technical assistance consultant’s report · x there is a signified willingness of development...
TRANSCRIPT
Technical Assistance Consultant’s Report
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
Project Number: P42171-012 April 2011
BANGLADESH: Khulna Water Supply Project (Financed by the Technical Assistance Special Fund)
Prepared by
Pöyry IDP Consult, Inc. For Government of the People’s Republic of Bangladesh Khulna Water Supply and Sewerage Authority (KWASA) (Executing Agency)
FINAL REPORT
I
PÖ
YR
Y ID
P C
ON
SU
LT, I
NC
.
PREPARING THE KHULNA WATER SUPPLY ADB TA 7385 - BAN
Pöyry IDP Consult, Inc.
In association with
HB CONSULTANTS LTD.
APRIL 2011
Asian Development Bank
Khulna Water Supply & Sewerage Authority (KWASA)
MAIN REPORT and APPENDIX 1 - 9
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
i
TABLE OF CONTENTS 1. INTRODUCTION ...................................................................................................................1
1.1. Project Background .................................................................................................................. 1
1.2. Scope and Objectives of the TA ................................................................................................ 2
1.3. Purpose of this Report.............................................................................................................. 2
2. SUMMARY OF OUTPUTS .....................................................................................................3
2.1. Capital Investment Plan............................................................................................................ 3
2.2. Socio Economic Assessments and Impact on Project ................................................................ 4
2.3. Institutional Development Program ......................................................................................... 5
2.4. Operational Support................................................................................................................. 8
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
ii
LIST OF APPENDIXES
Appendix 1 – Capital Investment Plan Appendix 2 – Contract Procurement Appendix 3 – Subsidiary Loan Agreement Appendix 4 – Sector Assessment Appendix 5 – Social Poverty Assessment Appendix 6 – Business Plan Appendix 7 – Draft Performance Agreement between KWASA and LGD Appendix 8 – Financial Management Assessment Report Appendix 9 – Financial Analysis of KWASA Appendix 10 – Annex A – KWASA Tube Well Reconnaissance and Monitoring Survey Appendix 10 – Annex B Workshops and Technical Meetings Conducted Appendix 10 – Annex C of Existing and Future Network Appendix 10 – Annex D Draft Meter Connection Policy Appendix 10 – Annex E Meter Specification Policy Appendix 10 – Annex F Terms of Reference for KWASA Financial Auditing Appendix 10 – Annex G Grameenphone Contract
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
1
1. INTRODUCTION
1.1. PROJECT BACKGROUND
Citizens in Khulna have been suffering from limited access to safe and potable water. Only 18% of total 1
million populations in the City have access to piped water supply and the rest resorts to alternative
water sources such as river, pond and shallow tube well etc. Shallow tube well water often contains
significant salinity. Recognising the challenges, the Government of Bangladesh established a separate
and independent Khulna Water Supply and Sewerage Authority (KWASA) in February 2008. KWASA,
which is the third WASA in the country established following the DWASA and CWASA. While the KWASA
was established legally, substantial work was required to develop it into a capable water utility with
proper corporate governance, competent human resources, and effective financial management.
ADB initiated support to the KWASA through SSTA: Supporting the establishment of KWASA (the SSTA),
approved in December 2008. During the SSTA, a unified policy matrix was developed as the road map
for reform and development partner’s support based on which Japan International Cooperation Agency
(JICA) is currently funding a feasibility study in KWASA looking at all aspects of the investment. It is
principally agreed that JICA will fund infrastructure from raw water intake to water treatment plant
outlet and ADB will fund the investment in distribution, storage.
Technical assistance is now being carried out to KWASA through ADB TA 7385 BAN in order to develop
KWASA institutional capacity and project proposal for future investment.
The Consultants are Pöyry IDP Consult, Inc. as the lead project team in association with HB Consultants
Ltd. and two other Bangladeshi firms, BETS Consulting Services and DPC Group, as sub consultants.
Mr Jaglul Haider, KWASA Deputy Managing Director (DMD) for Engineering is the project liaison officer
serving as the direct link between KWASA and the consultants’ team.
Oversight of the TA project will be ensured through a Project Steering Committee. The committee,
based in LGD of MLGRD&C has already been established. The purpose of the committee is to ensure
progress is in line with the Terms of Reference (TOR) and KWASA requirements and that the deliverables
are met in accordance with the work schedule.
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
2
1.2. SCOPE AND OBJECTIVES OF THE TA
There are two principle objectives of the TA. The first is to focus on establishment of corporate
management systems and developing the capacities of KWASA staff to improve operational efficiency
and to prepare it in meeting the demand for increased and expanded water services, the second is to
support the development of the ADB project proposal and related documents, some activities fall under
both components e.g. preparation of the business plan is directly related to institutional as well as
project proposal scopes. The principal outputs achieved under the TA are summarized below and
provided in more detail in section 2.
- a 5 year Business Plan and Institutional Strengthening Program comprising Mission
computerized accounting and Vision for KWASA, a capital work plan, financial development plan
and human resource/organizational development plan
- a project proposal for ADB financing that specifies the capital investment requirements, outline
design concepts, costing and procurement criteria and mechanisms for the ADB component of
the infrastructure investment; TOR for specialist consultants; social development
considerations; and Performance agreement between KWASA and LGED;
Operational support to KWASA in areas of priority need identified by them – these included support
with tender document preparation; arranging consultants to implement a billing system, hiring of
auditors, introduction of the computerized accounting system; GIS mapping of network assets; general
reconnaissance of all KWASA production tube wells and detailed monitoring and analysis of production
well conditions.
1.3. PURPOSE OF THIS REPORT
The purpose of the report is to summarize the activities carried out throughout the course of the TA and
more importantly to organise and present the results of the work carried out in a format suitable for
collation within ADB project reporting framework/s.
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
3
2. SUMMARY OF OUTPUTS
2.1. Capital Investment Plan A number of investments are being planned for improvement of water supply in Khulna in the
immediate and near future. The features of the immediate planned investments with the Government
of Bangladesh (GOB) funding are linked to the development of Water Supply System in Khulna City,
which include construction of new pipeline, replacement of pipeline, construction of new production
wells, construction of new SWTP, rehabilitation of existing SWTP, service connections with water meter
and expansion of water supply network for distribution of water from Phultala Source.
The most significant part however of KWASA investment plan is a joint initiative between JICA and ADB
for the implementation of new surface water treatment facilities (110 Mld) and the complete
replacement of the clean water distribution network (approximately 600 km of water mains).
A feasibility study report was undertaken for the full scope of work by JICA consultants. The TA team
reviewed the initial design concepts from source to tap and then prepared more detailed design and
costing for the ADB component proposed by the JICA team in their Feasibility Study Report - November
2010 and included additional investment requirements which were not previously discussed.
The total value of investments proposed under this initiative is US$ 365m. JICA has committed to
developing new surface water source with intake structures, raw water transmission, impounding
reservoir and surface water treatment plant facilities. ADB is planning to invest in developing the clean
water transmission, distribution reservoirs, overhead tanks and pipeline distribution network
improvement for Khulna. In addition, ADB support is also envisaged for capacity building and technical
assistance to KWASA for the implementation of the proposed project and assistance is also planned for
institutional capacity building of KWASA with provisions for better office facilities, equipment, vehicles
and other sundry activities.
The timeline for implementation is loan agreement in early 2011 and commissioning of all facilities by
July 2016. Engineering design consultants will be hired by KWASA (managed by the KWASA Project
Management Unit – PMU) to undertake detailed design of all infrastructure and project safeguards
compliance.
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
4
Full details of the ADB component of KWASA capital investment plan is shown in Appendix 1 – Capital
Investment Plan.
Associated Appendices include Appendix 2 – Contract Procurement; Appendix 3 – Subsidiary Loan
Agreement; and Appendix 4 – Sector Assessment;
2.2. Socio Economic Assessments and Impact on Project
In addition to the engineering aspects of the project considerable amount of time has been put into the
necessary assessment of socio-economic considerations.
It is a fact that very significant portions (up to 40%) of the potential new customers of KWASA are
classified economically as being in the low income bracket. The production assumptions include uptake
of water from this sector of the community so it is vitally important that the conditions (cost and access)
under which people will wish to have water supply are understood and planned for by KWASA.
ADB preference, where ever possible is for customers to have individual household connections, and
cost estimates reflect this aspiration. They also recognize that individual connections are not always
practical (even if provided through grant or very high subsidy conditions) due to environmental factors
at the household level.
As part of the TA work detailed socio economic analysis has been undertaken and the output from this
been included in asset costing and planning for capacity building within KWASA and low income
communities.
A detailed SPA report has been prepared the key findings of which are that:
There is a demand from low income communities subject to cost of connection of Tk
1,000 maximum and monthly charges of Tk 100 maximum;
The preference for water sources is based on adequacy, affordability, accessibility and
availability of water;
The project offers a wide range of benefits which will contribute to poverty reduction;
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
5
There are significant positive gender impacts as a result of the project with no significant
negative impacts foreseen;
There is a signified willingness of development partners to participate in the process of
connection the low income communities.
The SPA is included in Appendix 5, which itself has a number of Annexes referencing poverty reduction,
gender action planning and community action planning and capacity building.
2.3. Institutional Development Program
2.3.1. Business Plan
The key output in relation to Institutional Development is the 5 year business plan. The business plan
was prepared jointly with KWASA starting from identifying their business objectives, matching these
with capital investment requirements to meet growth forecasts and achieve performance objectives
related to service coverage, continuity and quality.
The plan takes into account all aspects of the business operation across the plan period:
KWASA Mission and Vision;
Business Objectives and Performance Criteria;
Capital investment;
Operational issues – forecasts of production, sales and expenditures;
Financial requirements – tariff levels; financing terms;
Organizational Development;
The business plan is included in full in Appendix 6. Associated Appendix includes 7 - Draft Performance Agreement between KWASA and LGD; Whilst the key focus of the TA is the ADB component of the proposed investment in KWASA the inter-relationship with the JICA component of the investment is essential and is dealt with throughout the report.
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
6
2.3.2. Financial Management Performance & Strengthening One of the key components of the work carried out by the TA team is the Financial Management
Assessment of KWASA. This covers both financial management performance and financial strengthening
and outlines the strategy for the capacity building of KWASA financial management capability.
The detailed financial management assessment report is included in Appendix 8 this will serve as the
starting point for the Capacity Building consultants to be employed under the bridging TA and the loan
project.
Fundamental to the financial management assessment is the financial analysis of KWASA. This is fully
detailed in Appendix 9. The analysis looks first at past and current performance and highlights the
limited level of detailed information currently available to KWASA (which will be addressed through the
Financial Management Strengthening program); secondly it considers future financial performance in
light of the proposed investment by JICA, ADB and GoB detailing the base case assumptions that have
gone into the financial model as well as 2 sensitivity scenarios; the analysis also includes a summary of
risks around the forecast and the safeguard actions that need to be put in place.
2.3.3. Capacity Building Support to KWASA
ADB has been providing support institutional and operational support to KWASA for a number of years
now through the SSTA 7283 BAN, TA7385 BAN – Preparing the Khulna Water Supply (which comprises
the Institutional, Operational and Project Preparation Support reported on here; the Customer Census
Survey carried out in 2010; Phultala Groundwater Assessment survey; and the Khulna Aquifer Modelling
survey.
ADB wish to continue supporting the operationalization and management of KWASA in advance of and
during the project implementation such that KWASA is functioning effectively and efficiently as the
investment is realized. KWASA will be a professionally managed utility tasked with improving services
through operations and infrastructure investment.
There are two sets of capacity Building support planned. The first will be an Interim Capacity Building TA
Project, with start date as soon as the loan becomes effective (anticipated by May 2011). The second
will be a three year program funded by KWASA out of the loan itself.
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
7
The TA program is designed to ensure the ongoing capacity building of KWASA in the interim period
between loan effectiveness and appointment of long term institutional capacity building consultants
under the loan agreement. It will focus on meter connection implementation, financial and accounting
management policies and process implementation, Information technology systems strategy and
planning, support to business plan implementation, Communications and public awareness and
Engineering planning support to develop KWASA in advance of the appointment of engineering
consultants for the project implementation.
Capacity Building support provided under the ADB loan will continue on from the initiatives in the TA
program and will widen its view to cover broader institutional issues focus to improve the corporate
management of KWASA; this will focus on a number of issues, including:
KWASA revenue management - this will be overhauled during the early years of the business
plan period. A key aim is for all supplies to be metered and for customers to pay on a volumetric
basis for water received;
Implementation of a connection metering program with the aim of having all existing
connections metered by FY 2017
Implementation of business management systems;
Establishment of linkages and connection implementation mechanisms for low income
customers to ensure the smooth uptake of piped water facilities when they become available;
KWASA Human Resources management – policy, processes, and organisational change
implementation;
Terms of Reference for the TA and Loan funded Capacity Building have been prepared and submitted to
ADB under separate cover..
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
8
2.4. Operational Support
Operational support has been provided to KWASA during TA7385 from August to December 2010 and
will continue to completion of the project period in January 2011.
The TA team responded to the expressed needs of KWASA, where resources permitted, in order to
provide best value and support.
Areas of activity are listed and discussed below:
2.4.1. Tender and Contract Document Preparation
Prior to the commencement of the TA project in August 2010, a GoB funded project was approved and
funds allocated. The project included for the installation of 13 Deep Tube Wells; transmission and
distribution network; rehabilitation and extension of a SWTP to 6.75 Mld; The TA team were asked to
provide support in order to operationalize the project as quickly as possible – support provided was:
Review of tender and contract documents for engineering consultants;
Preparation of standard specifications, tendering and contract documentation for Deep Tube
Well construction;
Preparation of Materials Procurement specification, tendering and contract documentation;
Subsequent to issue of tenders the TA team were also involved in the evaluation of tenders for the deep
tube well implementation contract;
Documentation for Production Tube Well Installation and documentation for Materials Procurement has
been submitted separately to ADB under separate cover.
2.4.2. Tube Well Reconnaissance Survey and Condition Monitoring of Production Tube Wells
An extensive survey of all wells was carried out to ascertain the condition and efficiency of water
abstraction.
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
9
Following on from the initial reconnaissance a detailed survey of all production wells was undertaken
and an estimate made of the cost to regenerate and/or rehabilitate the wells. The cost is included in the
Capital Investment Plan.
The survey report is included in Appendix 10 – Annex A – KWASA Tube Well Reconnaissance and
Monitoring Survey.
The survey was organised by the TA team but KWASA staff were involved in the reconnaissance survey
were responsible for undertaking the monitoring and recording of results under the supervision of the
Water Engineering Advisor – Pumps.
2.4.3. Workshops
A number of workshops and technical meetings were arranged throughout the duration of the project;
they covered:
A Workshop was organized by TA Team with full support and cooperation of KWASA management on 22
Feb 11 in Hotel Castle Salam. Honorable Mayor and Councillors of KCC, stake holders, NGO
representatives, local elites and representatives of slum people participated in the workshop. The key
issues discussed in workshop are:
- KWASA Vision, Mission, Objectives;
- Water Resource and Ground Water Potential;
- ADB Capital Investment Plan;
- Key Performance Indicators;
- Revenue Improvement Action Plan.
The participants shows their great satisfaction with the planned activities to be carried out by ADB/GOB
co-financing in order to improve water production and supply system in Khulna City.
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
10
Accounting Practice;
Two separate workshops on Accounts Keeping were conducted in 23 October 2010 and
13 November 2010. Topics of the first workshop included: Functions and responsibility
of the KWASA Accountant, Existing and Proposed KWASA Books of Accounts, and
Journal Preparation. Additional topics covered in the second workshop included:
Conversion of Single Entry System into Double Entry System, Bank Reconciliation
Statement, and Journal Preparation. Participants of the workshops included the Finance
and Accounts Section officers and staff members of KWASA.
Operational issues – Demand forecasting; Organization structure;
Output from the discussions has been included in the production and demand modeling
within the financial model preparation, and in the organization structure proposals put
forward in the business plan;
KWASA Mission, Vision, Values and Objectives formulation;
The output from the discussions is included within the business plan document and
objectives have been transposed into the proposed Key Performance Indicators
included in the business plan and the draft performance agreement between KWASA
and LGED,
2.4.4. Technical Training Attached as Appendix 10 – Annex B is a summary of the Technical Trainings conducted for the KWASA
technical staff. The coverage of the workshops included both theoretical classroom training and field
demonstration. The TA Team has been conducting sequentially on selected topics in order to enhance
both the theoretical and practical knowledge of KWASA technical staffs so that they can be quite
capable of operation and maintenance of the existing water supply system and the new system after
investment of ensuing loan.
The TA Team conducted 12-Technical Training Programs; of which 7 programs include only theoretical
classroom discussion, 3 include field demonstration along with classroom discussion, 1 was only field
demonstration on some practical issues related to well and pump operation and the rest 1 program was
outing to Faridpur Pourashava to gather practical knowledge of water works operation and billing
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
11
activity. All the trainings except training no. 8 & 9 were conducted to the technical staffs mentioned in
the Table 02. Training no. 8 & 9 were conducted exclusively for the pump operators (60+65) of KWASA
in two phases on pumps and wells operation and trouble shooting. Adequate refreshments with tea/
coffee were served during the tea breaks of the training. Good lunch was arranged in the nearby restaurants
as well as the training venue. Training bags have been provided to the trainees. The summary of the training
program conducted by TA Team is shown in the Table 02 below:
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
12
Table 02: Summary of Training Activities Conducted by TA Team
Sl No. Training Topics in Brief Conducted By No. of Trainees Attended Date and Duration Venue 1 Classroom Training
a. Interaction on some relevant MCQ on pumps and water distribution system; b. Introduction and classification of pumps. c. Pumps used in water supply system
Md. Abu Musa Mollah National Consultant (Pumps) &
20 Nos. (Engineers, Supervisors, Mechanic, Pipeline Mistry etc.)
23 October 2010 (09:30 am-03:30 pm)
Conference Hall of Hotel Castle Salam, Royal More, Khulna
d. Water pipeline Installation Technique (Part-01) Md. Zahangir Alam Deputy Team Leader
2 Classroom Training a. Major Component of Pump Unit b. Selection of Appropriate Pumps c. Determination Pump Head and Discharge d. Pump Characteristics Curves
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Pipeline Mistry etc.)
19 November 2010 (09:30 am-03:30 pm)
Conference Hall of Hotel Castle Salam, Royal Mor, Khulna
e. Water pipeline Installation Technique (Part-02) Md. Zahangir Alam Deputy Team Leader
3 Classroom Training a. Well Fixture b. Static Water Level (SWL) c. Pumping Water Level (PWL) d. Draw Down e. Well Yield f. Specific Capacity
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
01 December 2010 (09:30 am-03:30 pm)
Conference Room of KWASA HQ Building
Field Demonstration a. SWL & PWL Monitoring b. Determination of Draw Down c. Well Discharge Measurement by Trajectory d. Determination of Specific Capacity of Well e. Dismantling & Assembling of a Multi-stage submersible Pump-unit
Md. Abu Musa Mollah National Consultant (Pumps)
Pump House and Office yard for field demonstration
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
13
Sl No. Training Topics in Brief Conducted By No. of Trainees Attended Date and Duration Venue 4 Classroom Training
a. Series Operation of Pumps b. Parallel Operation of Pumps c. Combined Characteristic Curves for Series Operation d Combined Characteristic Curves for Parallel Operation
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
14 December 2010 (09:30 am-01:15 pm)
Conference Room of KWASA HQ Building
5 Classroom Training a. Basic of Electricity b. Electrical Control & Protective Component used in Pumping Plant. c. Measuring Instrument in Pumping Plant. d. Circuit Diagram of Elec. Equipment in Pumping Plant
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
23 December 2010 (09:30 am-01:15 pm)
Conference Room of KWASA HQ Building
6 Classroom Training a. Pump Station b. Piping Gallery c. Measuring instrument d. Identification & Selection of Cable
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
29 December 2010 (09:30 am-01:15 pm)
Conference Room of KWASA HQ Building
Field Demonstration a. Pumps & Piping Gallery b. Measuring instrument and Electrical Component in a pump station
Nearby Pump House
7 Classroom Training a. Installation of Submersible Pump b. Operation b. Maintenance c. Monitoring d. Trouble Shooting e Points to be considered during O & M of Electrical equipment
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
05-01- 2011 (09:30 am-01:15 pm)
Conference Room of KWASA HQ Building for Classroom Discussion.
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
14
Field Demonstration Visit to nearby Pump House and demonstration of operation and monitoring of pump & well.
Nearby Pump House
8 Classroom Training Technical Details, Operation, Maintenance, Monitoring and Trouble Shooting of Production Well with Submersible Pumping Equipment.
Md. Abu Musa Mollah National Consultant (Pumps)
65 Nos. Pump Operators & 4 nos Pump Mechanics (1st Group)
11-01- 2011 (2:30 PM-5:30 PM)
Meeting Room of KWASA Staff Association.
9 Classroom Training Technical Details, Operation Maintenance, Monitoring and Trouble Shooting of Production Well with Submersible Pumping Equipment.
Md. Abu Musa Mollah National Consultant (Pumps)
60 Nos. Pump Operators (2nd Group)
12-01- 2011 (9:30 AM-12:30 PM)
Meeting Room of KWASA Staff Association.
10 Classroom Training a. Un-accounted for Water (UFW) b. Non-Revenue Water (NRW) c. Measure to Control Wastage d. Key to Non-Revenue Water e. Leak Detection Methods f. Benefits of Leak detection g. Leak Detection Equipments
Md. Zahangir Alam Deputy Team Leader
29 Nos. (Engineers, Supervisors, Mechanic, Electricians)
20-01- 2011 (9:30 AM-12:30 PM)
Conference Hall of Hotel Castle Salam, Royal More, Khulna
b. Continuity Equation c. Bernaullie’s Equation d. Water Hammer e. Cavitations f. Air Locking g. Principle of Water Treatment
Md. Abu Musa Mollah National Consultant (Pumps)
11 Visit to Faridpur Paurashava Power Point Presentation on present status of Water
Supply System and billing status of Faridpur Paurashava, presented by Pourashava Authority.
Visit & observe Water Treatment Plant (480m3/h) operation at Old W/W, Jhiltuli
Visit & Observe Water Treatment Plant (480m3/h) operation at Goalchamat.
Md. Zahangir Alam Deputy Team Leader
MD. Abu Musa Mollah National Consultant (Pumps)
Md. Kayemuddin National Consultant (Finance)
46 Engineering and Financial Staffs of KWASA
22-01-2011 (7:30AM to 7:30PM)
Faridpur Pourashava Water Works
12 Field Demonstration Md. Abu Musa Mollah 29 Nos. (Engineers, 26-01-2011 KWASA Office Compound
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
15
Practical Demonstration with hydraulic model (fabricated) to explain the following technical terms: Continuity Equation & Bernaullie’s Equation Head Loss Water Hammer Air Locking
National Consultant (Pumps) Supervisors, Mechanic, Electricians)
(7:30AM to 7:30PM)
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
16
2.4.5. Network Mapping AutoCAD drawings of the existing KWASA network and borehole locations as well as the future
proposed networks have been prepared. The soft copy files will be passed to KWASA for their use in the
future.
Hard copy print outs are included in Appendix 10 - Annex C of Existing and Network and Future network.
2.4.6. Meter Connection Policy
A draft meter connection policy has been prepared to assist KWASA as they prepare to commence the
metering of connections on a large scale. The policy needs to be approved by KWASA Board in advance
of the Interim Capacity Building TA, starting in May 2011. The draft policy is included in Appendix 10 –
Annex D.
In addition to connection policy a meter specification policy has also been prepared to support the
meter connection process. This is included in Appendix 10 – Annex E.
2.4.7. Appointment of Auditors
Since the establishment of KWASA in 2009 the accounts have not been audited. The TA team supported
KWASA in preparing Terms of Reference for suitably qualified and interested audit companies to bid
against. The TOR included for Audit reporting for two Fiscal periods – FY 2008/09 and FY 2009/10; bids
were received in November and an auditor was appointed by letter on 26 December 2010. The starting
date for the audit was set as 22 February 2011 with anticipated completion by mid April 2011.
Copy of the Terms of Reference prepared is included in Appendix 10 – Annex F.
2.4.8. Billing System Implementation
KWASA currently have no billing system in place. The Board of KWASA has requested management to
push ahead with the implementation of a billing system that can be used for both flat rate and
volumetric billing methodologies. KWASA management requested the support of the TA team to identify
and discuss with potential suppliers.
PPTA 7385-BAN: Preparing the Khulna Water Supply Final Report April 2011
17
Discussions were held with two potential suppliers:
An independent software consultant with extensive experience of the LGD billing system who
was proposing to customize the LGD system (free license copy had been passed to KWASA by
LGD) to suit KWASA requirements;
Grameenphone IT – who have submitted a proposal to create a new billing system based on the
requirements of KWASA;
A meeting was held with GP IT; ADB; and KWASA in late November and concepts discussed further. ADB
agreed that, subject to GPOIT submitting a more detailed specification and proposal, ADB would be able
to support the cost of the implementation (US$ 4,500). A more detailed proposal was submitted during
the first week of December and is under consideration of ADB.
The draft agreement prepared between KWASA and GP IT is included in Appendix 10 – Annex G.
2.4.9. Accounting System Re-Introduction
In 2009 a computerized accounting system was introduced to KWASA. The system also includes a
number of support modules for inventory, fixed assets, payroll, HR, etc. Subsequent to becoming
operational a problem occurred with data corruption and the system was abandoned pending additional
support for re-introduction.
The system has been reviewed by an independent IT solutions provider who believes the system is
robust and could be re-introduced relatively simply provided that KWASA staff have sufficient to ensure
the correct operation in the future.
A proposal has been prepared by GP IT to undertake the re-introduction of the software, resolving the
hardware corruption problems and imparting training to KWASA staff. Quotations have also been
solicited from two other companies for the same scope of work - Further discussion is now required
between KWASA and ADB to agree on the preferred way forward with this implementation.
Appendix 1 CAPITAL INVESTMENT PLAN
i
KHULNA WATER SUPPLY AND
SEWERAGE AUTHORITY (KWASA)
CAPITAL INVESTMENT PLAN
2010
PREPARING THE KHULNA WATER SUPPLY
ADB TA 7385 – BAN
Appendix 1 CAPITAL INVESTMENT PLAN
i
Table of Contents Part A: Capital Investment for Khulna Water Supply Improvement ................................................................. 1
1.1 Introduction ...................................................................................................................................... 1
Part B: Supply Augmentation and Transmission ............................................................................................... 3
2.1 Production Well Collection to Distribution Storage .......................................................................... 3
2.2 Water Transmission .......................................................................................................................... 3
Part C: System Rehabilitation, Strengthening and Expansion ........................................................................... 5
3.1 Distribution Network Expansion ....................................................................................................... 5
3.2 Replacement of Existing lines............................................................................................................ 6
3.3 Metering and Service Connections ................................................................................................... 7
3.4 Installation of Valves and Bulk Meters .............................................................................................. 8
3.5 Provision of Distribution and Overhead Reservoirs .......................................................................... 8
3.5.1 Electro-mechanical Equipment ................................................................................................. 9
3.5.2 Pavement Reinstatement .......................................................................................................... 9
3.5.3 Sundry Improvement Works ................................................................................................... 10
Part D: Materials and Estimation ................................................................................................................ 10
4.1 Selection of Pipe Materials ............................................................................................................. 10
4.1.1 DNI Pipeline Materials ............................................................................................................. 10
4.1.2 Ductile Iron (DI) Pipes .............................................................................................................. 10
4.1.3 Polyethylene (PE) Pipes ........................................................................................................... 11
4.1.4 Unplasticized PVC Pipes .......................................................................................................... 11
4.1.5 Comparative Assessment of Pipe Materials ............................................................................ 11
4.1.6 DNI Pipe Material Recommendation ...................................................................................... 12
4.2 Unit Costing ..................................................................................................................................... 13
4.3 Project Investment .......................................................................................................................... 14
4.3.1 Clean Water Transmission....................................................................................................... 14
4.3.2 Distribution Reservoir and Overhead Tanks ........................................................................... 16
4.3.3 Distribution Network Improvement in Service Zones ............................................................. 16
4.3.4 Infrastructure Development and Supporting Activities .......................................................... 22
4.4 Procurement and Contract Packaging ............................................................................................ 24
4.5 Conclusions and Recommendations ............................................................................................... 25
Appendix 1 CAPITAL INVESTMENT PLAN
ii
List of Tables
Table 1: Overall Project Investment Plan .......................................................................................................... 2
Table 2: Overall Project Financing Plan ............................................................................................................. 2
Table 3: Clean Water Transmission Pipeline ..................................................................................................... 4
Table 4: Distribution Reservoir and Associated OHTs in Five Zones ................................................................. 4
Table 5: Design Pipe Lengths by Pipe Diameter in Zones ................................................................................. 5
Table 6: Existing Pipeline Details ....................................................................................................................... 6
Table 7: Household Service Connections – 2018 -2019 .................................................................................... 7
Table 8: Zonal Population Forecast ................................................................................................................... 8
Table 9: Projected Demand and Storage Requirement .................................................................................... 9
Table 10: Comparison of Pipe Materials ......................................................................................................... 11
Table 11: Project Investment Cost .................................................................................................................. 14
Table 12: Investment for Clean Water Transmission Works .......................................................................... 15
Table 13: Project Investment for Reservoirs and Overhead Tanks ................................................................. 16
Table 14: Project Investment for DNI Works in Zone 1................................................................................... 17
Table 15: Project Investment for DNI Works in Zone 2................................................................................... 18
Table 16: Project Investment for DNI Works in Zone 3................................................................................... 19
Table 17: Project Investment for DNI Works in Zone 4................................................................................... 20
Table 18: Project Investment for DNI Works in Zone 5................................................................................... 21
Table 19: Procurement of Goods and Works .................................................................................................. 24
Table 20: Probable List of Contract Packages under the Project .................................................................... 24
Appendix 1 CAPITAL INVESTMENT PLAN
1
Capital Investment for Production Increment and Distribution Network
Improvement
Part A: Capital Investment for Khulna Water Supply Improvement
1.1 Introduction
Residents of Khulna city have been suffering long time from limited access to safe potable water. Only 18 %
of over a 1.0 million city population have access to piped water supply and the rest resort to alternative
water sources such as river, pond and hand tube wells etc. Shallow hand tube wells water often contains
significant salinity and the surface water in the adjoining regions is saline for most part of the year. Piped
water supply was so far the responsibility of Khulna City Corporation (KCC), who could not supply adequate
piped water to the city dwellers due to non availability of suitable water source near to the city.
Recognizing the challenges, Government of Bangladesh established a separate and independent Khulna
Water Supply and Sewerage Authority (KWASA) in February 2008 with a view to meet the safe and reliable
water needs of the city people. KWASA is the third such organization in the country following similar
institutions in Dhaka (DWASA) and Chittagong (CWASA). KWASA has been established to provide water
supply and wastewater services for the Khulna City Corporation (KCC) area of about 45.60 sq km with over
1.0 population.
The existing water supply services are quite basic and limited in Khulna. Altogether some 230 kilometres of
pipe network of various materials and age supply water produced from groundwater wells. The quality,
quantity, reliability and accessibility of the present services are quite poor. After the establishment of
KWASA, Government of Bangladesh (GOB) has been actively promoting improvement in the services. In
this bid, support has been provided by JICA and ADB. ADB initiated its support through the SSTA 7223:
Supporting the Establishment of KWASA, which apart from other things went on to develop a roadmap for
the overall development of water supply in Khulna. The Japan International Cooperation Agency (JICA) has
shown strong interest in co-financing the various activities and initiated a feasibility study for the Khulna
Water Supply Project.
A number of investments are being planned for improvement of supply in the immediate and near future.
Apart from the proposed JICA and ADB investments envisaged with a more long term planning objectives
for development of Khulna water supply, some immediate investments have been earmarked by GOB,
which are being finalized for immediate implementation. The features of the immediate planned
investments with GOB funding are linked to the development of Water Supply System in Khulna City, which
include construction of new pipeline, replacement of pipeline, construction of new production wells,
construction of new SWTP, rehabilitation of existing SWTP, service connections with water meter and
expansion of water supply network for distribution of water from Phultala Source.
Appendix 1 CAPITAL INVESTMENT PLAN
2
JICA has committed to developing new surface water source with intake structures, raw water
transmission, impounding reservoir and surface water treatment plant facilities. ADB is planning to invest
in developing clean water transmission, distribution reservoirs, overhead tanks and pipeline distribution
network improvement for Khulna. In addition, ADB support is also envisaged for capacity building and
technical assistance to KWASA for the implementation of the proposed project and assistance is also
planned for institutional capacity building of KWASA with provisions for better office facilities, equipment,
vehicles and other sundry activities. The total project investment for the entire Khulna Water Supply
Project including budget from GOB and co-financing from JICA and ADB is summarized in the tables below:
Table 1: Overall Project Investment Plan
Item Amount
(million)
A. Base Costa
1. Civil works and equipment 238.9
2. Consultants 18.2
3. Land acquisition and resettlement 5.9
4. Administration costs 1.6
B. Contingenciesb
1. Physical Contingencies 13.6
2. Price Contingencies 24.3
C. Interest Charges During Implementation c 2.7
D. Taxes and Duties 58.4
Totald 363.5
a In mid-2010 prices.
b Physical contingencies computed at 4.9% for ADB-funded components and 5.0% for JICA-funded
components. Price contingencies computed at -3.7-0.5% for ADB-funded components and 1.8% for
JICA-funded components on foreign exchange costs and 7.2-7.3% for ADB and 4.8% for JICA funded
portion on local currency costs.
c Interest during construction has been computed at 1.0% ADF loan rate during the grace period for ADB
loan, and at 0.01% MIRAI loan rate for JICA loan.
d Figures may not add up due to rounding.
Table 2: Overall Project Financing Plan
Source
Amount
($ million)
Share of
Total (%)
Asian Development Bank 75.0 20.6
Japan International Cooperation Agency 184.0 50.6
Government 104.6 28.8
Total a 363.5 100.0
a Figures may not add up due to rounding.
The following sections of this report describe the proposed ADB support for water supply services
improvement of Khulna and related capacity building activities of KWASA.
Appendix 1 CAPITAL INVESTMENT PLAN
3
Part B: Supply Augmentation and Transmission
2.1 Production Well Collection to Distribution Storage
Ground water will continue to account for a significant component of the water supply in Khulna into the
future. The basic design philosophy of the JICA project is that water from the existing DTW’s is collected
and conveyed to the distribution service reservoirs rather than pumped directly into the distribution
network. The practicality of achieving this for all of the existing DTW’s (111 at 71 sites) will be difficult and
expensive given their relatively low and decreasing yield, age / useful life and deteriorating condition and
sparse nature of their locations.
From an operational point of view management and operation of so many small DTW’s is inefficient (in
terms of organisation and operating cost). Currently KWASA are abstracting around 30 Mld from the
aquifer through 31 production wells and 80 mini wells (at 40 sites). The output from all wells is reducing
principally due to aging of the wells – of the 31 production wells in operation, 21 have been regenerated
more than once and their useful life is coming to an end. KWASA also have plans to install 20 new
production wells through two GoB funded projects by the end of FY 2013/14 – the first already approved
for 13 wells, and the second yet to be approved for 7 wells. Therefore, from an operational point of view
and optimization of investment, it is advisable to initiate gradual abandoning of mini-wells and focus on the
regeneration and rehabilitation of production wells to enhance reliability and adequacy of water.
Given this KWASA would require 25 no. DTW’s producing 100 m3/hr for 20 hours a day to abstract the full
sustainable yield. It may also be prudent to retain some standby capacity in the case of the need for well
maintenance so it is suggested that KWASA in the medium term well develop strategy would include a
total of 30 no. 6” production wells producing 100 m3/day. This may further increase over the long term as
present KWASA HTW and private Deep Well users gradually shift to the piped network.
The location of the DTW’s should be such that, on average, within a distance of about 500 -700m from the
nearest storage reservoir. It appears that KWASA have sufficient funds identified to develop the wells
through GoB. Provision for the collector mechanism has been included in the ADB proposal. Accordingly,
based on an average collector pipe distance of 650 metres from the nearest storage reservoir this would
require a total collector length of about 20 km assuming an average pipeline diameter of 200 mm using DI
pipes.
2.2 Water Transmission
The treated clean water from the surface water treatment plant proposed under JICA support needs to be
conveyed to the five distribution reservoirs proposed for each zone. The total pipe length required for the
transmission mains from the SWTP is about 27 kilometres. These pipes vary in size from 1100 mm to 300
mm in diameter. The pipe sizing and their alignment is in accordance with the proposal made under the
JICA supported Feasibility Study for Khulna Water Supply Project. The pipe materials for clean water
transmission shall be DI conforming to ISO 2531, as mentioned below. The various pipe sizes and their
length proposed for clean water transmission is given in the table below.
Appendix 1 CAPITAL INVESTMENT PLAN
4
Table 3: Clean Water Transmission Pipeline
Diameter (mm) Length (m)
1100 mm 10,900
900 mm 1,500
800 mm 1,900
600 mm 4,400
500 mm 6,300
300 mm 400
Total 25,400
It is to be reiterated that no service connections shall be permitted from the transmission mains, which are
specifically meant for feeding the five distribution reservoirs.
Another type of pipe not clearly seen accounted for in the JICA estimates were the pump mains from the
distribution reservoir to the overhead tanks. The pipe length of the pumping mains from each of the five
distribution reservoirs to the eleven overhead tanks in their respective distribution zones has been
estimated. The total length of such pumping mains is estimated as 35 kilometres with an average diameter
of 250 mm using DI pipes, the details of the same is given in the table below.
Table 4: Distribution Reservoir and Associated OHTs in Five Zones
Location of Ground Reservoir Location of Connected OHT Length of Transmission
main (m)
Zone-1 : Deana Westpara UGR Rab Sarani 5280
Deana West Para 240
Zone-2 : W-16 office UGR
W-16 office OHT 240
Mujgunni OHT 1200
Sonadanga Moh-S-OHT 2400
Zone-3 : Sonadanga Moha Sarak UGR Andir Pukur OHT 3360
W-31 office OHT (South) 7920
Zone-4 : W-7 office UGR W-7 office OHT 240
Khalispur Charar Hat ghat -OHT 4080
Zone-5 : Khalispur Carerhat ghat UGR Ferry Ghat Power House OHT 3600
DPHE Pupsha Ghat OHT 6240
Appendix 1 CAPITAL INVESTMENT PLAN
5
Part C: System Rehabilitation, Strengthening and Expansion
3.1 Distribution Network Expansion
JICA has proposed for the division of the entire service area under KWASA into five service zones. Each of
the five service zones are further divided into several sub-zones in consideration of the proposed eleven
overhead tanks located at various vantage points. Working under the principle that any distribution zone
shall only be supplied through a distribution reservoir / overhead tanks, a total of eleven sub-zones have
been identified.
Totally new distribution networks for each of the eleven sub-zones proposed by the JICA Report has been
verified and adopted for the network development and expansion in each of the five supply zones. Each of
the proposed distribution networks consist of pipelines from the overhead tank to all the major areas along
existing road networks. These are the primary and secondary distribution mains down to a pipe size of 150
mm. Service and connection mains of sizes below 150 mm diameter have not been considered at this
stage, which can be done at a later stage when detailed design and implementation works are being
conducted. However, an assessment of the pipelines below the size 150 mm has been made, i.e. 100 mm,
75 mm and 50 mm uPVC pipes have been estimated for each zone in consideration of the service area,
population to be served and other related parameters. The estimation of the secondary and tertiary
service mains have been based on the settlement pattern and area under consideration in each zone.
The distribution network has been designed using discrete pipe sizes ranging from 150 mm to 400 mm. It
has been proposed that DI pipes be utilized for pipe sizes of diameter 250 mm and above, while uPVC pipes
are proposed for distribution supply pipelines of sizes 200 and below. The design length of the major pipes
has been increased by 5 % in the cost estimates to account for any unforeseen scenarios.
The distribution network cost proposals include procurement and installation of various lengths of
distribution pipelines ranging in diameter from 400 – 150 mm. These are DI and PVC type of pipes.
Distribution and service pipes of diameters 100mm, 75mm and 50mm have been proposed also in each
zone, which are of uPVC material. The actual pipe lengths by diameter in the various zones, as proposed for
project costings are summarized the table below:
Table 5: Design Pipe Lengths by Pipe Diameter in Zones
Diameter
(mm)
Pipe Lengths in Service Zones (m) Total Length
(m) Zone 1 Zone 2 Zone 3 Zone 4 Zone 5
400 0 1,500 1,200 0 0 2,700
350 1,300 1,600 3,500 2,500 900 9,800
300 3,700 2,900 1,200 1,600 1,300 10,700
250 13,800 21,800 9,900 9,500 11,700 66,700
200 15,700 27,700 20,000 10,700 6,400 80,500
150 20,700 32,700 24,500 19,200 13,400 110,500
100 25,000 25,000 25,000 15,000 15,000 105,000
75 25,000 25,000 25,000 15,000 15,000 105,000
50 15,000 15,000 15,000 10,000 10,000 65,000
120,200 153,200 125,300 83,500 73,700 555,900
Appendix 1 CAPITAL INVESTMENT PLAN
6
For improvement in the water supply services it is proposed to gradually carry out the following:
• As proposed, the surface water transmission and feeder mains shall feed directly in to the
distribution / service reservoirs.
• All existing and proposed production wells under KWASA should also connect into proposed
reservoirs or overhead tanks in their respective zones. The production wells should not inject
water into the distribution network directly to the extent it is technically viable.
• It is expected that the designated zone or sub-zones within the area shall be fed by a single
dedicated supply main coming out of the reservoir / overhead tank with bulk flow meter for
monitoring and management.
• No connections, private, commercial or institutional, shall be permitted directly from supply mains.
Connections will only be permitted from distribution pipelines only in zones or their sub-zones.
3.2 Replacement of Existing lines
There are about 230 kilometres of existing pipe lines, which comprise of asbestos, MS, PVC among others.
A breakdown of the existing pipelines under KWASA is given in the table below:
Table 6: Existing Pipeline Details
S.N. Diameter (mm) Approximate Length (km) Material
1. 75 2.62 PVC
2. 100 110 PVC
3. 150 66 PVC
4. 200 22 (MS, AC 6 km)
5. 250 10.55 MS, AC
6. 300 16.30 MS, AC
The old large pipes are envisaged to be in a poor state and unusable, therefore needs to be replaced.
However, some of the uPVC pipelines installed in the last decade or so may be in a form to be used again.
This can only be ascertained after a detailed investigation and assessment. uPVC pipes in the diameter
range 150 mm – 100 mm may be considered for reuse, if found in a good and usable state. But, smaller
diameter service pipelines are likely to be disturbed and damaged during the implementation process of
the ensuing loan and, hence, will have to be largely replaced. In conclusion the salvage value of the existing
pipelines is very small.
Appendix 1 CAPITAL INVESTMENT PLAN
7
3.3 Metering and Service Connections
Metering of service connections is a priority for KWASA and has been accorded considerable importance in
the ensuing ADB loan. The metering and connection programs include metering of existing connections –
legal and illegal – and installation of service connections in distribution areas where supplies are gradually
enhanced. The Project also envisages setting up District Metering Areas (DMA) within the service zones to
monitor production, supply and consumption of water supplied and monitor UFW and NRW. Major
investment would be in the installation of household service connections. It is assumed that with gradual
increase in production and improved distribution system, the number of household service connections
will gradually increase. Each household connection shall comprise of saddle tap, fittings, 6 m length of 20
mm uPVC pipe, 20 mm household cold water meter and other related materials. It has been estimated that
the unit cost of a household service connection is estimated at about $ 135. For project costing purposes,
the number of households assumed availing services from KWASA piped water supply at the end of the
fiscal year 2018 in each of the five zones has been used. However, field observations have indicated that
the on the average 2.82 households would be connected through a service connections. Accordingly, some
54,300 service connections would be required to distribute water to the end-user through the KWASA
piped network. However, considering higher number of connections with better services, uncertainty
involved in households to service connection ratios and need for replacement of malfunctioning service
connections; a 20 percent contingency to the number of connections has been proposed. Accordingly, the
details of the service connections in service zone are given in the table below:
Table 7: Household Service Connections – 2018 -2019
Service Connection Requirement in 2018
- 2019 Zone 1 Zone 2 Zone 3 Zone 4 Zone 5 Total
House / Service Connections 9,535 16,700 15,507 14,291 9,127 65,160
Additional Meters for KWASA Inventory 2,500 4,000 1,550 1,430 910 10,390
The primary criterion for the establishment of a DMA / DMZ is that the distribution network for the
demarcated area can be easily isolated by installation of control valves and other such mechanisms. Bulk
meters will be installed to monitor the total volume of water supplied to the demarcated area. It shall be
mandatory that all the connections within the area are properly metered. At the moment it is difficult to
state the number of DMA / DMZs that can be established, but provision has been earmarked in the project
estimates for individual zones for the provision of house connections, additional household meters, control
valves, bulk meters, chambers, etc. which is required for establishing a DMA/DMZ. Detailed layout of
individual DMA/DMZs and the location of control valves and bulk meters shall be done during the detailed
design phase. For the present purposes a DMA is expected to have about 2500 house connections. Initial
assessments performed indicate that about 22 DMAs can be developed with 3 DMAs in Zone 1; 6 in Zone 2;
5 in Zone 3; 5 in Zone 4 and 3 in Zone 5.
For KWASA to develop in to a robust, vibrant and profitable water utility, it must focus on metering of all
service connections including connections provided to low income communities. In this regard, use and
stocking of a standard household cold water meter would be essential in line with an approved KWASA
connection policy. To make this effort sustainable, the staff should be well trained in metering, calibration
and repair of meters. Thus, a small meter calibration and testing workshop with repair facilities should be
developed within KWASA well supported by spare parts.
Appendix 1 CAPITAL INVESTMENT PLAN
8
3.4 Installation of Valves and Bulk Meters
The project cost estimation also account for installation of valves and bulk meters at vantage points in the
distribution system, inlet and outlets of reservoirs and OHTs and demarcated DMAs in the system. A
number of control valves including air release valves have been provided for in the estimates for individual
service zones. RCC chambers with easy access and manhole covers have also been provided for to protect
major valves and bulk meters from vandalism and weather elements. Units costs of the fittings, meters,
and valves have been developed after exhaustive assessment of available rates and installation charges
and cost of valve and meter chambers also formulated in a similar manner. Zone wise estimation of these
valves and meters and RCC chambers housing them has been performed.
3.5 Provision of Distribution and Overhead Reservoirs
The total service area under KWASA includes all the 31 wards of KCC. In each zone apart from a robust and
rehabilitated pipe distribution network there would be a distribution reservoir and overhead tanks. It has
been deemed necessary that virtually a new distribution network be developed, which can be easily
monitored for efficient operation and maintenance. Five distribution zones have been recommended for
further planning, design and implementation, wherein the railway and trunk road act as the boundary and
the western area is divided into 3 zones and the eastern area is divided into 2 zones. The zone population,
storage and balancing capacities proposed for service area is given in the table below:
Table 8: Zonal Population Forecast
Wards covered Pop. 2010 Pop. 2020 Pop. 2030 Distribution
Reservoir
Capacity –
Based on
Demand
Distribution
Reservoir
Capacity -
Adopted
OHT
Proposed
Zone 1 1,2,3,4,5,6 143101 174439 212639 8000 8,000 300 – 2 Units
Zone 2 9,14,16,17,18,19,25 250643 305533 372442 14,000 9,000 300 – 2 Units
500 – 1 Unit
Zone 3 24,26,27,28,30,31 232715 283679 345804 13,000 18,000 500 – 2 Units
Zone 4 7,8,10,11,12,13,15 214478 261447 318703 10,000 5,000 500 – 2 Units
Zone 5 20,21,22,23,29 136969 166965 203530 8,000 15,000 300 – 2 Units
977906 1192063 1453118 53,000 55,000
The distribution zones adopted by the JICA Feasibility Study are generally pragmatic from an operational
point of view. Their location and sizes are such that a balanced distribution zones can be developed and
operated, except for the case of Zone 3 and Zone 5 where they are located in slightly away location. This
Appendix 1 CAPITAL INVESTMENT PLAN
9
could be due to the non-availability of adequate and proper land to locate such large structures within the
centre of the city. The approach of having individual distribution reservoirs with 12 hours retention of the
daily demand and overhead tanks to streamline water distribution is valid.
Using the projected zonal demand scenario, the individual zonal storage requirement has been developed
for 2020 and 2030. However, in consideration of the KWASA objective of developing the distribution
scenario for 2030, the projected storage requirement for 2030 at 25 % storage capacity has been
recommended for adoption. This storage requirement is very similar to the JICA Study Team’s
recommended total storage capacity of 55000 cu.m. The projected demand and storage estimated carried
out under the present assessment is given in the table below:
Table 9: Projected Demand and Storage Requirement
Average Daily Water Demand (m3/day)
Storage Requirement “m3”
(25%)
2009 2010 2015 2020 2025 2030 2020 A.D. 2030 A.D.
Zone 1 4464 5277 9072 16033 24818 29891 4000 7000
zone 2 7818 9245 15888 28079 43469 52354 7000 13000
Zone 3 7259 8580 14753 26073 40360 48607 7000 12000
Zone 4 6691 7907 13597 24031 37197 44797 6000 11000
Zone 5 4273 5051 8683 15346 23757 28610 4000 7000
28000 50000
3.5.1 Electro-mechanical Equipment
A detailed assessment of the provisions made in the electro-mechanical estimates of JICA for the proposed
SWTP, pumping stations at reservoirs, etc. was made by the PPTA Team. The PPTA team based on the JICA
Report assessment made an independent estimate of the various components, its capacity, required
accessories and other equipment. Unit rates for the various equipment identified, their transportation and
installation charges were also developed and adopted to develop the costs for the mechanical and
electrical equipment required at the five distribution reservoirs and six of the overhead tanks – for the
remaining five overhead tanks the costing was done jointly for ground reservoirs and OHTs considering the
proximity of their location on the same premises.
3.5.2 Pavement Reinstatement
With nearly 600 kilometres of pipe being laid within the city precincts, the existing paved and also unpaved
road surfaces are going to be disturbed during the installation of pipes, fittings, valves, etc. The project has
Appendix 1 CAPITAL INVESTMENT PLAN
10
made provisions to reinstate the paved and unpaved road surfaces to its original position once the
activities have been completed. In this regard, it has been assumed that of the total pipe length nearly 60
% of the length would laid on paved roads while 40 % length would be unpaved or gravel road surface.
Reinstatement works involve of base course, compaction, grouting, seal coating etc., as per the standards
and requirements of KCC. Costing has been done on the reinstatement area estimated based on the pipe
trench length and width.
3.5.3 Sundry Improvement Works
Other sundry activities would involve setting up of a small water quality monitoring unit at each of the
distribution reservoirs, some required tools and equipment, leak detection equipment, etc. These have
also been included in the zone wise project cost to enhance the overall performance of the project and the
investments made.
Part D: Materials and Estimation
4.1 Selection of Pipe Materials
4.1.1 DNI Pipeline Materials
For pipes used in water supply conveyance and distribution, a number of materials exist including Ductile
Iron (DI), Galvanized Iron (GI), PVC, Polyethylene (PE) and Glass Reinforced Plastic (GRP), among many
others. Several studies in the past have made specific recommendations based on the pipe size to be used
and the soil conditions and experience of local craftsman in laying and joining distribution network pipes.
Other considerations like cost, ease in installation and better performance over a long period of time also
needs to be assessed.
For the current study, it seemed prudent that a brief comparative assessment of major pipe materials for
distribution network pipes be considered before recommending particular materials for subsequent use
and implementation. The following comparison is for the most appropriate materials to be considered for
the Distribution Network Improvement (DNI), i.e., DI, PE, GI, and uPVC. These materials are compared for
their relative ease in transportation, installation and laying, material and laying costs, availability of fittings,
internal and external coating and operation and long term maintenance.
4.1.2 Ductile Iron (DI) Pipes
Ductile Iron pipes have been extensively used for water works throughout the world because of the
flexibility and ease in installation, pressure ratings, longevity and resistance to different soil conditions. The
most common type of DI pipes are the K9 class conforming to ISO 2531 (1998) and EN 545 (2006). The
principal properties of the ductile iron is a yield stress of over 300 MPa, tensile strength of over 420 MPa,
elongation of over 10%, and Brinell hardness less than 230. The impact strength of DI pipes is exceptional
and allows a variation in pipe alignment up to 4%; depending upon pipe diameter. Normally, DI pipes are
available for diameters ranging from 80 mm to 1200 mm. Normal allowable operating pressure for K9 class
pipes range from 29.4 to 58.8 bars. The internal surface of DI pipes is coated with cement mortar lining,
which is applied by centrifugal process. Similarly, the external protective coating of DI pipes is zinc plus
bitumen. This provides a high degree of protection against most soil conditions. Other features of DI pipes
shall be similar to the earlier description made under BDS pipe material options.
Appendix 1 CAPITAL INVESTMENT PLAN
11
4.1.3 Polyethylene (PE) Pipes
Polyethylene pipes are extensively used for bulk water supply especially in Europe considering their
flexibility and ease in laying quickly. PE pipes are designed, manufactured and supplied under a BS EN ISO
9001:2000 accredited Quality Management System. Two most common types of PE pipes used are PE80
and PE 100.
PE80 – This is the term used to denote the polyethylene material which has been widely used for gas,
water and industrial applications for many years. The terms MDPE and HDPE were commonly used to
describe this material.
PE100 – This is a term used to denote high performance polyethylene. PE100 is a higher performance
material than PE80 and demonstrates exceptional resistance to rapid crack propagation as well as to long-
term stress cracking. Moreover, the higher strength of PE100 permits thinner pipe walls than PE80 for the
same operating pressure. PE100 uses less polymer and provides for a larger bore and increased flow
capacity for a given nominal pipe size. This can result in significant cost savings at certain sizes and pressure
ratings.
PE pipes are manufactured from a diameter of 20 mm to 1000mm normally. However, larger diameter PE
pipes can also be manufactured subject to scale or magnitude of order. Allowable working pressure for
PE80 pipes varies from 12.5 to 8 bars, whereas for PE100 it varies from 16, 10, 8 and 6 bars for SDRs (ratio
of outer diameter to average wall thickness) 11, 17, 21 and 26.
4.1.4 Unplasticized PVC Pipes
More recently uPVC pipes are being used in urban water systems, as they are available in large range of
pipe diameters and pressure classes. There are a few manufacturers of uPVC pipes in the country and also
imported from third countries. They are available in pipe diameters ranging from 20 mm to over 300 mm
and in pressure classes ranging from 2.45 – 14.7 bars.
4.1.5 Comparative Assessment of Pipe Materials
The four pipe materials discussed have their own distinct advantages and disadvantages. However, for the
present purposes the pipe materials have been comparatively assessed in terms of the following factors –
transportation; laying and joining; strength, operation and maintenance (including availability of spare
parts) and initial investment costs. The comparative table below summarizes the advantages and
disadvantages of the four pipe materials:
Table 10: Comparison of Pipe Materials
Pipe Material Advantages Disadvantages
DI (K9 Class) • Pipes are relatively strong and can withstand
large external loads with modest bedding.
• The majority of standard pipes and fittings can
handle pressures up to 16 Bar.
• The flexible joint system means that earthquake
movements can be accommodated.
• The strength of the pipes means they are less
likely to be damaged.
• Ductile iron pipes can be laid quicker with short
lengths of trench causing less disruption to road
traffic.
• The system can be modified and additional
facilities easily added to the pipe network.
• Ductile iron pipes are semi-rigid pipes and
generally do not require bedding to be of as high
a standard as PE or PVC pipes.
• Restrained joint can be provided by
most manufactures where the pipes
are to withstand some longitudinal
forces; however, generally anchor
(thrust) blocks are required.
• Unit weight of pipes is generally
higher than PE and PVC Pipes.
• Transportation cost can be relatively
higher.
• Per unit cost of DI pipes in
comparison with GI Pipes is similar,
but becomes cheaper for larger
diameter pipes.
Appendix 1 CAPITAL INVESTMENT PLAN
12
Pipe Material Advantages Disadvantages
PE100 / HDPE • PE100 pipes are relatively lighter in unit weight
and easier to transport.
• The internal surface is much smoother resulting
in higher “C” value or lower resistance.
• Repair and maintenance is relatively easy
• More suited for conveyance of potable water.
• Greater laying flexibility and requires average
bedding requirements.
• The pressure rating of the larger
diameter pipes is limited.
• Without good storage conditions
plastic pipes deteriorate, and storage
of materials for future repairs may be
difficult.
• Butt-fusion welding of joints needs
special equipment and skill.
• Susceptible to damage by rodents
and creatures of that nature.
uPVC Pipes • uPVC pipes are relatively lighter in unit weight
and easier to transport.
• The internal surface is much smoother resulting
in higher “C” value or lower resistance.
• Suited for conveyance of potable water.
• uPVC pipes are rigid enough for threading and
joining works similar to GI pipes.
• The pressure rating of the larger
diameter pipes is limited.
• To ensure the pipeline has good
structural properties, a good standard
of bedding is required.
• Without good storage conditions
plastic pipes deteriorate and storage
of materials for future repairs may be
difficult.
• Laying and joining of uPVC pipes
requires better skills and joining
materials.
A comparison of the three pipe materials in relation to their unit costs is presented in the chart below. As is
evident, there is not to choose from in terms of unit rates between uPVC and PE 100 for smaller diameter
ranges. However, for larger diameter sizes the costs for DI pipes do increase comparatively. Thus, choosing
of pipe materials should be contingent upon the unit rate, ease in installation, longevity and availability of
spares for repair and maintenance works.
4.1.6 DNI Pipe Material Recommendation
For the present DNI works in Khulna it is recommended that all pipes of sizes DN 250 and above shall be DI.
While for smaller diameter pipes including those for house connections, non-metallic pipes – i.e. PE and
0
50
100
150
200
250
300
350
400
450
500
50 75 110 160 200 225 250 280 315 355 400 450 560
Un
it C
ost
$/m
)
Diameter (mm)
DNI PIPE COMPARISON
PE 100
uPVC
DI
Appendix 1 CAPITAL INVESTMENT PLAN
13
uPVC are recommended for use. However, the extensive experience in use and installation of uPVC pipes in
Bangladesh, it is recommended for use in the distribution system. PE100 material of pipes is relatively new
for Bangladesh and skill in pipe joining techniques is not readily available locally. Till such a time when use
of PE100 pipes becomes more common and good skills in pipe joining is easily available, uPVC should be
the prime pipe material for use in water distribution systems. However, PE100 can be used on a pilot basis,
if new technology and materials are to be encouraged.
4.2 Unit Costing
The PPTA reviewed the costing done by the JICA Team and carried out extensive exercise to further
develop the packages, which were termed Package 3 and 4 by the JICA Feasibility Study. The PPTA Team
developed total project cost for ADB financing primarily for the transmission of clean water from the
proposed surface water treatment plant, DNI in five zones, reservoirs and OHTs for various zones and
related electro-mechanical works
Estimation of investment packages for the ensuing ADB loan has been done using existing market rates,
prevalent unit rate analyses and other quick estimation tools based on previous actual incurred costs
adjusted for inflation. For material rates market rates from both national and international suppliers and
manufacturers have been collated and adjusted for present use. Rates from Public Works Department
(PWD), Bangladesh Water Development Board (BWDB) and Dhaka Water Supply and Sewerage Authority
(DWASA) were also collected to develop unit rates for estimation purposes.
Costs for the DI pipe materials for sizes ranging from 250 mm to 1100 mm were developed using a cost
function developed and stated in "Design of Water Supply Pipe Networks" Prabhata K. Swamee and Ashok
K. Sharma, WILEY-Interscience. The prices established using the above mentioned cost function was further
compared with existing market rates, JICA proposed rates, DWASA rates. The results from this exercise
were consolidated to develop unit rates for DI pipes and fittings. Similarly, unit rate analyses for earthwork,
blanket, backfill materials, pavement reinstatement, etc. were carried out in accordance with GOB norms
and per unit rates developed.
Costing for the Distribution Network Improvement (DNI) has been based on actual costs developed for
GOB funded improvement works being proposed for implementation by KWASA and other similar works.
Typical DNI works with distribution pipeline, valves, appurtenances, household meters, pavement
reinstatement, etc. were costed and unit cost developed.
Electro-mechanical equipment primarily comprises of pumps, motors, panel boards, transformers,
generators, dosing units and other such components. Costing of such components has been based on
prevailing market rates, which were further collaborated with actual rates obtained from tender awards for
similar works carried out in Bangladesh and neighboring areas in the region. Installation charges etc. of
such equipment were added to the equipment cost and the total budget / investment developed.
Distribution reservoirs and overhead tanks (OHT) proposed under the ensuing loan have been costed using
unit rates developed from actual costs of construction of such reservoirs elsewhere in Bangladesh and
construction rates of PWD, LGED and BWDB. It has been presumed that all newly proposed reservoirs shall
be RCC, either elevated overhear tanks or ground storage reservoirs. Actual costs from a number of
projects in Bangladesh in the recent past were analyzed and a unit cost was developed.
Costing for other civil works like chambers, construction of small buildings, etc. has been done using
prevailing unit rates for construction adjusted for inflationary measures. Such unit rates have been
developed using actual costs of similar structures and works.
Other procurement materials include leak detection equipment, meter calibration bench, portable water
quality equipment, tools and equipment and similar equipment. Budgeting for such items have been based
market rates and unit costs used in similar projects in the region. These unit costs have accordingly
adjusted for potential price fluctuations and rounded for establishing budgetary requirements.
Appendix 1 CAPITAL INVESTMENT PLAN
14
4.3 Project Investment
Total project cost for ADB financing comprises primarily of the transmission of clean water from the
proposed surface water treatment plant, DNI in five zones, reservoirs and OHTs for various zones and
related electro-mechanical works and other support for KWASA building infrastructure, equipment and
vehicles and technical assistance. The sections here summarize the investment for transmission,
distribution improvement, reservoir and overhead tank construction and other infrastructure development
activities. The overall project investment excluding price or physical contingencies for transmission and
distribution network improvement works and related works is given in the table below:
Table 11: Project Investment Cost
CONSTRUCTION & SUPPLY CONTRACTS US$ Million Taka Billion
1 Transmission Main Installation; 29.49 2.06
2 Civil Works – Distribution Storage and OHT’s; 21.47 1.50
3 Zone 1 DNI 8.86 0.62
4 Zone 2 DNI 13.59 0.95
5 Zone 3 DNI 9.97 0.70
6 Zone 4 DNI 7.41 0.52
7 Zone 5 DNI 6.10 0.43
8 DTW Rehabilitation – Equipment supply and installation contracting Including provision for regeneration of Phultala Wells
0.30 0.02
9 Construction of HQ and 3 2-Storey Zonal Offices 2.12 0.15
10 Provision of Operational Vehicles & Office Equipment 1.24 0.09
11 LIC & Slum Area Infrastructure Provision 1.70 0.12
12 Groundwater Monitoring System 0.22 0.02
13 Deep Aquifer Test Drilling 0.75 0.05
14 Meter Testing Laboratory equipment 0.25 0.02
15 Business Systems hardware & software 0.75 0.05
Construction/Materials Sub-Total 104.22 7.30
CONSULTANCY CONTRACTS
16 Corporate Management – Consultant support to KWASA 2.00 0.14
17 Engineering Design – Detailed survey & design, contractor procurement and implementation supervision
5.49 0.38
Consultancy Sub-Total 7.49 0.52
TOTAL 111.71 7.82
4.3.1 Clean Water Transmission
The major components under this are transmission mains from the treatment plants to the five distribution
reservoirs including necessary fittings, valves, bulk meters, RCC chambers, etc. Cost for a major river
crossing for the transmission main is also accounted for under this heading. Reinstatement costs for
existing road pavement surfaces and costs for pipeline excavation, filling and bedding has also been
Appendix 1 CAPITAL INVESTMENT PLAN
15
included. The collector mains from existing and proposed production wells of KWASA to the distribution
reservoirs and the pumping mains from the distribution reservoirs to the eleven overhead tanks has also
been included under this project component. It is proposed that a common meter calibration and testing
facility should also be developed. Details of the various components, units costs / rates and total
investment under this package is given in the summary table below:
Table 12: Investment for Clean Water Transmission Works
S.No. Description Quantity Unit Rate US$ Total Amount US$
I Water Supply Component
A Civil Works & Distribution Pipe Line
1 Meter / Valve Chambers (Type 3) 20 Nos. 594.02 11,880
2 Meter / Valve Chambers (Type 4) 20 Nos. 617.97 12,359
3 Meter / Valve Chambers (Type 5) 5 Nos. 667.71 3,339
4 Meter / Valve Chambers (Type 6) 5 Nos. 1,167.82 5,839
5 River Crossing (390 m) 390 m 12,000.00 4,680,000
6 Reinstatement & Re-sealing of Black topped Road 48,120 Sq.m 25.00 1,203,000
7 Re-instatement of the Gravel Road 32,080 Sq.m 10.00 320,800
Sub-Total "A1"
6,237,217
B 1. Pipeline & Fittings Works
1 Pipes - Supply, Laying, Installation and Testing
a) DI
1100 mm 10,900 m 785.50 8,561,950
900 mm 1,500 m 659.50 989,250
800 mm 1,900 m 585.50 1,112,450
600 mm 4,400 m 457.30 2,012,120
500 mm 6,300 m 382.30 2,408,490
300 mm 400 m 147.25 58,900
250 mm (Pumping Mains RVT to OHT) 34,800 m 114.25 3,975,900
200 mm (Collector Mains from DTW to RVT) 20,000 m 89.25 1,785,000
2 Pipe Fittings - Supply and installation
b) DI
Sizes 200mm - 250mm 1,096 Nos 880.08 964,568
Sizes 300mm - 400mm 13 Nos 1,009.16 13,119
Sizes 500mm - 600mm 214 Nos 2,015.00 431,210
Sizes 800mm - 900mm 34 Nos 3,520.00 119,680
Sizes 1000mm and above 44 Nos 7,525.00 331,100
3 Valves
Sizes 300mm - 400mm 2 Nos 2,509.72 5,019
Sizes 500mm - 600mm 10 Nos 3,615.00 36,150
Sizes 800mm - 900mm 3 Nos 10,020.00 30,060
Sizes 1000mm and above 5 Nos 14,775.00 73,875
4 Bulk Meters
Sizes 200mm - 250mm 15 Nos 3,505.36 52,580
Sizes 300mm - 400mm 15 Nos 5,009.25 75,139
5 Pipeline Trench Excavation & Backfilling
a) Excavation for pipeline trenches in Boulder Mixed Soil 43,308 m3 3.60 155,909
b) Backfilling in Layers 38,977 m3 0.99 38,587
c) Sand bed for pipe laying (at least 100 mm thick) 4,000 m3 6.50 26,000
6 Supply and Installation of Water Meter Testing 1 Nos. 15,000.00 15,000
and Calibration Benches (units)
Sub-Total "B"
23,257,057
Total A and B
29,494,274
Appendix 1 CAPITAL INVESTMENT PLAN
16
4.3.2 Distribution Reservoir and Overhead Tanks
As discussed earlier, there are altogether five distribution reservoirs and eleven overhead tanks in the five
supply zones. The project investment under this component includes cost of the reservoirs and overhead
tanks and the associated electro-mechanical equipment at each reservoir and overhead tank location. The
costs also include outflow bulk meters, telemetry equipment, etc. for the reservoirs and the overhead
tanks. In addition some budget has been allocated to rehabilitate and regenerate some of the existing
production wells as well as install necessary items like bulk meters at these wells. Details of the various
components, units costs / rates and total investment under this package is given in the summary table
below:
Table 13: Project Investment for Reservoirs and Overhead Tanks
S.No. Description Quantity Unit Rate US$ Total Amount US$
I Distribution Reservoir
A Civil Works
1 Deana West Para Reservoir - 8000 m3 1 Nos. 2,493,770 2,493,770
2 Ward No. 16 O- 9000 m3 1 Nos. 2,668,383 2,668,383
3 Sonadanga Moha Sarak Reservoir - 18,000 m3 1 Nos. 4,320,196 4,320,196
4 Beside of No.7 Ward Office Reservoir - 5000 m3 1 Nos. 1,885,445 1,885,445
5 Khalishpur Charehat River Ghat Reservoir - 15,000 m3 1 Nos. 3,703,368 3,703,368
Sub-Total "A"
15,071,162
B Mechanical Works
1 Distribution Reservoirs - 5 Pumping Stations 1 Set 1,030,282 1,030,282
2 Rehabilitation and regeneration of existing production wells 1 Set 300,000 300,000
Sub-Total "B"
1,330,282
C Electrical Works
1 Deana West Para Reservoir - 8000 m3 1 Set 250,441 250,441
2 Ward No. 16 O- 9000 m3 1 Set 238,798 238,798
3 Sonadanga Moha Sarak Reservoir - 18,000 m3 1 Set 440,227 440,227
4 Beside of No.7 Ward Office Reservoir - 5000 m3 1 Set 172,216 172,216
5 Khalishpur Charehat River Ghat Reservoir - 15,000 m3 1 Set 445,441 445,441
Sub-Total "C"
1,547,124
Total "I"
17,948,568
II Overhead Tanks
A Civil Works
1 OHT - 500 m3 6 Nos. 337,066 2,022,396
2 OHT - 300 m3 5 Nos. 256,898 1,284,489
Sub-Total "A"
3,306,885
B Electrical Works
1 Six OHTs located away 1 Set 213,673 213,673
Sub-Total "B"
213,673
Total "II"
3,520,559
Total "I" and "II"
21,469,127
4.3.3 Distribution Network Improvement in Service Zones
Distribution network improvement works in each zone includes costs of distribution and service mains,
house connections, water meters and associated fittings, valves and bulk meters. All the costs associated in
establishing District Metering Areas (DMAs) have also been accounted for within the DNI costs.
Reinstatement costs for existing road pavement surfaces and costs for pipeline excavation, filling and
bedding has also been included in each zone. DNI works also include small costs for the procurement of
tools and equipment required for pipe and fittings installation and repairs, leak detection equipment and a
portable water quality monitoring equipment in each zone. Details of the various components, units costs /
Appendix 1 CAPITAL INVESTMENT PLAN
17
rates and total investment under packages for each of the service zone is given in the summary tables
below:
Table 14: Project Investment for DNI Works in Zone 1
S.No. Description Quantity Unit Rate US$ Total Amount US$
I Water Supply Component
A Civil Works & Distribution Pipe Line
1 Meter / Valve Chambers (Type 1) 70 Nos. 544.68 38,127
2 Meter / Valve Chambers (Type 2) 75 Nos. 570.03 42,752
3 Meter / Valve Chambers (Type 3) 35 Nos. 594.02 20,791
4 Meter / Valve Chambers (Type 4) 30 Nos. 617.97 18,539
5 Meter / Valve Chambers (Type 5) 15 Nos. 667.71 10,016
6 Miscellaneous Structure 1 LS 50,000.00 50,000
7 Reinstatement & Re-sealing of Black topped Road 50,484 Sq.m 25.00 1,262,100
8 Re-instatement of the Gravel Road 33,656 Sq.m 10.00 336,560
9 House / Service Connections 9,558 No 135.28 1,293,052
10 Additional Meter for KWASA Inventory 2,500 Sets 30.00 75,000
Sub-Total "A1"
3,146,937
B 1. Pipeline & Fittings Works
1 Pipes - Supply, Laying, Installation and Testing
a) DI
350 mm 1,300 m 220.30 286,390
300 mm 3,700 m 147.25 544,825
250 mm 13,800 m 114.25 1,576,650
b) PVC
200 mm 15,700 m 59.25 930,225
150 mm 20,700 m 17.60 364,320
100 mm 25,000 m 14.55 363,750
75 mm 25,000 m 11.47 286,750
50 mm 15,000 m 9.47 142,050
2 Pipe Fittings - Supply and installation
a) PVC
Sizes 50mm - 75mm 1,600 Nos 22.02 35,232
Sizes 100mm- 150mm 1,523 Nos 38.04 57,935
Sizes 200mm 523 Nos 55.08 28,807
b) DI
Sizes 250mm - 300mm 583 Nos 880.08 513,087
Sizes 350mm - 400mm 26 Nos 1,009.16 26,238
3 Valves
Sizes 80mm - 100mm 25 Nos 509.72 12,743
Sizes 100mm - 150mm 21 Nos 1,009.72 21,204
Sizes 200mm - 250mm 14 Nos 1,518.44 21,258
Sizes 300mm and above 7 Nos 2,025.00 14,175
4 Bulk Meters
Sizes 65mm - 80mm 40 Nos 755.36 30,214
Sizes 100mm - 150mm 46 Nos 1,509.25 69,426
Sizes 200mm - 250mm 14 Nos 2,515.25 35,214
Sizes 300mm and above 7 Nos 1,500.00 10,500
5 Pipeline Trench Excavation & Backfilling
a) Excavation for pipeline trenches 64,908 m3 3.60 233,669
b) Backfilling in Layers 58,417 m3 0.99 57,833
c) Sand bed for pipe laying (at least 100 mm thick) 6,000 m3 6.50 39,000
Sub-Total "B"
5,701,494
C Tools, Equipments & Transportation
1 Tools & Equipment 1 Nos. 15,000 15,000
Appendix 1 CAPITAL INVESTMENT PLAN
18
S.No. Description Quantity Unit Rate US$ Total Amount US$
2 Portable Water Quality Monitoring Equipment 1 Nos. 12,000 12,000
3 Leak Detection Equipment 1 Nos. 12,000 12,000
4 Environmental and Social Monitoring Cost 1 Nos. 15,000 15,000
Sub-Total "C"
54,000
Total A, B and C
8,902,431
Table 15: Project Investment for DNI Works in Zone 2
S.No. Description Quantity Unit Rate US$ Total Amount US$
I Water Supply Component
A Civil Works & Distribution Pipe Line
1 Meter / Valve Chambers (Type 1) 125 Nos. 544.68 68,085
2 Meter / Valve Chambers (Type 2) 300 Nos. 570.03 171,008
3 Meter / Valve Chambers (Type 3) 100 Nos. 594.02 59,402
4 Meter / Valve Chambers (Type 4) 25 Nos. 617.97 15,449
5 Meter / Valve Chambers (Type 5) 5 Nos. 667.71 3,339
6 Miscellaneous Structure 1 LS 50,000.00 50,000
7 Reinstatement & Re-sealing of Black topped Road 64,344 Sq.m 25.00 1,608,600
8 Re-instatement of the Gravel Road 42,896 Sq.m 10.00 428,960
9 House / Service Connections 16,740 No 135.28 2,264,695
10 Additional Meter for KWASA Inventory 4,000 Sets 30.00 120,000
Sub-Total "A1"
4,789,537
B 1. Pipeline & Fittings Works
1 Pipes - Supply, Laying, Installation and Testing
a) DI
400 mm 1,500 m 310.30 465,450
350 mm 1,600 m 220.30 352,480
300 mm 2,900 m 147.25 427,025
250 mm 21,800 m 114.25 2,490,650
b) PVC
200 mm 27,700 m 59.25 1,641,225
150 mm 32,700 m 17.60 575,520
100 mm 25,000 m 14.55 363,750
75 mm 25,000 m 11.47 286,750
50 mm 15,000 m 9.47 142,050
2 Pipe Fittings - Supply and installation
a) PVC
Sizes 50mm - 75mm 1,600 Nos 22.02 35,232
Sizes 100mm- 150mm 1,923 Nos 38.04 73,151
Sizes 200 mm 923 Nos 55.08 50,839
b) DI
Sizes 250mm - 300mm 823 Nos 880.08 724,306
Sizes 350mm - 400mm 62 Nos 1,009.16 62,568
3 Valves
Sizes 80mm - 100mm 25 Nos 509.72 12,743
Sizes 100mm - 150mm 33 Nos 1,009.72 33,321
Sizes 200mm - 250mm 22 Nos 1,518.44 33,406
Sizes 300mm and above 3 Nos 2,025.00 6,075
4 Bulk Meters
Sizes 65mm - 80mm 100 Nos 755.36 75,536
Appendix 1 CAPITAL INVESTMENT PLAN
19
S.No. Description Quantity Unit Rate US$ Total Amount US$
Sizes 100mm - 150mm 250 Nos 1,509.25 377,313
Sizes 200mm - 250mm 50 Nos 2,515.25 125,763
Sizes 300mm and above 25 Nos 1,500.00 37,500
5 Pipeline Trench Excavation & Backfilling
a) Excavation for pipeline trenches in Boulder Mixed Soil 82,728 m3 3.60 297,821
b) Backfilling in Layers 74,455 m3 0.99 73,711
c) Sand bed for pipe laying (at least 100 mm thick) 7,650 m3 6.50 49,725
Sub-Total "B"
8,813,907
C Tools, Equipments & Transportation
1 Tools & Equipment 1 Nos. 15,000 15,000
2 Portable Water Quality Monitoring Equipment 1 Nos. 12,000 12,000
3 Leak Detection Equipment 1 Nos. 12,000 12,000
4 Environmental and Social Monitoring Cost 1 Nos. 15,000 15,000
Sub-Total "C"
54,000
Total A, B and C
13,657,444
Table 16: Project Investment for DNI Works in Zone 3
S.No. Description Quantity Unit Rate US$ Total Amount US$
I Water Supply Component
A Civil Works & Distribution Pipe Line
1 Meter / Valve Chambers (Type 1) 65 Nos. 544.68 35,404
2 Meter / Valve Chambers (Type 2) 60 Nos. 570.03 34,202
3 Meter / Valve Chambers (Type 3) 35 Nos. 594.02 20,791
4 Meter / Valve Chambers (Type 4) 35 Nos. 617.97 21,629
5 Meter / Valve Chambers (Type 5) 12 Nos. 667.71 8,012
6 Miscellaneous Structure 1 LS 50,000.00 50,000
7 Reinstatement & Re-sealing of Black topped Road 52,626 Sq.m 25.00 1,315,650
8 Re-instatement of the Gravel Road 35,084 Sq.m 10.00 350,840
9 House / Service Connections 15,507 No 135.28 2,097,785
10 Additional Meter for KWASA Inventory 1,550 Sets 30.00 46,500
Sub-Total "A1"
3,980,812
B 1. Pipeline & Fittings Works
1 Pipes - Supply, Laying, Installation and Testing
a) DI
400 mm 1,200 m 310.30 372,360
350 mm 3,500 m 220.30 771,050
300 mm 1,200 m 147.25 176,700
250 mm 9,900 m 114.25 1,131,075
b) PVC
200 mm 20,000 m 59.25 1,185,000
150 mm 24,500 m 17.60 431,200
100 mm 25,000 m 14.55 363,750
75 mm 25,000 m 11.47 286,750
50 mm 15,000 m 9.47 142,050
2 Pipe Fittings - Supply and installation
a) PVC
Sizes 50mm - 75mm 1,600 Nos 22.02 35,232
Sizes 100mm- 150mm 1,650 Nos 38.04 62,766
Sizes 200 mm 667 Nos 55.08 36,738
b) DI
Appendix 1 CAPITAL INVESTMENT PLAN
20
S.No. Description Quantity Unit Rate US$ Total Amount US$
Sizes 250mm - 300mm 370 Nos 880.08 325,630
Sizes 350mm - 400mm 94 Nos 1,009.16 94,861
3 Valves
Sizes 80mm - 100mm 25 Nos 509.72 12,743
Sizes 100mm - 150mm 25 Nos 1,009.72 25,243
Sizes 200mm - 250mm 10 Nos 1,518.44 15,184
Sizes 300mm and above 6 Nos 2,025.00 12,150
4 Bulk Meters
Sizes 65mm - 80mm 40 Nos 755.36 30,214
Sizes 100mm - 150mm 25 Nos 1,509.25 37,731
Sizes 200mm - 250mm 10 Nos 2,515.25 25,153
Sizes 300mm and above 6 Nos 1,500.00 9,000
5 Pipeline Trench Excavation & Backfilling
a) Excavation for pipeline trenches in Boulder Mixed Soil 67,662 m3 3.60 243,583
b) Backfilling in Layers 60,896 m3 0.99 60,287
c) Sand bed for pipe laying (at least 100 mm thick) 6,250 m3 6.50 40,625
Sub-Total "B"
5,927,076
C Tools, Equipments & Transportation
1 Tools & Equipment 1 Nos. 15,000 15,000
2 Portable Water Quality Monitoring Equipment 1 Nos. 12,000 12,000
3 Leak Detection Equipment 1 Nos. 12,000 12,000
4 Environmental and Social Monitoring Cost 1 Nos. 15,000 15,000
Sub-Total "C"
54,000
Total A, B and C
9,961,888
Table 17: Project Investment for DNI Works in Zone 4
S.No. Description Quantity Unit Rate US$ Total Amount US$
I Water Supply Component
A Civil Works & Distribution Pipe Line
1 Meter / Valve Chambers (Type 1) 40 Nos. 544.68 21,787
2 Meter / Valve Chambers (Type 2) 45 Nos. 570.03 25,651
3 Meter / Valve Chambers (Type 3) 20 Nos. 594.02 11,880
4 Meter / Valve Chambers (Type 4) 25 Nos. 617.97 15,449
5 Meter / Valve Chambers (Type 5) 10 Nos. 667.71 6,677
6 Miscellaneous Structure 1 LS 50,000.00 50,000
7 Reinstatement & Re-sealing of Black topped Road 35,070 Sq.m 25.00 876,750
8 Re-instatement of the Gravel Road 23,380 Sq.m 10.00 233,800
9 House / Service Connections 14,291 No 135.28 1,933,293
10 Additional Meter for KWASA Inventory 1,430 Sets 30.00 42,900
Sub-Total "A1"
3,218,188
B 1. Pipeline & Fittings Works
1 Pipes - Supply, Laying, Installation and Testing
a) DI
350 mm 2,500 m 220.30 550,750
300 mm 1,600 m 147.25 235,600
250 mm 9,500 m 114.25 1,085,375
b) PVC
200 mm 10,700 m 59.25 633,975
150 mm 19,200 m 17.60 337,920
100 mm 15,000 m 14.55 218,250
75 mm 15,000 m 11.47 172,050
Appendix 1 CAPITAL INVESTMENT PLAN
21
S.No. Description Quantity Unit Rate US$ Total Amount US$
50 mm 10,000 m 9.47 94,700
2 Pipe Fittings - Supply and installation
a) PVC
Sizes 50mm - 75mm 1,000 Nos 22.02 22,020
Sizes 100mm- 150mm 1,140 Nos 38.04 43,366
b) DI
Sizes 250mm - 300mm 370 Nos 880.08 325,630
Sizes 350mm - 400mm 50 Nos 1,009.16 50,458
3 Valves
Sizes 80mm - 100mm 15 Nos 509.72 7,646
Sizes 100mm - 150mm 19 Nos 1,009.72 19,185
Sizes 200mm - 250mm 10 Nos 1,518.44 15,184
Sizes 300mm and above 4 Nos 2,025.00 8,100
4 Bulk Meters
Sizes 65mm - 80mm 25 Nos 755.36 18,884
Sizes 100mm - 150mm 19 Nos 1,509.25 28,676
Sizes 200mm - 250mm 10 Nos 2,515.25 25,153
Sizes 300mm and above 5 Nos 1,500.00 7,500
5 Pipeline Trench Excavation & Backfilling
a) Excavation for pipeline trenches in Boulder Mixed Soil 45,090 m3 3.60 162,324
b) Backfilling in Layers 40,581 m3 0.99 40,175
c) Sand bed for pipe laying (at least 100 mm thick) 4,200 m3 6.50 27,300
Sub-Total "B"
4,130,220
C Tools, Equipments & Transportation
1 Tools & Equipment 1 Nos. 15,000 15,000
2 Portable Water Quality Monitoring Equipment 1 Nos. 12,000 12,000
3 Leak Detection Equipment 1 Nos. 12,000 12,000
4 Environmental and Social Monitoring Cost 1 Nos. 15,000 15,000
Sub-Total "C"
54,000
Total A, B and C
7,402,407
Table 18: Project Investment for DNI Works in Zone 5
S.No. Description Quantity Unit Rate US$ Total Amount US$
I Water Supply Component
A Civil Works & Distribution Pipe Line
1 Meter / Valve Chambers (Type 1) 50 Nos. 544.68 27,234
2 Meter / Valve Chambers (Type 2) 50 Nos. 570.03 28,501
3 Meter / Valve Chambers (Type 3) 20 Nos. 594.02 11,880
4 Meter / Valve Chambers (Type 4) 25 Nos. 617.97 15,449
5 Meter / Valve Chambers (Type 5) 5 Nos. 667.71 3,339
6 Miscellaneous Structure 1 LS 50,000.00 50,000
7 Reinstatement & Re-sealing of Black topped Road 30,954 Sq.m 25.00 773,850
8 Re-instatement of the Gravel Road 20,636 Sq.m 10.00 206,360
9 House / Service Connections 9,127 No 135.28 1,234,713
10 Additional Meter for KWASA Inventory 910 Sets 30.00 27,300
Sub-Total "A1"
2,378,627
B 1. Pipeline & Fittings Works
1 Pipes - Supply, Laying, Installation and Testing
a) DI
350 mm 900 m 220.30 198,270
Appendix 1 CAPITAL INVESTMENT PLAN
22
S.No. Description Quantity Unit Rate US$ Total Amount US$
300 mm 1,300 m 147.25 191,425
250 mm 11,700 m 114.25 1,336,725
b) PVC
200 mm 6,400 m 59.25 379,200
150 mm 13,400 m 17.60 235,840
100 mm 15,000 m 14.55 218,250
75 mm 15,000 m 11.47 172,050
50 mm 10,000 m 9.47 94,700
2 Pipe Fittings - Supply and installation
a) PVC
Sizes 50mm - 75mm 1,000 Nos 22.02 22,020
Sizes 100mm- 150mm 947 Nos 38.04 36,024
Sizes 200 mm 213 Nos 55.08 11,732
b) DI
Sizes 150mm - 200mm - Nos 485.08 -
Sizes 250mm - 300mm 433 Nos 880.08 381,075
Sizes 350mm - 400mm 18 Nos 1,009.16 18,165
3 Valves
Sizes 80mm - 100mm 15 Nos 509.72 7,646
Sizes 100mm - 150mm 13 Nos 1,009.72 13,126
Sizes 200mm - 250mm 12 Nos 1,518.44 18,221
Sizes 300mm and above 3 Nos 2,025.00 6,075
4 Bulk Meters
Sizes 65mm - 80mm 25 Nos 755.36 18,884
Sizes 100mm - 150mm 28 Nos 1,509.25 42,259
Sizes 200mm - 250mm 12 Nos 2,515.25 30,183
Sizes 300mm and above 4 Nos 1,500.00 6,000
5 Pipeline Trench Excavation & Backfilling
a) Excavation for pipeline trenches in Boulder Mixed Soil 39,798 m3 3.60 143,273
b) Backfilling in Layers 35,818 m3 0.99 35,460
c) Sand bed for pipe laying (at least 100 mm thick) 3,700 m3 6.50 24,050
Sub-Total "B"
3,640,653
C Tools, Equipments & Transportation
1 Tools & Equipment 1 Nos. 15,000 15,000
2 Portable Water Quality Monitoring Equipment 1 Nos. 12,000 12,000
3 Leak Detection Equipment 1 Nos. 12,000 12,000
4 Environmental and Social Monitoring Cost 1 Nos. 15,000 15,000
Sub-Total "C"
54,000
Total A, B and C
6,073,279
4.3.4 Infrastructure Development and Supporting Activities
Construction of KWASA Office Buildings – KWASA are currently working out of a single three-storey office
building located to the south east of the service area. These offices are not adequate for existing staff and
are remote from many parts of the service area. KWASA have plans to increase the number of offices
within the next 2 years in order to accommodate increasing numbers of staff, these will also be built at
strategic locations within the service area in line with the proposed zoning under the investment plan.
Provision has been made for the construction of a six-storey Headquarters building and three two-storey
zonal offices.
Appendix 1 CAPITAL INVESTMENT PLAN
23
Production Tubewell Rehabilitation – Analysis of the performance of KWASA production tube wells has
indicated a number of problems with the existing pumps and wells. A provision has been included for
rehabilitation of a number of wells, which includes well regeneration (15 no. Wells), Pump and motor
control panel replacement (14 nos.), and Column Shaft Riser Assembly replacement (104.
In addition to the rehabilitation of wells in the Khulna City area a provision has also been made for the
proper regeneration and development of the 20 wells in the Phultala well field.
Deep Aquifer Test Drilling – Water in Khulna is currently abstracted from aquifers down to 300m; the
location and capacity of these aquifers is well documented through the recent IWM modelling studies
undertaken for KWASA. There is also an aquifer at around 600m deep from which it is believed sustainable
supplies can also be developed. A provision is included in the investment plan to undertake test drilling of
this very deep aquifer to ascertain whether future abstraction is viable.
Meter Testing Laboratory Equipment – In the next two years KWASA will be implementing comprehensive
metering of all customer connections. Provision has been made for the purchase of a meter testing rig to
allow checking of meter accuracy and if necessary allow the recalibration of meters after refurbishment. It
has been assumed that the office space for the equipment and staff will be provided at one of the office
sites to be constructed under the project.
Provision of Operational Vehicles – KWASA currently have very few vehicles for operational purposes. A
provision is included in the investment plan for vehicles to support KWASA operations (Head office,
Production and customer service) the vehicles include pickups, motorbikes, water tankers, sludge truck and
cars. The purchase of vehicles will be phased over time and purchased as the need arises.
Groundwater Monitoring System – A key recommendation of the IWM groundwater modelling study was
that KWASA should monitor the condition of the aquifers from which their supply is being abstracted. A
provision of US$ 220,000 has been included for monitoring wells and equipment to allow an effective
monitoring system to be set up.
Business Systems Hardware and Software - As KWASA capacity is developed so business management
systems will be introduced to support the growth of the business. A provision of US$ 750,000 has been
included here to cover expenditure on hardware and software for meter reading and billing, customer
management systems, GIS etc. Details will be specified during future TA support to be provided to KWASA
Water Point Infrastructure within Slum Community and Informal Settlements – A significant proportion of
the population of Khulna live in low income areas or slum settlements. ADB policy is, wherever possible, to
provide individual connections to customers irrespective of economic status. In practice there will be some
areas in which provision of individual connections is not practical – be it from an economic point of view or
from an environmental point of view (available space, drainage, etc.). For this reason the cost of the
provision of communal infrastructure for water delivery has been included in the investment plan.
A provision of US$ 1.7 million has been included on the following basis:
• Extreme poor population of Khulna estimated at 20% - 280,000 people (2017); 39,000 households
• Water point density – 1 point per 15 households
• Total Water Points – 2,700
Appendix 1 CAPITAL INVESTMENT PLAN
24
• Water point cost – US$ 6301/point (including pipework within the settlement area from the bulk
meter)
Consultancy and Technical Assistance – The provision of two types of consultancy is included for under the
Project, they are:
• Engineering design, tendering, and construction supervision of all investment packages; and
• Corporate Management Support to KWASA for institutional and operational capacity building.
4.4 Procurement and Contract Packaging
The Khulna Water Supply Project is a fairly large project involving civil works, pipe works, electro-
mechanical equipment and other related works and goods required for a typically large water supply
improvement project. In this regard procurement of works and goods will dominate the total procurement
plan with some procurement of services primarily for consulting services. The ADB threshold for various
procurement of goods and works is as follows:
Table 19: Procurement of Goods and Works
Method Threshold
International Competitive Bidding (ICB) for Works Over $2,000,000
International Competitive Bidding for Goods Over $1,000,000
National Competitive Bidding (NCB) for Works Below $2,000,000
National Competitive Bidding for Goods Below $1,000,000
Shopping for Works Below $100,000
Shopping for Goods Below $100,000
The following table provides an indicative list of all procurement (goods, works and consulting services)
over the life of the project. Contracts financed by the Borrower and others should also be indicated, with
an appropriate notation in the comments section.
Table 20: Probable List of Contract Packages under the Project
General Description Estimated Value
(cumulative, $1000)
Estimated
Number of
Contracts
Procurement
Method
Domestic
Preference
Applicable
Comments
Equipment
Tools and equipment for
zone offices $67,873 1 Shopping Yes
Water quality monitoring
equipment for zone offices $54,299 1 Shopping Yes
Leak detection equipment
for zone offices $54,299 1 Shopping Yes
1Implementation Guidelines for Urban Water Point/Stand Post – Water Aid, 2007: Estimated Tap Stand Cost – Tk 31,500; TA7385
Estimate for internal pipework (50m) and fittings Tk 12,575.
Appendix 1 CAPITAL INVESTMENT PLAN
25
General Description Estimated Value
(cumulative, $1000)
Estimated
Number of
Contracts
Procurement
Method
Domestic
Preference
Applicable
Comments
Office equipment $111,700 Multiple Shopping Yes
Vehicles 906,787 Multiple ICB/shopping Yes
Works
Construction of clear water
transmission mains $ 26,705,225 1 ICB Yes
Construction of distribution
reservoirs and OHTs $ 21,174,387 1 ICB Yes
Construction of distribution
pipe network $ 39,624,705 1 ICB Yes
Service connections with
meters $1,836,421 1 NCB
Connections for low income
areas $1,710,000 1 NCB
Rehabilitation of deep tube
wells (DTW) $266,143 1 NCB
Development of deep
exploratory well $100,000 1 SSS
Development of monitoring
wells $106,429 1 NCB
Consulting Services
Design and Supervision $5,118,300 1 QCBS, 80:20 FTP
Corporate Management
Support $2,044,700 1 QCBS, 80:20 FTP
Groundwater Monitoring $ 182,294 1 CQS STP
QCBS = quality cost based selection, CQS = consultants qualifications selection, ICB = international competitive bidding, NCB = national competitive bidding, SSS = single source selection, FTP = full technical proposal, STP = simplified technical proposal
4.5 Conclusions and Recommendations
The PPTA Teams recommendation for distribution system improvement works, transmission of clean water
and storage requirements are generally in conformity with the concepts and recommendations of the JICA
Feasibility Study. However, considering the scheduling the proposed investment of JICA and ADB and the
immediate improvement works being carried out with GOB funds by KWASA, a number of issues need to
be considered for immediate development and subsequent long-term investment planned under ADB and
JICA assistance.
• All ground water production wells being planned for implementation by KWASA with GOB funding
has to be done in line with the recommendations of the recently concluded groundwater study and
strategy being developed. In other words, the production wells need to be clustered as well fields
in areas identified with good ground water potential and in the proximity of the proposed
groundwater reservoirs in the various zones. This would entail that the production wells can be
easily connected to the ground reservoirs and supplied to the consumers through their respective
overhead tanks. Sparse and dispersed installation of production wells should be avoided.
Appendix 1 CAPITAL INVESTMENT PLAN
26
• KWASA is thinking along the lines that a consumptive supply pattern be developed for water from
the Phultala Well fields and the proposed small surface water source with treatment plant aimed
to supply water to the northern part of Khulna – primarily area under Zone 1. As considerable
investment has been made to exploit the Phultala Well Fields, KWASA feels that it makes sense to
use the investment in conjunction with the proposed surface water supply for part of the year and
supply water to Zone 1 in the immediate future – prior to commissioning of the proposed system
under JICA and ADB assistance. If this materializes then this needs to be factored in by the Project
during detailed design stage.
• Any distribution network improvement being planned for immediate service improvement by
KWASA has to be done within the overall framework of the distribution network developed for
each of the five distribution zones. Any independent and isolated attempt to design and lay
distribution pipes in these zones shall make these investments redundant and useless later on.
• Location of groundwater reservoirs in Zone 3 and Zone 5 has increased pumping requirements and
length of pumping mains from the ground reservoirs to the overhead tanks. Ideally, the
groundwater reservoirs for these two zones ought to have been located at a more vantage point
within the Zones. However, in the core city area it is always difficult to find appropriate and
adequate land for such structures. Therefore, during the detailed engineering design phase it may
be worthwhile to consider an exercise in optimization by varying the sizes and location of the
ground reservoirs and the overhead tanks.
Appendix 2 CONTRACT PROCURMENT
1
Procurement of Good, Works and Services
General
The Khulna Water Supply Project is a fairly large project involving civil works, pipe works, electro-
mechanical equipment and other related works, goods and services required for a typically large water
supply improvement project. In this regard procurement of works and goods will dominate the total
procurement plan with some procurement of services primarily for consulting services.
All advance contracting and retroactive financing will be undertaken in conformity with ADB’s
Procurement Guidelines (April 2010, as amended from time to time)1 and ADB’s Guidelines on the Use
of Consultants (2010, as amended from time to time).2 Advance contracting and retroactive financing
will be subject to ADB approval. The Government has been advised that approval of advance contracting
and retroactive financing does not commit ADB to finance the Project.
Advance Contracting – Advance contracting will be allowed upon ADB's approval for selection of
consulting services, including (i) request for EOI, (ii) short-listing, (iii) request for proposals, and (iv)
evaluation of proposals; and for procurement of goods and works, including (a) prequalification, (b)
tendering, and (c) bid evaluation.
Retroactive Financing – The maximum amount of eligible expenditures for retroactive financing is $15
million, the equivalent of 20% of the total ADB loan, incurred before the loan effectiveness, but not
more than 12 months before the signing of the loan agreement.
Procurement of goods and works – All procurement of goods and works will be undertaken in
accordance with ADB’s Procurement Guidelines. International competitive bidding (ICB) procedures will
be used for civil works contracts valued at $2.0 million or higher, and goods supply contracts valued at
$1.0 million or higher. Below the thresholds for ICB, National competitive bidding (NCB) procedure may
be used for works contracts and goods supply contracts. Shopping may be used for works and goods
supply contracts worth less than $100,000. ADB and the Government will review the public
procurement laws of the Government to ensure consistency with ADB’s Procurement Guidelines. The
detail procedures of procurement will be found in PAI. The most relevant sections of PAI3 for the Project
are as follows:
• Procedure and flow charts for NCB: PAI 3.04
• Procedure and flow chart for ICB: PAI 3.03
Consultant selection – All consultants, community-based organizations (CBOs) and nongovernment
organizations (NGOs) will be recruited according to ADB’s Guidelines on the Use of Consultants.4
Consulting services are required to (i) support project management, (ii) carry out detailed design and
1 Available at: http://www.adb.org/Documents/Guidelines/Procurement/Guidelines-Procurement.pdf
2 Available at: http://www.adb.org/Documents/Guidelines/Consulting/Guidelines-Consultants.pdf
3 http://www.adb.org/Documents/Manuals/PAI/default.asp
4Checklists for actions required to contract consultants by method available in e-Handbook on Project Implementation
at: http://www.adb.org/documents/handbooks/project-implementation/
Appendix 2 CONTRACT PROCURMENT
2
construction supervision, including monitoring for safeguards compliance, (iii) provide institutional and
capacity development programs. Most consultants will be engaged through international consulting
firms. Consulting firms will be engaged using the quality- and cost-based selection (QCBS) method with a
standard quality/cost ratio of 80/20 and full-technical proposals, or Consultancy Qualification Selection
(CQS) method. The most relevant sections of PAI5 are as follows - Procedure and flow chart: PAI 2.03,
2.05.
Procurement Plan
The ADB threshold for various procurement of goods and works are as follows under the proposed 18-
Month Procurement Plan. Except as the Asian Development Bank (ADB) may otherwise agree, the
following process thresholds shall apply to procurement of goods and works.
Table 1: Procurement of Goods and Works
Method Threshold
International Competitive Bidding (ICB) for Works Over $2,000,000
International Competitive Bidding for Goods Over $1,000,000
National Competitive Bidding (NCB) for Works Below $2,000,000
National Competitive Bidding for Goods Below $1,000,000
Shopping for Works Below $100,000
Shopping for Goods Below $100,000
ICB = international competitive bidding, NCB = national competitive bidding.
ADB Prior or Post Review – Except as ADB may otherwise agree, the following prior or post review
requirements apply to the various procurement and consultant recruitment methods used for the
project.
5 http://www.adb.org/Documents/Manuals/PAI/default.asp
Appendix 2 CONTRACT PROCURMENT
3
Table 2: ADB Review of Contract Packages
Procurement Method Prior or Post Comments
Procurement of Goods and Works
ICB Works and Goods Prior
NCB Works and Goods Prior if over $500,000
NCB Works and Goods Post if below $500,000
Shopping for Works Post
Shopping for Goods Post
Recruitment of Consulting Firms
Quality- and Cost-Based Selection (QCBS) Prior
Quality-Based Selection (QBS) Prior
Other selection methods: Consultants Qualifications
(CQS), Least-Cost Selection (LCS), Fixed Budget
(FBS), and Single Source (SSS)
Prior
Recruitment of Individual Consultants
Individual Consultants Prior
CQS = consultants qualifications selection, FBS = fixed budget selection, ICB = international competitive
bidding, LCS = least-cost selection, NCB = national competitive bidding, QBS = quality-based selection,
QCBS = quality- and cost-based selection, SSS = single source selection.
Goods and Works Contracts Estimated to Cost More Than $1 Million – The following table lists goods
and works contracts for which procurement activity is either ongoing or expected to commence within
the next 18 months.
Appendix 2 CONTRACT PROCURMENT
4
Table 3: Contract Packages (Goods and Works) Over US $ 1 Million
General Description Contract
Value
Procurement
Method
Prequalification
of Bidders (y/n)
Advertisement
Date
(quarter/year)
Comments
Construction of clear
water transmission
mains
$ 26,705,225 ICB No Q3/2012
Construction of
distribution reservoirs
and OHTs
$ 21,174,387 ICB No Q3/2012
Construction of
distribution pipe
network
$ 39,624,705 ICB No Q3/2012
Service connections with
meters $1,836,421 NCB No Q3/2011
Connections for low
income areas $1,710,000 NCB No Q3/2012
Consulting Services Contracts Estimated to Cost More Than $100,000 – The following table lists
consulting services contracts for which procurement activity is either ongoing or expected to commence
within the next 18 months.
Table 4: Consulting Services Contracts >US $100,000
General Description Contract
Value
Recruitment
Method
Advertisement
Date
International or
National
Assignment
Comments
Design and Supervision $5,118,300 QCBS
80:20 Q1 2011 International
Corporate Management
Support $2,044,700
QCBS
80:20 Q1 2011 International
Groundwater Monitoring $ 182,294 CQS Q1 2011 National
Goods and Works Contracts Estimated to Cost Less than $1 Million and Consulting Services Contracts
Less than $100,000 – The following table groups smaller-value goods, works and consulting services
contracts for which procurement activity is either ongoing or expected to commence within the next
18 months.
Appendix 2 CONTRACT PROCURMENT
5
Table 5: Small Contracts – Works, Goods and Services
General
Description
Value of Contracts
Number of
Contracts
Procurement /
Recruitment
Method
Comments
Rehabilitation of deep tube
wells (DTW) $266,143 1 NCB
Development of deep
exploratory well $100,000 1 SSS
With
Geological
Survey of
Bangladesh
Development of monitoring
wells $106,429 1 NCB
Tools and equipment for zone
offices $67,873 1 Shopping
Portable water quality
monitoring equipment for
zone offices
$54,299 1 Shopping
Leak detection equipment for
zone offices $54,299 1 Shopping
Office equipment $111,700 Multiple Shopping
Vehicles $906,787 Multiple ICB/shopping
Indicative List of Packages Required Under the Project – The following table provides an indicative list of
all procurement (goods, works and consulting services) over the life of the project.
Table 6: Indicative List of Contract Packages under the Project
General Description
Estimated Value
(cumulative,
$1000)
Estimated
Number of
Contracts
Procurement
Method
Domestic
Preference
Applicable
Comments
Equipment
Tools and equipment
for zone offices $67,873 1 Shopping Yes
Water quality
monitoring equipment
for zone offices
$54,299 1 Shopping Yes
Leak detection
equipment for zone
offices
$54,299 1 Shopping Yes
Office equipment $111,700 Multiple Shopping Yes
Vehicles 906,787 Multiple ICB/shopping Yes
Appendix 2 CONTRACT PROCURMENT
6
General Description
Estimated Value
(cumulative,
$1000)
Estimated
Number of
Contracts
Procurement
Method
Domestic
Preference
Applicable
Comments
Works
Construction of clear
water transmission
mains
$ 26,705,225 1 ICB Yes
Construction of
distribution reservoirs
and OHTs
$ 21,174,387 1 ICB Yes
Construction of
distribution pipe
network
$ 39,624,705 1 ICB Yes
Service connections
with meters $1,836,421 1 NCB
Connections for low
income areas $1,710,000 1 NCB
Rehabilitation of deep
tube wells (DTW) $266,143 1 NCB
Development of deep
exploratory well $100,000 1 SSS
Development of
monitoring wells $106,429 1 NCB
Consulting Services
Design and Supervision $5,118,300 1 QCBS, 80:20 FTP
Corporate
Management Support $2,044,700 1 QCBS, 80:20 FTP
Groundwater
Monitoring $ 182,294 1 CQS STP
QCBS = quality cost based selection, CQS = consultants qualifications selection, ICB = international
competitive bidding, NCB = national competitive bidding, SSS = single source selection, FTP = full
technical proposal, STP = simplified technical proposal.
Appendix 3 SUBSIDIARY LOAN AGREEMENT
SUBSIDIARY LOAN AGREEMENT (SLA)
BETWEEN
GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH
AND
KHULNA WATER SUPPLY AND SEWERAGE AUTHORITY (KWASA)
FOR
KHULNA WATER SUPPLY PROJECT (KWSP)
Date: …………………………….
Appendix 3 SUBSIDIARY LOAN AGREEMENT
1
SUBSIDIARY LOAN AGREEMENT (SLA)
The Subsidiary Loan Agreement (hereinafter called “SLA”) made this …….. day of ……………….. 2010.
BETWEEN
The Government of the People’s Republic of Bangladesh represent by the Finance Division, Ministry of
Finance (hereafter called “GoB”)
AND
The Khulna Water Supply and Sewerage Authority (hereafter called “KWASA”) originally established
under The Water Supply ….. represented by the Managing Director, having its office at 1062/1Ka, Khan-
A-Sabur Road, Khulna-9100, Bangladesh.
WHEREAS
a) By a Credit Agreement No. ……………. Dated …………………. (hereinafter referred to as the Loan
Agreement) between the Asian Development Bank (hereafter called “ADB”) and the
Government, ADB has agreed to make available to the Government from its special funds
resources a loan in an amount equivalent to Special Drawing Rights
………………………………………………… (SDR ………………..) , (hereinafter called the “Loan”, for the
purposes of implementation of Khulna Water Supply and Sewerage Authority Project
(hereinafter called the Project) on the terms and conditions set forth therein;
b) Under the terms of the Loan Agreement, the Government has agreed to make available to
KWASA part of the proceeds of the Loan under terms and conditions acceptable to ADB;
c) By a Project Agreement entered into by ADB and KWASA on ……………………………… (hereinafter
call the Project Agreement), KWASA has undertaken certain obligations to ADB in connection
with its use of the proceeds of the said Loan and the implementation of the project; and
d) In view of the foregoing, parties hereto have agreed to enter into this Agreement which is the
Subsidiary Loan Agreement referred to in Art. XXXX of the Financing Agreement.
NOW THEREFORE, the parties hereto agree as follows:
ARTICLE – I DEFINITIONS
Section 1.01 Wherever used in this Subsidiary Loan Agreement, unless the context otherwise
requires, the several terms defined in the Loan Agreement (as so defined) and the
Appendix 3 SUBSIDIARY LOAN AGREEMENT
2
Project Agreement shall have the respective meanings therein set-forth and following
additional terms shall have the following meanings.
“Subsidiary Loan” means the loan made available by the Government to KWASA.
ARTICLE –II SUBSIDIARY LOAN
Section 2.01 a) unless otherwise agreed to by and between ADB and the Government, the
Government hereby agrees to lend to KWASA the amount equivalent to SDR XXXXXX
(Equivalent of US$ YYYYYY as per exchange rate, 1 SDR = YYUS$ as on [date]) subject to
and upon the terms and conditions set-forth in the Loan Agreement and this Agreement
for the purpose of carrying out the Project. Unless and until expressly revoked by the
Government at its sole discretion, the Government hereby appoints KWASA as its agent
for the purpose of taking actions or entering into agreements required or permitted
under Sections xxxx Loan Agreement and Sections xxx.
b) The Government shall establish and maintain an imprest account with a commercial
Bank in Khulna in consultation with ADB as per additional instructions: Disbursement of
ADB vide a letter dated xxxxxx etc…….
c) The Government shall open a Subsidiary Loan Account on its books in the name of
KWASA. Each part of the Subsidiary Loan shall be deemed to be withdrawn by KWASA
from such Subsidiary Loan Account on the date given in the official payment advice of
the ADB,
d) KWASA shall bear the foreign exchange risk on the Subsidiary Loan.
Section2.02
The business plan shows that the project will not be viable under the standard terms of
the government for loans to WASAs. Concessionary terms are needed and these are
provided by the Government as follows: a) KWASA shall pay to the Government interest
on the principal of the Subsidiary Loan outstanding from time, at the rate of 2% per
annum. Interest on the Subsidiary Loan shall accrue from the respective value dates as
given in the official payment advice of the ADB and shall be computed on the basis of a
360 day year of twelve 30 day months. Interest during the grace period shall be
capitalized.
b) The Term of the Subsidiary Loan shall be thirty (30) years. KWASA shall repay the
Government the principal amount of the Subsidiary Loan in Twenty Two (22) equal
annual installments payable after 8 years grace period. Payment of interest due shall
also commence after the grace period.
Appendix 3 SUBSIDIARY LOAN AGREEMENT
3
c) Grace period will commence on the date of the first withdrawal of proceeds from the
Subsidiary Loan.
Section 2.03 KWASA may repay to the Government in advance of maturity any part or all of the
principal amount of the Subsidiary Loan with the interest accrued thereon to the date of
such repayment, without premium or penalty, any such repayment shall be applied pro-
rata to the remaining outstanding installments.
Section 2.04 KWASA shall a) maintain or cause to be maintained records and accounts adequate to
reflect, in accordance with consistently maintained sound accounting principles, the
expenditures financed out of the Subsidiary Loan, and b) have such records and
accounts audited for each fiscal year in accordance with appropriate auditing principles.
ARTICLE-III CONDITIONS FOR WITHDRAWAL AND PROCUREMENT PROCEDURES
Section 3.01 The conditions for withdrawal of funds and procurement procedures applicable under
the Loan Agreement apply to the proceeds of the Subsidiary Loan and procurements
utilizing such funds.
ARTICLE-IV EXECUTION OF THE PROJECT
Section 4.01 KWASA shall perform all of its obligations under the Project Agreement and, to the
extent applicable to it, under the Loan Agreement and carry out the project with due
diligence, efficiency and in conformity with sound administration, financial, engineering
and public utility practice.
Section 4.02 KWASA shall not utilize any part of the proceeds of the Subsidiary Loan or any goods
and services financed out of the proceeds of the Subsidiary Loan for any purpose what
so ever other than exclusively for the carrying out of the project.
Section 4.03 KWASA shall duly perform the obligations, which the Government is obliged to cause
KWASA to comply with under the Loan Agreement to the extent applicable to KWASA.
Section 4.04 The Government shall facilitate the availability of the facilities, services, land and other
resources required by KWASA, in addition to the loan proceeds for carrying out of the
Project in accordance with the Project Agreement.
Section 4.05 The Government shall take all action, which shall be necessary on its part to enable
KWAS to perform its obligations under the Project Agreement and Loan Agreement, and
shall not take any action which would impair the performance of such obligations.
Section 4.06 KWASA shall take all action as shall be necessary on its part to enable the Government
to comply with its obligations under the Loan Agreement in respect of the Project.
Section 4.07 KWASA shall not assign any rights or obligations under this Agreement without the prior
written concurrence of the Government and ADB.
Appendix 3 SUBSIDIARY LOAN AGREEMENT
4
ARTICLE-V REMEDIES OFTHE GOVERNMENT
Section 5.01 If any of the following events shall occur and shall continue for the period specified
below, than at any subsequent time during the continuance thereof, the Government,
at its option, may by notice to KWASA declare the principal of the Subsidiary Loan then
outstanding to be due and payable immediately together with the interest and other
charges thereon and upon any such declaration the principal , together with the interest
and other charges thereon, shall become due and payable immediately.
a) A default shall occur in the payment of principal or interest or any other payment
required under the Subsidiary Loan Agreement and such default shall continue for a
period of 30 days;
b) A default shall occur in the performance of any other obligation on the part of
KWASA under this Subsidiary Loan Agreement, and such default shall continue for a
period of sixty days after notice thereof shall have been given by the Government to
KWASA.
ARTICLE-VI EFFECTIVENESS AND TERMINATION
Section 6.01 This Subsidiary Loan Agreement shall come into force and effect on the date on which
the Loan Agreement and Project Agreement shall come into force and effect.
Section 6.02 This Subsidiary Loan Agreement and all obligations of the parties hereunder shall
terminate on the earlier of the following two dates
I. The date on which the Loan Agreement or Project Agreement shall terminate in
accordance with its terms; or
II. A date XX years after the date of this Subsidiary Loan Agreement
ARTICLE-VII GENERAL PROVISIONS AND MISCELLANEOUS
Section 7.01 Any notice or request required or permitted to be given or made under this Subsidiary
Loan Agreement and any Agreement between the parties contemplated by this
Subsidiary Loan Agreement shall be in writing. Such notice or request shall be deemed
to have been duly given or made when it shall be delivered by hand or mail, telegram,
cable, telex or e-mail radiogram to the party to which it is required or permitted to be
given or made at its address hereinafter specified, or at such other such address as such
party shall have designated by notice to the party giving such notice or making such
request. The addresses so specified are as follows:
Managing Director, Khulna Water Supply & Sewerage Authority (KWASA) 1062/1Ka,
Khan-A-Sabur Road, Khulna-9100, Bangladesh.
Appendix 3 SUBSIDIARY LOAN AGREEMENT
5
Secretary, Ministry of Finance, Bangladesh Secretariat, Government of the People’s
Republic of Bangladesh.
Section 7.02 No delay in exercising, or omission to exercise, any right, power or remedy accruing to
either party under this Agreement upon any default, shall impair any such right, power
or remedy or be constructed t be a waiver thereof or an acquiescence in such default;
nor shall action or such party in respect to any default, or ay acquiescence in any
default, affect or impair any right, power of remedy of such party in respect of any other
or subsequent default.
IN WITNESS WHEREOF the parties hereto, acting through their representatives thereunto duly
authorized have caused this Subsidiary Loan Agreement to be signed in their respective names as of the
day and year first above written
For and on behalf of
Khulna Water Supply and Sewerage Authority (KWASA)
For and on behalf of
Government of the People’s Republic of Bangladesh
Appendix 3 SUBSIDIARY LOAN AGREEMENT
6
Annex 1
NEED FOR CONCESSIONARY LOAN TERMS FOR KWASA
A financial model has been prepared for KWASA taking into account all investment and operational
costs, forecast of production and demand and estimates of revenues to assess the viability of the
proposed investments and KWASA in the long term (FY2012-FY 2030). Financial viability is demonstrated
through the financial projections which show sufficiency of cash to cover operational expenses and debt
service, thereby eliminating the need for government subsidy other than explicit exceptions in initial
years.
A critical assumption in the financial forecasts is that within the period 2011 to 2017, KWASA will be able
to implement a much needed Revenue Improvement Action Plan covering required tariff increases,
increase in number of connections, registration of all illegal connections, conversion from billing per
connection to billing per household, metering of all connections and charging annual fees to owners of
private deep tubewells.
Using these revenue assumptions several scenarios were prepared, considering that 30% of the project
cost will be funded by government equity and 70% through a government loan using standard loan
terms for WASA loans (4% interest per year and 20 years repayment inclusive of a 5 year grace period on
interest and principal repayment). One scenario (Low Tariff Option) show that even with the
implementation of a Revenue Improvement Action Plan, KWASA operations will result in continuous
losses and cash deficits if lower tariffs similar to that implemented in Dhaka WASA (e.g. domestic tariffs
at Tk 6/m3 in real prices) and standard loan terms for WASAs are used.
Another scenario (High Tariff option) explored what level of tariffs will allow KWASA to operate viably at
the standard WASA loan terms. The analysis reveals that a domestic tariff of Tk 26.00/m3 in real prices,
needs to be implemented to avoid losses and cash deficits. This tariff is beyond the willingness to pay of
the project beneficiaries and as a result, a compromise scenario was developed which would try to
protect the interests of the stakeholders. This compromise scenario referred to as the base scenario
requires that at the start of the metering program in 2017, an initial tariff in real prices of Tk 13.00/m3
for domestic connections (Tk 19.21/m3 in 2017 prices) and Tk 26.00/m3 for non domestic connections
(Tk 38.41/m3 in 2017 prices) be implemented. These tariffs and other measures in the revenue
improvement program will result in viable operations of KWASA as follows:
• While some years will result in annual cash deficits, KWASA’s cash balances will generally be
sufficient to cover cash operating and maintenance costs and debt service,
• Operating ratio (Operating and Maintenance Expenses before depreciation divided by Operating
Revenues) shows significant improvement from the current 5.17 to .46 in 2017 when the
metered tariffs are implemented. As a result, net income ratio also improves from 2017
onwards with the implementation of annual tariff increases to keep up with inflation and the
growth in connections.
The base scenario however requires the Government of Bangladesh to provide more concessionary
terms on the loan to KWASA as follows: 2% per annum interest rate and 30 year repayment period
inclusive of an 8 year grace period on interest and principal repayment.
Appendix 4 SECTOR ASSESSMENT
1
SECTOR ASSESSMENT
A. Sector Performance, problem, and opportunities
Bangladesh has become increasingly urbanized since independence in 1971. In 2008 an estimated 36
million people, or 25.0% of the total population, lived in the urban areas. Though urbanization is still
relatively low, population growth in the urban areas has been high, at 6.0% yearly, compared with the
total population growth rate of 1.3%. If this growth is sustained, the country’s urban population will
double to 74 million by 2035, or 40.0% of the total population. The contribution of the urban areas to
GDP grew from 26.0% in FY1973 to 42.0% in FY1999. Rapid urbanization has created growing demand
for urban infrastructure and services.
The development of urban infrastructure has not kept pace with rapid urbanization, causing an acute
shortage in urban services. Piped water is available in only one third of pourashavas, and typically for
only 2–4 hours a day. Water quality in many pourashavas is poor, with high iron content or arsenic
contamination.
After more than 20 years of support for infrastructure development in secondary towns, ADB is now
supporting major investments in Dhaka. The Urban Governance and Infrastructure Improvement Project
is significantly improving basic infrastructure and encouraging beneficiaries to participate in pourashava
(municipality) activities. Among the expected outcomes over the long term is full access by the urban
population to safe water by 2015 and to better sanitation by 2010. ADB projects involving public–private
partnerships (PPPs) in urban primary health care have been effective in delivering basic health services,
particularly to the poor. Multidimensional approaches will have to be taken to strengthen urban
institutions, introduce effective regulations, improve municipal finances, and empower local
governments to use information for the public good.
Wide-ranging reforms by the Government in public financial and fiscal management have resulted in
more effective resource allocation, spending prioritization, and budget execution. The Medium-Term
Budgetary Framework (MTBF) introduced in FY2007 covers 53% of budgetary resources. It seeks to
strengthen fiscal management authority and flexibility, and resource management by the line ministries.
The ministries under the MTBF, however, are still incapable of preparing budgets and spending plans.
Fiscal reporting has been more timely since a web-based integrated budget and accounting system was
introduced. Off-budget activities are limited, but weak implementation capacity is to blame for the
shortfall in capital spending. Further, performance-based budgeting, without quantifiable indicators and
benchmarks, is not fully operational, and government accounting and auditing is not up to international
standards.
Public procurement standards have improved since the passage of the Public Procurement Act of 2006
and the Public Procurement Rules of 2008, and the extensive training of procurement staff. The new
laws, which conform to international best practices, will increase the efficiency and transparency of
resource use in this major area of fiduciary risk in Bangladesh. But to realize the full benefits of the
reforms, capacity constraints must be dealt with and political meddling in public tendering removed.
Greater financial delegation and simplified approval must be accompanied by intensive oversight and
Appendix 4 SECTOR ASSESSMENT
2
more effective accounting and auditing procedures. Procurement must be better managed, and
stronger confidentiality mechanisms need to be in place.
The Anti-Corruption Commission (ACC) has been reorganized, the United Nations Convention Against
Corruption (UNCAC) ratified, ACC legislation amended in line with the UNCAC, asset declaration made a
requisite for public servants and lower-court judges, and grievance handling made part of line-agency
procedures.
The new Right to Information Act should result in a more transparent and accountable government. But
the ACC still lacks the capacity to investigate, conduct surveillance, gather evidence, and prosecute
cases, among other capacity building needs of key institutions.
The Bangladesh National Policy for Safe Water Supply and Sanitation 1998 (NPSWSS 1998) recognizes
water as a social as well as an economic good. The different economic benefits that result from water
and sanitation interventions are direct health benefits such as less expenditure by avoiding diseases,
indirect health benefits such as value of avoided loss of work days and other non-health benefits such as
value of time saved to collect water – these are shown in Table 1 below.
Table 1 Economic benefits arising from water supply and sanitation interventions
Benefits Descriptions
Direct economic
benefits of avoiding
diseases
• Less expenditure on treatment of diseases related to water
and sanitation
• Less expenditure on transportation in seeking treatment
• Less time spent due to treatment seeking
Indirect economic
benefits related to
health improvements
• Value of avoided days loss at work or at school
• Value of avoided time loss of parent or caretakers of sick
children
• Value of economic contribution of a saved life
Non-health benefits • Convenience - time saving related to water collection or
accessing sanitation facility
• Labor saving device in households
• Switch away from more expensive water sources
• Property value rise
• Development of small businesses, improvement to fisheries
and other sectors, such as development in tourism
Source: WHO 2006. Human Development Report: Occasional paper on Economic and Health Effects of increasing
coverage of Low Cost Water and Sanitation Interventions.
Appendix 4 SECTOR ASSESSMENT
3
Bangladesh has made good, if uneven, progress in human development and poverty reduction and
seems likely to achieve several Millennium Development Goals. While income poverty has decreased
steadily, it is still high (40% in 2005), income distribution has not improved, and regional disparities
persist. Child health indicators have improved, with fewer neonatal deaths; maternal mortality,
however, remains high in absolute numbers. Clean drinking water and adequate sanitation are more
accessible, but rapid urbanization is a particular challenge, as is the high incidence of arsenic in the
water table.
For Bangladesh the return on US$ 1 invested on water and sanitation intervention for achieving MDGs
was estimated to be US$ 5.4. The return would be US$ 5.6 for achieving universal coverage. In other
words, the benefits from investments in water and sanitation in Bangladesh would be over five-fold. It
may be noted that, when comparing returns on only water supply and only sanitation, the return on
sanitation is higher than water supply.
B. Government’s Sector Strategy
In 2005, the Local Government Division (LGD), Ministry of Local Government, Rural Development and
Cooperatives (LGRD&C) prepared a ten-year Sector Development Programme (SDP 2005) for the Water
Supply and Sanitation (WSS) sector in Bangladesh.
The Policy Support Unit (PSU) under the LGD initiated revision and updating of the SDP 2005. The SDP
will be for a period of 15 years (FY 2011- 25). The objective of the SDP is to provide a framework for
planning, implementing, coordinating and monitoring all activities in the WSS sector. It is envisaged that
all WSS-related national and sectoral policies and strategies and international commitments will be
aligned with the SDP.
As a strategic planning document, the SDP is expected to address emerging and future challenges of the
WSS sector. The SDP provides a road map for development of the sector and a corresponding sector
investment plan and will be implemented under a Sector Development Framework. The SDP has
assessed existing legal instruments, policies and strategies and recommended specific measures to
streamline and address the gaps.
The government has given high priority to develop the WASAs as efficient agencies and has signed a
Partnership Framework Agreement1 for the three WASAs with Development Partners. The objective of
the Agreement is to address reform issues and to improve and extend water, sanitation, drainage and
waste water services. Under the Framework Agreement the strategies are: i) governance improvement
and organizational development, ii) financial management improvement, and iii) service delivery
improvement and expansion. To support the strategies a policy matrix was prepared to agree on the key
activities and reform milestones, milestones to monitor the progress and the investments to be made by
the government and the Development Partners. Many development activities have already started,
1 Partnership Framework Agreement was signed between Bangladesh Government and Development Partners (ADB, DANIDA, Government of Japan, Government of Korea and World Bank) in 2007 for Dhaka and Chittagong WASAs and amended in 2009 to include Khulna WASA.
Appendix 4 SECTOR ASSESSMENT
4
including feasibility and engineering design, studies for capacity building and financial management and
investments in infrastructure rehabilitation and expansion.
At national level the LGD of the Ministry of LGRD&C is responsible for the overall development of the
WSS sector. DPHE and WASAs are under the administrative control of LGD. DPHE is responsible for
implementation of water supply and sanitation projects in the public sector in rural and in urban areas
outside the areas covered by the WASAs. In addition to DPHE, the Local Government Engineering
Department (LGED), also under the LGD, implements water and drainage projects in urban areas as part
of urban infrastructure development projects. The coordination at the national level between the sector
stakeholders like government agencies, NGOs, DPs and private sector is done by the National Forum for
Water Supply and Sanitation (NFWSS) established in the LGD. The Secretary, LGD, is the chairperson of
the NFWSS.
In rural areas, Water Supply and Sanitation Committees (WATSAN Committees) are established in most
of the Local Government Institutions (LGIs) – Upazila Parishads and Union Parishads. The District level
LGI (Zila Parishad) is not presently functional. DPHE, NGOs and other stakeholders coordinate with the
LGIs and WATSAN Committees to implement development projects.
In urban areas, DPHE was originally responsible for WSS services, but gradually Paurashavas
(Municipalities) and City Corporations are getting more involved in planning, implementation and
management of the water systems. WASAs were established in 1963 in Dhaka and Chittagong cities,
being responsible for water supply, sewerage and drainage. Since 1990 Dhaka WASA’s coverage
extended to Narayanganj Town. In 2008 Khulna WASA was created.
The National Strategy for Urban Water Supply and Sanitation will delineate the roles and responsibilities
of LGD, DPHE, LGED, WASAs, City Corporations and Paurashavas, private sector and NGOs for
development of the WSS sector. It will outline a reform and capacity building agenda with milestones.
Some of the elements of the strategy are general, applicable to all urban areas, while others are specific
to WASAs, City Corporations and Paurashavas. These are given below.
General:
1. Take immediate measures to improve the operational and management efficiencies by: i) reducing
the unaccounted for water to at least 25 % by 2015 and 20% by 2020, ii) identifying and taking
actions against illegal connections, leakage and waste control, iii) replacing old and defective
pipelines, and iv)introducing distribution zone management, including installation of bulk meters at
sources and zones
2. Give special attention to address the needs of the low income communities
3. Install water meters to all customers and establish progressive water tariffs that reflect the true
costs of services, while providing safety net for the poor
4. Ensure application of the IEC Guidelines for WASH Promotion by all sector partners
Appendix 4 SECTOR ASSESSMENT
5
5. Carry out R&D to develop appropriate technologies to address the diversified needs
6. Set up monitoring and coordination mechanism at community, local government and central levels
7. Build capacities of sector institutions and communities to protect environment, adapt to climate
change and build resilience for disaster management
8. Support and encourage private sector to take up greater role in future
WASA Specific:
1. Implement the Partnership Framework to strengthen governance and organization structure,
improve financial management capacity and sustain service delivery.
City Corporations and Paurashavas Specific:
1. Develop a database by conducting a baseline survey and regularly update it
2. Establish a dedicated “Fund” for development of WSS services, which could be accessed based on
their performance
3. Support provided by DPHE to the City Corporations and Paurashavas to i) Prepare master plans,
including land use plan, ii) build operational and financial management capacities, iii) install water
meters, iv) repair pipelines, control wastage and leakage and upgrade the water supply systems, v)
develop consumer care and customer relationship, and vi) improve management of sludge from
septic tanks and pit latrines
The benefits of private sector participation in WSS sector include (i) mobilizing private resource to the
sector to meet growing investments needs, (ii) competition because of the entry of more investors, (iii)
increased innovation and efficiency, (iv) lower prices, and (iv) universal coverage.
At present there is no major large scale private sector participation in management of WSS services in
urban areas. In Dhaka, billing and collection contracts awarded by DWASA to private firms for some
areas have met with varied success. DWASA is also exploring the potential viability of management
contracts for the operations and maintenance of District Metered Areas (DMA). In 2005 Faridpur
municipality made a 3-year service contract with a local private operator for billing and collection.
Although the revenue collection improved, the contract was not extended by the municipalities for a
variety of reasons.
Private sector participation models for urban utilities range from simple service contracts and
management contracts to advanced types like Build Operate and Transfer (BOT) and concessions. The
NPSWSS encourages promotion of private sector participation in urban water supply by Build Operate
and Owned (BOO)/BOT. The Public Private Partnership (PPP) (with Foreign Direct Investment, FDI) is
regulated by the Bangladesh Private Sector Infrastructure Guidelines (BPSIG) 2004 where water and
sanitation is one of the eligible sectors. Private Infrastructure Committee (PICOM) does the listing,
processing and monitoring of PPP projects. The government has attached high priority to PPP
Appendix 4 SECTOR ASSESSMENT
6
development and in June 2009 the Finance Division published a Position Paper titled “Invigorating
Investment initiative through Public-Private Partnership”. Studies have shown that there is a good
potential for PPP in the WSS sector in Bangladesh2. However the country investment environment is not
very conducive to advanced types of PPP. The prospect of FDI is low unless investors are supported by
solid guarantees and financial support from international financers. Initially PPPs should be based on
local private sector models (Local PPP Models). With gradual building up of PPP experiences, higher
forms of PPP, including attracting private capital, would be possible. It is also suggested that any PPP
development be implemented as a Tripartite Partnership, or TPP (B
Role and capacity of KWASA, the critical areas for developing capacity, and the commitment to
institutional reform;
WASAs were first established to address the WSS needs of large cities. The intention was to operate the
organizations under different laws because the public law was considered not to have the flexibility to
operate utilities under commercial practices. However the management was by government appointed
staff and functioned under mostly the public rules and regulation and as such the desired commercial
efficiency did not materialized. In order to face the growing needs, WASA Acts was enacted in 1996 to
give more autonomy in its operations by establishing WASA Board consisting of members representing
different stakeholders. Till now only the top management, i.e. the Managing Director and the Deputy
Managing Director are recruited from outside the organizations on commercial terms and conditions.
There is a need for the institutional reforms that have been started to continue in order that the WASA’s
can function as commercial entities.
The present and future major functions of the WASAs are shown below; support will be required in
developing WASA capacity for future functions.
Present Functions Future Function
• Operations of the
WASAs which needs
improvements in
technical and financial
matters.
• Provide WSS services in accordance to the quality and
service standards set by LGD/Water Regulatory
Commission.
• Ensure customer care and services to the disadvantageous
communities.
• Operate the water supply section (and conservancy section)
following sound technical and commercial practices.
• Partner with private sector and NGOs in some service
delivery.
2 Inventory of Possibilities of Involving the Private Sector in Water Supply and Sanitation Services in Bangladesh by
Royal Netherlands Embassy, Dhaka, April 2006
Appendix 4 SECTOR ASSESSMENT
7
Capacity building plan of WASAs and their staff
The Bangladesh Government and some Development Partners (ADB, DANIDA, GOJ, ROK and WB) has
already prepared a Partnership Framework with agreed investment plans and action plans including
improvement of the organizational structure, technical improvement and financial management. A
policy matrix is prepared with timeframe to implement and monitor the agreed actions. In this context it
is suggested to follow the agreed Partnership Framework.
C. ADB’s and JICA’s sector experience and assistance program
ADB is a lead agency in urban development in Bangladesh, actively supporting development initiatives
for both policy reform and capital investment. The first Urban Governance and Infrastructure
Improvement Project (UGIIP-I) introduced performance-based allocation of investment funds as an
incentive for municipal governance reform. ADB has been supporting sector reforms in urban
development such as the development of sector policy and 32 Related national policies include the
National Policy of Arsenic Mitigation (2004), with focus on arsenic contamination of water sources, and
the National Water Management Plan (2004), giving broad directions for water resources management.
The Dhaka Water Supply Sector Development Program supports policy reforms in the urban water and
sanitation sector.
Given the low capacity of the pourashavas and government agencies, effective and sustainable sector
development demands institutional reform and capacity development along with capital investments.
Progress in policy and institutional reforms has been slow. Long-term engagement and substantial
support is needed to materialize and further institutionalize tangible changes in sector governance and
management.
Role of Other Development Partners in the Sector
The major development partners in urban water supply and sanitation are the signatories of the joint-
partnership framework—the World Bank, the Governments of Japan and Korea, and Danida. The World
Bank supports sewerage and drainage in Dhaka, and is considering extending its support in Chittagong.
The Government of Japan is active in the water supply sector of Chittagong. Danida is funding a new
surface-water treatment plant in Dhaka, and will also provide support to develop and update the SDP-
WSSB.
The World Bank supports infrastructure development and the capacity building of pourashavas; DFID,
UNDP, and UNICEF, the improvement of urban slums; JICA, solid waste management in Dhaka; and KfW
and GTZ, urban development as cofinanciers of UGIIP-II.
Appendix 4 SECTOR ASSESSMENT
8
Intended Sector Outcomes and Key Outputs Supported by ADB
The Government’s target is full coverage of the urban population for safe water by 2015, and for
sanitation by 2010. To effectively expand coverage, sector performance and governance must improve.
The Government will implement a series of sector reforms, particularly the financial sustainability and
autonomy of urban water entities.
Sector outcomes for urban development are improved access to municipal infrastructure and services,
and improved municipal governance. The improvements in municipal governance include the
strengthening of the national policy framework and the introduction of actual changes in municipal
governance to ensure the participation of citizens.
Links to Country Partnership Strategy (CPS) Outcomes and Other Sectors and Themes
Improved access to urban water supply and sanitation, and other municipal infrastructure and services,
directly supports one of the CPS outcomes: social development. Better access to and availability of
urban infrastructure will help achieve another CPS outcome - economic growth through local economic
activities. Sector reforms in water utilities and municipalities will contribute to the good-governance
outcome. Improvement of urban infrastructure, in particular sanitation and solid waste management,
will contribute directly to improving the environment. Local governance reform under UGIIP-I and
UGIIP-II will strengthen the inclusion and mainstreaming of the poor and women.
ADB will continue supporting sector reform in Dhaka and the pourashavas as the leading development
partner, and will sustain its support for the expansion of access to safe water and sanitation through
capital investment and sector reform. ADB will consider supporting the augmentation of production
capacity from surface water to avoid over extraction of groundwater, after the ongoing rehabilitation of
distribution networks. It will also explore PPP modalities in the urban water supply sector.
Through capital investment and sector reform, ADB will continue to assist the Government in expanding
access to municipal infrastructure and services in pourashavas, including municipal transport, drainage,
water supply, sanitation, solid waste management, and other urban infrastructure services with
significant impact on urban public and environmental health. ADB will also continue supporting the
Government in strengthening national policy frameworks and local governance reforms. In particular,
ADB will support the finalization and operationalization of the Urban Sector Policy of Bangladesh, and
will expand its support for participatory local governance reform through performance-based allocation
under UGIIP-II.
Further, ADB will develop a new approach to urban development, centered on its potential to lead to
economic growth and employment generation. New interventions may cover larger metropolitan areas
and entail cohesive regional development planning based on a strategic assessment of growth potential.
Considering the high vulnerability of Bangladesh to climate change, ADB will incorporate climate-change
risks into the planning and design of urban development projects, as appropriate. The possibility of
Appendix 4 SECTOR ASSESSMENT
9
adopting and disseminating energy-saving lighting technology and recovering landfill methane emissions
from waste will also be explored in such subsectors
ADB proposed country operations for 2010–2012 are consistent with the CPS strategies and operational
priorities. The proposed operations take into account potential risks identified in the CPS, including
possible slippages in reforms, a slowdown in government revenue collection, which could constrain the
Government’s ability to finance essential public spending on infrastructure and social sector programs,
and the still weak implementation capacity in some agencies. The recurrence of natural disasters is also
a major risk; in line with the CPS, this risk is being addressed through the mainstreaming of climate
change in all Asian Development Bank (ADB)–supported development projects. In 2010–2012, ADB is
expected to continue to play a major role in supporting investment and policy and institutional reforms
in energy and power, transport, education, and integrated urban infrastructure (including water supply
and sanitation). Given the unfolding effects of the global economic slowdown on the Bangladesh
economy, especially on government revenues, ADB in 2009 processed a quick-disbursing public
expenditure support facility to help the Government strengthen social safety nets and sustain its
infrastructure investment program. ADB is also processing a countercyclical support facility to help the
Government implement its countercyclical development program announced in the FY2010 budget.
ADB will continue integrating governance concerns into its sector operations as well as its support for
building local government capacity to plan and deliver services, urban primary health care, and
participatory water management, as well as rural development. In view of the success of earlier
programs, ADB will consider providing further assistance to improve core governance through programs
to combat corruption, improve access to justice, and move ahead with civil service reform, and to
develop the small and medium-sized enterprise sector. Considering the emerging concerns and impact,
ADB will also scale up support for enhancing the Government’s preparedness to cope with the effects of
climate change. To effectively deliver development results, ADB will seek to strengthen cooperation
with the development partners, mobilize greater cofinancing, catalyze private sector and civil society
involvement in development activities, promote public–private partnerships, further improve portfolio
performance, and enhance sub-regional cooperation.
The 2009–2010 biennial performance-based Asian Development Fund (ADF) allocation available for
Bangladesh is $725.28 million or $362.6 (approx.) per year. For 2011 and 2012, $363 million in ADF is
available for each year. The proposed allocations from ordinary capital resources (OCR), including multi-
tranche financing facility (MFF) subprojects, are: $500 million for 2010, $400 million for 2011, and $400
million for 2012. With a debt service ratio of 3.2% and a ratio of external debt to gross domestic product
(GDP) of 25.5% in FY2008, the risk of external debt distress for Bangladesh is low.
ADB’s proposed technical assistance (TA) program averages about $6.2 million per year for 2010–2012.
Additional grant cofinancing will also be sought to augment support for governance improvement,
institutional capacity building, sequencing of key sector reforms, promotion of private sector
participation in infrastructure development, and regional cooperation.
Appendix 5 SOCIAL ASSESSMENT REPORT
1
Acronyms
ADB Asian Development Bank
CBO Community Based Organization
CDC Community Development Center
CDO Community Development Organizer
DWASA Dhaka Water and Sanitation
CWASA Chittagong Water and Sanitation
CPP Consultation Participatory Plan
GO Government Organization
GOB Government of Bangladesh
GAP Gender Action Plan
JICA Japan International cooperation Agency
LIC Low Income Community
LPUPP Local People Urban Partnership Project
KCC Khulna City Corporation
KWASA Khulna Water Supply and Sanitation
PRS Poverty Reduction Strategy
UPPRP Urban Partnership on Poverty Reduction Project
Appendix 5 SOCIAL ASSESSMENT REPORT
2
Appendices
Appendix 1 Poverty Reduction Strategy (PRS)
Appendix 2 Gender Action Plan (GAP)
Appendix 3 Consultation and Participation Plan (CPP)
Appendix 4 Documentation of FGD Proceedings
Appendix 4.1 Attendance of FGD Participants
Appendix 4.2 Questionnaire used in FGD
Appendix 5 List of NGOs
Appendix 6 List of Persons Met
Tables
Table 2.1: Sources of Domestic Water of Khulna Respondents - Overall
Table 2.2: Major Source(s) of Drinking Water
Table 2.3 Household consumption and Cost of water (m3)
Table 2.4 Willingness to connect and pay (HHs with connection)
Table 2.5 Willingness to connect and pay (HHs without connection)
Table 3.1 Land Use, KCC area, 1999
Table 3.2 Population Size and Number of Household, 2001, 2009 & 2010, Khulna City
Table 3.3 Comparative Results on Categories of Households
Table 3.4 Basic information by Categories on Households
Table 3.5 Gender and Education of Adult Household Members
Table 3.6 Sources of Income
Table 3.7 Occupation
Table 3.8 Average Monthly Expenses (Taka)
Table 3.9 Sanitation Facilities
Table 4.1 Gender Issues and Mitigation Measures
Figures
Figure 2.1 Availability of Water
Figure 2.2 Is Water Boiled or Filtered
Figure 2.3 Connected to KWASA Piped Water
Figure 2.4 Availability of Water
Figure 2.5 Perception on Cost of KWASA Piped Water
Figure 2.6 Households Using Public Hand Tube Well
Figure 2.7 Perception on Cost and Availability of Water on Public Tube Well
Figure 2.8 Households Using Private Hand Tube Well
Figure 2.9 Perception on Cost and Availability of Private Tube Well
Appendix 5 SOCIAL ASSESSMENT REPORT
3
1. INTRODUCTION
1.1 Background
There is a growing demand for safe and affordable water in Khulna. While there are various sources
available, these are not sufficient to meet the populations’ demand for water. The current sources are
not sufficient and only 18% of total 1 million populations in the City have access to piped water supply
and the rest resorts to alternative water sources such as river, pond and shallow tube well etc. Shallow
tube well water often contains significant salinity. Recognising the challenges, the Government of
Bangladesh established a separate and independent Khulna Water Supply and Sewerage Authority
(KWASA) in February 2008. KWASA, which is the third WASA in the country established following the
DWASA and CWASA. While the KWASA was established legally, substantial work was required to
develop it into a capable water utility with proper corporate governance, competent human resources,
and effective financial management.
ADB initiated support to the KWASA through SSTA: Supporting the establishment of KWASA (the SSTA),
approved in December 2008. During the SSTA, a unified policy matrix was developed as the road map
for reform and development partner’s support based on which Japan International Cooperation Agency
(JICA) is currently funding a feasibility study in KWASA looking at all aspects of the investment. It is
principally agreed that JICA will fund infrastructure from raw water intake to water treatment plant
outlet and ADB will fund the investment in distribution, storage.
Technical assistance is now being carried out to KWASA through ADB TA 7385 BAN in order to develop
KWASA institutional capacity and project proposal for future investment.
1.2 Project Components
The two major components of the TA are:
Component 1: Preparation of the Institutional Development Plan – This involves the development of a
comprehensive institutional strengthening program for KWASA that will be stated in the form of a 5-
year Business Plan. The key elements of the IDP include:
Recommended organizational structure at different stages of KWASA development:
• Training needs assessment and capacity building plan;
• Operational expenditure plan based on forecast development of KWASA;
• Investment Plan, which also accounts for KWASA investment requirements;
• Annual performance targets based on the period covered in the Business Plan;
• Support to KWASA in the preparation, design and implementation of interim projects funded by
GOB.
To achieve the expected outputs of the various elements of the IDP, details of work plan and strategies
to be pursued are laid out by the Consultant.
Appendix 5 SOCIAL ASSESSMENT REPORT
4
Component 2: Preparation of the Project Proposal – This involves the preparation of a project proposal
for ADB investment in Khulna Water Supply System. Based on the evaluation of the design options
developed by the JICA study team and other consultants recruited under this TA, the project proposal
will include alternative design options if appropriate and may identify additional investment
requirements if relevant.
The proposal will be assessed based on the safeguard measures required by the ADB and the GOB.
Accordingly, this section of the Report discusses the outcome of the social assessments undertaken and
the various mitigating measures proposed to address the social safeguard requirements.
1.3 Project Stakeholders and Beneficiaries
The Project stakeholders and beneficiaries are as follows:
• Financing and donor institutions
• Government sector – KWASA, KCC, Local Government Division of the Ministry of Local
Government Rural Development and Cooperatives, Department of Environment under the
Ministry of Environment and Forest
• Private sector including industrial, commercial/business and institutional groups
• Consumer Public including the poor households in low-income and slum areas of KCC, and
• NGOs, CBOs and women organizations
1.4 ADB’s Guidelines for incorporation of social dimension
The social viability, acceptability and sustainability are the elements that are considered in this study.
This was achieved by following the Asian Development Bank’s guidelines on social dimension which
require appropriate consultation with various stakeholders. The policy of ADB on social dimension which
were utilized in the social analysis of the KWASA project include:
(i) Identification of Project beneficiaries
(ii) Identifying the needs and demands of the beneficiaries
(iii) Assessment of Project Impacts and Benefits
(ii) Addressing poverty issue as a result of project
(iii) Enhancing the role of women
(iv) Preserving and protecting the interest of the minorities
(v) Community participation in development project
1.5 Objectives and Methodology
1.5.1 Objectives of the Social, Poverty and Gender Assessment
This Social and Poverty Assessment (SPA) provides the assessment of risks and mitigation measures and
potential benefits resulting from the planned rehabilitation and upgrading of Khulna Water Supply
Project. Based on the Consultant’s terms of reference (TOR), the following tasks are to be undertaken as
part of this SPA:
• Conduct of focus group discussions to determine access to water and sanitation of consumers
especially the low income groups and liaise with potential partners in Project implementation;
Appendix 5 SOCIAL ASSESSMENT REPORT
5
• Assist GOB establish consultation and participatory processes, identify and consult stakeholders
and incorporate needs in the project or parallel initiatives;
• Propose appropriate water supply facilities for low income areas and study options for low cost
connections for the poor;
• Formulate a Gender Action Plan as part of gender inclusive development; and
• Address other social safeguards requirements of the Project.
1.5.2 Methodology and Scope of the Assessment
Several methods were utilized to accomplish the requirements for social study. These include the
following:
a) Review and Update of Previous Social and Poverty Assessment Documents
A desk study and review of related literatures and documents were done. These included past and
current survey such as:
(i) Consumer Survey Report, 2009
(ii) Consumers Census, 2010
The 2009 Consumer Survey undertook a comprehensive assessment including a review of the
affordability and willingness to pay of 3006 sample households who were connected and not connected
to the KWASA water supply system.
Using the raw data of the Consumer’s Survey, this was further processed to segregate and analyze
various categories of households and determine the characteristics, levels of affordability and willingness
to pay of the low-income households.
Additional information made use of the current Consumer’s Census in Khulna City (2010) covering
around 51,370 households, to validate and compare the results of both studies.
b) Focus Group Discussions
To reinforce the findings of the reviews, focus group discussions were conducted in 12 wards,
participated by over 400 participants, including women from slums and low-income areas. The FGD is a
powerful tool to gather both qualitative and quantitative data on the water situation in the area, and to
determine strategies for ensuring the inclusion of the vulnerable groups in the Project coverage. A
separate report in the FGD exercise is attached as Appendix 4.
(c) Key Informants’ Interview
Key informants included heads of agencies, female headed households, community residents, CDC
leaders, community facilitators and organizers. Data obtained qualitative perceptions on the current
water sources, poverty alleviation programs and current activities undertaken for the community
including women. While KWASA has the primary responsibility for the Project, relevant stakeholders in
the low- income communities including local governments, NGOs and CBOs were also consulted to
identify initiatives which are able to complement the Project. A list of persons met is provided as
Appendix 6.
Appendix 5 SOCIAL ASSESSMENT REPORT
6
c) Assessment of Project Impacts
Using the data from the above activities, a social and poverty assessment (SPA) was prepared which are
discussed in details in the preceding Sections, which include data on sample households, poverty profile,
economic activity, access and constraints to access WSS (availability, affordability), health and other
services. An important element of the profile is the description of the poor, i.e. identification of sub-
groups within the poor (the poorest, the vulnerable poor and the transitional poor) and whether
minority groups, female-headed households, or the slum residents are disproportionately represented.
The output of the SPA formed the basis in drawing out appropriate recommendations and strategies to
enhance the sustainability of access to water by the poor. The recommended strategies and programs
have been drawn accompanying the SPA which include the following documents:
(i) Appendix 1 Poverty Reduction and Social Strategy
(ii) Appendix 2 Gender Action Plan
(iii) Appendix 3 Consultation and Participatory Plan
Appendix 5 SOCIAL ASSESSMENT REPORT
7
2. OVERVIEW OF THE WATER SECTOR
2.1 Coverage and Current Sources of Water Supply in KCC
KWASA water supply system services serves approximately 25% of the population. These include water
users using piped water (18%) public tap (1%), and non-revenue water (6%). On the other hand, hand
pump tube wells supply water to approximately 30.1%, private tube wells for approximately 44% and
pond/river to about 2%. Based on the Consumer Survey result, there is only a very small proportion of
the population using water vendors as their main source of water.
The Consumers Survey showed that water supply sources of surveyed households (3006) include piped
connection (KWASA) 19.4%, hand pump tube well (KWASA) (39.4), street hydrants/public taps (KWASA),
private tube wells, (31.9%) water vendors (0.7%) pond canals and rivers, (1.4%)
Table 2.1: Sources of Domestic Water of Khulna Respondents - Overall
Source Piped
water
Public
tube
well
Private
tube
well
Stand
Pipe
Water
vendor
River,
pond
Other
sources
% Respondents 19.4% 39.4.1% 31.9 0.2 0.7 6.9 1.4 Source: Md. Wahiduzzaman, Water Consumer Survey in Khulna City – TA 7223 BAN: Establishing the Khulna Water
Supply and Sewerage Authority, August 2009.
The Consumers survey also showed that drinking water is sourced by the majority from public hand tube
well (59.1%) and private tube well (38.45). Only 0.2% use the KWASA piped water for drinking.
Table 2.2: Major Source(s) of Drinking Water by Sample Households
Source KWASA
Piped water
Public hand
pump tube well
Private
tube well
Water
vendor
Other
sources
% Respondents 0.2 59.1 38.4 1.1 1.2 Source: Md. Wahiduzzaman, Water Consumer Survey in Khulna City – TA 7223 BAN: Establishing the Khulna Water
Supply and Sewerage Authority, August 2009
2.2 Community Perceptions and Views on Current Water sources
2.2.1 Water Quality and Availability
Households utilize one or more sources of water wherever is accessible. The KWASA hand pump tube
wells are considered as an essential major source of drinking water among the surveyed households.
The public hand pump tube well is generally utilized by the majority (62%) extreme poor households,
63% of the poor households and 55% above poor. Both extreme poor and poor households likewise
utilize private tube wells. Overall, 94% of households affirmed the quality of water is fit for drinking and
is abundant throughout the year. There is no need to boil water for drinking according to 96% of all
households.
Appendix 5 SOCIAL ASSESSMENT REPORT
8
Figure 2.1 Availability of Water
Figure 2.2 Is Water Boiled or Filtered?
2.2.2 Households Connected to Piped Water (913)
Of the 3006 households surveyed, only 913 (30%) households have got connections to piped water. Of
913 households, 64 households (07%) belong to extreme poor, 376 (41%) poor and 52% (473) are above
poor. This finding reveals extreme poor and poor households have very low access to piped water.
Figure 2.3 Connected to KWASA Piped Water
94%94%
4% 2%
94%
5%1%
0
20
40
60
80
100
Abundant Seasonal Scarce
Extreme poor 351
Poor 1343
Above Poor 1312
99% 97% 92%
0
20
40
60
80
100
120
351 1343 1312
Extreme poor Poor Above Poor
No
yes
82
1828
36
0
20
40
60
80
100
351 1343 1312
Extreme poor Poor Above Poor
No
yes
Appendix 5 SOCIAL ASSESSMENT RE
Several reasons were cited for not getting connected to piped water such as distance of the house to the
network (69%) and, (ii) poor quality of water which is viewed by 71% of the respondents. As to the
availability of water, respondents complain that KWA
extreme poor and (77%) of poor households. The FGD results also affirmed that there is constant low
pressure on water thus supply is not sufficient. Overall, views on KWASA piped water is considered as
poor.
Figure
KWASA piped water is cheaper compared to public and private tube wells according to majority of
households, and they are generally willing to get connected to the network.
sharing the cost and spends Tk 69.38 per month for each connection.
as affordable and fair, although some 47% of the poor thinks that piped water is somewhat expensive.
Figure 2.5 Perception on
2.2.3 Households using public hand tube
Of the 3006 households, 1852 (62%) households are using public tube well. Of this, 244 HHs (13%)
comprise of extreme poor and 857HHs (46%) are poor. About 751 HHs (41%) of the above poor also use
this facility. The use of public hand tube wells is
57% above non poor households. Extreme poor households have higher consumption of about 10.8
cubic meters per month, while 8.41 cubic meters per month for the poor and 5.27 cubic meters per
month for the above poor. This is expected as average household among extrem
compared to poor households (5.8).
0
20
40
60
80
100
64
Extreme poor
84%
16%
28%
41%
36
0
10
20
30
40
50
60
Cheap
SOCIAL ASSESSMENT REPORT
Several reasons were cited for not getting connected to piped water such as distance of the house to the
network (69%) and, (ii) poor quality of water which is viewed by 71% of the respondents. As to the
availability of water, respondents complain that KWASA piped water is insufficient according to 84% of
extreme poor and (77%) of poor households. The FGD results also affirmed that there is constant low
pressure on water thus supply is not sufficient. Overall, views on KWASA piped water is considered as
Figure 2.4 Availability of Piped Water
KWASA piped water is cheaper compared to public and private tube wells according to majority of
are generally willing to get connected to the network. An average of 1.9 families is
sharing the cost and spends Tk 69.38 per month for each connection. This is viewed by the respondents
ome 47% of the poor thinks that piped water is somewhat expensive.
Figure 2.5 Perception on Cost of KWASA Piped Water
using public hand tube well (1852 respondents)
Of the 3006 households, 1852 (62%) households are using public tube well. Of this, 244 HHs (13%)
comprise of extreme poor and 857HHs (46%) are poor. About 751 HHs (41%) of the above poor also use
public hand tube wells is popular among 70% of the extreme poor
non poor households. Extreme poor households have higher consumption of about 10.8
cubic meters per month, while 8.41 cubic meters per month for the poor and 5.27 cubic meters per
. This is expected as average household among extreme poor is higher (7.2)
compared to poor households (5.8). Likewise, there is no limit in drawing water from public tube wells
376 473
Extreme poor Poor Above Poor
77%70%
16%23%
30% Insufficient
Sufficient
48%
23%
45%47%
3647%
17%
Fair Expensive
Extreme poor 64
Poor 376
Above Poor 473
9
Several reasons were cited for not getting connected to piped water such as distance of the house to the
network (69%) and, (ii) poor quality of water which is viewed by 71% of the respondents. As to the
SA piped water is insufficient according to 84% of
extreme poor and (77%) of poor households. The FGD results also affirmed that there is constant low
pressure on water thus supply is not sufficient. Overall, views on KWASA piped water is considered as
KWASA piped water is cheaper compared to public and private tube wells according to majority of
An average of 1.9 families is
his is viewed by the respondents
ome 47% of the poor thinks that piped water is somewhat expensive.
Of the 3006 households, 1852 (62%) households are using public tube well. Of this, 244 HHs (13%)
comprise of extreme poor and 857HHs (46%) are poor. About 751 HHs (41%) of the above poor also use
of the extreme poor, 64% poor and
non poor households. Extreme poor households have higher consumption of about 10.8
cubic meters per month, while 8.41 cubic meters per month for the poor and 5.27 cubic meters per
e poor is higher (7.2)
Likewise, there is no limit in drawing water from public tube wells
Appendix 5 SOCIAL ASSESSMENT REPORT
10
Cost of water varies depending on consumption. Overall, the average cost of water from hand pump
tube well is about Tk 8.16 per cubic meter.
Figure 2.6 HHs Using Public Hand Tube Well
As to perception on the quality of water, 90% in all categories claimed that water from public hand
pump tube well is sufficient for their needs. The FGD result cited several advantages of public hand
pump; i.e., accessible, convenient and affordable, particularly for the extreme poor. Distance of water to
households is less than 50 meters and this affords convenience. This implies that more productive tasks
could be accomplished due to savings on time for fetching water from tube wells. Extreme poor
households are greatly benefited in terms of convenience and savings of time as the majority (88%) of
the extreme poor and 67% of the poor fetch water by themselves. On the other hand, 66% of the above
poor can afford to hire domestic helper or contract supplier. Overall perception on the water quality is
good as signified by 88% of the respondents.
Figure 2.7 Perception on Cost and Availability of Water on Public Tube Well
2.2.4 HHs using private hand tube well (1500 respondents)
Water users of private hand tube well comprise 50% of the surveyed 3006 households, Of the 1500
water users, very few 127 (9%) comprise of extreme poor, 648 (43%) poor households. The majority 725
(48%) are above poor.
The majority 96% of the respondents from all categories affirmed that there is sufficient water in private
hand tube wells that meets their demand. Water from private hand tube wells is perceived as cheap by
30%36%
43%
70%64%
57%
01020304050607080
351 1343 1312
Extreme poor Poor Above Poor
No
Yes
89%
4% 7%
86%
14%
76%
16%7%
92%
8%
52%
31%
17%
91%
9%
0
20
40
60
80
100
Extreme poor 244
Poor 857
Above Poor 751
Appendix 5 SOCIAL ASSESSMENT RE
the majority of water users. Views on water
there are private tube wells that have been installed for over 10 years ago, thus, water quality is not so
good, with suspected iron content and saline taste.
Figure 2.8 Households using private hand tube well
According to some households, the cost of installing a private tube well varies which ranges from over
10 thousand Taka to less than 22000 Taka, dependi
Figure 2.9 Perception
2.3 Unit Cost and Water Consumption of HHs
The consumption and cost of water varies by sources. Table 3.3 provides a general picture of the
consumption and cost by various sources.
Piped water
Families connected to piped water generally consume an average of 20.6 m3/month with an average
cost of Tk68/month. This gives a unit cost of 3.4 taka per m/3. Given an
extreme poor indicates about 94.9
average family size of the poor and above poor is 5.84 and 4.59 respectively. Overall, average
consumption on piped water gives an average of 120l/c/day.
0
20
40
60
80
351
Extreme poor
64%
96%
2
93%
2
92%
0
20
40
60
80
100
120
SOCIAL ASSESSMENT REPORT
the majority of water users. Views on water quality is generally good and fair although some claims that
there are private tube wells that have been installed for over 10 years ago, thus, water quality is not so
nt and saline taste.
.8 Households using private hand tube well
households, the cost of installing a private tube well varies which ranges from over
10 thousand Taka to less than 22000 Taka, depending on the brand and depth of installation.
2.9 Perception on cost and availability of private tube well
Consumption of HHs
The consumption and cost of water varies by sources. Table 3.3 provides a general picture of the
consumption and cost by various sources.
Families connected to piped water generally consume an average of 20.6 m3/month with an average
Tk68/month. This gives a unit cost of 3.4 taka per m/3. Given an average family
about 94.9 l/c/d, 117l/c/d for poor and 149 l/c/d for the above poor. The
average family size of the poor and above poor is 5.84 and 4.59 respectively. Overall, average
consumption on piped water gives an average of 120l/c/day.
351 1343 1312
Extreme poor Poor Above Poor
64%52%
45%36%
48%55%
No
Yes
2 5
95%
4 4
96%
4 7 3
97%
Extreme poor 127
Poor 648
Above Poor 725
11
is generally good and fair although some claims that
there are private tube wells that have been installed for over 10 years ago, thus, water quality is not so
households, the cost of installing a private tube well varies which ranges from over
ng on the brand and depth of installation.
The consumption and cost of water varies by sources. Table 3.3 provides a general picture of the
Families connected to piped water generally consume an average of 20.6 m3/month with an average
average family size of 7.23 for
l/c/d, 117l/c/d for poor and 149 l/c/d for the above poor. The
average family size of the poor and above poor is 5.84 and 4.59 respectively. Overall, average
Extreme poor 127
Above Poor 725
Appendix 5 SOCIAL ASSESSMENT REPORT
12
Public tube well
On the other hand households using public tube wells consume lower compared to other sources, with
an average consumption of 7.5m3/month. Given an average size of 7.24 for extreme poor and 5.84 for
poor households give a consumption of 34.5 l/c/day for extreme poor and 42 l/c/day for the poor.
The cost of water of public tube well is generally free, however some households (2%) pay for water
carrier costing them an average of Tk 123/month for 7.5m3 which gives a unit cost of Tk 16.4/m3.
Private tube well
Households using private tube well consume as much as households using piped water with an average
of 19.9 m3 per month, at an average cost of Tk 133 per month. The unit cost of private tube well is Tk
6.7/m3. This amount is paid to owners of private tube well.
Overall, the Consumer’s survey indicated that water consumption from private tube and piped water is
higher than public tube well. In contrast, the cost of private tube well Tk 6.7/m3) is less than public tube
well (Tk 16.4/m3), the latter having higher volume of water. The difference in cost is due to distance of
most public hand pumps from the residence, compelling some households to hire a water carrier. The
difference on the volume of water taken from public water is also less compared to private tube well.
Women generally fetch water and could not carry much, so this explains why the volume of water
consumption from public tube well is less than volume of water consumption from private tube well. In
addition, private tube wells are nearer to most households, facilitating easier access.
Water Vendor
Cost of water vendor is high as expected. Some households consume an average of 2.6m3/month with
an average cost of about Tk194. Unit cost of water from vendors is Tk74.6 per m3.
Majority (90%) of the extreme poor and 87% of poor households, including 58% of the non poor fetch
water by themselves. By doing so, instead of paying for water carrier, households utilizing public tube
well have a guaranteed savings of about Tk123/month which can be used for other needs. Given the
above scenario implies that in order to convince households to connect to piped water would require
intensive social preparation and marketing. Households have very low assessment on the current
KWASA services and this would defer people’s willingness to connect to services. However, if people are
assured of the quality and continuous supply of safe water, they would be willing to invest.
Table 2.3 Household consumption and Cost of water (m3)
Source of Water No. Of
Volume / Month
m3
Cost /Month
Taka
Unit Cost
Taka/m3
Piped 913 20.6 68 3.4
Public Tube well 1852 7.5 123 16.4
Private Tube well 1500 19.9 133 6.7
Appendix 5 SOCIAL ASSESSMENT REPORT
13
Source of Water No. Of
Volume / Month
m3
Cost /Month
Taka
Unit Cost
Taka/m3
Water Vendor 34 2.6 194 74.6
Other Source 6.0 158 26.3
Public Tap 4.7 0 -
Overall findings show that the pattern of consumption between the extreme poor, poor and above poor
varies. Above poor have higher consumption level due to various factors like having a car to wash,
maintaining a garden, flush toilets, laundry which could readily consume over 120 l/c/d. On the other
hand, the poor and extreme poor do not have the luxury that above poor has, thus having less
consumption. Low income people are forced to limit consumption because of the lack of an interior
plumbing system and an ability to dispose of waste water created by uncontrolled consumption.
2.4 Affordability and Willingness to pay
(i) HHs with connections
The consumer’s survey showed that households’ budget for water represents only 1% of the
households’ expenditures. Cost of water paid by extreme poor currently is only Tk126 per month, while
poor households pay Tk118/month and the above poor pay Tk139/month. Applying an average to these
values gives about Tk127/month for a 20m3/month of piped water.
With regards to willingness to pay, the survey showed that a high percentage from the majority of the
extreme poor (87%), poor (96%) of the above poor (97%) are willing to pay about Tk 100/month.
However, since water is viewed as an important commodity of the household, there is still signified
willingness to pay to maintain connection up to Tk200 per month as declared by 70% of the extreme
poor, 71% of the poor and 75% of the above poor. At Tk300 per month, the willingness to pay gradually
drops down by 24% particularly from the extreme poor and poor households. As the water tariff goes
higher, (Tk 400-500) the willingness to pay significantly drops down and the majority would rather
resolve to disconnection.
Appendix 5 SOCIAL ASSESSMENT REPORT
14
Table 2.4 Willingness to connect and pay (HHs with connection)
Taka Variables Sample
Extreme
poor Poor Above Poor
10
0 Disconnect to avoid the bill 8 2 13% 2 3% 4 4%
Stay connected and pay the
bill 179
13 87%
71 97%
95 96%
20
0 Disconnect to avoid the bill 49 3 30% 23 29% 23 25%
Stay connected and pay the
bill 130
7 70%
55 71%
68 75%
30
0
Disconnect to avoid the bill 91
7 54%
42 62%
42 40%
Stay connected and pay the
bill 94
6 46%
26 38%
62 60%
40
0 Disconnect to avoid the bill 120 12 100% 59 76% 49 53%
Stay connected and pay the
bill 63
0 0%
19 24%
44 46%
50
0 Disconnect to avoid the bill 124 12 86% 61 77% 51 59%
Stay connected and pay the
bill 55
2 14%
18 23%
35 41%
913 64 376 473
The overall findings show that households of all categories are generally willing to increase their budget
for water up to an average Tk 200/month. Applying this amount to an average consumption of
20m3/month gives about Tk10/m3. This amount is reasonably affordable to the majority 70% of
households in all categories.
(ii) HHs without connection
Households not presently connected to piped water were asked on their willingness to pay for water at
various range and different amount of connection fee and corresponding water bill. The Consumers
Survey results showed that for a connection fee of TK1,000 and TK 100 water bill; 60% of extreme poor,
59% of the poor and 83% of the above poor are willing to pay the proposed amount. Some 56% of poor
and 60% of the above poor are still willing to pay Tk200. The percentage goes lower as the cost
increases from 300 to 500 Taka.
For a connection fee of 3,000 taka and 100 taka water bill, the willingness to pay among extreme poor
households significantly drops down to 29%, while the poor (61%) and above poor (65%) have
consistently maintained their willingness to connect and pay. As the water bill goes up to Tk300 -Tk500,
the percentage among all categories decreased by almost 40%.
For a connection fee of 5,000 and water bill at 100 Taka, the poor (60%) as well as the above poor (71%)
are still willing to pay. Only 29% of the extreme poor signified their willingness to pay.
Overall, this findings show that for a one time connection fee of Tk 1,000 and Tk100 water bill, there is a
high assurance of willingness to connect and pay from all categories of household. Although water bill
extending up to Tk 200 is still affordable to 56% poor and 60% above poor this amount is no longer
affordable to 70% of extreme poor.
Appendix 5 SOCIAL ASSESSMENT REPORT
15
An important finding is that, households are willing to pay for a one-time connection fee of Tk1,000 and
to some extent increase their budget up to Tk200/month. This is the maximum amount that over 50% of
households could still afford.
It is important to note that while willingness to pay for connection and cost of water is primarily based
on affordability; the strategy to motivate and encourage water users to connect must magnify also on
the adequacy, acceptability of water quality and availability at all times. These are potential factors for
the social marketing strategy of KWASA management.
Table 2. 5 Willingness to connect and pay (HHs without connection)
2.5 Perception on billing
Perception on billing based on meter consumption is considered as fair as supported by 77% of those
already connected and 68% of those with no connections yet. Again this emphasizes that a tariff
structure only works properly when supported by a proper metered service system.
Water consumption basically depends on how households use water. For those using piped water, there
is the tendency of households to excessively use water due to ease, resulting to waste water and
increase on billing. Along with promotion of piped water, there is a need for an education campaign on
proper management of water so that households will not be burdened of paying for excess of or wasted
water.
Connection Value Sample Extreme
Above %
Fee Taka Size Poor % Poor % Poor % Total
1000 100 135 9 60% 44 59% 30 67% 83 61%
200 150 5 31% 37 56% 41 60% 83 55%
300 150 7 28% 24 36% 26 44% 57 38%
400 136 3 13% 13 23% 23 41% 39 29%
500 134 0 0 14 20% 16 35% 30 22%
3000 100 141 5 29% 34 61% 44 65% 83 59%
200 142 4 22% 24 34% 30 57% 58 41%
300 131 1 5% 26 43% 15 31% 42 32%
400 137 4 22% 21 34% 16 28% 41 30%
500 136 1 6% 17 43% 16 29% 34 25%
5000 100 140 4 29% 40 60% 42 71% 86 61%
200 138 5 22% 31 46% 23 44% 59 43%
300 136 2 11% 14 23% 17 30% 33 24%
400 136 5 5 17 25 13 28% 35 26%
500 143 0 0 8 8 13 21% 21 15%
Appendix 5 SOCIAL ASSESSMENT REPORT
16
2.6 Issues on Water
The Consumers survey and the FGD results revealed a number of problems on the current water supply.
These include:
1) Breakdown on water facilities constantly occur as most private hand pumps had been installed
for over 12 years.
2) There is prevalence of water borne diseases such as dysentery and diarrhea which occur about
0.8 times per year.
3) Quality of water is not good which is suspected of high iron content. It is also saline in taste.
4) Insufficiency of water
5) Distance of water from their location
3. SOCIAL, POVERTY AND GENDER PROFILE OF THE STUDY AREA
3.1 Socio-economic Condition of the Project Area
The coverage for this assessment includes the whole area of Khulna City Corporation (KCC) covering 31
wards, and specific information on 3006 sample surveyed households from Consumers Survey 2009 and
Consumer’s Census 2010.
3.1.1 Geography and Climate
Khulna City is the third largest City in Bangladesh after Dhaka and Chittagong. It is part of Khulna District,
which is within Khulna Division located at the southwest portion of Bangladesh with India at its western
boundary. It is 333 km southwest of Dhaka and can be reached through air, road, rail and water
transport system. Its close proximity to Mongla port the second largest port of the country gives it a
distinction as a port city. Its location and linkage with regional towns and growth centers has made it a
strategic hub in the region.
The City originated as a market town with a history going back more than a hundred years. In the early
19th century, Khulna had a close market link with Calcutta with tobacco and sugarcane as the major
goods being traded then. In 1884, it was declared a municipality and in 1885 a railway link was
established therein. In 1961, it became the district headquarter and was promoted to a municipal
corporation in 1984; and, in 1990, it was declared a City Corporation.
The City itself lies on the natural banks of Rupsha and Bhairab rivers, which are characterized by Ganges
tidal floodplains with low relief, crisscrossed by river and water channels and surrounded by tidal
marshes and swamps. Sundarban considered as the largest mangrove forest in the world is located
some 90 kms south west of the city and attracts a large number of visitors who usually pass through
Khulna to get to the site.
The annual average temperature in Khulna is 35.5 OC with a record low of 12.5 OC. The average rainfall is
1,605 mm.
Appendix 5 SOCIAL ASSESSMENT REPORT
17
3.1.2 Administration
The current jurisdiction of Khulna City Corporation (KCC) encompasses the thanas (sub-district within a
city corporation) of Daulatpur, Khalishpur, Sonadanga, and Khulnna Sadar covering approximately 45.7
km2 of land area. The City is subdivided into 31 wards with the mayor and 31 ward commissioners
elected every five years tasked for its civil administration. In addition, 10 women Councilors are elected
at the same time as the Mayor and ward Commissioners. These women Councilors represent the
women affairs and concerns in 3-4 wards each. The law enforcement of Khulna is under the jurisdiction
of Khulna Metropolitan Police.
3.1.3 Land Use
In the late 1990s, around 80% of the total land area of KCC was reported1 as built up with almost two
thirds consisting of residential use (see Table 3.1 below). In 2009, a significant portion of the remaining
land may have been already developed and became more urbanized but land use has not changed
drastically. Khulna City’s urbanization is said to be more in synch with population growth than land use.
Table 3.1 Land Use, KCC area, 1999
Land Use Km2 % of total
Residential 23.5 65
Mixed Use 6.6 18
Industry (incl. railway and shipyards) 3.6 10
Commercial/government/education 1.0 3
Others 1.5 4
Subtotal 36.2 79
Agricultural 9.8 21
TOTAL 46.0 100
3.1.4 Population
Accurate assessment of Khulna City’s current population is constrained by the absence of reliable
information since the 2001 Census. In the JICA Feasibility Study (2010), water demand was based on
population projection2, which considered the various data limitations. In its projection, an intermediate
estimate has been obtained using the national urban growth rate of 2.35% but assumed to be slightly
lower (2.0%) in KCC areas as more growth would have occurred outside of the city’s actual
1 KWASA, Final Report: Feasibility Study for Khulna Water Supply Improvement Project in the People’s Republic of
Bangladesh, Khulna City: May 2010. 2 JICA Study Team, Progress Report (2) – Main Report: Feasibility Study for Khulna Water Supply Improvement
Project in the People’s Republic of Bangladesh, Khulna City: July 2010.
Appendix 5 SOCIAL ASSESSMENT REPORT
18
administrative boundary. With this assumption, the 2009 population of KCC is around 957,000 as
compared to the corrected 2001 figure of 817,000.3 Table 3.1.2 shows the comparative total population
and households in 2001, 2009 and 2010 of KCC. The population by Wards is shown in the Table
overleaf.
Table 3.2: Population Size and Number of Household, 2001, 2009 & 2010, Khulna City
Indicator Year
2001* 2009** 2010**
Population Size 817,000 957,000 976,000
Average Household Size 4.8 4.4 4.4
Number of Households 170,208 217,500 223,900
*Based on 2001 Census
**Based on JICA Consultant’s Estimate
Male to female ratio of Khulna population in 2001 was 53:47; in 2009, it had been estimated to be of
almost equal proportion at 51:49. Based on the 2009 population estimate, the population density in KCC
would be around 21,218 persons per square km (212 pers/m2).
3 Based on the 2001 Census, Khulna City’s population was 770,000; however in the 2001 census there was a
recognized undercounting of the urban population by 6.2%. This has been adjusted in the JICA Team estimate.
Appendix 5 SOCIAL ASSESSMENT REPORT
19
Khulna City Corporation Population Census
Ward 1981 Census 1991 Census 2001 Census 1 24134 24005 20311 2 11327 14809 18815 3 19275 19059 23016 4 10366 11558 14299 5 15918 17828 15314 6 8878 14294 20995 7 12447 11540 14808 8 14158 14698 18545 9 24532 24683 34614 10 31247 29276 18518 11 15503 13819 19398 12 29506 25418 52036 13 21965 14715 19959 14 15033 21334 26444 15 16311 17150 25724 16 23465 22355 35881 17 15231 20122 30352 18 14403 16896 16765 19 16226 19737 26321 20 24870 17374 22539 21 18677 15953 27106 22 14772 12296 21633 23 16554 13995 18332 24 19861 28023 42959 25 18677 15953 27106 26 10925 15893 18087 27 22969 24285 31489 28 11877 13212 22404 29 18316 21269 20431 30 28756 30640 35827 31 17600 23851 32592 Total 577533 597795 770498
Note: Actual Population growth 1981-1991=0.4% pa Actual Population growth 1991-2001=2.6% pa Forecast Population growth 2001-2010=2.6% pa Forecast Population growth 2010-2030=2.6% pa
Appendix 5 SOCIAL ASSESSMENT REPORT
20
3.1.5 Infrastructure and Social Services
Like any other developing cities in Bangladesh, Khulna City’s infrastructure is insufficient to meet the
need of its fast growing population. Although it has adequate transport system that enables it to link
with all the districts of Bangladesh, the approximately 357 km of road network with 16 automated traffic
signal points and 18,750 street lights in the city remains inadequate to ensure the smooth traffic flow.
More than 17,000 rickshaws have been recorded officially and they constitute as the major source of
congestion although traffic jam seldom occurs. Other means of transport include the railway which links
Khulna to northern Bangladesh and Dhaka City, water transport through Barisal Division, and through air
via Jessore airport, about 70 km from Khulna.
The telecommunication requirement, the landline telephone system, cellular phone and internet service
of the population are served by various providers including BTCL, PSTN, Grameen Phone, Teletalk,
Warid, Aktel, City cell, and AKIJ Online Ltd.
The City has 26 ward offices also serving as community centers, 2 public halls, 6 public parks and 1
modernized park for children. Supplying the daily needs of the population are four supermarkets, 21
bazaars, 3 slaughterhouses and 1 meat market.
The health and medical infrastructures include 24 primary health care centers, 35 urban dental clinics,
10 hospitals and 8 nursing home/clinics and maternity ward. There are also 3 crematoria and 8
graveyards in the city.
As for the educational system, Khulna is under the jurisdiction of the Jessore Board. Several educational
institutions provide the requirement of Khulna, which include six integrated general and vocational
schools and a technical school for under-privileged students. Likewise, 8 universities and a medical
college provide the higher educational requirement. In addition, under KCC’s direct supervision are 51
primary schools, 3 secondary schools and 1 university.
3.1.6 Economic Resources and Activities
Khulna’s strategic importance to the economy of the country cannot be overlooked. Its proximity to the
port of Mongla, the second biggest in Bangladesh after Chittagong, has given it recognition as a port City
considering that most goods going to Mongla pass through Khulna. Khulna has the biggest shipyard in
the country, operated by the Bangladesh Navy. About 25% of all port trades handled in Bangladesh
passes through Mongla with the rest through Chittagong. Most (approx. 75%) of the shrimps and other
fishery products exported from Bangladesh are grown in Khulna district. Furthermore, a major
proportion of the jute exported goes through Khulna.
Some of the heavy and medium type industries located in Khulna are the following: Khulna Hardboard
Mills, Bangladesh Oxygen Company, Khulna Oxygen Company, Khulna Textile Mills, Platinum Jubilee
Mills, Star Jute Mills and Dada Match Factory, Khulna Power Station and 17 jute mills. Khulna also has a
number of fish processing centers. In support of its aquaculture industry, there are a number of fertilizer
and feeds plants. Likewise, a cement factory and salt processing industry had been established.
Furthermore as transport is critical to the economy, a number of land and water based transport
companies operate in Khulna.
Appendix 5 SOCIAL ASSESSMENT REPORT
21
The construction of Padma Bridge, which is a road and rail bridge, will provide a direct link to the
country capital, Dhaka, from Khulna. This is expected to facilitate the proposed pipeline project to
increase gas supply to Khulna, improve power supply, develop a multi-modal transport system, revive
the Mongla port and encourage the establishment of free export zone, stimulate the growth of farm and
non-farm sectors as well and encourage development of tourism.
3.1.7 Sanitation and Sewerage
Despite the significant achievement in the improvement of the general health status of the population
of Bangladesh over the years, much remains to be done especially in the urban areas. Water borne
diseases due to lack of proper hygiene and sanitation and potable water remain among the top causes
of morbidity and mortality especially among infants, children and pregnant women. Infection is often
aggravated by congestion due to the high concentration of population in slum and low-income areas.
Most common water related diseases recorded from admission and consultation data in medical
facilities in Khulna include dysentery, cholera and typhoid. The 2009 Consumer Survey reported an
average of 0.85 incidence per person of diarrhea per year. However, actual number of cases appears to
be still under-reported.
KCC’s basic statistics reports that there is approximately 642 kms of drainage in the City. But the low
lying topography and the City’s location next to the riverbanks, which overflow during the regular
occurrence of intensive monsoon, are continuing sources of problem. The City drain is limited through
the existing railway embankment and Khanjahan Ali Road. Khulna’s sewerage system is practically non-
existing. Domestic and industrial liquid wastes are often disposed without treatment.
3.1.8 Slum Areas
While the average population density of the city is already very high, the enormity of the problem in
terms of land use, availability of basic infrastructure and services and the population’s access to them
become more apparent if population distribution and location is viewed at the micro level.
A study of slum4 areas of urban Bangladesh5, which included Khulna City showed that in 2005 the city
had about 520 slum clusters with a population of about 188,442 (37,826 households) or approximately
20% of the city’s population. One of the largest concentrations is along the railway line, which traverses
the city almost through the middle. Another large concentration could be found in the two industrial
zones, Daulatpur and Khalishpur. Still another is in the Rupsha Ghat area near the city center.
Furthermore, some of the largest individual slums are located in Mujgunni and Nurnagar area. Ward 26
for example contains 32 slums; though small in size, the population density within them is really high.
Average person per km2 in the slum area of KCC is 132,988, which is almost 7 times higher than the city
average of 21,218 per km2.
4 Slum is defined as a neighborhood or residential area with a minimum of 10 households or a mess unit with a t least
25 members with four of the ff conditions prevailing: predominantly poor housing, very high population density and room crowding, very poor environmental services, particularly water and sanitation facilities, very low socioeconomic status for the majority of residents, and lack of security of tenure. The definition does not distinguish between slums and communities often referred to as squatter settlements (usually on public lands). 5 Center for Urban Studies (CUS), National Institute of Population Research and Training (NIPORT) and MEASURE
Evaluation. 2006. Slums of Urban Bangladesh: Mapping and Census, 2005. Dhaka, Bangladesh and Chapel Hill, USA.
Appendix 5 SOCIAL ASSESSMENT REPORT
22
As in the rest of the major urban areas in Bangladesh, about 80% of the slum areas in KCC had been in
existence even before the 1990 with 27.3% of the total reported to have been there prior to 1971 (the
year of independence of the country). Almost 80% of the slum clusters (520) in KCC were established on
privately owned land. About 12.5% were on public land while the rest were on land owned by other
organizations. Of the total slum population, 54.3%, 27.1% and 18.6% are located in private, public and
other land category, respectively. Out of the total slum households, 59.4% rented their residence, 17.4%
owned them while 23.1% are rent-free.
3.2 Socio-economic Characteristics of Sample Households
The socio-economic characteristics of households were derived from three sources: (I) Consumers
Survey (2009) with 3006 households as sampling size, (ii) Focus group discussions (FGD) represented
from various sectors (400 persons) of the 12 wards of the KCC, and Consumers Census 2010,
represented by over 50,000 households.
In order to capture the socioeconomic characteristics of households, a segregation of “extreme poor”,
“poor” and “above poor” was done using household expenses from the raw data of 2009 Consumer
Survey. Using expenditures was considered more logical as respondents tend to overestimate or
underestimate their income while expenditures would tend to reflect the real figure as households
magnify on their expenses. While the Consumers Survey did not provide data on savings, earlier work
conducted in Bangladesh in 2005-20066 showed that average savings of households range from 5 to 12%
of the total income. Many programs have been initiated over the years till now by NGOs to promote
households savings, so, it is assumed that savings rates must have increased. Thus, a 17% savings factor
was added to expenditures to represent real income, which is consistent with the national figure.
Give the above data, the formula was applied as shown below:
Estimated average monthly income = Households monthly expenditures x .17 % (savings)
Average annual income = Household expenditures multiplied by .17 X 12 months
Monthly Expenditures
(Consumer’s Survey Raw data)
Average Per Capita
Expenditure/annum
Estimated Average Monthly
Income
(incorporating 0.17 savings)
Below <27500
12,510 21,446 25,091 Extreme Poor
and poor
Each individual profile on expenditures was calculated using the above formula. The overall results show
that:
Extreme poor: HHs expenditures under Tk 13,750 per annum;
Poor: HHs expenditures under Tk 27,500 per annum;
Above poor: HHs expenditures above Tk 27500 per annum.
In terms of income, the classification emerged as shown below which is consistent with the
classification standard used by UPPRP:
6 ADB BAN Secondary Towns Water Supply and Sanitation (2006)
Appendix 5 SOCIAL ASSESSMENT REPORT
23
Extreme poor - income is less than Tk 2,500;
Poor – income is less than TK 5,000
Above poor – income over TK5,000
From the sample size, three major categories of households have emerged as indicated in Table 3.3.
The Consumer’s Survey 2009 represented by 3006 households showed that extreme poor represents
about 12%, while the poor 44.6%, and, above poor 44%.
The results of the Consumers Survey 2010 represented by 51,370 households did not include household
income/expenses, but instead, a classification on type of housing structures to represent certain
categories of households. These are classified as pucca (48.6%); semi pucca (28.9%) and tin sheets
(22.5%), where pucca, are housing structures representing the above poor, semi pucca-poor, and tins
sheets-extreme poor.
Table 3.3 Comparative Results of Categories of Households
Consumer’s Survey 2009 Consumer’s Survey 2010
Sampling Size: 3006 Sampling size: 51,370
Category No. % Category No %
Extreme Poor 351 11.4 Tin sheets (extreme poor) 11,581 22.5
Poor 1343 44.6 Semi Pucca (poor) 14885 28.9
Above poor 1312 44% Pucca (above poor) 24904 48.6
Source: Consumer’s Survey 2009, Modified and segregated by Consultant 2010
For purposes of social analysis, both studies are made as reference where applicable as there are
variables which are not included in 2010 survey but are present in the 2009 survey.
The overall results showed that based on CS 2009, low income households represented by the poor and
extreme poor, comprise 56%, while the CS 2010 showed 51.4%. There is a slight margin of 4.6% higher
from the results of the CS 2009 compared with that of the CS 2010. However, with due consideration on
the wide coverage on sampling size of CS 2010, the results of the latter proved to be more acceptable in
terms of categorization. Thus, this figure (51.4%) must be kept in mind when planning for access of low
income households to safe water, and more focus on consideration of some 22.5% of extreme poor to
achieve the Project’s objectives.
Household Size and Gender
Of the 3006 sampling households (CS 2009), total household members are 16,402 persons. Of this, 2698
(90%) are male and 308 (10%) are female. Average size of extreme poor appears higher (7.23) as
compared to poor (5.84) and above poor (4.59).
Appendix 5 SOCIAL ASSESSMENT REPORT
24
Table 3.4. Basic Information on Households
Consumers survey
Sampling
Extreme poor Poor Above Poor Total
3006
351 1343 1312
3006
Percentage
11.4% 44.6% 43%
100%
HHs Members
2,537 7843 6,022
16,402
Average size/HH
7.23 5.84 4.59
Source: Consumer’s Survey 2009
Education
There are in total 7164 persons (43%) household members who are 18 years and above. Of this, male
outnumbered women which is consistent in all categories of households. Of the “extreme poor”, male
comprise 65% while female earners comprise 35%. On the other hand, among poor households, male
comprise 63% and female 37%.
Education is perhaps the single most important socio-demographic factor influencing occupations. The
latter is certainly a pre-requisite to obtain job placement in the formal sector. Of the total 7164 adult
members, 7062 persons (98%) have reached certain levels of education. Only 5% have not been to
school. Overall, a high percentage (58%) has reached primary (35%) and secondary (23%) education.
Access to education as it reaches higher level is rather limited to the extreme poor. The majority of the
extreme poor (43%) have reached at least primary school and only 29% has reached secondary school.
Only 9% has reached high school. Compared to other categories, extreme poor has higher result in
terms of not having been to school (13%) and has the lowest result also as the education level goes
higher. On the other hand, compared to extreme poor, the “poor” has lower access to primary school
(27%), but higher access to secondary school (39%) and high school (13%)
The survey results also showed that the above poor have higher percentage in reaching college (31%).
Both the extreme poor (5%) and poor (13%) have low access to college education.
Appendix 5 SOCIAL ASSESSMENT REPORT
25
Table 3.5 Gender and Education of Adult Household Members
(1) Male 4407 62% 560 65% 2066 63% 1781 59%
(2) Female 2757 38% 308 35% 1226 37% 1223 41%
7164 100% 868 100% 3292 1.00 3004 1.00
(1) Never been to school 373 5% 103 13% 198 6% 72 2%
(2) Primary school 1635 23% 353 43% 885 27% 397 13%
(3) SSC 2501 35% 235 29% 1248 39% 1018 34%
(4) HSC 1045 15% 71 9% 437 13% 537 18%
(5) Madrassa 43 1% 13 2% 22 1% 8 0%
(6) Vocational and technical school 51 1% 2 0% 22 1% 27 1%
(7) College, University or above 1414 20% 45 5% 429 13% 940 31%
7062 100% 822 100% 3241 100% 2999 100%
5.46 7.23 5.84 4.59
Above Poor
Gender
Highest Educational Attainment
Average No. of Family Members
Total Extreme Poor Poor
Source: Consumer’s Survey 2009, Modified and segregated by Consultant 2010
Overall, the results show that the majority of the respondents have at least reached secondary school.
About 13% of the extreme poor have never been to school and 6% of the “poor.” The overall results
also showed that of the 7062 persons, a significant 20% have obtained college education. Of this, only
5% represents the “extreme poor, 13% of the “poor” and 31% of the “above poor.”
Income
Income must be interpreted with caution in any survey as true income is most often not revealed by
respondents. However to give an indicative pattern on income, the segregation results showed that the
majority 37% earns between Tk 5000-10,000 per month. According to national standard, the poverty
line is set at TK 5,000 (US$71.4) given this figure shows that overall, 41% of the respondents fall below
the poverty line. Assuming an average of TK 5000 per month for poor households and with an average
family size of 5.8 (applicable for poor households) gives an average of TK862 (US $12.3)/capita per
month or TK 28.7(US$.41) per capita per day. This amount is not sufficient to meet the daily (3 meals)
nutritional requirement of poor households.
Table 3.6 Income Profile of Households
Source: Consumer’s Survey 2009, Modified and Segregated by Consultant 2010
Sources of Income
Income (person)
Extreme Poor
Poor
Above Poor
(1) 0-3000 Taka 872 17% 213 37% 388 17% 271 12%
(2) 3000-5000 Taka 1190 24% 244 42% 620 28% 326 15%
(3) 5000-10,000 Taka 1868 37% 114 20% 943 42% 811 36%
(4)10,000-20,000 Taka 907 18% 7 1% 249 11% 651 29%
(5) More than 20,000
Taka 218 4%
4 1%
34 2% 180 8%
Total 5055 100% 582 100% 2234 100% 2239 100%
Appendix 5 SOCIAL ASSESSMENT REPORT
26
There are in total 5055 persons who are family earners. The pattern is again similar with regards to
sources and status of income. The regular income is comparatively lower among the extreme poor (19%)
as compared to the poor (32%) and non poor (36%). The two major sources of income that are common
to all categories are coming from employment by government and private companies which can be
classified as regular income. Apparently, the findings show that the lack of adequate education among
the extreme poor and poor households inhibits them from gaining access to regular jobs in the formal
sector.
Table 3.7 Sources of Income
Source: Consumer’s Survey 2009, Modified and Segregated by Consultant 2010
Occupation
Aside from regular earning jobs, other types of occupation include professional and non professional
jobs. The majority among the extreme poor (30%), poor (33%) and above poor (34%) are housewives
which are considered as an occupation. The FGD affirmed that housewives, aside from doing domestic
work are also engaged in varied forms of income generation activities to supplement family needs, such
as housemaids, tailoring, embroidery, poultry, animal husbandry, batik making, goat raising, and home
based cottage industry.
The next significant form of livelihood is owning a small business as signified by 24% of the extreme
poor, as well as the poor (22%) and non poor (20%). Business is mostly home based such as garment
making, raising animals, small restaurant, etc. A number of persons are unemployed but rather
insignificant in number. A few are retirees and pensioners.
Other common forms of work among the extreme poor and poor households include labourer (12%),
rickshaw puller (2%) farmer (5%). This findings show that the lack of adequate education among the
extreme poor and poor households inhibits them from gaining access to regular jobs in the formal
sector.
Sources of Income (person) Total
Extreme Poor
Poor
Non-Poor
(1) Regular salary from the government / 780 15% 32 5% 299 13% 449 20%
(2) Regular salary from the private
companies 868 17%
81 14%
420 19% 367 16%
(3) Daily / Temporary wages 129 3% 45 8% 74 3% 10 0%
(4) House Rent 517 10% 22 4% 169 8% 326 15%
(5) Others 2761 55% 402 69% 1272 57% 1087 49%
Total 5055 100% 582 100% 2234 100% 2239 100%
Appendix 5 SOCIAL ASSESSMENT REPORT
27
Table 3.8 Occupation
(1) Employee of a state owned enterprise 593 8% 16 5% 237 7% 340 11%
(2) Employee of a private enterprise 174 2% 15 2% 58 2% 101 3%
(3) Government employee (including teachers) 855 12% 83 8% 421 13% 351 12%
(4) Farmer 66 1% 38 4% 25 1% 3 0%
(5) Rural doctor 15 0% 2 1% 7 0% 6 0%
(6) Doctor 20 0% 0 0% 4 0% 16 1%
(7) Own business (not street vendor) 1536 21% 209 24% 729 22% 598 20%
(8) Daily labor 253 4% 66 7% 155 5% 32 1%
(9) Street vendor 8 0% 0 0% 6 0% 2 0%
(10) Rickshaw puller 37 1% 18 2% 16 0% 3 0%
(11) Responsible for house work (house wife) 2384 33% 266 30% 1093 33% 1025 34%
(12) Retired, pensioner 468 7% 30 4% 193 6% 245 8%
(13) Student 9 0% 1 0% 3 0% 5 0%
(14) Unemployed 110 2% 21 2% 53 2% 36 1%
(15) Disabled 49 1% 14 2% 22 1% 13 0%
(16) Overseas workers 125 2% 1 0% 49 1% 75 2%
(17) House Rent 104 1% 10 1% 46 1% 48 2%
(18) Other 358 5% 78 8% 175 5% 105 3%
Total Extreme Poor Poor Above Poor
Source: Consumer’s Survey 2009, Modified and Segregated by Consultant ‘2010
Household Expenses
There is similar pattern among the poor and extreme poor with regards to expenses. Overall, the first
three important priorities are food (32%), followed by repayment of loans, (19%) and education (14%).
The remaining amount is allotted for other items such as clothing (4%), housing (3%), medical bills (5%)
transportation (3%), fuel (3%) and electricity (3%). The survey results showed that household expenses
are higher than household income. Most households result to acquiring debts or loans which explains
why repayment of debts ranks second in terms of expenses.
Water represents only 1% of the expenses of the households in all categories. The monthly budget
appropriated for water by the extreme poor amounts to Tk 126, and Tk118 for the poor and Tk139 for
the above poor.
Appendix 5 SOCIAL ASSESSMENT REPORT
28
Table 3.9 Average Monthly Expenses (Taka)
Total %
Extreme
Poor % Poor %
Above
Poor %
Food 5406 32% 3451 41% 4691 39% 6575 29%
Clothing 657 4% 414 5% 578 5% 758 3%
Housing (rent and maintenance) 536 3% 299 4% 364 3% 672 3%
Medical bills 862 5% 397 5% 553 5% 1219 5%
Water 130 1% 126 1% 118 1% 139 1%
Telephone / Mobile 428 3% 200 2% 320 3% 557 2%
Fuel for cooking (Gas/firewood) 571 3% 380 5% 480 4% 707 3%
Electricity 473 3% 305 4% 393 3% 596 3%
Education 2297 14% 804 10% 1476 12% 3373 15%
Transportation 541 3% 293 3% 387 3% 708 3%
Donation/giving 170 1% 80 1% 105 1% 224 1%
Repayment of loans 3242 19% 1254 15% 1732 15% 4962 22%
Others 1513 9% 423 5% 699 6% 2002 9%
Total Summary 16825 100% 8427 100% 11896 100% 22493 100%
Source: Consumer’s Survey 2009, Modified and segregated by Consultant 2010
Sanitation
Almost all households have sanitation facilities. Among the extreme poor, the facility that is commonly
used is pit latrine (59%) and pit latrine with septic tank (28%). On the other hand the majority of poor
households (44%) and above poor (53%) use private pit latrine but without flush. Very few households
use private flush toilet with septic tank especially among the poor households. This facility is affordable
only among 18% of the above poor.
Table 3.10 Sanitation Facilities
Source: Consumer’s Survey 2009, Modified and segregated by Consultant
Source: Consumer’s Survey 2009, Modified and segregated by Consultant 2010
Sanitation Total % Extreme
Poor
% Poor % Non
Poor
%
(0) Private latrine with septic tank
(without flush)
1387 46% 98 28% 590 44% 699 53%
(1) Private flush toilet with septic
tank
303 10% 6 2% 55 4% 242 18%
(2) Private flush toilet with pit
latrine
21 1% 1 0% 9 1% 11 1%
(3) Private pit latrine 1121 37% 206 59% 579 43% 336 26%
(4) Shared latrine with neighbor 5 0% 3 1% 1 0% 1 0%
(5) Public pit latrine 149 5% 28 8% 100 7% 21 2%
(6) No facilities 1 0% 1 0% 0 0% 0 0%
(7) Other 19 1% 8 2% 9 1% 2 0%
Total 3006 100% 351 100% 1343 100% 1312 100%
Appendix 5 SOCIAL ASSESSMENT REPORT
29
3.3 Dimensions of Poverty
Studies7 indicate that the poverty in Bangladesh has become steady from 1990 with a sustained
economic growth of almost 5% and a rise in real per capita GDP 35%, or twice that average of other low
and middle countries. The population growth rate also dropped down to an annual average of 1.5%
which is viewed as a significant achievement in term of poverty reduction.
Bangladesh also made progress in the following areas such as reduced malnutrition, low birth weight by
20-25% and increased in literacy by 12.5%.
While poverty incidence in Bangladesh is decreasing in absolute terms, the number of urban poor grows
with the rapid urbanization. Employment opportunity draws large migration from rural areas to cities,
resulting in expansion of slums under ineffective urban planning and control. Of the urban population,
45% lives in poverty and 25% is classified as extremely poor (defined by consumption of less than 1,805
kilocalories per day). Poor urban infrastructures such as inadequate drainage, water supply, and
sanitation often expose the population to public and environmental health hazards. Most urban poor
live in slums without access to basic services like water, sanitation, and energy. Most low-income groups
are migrants from rural areas and rely on informal and unsecured income sources. The ready-made
garment industries employ a large proportion of these urban poor and the majority of them are women.
Lack of awareness and measures to control household and industrial waste have become a major cause
of pollution in the urban areas. The city corporations and pourashavas often do not have enough
capacity and proper mechanisms to deal with the needs of the poor and women.
A study of slum8 areas of urban Bangladesh9, which included Khulna City showed that in 2005 the City
had about 520 slum clusters with a population of about 188,442 (37,826 households) or approximately
20% of the City’s population. One of the largest concentrations is along the railway line, which traverses
the City almost through the middle. Another large concentration could be found in the two industrial
zones, Daulatpur and Khalishpur. Still another is in the Rupsha Ghat area near the City center.
Furthermore, some of the largest individual slums are located in Mujgunni and Nurnagar area. Ward 26
for example contains 32 slums; though small in size, the population density within them is really high.
Average person per km2 in the slum area of KCC is 132,988, which is almost 7 times higher than the
City’s average of 21,218 per km2.
3.3.1 Definition and Magnitude of Poor Households
Who are the poor?
Within the study area, there are three categories of households. These are extreme poor representing
11.4%; poor (44.6%) and above poor (44%). The focus of this assessment is on the first two categories.
7 Poverty in Bangladesh: Building on Progress, WB.
8 Slum is defined as a neighborhood or residential area with a minimum of 10 households or a mess unit with a t least
25 members with four of the ff conditions prevailing: predominantly poor housing, very high population density and room crowding, very poor environmental services, particularly water and sanitation facilities, very low socioeconomic status for the majority of residents, and lack of security of tenure. The definition does not distinguish between slums and communities often referred to as squatter settlements (usually on public lands). 9 Center for Urban Studies (CUS), National Institute of Population Research and Training (NIPORT) and MEASURE
Evaluation. 2006. Slums of Urban Bangladesh: Mapping and Census, 2005. Dhaka, Bangladesh and Chapel Hill, USA.
Appendix 5 SOCIAL ASSESSMENT REPORT
30
According to UPPRP, extreme poor are those whose household income is below Tk2500/month while
the poor are below Tk 5,000/month. These figures are consistent with the national standard.
The 2UPHCP and UPPRP have adopted the following indicators to define the extreme poor and poor
households.
a. More than 6 people are dependent on one earning member;
b. Has 3 children of less than 5 years old;
c. Child labour of less than 15 years age works for full day;
d. Age of family’s main income earner is more than 60 years;
e. Female headed households;
f. Have disabled family member;
g. Suffering from prolonged ailment;
h. Have drug addicted member of the family;
i. All family members above 16 years of age are illiterate;
j. Has school age children but not going to school or is a drop out;
k. Lack of access to safe drinking water;
l. Lack of access to sanitary latrine;
m. Live in hut (made of hay, thatch, polythene). Continuously afraid of eviction;
n. Culturally or socially isolated family.
A household will be considered extremely poor if any of 6 out of 14 criteria are met. A household can be
considered as extreme poor even if only one of the following criteria “a”, “d” or “f” is met.
3.3.2 Poverty Indicators
(i) Low status of land and housing
Almost 80% of the slum clusters (520) in KCC were established on privately owned land. About 12.5%
are on public land while the rest are on land owned by other organizations. Of the total slum population,
54.3%, 27.1% and 18.6% are located in private, public and other land category, respectively. Out of the
total slum households, 59.4% rent their residence, 17.4% owned them while 23.1% are rent-free.
(ii) Low access to water and sanitation services
Most of the poor households in slum communities access their water from shared hand tube wells and
hand pumps. Extreme poor and poor households have low access to piped water due to distance. The
FGD report indicated that many households showed interest in connecting to KWASA system as existing
supply is inadequate to meet community (group of households) requirement. Field assessment has
shown that for many poor households in slum communities, individual connection is impractical. The
household’s dwelling is normally a one-room unit used primarily for sleeping by 5-6 members. Cooking,
bathing, toilet and sanitation facilities are communal in a separate corner of the residential compound.
Among the extreme poor (59%) the facility that is commonly used is pit latrine.
Appendix 5 SOCIAL ASSESSMENT REPORT
31
(iii) Low income and expenditures
Income is another indicator of poverty. The Consumers Survey results showed that of the 3006 Overall,
a total of 41% are considered as vulnerable families whose household incomes are below Tk5,
000/month (US$71.4) or below Tk 60,000 per household per annum. Given an average of household size
of 5.46 shows an average of Tk 915 (U$13)/c/month. This amount hardly meets the daily nutritional
requirement of household members. The Consumers Survey also showed that household expenses are
more than income, resulting to borrowing money from neighbors or institutions. As such, there is not
enough money for savings.
(iv) Limited access to education and employment
Access to education among the poor households is limited. Education is certainly a pre-requisite to
obtain employment in the formal sector. A high percentage of the extreme poor have not been to
school. Only 9% has reached high school. On the other hand, poor households have also low access to
higher education. Access to education as it reaches higher level is rather limited to both extreme poor
and poor households. Only 5% of the extreme poor and 13% of the poor have reached college.
3.4. Gender Disparity
The characteristics of the water project determine the specific role gender issues will have. Since the
beginning of the International Water and Supply Decade, this role in the water and sanitation sector has
been delineated and its implications for project elaborated. Gender issues have been placed within the
overall context of community participation. Much has been learned about the importance of
participation and gender issues. While many lessons have been learned, there are still some issues to be
addressed.
(i) Access to education
The Consumers survey showed that there are various aspects of gender bias and discrimination in the
area of education, employment and income, household roles, and decision-making that is visible in the
Project area. There is a higher proportion of female who are illiterate and functionally literate compared
to the male. In terms of educational attainment, the proportion of men and women who have obtained
or finished lower level of education appears to be equal primarily because of the national government’s
interventions; however, at the higher level, the gender disparity becomes apparent again. More males
have attained or finished Bachelor’s degree and/or post-graduate level than the females. In the area of
employment, the situation appears to be no better. While women constitute 48% of the total labor
force, only about 11% of the total is gainfully employed. The average annual income of female-headed
households is Tk46, 621 compared to the male-headed households, which is Tk65, 388. Accordingly, the
proportion of female-headed households (44.1%) who are below the poverty threshold is very much
higher than the male-headed households (27%). On decision-making at the household level, the male is
primarily responsible, except in female-headed households. But even there, the female head has to
often consult with the male adult member of the households on major decision areas.
The findings indicated that status of women in the Project area is generally similar to the status of their
national counterpart. The females appear to have equal chances of being schooled at lower level;
however at higher level, men appear to have the advantage. The proportion of male household
Appendix 5 SOCIAL ASSESSMENT REPORT
32
members, having attained university level is higher than the proportion of female household members.
(ii) Employment
In terms of employment, of the total employable male, 62% is employed while only 58% of the total
employable females are actually employed. However, if one looks at the contribution to total household
income, the proportion of women contribution is almost equal to that of the men. It would appear then
than that while in comparison to the male counterpart the percentage of women who are employed is
low, still an almost equal proportion are gainfully occupied (e.g., operating small business and not
reported as employed) and contribute to the total household income. Per Consumer Survey data,
women headed households included in the survey appear to fare better than their male counterpart.
(iii) Decision Making
Women in the urban households have equal voices in decision-making. However, in the wards and
community administrative system, women’s role appears to be limited by cultural/religious attitude.
Efforts had been undertaken to address such imbalance as social institutions join efforts in improving the
welfare of women. The UPPRP report showed that 90% of women are members of the community
based centers (CBC) and are making major decision in community affairs. A number of NGOs and
development agencies’ undertaking community based project also affirmed that women are often the
chairs and/or manager of the program activities especially if these programs are concerned with health,
sanitation and or microcredit and supplemental livelihood activities. This reflects the reality in the field
that the men are normally busy in formal livelihood and income generation activities for the households
and it is the women who are available to attend to other community related activities.
(iv) Access to basic services
In the predominantly Muslim country, the women’s role in the households and communities is pretty
much defined by religious and cultural/social expectations unlike their counterpart Hindu women.
However, the women in the urban areas as in KCC appear to have better access to social infrastructure
and services than their rural counterpart as the households generally live in more urbanized location
where the infrastructure and services are concentrated. Services such as health institutions are available.
An area where improvement is needed is sanitation especially in the slum areas where roads are dirty
and environmental situation is very poor.
(v) Gender Roles
Water collection and water/sanitation management at the household and community levels are the
traditional roles of women in the country. Because of this gender role and expectation, women had
become more vulnerable to health risks imminent due to hygiene and sanitation resulting from the poor
of quality of water supply and low level of sanitation practices in the households and the community.
They endure the high possibility of getting sick due to higher exposure to contaminated water and other
water borne diseases. Their access to latrines and other sanitation facilities is often inhibited because of
the gender insensitivity to the construction and management of such facilities.
Appendix 5 SOCIAL ASSESSMENT REPORT
33
4. SOCIAL, POVERTY and GENDER IMPACT ASSESSMENT
The social acceptability, viability and sustainability are the core contents which were considered in the
technical assistance of the KWASA Project. The social elements that were examined and assessed to
achieve the social dimension include the following:
(i) Identification and categories project beneficiaries;
(ii) Establishing needs and demand for water facilities;
(iii) Project benefits and impacts;
(iv) Safeguarding and protecting the interest of the vulnerable group;,
(v) Addressing poverty issues;
(vi) Addressing gender issues and concerns, and;
(vii) Enhancing community participation.
4.1 Project Beneficiaries
There are basically two categories of beneficiaries identified in the KWASA project namely; direct and
indirect beneficiaries.
Direct beneficiaries
The direct beneficiaries of the Project are the general population of Khulna City Corporation particularly
those living within the service coverage area of KWASA which include the 31 wards, business
establishments, institutions, government offices, schools and other establishments. The direct
beneficiaries can be further classified into:
a) Extreme poor – these are low income households living below TK 2,500, represented by an
estimated 11.4% of the target consumer population. Majority are living in slum areas. Over
50% of these households cannot afford to pay for connection and water bill exceeding
Tk100.
b) Poor households - those living below the poverty line, with income below Tk 5,000. An
estimated number of 24.6 fall under this category. Over 50% of these households can less
afford to pay for connection of over Tk1, 000 and water bill exceeding Tk100.
c) Above poor- estimated at 44%. These are households whose income are over TK5, 000 and
can afford to pay for water services.
The Consumers Survey 2010 indicates that around 22.5% of KWASA’s potential customers are slum
dwellers, which translate at approximately over 20,000 potential household customers of the total
household’s population targeted (286,545) by 2017. With an average household size of 5.5, the
estimated population to be served is estimated at over 1.6 million.
Indirect beneficiaries are those on the surrounding towns and people passing through the Khulna City;
the migrants, business men, and tourists.
Appendix 5 SOCIAL ASSESSMENT REPORT
34
4.2 Community’s need and demand for safe water
The social assessment showed high acceptability as demand for safe and adequate water has been
established through consultations with various stakeholders. The study shows that many households
indicate interest in connecting to KWASA system as existing supply is inadequate to meet community
requirement.General awareness of the project is high regarding the KWASA water supply improvement
plans. Overall, there is a general need for improved water facilities within the proposed project areas.
The FGD consultations affirmed that the public are hopeful that the water to be provided by KWASA will
be affordable, adequate, and acceptable in terms of quality and available at all times. There was
generally a high indication of the people’s willingness to pay for water system that could provide good
quality of drinking water regularly.
4.3 Social and Poverty Impacts
Positive Impacts
4.3.1 Impact on public health, sanitation and environment
The project is expected to have major beneficial impact on public health, sanitation and environmental
condition of the communities and households. The abundance of water will contribute to the
improvement of the environment as women begin to take care of their surroundings.
The primary benefit will be the health improvement resulting from improved access to affordable safe
water. Women and children are the most common drawers of water and hence have a vested interest
in ensuring that water and sanitation facilities continue to function. It is expected that the availability of
safe and adequate water will change in health behaviour, as women and children pay more attention to
hygiene and sanitation. Water of a better quality which remains uncontaminated helps to decrease
water-related diseases.
However, the health gains so confidently anticipated in water program has yet to be realized. The FGD
results indicated that water borne diseases continuous to be prevalent even in areas where there are
existing tube wells. The problem is that, drinking tube well water will not necessarily protect health
unless there is parallel health education and improvement in environmental sanitation and hygiene
awareness. In water projects, there is ample evidence to show that unless water sanitation and hygiene
education go together, the health impact of improved water facilities may be lost.
This is the challenge that the Project will have to address and women themselves will take the lead to
ensure the proper use of water along with application of proper hygiene if improvement on health
status will be achieved.
4.3.2 Improved community involvement, participation and planning
Participation of stakeholders is essential to reach the objectives of the KWASA Project. Participation
means, readiness of the government (KWASA), private sectors, NGOs, and the target communities to
accept responsibilities. The contribution of each is recognized, utilized and appreciated.
Appendix 5 SOCIAL ASSESSMENT REPORT
35
The FGD consultation affirmed that the areas where the community can participate would be in the
construction of the system (and hence can learn new skills) thereby they can contribute in terms of
labor or receive sweat equity payment. They can help in deciding where the communal water facilities
should be located and be responsible for their maintenance, repair and for the collection of service fees.
It has always been recognized that community participation motivates a sense of ownership and this can
be effectively realized if community assumes responsibility and accountability of the project.
4.3.3 Socioeconomic development
Benefits men and women may receive with improved or new water system can be classified into health
and socio-economic categories. Water sources that are closer to homes and provide an adequate supply
can significantly decrease collection time. This leads to gains in both time and energy. It can significantly
reduce physical strain due to walking and hauling water by long distances. Time and energy gains may
be applied to a variety of activities, including leisure and income generation. An increase in the water
supply can result in increase in agricultural activities (such as home gardening and other productive
activities.
4.3.4 Contribution to Poverty Reduction
4.3.4.1 Improved Access to Safe Water at Affordable Costs
The poverty impact analysis finds that the primary mechanism through which benefits will accrue to the
poor is by the potential savings derived from less medical expenses as access to safe water will result in
less exposure to water borne diseases.
4.3.4.2 Enhanced Economic Impact
Improved health condition and general well being of the household members will hopefully result into
more economic productivity. The proportion of poor, dependent on wage labor is high in the Project
area and increased job opportunities will benefit them and greatly enhanced the wellbeing of people
living in the Project area including women and the poor households. The saved time and energy gains or
surplus water for an improved water supply can be utilized by women for work in agriculture,
horticulture, dairying, and animal raising which is common income generating activities of women. This
will enhance their productive capacities and contribute to family income.
4.3.4.3 Enhanced Employment and Income Generation
Although the Project will not directly engage in income generating and livelihood activities for the poor
beneficiaries, however, as part of the community development activities, the Community Development
Specialist of KWASA will work closely with NGOs involved in micro credit and livelihood enhancement
training and link the members of the WUG to these development organizations. This will also assist the
community and the WUGs in addressing affordability and sustainability concerns to pay for the water bill
regularly if they are able to get involved in income supplementing activities.
Employment opportunities will open for unskilled as well as skilled labor during construction. Specific
measures will be taken by KWASA (the executing agency) to ensure the enforcement of CLS by the
contractor on the work camps/sites. Indirect employment opportunities will arise from better
infrastructure.
Appendix 5 SOCIAL ASSESSMENT REPORT
36
4.3.5 Gender Impacts
The SPA findings did not identify any significant gender related impacts resulting from Project
implementation. Both women and men are more likely to benefit from the inclusion of the slum areas in
KWASA water supply coverage area but women and girls are more likely to have greater benefit in terms
of relief from the constant task of accessing water which are often tedious and unsafe and constitute as
health hazard due to constant exposure to risk of water borne diseases. Thus the increased health
benefit due access to safe water for the household and community will also make it easier for the
women to manage household responsibility since less illness in the family will now require less time for
them as the primary health care takers. During construction, to ensure that women equally share from
employment and income generation opportunities certain measures are proposed as part of the social
development action. Likewise, the Project will enable the women to play a more active role in managing
the community water user organization. Training and capacity building will be provided to women.
Special attention will be paid to the design of messages and the method of communication to ensure
that women receive the intended Project messages. Places frequented by women, household level
messaging and focus groups will be organized to disseminate information about the Project. Benefits
from increased earnings for women resulting from construction employment will be optimized where
KWASA and the concerned ward officials will ensure that:
• Contracts will specify the maximization of use of local labor;
• Workers will be paid the legal wages;
• Child labor will not be used for construction and maintenance activities;
• Employment targets for ethnic people and women will be set;
• No differential wages are paid between men and women for work of equal value; and
• A specific clause is placed in bidding documents that compliance will be strictly monitored
during Project implementation.
Negative Impact
• Resettlement
Land acquisition and resettlement maybe required for some storage reservoirs planned under the JICA
component. Most of the planned facilities are going to be accommodated in government owned lands
and will not requirement relocation but private land acquisition maybe required for some potential
storage sites. Under the JICA component, a Project Resettlement Framework following ADB’s 2009
Safeguard Policy Statement 2 on Involuntary Resettlement and JICA’s guidelines on social considerations
had been prepared earlier. Where land acquisition and resettlement are required, Resettlement Plans
will be prepared accordingly. JICA Specialist will be responsible for the formulation and promulgation of
the RP.
Proposed Measures
The project is designed for minimal or no land acquisition and resettlement. A resettlement framework
has been prepared to guide the development of Resettlement Plans (RP) for various potential reservoir
sites. JICA Specialists will prepare the individual RPs. Most of the sites will not involve land acquisition as
Appendix 5 SOCIAL ASSESSMENT REPORT
37
these are in government properties with no impacts anticipated. But some private lands may have to be
acquired and may involve limited scope of resettlement.
4.4 Key Issues and Mitigation Measures
4.4.1 Affordability and Willingness to pay
An analysis on affordability to piped water to determine peoples’ affordability is highlighted below. The
minimum cost for a house connection can be calculated as follows:
Scenario A Connection Fee (1,000)
Connection fee ( start up investment cost of HHs Tk 1,000
HHs current budget for water ( minimum of 20m3 (6.33/m3 Tk 127
Total budget of water for one year ( 12X Tk 127) Tk 1296
Total investment for 1 year Tk 2423
Scenario B Connection (Tk 300) - Assumption
It is clear that the connection fee in Scenario 1 places a burden on households, particularly for the
extreme poor and poor since it forms 100X higher than the budget appropriated for water for the first
year. On the other hand, if the connection fee is lowered by 70%, assuming that Project pays for
connection, households are able to maintain their current budget for one year with only 30% additional
cost for connection.
The Consumers Survey indicates that about 83% of the population have a monthly income of more than
Tk3, 000/month or 36,000/per annum. These households may be considered as having capacity to pay
for house connection. Under Scenario A, the total costs of a house connection plus water bill during the
first year amounts to TK2, 423. This is about 6.8% of the annual income of Tk36, 000. This amount is
quite high, which is unaffordable, especially for the extreme poor.
On the other hand, under Scenario B, the total costs of a house connection plus water bill during the
first year amounts to TK 1723. This is only about 3.5% of the annual income of Tk36, 000 which has
reduced the cost by over 50%, and therefore more reasonably affordable.
Measures
The project will directly benefit the poor through the provision of bulk supply of water to community
based organization in slum areas adjacent to the KWASA pipe system. Pricing of connection and monthly
Connection fee ( start up investment cost of HHs Tk 300
HHs current budget for water ( minimum of 20m3 (6.33/m3 Tk 127
Total budget of water for one year ( 12X Tk 127) Tk 1296
Total investment for 1 year Tk 1723
Appendix 5 SOCIAL ASSESSMENT REPORT
38
fees would be at subsidized rate to be recovered partially from lower O&M cost to be participated in by
the water user organizations. In identification of beneficiary targets, selection of communal tap site,
pricing and O & M and monitoring activities, the needs and concerns of low-income and vulnerable
groups will be duly considered. One option being explored currently is the inclusion of poor households
in the slum and low income areas in the KWASA service coverage the through a communal water tap
system. One time connection fee can be subsumed and/or a portion (say 30%) to be shouldered by the
group of households and amortized over a certain period. Monthly bill of not more than 100 taka per
household could be charged for a bulk delivery on a guaranteed quantity (and quality) per water user
group. Individual collection of the monthly dues will be the responsibility of WUG.
This strategy will require very intensive social//community development support program in terms of
organization of the households, capacity building for O&M and monitoring activities. The role of the
Community Development Specialist to facilitate the social preparation, marketing and community
mobilization is important requiring full time immersion in the field.
C. Poverty Reduction Strategy
1. Inclusion and Targeting of the Poor Households in Water Supply System Coverage
The main purpose is to increase access of poor households to water services. The identification and
targeting criteria of poor and extreme poor households have been developed following the approach
and methods developed under the ADB financed 2nd Urban Primary Health Care Project (2005)
complemented by the methodology used in the UPPRP where community members themselves identify
the extreme poor and poor households using a set of criteria similar to the ones suggested in the
2UPHCP.
The strategy for inclusion of poor communities can be done in three ways:
1. Community based water management of communal tap stand system
For LIC, the installation of common water points, community stand-posts / hydrants / standpipe should
be metered and responsibility given to a local WUG for operating and maintaining the unit and collecting
monthly tariff. The cost of connection can be shared by WUGs. To ensure that water consumption does
not exceed a certain quantity per month charged at a fixed price, a flow limiting device is an alternative
for low volume or higher rates for metered volumes if he chooses to increase his consumption.
KWASA will provide a communal tap system which can be shared by 10-12 households. A one time
connection fee can be subsumed and/or a portion to be shouldered by the group of households and
amortized over a certain period. Monthly bill of not more than 100 taka per household could be charged
for a fixed volume quantity per water user group say 20m3/month. The Consumer Survey Report (2009)
estimated that approximately 20% of the potential costumers of KWASA are the unconnected poor
households in slum areas and low-income areas. Based on a population growth projection for 2017,
there will be approximately over 20,000 such households requiring connection to safe water. With 10-12
households per communal tap, the Project will need to organize over 2,000 water user associations by
2017 which translates to the same amount of water tap stand.
Appendix 5 SOCIAL ASSESSMENT REPORT
39
2. Fixed rate at subsidized cost for individual connection of poor households
When considering a tariff associated solely with water supply, the Project can establish a tariff structure
which supports the social objectives of income redistribution quite readily. For individual connection,
one way is to provide a fixed rate for a consumption of say 20-25 l/c/d for all consumers at a price less
than the average cost of supply. Individuals connected to water piped could also sell water to
unconnected households, at a fixed rate agreed by water user and seller.
3. Delivery of bulk water in high capacity storage or mobile tanks
For low income areas where connection to the network is not feasible, the provision of bulk supply of
water to community based organization adjacent to the KWASA pipe system will be provided through
mobile water tanks or fixed large volume capacity storage tanks. Similar to the community based
management of communal taps, collection and maintenance will be managed by the WUG and cost of
water will also be charged at fixed rate using per liter container, or a flow limiting device, at subsidized
rate to be recovered partially from lower O&M.
2. Establishment of a Water Fund Provider (WFP)
The establishment of a Water Fund especially for the extreme poor can also be a workable alternative to
provide access of extreme poor who cannot afford connection. The Water Fund Provider (WFP) can also
provide immediate recovery of connection costs to KWASA. A Water Fund can be worked out with an
existing program of NGOs or the UPPRP who are able to provide the initial capital for loan assistance to
low income households, make a certain number of connections per year. The beneficiary consumer is
then billed the full costs of the connection in equal monthly instalment over several months, including
an interest charge of normal commercial rates in addition to the normal bill for consumption. The Water
Fund then becomes self-supporting without burdening the financial resources of the WFP.
Individual collection of the monthly dues will be the responsibility of the WUG to be turned over to the
Water Funder who in turn will turn over the fund to KWASA. The WF can be established as a social fund
under the KWASA structure, or in partnership with NGOs. The UPPRP has the potential to be the WFP as
an initiative to complement their current reduction poverty program, within the KWASA service
coverage. The UPPRP can readily absorb low income households as water fund beneficiaries, at the
same time stream line into their poverty reduction program. This partnership will also enhance and
strengthen coordinated efforts between KWASA and UPPRP as the latter has already established social
structures all over Khulna city, making it easier for facilitating social marketing and mobilization of
KWASA’s Community Development Organizers.
(3) Income Enhancement Measures
Although the Project will not directly engage in income generating and livelihood activities for the poor
beneficiaries, however, as part of the community development activities, the Community Development
Specialist of KWASA will work closely with NGOs involved in micro credit and livelihood enhancement
training and link the members of the WUG to these development organizations. This will also assist the
community and the WUGs in addressing affordability and sustainability concerns to pay for the water
bill regularly if they are able to get involved in income supplementing activities.
Appendix 5 SOCIAL ASSESSMENT REPORT
40
(4) Mobilization of NGO and CBO Support for Poor communities
A number of NGOs are currently operating in the areas which can be tapped to link capacity building
program and income enhancement support for LIHs.
4.6 Social Strategy
The overall objective is to enable the community proximate to the KWASA water supply pipe system,
particularly the vulnerable groups (the poor and women-headed households) to be active in the
development and implementation of the Project. The Poverty Reduction Strategies and Gender Action
Plan will institutionalize and internalize the beneficiary driven approach for sustainable social
development interventions particularly for the women members of households, poor households and
low income households in slum areas.
The Consultation and Participation Plan will be a program to be coordinated by KWASA, implemented by
the Social/Community Development Organizers hired by KWASA under the Customers Relation Unit. An
experienced NGO will be contracted for the first three years of Project implementation to assist the field
staff in the community organization and capacity building activities as well as community level
information campaign on the program.
1. Awareness creation and project dissemination
One of the key elements of the participatory approach is the intensive program of communication
activity to enhance water, hygiene and health awareness. A whole new range of promotional literature
and visual aids will be incorporated in water, sanitation, hygiene and health promotion messages. These
will be produced both for use in training programs and among user groups. Messages on flyers, posters,
and leaflets must be kept simple but with impact: for example: “Conserve Water”. “Water is life”.
Coordinated efforts with mass media and the academe will also be done to include right use of water
and health messages as part of health education in schools. KWASA staff together with the Program
Consultants and the COMREL and the KCC officials/staff at the ward level as well as the WUGs and Ward
Water Supply and Sanitation Committees (WSSC) will work closely with the local officials to undertake a
marketing/information campaign on the new program of KWASA on WSS. The communication materials
and strategy developed by Consultant Specialists will be utilized.
2. Building capacity of WUGs and Committees in low income and slum areas
A major feature of PRS is enabling the WUGs, Committees, and ward officials to plan and implement the
GAP, PRS and CPP in a participatory manner with the participation of beneficiary households, NGOs, and
women. Planning will involve the formulation of strategies to ensure access of services and benefits of
the Project by the poor households in the slum and low-income areas of the wards under the service
coverage of KWASA groups. To sustain affordability and sustainability of services, strategies will be
pursued involving employment provision, capacity building, including improving O&M which eventually
can lead to income generation/income enhancement and monitoring activities especially related to
leakage detection, reporting of illegal connection.
Appendix 5 SOCIAL ASSESSMENT REPORT
41
3. Establishment of Complaints and Response Mechanism at the Ward Level
While KWASA will ultimately be responsible for addressing complaints of customers, the participatory
mechanism will provide a mechanism where at ward CCW level, complaints re service, leakages, billing
and other customer relation matters, could first be heard and possibly mitigated. If the CCW is unable to
provide a solution, the complaint would then be referred to the KWASA zonal team (SocDev/ComDev
Specialist) for appropriate action.
4. Participation in Operation, Maintenance and Monitoring Activities
The WUG will be responsible for collection of monthly dues from individual members and remittance of
payment of the monthly bill to KWASA. Pipe leakages, damage to the communal tap as well as illegal
connection will be monitored at community level and reported to KWASA through an established
system. The WUG elected officers will be responsible for record keeping, updating and maintaining the
books of account for regular reporting to the members. The Project Community Development Specialist
will provide the appropriate trainings to the WUG officials.
5. Develop and establish partnership with other support groups
The water project is closely linked to other sectors such as environmental, health, poverty reduction and
to goals for sustainable urban/rural development. The use of NGOs as partner in water sector is crucial
particularly in addressing gender concerns and poverty reduction. Because of the special character that
places them somewhere in between the public and the private sectors, NGO partners are of great
importance in helping to reach the twin goals of universal water and sanitation coverage towards health
for all, and at the same time addressing poverty reduction program that will contribute to the
sustainability of the project. A list of NGOs has been identified.
4.6. Gender Issues and Concerns:
Adverse impacts and risks from Project related activities faced by women are deemed not very
significant; nonetheless, during Project implementation if there are unforeseen risks identified, proper
measures will be undertaken for their mitigation.
Some of the issues that are common in water projects affecting women are spelled out in Table. 4.1,
along with mitigation measures.
Appendix 5 SOCIAL ASSESSMENT REPORT
42
Table 4.1 Gender Issues and Mitigation
Issues Mitigation Measures
1. Certain categories of women are excluded
from access to water and participation, such as
minority group, women headed households
and very poor households.
Targeting and issuance of ID to particularly vulnerable
women such as minorities and women headed
households, to ensure access to water services.
2. Special needs of women are not met such as;
location, design of facilities, operating hours;
bathing provision, laundry.
Ensure accessibility by consulting with women to agree
on location, design, operation hours, bathing provision
and laundry area.
3. Involvement of women has been limited to
domestic work, physical labor of hauling water,
passive audience for health education;
separate women’s project
Involve women in the operations in maintenance,
collection, promotion of health messages.
Use women as resource persons on health education,
awareness creation
Allow women to assume leadership roles.
Encourage men to support community activities of
women and efforts of women to promote hygiene and
sanitation at home.
4. Workload has been increased by lack of
assistance in water collection and voluntary
labor for community related initiatives.
Community seminar on gender awareness must be
initiated to raise level of awareness of men on the
multi-roles of women in the home.
Men should be encouraged to participate in seminars
and support women, share in household’s tasks as well
as in equal sharing of resources.
5. Loss of productive activities due to time spent
on water collection and other domestic
concerns
Linkages with NGOs to enhance productive capacity of
women, to engage in income generating activities
6. Loss of access to improved water facility due to
distance and cost of water
Participation of women in the selection site that will
proximate water facilities to women.
4.6.1 Gender Action Plan
A Gender Action Plan has been drawn to address gender issues related to water project. Details of the
GAP are attached as Appendix 2.
The objectives of the GAP are as follows:
(i) Increase participation of women in identification of location site for the tap stands,
planning construction, operations and maintenance and monitoring;
(ii) Increase time availability for livelihood opportunities/activities by women as less time
will now be devoted to access water for the households;
(iii) Ensuring reduced wage disparities between women and men for work of equal value
and effective application of core labour standards in Project related work opportunities;
(iv) Women’s effective participation in governance and community decision-making
processes and structures; and
Appendix 5 SOCIAL ASSESSMENT REPORT
43
(v) Improved gender awareness and capacity among the staff of KWASA, Khulna City
Corporation and the concerned wards.
5. COMMUNITY PARTICIPATION
5.1 Process
During the course of the Study, the consultation took place at ward level participated by various
stakeholders. Community stakeholders include the KWASA, KCC ward officials, NGOs, CBOs, line agency
representatives, poor and vulnerable households, women’s group and residents in low income and slum
areas including local businesses. Consultation began during the preparation of the pre-feasibility study,
which focused on the alternatives for the water supply sources and distribution systems. Further
consultations were carried out to determine the optimal way to enable the poor in slum and low-income
areas to access the KWASA water supply systems. The local stakeholder consultations and focus group
discussions were held to help formulate strategies to ensure coverage and inclusion of the poor in the
Project.
In addition, interviews with key informants (KII) were also done with heads of institutions and
organizations like UPPRP, KCC, CDC, Urban Primary Health Care (UPHC), community leaders and head of
households. Information collected from both FGDs and KIIs were analyzed and processed which formed
the benchmark for the social analysis and in formulation of the GAP and, PRS, and CCP.
An estimated number of 400 persons participated in the FGDs which were conducted from 23rd
September to 3rd October 2010. Of this, about 60% were women. The approach involved open and
participatory method intended to provide a forum for the communities to give their perceptions,
comments, project impacts or risks and recommendations on their specific concerns. The
documentation of this process and list of attendance, and persons met is attached as Appendix 4.
5.2 Highlights of FGD Findings
A summary of findings on the FGD is presented below. A documentation of the FGD exercise is attached
as Appendix 4.
A. Essential Information
• There is generally a signified needs and demand for clean and safe water in the District of
Khulna.
• The main source of water in the target area comprise of deep and shallow hand tube wells
installed by the former KCC, GOs and NGOs. These are used for domestic and drinking
consumption of households. River or pond water is also utilized in other areas for domestic
needs.
• The quality and quantity of water is viewed as poor. The intrusion of sea water affects the
quality of water. Incidence of poisoned water was raised in some area.
• Most common form of water borne diseases includes dysentery, cholera, and typhoid fever.
There are cases of women suffering from urinal infection and reproductive infection.
• Women and children are main carriers of water. Others have to get water from far distance
affecting the health of women and children.
• Many of the water facilities are malfunctioning or out of order resulting to scarcity of water.
Appendix 5 SOCIAL ASSESSMENT REPORT
44
• Households are generally willing to gain access to piped water which is perceived to bring
several benefits such as: (i) 24 hrs. supply; (ii) sufficient quantity of water; (iii) fresh and potable
water; (iv) free from water born diseases (v) reduced conflicts among the water consumer/user;
(vi) clean environment; (vii) Reduced health related sickness of women due to distance travelled
from collecting water.
• Preference on water service: Majority of the participants opted for communal tap water service
to be shared by 10-12 households. Land owner in the area interested to have individual water
connection for the household. For a cluster of households the probable location of common
water tap should be central point of the cluster and away from the KWASA existing
deep/shallow hand tube wells location.
• Affordability of members reflect their willingness to pay for water service which ranges from Tk.
10-20 per month for public tube wells and Tk 100 per month for piped water.
5.3 Issues Raised
• Lack of access to safe water
• Inadequacy of water supply
• Quality of water is not good
• Poor maintenance of water facility
• Prevalence of water borne diseases
• Affordability level of poor income households
5.4. Recommendations
• Provision of an appropriate, cost effective water service
• Effective operation and maintenance of water facility
• Provision of basic infrastructure facility to access water supply (roads)
• Identification of various categories of water users (poor, extreme poor)
• Conduct skill development activity/programme;
• Create job opportunity for unemployed;
• Create job opportunity for women;
• Control drug and narcotics;
• Education for all;
• To control child marriage, violence against woman, trafficking, dowry;
• Arrangement for old home;
• Campaign for social awareness.
5.5.3 Community Participation Plan
The details of the participatory activities to be undertaken during Project implementation is discussed in
the Community Participation Plan, attached as Appendix 3. The ADB’s Policy on social safeguard
advocates open public consultation of stakeholders to achieve the following objectives. (i) involvement
of stakeholders (men and women) in water project development planning and enable them to
Appendix 5 SOCIAL ASSESSMENT REPORT
45
participate in the assessment of impacts and risks (ii) participate in making decision that affects their
lives (iii) understand the role of men and women in the implementation of the Project.
6. CONCLUSIONS AND RECOMMENDATIONS
6.1 SUMMARY of Findings
1. Maximum demand at minimum cost
The social assessment showed high acceptability and social viability as affirmed by the FGDs and
Consumer’s Survey. There is a clear demand for improved water supply as over 90% of households
affirmed and indicated their interest to connect to KWASA piped water system. The existing major water
sources, which are the KWASA piped water, public tube wells and private wells are inadequate to meet
the demand of the public in the coming years.
The potential population to be served by the Project is estimated at over 200,000 by 2017. Of these,
about 22 % belong to slums income households. Average consumption of households on water is
estimated at about 20-25l/c/d.
Corollary to the various options for water supply, affordability of water connections and rate of monthly
bill for most of these low income and slum communities is the major deterrent to connection and
willingness to pay. Study has shown that connection fee of 3,000 is beyond the budget of the poor
households; more than 100 taka of monthly bill will also deter many of the households from connecting.
51% of the surveyed households are considered as poor and extreme poor indicating a per capita
income below the national threshold which Tk5, 000/month.
However, a significant finding on this survey is that, although there is a high percentage (51%) of poor
and extreme poor households, people are still willing to appropriate a budget at maximum Tk 100 per
month and a connection fee of Tk 1000 in order to obtain safe and secure water supply.
2. Preference on water sources is based on adequacy, affordability, accessibility and availability of
water at all times.
There are basically two major water sources used by the majority of households; i.e. public tube well
and private tube well. Most of the poor households in slum communities access their water from these
sources which are viewed as affordable, convenient and adequate in supply. KWASA’s current piped
water is considered as inadequate and often fails to deliver water. However, bulk connection to a
registered community organization in slum areas, which will manage the delivery through a communal
tap stand, is viewed as acceptable. The management of community water tap such as collection and
maintenance can be done by the WUG.
The willingness to pay for piped water is on average Tk100/month/household. Given an average
consumption of 20m3/household, cost of water is about Tk10/m3. This amount is reasonably affordable
to 70 percent of households in all categories.
3. Wide range of significant benefits
Appendix 5 SOCIAL ASSESSMENT REPORT
46
The project is viewed as an initiative with a wide range of beneficial impacts. It will have major beneficial
impact on the health and sanitation condition in the households and communities which would have
positive impact on improving man-hours for productive endeavors and translate into savings in medical
and health expenditure related to water borne diseases. Likewise, during construction period of piping
and tap installation, the poor may directly or indirectly benefit. Civil works will create short-term job
opportunities, and general promotion of economic activities will expand the job market in the longer
term.
4. Significant gender impact
While both women and men are more likely to benefit from the planned WSS upgrading, the Project has
the potential to contribute to the general wellbeing of women especially of poor households in the slum
and low-income areas. Women and girls who are usually the ones responsible for obtaining water from
various sources sometimes far from their place of domicile will now have more time for other
community activities. Women in the low income and slum communities are also more likely to have
increased health benefit due to improvements and availability of safe water. Furthermore, women of
poor households will be empowered through participation in Project planning and decision-making,
capacity building interventions and access to project related employment opportunities. Socioeconomic
development
Benefits women may receive with improved or new water and sanitation facilities can be classified into
health and socioeconomic categories. Water sources that are closer to homes and that provide an
adequate supply can decrease collection time. This will lead to economic gains in both time and energy
which can be utilized for other productive activity and enhance family income.
Adverse impacts and risks from Project related activities faced by women are deemed not significant;
nonetheless, during Project implementation if there are unforeseen risks identified, proper measures
will be undertaken for their mitigation.
Some of the prevailing issues that are common in water projects affecting women are spelled out in the
Table below along with mitigation measures. Strategies to address gender concerns are provided in the
Gender Action Plan (Appendix 2). Signified willingness and participation of development partners
NGOs have grown to a level where today they are an accepted feature of the administrative landscape.
Because of the special character that places them somewhere in between the public and the private
sectors, NGO partners are of great importance in helping to reach the twin goals of universal water and
sanitation coverage towards health for all.
There are a number of NGOs operating in the area that provide support on water and sanitation projects
to underpin other income generating and health related schemes. There are about 32 local institutions
and NGOs operating within Khulna. These NGOs are undertaking several development initiatives which
can be linked with the water project.
In particular, the UPPRP has signified their willingness to become partner with KWASA by funding line
connections of poor households to the water tap or network. UPPRP has also the potential to assist in
the delivery of community based water management through their existing community development
committees (CDCs) which has been established in 31 wards of Khulna.
Appendix 5 SOCIAL ASSESSMENT REPORT
47
Recommendations
3. Inclusion and Targeting of the Poor Households in Water Supply System Coverage
The main purpose is to increase access of poor households to water services. The identification and
targeting criteria of poor and extreme poor households have been developed following the approach
and methods developed under the ADB financed 2nd Urban Primary Health Care Project (2005)
complemented by the methodology used in the UPPRP where community members themselves identify
the extreme poor and poor households using a set of criteria similar to the ones suggested in the
2UPHCP.
The community members assisted by an NGO and KWASA community development officer needs to
undertake the identification of vulnerable target beneficiaries where 10-12 such households proximate
to each other will form a water user association to be officially registered with the ward office as a legal
community based organization. It is necessary that Community Development Specialists will be assigned
(5 wards each) to develop action plan, immerse in the community and work with the WUG in addressing
water issues and identify community resources.
To include low income households gain accessibility to water is through a provision of a communal tap
system which can be shared by 10-12 households. A one time connection fee can be subsumed and/or a
portion to be shouldered by the group of households and amortized over a certain period. Monthly bill
of not more than 100 taka per household could be charged for a bulk delivery on a guaranteed quantity
and quality per water user group.
When considering a tariff associated solely with water supply, the Project can establish a tariff structure
which supports the social objectives of income redistribution quite readily.
One way is to provide fixed rate for a consumption of say 20-25 l/c/d for all consumers at a price less
than the average cost of supply.
For LIC, the installation of common water points, community stand-posts / hydrants / standpipe should
also be metered and responsibility given to a local WUG for operating and maintaining the unit and
collecting monthly tariff.
The establishment of a Water Fund especially for the extreme poor can also be a workable alternative to
provide access of extreme poor who cannot afford connection. The Water Fund Provider can also
provide immediate recovery of connection costs. A Water fund can be worked out with an existing
program of NGOs or the UPPRP who are able to provide the initial capital to for low income beneficiary
households make a certain number of connections per year. The beneficiary consumer is then billed the
full costs of the connection in equal monthly instalment over several months, including an interest
charge of normal commercial rates in addition to the normal bill for consumption. The Water fund then
becomes self-supporting without burdening the financial resources of the water fund provider.
Individual collection of the monthly dues will be the responsibility of the WUG to be turned over to the
water funder. This strategy will require very intensive social//community development support program
in terms of organization of the households, capacity building for O&M and monitoring activities. The
UPPRP has already established this type of community development program covering the 31 wards of
Khulna, carried out by through the CDCs and coordination with the CDCs will significantly be beneficial.
Appendix 5 SOCIAL ASSESSMENT REPORT
48
4. Building on options and preferences of the community
Field visit has shown that for many poor households in slum communities, individual connection is
impractical and connection fee is unaffordable. It will also need to deal with issues of tenure and
permanency of resident status of concerned households. It has also been observed that most of such
areas have very little space for having independent water supply connections.
Therefore, in such cases it is imperative that an approach needs to be developed to install common
water points – community stand-posts / hydrants / standpipes. Such common facilities should also be
metered and responsibility given to a local WUG for operating and maintaining the unit and collecting
monthly tariff. A standard set of designs suitable for specific LIC or slum areas should be developed and
numbers estimated for investment purposes.
In areas where piped water can no longer be served, culturally acceptable technology of water facility in
preference expressed tube wells where they are predominant and extensively used among low income
groups. It offers advantages of convenience, reliability, convenience and affordability. The UPPRP can
also be tapped to provide hand pump tube well to areas where individual connection is not advisable.
5. Increase participation and involvement of the community in the planning, implementation and
M&E.
The risks of formulating interventions not appropriate to the local situation and divergent from the
needs and priorities of the local population must be addressed through regular consultation and
participation. This activity will have to be facilitated by the Community Development Specialist, who will
immerse in the area for a period of 6 months. The consultations and participatory processes will have to
start from the bridging period up to Project implementation and the CDS will ensure that the
Consultation and Participation Plan is implemented. The presence of the CDS in the area will motivate
the community to create awareness, take action that respond to their immediate and long term needs.
Some areas that need to be strengthened are on water conservation, preservation and sanitation at
household level. It is expected that the availability of safe and adequate water will change in health
behaviour, as women and children pay more attention to hygiene and sanitation. Water of a better
quality which remains uncontaminated helps to decrease water-related diseases which are prevalent in
the slum areas.
However, the health gains so confidently anticipated in water program has yet to be realized. The FGD
results indicated that water borne diseases continuous to be prevalent even in areas where there are
existing tube wells. The problem is that, drinking tube well water will not necessarily protect health
unless there is parallel health education and improvement in environmental sanitation and hygiene
awareness. In water projects, there is ample evidence to show that unless water sanitation and hygiene
education go together, the health impact of improved water facilities may be lost.
This is the challenge that the Project will have to address and the CDS, together with the community,
particularly women, will take the lead to ensure the proper use of water along with application of
proper hygiene if improvement on health status will be achieved.
Appendix 5 SOCIAL ASSESSMENT REPORT
49
6. Enhancing productive capacities and involvement of women
Gender considerations are important at community level where partnership approach depends on all
potential beneficiaries having a say in water project. If women are to make their full contribution to the
project, they must be involved also in decision making and other responsibilities in the project such as
selection of site, operations and maintenance, monitoring and evaluation. The broad field of gender
issues focuses on the roles and tasks of men and women and in what ways they interact to make
decisions and share responsibilities. The focus on gender recognizes the fact that full benefits only
accrue from improved water when men are encouraged to become also involved in supporting women,
allow women to participate in management committees and in operations and maintenance. Project
contribution of time, labor and money need to be shared fairly and not expected of women alone.
Likewise, to involve women create sustainable water system and reach the poorest, program on water
must include or linked to economic development and poverty reduction program. If the Project expects
poor people, especially women to pay for water, initiative to create opportunities for productive
capacities must be incorporated as a part of the Project framework.
The role of the Gender Specialist is important in undertaking the above activities and in the
implementation of the Gender Action Plan (Appendix 2) attached in this document.
7. Develop and establish partnership with other support groups
The water project is closely linked to other sectors such as environmental, health, poverty reduction and
to goals for sustainable urban/rural development. The use of NGOs as partner in water sector is crucial
particularly in addressing gender concerns and poverty reduction.
In terms of addressing health and sanitation, the Urban Primary health Care Project (UPHCP) deals with
various programs which include maternal child care, reproductive health, sanitation and nutrition. This
government program could be tapped for linking water with health and sanitation.
Because of the special character that places them somewhere in between the public and the private
sectors, NGO partners are of great importance in helping to reach the twin goals of universal water and
sanitation coverage towards health for all, and at the same time addressing poverty reduction program
that will contribute to the sustainability of the project. A list of NGOs has been identified. In particular,
partnership with the UPPRP for joint financial funding of provision of tube wells, as well as funding
connection of water pipe from tap stand to the residence in the slum areas must be sustained.
A list of NGOs is provided where linkages can be organized by the Community Development Organizer.
Appendix 5 SOCIAL ASSESSMENT REPORT
50
Appendix 1 – Summary Poverty Reduction and Social
I. POVERTY ANALYSIS AND STRATEGY A. Linkages to the National Poverty Reduction Strategy and Country Partnership Strategy
The program of Bangladesh on poverty reduction is reflected in the government’s National Strategy for Accelerated Poverty Reduction (NSAPR). The strategy highlights a holistic programmatic approach which includes provision of civic amenities, public transportation, employment generation, basic infrastructure facilities and water and sanitation. One of the GoB’s current initiatives is focused on expanding water services in urban areas specifically in Dhaka and Khulna. The GoB’s approach puts emphasis on building capacity of local governance and the involvement and participation of communities and local organization to sustain development initiatives particularly in water and sanitation.
The NSAPR is in line with the country strategy and program of the Asian Development Bank (ADB) for Bangladesh (2006-2010), within the framework of urban water supply and sanitation sector, which play a very significant role in achieving the envisaged economic growth and poverty reduction program of Bangladesh. In particular, the objectives of the KWASA Project aim to provide clean, safe and affordable water to all Khulna residents. Various socioeconomic, health and environmental benefits are expected to significantly contribute to the overall improvement on the quality of life the populace, which is also in line with the ADB’s and the GOB’s program towards attaining water for all and poverty reduction.
B. Poverty Analysis Targeting Classification: General
Key Issues: While poverty incidence in Bangladesh is decreasing in absolute terms, the number of urban poor grows with the rapid urbanization. Employment opportunity draws large migration from rural areas to cities, resulting in expansion of slums under ineffective urban planning and control. Of the urban population, 45% lives in poverty and 25% is classified as extremely poor (defined by consumption of less than 1,805 kilocalories per day). Poor urban infrastructure such as inadequate drainage, water supply, and sanitation often exposes the population to public and environmental health hazards. Most urban poor live in slums without access to basic services like water, sanitation, and energy. Most low-income groups are migrants from rural areas and rely on informal and unsecured income sources. The ready-made garment industries employ a large proportion of these urban poor and the majority of them are women. Lack of awareness and measures to control household and industrial waste have become a major cause of pollution in the urban areas. The city corporations and pourashavas often do not have enough capacity and proper mechanisms to deal with the needs of the poor and women.
B.2 Poverty Indicators
In Khulna City, findings from reviews and the Consumers Survey reveal the dimensions of poverty.
(i) Limited land ownership and permanent housing
Almost 80% of the slum clusters (520) in KCC were established on privately owned land. About 12.5% are on public land while the rest are on land owned by other organizations. Of the total slum population, 54.3%, 27.1% and 18.6% are located in private, public and other land category, respectively. Out of the total slum households, 59.4% rent their residence, 17.4% owned them while 23.1% are rent-free.
Appendix 5 SOCIAL ASSESSMENT REPORT
51
(ii) Poor Housing structures
The Consumer’s Survey (2010) indicates that 51% of the survey households live in poor housing structure. Housing materials of the extreme poor (22.5%) are made of tin sheets while the poor (28.9%) are made of combined or unfinished cement and low quality wood.
(iii) Low access to piped water and sanitation services
While there are varied sources of water, the majority of the poor households in slum communities access their drinking water from shared public (59.1%) and private hand tube wells (38.4%). The Consumers Survey showed that, of the 3006 households surveyed, only 913 (30%) households have got connections to piped water. Of this (30%) only 7% of the extreme poor and 41% of the poor households have got connections. Several reasons were cited for not getting connected to piped water such as distance of the house to the network (69%) and, (ii) poor quality of water which is viewed by 71% of the respondents. Poor households result to using water from public and private tube wells. However, the quality of water in some of the tube wells is not fit to drink. The intrusion of sea water affects the quality of water giving a saline taste. Incidence of poisoned water (presence of arsenic) was raised in other areas. Some private hand tube wells are over 12 years and water coming has accompanied iron content. Field assessment has shown that for many poor households in slum communities, individual connection is impractical. The household’s dwelling is normally a one-room unit used primarily for sleeping by 5-6 members. Cooking, bathing, toilet and sanitation facilities are communal in a separate corner of the residential compound. (iv) Prevalence of water borne diseases in slum areas affecting women and children
The FGDs affirmed that the most common form of water borne diseases which are prevalent in slum areas include dysentery, cholera, and typhoid fever. There are cases of women suffering from urinal infection and reproductive health infection. When the existing water facilities malfunction, women and children who are the main carriers of water had to travel long distance to fetch water and this has a bearing on the reproductive health of women.
(v) Low Income
The Consumers Survey reveals that the majority of households (37%) earn between Tk 5000-10,000 per month. According to national standard, the poverty line is set at TK 5,000 (US$71.4). Given this figure shows that an overall 41% of the respondents fall below the poverty line. Assuming an average of TK 5000 per month for poor households and with an average family size of 5.8 (applicable for poor households) gives an average of TK862 (US $12.3)/capita per month or TK 28.7(US$.41) per capita per day. This amount is not sufficient to meet the daily (3 meals) nutritional requirement of poor households.
(vi) Low access to education
Access to regular employment is constrained by low level of education which is high among the extreme poor and poor households. 13% of the extreme poor have not been to school, and very few (9%) has reached high school. Access to education as it reaches higher level is rather limited to both extreme poor and poor households.
Consumer’s Survey 2010 Sampling size: 51,370
Indicator: Housing structure Category No %
Tin sheets (extreme poor)
11,581 22.5
Semi Pucca (poor) 14,885 28.9 Pucca (above poor) 24,904 48.6
Appendix 5 SOCIAL ASSESSMENT REPORT
52
(vii) Low access to regular employment
Access to regular employment is again low among the extreme poor (19%) poor (32%) is also low. Apparently, the findings show that the lack of adequate education among the extreme poor and poor households inhibits them from gaining access to regular jobs in the formal sector. The majority among the extreme poor (30%), poor (33%) are housewives which are considered as an occupation. The FGD affirmed that housewives, aside from doing domestic work are also engaged in varied forms of income generation activities to supplement family needs, such as housemaids, tailoring, embroidery, poultry, animal husbandry, batik making, goat raising, and home based cottage industry. Home based income generating activity comprise of cloth or garment making, raising animals, small restaurant, etc. Other common forms of work among the extreme poor and poor households include laborer (12%), rickshaw puller (2%) farmers (5%).
Key Issues
(i) Affordability and willingness to pay
Corollary to the options for water supply, affordability of water connections and rate of monthly bill for the
majority of low income and slum communities is the major deterrent to connection and willingness to pay. The
signified willingness to pay is not more the Tk 100/month for extreme poor and poor households.
The Consumer’s Survey results show that, overall, the three categories of water consumers can be classified as follows:
a) Extreme poor – households living below TK 2,500, (11.4%) of the target consumer population. Over 50% of these households cannot afford to pay for connection and water bill exceeding Tk100.
b) Poor households - households living below Tk 5,000, (28.9%). Over 40% of these households can less afford to pay for connection of over Tk1, 000 and water bill exceeding Tk100.
c) Above poor- estimated at 48.6%. These are households whose income are over TK5, 000 and can afford to pay for water services.
The focus of the PRS is to maximize water service coverage and define strategies for inclusion of categories (a) and (b) to the KWASA project.
(ii) Access of low-income households to piped water
Access to piped water is constrained by limited housing space, distance and capacity to pay. This is also constrained by issues on land tenure thus limiting permanent connection to piped water
Design Features
From the outcome of the Consumers Survey and FGD, it is clear that the intent of the citizens of Khulna is to get connected to KWASA network through individual connection or cheaper yard connection. Both positive and negative impacts are affected as a result of the project. Positive impacts of the Project include:
(i) Improved access to safe water at affordable costs - the primary mechanism through which benefits will
Appendix 5 SOCIAL ASSESSMENT REPORT
53
accrue to the poor is by the potential savings derived from less medical expenses as access to safe water will result in less exposure to water borne diseases.
(ii) Enhanced economic impact - improved health condition and general well being of the household members will result into more economic productivity. The saved time and energy gains or surplus water for an improved water supply can be utilized by women for work in agriculture, horticulture, dairying, and animal raising which is common income generating activities of women. These will enhance their productive capacities and contribute to family income.
(iii) Enhanced employment and Income Generation - employment opportunities will open for unskilled as well as skilled labor during construction. Specific measures will be taken by KWASA (the executing agency) to ensure the enforcement of CLS by the contractor on the work camps/sites. Indirect employment opportunities will arise from better infrastructure facilities.
(iv) Equitable distribution of contributions and benefits- derived from increased earnings for men and women resulting from construction employment generated by the project.
The design for the water provision for low income households among others shall include:
(i) Community based water management of communal tap stand system
For LIC, the installation of common water points, community stand-posts / hydrants / standpipe should be metered and responsibility given to a local WUG for operating and maintaining the unit and collecting monthly tariff. The cost of connection can be shared by WUGs. To ensure that water consumption does not exceed a certain quantity per month charged at a fixed price, a flow limiting device is an alternative for low volume or higher rates for metered volumes if household chooses to increase his consumption. KWASA will provide a communal tap system which can be shared by 10-12 households. A one time connection fee can be subsumed and/or a portion to be shouldered by the group of households and amortized over a certain period. Monthly bill of not more than 100 taka per household could be charged for a fixed volume quantity per water user group say 20m3/month. The Consumer Survey Report (2009) estimated that approximately 20% of the potential costumers of KWASA are the unconnected poor households in slum areas and low-income areas. Based on a population growth projection for 2017, there will be approximately over 20,000 such households requiring connection to safe water. With 10-12 households per communal tap, the Project will need to organize over 2,000 water user associations by 2017 which translates to the same amount of water tap stand.
(ii) Fixed rate at subsidized cost for individual connection of poor households
When considering a tariff associated solely with water supply, the Project can establish a tariff structure which supports the social objectives of income redistribution quite readily. For individual connection, one way is to provide a fixed rate for a consumption of say 20-25 l/c/d for all consumers at a price less than the average cost of supply. Individuals connected to water piped could also sell water to unconnected individual households, at a fixed rate agreed by water user and seller.
(iii) Delivery of bulk water in high capacity storage or mobile tanks
For low income areas where connection to the network is not feasible, the provision of bulk supply of water to community based organization adjacent to the KWASA pipe system will be provided through mobile water tanks or fixed large volume capacity storage tanks. Similar to the community based management of communal taps, collection and maintenance will be managed by the WUG and cost of water will also be charged at fixed rate using per litre container, or by using a flow limiting device. Cost of water will be at subsidized rate to be recovered partially from lower O&M.
Appendix 5 SOCIAL ASSESSMENT REPORT
54
Poverty Impact Analysis
While the project provides with wide ranging significant benefits and positive impacts, the capacity to pay and affordability of water tariff particularly to extreme poor and poor households connotes negative impact. An analysis on affordability to piped water to determine peoples’ affordability is shown in two scenarios. The minimum cost for a house connection can be calculated as follows: Scenario A Connection Fee (1,000)
Connection fee ( start up investment cost of HHs Tk 1,000 HHs current budget for water (minimum of 20m3 @ 6.33/m3 Tk 127 Total budget of water for one year ( 12X Tk 127) Tk 1296 Total investment for 1 year Tk 2423
Scenario B Connection (Tk 300) - Assumption
Current budget for water represents only 1 percent of household expenses which is estimated at Tk127 for 20m3. It is clear that the connection fee in Scenario 1 places a burden on households, particularly for the extreme poor and poor since it forms 46.5% higher than the budget appropriated for water for the first year. On the other hand, if the connection fee is lowered by 70%, assuming that Project pays for connection, households are able to maintain their current budget for one year with only 30% additional cost for connection. The Consumers Survey indicates that about 59% of the population have a monthly income of more than Tk5, 000/month or Tk60, 000/per annum. These households may be considered as having capacity to pay for house connection. Under Scenario A, the total costs of a house connection plus water bill during the first year amounts to TK2, 423. This is about 4% of the annual income of Tk60, 000. This amount is affordable to 59% of households but unaffordable to 41% of the extreme poor and poor. On the other hand, under Scenario B, the total costs of a house connection plus water bill during the first year
amounts to TK 1,723. This is only about 2.8% of the annual income of Tk60, 000 per month, and is considered
as more affordable for the low income households.
Measures:
It is clear that a fixed rate of TK 100 with a connection fee of Tk 300 will enable all categories of households to
gain access to KWASA network. Reduction of cost to an affordable rate while equally recovering costs will
maximize access of poor households to safe water thus achieving the project’s objectives. Addressing the
above measure would require policy action from KWASA.
C. Poverty Reduction Strategy
1. Inclusion and Targeting of the Poor Households in Water Supply System Coverage
Connection fee ( start up investment cost of HHs Tk 300
HHs current budget for water ( minimum of 20m3 (6.33/m3
Tk 127
Total budget of water for one year ( 12X Tk 127) Tk 1296 Total investment for 1 year Tk 1723
Appendix 5 SOCIAL ASSESSMENT REPORT
55
The main purpose is to increase access of poor households to water services. The identification and targeting
criteria of poor and extreme poor households have been developed following the approach and methods
developed under the ADB financed 2nd Urban Primary Health Care Project (2005) complemented by the
methodology used in the UPPRP where community members themselves identify the extreme poor and poor
households using a set of criteria similar to the ones suggested in the 2UPHCP. The following indicators define
the extreme poor and poor households, which can be applied for the Project.
a. More than 6 people dependent on one earning member b. Has 3 children of less than 5 years old c. Child labour of less than 15 years age works for full day d. Age of family’s main income earner is more than 60 years e. Female headed households f. Have disabled family member g. Suffering from prolonged ailment h. Have drug addicted member of the family i. All family members above 16 years of age are illiterate j. Have school age children but not going to school or is a drop out k. Lack of access to safe drinking water l. Lack of access to sanitary latrine m. Live in hut (made of hay, thatch, polythene). Continuously afraid of eviction. n. Culturally or socially isolated family.
2. Establishment of a Water Fund Provider (WFP)
The establishment of a Water Fund Provider (WFP) especially for the extreme poor can also be a workable alternative to provide access of extreme poor to KWASA network who cannot afford connection. The WFP can also provide immediate recovery of connection costs to KWASA. The Water Fund can be established as a social fund under the KWASA structure, or in partnership with NGOs with poverty reduction program which are able to provide the initial capital for loan assistance to low income households, make a certain number of connections per year. The beneficiary consumer is then billed the full costs of the connection in equal monthly instalment over several months, including an interest charge of normal commercial rates in addition to the normal bill for consumption. The Water Fund then becomes self-supporting without burdening the financial resources of the WFP.
Individual collection of the monthly dues will be the responsibility of the WUG to be turned over to the Water Funder who in turn will turn over the fund to KWASA. 3. Income Enhancement Measures
Although the Project will not directly engage in income generating and livelihood activities for the poor beneficiaries, however, as part of the community development activities, the Community Development Specialist of KWASA will work closely with NGOs involved in micro credit and livelihood enhancement training and link the members of the WUG to these development organizations. This will also assist the community and the WUGs in addressing affordability and sustainability concerns to pay for the water bill regularly if they are able to get involved in income supplementing activities. 4. Mobilization of NGO and CBO Support for Poor communities
A number of NGOs are currently operating in the areas which can be tapped to link capacity building program and income enhancement support for LIHs.
Appendix 5 SOCIAL ASSESSMENT REPORT
56
II. SOCIAL ANALYSIS AND STRATEGY
Findings of Social Analysis
A social analysis was carried out for the project through a sample socioeconomic baseline survey covering approximately 3,000 households. Close to 11% of residents of the surveyed households are migrants, and 89% are locals. Household heads are mainly self-employed or have jobs in private and public offices. Average size of households among extreme poor is 7.23; poor 5.84; and above poor 4.59. More than half (57%) live in their own houses, one-third in rented houses, and 9% on government land. About 96% of households have electricity with unreliable supply and 76% have gas connections. Residents depend on piped water supply, hand tube wells, street hydrant/community taps, pond/canal for bathing, and public hand tube wells. Residents complained about inadequate supply of piped water and street hydrants/taps, and supply is still lower in slums. Average consumption of households on water is estimated at about 20-25l/c/d. The SPA reveals that the pattern of consumption and management of water between the extreme poor, poor and above poor varies. Above poor have higher consumption level due to various factors like having a car to wash, maintaining a garden, flush toilets, laundry which could readily consume over 120 lc/d. On the other hand, the poor and extreme poor do not have the luxuries that above poor have, thus having less consumption. Low income people in slum areas are forced to limit consumption because of the lack of an interior plumbing system and an ability to dispose of waste water created by uncontrolled consumption.
The majority (37%) of families use private pit latrines. Lack of sewerage and drainage creates environmental health hazards. To varying degrees, most households experience common problems such as unreliable power/gas supply; pollution and unhygienic urban environment; traffic congestion; inadequate water supply; poor drainage, sewerage and waste management; and poor government/municipality services.
A high percentage (58%) has reached primary (35%) and secondary (23%) education. Some 20% have obtained college education. Some 13% of the “extreme poor” and “poor” have never attended school.
Household expenses are higher than household income. In comparison to household expenses, “extreme poor”
households spend about Tk 5,381/month. Assuming an income of Tk2, 500 for extreme poor reveals that
expenses are 1.15 % higher than income. This is slightly lower than the national average which is set at 1.17%
higher. On the other hand, the “poor” households spend Tk8, 292 per month. Assuming an average of TK3,
000 per month, shows that expenditure is 1.17 higher, which is consistent with the national figure.
Because of lack of income, households result to debts or loans. The findings showed that aside from food
which ranks first among household expenses of the extreme poor and poor households, this is followed closely
by repayment of loans.
Overall, the first three important priorities of the extreme poor in terms of expenses are: food (51%), followed by
repayment of loans (19%) and education (14%). The remaining amount is allotted almost equally in other items
such as clothing (5%) housing (4%) medical bills (5%), transportation, and fuel (5%) electricity (3%).
Overall, the social assessment showed high acceptability and social viability as affirmed by the FGDs and Consumer’s Survey. There is a clear demand for improved water supply as over 90% of households affirmed and indicated their interest to connect to KWASA piped water system. The existing major water sources, which are the KWASA piped water, public tube wells and private wells are inadequate to meet the demand of the public in the coming years.
Appendix 5 SOCIAL ASSESSMENT REPORT
57
The potential population to be served by the Project is estimated at over 200,000 by 2017. Of these, about 22 % belong to slums income households. Average consumption of households on water is estimated at about 20-25l/c/d.
Corollary to the various options for water supply, affordability of water connections and rate of monthly bill for most of these low income and slum communities is the major deterrent to connection and willingness to pay. Study has shown that connection fee of over Tk1,000 is beyond the budget of the poor households; more than 100 taka of monthly bill will also deter many of the households from connecting. 51% of the surveyed households are considered as poor and extreme poor indicating a per capita income below the national threshold which Tk5, 000/month.
However, a significant finding on this survey is that, although there is a high percentage (51%) of poor and extreme poor households, people are still willing to appropriate a budget at maximum Tk 100 per month and a connection fee of Tk 1000 in order to obtain safe and secure water supply.
Key Issues
(i) Social Equity
Most often the objectives related to social equity has become a controversial argument especially when it relates to cost of water. Arguments on water tariff is based on the premise that water is an indispensable need therefore should be provided at a lower cost and subsidized for all income groups or free to the poorest of the poor. While it is true that water itself is free, the services of bringing good quality water to the doorstep with 24 hours service definitely incurs cost. The government often cannot afford to subsidize the price of water in addition to supplying services in other sectors due to factors like increase in energy cost, operating costs, etc. Subsiding cost often result to more volume of water used but low recovery which results to another problem of low maintenance on water services. Once maintenance breaks down and quality is sacrificed, people would be reluctant to pay for water bills.
(ii) Unsanitary health practices in slum areas
Unsanitary environmental condition and practices are dominant in slum condition due to lack of efficient domestic wastewater management. There is prevalence of water borne diseases occurring in the area which is triggered not only by unsafe water but the lack of sanitary and hygiene practices. A. Social Strategy
The overall objective is to enable the community proximate to the KWASA water supply pipe system, particularly the vulnerable groups, to be active in the development and implementation of the Project. The Poverty Reduction Strategies and Gender Action Plan will institutionalize and internalize the beneficiary driven approach for sustainable social development interventions particularly for the women members of households, poor households, IPs (if any) and low income households in slum areas. The Consultation and Participation Plan (CPP) will be a program to be coordinated by KWASA, implemented by the Social/Community Development Organizers hired by KWASA under the Customers Relation Unit. An experienced NGO will be contracted for the first three years of Project implementation to assist the field staff in the community organization and capacity building activities as well as community level information campaign on the program.
1. Awareness creation and project dissemination
Appendix 5 SOCIAL ASSESSMENT REPORT
58
One of the key elements of the participatory strategy is the intensive program of communication activity to enhance water, hygiene and health awareness. A whole new range of promotional literature and visual aids will be incorporated in water, sanitation, hygiene and health promotion messages. These will be produced both for use in training programs and among user groups. Messages on flyers, posters, and leaflets must be kept simple but with impact, for example: “Conserve Water”. “Water is life”. Coordinated efforts with mass media and the academe will also be done to include right use of water and health messages as part of health education in schools. KWASA staff together with the Program Consultants and the COMREL and the KCC officials/staff at the ward level as well as the WUGs and Ward Water Supply and Sanitation Committees (WSSC) will work closely with the local officials to undertake a marketing/information campaign on the new program of KWASA on WSS. The communication materials and strategy developed by Consultant Specialists will be utilized for this purpose.
2. Building capacity of WUGs and Committees in low income and slum areas
A major feature of PRS is enabling the WUGs, Committees, and ward officials to plan and implement the GAP, PRS and CPP in a participatory manner with the participation of beneficiary households, NGOs, and women. Planning will involve the formulation of strategies to ensure access of services and benefits of the Project by the poor households in the slum and low-income areas of the wards under the service coverage of KWASA groups. To sustain affordability and sustainability of services, strategies will be pursued involving employment provision, capacity building, including improving O&M which eventually can lead to income generation/income enhancement and monitoring activities especially related to leakage detection, and reporting of illegal connection. 3. Establishment of Complaints and Response Mechanism at the Ward Level
While KWASA will ultimately be responsible for addressing complaints of customers, the participatory mechanism will provide a mechanism where at ward CCW level, complaints regarding service, leakages, billing and other customer relation matters, could first be heard and possibly mitigated. If the CCW is unable to provide a solution, the complaint would then be referred to the KWASA zonal team (SocDev/ComDev Specialist) for appropriate action. 4. Participation in Operation, Maintenance and Monitoring Activities
The WUG will be responsible for collection of monthly dues from individual members and remittance of payment of the monthly bill to KWASA. Pipe leakages, damage to the communal tap as well as illegal connection will be monitored at community level and reported to KWASA through an established system. The WUG elected officers will be responsible for record keeping, updating and maintaining the books of account for regular reporting to the members. The Project Community Development Specialist will provide the appropriate trainings to the WUG officials.
5. Develop and establish partnership with other support groups
The water project is closely linked to other sectors such as environmental, health, poverty reduction and to goals for sustainable urban/rural development. The use of NGOs as partner in water sector is crucial particularly in addressing gender concerns and poverty reduction. Because of the special character that places them somewhere in between the public and the private sectors, NGO partners are of great importance in helping to reach the twin goals of universal water and sanitation coverage towards health for all, and at the same time addressing poverty reduction program that will contribute to the sustainability of the project. A list of NGOs has been identified.
Appendix 5 SOCIAL ASSESSMENT REPORT
59
Overall, the above strategies will require very intensive social/community development support program in terms of organization of the households, capacity building for O&M and monitoring activities. The expertise of the Community Development Specialist / Organizers and Community Facilitators will be needed to mobilize communities, access resources and link these resources to support low income households increase their income to sustain not only the cost of water but other needs as well. B. Consultation and Participation 1. Provide a summary of the consultation and participation process during project preparation. Consultations were carried out with all stakeholders during project preparation through interviews, public meetings, focus group discussions and workshops. As integral part of the planning of safeguards, slum communities and other stakeholders were consulted during project preparation and design. Local communities, local government units, and government agencies were all involved throughout the preparation process to minimize negative impacts, ensure social acceptance, and increase community participation to ensure inclusion of the poor households in the slum area for potential coverage. Consultations were also held with emphasis on vulnerable groups and women, and played a vital role in raising awareness, gaining local support, and enabling affected people to voice their opinions and suggestions on project design and implementation. 2. What level of consultation and participation (C&P) is envisaged during implementation and monitoring? Selection and implementation of appropriate water supply system for the poor households will be done in a participatory manner. Identification and targeting of the beneficiary households will be community based with the Water User Associations and WSS committees involved in the process. The budget for C&P is integrated in the project consultancy budget. Views and concerns of all stakeholders will be taken into account in planning, implementation, management, and local governance through coordination committees at zonal and wards. Vulnerable groups, such as women and poor, will be properly represented in these committees. The update of the KWASA WSS Plan will be done in full consultations with citizens in the target area. 3. Was a C&P Plan prepared? YES, attached as Appendix 3. C. Gender and Development
Despite recent gains for women in the economic and social development of Bangladesh, women still remain particularly vulnerable to poverty. In urban areas, it is women who are responsible for managing water and waste in the households, and poor women are mostly engaged in informal waste-picking and recycling activities for their livelihood. Participation of women in stable, skilled jobs is low. The migrant women living in slums suffer from insecurity and inadequate services. Low standards of public and environmental health are a particular concern for women, as they are caretakers of household health. Khulna city offers a wide range of opportunities as an industrial zone, only a small portion of women have access to regular employment. As an alternative, women most often avail of micro credit programs and involved in other forms of work such as housemaids, sewing, raising poultry, embroidery, beef fattening, goat raising, small cottage industry (cloth, fire wood, cake, handicrafts, paper bag.) The multi roles that women function such as raising children, fetching water, doing domestic work and helping augment family income places a burden on women, which inevitably affects their health. The FGD affirmed that women suffer from various ailments affecting their reproductive health. The input of women in identifying community priorities is still limited, although the emerging citizens’ committees with female representation will boost women’s role in decision making. Women in the urban households have equal voices in decision-making. However, in the wards and community administrative system, women’s role appears to be limited by cultural/religious attitude. Efforts had been undertaken to address such imbalance and now aside from the ward commissioners there are now 10 positions for women councilors designated to take charge of women affairs in 2-3 wards per woman commissioner. However, aside from these formal elected positions, actual participation in decision-making by women in community
Appendix 5 SOCIAL ASSESSMENT REPORT
60
administration continuous to be limited and need to be addressed.
1. Key Issues
Gender Disparity. Various aspects of gender bias and discrimination in the area of education, employment and income, household roles and decision-making exist in the proposed Project areas. There is a higher proportion of female who are illiterate and functionally literate compared to the male. In terms of educational attainment, the proportion of men and women who have obtained or finished lower level of education appears to be equal primarily because of the national government’s interventions; however, at the higher level, the gender disparity becomes apparent again: more males have attained or finished Bachelor’s degree and/or post-graduate level than the females. In the area of employment, the situation appears to be no better. While women constitute almost half of the total labor force, only minor percentage is gainfully employed in the formal labor sector. The average annual income of female-headed households is usually lower compared to the male-headed households. Accordingly, the proportion of female-headed households who are below the poverty cut-off lines is very much higher than the male-headed households. On decision-making at the household level, the male is primarily responsible, except in female-headed households. But even there, the female head has to often consult with the male adult member of the households on major decision areas. Water collection and water/sanitation management at the HH and community levels are the traditional roles of women in the country. Because of this gender role and expectation, women had become more vulnerable to health risks imminent due to hygiene and sanitation resulting from the water supply and sanitation situation in the households and the community. They endure the high possibility of poisoning and getting sick due to constant exposure to arsenic-contaminated water and other water borne diseases. Their access to latrines and other sanitation facilities is often inhibited because of the gender insensitivity to the construction and management of such facilities. The proposed project must ensure that gender issues are addressed and that women benefit as well from the project and that interventions avoid gender biases; efforts at bridging the gap will need to be undertaken. It is expected that the availability of safe and adequate water will change in health behaviour, as women and children pay more attention to hygiene and sanitation. Water of a better quality which remains uncontaminated helps to decrease water-related diseases which are prevalent in the slum areas. However, the health gains so confidently anticipated in water program has yet to be realized. The FGD results indicated that water borne diseases continuous to be prevalent even in areas where there are existing tube wells. The problem is that, drinking tube well water will not necessarily protect health unless there is parallel health education and improvement in environmental sanitation and hygiene awareness. In water projects, there is ample evidence to show that unless water sanitation and hygiene education go together, the health impact of improved water facilities may be lost. This is the challenge that the Project will have to address and the CDS, together with the community, particularly women, will take the lead to ensure the proper use of water along with application of proper hygiene if improvement on health status will be achieved. Overall, the project is viewed as an initiative with a wide range of beneficial impacts. It will have major beneficial impact on the health and sanitation condition in the households and communities which would have positive impact on improving man-hours for productive endeavours and translate into savings in medical and health expenditure related to water borne diseases. Likewise, during construction period of piping and tap installation, the poor may directly or indirectly benefit. Civil works will create short-term job opportunities, and general promotion of economic activities will expand the job market in the longer term. Gender Issues and Mitigation
Issues Mitigation Measures 1. Certain categories of women are
excluded from access to water and participation, such as minority group, women headed households and very poor households.
Targeting and issuance of ID to particularly vulnerable women such as minorities and women headed households, to ensure access to water services. The ID will specify special rate for women headed households and IPs.
2. Special needs of women are not met Ensure accessibility by consulting with women to
Appendix 5 SOCIAL ASSESSMENT REPORT
61
such as; location, design of facilities, operating hours; bathing provision, laundry.
agree on location, design, operation hours, bathing provision and laundry area.
3. Involvement of women has been limited to domestic work, physical labor of hauling water, passive audience for health education; separate women’s project
Involve women in the operations in maintenance, collection, promotion of health messages. Use women as resource persons on health education, awareness creation Allow women to assume leadership roles. Encourage men to support community activities of women and efforts of women to promote hygiene and sanitation at home.
4. Workload has been increased by lack of assistance in water collection and voluntary labor for community related initiatives.
Community seminar on gender awareness must be initiated to raise level of awareness of men on the multi-roles of women in the home. Men should be encouraged to participate in seminars and support women, share in household’s tasks as well as in equal sharing of resources.
5. Loss of productive activities due to time spent on water collection and other domestic concerns
Linkages with NGOs to enhance productive capacity of women, to engage in income generating activities
6. Loss of access to improved water facility due to distance and cost of water
Participation of women in the selection site that will proximate water facilities to women.
2. Key Actions Measures included in the design to promote gender equality and women’s empowerment – access to and use
of relevant services, resources, assets, or opportunities and participation in decision-making. Various measures
are included to promote gender equality and women’s empowerment. A Gender Action Plan (GAP) has been
formulated to maximize project benefits especially for women who are responsible for water management in the
home. Women will be properly represented in various committees, including coordination committees in towns
and wards, and water and sanitation committees. Better infrastructure services will improve livelihood
opportunities for women. Efforts to reduce gender disparity in wages for work of equal value will be in place.
Women’s participation in local governance and community decision making will be improved. Provisions have
been made for gender and social development consultants, and a monitoring system will be in place.
To involve women create sustainable water system and reach the poorest, program on water must include or
linked to economic development and poverty reduction program. If the Project expects poor people, especially
women to pay for water, initiative to create opportunities for productive capacities must be incorporated as a
part of the Project framework.
Appendix 5 SOCIAL ASSESSMENT REPORT
62
Gender plan Other actions/measures No action/measure
III. SOCIAL SAFEGUARD ISSUES AND OTHER SOCIAL RISKS Issue Significant/
Limited/ No Impact
Strategy to Address Issue Plan or Other Measures Included in Design
Involuntary Resettlement
Limited impacts (a)The project is designed for minimal or no land acquisition and resettlement.
(b) A resettlement framework has been prepared to guide the development of Resettlement Plans (RP) for various potential reservoir sites.
(c) JICA Specialists will prepare the individual RPs.
Resettlement plans
Resettlement framework
Combined resettlement plan and indigenous peoples plan
Combined resettlement framework and indigenous peoples planning framework
Environment and social management system arrangement
Environment and social impact matrix
None
Indigenous People
No impact Indigenous peoples were not found in the project area.
Indigenous peoples plan
Indigenous peoples planning framework
Combined indigenous peoples plan and resettlement framework
Combined resettlement framework and indigenous peoples planning framework
Indigenous peoples plan elements integrated in project design with a summary
Environmental and social management system arrangement
Environmental and social impact matrix
None
Labor ___Employment opportunities __ Labor retrenchment __ Core labor
Limited positive impact
Employment opportunities will open for unskilled labor during construction.
Plan
Other action
No action
Appendix 5 SOCIAL ASSESSMENT REPORT
63
standards (CLS) Affordability
Significant impact particularly for extreme poor and poor households
Discussed already in details in PRS and social strategy and GAP.
,
Other Risks and/or Vulnerabilities __ HIV/AIDS __ Human Trafficking __ Others (conflict, political instability, etc). Please specify: ___
Not known Civil works contracts, though they are small in size, may become a channel of HIV/AIDs. KWASA and the civil contractors will minimize the risk through a relevant clause in the contracts and awareness-raising programs.
Plan
Other action
No action
IV. MONITORING AND EVALUATION Are social indicators included in the design and monitoring framework to facilitate monitoring of social development activities and/or social impacts during implementation? YES
Appendix 5 SOCIAL ASSESSMENT REPORT
64
Appendix 2 – Gender Action Plan
1. Introduction
It has been recognized that water and sanitation are issues for men, women and children. To have
effective water and sanitation program, men must also support and adopt improved hygiene practices.
In water project, contribution of time, labor and money should be shared fairly and not expected of
women alone. Training should also be equally divided. In this way, both men and women can benefit
and human resources will not be wasted.
Gender Action Plan (GAP) is formulated to provide measures to address issues concerning gender
equity and participation in the Project and enhance sustainability of such efforts. However, since
women’s involvement in water and sanitation springs logically from their traditional roles, they are often
the most disadvantaged and more affected. Thus, the GAP is formulated to maximize project benefits
for women. The GAP identifies the role of women in the project design, implementation, operation, and
maintenance. Women will be properly represented in various WUG and WSS committees and
organizations including coordination committees at wards levels.
2. Objectives of the GAP
The preparation of the Gender Action Plan (GAP) follows the framework of ADB Policy on Gender and
Development and Khulna WSS’s Gender Strategy and Action Plan. The objectives of the GAP are as
follows:
(vi) Increase participation of women in identification of location site for the tap stands,
planning construction, operations and maintenance and monitoring;
(vii) Increase time availability for livelihood opportunities/activities by women as less time
will now be devoted to access water for the households;
(viii) Ensuring reduced wage disparities between women and men for work of equal value
and effective application of core labour standards in Project related work opportunities;
(ix) Women’s effective participation in governance and community decision-making
processes and structures; and
(x) Improved gender awareness and capacity among the staff of KWASA, Khulna City
Corporation and the concerned wards.
3. Gender Issues and Concerns
The Consumers survey shows that there are various aspects of gender bias and discrimination in the
area of education, employment and income, household roles and decision-making exist in the Project
area. There is a higher proportion of female who are illiterate and functionally literate compared to the
male. In terms of educational attainment, the proportion of men and women who have obtained or
finished lower level of education appears to be equal primarily because of the national government’s
interventions; however, at the higher level, the gender disparity becomes apparent again: more males
have attained or finished Bachelor’s degree and/or post-graduate level than the females. In the area of
employment, the situation appears to be no better. While women constitute 48% of the total labor
force, only about 11% of the total is gainfully employed. The average annual income of female-headed
households is Tk46, 621 compared to the male-headed households, which is Tk65, 388. Accordingly, the
Appendix 5 SOCIAL ASSESSMENT REPORT
65
proportion of female-headed households (44.1%) who are below the poverty threshold is very much
higher than the male-headed households (27%). On decision-making at the household level, the male is
primarily responsible, except in female-headed households. But even there, the female head has to
often consult with the male adult member of the households on major decision areas such as children’s
education, or type of work to be engaged in, choosing marriage partners for children.
Water collection and water/sanitation management at the HH and community levels are the traditional
roles of women in the country. Women are the ones who obtain water for the home, store it and
manage it. Women are usually the guardians of household hygiene and maintaining health care of
children. Time spent for domestic households as well as in doing other income generating activities puts
so much pressure on the multi tasks done by women. Because of this gender role and expectation,
women had become more vulnerable to health risks imminent due to hygiene and sanitation resulting
from the water supply and sanitation situation in the households and the community. They endure the
high possibility of getting sick due to higher exposure to contaminated water and other water borne
diseases. Their access to latrines and other sanitation facilities is often inhibited because of the gender
insensitivity to the construction and management of such facilities.
The SPA findings indicated that status of women in the Project area is generally similar to the status of
their national counterpart. The females have equal chances of being schooled at lower level; however at
higher level though, men generally obtain higher education than women. Overall, the proportion of male
household members out of total males having attained university level is higher than the proportion of
female members.
In term of employment, of the total employable male, 52 % is employed while only 48% of the total
employable females are actually employed. However, if one looks at the contribution to total household
income, the proportion of women contributing is almost equal to that of the men. It would appear that
while in comparison to the male counterpart the percentage of women who are employed is low, still an
almost equal proportion are gainfully occupied (e.g., operating small business and not reported as
employed) and contribute to the total household income. Cost of water is often taken from women’s
earning as always being left at home while men are at work. Per Consumer Survey data, women headed
households included in the survey appear to fare better than their male counterpart. Women in the
urban households have equal voices in decision-making. However, in the wards and community
administrative system, women’s role appears to be limited by cultural/religious attitude. Efforts had been
undertaken to address such imbalance and now the UPPRP reports showed that 90% of women are
members of the CBC and are making major decision in community affairs. A number of NGO and
development agencies’ community based project also affirmed that women are often the chairs and/or
manager of the program activities especially if these programs are concerned with health, sanitation and
or microcredit and supplemental livelihood activities. This would tend to reflect the reality in the field
that the men are normally busy in formal livelihood and income generation activities for the households
and it is the women are available to attend to these other community related activities.
In the predominantly Muslim country, the women’s role in the households and communities is pretty
much defined by religious and cultural/social expectations unlike their counterpart Hindu women.
However, the women in the urban areas as in KCC reveals to have better access to social infrastructure
and services than their rural counterpart as the households generally live in more urbanized location
where the infrastructure and services are concentrated.
While both women and men are more likely to benefit from the planned WSS upgrading, the Project has
Appendix 5 SOCIAL ASSESSMENT REPORT
66
the potential to contribute to the general wellbeing of women especially of poor households in the slum
and low-income areas. Women and girls who are usually the ones responsible for obtaining water from
various sources sometimes far from their place of domicile will now have easier time. Women in the low
income and slum communities are also more likely to have increased health benefit due to improved
availability of safe water. Furthermore, women of poor households will be empowered through
participation in Project planning and decision-making, capacity building interventions and access to
project related employment opportunities.
Adverse impacts and risks from Project related activities faced by women are deemed not
significant; nonetheless, during Project implementation if there are unforeseen risks identified, proper
measures will be undertaken for their mitigation. The table below identifies some gender issues and the
corresponding mitigation measures.
Gender Issues and Mitigation
Issues Mitigation Measures
1. Certain categories of women are
excluded from access to water and
participation, such as minority group,
women headed households and very
poor households.
Targeting and issuance of ID to particularly
vulnerable women such as minorities and women
headed households, to ensure access to water
services. The ID will specify special rate for women
headed households and IPs.
2. Special needs of women are not met
such as; location, design of facilities,
operating hours; bathing provision,
laundry.
Ensure accessibility by consulting with women to
agree on location, design, operation hours, bathing
provision and laundry area.
3. Involvement of women has been limited
to domestic work, physical labor of
hauling water, passive audience for
health education; separate women’s
project
Involve women in the operations in maintenance,
collection, promotion of health messages.
Use women as resource persons on health
education, awareness creation
Allow women to assume leadership roles.
Encourage men to support community activities of
women and efforts of women to promote hygiene
and sanitation at home.
4. Workload has been increased by lack of
assistance in water collection and
voluntary labor for community related
initiatives.
Community seminar on gender awareness must be
initiated to raise level of awareness of men on the
multi-roles of women in the home.
Men should be encouraged to participate in
seminars and support women, share in
household’s tasks as well as in equal sharing of
resources.
5. Loss of productive activities due to time
spent on water collection and other
domestic concerns
Linkages with NGOs to enhance productive
capacity of women, to engage in income
generating activities
6. Loss of access to improved water facility
due to distance and cost of water
Participation of women in the selection site that
will proximate water facilities to women.
Appendix 5 SOCIAL ASSESSMENT REPORT
67
4. Practical Steps to enhance gender roles in KWASA Project
Overall, the GAP objectives aims to maximize benefits derived from the project and enhance
participation of both women and women in the planning, implementation, operation and maintenance
of the project.
a) Local intervention and support
Men and women’s involvement should begin during the first stage of the project process. If not included
at this point, it is more likely that they will be excluded at later stage as well. It is also effective to involve
them in decision making about appropriate technology and suitable location to benefit primary users
who are women. Contact of male leadership for understanding and support for women’s involvement
increases the chance of increasing more women to participate in community initiatives and other
projects.
b) Implementation of national policy agenda on gender concerns.
The implementation of national policy on gender concerns must be enforced to continuously protect
women’s interest. The participation of women in various project activities (data collection, selection of
technology, project site, etc) will be greatly enhanced when they have the support of men and women
in higher levels from field staff to managers and decision makers at the regional and national level.
Women’s involvement in the water sector could create a crucial impact on project sustainability. For
instance consideration of women’s demand and willingness to pay for piped water or particular type of
water system could raise the level of increased coverage since they are the ones who are the prime
users of water.
c) Facilitation for women to participate in project meetings
Women will be encouraged to participate and facilitate meetings. They will be tasked to organize time
and place of meeting, prepare invitations, make appropriate sitting arrangements, choice of resource
person and conduct separate meetings with women where needed.
d) Involvement of women in planning and decision making
Men and women should be represented equally (at least 50% men and 50% women) in the planning and
in deciding as to:
• Choice of caretakers or electing the WUG officers
• Design and location of facilities
• Local management arrangements
• Local financing scheme
In particular, women will be allowed to choose their own representatives for trust, ease of contacts and
leadership capacities. They will also be encouraged and allowed in higher level committees.
e) Expansion of traditional tasks and responsibilities of women’s roles in the Project
Expansion of traditional domestic roles of women need to consider other tasks such as management of
water, maintenance and repair of water points, hygiene education with fellow women, collection of
tariffs and management of funds. Appropriate training will be provided to effectively manage these
tasks.
Appendix 5 SOCIAL ASSESSMENT REPORT
68
Experience with women in maintenance roles indicates that while some costs may be higher (due to
more demand for training) their effectiveness in regular and preventive maintenance is better than
men’s and costs of repair become lower since women are more meticulous when it comes to care of
facilities.. However negative impact resulting from women’s involvement needs to be considered as
reduced women’s time in water collection create new demands for work related to maintenance,
management and financing.
f) Linkage of water project with capacity building and income generation and employment
Benefits derived from improved water facilities such as time and energy gains may be applied to a
variety of activities such as home gardening and food production for sale. Linking support with other
NGOs which can provide micro-credits and training on business development could widen women’s
potential to contribute to household income and this has an impact on poverty reduction. Benefits from
increased earnings for women resulting from construction employment will be optimized where KWASA
and the concerned ward/community officials will ensure that:
• Contracts will specify the maximization of use of local labour;
• Workers will be paid the legal wages; Contractors will be given orientation on jobs specification
and hiring to include women.
• Child labour will not be used for construction and maintenance activities;
• Employment targets for members of poor households and women will be set to include at least
30% women;
• No differential wages are paid between men and women for work of equal value; and
A specific clause is placed in bidding documents that compliance will be strictly monitored during Project
implementation.
g) Conscientization and training of project staff and management on gender sensitive
awareness and programming
Special attention will be paid to the design of messages and the method of communication to ensure
that women receive the intended Project messages. Places frequented by women, household level
messaging and focus groups will be organized to disseminate information about the Project. The role of
project staff is crucial in the awareness campaign and promotion of women’s concerns and practicalities
of women’s involvement in the water project.
The initial step is to conduct seminars and workshops to discuss gender related issues and involve key
leaders to address women’s’ concerns and involve women in the project cycle. The above training has
been included in the capacity building program of the Project.
h) Strengthening Organizational/Management Capacity of WUG
To further ensure sustainability of development efforts and management capacity of the WUG, various
seminars and workshops will be designed to focus on the following skills:
Appendix 5 SOCIAL ASSESSMENT REPORT
69
Table 1: Training Plan
5. Institutional and Implementation Mechanism
Implementation of the GAP will be the primary responsibility of KWASA with the Community
Development Organizers undertaking gender related concerns at the zonal level mainly responsible for
its execution.
KWASA could utilize the current social structure already organized at community level by UPPRP. There
are currently 239 Community Development Committees (CDCs) that have been organized and
undertaking several community development initiatives, including water management. The Project
could linked with the CDCs and strengthen this existing group to undertake responsibilities related to
water management and initiatives to enhance the productive capacities of women. The advantage of
using the current CDC structure is that adequate training on capacity building has been provided and
75% are represented by women. It is expected that the CDC will continue to be self reliant and
functional even after UPPRP or the KWASA CDOs have exited from the project.
An initial consultation with UPPRP affirmed their interest to establish linkage where appropriate. Areas
of cooperation have been seen towards providing funding to poor households, especially women, on
pipe connection from the house to the communal tap water. Other initiatives for cooperation include
capacity building and income generating activities.
To involve women create sustainable water system and reach the poorest, program on water must
include or linked to economic development and poverty reduction program. If the Project expects poor
people, especially women to pay for water, initiative to create opportunities for productive capacities
must be incorporated as a part of the Project framework. A strategy to incorporate poverty reduction
program is attached as Appendix 1.
Costs to undertake the activities under the Plan have been provided in the business plan of the project
which includes capacity building and communication awareness campaign.
Type of Training/Activities Skills Development Participants
Self awareness Gain self confidence and image Members of WUG
Gender Sensitive Planning Ability to prepare and implement plan
the GAP, and address gender issues and
concerns
Members
Collection, simple bookkeeping and
Recording
Ability to collect and maintain keep
records of account
Representative –
WUG
Problem Solving Process/Decision Making Ability to resolve community issues and
make right decision
WUG members
Water management, maintenance and
operation, M and E
Ability to manage, operate, maintain,
monitor and evaluate project results
WUG members
Enterprise Development and Project
Management
Ability to manage small scale income
generating activities
Low-income women
Field Exposure Ability to apply lessons learned and
replicate to current situation
WUG members
Appendix 5 SOCIAL ASSESSMENT REPORT
70
6. Monitoring and Evaluation
Plan implementation will be monitored regularly with indicators incorporated as part of the Project M&E
framework.
Table 2: Monitoring and Evaluation Framework Component Activities Main
Responsibilities
Target group Indicator Time Frame
Ensuring Safe
Water Access to
Poor especially
women-headed
households
Identification and selection criteria of
target beneficiary households in slum and
low income areas will ensure inclusion of
women headed households:
i) KWASA and NGO will ensure that
criteria incorporates indicators to id
and qualify women headed households
ii) Women headed HH will be ensured
membership in the Water User
Association and will not be excluded
from being an officer of the
Association
iii) KWASA and NGO will ensure
that women are provided and included
in the capacity building program of the
Project.
KWASA Social
Development
Group
Contracted
NGO
Project
consultants
Development
agencies
Women in
general and
women
headed
households
in the slum
areas of
KWASA
service
coverage
areas
Number of indicator
in the selection
criteria that are
women friendly
% of women who
are members of the
WUA
% of women who
are officers of the
WUA
% women headed
HH who are
connected to
KWASA water
system
% of women WUA
who are provided
training
% of women who
are referred to
micro lending
project and
provided credit and
engaged in income
generating project
2011-2015
Institutional
Strengthening and
Capacity Building
Women’s effective participation in
governance and community decision-
making processes and structures will be
strengthened
i) KWASA and NGO will enhance women’s
capacity to manage WSS activities at HH
and community level through training
interventions
ii) KWASA and NGO will ensure women
participation in O&M and monitoring
activities of the Project
iii) Women will play a more active role in
water supply management program
(i) KWASA and NGO will develop
leadership skills of women and allow
them to take leadership role in the
community
KWASA
NGO
Project
consultant
Development
Agencies
Women in
the target
communities
Female staff
of KWASA
and ward
offices
Community
development
organizations
Number of women
trained and active in
WS management
activities
# of women staff
hired by KWASA
involved in technical
and management
activities
#No of women
occupying
leadership roles in
the community and
project
management
Public Awareness
and Information
Campaign on
KWASA program
Ensure all the campaign messages are
gender friendly:
i) Media and messages will be formulated
to be gender sensitive in the context of
Bangladesh society
ii) Delivery of messages will ensure that
women are reached appropriately
without any bias and interference due to
gender role and religious/social
restrictions
KWASA
NGO
Project
consultant
Development
Agencies
Women in
the
community
Women friendly
messages
developed and
disseminated
2011 – 2017
Enhancing This strategy will involve identifying poor KWASA Women in # of women trained 2011-2017
Appendix 5 SOCIAL ASSESSMENT REPORT
71
Component Activities Main
Responsibilities
Target group Indicator Time Frame
Productive
capacities of
women
and extreme poor households, poor
headed households to link institutional
support with income generating
activities.
Social Development Specialist will tap
local resources (NGOs) for skills
development, credit assistance and
project management training.
NGO
Community
Development
Specialist
Development
Agencies
the
community
WUG
CDCs
in IGP
# of women
engaged in IGP
% of income raised
7. Budget Requirement
The following costs will be entailed in the implementation of the GAD.
a.) Capacity building –this will involve raising knowledge and developing skills and capacity of
women to participate in decision making, resolve community conflicts, undertake water
management. The training plan and budget is provided below. Overall cost for capacity building
is estimated at Taka 2,244,970 (US$32,071).
Table 3: Budget for Capacity Building - GAP
b) Exposure Trips
Field exposures to successful water project will be initiated for the WUG and women members to visit
community-based projects managed by women. . Some of these water projects are currently
implemented by UPPRP (UNDP). This will allow members of the WUG to assess by themselves what
learning experiences can be replicated for their group. The budget cost for this activity is estimated at
Tk 250,000 (US$3,571).
No of
No
of Budget
No Training /Activity PAX days Food Allowance Venue Materials Total
1 Self Awareness
1,734
1
693,600.00
173,400.00
15,000.00
121,380.00
1,003,380.00
2
Gender Sensitive
Planning
624
2
249,600.00
124,800.00
15,000.00
43,680.00
433,080.00
3 Simple bookkeeping
289
1 57,800.00
28,900.00
15,000.00
20,230.00
121,930.00
4
Problem Solving
Process
578
1
115,600.00
57,800.00
15,000.00
40,460.00
228,860.00
5
Operations and
maintenance
578
1
115,600.00
57,800.00
15,000.00
40,460.00
228,860.00
6
Monitoring and
Evaluation
578
1
115,600.00
57,800.00
15,000.00
40,460.00
228,860.00
Total in Taka
4,381 7
1,347,800.00
500,500.00
90,000.00
306,670.00
2,244,970.00
Total US Dollars 19,254.29
7,150.00
1,285.71
4,381.00
32,071.00
Appendix 5 SOCIAL ASSESSMENT REPORT
72
c) Gender Awareness Workshop and Information Campaign
An important consideration in this activity is to raise the commitment of the Project Staff, Planners,
NGOs, GOs and other social institutions on the critical role of women in development initiatives such as
water projects. Information campaign through the use of mass media and information materials will be
utilized to sensitize the public on gender issues and concerns and how to address them. An estimated
budget for this activity is estimated at Taka 1,200.000 (U$ 17,142). The activity shall be undertaken
regularly at community level at least once every quarter r within a period of 3 years.
Overall, the total cost to implement the GAP is estimated at Taka 3,694,970 (US$52,785).
Appendix 5 SOCIAL ASSESSMENT REPORT
73
GENDER ACTION PLAN – IMPLEMENTATION TABLE
Activity / Objectives Indicators/Targets Responsibility Time
Schedule
1. Ensuring Safe Water Access to Poor especially women-headed households
• Develop effective mechanism to ensure increased female involvement.
• Identification and selection criteria of target beneficiary households in slum
and low income areas will ensure inclusion of women headed households:
• KWASA and NGO will ensure that criteria incorporates indicators to id and
qualify women headed households
• Women headed HH will be ensured membership in the Water User
Association and will not be excluded from being an officer of the
Association
• KWASA and NGO will ensure that women are provided and included in the
capacity building program of the Project.
• Referral of women to NGOs for income generating opportunities
• Women in general and women headed
households in the slum areas of KWASA
service coverage areas
• Number of indicator in the selection
criteria that are women friendly
• % of women who are members of the
WUA
• % of women who are officers of the WUA
• % women headed HH who are connected
to KWASA water system
• % of women WUA who are provided
training
• % of women who are referred to micro
lending project and provided credit and
engaged in income generating project
KWASA Social
Development
Group
Contracted NGO
Project
Consultants
Development
agencies
2011-
2015
2. Institutional Strengthening and Capacity Building
• Women’s effective participation in governance and community decision-
making processes and structures will be strengthened
• KWASA and NGO will enhance women’s capacity to manage WSS activities
at HH and community level through training interventions
• KWASA and NGO will ensure women participation in O&M and monitoring
activities of the Project
• Women will play a more active role in water supply management program
• KWASA and NGO will develop leadership skills of women and allow them to
take leadership role in the community
• Women in the target communities
Female staff of KWASA and ward offices
Community development organizations
KWASA
NGO
Project
Consultant
Development
Agencies
2011-
2017
Appendix 5 SOCIAL ASSESSMENT REPORT
74
Activity / Objectives Indicators/Targets Responsibility Time
Schedule
3. Public Awareness and Information Campaign on KWASA program
• Ensure all the campaign messages are gender friendly:
• Media and messages will be formulated to be gender sensitive in the
context of Bangladesh society
• Delivery of messages will ensure that women are reached appropriately
without any bias and interference due to gender role and religious/social
restrictions
• Women in the community
• Women friendly messages developed and
disseminated
• Women's participation in WUA-financed
training and capacity development programs
[target: 75% participation]
KWASA
NGO
Project
Consultant
Development
Agencies
2011-
2017
4. Enhancing Productive Capacities of Women
• This strategy will involve identifying poor and extreme households, poor
headed households to link institutional support with income generating
activities and or employment
• Social Development Organizers will tap local resources (NGOs) for skills
development, credit assistance and project management training.
• . Women in the community
• # of women engaged in IGP
• Increased earning capacity by at least 10-15%
• # of women given skills training
• # of women utilizing training given
• # of women referred for employment
•
KWASA
NGO
Project
Consultant
Development
Agencies
2011-2017
5. Participation of Women in Project Implementation
• Ensure women's participation in all consultative processes and structures for the
prioritization of plans and decision-making.
• Ensure equal job opportunity for female workers in the project
• Women in the community
• Number of women in attendance and
actively participating in meetings
• Type of activities that women are involved
in
KWASA
NGO
Project
Consultant
Development
Agencies
2011-2017
Appendix 5 SOCIAL ASSESSMENT REPORT
Appendix 3 – Consultation and Participation Plan
1. Definition and Background
There is a general awareness and recognition on the importance of community participation in the
implementation of water and sanitation initiatives. Over the years, the community has now emerged as
an operative factor in Bangladesh’s water and sanitation development program. User groups and
caretakers, by their financial contribution and their knowledge of how things are supposed to be done,
have become an integral part of the programme’s sustainability.
How is community participation defined within the context of the KWASA project?
In its simplest definition, participation means, readiness of the government (KWASA), private sectors,
NGOs, and the target communities to accept responsibilities. The contribution of each is recognized,
utilized and appreciated.
In regards to the readiness, both the government, private sectors, NGOs and the community have
worked together for a long time. Currently, there are a number of NGOs operating in the area that
provide support on water and sanitation projects to underpin other income generating and health
related schemes. An impressive example of collaboration with a private organization is provided by the
Grameen Bank – an institution set up to improve the standard of living of Bangladesh’s poorest group.
Grameen offers collateral-free assistance to rural poor for productive enterprises such as dairy cow
fattening and poultry raising.
With regards to government sector, the Local Government Engineering Department (LGED) through its
program Urban Partnership for Poverty Reduction (UPPR) Project has successfully initiated a community
participatory model which has been implemented in 31 wards of Khulna. To date, UPPRP has
established 239 Community Development Centers (CDCs) covering the entire KCC. Observation and
interviews conducted at field level among CDCs revealed that the enthusiastic participation of the
beneficiary communities contributed greatly to the achievement of a sustainable impact of the UPPRP
program.
On the other hand, the community, through the development programs carried out by the government
and NGOs instituted community based management program such as poverty reduction program, and
health and sanitation. Communities have demonstrated enthusiastic re Communities have succeeded in
identifying their own resources, and develop initiatives that respond to their immediate and long term
needs.
The KWASA Project requires strong advocacy, institutional support and community participation to
sustain its developmental objectives. Since the target communities are ultimately the water users and
will pay for water services, it is expedient that appropriate community organization, social mobilization
and marketing must be undertaken before and during its implementation.
This document provides the framework for the participatory process and activities in the
implementation of the KWASA Project. The Community Participation Plan, together with the Poverty
Reduction Strategies and Gender Action Plan will institutionalize and internalize the beneficiary driven
approach for sustainable social development interventions particularly for the women members of
households, poor households and low income households in slum areas.
Appendix 5 SOCIAL ASSESSMENT REPORT
2. Objectives
The objectives of the participation strategy are to:
1. Increase access of the community to the KWASA water supply pipe system, particularly the
vulnerable groups, the poor and women-headed households;
2. Help maximize the impact and effectiveness of the water project;
3. Create a sense of responsibility and ownership of the project;
4. Develop potential for long term sustainability;
5. Address and support other developmental needs such as health and sanitation and poverty
reduction.
3. Mechanism for Participation
The community participation strategy involves 3 phases with various sets of running activities which
shall be undertaken at different stages of the project cycle. This CCP shall be implemented within a
period of three years, from 2011-2013.
3.1 Pre-Implementation-Social Preparation Phase ( Bridging Period 2011 -2012)
The social preparation phase shall begin at the early planning stage, during the bridging period (9
months) to bridge from between the conception of the project and its implementation. The social
preparation phase will take about 6 months to undertake the series of activities.
Key Activities
1) Establishment of a functional Community Relations Office
The establishment of a Community Relations Office (COMREL) is essential to serve as focal point and
orchestrate community development participatory activities in the field and managing problems, issues
and concerns of the community. This office shall be under the supervision of the Customers Relation
Office planned under the proposed organizational structure of the KWASA. The COMREL shall include
among others a Community Development Specialist and a Gender Specialist who will be responsible to
manage day to day activities at the community level. They will also identify community volunteers of
facilitators who will assist them in the field. A community action plan with specific activities shall be
prepared by the CDS before the formation phase.
2) Identification and targeting of poor households
The Community Development Specialist shall conduct social investigation and careful analysis of the
specific needs and problems in target Wards, including identifying of potential community volunteers
who will assist in the participatory activities to be initiated. Main activities shall include:
(i) Mapping, identification and listing of extreme poor and poor households;
(ii) Identification of NGOs and social organizations present in the area to accurately address the
specific needs of the poor;
(iii) Identification of community resources such as man power, location of water points, etc.
Appendix 5 SOCIAL ASSESSMENT REPORT
3) Creation of a data base information
Data base information (consumers’ data) will be established especially on vulnerable families.
Disaggregation of gender data shall form the data base with relevant information on income and skills of
households.
The use of the criteria established by the UPPRP would be useful in identifying the poor. These criteria
are as follows:
o. .More than 6 people dependent on one earning member
p. Has 3 children of less than 5 years old
q. Child labour of less than 15 years age works for full day
r. Age of family’s main income earner is more than 60 years
s. Female headed households
t. Have disabled family member
u. Suffering from prolonged ailment
v. Have drug addicted member of the family
w. All family members above 16 years of age are illiterate
x. Have school age children but not going to school or is a drop out
y. Lack of access to safe drinking water
z. Lack of access to sanitary latrine
aa. Live in hut (made of hay, thatch, polythene). Continuously afraid of eviction.
bb. Culturally or socially isolated family.
A household will be considered extremely poor if any of 6 out of 14 criteria are met. A household can be
considered as extreme poor even if only one of the following criteria “a”, “d” or “f” is met.
4. Conduct of Planning Workshops
A major feature of PRS is enabling the community and ward officials to plan and implement the WSS in a
participatory manner with the participation of beneficiary households, NGOs, and women. Planning will
involve the formulation of strategies to ensure access of WSS services and benefits of the Project by the
poor households in the slum and low-income areas of the wards under the service coverage of KWASA
groups. To sustain affordability and sustainability of services strategies will be pursued involving
employment provision, capacity building including improving WSS O&M which eventually can lead to
income generation/income enhancement and monitoring activities especially related to leakage
detection and reporting and illegal connection reporting.
One of the initial activities of the group is to identify the central location of the water tap for the
association and the manner and procedure for ensuring management and control of the system.
Identification of roles and responsibilities and accountabilities will have to be agreed upon. Another
important issue that will have to be decided at the outset is the amount of monthly due to be paid by
each member household considering the amount required to pay for the bulk water from KWASA and
some minimal amount required to ensure the viability of the community organization (i.e., payment for
maintenance of the communal tap and some minimal stipend for community members working for the
association).
Appendix 5 SOCIAL ASSESSMENT REPORT
5. Project Information and Dissemination
One of the key elements of the participatory approach is the intensive program of communication
activity to enhance water, hygiene and health awareness. A whole new range of promotional literature
and visual aids will be incorporated in water, sanitation, hygiene and health promotion messages. These
will be produced both for use in training programs and among user groups. Messages on flyers, posters,
and leaflets must be kept simple but with impact: for example: “Conserve Water”. “Water is life”.
Coordinated efforts with mass media and the academe will also be done to include right use of water
and health messages as part of health education in schools.
KWASA staff together with the Program Consultants and the COMREL and the KCC officials/staff at the
ward level as well as the WUGs and Ward Water Supply and Sanitation Committees (WWSSC) will work
closely with the local officials to undertake a marketing/information campaign on the new program of
KWASA on WSS. The communication materials and strategy developed by Consultant Specialists will be
utilized.
This activity shall be undertaken within the next 6-9 months as preparation for the community’s
acceptance on the upgrading of the system which shall comprise of series of training seminar and
educational campaign
3.2 Implementation Phase – Community Mobilization (2012-2013)
This phase will involve Community Development Specialist (CDS to immerse themselves in the field with
the poor to gain their confidence and to form groups to analyze the information collected, and identify
key issues and areas where support is needed. At this stage, the CDS also shall initiate and promote the
project by raising the level of awareness on the importance of and use of safe water, thereby motivating
the people to consider the best option. Discussion will also revolve around the community’s
responsibilities in the water project.
Key Activities
1) Organization and training of Water User Groups
Once the community interest has been mobilized, this must quickly be crystallized into a formal
mechanism usually formed through which communities are encouraged to take small steps to improve
their own condition. It is imperative that this action spring from their own ideas.
Water User Groups and Committees will be organized in low income and slum areas adjacent to KWASA
water supply lines in 12 identified wards of Khulna City Corporation. The Water User Group will be
composed of 10-15 households proximate to each other and they will elect their officials who will be
responsible for directing and managing the activities of the group. The Group Chair and Secretary will
represent the community WUG in the WSS Committee to be organized in each concerned ward under
KWASA service coverage.
A WSS committee will be composed of about 10 WUG. There may be more than one WSS committee in
a ward if there is a substantial number of WUGs due to the high number of low income households in
the ward. The WSS committee shall include members of ward officials, NGO and similar development
workers especially in the water and sanitation section to provide technical support to the WUG member
Appendix 5 SOCIAL ASSESSMENT REPORT
representatives. Their primary task is to ensure the successful planning and implementation of
measures to address concerns of water and sanitation concerns in the concerned service area.
2) Establishment of Complaints and Response Mechanism at the Ward Level
While KWASA will ultimately be responsible for addressing complaints of customers, the participatory
mechanism will provide a mechanism where at ward WSS committee level, complaints re service,
leakages, billing and other customer relation matters, could first be heard and possibly mitigated. If the
WSS Committee is unable to provide a solution, the complaint would then be referred to the KWASA
zonal team (SocDev/ComDev Specialist) for appropriate action.
3) Training of WUG Committees in Operation, Maintenance and Monitoring Activities
The WUG will be responsible for collection of monthly dues from individual members and remittance of
payment of the monthly bill to KWASA.
Pipe leakages, damage to the communal tap as well as illegal connection will be monitored at
community level and reported to KWASA through an established system.
The WUG elected officers will be responsible for record keeping, updating and maintaining the books of
account for regular reporting to the members. The Project Community Development Specialist will
provide the appropriate trainings to the WUG officials.
a) Site selection
Community involvement in the installation of water services should start at site selection, an area often
fraught with conflict. A communal tap water may end up on a private property, access to which can be
controlled by land owner. The number of new communal tap water facilities in each union would be
decided at the Thana level, but the actual sites would be decided by the users group.
b) Selecting the caretaker
Members should decide who among themselves should be the caretaker. The WUG should also comply
themselves to the conditions governing the installation of the communal tap water facility, including site
selection criteria. The FGD participants established minimal guidelines in the selection of WUG
representatives:
• Selection of representative must have a mutual consent by the group.
• Ward Councillor can select a representative with the consent of community;
• CDC, UPPRP can select representative from beneficiaries.
c) Collection of water fees and maintenance
The WUG will be responsible for collection of monthly dues from individual members and remittance of
payment of the monthly bill to KWASA. As suggested by the FGD participants, the WUG elected officers
will be provided with training on maintenance of the facility, book keeping and collecting bills. The WUG
elected officers will be responsible for record keeping, updating and maintaining the books of account
for regular reporting to the members. The Project Community Development Specialist will provide the
appropriate trainings to the WUG officials. This would require trust and confidence on the part of
KWASA to consider this activity.
Appendix 5 SOCIAL ASSESSMENT REPORT
d) Monitoring and evaluation
Community based monitoring will be organized by the CDO per WUG. The use of the monitoring
instrument as provided in this document will be used to monitor progress and achievements.
Monitoring inequity
In order to avoid inequitable sitting, the site selection committee which will be formed by the WUG,
must ensure that caretakers and users has the full appreciation of the public nature of the service.
Distance criteria must be set to ensure a more even spread of the water facility coverage. The criteria
for positioning must include a convenient distance from all prospective user families as well as public
health consideration and local hydrological conditions. It is suggested that no family should be farther
away than 250 yards away from the facility.
Pipe leakages, damage to the communal tap as well as illegal connection will be monitored at
community level and reported to KWASA through an established system.
5.3. Sustenance phase - 2013 – year end
This phase will mark the evaluation progress as well as providing intervention to sustain efforts of the
WUGs including developing strategies that will improve operation. Gradually, the intervention will be
minimized but paving the way for the assumption of more active involvement of community volunteers,
NGOs and other support groups.
1) Coordination and Linkages
Coordination activities with existing support groups shall be done by the CDOs to link economic
development with the skills and needs of LIH, particularly women. This activity will involve mobilizing
other support groups to address immediate as well as long term needs of the community which can be
link with existing program of NGOs. The training programs will most likely provide specific skills to
community members on income generation, credit assistance, etc.
2) Institutionalization
The mainstreaming of community participation in the KWASA project requires policy support to
institutionalize the approach. The CP model will be implemented along with the GAP and the PRS to
maximize its benefits. A handbook or manual on participatory process needs to be prepared to guide in
its implementation. The Manual will serve as a model not only for this project but for other
development projects in the future.
The UPPRP CDC model provides a participatory approach which can also be adopted in the design of the
KWASA participatory plan. An advantage of using the CDC model is that, there is already an established
guidelines and social structure in place within 31 wards of KCC. The CDCs have also acquired sufficient
training and 90% of the members are women representing the poor families.
As potential partner in the implementation of the CPP, The UPPRP has likewise signified their interest to
become partners with KWASA in the community based management of water project, in line with
UPPRP’s poverty reduction program. Specific area of assistance is specified on the provision of water
line connection from the house of poor families to the water network. UPPRPs initiatives will certainly
match with the features of the PRS which is to ensure access of WSS services and benefits of the Project
by the poor households in the slum and low-income areas of the wards under the service coverage of
KWASA groups.
Appendix 5 SOCIAL ASSESSMENT REPORT
To sustain affordability and sustainability of services, strategies will be pursued involving employment
provision, capacity building including improving WSS O&M which eventually can lead to income
generation/income enhancement. This can be effectively achieved through partnership with existing
social institutions as well as with other NGOs as partner in development initiatives.
6. Components of the Participation Strategy
6.1 Capacity Building
The ability to access resources is closely linked to one’s capacity to assert rights. The poor are often
passive role-players against other more powerful interests. To provide and increase the capacity of
vulnerable group to effectively claim and defend their rights, define and solve their problems the
program will equip the poor, women and ethnic minority households with proper tools and knowledge.
To ensure that the community obtains efficient and equitable service from the delivery system requires
a process of delicate fine tuning of responsibilities, including maintenance and operations. This in turn
also requires that more knowledge about water and dirt as sources of diseases is disseminated within
the user group, extreme poor, poor and non poor alike. The existing demand for safe water cannot be
transformed into better health unless users fully understand the health protective applications of these
amenities and implement them accordingly. This would require developing the capacities and skills
6.2 Education and Awareness Creation
One of the key elements of the participatory approach is the intensive program of communication
activity to enhance water, hygiene and health awareness. A whole new range of promotional literature
and visual aids will be incorporated in water, sanitation, hygiene and health promotion messages. These
will be produced both for use in training programs and among user groups. Messages on flyers, posters,
and leaflets must be kept simple but with impact: for example: “Conserve Water”. “Water is life”.
Coordinated efforts with mass media and the academe will also be done to include right use of water
and health messages as part of health education in schools.
The development of mechanism for community participation involving women in particular as the prime
haulers and users of domestic water supplies must be streamlined with the development of linkages
between sanitation, health education and water supply capitalizing on the popularity of water supply to
create demand for sanitation and advance the prospect of health impact
6.3 Sustainability Mechanism
Aside from need for water, communities has needs and problems but have limited options due to lack of
access to funds or local resources. In many ways, their lack of access or skills to access the resources
place them at a disadvantage. For basic services and other support to reach the communities especially
the low-income group, there is a need therefore for external resources to be made available, to link
demand with present skills. This can be complemented with manpower support (community organizer)
to guide user groups and low income households to gain access to other form of productive activities
that will improve their economic welfare and sustained community activities.
Appendix 5 SOCIAL ASSESSMENT REPORT
The involvement of an NGO or UPPRP is needed for coordinative efforts and sharing of resources. There
are a number of NGOs operating in the area that provide support on water and sanitation projects to
underpin other income generating and health related schemes.
NGOs have grown to a level where today they are an accepted feature of the administrative landscape.
Because of the special character that places them somewhere in between the public and the private
sectors, NGO partners are of great importance in helping to reach the twin goals of universal water and
sanitation coverage towards health for all.
6.4 Consultation and Participation Activities
A summary of the participatory process that will be employed by the project is summarized in the Table
below.
6.5 Timeframe and Budget Requirement
The Community Participation Plan shall be implemented within a period of 3 years. The budget has been
included in the Business Plan which includes support for training, and management.
Appendix 5 SOCIAL ASSESSMENT REPORT
Table 4.1 Participatory Framework in KWASA
Activity Task Time Frame Stakeholders
/Responsibility
Expected
Output
Remarks
Pre-Implementation Phase – Social Preparation
1. Establishment of a
functional COMREL
Office
+ Hiring of Personnel
Social Development
Specialist and Gender
Specialist
2011 (mid
year)
KWASA, Focal
point/person in
place
This would
require at
least 6
months
2. Identification and
Targeting of poor
households
Census of poor
households, issuing of
IDs
FGDs
Surveys
2011 Social Dev
Specialist
Gender
specialist
Ward level
communities
prospective
KWASA
customers for
connection to
water supply
system secured
3. Create Data base
Information Profile
Profile of households
Gender disaggregation
of data
2011 KWASA
Social Dev
Specialist
Gender
specialist
Ward level
communities
Data base
information in
place
Requiring IT
person to
manage data
base
Implementation Phase – Social Mobilization
1. Project Information
Dissemination
Development of
information materials
Flyers
Information campaign
via mass media, radio
Social marketing and
information campaign;
2011 – 6
months
Potential
customers, local
citizens of KCC,
commercial
customers
Improved
program of KCC:
issues on billing
rates, water
quality & qty,
O&M,
monitoring &
reporting
Should be
conducted
before
COMDEV
and
marketing
activities
2. Community
mobilization
Formation of
Water User
Groups(WUG)
Community organizing
Coordinating with CDC
Formation of
Community
Volunteers
CDCs
Poor
Households
Organization of
water user
groups and WSS
committees at
ward level in
place
Utilize
current CDC
organized
and
developed
by UPPRP
3. Coordination and
Linkages with
other institutions
Identification of NGOs
Link water with other
initiatives
Skills training
Capacity building
Income generation
Referral of Poor
households to
2011-0nwards NGOs
Private Sectors
Government
Funding
Agencies
Poor and
women
households
provided with
skills trainings
And engaged in
IGPs
Link with
existing
NGOs like
UPPRP
Appendix 5 SOCIAL ASSESSMENT REPORT
Activity Task Time Frame Stakeholders
/Responsibility
Expected
Output
Remarks
appropriate
institutions
4. Institutionalizatio
n
4.1 Workshop on
Mainstreaming of
Community
Participation in water
management
,
a) Prepare
workshop/training
design
b) Prepare Operations
Manual on
participation
process in project
cycle
c) Conduct of
workshop
Mid 2012
WUG, women
poor
households,
KWASA -
Community
Development
Specialist and
Technical Staff
Operations
manual and
guidelines
established
Invite
resource
person or
Expert in
4.2 Implementation
of Operations Manual
4.2. 1. Participation in
site selection and
installation,
operations and
maintenance
b) Training on
operations and
maintenance
c) Training on
collection
bookkeeping and
reporting
d) Training on M & E
- water leakage
-illegal connection
2012 -2017
KWASA,
Technical staff
WUG
Committee
Appropriate
training
provided to
develop
capacity of
WUG
4.2.3 Establishment of
Complaints and
Response Mechanism
at the Ward Level
Response procedures
at community level
Set up local based
Action Committee to
facilitate complaints
and action –ward level
KWASA – COMREL to
address issues within
a specified time
Meetings/dialogue
with HHs
Conflict resolution
2012 -2017 KWASA
WUG
COMREL
4.2.4
Participation in
monitoring and
evaluation
Establish monitoring
Internal monitoring
team
Monitoring of target
vis-a vis achievement
Appendix 5 SOCIAL ASSESSMENT REPORT
Appendix 4: FGD Documentation
ADB TA 7385 BAN: Preparing for the Khulna Water Supply Project
1. INTRODUCTION
The Focus Group Discussions (FGD) intends to generate information from community-based
stakeholders (government, non-government, community based including women organizations) and
households of low-income and slum areas on existing efforts and management systems related to water
supply and sanitation activities as well as income generation and micro-financing schemes.
Recommendation and suggestions on the most affordable cost effective and sustainable schemes to
ensure water supply for low-income and slum households have been solicited and issues and concerns
reviewed. Willingness to participate in Project activities has also been discussed and proposals on
participatory activities and mechanisms have been solicited.
2. OBJECTIVES
The main objectives of the focus group discussion (FGD) are to:
• Identify existing water source, supply condition and gender role to arrange water for household use
in the low income/slum areas;
• Justify the probability of KWASA piped water supply in the slums/low income areas in the city;
• Assess willingness to access water to KWASA piped water supply and pay for that by the slum
people;
• Assess willingness to participate in the management of water supply system;
• Recommendations on how to improve capacity of the slum people to pay for service.
In order to achieve the above objectives the TA Consultant carried out FGD in 12 Wards of Khulna City
Corporation (KCC) starting from 23rd September and ended to 3rd October 2010.
3. FGD PREPARATION
Activities undertaken in preparation for the FGD were as follows:
• Initially the existing water distribution network was studied and based on the waterline traversed
the area, 12 out of 31 Wards were identified/selected for Focus Group Discussion (FGD).
• Prepared List of the different community-based organizations (government and non-government)
operating in the 12 wards where the FGDs were conducted.
• The TA Team had a discussion with the National Project Coordinator (NPC) and Team in Khulna of
Urban Participatory Poverty Reduction Project (UPPRP) of UNDP. They were requested to provide
the details of CDCs (Community Development Committee) formed under UPPRP in the respective
Wards.
• The UPPRP COs (Community Organizer) assist, facilitate and coordinate the participation and
logistics preparation with the ward officials.
Appendix 5 SOCIAL ASSESSMENT REPORT
• Various forms and questionnaire required to conduct FGD, receipt and financial forms required for
accounts were prepared.
• Two facilitators (male and female) were recruited in order to facilitate planed FGD.
• TA Consultant and UPPRP team had a meeting and finalized the schedule including date, time and
location of FGD. The strategy was finalized to communicate with Ward Councilors, stakeholders,
representatives of CDCs etc in conducting FGD.
• After completion of the preparatory activities, TA Consultant conducted FGD from 23rd September
to 3rd October 2010, successfully with the help and assistance of respective/concerned persons, in
the 12 Wards of Khulna City Corporation (KCC).
• Documentation of the FGD proceedings was done properly. The list of participants, their gender and
organizations represented were fully documented. The discussion proceedings were also fully
reflected in the records and documented, especially the comments and recommendations on the
issues and concerns, which have been discussed in the following paragraphs.
4. EXECUTION OF FGD
4.1 Schedule
The schedule of FGD prepared by the TA Consultant after discussion with the stakeholders and all party
concerned and conducted accordingly are given the following table:
Table 1: The Schedule of FGD
Sl
No.
Ward
No.
FGD Conducted
On
Duration Venue Remarks
1 12 23 Sep 2010 09:30 – 12:30 am Ward Office TA Consultant and
two facilitators
assisted organized
the FGD.
2 13 23 Sep 2010 03:30– 06:00pm Chararhat School -Do-
3 7 26 Sep 2010 09:30 – 12:30 am Ward Office -Do-
4 8 26 Sep 2010 03:30– 06:00pm Ward Office -Do-
5 11 27 Sep 2010 09:30 – 12:30 am Ward Office -Do-
6 9 27 Sep 2010 03:30– 06:00pm Ward Office -Do-
7 21 28 Sep 2010 09:30 – 12:30 am Greenland Office -Do-
8 15 28 Sep 2010 03:30– 06:00pm Khalishpur Girls
High School
-Do-
9 30 29 Sep 2010 09:30 – 12:30 am Ward Office -Do-
10 10 29 Sep 2010 03:30– 06:00pm Ward Office -Do-
12 31 03 October
2010
09:30 – 12:30 am Ward Office -Do-
11 22 03 October
2010
03:30– 06:00pm Customghat Pre-
primary School
-Do-
Appendix 5 SOCIAL ASSESSMENT REPORT
4.2 Participants
Based on the initial assessment of the low-income areas
in the various wards of KCC traversed by the KWASA
water supply pipe system, 12 wards were identified and
selected for FGDs. In these 12 wards, the UPPRP, UNDP
has already organized the extreme poor and poor
households into primary groups; 10 primary groups
constituting a community development Committee (CDC)
with a committee representing the various primary
groups already organized. Some wards have substantial
number of extreme poor and poor households as
reflected in the number of community development
committee (CDC). The following table shows the number of wards and CDC in these wards.
Table 2: Wards and CDO/C for inclusion in the FGD
Ward Number Community Development Committee (CDC) Category
Old New Subtotal
7 3 5 8
8 - 4 4
9 2 10 12
10 7 3 10
11 3 - 3
12 7 - 7
13 2 6 8
15 - 3 3
21 5 3 8
22 4 - 4
30 5 6 11
31 6 14 20
Total = 12 44 54 98
Appendix 5 SOCIAL ASSESSMENT REPORT
The participants to the FGD were the representatives of
the community-based committees (CDCs), stakeholder
(government and non-government), Ward Councilors and
officials, school teachers, Immams etc. One FGD/Ward
was conducted in one session where there were average
30-35 participants in each of the individual FGD. Table 3
below shows the tentative composition of the FGD
participants per Ward.
The Team leader & the Deputy Team leader also visited
some venues and took part in the discussion
Table 3: FGD Participants
Ward
No.
CDC CDC
Participant
s
Organization
/ Stakeholder
Participants
Ward Official
Participants
FGD
Organizers
TOTAL
7 8 16 8 2 4 30
8 4 15 8 2 4 29
9 12 15 - 30 8 2 4 29 - 44
10 10 15 - 20 8 2 4 29 - 34
11 3 15 8 2 4 29
12 7 15 8 2 4 29
13 8 15 8 2 4 29
15 3 15 8 2 4 29
21 8 15 8 2 4 29
22 4 15 8 2 4 29
30 11 15 - 22 8 2 4 29 - 36
31 20 20 - 40 8 2 4 34 -54
Total:
12
98 354-401
The participant’s attendance sheet is attached as Appendix 4.1.
4.3 FGD Approach
Two sessions per day for a total of 12 FGD sessions were undertaken starting the third week of
September and ending by first week of October 2010. Discussions were held following a specific
questionnaire where at the beginning of the session, the TA Consultant presented the objective and
purpose of the FGD. The Consultant (National Social Development Specialist) two facilitators including
Community Organizer (CO) of UPPRP organized and facilitate the focus group discussions.
Two facilitators assisted the Consultant in the documentation, time management and logistical
consideration of the FGD conduct too. The questions included in the questionnaire used to conduct FGD
are enclosed in Annex – 2.
Appendix 5 SOCIAL ASSESSMENT REPORT
5. Findings of Focus Group Discussion (FGD)
The National Consultant (Social Development Specialist) carefully studied and analyzed the
message/information provided by the FGD participants, documented by the facilitator and prepared the
summary of findings which can be described as follows:
Present Source of Water supply in Slums/Low Income Areas
The FGD participants from almost all the slums/low income areas reported that the main source of
water supply in the areas is the deep and shallow hand tube wells installed by former KCC, GOs and
NGOs. The water from the tube wells are generally used for drinking, cooking and washing purposes.
River/pond water in some areas where available, is used for domestic purpose only.
Justification for KWASA Piped Water Supply to the Slums
The participants in the discussion programme include the respective Ward Councilors and officials;
stakeholders reported that the inhabitants in the slums are in need for sufficient supply of water for
drinking and other domestic use. The scarcity of fresh water in the whole region is likely to worsen
further with the rise of sea level and intrusion of saline water deep into the greater Khulna district. In
some area a little arsenic was identified. In some area women and children are the worst victims. They
have to carry water from long distances. Most common water related diseases in Khulna are dysentery,
cholera and typhoid. The women are also suffering by urinal infection and reproductive infection.
It is informed by the Ward councilors and participants that many of the hand tube wells, only source of
potable water supply in the slums, are out of order due to lack of proper repair/rehabilitation for want
of required spare parts. As a result water supply situation in the slums are getting worse and worse day
by day.
In order to cope with the situation the slums/low-income areas should be connected to KWASA piped
water supply.
Willingness to Access to KWASA piped Water Supply
From the discussion and interaction during FGD it is reflected that the slum/low income area peoples
are severely suffering from supply of adequate quantity of fresh potable water. After implementation of
JICA and ADB investment, KWASA will have capacity of producing large quantity of fresh water.
Therefore the peoples have shown their great interest to have an access to KWASA piped water supply
because it is expected to be ensured for:
• 24 hrs. supply;
• Sufficient quantity of water;
• Fresh and potable water;
• Free of water born diseases and good health;
• Reduction of conflicts among the water consumer/user;
• Maintaining good environment;
• Reduction of women sufferings for collecting water.
Appendix 5 SOCIAL ASSESSMENT REPORT
Location of Water Tap
Most of the participants opined to introduce water service connection in the area for a cluster consisting
of 10-12 households. A very few especially the land owner in the area interested to have individual
water connection for the household. For a cluster of households the probable location of common water
tap should be central point of the cluster and away from the KWASA existing deep/shallow hand tube
wells location.
Willingness to Pay
It was enquired by the FGD organizer and facilitator to the participants from slums/low income areas
that whether they are interested to pay for water if connected to the KWASA piped water supply
system. The participants responded to the queries that they are ready to pay for water to some extent.
For group connection, each of the members intends to pay Tk.10-20 per month but for individual
connection they are ready to pay Tk 100 per month.
Water Tap Management
An outline of water tap management was obtained after discussion/interaction with the participants.
They suggested selecting a representative through following selecting procedures, who will be taking
care of the water tap. The options of selecting representative can be described below.
i) Mutual discussion and understanding among the group can be the way of selecting the
representative;
ii) Ward Councillor can select a representative with the consent of community;
iii) CDC, UPPRP can selective representative from beneficiaries.
The care taker/representative will be provided training on maintenance of the tape, book keeping on
collecting bills and payment. Maintenance of the water connection will be the responsibility of the
group. It was agreed that the user especially the women will be careful of using the water tap. The
selected representative will make necessary repair and maintenance by the money to be collected from
the member of the group. He/She will also collect the monthly subscription and pay the bill on time. The
participants requested to keep provision of paying bill to Bank through mobile SMS.
Status of Women in Slum
FG discussion and interaction with the participants reflects that
the women in the slums and in low income areas are more
considerable as the water users are mainly women and they are
main responsible for water use at homestead level. Women are
involved in care taking of hand tube well, sanitary latrine, family
health, and all sorts of water uses at household works. Women
consider that lack of pure drinking water & sanitation facility is
also effects on their reproductive health but men are usually not
much concerned about the sanitation and hygiene status of the
household, lack of portable drinking water affects them differently.
Appendix 5 SOCIAL ASSESSMENT REPORT
The educational levels of women in slums/low income areas are varied:
• Never been to school;
• Primary School pass;
• SSC Pass-(a few);
• HSC pass-(a few);
• Vocational and Technical School;
• Madrassa
• University (rare)
Most of them are involved in different kind of income generating activities for their livelihood. Majority
of them are involved with NGOs had access to micro credit. Among the people would not receive micro
credit are interested to get it. The occupation of the women is as follows;
• House wife
• Housemaid
• Sewing
• Labor
• Embroidery
• Poultry
• Beef Fattening, Goat Roaring
• Block, Batik
• Cottage Industry
• Small Trade (Cloth, Fire Wood, Cake, Fish Vendors, Handicrafts, Paper Bag, Hawker)
• Nursing maid
• Tea Stall
• Day Labor
• Teacher
NGOs & Activities in Slums
There are more than 30 NGOs working in the slums in Khulna City Corporation (KCC) with different social
development activities. The programme in particular, is micro credit, health and hygiene, solid waste
management, education and job placement activity, mother and child care, protection of child
trafficking, legal support to women etc. The list of the NGOs and their programme in details are
attached as Appendix 4.1.
6. Suggestions/Recommendations from FGD Participants for Future Development
The FGD participants recommended the following activities to be carried for their future development:
• Arrangement for supplying sufficient quantity of potable water with minimum cost;
• Emergency repair/rehabilitation of hand tube wells which are out of order.
• Construction of road and drain and provide sanitation facility in the area in a planned way;
• Widening the existing narrow roads;
Appendix 5 SOCIAL ASSESSMENT REPORT
• Identify the poor & extreme poor in the slums;
• Conduct skill development activity/programme;
• Create job opportunity for unemployed;
• Create job opportunity for women;
• Control drug and narcotics;
• Rehabilitate the floating people;
• Education for all;
• To control child marriage, violence against woman, trafficking, dowry;
• Arrangement for old home;
• Campaign for social awareness.
Appendix 5 SOCIAL ASSESSMENT REPORT
Appendix 4.2
Questionnaire used to conduct FGD
i) What are the ongoing activities regarding water & sanitation in your area?
ii) What kinds of Income Generating Activities program are going on?
iii) What type of micro credit programs are being carried out in your area?
iv) What kind of skill development activities are taken in your area?
v) What kinds of activities are being carried out for community development?
vi) What kind of program do you consider necessary for your future development?
vii) What is your opinion if your area is supplied /connected to KWASA pipe water supply system?
viii) How do you want to avail this service?
ix) What kind of steps should be taken for accessibility of pure drinking water for all?
x) How the water supply program can be operated?
xi) What is your expectation in this issue, what kind of measures should be taken by KWASA?
xii) How the expenditures in this issue can be managed?
xiii) How can you manage to pay the Bill?
xiv) What is the existing source of water supply in your area?
xv) What will be the probable location of water tap –will it be at the existing tube well location or
some other location?
xvi) Specify the location?
xvii) Are you ready to pay for piped water supply?
xviii) How much per HH are able to pay?
xix) How can you assist KWASA regarding water supply?
xx) What roles the women can play regarding water supply?
xxi) Are you willing to take supply water? How much per HH could pay? Are you capable of giving
decision in this respect?
xxii) What kind of IGA you require in your area?
xxiii) What kind of program you can undertake for awareness build up?
xxiv) What will be the system of payment for water bill?
xxv) Do you need any training for your skill development?
Appendix 5 SOCIAL ASSESSMENT REPORT
Appendix-5
List of NGOs Working in KCC
Sl
No.
NGOs Working in the Slums
in Khulna
Activities
1 BNSB Eye Hospital Treatment support to all Eye Diseases
2 Urban Primary Health Care
Project (UPHCP)
Primary health care, anti natal and post natal check up,
children and mother health care
3 Intellectually Disabled
Children Education
Programme (IDCEP)
Make education, mental and physical exercise and
cultural development
4 RUPANTAR Good governance, human rights, awareness
development and theatre development
5 World Vision Bangladesh Education, micro-credit, health and sanitation, HIV/AIDS
6 Unprivileged Children’s
Education Programme
(UCEP)
Technical education and training, job placement
7 NOBOLOK Micro credit, water sanitation and hygiene
8 Somaj Progoti Sansthya (SPS) Micro credit, water sanitation and hygiene, solid waste
management
9 PRODIPAN Micro credit, water sanitation and hygiene, solid waste
management
10 Jagrato Juba Sansthya (JJS) Education, micro credit, health and sanitation, HIV/AIDS.
11 DIPTE Bangladesh Education, micro credit, health and sanitation, HIV/AIDS,
election etc.
12 ADAMS Micro credit, water sanitation, hygiene and solid waste
management
13 Paribar Kalyan Sansthya
(PKS)
Primary health care, anti natal and post natal check up,
children and mother health care
14 Bangladesh National Women
Lawyer Association (BNWLA)
Legal support training
15 Bangladesh Legal Aid
Services Trust (BLAST)
Legal support training
16 NGO Forum Health, sanitation, hygiene and water supply
17 KARITAS Education, micro credit, health and sanitation,
rehabilitation
18 Kh.UDA Day care facilities for urban poor children, food and
nutrition, health services
19 UTTARAN Education, micro credit, health and sanitation, health
services
20 CONCERN Bangladesh Education, micro credit, health and sanitation,
awareness building, rehabilitation
21 SHUSHILAN Education, micro credit, health and sanitation,
rehabilitation
22 OPERAJEO Bangladesh Shelter for street and trafficking children, life skill
Appendix 5 SOCIAL ASSESSMENT REPORT
Sl
No.
NGOs Working in the Slums
in Khulna
Activities
development, prevention of child trafficking.
23 NAGORIK Forum Transparency, good governance, solid waste
management
24 PCAR Non-formal education, shelter for street children, life
skill development, job placement, rehabilitation, skill
development
25 ASROY Health and sanitation, rehabilitation
26 BRAC Education, micro credit, health and sanitation, delivery
centre
27 Jagoroni Chakra Foundation Hard to reach school programme, non-formal education,
micro credited
28 MARIE STOPS CLINIC Reproductive health care facilities, health services
29 DSK (Dusthay sasthya
Kandro)
Health and sanitation, micro credit
30 SOS Shishu Polly Non-formal education, programme for street children,
life skill development, job placement, rehabilitation, skill
development training
31 MSSES Life skill development, theatre development,
programme for street children.
32 PROSHIKA Education, micro credit, health and sanitation, delivery
centre
Appendix 5 SOCIAL ASSESSMENT REPORT
Appendix 6: List of Persons Met
Date Names/ Organization Gender Issues Discussed
26/08/10 Kazi Fazlur Rahman
Secretary
Khulna City Corporation
M Introduction on TA project & requested them to
support this program.
30/08/10 1.Mr. Tapon Kumer Ghosh
Chief Executive officer
Khulna City Corporation
2.Kazi Fazlur Rahman
Secretary
Khulna City Corporation
M
M
Discussion on involving the ward Commissioners for
participating in the cluster wise focus group
discussion, & collection the list of ward
commissioners with their name & addresses.
30/08/10 1.Md. Shahidul Islam
Urban Agricultural Expert
UPPRP Project
Khulna
2.Mr. Shahidul Islam
Settlement Improvement
Expert
UPPRP Project
Khulna
M
M
Project orientation, Ways where the Project and the
organization could cooperate. Arrange meeting with
the NPC of UPPRP Project.
31/08/10 1. Mr. Azahar Ali
NPC
UPPRP Project
UNDP
Dhaka
2.Mr. S M Nazrul Islam
Town Manager
UPPRP Project
Khulna
M
M
Introducing with KWASA program
do
05/09/10 Mr. S M Nazrul Islam
Town Manager
UPPRP Project
Khulna
M To discuss about FGD & how they could assist in this
program
17/10/10 Mr. S M Nazrul Islam
Town Manager
UPPRP Project
Khulna &
All sector Specialist
UPPRP
All Community organizers
UPPRP
M - 15
W - 03
Meeting with UPPRP Staff to selection of venue,
arranging the program of FGD, & distribution the
responsibilities.
21/10/10 Mr. S M Nazrul Islam
Town Manager
UPPRP Project
Khulna & staff.
Provide all kind of logistic support.
Appendix 5 SOCIAL ASSESSMENT REPORT
References:
Md. Wahiduzzaman, Water Consumer Survey in Khulna City – TA 7223 BAN: Establishing the Khulna
Water Supply and Sewerage Authority, August 2009.
KWASA, Final Report: Feasibility Study for Khulna Water Supply Improvement Project in the People’s
Republic of Bangladesh, Khulna City: May 2010.
JICA Study Team, Progress Report (2) – Main Report: Feasibility Study for Khulna Water Supply
Improvement Project in the People’s Republic of Bangladesh, Khulna City: July 2010
Arthur McIntosh, TA Consultant’s Report: Diagnostic Report - Bangladesh: Supporting the Establishment
of the Khulna Water Supply and Sewerage Authority, Khulna City: December 2008.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page i
KHULNA WATER SUPPLY AND SEWERAGE AUTHORITY (KWASA)
KWASA BUSINESS PLAN 2011 to 2017
2011
PREPARING THE KHULNA WATER SUPPLY ADB TA 7385 – BAN
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page ii
TABLE OF CONTENTS
A. EXECUTIVE SUMMARY .............................................................................................................................................. 1
Summary ............................................................................................................................................................................ 1
B. Vision, Mission, Values & Objectives ........................................................................................................................ 3
Key Performance Indicators ............................................................................................................................................... 4
C. Production & Demand Analysis ................................................................................................................................. 7
Introduction ........................................................................................................................................................................ 7
KWASA Future Source Planning ....................................................................................................................................... 8
KWASA Production, Demand and Coverage Assumptions ............................................................................................... 9
Population & Households .............................................................................................................................................. 9
Slum Service & Low Income Community Service Provision .............................................................................................. 9
Production Source Development ................................................................................................................................. 11
Service Coverage & Demand ...................................................................................................................................... 11
D. INVESTMENT PLAN .................................................................................................................................................. 14
D1. Projects Included In The Investment Plan ................................................................................................................. 14
D1.1 Projects Approved & Budgeted...................................................................................................................... 14
D1.2 Investment Projects at Feasibility/Pre-approval Stage: ................................................................................. 14
D1.3 Additional Projects Identified Under ADB TA 7385 ........................................................................................ 14
D1.4 Consultancy & Management Systems ........................................................................................................... 15
D2 Projects Not Included in Investment Plan ........................................................................................................... 15
E. Financial Plan ............................................................................................................................................................ 17
Introduction ...................................................................................................................................................................... 17
Major Assumptions .......................................................................................................................................................... 17
Financial Model Base Case ......................................................................................................................................... 18
Sensitivity Scenarios ........................................................................................................................................................ 19
F. Human Resources Development Plan ..................................................................................................................... 21
F.1 KWASA Human Resource Management ........................................................................................................... 21
F.1.1 Introduction .................................................................................................................................................... 21
F.1.2 KWASA Current Organisation ....................................................................................................................... 21
F.1.3 Phase 1 Organisation .................................................................................................................................... 24
F.1.4 Phase 2 Organisation .................................................................................................................................... 26
F.1.5 Staff Efficiency Ratios .................................................................................................................................... 28
F.1.6 Organisation Development During Business Plan Period.............................................................................. 28
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page iii
F.2 KWASA Capacity Building.................................................................................................................................. 30
List of Tables Table 1: List of KWASA Key Performance Indicators ......................................................................................................... 5 Table 2: KWASA Key Performance Indicator Targets 2011/12 to 2016/17 ....................................................................... 6 Table 3: Sources of Water in Use in Khulna City ................................................................................................................ 7 Table 4: Population, Household and Service Coverage data........................................................................................... 10 Table 5: Summary of Production Source Development.................................................................................................... 12 Table 6: Demand Forecast and Derived Service Coverage Ratios ................................................................................. 13 Table 7: Summary of Five Key Projects to be undertaken during the Business Plan Period by Project Totals............ 16 Table 8: Key Revenue Improvement Action Plan ............................................................................................................. 18 Table 9: Results of Base Case ........................................................................................................................................... 19 Table 10: Financial Model Scenario Variables .................................................................................................................. 20 Table 11: Summary of KWASA Existing Staff Numbers by GoB Classification .............................................................. 23 Table 12: Summary of KWASA Staff Numbers by GoB Classification to Phase 1 ......................................................... 24 Table 13: Summary of KWASA Staff Numbers By GoB Classification All Phases ......................................................... 26 Table 14: Summary of Connections and Staff Efficiency Ratio through the Corporate Plan Period ............................. 28 Table 15: Structure and Staff Numbers ............................................................................................................................. 29
APPENDICES
Annex 1 – Summary of Proposed Capital Investment for KWASA under GOB/JICA/ADB Loan
Annex 2 – Preliminary Financial Statements 2009 and 2010
Annex 3 – Financial Plan: Major Assumptions
Annex 4 - Financial Projections for the Base Case Scenario
Annex 5 – Results of Scenario Analysis
Annex 6 – KWASA Organisation Structure Staffing Requirements
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page iv
ABBREVIATIONS
ADB - Asian Development Bank BAN - Bangladesh DMD - Deputy Managing Director DPP - Development Project Proposal DTW - deep tube wells FY - Financial Year GoB - Government of Bangladesh HTW - hand tube well JICA - Japan International Cooperation Agency KCC - Khulna City Corporation KWASA - Khulna Water Supply and Sewerage Authority LGD - Local Government Division LGRD - Local Government Rural Development MD - Managing Director O & M - Operations and Management SSTA - Supporting and Establishment of Khulna water Supply TA - Technical Assistance TK - Taka TOR - Terms of Reference WASA - Water Supply and Sewerage Authority
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 1 of 60
A. EXECUTIVE SUMMARY
Summary
This Business Plan covers the 5 year period from FY 2012 to 2017. The key theme of the business plan is the expansion of KWASA water coverage and increasing the availability of water to 24 hour supply through the construction of surface water treatment facilities, the rationalization of groundwater abstraction and the construction of new storage and distribution network infrastructure throughout the city. KWASA principle focus for service expansion will be the conversion of KWASA Hand Tube Well users to a safer and more abundant and available piped water supply; per capita consumption for these users is forecast to increase from around 82l/c/d to 120 l/c/d with the proposed projects. The second target for the new supply will be natural growth in population of Khulna City and thirdly will be the private well users in particular those using private wells for commercial uses. A number of key projects are planned for the period – the largest of which is the design and construction of a 110 Mld surface water treatment plant and associated transmission, storage and distribution network to provide water all year round to KWASA. Low income communities account for a significant proportion of the population of Khulna. Equitable provision of supplies for slum and low income communities is a key objective for KWASA and mechanisms will be put in place to ensure individual or community uptake of connections as appropriate. Service coverage is forecast to increase from 24.1% to 57.0% over the plan period rising to a maximum of 73.0% in 2025 (further growth in coverage from 2025 will require additional investment in source development of which a further 10% of coverage could come from unexploited groundwater). Water availability, based on power availability for pumping and KWASA operating regime is currently in the order of 16-20 hours per day. This will become 24 hour in 2017 with the commissioning of the new SWTP. In terms of water resources KWASA will follow a conjunctive use concept utilizing groundwater from the Khulna City (sustainable yield 159 Mld1 with additional 4 meter drawdown on current level) and Phultala aquifers in a sustainable manner and supplementing this with surface water from the proposed intake at Mollarhat on the Madhumati river. Significant changes are planned for KWASA over the business plan period starting immediately with the rationalisation of customers to correctly reflect the customer base; investment (with GOB grant funds) in groundwater development schemes; opening of zonal offices within the city of Khulna; move to customer metering and volumetric charging for water; development of a major surface water treatment plant and the introduction of treated water storage and distribution on a zonal basis across the city significantly increasing the service coverage and customer base. All these changes require appropriate organization structures to be in place if the benefits of the changes are to be realised by KWASA customers. It is planned to amend KWASA organisation structure in 2 phases:
the first phase for the start of FY 2014 when a third Deputy Managing Director is introduced to focus on customer service; and the second phase at the time of the commissioning of the new WTP at the start of FY 2017 when a zonal operations system will be implemented whereby all customer-related activity is managed at the zone level.
1 Result of analytical analysis of Khulna aquifer as part of ADB TA 7385 Groundwater Assessment Report 2010
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 2 of 60
Capacity Building support will be available to KWASA, under the ADB loan, to improve the corporate management of KWASA; this will focus on a number of issues, including:
KWASA revenue management - this will be overhauled during the early years of the business plan period. A key aim is for all supplies to be metered and for customers to pay on a volumetric basis for water received;
Implementation of a connection metering program with the aim of having all existing connections metered by FY 2017
Support to the development and implementation of appropriate business management systems for KWASA day to day operation
Establishment of linkages and connection implementation mechanisms for low income customers to ensure the smooth uptake of piped water facilities when they become available;
KWASA HR management – policy, processes, and organisational change implementation;
In order to fund the planned major infrastructure investment KWASA will avail, through the Government of GoB, a loan/equity of Taka 25.4 billion (US$ 363.5 million), this fund will be made by three investors, namely JICA, ADB and GoB. A summary of the proposed investment by investor is included in Annex 1.
A detailed financial model has been prepared for KWASA taking into account all investment and operational costs, forecast of production and demand and estimates of revenues to assess the viability of the proposed investments and KWASA in long term (FY2012-FY 2030). The base case financial analysis reveals that cash balances will be sufficient to cover cash operating and maintenance costs and debt service under the following key assumptions:
By project completion in 2017, metering of all connections and an initial tariff in real prices of Tk 13.10/m3 for domestic connections (Tk 19.35/m3 in 2017 prices) and Tk 26.20/m3 for non domestic connections (Tk 38.71/m3 in 2017 prices)
30% of the project cost will be funded by government equity and 70% through government loan, and concessional loan terms at 2% interest rate per annum, 30 years repayment period including an 8 year grace
period on principal and interest payment
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 3 of 60
B. Vision, Mission, Values & Objectives
KWASA has a clear vision for the direction and development of the business. This is supported by mission and value statements and clear objectives that form the basis for the investments and future actions identified in this business plan.
KHULNA WASA Vision:
To be the pioneer in the water and sewerage sector in Bangladesh ensuring a safe and sustainable water supply and environment friendly sewerage management for Khulna City to the satisfaction of the customer
KHULNA WASA Mission:
To ensure digital service to all customers supplying sufficient amount of potable water and proper sewerage solutions by 2020; through use of e-technology, automation, research, effective planning and HR development, raising finance for investment in service expansion, efficient operation & maintenance and sharing of experience with similar organisations;
KHULNA WASA Values:
Honesty; Transparency; Sincerity; Accountability; Customer focused service Serving future generations
KHULNA WASA Objectives:
24 hour water supply to all customers - from FY 2017 (SWTP commissioning) 100% Water coverage by 2020 through sustainable sources including rain water harvesting, surface water
treatment minimising ground water abstraction Deliver water to Bangladeshi water quality standards – by FY 2017 Think about customers first - establish one stop service – within FY 2011 Digital Billing for all customers by FY2012; Metering of all connections by FY2015; Establish customer friendly revenue collection options – within FY2012 Develop/implement computerized management systems – accounting, billing, within FY2012 Establish an effective Sewerage Master Plan – within FY2015
The slogan for the company is “KHULNA WASA – Safe Water, Safe Life”.
The company objectives are primarily focused on:
expansion of the water supply – addressing the coverage, availability and quality of water supplied; improving the management of KWASA (through the use of effective management systems) – in
particular revenue management; supporting the customer in their dealings with KWASA and facilitating ease of payment for services
provided.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 4 of 60
The management team recognise that objectives will change over time as the needs of the customer and the business will change.
The proposals under preparation for new sources of water, investment in network and the capacity building of KWASA are all consistent with the objectives defined by KWASA management team
Key Performance Indicators
In line with the objectives described above KWASA have identified a number of high level Key Performance Indicators (KPI’s) to be used as a means of measuring the success and progress towards achieving stated goals across all aspects of the organisation operation.
The Objectives are described in Table 1 below along with the relevant data requirements and infrastructure/monitoring requirements to allow them to be properly gathered. Targets for the each of the objectives across the business plan period are shown in Table 2.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 5 of 60
Table 1: List of KWASA Key Performance Indicators
No. INDICATOR TITLE FORMULA FOR INDICATOR TO BE USED
WHAT THE FORMULA MEASURES AND WHAT ACTION IT SHODL GENERATE DATA REQUIRED ADDITIONAL INFRASTUCUTRE/
MONITORING REQUIREMENTRESPONSIBILITY FOR DATA COLLECTION & REPORTING TIMING OF IMPLEMENTATION
1 Water Coverage – KWASA Piped Water
Population Served by Piped NetworkPopulation Total
Measures the number of people supplied by KWASA in relation to total population – and is linked to the drive for increasing coverage
No. Of households connected to KWASA piped network; Household occupancy rate;
Consumer Census results;Data will be collected
DMD Engineering through Planning Department;
FY 2012 onwards
2 Water Quailty Testing Compliance
No. of tests carried outNo. of tests that should be carried out
Measures compliance with statutory testing requirements
Bangladeshi Statutory Water Quality Requirements
none DMD Engineering through Production Department;
2013 - with Phase 1 of Organisation
3Bacteriological Quality of water supplied
No. of Bacti. tests that pass BD stndsNo of tests carried out
Measures bacteriological water quality Test results for :
Bacteriological analysis
Water quality monitoring unit set up and equipped
DMD Engineering through Production Department;
2013 - with Phase 1 of Organisation
4 NRW Ratio Water Produced – Water Sold Water Produced
The difference between the volume of water produced and the volume of water sold/billed in a period.
Production Volume;Billed volume;
100% production sources metered and recorded on a monthly basis;All customer connections metered;
DMD Engineering through Production Department;
Start of 2016;
In the period between now and 2015 periodic assessments of UFW should be carried out;
5 Meter Coverage Metered ConnectionsTotal No. of Connections
Measures implementation performance of the 100% metering program
Implementation plan Meter purchase;
Responsibility
DMD Engineering through Distribution Department;
On Availability of funds - from FY2013 onwards
6 Billing Ratio No. of connections billedTotal No. of connections
Measures implementation performance of the household billing project
Implementation plan Billing system in place - this may or may not be linked to a connection program
DMD F&A through Revenue Department to FY 2013;
DMD Customer Service through revenue Section from FY 2014
FY 2012 onwards
7 Revenue Collection Efficiency Revenue CollectedRevenue Billed
This indicates effectiveness of collection system which impacts on the financial health of a utility. Collection efficiency higher than 100% indicates that total collections for the period included payment of bills for the previous period.
Value of revenue collected in the period;Total value of billings in the period
Accounting software in operation; DMD F&A through Revenue Department to FY 2013;
DMD Customer Service through revenue Section from FY 2014
FY 2012 onwards
8 Operating Ratio Operating Expenses (excl.depreciation) Operating revenues
A low operating ratio means revenues from tariffs cover the O&M costs comfortably. A healthy utility should have a ratio of about 0.75. A ratio above one means revenues do not cover O&M costs and relies heavily on subsidy/cross subsidy.
Operating expenses for the period;Operating revenue for the period (is this billed revenue or collected revenue?)
Accounting software in operation; DMD Customer Service through Revenue Department from FY 2014
FY 2012 onwards
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 6 of 60
Table 2: KWASA Key Performance Indicator Targets 2011/12 to 2016/17
No. INDICATOR TITLE FORMULA FOR INDICATOR TO BE USED Current Year 2012 2013 2014 2015 2016 2017
1 Water Coverage – KWASA Piped Water
Population Served by Piped NetworkPopulation Total 24.1% 25.6% 27.1% 28.5% 29.9% 31.3% 57.0%
2 Water Quailty Testing Compliance No. of tests carried outNo. of tests that should be carried out 0% n/a 100% 100% 100% 100% 100%
3Bacteriological Quality of water supplied
No. of Bacti. tests that pass BD stndsNo of tests carried out 0% n/a 80% 80% 80% 80% 90%
4 NRW Ratio Water Produced – Water Sold Water Produced 100% n/a n/a n/a 31% 30% 25%
5 Meter Coverage Metered ConnectionsTotal No. of Connections 0% 0% 0% 0% 0% 0% 100%
6 Billing Ratio No. of connections billedTotal No. of connections 84% 100% 100% 100% 100% 100% 100%
7 Revenue Collection Efficiency Revenue CollectedRevenue Billed 80% 85% 90% 95% 98% 98% 98%
8 Operating Ratio Operating Expenses (excl.depreciation) Operating revenues
4.17 1.48 1.52 1.97 1.57 1.49 0.45
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 7 of 60
C. Production & Demand Analysis Introduction
The inhabitants of Khulna currently receive water from three principal sources. Estimates of the numbers of people using each type of source have been made based on prior studies carried out – these are shown in Table 3 below. The total population of KWASA at midyear 2010 is taken as 966,500 – this is based on the 2009 population included in the JICA FS report with a growth rate of 2% per annum:
Table 3: Sources of Water in Use in Khulna City
Source Population 2010
Abstraction m3/day
Usage l/c/d
Private Deep Tube Wells 412,000 49,700 120.6 KWASA Pipe Network Via Deep Tube Wells * 218,055 30,100 138.0 **
KWASA Hand Tube Wells ** 336,445 20,817 60.0
TOTAL 966,500 99,987 103.5 * Breakdown of Piped Supply Production 30,100 m3/day
Loss 10,807 m3/day Non Domestic Use 1,412 m3/day Domestic Use 17,881 m3/day Per Capita Domestic Use ** 82 l/c/d
Source data for the population and consumption figures above are as follows:
Private Deep tube Wells – ADB Diagnostic Report, 2009; and JICA Feasibility Report, 2010; KWASA Pipe Network Via Deep Tube Wells – ADB Consumer Census Survey 2010; KWASA Hand Tube Wells – Derived from total population less sum of all other users;
** From the table it can be seen that the per capita usage from HTW sources is low, there is a discrepancy between the JICA estimated HTW output of 39,300 m3/day (based on sample testing of operational HTW’s multiplied by total number of installed HTW’s) and the ADB estimated output of 20,817 m3/day (based on per capita consumption from the ADB Consumption Survey – 2009, and population served); The volume abstracted however is not relevant for production and demand forecasting purposes2, this relies instead on the estimate of population and forecast of per capita consumption.
It should also be noted that the current per capita consumption from KWASA piped network is low at 82 l/c/d. Non domestic use of KWASA piped water supply is based on number of known connections multiplied by the average consumption of 81m3/mth derived in the Consumption Survey 2009.
From the results of the Groundwater Assessment study carried out by IWM under the TA 7385 the safe yield of the Aquifer in Khulna is estimated to be 159 Mld (current abstraction from Private deep tube wells, KWASA hand tube wells and 59 Mld). Current abstraction is considered to be 100.0 Mld from the sources outlined above which means that potential for abstraction of an additional 59 Mld exists over and above that currently existing.
From the figures above the long term need for additional sources of water to supply Khulna City is evident.
2 Whilst not important for demand forecasting purposes, the estimate of abstraction by HTW’s is important in assessing the sustainable yield from the Khulna aquifer – in this regard the estimate of ADB TA team could be considered conservative.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 8 of 60
KWASA Future Source Planning
Recognising the need for additional water sources KWASA have initiated a number of actions to increase water resources for Khulna City. These include approved and budgeted projects and projects at feasibility/pre-approval stage:
Projects Approved & Budgeted:
Development of Water Supply System in Khulna, split into 2 components Part 1: Additional groundwater abstraction from Khulna City Aquifer through the construction of 13 deep tube wells – 20 Mld; Part 2: Upgrade and expansion of existing surface water treatment plant3 – 6.75 Mld;
KCC Mini-Tube well project – 3.5 Mld;
Import of groundwater from an adjacent aquifer in Phultala, funded by KCC 4– 20 Mld;
Projects at Feasibility/Pre-approval Stage:
Construction of a new surface water treatment plant using JICA funds – 91.1 Mld (average useable volume); Construction of new distribution storage and network assets, including customer connections to be able to utilise
the increased volume of water through the new SWTP – using ADB funds; Additional Groundwater abstraction from Khulna City Aquifer through the use of GoB funds – 16 Mld; Construction of KWASA offices through the use of ADB/GoB funds
The medium to long term objective of KWASA is to significantly increase service coverage, service availability and service volume. This will be achieved by providing current users of KWASA HTW’s as well as private DTW users with piped water supply connection and by increasing the volume of water available to piped water supply users to around 120 l/c/d.
For the purposes of demand and service coverage forecasting it has been assumed that all currently approved and budgeted projects will go ahead as per their proposed schedules; in addition the new JICA funded SWTP and associated distribution storage and network assets will go ahead; the proposed additional groundwater abstraction of 16 Mld using GoB funds has not been included;
Rationalisation of KWASA HTW’s will be necessary during the business plan period. KWASA currently have 111 wells – 30 no. production wells of 150m diameter and 81 mini wells of smaller diameter. From a management and operation point of view the mini wells are very inefficient and KWASA will over the business plan period reduce the number of mini wells and increase the volume output of production wells.
It can be seen from the forecast that as users of KWASA HTW’s and also Private DTW users switch over to the piped network supply the volume of groundwater available for abstraction will also increase. There are currently no plans to exploit this volume of water as it becomes available however consideration needs to be given to this (or additional surface water utilisation) if service coverage is to exceed 73%.
3 GoB funds have been approved for this project; Design consultants have been selected and will commence work in Q1 2011 - KWASA wish to push ahead with the project as the transmission line is already in place under the Phultala project; 4 KCC are responsible for all costs associated with commissioning of the well field, however cost provision for the regeneration of 20 wells is included within the ADB investment proposal ;
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 9 of 60
KWASA Production, Demand and Coverage Assumptions Population & Households
Table 4 below shows population, household and service coverage forecasts for the period 2011 to 2020 at which time ADB investment package will be fully utilised. The population forecast is taken from the JICA Feasibility Study which assumes 2% per annum growth from 2009 onwards, adjusted to coincide with fiscal year rather than calendar year. The average household occupancy rate of 5.5 persons per household has been taken from the findings of the ADB Consumption Survey 2009, validated by the Customer Census Survey 2010.
Slum Service & Low Income Community Service Provision
Approximately 47% of the population of Khulna are classed as poor; their main source of water is KWASA Hand Tube Wells. With the introduction of piped water supply this population will become a significant proportion of KWASA customers.
KWASA policy is to treat all inhabitants of Khulna equally and provide access to water made available through the investments proposed; However recognising disparities in social and economic status of citizens in Khulna City, KWASA also intend to incorporate measures for inclusive service coverage of the poor and vulnerable households in low income and slum communities, this will include the implementation of a Gender Action Plan and Poverty Reduction strategy as an integral component of KWASA operating plan.
The Poverty Reduction Strategy and Gender Action Plan will institutionalize and internalize the beneficiary driven approach for sustainable social development interventions particularly for the female members of low income households and households in slum areas.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 10 of 60
Table 4: Population, Household and Service Coverage data
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020Population Growth Rate - From JICA FSR 2.0% 2.0% 2.0% 2.0% 2.0% 2.0% 2.0% 2.0% 2.0% 2.0%Population Forecast (Rounded to '000) 986,000 1,006,000 1,026,000 1,047,000 1,068,000 1,089,000 1,111,000 1,133,000 1,156,000 1,179,000
POPULATION BY SUPPLY SOURCEPopulation Supplied by Private Tube Well (Jica FSR) 412,000 412,000 412,000 412,000 412,000 412,000 309,000 309,000 288,400 288,400
Population Supplied by KWASA HTW (derived) 336,445 336,445 336,445 336,445 336,445 336,445 168,222 117,756 100,933 84,111
Other Population Supplied by HTW 148,003 148,003 148,003 148,003 148,003 148,003 74,001 51,801 44,401 37,001
Slum/LIC population Supplied by HTW 188,442 188,442 188,442 188,442 188,442 188,442 94,221 65,955 56,533 47,111
Population Supplied by KWASA Network * 237,555 257,555 277,555 298,555 319,555 340,555 633,778 706,244 766,667 806,489
TOTAL POPULATION 986,000 1,006,000 1,026,000 1,047,000 1,068,000 1,089,000 1,111,000 1,133,000 1,156,000 1,179,000
Household Occupancy rate 5.5 5.5 5.5 5.5 5.5 5.5 5.5 5.5 5.5 5.5
HOUSEHOLDS BY SUPPLY SOURCEHouseholds Supplied by Private Tube Well 74,909 74,909 74,909 74,909 74,909 74,909 56,182 56,182 52,436 52,436
Households Supplied by KWASA HTW 61,172 61,172 61,172 61,172 61,172 61,172 30,586 21,410 18,352 15,293
Households Supplied by KWASA Network 43,192 46,828 50,465 54,283 58,101 61,919 115,232 128,408 139,394 146,634
TOTAL HOUSEHOLDS 179,273 182,909 186,545 190,364 194,182 198,000 202,000 206,000 210,182 214,364
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 11 of 60
Production Source Development
Table 5 below shows the production forecast from the different sources anticipated by KWASA for the period 2011 to 2020. It should be noted that the total aquifer capacity included here is based on current estimated abstraction from Private deep tubewells; KWASA Deep Tube Wells; KWASA Hand tube Wells; plus an allocation of an additional 59 Mld for KWASA Deep tube Wells based on the results of hydrogeological modelling of the Khulna City aquifer.
The growth of unexploited aquifer volume over time is a function of the change-over of private well users and KWASA HTW users to the new KWASA piped supply. This presents an opportunity in the long term when the new surface water source is fully utilised – this is outside the timeframe of this business plan.
Service Coverage & Demand
Table 6 below shows the forecast of number of households, connections, population and service coverage supplied from available sources during the period 2011 to 2020.
Key assumptions are:
Growth in per capita consumption from the current estimate for pipe network users of 82 l/c/d to 120 l/c/d in 2014 as additional supply volume becomes available from GoB projects and Phultala well field.
Growth in commercial consumption from current level of 7.9% of supply to 10% as additional supply volume becomes available; the current level of commercial consumption is based on total number of known commercial users of KWASA (legal and illegal) identified during the ADB Customer Census (2010) multiplied by the average commercial usage identified during the ADB Customer Survey (2009);
Utilisation of 49% of the full volume from the new SWTP within a period of 2 years from commissioning and 100% utilisation within 10 years from commissioning;
Total NRW is estimated to reduce to 20% overall by 2018 – broken down as 15% technical loss and 5% commercial loss; This assumes almost total replacement of the current pipe network and effective control on connection to the new network;
The nature of housing use in Khulna means that not all households will have an individual connection – the ratio of households per connection based on the results of the ADB Customer Census (2010) is 2.82. This has been used in deriving the number of meters to be installed as part of the ADB loan project.
Users of Existing Private Tubewells and KWASA Hand Tube Wells convert to piped water supply as described in Table 6.
Without additional future groundwater abstraction KWASA service coverage is forecast to peak at around 73.5% in 2026;
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 12 of 60
Table 5: Summary of Production Source Development
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
SUMMARY OF PRODUCTION SOURCE DEVELOPMENTReduction in private well use - % 0% 0% 0% 0% 0% 0% 25% 25% 30% 30%Private Well Production - m3/day 49,700 49,700 49,700 49,700 49,700 49,700 37,275 37,275 34,790 34,790
No. of Private Tube Wells in Operation 23,732 23,732 23,732 23,732 23,732 23,732 17,799 17,799 16,612 16,612
Reduction in HTW use - % (from 2010 level) 0% 0% 0% 0% 0% 0% 50% 65% 70% 75%HTW Production - m3/day 20,187 20,187 20,187 20,187 20,187 20,187 10,093 7,065 6,056 5,047
Transfer from Private Use - m3/day 0 0 0 0 0 0 12,425 12,425 14,910 14,910
Transfer from HTW Use - m3/day 0 0 0 0 0 0 10,093 13,121 14,131 15,140
KWASA PRODUCTION FACILITIESReduction DTW use - % 0% 10% 20% 30% 35% 30% 20% 10% 0% 0%
Existing DTW's - m3/day 30,100 27,090 24,080 21,070 19,565 21,070 24,080 27,090 30,100 30,100
KCC Mini Tubewell Project (3.5 Mld) - m3/day 1,448 3,500 3,500 3,500 2,500 1,500 500 0
GOB Approved (20 Mld) - m3/day 10,769 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000
GOB In Process of Approval - 16 Mld 0 0 0 0 0 0 0 0
Phultala Well Field (20 Mld) - m3/day 7,429 14,286 16,000 17,000 18,000 19,000 20,000 20,000
Additional Surface WTP (6.75 Mld) - m3/day 6,750 6,750 6,750 6,750 6,750 6,750 6,750
New SWTP - m3/day 91,097 91,097 91,097 91,097
KWASA Water Into Network - m3/day 30,100 37,859 52,957 65,606 65,815 68,320 162,427 165,437 168,447 167,947
KWASA HTW - m3/day 20,187 20,187 20,187 20,187 20,187 20,187 10,093 7,065 6,056 5,047
KHULNA TOTAL PRODUCTION - m3/day 99,987 107,746 122,844 135,492 135,702 138,207 209,795 209,777 209,293 207,784
AQUIFER CAPACITY - m3/day 158,987 158,987 158,987 158,987 158,987 158,987 158,987 158,987 158,987 158,987
AQUIFER ABSTRACTION FORECAST - m3/day 99,987 107,746 115,415 114,457 112,952 114,457 93,948 92,930 91,446 89,937
Private DTW's - m3/day 49,700 49,700 49,700 49,700 49,700 49,700 37,275 37,275 34,790 34,790
KWASA HTW's - m3/day 20,187 20,187 20,187 20,187 20,187 20,187 10,093 7,065 6,056 5,047
KWASA DTW's 30,100 27,090 24,080 21,070 19,565 21,070 24,080 27,090 30,100 30,100
KCC Mini Tubewell Project 0 0 1,448 3,500 3,500 3,500 2,500 1,500 500 0
GoB - Deveopment of Water Supply In Khulna City 0 10,769 20,000 20,000 20,000 20,000 20,000 20,000 20,000 20,000
KWASA Groundwater Into Piped Supply - m3/day 30,100 37,859 45,528 44,570 43,065 44,570 46,580 48,590 50,600 50,100
AQUIFER VOLUME UNEXPLOITED - m3/day 59,000 51,241 43,572 44,530 46,035 44,530 65,038 66,056 67,541 69,050
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 13 of 60
Table 6: Demand Forecast and Derived Service Coverage Ratios
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020Per Capita Consumption - l/c/d 70 82 105 120 120 120 120 120 120 120
Domestic Demand Derived from Population - m3/day 16,629 21,120 29,143 35,827 38,347 40,867 76,053 84,749 92,000 96,779
Commercial Use % 7.9% 7.9% 8.4% 10.0% 10.0% 10.0% 10.0% 10.0% 10.0% 10.0%
Commercial Volume Derived from Domestic - m3/day 2,341 2,973 4,403 6,514 6,499 6,811 11,701 12,107 13,143 13,826
NRW % 36.0% 36.0% 36.0% 35.0% 31.0% 30.0% 25.0% 20.0% 20.0% 20.0%
NRW Volume derived from Domestic - m3/day 10,670 13,552 18,870 22,799 20,148 20,433 29,251 24,214 26,286 27,651
Total Water Into Supply Required - m3/day 29,640 37,644 52,416 65,139 64,994 68,111 117,005 121,070 131,429 138,255
KWASA Production Capacity - m3/day 30,100 37,859 52,957 65,606 65,815 68,320 162,427 165,437 168,447 167,947
Production Surplus/-Deficit - m3/day 460 215 541 466 821 209 45,422 44,367 37,018 29,692
Total Water For Revenue Generation 29,640 37,644 52,416 65,139 64,994 68,111 117,005 121,070 131,429 138,255
Domestic Volume - m3/day 16,629 21,120 29,143 35,827 38,347 40,867 76,053 84,749 92,000 96,779
Commercial Volume - m3/day 2,341 2,973 4,403 6,514 6,499 6,811 11,701 12,107 13,143 13,826
NRW Volume - m3/day 10,670 13,552 18,870 22,799 20,148 20,433 29,251 24,214 26,286 27,651
Utilisation of New SWTP Volume (%) 50% 51% 59% 67%
Volume output of New SWTP - m3/day 45,675 46,730 54,079 61,405
Households Supplied 43,192 46,828 50,465 54,283 58,101 61,919 115,232 128,408 139,394 146,634
Households : Connections Ratio 2.82 2.82 2.82 2.82 2.82 2.82 2.82 2.82 2.82 2.82
Domestic Connections Supplied 15,316 16,606 17,895 19,249 20,603 21,957 40,863 45,535 49,430 51,998
Non Domestic Connections Supplied 867 1,101 1,631 2,413 2,407 2,523 4,334 4,484 4,868 5,121
Total Connections Supplied 16,183 17,707 19,526 21,662 23,010 24,480 45,196 50,019 54,298 57,119
Population Supplied by KWASA Network 237,555 257,555 277,555 298,555 319,555 340,555 633,778 706,244 766,667 806,489
Service Coverage KWASA Network 24.1% 25.6% 27.1% 28.5% 29.9% 31.3% 57.0% 62.3% 66.3% 68.4%
Service Coverage KWASA HTW's 34.1% 33.4% 32.8% 32.1% 31.5% 30.9% 15.1% 10.4% 8.7% 7.1%
Service Coverage Private DTW's 41.8% 41.0% 40.2% 39.4% 38.6% 37.8% 27.8% 27.3% 24.9% 24.5%
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 14 of 60
D. INVESTMENT PLAN In order to achieve the stated objectives of attaining 24 hour supply and increasing the coverage of piped water supply in Khulna City a number of key investment and grant projects are being planned.
D1. Projects Included in the Investment Plan
D1.1 Projects Approved & Budgeted
Development of Water Supply System in Khulna – total value 4,320 lakh Taka, Grant Funds from GoB
The project is split into 2 parts;
Part 1: Additional groundwater abstraction from Khulna City Aquifer through the construction of 13 deep tube wells – 20 Mld (Tk 3,142);
Part 2: Upgrade and expansion of existing surface water treatment plant – 6.75 Mld (Tk 1,175);
Project approval has already been given and KWASA are commencing the implementation, the project will be implemented over a two year period with 10 Mld becoming available in 2012 and the balance in 2013. Tenders have been issued for borehole construction and consultants appointed to manage the project from January 2011. Anticipated timeframes appear to be realistic.
KCC Mini-Tube well project – GoB grant project being implemented by KCC and to be handed over to KWASA on completion; the scheme is to provide an additional 3.5 Mld in specific water stressed areas of Khulna.
Import of groundwater from an adjacent aquifer in Phultala, funded by KCC. GoB grant project being implemented by KCC and to be handed over to KWASA on completion; the original scheme was for the production of 28 Mld for use in KWASA service area; The scheme has been constructed however there is now a court injunction in place preventing the use of the well field; ADB have been supporting technical investigations into the availability of water from the aquifer and the impact of the well field on the surrounding area of Phultala. It is expected that eventually the well field will be handed over to KWASA to abstract 20 Mld; The timing of this has been assumed as FY 2015 - the timing of resolution of the political difficulties is hard to predict we have therefore assumed a medium time frame for this, once the political issues are sorted out the technical commissioning issues will still need to be resolved – this gives weight to the proposed delivery time frame assumed;
D1.2 Investment Projects at Feasibility/Pre-approval Stage:
Construction of a new surface water treatment plant using JICA loan funding. The project is expected to be on line mid-way through FY 2017 providing an additional usable volume 91.1 Mld; Thorough details of this project are included in the JICA Feasibility Study – the JICA component of the project covers packages1 and 2 – Intake, raw water transmission, Water Treatment Plant, clear water Transmission pump station.
Construction of new distribution storage and network assets, including customer connections to be able to utilise the increased volume of water through the new SWTP – using ADB loan funding; Details of the project were initially outlined in the JICA Feasibility Study (Packages 3 & 4) and have since been developed by TA7385 team. The proposed capital investment plan is included separately within the ADB project report.
D1.3 Additional Projects Identified Under ADB TA 7385 A number of projects outside the original scope of the JICA/ADB were identified during the ADB TA 7385. These additional projects cover:
Production tubewell rehabilitation;
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 15 of 60
Deep aquifer test drilling; Construction of KWASA head and zonal offices; Provision of customer meter testing/laboratory equipment; Provision of operational vehicles; Groundwater monitoring system; Business systems hardware and software; Water point infrastructure for informal settlement areas;
The scope of these projects is documented within the ADB project report.
D1.4 Consultancy & Management Systems
Engineering Design, Tendering & Construction Implementation; Implementation of Management Systems – e.g. Customer Management; Accounting; Billing; Maintenance;
etc. Groundwater Monitoring Systems – to understand and ensure sustainability of the Khulna and Phultala
aquifers;
D2 Projects Not Included in Investment Plan Additional Groundwater abstraction from Khulna City Aquifer through the use of GoB funds – 16 Mld, Value Taka
2,287 Lakh; KWASA have submitted a DPP for this DTW construction project which is still undergoing approval. It has been assumed that this project will not push through.
Table 7 summarizes the project costs for the 5 major projects to be undertaken during the business plan period as included in the financial model.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 16 of 60
Table 7: Summary of Five Key Projects to be undertaken during the Business Plan Period by Project Totals
NB - Project 3 – KCC Development of Water Supply System in Phutala (20 Mld) and Project 5 – KCC Mini Tubewell Project will be implemented by KCC and handed over after completion to KWASA. The other projects will be implemented by KWASA.
SUMMARY INVESTMENT PLAN (In Current Tk 000s) FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 Total
PROJECT 1a- GoB Project: Development of Water Supply System in Khulna City - : 20 Mld 97,428 177,339 39,253 - - - - - 314,020 PROJECT 1b - GoB Project: Development of Water Supply System in Khulna City - 6.75 Mld SWTP - 55,776 61,681 - - - - - 117,457 PROJECT 2 - GoB Rehab Of DTW & Water Supply Expansion - 16mld - - - - - - - - - PROJECT 3 - KCC Development of Water Supply System in Phultala - (28 Mld) - - - - 339,350 - - - 339,350 PROJECT 4a - JICA Packages 1 & 2 - Intake, Raw Water Transmission & WTP - - 373,443 3,179,944 6,464,031 4,517,623 1,263,622 30,029 15,828,691 PROJECT 4b - ADB Packages 3 & 4 - Treated Water Transmission, Storage and Distribution - 1,506,363 3,829,562 1,270,837 1,352,143 688,805 589,736 195,296 9,432,741 PROJECT 5 - KCC Mini Tubewell Project -3.85 Mld 22,455 - - - - - 22,455
Total 97,428 1,761,933 4,303,939 4,450,781 8,155,524 5,206,427 1,853,358 225,325 26,054,715
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 17 of 60
E. Financial Plan Introduction
The financial plan is prepared over a longer period (FY 2012-2030) than the period of the business plan to ensure that KWASA will remain viable during the period of project implementation up to loan repayment of the ADB/JICA loan. Financial viability is demonstrated through the financial projections which show sufficiency of cash to cover operational expenses and debt service, thereby eliminating the need for government subsidy other than explicit exceptions in initial years.
Major Assumptions
The assessment of the current financial condition of KWASA in FY 2009 and FY 2010 is based on the Preliminary Financial Statements in Annex 2. These financial statements were based on studies prepared under the ADB SSTA as well as the JICA feasibility studies. It is understood that the figures presented in the Preliminary Financial Statements are estimated figures and the financial audit will provide a more sound basis for the assessing the current and future financial viability of KWASA. KWASA is taking steps to get the audit started and completed by end of 2010. When the audited financial reports are available, it may be necessary to revise the assessment of KWASA’s financial performance as well as its business plan.
Based on the preliminary financial statements, it appears that KWASA’s performance has deteriorated from FY2009 to FY2010. The net loss has increased from Tk 8.5 million to Tk 50 million due to the significant reduction in revenue and the huge increase in expenses. There were different bases for estimation of revenues for the two years. It appears that revenue estimates for 2009 were based on 15,236 registered connections while the figure for 2010 revenues is based on a significantly lower number of connections of 11,853 based on the survey results. Salaries and allowances increased due to implementation of the new pay scale as well as hiring of additional personnel. Electricity bill also increased due to the general increase in cost of power as well as the increase from 60 pumps in 2009 to 78 pumps in 2010. KWASA also undertook numerous repair and maintenance of pipelines, pump motors, vehicles, office equipment and buildings in 2010 resulting in higher repair costs.
In order to assess future performance, during the business plan period, the following basic assumptions were used:
1. Investment and Production. The investment plan shown in Table 7 above will increase production from 30,100 m3/day to 162,427 m3/day in 2017. Investments in the network will reduce Non Revenue Water from the current estimated level of 36% to 25% by 2017 and down further to 20% by 2018.
2. Revenues. Although the survey reports 32,292 domestic users, only 11,853 households are currently registered as connections. The rest are unbilled household users resulting from the practice of several households sharing a connection or else are illegal users. In the coming years, the KWASA will embark on five major programs to increase connections and bill all users as shown in Table 8 below.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 18 of 60
Table 8: Key Revenue Improvement Action Plan
3. O&M. Salaries and allowances will increase substantially as number of staff will increase from 284 to 502 by 2017. Average salaries and % allowances will also increase, the latter the result of the planned conversion of most of casual staff to permanent staff by 2017. Chemicals and Depreciation expenses will start to be recognized and recorded as part of O&M expenses.
See detailed assumptions in Annex 3.
Financial Model Base Case
The base case considers the following:
Tariff increases on the monthly flat rate at 5% per year from 2012 to 2016
At the start of the metering program in 2017, an initial tariff in real prices of Tk 13.10/m3 for domestic connections (Tk 19.35/m3 in 2017 prices) and Tk 26.20/m3 for non domestic connections (Tk 38.71/m3 in 2017 prices)
Annual tariff increases at 5% after 2017
30% of the project cost will be funded by government equity and 70% through government loan. The assumed concessional terms of the loan are 2% interest rate per annum, 30 years repayment including an 8 year grace period on principal and interest payment.
Numbers Fiscal Yeara Increase in number of connections from 2011 to 2017
as more volume of water is made available from ongoing and future projects. Domestic Connections (end of fiscal year) 11853 40863 FY 2017Non Domestic Connections (end of fiscal year) 385 4334 FY 2017
b Registration of all illegal connections 2206 illegal domestic connections and 138 illegal non domestic connections
zero FY 2012
c Conversion billing per household Domestic Households (end of fiscal year) 11853 32292 FY 2012
d Metering of all connections by 2017 (end of fiscal year) zero 45197 FY 2017
e Charging owners of private deep tubewells an annual flat fee
no charges 17,799 private DTWs billed
FY 2017
f Annual flat fee for deep tubewells Tk 3000 FY 2017
Present Target
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 19 of 60
Table 9 shows the results of the base case analysis which reveal the following:
While some years will result in annual cash deficits, KWASA’s cash balances will be sufficient to cover cash operating and maintenance costs and debt service.
Debt service coverage ratios are generally lower than the standard 130%, but this target will eventually be met in future years
Operating ratio before depreciation shows significant improvement from the current 5.17 to .45 in 2017 when the metered tariffs are implemented. As a result, net income ratio also improves in the coming years with the implementation of tariff increases and the growth in connections.
See Annex 4 showing the resulting financial projections for the base case.
Table 9: Results of Base Case
Sensitivity Scenarios
Two other scenarios were developed to test the financial viability of the project under the standard terms for relending to WASAs. See Table 10.
Year
2010 (28,513) 27,108 5.17 (4.17) 2011 32,571 59,679 4.17 (5.22) 2012 57,926 117,605 1.48 (1.26) 2013 57,607 175,212 1.52 (1.26) 2014 (48,320) 126,893 1.97 (1.47) 2015 (38,584) 88,308 1.57 (1.06) 2016 (37,629) 50,679 1.49 (1.11) 2017 337,199 387,878 0.45 0.47 19.35
2018 528,983 916,862 0% 0.38 0.58 20.32 5%2019 619,334 1,536,195 0% 0.36 0.61 21.34 5%
2020 (398,936) 1,137,260 65% 0.35 0.28 22.41 5%
2021 (383,485) 753,775 68% 0.38 (0.14) 23.53 5%
2022 (303,092) 450,683 74% 0.38 (0.07) 24.70 5%
2023 (230,060) 220,623 81% 0.37 0.00 25.94 5%2024 (151,457) 69,166 88% 0.36 0.06 27.23 5%2025 (58,136) 11,030 97% 0.36 0.05 28.60 5%
SCENARIO 1 (Option 1) - Selected KPIs
Annual Cash Surplus
(Defiiciency)
Ending Cash
(Tk000)
Debt Service Ratio
Operating Ratio before
depr
Net Income Ratio
Domestic Tariff
Tariff Adjustment
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 20 of 60
Table 10: Financial Model Scenario Variables
The scenario analysis results reveal the following:
Under Scenario 2, KWASA’s operations will result in substantial losses and cash deficits under a scenario where lower tariffs (domestic tariff of Tk 6/m3 and non domestic tariff of Tk 12/m3, both in real prices) are implemented.
Under Scenario 3, KWASA’s revenues can recover O&M costs and debt service under a scenario where higher tariffs (domestic tariff of Tk 26/m3 and non domestic tariff of Tk 52/m3, both in real prices) are implemented.
The results of the sensitivity analysis are given in Annex 5.
Scenario 1 (Base) Scenario 2 Scenario 3
TariffsStarting Tariff (2009 prices)
Domestic connections Tk 13.10/m3 Tk 6.00/m3 Tk 26.00/m3Non domestic connections Tk26.20/m3 Tk12.00/m3 Tk52.00/m3
Annual Tariff Increases starting 2012 5% 5% 5%
Financing% Grant, % Loan 30% Grant; 70% Loan 30% Grant; 70% Loan 30% Grant; 70% Loan
Loan termsInterest Rate 2% 4% 4%
Grace/Repayment period8 years grace period, 22 years repayment
period
7 years grace period, 15 years repayment
period
7 years grace period, 15 years repayment
period
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 21 of 60
F. Human Resources Development Plan F.1 KWASA Human Resource Management
F.1.1 Introduction
The success of an organisation is determined largely by its workforce through their experience, capability, dedication and willingness to change to meet the needs of the business environment. To date KWASA have been under-resourced in particular in relation to junior and middle management and engineering staff. Additional staff to complete the approved structure is now largely in place however a key area of focus for KWASA over the next few years is the development of staff capabilities across all areas of operation. In addition to having in place the right, properly trained staff the structure of any organisation plays an essential role in determining the efficiency of the organization in delivering services effectively. Significant changes are planned for KWASA in the next 10 years starting immediately with the rationalisation of customers to correctly reflect the customer base, investment (with GOB funds) in groundwater development schemes, opening of zonal offices within the city of Khulna, move to customer metering and volumetric charging for water, development of a major surface water treatment plant and the introduction of treated water storage and distribution on a zonal basis across the city significantly increasing the service coverage and customer base. All these changes require appropriate organization structures to be in place if the benefits of the changes are to be realised by KWASA customers.
F.1.2 KWASA Current Organisation Following KWASA’s establishment under the WASA Act 1996 in February 2008, a new organisational structure was developed and approved by Local Government Division (LGD) in November 2008. The approved structure shown in Figure 1 below comprises of 2 main departments namely, Engineering and Finance & Administration and provides for a permanent staff complement of 157. Since its formation KWASA has been operating at sub-optimal staffing levels, in particular lacking qualified staff in accounting, planning and engineering disciplines. This issue has now been largely addressed through recruitment and the approved organisation structure of KWASA is almost complete. In addition there are 127 Master Roll staff (employed on a temporary basis although in practice most of them have been working with KWASA for many years), the majority of who work in Operations.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 22 of 60
Figure 1: Khulna WASA Organisation Structure - 2011
Financial (A/C & Budget)
Staff - 8
Commercial (Consumer &
Revenue)Staff - 12
HR Development
Staff - 8
General Section
Staff - 9
Production &
DistributionStaff - 72
Consumer Service O&M
Staff - 12
Planning &
Development Staff - 6
Project Mgmt &
ImplementationStaff - 4
Accts Officer - 1Budget Officer – 1Accountant – 1Lower Div Asst - 1Asst Acct. - 1Cashier - 1Asst. Cashier – 1MLSS – 1
Rev. Officer - 3Rev. Supervisor – 4Rev. Inspector – 2Lower Div Asst - 1Asst Acct. – 1MLSS – 1
Admin. Officer - 1Upper Div. Asst. – 1Guard – 2Cleaner/Gardener – 4
Medical Officer - 1Upper Div. Asst. – 1Storekeeper – 3Compounder – 1Dresser – 2Nurse – 1
Asst. Enggr - 1Sub Asst. Enggr – 2Pump Operator – 30Asst Pump Operator – 30Electrician – 2Head Tubewell Fitter – 1Filter Operator – 3Plumber – 2MLSS - 1
Asst. Enggr - 1Sub Asst. Enggr – 2Lower Div Asst. – 1Foreman - 1Electrician – 2Head Tubewell Fitter -1Surveyor – 1Plumber – 2MLSS - 1
Asst. Enggr - 1Sub Asst. Enggr – 2Head Asst – 1Draftsman - 1MLSS - 1
Asst. Enggr - 1Sub Asst. Enggr – 2Surveyor – 1
Commercial ManagerStaff - 23
SecretaryStaff - 20
Chief EngineerStaff - 89
Superintending EngineerStaff - 15
Executive EngineerStaff - 86
Executive EngineerStaff - 12
Typist – 1MLSS – 1
Typist – 1MLSS – 1
Typist – 1MLSS – 1
Typist – 1MLSS – 1
Deputy Managing Director(Finance & Administration)
Permanent Staff – 46(Master Roll Staff – 16)
Typist – 1; MLSS – 1Typist – 1; MLSS – 1
Deputy Managing Director(Engineering)
Permanent Staff – 107(Master Roll Staff 111)
Managing DirectorPermanent Staff – 157(Master Roll Staff 121)
Computer Operator – 1MLSS – 2
KHULNA WASA ORGANISATION STRUCTURE - 2011
MLSS – 1MLSS – 1
Summary of Master Roll Staff:
Finance & Administration Division: 16; Engineering Division: 111; Total: 127
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 23 of 60
The existing staff numbers by Government Classification are shown in Table 11 below.
Table 11: Summary of KWASA Existing Staff Numbers by GoB Classification
TOTAL KWASA Current Structure
Approved Staff
Master Role Staff
Total Staff
Staff % by
Class CLASS I: Grade 1 to 9 14 0 14 4.9%
CLASS II: Grade 10 13 0 13 4.6% CLASS III: Grade 11 to 16 84 118 202 71.1%
CLASS IV: Grade 17 to 20 46 9 55 19.4%
TOTAL 157 127 284 As can be seen the structure is very much skewed to Classes III and IV – workers and labourers with less than 10% of the staff involved in management, supervision or engineering. In order to be able to manage the growth and development of KWASA in the future there is a need to change the organisation accordingly to make it responsive to the needs of the customer and capable of delivering efficient services at affordable prices. The basic principles in the organisation development of KWASA are:
• Separation of the finance and revenue functions for accountability purposes; • Establish a clearer customer focus through the organisation structure – introduction of customer service
accountability through a commercial Directorate and move towards a zonal operating structure in order to be more responsive to customers.
• Internal audit and corporate planning functions should be introduced to the organization; • The organisation should support the sustainable operation and maintenance of all KWASA facilities;
A two-phase evolution in KWASA organisation from the current structure has been developed. It is assumed that the current structure will remain in place until the zonal offices in Khulna town are constructed and operational in FY 2014. This evolution takes into the key factors related to organisation change in KWASA, namely:
Customer focus; Affordability; Staff location/deployment; Support Infrastructure; Growth in KWASA asset base; Introduction of new facilities -SWTP; additional boreholes; new network storage; new network;
It is essential that KWASA is correctly organized in order to manage the new facilities being constructed under the JICA/ADB loan facilities; both of the phases are discussed in more detail below.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 24 of 60
F.1.3 Phase 1 Organisation Phase 1 organisation will come into effect at the start of FY 2014. At this time a Commercial Directorate overseen by a DMD will be established. This will be the first step in establishing a more customer focused delivery mechanism. The Commercial Directorate will have responsibility for customer service, revenue and accounting functions – separating these responsibilities from their current position under the DMD Finance and Administration; for operational purposes KWASA will locate production distribution teams at the newly constructed zonal offices however they will continue to be managed from the centre of the organization. To support the MD function a number of functional teams will be introduced to cover corporate planning, internal audit, MIS/IT and legal. The total staff requirement for this organization structure is 371 an increase of 87 staff. The staff numbers by Government Classification to Phase 1 are shown in Table 12 below.
Table 12: Summary of KWASA Staff Numbers by GoB Classification to Phase 1
TOTAL KWASA
Current Structure
Organization Phase 1 - FY2013 - 2017
Approved Staff
Master Role Staff
Total Staff
Staff % by Class
Total Staff
Staff % by
Class CLASS I: Grade 1 to 9 14 0 14 4.9% 36 9.7%
CLASS II: Grade 10 13 0 13 4.6% 27 7.3% CLASS III: Grade 11 to 16 84 118 202 71.1% 172 46.4%
CLASS IV: Grade 17 to 20 46 9 55 19.4% 136 36.7%
TOTAL 157 127 284 371
Of particular note is the increase of management and technical specialist staff in Classes I and II by 22 and 14 respectively. The number of Class I & II staff as a percentage of total staff increase from 9.5% to 17% which is a more acceptable ratio for efficient operation of the business; additionally the number of Class three staff is reduced in absolute terms and the number of Class 4 staff increased. Figure 2 below shows the organisational linkages and functionality along with staff numbers at Division level.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 25 of 60
.Figure 2: Phase 1 Organisation Structure – FY 2014
MANAGING DIRECTORS OFFICE
ENGINEERING DIVISION
CUSTOMER SERVICE DIVISION
FINANCE & ADMINISTRATION DIVISION
Production &DistributionDepartment
Planning & Development Department
Customer Service
Department
AdministrationDepartment
Finance & Accounting Department
Customer Accounts
Department
• Production Section• Distribution Section
• Planning & Design Section• Project Management &
Implementation Section
• Credit & Collection Section• Customer Service Section
• Meter Reading Section• Billing Section
• Accounting Section• Budget & Treasury Section
• Human Resources Section• General Services Section
• Internal Control/Audit• Corporate Planning & MIS• Legal• Public Affairs and Information
Management Services Section
KWASA PROPOSED ORGANISATION STRUCTURE – 2014
205
371
6488
10
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 26 of 60
F.1.4 Phase 2 Organisation
Phase 2 organisation structure will be set in place from commissioning of the newly planned SWTP and distribution storage zones in 2017. This maintains the previously established three directorate structure however the Commercial Division is re-focused on whole cycle business delivery. The proposed structure is summarised in Figure 3. The total staff requirement for this organization structure is 502. The key features and changes in each Division are discussed in more detail below. Commercial Division: There will be three customer service zones each under the responsibility of a zone manager who will have complete responsibility for all customer service activities carried out in his zone – this includes management of distribution storage reservoirs and overhead tanks; management of the distribution network; revenue management (billing and collection – current and arrears); customer complaint management; connection and meter management; The operating zones have been allocated according to number of connections to ensure some equitability in resource allocation, level of activity etc. Technical Services Division: The Technical Services Division comprises all production activities – surface water treatment plant as well as borehole management; A Maintenance department is also created under this organisation structure to reflect the need for effective maintenance of newly installed assets. The maintenance department will also be responsible through service level agreements for the maintenance of mechanical and electrical equipment used in the Customer Zones (i.e. pumps and motors at the distribution storage reservoirs and overhead tanks). Finance & Administration Division: The fundamental changes to the Finance & Administration Division will have taken place at the Phase re-organisation, namely separation of Accounting and Revenue Functions and introduction of Internal Audit under the office of the Managing Director. The staff numbers by Government Classification for all organisational phases are shown in Table 13 below. Table 13: Summary of KWASA Staff Numbers By GoB Classification All Phases
In the Phase 2 organisation the percentage of Class I and Class II staff reduces very slightly on the Phase 1 structure to 15%; the absolute number of Class II staff remains almost the same and the most significant increase in staff comes in the Class 4. Figure 3 below shows the organisational linkages and functionality along with staff numbers at Division level.
Approved Staff
Master Role Staff
Total Staff
Staff % by Class Total Staff Staff % by
Class Total Staff Staff % by Class
CLASS I: Grade 1 to 9 14 0 14 4.9% 36 9.7% 41 8.2%
CLASS II: Grade 10 13 0 13 4.6% 27 7.3% 34 6.8%
CLASS III: Grade 11 to 16 84 118 202 71.1% 172 46.4% 208 41.4%
CLASS IV: Grade 17 to 20 46 9 55 19.4% 136 36.7% 219 43.6%
TOTAL 157 127 284 371 502
TOTAL KWASA
Current Structure Organisation Phase 1 - 2014 - 2017
Organisation Stage 2 - 2017 Onwards
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
\
Page 27 of 60
Figure 3: Phase 2 Organisation Structure FY 2017
MANAGING DIRECTORS OFFICE
TECHNICAL SERVICES DIVISION
COMMERCIAL SERVICES DIVISION
FINANCE & ADMINISTRATION DIVISION
Production Department
Planning & Development Department
Maintenance Services
Department
Customer Service
Zone 1 & 4
AdministrationDepartment
Finance & Accounting Department
CustomerService
Zone 3 & 5
Customer ServiceZone 2
• SWTP Operation Section• Wells Section
• Planning & Design Section• Project Monitoring &
Implementation Section
• Maintenance Section
• Revenue Section• Customer Service Section
• Revenue Section• Customer Service Section
• Revenue Section• Customer Service Section
• Accounting Section• Budget & Treasury Section
• Human Resources Section• General Services Section
• Internal Control/Audit• Corporate Planning & MIS• Legal• Public Affairs and Information
Management Services Section
KWASA PROPOSED ORGANISATION STRUCTURE – 2017
207
502
71210
10
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 28 of 60
F.1.5 Staff Efficiency Ratios
In terms of the traditional measure of organization efficiency – no. of staff per ‘000 connections - KWASA efficiency is currently poor. Table 14 below shows the improvement in this ratio during the period of the Corporate Plan. It should also be noted that when the new SWTP volume is fully utilised in 2025 the staff ratio is forecast to be 6.1 staff/’000 connections.
Table 14: Summary of Connections and Staff Efficiency Ratio through the Corporate Plan Period
2011 2012 2013 2014 2015 2016 2017 2018
Total Connections 16,655 18,472 20,686 22,815 24,517 26,215 52,708 59,112
Staff/’000 Connections 17.1 15.4 17.9 16.3 15.1 19.1 9.5 8.5
Total Households 35,881 39,518 43,154 46,972 50,790 54,608 111,577 125,849
Staff/’000 Households 7.9 7.2 8.6 7.9 7.3 9.2 4.5 4.0
F.1.6 Organisation Development During Business Plan Period
Table 15 below shows the breakdown of staff by Division and by Department under each organisation structure. It clearly shows the migration of the structure from the current situation to the proposed structure on commissioning of the new facilities under the loan project.
Tables showing Department and Section staffing numbers are shown in Annex 6.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 29 of 60
Table 15: Structure and Staff Numbers
EXISTING STRUCTURE 2011 PROPOSED STRUCTURE 2014 PROPOSED STRUCTURE 2017
ORGANISATIONAL UNIT Staff Numbers ORGANISATIONAL UNIT Staff
Numbers ORGANISATIONAL UNIT Staff Numbers
THE MANAGING DIRECTOR THE MANAGING DIRECTOR THE MANAGING DIRECTOR Managing Director and Staff 4 Managing Director and Staff 4 Managing Director and Staff 4
Management Services Section 10 Management Services Section 10 4 14 14 ENGINEERING DIVISION ENGINEERING DIVISION TECHNICAL SERVICES DIVISION
Office of the DMD 4 Office of the DMD 3 Office of the DMD 3 Chief Engineers Office 3
Production & Distribution Department 186 Production Department 146 Production, Distribution, Consumer Service Department 196
Superintending Engineers Office 3 Planning and Development Department 16 Planning and Development Department 16 Planning, Development & Project Management
Department 12
Maintenance Services Department 42 218 205 207 FINANCE AND ADMINISTRATION DIVISION FINANCE AND ADMINISTRATION DIVISION FINANCE AND ADMINISTRATION DIVISION
Office of the DMD 3 Office of the DMD 3 Office of the DMD 3 Office of the Commercial Manager 3
Finance and Accounting Department 17 Finance and Accounting Department 18 Finance and Commercial (Revenue) Department 34
Office of the Secretary 4 Administration Department 44 Administration Department 50
Administration, HR & General Department 18 62 64 71 CUSTOMER SERVICE DIVISION COMMERCIAL SERVICES DIVISION Office of the DMD 3 Office of the DMD 3 Customer Service Department 29 Customer Service Zone 1 & 4 Department 69 Customer Revenue Department 56 Customer Service Zone 2 Department 69 Customer Service Zone 3 & 5 Department 69 88 210
TOTAL 284 371 502
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 30 of 60
F.2 KWASA Capacity Building
KWASA will be a professionally managed utility tasked with improving services through operations and infrastructure investment.
In order for KWASA to achieve their objectives of increased service coverage and continuity of supply they will require operational and management support in advance of the anticipated investment such that they can function effectively and efficiently once the investment has been realized.
To this end two Capacity Building support components will be initiated as a result of the loan agreement, namely:
1. Bridging TA Capacity Building – this will be a TA grant from ADB to KWASA to cover the period between the end of the current TA7385 in January 2011 and the mobilization of Capacity Building consultants under the second CB component described below;
2. Corporate Management Support Capacity Building – will be funded through the ADB loan to support the KWASA to fulfill its service mandate and its responsibilities in order to manage and operate the capital works financed under the ADB Loan. This Capacity Building will cover support and advice in the following areas:
(i) KWASA operations, including institutional reform and organizational strengthening; HR management and training needs analysis;
(ii) Implementation of the KWASA business plan;
(iii) Operations and management systems;
(iv) Implementation of a pilot Distribution Network Improvement (DNI) initiative, including NRW management and reduction strategies;
(v) network implementation project;
(vi) Expand and institutionalize sustainable service provision to low income consumers; and
(vii) Establishing sound practices in program monitoring and evaluation, and results measurement.
Outline TOR for each of the Capacity Building packages are included in the TA 7385 ADB Project Final Report April 2011.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 31 of 60
Annex 1 - Summary of Proposed Capital Investment for KWASA under GOB/JICA/ADB Loan
% of total cost Including Taxes % of total costA. Base Cost 1. Civil Works and Equipment 238,889,613 65.71% 293,688,399 80.79% 2. Consultants 18,210,602 5.01% 21,778,576 5.99% 3. Resettlement Cost 5,926,737 1.63% 5,926,737 1.63% 4. Administration Cost 1,614,410 0.44% 1,614,410 0.44%Sub-total A 264,641,363 72.80% 323,008,123 88.85%B. Contingencies 1. Physical 13,603,433 3.74% 13,603,433 3.74% 2. Price 24,266,056 6.68% 24,266,056 6.68%Sub-total B 37,869,489 10.42% 37,869,489 10.42%C. Interest During Implementation 2,655,237 0.73% 2,655,237 0.73%Sub-total C 2,655,237 0.73% 2,655,237 0.73% D Tax and duties 58,366,760 16.06%Grand Total 363,532,849 100.00% 363,532,849 100.00%
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 32 of 60
Annex 2 - Preliminary Financial Statements for FY 2009 and FY 2010 A. General Assumptions KWASA uses a fiscal year (FY) ending June 30 in its financial reporting. KWASA was created in March 2008 and is yet to prepare FY 2009 and FY2010 Financial Statements and have these reports audited. In view of the urgency to complete the business plan in time for the ADB/JICA Mission in November 2010, there was a need to estimate KWASAs results of operations for FYs 2009 and 2010 and its financial condition as of FY 2010 as a starting point for the financial projections, which is a key feature of the business plan. The ADB TA consultants estimated income and balance sheet figures for FY 2009 based on studies prepared in the ADB SSTA5 as well and the JICA feasibility studies6. The ADB TA consultants also prepared preliminary financial reports for FY 2010 based on available data. Notes showing the basis of the figures are discussed in this Appendix. It is understood that the figures presented in the Preliminary Financial Statements are indicative figures and the financial audit will provide a more sound basis for the assessing the current financial viability of KWASA, which is also the basis for its future viability. KWASA is taking steps to get the audit started and completed by end of 2010. When the audited financial reports are available, it may be necessary to revise the assessment of KWASA’s financial performance as well as its business plan. For FY 2010, it is estimated that around Tk 39 million was received by KWASA as government subsidy. This is shown under the account name capital fund. These preliminary financial reports were discussed with KWASA accounting unit which accepted the valuation pending the results of the audit. See Tables Ap2.1 and Ap2.2.
5 Supporting the Establishment of Khulna Water Supply and Sewerage Authority (ADB TA 7223-BAN), Final Report, November 2009. 6 Feasibility Study for Khulna Water Supply Improvement Project in Bangladesh, Japan International Cooperation Agency, July 2010.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 33 of 60
Table Ap2.1. Preliminary Income Statement FY 2009 and 2010
Notes Inc/Dec
IncomeOperating Revenues 16,444 100.0% 11,764 100.0% -28%
Water Sales 1 15,898 96.7% 11,121 94.5% -30%Other Water Sales 2 96 0.6% 167 1.4% 74%New Connection Fees 450 2.7% 476 4.0% 6%
Non-Operating Revenues 2 64 0.4% 109 0.9% 70%Total Income 16,508 100.4% 11,873 100.9% -28%
ExpensesPersonnel Expenses 3 17,758 108.0% 36,696 311.9% 107%
Salaries and Wages 15,591 94.8% 29,011 246.6% 86%Allowances and Benefits 2,167 13.2% 7,684 65.3% 255%
Fuel and Electricity 4,659 28.3% 11,230 95.5% 141%Fuel 547 3.3% 1,401 11.9% 156%Electricity Bill 4,112 25.0% 9,830 83.6% 139%
Chemicals 0.0% 0.0%
Repair & Maintenance 546 3.3% 5,497 46.7% 907%0.0%
Plant & Machinery 163 1.0% 753 6.4% 362%Vehicles 288 1.8% 0.0% -100%Office 95 0.6% 4,744 40.3% 4893%
Administrative and General Expenses 2,081 12.7% 8,005 68.0% 285%Advertisement Expenses 182 1.1% 629 5.3% 245%Representation and Entertainment 19 0.1% 116 1.0% 513%Board Expenses 333 2.0% 407 3.5% 22%Office Supplies and Other Expenses 1,298 7.9% 4,272 36.3% 229%Communications 1 0.0% 320 2.7% 31895%Trade Union Fee 4 0.0% 0.0% -100%Travelling Expense 190 1.2% 658 5.6% 246%Miscellaneous Expenses 54 0.3% 1,603 13.6% 2869%
Total Expenses 25,044 152.3% 61,428 522.2% 145%Net Profit/Loss (8,536) -51.9% (49,555) -421.2% 481%
June 30, 2009 June 30, 2010
Khulna Water Supply and Sewerage Authority (KWASA)Income Statement
For the Period Ending 30 June 2009 and 2010In Thousand Taka
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 34 of 60
Table Ap2.2. Preliminary Balance Sheet FY 2009 and 2010
IAS RefAccount Code
# ASSETS
IAS 1.51 Non-Current Assets
IAS 1.68(a)# Property, plant & equipment 4 483,056 11,738 496,294 1,500
# Capital work in progress 4 1,500 1,500 -
IAS 1.51# Current Assets
IAS 1.68(g)# Stock & stores 5 702 2025 2,727 IAS 1.57, 1.68(h)# Accounts receivable 6 48,270 11121 8976 50,415
IAS 1.57, 1.68(h)# Advance, deposits and prepayments,
deferred assets, others7 3,668 1505 5,173
IAS 1.68(i)# Cash & bank balance 8 55,621 752 11,738 27,107 8976 61428
38994 20251505
IAS 1.51 540IAS 1.68(p), 75(e)# Total current assets 108,261 85,422
# Total assets 592,817 581,716
EQUITY FUNDIAS 1.51 Capital fund 9 590,282 38994 629,276
Retained earnings (8,536) 61428 11121 (58,091) IAS 1.51 752
Total equity fund 581,746 571,185 IAS 1.60, 1.68 (j)#IAS 1.60, 1.68 (j)# LIABILITIES
Current Liabilities
Accounts payable for expenses 10 840 840 Creditors for expense 10 10,231 540 9,691 Total current liabilities 11,071 10,531
Total liabilities and owners' equity 592,817 581,716
In thousand TakaAs at 30 June 2009 and 2010
Balance SheetKhulna Water Supply and Sewerage Authority (KWASA)
Notes June 30, 2009 June 30, 2010Addition Deduction
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 35 of 60
B. Notes to Preliminary Financial Statements
1. INCOME STATEMENT ITEMS
Note 1 - Revenues The major revenue item is the operating income from water sales from connections amounting to Tk 11.12 million which was estimated based on the number of active connections resulting from the survey conducted in 2010 as shown in Table Ap2.1. KWASA computed revenues at a higher figure of Tk 16 million based on total number of connections of 15718. It was agreed that these are still estimates and the audit will provide the final actual figures. Table Ap2.3 – Estimated Revenues in 2010
Note 2 – Figures for other water sales (water sales through delivery trucks), new connection fees and other non-operating revenues were derived from KWASA’s Collection Report for FY 2010.
Note 3 - Operating and Maintenance (O&M) Costs were obtained from KWASA’s Summary of Expenditures for FY 2010.
Service Connections Dom Non-Dom Total1/2" 1,787 17 1,804 3/4" 9,698 244 9,942 1" 353 95 448 1.5" 15 20 35 2" 9 9 Total 11,853 385 12,238
Monthly Bill RateDia1/2" 45 3/4" 70 1" 200 1.5" 1,200 2" 2,000
Annual Water SalesDia1/2" 0,9743/4" 8,3511" 1,0751.5" 0,5042" 0,216
11,121
Estimated Revenues (Tk 000)
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 36 of 60
2. BALANCE SHEET ITEMS Note 4 - Fixed Assets – Table Ap2.4 shows the FY 2009 opening balances based on the SSTA and the JICA studies as well as the additions to fixed assets based on (i) KWASA Summary of Expenditures and (ii) the capital works in progress transferred to Fixed Asset in FY 2010.
Capital Works In Progress (CWIP) - Based on the SSTA Study, as of 30 June2009, KWASA has a total of Taka 1.5 Million in its Capital Works in Progress (CWIP) account. There are no details available as to when these assets will be finally commissioned as well as the breakdown into specific property, plant and equipment categories. It is assumed that the capital works are part of the works being done on the office buildings for which there was substantial activity in FY 2009 and 2010. The beginning balance of Taka 1.5 Million is assumed to have been part of work that has been completed and therefore transferred to Fixed Assets – Building in FY 2010 as part of additions totaling Taka 4.68 million. Note 5 – Inventory represents the beginning balance plus purchases for the year amounting to Tk 2.7 million.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 37 of 60
Table Ap2.4 Fixed Assets
Note 6 - Receivables
(From KWASA Expenditures)Additions Balance
LandUnderwater Clearing water 999,999 WASA Office 108,889 Nirala pump house 53,965 Car Parking 105,744 Pump house at hospital 139 Shahid hadis park pond 696,310 1,965,046 1,965,046
Tubewell50 Production tubewell 150,000,000 14 Mini production tubewell 17,000,000 mini production tubewellDhaka sanitary store 833,964 MK Construction 833,964 3270 1.5" deep Tubewell 100,000,000 5560 1.5" shalow tubewell 40,000,000 Tubewell-shallow and deep 409,000 Deep tubewell 2,447,952 Shallow Tubewell 748,524 312,273,404 1,571,187 313,844,591
Transmission and distribution lines220Km main pipeline 88,000,000 Pipeline (7KM) 3,145,056 91,145,056 91,145,056
Buildings (Including Construction in Progress of Taka 1.5 million)KWASA (Ground Floor) 5,000,000 KWASA (First Floor) 3,036,543 8,036,543 4,682,278 12,718,821
Sewerage 11,000,000 11,000,000 11,000,000 Safety tank
Pump houseNirala 4,000,000
Pump Dhaka sanitary 371,668 4,371,668 2,323,322 6,694,990
Motor VehicleKhulna Mettro-Kha-11-0133 850,000 Khulna Mettro-E-11-0002 987,800 Sprinkler 1,280,000 Bowser 920,390 Khulna Mettro-Mo-02-0027 725,000 4,763,190 4,763,190
Furniture and FixtureChairman's office 33,228 Board room 162,251 Managing Director's office 188,693 MD Secretary and Chief Engineer' office 35,034 Furniture 388,300 807,506 4,661,672 5,469,178
Water Treatment PlantTreatment Equipment 135,900 New material list of chlorine saved 998,800 Spare parts list of Chlorine saved 394,500 Mini treatment plant 11,265,500 Chlorine equipment, pipelines and tubewell 13,800,000
22,098,800 48,693,500 48,693,500 Total 483,055,913 13,238,459 496,294,372
FY 2009(From SSTA Study)
FY 2010
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 38 of 60
Opening and Beginning balances for FY 2009 are based on the SSTA study and JICA study. For FY 2010, receivables are computed as follows:
KWASA believes that the actual figures for receivables is much less than this, at around Taka 20 million. This considered only unpaid amount during operations starting 2008 and was based on estimates for revenues based on total number of connections of 15718. It was agreed that these figures are still estimated and the audit will provide the final actual figures. Note 7 - Advance, Deposits, prepayments, deferred assets and others There is a total of Taka 1.504 million deferred assets were added to the beginning balance of this account resulting in an ending balance of Tk 5.173 million in FY 2010.
Note 8 – Cash
Total cash in bank amounted to Taka 27.11 million as of June 30, 2010 comprising the following.
Note 9 – Subsidy The cash flow statement in Table Ap2.5 shows a total subsidy received from the government amounting to Tk 38.99 million.
ReceivablesBeginning Balance 48,270 Add Water Sales July 1 to June 30, 2010 11,121 Less Collections 8,976 Ending Balance 50,415
Collection EfficiencyCollection 8,976 81%
Estimated Bills 11,121
Cash on Hand 0Cash in Bank
Janata Bank 17398Bank Asia 217Pubali Bank 9492Subtotal 27107
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 39 of 60
Table Ap2.5 Cash Flow
Khulna Water Supply and Sewerage AuthorityProjected Cash Flow Statement('000)
2010Estimated
Cash Balance, Beginning 55,621Add: ReceiptsOperations: - from Water Billings 8,976 - from Other Revenues 752 - from Accounts Receivables - Project Loans / Grant - Project Grants - Subsidies / Grants for Operations 38,995Miscellaneous ReceiptsTotal Receipts 48,723Less: DisbursementsOperations: - Operating Expenses 61,428 - Capital Expenditures 11,738 - Payment of Suppliers/Contractors (Accounts Payable) - - Purchase of Inventory 2,025 Project Disbursements - Loans / Grants - - Grants - Debt Service - Interests - - Principal - Miscellaneous 2,045 Total Disbursements 77,236 Cash Inflow (Deficit) (28,513) Cash Balance, Ending 27,108
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 40 of 60
Annex 3 – Financial Plan: Major Assumptions
A. GENERAL ASSUMPTIONS
1. KWASA uses a fiscal year (FY) ending June 30 in its financial reporting. KWASA was established in March 2008 and is yet to prepare FY 2009 and 2010 Financial Statements and have these reports audited. In the meantime, estimated income and balance sheet figures for these periods are shown in Annex 2 and were prepared based on the ADB SSTA7 as well and the JICA feasibility studies8. These preliminary financial reports were discussed with KWASA accounting section which accepted the preliminary financial reports pending the results of the audit.
2. The business plan covers the period up to 2030.
B. SUPPLY AND DEMAND
1. Production
As a result of 5 major projects, KWASA’s production capacity will increase from the existing 30,100 m3/day to 162,427 m3/day in 2017 as shown in Table 1. However not all of the water will be billed due to losses from NRW. Moreover, billed volume is less than available volume considering that some water cannot be billed for a full year as it takes time to install connections and bill the water.
Table 1. Production (m3/day)
7 Supporting the Establishment of Khulna Water Supply and Sewerage Authority (ADB TA 7223-BAN), Final Report, November 2009. 8 Feasibility Study for Khulna Water Supply Improvement Project in Bangladesh, Japan International Cooperation Agency, July 2010.
2010 2011 2012 2013 2014 2015 2016 2017
Existing 30,100 30,100 27,090 24,080 21,070 19,565 21,070 24,080PROJECT 1a- GoB Project: Development of Water Supply System in Khulna City - : 20 Mld 10,769 20,000 20,000 20,000 20,000 20,000
6,750 6,750 6,750 6,750- - - - - - - -
7,429 14,286 16,000 17,000 18,000- - - - - - - -
91,0971,448 3,500 3,500 3,500 2,500
30,100 30,100 37,859 52,957 65,606 65,815 68,320 162,427
PROJECT 1b - GoB Project: Development of Water Supply
PRODUCTION CAPACITY AND UTILIZATION
PROJECT 2 - GoB Rehab Of DTW & Water Supply PROJECT 3 - KCC Development of Water Supply System PROJECT 4a - JICA Packages 1 & 2 - Intake, Raw Water PROJECT 4b - ADB Packages 3 & 4 - Treated Water PROJECT 5 - KCC Mini Tubewell Project -3.85 MldTotal Production Capacity (m3/day)
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 41 of 60
2. Population Served
Based on the JICA Feasibility Study Report, the population of Khulna stood at 958,000 in 2009. Household size has been found, through customer surveys to be 5.5 persons/household. Population is forecast to increase annually at the rate of 2.0% based on the findings of the JICA Feasibility Study Report. KWASA serves its customers through connections and tubewells. KWASA currently serves 23% of the city population with piped water; this is expected to increase to 57% by 2017.
Table 2. Population Served
3. Consumption
Demand at the start of the business plan period as indicated by the consumption surveys carried out under ADB SSTA project are:
Domestic – 2010: 82 l/cap/d;
Non Domestic – 2010: 9.7 % of total demand;
It is assumed that per capita consumption will increase to 120 l/c/d by 2014.
Similarly it is assumed that non-domestic consumption remains at 81 m3/conn/month.
4. Demand
Table 3 shows that in 2014, the first year when there will be additional connections, there will be available water to allow for additional 10,995 households and 945 non domestic units to be served with water from the system. By 2017, a total of 56,284 additional households and 2,905 non domestic units will be served by the system.
Jun-10 2010/2011 2011/2012 2012/2013 2013/2014 2014/2015 2015/2016 2016/2017Base Data Assumptions - From JICAPopulation Growth Rate 2.0% 2.0% 2.0% 2.0% 2.0% 2.0% 2.0%Population Forecast (Rounded to '000) 966,500 986,000 1,006,000 1,026,000 1,047,000 1,068,000 1,089,000 1,111,000POPULATION BY SUPPLY SOURCEPopulation Supplied by Private Tube Well (Jica 3-25) 412,000 412,000 412,000 412,000 412,000 412,000 412,000 309,000Population Supplied by KWASA HTW (derived) 376,654 376,654 376,654 376,654 376,654 376,654 376,654 188,327
Other Population Supplied by HTW 188,212 188,212 188,212 188,212 188,212 188,212 188,212 94,106Slum/LIC population Supplied by HTW 188,442 188,442 188,442 188,442 188,442 188,442 188,442 94,221
Population Supplied by KWASA Network 177,846 197,346 217,346 237,346 258,346 279,346 300,346 613,673TOTAL POPULATION 966,500 986,000 1,006,000 1,026,000 1,047,000 1,068,000 1,089,000 1,111,000KWASA HTW Coverage 39.0% 38.2% 37.4% 36.7% 36.0% 35.3% 34.6% 17.0%KWASA Network Coverage 18.4% 20.0% 21.6% 23.1% 24.7% 26.2% 27.6% 55.2%Private Tube well coverage 42.6% 41.8% 41.0% 40.2% 39.4% 38.6% 37.8% 27.8%
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 42 of 60
Table 3. Demand
5. Water Loss9
The most current estimate of Water Loss in the KWASA piped network can be calculated by using data from three different sources:
Households and non-domestic connections served - from the Customer Census Survey;
Average consumptions for Domestic and Non-domestic - from the ADB Consumption Surveys (Domestic & Non-domestic);
DTW Production Volume – from the JICA FS estimate;
Table 4 below indicates that based on this data Water Losses are around 42%.
Table 4. CURRENT WATER LOSS
Domestic Demand Surveyed Domestic Connections (Legal and Illegal) 14,059
Households Served (hh:connection ratio 2.82) 39,639
Per Capita Consumption - l/c/d 82
Daily Domestic Demand - m3/day 17,881
9 The term Water Loss is used here rather than NRW as currently almost no revenue is collected. With the introduction of 100% metering as a result of the investment project KWASA will report NRW rather than water loss.
FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017
1 Households/ non domestic unitsExisting units
Actual households using KWASA water per survey 32,292 32,292 32,292 32,292 32,292 32,292 32,292 32,292 Actual non domestic units using KWASA water per survey 523 523 523 523 523 523 523 523
New units Domestic households Cumulative increases 10995 23900 27718 56284
Total (midyear) 43287 56192 60010 88576
Non Domestic Units Cumulative increases - - - 945 1887 1942 2905Total (midyear) 1468 2410 2465 3,428
Cumulative Total (midyear)Domestic households 32,292 32,292 32,292 32,292 43,287 56,192 60,010 88,576 Non Domestic Units 523 523 523 523 1,468 2,410 2,465 3,428
2 Demand Volume (m3/day)KWASA Network - Domestic 14,564 12,432 14,564 18,649 28,570 37,087 39,607 58,460 KWASA Network - Non Domestic 1,412 1,412 1,412 1,412 3,963 6,507 6,655 9,256
Demand volume from KWASA Network 15,976 13,845 15,976 20,061 32,533 43,593 46,262 67,716
DEMAND
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 43 of 60
Non Domestic Demand
Surveyed Non Domestic Connections 523
Average Consumption per Connection - m3/day 3 Daily Non Domestic Demand - m3/day 1,412
Total Demand - m3/day 19,293 Production - m3/day 30,100 Water Loss Volume - m3/day 10,807
Water Loss % 35.9%
The value of water loss is higher than the 18% that is assumed in the JICA model. The forecast of NRW in the financial model assumes that current losses will gradually be reduced to 25% until the year of commissioning of the new SWTP and will then decrease to 20% after the first year of operation of the new SWTP when all network will have been replaced – the assumption is that of the 20% NRW – 15% will be due to technical losses and 5% due to commercial loss.
C. REVENUES
1. Revenue Improvement Program
Although the survey reports 32,292 household users, only 11,853 households are currently registered. The rest are unbilled household users resulting from the practice of several households sharing a connection or else are illegal users. In the coming years, the KWASA will embark on five major programs to increase connections and bill all users as shown in Table 5.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 44 of 60
Table 5. Revenue Improvement Program
2. Water Sales
As a result of the above programs, there are three possible sources of water sales, namely:
revenues from water connections through flat rate billing;
revenues from metered billings based on volume of consumption, and
revenues from private deep tubewells (DTW) to be billed as a fixed fee per DTW.
Another option in the future are revenues from hand tubewells to be billed on a flat rate basis per household.
3. Connections
While most of the above programs will increase the number of households billed, up to year 2017, the number of domestic connections will continue to be less than the number of households by a factor of 2.30 as shown in Table 6 below. It is expected that multi-storied building will continue to have one connection and eventually one meter, but in the future they will be billed on the basis of the number of households drawing water from that connection.
Numbers Fiscal Yeara Increase in number of connections from 2011 to 2017
as more volume of water is made available from ongoing and future projects. Domestic Connections (end of fiscal year) 11853 40863 FY 2017Non Domestic Connections (end of fiscal year) 385 4334 FY 2017
b Registration of all illegal connections 2206 illegal domestic connections and 138 illegal non domestic connections
zero FY 2012
c Conversion billing per household Domestic Households (end of fiscal year) 11853 32292 FY 2012
d Metering of all connections by 2017 (end of fiscal year) zero 45197 FY 2017
e Charging owners of private deep tubewells an annual flat fee
no charges 17,799 private DTWs billed
FY 2017
f Annual flat fee for deep tubewells Tk 3000 FY 2017
PresentTarget
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 45 of 60
Table 6. Computation of Households/Connection Factor
Table 7 shows the number of households and non domestic units that can be served through the KWASA network. Using the above factors, the estimated number of connections is expected to increase from the current 11,853 to 31,410 domestic connections and from 385 to 3,428 non domestic connections by 2017. KWASA will also embark on a Metering Program and by the end of FY 2012 all connections will be metered.
Table 7 - Summary of Connections
4. Base Case Tariff
The assumed tariff and fees for each revenue source is shown in Table 8. It is expected that there will be 5% annual tariff increases from 2012 to 2016.
Domestic Connections
Legal Con-nections
Illegal Con-nections Total
Domestic ConnectionsConnections 11,853 2,206 14,059 Households 25,784 6,508 32,292 Factor 2.30 Non Domestic ConnectionsConnections 385 138 523 Non Domestic units 385 138 523 Factor 1.00 Total ConnectionsConnections 12,238 2,344 14,582 Households/Non Domestic units 26,169 6,646 32,815
FY 2010 FY 2011 FY 2012 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017
1 EXISTING CONNECTIONSHouseholds 25,784 25,784 32,292 32,292 32,292 32,292 32,292 32,292 Domestic Connections 11853 11853 14059 14,059 14,059 14,059 14,059 14,059 Non Domestic Units 385 385 523 523 523 523 523 523 Non Domestic Connections 385 385 523 523 523 523 523 523
2 NEW CONNECTIONSHouseholds 10995 12904 3818 28566Domestic Connections 2595 3272 1354 10130Non Domestic Units 945 942 55 963Non Domestic Connections 945 942 55 963
3 CUMULATIVE TOTAL ALL CONNECTIONS (mid year)Households 25,784 25,784 32,292 32,292 43,287 56,192 60,010 88,576 Domestic Connections 11,853 11,853 14,059 14,059 16,654 19,926 21,280 31,410 Non Domestic Units 385 385 523 523 1,468 2,410 2,465 3,428 Non Domestic Connections 385 385 523 523 1,468 2,410 2,465 3,428
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 46 of 60
Table 8. Tariff Summary
5 Other Operating Revenues
Other Operating revenues include connection fees and water sales from bowsers and connection fees which are estimated at 5% of water sales based on FY 2011 experience.
6 Non-Operating Revenues
Non Operating Revenues from other sources including sale of bidding documents, are estimated at 1% of operating revenues based on the experience in FY 2011.
D. OPERATIONS AND MAINTENANCE COST
1. Salaries
KWASA staff currently number 284 comprising permanent and casual staff. This is expected to increase to 502 in 2017. Monthly salaries average Taka 7,306 and allowances are provided to permanent employees at around 41% of their salaries. As a % of total salaries, allowances are currently estimated at around 26%. Average monthly salaries are expected to increase to Taka11,666 by 2017, and by that time it is expected that all employees will be permanent. As permanent employees they will be entitled to allowances at 41% of these salaries. See Table 9.
2008/2009 2009/2010 2010/2011 2011/2012 2012/2013 2013/2014 2014/2015 2015/2016 2016/2017
A Monthly flat rate (Tk/connection)1/2" 45.00 45.00 45.00 47.25 49.61 52.09 54.70 57.43 3/4" 70.00 70.00 70.00 73.50 77.18 81.03 85.09 89.34
1" 200.00 200.00 200.00 210.00 220.50 231.53 243.10 255.26 1.5" 1,200.00 1,200.00 1,200.00 1,260.00 1,323.00 1,389.15 1,458.61 1,531.54
2" 2,000.00 2,000.00 2,000.00 2,100.00 2,205.00 2,315.25 2,431.01 2,552.56
B Metered rate (Tk/m3)Domestic 19.35
Non-Domestic 38.71
C DTW annual fees (Tk/DTW) 3,000
D Tariff Increases 0% 0% 0% 5% 5% 5% 5% 5%
Tariff Summary
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 47 of 60
Table 9. Staffing and Salaries
Direct Costs
Direct costs comprise power and chemicals which are estimated based on a composite rate per m3 produced computed on the basis of the following in Table 10:
EXISTING STRUCTURE 2011 PROPOSED STRUCTURE 2014 PROPOSED STRUCTURE 2017 ORGANISATIONAL UNIT
Staff Numbers
ORGANISATIONAL UNIT Staff
Numbers ORGANISATIONAL UNIT
Staff Numbers
THE MANAGING DIRECTOR THE MANAGING DIRECTOR THE MANAGING DIRECTOR Managing Director and Staff 4 Managing Director and Staff 4 Managing Director and Staff 4
Management Services Section 10 Management Services Section 10 4 14 14 ENGINEERING DIVISION ENGINEERING DIVISION TECHNICAL SERVICES DIVISION
Office of the DMD 4 Office of the DMD 3 Office of the DMD 3 Chief Engineers Office 3 Production & Distribution Department 186 Production Department 146 Production, Distribution, Consumer Service
Department 196
Superintending Engineers Office 3 Planning and Development Department 16 Planning and Development Department 16 Planning, Development & Project Management Department
12
Maintenance Services Department 42 218 205 207 FINANCE AND ADMINISTRATION DIVISION FINANCE AND ADMINISTRATION DIVISION FINANCE AND ADMINISTRATION DIVISION
Office of the DMD 3 Office of the DMD 3 Office of the DMD 3 Office of the Commercial Manager 3 Finance and Accounting Department 17 Finance and Accounting Department 18 Finance and Commercial (Revenue) Department 34
Office of the Secretary 4 Administration Department 44 Administration Department 50 Administration, HR & General Department 18 62 64 71 CUSTOMER SERVICE DIVISION COMMERCIAL SERVICES DIVISION Office of the DMD 3 Office of the DMD 3 Customer Service Department 29 Customer Service Zone 1 & 4 Department 69 Customer Revenue Department 56 Customer Service Zone 2 Department 69 Customer Service Zone 3 & 5 Department 69 88 210
TOTAL 284 371 502 Av ge. Salary 2013 (Tk/Month) – Mid Range 6,803 Avge. Salary 2017 (Tk/Month) – Top Range 11,696
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 48 of 60
Table 10 – Composite Rates for O&M
2. Maintenance & Other Overheads
Repairs and maintenance is assumed at 0.15% of fixed assets. Administrative expenses are computed at 15% of expenses in 2011 and this is expected to reduce to 5% by 2017.
In addition to the regular repairs and maintenance, the JICA feasibility studies provided for replacement of mechanical equipment in year 16. It is assumed that 15 years after project completion, major repair/replacement of electrical and mechanical equipment will be undertaken gradually over a period of 5 years
4. Depreciation
Depreciation is based on assumptions following the DWASA depreciation rates except for depreciation on plant and machinery. Per DWASA the rate for this is 15% representing a 7 year life. It is believed that the plants and machineries including plants would have at least a 20 year life, and it was on this basis that depreciation was computed. The depreciation rates used are shown in Table 11.
Table 11. Depreciation Rates
In 2010, it was estimated that KWASA had beginning fixed assets of Tk 496 million of which Tk314 million represented tubewells, most of which were installed prior to 2000. With a depreciation rate of 6%, or a life of 15 years, it is estimated these tubewells are generally 50% depreciated in 2010. For this reason, they are assumed fully depreciated by 2018 or 7 years after KWASA started depreciating its assets in 2011.
FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY 2016 FY 2017
A. COMPOSITE UNIT COST - POWER (Taka/m3 produced)0.89 0.89 0.64 0.41 0.29 0.27 0.28 0.13 - - 0.08 0.11 0.09 0.09 0.09 0.04 - - - - 0.07 0.07 0.06 0.03 - - - 0.06 0.09 0.10 0.10 0.05 - - - - - - - 1.54 - - - 0.06 0.12 0.12 0.12 0.03
Composite Unit Cost 0.89 0.89 0.72 0.64 0.65 0.64 0.64 1.82
B. COMPOSITE UNIT COST - CHEMICALS (Taka/m3 produced)0.02 0.02 0.01 0.01 0.01 0.01 0.01 0.00
- - 0.00 0.00 0.00 0.00 0.00 0.00 - - - - 0.03 0.03 0.02 0.01 - - - 0.00 0.00 0.00 0.00 0.00 - - - - - - - 0.67 - - - 0.00 0.00 0.00 0.00 0.00
Composite Unit Cost 0.02 0.02 0.02 0.02 0.04 0.04 0.04 0.69
PROJECT 5 - KCC Mini Tubewell Project -3.85 Mld
Existing Assets PROJECT 1a- GoB Project: Development of Water Supply System in Khulna City - : 20 Mld PROJECT 1b - GoB Project: Development of Water Supply System in Khulna City - 6.75 Mld PROJECT 3 - KCC Development of Water Supply System in Phultala - (28 Mld)PROJECT 4 - JICA Packages 1 & 2 and ADB Packages 3 & 4PROJECT 5 - KCC Mini Tubewell Project -3.85 Mld
Existing Assets PROJECT 1a- GoB Project: Development of Water Supply System in Khulna City - : 20 Mld PROJECT 1b - GoB Project: Development of Water Supply System in Khulna City - 6.75 Mld PROJECT 3 - KCC Development of Water Supply System in Phultala - (28 Mld)PROJECT 4a - JICA Packages 1 & 2 - Intake, Raw Water Transmission & WTP
DEPRECIATION RATES FOR FIXED ASSETS*
Building Freehold 2%Tubewells 6%Pumping Plant and Equipment (DWASA 15%) 5%Transmission and Distribution Lines 2%Water Treatment Plant 2%Furniture, Fixtures and Equipment 10%Motor Vehicles 20%Other Assets 20%
*Straight line, no salvage value
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 49 of 60
E. CAPITAL EXPENDITURES
1. Investment Plan
Capital expenditures included in the business plan model include all expenditures proposed under the JICA and ADB loan components, as well as ongoing and future planned GoB projects. Six key projects will be undertaken during the business plan period totalling around Tk 23 billion. See Table 12.
Table 12. Investment Plan (In Taka 000s)
Project 3 – KCC Development of Water Supply System in Phutala (28 mld) and Project 5 – KCC Mini Tubewell Project will be implemented by KCC and handed over after completion to KWASA. The other projects will be implemented by KWASA. The projects being executed by KCC will be incorporated into KWASA asset register upon turn over.
2. The Khulna Water Supply Improvement Project
This was based on the following key assumptions used in the feasibility study prepared by JICA10:
(i) the ADB/JICA loan will be effective in March 2011,
(ii) the 6-year disbursement period will be completed in December 2018, during which time the project is expected to be completed.
(iii) the ADB/JICA loan will be relent to KWASA and will be payable under the following terms (i) 2% interest, (ii) 8 years grace period, and (iii) 20 years repayment period.
Investment figures for the ADB/JICA project were based on July 2010 prices. During that month, the exchange rate was $1 to Taka 70 and 91.5 Japanese Yen. Annual cost-escalation factors used are 3.1% for foreign currency (JICA estimates) and 5% for local currency.
10 Feasibility Study for Khulna Water Supply Improvement Project in Bangladesh, Japan International Cooperation Agency, July 2010, Page11-2
SUMMARY INVESTMENT PLAN (In Current Tk 000s)
FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 Total
PROJECT 1a- GoB Project: Development of Water Supply System in Khulna City - : 20 Mld 97,428 177,339 39,253 - - - - - 314,020 PROJECT 1b - GoB Project: Development of Water Supply System in Khulna City - 6.75 Mld SWTP - 55,776 61,681 - - - - - 117,457 PROJECT 2 - GoB Rehab Of DTW & Water Supply Expansion - 16mld - - - - - - - - - PROJECT 3 - KCC Development of Water Supply System in Phultala - (28 Mld) - - - - 339,350 - - - 339,350 PROJECT 4a - JICA Packages 1 & 2 - Intake, Raw Water Transmission & WTP - - 373,443 3,179,944 6,464,031 4,517,623 1,263,622 30,029 15,828,691 PROJECT 4b - ADB Packages 3 & 4 - Treated Water Transmission, Storage and Distribution - 1,506,363 3,829,562 1,270,837 1,352,143 688,805 589,736 195,296 9,432,741 PROJECT 5 - KCC Mini Tubewell Project -3.85 Mld 22,455 - - - - - 22,455
Total 97,428 1,761,933 4,303,939 4,450,781 8,155,524 5,206,427 1,853,358 225,325 26,054,715
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 50 of 60
F. RECEIVABLES
1. Opening And Beginning Balances For Receivables
Beginning balances are estimated based on SSTA study (FY 2009) and the listing of accounts provided by KWASA (FY 2010). The figures are yet to be audited. KWASA is in the process of hiring an auditor and it is expected that the audited Financial Statements for 2009 and 2010 will be available by early 2011. See Annex 2.
2. Collection Efficiency
Due to lack of data, and the lack of systems to account for receivables, the projections assume a lower starting collection efficiency of 80% in 2011 (as against 90% collection efficiency, in the JICA Feasibility Study). From 2011 to 2014, there will also be numerous programs for which some resistance from customers is initially expected such as conversion to billing per household, registration of illegal connections and metering. For this reason, although improvement in the systems is expected through the implementation of a computerized billing and collection system, increase in collection efficiency is expected to be gradual and will reach 95% only by 2014.
G. INVENTORY
It is assumed that inventory levels will be maintained at 4 months of chemicals and repair expenses.
FIXED ASSETS
1. Fixed Assets
Fixed Assets represent the accumulation of existing fixed assets of P496 million in 2011 plus the value of all the investments amounting to Tk 26 billion. The fixed assets are presented net of accumulated depreciation.
2. Capital Works In Progress (CWIP)
Project Disbursements are recorded as CWIP until the year project completion. These amounts are transferred to Fixed Assets and made subject to depreciation the year after completion.
H. LOANS PAYABLE
The project will be financed through an ADB/JICA loan to the Government of Bangladesh and relent to KWASA to under the following concessional terms: 30 years repayment including 8 years grace period and 2% interest rate.
I. PAYABLES TO CREDITORS
Payables are estimated at 2 months of fuel and electricity costs.
J. GOVERNMENT SUBSIDY
KWASA reported that it received Tk 76.5 million as government subsidy in FY 2011. It is assumed that the government will continue to provide the same amount for FY 2012 and FY 2013.
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 51 of 60
Annex 4 - Financial Projections for the Base Case Scenario
Khulna Water Supply and Sewerage AuthorityProjected Income Statement(In Current Tk '000)
FY2009 FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 FY2019 FY2020
Operating Revenues 16,444 11,764 11,672 31,976 33,575 49,529 69,079 77,106 627,017 870,507 986,913 1,102,662 Non-Operating Revenues 64 109 117 320 336 495 691 771 6,270 8,705 9,869 11,027 Total Income 16,508 11,873 11,789 32,296 33,911 50,024 69,769 77,877 633,287 879,212 996,782 1,113,689
Personnel Expenses 17,758 36,696 34,588 36,318 39,344 77,559 81,437 85,509 146,400 153,720 161,406 169,476 Fuel and Electricity 4,659 11,230 7,765 7,604 8,831 14,668 20,398 21,981 90,739 120,640 132,313 148,257 Chemicals - - 174 181 227 926 1,303 1,369 34,257 45,422 49,682 55,866 Repairs and Maintenance 546 5,497 708 704 667 629 1,087 1,485 1,584 1,536 1,492 1,458 Administrative and General Expenses 2,081 8,005 5,874 3,136 2,453 4,689 5,211 5,517 13,649 16,066 17,245 18,753
Total O & M Expenses 25,044 61,428 49,110 47,943 51,522 98,471 109,436 115,861 286,629 337,383 362,138 393,811 Gross Operating Profit /(Loss) (8,536) (49,555) (37,321) (15,647) (17,612) (48,447) (39,667) (37,984) 346,658 541,829 634,644 719,878 Less: Depreciation Expenses - - 24,266 24,984 24,984 24,984 33,973 48,817 51,304 32,473 29,173 22,525 Net Operating Profit /(Loss) before Interest Expense (8,536) (49,555) (61,587) (40,631) (42,596) (73,431) (73,640) (86,800) 295,354 509,356 605,471 697,354 Interest Expense - - - - - - - - - - - 389,151 Net Income/(Loss)before Taxes (8,536) (49,555) (61,587) (40,631) (42,596) (73,431) (73,640) (86,800) 295,354 509,356 605,471 308,203
Estimated Projected
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 52 of 60
Khulna Water Supply and Sewerage AuthorityProjected Balance Sheet('000)
FY2009 FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 FY2019 FY2020
ASSETS AND OTHER DEBITSNon-Current AssetsProperty, Plant & Equipment (net) 483,056 496,294 472,028 469,499 444,515 419,530 724,908 990,111 1,056,264 1,023,792 994,618 972,093Capital Work in Progress 1,500 - 97,428 1,847,450 6,202,110 10,765,204 18,781,804 23,969,805 26,056,630 26,654,448 27,035,968 27,035,968
484,556 496,294 569,456 2,316,949 6,646,625 11,184,734 19,506,712 24,959,917 27,112,894 27,678,240 28,030,587 28,008,061Current Assets Inventories 702 2,727 294 295 298 518 796 951 11,947 15,652 17,058 19,108Customer Accounts Receivables 48,270 50,415 51,059 53,958 55,441 56,066 55,660 55,415 65,337 79,461 95,311 112,825Deposits and Advances 3,668 5,173 5,173 5,173 5,173 5,173 5,173 5,173 5,173 5,173 5,173 5,173Cash and bank accounts 55,621 27,108 59,679 117,605 175,212 126,893 88,308 50,679 387,878 916,861 1,536,195 1,137,260SUB-TOTAL 108,261 85,423 116,205 177,031 236,124 188,650 149,938 112,218 470,336 1,017,147 1,653,738 1,274,366Total Assets 592,817 581,717 685,661 2,493,980 6,882,750 11,373,384 19,656,650 25,072,135 27,583,230 28,695,387 29,684,325 29,282,427EQUITY AND LIABILITIESCapital and ReservesEquity Capital 590,282 629,276 705,776 782,276 858,776 858,776 858,776 858,776 858,776 858,776 858,776 858,776Funds and Grants 0 0 97,428 804,907 2,166,742 3,501,977 6,186,179 7,748,107 8,304,115 8,371,712 8,371,712 8,371,712Accumulated Profit/(Loss) (8,536) (58,091) (119,677) (160,309) (202,904) (276,336) (349,976) (436,776) (141,422) 367,934 973,405 1,281,608
581,746 571,185 683,527 1,426,874 2,822,614 4,084,417 6,694,979 8,170,107 9,021,469 9,598,422 10,203,893 10,512,095Non-Current LiabilitiesLoans Payable - - - 1,064,999 4,057,823 7,285,682 12,957,431 16,897,524 18,545,798 19,076,018 19,457,539 18,744,782 Other Deferred Liabilities -
- - - 1,064,999 4,057,823 7,285,682 12,957,431 16,897,524 18,545,798 19,076,018 19,457,539 18,744,782 Current LiabilitiesCreditors 10,231 9,691 1,294 1,267 1,472 2,445 3,400 3,664 15,123 20,107 22,053 24,710
Loans Interest PayableOther Payables 840 840 840 840 840 840 840 840 840 840 840 840 11,071 10,531 2,134 2,107 2,312 3,285 4,240 4,504 15,963 20,947 22,893 25,550Total Equity and Liabilities 592,817 581,716 685,661 2,493,980 6,882,749 11,373,383 19,656,650 25,072,135 27,583,230 28,695,386 29,684,325 29,282,427
Estimated Projected
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 53 of 60
Khulna Water Supply and Sewerage AuthorityProjected Cash Flow Statement('000)
FY2009 FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 FY2019 FY2020
Cash Balance, Beginning 55,621 27,108 59,679 117,605 175,212 126,893 88,308 50,679 387,878 916,862 1,536,195 Add: ReceiptsOperations: - from Water Billings 8,976 8,893 25,885 28,778 44,812 64,473 71,966 585,216 812,473 921,119 1,029,151 - from Other Revenues 752 673 1,842 1,935 2,854 3,980 4,443 36,128 50,158 56,865 63,534 - from Accounts Receivables - 1,579 1,669 1,715 1,734 1,721 1,714 2,021 2,458 2,948 3,489 Project Loans - - 1,064,999 2,992,824 3,227,859 5,671,749 3,940,093 1,648,274 530,221 381,520 - Project Grants - 97,428 685,024 1,361,835 1,335,234 2,344,852 1,561,928 556,007 67,597 - - Subsidies for Operations 38,995 76,500 76,500 76,500 - - - - - - - Miscellaneous Receipts Total Receipts 48,723 185,073 1,855,919 4,463,587 4,612,493 8,086,776 5,580,143 2,827,646 1,462,907 1,362,452 1,096,175 Less: DisbursementsOperations: - Operating Expenses 61,428 38,912 39,454 41,798 82,248 86,649 91,026 160,049 169,786 178,650 188,229 - Capital Expenditures 11,738 - Payment of Suppliers/Contractors (Accounts Payable) - 16,162 7,631 8,627 13,695 19,443 21,717 79,279 115,656 130,368 145,600 - Purchase of Inventory 2,025 - 886 896 1,776 2,668 3,008 46,838 50,663 52,579 59,374 Project Disbursements - Self Financed - Loans - - 1,064,999 2,992,824 3,227,859 5,671,749 3,940,093 1,648,274 530,221 381,520 - - Grants - 97,428 685,024 1,361,835 1,335,234 2,344,852 1,561,928 556,007 67,597 - - Debt Service - Interests - - - - - - - - - - 389,151 - Principal - - - - - - - - - - 712,757 Miscellaneous 2,045 - - - - - - - - - - Total Disbursements 77,236 152,501 1,797,994 4,405,980 4,660,813 8,125,360 5,617,772 2,490,447 933,923 743,118 1,495,111 Cash Inflow (Deficit) (28,513) 32,571 57,926 57,607 (48,320) (38,584) (37,629) 337,199 528,983 619,334 (398,936) Cash Balance, Ending 27,108 59,679 117,605 175,212 126,893 88,308 50,679 387,878 916,862 1,536,195 1,137,260 Balance at 2 months O&M excluding depreciation 8,185 7,991 8,587 16,412 18,239 19,310 47,772 56,231 60,356 65,635
Estimated Projected
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 54 of 60
Khulna Water Supply and Sewerage AuthorityProjected Funds Flow Statement('000)
FY2009 FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 FY2019 FY2020
Net Cash Flow from Operating ActivitiesNet Income before Interests (61,587) (40,631) (42,596) (73,431) (73,640) (86,800) 295,354 509,356 605,471 697,354 Add: Depreciation 24,266 24,984 24,984 24,984 33,973 48,817 51,304 32,473 29,173 22,525 (Inc) /decrease in accounts receivables (644) (2,899) (1,483) (625) 406 245 (9,922) (14,124) (15,851) (17,514) (Inc) /decrease in inventories 2,433 (1) (3) (221) (278) (155) (10,996) (3,705) (1,405) (2,050) Inc (dec) in accounts payable (8,397) (27) 205 973 955 264 11,460 4,984 1,946 2,657 Inc (dec) in taxes payablesInterest payments on LT-debt - - - - - - - - - (389,151) Net cash flow from Operating Activities (43,929) (18,574) (18,893) (48,320) (38,584) (37,629) 337,199 528,983 619,334 313,821 Cash Flows from Investing ActivitiesProject Disbursements (97,428) (1,750,023) (4,354,660) (4,563,093) (8,016,601) (5,502,021) (2,204,282) (597,818) (381,520) - CAPEX / Asset Acquisitions - - - - - - - - - - InvestmentsSale of Investments Net cash used by investing activities (97,428) (1,750,023) (4,354,660) (4,563,093) (8,016,601) (5,502,021) (2,204,282) (597,818) (381,520) - Cash Flows from Financing ActivitiesProceeds of Grants / Oper'l Subsidies 173,928 761,524 1,438,335 1,335,234 2,344,852 1,561,928 556,007 67,597 - - Proceeds of LT Loans / Grants - 1,064,999 2,992,824 3,227,859 5,671,749 3,940,093 1,648,274 530,221 381,520 - Principal Payment of LT Loans - - - - - - - - - (712,757) Net cash used by financing activities 173,928 1,826,523 4,431,160 4,563,093 8,016,601 5,502,021 2,204,282 597,818 381,520 (712,757)
Net Increase in Cash 32,571 57,926 57,607 (48,320) (38,584) (37,629) 337,199 528,983 619,334 (398,936) Cash balance at beginning of the Year 27,108 59,679 117,605 175,212 126,893 88,308 50,679 387,878 916,862 1,536,195 Cash Balance, End of Year 27,108 59,679 117,605 175,212 126,893 88,308 50,679 387,878 916,862 1,536,195 1,137,260
Estimated Projected
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 55 of 60
Annex 5 – Results of Scenario Analysis
Year
2010 (28,513) 27,108 5.17 (4.17) 2011 32,571 59,679 4.17 (5.22) 2012 57,926 117,605 1.48 (1.26) 2013 57,607 175,212 1.52 (1.26) 2014 (48,320) 126,892 1.97 (1.47) 2015 (38,584) 88,308 1.57 (1.06) 2016 (37,629) 50,679 1.49 (1.11) 2017 30,376 81,055 0.89 (0.05) 8.86
2018 (1,727,407) (1,646,352) 3% 0.87 (3.20) 9.31 5%2019 (1,685,869) (3,332,221) 5% 0.83 (2.66) 9.77 5%2020 (1,662,352) (4,994,573) 6% 0.80 (2.13) 10.26 5%2021 (1,643,203) (6,637,776) 7% 0.78 (1.85) 10.78 5%2022 (1,626,063) (8,263,839) 8% 0.77 (1.62) 11.31 5%2023 (1,606,609) (9,870,448) 9% 0.76 (1.41) 11.88 5%2024 (1,585,710) (11,456,158) 11% 0.75 (1.21) 12.47 5%2025 (1,563,925) (13,020,082) 12% 0.74 (1.16) 13.10 5%
Domestic Tariff
SCENARIO 2 (Option 2) - Selected KPIs
Annual Cash Surplus
(Defiiciency)
Ending Cash (Tk000)
Debt Service
Ratio
Operating Ratio before
depr
Net Income Ratio
Tariff Adjustment
Appendix 6 KWASA BUSINESS PLAN 2011 TO 2017
Page 56 of 60
Year
2010 (28,513) 27,108 5.17 (4.17) 2011 32,571 59,679 4.17 (5.22) 2012 57,926 117,605 1.48 (1.26) 2013 57,607 175,212 1.52 (1.26) 2014 (48,320) 126,893 1.97 (1.47) 2015 (38,584) 88,308 1.57 (1.06) 2016 (37,629) 50,679 1.49 (1.11) 2017 894,667 945,346 0.24 0.72 38.41 2018 (498,286) 447,060 74% 0.23 (0.08) 40.33 5%2019 (278,081) 168,978 86% 0.21 0.07 42.35 5%2020 (82,961) 86,017 97% 0.20 0.21 44.47 5%2021 83,085 169,102 107% 0.20 0.28 46.69 5%2022 240,350 409,452 116% 0.19 0.34 49.03 5%2023 410,756 820,207 126% 0.19 0.40 51.48 5%2024 594,228 1,414,435 136% 0.19 0.45 54.05 5%2025 817,416 2,231,851 149% 0.18 0.46 56.75 5%
SCENARIO 3 (Option 3) - Selected KPIsAnnual Cash
Surplus (Defiiciency)
Ending Cash
(Tk000)
Debt Service
Ratio
Operating Ratio before
depr
Net Income Ratio
Domestic Tariff
Tariff Adjustment
Appendix 7 KWASA BUSINESS PLAN 2011 TO 2017
Page 57 of 60
Annex 6 – KWASA Organisation Structure Staffing Requirements
A6.1 – The Managing Directors Office
THE MANAGING DIRECTORS OFFICE
EXISTING STRUCTURE 2011 PROPOSED STRUCTURE 2014 PROPOSED STRUCTURE 2017
ORGANISATIONAL UNIT Staff Numbers
ORGANISATIONAL UNIT Staff Numbers
ORGANISATIONAL UNIT Staff Numbers
THE MANAGING DIRECTOR THE MANAGING DIRECTOR THE MANAGING DIRECTOR Managing Director and Staff 4 Office Of the MD 4 Managing Director and Staff 4 Management Services Section Management Services Section Office of the Section Head 1 Office of the Section Head 1 Internal Control/Audit 2 Internal Control/Audit 2 Corporate Planning 2 Corporate Planning 2 Legal 1 Legal 1 Public Affairs and Information 2 Public Affairs and Information 2 Management Information Systems 2 Management Information Systems 2 4 14 14
Appendix 7 KWASA BUSINESS PLAN 2011 TO 2017
Page 58 of 60
A6.2 – Technical Services
TECHNICAL SERVICES
EXISTING STRUCTURE 2011 PROPOSED STRUCTURE 2014 PROPOSED STRUCTURE 2017
ORGANISATIONAL UNIT Staff Numbers
ORGANISATIONAL UNIT Staff Numbers
ORGANISATIONAL UNIT Staff Numbers
ENGINEERING DIVISION ENGINEERING DIVISION TECHNICAL SERVICES DIVISION Office of the DMD 4 Office of the DMD 3 Office of the DMD 3 Production Department Production Department Chief Engineers Office 3 Office of the Department Manager 3 Office of the Department Manager 3 Production, Distribution, Consumer Service Department 196 Production Section 144 SWTP Operations Section 62
Distribution Section 39 Wells Section 81 Planning and Development
Department Planning and Development Department
Superintending Engineers Office 3 Office of the Department Manager 3 Office of the Department Manager 3
Planning, Development & Project Management Department 12
Planning Section 7 Planning and Design Section 7 Project Management & Implementation Section 6 Project Monitoring and Management
Section 6
Maintenance Services Department Office of the Department Manager 3 Maintenance Section 39 218 205 207
Appendix 7 KWASA BUSINESS PLAN 2011 TO 2017
Page 59 of 60
A6.3 – Finance & Administration
FINANCE AND ADMINISTRATION
EXISTING STRUCTURE 2011 PROPOSED STRUCTURE 2014 PROPOSED STRUCTURE 2017
ORGANISATIONAL UNIT Staff Numbers
ORGANISATIONAL UNIT Staff Numbers
ORGANISATIONAL UNIT Staff Numbers
FINANCE AND ADMINISTRATION DIVISION FINANCE AND ADMINISTRATION DIVISION FINANCE AND ADMINISTRATION DIVISION Office of the DMD 3 Office of the DMD 3 Office of the DMD 3 Finance and Accounting Department Finance and Accounting Department Office of the Commercial Manager 3 Office of the Department Manager 3 Office of the Department Manager 3 Finance and Commercial (Revenue) Department 34 Accounting Section 8 Accounting Section 10
Budget and Treasury Section 6 Budget and Treasury Section 5 Administration Department Administration Department Office of the Secretary 4 Office of the Department Manager 3 Office of the Department Manager 3 Administration, HR & General Department 18 Human Resources Section 7 Human Resources Section 10
General Services Section 34 General Services Section 37 62 64 71
Appendix 7 KWASA BUSINESS PLAN 2011 TO 2017
Page 60 of 60
A6.4 – Commercial Services
COMMERCIAL SERVICES EXISTING STRUCTURE 2011 PROPOSED STRUCTURE 2014 PROPOSED STRUCTURE 2017
ORGANISATIONAL UNIT Staff Numbers
ORGANISATIONAL UNIT Staff Numbers
ORGANISATIONAL UNIT Staff Numbers
CUSTOMER SERVICE DIVISION COMMERCIAL SERVICES DIVISION Office of the DMD 3 Office of the DMD 3 Customer Service Department Customer Service Zone 1 & 4
Department
Office of the Department Manager 3 Office of the Department Manager 3 Credit and Collection Section 13 Revenue Section 26 Customer Service Section 13 Customer Service Section 40 Customer Accounts (Revenue)
Department Customer Service Zone 2 Department
Office of the Department Manager 3 Office of the Department Manager 3 Meter reading Section 38 Revenue Section 26 Billing Section 15 Customer Service Section 40 Customer Service Zone 3 & 5
Department
Office of the Department Manager 3 Revenue Section 26 Customer Service Section 40 88 210 TOTAL 284 371 502
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
1
FINANCIAL MANAGEMENT ASSESSMENT REPORT
This chapter presents a key output of the PPTA, the Financial Management Assessment Report covering
financial management performance and the financial management strengthening program.
A. Financial Management Assessment
The financial management assessment covers organization and staffing, systems, revenue adequacy and
financial management.
1. Organization and Staffing
Under the KWASA approved organization structure, finance and accounting functions are currently
performed by two sections namely Financial and Commercial sections which both report to a
Commercial Manager under the DMD for Finance and Administration. There are currently 23 positions in
these sections of which 18 have been filled out. The other 5 positions will be filled out in the coming
months.
The KWASA organization structure has been reviewed twice as part of JICA and ADB studies in the last
two years. The recommendations, whilst not being exactly the same, engender the same principles and
agree on some fundamental organizational requirements as follows:
• Separation of the finance and revenue functions for accountability purposes;
• Establish a clearer customer focus through the organisation structure – introduction of
customer service accountability through a commercial Directorate and move towards a
zonal operating structure in order to be more responsive to customers;
• An internal audit function should be introduced to the organization;
Several positions have been recently hired (Commercial Manager, Accounts Officer, Budget Officer, 3
Revenue Officers) and as a result, most of the key accounting and revenue positions under the approved
organization have already been filled out. The organizational concerns mentioned above as well as the
views of KWASA MD have been taken into account in preparation of organization proposals which are
included in the business plan and also presented in this report.
(b) Staff capability
Preliminary training needs analysis reveal lack of staff capacity in three critical areas, namely technical
knowledge of accounting and financial management and computer skills. Some capacity building is
being provided under this PPTA through training and coaching sessions but a lot more is needed in the
coming years. A comprehensive capacity building program is proposed covering the period up to 2017
and using a three pronged approach comprising training, systems manuals development and
consultancy assistance. Under the PPTA, a short term training plan for financial management is being
implemented. Please see Chapter II, Section 2 on Institutional Strengthening including capacity building.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
2
2. Systems and controls
During the PPTA there were no appropriate systems yet in place and there was lack of staff capability to
enable the generation of financial and operating results. With the recent recruitment of the accounting
officer and revenue officers, the accounting and commercial activities are now in the process of being
organized and action is being done to address the deficiencies noted. The key findings relating to
financial management systems and controls are presented below. Substantial work needs to be done in
the coming years so that KWASA will have a fully functioning and dynamic financial management
system. Detailed findings and related action needed is provided in Appendix 5.
a) General Accounting System
KWASA was not yet operating a proper accounting system during the PPTA. The existing system works
on a single entry and cash basis resulting in the following observations and deficiencies:
(i) Currently there is no suitable Chart of Accounts in place, the system is still on single-entry
method and therefore accounting staff do not use standard account titles.
(ii) Only the Collection Report and Statement of Cash Expenditures were being prepared. No
other financial reports were prepared.
(iii) Since only a single entry is in use, there is no General or Control Ledger. KWASA maintains
only the following ledgers and registers and even these are not properly maintained:
• Consumer Ledger
• Check Issue Register
• Inventory Register
• Line Registers (New Line Connection Register and Line Disconnection Register)
• Salary Register, Provident Fund Register
• Others (Stationery Register, Attendance Register, )
Due to the lack of registers and ledgers summarizing data, there is no information on other
key financial information such as total sales generated, expenses other than cash expenses,
and capital expenditures.
(iv) Beginning balances for all accounts were not established and only the ADB SSTA and JICA
figures for FY 2009 were available. As a result, beginning balances for key accounts like
accounts receivable and fixed assets were not yet available during the PPTA. The PPTA
provided assistance to the KWASA in preparing for the audit of its FY 2009 and FY 2010
financial statements including:
• Preparing preliminary financial statements for FY 2010
• Preparing invitation for EOI in connection with the appointment of the Auditor of
KWASA
• Collecting information from the Institute of Charted Accountants of Bangladesh and
DWASA on the appointment of Auditor in KWASA.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
3
Eventually the financial audit will establish the beginning balances but in the mean time the
PPTA prepared preliminary financial reports for 2009 and 2010 based on ADB SSTA and JICA
reports as well as other estimates. The preliminary financial reports are shown in Appendix
1. Assistance has been provided to KWASA in securing the services of an external auditor
for KWASA. External Audit firms who submitted their proposals have been requested to
submit their financial offer by November 28, 2010.
(v) Under the previous ADB SSTA, the Hoda Vasi consultants developed a computerized
accounting system and prepared 4 manuals in August 2009 covering the Accounts Manual,
Inventory, HRM and Payroll Manual and the Training Manual. This also includes a Chart of
Accounts. This system is not yet operational and so the PPTA assisted KWASA in drafting
terms of reference (TOR) for a service provider, discussing with potential service providers
and preparing relevant contracts, securing financing from ADB. The TOR requires the
provider to resolve the software problems encountered in the Hoda Vasi accounting
program, provide training, and ensure that the initial financial reports are produced.
b) Cash Operations System
(i) Receipts. The current procedure for the collection of water sales and other receipts is fairly
good. KWASA has its own bank account and it deposits its receipts intact on a regular basis
(ii) Disbursements. The MD approves all disbursements since there are no appropriate policies
relating to approval levels.
(iii) Petty Cash. Most payments are made by check. KWASA does not currently see the need for
petty cash. For the moment, emergency purchases are handled by the employees
advancing the amounts needed.
(iv) A bank reconciliation statement is not prepared.
c) Billing and Collection System
(i) Billing. There is a simple billing system in place in KWASA that is appropriate to the current
needs of KWASA with its unmetered connections. In the coming years however, appropriate
systems need to be developed to handle billing of more customers as well as billing on a
volumetric tariff basis.
(ii) A Consumer Ledger is maintained but the total of the consumer account balances is not
computed as such, it is difficult to determine the accounts receivables balance. The
accounting staff finds it difficult to manually compute the total of the balances of the 12,000
plus customers.
(iii) The collection effort is difficult in the absence of a well maintained Customer Ledger which
is also the basis for the preparation of the Aging of accounts. As a result, there are no
policies on providing allowances for uncollectible accounts and write off of bad debts.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
4
(iv) Monitoring and Reporting. The system does not provide, for the monitoring of customer
accounts and is not able to generate important summary reports like billing summaries,
water sales reports, accounts receivables balance, status of service connections, collection
performance reports and others that are necessary for planning and control. The system
because of its limited features will not be able to support future growth in services.
(v) It is planned that a computerized billing and collection system will be developed The PPTA
assisted KWASA in drafting terms of reference (TOR) for a service provider, discussing with
potential service providers, preparing relevant contracts, and securing financing from ADB.
The TOR requires the provider to develop the software, install the program, provide
training, and ensure that the initial bills are generated.
(d) Inventory Management and Procurement
(i) The stores (inventory) are still maintained centrally in KWASA although KWASA does not
have sufficient space with which to store these stocks.
(ii) KWASA received list of inventories from KCC which as of June 2009 amounted to some Taka
702,000 but to date KWASA has not had the opportunity to verify the existence of these
inventories as well as inventories of purchased items on stock. There are no stock cards
maintained for individual inventory items.
(iii) The inventory system currently in operation is not adequate. KWASA maintains inventory
registers containing quantities received and issued. KWASA finds it difficult to maintain the
registers manually. And since summary totals are not also determined, there is no way to
check whether the information in the registers is correct.
(iv) There is lack of policies on inventory, such as minimum stock levels, valuation of obsolete
items, etc.
(v) All purchases are approved by the MD up to Tk 14999 beyond which a Purchase Committee
evaluates and approves purchases.
(e) Fixed Assets
(i) There are no policies for asset requisitioning, transfer, disposal, depreciation and
retirement. There is no system on fixed asset management
(ii) There is no fixed assets register
(iii) A listing of assets that were turned-over during the establishment of KWASA is available.
However, the amounts reported have not yet been verified as to the correctness of the
values of the assets. Individual property cards have yet to be set up.
(iv) Assets reported in the listing of assets are not properly classified and no depreciation is
computed and recognized.
(v) There is a need to conduct a physical inventory to verify existence of the assets. If funds will
allow, an asset condition survey should also be conducted to establish sufficient information
on the assets and which will be useful later on for asset management planning.
See Appendix 5 for detailed assessment and action plan for existing systems.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
5
(f). Financial Management Assessment Questionnaire (FMAQ) – see Appendix 6.
The FMAQ prepared during the ADB SSTA and updated during the JICA studies, was further updated in
the current PPTA. No substantial improvements have been noted in financial management systems.
This is expected to happen only after the accounting and billing and collection systems have been
implemented.
3. Financial Management practices
The financial concerns of KWASA are currently focused on the running of the accounting system on a
cash basis and a simplified billing system based on flat rate billings. Comprehensive financial
management concepts practiced by more advanced water utilities still need to be introduced to KWASA.
These include concepts on:
• Cost Recovery
• Tariff Structuring
• Revenue Management
• Collection Enforcement
• Cost Analysis and Control
• Financial Reporting, Financial Statement Interpretation and Analysis
• Planning and Budgeting
• Business Planning/ Financial Modelling
B. Financial Management Strengthening Program
The financial management strengthening program addresses each of the areas assessed in the previous
section on the financial management assessment.
1. Organization and Staffing
As proposed in the business plan, a Phase 1 organisation will come into effect at the start of FY 2013/14.
At this time a Commercial Directorate, reporting to a DMD, will be established. This will be the first step
in establishing a more customer focused delivery mechanism. The Commercial Directorate will have
responsibility for customer service and customer accounts, thereby separating these responsibilities
from their current position under the DMD Finance and Administration. For operational purposes
KWASA will function as 2 zones controlled from the centre of the organization. To support the MD
function a number of functional teams will be introduced to cover corporate planning, internal audit,
MIS/IT and legal activities. The total staff requirement for this organization structure is 426 of which 98
will be under the DMD Customer Service and 72 will be under the DMD Finance and Administration.
There will also be 4 staff in the Internal Control Office under the Managing Directors Office.
Phase 2 organisation structures will be set in place from commissioning of the newly planned SWTP and
distribution storage zones in 2017. This maintains the previously established three directorate structure;
however the Commercial Directorate is re-focused on whole cycle business delivery. This organization
will have a total staff complement of 502 of which 73 are under the office of the DMD Finance and
Administration and 215 will be under the DMD Customer Service including the staffing needs for 5
service delivery zones.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
6
A Capacity Building Program is being proposed as discussed in Chapter II. A major focus of the program
is in the area of financial management. Under the Long Term Capacity Building Program for Financial
Management, a continuous and progressive Capacity Building Program is being implemented and
proposed from 2010 up to 2017. This covers assistance provided under the current PPTA, the proposed
bridging TA and the loan implementation assistance. Based on the program, there will be a three
pronged approach to capacity building program, namely through training, development of manuals and
consultancy assistance.
Training comprises technical skills training and computer skills training. This can be done through
• in house training with the help of consultants or other short term trainors conducting workshops
or seminars for the KWASA staff. This is the mode for most of the suggested areas. In fact, this
has already started with training provided by the PPTA consultants.
• Obtaining course degrees and/or short courses in universities or other service providers. This is
appropriate for obtaining accounting degrees as well as taking short term computer courses
All staff members need some basic and advance training in computer skills. There are two ways to
provide this namely through (i) the hiring of a trainor and providing the training in house or (ii) getting
the staff to enrol in computer courses. One of the deliverables of the PPTA is the Business Plan which
includes a financial model. It is important for KWASA to eventually be able to use the financial model
themselves to help them update and develop new strategies in the years to come. This can only be
done by staff that has advanced training and experience with the use of excel. It is proposed that the
Accounts officer and at least one other staff, be provided with basic and advanced training in the use of
excel. Introduction to the model is being done under the current PPTA but training in the use of the
model should be continued by the succeeding bridging TA consultants as well as the loan
implementation consultants.
Development of Manuals. To accelerate capacity building to keep up with the immediate needs of
KWASA, it is further proposed that KWASA embark on the development of all required accounting and
commercial systems. There are 10 key systems and six of these are proposed to be computerized
namely General Accounting, Billing, Meter Reading, Fixed Assets, Inventory and Payroll. Once these
computerized systems are developed, the contractor will also train the users and provide them manuals
to guide them in operating the computerized systems.
It is proposed that policy and procedures manuals be prepared for the other manual based systems such
as Budgeting, Procurement, Project Accounting and Business Planning. The manuals will be used both as
a training tool and a guide in actual operations.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
7
Table 1. Capacity Building on Financial Management
Under the Short Term Training Plan for Financial Management. The training component has already
started with training provided by the PPTA consultants in the areas of accounting and financial
management. Table 2 shows the training conducted and to be conducted by the PPTA consultants in the
coming months. Training has been provided in the form of
• formal workshops. These are seminar/workshops usually covering more general topics for
KWASA. A total of two formal workshops were conducted during the PPTA
• informal sessions on specific topics which were conducted in the accounting room with the
participation of accounting, stores and revenue section staff. A total of eleven informal training
sessions will be conducted
• coaching sessions. These sessions provide on the job training for accounting staff in areas
where they need assistance and are provided whenever needed.
2010 2011 2012 2013 2014 2015 2016 2017
PPTA
PART I - TRAINING
A Techinical Skills Training
Accounting
Accounting Concepts and Practice x
Financial Management Concepts
Cost Recovery and Tariffs x
Planning and Budgeting x x
Business Planning x x x x x x x x
Financial Modelling x x x x x x x x
Meter Reading x x x
B Computer Skills
Basic Skills
Word x
Excel x
Advanced Skills
Excel x
PART II - SYSTEM DEVELOPMENT MANUALS
Development of Manuals
Manual Systems
Budgeting x x
Procurement x x
Project Accounting x x
Business Planning x x
Computerized Systems
General Accounting x x
Billing x x
Meter Reading x x
Fixed Assets x x
Inventory x x
Payroll x x
Loan ImplementationBridging TA
Beyond
2017
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
8
Date Time Topic Speaker
2011
13 January
16 January
18 January
20 January
25January
2.00-3.00
3.00-4.00
4.00-5.00
2.00-3.00
3.00-4.00
4.00-5.00
2.00-3.00
3.00-4.00
4.00-5.00
2.00-3.00
3.00-4.00
4.00-5.00
2.00-3.00
3.00-4.00
4.00-5.00
Books of Accounts and Forms required for
KWASA.
Other Records and Registers required for
keeping accounts of KWASA.
Introduction to relevant Vouchers and
Documents required in preparation of
accounts.
Preparation of Receipt and Payments Vouchers
and Recording.
Debit Voucher and Credit Voucher Journal
Voucher
Types of Bank Accounts and their control.
Collections of Bills through Banks.
Bank reconciliation Statement.
Preparation of Double column Cash book &
Petty Cash Book, Imprest System of Petty Cash
Book.
Posting of figures from Cash Book to General
and Subsidiary Ledgers.
Writing and Balancing of General Ledger
General Ledger and Trial Balance.
Writing and Balancing of Subsidiary Ledgers.
Types of Adjustment Entries.
Adjustment through Journal Book
Adjustment through Journal Voucher.
Adjustment of Advances to staff, contractors,
suppliers etc.
Types of Trial Balance.
Preparation of different Types of Trial Balance.
Preparation of Income Statement.
Items of Assets and Liabilities.
Preparation of Balance Sheet and related
schedule of outstanding assets & liabilities
ALL Classes will be
taken by Prof. Dr.
Md. Kayemuddin
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
9
Date Time Topic Speaker
26
January
10-11
11-12
12-1.00pm
2.00-3.00
3.00-4.00
4.00-5.00
schedule.
Budget –Physical Targets in the Budget.
Resource of Budget.
Utilization of Budgeted Resources.
Preparation of Budget and Budget Variance
report.
Accounting Ratio.
Preparation of break-even and their uses.
Fund Flow, Cash planning & Budgeting.
Business Plan and Improving Financial
Management System.
2. Systems and controls
a) Computer Based systems
Ongoing Computerization Efforts
The most urgent financial management activity is the implementation of the computerized general
accounting system and billing and collection system.
(i) Computerized accounting system
Coverage. The computerized accounting system covers only the general accounting system.
Status. Under the previous ADB SSTA, the Hoda Vasi consultants developed a computerized accounting
system and prepared 4 manuals in August 2009 covering the Accounts Manual, Inventory, HRM and
Payroll Manual and the Training Manual. It appears there are two problems that constrain
implementation of the accounting system:
· The software problems have not been resolved. The system has been tested by
an independent source who believes the system is usable and is prepared to
support the training of KWASA staff in its use.
· Lack of accounting knowledge and computer skills as there is limited relevant
education and experience within the accounting staff. An Accounts Officer was
recently hired who will now lead the effort to set the accounting system in
place.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
10
Action taken under the PPTA. The PPTA assisted KWASA in drafting terms of reference (TOR) for a
service provider, discussing with potential service providers and preparing relevant contracts, and
securing financing from ADB. The TOR requires the provider to resolve the software problems
encountered in the Hoda Vasi accounting program, provide training, and ensure that the initial FY 2011
financial reports are generated.
As of end of November, the status of this activity is that a provider for the training has been identified,
discussions are ongoing with ADB as to how the implementation can be funded in compliance with
appropriate ADB regulations for this type of procurement. It is expected that the computerized system
will be fully operational and run by KWASA staff at the start of FY 2012.
(ii) Computerized billing system
Coverage. The computerized billing system includes (i) billing of customers, (ii) recording of collections,
and (iii) creation, updating and maintenance of customer accounts.
Action taken under the PPTA. The PPTA assisted KWASA in drafting terms of reference (TOR) for a
service provider, discussing with potential service providers and preparing relevant contracts, securing
financing from ADB. The TOR requires the provider to develop the software, install the program, provide
training, and ensure maintenance for a period of four months.
As of end of November, the status of this activity is that a detailed proposal has been submitted to ADB
for their consideration by the supplier - this will be reviewed in December and clarification of
procurement mechanism will be made by ADB. It is expected that the computerized system will be fully
operational and run by KWASA staff at the start of FY 2012.
Future computerization
Four other areas are proposed to be computerized in the coming years namely Inventory, HRM and
Payroll, Meter Reading and Fixed Assets.
Meter reading. Billing based on volume consumed which will be metered is planned to commence 2017
and it is expected that by 2017 all connections will be metered. It becomes imperative then, that prior to
2017 preparations are made for installation of connections and meters as well as development of a
systems for Meter Reading. It is planned that meter reading will be done in-house with IT handheld
units data on these devices will be uploaded to the computerized billing system which is expected to be
fully operational by 2017. A provision for automated meter reading is thus provided in the IT plan.
Fixed Asset Management System. Computerization of the creation, updating and maintenance of the
fixed asset register will facilitate KWASA’s asset management of its assets the growth of which will be
substantial in the coming years (from Tk 496 million to Tk 23 billion).
See table 2 for computerization plan.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
11
Table 2. Computerization Plan
b) Manual Based Systems
Other key systems do not need to be computerized. However it is important that policies and standard
procedures also be developed for these systems and these are documented in manuals for which
provides a training tool and guide for operations of KWASA. Table ___ shows the systems for which
manuals are proposed to be developed.
2011 2012 2013 2014 2015 2016 2017
PPTABridging
TA
A Package 1 - Billing System
1 Billing
2 Collection
3 Accounts Ledgers
B Package 2 - Accounting System
1 General Accounting
C Package 3 - Inventory and Payroll
2 Inventory
3 HRM and Payroll
D Package 4 - Meter Reading
E Package 5- Fixed Assets
Legend:
Regular recording and reporting operations by KWASA
Beyond
2017Loan Implementation
Bidding/Selection of Service Provider
Implementation (Program Development/Testing/Encoding of Beginning Balances/ Training/ Development
of Users Manual)
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
12
2010 2011 2012 2013 2014 2015 2016 2017
PPTA
1 Budgeting and Planning
Implement budget system based on KWASA practice
Prepare annual income budget for FY 2012 x x
Prepare annual Cash Budget for FY 2012 x x
Prepare Manual for comprehensive budgeting system x
Implement comprehensive budgeting system x x
2 Cash Operations
x x
Implement key cash operations
Recording and reporting of cash receipts x x
Recording and reporting of cash disbursementsx x
Preparing Bank reconciliation x x
Assess need for petty cash operation x x
Prepare Manual for comprehensive cash operations system x
Implement comprehensive cash operation system x x
3 Procurement
Prepare Manual for procurement system x
4 Project Accounting
Prepare Manual for project accounting system x
Implement project accounting system x x
5 Business Planning
Study 2010 Business Plan prepared by PPTA consultantsx x
Monitor targets in 2010 Business Plan x x x x x x x x
x x x x x x x
Implement business planning system x x x x x x x
Beyond
2017Bridging TA Loan Implementation
Develop policies related to cash operations
including policy related to approval limits
Prepare Manual for business planning
including update of the financial model
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
13
3. Revenue Management
A key feature of the KWASA Business Plan are the implementation of a volumetric tariff in FY 2017 and
the implementation of a revenue enhancement program comprising five major programs in the coming
years, as shown in Table 3:
Present
Target
Numbers Fiscal Year
a Increase in number of households and
connections from 2011 to 2016 as more
volume of water is made available from
ongoing and future projects.
Domestic Connections 26804 2016/2017
Non Domestic Connections 3811 2016/2017
b Registration of all illegal connections 2206 domestic
connections (6,508
households) and
138 non domestic
users using illegal
connections
all registered 2011/2012
c Conversion billing per household
Domestic Households 11853 additional
21,278
2011/2012
d Metering of all connections by 2017 100% metered 2016/2017
e Charging owners of private deep tubewells an
annual flat fee
17,799 private
DTWs billed
2016/2017
With the plan to implement a volumetric tariff by FY 2017 and the move towards cost recovery tariffs,
there is a need in the immediate future, to review the existing tariff setting policies and procedures and
cost recovery framework in KWASA. An appropriate tariff and cost recovery framework including the
tariff structure will be proposed under the Bridging TA and implemented during the loan
implementation period.
4. Financial Management Policies and Practices
The financial activities of KWASA are currently focused on the running of the accounting system which is
currently on a cash basis, and a simplified billing system, which is based on flat rate billings.
Comprehensive financial management concepts practiced by more advanced water utilities still need to
be introduced to KWASA in the coming years. These include concepts on:
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
14
• Cost Recovery
• Tariff Structuring
• Revenue Management
• Collection Enforcement
• Cost Analysis and Control
• Financial Reporting (as part of the MIS), Financial Statement Interpretation and Analysis
• Planning and Budgeting
• Business Planning/ Financial Modelling
The proposed consultancy assistance provided as part of the Bridging TA and loan implementation,
includes assistance to KWASA in policy development and implementation covering the above areas. By
the start of the loan implementation, it is expected that sufficient capacity would have been developed
by the staff to fully appreciate and actively participate in putting these concepts into practice.
List of Appendices for the Financial management Assessment Report
Appendix 1 – Preliminary 2009 and 2010 Financial Statements (same as Appendix 2 of the Business Plan)
Appendix 2 – List of Assumptions (same as Appendix 3 of the Business Plan)
Appendix 3 – Financial Projections for the Base Case (same as Appendix 4 of the Business Plan)
Appendix 4 – Scenario Analysis (same as Appendix 5 of the Business Plan)
Appendix 5 - Financial Management Systems Findings and Action Plan (See below)
Appendix 6 – Financial Management Assessment Questionnaire (See below)
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
15
Appendix 5
FINANCIAL MANAGEMENT STRENGTHENING PROGRAM
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
A. GENERAL ACCOUNTING
1. Financial Statements
a. Financial Statements (Income Statement,
Balance Sheet, and Cash Flow Statements) are
not prepared. KWASA prepares only a Cash
Collection Report and Cash Expenditures
Report. These do not give a complete picture
of the financial operations of KWASA.
The main reasons for this are lack of staff
capacity and systems.
KWASA should prepare the Income Statement,
Balance Sheet, and Cash Flow Statements
preferably every month and these should be
provided to management for review and action. A
computerized system will be finalized and
implemented to produce monthly financial
statements. Training will also be provided to the
staff so they could operate the system.
As of end of November 2010, a provider for
finalization of the system and training has been
identified; discussions are ongoing with ADB as to
how the implementation can be funded in
compliance with appropriate ADB regulations for
this type of procurement. It is expected that the
computerized system will be fully operational and
X X
X
b. There is lack of computer skills and lack of
capacity in handling accounting and financial
management responsibilities.
The proposed Capacity Building program includes
substantial training for the accounting and
revenue staff.
X X X X X
c. There is presently no Accounting Manual and
no Chart of Accounts. Previously Hoda Vasi
Chowdhury &Co prepared an Accounts Manual
and Chart of Accounts. However, these were
not used since the software they prepared did
not successfully run.
The computerized system will provide an
accounting manual and chart of accounts.
X
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
16
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
2. Double Entry Accounting System, Trial
Balance
a. At present, a single entry bookkeeping
system is being used and as a result only cash
transactions are recorded. This does not give
a complete picture of accounts since it does
not recognize income receivables and non
cash expenses.
A double entry bookkeeping system should be
implemented.
X X
3. General Ledgers
No general/control ledger is maintained. General ledgers should be maintained. X
4 Subsidiary Ledgers
a. KWASA maintains only the following ledgers
and registers and even these are not properly
maintained:
• Consumer Ledger
• Checque Issue Register
• Inventory Register
• Line Registers (New Line Connection
Register and Line Disconnection Register)
• Salary Register, Provident Fund Register
• Others (Stationery Register, Attendance
Register, )
But these subsidiary ledgers are not maintained
properly and totals are not obtained as a control
for the accuracy of the individual account balances.
Subsidiary ledgers should be maintained and
totals checked against the general ledger
balances.
X
5.Book of Original Entry
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
17
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
Journal voucher and journal proper are not
prepared for the opening entries, adjusting entries
and transfer entries
KWASA should prepare journal voucher and
journal proper to make opening entries, adjusting
entries and transfer entries.
X
6. Supporting Documents (preparation,
approval, filing)
Preparation, approval and filing of supporting
documents (Official receipts and disbursement
vouchers) are done properly.
X
7. Journal Vouchers
Journal Vouchers are not prepared for the
adjusting entries, transfer entries , etc.,
Journal vouchers will be prepared when the
double entry system will be introduced.
X
B. CASH OPERATIONS
1.Petty Cash
KWASA does not currently see the need for petty
cash. For the moment, emergency purchases are
handled by the employees advancing the amounts
needed.
In the future, when volume of operations have
increased, it is likely that there will be a need for
petty cash.
We propose that petty cash be maintained on
impress system whereby an impress amount will
be given as an advance to the petty cashier. The
petty cashier will disburse for the petty expenses
for the month. When the fund is used up, the
supporting documents for the disbursed amount
will be submitted to the head cashier for
reimbursement.
X X X
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
18
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
It is proposed that KWASA evaluate the need for
petty cash and prepare an appropriate policy
operationalize the fund.
2.Cash Receipts
The current procedure for the collection of water
sales and other receipts is fairly good. After
collection, the collectors hand over the collected
cash to the cashier who prepares a “pay in slip”
and deposits these collections. These are then
recorded in the Daily Cash Collection Report.
There is very limited amount of receipts that are
handled though as most of the water sales are
directly paid to the account of the KWASA in the 9
branches of Janota Bank.
3.Cash in Bank
Bank statements are not collected by the KWASA
at the end of each month. KWASA also does not
prepare Bank Reconciliation Statements to check
the balance of the bank statement with the
balance of the cash book.
Bank Reconciliation Register should be
maintained immediately. Training will be needed
for the accounting staff members on the
preparation of Bank Reconciliation Statement.
Bank Reconciliation Register will be designed. In
this connection bank statement should be
collected from the banks at the end of each
month.
X
4.Cash Disbursements
(a)There are no clear policies on disbursements to
ensure such as policies delineating approval levels.
All disbursements, regardless of amount are
approved by the Managing Director.
(i) Considering the expected increase in volume
of disbursements in the coming years, policies
on approval levels need to be developed so as
not to overburden the MD with administrative
tasks.
X
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
19
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
(b) Debit vouchers are now prepared to authorize
disbursements. These are supported by a piece of
paper which is prepared to note the need for
payment.
(c )Existing systems on disbursements provide for
most payments to be made by check. Only
employees who are in the master roll are paid in
cash.
C. BILLING SYSTEM
1.Billing on flat rate per connection
Bills are prepared on flat rates per connection. Bills
are prepared manually and given to the
consumers.
Instead of flat rate for different types of
consumers, different rates should be charged
for different types of consumers.
X
2. Manual billing system Computerized system
(a) There is a simple billing system in place in
KWASA that is appropriate to the current needs
of KWASA with its unmetered connections as
follows:
• KWASA issues a demand note at the
beginning of the FY to its customers. This
demand note contains the payment for 1
year which the customer can pay either
through the bank, through the field
collector or in the office. If a customer
chooses to pay through the bank, he has to
get a receipt book for 25 taka, which
It is planned that a computerized billing and
collection system will be developed. The PPTA
assisted KWASA in drafting terms of reference
(TOR) for a service provider, discussing with
potential service providers and preparing
relevant contracts, securing financing from ADB.
The TOR requires the provider to develop the
software, install the program, provide training,
and ensure maintenance for a period of four
months.
As of end of November, a detailed proposal has
been submitted to ADB for their consideration by
the supplier. This will be reviewed in December
X X X
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
20
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
consists of 3 parts; one for the bank, one
for KWASA and one for the customer.
Another check receipt is issued for field
collection.
• There are at least 14 employees who
handle billing and collection which includes
1 cashier, 10 doing field collection, and 43
persons doing billing and maintenance of
customer records. KWASA issues a two-
part receipt with one part given to the
customer and the other part, retained in
the office and is in the recorded in the
customer ledger card.
• A receipt book for free water is also
maintained. It is the policy of KWASA to
provide free water to the mayor and police
officers from bowsers; they pay only the
petrol bill.
and clarification of procurement mechanism will
be made by ADB. It is expected that the
computerized system will be fully operational and
run by KWASA staff at the start of FY 2012.
The computerized billing and collection system
will correct all the system deficiencies previously
noted.
(b) A Consumer Ledger is maintained but the
total of the consumer account balances is not
computed as such, it is difficult to determine the
accounts receivables balance. The accounting staff
find it difficult to manually compute the total of
the balances of the 12,000 plus customers.
Eventually, implementation of a computerized
billing and collection system will result in a well
maintained Customer Ledgers. In the meantime,
KWASA needs to start cleaning up and updating
the Customer Ledger so that it is reading for
encoding of the beginning balances once the
billing and collection system is ready for
implementation.
X X X
(e) Monitoring and Reporting. The system does
not provide, however, for the monitoring of
customer accounts and is not able to generate
important summary reports like billing summaries,
water sales reports, accounts receivables balance,
Implementation of a computerized billing and
collection system.
X X X
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
21
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
status of service connections, collection
performance reports and others that are
necessary for planning and control. The system
because of its limited features will not be able to
support future growth in services.
D. COLLECTION SYSTEM
1. Collection by bank
Now collection is done by three ways, namely
a) collection by bank
b) collection by field collectors
c) collection in the KWASA head office
There is currently no system of providing discounts
for early payments and imposing penalties on
delayed payments.
KWASA should study the feasibility of providing a
system of discounts and penalties as part of its
collection enforcement program.
X x x x X
2. Disconnection Policy
(a )The collection effort is difficult in the absence
of a well maintained Customer Ledger which is also
the basis for the preparation of the Aging of
accounts.
The Customer Ledger should be maintained
properly and resources provided (computers and
staff training) to allow revenue staff to compute
the totals of customer accounts. Eventually, the
computerized billing and collection system will
correct system deficiencies.
X X X X X
(b) The WASA’s disconnection policy is as follows.
A red notice is given to the consumer whose
outstanding bills exceed Tk.5000. On this basis, a
KWASA team goes on door collection drive door
and requests the party with arrears to pay the bill.
If the party does not pay the bills after receiving
the red notice and verbal request, then his /her
Implementation of a computerized billing and
collection system.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
22
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
connection is disconnected.
Effective implementation of the disconnection
policy depends to a large extent on well
maintained Customer Ledgers.
3. Aging of receivables
Aging of receivables is not prepared because of the
absence of a well maintained Customer Ledger.
Aging should be done which can be the basis for
developing a policy on writing off of accounts and
providing an allowance for bad Debts.
• Unrecoverable receivables from KCC
• Consumers who are not available now or who
have shifted to an unknown place
• Outstanding receivables of more than 10
years
X X X X X
4. Allowance for Bad Debts
KWASA has no policy for writing off bad debt Develop policies on providing allowances for
uncollectible accounts. KWASA needs to develop
a policy for setting up an allowance for bad debts
and discuss this with the auditor. This can be set
up based on the aging of receivables.
KWASA can also consider DWASA’s policy which
is to provide 5% of water sales as an allowance
for bad debts in setting up the policy.
X
5.Write Off of Bad Debts
Based on the aging of accounts, a policy on
writing off of accounts can be developed and
discussed with the auditor. The policy can
X X X
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
23
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
consider the following:
• Unrecoverable receivables from KCC
• Consumers who are not available now or who
have shifted to an unknown place
• Outstanding receivables of more than 10
years
E. FIXED ASSETS
There are no policies for asset requisitioning,
transfer, disposal, depreciation and retirement.
There is no system on fixed asset management.
KWASA needs to develop appropriate policies on
asset requisitioning, transfer, disposal,
depreciation and retirement. There is no system
on fixed asset management
1. Physical Count
A listing of assets that were turned-over during the
establishment of KWASA is available. However, the
amounts reported have not yet been verified as to
the correctness of the values of the assets.
Individual property cards have yet to be set up.
Also, the assets reported in the listing of assets are
not properly classified and no depreciation is
computed and recognized.
External Auditor is expected to conduct physical
verification of fixed assets. Subsequently staff
members should conduct the annual
verification.If funds will allow, an asset condition
survey should also be conducted to establish
sufficient information on the assets and which
will be useful later on for asset management
planning.
X x x X
2. Assets Register
There is no fixed assets register to keep record of
fixed assets
Fixed assets register will be computerized. Staff
members will be developed through training.
Implementation with the help of software
consultant.
X
3. Purchasing of Assets
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
24
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
At present there is no policy on purchasing and
procurement of fixed assets
Appropriate policies need to be developed. X x
4. Depreciation
Depreciation has not yet been taken into account. Depreciation should be charged at prescribed
rate against each fixed asset. External auditor will
help in this regard.
X X X X X
5. Safeguarding fixed assets
Responsibilities have not been allocated among the
staff members to safe guard fixed assets. Security
arrangement is inadequate to safe guard the fixed
assets.
Responsibilities are to be allocated among staff
members to safeguard and protect the fixed
assets. Proper security is to be provided to
protect the fixed assets.
X
6. Sale and disposition
Rules for sales and disposition of fixed assets are
lacking now
Rules for sale and disposition should be framed
immediately
X
7. Insurance
Valuable fixed assets are not insured All fixed assets should be insured X
8. Project Accounting -
At present no one handles project accounting.
KWASA does not record any construction in
progress.
In near future there will be a need for introducing
project accounting to the accounting unit so that
the proper construction in progress accounts can
be reflected in the financial reports. The Accounts
Officer needs to be given training to equip her to
handle Project Accounting in the future.
X
F. INVENTORY MANAGEMENT
1. Warehousing
The stores (inventory) are still maintained centrally
in KWASA although KWASA does not have
sufficient space with which to store these stocks.
KWASA needs to study how to address these
warehousing space issues.
X X
2. Inventory Policies
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
25
Findings Proposed Action Plan
Implementation
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
There is a lack of policies on inventory, such as
minimum stock levels, valuation of obsolete items,
disposal, etc.
Moreover, all purchases are approved by the MD
up to Tk 14999 beyond which a Purchase
Committee evaluates and approves purchases.
Appropriate policies need to be developed in
these areas including policies on approval levels
for purchases.
X X
3. Inventory System
The existing inventory system is not adequate.
There are simple systems whereby requisition slips
are the basis for release of inventory items.
KWASA also maintains inventory registers
containing quantities received and issued.
However, KWASA finds it difficult to properly
maintain the registers manually. And since
summary totals are not also determined, there is
no way to check whether the information in the
registers is correct.
Development of a computerized inventory
system is proposed in the MIS and IT Plan to
resolve these problems.
X X X X X
4. Physical Verification
KWASA received list of inventories from KCC which
as of June 2009 amounted to some Taka 702,000
but to date KWASA has not had the opportunity to
verify the existence of these inventories as well as
inventories of purchased items on stock. There are
no stock cards maintained for individual inventory
items.
External Auditor will conduct physical verification
of all stores. Subsequently, at the end of each
year KWASA should conduct physical verification
of all inventories.
X X x X X
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
26
Appendix 6
Khulna Water Supply and Sewerage Authority
Financial Management Assessment Questionnaire
Topic Response Remarks
1. Implementing Agency
1.1 What is the entity’s legal
status / registration? Khulna WASA was established
under Ordinance No. Gazette No.
(Dhaka, 25 February 2008; S.R.O
no-43-law/2008- law/division pass-
2/K 1/2007) as an autonomous
entity in charge of water supply and
sewerage services in Khulna. Under
the ordinance, the assets and
liabilities of the then waterworks
department were transferred to the
new organization including all the
rights and obligations of a WASA
under the WASA Act of 1996.
Khulna WASA is in very early stage of development.
It is still in the process of staffing its organization
and setting up required systems and procedures.
1.2 Has the entity implemented
an externally-financed project
in the past (if so, please
provide details)?
No, Khulna WASA has just recently
been established.
There are proposed projects already, the JICA and
ADB projects among others.
1.3 What are the statutory
reporting requirements for
the entity?
These reporting requirements are
not yet well defined, except those
contained in the KWASA Act.
1.4 Is the governing body for the
project independent?
The Board is the Governing Body of
KWASA. In the spirit of the 1996 Act
the Board should perform its
functions in full autonomy.
There is no basis yet to comment on this as the
Board has also been recently established.
1.5 Is the organizational structure
appropriate for the needs of
the project?
Several key positions such as the
Accounts Officer and Revenue
Officers have been recently
recruited.
Phase 2(FY 2013/2014) organization structure
creating a separate department handling customer
service and Phase 3 (FY 2016/ 2017) organization
structure introducing a zonal operation system have
both been proposed in the Business Plan.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
27
Topic Response Remarks
2. Funds Flow Arrangements
2.1 Describe (proposed) project
funds flow arrangements,
including a chart and
explanation of the flow of
funds from ADB, government
and other financiers.
The funds will be lent to GoB which
in turn will re-lend them to KWASA.
Proposed re-lending terms include:
- Interest rate 2%
− 30 years repayment
period including grace
period of 8 years.
- 70% Loan
- 30% Grant
JICA will also lend USD 100 Million
for water supply development
2.2 Are the (proposed)
arrangements to transfer the
proceeds of the loan (from
the government / Finance
Ministry) to the entity
satisfactory?
The current system of transfer of
funds is from the Ministry of Local
Government and Rural
Development to KWASA.
KWASA receives funds from the national govt.
through the MLGRD for its on-going project which is
a grant and for its regular subsidies.
2.3 What have been the major
problems in the past in
receipt of funds by the entity?
Nothing to report on this yet.
2.4 In which bank will the Imprest
Account be opened?
Most probably Janata Bank, Ltd. in
Khulna
This is a state owned commercial bank
2.5 Does the (proposed) project
implementing unit (PIU) have
experience in the
management of
disbursements from ADB?
No experience yet.
2.6 Does the entity have/need a
capacity to manage foreign
exchange risks?
There is no need to develop the
capacity to manage foreign
exchange risks, as the relending will
be most likely in local currency.
2.7 How are the counterpart
funds accessed?
ADB and GOB funds will be
allocated in the Annual
Development Program (ADP) with
regards to the budget estimates
prepared by the PMU based on the
annual work plan of the project.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
28
Topic Response Remarks
2.8 How are payments made
from the counterpart funds?
The Project Director (PD) of PMU
who is the authorized signatory to
withdraw ADB loan proceeds is also
the Drawing and Disbursement
Officer (DDO) to draw the
Government funds. GOB funds
allocated in the ADP will be
released quarterly and the PMU will
present the bills to the Chief
Accounts Officer (CAO) for actual
disbursement.
2.9 If part of the project is
implemented by communities
or NGOs, does the PIU have
the necessary reporting and
monitoring features built into
its systems to track the use of
project proceeds by such
agencies?
No.
2.10 Are the beneficiaries required
to contribute to project
costs? If beneficiaries have an
option to contribute in kind
(in the form of labor), are
proper guidelines formulated
to record and value the labor
contribution?
N/A
3. Staffing
3.1 What is the organizational
structure of the accounting
department? Attach an
organization chart.
Under the approved organization
structure, the Financial Unit (A/C
and Budget) is under the
Commercial Department.
Please refer to the organization and composition of
the finance unit in Chapter IV of the main report.
3.2 Identify the (proposed)
accounts staff, including job
title, responsibilities,
educational background and
professional experience.
Attach job descriptions and
CVs of key accounting staff.
Please refer to Appendix for
accounting staff qualifications
3.3 Is the project finance and
accounting function staffed
adequately?
No, these divisions are yet to be
established
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
29
Topic Response Remarks
3.4 Is the finance and accounts
staff adequately qualified and
experienced?
Not yet. Recruitment is still in
process to complete the staff
complement for the accounting and
revenue sections.
3.5 Is the project accounts and
finance staff trained in ADB
procedures?
They are not yet trained on ADB
procedures.
Some of the staff are qualified and can be trained
on ADB procedures
3.6 What is the duration of the
contract with the finance and
accounts staff?
7 out of the 15 staff finance and
commercial staff are on contractual
basis with annual renewable
contracts and have been with
KWASA (KCC) for a long time
already
3.7 Indicate key positions not
contracted yet, and the
estimated date of
appointment.
Key positions already contracted. In
the coming months, KWASA plans
to hire an accountant, revenue
inspectors (2) and assistant
accountants (2).
3.8 Does the project have written
position descriptions that
clearly define duties,
responsibilities, lines of
supervision, and limits of
authority for all of the
officers, managers, and staff?
No
3.9 At what frequency are
personnel transferred?
There is very little transfer of
personnel as most staff have been
on the job for quite some time,
even the casual/temporary
employees.
Those who are deputed from other govt. agencies
(like the posts of the DMD for Finance and the
Secretary) have indefinite period of assignments
and may or not stay for a long period with KWASA.
3.10 What is training policy for the
finance and accounting staff?
Not existing
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
30
Topic Response Remarks
4. Accounting Policies and
Procedures
4.1 Does the entity have an
accounting system that allows
for the proper recording of
project financial transactions,
including the allocation of
expenditures in accordance
with the respective
components, disbursement
categories, and sources of
funds? Will the project use
the entity accounting system?
No, the current system is cash
based, using a single entry method.
Contracts for software
development for the general
accounting and billing and
collection systems are currently
being negotiated. Eventually, the
project will be using the proper
entity accounting system.
4.2 Are controls in place
concerning the preparation
and approval of transactions,
ensuring that all transactions
are correctly made and
adequately explained?
Not sufficient.
4.3 Is the chart of accounts
adequate to properly account
for and report on project
activities and disbursement
categories?
No chart of accounts. Contracts for software development for the general
accounting system is currently being negotiated.
This includes the development of a chart of
accounts.
4.4 Are cost allocations to the
various funding sources made
accurately and in accordance
with established agreements?
Not yet applicable
4.5 Are the General Ledger and
subsidiary ledgers reconciled
and in balance?
Since the system is still on single-
entry; this is not yet applicable.
There are however subsidiary
ledgers particularly for accounts
receivable but there is no general
ledger balance
4.6 Are all accounting and
supporting documents
retained on a permanent
basis in a defined system that
allows authorized users easy
access?
Per GOB regulations there is no
prescribed period for disposal of
accounting and supporting
documents. Everything is retained.
i Segregation of Duties
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
31
Topic Response Remarks
4.7 Are the following functional
responsibilities performed by
different units or persons: (i)
authorization to execute a
transaction; (ii) recording of
the transaction; and (iii)
custody of assets involved in
the transaction?
Yes, to a limited extent, since the
staff complement is not yet
complete
4.8 Are the functions of ordering,
receiving, accounting for, and
paying for goods and services
appropriately segregated?
Not yet implemented
4.9 Are bank reconciliations
prepared by someone other
than those who make or
approve payments?
No. PPTA consultants are providing
on the job training on the
preparation of bank reconciliation
statements.
ii Budgeting System
4.10 Do budgets include physical
and financial targets?
They have annual budgets but
these are not tied to physical
targets.
4.11 Are budgets prepared for all
significant activities in
sufficient detail to provide a
meaningful tool with which to
monitor subsequent
performance?
They have annual budgets but do
not provide for sufficient details.
4.12 Are actual expenditures
compared to the budget with
reasonable frequency, and
explanations required for
significant variations from the
budget?
Not yet being done.
4.13 Are approvals for variations
from the budget required in
advance or after the fact?
Yes, it is required.
4.14 Who is responsible for
preparation and approval of
budgets?
The MD with support from the
DMD for Finance is responsible for
budget preparation. Approval of
the budget is by the Board of
Directors under the current set-up.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
32
Topic Response Remarks
4.15 Are procedures in place to
plan project activities, collect
information from the units in
charge of the different
components, and prepare the
budgets?
Project activities are being done
sparingly under the Engineering
Division under the DMD for
Engineering. The systems for
planning and budgeting for various
activities are not yet in place.
4.16 Are the project plans and
budgets of project activities
realistic, based on valid
assumptions, and developed
by knowledgeable
individuals?
The existing plans and budgets (for
proposed investments) are not very
clear on the effect on the levels of
service, as in they do not indicate
details on projected production and
demand for instance.
Payments
4.17 Do invoice-processing
procedures provide for: (i)
Copies of purchase orders
and receiving reports to be
obtained directly from issuing
departments? (ii) Comparison
of invoice quantities, prices
and terms, with those
indicated on the purchase
order and with records of
goods actually received? (iii)
Comparison of invoice
quantities with those
indicated on the receiving
reports? (iv) Checking the
accuracy of calculations?
Some procedures are in place, but
they are very limited to provide
internal controls.
4.18 Are all invoices stamped PAID,
dated, reviewed and
approved, and clearly marked
for account code assignment?
Not being done.
4.19 Do controls exist for the
preparation of the payroll and
are changes to the payroll
properly authorized?
Yes
Policies And Procedures
4.20 What is the basis of
accounting (e.g., cash,
accrual)?
Cash basis
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
33
Topic Response Remarks
4.21 What accounting standards
are followed?
The following standards were used
in the initial statements prepared
by KCC and subsequent ones (for
June 2009) prepared by Hoda Vasi:
Generally Accepted Accounting
Principles (GAAP) and the
Bangladesh Accounting Standards
adopted by the Institute of
Chartered Accountants of
Bangladesh (ICAB).
4.22 Does the project have an
adequate policies and
procedures manual to guide
activities and ensure staff
accountability?
Not yet applicable.
4.23 Is the accounting policy and
procedure manual updated
for the project activities?
Not yet applicable.
4.24 Do procedures exist to ensure
that only authorized persons
can alter or establish a new
accounting principle, policy or
procedure to be used by the
entity?
No.
4.25 Are there written policies and
procedures covering all
routine financial management
and related administrative
activities?
None
4.26 Do policies and procedures
clearly define conflict of
interest and related party
transactions (real and
apparent) and provide
safeguards to protect the
organization from them?
None None
4.27 Are manuals distributed to
appropriate personnel?
No. No.
Cash and Bank
4.28 Indicate names and positions
of authorized signatories in
the bank accounts.
Abdullah Pinze (Managing Director)
and Alimuddin (Deputy Managing
Director for Administration and
Finance
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
34
Topic Response Remarks
4.29 Does the organization
maintain an adequate, up-to-
date cashbook, recording
receipts and payments?
Yes
4.30 Do controls exist for the
collection, timely deposit and
recording of receipts at each
collection location?
Yes
4.31 Are bank and cash reconciled
on a monthly basis?
No
4.32 Are all unusual items on the
bank reconciliation reviewed
and approved by a
responsible official?
Not applicable. Bank reconciliation
is not currently prepared
4.33 Are all receipts deposited on
a timely basis?
Yes
Safeguard over Assets
4.34 Is there a system of adequate
safeguards to protect assets
from fraud, waste and abuse?
None
4.35 Are subsidiary records of fixed
assets and stocks kept up to
date and reconciled with
control accounts?
Records are incomplete especially
for fixed assets and are not
reconciled with total ledger
balance.
4.36 Are there periodic physical
inventories of fixed assets and
stocks?
No.
4.37 Are assets sufficiently covered
by insurance policies?
No.
Other Offices and Implementing
Entities
4.38 Are there any other regional
offices or executing entities
participating in
implementation?
No.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
35
Topic Response Remarks
4.39 Has the project established
controls and procedures for
flow of funds, financial
information, accountability,
and audits in relation to the
other offices or entities?
NA.
4.40 Does information among the
different
offices/implementing
agencies flow in an accurate
and timely fashion?
NA.
4.41 Are periodic reconciliations
performed among the
different
offices/implementing
agencies?
NA
Other
4.42 Has the project advised
employees, beneficiaries and
other recipients to whom to
report if they suspect fraud,
waste or misuse of project
resources or property?
Not yet applicable.
5. Internal Audit
5.1 Is there an internal audit
department in the entity?
No. No.
5.3 To whom does the internal
auditor report?
N.A.
5.4 Will the internal audit
department include the
project in its work program?
An Internal Control Unit is proposed
to be created as part of Phase 3
organization structure to be
implemented in FY 2016/2017. This
unit will perform the internal audit
function for KWASA transactions
including those pertaining to the
project.
.
5.5 Are actions taken on the
internal audit findings?
N.A.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
36
Topic Response Remarks
6. External Audit
6.1 Is the entity financial
statement audited regularly
by an independent auditor?
Who is the auditor?
KWASA is in the process of hiring an
external auditor.
6.2 Are there any delays in audit
of the entity? When are the
audit reports issued?
Not yet applicable.
6.3 Is the audit of the entity
conducted according to the
International Standards on
Auditing?
Not yet applicable.
6.4 Were there any major
accountability issues brought
out in the audit report of the
past three years?
Not yet applicable
6.5 Will the entity auditor audit
the project accounts or will
another auditor be appointed
to audit the project financial
statements?
Not yet applicable.
6.6 Are there any
recommendations made by
the auditors in prior audit
reports or management
letters that have not yet been
implemented?
Not yet applicable.
6.7 Is the project subject to any
kind of audit from an
independent governmental
entity (e.g., the supreme
audit institution) in addition
to the external audit?
6.8 Has the project prepared
acceptable terms of reference
for an annual project audit?
Not yet
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
37
Topic Response Remarks
7. Reporting and Monitoring
7.1 Are financial statements
prepared for the entity? In
accordance with which
accounting standards?
Yes. GAAP, and Bangladesh
Accounting Standard ( BAS), see
question 4.21
7.2 Are financial statements
prepared for the
implementing unit?
Yes, initial statements being
prepared by KCC; subsequent ones
(for June 2009) were prepared by
Hoda Vasi.
7.3 What is the frequency of
preparation of financial
statements? Are the reports
prepared in a timely fashion
so as to useful to
management for decision
making?
Not yet defined.
7.4 Does the reporting system
need to be adapted to report
on the project components?
Yes
7.5 Does the reporting system
have the capacity to link the
financial information with the
project's physical progress? If
separate systems are used to
gather and compile physical
data, what controls are in
place to reduce the risk that
the physical data may not
synchronize with the financial
data?
No.
Project management guidelines will
be established to link financial
information and physical progress
of the project.
7.6 Does the project have
established financial
management reporting
responsibilities that specify
what reports are to be
prepared, what they are to
contain, and how they are to
be used?
This is to be part of the Loan
Agreement.
7.7 Are financial management
reports used by
management?
No.
Appendix 8 FINANCIAL MANAGEMENT ASSESSMENT REPORT
38
Topic Response Remarks
7.8 Do the financial reports
compare actual expenditures
with budgeted and
programmed allocations?
No. the only financial statements
available were those prepared with
the aid of the consultants.
7.9 Are financial reports prepared
directly by the automated
accounting system or are they
prepared by spreadsheets or
some other means?
KWASA does not have an
automated accounting system.
Reports are prepared manually by
spreadsheets.
8. Information Systems
8.1 Is the financial management
system computerized?
No.
8.2 Can the system produce the
necessary project financial
reports?
Not Applicable
8.3 Are the staff adequately
trained to maintain the
system?
Not Applicable
8.4 Does the management
organization and processing
system safeguard the
confidentiality, integrity and
availability of the data?
Not Applicable
Appendix 9 FINANCIAL ANALYSIS OF KHULNA WASA
1
FINANCIAL ANALYSIS OF KHULNA WASA
A. Past and Current Financial Performance
Financial assessment of past and current financial performance was based on estimates of KWASA’s
results of operations for FY 2009 and FY 2010 and its financial condition as of FY 2010. Income and
balance sheet figures for FY 2009 were based on the ADB SSTA1 as well and the JICA feasibility study
2
reports. In addition to these, the consultants prepared preliminary financial reports for FY 2010 based
on available data provided by KWASA and results of the consumer survey. See Annex 2 of Appendix 6 -
Business Plan for the Preliminary Financial Statements. It is understood that the figures presented in the
Preliminary Financial Statements are indicative figures and the financial audit will provide a more sound
basis for the assessing the current and future financial viability of KWASA. KWASA is taking steps to get
the audit completed by end of FY 2010. When the audited financial reports are available, it may be
necessary to revise the assessment of KWASA’s financial performance.
Based on the preliminary financial statements, it appears that KWASA’s performance has deteriorated
from FY 2009 to FY 2010. The net loss has increased from Tk 8.5 million to Tk 50 million due to the
significant reduction in revenue and the huge increase in expenses as shown in Table 1.
Table 1. Summary Income Statement (FY 2009 to FY 2010)
There were different bases for estimation of revenues for the two years. It appears that revenue
estimates for FY 2009 were based on 15,236 registered connections while the figure for FY 2010
revenues is based on a significantly lower number of connections of 12,238 based on the survey results.
The significant increase in expenses from was also due to the following:
1 Supporting the Establishment of Khulna Water Supply and Sewerage Authority (ADB TA 7223-BAN), Final Report, November 2009. 2 Feasibility Study for Khulna Water Supply Improvement Project in Bangladesh, Japan International Cooperation Agency, July 2010.
Inc/Dec
Income
Operating Revenues 16,444 100.0% 11,764 100.0% -28%
Non-Operating Revenues 64 0.4% 109 0.9% 70%
Total Income 16,508 100.4% 11,873 100.9% -28%
Expenses
Personnel Expenses 17,758 108.0% 36,696 311.9% 107%
Fuel and Electricity 4,659 28.3% 11,230 95.5% 141%
Chemicals 0.0% 0.0%
Repair & Maintenance 546 3.3% 5,497 46.7% 907%
Administrative and General Expenses 2,081 12.7% 8,005 68.0% 285%
Total Expenses 25,044 152.3% 61,428 522.2% 145%
Net Profit/Loss (8,536) -51.9% (49,555) -421.2% 481%
June 30, 2009 June 30, 2010
In Thousand Taka
Appendix 9 FINANCIAL ANALYSIS OF KHULNA WASA
2
• Increase in salaries and allowances due to implementation of the new pay scale as well as hiring
of additional personnel.
• Higher electricity bills due to the general increase in cost of power as well as the increase in
number of pumps from 60 in 2009 to 78 in 2010.
• KWASA undertook numerous repair and maintenance of pipelines, pump motors, vehicles,
office equipment and buildings in 2010 resulting in higher repairs costs.
Analysis of KPIs in Table 2 also show other factors leading to the lack of revenues to sustain operations.
These factors include flat rate billings instead of consumption based billings, less than 100% ratio of
connections billed due to illegal connections, around 70% of households which are not billed since
billing does not consider number of households and an 80% collection efficiency. The resulting low
revenues could only partially cover cash operating and maintenance expenses resulting in an operating
ratio of 5.17.
Table 2. KPIs
Formula FY 2011
Metered Connections 0
Total Number of Connections Connections billed 84%
No. of Connections Supplied
Households billed 37%
No. of households Supplied
Total Year-to-Date Collection 80% Total Year-to-Date Billing
Operating Expenses (excl depreciation) 4.17
Operating Revenues
B. Projected Financial Performance
The financial plan is prepared to ensure that KWASA will remain viable during the period of project
implementation up to loan repayment of the ADB/JICA loan. Financial viability is demonstrated through
the financial projections which should show sufficiency of revenues to cover O&M (excluding
depreciation) and sufficiency of cash to cover operational expenses and debt service, thereby
eliminating the need for government subsidy. The financial projections shown in this report cover up to
year 2020.
1. Major Assumptions
In order to assess future performance, during the projection period, the following basic assumptions
were used:
a. Investment and Production. The investment plan shows that KWASA will implement 5
major projects including 2 projects implemented by KCC to be turned over to KWASA upon
Appendix 9 FINANCIAL ANALYSIS OF KHULNA WASA
3
completion, 2 projects funded by GoB and the ADB/JICA project all totalling Tk 26 billion.
These projects will result in an increase in production from the current 30,100 m3/day to
162,427 m3/day in 2017. Investments in the network will reduce Non Revenue Water from
the current estimated level of 36% to 25% by 2017 and down further to 20% by 2018.
b. Revenues. Although the survey reports 32,292 domestic users, only 11,853 households are
currently registered. The rest are unbilled household users resulting from the practice of
several households sharing a connection or else are illegal users. In the coming years, the
KWASA will embark on five major programs to increase connections and bill all users as
shown in Table 3 below.
Table 3 - Key Revenue Improvement Action Plan
c. O&M. Salaries and allowances will increase substantially as number of staff will increase
from 284 to 502 by 2017. Average salaries and % allowances will also increase, the latter the
result of the planned conversion of most of casual staff to permanent staff by 2017.
Chemicals and Depreciation expenses will start to be recognized and recorded as part of
O&M expenses.
See detailed assumptions in Annex 3 of Appendix 7- Business Plan.
2. Financial Projections
a. Financial Model
Under the PPTA, the consultants prepared a draft Business Plan to help KWASA attain its corporate
objectives and targets in the years to come. A strategic tool used in the preparation of the Business Plan
is the financial model which allows management to assess the impacts of various scenarios on the
Numbers Fiscal Year
a Increase in number of connections from 2011 to 2017
as more volume of water is made available from ongoing
and future projects.
Domestic Connections (end of fiscal year) 11853 40863 FY 2017
Non Domestic Connections (end of fiscal year) 385 4334 FY 2017
b Registration of all illegal connections 2206 illegal
domestic
connections and
138 illegal non
domestic
connections
zero FY 2012
c Conversion billing per household
Domestic Households (end of fiscal year) 11853 32292 FY 2012
d Metering of all connections by 2017 (end of fiscal year) zero 45197 FY 2017
e Charging owners of private deep tubewells an annual flat
fee
no charges 17,799 private
DTWs billed
FY 2017
f Annual flat fee for deep tubewells Tk 3000 FY 2017
PresentTarget
Appendix 9 FINANCIAL ANALYSIS OF KHULNA WASA
4
financial performance of KWASA. Under the PPTA consultancy, a model was developed which is the
basis for the financial assessment of KWASA’s future performance in the succeeding sections.
b. Base Case
The base case considers the following tariff scenario:
• Tariff increases on the monthly flat rate at 5% per year from 2012 to 2016
• At the start of the metering program in 2017, an initial tariff in real prices of Tk 13.00/m3 for
domestic connections (Tk 19.21/m3 in 2017 prices) and Tk 26.00/m3 for non domestic
connections (Tk 38.41/m3 in 2017 prices)
• Annual tariff increases at 5% after 2017
The base case also assumes that 30% of the project cost will be funded by government equity and 70%
through government loan. The assumed concessional terms of the loan are 2% interest rate per annum,
30 years repayment including an 8 year grace period on principal and interest payment. The results of
the analysis in Table 4 reveal that:
• While some years will result in annual cash deficits, KWASA’s cash balances will generally be
sufficient to cover cash operating and maintenance costs and debt service.
• Debt service coverage ratios are lower than the standard 130%, but this target will eventually be
met in future years
• Operating ratio before depreciation shows significant improvement from the current 5.17 to .46
in 2017 when the metered tariffs are implemented. As a result, net income ratio also improves
in the coming years with the implementation of the metered tariffs and the growth in
connections.
See Annex 4 of Appendix 6 – Business Plan showing the resulting financial projections for the base
case.
Appendix 9 FINANCIAL ANALYSIS OF KHULNA WASA
5
Table 4 – Results of Base Case
c. Sensitivity Scenarios
Two other scenarios were developed to test the financial viability of the project. See Table 5.
Year
2010 (28,513) 27,108 5.17 (4.17)
2011 32,571 59,679 4.17 (5.22)
2012 57,926 117,605 1.48 (1.26)
2013 57,607 175,212 1.52 (1.26)
2014 (48,320) 126,893 1.97 (1.47)
2015 (38,584) 88,308 1.57 (1.06)
2016 (37,629) 50,679 1.49 (1.11)
2017 332,878 383,557 0.46 0.46 19.21
2018 522,838 906,395 0% 0.39 0.58 20.17 5%
2019 612,295 1,518,690 0% 0.37 0.60 21.18 5%
2020 (406,833) 1,111,857 65% 0.36 0.27 22.23 5%
2021 (392,116) 719,741 67% 0.39 (0.15) 23.35 5%
2022 (312,424) 407,316 73% 0.38 (0.07) 24.51 5%
2023 (240,147) 167,170 80% 0.37 (0.01) 25.74 5%
2024 (162,356) 4,813 87% 0.37 0.06 27.03 5%
2025 (70,043) (65,230) 96% 0.36 0.04 28.38 5%
SCENARIO 1 (Option 1) - Selected KPIsAnnual
Cash
Surplus
(Defiiciency)
Ending
Cash
(Tk000)
Debt
Service
Ratio
Operating
Ratio before
depr
Net Income
Ratio
Domestic
Tariff
Tariff
Adjustment
Appendix 9 FINANCIAL ANALYSIS OF KHULNA WASA
6
Table 5 – Financial Model Scenario Variables
The scenario analysis results reveal the following:
Under Scenario 2, KWASA’s operations will result in substantial losses and cash deficits under a scenario
where a lower domestic tariff of Tk 6/m3 and non domestic tariff of Tk 12/m3 (both in real prices) are
implemented.
Under Scenario 3, KWASA’s revenues can recover O&M costs and debt service under a scenario where a
higher domestic tariff of Tk 26.00/m3 and non domestic tariff of Tk 52..00/m3 (both in real prices) are
implemented.
The results of the sensitivity analysis are given in Annex E of Appendix 6 – Business Plan.
C. Major Risks and Safeguards
Major risks to the attainment of the project objectives include:
a) Inadequate capacity of EA to manage the project
b) Inadequate capacity of EA to implement the key assumptions in the Business plan including the
revenue enhancement measures and the required tariff increases
KWASA needs to operationalize the Business Plan which provides a roadmap toward the attainment of
the project viability. The Government on the other hand, needs to give KWASA the support it needs
particularly in the area of more concessionary loan terms to enable the project to be viable.
Scenario 1 (Base) Scenario 2 Scenario 3
Tariffs
Starting Tariff (2009 prices)
Domestic connections Tk 13.00/m3 Tk 6.00/m3 Tk 26.00/m3
Non domestic connections Tk26.00/m3 Tk12.00/m3 Tk52.00/m3
Annual Tariff Increases starting 2012 5% 5% 5%
Financing
% Grant, % Loan 30% Grant; 70% Loan 30% Grant; 70% Loan 30% Grant; 70% Loan
Loan terms
Interest Rate 2% 4% 4%
Grace/Repayment period
8 years grace period,
22 years repayment
period
7 years grace period,
15 years repayment
period
7 years grace period,
15 years repayment
period
FINAL REPORT
I
PÖ
YR
Y ID
P C
ON
SU
LT, I
NC
.
PREPARING THE KHULNA WATER SUPPLY ADB TA 7385 - BAN
Pöyry IDP Consult, Inc.
In association with
HB CONSULTANTS LTD.
APRIL 2011
Asian Development Bank
Khulna Water Supply & Sewerage Authority (KWASA)
APPENDIX 10: Annex A - G
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
Khulna Water Supply and Sewerage Authority (KWASA)
ADB TA 7385 BAN: Preparing the Khulna Water Supply
Report on Survey and Monitoring
Of
Existing Production Tube Wells and Pumping Equipment in KWASA
POYRY IDP Consult, Inc.
In association with
HB CONSULTANTS LTD
November 2010
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
1
Report on Survey and Monitoring of Existing Production Tube Wells and Pumping Equipment
Table of Content
1.0 Background
2.0 Methodology
2.1 Reconnaissance Survey
2.2 Detail Field Investigation and Monitoring
3.0 General Observations and Findings
3.1 Status of Wells
3.2 Status of Pumps and Motors
3.3 Electrical Control Panel
3.4 Water Meters
3.5 Chlorination Facilities
3.6 Operators and Operating Hours
3.7 Water production cost
4.0 Recommendations for Improvement of Production Well Operational Efficiency
Appendix-1 : Technical Details of Existing Production Wells and Pumping Equipment Appendix-2 : Technical Details of Existing Mini Wells and Pumping Equipment
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
2
ADB TA 7385-BAN, Preparing the Khulna Water Supply
Report on Reconnaissance Survey of Existing
Production Tube Wells and Pumping Equipment
Abbreviations
ADB Asian Development Bank
JICA Japan International Co-operation Agency
KWASA Khulna Water Supply and Sewerage Authority
DTW Deep Tube Wells
PTW Production Tube Wells
SWL Static Water Level
PWL Pumping Water Level
DD Draw Down
DP Delivery Pressure
TFH Total Field Head
WP Water Power
MP Motor Power
RC Rated Current
LC Load Current
PF Power Factor
LV Load Voltage
IP Input Power
OE Overall efficiency
OpC Operator’s Cost
PrC Power Cost
PdnC Production Cost
UWC Upper Well Casing
DOL Direct On Line
FS Feasibility Study
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
3
1.0 Background
As stipulated in TOR, one of the important goals of the program of ADB TA 7385 BAN: Preparing the Khulna Water Supply is to optimization of ground water resources. In order to achieve the target, survey, investigation and detailed monitoring were carried out since commencement of the project to know the actual status of the production wells currently in operation in KWASA service area. The survey and monitoring data were carefully analyzed and detail observation and findings were prepared for each of the individual wells, based on which recommendations for rehabilitation of each of the individual wells for operational efficiency improvement were made. Considerable improvement on ground water production and distribution is expected after proper implementation of proposed rehabilitation activity.
The activities carried out by the Consultant under the program such as reconnaissance survey, field
monitoring, survey methodology, observation and findings, recommendation etc are described in detailed
in the following paragraph of the report.
2.0 Methodology
The program of survey, investigation and monitoring on production wells & pumping equipment were
conducted by Engr Mr. Musa Mollah, the National Water Supply Engineer (Pumps) of the TA team. He was
assisted by a team of KWASA staff in carrying out the work in the field. The list of the KWASA team members are as follows:
1. Md. Monirul Islam, Assistant Engineer (In-charge) 2. Md. Abu Bakar Siddique, Supervisor
3. Md. Kabir Hossain, Supervisor
4. Md. Abul Kalam, Electrician
The total program of survey and monitoring activity was executed in two Phases: (i) Reconnaissance Survey
and (ii) Detail field investigation and monitoring.
Phase-1: Reconnaissance survey was conducted in order to get an overall status of the tube wells located
across the Khulna city based on which the next Phase of the detailed investigation and monitoring was
designed.
Phase-2: Detail survey, investigation and monitoring were carried out and analysis was done to obtain
actual status of production wells based on which detail rehabilitation plan was prepared for operational
efficiency improvement of the tube wells.
2.1 Reconnaissance Survey
Reconnaissance survey was conducted during the period of 3 August, 2010 to 7 September, 2010. This
survey included collection of key information through a specific format such as size and depth of well, type of
pumps and motors used, existing provisions available & additional provisions required for detail monitoring
activities etc.
A total of 110 DTW’s are in use at 70 sites across Khulna City. Two different types of wells are in use. Wells
of 350mm x 150mm size are named as production well where as wells of 200mm x 75mm, 150mmx75mm
and 150mmx50mm sizes are named as mini well.
There are total 31 nos. of production wells in 31 sites and 81 nos. mini wells in 40 sites. Out of 31
production wells 29 are found in operation and remaining 2 are abandoned. An overall picture of existing
production wells and mini wells as found during reconnaissance survey are summarized in Appendix-1 & 2
respectively.
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
4
2.2 Detail Field Investigation and Monitoring
During reconnaissance survey it is observed that out of 81 mini wells, 37 nos. are being operated by
centrifugal pumps which become inoperable due to significant lowering of ground water level goes beyond
suction limit during dry season. Moreover yield of almost all the mini wells are very poor and not
economical to keep them operated. The KWASA management’s intention is not to continue the mini well
operation too. Considering the situation, detailed monitoring has been carried out only to the 29 nos.
running production tube wells.
Detailed survey and monitoring on Production Wells and related Pumping Equipment have been conducted
during the period of 3 October to 3 November, 2010. The specific parameters monitored for each of the
well are as follows:
• Static and Pumping Water Level;
• Draw Down;
• Yield and Specific Capacity of Well;
• Delivery Pressure;
• Type of pump;
• Load Current;
• Overall Efficiency;
• Production Cost
The data and information were inserted in data sheet (Table-01) and analysis was made in order to find out
the actual tube well status based on which recommendation were made for operational efficiency
improvement of the wells.
The tools and equipments used in investigation and monitoring are summarized as:
• Water level monitoring equipment;
• Pressure gauge;
• Bulk water meter;
• Trajectory equipment to monitor yield of well;
• Clip –on-meter to measure load current and line voltage.
It was identified during reconnaissance survey that, there were no provisions in most of the existing tube
wells to perform monitoring of water level, delivery pressure, discharge etc. Consequently the Consultant
had to made necessary provision in the tube wells for performing the monitoring which are stated below:
• 25 mm dia. inspection hole on the well in order to introduce water level monitoring probe;
• Arrangement to install pressure gauge on the well discharge pipe;
• Arrangement to install trajectory for well yield monitoring.
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
5
Table-01: Production Well Monitoring Data
Ward No
Sl No
Welll No
SWL (m)
PWL (m)
DD (m)
DP (m)
TFH (m)
Yld. (m3/h)
Sp.Cap. m3/h/m
WP (KW)
MP (KW)
RC (A)
LC (A)
% of LC/RC
PF LV (Volt)
IP/hr (KW)
OE (%)
OpC (Tk/hr)
PrC (Tk/hr)
PdnC Tk/m3
Daily Prdn (m3)
PdnC Tk/day
9
1 18 4.26 21.65 17.4 17 38.65 70 4.03 7.363 18.5 40.0 26 65 NA 405 17.80 41 62.50 89.00 2.16 1120 2,424
2 83 3.81 22.00 18.2 10 32 50 2.75 4.355 22.5 39.5 21 53 0.7 405 13.00 33 62.50 65.00 2.55 800 2,040
3 84 3.96 16.77 12.8 10 26.77 80 6.25 5.828 18.5 40.0 32 80 0.6 405 13.00 45 62.50 73.62 1.70 1280 2,178
12 4 85 6.10 22.26 16.2 19 35.16 45 2.78 4.306 18.5 40.0 26 65 0.7 380 15.00 29 62.50 71.25 2.97 720 2,140
16
5 67 3.96 24.39 20.4 10 34.39 22 1.08 2.059 18.5 37.5 22 59 NA 390 9.00 23 62.50 42.75 4.78 352 1,684
6 62 3.96 21.34 17.4 5 26.34 9 0.52 0.645 7.5 16.5 9 55 NA 390 4.50 14 62.50 21.37 9.32 144 1,342
7 76 5.18 13.11 7.93 5 18.11 16 2.02 0.789 7.5 7.0 6 86 NA 390 4.00 20 62.50 19.00 5.09 256 1,304
17
8 43 5.03 21.34 16.3 5 26.34 46 2.8 3.298 15.0 32.0 28 88 NA 380 11.00 30 62.50 52.25 2.49 736 1,836
9 70 5.18 9.60 4.42 12 21.6 15 3.39 0.882 15.0 7.0 6 86 0.7 380 3.00 29 62.50 14.25 5.12 240 1,228
10 85 5.03 19.82 14.8 12 31.82 80 5.41 6.928 15.0 40.0 32 80 0.7 380 17.50 40 62.50 83.12 1.82 1280 2,330
20 11 60 5.49 19.82 14.3 5 24.82 9 0.63 0.608 2.2 9.0 7 78 0.98 380 3.00 20 62.50 14.25 8.53 144 1,228
12 92 6.40 22.26 15.9 5 27.26 20 1.26 1.484 7.5 16.5 12 73 NA 380 7.50 20 62.50 35.62 4.91 320 1,570
21 13 72 6.40 22.87 16.5 5 27.87 55 3.34 4.171 18.5 37.5 23 61 NA 374 14.50 29 62.50 68.87 2.39 880 2,102
22 14 51 6.40 23.78 17.4 1 24.78 10 0.58 0.674 2.2 16.0 12 75 0.98 230 4.00 17 62.50 20.00 8.25 160 1,320
23 15 90 6.10 23.78 17.7 14 37.78 35 1.98 3.599 18.5 40.0 19 48 0.8 402 12.20 29 62.50 57.95 3.44 560 1,927
24 16 36 5.18 18.60 13.4 8 26.6 38 2.83 2.751 18.5 35.5 19 54 0.7 395 9.50 29 62.50 45.12 2.83 608 1,722
24 17 79 5.79 20.73 14.9 8 28.73 50 3.35 3.91 22.5 42.5 15 35 0.75 395 10.00 39 62.50 47.50 2.20 800 1,760
25
18 44 6.10 20.73 14.6 10 30.73 45 3.08 3.764 7.5 16.5 17.5 106 0.98 390 9.50 40 62.50 45.12 2.39 720 1,722
19 82 6.40 10.67 4.27 6 16.67 52 12.14 2.351 18.5 37.5 17 45 0.43 380 6.47 36 62.50 30.73 1.80 829 1,492
20 93 6.71 23.78 17.1 10 33.78 35 2.05 3.218 18.5 41.0 28 68 0.98 390 16.77 19 62.50 79.65 4.06 560 2,275
26 21 81 6.40 21.34 14.9 15 36.34 60 4.02 5.935 22.5 42.5 16 38 0.76 373 12.50 25 62.50 35.62 3.81 512 1,950
22 88 6.40 24.39 18 10 34.39 39 2.17 3.65 18.5 40.0 21 53 0.76 385 10.84 34 62.50 51.49 2.92 624 1,824
27 23 45 6.10 24.39 18.3 8 32.39 24 1.31 2.116 18.5 40.0 25 63 0.5 400 10.00 21 62.50 47.50 4.58 384 1,760
24 86 5.49 19.82 14.3 12 31.82 120 8.37 10.39 18.5 40.0 40 100 0.8 400 25.00 42 62.50 118.75 1.51 1920 2,900
28 25 89 5.18 22.87 17.7 12 34.87 35 1.98 3.321 18.5 40.0 26 65 0.8 400 14.00 24 62.50 66.50 3.69 560 2,064
29 26 78 5.79 9.76 3.96 12 21.76 45 11.35 2.665 18.5 35.5 19 54 NA 400 11.00 24 62.50 52.25 2.55 720 1,836
29 27 91 6.10 22.87 16.8 5 27.87 70 4.17 5.309 7.5 16.5 16.5 100 0.8 400 10.00 53 62.50 47.50 1.57 1120 1,760
30 28 69 6.10 24.39 18.3 2 26.39 6 0.33 0.431 2.2 12.0 9 75 0.8 380 3.00 14 62.50 14.25 12.79 96 1,228
31 29 57 3.05 19.21 16.2 5 24.21 38 2.35 2.504 18.5 35.5 16 45 NA 405 10.00 25 62.50 47.50 2.89 608 1,760
Average yield rate per production well in m3/h= 42.02 Total production and production cost per day respectively= 19,501 52,706
Average Production Cost Tk/m3
2.68
SWL=Static water Level PWL=Pumping Water Level DD =Draw Down DP =Delivery Pressure TFH=Total Field Head Yld.=Yield Sp. Cap.=Specific Capacity
WP =Water Power MP =Motor Power RC=Rated Current LC =Load Current PF =Power Factor LV =Load Voltage IP=Input Power
OE =Overall Efficiency OpC=Operator Cost PrC=Power Cost PdnC=Production Cost NA = Not Available
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
6
3.0 General Observation and Findings
General observation and findings on production wells derived from the data collected during investigation and
monitoring are summarized below:
3.1 Status of Wells
Static and Pumping Water Levels
• Static Water Levels of the existing production wells varies from 3.0 to 6.71m.
• Pumping Water Levels of the existing production wells varies from 9.6m to 24.39m.
• Pumping Water Level of 13 wells goes below pump bowl assembly when operated with full opening of delivery
valves.
Draw-Down
• Draw down of 4 nos. wells found below 8m indicating the well is being operated by the pump with lower capacity;
• Draw down of 7 wells found between 8-15m indicating the well is being operated by the pump with appropriate
capacity;
• Draw down of 18 wells are found beyond 17m which indicate higher pump capacity as compared to actual field
requirement;
Yield
Yield of the existing wells varies from 6 to 120 m3/h. Average yield of the existing wells as found from the monitoring
survey is 42 m3/h.
Delivery Pressure
Delivery pressure of all the production wells have been measured by installing a pressure gauge at the discharge pipe
of the production wells. The maxm pressure was observed below 10 MWC when read with full opening of the delivery
sluice valve. It was observed in some cases that the water is flowing in the discharge pipe like open channel flow
indicating no pressure at all in the pipe.
Specific capacity of wells
The specific capacity of all the wells have been calculated based on well monitoring data and the well have categorized
accordingly into following groups:
• Specific capacity of 3 nos. wells is found above 8 m3/h/m indicating rich well;
• Specific capacity of 5 nos. wells is found between 3.5-8 m3/h/m indicating moderately good well;
• Specific capacity of 17 wells are found between 1-3.5 m3/h/m indicating poor well condition and needs to be
improved;
• Specific capacity of 4 wells are found below 1 m3/h/m indicates not to be economical to operate wells.
3.2 Status of Pumps and Motors
Pumps
Out of total 29 functional wells, 9 nos. are being operated by turbine pumps while 20 nos by submersible pumps.
It has been found by field monitoring that 13 nos. of the production wells are being operated with throttling of delivery
valve as pumping water level of the wells goes below pump-bowl assembly within 3 minutes of pump starts keeping
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
7
delivery valves full open. It indicates that wells are being operated by the pumps of higher discharge capacity compared
to the yield capacity of wells. It may be mentioned here that abstraction of ground water from wells with higher discharge
capacity pump beyond the safe yield is a major cause for clogging/damaging of wells.
Motors
Assessment of running condition of motors has been made based on data collected from the field and findings are
shown below:
• Load current of 3 nos. motors are found above 98% of rated current indicating critical condition of motor;
• Load current of 5 nos. pump motors are ranging from 80-98% of rated current indicates appropriate motor
selection.
• Load current of 12 nos. ranging from 55-79% of rated current within acceptable limit;
• Load current of 9 nos. pump motors are found below 55% of rated current and considered for replacement
including rejected wells.
Overall Efficiency of Pump-Motor
Overall efficiency of pump and motor derived from field data is shown below:
• Overall efficiency of 4 nos. pump-motors is found above 40% indicating appropriate selection of pump-motor;
• Overall efficiency of 7 nos. pump-motors found between 31-40%, is within acceptable limit;
• Overall efficiency of 14 nos. pump-motors found between 20-30% indicates poor selection of pump and motor;
• Overall efficiency of 4 nos. pump-motors are found below 20% indicates very poor selection of pump and motor;
3.3 Electrical Control Panel
Pumping Equipment of Production Wells is operated by Star-Delta Starter and that of Mini Wells are operated by Direct
on Line (DOL) Starter. It is found that Ammeters and Voltmeters in the control panel are not working in most of the
cases.
Component of starters & measuring instrument are often found accommodated in an unnecessary big steel panel board
which occupied a major space of the control room.
Some control room are occupied with unusable, old and rejected panel boards which make the room dark and dirty.
3.4 Water Meter
Out of 29 nos. operational wells, 22 nos. have water meter. The water meter can be classified into two groups:
(i) 150 mm Dia.: There is a total of 17 nos. water Meters of which 4 are functional.
(ii) 75 mm Dia.: There is a total of 5 nos. water Meters of which 4 are functional.
3.5 Chlorination Facilities
There are provisions for chlorination units (with chlorine gas cylinder) with production wells. But all the chlorination units
are out of order in all the production wells due to lack of maintenance.
3.6 Operators & Operating Hours
The scheduled operation hours of production wells are 16 hours a day. Two operators are operating the pump for 8 hours
in a day with shifting duty.
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
8
3.7 Water production cost
• Water production cost of 5 wells are found below Tk. 2./m3 indicating economic for operation;
• Water production cost of 20 wells are found between Tk. 2-6/m3 indicating that the wells are in moderately good
condition and need rehabilitation to increase operational efficiency;
• Water production cost of 4 wells are found above Tk. 6/m3 indicating the wells have very poor efficiency and
difficult to improve by rehabilitation; that’s why the wells may be abandoned.
4.0 Recommendation for Improvement of Production Well Operational Efficiency
Based on the above findings of the survey work, the Consultant’s recommendations for operational efficiency
improvement of the wells are given in the following table:
Ward
No.
Sl.
No.
Well
No. Existing Status Proposed Rehabilitation
9 1 18 i) Draw-down =17.4m
ii) Specific capacity =4.03 m3/h/m
iii) Load current =65% of rated current
iv) Overall efficiency =41%
v) Production cost =Tk.2.16/ m3
vi) Capacitor bank -Not available
vii) Regeneration-Twice & last in 2007
i) No rehabilitation is required except installation of
capacitor bank in motor circuit;
ii) The well can be allowed to be operated.
9 2 83 i) Draw-down =18.2m (suction cut-off)
ii) Specific capacity =2.75 m3/h/m
iii) Load current =53% of rated current
iv) Overall efficiency =33%
v) Production cost =Tk.2.55/ m3
vi) Motor control panel -Not -standard
vii) Regeneration-Once in 2008
i) Regeneration of the well;
ii) Replacement of existing turbine pump-motor and
column pipe assembly by submersible pump-motor and
riser pipe sets as per well improvement after
regeneration;
iii) Replacement of the existing motor control panel.
9 3 84 i) Draw-down =12.8m
ii) Specific capacity =6.25 m3/h/m
iii) Load current =80% of rated current
iv) Overall efficiency =45%
v) Production cost =Tk.1.70/m3
vi) Capacitor bank -Not available
vii) Ammeter – Not functional
viii) Voltmeter-Not functional
i)Performance of the well is satisfactory and can be
allowed to be operated;
ii) Installation of 7.5 KVAR TP capacitor bank with the
motor circuit to improve the power factor;
iii) Replacement of ammeter and voltmeter;
12 4 85 i) Draw-down =16.2m (suction cut-off)
ii) Specific capacity =2.78 m3/h/m
iii) Load current =65% of rated current
iv) Overall efficiency =29%
v) Production cost =Tk.2.97/ m3
vi) Capacitor bank -Not available
vii) Voltmeter – Not functional
viii) Regeneration-Not yet carried out
i) Regeneration of the well;
ii) Replacement of existing submersible pump unit as per
well improvement after regeneration;
iii) Replacement of motor control panel with DOL Starter
including protective & measuring device.
16 5 67 i) Draw-down =20.4m (suction cut-off)
ii) Specific capacity =1.08 m3/h/m
iii) Load current =59% of rated current
iv) Overall efficiency =23%
v) Production cost =Tk.4.78/ m3
vi) Capacitor bank -Not available
i) Replacement of existing turbine pump-motor (25HP)
with new submersible pump set (30m3/h discharge at
40m head and 7.5 HP submersible motor) including
pump cable & DOL starter of adequate size.
ii) Replacement of column pipe assembly with 75mm dia
flanged steel riser pipe sets
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
9
Ward
No.
Sl.
No.
Well
No. Existing Status Proposed Rehabilitation
vii) Regeneration-Twice & last in 2009
16 6 62 i) Draw-down =17.4m(suction cut-off)
ii) Specific capacity =0.52 m3/h/m
iv) Overall efficiency =14%
v) Production cost =Tk.9.32/m3
vi) Regeneration-Twice & last in 2009
i) The well condition is very poor and cannot be
improved by regeneration. The well may be abandoned.
16 7 76 i) Draw-down =7.93m
ii) Specific capacity =2.02 m3/h/m
iii) Load current =86% of rated current
iv) Overall efficiency =20%
v) Production cost =Tk.5.09/ m3
vi) Regeneration-Thrice & last in 2009
i) Replacement of existing submersible pump-motor
(3HP) with new submersible pump set (35m3/h
discharge at 45m head and 10 HP submersible motor)
including pump cable & DOL starter of adequate size.
ii) Replacement of column pipe assembly with 75mm dia
and 36m long flanged steel riser pipe sets.
17 8 43 i) Draw-down =16.3m (suction cut-off)
ii) Specific capacity =2.8 m3/h/m
iii) Load current =88% of rated current
iv) Overall efficiency =30%
v) Production cost =Tk.2.49/ m3
vi) Capacitor bank -Not available
vii) Voltmeter – Not functional
i) Regeneration of the well;
ii) Reduction of Impeller diameter of existing pump set
as per well improvement after regeneration;
iii) Replacement of the damaged Voltmeter with new
one.
iv) Installation of one 5.0 KVAR TP capacitor Bank with
the motor circuit to improve the power factor.
17 9 70 i) Draw-down =4.42m
ii) Specific capacity =3.39 m3/h/m
iii) Load current =86% of rated current
iv) Overall efficiency =29%
v) Production cost =Tk.5.12/ m3
i) Replacement of existing submersible pump set with
higher capacity submersible pump-motor (35m3/h x 35m
x 7.5HP) including submersible pump cable & DOL
starter and 75mm dia flanged steel riser pipes.
17 10 85 i) Draw-down =14.8m
ii) Specific capacity =5.41 m3/h/m
iii) Load current =80% of rated current
iv) Overall efficiency =40%
v) Production cost =Tk.1.82/ m3
Performance of the well and pump are satisfactory and
can be allowed to be operated
20 11 60 i) Draw-down =14.3m
ii) Specific capacity =0.63 m3/h/m
iii) Load current =78% of rated current
iv) Overall efficiency =20%
v) Production cost =Tk.8.53/m3
i) The well condition is very poor and cannot be
improved by regeneration. The well may be abandoned.
20 12 92 i) Draw-down =15.9m (suction cut-off)
ii) Specific capacity =1.26 m3/h/m
iii) Load current =73% of rated current
iv) Overall efficiency =20%
v) Production cost =Tk.4.91/ m3
i) Regeneration of the well
21 13 72 i) Draw-down =16.5m (suction cut-off)
ii) Specific capacity =3.34 m3/h/m
iii) Load current =61% of rated current
iv) Overall efficiency =29%
v) Production cost =Tk.2.39/ m3
vi) Capacitor bank -Not available
vii) Ammeter – Not functional
i) Regeneration of the well;
ii) Replacement of existing turbine pump-motor and
column pipe assembly by submersible pump-motor and
riser pipe sets as per well improvement after
regeneration;
iii) Replacement of the existing motor control panel with
DOL starter including protective device.
22 14 51 i) Draw-down =17.4m (suction cut-off)
ii) Specific capacity =.58 m3/h/m
iii) Load current =75% of rated current
i) The well condition is very poor and cannot be
improved by regeneration. The well may be abandoned.
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
10
Ward
No.
Sl.
No.
Well
No. Existing Status Proposed Rehabilitation
iv) Overall efficiency =17%
v) Production cost =Tk.8.25/ m3
23 15 90 i) Draw-down =17.7m (suction cut-off)
ii) Specific capacity =1.98 m3/h/m
iii) Load current =48% of rated current
iv) Overall efficiency =29%
v) Production cost =Tk.3.44 m3
vi) Capacitor bank -Not available
vii) Voltmeter – Not functional
i) Regeneration of the well;
ii) Replacement of existing submersible pump unit as per
well improvement after regeneration;
iii) Replacement of motor control panel with DOL Starter
including protective and measuring device.
24 16 36 i) Draw-down =13.4m
ii) Specific capacity =2.83m3/h/m
iii) Load current =54% of rated current
iv) Overall efficiency =29%
v) Production cost =Tk.2.83/ m3
vi) Capacitor bank -Not available
vii) Voltmeter – Not functional
i) Replacement of the existing turbine pump-motor and
column pipe assembly 45m3/h x 36m x 12.5 HP
submersible pump and 100mm dia riser pipe
ii)Replacement of the existing Motor Control Panel with
DOL Starter including protective & measuring device,
24 17 79 i) Draw-down =14.9m
ii) Specific capacity =3.35 m3/h/m
iii) Load current =35% of rated current
iv) Overall efficiency =39%
v) Production cost =Tk.2.20/ m3
vi) Capacitor bank -Not available
vii) Voltmeter – Not functional
i) Regeneration of the well;
ii) Replacement of existing turbine pump-motor and
column pipe assembly by submersible pump-motor and
riser pipe sets as per well improvement after
regeneration;
iii) Replacement of the existing motor control panel with
DOL starter including protective device.
25 18 44 i) Draw-down =14.6m (suction cut-off)
ii) Specific capacity =3.08 m3/h/m
iii) Load current =106% of rated current
iv) Overall efficiency =40%
v) Production cost =Tk.2.39/ m3
vi) Capacitor bank -Not available
vii) Ammeter – Not functional
i) Regeneration of the well;
ii) Replacement of existing submersible pump unit as per
well improvement after regeneration;
iii) Replacement of motor control panel with DOL Starter
including protective & measuring device.
25 19 82 i) Draw-down =4.27m
ii) Specific capacity =12.14 m3/h/m
iii) Load current =45% of rated current
iv) Overall efficiency =36%
v) Production cost =Tk.1.80/ m3
i) Replacement of existing Turbine pump-motor and
column pipe assembly with 80 m3/h x 36m x 25 HP
submersible pump & 125mm dia riser pipe.
iii) Replacement of motor control panel with DOL Starter
including protective & measuring device.
25 20 93 i) Draw-down =17.1m (suction cut-off)
ii) Specific capacity =2.05 m3/h/m
iii) Load current =68% of rated current
iv) Overall efficiency =21%
v) Production cost =Tk.3.82/ m3
i) Regeneration of the well;
ii) Replacement of existing submersible pump unit as per
well improvement after regeneration;
iii) Replacement of motor control panel with DOL Starter
including protective & measuring device.
26 21 81 i) Draw-down =14.9m
ii) Specific capacity =4.02 m3/h/m
iii) Load current =38% of rated current
iv) Overall efficiency =25%
v) Production cost =Tk.3.81/m3
vi) Sand Yielding
Regeneration of the well will not be feasible due to sand
yielding. The well may be operated as it is.
26 22 88 i) Draw-down =18m (suction cut-off)
ii) Specific capacity =2.17m3/h/m
iii) Load current =53% of rated current
iv) Overall efficiency =34%
i) Regeneration of the well;
ii) Replacement of existing submersible pump unit as per
well improvement after regeneration;
iii) Replacement of motor control panel with DOL Starter
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
11
Ward
No.
Sl.
No.
Well
No. Existing Status Proposed Rehabilitation
v) Production cost =Tk.2.92 m3 including protective & measuring device.
27 23 45 i) Draw-down =18.3m (suction cut-off)
ii) Specific capacity =1.31 m3/h/m
iii) Load current =63% of rated current
iv) Overall efficiency =21%
v) Production cost =Tk.4.58/m
i) Replacement of existing submersible pump-motor
(25HP) with 35m3/h x 35m x 7.5 HP submersible pump
motor including pump cable & riser pipe of adequate
size.(75mm)
ii) Replacement of the existing Motor Control Panel with
DOL Starter including protective & measuring device
27 24 86 i) Draw-down =14.3m
ii) Specific capacity =8.37 m3/h/m
iii) Load current =100% of rated current
iv) Overall efficiency =42%
v) Production cost =Tk.1.51/m3
vi) Motor control Panel-Very bad condition
i) Performance of the well and pump are satisfactory and
can be allowed to be operated.
ii) Motor control panel including accessories are to be
replaced with new ones as per existing motor capacity
(25HP)
28 25 89 i) Draw-down =17.7m (suction cut-off)
ii) Specific capacity =1.98m3/h/m
iii) Load current =65% of rated current
iv) Overall efficiency =24%
v) Production cost =Tk.3.69/m3
i) Regeneration of the well;
ii) Replacement of existing submersible pump unit as per
well improvement after regeneration;
iii) Replacement of motor control panel with DOL Starter
including protective & measuring device.
29 26 78 i) Draw-down =3.96m
ii) Specific capacity =11.35m3/h/m
iii) Load current =54% of rated current
iv) Overall efficiency =24%
v) Production cost =Tk.2.55/m3
vi Ammeter – Not functional
vii) Voltmeter – Not functional
viii) Capacitor bank -Not available
i) Replacement of existing Turbine pump-motor and
column pipe assembly with 80 m3/h x 36m x 25 HP
submersible pump unit & 125mm dia riser pipe sets.
ii) Replacement of motor control panel with 25HP DOL
Starter including protective & measuring device.
iii) 7.5 KVAR TP capacitor bank shall be connected in
the motor circuit.
29 27 91 i) Draw-down =16.8m
ii) Specific capacity =4.17m3/h/m
iii) Load current =100% of rated current
iv) Overall efficiency =53%
v) Production cost =Tk.1.57/m3
vi TP MCCB– Not Available
viii) Capacitor bank -Not available
i) Withdrawing, dismantling and reduction in diameter of
pump impellers by 2mm and then lowering after re-
assembling.
ii) Installation of 3 KVAR TP Capacitor Bank and 40A TP
MCCB shall be connected with the motor circuit.
30 28 69 i) Draw-down =18.3m
ii) Specific capacity =0.33m3/h/m
iii) Load current =75% of rated current
iv) Overall efficiency =14%
v) Production cost =Tk.12.79/m3
i) The well condition is very poor and cannot be
improved by regeneration. The well may be abandoned.
31 29 57 i) Draw-down =16.2m
ii) Specific capacity =2.35m3/h/m
iii) Load current =45% of rated current
iv) Overall efficiency =25%
v) Production cost =Tk.2.89/m3
i) Regeneration of the well;
ii) Replacement of existing turbine pump-motor and
column pipe assembly by submersible pump-motor and
riser pipe sets as per well improvement after
regeneration;
iii) Replacement of the existing motor control panel with
DOL starter including protective & measuring device.
During Consultant’s investigation, it was observed that almost all the pump houses are not well maintained and found dirty. All
chlorination cylinders in the production tube well are out of order. The pump houses should be cleaned and the inactive
chlorination cylinders should be removed.
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
12
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
13
Appendix-01
Technical Details of Existing Production Wells and Pumping Equipment
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
14
Table-01: Technical Details of Existing Production Wells and Pumping Equipments
Ward No
Well No
Well Location Year of Constn.
Depth of Well, m Pump
Type Motor Details
Size, Mat & Length of Riser Pipe
Condition of Pumping Unit Total UWC Filter
9
18 R & H Baikali 1980 275 36 30 Submersible 3-Phase, 50 HZ, 1450 RPM, 25 HP 125mm x 24m (MS, flanged) Workable
83 Mujgunni Lebutala 2002 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 30 HP 150mm x 24m Frequent malfunction
84 Mujgunni Battala (MSP) 2003 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 25 HP 125mm x 24m Workable
10 75 Khalispur Jheel pukur 2000 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 25 HP 125mm x 24m (MS, threaded) Not Workable
12 85 Khalispur KCC Branch Office (MSP)
2003 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 25 HP 125mm x 24m (MS, flanged) Workable
16
67 Noor Nagar Fire service 1995 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 25 HP 125mm x 24m (MS, threaded) Workable
62 250 Bed Hospital 1995 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 2 HP 40mm x 24m Poor Workability
76 Modina Mosque Boyra 2000 275 76 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP 125mm x 24m (MS, flanged) Workable
17
43 Sonadanga-1 1987 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 10 HP 100mm x 24m Workable
70 Sonadanga KCC Park 1997 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI, Flanged) Workable
87 KDA App. Road (MSP) 2004 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 25 HP 125mm x 24m Workable
20 60 Saikpara Bazar-3 1994 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI, Flanged) Workable
20 92 Saikpara Bazar Mosq. (MSP)
2005 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 10 HP 100mm x 24m (GI, Flanged) Workable
21 72 D.C. Office 1997 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 25 HP 125mm x 24m (MS, threaded) Workable
22 51 Zilla School 1994 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI, Flanged) Workable
23 74 Sir Iqbal Road Park 2000 275 36 30 Submersible 1-Phase, 50 HZ, 2900 RPM, 2 HP 40mm x 24m (GI, Flanged) Workable
23 90 PTI More (MSP) 2004 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 25 HP 125mm x 24m (MS, Flanged) Workable
24 36 Nirala WF-3 1986 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 25 HP 125mm x 24m (MS, threaded) Very Poor Workability
24 34 Nirala WF-1 1980 275 36 30 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI, Flanged) Very Poor Workability
24 79 Nirala KCC Park 2001 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 30 HP 125mm x 24m (MS, threaded) Workable
25 44 Arambag 1987 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 10 HP 100mm x 24m (GI, Flanged) Not Workable
25 82 Bosupara Graveyard 2002 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 30 HP 125mm x 24m) Workable
25 93 Old Gollam- ari Road 2005 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 25 HP 125mm x 24m Workable
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
15
Ward No
Well No
Well Location Year of Constn.
Depth of Well, m Pump
Type Motor Details
Size, Mat & Length of Riser Pipe
Condition of Pumping Unit Total UWC Filter
26 81 West Baniakhamar Urban 2002 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 30 HP 150mm x 24m Workable
26 88 Sher-A-Bangla Road 2004 275 36 18 Submersible 3-Phase, 50 HZ, 2900 RPM, 10 HP 100mm x 24m (MS, Flanged) Workable
27 45 Tarer Pukur 1987 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 10 HP 125mm x 24m (MS, Flanged) Workable
27 86 East Baniakhamar Madrasha
2003 275
36 30 Submersible
3-Phase, 50 HZ, 2900 RPM, 25 HP 125mm x 24m (MS, Flanged) Workable
28 89 West Toothpara Primary School (MSP)
2004 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 25 HP 125mm x 24m (MS, Flanged) Workable
29 78 Babu Khan Road 2001 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 25 HP 125mm x 24m (MS, threaded) Workable
29 91 KCC Rest House (MSP) 2004 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 10 HP Workable
30 69 Rupsa Kasai khana 1997 275 36 30 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI, Flanged) Workable
31 57 Hazi Malek College 1994 275 36 30 Turbine 3-Phase, 50 HZ, 1450 RPM, 25 HP 125mm x 24m (MS, threaded) Workable
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
16
Appendix-02
Technical Details of Existing Mini Wells and Pumping Equipment
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
17
Table-02: Technical Details of Existing Mini Wells with Pumping Equipment
Ward No
Well No
Well Location Year of
Construction
Depth of Well, m Pump Type Motor Details
Size, Mat & Length of Riser Pipe
Condition of Pumping Unit Total UWC Filter
9 M-4 Mujgunni Well Field-3 2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP 75mm x 24m (PVC) Workable*
2002 284 36 18 Centrifugal. 3-Phase, 50 HZ, 2900 RPM, 3 HP 75mm x 24m (PVC) Not Workable
9 M-40 Muzgunni Park 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
10 M-1 Khalispur Durbar Shanga
2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC)
Not Workable
2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 5 HP Workable*
10 M-2 Khalispur Nayabati More
2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP 75mm x 24m (PVC) Malfunction
2002 284 36 18 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged) Workable
10 M-33 Babur salam Mosque 2010
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI, Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
10 M-8 Khalispur Maternity Hospital
2003 284 36 18 Centrifugal 1-Phase, 50 HZ, 2900 RPM, 2 HP 75mm x 24m (PVC)
Workable*
2003 284 36 18 Centrifugal 1-Phase, 50 HZ, 2900 RPM, 2 HP Workable*
11 M-32 Peoples 5th floor 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
11 M-19 Khalispur Toyeba Mosque 2006 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable*
2006 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
12 M-9 Khalispur 12 no Road 2003 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable*
2003 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
13 M-20 Khalispur Charer Hat ghat 2008 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable*
2008 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
14 M-10 Boyra Public College 2004 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable*
2004 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
14 M-37 Rayer Mohal Bazar Mondir 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
14 M-17 Royer Mohal School 2006 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable*
2006 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
18
Ward No
Well No
Well Location Year of
Construction
Depth of Well, m Pump Type Motor Details
Size, Mat & Length of Riser Pipe
Condition of Pumping Unit Total UWC Filter
16 M-5 Noor Nagar Mosque 2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Not Workable
2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
16 M-26 Women Hostel Boyra 2010
284 36 18 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI, Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
16 M-25 Front of 250 Bed Hospital 2010
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI, Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
16 M-11 Sonadanga Swiper quarter
2004 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP 75mm x 24m (PVC)
Workable*
2004 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
18 M-39 Galla Mari Bypass 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
18 M-12 Front of Sonadanga Police Station
2004 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP 75mm x 24m (PVC)
Workable*
2004 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
19 M-35 Polli Mongal 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
19 M-21 Islamabad Community Centre
2008 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable
20
M-7 Ferryghat-3 (KCC Workshop)
2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP 75mm x 24m (PVC) Not Workable
2002 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged) Workable
M-34 Ferighat Zinna Mosque 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
21
M-3 Khulna Circuit House 2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable*
2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
M-27 Kornation Tech. School 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
22
M-15 Zilla School Quarter 2004 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable
2004 284 36 18 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable
M-29 Bagmara Tetultala 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged) Workable
Appendix 10 ANNEX A TUBE WELL RECONNAISSANCE AND MONITORING SURVEY
19
Ward No
Well No
Well Location Year of
Construction
Depth of Well, m Pump Type Motor Details
Size, Mat & Length of Riser Pipe
Condition of Pumping Unit Total UWC Filter
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
25 M-25 Basupara PWD Quarter 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
26
M-38 Nort Khal Bank Road 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
M-22 Habelibag 2008 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable*
2008 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
M-13 Mistiripara Bazar 2004 275 36 30 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable*
2004 275 36 30 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
M-24 Dole Khola More 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
M-30 Toothpara Gastola Mondir 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
29
M-6 Alia Madrasha 2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable
2002 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable
M-31 Saburunnesa School 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP
50mm x 24m (GI, Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
M-14 Municipal Tank Road 2010 284 36 18 Submersible 3-Phase, 50 HZ, 2900 RPM, 3 HP
50mm x 24m (GI, Flanged)
Workable
284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
30
M-16 Toothpara Taltola Hospital 2005 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP
75mm x 24m (PVC) Workable*
2005 284 36 18 Centrifugal 3-Phase, 50 HZ, 2900 RPM, 3 HP Workable*
M-23 Chanmari Bazar Madrasha
2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
M-28 Hazi Malek Pakar Matha 2010 284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP 50mm x 24m (GI,
Flanged)
Workable
284 36 18 Submersible 1-Phase, 50 HZ, 2900 RPM, 3 HP Workable
* Centrifugal pumps frequently become inoperative due to lowering of ground water level during dry season
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Report on Technical Training Conducted By TA Team 1.0 Introduction In compliance with the requirement of ToR, special emphasis has been given on imparting training to KWASA staffs. Both the theoretical classroom training and field demonstration have been rendered to the relevant officers/staffs of KWASA. The main training topics selected by the TA Team with consent of client relevant to develop skill of KWASA are as follows: A. Water Distribution System
- Pipeline Installation Standard and technique; - Rehabilitation and System Improvement; - Understanding Un-accounted for Water (UFW); - Non-revenue Water (NRW); - Leak Detection Methodology.
B. Wells and Pumps
- Production Well; - Pumps; - Pump Station/Pumping Plant; - Operation, Maintenance & Trouble Shooting; - On – Job- Training/Field Demonstration
Training Team comprised mainly Mr. Md. Zahangir Alam, Deputy Team Leader and Md. Abu Musa Mollah, National Consultant (Pump). They are supported by KWASA management and assisted by KWASA staffs in organizing the training programs. 2.0 Selection of Trainees The Consultant collected the total list of KWASA technical staffs; out of which around 29 were nominated based on education, experience and position in KWASA for involving them in the regular training programs. The list of technical staffs finally approved by KWASA management is shown in the Table 01 below:
Table 01: List of Trainees Participated in Regular Technical Training Programs Conducted by
ADB TA Team
SL No Name of Officer/Staff Designation
1 Md. Mofiz Uddin Ahmed Executive Engineer (In Charge)
2 Md. Rezaul Islam Executive Engineer
3 Debotosh Kumer Das Assistant Engineer (In Charge)
4 Md. Monirul Islam Assistant Engineer (In Charge)
5 Md. Ashekur Rahman Asst. Engineer
6 Sk. Maruful Haque Asst. Engineer
7 Rafiqul Alam Sarder Sub-Asst. Engineer
8 G. M. Abdul Gaffer Sub-Asst. Engineer
Appendix 12 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
SL No Name of Officer/Staff Designation
9 Amit Kumar Kundu Sub-Asst. Engineer
10 Biplab Majumdar Sub-Asst. Engineer
11 Md. Afiqual Islam Sub-Asst. Engineer
12 Abul Bashar Sub-Asst. Engineer
13 Md. Tazamul Haq Sub-Asst. Engineer
14 A.B.M Sattar Supervisor
15 Abu Bakar Siddique Supervisor
16 Md. Kabir Hossain Supervisor
17 Md. Saiful Islam Sardar Head Mechanic
18 Md. Abul Kalam Electrician
19 Sanjoy Kumar Devnath Asst. Electrician
20 Md. Abu Said Pump Mechanic
21 Md. Selim Pump Mechanic
22 Md. Jasim Pump Mechanic
23 Md. Abdur Rab Pump Mechanic
24 Md. Abul Kalam Electrical Meter Reader
25 Abdul Motleb Pipe Line Mechanic
26 Khoka Mia Pipe Line Mechanic
27 Aziar Hossain Pipe Line Mechanic
28 Edris Ali Pipe Line Mechanic
29 Zahangir Hossain Pipe Line Mechanic
Note : Serial no of the trainee as mentioned above does not represent the seniority of staff
Appendix 12 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
3.0 Details of Training Conducted by TA Team The TA Team conducted 12-Technical Training Programs; of which 7 programs include only theoretical classroom discussion, 3 include field demonstration along with classroom discussion, 1 were only field demonstration on some practical issues related to well and pump operation and the rest 1 program was outing to Faridpur Pourashava to gather practical knowledge of water works operation and billing activity. All the trainings except training no. 8 & 9 were conducted to the technical staffs mentioned in the Table 01. Training no. 8 & 9 were conducted exclusively for the pump operators (60+65) of KWASA in two phases on pumps and wells operation and trouble shooting. Adequate refreshments with tea/ coffee were served during the tea breaks of the training. Good lunch was arranged in the nearby restaurants as well as the training venue. Training bags have been provided to the trainees. The summary of the training program conducted by TA Team is shown in the Table 02 below:
Table 02: Summary of Training Activities Conducted by TA Team
Appendix 12 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Sl No. Training Topics in Brief Conducted By No. of Trainees Attended Date and Duration Venue
1 Classroom Training a. Interaction on some relevant MCQ on pumps and water distribution system; b. Introduction and classification of pumps. c. Pumps used in water supply system
Md. Abu Musa Mollah National Consultant (Pumps) &
20 Nos. (Engineers, Supervisors, Mechanic, Pipeline Mistry etc.)
23 October 2010 (09:30 am-03:30 pm)
Conference Hall of Hotel Castle Salam, Royal More, Khulna
d. Water pipeline Installation Technique (Part-01) Md. Zahangir Alam Deputy Team Leader
2 Classroom Training a. Major Component of Pump Unit b. Selection of Appropriate Pumps c. Determination Pump Head and Discharge d. Pump Characteristics Curves
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Pipeline Mistry etc.)
19 November 2010 (09:30 am-03:30 pm)
Conference Hall of Hotel Castle Salam, Royal Mor, Khulna
e. Water pipeline Installation Technique (Part-02) Md. Zahangir Alam Deputy Team Leader
3 Classroom Training a. Well Fixture b. Static Water Level (SWL) c. Pumping Water Level (PWL) d. Draw Down e. Well Yield f. Specific Capacity
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
01 December 2010 (09:30 am-03:30 pm)
Conference Room of KWASA HQ Building
Field Demonstration a. SWL & PWL Monitoring b. Determination of Draw Down c. Well Discharge Measurement by Trajectory d. Determination of Specific Capacity of Well e. Dismantling & Assembling of a Multi-stage submersible Pump-unit
Md. Abu Musa Mollah National Consultant (Pumps)
Pump House and Office yard for field demonstration
Appendix 12 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Sl No. Training Topics in Brief Conducted By No. of Trainees Attended Date and Duration Venue
4 Classroom Training a. Series Operation of Pumps b. Parallel Operation of Pumps c. Combined Characteristic Curves for Series Operation d Combined Characteristic Curves for Parallel Operation
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
14 December 2010 (09:30 am-01:15 pm)
Conference Room of KWASA HQ Building
5 Classroom Training
a. Basic of Electricity
b. Electrical Control & Protective Component used in
Pumping Plant.
c. Measuring Instrument in Pumping Plant.
d. Circuit Diagram of Elec. Equipment in Pumping Plant
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
23 December 2010 (09:30 am-01:15 pm)
Conference Room of KWASA HQ Building
6 Classroom Training
a. Pump Station
b. Piping Gallery
c. Measuring instrument
d. Identification & Selection of Cable
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
29 December 2010 (09:30 am-01:15 pm)
Conference Room of KWASA HQ Building
Field Demonstration
a. Pumps & Piping Gallery
b. Measuring instrument and Electrical Component in a
pump station
Nearby Pump House
7 Classroom Training
a. Installation of Submersible Pump
b. Operation
b. Maintenance
c. Monitoring
d. Trouble Shooting
e Points to be considered during O & M of Electrical
equipment
Md. Abu Musa Mollah National Consultant (Pumps)
19 Nos. (Engineers, Supervisors, Mechanic, Electricians)
05-01- 2011 (09:30 am-01:15 pm)
Conference Room of KWASA HQ Building for Classroom Discussion.
Appendix 12 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Field Demonstration
Visit to nearby Pump House and demonstration of
operation and monitoring of pump & well.
Nearby Pump House
8 Classroom Training
Technical Details, Operation, Maintenance, Monitoring
and Trouble Shooting of Production Well with
Submersible Pumping Equipment.
Md. Abu Musa Mollah National Consultant (Pumps)
65 Nos. Pump Operators & 4 nos Pump Mechanics (1st Group)
11-01- 2011 (2:30 PM-5:30 PM)
Meeting Room of KWASA Staff Association.
9 Classroom Training
Technical Details, Operation
Maintenance, Monitoring and Trouble Shooting of
Production Well with Submersible Pumping Equipment.
Md. Abu Musa Mollah National Consultant (Pumps)
60 Nos. Pump Operators (2nd Group)
12-01- 2011 (9:30 AM-12:30 PM)
Meeting Room of KWASA Staff Association.
10 Classroom Training a. Un-accounted for Water (UFW) b. Non-Revenue Water (NRW) c. Measure to Control Wastage d. Key to Non-Revenue Water e. Leak Detection Methods f. Benefits of Leak detection g. Leak Detection Equipments
Md. Zahangir Alam Deputy Team Leader
29 Nos. (Engineers,
Supervisors, Mechanic,
Electricians)
20-01- 2011 (9:30 AM-12:30 PM)
Conference Hall of Hotel Castle Salam, Royal More, Khulna
b. Continuity Equation c. Bernaullie’s Equation d. Water Hammer e. Cavitations f. Air Locking g. Principle of Water Treatment
Md. Abu Musa Mollah National Consultant (Pumps)
11 Visit to Faridpur Paurashava
• Power Point Presentation on present status of Water Supply System and billing status of Faridpur Paurashava, presented by Pourashava Authority.
• Visit & observe Water Treatment Plant (480m3/h) operation at Old W/W, Jhiltuli
• Visit & Observe Water Treatment Plant (480m3/h) operation at Goalchamat.
Md. Zahangir Alam Deputy Team Leader
MD. Abu Musa Mollah National Consultant (Pumps)
Md. Kayemuddin National Consultant (Finance)
46 Engineering and Financial Staffs of KWASA
22-01-2011 (7:30AM to 7:30PM)
Faridpur Pourashava Water Works
12 Field Demonstration Practical Demonstration with hydraulic model (fabricated)
Md. Abu Musa Mollah National Consultant (Pumps)
29 Nos. (Engineers, Supervisors, Mechanic,
26-01-2011 (7:30AM to 7:30PM)
KWASA Office Compound
Appendix 12 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
to explain the following technical terms:
• Continuity Equation & Bernaullie’s Equation
• Head Loss
• Water Hammer
• Air Locking
Electricians)
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Appendix-01
Attendance List of the Participants
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Appendix-02
Training Materials 1
GUIDE TO PIPELINE INSTALLATION
Discussion Summary
⇒ General ⇒ Excavation ⇒ Transportation and Storing Pipes and Fittings ⇒ Installation Technique ⇒ Pipe Bedding & Backfilling ⇒ Road Crossings ⇒ Bridge and Culvert Crossing
1. Detailed of Standard Chamber All the
� All Existing Utility Lines and Services have been Located; � Safety Measures – Arrangements for Lighting, Watching and
Signposting etc.; � Obtain Permission from Concerned Authorities for Diverting Traffic; � Observation Regularly the Arrangements so that Inconvenience to
Public would be minimized.
2. Excavation
� Obtain Road Cutting Approval from Authority; � Identification of Pipe Alignment; � Width of Excavation will be within Design Limit; � Excavation for Invert Elevation Must Allow Pipe Bedding; � Excavated Material Placed might not Create Obstacle to Traffic
Movement; � Shoring
- Shoring is required to ensure workers in excavated trenches are sufficiently protected and working in safe condition;
- Ensure the timbers used for upright and bracing are of sufficient size;
- Width and shoring must produce sufficient access to permit installation of pipe;
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
� Depth of Trench: Recommended Depth for Pipelines in Different
Situations:
- Through bush : 100 cm (min 40 cm) - Along roads : 100 cm - Underneath roads : 120 cm
� Utmost care should be taken to ensure that each pipe is properly and
uniformly bedded along its whole length except at the joints.
3. Transportation and Storing Pipes and Fittings
� PVC Pipes should be Transported in a Vehicle having a Bed Long Enough to Provide Support for the Full Length of the Pipe;
� PVC Pipes should be Stored in a Flat Horizontal Position; � In General the Height of Pipes Stack should not be more than 7
Times of its Diameter.
4. Installation Technique: Operation Involved in the Laying of Pipelines include the Following Steps:
� Preparation of Detailed Maps of Roads and Streets: Showing
Position of: - Curbs; - Gutters; - Existing water line; - Sewerage pipes; - Gas Pipes; - Telephone & electric conduits.
� Locating the proposed alignment on the ground: the trench line is marked by driving centrally stakes 30 meter apart on straight lines and 10 meter apart on curves.
� Excavating the Trenches: The Trench will be Sufficiently Wide to
Allow the Pipes to be Laid Properly. The Width of the Trench Generally Depends on:
- Diameter of pipes; - Soil type and conditions; - Cost involves.
� Preparation of Laying
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
- All pipes and fittings would be checked for class; - The entire length of the barrel of the pipe should be well
supported on solid and even foundation; - Check the grade level of each pipe laying to ensure that the
invert level is correct; - Check the alignment to ensure that the deviations at the joints
do not exceed the permissible amounts; - Pipe jointing should be carefully supervised to ensure the
specifications and manufacturer’s instructions are strictly followed.
- Where concrete surrounds, thrust blocks and valve chambers are to be provided, attention should be paid to the quality of materials and workmanship
- In no case, pipe shall be jointed before lowering.
� Pipes Laying
- The pipeline should be laid along the straightest route possible; - Road crossings should be done at 450 angle to the road; - Pipe should be laid with a continuous rise of about 2% to 5% to
high points so that air can be released through air valves or with a continuous fall to low point.
- Pipes should be laid on firm ground in order to prevent uneven settlement which may damage pipe joints.
- Couplings (rubber sealing rings) may be loaded unevenly and may cause of leakage.
- Immediately before the pipes being laid, all dust, dirt and foreign matter shall be removed from the inside;
- In order to prevent stones and soil from entering the pipe, a suitable plug shall be provided with the last pipe laid when pipe laying is not actually in progress.
- All trees roots between the surface and a depth of 1 m should be cut prevent damage to pipes from root growth or by uprooted trees.
5. Pipe Bedding & Backfilling
� The pipe should be laid in bed of sand, 150 mm below the bottom
and 150 mm above the top of the pipe barrel and over the full trench width;
� The applied sand should be free of clay, stones or hard lumps. � In road crossings, sand filling shall be done over the full depth of the
trench � Backfilling of trenches shall be carried out by excavated soil in 150
mm layers; each layer being thoroughly rammed and consolidated before the succeeding layer is placed.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
6. Road Crossings
� Pipes at road crossing preferably are of galvanized (G.I) or mild steel (M.S) casing with a minimum cover of 1.0 meter above the pipe.
� The entire backfilling over the length of the crossing shall consist of sand.
� Where the application of G.I or M.S pipes is not possible, the PVC pipe shall be protected on a proper manner against the pressure caused by traffic.
� The contractor shall operate a system of traffic control; � Road, drain and channels should be free from obstructions at all time. � Excavated material should not be placed in such way that it will
obstruct the flow of traffic. � Backfill should be placed in 150 mm lifts and proper effort to be
applied to obtain consolidation and compaction. � Restoration of the roads damaged at the time of laying of pipeline into
its original condition. 7. Bridge and Culvert Crossing
� Pipes in Bridge or Culvert Crossing shall be of galvanized Iron or Mild Steel;
� In no Case the Pipe shall Hamper any Boat, Traffic or the Free Flow of Water;
� It is better to Cross the Bridge or Culvert Outside of the Bridge or Culvert and Clamped to the Railing Post than Passes Inside the Bridge or Culvert;
� During the Crossing of Bridge or Culvert the Bend Use should be 450 to minimize the Head Losses. Head Loss for 900 = 1.5 Times of Head Loss for 450
� During construction of bridge or culvert crossing fewer joints should
be provided and joints should be of flanged type. � If possible full length of a pipe should be used for minimizing the
joints.
To be Continued………
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
GUIDE TO PIPELINE INSTALLATION (Part – 02)
8. Details of Standard Valve Chamber The Main Objective of Valve Chamber in Water Distribution System are:
⇒ Easy Location of Sluice Valve; ⇒ Easy Operation in Diverting Water Flow; ⇒ Protection from Damage;
The Chambers are also urgently required for:
⇒ Washout Point; ⇒ Air Release Valve Location;
The Valve Chamber can be Categorized into:
⇒ Inside the Road for Heavy Traffic; ⇒ Off the Road for Light Traffic;
The Points to be Considered during Construction of Chamber:
⇒ Slab shall be constructed in three parts; ⇒ Top slab of the chamber shall be flushed with the existing
road/ground level; ⇒ The base slab of the chamber shall be of CC or RCC; ⇒ A concrete block shall be provided under the seat of the sluice
valve so that load of sluice valve does not transfer to PVC pipelines;
⇒ Sufficient space shall be provided between floor and pipe for easy maintenance;
⇒ Fittings and joints should not be within brick wall of the chamber; ⇒ For PVC pipe, casing shall be provided inside brick wall to
overcome any load from the brick wall;
9. Anchoring of Pipes and Thrust Block At all bends, tees, valves and other branch connections, it should be necessary to provide thrust blocks of concrete to transmit the hydraulic thrust and distribute it over a wide area of the ground.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Where hydraulic thrust is upward in case of pipes on sloping ground, anchor blocks would be required to be provided at regular intervals and pipes should be firmly secured to them with steel straps.
⇒ The thrust block shall be constructed in such way that the force resulting from internal pressure in pipe is transferred to the undisturbed soil;
⇒ Anchorage blocks shall have such dimension that upward force resultant from internal pressure in pipe is counterbalanced by its weight;
9.1 Size of Thrust Blocks Every change of direction in a pipe line will cause lateral forces, when the water inside the pipe is brought under pressure. These forces can be calculated as follows: F = C x P x A Where, F = Force (Kg) C = Coefficient, depending on the angle c = 2Sinα/2 for bends c = 0.7 for tee,s c = 1.0 for end caps P = Internal Pressure (bar = kg/cm2 ) A = Cross Sectional Area of Pipe = 0.25 x π x d2 , d = Pipe Diameter (cm) Table: Force (F in kg) in bends, Tee’s and End Caps (under pressure 6 bar/87 psi)
Pipe Dia. (mm)
Angle of Bends Tee End Cap 22.5 0 30 0 45 0 90 0
100 180 240 360 660 330 470 150 410 550 820 1500 740 1100 200 740 1000 1450 2700 1320 1900 250 1150 1500 2300 4200 2100 2900 300 1650 2200 3300 6000 3000 4200
Thrust block must be designed in such way that the force F is transferred from the pipe to the surrounding.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
The Contact Area of Thrust Block C = (µ x F)/r Where, C = Contact Area (cm2) µ = Safety Factor = 1.4 F = Force (kg) r = Soil Resistance (kg/cm2) Soil Resistance (r) Soft Clay 0.5 kg/cm2
Medium Clay 0.7 kg/cm2
Sand 1.0 kg/cm2
Force F for 150 mm Tee = 740 kg C for Soft Clay = (1.4 x 740 ) / 0.5 = 2072 cm2 9.2 Size of Anchorage Blocks In case of providing anchorage block, weight of the block must be equal 1.4 x Force F Table: Volumes of Anchorage Blocks (Cubic Meter)
Pipe Diameter Type of Special 22.5 0 & 30 0
Bend 45 0 Bend 90 0 Bend
75 & 100 mm 0.14 0.21 0.39 150 mm 0.32 0.48 0.88 200 mm 0.58 0.85 1.58 250 mm 0.88 1.34 2.45 300 mm 1.28 1.93 3.50
For Internal Pressure up to 5 Bar 10. Different Type of Pipe Joints
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Pipe joint is one of the vital point to give attention at time of pipe laying, even many transmission and distribution system with high quality pipe material deteriorate due to poor workmanship and material at the pipe joint. Few common types of pipe joints are given below: a. PVC Coupler Joint with Gasket This type of joint is good for PVC, medium diameter DI and CI pipes. It gets more flexibility also construction procedure is much easier. In this type of joint, two pipe ends are pushed into a socket piece with built in rubber gasket.
b. Push-fit Joint
There should be a groove in the female end of the pipe where rubber can placed. The male end is pushed inside with pressure. There may be provision of more grooves. c. Socket Nipple Joint with Glue (Solvent Cement) For PVC pipes less than 100 mm this type of joint is feasible and economical. On technical point of view this type of joint is not very good due to less flexibility and precise working procedure. Following important points should be considered very carefully to overcome trouble. d. Socket Nipple Joint with Thread This type of Joint is commonly used for small diameter PVC and GI pipes in Bangladesh. It is good for small diameter fittings at in house plumbing. e. Mechanical Joint For bigger diameter pipes and fittings this type of joint is suitable. Also this is commonly used in fitting installation of medium diameter pipes. The maintenance of this type joint is very easy. The common mechanical joints in pipe laying are done by dresser coupling and flange adaptor fittings. f. Welding Joints Presently the use of this joint is very limited in water pipeline. In special cases like production wells, culvert, bridge and railway crossing it is commonly used. It is difficult to maintain also in construction.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
UNDERSTANDING UN-ACCOUNTED FOR WATER Unaccounted-for Water (UFW): It can be defined as the difference between the amount of water supplied to the system and the sum of water billed or in other word, equivalent sold water quantity. Q Supplied – Q Sold = Ufw Unaccounted for Water can be categorized into two major heads:
Technical Water Losses: It means actual quantity of water lost from leaking valves, pipe leaks, bursts, over flow from high level reservoir and the like.
Commercial/ Administrative losses: It comprises a number of separate items which do not necessarily refer to lost water but mainly to loss of income for the utility through:
• Unauthorized connection;
• By-pass around the water meter;
• Inaccurate water meters;
• Meters with a relatively high starting flow (i.e. starting flow for a 3/4”
meter is normally 40 l/hr, if the actual starting flow is say 60 l/hr then at
each such service connection 20 l/hr are lost.);
• Broken/tampered water meters;
• Unmetered customers are charged with a flat rate;
• Meter reading errors, calculation error of water consumption;
Non-Revenue Water (NRW): Non-revenue Water refers to water that a water utility does not receive any compensation for. Figure -1 presents details of Non-revenue Water. Water Wastage: Wastage is that quantity of water in the water supply system which is received, but not utilized by the consumers for any useful purpose. Wastage is considered to occur behind the service water meter so it is actually paid for but it is not available to others. At flat rate billed unmetered connections, where the quantity of water used has no influence on the revenue, but only on the availability of water to others. Reduction in wastage will create the possibility for postponement of extensions and corresponding investment due to more water being available in the system, thereby generating additional revenue for Water Supply Department.
Wastage is occurring basically due to the following reasons: • Users keep taps open when no water is required (for both house
connection and street hydrant);
• Overflowing of storage tanks;
• Leaks in the in-house plumbing in service connection;
Loss of Water Due to Leaky Bib Cock:
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Sl. No. Leakage Loss of Water (Liter/day) 1 30 drops per minute 8
2 60 drops per minute 17
3 120 drops per minute 36
4 13 mm deep solid stream 153
5 38 mm deep solid stream 333
Measure to Control Wastage:
• Good quality in-house plumbing;
• Good quality service connection and street hydrant fittings;
• Public awareness;
• Appropriate supervision by KWASA engineers before connecting the
service connection to the water supply line.
Figure -1: Key to Non Revenue Water (NRW)
TOTAL WATER PRODUCTION
Total equivalent water quantity sold
Lump sum payment
Water tanker supply
Metered payment
Un-metered payment
Others
Technical losses
Non-Revenue water
Administrative Losses
Tampered meter
Inaccurate meters
Un-metered connection
Illegal connection
Faulty reading
Non-billing/forgotten
Improper consumer
Public hydrant usages
Seepage and over flow of tanks and
reservoirs
Open washout
Pipe leak
Leakage from service connections
Mains flushing, etc.
Others
Others
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Leakage Control: The aim of leakage control is to reduce Leakage (and Wastage) in a systematically and economically. Leak Detection Program: Leak detection program includes thorough investigation of water distribution system in order to identify most vulnerable areas causing major leakages in the system, determine water and revenue losses and help the utility to select and implement programs to reduce the distribution system loss and make better use of water resources. The major steps of Modern Leak Detection Program are as follows:
• Selection of Study Area (Pilot Area);
• Survey and Investigation of Pilot Area;
• Pilot Area Preparation;
• Monitoring and Measurement;
• Leak Detection Campaign;
• Post Leak Detection Activity
• Data Analysis and Findings;
• Conclusion and Recommendations. Leak Detection Methods: The leak detection methods generally in practice are:
• Pressure Control;
• Passive Leakage Control;
• Routine or Regular Sounding;
• District Metering;
• Waste Metering;
• Combined District and Waste Metering
Benefits of Leak Detection: The benefits of leak detection are as follows:
• Reduced Water Losses;
• Financial Improvement;
• Increased Knowledge of the Distribution System;
• More Efficient Use of Existing Supplies;
• Safeguarding Public Health and Property;
• Improved Public Relations;
• Reduced Legal Liability.
Leak Detection Equipments: The followings are the popular equipments widely used in leak detection activity:
• Tokimec Portable Ultrasonic Flowmeter (UFP-10);
• Fuji Portable Water Pressure Recorder (FJN-501);
• Fuji Digital Sound Recorder (FSB-8D);
• Fuji Water Leak Detector (Hydrolux DNR-18);
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
• Fuji Metal Pipe and Cable Locator (PL-960);
• Fuji Metal Locator (F-90M).
Guide to Pipeline Installation
Slide 1
GUIDE TO PIPELINE INSTALLATION
Discussion Summary
� General� Excavation� Transportation and Storing Pipes and Fittings� Installation Technique� Pipe Bedding & Backfilling� Road Crossings� Bridge and Culvert
Slide 2
1. General
Before Starting Construction of Pipelines, It is Necessary to Ensure That:
� All Existing Utility Lines and Services have been Located;� Safety Measures – Arrangements for Lighting, Watching and Signposting etc.;� Obtain Permission from Concerned Authorities for Diverting Traffic;� Observation Regularly the Arrangements so that Inconvenience to Public would be
Minimized.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
2. Excavation
� Obtain Road Cutting Approval from Authority;� Identification of Pipe Alignment;� Width of Excavation will be within Design Limit;� Excavation for Invert Elevation Must Allow Pipe Bedding;� Excavated Material Placed might not Create Obstacle to Traffic Movement; .� Shoring
- Shoring is required to ensure workers in excavated trenches are sufficientlyprotected and working in safe condition;
- Ensure the timbers used for upright and bracing are of sufficient size;- Width and shoring must produce sufficient access to permit installation of pipe;
Slide 4
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
� Depth of Trench: Recommended Depth for Pipelines in Different Situations:- Through bush : 100 cm (min 40 cm)- Along roads : 100 cm- Underneath roads : 120 cm
� Utmost Care Should be Taken to Ensure that Each Pipe is Properly and UniformlyBedded along its Whole Length Except at the Joints.
Slide 6
3. Transportation and Storing Pipes and Fittings
� PVC Pipes should be Transported in a Vehicle having a Bed Long Enough to Provide Support for the Full Length of the Pipe;
� PVC Pipes should be Stored in a Flat Horizontal Position;
� In General the Height of Pipes Stack should not be more than 7 Times of its Diameter.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
Slide 8
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 9
4. Installation Technique
Operation Involved in the Laying of Pipelines include the Following Steps:
� Preparation of Detailed Maps of Roads and Streets: Showing Position of:
- Curbs;
- Gutters;
- Existing water line;
- Sewerage pipes;
- Gas Pipes;
- Telephone & electric conduits.
� Locating the Proposed Alignment on the Ground: The Trench Line is Marked by Driving Centrally Stakes 30 Meter Apart on Straight Lines and 10 Meter Apart on Curves.
� Excavating the Trenches: The Trench will be Sufficiently Wide to Allow the Pipes to be Laid Properly. The Width of the Trench Generally Depends on:
- Diameter of pipes;
- Soil type and conditions;
- Cost involves.
Slide 10
� Preparation of Laying
- All pipes and fittings would be checked for class;
- The entire length of the barrel of the pipe should be well supported on solid and
even foundation;
- Check the grade level of each pipe laying to ensure that the invert level is
correct;
- Check the alignment to ensure that the deviations at the joints do not exceed
the permissible amounts;
- Pipe jointing should be carefully supervised to ensure the specifications and
manufacturer’s instructions are strictly followed.
- Where concrete surrounds, thrust blocks and valve chambers are to be
provided, attention should be paid to the quality of materials and workmanship
- In no case, pipe shall be jointed before lowering.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 11
� Pipe Laying
- The pipeline should be laid along the straightest route possible;
- Road crossings should be done at 450 angle to the road;
- Pipe should be laid with a continuous rise of about 2% to 5% to high points so
that air can be released through air valves or with a continuous fall to low point.
- Pipes should be laid on firm ground in order to prevent uneven settlement
which may damage pipe joints.
- Couplings (rubber sealing rings) may be loaded unevenly and may cause of
leakage.
Slide 12
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 13
Slide 14
5. Pipe Bedding & Backfilling
� The pipe should be laid in bed of sand, 150 mm below the bottom and 150 mm above the top of the pipe barrel and over the full trench width;
� The applied sand should be free of clay, stones or hard lumps;
� In road crossings, sand filling shall be done over the full depth of the trench;
� Backfilling of trenches shall be carried out by excavated soil in 150 mm layers; each layer being thoroughly rammed and consolidated before the succeeding layer is placed.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 15
Slide 16
6. Road Crossings
� Pipes at road crossing preferably be of galvanized (G.I) or mild steel (M.S) casing with a minimum cover of 1.0 meter above the pipe.
� The entire backfilling over the length of the crossing shall consist of sand.
� Where the application of G.I or M.S pipes is not possible, the PVC pipe shall be protected on a proper manner against the pressure caused by traffic.
� The contractor shall operate a system of traffic control;
� Road, drain and channels should be free from obstructions at all time.
� Excavated material should not be placed in such way that it will obstruct the flow of traffic.
� Backfill should be placed in 150 mm lifts and proper effort to be applied to obtain consolidation and compaction.
� Restoration of the roads damaged at the time of laying of pipeline into its original condition.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 17
Slide 18
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 19
To
Be
Continued…….
THANKS
Slide 1
7. Details of Standard Valve Chamber
The Main Objective of Valve Chamber in Water Distribution System are:
� Easy Location of Sluice Valve;� Easy Operation in Diverting Water Flow;� Protection from Damage;
The Chambers are also urgently required for:
� Washout Point;� Air Release Valve Location;
GUIDE TO PIPELINE INSTALLATION
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 2
The Valve Chamber can be Categorized into:
� Inside the Road for Heavy Traffic;� Off the Road for Light Traffic;
The Points to be Considered during Construction of Chamber:
� Slab shall be constructed in three parts;� Top slab of the chamber shall be flushed with the existing road/ground level;� The base slab of the chamber shall be of CC or RCC;� A concrete block shall be provided under the seat of the sluice valve so that
load of sluice valve does not transfer to PVC pipelines. � Sufficient space shall be provided between floor and pipe for easy
maintenance.� Fittings and joints should not be within brick wall of the chamber� For PVC pipe, casing shall be provided inside brick wall to overcome any
load from the brick wall
Slide 3
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 4
Slide 5
8. Anchoring of Pipes and Thrust Block
At all bends, tees, valves and other branch connections, it should be necessaryto provide thrust blocks of concrete to transmit the hydraulic thrust anddistribute it over a wide area of the ground.
Where hydraulic thrust is upward in case of pipes on sloping ground , anchorblocks would be required to be provided at regular intervals and pipes shouldbe firmly secured to them with steel straps.
� The thrust block shall be constructed in such way that the force resultingfrom internal pressure in pipe is transferred to the undisturbed soil ;
� Anchorage blocks shall have such dimension that upward force resultantfrom internal pressure in pipe is counterbalanced by its weight
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 6
9.1 Size of Thrust Blocks
Every change of direction in a pipe line will cause lateral forces, when the waterinside the pipe is brought under pressure.
These forces can be calculated as follows:
F = C x P x A
Where,
F = Force (Kg)C = Coefficient, depending on the angle
c = 2Sinα/2 for bendsc = 0.7 for tee,sc = 1.0 for end caps
P = Internal Pressure (bar = kg/cm2 )A = Cross Sectional Area of Pipe
= 0.25 x π x d2 , d = Pipe Diameter (cm)
Slide 7
Pipe Dia.(mm)
Angle of Bends Tee End Cap
22.5 0 30 0 45 0 90 0
100 180 240 360 660 330 470
150 410 550 820 1500 740 1100
200 740 1000 1450 2700 1320 1900
250 1150 1500 2300 4200 2100 2900
300 1650 2200 3300 6000 3000 4200
Table: Force (F in kg) in bends, Tee’s and End Caps (under pressure 6 bar/87 psi)
Thrust block must be designed in such way that the force F is transferred from the pipe to the surrounding.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 8
The Contact Area of Thrust Block
C = (µ x F)/r
Where,
C = Contact Area (cm2)µ = Safety Factor = 1.4F = Force (kg)R = Soil Resistance (kg/cm2)
Soil Resistance (r)
Soft Clay 0.5 kg/cm2Medium Clay 0.7 kg/cm2Sand 1.0 kg/cm2Force F for 150 mm Tee = 740 kgC for Soft Clay = (1.4 x 740 ) / 0.5
= 2072 cm2
Slide 9
9.2 Size of Anchorage Blocks
In case of providing anchorage block, weight of the block must be equal 1.4 x Force F
Table: Volumes of Anchorage Blocks (Cubic Meter)
Pipe Diameter Type of Special
22.5 0 & 30 0 Bend 45 0 Bend 90 0 Bend
75 & 100 mm 0.14 0.21 0.39
150 mm 0.32 0.48 0.88
200 mm 0.58 0.85 1.58
250 mm 0.88 1.34 2.45
300 mm 1.28 1.93 3.50
For Internal Pressure up to 5 Bar
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 10
Slide 11
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 12
Slide 13
10. Different Type of Pipe Joints
Pipe joint is one of the vital point to give attention at time of pipe laying, even many transmission and distribution system with high quality pipe material deteriorate due to poor workmanship and material at the pipe joint. Few common types of pipe joints are given below:
a. PVC Coupler Joint with Gasket
This type of joint is good for PVC, medium diameter DI and CI pipes. It gets more flexibility also construction procedure is much easier. In this type of joint, two pipe ends are pushed into a socket piece with built in rubber gasket.
b. Push-fit Joint
There should be a groove in the female end of the pipe where rubber can placed. The male end is pushed inside with pressure. There may be provision of more grooves.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 14
Slide 15
c. Socket Nipple Joint with Glue (Solvent Cement)
For PVC pipes less than 100 mm this type of joint is feasible and economical. On technical point of view this type of joint is not very good due to less flexibility and precise working procedure. Following important points should be considered very carefully to overcome trouble.
d. Socket Nipple Joint with Thread
This type of Joint is commonly used for small diameter PVC and GI pipes in Bangladesh. It is good for small diameter fittings at in house plumbing.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 16
e. Mechanical Joint
For bigger diameter pipes and fittings this type of joint is suitable. Also this is commonly used in fitting installation of medium diameter pipes. The maintenance of this type joint is very easy.
The common mechanical joints in pipe laying are done by dresser coupling and flange adaptor fittings.
f. Welding Joints
Presently the use of this joint is very limited in water pipeline. In special cases like production wells, culvert, bridge and railway crossing it is commonly used. It is difficuilt to maintain also in construction
Slide 17
To
Be
Continued…….
THANKS
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 1
Khulna WASA 1
Presentation
On
Understanding of Unaccounted for Water (UFW)
Slide 2
Khulna WASA 2
UNDERSTANDING UNACCOUNTED FOR WATER
Un-accounted for Water (UFW)
It can be defined as the difference between the amount of water supplied to
the system and the sum of water billed or in other word, equivalent sold water
quantity.
Q Supplied – Q Sold = Ufw
Unaccounted for Water can be categorized into two major heads:
• Technical Water Losses
• Commercial Water Losses
Technical Water Losses: It means actual quantity of water lost from leaking
valves, pipe leaks, bursts, over flow from high level reservoir and the like.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
Khulna WASA 3
Commercial/ Administrative losses: It comprises a number of separate items
which do not necessarily refer to lost water but mainly to loss of income for the
utility through:
• Unauthorized connection;
• By-pass around the water meter;
• Inaccurate water meters;
• Meters with a relatively high starting flow (i.e. starting flow for a 3/4”
meter is normally 40 l/hr, if the actual starting flow is say 60 l/hr then at
each such service connection 20 l/hr are lost.);
• Broken/tampered water meters;
• Unmetered customers are charged with a flat rate;
• Meter reading errors, calculation error of water consumption.
UNDERSTANDING UNACCOUNTED FOR WATER
Slide 4
Khulna WASA 4
UNDERSTANDING UNACCOUNTED FOR WATER
Water Wastage: Wastage is that quantity of water in the water supply system
which is received, but not utilized by the consumers for any useful purpose.
Wastage is considered to occur behind the service water meter so it is actually
paid for but it is not available to others.
At flat rate billed unmetered connections, where the quantity of water used
has no influence on the revenue, but only on the availability of water to others.
Reduction in wastage will create the possibility for postponement of extensions
and corresponding investment due to more water being available in the
system, thereby generating additional revenue for Water Supply Department.
Wastage is occurring basically due to the following reasons:
• Users keep taps open when no water is required (for both house
connection and street hydrant);
• Overflowing of storage tanks;
• Leaks in the in-house plumbing in service connection;
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
Khulna WASA 5
UNDERSTANDING UNACCOUNTED FOR WATER
Sl. No. Leakage Loss of Water (Liter/day)
1 30 drops per minute 8
2 60 drops per minute 17
3 120 drops per minute 36
4 13 mm deep solid stream 153
5 38 mm deep solid stream 333
Loss of Water Due to Leaky Bib Cock:
Measures to Control Wastage:
• Good quality in-house plumbing;
• Good quality service connection and street hydrant fittings;
• Public awareness;
• Appropriate supervision by KWASA engineers before connecting the
service connection to the water supply line.
Slide 6
Khulna WASA 6
UNDERSTANDING UNACCOUNTED FOR WATER
TOTAL WATER PRODUCTION
Total equivalent water quantity sold
Lump sum payment
Water tanker supply
Metered payment
Un-metered payment
Others
Technical losses
Non-Revenue water
Administrative Losses
Tampered meter
Inaccurate meters
Un-metered connection
Illegal connection
Faulty reading
Non-billing/forgotten
Improper consumer lassification
Public hydrant usages
Seepage and over flow of tanks and reservoirs
Open washout
Pipe leak
Leakage from service connections
Mains flushing, etc.
Others
Others
Key to Non Revenue Water (NRW)
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
Khulna WASA 7
UNDERSTANDING UNACCOUNTED FOR WATER
Leakage Control: The aim of leakage control is to reduce Leakage (and
Wastage) in a systematically and economically.
Leak Detection Program: Leak detection program includes thorough
investigation of water distribution system in order to identify most vulnerable
areas causing major leakages in the system, determine water and revenue
losses and help the utility to select and implement programs to reduce the
distribution system loss and make better use of water resources. The major
steps of Modern Leak Detection Program are as follows:
• Selection of Study Area (Pilot Area);
• Survey and Investigation of Pilot Area;
• Pilot Area Preparation;
• Monitoring and Measurement;
• Leak Detection Campaign;
• Post Leak Detection Activity
• Data Analysis and Findings;
• Conclusion and Recommendations.
Slide 8
Khulna WASA 8
Leak Detection Methods: The leak detection methods generally in practice are:
• Pressure Control;
• Passive Leakage Control;
• Routine or Regular Sounding;
• District Metering;
• Waste Metering;
• Combined District and Waste Metering
UNDERSTANDING UNACCOUNTED FOR WATER
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 9
Khulna WASA 9
UNDERSTANDING UNACCOUNTED FOR WATER
Benefits of Leak Detection: The benefits of leak detection are as follows:
• Reduced Water Losses;
• Financial Improvement;
• Increased Knowledge of the Distribution System;
• More Efficient Use of Existing Supplies;
• Safeguarding Public Health and Property;
• Improved Public Relations;
• Reduced Legal Liability.
Slide 10
Khulna WASA 10
UNDERSTANDING UNACCOUNTED FOR WATER
Leak Detection Equipments: The followings are the popular equipments widely
used in leak detection activity:
• Tokimec Portable Ultrasonic Flowmeter (UFP-10);
• Fuji Portable Water Pressure Recorder (FJN-501);
• Fuji Digital Sound Recorder (FSB-8D);
• Fuji Water Leak Detector (Hydrolux DNR-18);
• Fuji Metal Pipe and Cable Locator (PL-960);
• Fuji Metal Locator (F-90M).
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 11
Khulna WASA 11
THANKS
For
Patience Hearing
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Training Materials 2
Guide to Pipeline Installation
Presentation-01-(23-10-10)
Slide 1
ADB TA 7385-BAN : Preparing
the Khulna Water Supply Project
WELCOME
TO
Training on Pumping Equipment,
Guide to Distribution Pipes
Installation and Accounts
Keeping
Participants : Officers/Staffs of KWASA
Date-23 October, 2010
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 2
Multiple Choice Questionnaires
1. Main responsibility of KWASA is to
a) Supply safe water to consumer
b) Supply safe & adequate water to consumer
c) Supply safe & adequate water to consumer
with minimum/cheapest price.
2 A Standard W/S system should have
capability to supply safe water
a) As per consumer requirement
b) 3 times per day
c) 24 hours in a day
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
Multiple Choice Questionnaires
3. Any W/S System must have
a) Production Well
b) Pipeline
c) Pump Unit
d) Overhead/underground Reservoir
e) House Connection
4. General function of a Pump is to
a) Lift water from ground reservoir to OHT
b) Supply water to consumer
c) Transfer any liquid from one place to
another place.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 4
Multiple Choice Questionnaires
5. Appropriate type of pump to extract
ground water from production well is
a) Turbine Pump
b) Submersible Pump
c) Surface Centrifugal Pump
6. KWASA are using following types of
pumps to extract ground water from PTW
a) Turbine & Submersible Pump
b) Submersible & Centrifugal Pump
c) Turbine, Submersible & Surface type
Centrifugal Pump
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
Multiple Choice Questionnaires
7. Theoretically centrifugal pump can lift
water from a maximum lift of
a) 8.33m
b) 9.33m
c) 10.33m
d) 11.33m
8. Output of a Pump mainly depends on
a) Capacity of drive unit (Motor/Engine)
b) Size, Type & RPM of Pump Unit
c) Power Supply to the Pump Unit.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 6
Multiple Choice Questionnaires
9. Main parameters to be provided for
procurement of a pump
a) Pump Discharge/Flow Rate
b) Motor Power (HP/KW)
c) Total Field Head and Discharge
10. Higher head pump as compared to field
requirement
a) Is always better
b) May causes serious problem for the system
c) Has no adverse effect to the system
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
Roles of Pump in a Water Supply System
• Nobody can imagine a Water Supply
System without Pump
• Breakdown of pump unit causes
breakdown of the Water Supply System
• Standby pump is essential for continuous
Water Supply System
• Fig-1.2 & Fig-1.2 indicate roles &
importance of Pump Unit for a Water
Supply System
Exception-A gravity flow system may run
without any pump unit and it depends on
geographical location of source, Treatment
unit & service area.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 8
Fig-1.1 : General Flow diagram of
Water Supply System
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 9
Fig-1.2 : W/S System Flow Diagram at
Noakhali Paurashava
IRP
AN OVERVIEW FOR THE COMPLETE WATER SUPPLY SYSTEM OF NOAKHALI POURASHAVA
CWR
Booster Pump Station
Pump
Well Field
House OGR
CONTROL ROOM
LLP
IRP
OHT
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 10
Topics on Pump
⇒Definition
⇒Principal of operation
⇒Application
⇒Classification
⇒Example of different types of pumps
used in Water Supply System
⇒Different types of pumps used in
Water Supply System of KWASA
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 11
Pump
⇒Pump is a mechanical device by
which liquid can be transferred
from one place to another place.
⇒Function of a pump is to
convert mechanical energy to
hydraulic/pressure energy.
Rotating/reciprocating motion
(mechanical energy) of pump
component causes pressure
difference for flowing of fluid.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 12
Principle of Pump Operation
• One nature of any fluid is to flow from high pressure region toward low presser region.
• The function of a pump is to bring liquid from the source by creating artificial low pressure at suction side and delivering the liquid to targeted point by creating artificial high pressure at the delivery side (see Fig-1.3 & Fig-1.4 )
• Pump cannot run alone. Rotating (impeller, gear, screw etc)/Reciprocating (Piston etc.) component of pump unit is being driven by Engine or Electric Motor and creates pressure difference which in turn causes fluid to flow from one place to another place.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 13
Fig-1.3 Principle of Pump Operation
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 14
Fig-1.3 : Principal of operation of a
Centrifugal Pump
Impeller
Water
delivery
due to high
pressure
Water
coming
due to low
pressure
Principal of operation of a
Centrifugal Pump
Pump
Shaft
Volute casing
(pump body)
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 15
Application
• There is no other mechanical m/c like
pump which have a wide range of field
application such as
• Irrigation for Agriculture including
fisheries
• Water Supply System
• Sewerage & Drainage Faciolities
• All types of Chemical; Industries
• Swimming Pool
• Flood Control etc.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 16
Classification of Pumps
According to Principal of Operation
• Positive displacement pumps (Such as Reciprocating Pump,Rotary Pump, Diaphragm Pump etc)
• Variable displacement pumps (Such as Centrifugals, propellerpumps, Jets Pumps, Air Lift pumps)
According to Number of Stages
• Single Stage Pumps
• Multi Stage pumps
According to types of suction inlet
• Single Suction Pumps
• Double Suction pumps
According to construction of casing
• Horizontally Split
• Vertically Split
Type of pumps used in urban/municipal water supply system
� Turbine Pump
� Submersible Pump
� Centrifugal Pump
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 17
Example of Different types of
Pumps used in W/S System
• Turbine Pump in production well-
• Mixed flow, single/multi-stage centrifugal
–Fig-2.1
• Submersible Pump in production well-
Mixed Flow/ Radial flow, single/multi-
stage centrifugal-Figure-2.2
• Section with Parts details of Multi-stage
Mixed Flow Submersible Pump set-Fig-
2.3
• Pump to lift water from Ground Reservoir
to Overhead Reservoir-Radial flow single
stage centrifugal- Fig-2.4
• Hand Tube well Pump-Manual
Reciprocating Pump
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 18
Fig-2.1 Turbine Pump-Motor Assembly
mvKkvb cvBc
cv¤ú evDj
G‡mge-x
Kjvg cvBc
Kjvg cvBc Kvcwjs G‡mge-x
jvBb k¨vdU
dvcv k¨vdU †gvUi
wWmPvR© †nW
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 19
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 20
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 21
Fig-2.4 : Installation drawing for
surface type centrifugal pump
ARRANGEMENT FOR INSTALLATION OF CENTRIFUGAL PUMP
CWR
PUMP HOUSE
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 22
Maximum Suction Lift of a Pump
• When water is moving into a pump, the maximum
suction lift is limited by four factors i.e. atmospheric
pressure, vapour pressure, head loss due to friction and
net positive suction lift of the pump itself.
Formula for maximum suction lift of a pump is expressed by
Hs=Ha-Hf-es-NPSH-Fs
Where
Hs=Maximum practical suction lift, m
Ha=Atm. pressure at the water surface, m (10.33m at sea level)
Hf=Head loss due to friction in Suction line, m
es=Saturated vapor pressure of water at specified temp., m
NPSH=Net positive suction head of the pump itself, m
Fs=Factor of safety, which is taken as 0.6m
Example : Determine the maximum practical suction lift for a pump
having discharge of 38l/s operated at an altitude of 300m above
sea level. Water temp=20oC, Friction loss in suction line &
fittings is =1.5m. The NPSH of the Pump, as obtained from the
characteristic curves supplied by the manufacturers is 4.7m.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 23
•Thank You
for your
participation
with attention
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Presentation-02-(13-11-10)
Slide 1
ADB TA 7385-BAN : Preparing
the Khulna Water Supply Project
WELCOME
TO
Training on Pumping Equipment,
Guide to Distribution Pipes
Installation and Accounts
Keeping
Participants : Officers/Staffs of KWASA
Date-13 November, 2010
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 2
Component Parts of a Surface Type
Centrifugal Pump
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
Static Head of Centrifugal Pump
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 4
Static Head of Submersible Pump
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
Typical Pump Characteristics Curve
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 6
Characteristics curve at different
impeller diameters
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
Family Curve
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 8
•Thank You
for your
participation
with attention
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 9
Pump Characteristic Curves
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Presentation-03-(01-12-10)
Slide 1
ADB TA 7385-BAN : Preparing
the Khulna Water Supply Project
WELCOME
TO
Training on Wells & Pumps
Participants : Engineers & Supervisors of
KWASA
Date-01 December, 2010
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 2
Topics on Training
A. Class-room Discussion on
• Well Fixture
• Well Terminology
• Well Monitoring
B. Field Demonstration on
• Measurement of SWL & PWL
• Determination of Draw-Down
• Measuring Yield by Trajectory Method
• Determination of specific Capacity Capacity
• Dismantling & Assembling of a submersible pump
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
Well Fixture
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 4
Well Terminology
1. Tube Well : A technical arrangement for tapping
ground water from the pervious zone.(Aquifer)
2. Static Water Level (SWL) : The level at which
the water stands in a well before pumping starts is
called the Static Water Level.
3. Pumping Water Level (PWL) : The level at
which water stands in a well when pumping at any
given rate is called the Pumping Water Level.
4. Draw Down : Draw down at any instant is the
difference between the static water level and the
pumping water level
5. Specific capacity of Well : Specific capacity of a
well is its yield per unit draw down and generally
expressed as cubic meter per hour per meter draw
down.
6. Yield of Well : The yield of a well is the volume
of water from it per unit time (m3/h or GPH).
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
Measurement of Water flow rate
by Trajectory Tethod
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 6
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 8
•Thank You
for your
participation
with attention
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 9
Pump Characteristic Curves
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Presentation-04-(14-12-10)
Slide 1
ADB TA 7385-BAN : Preparing
the Khulna Water Supply Project
WELCOME
TO
Training on Wells & Pumps
Participants : Engineers & Supervisors of
KWASA
Date14 December, 2010
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 2
Topics on Training
• Discussion on Series operation of
Pump 9 : 30AM to 10: 30 AM
• Discussion on Parallel operation of
Pump 10 : 30AM to 11 : 30 AM
• Revision on previous trainings
carried out so far 11: 30AM to
1 : 15 PM
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
Series & Parallel Operation of Pump
• Pumps are required to be connected in series
to meet up field head when head of one pump
available is not enough to meet up field head
(Figure-4.1.2). Pressure in transmission pipe
is also minimized by using series connection
of pumps.
No of Pump required in series=total head
required divided by the head available for one
pump.
• Pumps are required to be connected in
parallel to meet up total discharge when
discharge of one pump available is not
enough to meet up total discharge (Figure-
4..2. 2) .
No of Pump required in Parallel=Total
discharge required divided by the discharge
capacity for one pump.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 4
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 6
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 8
•Thank You
for your
participation
with attention
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Presentation-05-(23-12-10)
Slide 1
ADB TA 7385-BAN : Preparing the Khulna Water Supply Project
Khulna Water Supply and Sewerage Authority
Technical Training Program-5
Date : 22-12-2010
Venue : Conference Room
Topics on Training
Basic of Electricity 9 : 30- 10:30
•Refreshment 10 : 30- 10:45
•Electrical Control & Protective Component used in
Pumping Plant (including field demonstration).10: 45- 11:45
•Measuring Instrument in Pumping Plant 11 : 45- 12:30
•Circuit Diagram of Elec. Equipment in Pumping Plant12 : 30- 1:15
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 2
Session-1
BASIC OF ELECTRICITY
⇒ we`ywe`ywe`ywe`y¨̈̈̈ZZZZ wKwKwKwK ????
⇒ cwievnx cwievnx cwievnx cwievnx (Conductor), ‡iva ‡iva ‡iva ‡iva (Resistance)
⇒ ‡fvë ‡fvë ‡fvë ‡fvë (Voltage) ,‡fvë ‡fvë ‡fvë ‡fvë (Volt)
⇒ Kv‡i›U (Kv‡i›U (Kv‡i›U (Kv‡i›U (Current), G, G, G, G¨̈̈̈vw¤úqvi vw¤úqvi vw¤úqvi vw¤úqvi (Ampier)
⇒ cvwbi cÖevn I we`ycvwbi cÖevn I we`ycvwbi cÖevn I we`ycvwbi cÖevn I we`y¨̈̈̈r cÖev‡n mv`„kr cÖev‡n mv`„kr cÖev‡n mv`„kr cÖev‡n mv`„k¨̈̈̈ tttt
we`ywe`ywe`ywe`y¨̈̈̈rrrr cÖevncÖevncÖevncÖevn (G(G(G(G¨̈̈̈vw¤úqvvw¤úqvvw¤úqvvw¤úqv )))) cvwbicvwbicvwbicvwbi cÖevncÖevncÖevncÖevn
(Nbwgt/N›Uv)(Nbwgt/N›Uv)(Nbwgt/N›Uv)(Nbwgt/N›Uv)
KbvWvKUiKbvWvKUiKbvWvKUiKbvWvKUi cvBvccvBvccvBvccvBvc jvBbjvBbjvBbjvBb
‡iwRó‡iwRó‡iwRó‡iwRó¨̈̈̈vÝvÝvÝvÝ wd«Kkbwd«Kkbwd«Kkbwd«Kkb jmjmjmjm
‡fv‡ëR‡fv‡ëR‡fv‡ëR‡fv‡ëR cvwbicvwbicvwbicvwbi PvcPvcPvcPvc
‡fv‡ëRWªc‡fv‡ëRWªc‡fv‡ëRWªc‡fv‡ëRWªc ‡cÖmvi‡cÖmvi‡cÖmvi‡cÖmvi WªcWªcWªcWªc
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 4
Session-2
Electrical Protection & Control Component
⇒myBPu wK , e¨envi I cÖKvi‡f`
⇒ wdDR wK, e¨envi I cÖKvi‡f`
⇒ mvwK©U ‡eªKvi wK, e¨venvi I cÖKvi‡f`
⇒ g¨vM‡bwUK KbUvKUi wK, e¨envi I Qwe
⇒ Ifvi‡nW wi‡j wK, e¨envi I Qwe
⇒ UvBgvi wK, e¨envi I Qwe
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 6
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 8
Session-3
Measuring Instrument in Pumping Plant
⇒ ‡fvëwgUvi wK , e¨envi I GKK
⇒ G‡gUvi wK, e¨envi I GKK
⇒ GbvwR© wgUvi wK, e¨envi I GKK
⇒ ‡d¬vwgUvi wK, e¨envi I GKK
⇒ ‡cÖmviwgUvi wK, e¨envi I GKK
⇒ g¨vM‡bwUK KbUvKUi wK, e¨envi I Qwe
⇒ Ifvi‡nW wi‡j wK, e¨envi I Qwe
⇒ UvBgvi wK, e¨envi I Qwe
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 9
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 10
Session-3 : 1:30 Minutes
Measuring Instrument
⇒ ‡fvëwgUvi wK , e¨envi I GKK
⇒ G‡gUvi wK, e¨envi I GKK
⇒ GbvwR© wgUvi wK, e¨envi I GKK
⇒ ‡d¬vwgUvi wK, e¨envi I GKK
⇒ ‡cÖmviwgUvi wK, e¨envi I GKK
⇒ g¨vM‡bwUK KbUvKUi wK, e¨envi I Qwe
⇒ Ifvi‡nW wi‡j wK, e¨envi I Qwe
⇒ UvBgvi wK, e¨envi I Qwe
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 11
Session-4 : 1:30 Minutes
Electrical Circuit Diagram
GjwUGjwUGjwUGjwU cccc¨̈̈̈v‡bjv‡bjv‡bjv‡bj
⇒ wK wK hš¿vsk _v‡K
⇒ ‡KvbwUi wK KvR
⇒ e-K WvqvMÖvg
‡gvUi‡gvUi‡gvUi‡gvUi K‡›UªvjK‡›UªvjK‡›UªvjK‡›Uªvj BDwbUBDwbUBDwbUBDwbU
⇒ wK wK hš¿vsk _v‡K
⇒ ‡KvbwUi wK KvR
⇒ c¨v‡bj †ev‡W© Zv‡`i Ae¯’vb †Kv_vq
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 12
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 13
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 14
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Presentation-09-(20-01-11)
Slide 1
ADB TA 7385-BAN : Preparing the Khulna Water Supply Project.
Khulna Water Supply and Sewerage Authority
Technical Program-10
Date : 20-01-2011
Venue : Hotel Castle Salam
Participants: Engineers & Supervisors
Topics on Class-room Discussion 9: 30AM-1:00 PM
•Un-accounted for Water (UFW)
•Continuity Equation
•Bernaullie’s Equation
•Water Hammer
•Cavitation
•Air Locking
• Principle of Water Treatment
Slide 2
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
Slide 4
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
Pressure Relationship
Slide 6
Water Hammer, Air Locking, Cavitations etc.
• Water Hammer is a very destructive force that exists in a pumping
installation or piping system when the rate of flow changes abruptly for
various reasons.
• Cavitation : While pumping water, if the pressure at any point inside a
pump drops below the vapour pressure, corresponding to the
temparature of the liquid, the liquid will vaporize and form cavities of
vapour. The bubbles of vapour are carried along with the stream until a
reason of higher pressure is reached, when they collapse or expolde with
tremendous shock on adjacent walls. This phenomenon is called
cavitation.
• Air Locking : Accumulation of air (contained in water) in the elevated
portion of a pipeline system is called Air Locking which causes serious
resistance in the flow of liquid. Air release valve is used to remove air from
the pipeline.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
Principle of Water Treatment
Slide 8
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 9
Typical Section of Iron Removal Plant
Slide 10
Standard Details of Washout
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 11
• Thank You for your
Attentive
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Training Materials 3
Guide to Pipeline Installation
Slide 1
ADB TA 7385-BAN : Preparing the Khulna Water Supply Project.
Khulna Water Supply and Sewerage Authority
Technical Training Program-6
Date : 05-01-2011
Venue : Conference Room
Topics on Class-room Discussion 9: 30-11:30 AM
•Installation of Submersible Pump
•Operation
•Maintenance
•Monitoring
•Trouble Shooting
•Points to be considered during O & M of Electrical equipment
•Causes of loss of energy in pump operation
•Review on Survey & Monitoring Results of Existing PTW of KWASA
Topics on Field Demonstration 11:45– 1:00 PM
Visit to nearby Pump House and demonstration on operation and monitoring of pump & well.
Slide 2
mvemvemvemve----gviwmej †gvUi cv‡¤úi ¯’vcb wb‡`©kvejxgviwmej †gvUi cv‡¤úi ¯’vcb wb‡`©kvejxgviwmej †gvUi cv‡¤úi ¯’vcb wb‡`©kvejxgviwmej †gvUi cv‡¤úi ¯’vcb wb‡`©kvejx• ‡‡‡‡gvU‡igvU‡igvU‡igvU‡i cvwbcvwbcvwbcvwb fivfivfivfiv
• cv¤úcv¤úcv¤úcv¤ú BbBbBbBb÷÷÷÷jjjj I I I I wjdwUswjdwUswjdwUswjdwUs GiGiGiGi RbRbRbRb¨̈̈̈ cÖ‡qvRbxqcÖ‡qvRbxqcÖ‡qvRbxqcÖ‡qvRbxq hš¿cvwZhš¿cvwZhš¿cvwZhš¿cvwZ t t t t
• ivBRviivBRviivBRviivBRvi cvB‡cicvB‡cicvB‡cicvB‡ci eeee¨̈̈̈vmvmvmvm AbyhvqxAbyhvqxAbyhvqxAbyhvqx gagagaga¨̈̈̈w¯’Zw¯’Zw¯’Zw¯’Z cvwbicvwbicvwbicvwbi IRbIRbIRbIRb||||
• mvemvemvemve----gviwmejgviwmejgviwmejgviwmej cv¤úcv¤úcv¤úcv¤ú ¯’¯’¯’¯’vc‡bivc‡bivc‡bivc‡bi mgqmgqmgqmgq mveavbZvmveavbZvmveavbZvmveavbZv AejAejAejAej¤^b t¤^b t¤^b t¤^b t
• ‡‡‡‡Ke&j‡KKe&j‡KKe&j‡KKe&j‡K ivBRviivBRviivBRviivBRvi ††††gB‡bigB‡bigB‡bigB‡bi mvmvmvmv‡_ ‡_ ‡_ ‡_ AvUKv‡bvAvUKv‡bvAvUKv‡bvAvUKv‡bv t t t t
• ‡‡‡‡gvUigvUigvUigvUi Kv‡bKkbKv‡bKkbKv‡bKkbKv‡bKkb t t t t
• ‡‡‡‡gvU‡iigvU‡iigvU‡iigvU‡ii NyY©bNyY©bNyY©bNyY©b w`Kw`Kw`Kw`K wbY©qwbY©qwbY©qwbY©q t t t t
• ÷÷÷÷vwU©svwU©svwU©svwU©s t t t t
• KwgkwbsKwgkwbsKwgkwbsKwgkwbs tttt.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
cwiPvjbv I i¶Yv‡e¶YcwiPvjbv I i¶Yv‡e¶YcwiPvjbv I i¶Yv‡e¶YcwiPvjbv I i¶Yv‡e¶Y
• cwiPvjbv I i¶Yv‡e¶‡Yi Zvrch©cwiPvjbv I i¶Yv‡e¶‡Yi Zvrch©cwiPvjbv I i¶Yv‡e¶‡Yi Zvrch©cwiPvjbv I i¶Yv‡e¶‡Yi Zvrch©¨̈̈̈
• 2.2| 2.2| 2.2| 2.2| cwiPvjbvcwiPvjbvcwiPvjbvcwiPvjbv
• cv¤ú Pvjy Kivi c~‡e© KiYxq Kvh©cv¤ú Pvjy Kivi c~‡e© KiYxq Kvh©cv¤ú Pvjy Kivi c~‡e© KiYxq Kvh©cv¤ú Pvjy Kivi c~‡e© KiYxq Kvh©¨̈̈̈vejx tvejx tvejx tvejx t
• cv¤ú Pvjy Kiv tcv¤ú Pvjy Kiv tcv¤ú Pvjy Kiv tcv¤ú Pvjy Kiv t
• cv¤ú Pvjy Ae¯’vq ch©‡e¶bxq welqvejx (gwbUwis)cv¤ú Pvjy Ae¯’vq ch©‡e¶bxq welqvejx (gwbUwis)cv¤ú Pvjy Ae¯’vq ch©‡e¶bxq welqvejx (gwbUwis)cv¤ú Pvjy Ae¯’vq ch©‡e¶bxq welqvejx (gwbUwis)
• cv¤ú e‡Üi wbqgvejxcv¤ú e‡Üi wbqgvejxcv¤ú e‡Üi wbqgvejxcv¤ú e‡Üi wbqgvejx
• Ri“ix wfËx‡Z cv¤ú eÜRi“ix wfËx‡Z cv¤ú eÜRi“ix wfËx‡Z cv¤ú eÜRi“ix wfËx‡Z cv¤ú eÜ
• mvemvemvemve----gviwmej cv¤ú cwiPvjbvq mveavbZv Aej¤^b tgviwmej cv¤ú cwiPvjbvq mveavbZv Aej¤^b tgviwmej cv¤ú cwiPvjbvq mveavbZv Aej¤^b tgviwmej cv¤ú cwiPvjbvq mveavbZv Aej¤^b t
Slide 4
2.3| 2.3| 2.3| 2.3| i¶Yv‡e¶Yi¶Yv‡e¶Yi¶Yv‡e¶Yi¶Yv‡e¶Y
• i¶bv‡e¶b cwiKíbv I wb‡`©kvejxi¶bv‡e¶b cwiKíbv I wb‡`©kvejxi¶bv‡e¶b cwiKíbv I wb‡`©kvejxi¶bv‡e¶b cwiKíbv I wb‡`©kvejx
µwgK bs welq µwgK bs welq µwgK bs welq µwgK bs welq ‰`wbK‰`wbK‰`wbK‰`wbK gvwmKgvwmKgvwmKgvwmK evrmwiKevrmwiKevrmwiKevrmwiK
1. cv¤ú, cv¤ú, cv¤ú, cv¤ú,
2.2.2.2. ivBRvi cvBcivBRvi cvBcivBRvi cvBcivBRvi cvBc
3.3.3.3. ‡gvUi‡gvUi‡gvUi‡gvUi
4.4.4.4. cvBc jvBb, cvBc jvBb, cvBc jvBb, cvBc jvBb,
5.5.5.5. fvj¦, wgUvi Ges wdwUs BZfvj¦, wgUvi Ges wdwUs BZfvj¦, wgUvi Ges wdwUs BZfvj¦, wgUvi Ges wdwUs BZ¨̈̈̈vw` 4vw` 4vw` 4vw` 4
6.6.6.6. ‰e`y‰e`y‰e`y‰e`y¨̈̈̈wZK K‡›Uªvj cwZK K‡›Uªvj cwZK K‡›Uªvj cwZK K‡›Uªvj c¨̈̈̈v‡bj 5v‡bj 5v‡bj 5v‡bj 5
7.7.7.7. cv¤ú Ni I cwi‡ek6cv¤ú Ni I cwi‡ek6cv¤ú Ni I cwi‡ek6cv¤ú Ni I cwi‡ek6
8.8.8.8. bjK‚cbjK‚cbjK‚cbjK‚c
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
gwbUwis Kvh©gwbUwis Kvh©gwbUwis Kvh©gwbUwis Kvh©¨̈̈̈vejx vejx vejx vejx isisisis
• ‰`wbK gwbUwis Kvh©‰`wbK gwbUwis Kvh©‰`wbK gwbUwis Kvh©‰`wbK gwbUwis Kvh©¨̈̈̈vejx (cv¤ú PvjK):vejx (cv¤ú PvjK):vejx (cv¤ú PvjK):vejx (cv¤ú PvjK):
• mvßvwnK gwbUwis Kvh©mvßvwnK gwbUwis Kvh©mvßvwnK gwbUwis Kvh©mvßvwnK gwbUwis Kvh©¨̈̈̈vejx (cv¤ú PvjK, IqvUvi vejx (cv¤ú PvjK, IqvUvi vejx (cv¤ú PvjK, IqvUvi vejx (cv¤ú PvjK, IqvUvi
mycvi): mycvi): mycvi): mycvi):
• gvwmK gwbUwis Kvh©gvwmK gwbUwis Kvh©gvwmK gwbUwis Kvh©gvwmK gwbUwis Kvh©¨̈̈̈vejx (cv¤ú PvjK, IqvUvi mycvi): vejx (cv¤ú PvjK, IqvUvi mycvi): vejx (cv¤ú PvjK, IqvUvi mycvi): vejx (cv¤ú PvjK, IqvUvi mycvi):
• ‰ÎgvwmK gwbUwis Kvh©‰ÎgvwmK gwbUwis Kvh©‰ÎgvwmK gwbUwis Kvh©‰ÎgvwmK gwbUwis Kvh©¨̈̈̈vejx (IqvUvi mycvi, vejx (IqvUvi mycvi, vejx (IqvUvi mycvi, vejx (IqvUvi mycvi,
†gKvwbK): †gKvwbK): †gKvwbK): †gKvwbK):
• evrmwiK gwbUwis Kvh©evrmwiK gwbUwis Kvh©evrmwiK gwbUwis Kvh©evrmwiK gwbUwis Kvh©¨̈̈̈ejx (IqvUvi mycvi):ejx (IqvUvi mycvi):ejx (IqvUvi mycvi):ejx (IqvUvi mycvi):
Slide 6
cv¤ú †gvUi cwiPvjbvq mgmcv¤ú †gvUi cwiPvjbvq mgmcv¤ú †gvUi cwiPvjbvq mgmcv¤ú †gvUi cwiPvjbvq mgm¨̈̈̈vejx, m¤¢vevejx, m¤¢vevejx, m¤¢vevejx, m¤¢ve¨̈̈̈ KvibKvibKvibKvib GesGesGesGes Dnvi mgvavb Dnvi mgvavb Dnvi mgvavb Dnvi mgvavb (we‡klfv‡e UvievBb Ges mvegvimxej
cv‡¤úi Rb¨)
• myBP Ab Kiv m‡Ë¡I cv¤ú †gvUi Pwj‡Z‡Q bv
• cv¤ú P‡j A_P cvwb D‡V bv ev Kg D‡V Ges wWmPvR© †cÖmvi L~e Kg nq
• cv¤ú Pvjy nIqvi wKQy¶Y ciB cvwb mieivn eÜ n‡q hvq
• cv¤ú Pvjbv Ki‡Z AwZwi³ kw³i cÖ‡qvRb nq (‡gvUi Kv‡i›U †ekx Uv‡b)
• cv¤ú †gvU‡ii K¤úb ev A¯^vfvweK kã AbyfyZ nq
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
. ‰e`y‰e`y‰e`y‰e`y¨̈̈̈wZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶Y Kv‡R wZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶Y Kv‡R wZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶Y Kv‡R wZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶Y Kv‡R
wbivcËv i¶vi RbwbivcËv i¶vi RbwbivcËv i¶vi RbwbivcËv i¶vi Rb¨̈̈̈ mZ©KZv Aej¤^b|mZ©KZv Aej¤^b|mZ©KZv Aej¤^b|mZ©KZv Aej¤^b|
‡h †Kvb ˆe`y¨wZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶‡Yi mgq wbivcËvi Rb¨ wbæwjwLZ mZ©KZv Aej¤^b Acwinvh©¨ t • ‰e`y¨wZK eZ©bxi †gBb myBP eÜ Kivi c~‡e© †Kvb ai‡bi i¶Yv‡e¶Y KvR Kiv hvB‡e bv |
• hZUzKz m¤¢e mKj ai‡Yi ˆe`y¨wZK KvR w`‡bi †ejvq Ges ch©vß Av‡jvi Dcw¯’wZ‡Z m¤úbœ Kwi‡Z nB‡e|
• mKj ai‡Yi ˆe`y¨wZK ‡givg‡Zi KvR h_vh_ KZ…c‡¶i Aby‡gv`b K…Z jvB‡mÝ cÖvß †jv‡Ki gva¨‡g Kwi‡Z nB‡e|
• ‰e`y¨wZK mK ev `~N©Ubv Gov‡bvi Rb¨ †h †Kvb ai‡Yi ˆe`y¨wZK KvR Kivi mgq Bbmy‡jUi RvZxq ivevi †M-ve, Kv‡Vi RyZv BZ¨vw` e¨envi Kwi‡Z nB‡e|
• ‰e`y¨wZK m‡K Avµvš— †h †Kvb e¨w³i ms¯úk© cwinvi Ki“b | hZ ZvovZvwo m¤¢^e ˆe`y¨wZK cÖavb myBP‡K Ad Ki“b| ˆe`y¨wZK m‡K Avµvš— e¨w³‡K Kv‡Vi i‡Wi gZ †Kvb Bbmy‡jUi w`‡q gy³ Kiv DwPr|
Slide 8
Major Factors Influencing Wastage of energy In Pump Installation
• Wrong foot-valve and strainer units, causing high frictional losses and reduced discharges
• Undersized suction and/or delivery pipes
• Unnecessary height of delivery pipe and/or too long suction pipes
• Non-matching of pump with pumping head and discharge required
• Use of electric motors/engines with low efficiency
• Use of over-sized electric motors. i.e. under-loading of motor which reduces the power factors of the motor and hence the efficiency or use of over-sized engines like tractor to operate a small pump.
• Use of inferior quality pipes and or wrong pipe fittings.
• Non-replacement of worn-out bearings of pumps and electric motors and absence of periodic oiling and greasing of bearings.
• Excessive suction lift.
• Non-availability of information on draw down-discharge characteristics with those of well characteristics.
• Use of suction and delivery pipes with excessive friction.
• Leaky joints in the suction/delivery pipeline
• Too-tight gland packing, clogging of impeller/foot valve and improper bearings
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 1
ADB TA 7385-BAN : Preparing the Khulna Water Supply Project.
Khulna Water Supply and Sewerage Authority
Training on O & M of PTW (Program-8)
Date : 11-01-2011
Venue : KWASA Premises
Duration : 2: 30 PM-5:30 PM
Participants: Pump Operators (65 Nos)
Topics:
•Production Well Pump House
•Operation
•Maintenance
•Monitoring
•Trouble Shooting
•Points to be considered during O & M of Electrical equipment
Slide 2
Drcv`b bjKyc cv¤ú nvDR
• 2.1 Drcv`b bjK‚c
• 2.2 mve-gviwmej cv¤ú-‡gvUi ‡mU
• 2.3 cvBc jvBb
• 2.4 ‰e`y¨wZK K‡›Uªvj c¨v‡bj
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 3
Slide 4
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 5
cvw¤ús ccvw¤ús ccvw¤ús ccvw¤ús c-v‡›U ev‡›U ev‡›U ev‡›U e¨̈̈̈eüZ ‰e`yeüZ ‰e`yeüZ ‰e`yeüZ ‰e`y¨̈̈̈wZK wbqš¿b I wZK wbqš¿b I wZK wbqš¿b I wZK wbqš¿b I
cÖwZi¶v hš¿vw`cÖwZi¶v hš¿vw`cÖwZi¶v hš¿vw`cÖwZi¶v hš¿vw`
• 1.1| wdDRwdDRwdDRwdDR
• 1.2| mvwK©U †eªKvi mvwK©U †eªKvi mvwK©U †eªKvi mvwK©U †eªKvi (Circuit Breaker)
• 1.3| Ifvi‡jvW wi‡j Ifvi‡jvW wi‡j Ifvi‡jvW wi‡j Ifvi‡jvW wi‡j (Overload Relay)
• 1.4| gggg¨̈̈̈vM‡bwUK KbUvKUivM‡bwUK KbUvKUivM‡bwUK KbUvKUivM‡bwUK KbUvKUi (Magnetic
Contactor)
• 1.5| Kv‡i›U UªvÝdigviKv‡i›U UªvÝdigviKv‡i›U UªvÝdigviKv‡i›U UªvÝdigvi (Current Transformer) :
• 1.6| UvBgviUvBgviUvBgviUvBgvi (Timer)
Slide 6
cwiPvjbv I i¶Yv‡e¶YcwiPvjbv I i¶Yv‡e¶YcwiPvjbv I i¶Yv‡e¶YcwiPvjbv I i¶Yv‡e¶Y
• cwiPvjbv I i¶Yv‡e¶‡Yi Zvrch©cwiPvjbv I i¶Yv‡e¶‡Yi Zvrch©cwiPvjbv I i¶Yv‡e¶‡Yi Zvrch©cwiPvjbv I i¶Yv‡e¶‡Yi Zvrch©¨̈̈̈
2.2| 2.2| 2.2| 2.2| cwiPvjbvcwiPvjbvcwiPvjbvcwiPvjbv
• cv¤ú Pvjy Kivi c~‡e© KiYxq Kvh©cv¤ú Pvjy Kivi c~‡e© KiYxq Kvh©cv¤ú Pvjy Kivi c~‡e© KiYxq Kvh©cv¤ú Pvjy Kivi c~‡e© KiYxq Kvh©¨̈̈̈vejx tvejx tvejx tvejx t
• cv¤ú Pvjy Kiv tcv¤ú Pvjy Kiv tcv¤ú Pvjy Kiv tcv¤ú Pvjy Kiv t
• cv¤ú Pvjy Ae¯’vq ch©‡e¶bxq welqvejx (gwbUwis)cv¤ú Pvjy Ae¯’vq ch©‡e¶bxq welqvejx (gwbUwis)cv¤ú Pvjy Ae¯’vq ch©‡e¶bxq welqvejx (gwbUwis)cv¤ú Pvjy Ae¯’vq ch©‡e¶bxq welqvejx (gwbUwis)
• cv¤ú e‡Üi wbqgvejxcv¤ú e‡Üi wbqgvejxcv¤ú e‡Üi wbqgvejxcv¤ú e‡Üi wbqgvejx
• Riix wfËx‡Z cv¤ú eÜRiix wfËx‡Z cv¤ú eÜRiix wfËx‡Z cv¤ú eÜRiix wfËx‡Z cv¤ú eÜ
• mvemvemvemve----gviwmej cv¤ú cwiPvjbvq mveavbZv Aej¤^b gviwmej cv¤ú cwiPvjbvq mveavbZv Aej¤^b gviwmej cv¤ú cwiPvjbvq mveavbZv Aej¤^b gviwmej cv¤ú cwiPvjbvq mveavbZv Aej¤^b
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 7
i¶Yv‡e¶Yi¶Yv‡e¶Yi¶Yv‡e¶Yi¶Yv‡e¶Y
• i¶bv‡e¶b cwiKíbv I wb‡`©kvejxi¶bv‡e¶b cwiKíbv I wb‡`©kvejxi¶bv‡e¶b cwiKíbv I wb‡`©kvejxi¶bv‡e¶b cwiKíbv I wb‡`©kvejx
µwgK bs welq µwgK bs welq µwgK bs welq µwgK bs welq ‰`wbK‰`wbK‰`wbK‰`wbK gvwmKgvwmKgvwmKgvwmK evrmwiKevrmwiKevrmwiKevrmwiK
1. cv¤ú, cv¤ú, cv¤ú, cv¤ú,
2.2.2.2. ivBRvi cvBcivBRvi cvBcivBRvi cvBcivBRvi cvBc
3.3.3.3. ‡gvUi‡gvUi‡gvUi‡gvUi
4.4.4.4. cvBc jvBb, cvBc jvBb, cvBc jvBb, cvBc jvBb,
5.5.5.5. fvj¦, wgUvi Ges wdwUs BZfvj¦, wgUvi Ges wdwUs BZfvj¦, wgUvi Ges wdwUs BZfvj¦, wgUvi Ges wdwUs BZ¨̈̈̈vw` vw` vw` vw`
6.6.6.6. ‰e`y‰e`y‰e`y‰e`y¨̈̈̈wZK K‡›Uªvj cwZK K‡›Uªvj cwZK K‡›Uªvj cwZK K‡›Uªvj c¨̈̈̈v‡bj v‡bj v‡bj v‡bj
7.7.7.7. cv¤ú Ni I cwi‡ekcv¤ú Ni I cwi‡ekcv¤ú Ni I cwi‡ekcv¤ú Ni I cwi‡ek
8.8.8.8. bjK‚cbjK‚cbjK‚cbjK‚c
Slide 8
gwbUwis Kvh©gwbUwis Kvh©gwbUwis Kvh©gwbUwis Kvh©¨̈̈̈vejx vejx vejx vejx isisisis
• ‰`wbK gwbUwis Kvh©‰`wbK gwbUwis Kvh©‰`wbK gwbUwis Kvh©‰`wbK gwbUwis Kvh©¨̈̈̈vejx (cv¤ú PvjK):vejx (cv¤ú PvjK):vejx (cv¤ú PvjK):vejx (cv¤ú PvjK):
• mvßvwnK gwbUwis Kvh©mvßvwnK gwbUwis Kvh©mvßvwnK gwbUwis Kvh©mvßvwnK gwbUwis Kvh©¨̈̈̈vejx (cv¤ú PvjK, IqvUvi vejx (cv¤ú PvjK, IqvUvi vejx (cv¤ú PvjK, IqvUvi vejx (cv¤ú PvjK, IqvUvi
mycvi): mycvi): mycvi): mycvi):
• gvwmK gwbUwis Kvh©gvwmK gwbUwis Kvh©gvwmK gwbUwis Kvh©gvwmK gwbUwis Kvh©¨̈̈̈vejx (cv¤ú PvjK, IqvUvi mycvi): vejx (cv¤ú PvjK, IqvUvi mycvi): vejx (cv¤ú PvjK, IqvUvi mycvi): vejx (cv¤ú PvjK, IqvUvi mycvi):
• ‰ÎgvwmK gwbUwis Kvh©‰ÎgvwmK gwbUwis Kvh©‰ÎgvwmK gwbUwis Kvh©‰ÎgvwmK gwbUwis Kvh©¨̈̈̈vejx (IqvUvi mycvi, vejx (IqvUvi mycvi, vejx (IqvUvi mycvi, vejx (IqvUvi mycvi,
†gKvwbK): †gKvwbK): †gKvwbK): †gKvwbK):
• evrmwiK gwbUwis Kvh©evrmwiK gwbUwis Kvh©evrmwiK gwbUwis Kvh©evrmwiK gwbUwis Kvh©¨̈̈̈ejx (IqvUvi mycvi):ejx (IqvUvi mycvi):ejx (IqvUvi mycvi):ejx (IqvUvi mycvi):
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
Slide 9
cv¤ú †gvUi cwiPvjbvq mgmcv¤ú †gvUi cwiPvjbvq mgmcv¤ú †gvUi cwiPvjbvq mgmcv¤ú †gvUi cwiPvjbvq mgm¨̈̈̈vejx, m¤¢vevejx, m¤¢vevejx, m¤¢vevejx, m¤¢ve¨̈̈̈ KvibKvibKvibKvib Dnvi mgvavb Dnvi mgvavb Dnvi mgvavb Dnvi mgvavb
(we‡klfv‡e UvievBb Ges mvegvimxej cv‡¤úi Rb¨)
• myBP Ab Kiv m‡Ë¡I cv¤ú †gvUi Pwj‡Z‡Q bvmyBP Ab Kiv m‡Ë¡I cv¤ú †gvUi Pwj‡Z‡Q bvmyBP Ab Kiv m‡Ë¡I cv¤ú †gvUi Pwj‡Z‡Q bvmyBP Ab Kiv m‡Ë¡I cv¤ú †gvUi Pwj‡Z‡Q bv
• cv¤ú P‡j A_P cvwb D‡V bv ev Kg D‡V Ges wWmPvR© †cÖmvi L~e Kg nqcv¤ú P‡j A_P cvwb D‡V bv ev Kg D‡V Ges wWmPvR© †cÖmvi L~e Kg nqcv¤ú P‡j A_P cvwb D‡V bv ev Kg D‡V Ges wWmPvR© †cÖmvi L~e Kg nqcv¤ú P‡j A_P cvwb D‡V bv ev Kg D‡V Ges wWmPvR© †cÖmvi L~e Kg nq
• cv¤ú Pvjy nIqvi wKQy¶Y ciB cvwb mieivn eÜ n‡q hvqcv¤ú Pvjy nIqvi wKQy¶Y ciB cvwb mieivn eÜ n‡q hvqcv¤ú Pvjy nIqvi wKQy¶Y ciB cvwb mieivn eÜ n‡q hvqcv¤ú Pvjy nIqvi wKQy¶Y ciB cvwb mieivn eÜ n‡q hvq
• cv¤ú Pvjbv Ki‡Z AwZwicv¤ú Pvjbv Ki‡Z AwZwicv¤ú Pvjbv Ki‡Z AwZwicv¤ú Pvjbv Ki‡Z AwZwi³ ³ ³ ³ kwkwkwkw³³³³i cÖ‡qvRb nq i cÖ‡qvRb nq i cÖ‡qvRb nq i cÖ‡qvRb nq (‡gvUi Kv‡i›U †ekx Uv‡b)(‡gvUi Kv‡i›U †ekx Uv‡b)(‡gvUi Kv‡i›U †ekx Uv‡b)(‡gvUi Kv‡i›U †ekx Uv‡b)
• cv¤ú †gvU‡ii K¤úb ev A¯^vfvweK kã AbyfyZ nqcv¤ú †gvU‡ii K¤úb ev A¯^vfvweK kã AbyfyZ nqcv¤ú †gvU‡ii K¤úb ev A¯^vfvweK kã AbyfyZ nqcv¤ú †gvU‡ii K¤úb ev A¯^vfvweK kã AbyfyZ nq
Slide 10
. ‰e`y‰e`y‰e`y‰e`y¨̈̈̈wZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶Y Kv‡R wbivcËv i¶vi RbwZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶Y Kv‡R wbivcËv i¶vi RbwZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶Y Kv‡R wbivcËv i¶vi RbwZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶Y Kv‡R wbivcËv i¶vi Rb¨̈̈̈ mZ©KZv mZ©KZv mZ©KZv mZ©KZv
Aej¤^b|Aej¤^b|Aej¤^b|Aej¤^b|
‡h †Kvb ˆe`y¨wZK miÄvgvw` cwiPvjbv I i¶Yv‡e¶‡Yi mgq wbivcËvi Rb¨wbæwjwLZ mZ©KZv Aej¤^b Acwinvh©¨ t
• ‰e`y¨wZK eZ©bxi †gBb myBP eÜ Kivi c~‡e© †Kvb ai‡bi i¶Yv‡e¶Y KvR Kiv hvB‡e bv |
• hZUzKz m¤¢e mKj ai‡Yi ˆe`y¨wZK KvR w`‡bi †ejvq Ges ch©vß Av‡jvi Dcw¯’wZ‡Z m¤úbœ Kwi‡Z nB‡e|
• mKj ai‡Yi ˆe`y¨wZK ‡givg‡Zi KvR h_vh_ KZ…c‡¶i Aby‡gv`b K…Z jvB‡mÝ cÖvß †jv‡Ki gva¨‡g Kwi‡Z nB‡e|
• ‰e`y¨wZK mK ev `~N©Ubv Gov‡bvi Rb¨ †h †Kvb ai‡Yi ˆe`y¨wZK KvR Kivi mgq Bbmy‡jUi RvZxq ivevi †M-ve, Kv‡Vi RyZv BZ¨vw` e¨envi Kwi‡Z nB‡e|
• ‰e`y¨wZK m‡K Avµvš— †h †Kvb e¨w³i ms¯úk© cwinvi Ki“b | hZ
ZvovZvwo m¤¢^e ˆe`y¨wZK cÖavb myBP‡K Ad Ki“b| ˆe`y¨wZK m‡K Avµvš— e¨w³‡K Kv‡Vi i‡Wi gZ †Kvb Bbmy‡jUi w`‡q gy³ Kiv DwPr|
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
KWASA Finance Revenue and Accounts Training
25 January 2011
Introduction:
Training is an integral component of any kind of development program. Rapid development of
the country is only possible through proper use of modem science and technology and this
necessitates human resource development through appropriate training. It actually involves
project preparation, appraisal, implementation and financing. For achieving efficiency in those
aspects of project implementation and management, training has been recognized as a major
input. It has been considered as an essential element for creating awareness, improving skills
and bringing a change in the attitude of the concerned staff members.
The training 'need' is the lack of something and a systematic-training program can overcome this
shortfall. Training is, thus, a process of increasing knowledge, developing skill and changing the
attitude of the human resources so as to enhance their job performance. To be effective, a
training program needs to be adjusted to the needs of individual employees. In order to design a
needs based training program, a training needs assessment is a pre-requisite. The program
consists of course design, development and implementation of the program according to the
terms of reference and specifications of the requesting client organization. It has been found
that the development of human resources - "human capital" - has been critical to long term
success of such programs. And by "human capital" it is not only meant for the implementing staff
but also the intended beneficiaries in the program areas.
Formal training in a classroom is one of the most expensive communication methods available. It
requires physical facilities, trainers, transportation and a great deal of time on the part of both
the trainees and the trainers. All of the training elements were made available by the KWASA
and the ADB TA project.
Training Approach
The training institutions in the developing countries of this region used to have, until the recent
past, a conventional approach to training characterized by a one way communication. The need
for change in favor of a participatory approach to training has increasingly been realized since
the 1980s. This approach emphasizes the increased use of methods and techniques which allow
greater interaction between the trainers and the trainees in the process of learning. The trainees
are generally called -participants' and the trainers are called facilitators, a gaming process thus
becomes a mutually shared activity. Efforts are being made to incorporate this approach into the
planning, management and evaluation of training programs on development activities
Objectives of the course:
The specific objectives of the training course will be as follows:
i. to help the staff members of the Accounts, Revenue, Store and Finance Sections to
acquire practical knowledge in record and repotting of financial transaction.
ii. to enable the staff members to acquire knowledge and understanding of the various
aspects of financial management, such as cash management, recording and reporting
of financial transactions of day today affairs.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
iii. to enable the staff members of accounts and financial, revenue and store section to
help management in improving organizational performance and advise management in
proper planning and appropriate decision making.
iv. to enable the staff members of accounts and finance, stores and revenue sections to
acquire knowledge and understanding of financial management budget, and budgetary
control, breakeven analysis in the context of practical problems of the present time.
v. to create awareness and interest among the staff members about the benefit of the
training on the proposed activities.
vi. to make the accounts keeping concept clear to the staff members of
vii. Accounts, Revenue, and Finance Section. And to give them knowledge on finance and
billing system.
viii. to increase knowledge, develop skills; bring changes in the attitudes of the trainees for
making improvement of the KWASA.
ix. to enhance managing and organizing, capability of the staff members.
x. to bring about changes in the attitude of the staff members so as to adopt innovative
ideas for improving the financial condition of KWASA.
Training Technique:
TNA - Set Training objectives - Design Programme
1. On the job training
2. Job instruction Training
3. Lectures and group discussions
4. Audiovisual Training
5. Training for team building and team work
6. Using time most effectively-Time management
7. Evaluating Training Efforts.
8. Motivational training to the staff members for better performance
Training Contents:
Brief training contents are as follows
- Accounting concepts, convention and principles
- Documentation and preparation of vouchers
- Double entry concepts and maintenance of accounts under double entry system
- Cash book, Bank book and bank reconciliation statement
- Preparation of financial statements
- Analysis and interpretation of financial statements
- Cash and fund flew analysis
- Concept of financial management
- Breakeven analysis
The detailed training course is as follows:
A. Books of Account and Forms and Forms required for maintaining Accounts of KWASA
1. Books of Accounts and Forms required for KWASA.
2. Other Records and Registers required for keeping accounts of KWASA.
3. Preparation of voucher & Journal Vouchers Trial Balance, Cash Planning, Cash book and Bank
book
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
B. Receipt and Payment Vouchers
1. Introduction to relevant Vouchers and Documents required in preparation of accounts.
2. Items of receipts
3. Preparation of Receipt Voucher and Recording (credit voucher)
4. Items of Payment
5. Preparation of Payment Voucher and Recording (Debit voucher)
6. Preparation of Journal Voucher
C. Banking of KWASA.
1. Types of Bank Accounts and their control
2. Collection of Bills through Banks
3. Bank Reconciliation Statement.
D. Writing of Cash Book
1. Posting of figures from Cash Book to General and Subsidiary Ledgers
E. General Ledger/ Control Ledger
1. Writing and Balancing of General Ledger
2. General Ledger and Trial Balance
F. Subsidiary Ledger
1. Types of Subsidiary Ledger
2. Writing and Balancing of Subsidiary Ledgers
G. Adjustment Entries
1. Types of Adjustment Entries
2. Adjustment through Journal Book
3. Adjustment through Journal Voucher
4. Adjustment of Advances to staff, contractors, suppliers etc.
5. T.A. Bills- Checking + Passing
H. Trial Balance
1. Types of Trial Balance
2. Preparation of different Types of Trial Balance
3. Preparation of Income Statement
I. Balance Sheet
1. Items of Assets and Liabilities
2. Preparation of Balance Sheet and related schedule of outstanding assets & liabilities.
J. Budget
1. Budget –Physical Targets in the Budget
2. Resource of Budget
3. Utilization of Budgeted Resources
4. Preparation of Budget and Budget Variance Report
K. Stock
1. Types of Stock Books and Preparation of Stock Books (Inventory Books).
2. Physical Verification of Stock.
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
L. Others
1. Accounting Ratios
2. Business Plan and Financial Management Improvement Plan
3. Field visit to Faridpur WASA to look into their Financial Management System and Accounts
Keeping System
Actual Training:
A total of 17 staff members were trained from the Accounting, Finance, Revenues and Store
Section of KWASA. All facilities required to conduct the training course was available at the
proposed place for training. They are conducting such training courses for their employees as a
routine matter. As such there was no problem for conducting training. The training programs
were supervised locally by the coordinator of training who was designated as such from one of
the trainers of the project. Moreover the Deputy Team Leader supervised all training programs as
routine work. Monitoring and evaluation has been done by the Deputy Team Leader for the
training program. The evaluation of trainees for the course has been done locally at the class
room by the project assistant of the project. The trainers of the training course have reported
the training activities to the Deputy Team Leader Who have also monitored the training program.
Training activities and the Program
i. Selection of participants as per eligibility of the participant for the course
ii. Designing the course curriculum including training plan, lesson plan/Sheet etc.
iii. Institutional/arrangements including availability of training facilities.
iv. Fund mobilization.
v. Selection of trainers and their availability.
vi. Implementation of the training course.
vii. Supervision of the program.
viii. Monitoring & evaluation of the program.
ix. Reporting.
x. Documentation of the training program.
Conclusion:
During the training, the trainees reported that they have learned many things in the areas of
accounts keeping, budgeting, provision of depreciation, bank reconciliation statement, cash
planning, cash budget, financial management , etc. Developed training materials and distributed
among the trainees before the beginning of the class. These materials would be very much
helpful to enrich their knowledge of keeping accounts.
Besides this accounts keeping, training on motivation, time management, team building and
team building and team work also given at the request of the trainees.
This training program would be useful and helpful to them in many ways. Their (trainees)
conception about Double Entry System, Debit, Credit etc, are now clear to them. They wanted to
express their gratefulness and thanks to the ADB TA project for arranging such a training program
for them.
Education level of the trainees was not equal. Some of them were much below the expectations
and as such their understanding was very low. These training programs is expected to increase
their understanding and thinking power However, the trainees were very much attentive and
participative. The trainees expressed their opinions that the duration of the course was very
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
short. They recommended that the duration of the future courses for Accounts keeping
should be increased to15 days.
Annex 1
Training Program for the Accountants of KWASA (From 13 Dec 2010 to 22 Dec 2010)
Date Time Topic Speaker
2011
13 January
16 January
18 January
20 January
25January
2.00-3.00
3.00-4.00
4.00-5.00
2.00-3.00
3.00-4.00
4.00-5.00
2.00-3.00
3.00-4.00
4.00-5.00
2.00-3.00
3.00-4.00
4.00-5.00
2.00-3.00
3.00-4.00
4.00-5.00
Books of Accounts and Forms required for
KWASA.
Other Records and Registers required for
keeping accounts of KWASA.
Introduction to relevant Vouchers and
Documents required in preparation of
accounts.
Preparation of Receipt and Payments Vouchers
and Recording.
Debit Voucher and Credit Voucher Journal
Voucher
Types of Bank Accounts and their control.
Collections of Bills through Banks.
Bank reconciliation Statement.
Preparation of Double column Cash book &
Petty Cash Book, Imprest System of Petty Cash
Book.
Posting of figures from Cash Book to General
and Subsidiary Ledgers.
Writing and Balancing of General Ledger
General Ledger and Trial Balance.
Writing and Balancing of Subsidiary Ledgers.
Types of Adjustment Entries.
Adjustment through Journal Book
Adjustment through Journal Voucher.
Adjustment of Advances to staff, contractors,
suppliers etc.
Types of Trial Balance.
Preparation of different Types of Trial Balance.
Preparation of Income Statement.
Items of Assets and Liabilities.
Preparation of Balance Sheet and related
ALL Classes will be
taken by Prof. Dr.
Md. Kayemuddin
Appendix 10 ANNEX B SUMMARY OF WORKSHOPS AND TECHNICAL MEETINGS
26
January
10-11
11-12
12-1.00pm
2.00-3.00
3.00-4.00
4.00-5.00
schedule of outstanding assets & liabilities
schedule.
Budget –Physical Targets in the Budget.
Resource of Budget.
Utilization of Budgeted Resources.
Preparation of Budget and Budget Variance
report.
Accounting Ratio.
Preparation of break-even and their uses.
Fund Flow, Cash planning & Budgeting.
Business Plan and Improving Financial
Management System.
List of Officers and Staff
Members of Finance,
Accounts and Revenue Sections
Sl.No. Name Designation
1 Khademul islam Commercial Manager
2 Jasmin Akter Accounts Officer
3 Biplob Kanti Das Revenue Officer
4 M.M. Iftakarul Islam Revenue Officer
5 M. M. Nadimul Islam Revenue Officer
6 Bhola Biswash Budget Officer
7 Dara Shiko Accountant
8 Kazi Ileash Hossain Account Assistant
9 Mizanur Rahman Cashier
10 Mobarok Ali Account Assistant
11 Gazi Saleh Habib Store keeper
12 Probin Kumar Biswash Assistant Store keeper
13 Abdul alim Account Assistant
14 Md. Golam jafri Revenue Supervisor
15 Sk. Abdul Motaleb Revenue Assistant
16 Mohim Kumar Joarder Revenue Assistant
17 S.M. Abdur Rashid Revenue Assistant
Appendix 10 ANNEX C EXISTING AND FUTURE NETWORK
1
Appendix-03
Existing Network
Appendix 10 ANNEX C EXISTING AND FUTURE NETWORK
2
Proposed Network
Appendix 10 ANNEX D DRAFT METER CONNECTION POLICY
KHULNA WATER SUPPLY AND
SEWERAGE AUTHORITY (KWASA)
CONNECTION POLICY FOR PIPED WATER SUPPLY
SERVICE CONNECTIONS
2010
PREPARING THE KHULNA WATER SUPPLY
ADB TA 7385 – BAN
Appendix 10 ANNEX D DRAFT METER CONNECTION POLICY
Contents 1. Introduction .............................................................................................................................................. 1
2. Types of connection .................................................................................................................................. 1
3 Application Procedure ............................................................................................................................... 2
4. Approval of Connection ............................................................................................................................ 3
5. Services to Low Income Customers .......................................................................................................... 3
6. Connection Charges .................................................................................................................................. 3
7. Installation and Technical Specifications .................................................................................................. 3
8. Inspection of customers Connection and Internal Water Supply ............................................................. 4
9. Change of Connection ............................................................................................................................... 4
10. Disconnection / Reconnection .............................................................................................................. 4
11. Illegal Connection .................................................................................................................................. 4
12. Termination of Service Contract ........................................................................................................... 5
13. KWASA’s Responsibility ......................................................................................................................... 5
14. Customer’s Responsibility ..................................................................................................................... 5
15. Metering ................................................................................................................................................ 5
16. Water Tariff ........................................................................................................................................... 6
17. Customer Relationships and Grievances ............................................................................................... 6
Appendix 10 ANNEX D DRAFT METER CONNECTION POLICY
1
House Connection Policy - KWASA
1. Introduction
KWASA’s long term policy is to provide connections to all customers including domestic institutions,
housing and commercial complexes, and institutional buildings within its service area. Newly developing
housing complexes where multiple households reside would probably require bulk water supply with
individual connections distributed subsequently. However, during the interim service improvement works
being carried out, it may not be technically feasible to carry out the connection program in an effective
manner.
Although the survey reports 27,917 domestic and 492 non-domestic users, only 7762 domestic and 134
non-domestic users are registered. The rest are unaccounted and unbilled household users resulting from
the practice of several household sharing a connection or else are illegal users. In the coming years, KWASA
will embark on six major programs, as follows:
1. Increase in number of households and connections from 2011 to 2017 as more volume of water is
made available from ongoing and future projects.
2. Registration of all illegal connections by 2014
3. Conversion billing per household by 2014
4. Metering of all connections to start by 2012 and be completed for all existing and new connections by
2016
5. Charging owners of private deep tubewells at an annual flat rate by 2012
6. Charging users of hand tubewells by 2013
The water demand for Khulna shows that the number of households served will increase from the existing
27,917 to 55,932. Similarly on domestic units will increase from 492 to 536. The number of domestic
connections is determined by dividing the number of households with the factor of 2.72 above resulting in
a total of 20,563 domestic connections by 2016. KWASA will also embark on a Metering Program starting
2012 and by the end of 2016 all connections will be metered.
A provision for 90,000 metered connections is included in the JICA FS costing. The demand forecast
indicates that connections will be around 140,000 following commissioning of the SWTP in 2017. It is
therefore imperative that a sound house connection policy be adopted by KWASA to install new
connections and monitor all service connections. The following sections of this brief document deal with
installing, monitoring, terminating and overall management approach for service connections.
2. Types of connection
KWASA has adopted a policy to supply water to its consumers, which are primarily domestic consumers.
Domestic consumers are to be supplied based on demand of water mainly through ½”, ¾” and 1”
connections. Other consumers including commercial, government and academic institutions are classified
as non-domestic consumers, who shall also be supplied through connections of varying sizes depending on
their demand.
In addition, low income communities (LIC) and slum areas will be provided water through communal water
points serving about 10 households. The communal water points will be metered for monitoring the level
of consumption.
Appendix 10 ANNEX D DRAFT METER CONNECTION POLICY
2
KWASA shall provide all service connections from secondary and tertiary distribution pipes / networks. No
connection shall be provided through the main transmission pipes. KWASA shall provide private connection
through following diameter connection pipeline based on the requirement of the customer and type of
customer:
½” (15mm)
¾” (20 mm)
1” (25 mm)
1 ½ “(40 mm)
2” (50 mm)
3” (80 mm)
4” (100 mm)
Standard connection to individual house-building shall be provided through a ½” and ¾” ferrule on service
pipelines. However, large diameter pipelines can be provided if a group of customers jointly apply for a
larger diameter connection such as in a housing complex and apartment buildings. Such customers will be
provided with bulk supply and the distribution collection of tariff from individual users and payment of
dues to KWASA shall be the responsibility of the owner / operator of such complexes. Larger diameter pipe
connections will only be provided to housing complexes, apartment buildings, institutional, commercial
and industrial customers, if the demand is justifiable. Approval for large connections shall be made by the
committee for such activities within KWASA.
3 Application Procedure
The customers residing within KWASA service area can apply to the respective KWASA Zonal / Branch
Office for a new connection or upgrading of an existing connection. A standard application form available
at KWASA offices will be required to be filled up with the following supporting documentary evidences:
Domestic Customer
• One photograph of the applicant
• Attested photocopy of the land ownership certificate
• Attested photocopy of the citizenship certificate of resident permits
• Attested photocopy of the approval of “building drawing” or “certificate of completion” or any
other proof of the premises issued by the municipal office (KCC)
• Sketch of the location of the premises showing distance from the distribution network, name of
the street, junction, etc.
• In case of joint ownership of the property, a written consent of the co-owners attested by the ward
office of KCC
Commercial, institutional and industrial Customers
• Attested photocopy of registration / approval from concerned government authority for the
activities of the applicant
• Attested photocopy of the approval of “building drawing” or “certificate of completion” or any
other proof of the premises issued by the municipal office (KCC)
• A brief description of the quantity and quality of water needed
• Sketch of the location of the premises showing distance from the distribution network, name of
the street, junction, etc.
Appendix 10 ANNEX D DRAFT METER CONNECTION POLICY
3
4. Approval of Connection
The following procedure shall be followed for the approval of a connection:
• Application for new water connection by customer / applicant (First visit)
• Assessment and screening of the application by the concerned Inspector / supervisor
• Inspection of the customer’s premises and technical feasibility assessment
• Approval of new connection by the Zonal Manager based on recommendation from field
supervisors’ report
• Second visit by the applicant for payment of connection fees, deposits and other approval
documents from Roads authorities for digging, etc.
• Connection of the tap, commissioning of the house connection and handover of customer service
cards and other details.
5. Services to Low Income Customers
The proposed service area under KWASA clearly indicates that there are several low-income communities
including slums where there is a need for supplying potable water to the urban poor. It has been observed
that most of such areas have very less space for having independent water supply connections. They also
may lack resources to pay for individual private connections. Therefore, in such cases it is imperative that
an approach needs to be developed to install common water points – community stand posts / hydrants /
standpipes. Such common facilities should also be metered and responsibility given to a local tap group for
operating and maintaining the unit and collecting monthly tariff. A standard set of designs suitable for
specific LIC or slum areas should be developed and numbers estimated for investment purposes.
6. Connection Charges
The following fees will be levied upon the applicant before connection is made:
• Application fee to cover the administrative and inspection costs of KWASA
• Deposit money; once connection is approved and a service contract between the customer and
KWASA is made.
• House connection fee (BF Tk. 7500) to be paid by the customer prior to installation works, which
shall be inclusive of tapping saddles, fittings, one length of pipe, water meter and related
accessories.
• Any additional length of pipe required to reach the premises from the distribution network shall be
the responsibility of the customer / house owner.
7. Installation and Technical Specifications
All materials and workmanship shall be according to KWASA standards. All fittings, saddle taps, ferrules,
stop cocks, water meter, etc. will be supplied by KWASA once the connection has been approved and fees
paid. Additional pipe length, as required, will be purchased by the customer either from KWASA or KWASA
approved vendors.
Laying and installation of house connection pipe and fixtures shall be the responsibility of KWASA, while
excavation and filling in accordance with the KWASA specifications shall be done by the customers
themselves under the supervision of KWASA personnel.
Appendix 10 ANNEX D DRAFT METER CONNECTION POLICY
4
8. Inspection of customers Connection and Internal Water Supply
KWASA reserves the right to enter into the premises of a customer by giving a notice to the concerned
person along with the reason thereof, provided that there is sufficient reason or basis to suspect that a
person is misusing the service or conducting unauthorized use of service. KWASA can terminate services to
customers or premises found guilty of misuse, non-payment or unauthorized use of service connections
after giving due to notice to the owner.
Reconnection will be made after the customer carries out the remedial measures identified to check the
misuse to the satisfaction of KWASA. Any additional cost incurred by KWASA in this regard including
reconnection charges (BD Tk. 3500) will be levied upon the customer by KWASA.
9. Change of Connection
The customer may apply for a change of connection from the previous location if there is justifiable reason
for doing so. The change of connection shall be made at the cost of the customer and the process shall be
similar to a new connection.
However, if a change in connection is warranted because of technical reasons like installation of a new
main, removal of spaghetti connections etc., and all costs associated with such a change will be borne by
KWASA.
10. Disconnection / Reconnection
A connection may be disconnected if misuse, change in use, wastage of water, pollution of water from the
connection, tampering with the meters, etc. is found by KWASA. Any cost incurred in rectifying the
problem by KWASA in this regard including reconnection charges (BD Tk. 3500), fines, etc. levied upon the
customer in accordance with the authority vested with KWASA will be recovered from the customer /
owner.
Similarly, if the water bills are not cleared for a period of three (3) months in a row, the connection may be
disconnected after issuing necessary warnings / notices with a seven (7) days notice to pay the dues.
Reconnection may be done after the payment of arrears or in the case of technical reasons (misuse) after
the remedial measures have been taken to the satisfaction of KWASA. However, the due reconnection fees
will be levied upon the customer.
11. Illegal Connection
Any connection made to any of the water lines owned and operated by KWASA without its knowledge and
approval shall be deemed illegal connection. Illegal connections may be of the following type:
• Connections not approved by KWASA
• All self re-connected connections, which were earlier disconnected by KWASA due to reasons
mentioned earlier under Section 10.
KWASA will charge a penalty covering the total dues for the period of illegal use and a surcharge of 50% to
the total amount. The minimum penalty in any case will be equivalent to 12 months of fixed monthly tariff
or average tariff for the connection type.
Appendix 10 ANNEX D DRAFT METER CONNECTION POLICY
5
The connection may be legalized after payment of the penalty and the regular fees for new connections, if
the connection is technically feasible and the connection meets the KWASA standards.
12. Termination of Service Contract
Termination of the service contract between KWASA and the customer shall be done if the customer
applies in writing and all dues to KWASA are cleared.
However, termination of services shall also be done by KWASA, if:
• Water supply to the customer is found to be technically unfeasible.
• Non-payment of dues including any penalties, fees and tariff, etc.
• Misuse of services including tampering with water meters and other assets of KWASA
A temporary disconnection may be provided for a fixed period of time based on a written request from the
customer for a valid reason such as the house building or premise not being used for a prolonged period or
transfer of home base of customer, etc.
13. KWASA’s Responsibility
• KWASA will supply water to the customers as per the prevailing rules and regulations. However,
KWASA will not be held responsible for disruption in supply due to any force majeure events
beyond its control.
• KWASA is committed to supply or distribute water in an equitable manner to all its customers.
• KWASA reserves the right to inspect pipe lines, valves, appurtenances, etc. and to recover costs
due to losses and damages occurring from the customers’ negligence or actions.
• In case recommended repair and maintenance works are not carried out by the customers even
after a written notice, KWASA will execute the works and the costs thus incurred shall be
recovered from the customer concerned.
• KWASA will strive to address all complaints and grievances of the customers at the earliest and
rectify problems to have a smooth supply.
14. Customer’s Responsibility
• All dues including monthly tariff, fees, fines, penalties, etc. shall be paid in accordance with the
rules and regulations of KWASA.
• Customers are responsible for the upkeep of the plumbing system within its premises to prevent
wastage, pollution and other such events.
• Customers shall ensure full access to the water meters to KWASA staff and its designated staff.
• The customer shall immediately inform KWASA if there is any change in the ownership of the
priority and change the service contract with KWASA is warranted.
• Customers can and should provide information to KWASA complaint window, if any leaks or
damages are observed, as a matter of civic responsibility.
15. Metering
It is KWASA policy to install appropriate water meters in all connections so that tariff for water use can be
charged according to the volumetric use. All house connection, commercial, institutional and other such
Appendix 10 ANNEX D DRAFT METER CONNECTION POLICY
6
premises with KWASA service connections will be provided with standard meters from KWASA duly
checked and calibrated. A lead seal shall be tagged on each meter to prevent any tampering.
Considering the wear and tear of all mechanical equipment including water meters, it is necessary to
replace them if such equipment reach their normal working life (six years) or develop a technical snag.
Water meters shall be replaced by KWASA authorized personnel, as part of the routine replacement
procedures when required. The cost of such replacement shall be borne by KWASA.
However, if replacement is warranted because of external factors including manipulation or tampering by
the customers amounting to vandalism then all costs associated with such a meter replacement shall be
borne by the customer themselves.
All repairing including recalibration of household meters shall be done by trained and authorized KWASA
personnel using approved and standard testing facilities at KWASA. Repair works related to manufacturing
defects, flow problems, erroneous measurements and readings, etc. not related to the customer’s
activities shall be carried out by KWASA.
16. Water Tariff
Water tariff approved and administered by KWASA shall be charged to the customers. KWASA encourages
volumetric tariff based on the monthly meter reading and although a lump sum monthly fee will be
administered to unmetered connection – eventually KWASA will bring them all under metered
connections. The water tariff may be revised from time to time depending upon the cost of production and
distribution of potable water to the consumers, but the customers will be notified of such changes in
advance for consultation and communal approval.
17. Customer Relationships and Grievances
A customer relationship and grievance handling cell will be established and operated in each of the five
zonal offices of KWASA and the KWASA head office. Such complaints shall be handled in a prompt manner.
The Zonal manager will be responsible for supervising the cell and the actions required to handle the
grievances from KWASA management will be duly forwarded by the Zonal Managers, if required. The
central customer relations and grievances unit at the KWASA head office shall be supervised by the Head of
the Customer Service section / division.
Appendix 10 ANNEX E CUSTOMER METER SPECIFICATION
KHULNA WATER SUPPLY AND
SEWERAGE AUTHORITY (KWASA)
TECHNICAL SPECIFICATIONS
HOUSEHOLD WATER METERS
2010
PREPARING THE KHULNA WATER SUPPLY
ADB TA 7385 – BAN
Appendix 10 ANNEX E CUSTOMER METER SPECIFICATION
1
1. General
The water meters shall be used to record discharge to consumers from distribution systems and
recorded data shall be used for billing purposes. The meters must be accurate, easily readable,
multi-jet turbine type, magnetically driven with vane wheel and supplied with accessories as
specified herein. The supplier shall furnish all goods and supplies and conduct performance testing
as specified herein.
2. Materials & Construction
The materials should be of new and of the kind and quantities specified herein and shall be to the
satisfaction of the purchaser, that the material is equal to or superior to in quality and performance
as specified hereinafter. All components shall be new, robust in design and fit for purpose. Materials
should not create toxic hazard, shall not support microbiological growth, and shall not give rise to
unpleasant taste, odor or discoloration in the water supply.
The main casing of the meter must be made of good quality non-corrosive brass alloy conforming to
DIN50930 or equivalent; other materials will not be accepted. Materials must have adequate
strength and durability to ensure a design life of no less than 10 years.
The measuring chamber must have very high precision finishing. All materials must be resistant to
internal and external corrosion. The spindle and bearings inside the hydraulic chamber shall be made
of polished stainless steel with tungsten carbide tip and sapphire. The internal pressure cup shall be
made of low-ferrous non-magnetic brass not exceeding 0.05% iron and must overlap the meter
body.
3. Standards
All goods and workmanship throughout should where applicable comply with the latest provisions of
ISO standards or codes of practices as specified herein. Meters must conform to ISO-4064. The meter
manufacturers must have ISO 9001:2000 certificate (latest version) and ISO-14001 certificate or EEC
Directive 75/33 (or where superceded 2004/22/EC) or equivalent AWWA standard and at least 10
(ten) years experience in manufacturing meters.
Meters shall be suitable for use with water having the following characteristics:
Fe up to 5mg/l
Mn up to lmg/1
Chloride up to 500mg/l
Conductivity up to lOGOuS/cm
pH 6.5 to 8.5
Alkalinity 220mg/l
Temperature 30°C
Free chlorine 25ppm.
Appendix 10 ANNEX E CUSTOMER METER SPECIFICATION
2
4. Marking:
The following information shall be marked in an indelible manner or cold stamped clearly on the
meter:
• Year of manufacture,
• Direction of flow,
• The name or trade name of the manufacturer and its trade mark,
• Individual serial number in one or two places (Digit height not less than 2 mm),
• Nominal flow rate in m3/h,
• Maximum working pressure in bars.
• Size in mm,
• The letters 'KWASA'.
5. Sizes
Meter sizes shall be 20mm, 25mm and 40mm.
6. Meter Flow Chamber
The flow chamber shall conform to ISO standards and be completely water tight from the register. It
shall include the following:
• All moving parts shall be self-lubricating.
• Calibrating screen for flow adjustment should be sealed by a cap nut and seal wire.
• The inlet shall have non- ferrous strainer.
7. Register
The register shall be super-dry and be hermetically sealed and water tight to IP68. The register shall
also be protected with antimagnetic shield whereby meter manipulation by any outside magnetic field
can not be possible. The reading dial shall be of straight reading type of 15 mm to 50 mm diameters.
The registers shall be straight reading totalizer with roller type mechanism recording at least 99, 999
m3 (The smallest graduation being 0.05 liter). A visible indicator of flow through the meter shall be
included. The meter recording device should be such that after recording full capacity it will
automatically revert to zero. The unit symbol m3 should be shown on the dial. The dial should have a
hinged hood for protection.
8. Connectors
The end-connectors of the meters shall be included with supply. The meter shall be threaded on both
ends with tail-pieces which shall conform to BS 21 for threaded-end meters. It shall also include slip-
nuts and rubber washers. Slip-nuts shall have a ring to accept seal wire and be attached to main case
of meter to prevent theft of water.
Accessories to be supplied with each meter:
(i) 2 Coupling tail pipes,
(ii) 2 Coupling tail nut.
(iii) 2 Coupling gasket.
Appendix 10 ANNEX E CUSTOMER METER SPECIFICATION
3
9. Performance requirements of water meters
The water meters shall have a proven performance record with measuring error according to ISO
4064 standard class-C. In transitional flow to maximum flow range measuring error should not
exceed ± 2% and in minimum flow to transitional flow range measuring error should not exceed +
5%. The following data are the specified flow rates for class C meter:
Meter Size(mm) Qmax (m3/hr) 5.00
20mm Qn (nvVhr) 2.5
Qt (m3/hr) 0.0375
Qmin (m3/hr) 0.025
Approval Class C 25mm Qmax (m
3/hr) 7.00
Qn (m3/hr) 3.5
Qt (m3/hr) 0.0525
Qmin (m3/hr) 0.035
Approval Class C 40mm Qmax (m
3/hr) 20.00
Qn(m3/hr) 10.00
Qt (mj/hr) 0.150
Qmin (m3/hr) 0.100
Approval Class C
10. Pressure:
The working pressure (maximum admissible pressure) shall not be less than 16 bar and shall conform
to the testing in accordance with ISO-4064. The meter shall be tested at 25 bar with no leakage. The
supplier shall provide test results to prove that the meters perform to the accuracy specified above.
11. Head loss
The loss of pressure through the meter must conform to ISO-4064. The pressure loss must not
exceed 0.2 bar at the nominal flow rate and 0.8 bar at the maximum flow rate.
12. Sealing
The meters shall be equipped with a tamper-proof device consisting of a water-proof synthetic
thread/seal wire and lead seal which must be broken in order to remove the register box and
calibrating cap nut.
13. Coatings
Where necessary metallic parts of the meters shall have corrosion resistant coating applied suitable
for a tropical humid environment. Materials shall be selected to have adequate mechanical,
chemical and electrochemical resistance against abrasion and corrosion. Materials in contact with
the water shall be non-toxic and shall not affect the quality of the water
14. Manuals
For each size of meter the supplier shall furnish 10 (ten) copies of complete meter manual booklets
for installation, operation and maintenance.
Appendix 10 ANNEX E CUSTOMER METER SPECIFICATION
4
15. Spares
The supplier shall supply 5% spare parts of each size (comprising meter register unit, vane wheel and
spindle) of the total number of meters to be supplied.
16. Tools
The supplier shall supply 50 (fifty) complete sets of standard tools with boxes for repair and
maintenance of the meter.
17. Packing:
The finished materials should be packed for worthy handling following international standard suitable
for tropical climate. Also should be protected from damage during handling and delivery. All loose
items should be carefully packaged to protect during storage. Each package should be carefully
marked as to contents, quantity and date of packaging in an indelible manner.
18. Warranty
Bidder shall provide 1 (one) year warranty on the meter against material defects, workmanship and
design defects. In case of loss of meter accuracy or any defect with the installed meter, the Supplier
shall replace the defective meter with new one within 15 (Fifteen) days of instruction from the
Purchaser against the above stated warranty condition.
19. Inspection and Testing Samples at Bid Stage
The bidder shall submit 2(two) nos. sample of each size along with the Bid. Physical verification and
performance tests of these samples maybe carried out prior to the evaluation of the Bid
documentation. The purchaser reserves the right to test each meter in regard to all metrological
aspects at the Purchaser's test bench (Dhaka WASA Meter Laboratory) and for material composition of
the meter body at the BUET Laboratory, Dhaka or laboratories of similar standard. These tests may
form part of the evaluation of the Bid. Failure to submit the samples along the Bid will result in rejection
of the Bid.
Pre-shipment physical inspection and performance tests shall be done at the Manufacturer's factory
during production in order to determine the conformity of the goods to the Technical Specifications.
The bidder must notify the Purchaser a minimum of three weeks prior to production and final assembly.
The Purchaser reserves the right for two (2) engineers to visit the Manufacturer's factory during the
production run. Any such visit shall be organized by the Supplier at the request of the Purchaser and
at the Supplier's own cost. During the visit, the Purchaser reserves the right to select a mutually
agreed number of meters of each size at random for testing at the Supplier's own facilities in the
presence of the Purchaser's representatives. A further set of meters of each size shall be selected at
random and returned to the Purchaser's premises for testing.
In the event of non-compliance of meter(s) to the specification either at the Manufacturer's or the
Purchaser's premises, the non compliant meter shall be tested at a mutually agreed location which
shall be Internationally registered, qualified and certified to carry out water meter testing. Non
compliance of the meter shall result in termination of the contract.
Alternatively, the purchaser and the manufacturer can appoint an internationally recognized quality
assurance agent to carry out quality assurance checks in conformity with the ISO procedures for
each supply lot. Such a process shall be carried out in the presence of representatives from the
purchaser and the manufacturer, if the parties so decide. Expenses related with this quality
assurance process shall be built into the Manufacturers bid.
Appendix 10 ANNEX F AUDITORS TERMS OF REFERENCE
TA7385/FR App 10 Annex F Auditors Terms of Reference Page 1 of 2
Terms of Reference (TOR) for the Appointment of the Auditor of KWASA
for the Fiscal Year 2008/09 and 2009/10
A. Scope of Work
The auditor will be responsible for conducting the audit of the KWASA financial statements for the fiscal
year ending 2009 and 2010. The auditor shall use appropriate audit procedures following lnternational
Standards of Auditing (lSAs) in performing the following:
1. Preparation of an inventory of fixed asset and Consumable Store
2. Valuation of all Fixed Assets (All Land & Building, Plant & machinery, Vehicles) of KWASA and setting up of
appropriate depreciation charges
3. Valuation of Accounts Receivable and setting up appropriate Allowance for Bad Debts
4. Examination and verification of the Cash Book and other records
5. Preparation and submission of Audit Report for the fiscal years 2008/2009 and 2009/2010
6. Preparation of annual accounts including Income Statement, Balance Sheet, and Cash Flow Statement.
In addition to the audit report the auditor shall prepare a separate management Report containing among
others the following:
1. Analysis of annual budget including (a) comments on actual expenditure in comparison with budget of
different sections / units / projects and analysis of variance and on (b) Comments and proposals on the
budgetary control system of KWASA
2. Comments and proposals on record keeping of expenditure and income
3. Comments and proposals on billing system of KWASA
4. Specific Comments and proposals on vouchers and books of accounts of KWASA
5. Guidelines for KWASA's Financial Plan based on Historical Evidence
6. Guidelines on all procurement procedure
7. Performance evaluation of different Sections / Units / Projects.
B. Reporting Requirements
The audit should be concluded with a meeting/ presentation as well as written reports to the KWASA as
follows:
1. Audit Report
The auditor is to report whether in his opinion and based on his examination of KWASA books and records,
proper books of accounts as required by law have been kept by the KWASA;
The auditor is to report whether or not the balance sheet and income and expenditure statement and cash
flow statements have been prepared in accordance to the requirements of the standard accounting rules and
regulations;
Appendix 10 ANNEX F AUDITORS TERMS OF REFERENCE
TA7385/FR App 10 Annex F Auditors Terms of Reference Page 2 of 2
2. Management Report covering comments and proposals on the accounting system, budgeting, billing,
procurement and internal control as discussed above
C. Schedule of Audit
The proposed time period for carrying out the audit will be 2 months from the date of signing the contract.
D. Proposal
The firm should prepare a Technical and a Financial proposal to be submitted, in separate envelopes, to the
Managing Director of KWASA at the address given below no later than 12 noon on 23rd
September 2010. The
technical proposal should include a detailed methodology and timeline for delivering the required outputs; the
financial proposal will be used as the basis for negotiation with the selected firm.
Mr Md Abdullah
Managing Director
Khulna Water Supply & Sewerage Authority
Khan-a-Sabur Road, Khulna
Bangladesh 1062-1
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
1
SOFTWARE DEVELOPMENT AGREEMENT
This Software Development Agreement ("Agreement") is made as of October 04, 2010 (the
"Effective Date") between
Khulna Water Supply & Sewerage Authority, 1062/1 KA, Khan-a-Sabur Road, Khulna-9100,
Bangladesh (hereinafter referred to as "Party-1")
And
Grameenphone IT Ltd., a company incorporated under the laws of Bangladesh, having registered
office at GP House, Bashundhara, Baridhara, Dhaka-1229 Bangladesh, (hereinafter referred to as
"Party-2").
WHEREAS
1. Party-1 intends to purchase software which is custom developed as per the need of the
Party-1.
2. Party-2 has submitted a proposal to Party-1 mentioning its skill and efficiency to develop
such software for the Party-1.
3. Being satisfied that the Party-2 possesses the necessary expertise to successfully develop
software as per its need, Party-1 has signed a Memorandum of Understanding (MOU) dated
…29th
September, 2010 with the Party-2.
4. Now the Parties intend to execute this agreement to list out the roles and responsibilities of
the Parties in consideration of the mutual covenants set forth herein, sufficiency of which is
acknowledged by each party and subject to the terms and conditions as set forth herein.
NOW THIS DEED OF AGREEMENT WITNESSETH AND IT IS HEREBY AGREED
AMONG THE PARTIES AS FOLLOWS:
1. DEFINITIONS.
(a) "Deliverables" means the deliverables Party-2 provides to Party-1 as described in this
Agreement, including, without limitation, the Software Deliverables.
(b) "Government Authority" means any governmental authority or court, tribunal, agency,
department, commission, arbitrator, board, bureau, or instrumentality of the Bangladesh or any
other country or territory, or domestic or foreign state, prefecture, province, commonwealth, city,
county, municipality, territory, protectorate or possession.
(c) "Law" means all laws, statutes, ordinances, codes, regulations and other pronouncements having
the effect of law of any Government Authority.
(d) "Services" means the development and consultancy services Party-2 provides to Party-1 as
listed in the Annexure A of this Agreement.
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
2
(e) "Software Deliverables" means the software described in this Agreement, including for all
software the following:
(i) Executables: At least two (2) copy of executables of the software deliverables on a computer-
readable magnetic medium.
(ii) Documentation. Two (2) copies of the user manual provided to Party-1 of the Software
Deliverables.
(f) "Initial Maintenance Period" means the period following satisfactory receipt of the deliverables
during which software and user support will be provided free of charge to Party-1 by Party-2.
(g) "Future Maintenance Period" means the period after completion of successful initial
maintenance period of the deliverables during which software and user support will be provided
with mutually agreed charge by Party-1 and Party-2.
2. SERVICES. Party-2 agrees to provide all the Services listed in the Annexure A (List of
Services, Deliverables and Specifications) of this Agreement, which is a part of this Agreement and
details the specifications of the Services. it is agreed by the Parties that within the validity period of
this Agreement, upon mutual agreement, the Parties may include new services and/or deliverables
along with its specification in the Annexure A by following Clause No16 (a) (Entire Agreement
and Amendment) of this Agreement. Fees for such new services and/or deliverables shall be
decided as per the mutual agreement between the Parties and shall be included in the Annexure B
by following Clause No16 (a) (Entire Agreement and Amendment) of this Agreement
3. PERSONNEL.
(a) Competence. Party-2 agrees to provide the Services through fully trained and competent
personnel or subcontractors having a skill level appropriate for the tasks assigned to them.
(b) Key Personnel and Project Managers. Below appears an initial designation of a project
manager for each party who is the principal point of contact between the parties for all matters
under this Agreement. Either party may designate a new project manager by written notice to the
other party. Party-1's project manager: [Md Miraj ul Haque Bashir,Senior Specialist] Party-2's
project manager: Mr Jaglul Haider, Deputy Managing Director for Engineering.
4. DELIVERABLES. Party-2 agrees to provide all Deliverables including the Software
Deliverables and maintenance deliverables according to the specifications mentioned in the
Annexure A of this Agreement.
5. DEADLINE. The Services and Deliverables will be provided within the Ninety (90) of days
after the Effective Date: 04-Oct-10. Party-1 shall provide such support and assistance as may be
reasonably required by Party-2. If Party-1 delays in providing any such support or assistance
required by Party-2, Party-2's deadline shall be extended by the time necessary for Party-1 to meet
these requirements.
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
3
6. OWNERSHIP, TITLE, AND RISK OF LOSS. Ownership of, title to, and risk of loss for the
Deliverables passes to Party-1 upon acceptance of the Deliverables by Party-1. However,
ownership, title and risk of loss for the Software Deliverables applies to the copy only and does not
extend to the intellectual property and other proprietary rights in the Software Deliverables.
7. ACCEPTANCE. The Service shall be deemed accepted and delivered once Party-1 signs the
‘Acceptance’ in writing. Upon completion of the Services required under the Scope, Party- 2 shall
request in writing to Party-1 (Notice of Completion) to sign the Acceptance within 10 (ten)
working days. Party-1 reserves the right to delay the Acceptance if it is not satisfied with the
performance and completion of the Service as per Contract documents. In such case, Party-1 shall
provide a written notice to Party- 2 describing the reasons for non-acceptance (Non-Acceptance
Notice). If Party-1 unreasonably delays in signing the Acceptance and does not provide any Non-
Acceptance Notice to Party- 2 within 10 days from the date of receipt of Notice of Completion
from Party- 2, at the completion of 10 (ten) working days, the Service shall be deemed accepted
and delivered and Party- 2 shall be entitled to issue Invoice and receive payment. For any
unreasonable delay, Party- 2 shall be entitled to claim interest at the rate of 1.0% per month on the
unpaid amount.
8. FEES. In consideration for Party-2's performance under this Agreement, Party-1 agrees to pay
the Party-2 the fees set forth in Annexure B (the “Payment Schedule”). The amounts payable to the
Party-2 set forth in the Payment Schedule are inclusive of VAT inclusive of income tax. If Party-
1is required to pay any taxes based on this Clause, Party-1shall pay such taxes with no reduction or
offset in the amounts payable to the Party-2 hereunder. In the event that new or increased VAT
(when compared to the taxes applicable at the date of this Agreement commencement) are levied by
the governmental authorities on any Deliverable, then such new or increased taxes shall be borne
by the Party-1.
9. INVOICES AND TAXES. Party-1 agrees to pay to Party-2 all fees owed under this Agreement
within thirty (30) days after the date of Party-1's receipt of a complete invoice. A complete invoice
is one that contains the invoice number, invoice date, description of the transaction, and total
invoice amount along with the VAT 11. If past due amounts owing from Party-1 are not paid within
thirty (30) days, the unpaid amount shall accrue interest at the rate of 1.0% per month.
10. INTELLECTUAL PROPERTY RIGHTS IN THE DELIVERABLES. Party-2 grants
Party-1 an irrevocable, perpetual, non-exclusive, worldwide, transferable, and sublicenseable
license in the Deliverables to permit Party-1 to exercise all intellectual property and proprietary
rights to the Deliverables. Party-1 may sublicense its Deliverables license to Party-1's third party
contractors for Party-1's internal business purposes.
11. WARRANTIES.
(a) Mutual Warranties. Each party represents, warrants and covenants to the other that:
(i) General. It: (a) is a company duly organized and validly existing and in good standing under the
Laws of its jurisdiction of organization; (b) is qualified or licensed to do business and in good
standing in every jurisdiction where qualification or licensing is required; and (c) has the corporate
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
4
power and authority to negotiate, execute, deliver and perform its obligations under this
Agreement.
(ii) Law Compliance. It complies with all applicable Laws.
(b) Warranties by Party-2. Party-2 represents, warrants and covenants to Party-1 that:
(i) Warranty Length. For a period of one year after receipt, the Services and Deliverables conform
to the requirements of this Agreement, are free from any defect in material and workmanship, and
are free of all liens, claims and encumbrances of any kind.
(ii) Infringement. The Services and Deliverables do not violate any patent, trade secret, or other
intellectual property or proprietary rights of any third party, and as of the Effective Date.
(iii) No Litigation. There is no actual or threatened litigation: (a) that affects its ability to comply
with this Agreement, or (b) concerning the Services or Deliverables.
(iv) Service Performance. The Services are performed in a professional and competent manner,
conforming to generally accepted standards applicable to services provided by nationally
recognized firms specializing in the area of Services provided under this Agreement. Each of the
individuals assigned to provide any Services under this Agreement have the proper skill, training,
and background to provide the Services.
(v) Malicious Code Representation. All Software Deliverables are free of any "time-bombs,"
"worms," "viruses," "Trojan horses," "protect codes," "data destruct keys" or other programming
devices or code that might, or might be used to, access, modify, delete, damage, deactivate or
disable any Software Deliverables or other software, computer hardware, or data.
(c) Disclaimer. EXCEPT AS EXPRESSLY STATED IN THIS AGREEMENT, PARTY-1 AND
PARTY-2 EACH MAKE NO REPRESENTATIONS AND EXTEND NO WARRANTIES OR
COVENANTS OF ANY KIND, EITHER EXPRESS OR IMPLIED, INCLUDING, WITHOUT
LIMITATION, ANY WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A
PARTICULAR PURPOSE.
12. LIMITATION OF LIABILITY. THIS LIMITATION OF LIABILITY PROVISION
APPLIES IN THE AGGREGATE AND NOT ON A PER CLAIM BASIS, WHETHER ANY
DAMAGES ARE CHARACTERIZED IN TORT, NEGLIGENCE, CONTRACT, OR OTHER
THEORY OF LIABILITY, REGARDLESS OF WHETHER A PARTY HAS BEEN ADVISED
OF THE POSSIBILITY OF OR COULD HAVE FORESEEN ANY DAMAGES, AND
IRRESPECTIVE OF ANY FAILURE OF ESSENTIAL PURPOSE OF A LIMITED REMEDY.
THIS LIMITATION OF LIABILITY PROVISION DOES NOT LIMIT A PARTY'S LIABILITY
FOR GROSS NEGLIGENCE, INDEMNIFICATION OBLIGATIONS, BREACH OF
CONFIDENTIALITY REQUIREMENTS, INTENTIONAL MISCONDUCT, INTENTIONAL
TORTS AND INTENTIONAL VIOLATIONS OF LAW. NEITHER PARTY IS LIABLE TO THE
OTHER OR ANY THIRD PARTY UNDER THIS AGREEMENT FOR ANY INDIRECT,
SPECIAL, INCIDENTAL, PUNITIVE, EXEMPLARY, OR CONSEQUENTIAL DAMAGES
ARISING OUT OF OR RESULTING FROM THIS AGREEMENT. EACH PARTY'S
LIABILITY SHALL NOT EXCEED THE AMOUNTS PAID, DUE AND PAYABLE UNDER
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
5
THIS AGREEMENT.
13. INDEMNIFICATION. If a third party makes a claim against either Party-1 or Party-2
(“Recipient” which may refer to Party-1 or Party-2 depending upon which party received the
Material), that any Deliverable, information, design, specification, instruction, software, data, or
material (“Material”) furnished by either Party-1 or Party-2 (“Provider” which may refer to Party-1
or Party-2 depending on which party provided the Material), and used by the Recipient infringes its
intellectual property rights, the Provider, at its sole cost and expense, will defend the Recipient
against the claim and indemnify the Recipient from the damages, liabilities, costs and expenses
awarded by the court to the third party claiming infringement or the settlement agreed to by the
Provider, if the Recipient does the following:
a) notifies the Provider promptly in writing, not later than 30 days after the Recipient
receives notice of the claim (or sooner if required by applicable law);
b) gives the Provider sole control of the defense and any settlement negotiations; and
c) gives the Provider the information, authority, and assistance the Provider needs to
defend against or settle the claim.
If the Provider believes or it is determined that any of the Material may have violated a third party’s
intellectual property rights, the Provider may choose to either modify the Material to be non-
infringing (while substantially preserving its utility or functionality) or obtain a license to allow for
continued use, or if these alternatives are not commercially reasonable, the Provider may end the
license for, and require return of, the applicable Material and refund any fees the Recipient may
have paid to the other party for the Material. If Party-1 is the Provider and such return materially
affects Party-2’s ability to meet its obligations under the relevant order, then Party-2 may, at its
option and upon 30 days prior written notice, terminate whole or relevant part of this Agreement.
The Provider will not indemnify the Recipient if the Recipient alters the Material or uses it outside
the scope of use identified in the Provider’s user documentation or if the Recipient uses a version of
the Materials which has been superseded, if the infringement claim could have been avoided by
using an unaltered current version of the Material which was provided to the Recipient. The
Provider will not indemnify the Recipient to the extent that an infringement claim is based upon
any information, design, specification, instruction, software, data, or material not furnished by the
Provider. Party-2 will not indemnify Party-1 to the extent that an infringement claim is based upon
the combination of any Material with any products or services not provided by Party-2. Party-2 will
not indemnify Party-1 for infringement caused by the actions of Party-1 against any third party if
the Deliverables of the Party-2 delivered to you and used in accordance with the terms of this
agreement would not otherwise infringe any third party intellectual property rights. This section
provides the parties’ exclusive remedy for any infringement claims or damages.
14. TERM AND TERMINATION.
(a) Term. The term of this Agreement (together with any renewals, the "Term") begins on the
Effective Date and expires One 1 year. Any renewal term shall be mutually agreed to by the parties
in writing.
(b) Survival. The following captioned sections survive any termination, expiration or non-renewal
of this Agreement: "Disclaimer", "Limitation of Liability", "Indemnification", "Survival", and
"General", as well as any other provisions expressly stating that they are perpetual or survive this
Agreement.
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
6
(c) Termination for Insolvency. If either party is adjudged insolvent or bankrupt, or upon the
institution of any proceedings by it seeking relief, reorganization or arrangement under any Laws
relating to insolvency, or if an involuntary petition in bankruptcy is filed against a party and the
petition is not discharged within sixty (60) days after filing, or upon any assignment for the benefit
of a party's creditors, or upon the appointment of a receiver, liquidator or trustee of any of a party's
assets, or upon the liquidation, dissolution or winding up of its business (each, an "Event of
Bankruptcy"), then the party affected by any Event of Bankruptcy must immediately give notice of
the Event of Bankruptcy to the other party, and the other party may terminate this Agreement by
notice to the affected party.
(d) Termination for Breach. If either party breaches any provision contained in this Agreement, or
the breach is not cured within thirty (30) days after the breaching party receives notice of the breach
from the non-breaching party, the non-breaching party may then deliver a second notice to the
breaching party immediately terminating this Agreement.
15. FORCE MAJEURE. Any failure or delay by a party in the performance of its obligations
under this Agreement is not a default or breach of the Agreement or a ground for termination under
this Agreement to the extent the failure or delay is due to elements of nature or acts of God, acts of
war, terrorism, riots, revolutions, or strikes or other factor beyond the reasonable control of a party
(each, a "Force Majeure Event"). The party failing or delaying due to a Force Majeure Event agrees
to give notice to the other party which describes the Force Majeure Event and includes a good faith
estimate as to the impact of the Force Majeure Event upon its responsibilities under this
Agreement, including, but not limited to, any scheduling changes. However, should any failure to
perform or delay in performance due to a Force Majeure Event last longer than thirty (30) days, or
should three (3) Force Majeure Events apply to the performance of a party during any calendar
year, the party not subject to the Force Majeure Event may terminate this Agreement by notice to
the party subject to the Force Majeure Event.
16. GENERAL.
(a) Entire Agreement and Amendments. This Agreement is the entire agreement between the
parties and supersedes all earlier and simultaneous agreements regarding the subject matter,
including, without limitation, any invoices, business forms, purchase orders, proposals or
quotations. All the annexes constitute an integral part of this Agreement. This Agreement
may be amended only in a written document, signed by both parties.
(b) Independent Contractors, Third Party Beneficiaries, and Subcontractors. The parties
acknowledge that they are independent contractors under this Agreement, and except if
expressly stated otherwise, none of the parties, nor any of their employees or agents, has the
power or authority to bind or obligate another party. Except if expressly stated, no third
party is a beneficiary of this Agreement. Party-1 may not subcontract any obligation under
this Agreement without Party-2's prior written consent. Party-2 can subcontract without
Party-1's consent. Each party is responsible for its subcontractors' compliance with and
breach of this Agreement as if the subcontractors' acts and omissions were the party's own.
(c) Governing Law and Forum. All claims regarding this Agreement are governed by and
construed in accordance with the Laws of Bangladesh. Any controversy or claim arising out
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
7
of or relating to this Agreement or its breach shall only be settled in accordance with the
following sequence of dispute resolution procedures. First, authorized persons of the
Parties must meet to attempt to resolve their differences based upon advance written
submissions to each other. Second, if the parties are unable to resolve their issues, all
disputes whatever or claims arising out of or relating to this contract, or the breach,
terminating or invalidity thereof, shall be settled by the Arbitral Tribunal comprising of
three arbitrators in accordance with Arbitration Act, 2001 of Bangladesh. The place of
arbitration shall be Dhaka, Bangladesh. The language to be used in the arbitral proceedings
shall be English.
(d) Assignment. This Agreement binds and inures to the benefit of the parties' successors and
assigns. This Agreement is not assignable, delegable, sublicenseable or otherwise
transferable by any party in whole or in part without the prior written consent of the other
party (or parties). Any transfer, assignment, delegation or sublicense by a party without
such prior written consent is invalid. However, any party may assign this Agreement to a
third party purchasing: (a) majority control of the party's equity shares; or (b) all or
substantially all of either (i) a party's assets or (ii) the assets of the party's relevant business
unit under this Agreement.
(e) No Waivers, Cumulative Remedies. A party's failure to insist upon strict performance of
any provision of this Agreement is not a waiver of any of its rights under this Agreement.
Except if expressly stated otherwise, all remedies under this Agreement, at Law or in
equity, are cumulative and nonexclusive.
(f) Severability. If any portion of this Agreement is held to be unenforceable, the
unenforceable portion must be construed as nearly as possible to reflect the original intent
of the parties, the remaining portions remain in full force and effect, and the unenforceable
portion remains enforceable in all other contexts and jurisdictions.
(g) Notices. All notices, including notices of address changes, under this Agreement must be
sent by registered or certified mail or by overnight commercial delivery to the address set
forth in this Agreement by each party.
(h) Captions and Plural Terms. All captions are for purposes of convenience only and are not
to be used in interpretation or enforcement of this Agreement. Terms defined in the
singular have the same meaning in the plural and vice versa.
(i) Non Hire Non Solicitation. The Parties agree that during the period that this agreement is
in force, including extensions or modifications thereto, and for an additional 24 months
following this period, neither Party will directly or indirectly recruit, or solicit employees of
other Party without the prior written approval of the other Party. In case of non-compliance
with this clause, the innocent Party will be entitled to obtain an amount equivalent to 6 (six)
months’ salary of the recruited/ solicited employee or employees from the Infringing party.
Notwithstanding any other provision of this agreement, this clause shall survive termination
of this Agreement.
IN WITNESS WHEREOF, the parties execute this Agreement as of the Effective Date. Each
person who signs this Agreement below represents that such person is fully authorized to sign
this Agreement on behalf of the applicable party.
FOR AND BEHALF OF: FOR AND BEHALF OF:
KHULNA WASA Grameenphone IT Ltd
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
8
Name: Md Abdullah, P Eng.MBA Name: Kazi N. Islam
Designation: Managing Director Designation: Chief Executive Officer
In Presence of the following witness: In Presence of the following witness:
1. 1.
Name: Engr. S.M.Jaglul Haider Name: Dan Gallegos
Designation:Deputy Managing Director Designation: Director,
Strategy & Business Development
2. 2.
Name: Zahangir Alam Name: A.K.M Fahmedul Haque
Designation: Deputy Project Manager Designation: Head of Proposal Management
Deputy General Manager
Annexure A List of Services, Deliverables and Specifications for Utility Billing Software
Annexure B List of Services, Deliverables and Specifications for Accounting Software
Annexure C Payment Schedules
Appendix 10 ANNEX
Annexure A – List of Services, Deliverables and
Understanding of the Requirement: Khulna WASA (Khulna Water supply And Sewerage Authority) established on 2nd March 2008.
Specific objective of KWASA:-
• Construction, operation and maintenance of necessary
domestic, industrial and commercial purposes
• Construction, operation and maintenance of sewerage system
• Construction, operation and maintenance of drainage system
Implementation and execution of Water utility Billing so
achieving above visions. The developed software should be capable of followings:
Figure1: Modules of Utility Billing Software
Our Approach to meet Project objective
After going through the scope of work and discussions with KWASA team we have
understood that KWASA wants to a solution which will bring following benefits:
• Enhance Citizen Service
• Facilitate Real time Decision Making
• Improves Operational efficiency
• Easy to operate
• Maximize Revenue
• Dynamic Rate/surcharge/tariff management etc.
GPIT will leverage its expertise by providing high quality billing functionality for
managing tariffs/rates, conduct bill runs and proper reporting and invoices as an
integrated solution designed specifically for the unique needs of Khulna WASA.
Our focus area for the designing solutions;
Master Data Management
Bill Generation
Reconciliation
Reporting
ANNEX G GRAMEENPHONE CONTRACT
9
List of Services, Deliverables and Specifications for Utility Billing Software
Khulna WASA (Khulna Water supply And Sewerage Authority) established on 2nd March 2008.
Construction, operation and maintenance of necessary infrastructure for water supply for
domestic, industrial and commercial purposes
Construction, operation and maintenance of sewerage system
Construction, operation and maintenance of drainage system
Implementation and execution of Water utility Billing software will be an effective enabler in
achieving above visions. The developed software should be capable of followings:
Figure1: Modules of Utility Billing Software
Our Approach to meet Project objective:
After going through the scope of work and discussions with KWASA team we have
understood that KWASA wants to a solution which will bring following benefits:
Enhance Citizen Service
Facilitate Real time Decision Making
Improves Operational efficiency
Dynamic Rate/surcharge/tariff management etc.
GPIT will leverage its expertise by providing high quality billing functionality for
managing tariffs/rates, conduct bill runs and proper reporting and invoices as an
lution designed specifically for the unique needs of Khulna WASA.
Our focus area for the designing solutions;
•Customer Information Management
•Bank Information Management
•Municipality Information Management
Master Data Management
•Bill generation
•Advanced Bill generation (Customized)
•Due alert
•Invoicing & Deposit
Bill Generation
•Collection Information
•Reconciliation & proactive auditingReconciliation
•Capable of generating static & Dynamic reports
•Support for auditing
•Provide output to different system as per requirements
for Utility Billing Software
Khulna WASA (Khulna Water supply And Sewerage Authority) established on 2nd March 2008.
infrastructure for water supply for
ftware will be an effective enabler in
After going through the scope of work and discussions with KWASA team we have
understood that KWASA wants to a solution which will bring following benefits:
GPIT will leverage its expertise by providing high quality billing functionality for
managing tariffs/rates, conduct bill runs and proper reporting and invoices as an
lution designed specifically for the unique needs of Khulna WASA.
Provide output to different system as per requirements
Appendix 10 ANNEX
Figure: Focus on designing the solution
User Friendly
• Easy to implement
• Easy to Operate
• Easy to Monitor
ANNEX G GRAMEENPHONE CONTRACT
10
Figure: Focus on designing the solution
Easy to Monitor
Secured
• Ensure all level of Security
• Proper Access Management
• Secure data management
Flexibility
• Openness for expansion and integration
• Ensure availability
• Efficient Change Management
Flexibility
Openness for expansion and integration
Ensure availability
Efficient Change Management
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
11
Scope of Work:
Following is the Scope of work for this engagement:
Scope of Work Modules & Services
Software
Development
Master Data Management:
Maintenance Customer Lifecycle from creation to till deactivation and
reactivation with demographic and personal information’s
Customer Type Entry & Edition
Bank Information’s Entry & Edition
User Management
Rate/Tariff Management (Customer Type and Diameter wise)
Address/Location Information and edition
Meter Information and Edition
Customer Activation/Deactivation
System Administration
Bill Generation:
Customer wise Bill Entry
Different types of bill generation
Bill posting
Reconciliation:
Input Reconciliation for Bill Generation
Invoice Reconciliation
Collection Reconciliation
Reporting
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
12
Customer Register
Active/Deactivate/Cancel Customers Information
Dia and Customer type wise report
Arrear Bill reporting
New Customer Reports
Advance Bill payment Report
Bank Information Report
Bank Collection Report
Location Report
Single or all Bill Generation report
Part Arrear Bill Generation Report
Testing &
Implementation
Unit Testing
User Acceptance Testing
Deployment
Training Functional Training
Technical Training
Maintenance Operational Maintenance
Out of Scope:
1. Legacy System modification if any
2. Data Entry in Live Systems
3. Basic Computer Training
Note: For detail functionalities please go through chapter 4.
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
13
Roles & Responsibility:
Following is the Roles & Responsibility for this project between GPIT & KWASA:
GP IT KWASA
Application Development & Deployment Data Entry, Report Generation,
Hardware Readiness
Test case preparation & Facilitate
Testing
Do the Test and approve the test
Training Maintenance, Regular Backup &
Infrastructure Administration
2nd Level Support 1st Level Support to KWASA user
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
14
Risks and Mitigation Plan: Given in the table below are a few of the critical risks that GP IT has identified, with Action
Plans to mitigate them. During the course of Project Planning, these can be looked at in
greater detail.
Risk Intensity Mitigation Plan
Change in project
scope and
definition
High • The scope of the implementation project has to be
frozen before the start of the project.
• Any change in scope after the start of the project
will be addressed through Change Control
Procedures and may impact the project time and
cost.
• GP IT would raise all scope change requests from
users to the Steering Committee before accepting
such changes.
Delay in
providing inputs
or completing
activities for
which the KWASA
is responsible.
High • KWASA to identify personnel to work on the project
- full-time personnel on the project should be
relieved of non-project related responsibilities.
• GP IT to assign responsibilities and timelines to
KWASA designated personnel and help them
understand what is required of them.
• Commitment from the KWASA Top Management is
an important check against delays for their
activities.
Adaptability to
change
Medium • KWASA top management to communicate their
commitment to the project to all levels.
• KWASA to formulate a Change Management
Strategy through planned communication and user
training.
• GP IT to assist KWASA in change management by
providing inputs on progress, clarifications on
functionality and post-production support.
Delay in
providing
Hardware
Medium • KWASA to ensure that the Hardware is available as
per the Project Plan for Implementation.
Availability of
user SMEs
High • To plan for availability of user SMEs as required in
the resource plan. Mobilization / Year end pressures
as well as vacation have to be anticipated and
planned accordingly
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
15
Proposed Project Team & Structure
GP IT Proposes below team structure for the implementation.
Role Title Description of the role
Project Manager /
Architect
• Provide direction to GP IT team for this engagement
• Identify overall plans and requirements from KWASA for
people, technical skill areas, resources, etc.
• Resolve any outstanding issues
• Define project plan. Work closely with KWASA project
manager to identify participants for workshops
• Work closely with KWASA to enable seamless translation
of requirements for development of overall architecture
• Recommend best practices and provide technical inputs for
implementation plan of the same
• Report project status to KWASA project manager
Functional
Consultant
• Provide Functional Consultancy
• Understand information flow/source data structures/data
quality
• Participate in project reviews
• Configuration and implementation
Trainers • Train KWASA resources on functional & Technical Part
Developer • Responsible for developing the solution as per design and
requirements
QA Engineers • Responsible for total Quality Assurance
• User Acceptance
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
16
Expected Team Structure from KWASA:
Role Title Description of the role
KWASA Project
Manager
(100% During
Requirement
Phase )/ Rest
50%
• Coordinate all the project related activities from KWASA
side
• Responsible for Risk Management and Mitigation during
the project
• One point of contact for GP IT team to interact with the
business users
• Conduct ongoing reviews with GP IT team focusing on
project execution related issues
• Ensure infrastructure for GP IT team
• Facilitate issue resolution - scope of work, definition of
requirements or deliverables, and acceptance of final
product
• Work closely with GP IT team in resolving and
troubleshooting any conflicts that arise
KWASA subject
matter experts
(100% During
Entire
Implementation
Phase )
• Provide planning requirements
• Provide environment for implementing the solution
• Map requirements to source data and provide gap analysis
• UAT
• Support in integration and implementation as when
required
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
17
Assumptions:
Grameenphone IT Ltd. has been working closely with this project, and bellow is the
assumption and constrains that has been identified.
Business Discovery Sessions:
• As part of the business discovery sessions, GP IT would like to meet the identified
SPOC or Project Manager of KWASA who will share the business requirements for the
implementation.
• Minutes of Meeting to be signed for each and every business meetings conducted by GP
IT. These would be ‘deemed signed’ if there are no feedback received within 2 working
days
• KWASA and GP IT will together prepare business requirement that needs to be
captured for each entity & attribute.
Process Oriented assumptions
• Implementation is based out of Khulna at Head Quarters of KWASA.
• KWASA team, HW vendors and their partners shall be taking care of Installation of
Hardware, Operating System and Web Server Configurations.
• With the help of GP IT, KWASA IT team shall be taking care of installation and
Configuration for Utility Billing Software in production environments.
• UAT participants from the KWASA are available for the Testing
• All the required network ports would be opened on request
• Required KWASA testing team to be constituted
• Availability of Application and web servers to run the Accounting Software
• Required office space, computers, equipments, passes etc for GPIT are available
• Implementation assumed to be at Head Quarters of KWASA.
• All data would be captured from the Live source system environment or excel sheets,
no data would be loaded from tapes & other media devices
• GP IT consultants will be deployed at both Onsite and Offshore
• Change in scope would be handled through CRs
• GP IT assumes that all process specific formula will be provided by KWASA.
Project
• KWASA would provide round the clock access to GP IT personnel to KWASA
development & test environment.
• KWASA will provide VPN connectivity to GPIT team for remote access as and when
required
• The implementation team will be based out of a single location.
• KWASA would provide GP IT development team with Printer and scanner access for
onsite resources
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
18
3.5. Project Management:
Project management is the application of knowledge, skills, tools and techniques to a broad
range of activities in order to meet the requirements of the particular project. A project is a
temporary endeavor undertaken to achieve a particular aim.
GP IT’s Project Management is composed of several different types of activities such as:
� Planning the work
� Assessing and mitigating risk
� Estimating resources
� Organizing the work
� Acquiring human and material resources
� Assigning tasks
� Directing activities
� Controlling project execution
� Reporting progress
� Analyzing the results based on the facts achieved
� Analysis & Design
� Project control variables
GP IT’s Project Management tries to gain control over five variables:
Time - The amount of time required to complete the project. Typically broken down for
analytical purposes into the time required to complete the components of the project, which is
then further broken down into the time required to complete each task contributing to the
completion of each component.
Cost - Calculated from the time variable. Cost to develop an internal project is time multiplied
by the cost of the team members involved. When hiring an independent consultant for a
project, cost will typically be determined by the consultant or firm's hourly rate multiplied by
an estimated time to complete.
Quality - The amount of time put into individual tasks determines the overall quality of the
project. Some tasks may require a given amount of time to complete adequately, but given
more time could be completed exceptionally. Over the course of a large project, quality can
have a significant impact on time and cost (or vice versa).
Scope - Requirements specified for the end result. The overall definition of what the project is
supposed to accomplish, and a specific description of what the end result should be or
accomplish.
Risk - Potential points of failure. Most risks or potential failures can be overcome or resolved,
given enough time and resources. According to some definitions, risk can also be negative,
meaning that there is an opportunity to e.g. complete the project faster than expected.
GP IT’s project management models adopt a KWASA centric approach to the entire
engagement. These include workflow and project flow determination and domain and technical
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
19
teaming and help in proper requirements capture, regular project reporting and monitoring
and an efficient feedback mechanism for project progress
GP IT’s project engagement processes are customized to address specific project needs for
varying projects, right from service projects to maintenance projects to development and
conversion projects. This ensures that we can manage projects with different and evolving
needs seamlessly
GP IT employs several project management tools for smooth delivery of projects. GP IT’s
process documentation and consulting tools support multiple lifecycle models and ensure
everything on record. GP IT’s visibility tools help monitor projects on a real time basis and
ensure that customers are never out of touch
Process documentation tools
• Web enabled process documentation
• Supports multiple life-cycle models
• Process release updates to practitioners
• Employee participation through a PCR board
• Process consulting tools
• Tools identification and training
• Audits and assessments
• Automation
• Project Management
• Software Engineering
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
20
Management visibility tools
• Project kick-off reviews
• Project status reviews
• Post-mortem reviews
• Quarterly management reviews
• Clearly defined responsibilities and authorities
Customer visibility tools
• Customer extranets for project visibility
• Secure relationship portal for information needs
• Project dashboard for up-to-date information
• Built-in workflow and collaborative features
Our business continuity planning approach ensures un-interrupted project executions. GP IT
Limited has a robust infrastructure, an intensely managed communication network and a well-
implemented physical security policy to guard the integrity of our premises and a clear risk
mitigation state.
Project Meetings, Reporting and Review mechanisms:
The following project meetings will be held for proper co-ordination in successful execution of
the project.
• Steering Committee Meeting – The meeting with the Steering Committee (SC) will
be held once a month. The Project Manager will report the progress of the project to
the SC.
• Project Team Meeting – The Project Team Meeting will be held every week. This
meeting would include the GP IT Project Manager, Technical Leads, KWASA User
Manger and IT Project Manager.
• Module Team Meetings -- Module Team Meetings will be held twice a week. The
meetings would include GP IT Module Lead, Developers and Test Engineers.
• GP IT Project Manager may convene an extraordinary SC meeting if some unresolved
issues in the project need immediate escalation.
• The minutes of each meeting along with the action points, date and responsibility of
closure will be recorded and circulated at the end of each meeting. The problems
identified during these meetings will be escalated, if required.
• During these team meetings the following will be tracked:
a. Action points of previous team meetings
b. Technical issues
c. Project schedule
d. Changes in project resource requirements
e. Changes in project commitments
f. Critical dependencies within the project and with the support groups
g. Progress of the project with respect to the effort, size, productivity and other
commitments
h. Project risks
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
21
i. Any configuration management related issues like pending Change Requests,
changes to baseline library, etc.
Status Reporting
This report will be sent on every Monday during the entire duration of the project. In addition
to the weekly status reporting GP IT also, conduct Milestone reviews involving appropriate
KWASA personnel. Some of the reporting activities are mentioned below:
GP IT will follow the following reporting schedules:
Type of
reporting
Schedule Details
Status
Reporting
Weekly This will have a detailed Project report for the 15-day period. It
will consist of the Project schedule, Milestones achieved,
Activities performed for the fortnight, issues / concerns. The
status report will be initiated by GP IT Project Manager by
email and sent to KWASA IT Project Manager
Escalation
reporting
Fortnightl
y
This will be a report, which will highlight concern areas with
respect to technology, user, and project. It is expected that
KWASA will act on this escalation report with due diligence and
address the issues within 5 days to avoid schedule overruns
Conference
Calls
Fortnightl
y
Fortnightly conference call will be initiated by GP IT from the
station where the Project Manager is situated. The conference
call will be for 1 hour. All the team members from GP IT will be
present in this call & from KWASA; the Project Sponsor is
expected to participate.
Project Monitoring: This project would be tracked and monitored for the following:
• Schedule
• Effort
• Project activities
• Risks – Identification, prioritization and tracking throughout the project lifecycle
• Critical path, identified in the schedule
• Identification of potential overruns and under runs and appropriate corrective action
Review & Inspection Mechanisms
The purpose of this procedure is to ensure that the items that are reviewed or inspected are
complete, correct and fit for use. The review of document (or code) is done to evaluate that
the requirements are met and to identify the problems. It is done once the documents
prepared are complete and ready for review or once the code is free of compilation errors.
The review team should consist of the author of the work item, and one or more independent
reviewers who are technically capable of reviewing the work item. The Project Manager will
decide on the number of reviewers based on the size, complexity and criticality of the work
item to be reviewed.
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
22
Communication & Escalation procedures:
GP IT’s Project Management expertise will help reduce issues related to un-addressed
solutions. However, GP IT suggests the following escalation process, should issues be not
solved at the Project Manager level.
Type of Issue Who to communicate /
escalate
Location
Business Issues Business Development Manager Dhaka
Project & Schedule issues Delivery Head Dhaka
There would be three levels of escalation for issues/concerns raised by the KWASA Project
Manager.
Level – 1
The first level of escalation will be to the GP IT Project Manager.
Level – 2
Delivery Manager / Program Manager – GP IT
The table below describes the escalation process.
Level 1 Project Manager - GP IT
Level 2 Delivery Manager /
Program Manager (GP IT)
The proposed escalation procedure will address technical, personnel and invoicing issues. The
technical issues could originate from either KWASA or GP IT and will be handled as per the
above escalation chart.
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
23
Functionalities of Proposed Solution:
To develop an integrated solution to meet KWASA need GPIT proposed a web based
client/server solution. Following is the Architectural Diagram:
Figure: Architecture of the solution
Business Model of KWAS Billing Solution:
Appendix 10 ANNEX
Figure: KWASA Billing Solution Business Model
Detail Functionalities:
Master Data Management:
i) Maintenance Customer Lifecycle:
With this functionality KWASA will able to store customer related all information’s starting from customer
name, Location Address (Holding no, Street Address, etc), type of Customer, etc. After successful storing
of the record system will provide an Account ID. There will be functionality to associate Bank
information’s and Dia information with each Customer. As per need there will be option to active or
deactivate of the customer.
Sample of Customer information:
Account
ID
Account
No
Name of
The
Account Address
001-001-
100 1234
Mr. Abdul
Hakim
1st phase,
Sondanga
Resident
Residence
ANNEX G GRAMEENPHONE CONTRACT
24
Figure: KWASA Billing Solution Business Model
i) Maintenance Customer Lifecycle:
With this functionality KWASA will able to store customer related all information’s starting from customer
name, Location Address (Holding no, Street Address, etc), type of Customer, etc. After successful storing
Account ID. There will be functionality to associate Bank
information’s and Dia information with each Customer. As per need there will be option to active or
Address
Father/Husband
Name
Customer
Type Status 1st phase,
Sondanga
Residential
Residence
late Md. Hazer Ali
Gazi Residential Active
With this functionality KWASA will able to store customer related all information’s starting from customer
name, Location Address (Holding no, Street Address, etc), type of Customer, etc. After successful storing
Account ID. There will be functionality to associate Bank
information’s and Dia information with each Customer. As per need there will be option to active or
Rate
Type
Connection
Date
Fixed 01/12/09
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
25
ii) Customer Type Entry:
As per nature of usage there are different types of customer. Followings are some common types:
Residential, Commercial, Industrial, Government, etc.
There will be option to add or remove customer type in the system.
iii) Bank Information’s Entry:
In this system there will be option to entry for customer wise bank accounts including KWASA collection
bank accounts.
iv) User Management:
To get access in this system every person has to have a system account with password. There will be
additional functionalities for super user who will have access to create users, cancel access to user and
execute system administration.
v) Rate/Tariff Management:
There will be two types of Rate/Tariff definition in the System:
1. Dynamic Rating:
In this option there will be way to define customer and Dia wise Rate/Tariff. For an example:
If Customer type is Residential and Dia 0.5 Meter the rate/ tariff may be 250 taka per month.
For same dia different Customer type like Industrial rate /tariff may be different: 350 taka per month
2. Fixed Rating:
There may be fixed rate charge applicable for Customer type wise or Dia wise or location or combination
of any or all.
There will be an option to use slab wise billing and it can also be configured on customer type, Diameter
wise and usage basis. Other Pricing elements like surcharge, equipments cost, arrear charge etc.
Also in the system there will be options to add new pricing elements.
vi) Address/Location:
This system will have the both functionality of coding of address or location in numerically or
alphabetically. The system will provide the functionality of designing address hierarchy.
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
26
vii) Meter Information:
There will be option to store meter detail information’s like Meter type, Manufacturer, Billing cycle, etc.
Also will be additional features to tie up customer wise meter so that meter lifecycle can be tracked in
the system.
viii) Diameter Information:
There are different type of diameters exists in the whole water supply process and due to this there are
direct impact on Tariff/rate and water supply. In the system we will provide the features to add or
remove diameter types any point of the time. For removal of diameter all associated tariff/rate needs to
be changed first before execution.
ix) System Administration:
System administration is not only maintains the user creation and access management, also it will
ensure the uptime the system including backup of the database as well. Other system administration
functionalities will be shared in during training and handover process.
Bill Generation:
i) Customer wise Bill Entry:
If the rate/tariff designed in customer registration process then no need to enter any month transactional
data but if the process to rate on consumption although in fixed rate setup there is no need to entry data
for Bill generation. This will be integrated functionality for fixed rate. System will provide the options to
add additional charge for penalty or due to other reason if required.
For slub wise tariff there need to enter monthly consumption of each consumer to generate bill.
ii) Different types of bill generation:
There will be option to generate parametric reports starting from individual billing, all billing, Connection
bill, Advance bill, Part Arrear Bill, etc.
iii) Bill posting:
There will be functionality to post bills to confirm the calculation and processing. System will produce
both posted and unposted billing to review. User should post after proper reconciliation.
Reconciliation:
i) Input Reconciliation for Bill Generation: There will be an option to reconcile for entry of the
systems and it will provide the feature to check the entered data properly processing bill generation.
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
27
ii) Invoice Reconciliation: There will be mechanism for reviewing bill generation process through
invoice reconciliation functionality. Through this process user will be able to match with no of bill
generations data and invoice printed data.
iii) Collection Reconciliation:
This functionality will assist user to reconcile the collection of money in bank and system, so that it will
be ensure the right financial information the organization and review customers for collecting dues.
Reporting:
There will be several types of parametric reports as per business need and finalize in the requirement
finalization phase. Major already known reports are as follows:
Customer Register Report,
Active/Deactivate/Cancel Customers Information Report
Dia and Customer type wise Report
Arrear Bill Report
New Customer Report
Advance Bill payment Report
Bank Information Report
Bank Collection Report
Location Report
Single or all Bill Generation report
Part Arrear Bill Generation Report
Formats and parameters will be reviewed by KWAS at the time of requirement analysis phase.
Deliverables of this Engagement:
In this engagement GPIT will provide followings to KWASA:
1. Executables in Computer Readable Format to setup the Software: In Two Copies (2)
2. User Manual: Both Functional and Technical Manual in Two Copies (2)
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
28
3. Initial Maintenance: Software Maintenance and user support will be provided free of charge
for an initial maintenance period of 4 calendar months.
4. Future Annual Maintenance:
After successful completion GPIT will provide two years annual maintenance support to KWASA.
For pricing please review commercial section.
Schedule of Project Delivery:
The schedule for the development and implementation for this project is given below
Major Milestone includes:
• Business requirement Document including sign off
• Development
• System Integration
• Installation and Configurations
• UAT
• User Training
• Go live
• Initial Maintenance period
Project timeline considering additional requirements collected so far:
The schedule for the development and implementation for this project is given below
Major Milestone includes:
• Business requirement Document including sign off
• Development
• System Integration
• Installation and Configurations
• UAT
• User Training
• Go live
• Initial Maintenance period
• Future Maintenance
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
29
Project timeline considering additional requirements collected so far:
M4 M5 M6 2011 2012
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 M2 M3 M4 Y1 Y2
Project Plan
Project Management
Requirement Analysis
Sign off Specification by WASA
Design
Development
Testing
Implementation
Training
Go Live
Handover
Initial maintenance
Future Maintenance
Utility Billing Software
Month1 Month2 Month3
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
30
Annexure B- List of Services, Deliverables and Specifications for Accounting Software
Understanding of the Requirement:
Khulna WASA (Khulna Water supply And Sewerage Authority) established on 2nd March 2008.
Specific objective of KWASA:-
• Construction, operation and maintenance of necessary infrastructure for water supply for
domestic, industrial and commercial purposes
• Construction, operation and maintenance of sewerage system
• Construction, operation and maintenance of drainage system
To achieve KWASA’s objective with other initiatives they want to implement integrated Accounting
software by establishing controls and regular reporting. ADB is providing their support under TA
project. In this regard KWASA already developed integrated accounting software with the help of
renowned chartered accountant firm Huda Vasi Chowdhury & Co. After reviewing existing software
and meeting with KWASA identifies following financial module’s which are required to make
functional:
1. Accounting Module
2. Inventory Module
3. Human Resource Information Module
4. Training Module
KWASA also requires training needs on above modules to execute the application by their own.
Our Approach to meet Project objective:
After going through the scope of work and discussions with KWASA team we have
understood that KWASA wants to make functional their accounting software and train
the resources.
Considering all these GPIT propose following solutions:
• Send Professional resources to make this system functional
• Proper Training for resources to build capability both functional and technical
side
• Ensure support and maintenance to make the system up and running
This will ensure faster and Quality delivery to customer
Scope of Work:
Following is the Scope of work for this engagement:
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
31
1. making functional of the existing Accounting System
2. Review Accounting Manuals prepared by Hoda Vasi as follows and if require revise:
• Accounts Manual
• Inventory Manual
• HR and Payroll Manual
• Training Manual
3. Guide KWASA personnel in data entry of existing accounting data and help them
generating tentative 6 month Financial Statements as of December 2010
4. Train accounting staff and provide intensive on the job training and coaching sessions as
necessary.
Out of Scope:
1. New module or new functionality development in the application.
2. Change request of existing functionality in the application.
Roles & Responsibility:
Following is the Roles & Responsibility for this project between GPIT & KWASA:
GP IT KWASA
Application Deployment Data Entry, Report Generation
Training Maintenance, Regular Backup &
Infrastructure Administration
2nd Level Support 1st Level Support to KWASA user
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
32
Risks and Mitigation Plan:
Given in the table below are a few of the critical risks that GP IT has identified, with Action
Plans to mitigate them. During the course of Project Planning, these can be looked at in
greater detail.
Risk Intensity Mitigation Plan
Change in project
scope and
definition
High • The scope of the implementation project has to be
frozen before the start of the project.
• Any change in scope after the start of the project
will be addressed through Change Control
Procedures and may impact the project time and
cost.
• GP IT would raise all scope change requests from
users to the Steering Committee before accepting
such changes.
Delay in
providing inputs
or completing
activities for
which the KWASA
is responsible.
High • KWASA to identify personnel to work on the project
- full-time personnel on the project should be
relieved of non-project related responsibilities.
• GP IT to assign responsibilities and timelines to
KWASA designated personnel and help them
understand what is required of them.
• Commitment from the KWASA Top Management is
an important check against delays for their
activities.
Adaptability to
change
Medium • KWASA top management to communicate their
commitment to the project to all levels.
• KWASA to formulate a Change Management
Strategy through planned communication and user
training.
• GP IT to assist KWASA in change management by
providing inputs on progress, clarifications on
functionality and post-production support.
Delay in
providing
Hardware
Medium • KWASA to ensure that the Hardware is available as
per the Project Plan for Implementation.
Availability of
user SMEs
High • To plan for availability of user SMEs as required in
the resource plan. Mobilization / Year end pressures
as well as vacation have to be anticipated and
planned accordingly
Hardware
Delivery
High • On time Hardware delivery may impact project
schedule
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
33
Annexure C – Payment Schedules
Based on the requirements and proposed Solution GPIT provide following pricing, which is agreed
by both the Parties:
A) Utility Billing Software:
Software Development, Implementation & Training:
Description Sub-Total (BDT)
1 Requirement Study, System Analysis & Design 200,000
2 Application Development 425,000
3 System Setup, Implementation 70,108
4 Training 163,040
5 Contingencies * 84,402
Grand Total (BDT) 942,550
Note: BDT Nine Lac Forty Two Thousand Five Hundred Fifty Taka only.
B) Accounting Software:
Based on the requirements and proposed Consultancy GPIT Provide
following Pricing:
Head Sub-Total
(BDT)
1Implementation & Training
3,54,000.00
Grand Total
3,54,000.00
In Words: BDT Three Lac Fifty Four Thousand
Change Request / Customization price:
If Party 1 requests for any application development or
enhancement within the validity period of this Agreement,
the same will be addressed by the Party 2 on the following
man day charge basis through amendment of this Agreement
vide change Request.
Man Day Rate: BDT 8520
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
34
Future Maintenance:
After completion of successful initial maintenance period Party-1 and Party-2 may go for an
annual maintenance agreement. The pricing for the annual maintenance shall be as per the
followings:
Words: BDT Five Lac forty Thousand
Change Request / Customization price:
If Party 1 requests for any application development or enhancement within the validity period
of this Agreement, the same will be addressed by the Party 2 on the following man day charge
basis through amendment of this Agreement vide change Request.
Man Day Rate: BDT 8520
Payment Schedule:
The payment shall be made as per the following schedule:
Mile Stone Percentage
Successful Testing 50%
Successful Handover 50%
Commercial Terms and Conditions:
1. The pricing for software development is inclusive of any tax, vat and govt. duties
2. The pricing for Future Maintenance is exclusive of any tax, vat and govt. duties
3. The price quoted is based on the scope of work, assumptions and dependencies stated in this
document. Any changes to the scope will be taken up separately or change requests.
4. The pricing does not include hardware, software or third party tools.
Payment of Invoices:
• All invoices raised shall be payable within 15 days from the date of invoice. All invoices shall be
deemed to be accepted unless disputed within 7 days from the date of receipt of invoice.
HeadSub-Total
(BDT)
1 1st Year Maintenance Charge (20000/Month) 240,000.00
2 2nd Year Maintenance Charge (25000/Month) 300,000.00
Grand Total (BDT) 540,000.00
Appendix 10 ANNEX G GRAMEENPHONE CONTRACT
35
• All payments required to be made by the Customer shall be in the currency stated in the invoice
and shall be transferred to a designated bank account in Bangladesh.
• If the customer fails to pay the fees and other payments within the stipulated time, the customer
shall be liable to pay interest at 1.5% per month on such amount of Fees and Payments that have
become due.
• If whole or any part of the Fees and other payments remain outstanding for 90 days after the same
have become due, GP IT shall at its sole discretion, be entitled to discontinue the provision of
services