the aggregates has suddenly increased as there has been sudden
change in the grading of aggregate. The slump test gives warning to correct the causes for change of
slump value. Due to simplicity of the test it is popularly used to find workability of fresh concrete in spite
if that many workability tests are in vogue.
Bulking of sand
Increase in volume of sand due to moisture content is called bulking. Sand volume increases by
20% at a moisture content of 4% when compared to dry sand. Due to bulking of sand suitable
correction in quantity of sand should be made during volume batching of concrete.
Mixing process in concrete manufacture
Through mixing of the materials is essential for the production of uniform concrete mixing
should ensure that the mass becomes homogeneous, uniform in color and consistency. There are two
methods adopted for mixing concrete;
(1) Hand mixing
(2) Machine mixing
HAND MIXING:
Hand mixing is practiced for small scale unimportant concrete works. As the mixing can’t be
through and efficient, it is desirable to add 10% more cement to cater for the inferior concrete produced
by this method Hand mixing should be done over impervious concrete are brick floor of sufficiently
large size to take one bag of cement. Spread out the measure quantity of coarse aggregate and fine
aggregate in alternate layers. Pour the cement and the top of it, and mix them dry by shovel, turning the
mixer over and over again until uniformity of color is achieved. The uniform mixer is spread out in
thickness if above 20cm. Water is taken in a water can fitted with a sorehead and sprinkled over the
mixer and simultaneously turned over. This peration is continuing till such time a good uniform,
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
39
homogeneous concrete is obtained. It is of particular important to see that the water is not poured but it
is only sprinkled.
MACHINE MIXING:
Mixing of concrete is almost in variably carried out by machine, for reinforced concrete work and
for medium are large scale mass concrete works. Machine mixing is not only efficient, but also
economical; when the quantity of concrete to be produced is large many types of mixers are available
for using concrete. They can be classified as batch mixers and continuous mixers. Batch mixers
produced concrete, batch by batch with time interval, where as continuous mixers produce concrete
continuously without stoppage still such time the planet is working. In this material are feed
continuously by screw feeders and the ma trials are continuously mixer and continuously discharge.
This type of mixer is used in large works such as dams. Batch mixers may be of pan type or drum type.
Drum type may be further classified tilting.
STEEL
In case of steel there are only a limited standard structural sections like, I channel angle and the
designer can adopt. The aluminum offers limitless, possibilities of different shapes and profiles. The
designer enjoys full freedom in the matter of designing of a profile in such a way that the metal is
distributed exactly where it is needed for structural requirements whether proofing and mechanical
needs. In case of aluminum the infinite number of shapes and sections can be produced by the extrusion
process in continuous lengths.
Defects in steel
i) Cavities or blow-holes:
These are formed when gas confirmed or imprisoned in the molten mass of metal,
such confined gas presence of excess amount of phosphorous.
ii) Cold shortness:
The steel, having this defect, cracks when being worked in cold state .this effect is due to
the presence of excess amount of phosphorous.
iii) Red shortness:
The steel, having this defect, cracks when being worked in hot state. This defect is due to
the presence of excess amount of sulphur.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
40
Give the market forms of steel
i) Angle sections
ii) Channel sections
iii) Corrugated sheets
iv) Expanded metal
v) Float bars.
N-tilting reversing are forced actual type.
Write short notes on annealing.
Te main object of this process is to make the steel soft so that it can be easily worked upon
with a machine .the annealing reduces the tensile strength .but it increases ductility and brings
back the steel to the best physical state to resist fracture under sudden stresses
What are the uses of the steel?
Depending upon the carbon cement concrete, the steel is designed as the mild steel or
medium carbon steel or high carbon steel .the various uses of steel are governened by the
amount of carbon contained in it. The carbon content of medium carbon steel is about .25 to
.60%...The high carbon is also known as the hard steel and its carbon cement varies from 0.60 to
1.10%
Market forms are available in steel:
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
41
Angle section
The angle sections may be of equal legs or the unequal legs as shown in figure There are two
angle sections
a. Equal angle section:
The equal angle sections available in size varying form 20 mm *20mm*3 mm to
200mm* 200mm*25 mm.the corresponding weights per meter length are respectively 9n
t0 736 N.
b. Unequal sections
The un-equal angle sections are available in sizes varying from 30 mm*20mm*3 mm to
200mm* 1500 mm*18 mm.the corresponding weights per meter length are respectively
11n and 469 n
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
42
Channel sections
A channel sections is designed by the height of the web and width of flange .these sections are
available in sizes varying from 100 mm* 45mm to 400 mm* 100mm .the corresponding weighs
perimeter length are respectively 58 N and 494 N.
Corrugated sheets
These are formed by passing of steel through grooves .these groove bend and press steel sheets
and corrugations are formed .on the sheets and corrugated sheets are usually galvanized and
they corrugated sheets are usually galvanized and they are referred to as the galvanized iron
sheets.
Expand metal
This form of steel is available in different shapes and size it is preferred from sheets of mild steel
which are making cuts and drawn out or expanded It is used for reinforcing concrete in
foundations roads floors, bridges etc.
Flat bars
These are available in suitable width varying from10mm to 400mm width thickness varying from
3 mm to 4omm.they are widely used in the construction of bars.
I-sections:
These are popularly known as the rolled steel joints beams. If consists of two flanges connected
buy a web as shown in this fig,. It is designated by overall depth, width of flange and weight
perimeter length.
Varying of sizes: 75m x 50mm at 61 N to 600mm x 210 mm at995N. Joist of size 300mm x 150mm
of 377N.The wide flange beams are available in sizes varying from 150mm x 100 mm 170N to 600
mm x 250m at 1451N.The beams suitable for columns are available in H- sections which vary in
size form in 150mm x150mm at 271N to 450mm x 250mm at 925N. The Bureau Indian standards
has classified the I-section into junior beams light beams medium beams, wide flange beams and
heavy beams and they are accordingly designated as
I.S.J.B.,I.S.L.B,I.S.M.B,I.S.W.B.,respectively. The R.S. joists are economical in materials and
they are suitable for floor beams, Intels, columns.etc.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
43
Plates
The plate sections of steel are available in different sizes of thickness varying from 5mm to
50mm.The corresponding weights per square meter 392N and 3925N respectively.
i) To connect steel beams for extension of the length.
ii) To serve astensionance members of steel roof truss and
iii) To form built up sections.
Ribbed – Tor-steel bars:
These bars are produced from the ribbed to steel which is a deformed high strength. Steel each
bars is to be twisted individually and it is tested to confirm the standard requirements.
i) It is possible to bend these bars through 1800 without formation of any cracks for fractures on
their outside surface.
ii) It is possible to weld certain type of ribbed tor steel bars by electric flush sutt welding or arc
welding.
iii) They serve as a efficient and economical concrete reinforcement.
Round bar
These are available in circular cross sections with diameters varying from 5mm to 250mm they
are widely used as R.C.C and construction of steel work.
Square bars:
These are available in square cross section with sides varying from 5mm to 250mm they are
widely used in the construction of steel grill work for windows, gates etc.The commonly use
cross sections have sides varying from 5mm to 25mmm with corresponding weights peametre
length as 2N and 49N respectively.
T-sections:
The shape of this section is like that of letter and it is consists of flange and web. it is designed be
overall dimensions an thickness .this sections are available in sizes varying from 20 mm* 20 mm*
3 mm to 150 mm* 150 mm* 10 mm .The corresponding weights per meter length are 9 N and 228
N respectively. This section is widely used as members of the steel roof truss and from built-up
sections. In addition to eleven shapes, the rolled steel sections such as acute and obtuse angle
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
44
section rail sections, through sections and Z-sections .these sections are used to a limited extent
in the structures steel work.
Surveying and Civil Engineering Materials UNIT I Basic Civil And Mechanical Engineering
45