test plan template - rochester institute of...

34
Document Revision No.: 2 Revised: 02/20/22 RIT KGCOE MSD Program P10505 Low Energy Printing - Cold Pressure Fusing 2 Test Plans & Test Results By: Aniket Arora, David Hatch, Eric Wilcox, Jon Burville, and Thomas Stojanov Table of contents 1. MSD I: PRELIMINARY TEST PLAN..........................3 1.1......................................Introduction and Overview 3 1.2....................Systems and Critical Components being tested 4 1.3............Approval: Team, Guide, Technical TA, Customer/Sponsor 6 1.4................................................ Test Strategy 7 1.5.............................Definitions: Important Terminology 10 2. MSD II: FINAL TEST PLAN...............................12 2.1................................................. Introduction 12 2.2.. Test Structure, Sampling Techniques/Safety and Problem Reporting 13 2.3.................Measurement Capability, Equipment, Configuration 16 2.4............................Test Conditions, Setup Instructions 19 2.5........................Sponsor/Customer, Site Related, Requests 21 2.6...............................................DOE Test Matrix 23 2.7.................................................. Assumptions 23 MSD II – WKS 3-10 DESIGN TEST VERIFICATION...............24 2.8................................................. Test Results 24 2.9....................................Logistics and Documentation 24 2.10...........Definition of a Successful Test, Pass / Fail Criteria 24 2.11.Contingencies/ Mitigation for Preliminary or Insufficient Results 24 2.12.............................Analysis of Data – Design Summary 24 2.13..................................Conclusion or Design Summary 24 2.14.................................Function/ Performance Reviews 24 2.15.................................................. References 24 RIT KGCOE MSD Program Page 1 Revision:

Upload: doandang

Post on 14-Apr-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

P10505 Low Energy Printing - Cold Pressure Fusing 2Test Plans & Test Results

By: Aniket Arora, David Hatch, Eric Wilcox, Jon Burville, and Thomas Stojanov

Table of contents

1. MSD I: PRELIMINARY TEST PLAN............................................................31.1. Introduction and Overview.............................................................................................................3

1.2. Systems and Critical Components being tested.............................................................................4

1.3. Approval: Team, Guide, Technical TA, Customer/Sponsor........................................................6

1.4. Test Strategy.....................................................................................................................................7

1.5. Definitions: Important Terminology............................................................................................10

2. MSD II: FINAL TEST PLAN........................................................................122.1. Introduction....................................................................................................................................12

2.2. Test Structure, Sampling Techniques/Safety and Problem Reporting.....................................13

2.3. Measurement Capability, Equipment, Configuration................................................................16

2.4. Test Conditions, Setup Instructions.............................................................................................19

2.5. Sponsor/Customer, Site Related, Requests..................................................................................21

2.6. DOE Test Matrix............................................................................................................................23

2.7. Assumptions....................................................................................................................................23

MSD II – WKS 3-10 DESIGN TEST VERIFICATION..........................................242.8. Test Results.....................................................................................................................................24

2.9. Logistics and Documentation........................................................................................................24

2.10. Definition of a Successful Test, Pass / Fail Criteria....................................................................24

2.11. Contingencies/ Mitigation for Preliminary or Insufficient Results...........................................24

2.12. Analysis of Data – Design Summary............................................................................................24

2.13. Conclusion or Design Summary....................................................................................................24

2.14. Function/ Performance Reviews...................................................................................................24

2.15. References.......................................................................................................................................24

2.16. Appendices......................................................................................................................................25

RIT KGCOE MSD Program Page 1 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

P10505 Low Energy Printing - Cold Pressure Fusing 2Test Plans & Test Results

1. MSD I: PRELIMINARY TEST PLAN

1.1. Introduction and OverviewProject Purpose

The purpose of this year’s project is to design and test a fixture that is able to uniformly

fuse toner on the paper solely based on pressure instead of heat. This technology is

expected to reduce the overall energy consumed in the printing process.

Project Background

This project is the second part of the Cold Pressure Fusing project at Xerox. The project

last year (P09505) was focused at designing a text fixture that was capable of fusing

toner with high pressure instead of heat. This year’s project (P10505) is focused mainly

at optimizing the design from last year and testing the design under various

configurations.

Project Summary (provided by Xerox)

It is broadly recognized that xerographic digital printers are quite energy intensive and

as customers become more and more environmentally conscious they are demanding

improvements. The ability to be more energy efficient is not just the "green" thing to do;

it is increasingly becoming a significant competitive advantage. In addition, all print

engine providers, Xerox, HP, Ricoh, Samsung, Lexmark, Kodak, etc. strive to meet

more and more stringent Energy Star and other certification requirements. While print

engine providers have considerably reduced the power required to print at a given

process speed over the last decade, there still is opportunity and a need to further

reduce printer power. A large share of any xerographic printer power is consumed by

the fusing sub-system: where toner is heated well above its melting point, so as to

enable heat flow, coalescence and paper adhesion. Improved low energy fusing is the

target for this project.

RIT KGCOE MSD Program Page 2 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

Project testing plan

The testing for this project will encompass a full factorial DOE with 5 factors: skew

angle, load, compliance, paper orientation and paper weight. The output data from the

experiment will include the percentage of fusing and uniformity as metrics. These

outputs will be measured using the Smudge test (described later).

1.2. Systems and Critical Components being tested

The system level diagram consists of five input variables:

1. Paper Orientation – This is the direction the paper is fed into the fuser. This

factor has 2 levels: Landscape and Portrait. These levels affect the overall

print quality as the forces acting on the main rollers will change according to

the length of the paper in contact with the rollers. It is expected that the

RIT KGCOE MSD Program Page 3 Revision:

Figure 1: System level design (block diagram)

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

portrait configuration will cause a lower deflection as compared to the

Landscape configuration.

2. Paper Weight – The system needs to accommodate for different paper

weights. The paper weight factor has two levels: 20lb and 24 lb. The weight

of the paper in the system affects the overall paper thickness that goes

through the system. This thickness would affect the amount of load that is

exerted on the main rollers. It is assumed that the 24lb paper would exert

higher loads on the system because of greater thickness. To accommodate

for these load changes, the system is designed with compliance that can

adjust the load on the rollers.

3. Skew Angle – The system needs to be able to adjust to a minimum of three

different skew angles: 1.4°, 1.9° and 2.4°. These skew angles are defined as

the angle between the top main roller and the support rollers. The skew

angles concentrate the force of the support rollers towards the center of the

main top roller and hence help in reducing its deflection.

4. Compliance – The compliance in the system is required for adjusting to two

different paper weights. It is tested under two levels: Low and High. These

levels are important to decide the optimum level of compliance that would be

required for the system to adjust for the different paper weights. The

compliance also absorbs the ‘shock’ that the system undergoes as soon as

the paper enters the rollers.

5. Pressure/Load – The pressure or load is applied on the system at 4 points,

two on each side of the roller. The amount of load on the system can vary

from 50lbs – 150lbs for each of the four points. The load is measured by

Load Cells present on all four points and a signal conditioner will be used to

amplify the signal so that it is easily read in the DAQ system. The system is

analyzed under 2 different load conditions: 50lbs and 150lbs of weight on the

load points. These levels will help in the analysis of an optimum level for load

on the system.

RIT KGCOE MSD Program Page 4 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

1.3. Approval: Team, Guide, Technical TA, Customer/SponsorApproved by:

Team Members

i. Aniket Arora _____________________

ii. David Hatch _____________________

iii. Eric Wilcox _____________________

iv. Jon Burville _____________________

v. Thomas Stojanov _____________________

Guide i. Bill Nowak _____________________

Technical Teaching Assistant

i. Mike Zona _____________________

Customer/Sponsor

i. Grace Brewington _____________________

ii. Tony Condello _____________________

RIT KGCOE MSD Program Page 5 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

1.4. Test Strategyi. Product Specifications and Pass Criteria

Engr. Spec. # Imp. Source Specification (description) Unit of Measure Marginal Value Ideal Value Pass Criteria

ES4 1 Customer NeedPrototype will fuse print across 95% of the page

% fused, Width of unfused 90% fusing 95% fusing

90% of print fused according to

Xerox smudge test.

ES6 1 Customer NeedPrototype will vary in nip pressure less than 10%

Width of Pressure Indication, Xerox

Metric 10% variation 5% variation

Less than 10% variation on

pressure sensitive paper.

ES8 1 Customer NeedPrototype must be capable of adjusting to three skew angles

Number of Settings 3 angles Analog

3 sets of end plates at different

angles.

ES10 1 Customer NeedPrototype must adhere to Abaqus model created by Xerox Yes/No N/A Yes

Product follows all specs in the

Abaqus model.

ES12 1 Customer NeedPrototype must be able to reach a 1.9° skew angle Degrees 1.8°-2.0° 1.9°

1.9° end plate is manufacturable.

ES14 1 Customer Need

Prototype must be adjustable to the same skew angle to a 1/10th degree for ~25 runs

Standard Deviation

1/5th degree variation

1/10th degree variation

The % fusing does not change by more than 5%

ES16 1 Customer NeedPrototype vibration will be less than 3 lbs as measured by the load cells. Force 5 lbs 0 lbs

Load output stays within 5lbs while

running.

ES7 1 Customer Need

Prototype must accommodate both 20 and 24 lb paper while meeting all other specifications Yes/No

20 and 24lb paper

All paper weights

>90% fusing with no physical

damage to paper for 20 and 24lb.

ES3 2 Customer Need Prototype will minimally calendar print Qualitative Moderate NoneNo visible damage.

ES5 2 Customer Need

Prototype will produce trailing edge wrinkles less than once every twenty prints Number

1 wrinkle every 10 prints

No wrinkles ever

Number of wrinkles < 1 every

10 prints

ES11 3 Customer NeedFeed rate must not decrease by more than 15% Torque

15% reduction of speed

5% reduction of speed

Torque output does not show

>15% reduction.

ES1 3 ImpliedPrototype must be manufacturable within ~2 week

Time Required, Y/N 4 weeks 2 week

Time recorded for manufacture in

MSD 2 is < 4weeks.

ES15 3 ImpliedPrototype must be able to print >1000 copies without failure

Life Cycle (Number of Prints) 500 copies 1000

Outside scope of measurement.

ES2 4 Customer Need Prototype must cost less than $3000 Dollars $3,000 $1,500

Overall project cost <$3000 as

suggested by the BOM.

ES13 5 ImpliedPrototype must be dimensionally stable for a load of 4000 psi Force Vibration Stationary

No noticeable Vibration

ES9 5 ImpliedPrototype will take less than 60 sec. of user time to set up print Time Required 120 sec 0 sec.

Timing suggests time required <

120 sec.

Table 1: Engineering Specifications (Importance Scale, 1-Highest, 5-Lowest)

RIT KGCOE MSD Program Page 6 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

a. Test Equipment available

DAQ

1 Signal Conditioner

Motor

Power Supply

4 Load cells

Wires

P09505 Fixture

Pressure Sensitive Paper

Kill Switches

b. Test Equipment needed but not available

CPU

3 Signal Conditioners

Multi-meter

Tachometer

Dynamometer

Additionally, See BOM

ii. Phases of Testing

1.4.1.1. Component/ Device

1. Load Cells: The load cells provided to the group need to be tested to

check for load range compatibility and output voltage consistency.

2. Compliance washers: The compliance washers need to be tested for

spring factor (k) that is listed on the manufacturing specifications. The

spring factor for the washers (springs) can change overtime because of

repeated use or excessive force (fatigue).

3. Rollers: The rollers need to be checked for concentricity before they are

used for the project. They also need to be checked at pre-assigned

intervals between test runs.

4. Skew Angle: The skew angle needs to be checked for accuracy before

and during the course of the runs.

RIT KGCOE MSD Program Page 7 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

1.4.1.2. Subsystem

1. DAQ system: The DAQ system can be checked periodically by running

the load cells under known loads and checking for output in the VI. This

would ensure that the system is operating under the initial configuration.

The loads can be applied using the UTM and the outputs can be

compared to the expected output from the mathematical model.

2. Fusing System: The fusing system needs to be checked for:

I. Permanent roller deflection: This can be periodically checked by

inspection with a Micrometer.

II. Concentricity: This can be periodically checked by inspection with a

Micrometer.

III. Bearings Rotation: Deviations in the torque output could suggest

issues with the bearings. The bearings can be tested using a simple

torque experiment. In this experiment, the bearings are subjected to

a constant torque and the number of rotations it achieves before

coming to rest is used as the output. This output can be compared

over time to see the issues.

3. Safety System: The ‘kill switch’ can be tested periodically to ensure that

performs as expected.

1.4.1.3. Integration

1. Hardware: The machined part can be checked against the system

schematics to verify that the dimensions are within tolerance. This can

be done with the help of a micrometer. The critical areas of testing would

be:

a. Outside diameter of bearing vs. housing diameter.

b. Dimensions that affect the skew angle.

c. Inner diameter of the bearing vs. shaft diameter.

RIT KGCOE MSD Program Page 8 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

d. Diameter of rollers.

2. Software: The outputs can be checked against a known load to check

against expected response. Critical areas of testing could be:

I. Load cells

II. Torque output

III. Kill Switches

IV. Signal Conditioners

The wiring of the prototype must be checked against electrical schematics.

1.4.1.4. Reliability

The system can be periodically checked for wear in the following ways:

a. Roller deflection: As discussed in section 1.4.1.3.2.a

b. Concentricity: As discussed in section 1.4.1.3.2.b

c. Bearings issues: As discussed before 1.4.1.3.2.c

d. Compliance: As discussed in section 1.4.1.2.2

1.4.1.5. Customer Satisfaction

Show the customer the final optimized product and run the system under

randomized settings.

1.5. Definitions: Important Terminology

1.5.1. Skew Angle: The skew angle is the angle between the Main Roller and the

support rollers. It is designed in order to focus the pressure towards the

centre of the main roller.

1.5.2. Compliance: The compliance for the system is the ability for the system to

adjust to the variation in the load. This is achieved by the use of compliance

RIT KGCOE MSD Program Page 9 Revision:

1.9 degrees

Main Roller

Support Roller

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

washers or springs with a specified spring constant. Compliance is

understood to be the inverse function of spring constant of the compliant

material.

1.5.3. Calendaring: The change in the thickness of the paper (deformation) due to

pressures exceeding its yield strength.

1.5.4. Nip Width: This is the area of contact between the fusing rollers due to

application of load.

2. MSD II: FINAL TEST PLAN

2.1. Introduction

The testing process for the team will include specific test procedures that are

designed to test the configuration of all sub-systems. The testing is divided into

three sections:

i. Sub-systems testing: This testing is performed to check the configuration and

functioning of various sub-systems in the prototype. The various sub-systems in the

prototype are:

a. DAQ system: The DAQ system can be checked periodically by running the

load cells under known loads and checking for output in the VI. This would

ensure that the system is operating under the initial configuration. The loads

can be applied using the UTM and the outputs can be compared to the

expected output from the mathematical model.

RIT KGCOE MSD Program Page 10 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

b. Fusing System: The fusing system needs to be checked for:

I. Permanent roller deflection: This can be periodically checked by

inspection with a Micrometer.

II. Concentricity: This can be periodically checked by inspection with a

Micrometer.

III. Bearings Rotation: Deviations in the torque output could suggest issues

with the bearings. The bearings can be tested using a simple torque

experiment. In this experiment, the bearings are subjected to a constant

torque and the number of rotations it achieves before coming to rest is

used as the output. This output can be compared over time to see the

issues.

c. Safety System: The ‘kill switch’ can be tested periodically to ensure that it

performs as expected.

ii. Initial testing: This set of test procedures are used to define and understand the

scope of the final product testing. This stage of testing requires a small number of

tests under specific conditions (1/4th factorial design). The expected results from this

test include: prototype functioning, timing studies (setup, data acquisition and data

processing), types of output achieved, feasibility of concept etc. These test results

are analyzed and the used to determine the testing procedures for the Final testing

phase.

iii. Final testing: This is the main set of test procedures that are performed on the

prototype. These test procedures check and confirm the effects of the four factors

(skew angle, load, compliance and paper orientation) on the uniformity of the

pressure across the nip. The tests are performed under 24 different test conditions

(full factorial design) on medium or high grade pressure sensitive paper. The testing

is then extended to the check the effects of the four factors on the fusing of the print

on the paper. In this phase, only the factors with a co-relation with uniformity are

varied and tested on unfused printed paper. The results from the two tests are then

analyzed to determine the set of optimal settings that would achieve a uniform print

RIT KGCOE MSD Program Page 11 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

across the paper. These settings are then used to manufacture and assemble a final

working prototype.

2.2. Test Structure, Sampling Techniques/Safety and Problem Reporting2.2.1. Test Structure, Work Breakdown Structure

Test #

System Component

Details Pass criteria Person in charge

Due Date

TI1 Hardware The machined part needs to be checked against the system schematics to verify that the dimensions are in tolerance. Refer to section 1.4.1.3.

The critical dimensions are within tolerance indicated by the drawings

David Hatch, Eric Wilcox

TI2 System Wiring

The system wiring needs to be checked against the electrical schematics to ensure consistency.

The system absolutely follows the electrical schematics.

Thomas Stojanov, Jon Burville

TC1 Load cells The load cells are checked for compatibility of load range and consistency of output voltage by placing under the UTM at fixed load for 3 iterations and checking for output on the VI.

Load cells show consistent outputs (within 5% deviation of Voltage from the mean) for the test.

Thomas Stojanov, Aniket Arora

TC2 Compliance Washers

The compliance washers are checked for spring factor (k) by placing under specific loads and measuring the displacement. This needs to be done periodically (every 10 runs) to avoid spring fatigue.

The deviation stays within 5% of the original.

David Hatch, Aniket Arora

TC3 Skew Angle The prototype needs to be checked for consistency of skew angle using micrometer every 3-4 runs as defined in the Test Procedure.

The skew angle stays within 0.5° of the expected.

David Hatch, Aniket Arora

TS1 DAQ System

Check the DAQ system by applying known loads (using UTM) and checking the output on the VI.

The VI shows same output for the fixed load applied on the system.

Thomas Stojanov, David Hatch

TS2 Fusing System

Permanent Roller deflection – This can be checked with dial indicator. The roller is placed in ground V-blocks and checked axially for deflection.

The requirement for TIR is 0.5-1 thou.

David Hatch, Eric Wilcox

TS3 Fusing System

Concentricity – This can be checked with dial indicator. The roller is placed in ground V-blocks and checked radially for concentricity.

The requirement for TIR is 0.5-1 thou.

David Hatch, Eric Wilcox

TS4 Fusing System

Bearings Rotation – Bearings are subjected to a known torque and the number of rotations they make before stopping is measured.

The number of rotations stays within 5% of original.

Jon Burville, Eric Wilcox

TS5 Safety Kill Switch – The kill switch needs to Kill switch turns the Team (user)

RIT KGCOE MSD Program Page 12 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

System be checked after every test to ensure proper functioning.

system ‘off’ every time.

2.2.2. Phases of Testing

Refer to section 1.4.v.

2.2.3. Sampling Techniques

To ensure safety and valid data collection, certain steps need to be followed prior to every test:

a. Valid data collection:

i. Check the electrical connections with the electrical schematics.ii. Check and ensure that all the mechanical components are secured

tightly in place (for e.g. screws and bolts are fastened).iii. Check the DAQ’s and the LabVIEW VI to ensure that the configuration

for the test match the Text Matrix.

b. Safetyi. Check the Emergency STOP button for proper functioning by turning

the system ON and OFF with the emergency STOP prior to every test.ii. Always perform the tests with a partner to ensure safety in case of an

accident.iii. Avoid wearing loose clothing or a tie while operating the device. Use a

tie pin if necessary.

2.2.4. Reporting Problems; Corrective Action

Any problems that arise during the course of data collection and equipment configuration must be recorded and reported to the group in the following format.

S.No Date/Time

Test # (from Test

Structure table)

Configuration #

(from test matrix)

Team members present

Problem description

Reasons (if known)

Suggestions/ actions taken

Problem Fixed (Yes/No/Pending)

e.g. 3/14/2010, 6:30 PM TS5 4

Aniket Arora,

Thomas Stojanov

The kill switch does not turn the motor

OFF.Loose wiring

Rechecked wiring with schematics and

rewired the connection

Yes

1

2

RIT KGCOE MSD Program Page 13 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

3

4

5

6

7

8

2.3. Measurement Capability, Equipment, Configuration2.3.1. DAQ

DAQ Configuration

The Data Acquisition System (DAQ), however an advanced system, will

require slight user configuration for safe and proper use. A white and black

control panel, complete with real- time load cell readouts/ signal conditioners

for each of the four load cells and an emergency stop button, is provided with

the DAQ. Also provided is an analog motor controller which is capable of

controller motor status, direction, speed and torque. The test fixture will

accompany load cells which will provide the fastener load values. In addition

to the above devices a National Instruments (NI) Input/ Output (I/O) block will

be provided from which the above devices will indirectly interface to the

Personal Computer (PC).

RIT KGCOE MSD Program Page 14 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

The emergency stop button is located in the center of the DAQ control panel

evident by its bright red color. The emergency stop will allow for proper DAQ

operation when in the default mode and will shut power off to the DAQ when

engaged. Default mode is defined as when the button is in the full out

position while engaged mode is defined as when the button is in the pressed

in position.

Each of the load cell readouts/ signal conditioners will be configured prior to

powering on the DAQ system. No user interface shall be required for any of

the readouts. Should any erroneous action occur with respect to the load

cell readouts/ signal conditioners refer to the Transducer Techniques DPM-3

manual provided with the DAQ system.

The analog motor controller allows for the user to potentially the inputs to the

DAQ system as testing allows. The rightmost button, marked as power, is

the main power to the motor controller assembly. This should remain on at

all times. Two direction buttons exist in the middle. The direction buttons

must remain in the forward direction at all times for testing. The reverse

direction may be utilized to clear paper jams. The speed and torque may be

alternated for calibration or as the user requires. The torque dial must

remain at the “max” position whereas the speed must be adjusted to 583.7

RPM which should be verified real- time through the LabView interface.

The load cells shall not require any user interface other than torquing the test

fixture fasteners to the desired load. While the DAQ is operating the user

can utilize the real- time readout of the load cell readouts/ signal conditioners

to properly load the test fixture fasteners to the desired loads. This will also

be available to the user in the LabView interface and shall read the same

values as the real- time readouts.

The NI I/O block is fixed and does not require any user interface. Any

interaction with the I/O block should be performed by a trained professional

or person(s) familiar with National Instruments and LabView data interfaces.

RIT KGCOE MSD Program Page 15 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

Limitations of DAQ

The DAQ has few limitations as they are solely based on the measurement

capabilities of its components. The motor controller’s outputs or status can

be minimized or maximized to any point without damaging or adversely

altering the DAQ. The load cells are capable of handling up to 500lbs. of

force each which if exceeded may damage the load cells thus possibly

requiring replacement.

Outputs in LabView Interface

LabView is the primary point of data output and user interface for the DAQ

system. The motor can be electronically started and stopped through

software via a set of soft start and stop buttons. Motor speed in RPM and

torque in ft- lbs. is provided in both real- time and graphical formats with

respect to time. Horsepower is also calculated in real- time and graphical

formats with respect to time. The real- time output of each loadcell in lbs. will

also be given.

Load Cell Calibration

Load cell calibration is accomplished prior to testing with the test fixture.

Each load cell is tested in a calibrated hydraulic press with real- time output,

under which the load cells shall be measured for impedance at maximum

allowable load and shall be done at several points throughout its range. This

will be recorded as required. Thereby a calibration model can be obtained

for the load cells and applied to the LabView interface for the sake of load

correction.

Speed Output Calibration

Speed output calibration is also accomplished prior to testing with the test

fixture. Several speeds will be measured and recorded via the output shaft of

the motor through the use of a mechanical tachometer. Thereby a

calibration model can be obtained for the speed output and applied to the

LabView interface for the sake of speed correction.

RIT KGCOE MSD Program Page 16 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

Torque Output Calibration

Torque output calibration is again accomplished prior to testing with the test

fixture. Several weights of known masses shall be hung from a specific

diameter pulley at a given speed under which typical equations of motion

shall be utilized to gather torque values for given output voltages of the

torque output. These values will be recorded. Thereby a calibration model

can be obtained for the torque output and applied to the LabView interface

for the sake of torque correction.

2.3.2. Torque measurement for Bearings – The torque measurement to check

the performance of the bearings follows a simple testing procedure. The

roller with the bearings is subjected to a fixed torque by wrapping a thread

with a fixed weight attached to one end of the string. This weight is dropped

from fixed height and the number of revolutions the rollers make before

coming to a stop is counted. These revolutions can be counted with either by

naked eye or with a camera.

2.3.3. Micrometer for skew angle measurement – The skew angle can be

measured with a micrometer by measuring the gap between the ends of the

skewed rollers. The gap can then be plugged in to the trigonometric function:

sin−1( PH

)=θ

Where P = (0.5 * Gap) between the ends of the skewed rollers and H is the

Length of the skewed rollers.

2.3.4. UTM – The Universal Testing Machine (UTM) can exert fixed amounts of

forces on the load cells. This fixed force can then be compared to the outputs

on the multi-meter to check the increase in voltage. This measurement can

then be checked for 2 different loads. This would give a good idea of how the

outputs from the load cells compare with the load exerted on them.

RIT KGCOE MSD Program Page 17 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

2.4. Test Conditions, Setup Instructions2.4.1. Test Conditions

The test conditions for the testing procedure should remain fairly consistent

throughout the sampling and testing process. For the same reason testing is

to be performed in RIT, College of Engineering (4th floor, Design Center).

This would work best for controlling the temperatures and the humidity

factors for the current scope of the project.

As far as equipment verification and tests are considered, it is recommended

to use the same machine for each process throughout the entire length of the

project. For the machining process, it is recommended to use the same

machines and tools for the most part (might not be possible in some cases).

This will also reduce the variability in the testing process.

2.4.2. Setup Conditions and Procedure

The setup conditions for the prototype should remain fairly consistent

throughout the course of the project. After loading the rollers, it is necessary

to check the spacing between the main rollers. It has been observed during

the test runs that sometimes after loading the device, a small gap exists

between the main rollers on the P09505 prototype.

The setup procedure for the tests is:

1. Get the setup conditions from the test matrix.

2. If the skew angle stays the same go to step 9 or else go to step 3.

3. Take the main bolts out from the motor assembly. These bolts hold

the motor to the base. The motor should slide out of the assembly.

4. Unscrew the side bolts on the roller assembly. These bolts attach the

L-brackets that hold the roller assembly to the base. The roller

assembly should now be free and easy to take out.

5. Take the main bolts out off the roller assembly. These bolts go into

the end plates and hold the rollers in place.

RIT KGCOE MSD Program Page 18 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

6. The end plates can now be swapped with the new set for the required

angle.

7. After assembling the end plates, rebuild the system. Check the

assembly of the system with the assembly schematics.

8. Connect the load cells to the DAQ and configure the load cells if

necessary. The load cells need to stay ON for 15 minutes

(startup/warm up time).

9. Check the wiring of the prototype with the Wiring Schematic.

10.For test number U1, U4, U7, U9, U12, U15, U17, U20 and U23, the

skew angle needs to be checked with a micrometer for consistency

(refer to section 2.2.1 – TC1).

11.For test number U1, U4, U7, U10, U13, U16, U19 and U22, the load

cells need to be checked with the UTM (refer to section 2.2.1 – TC1).

12.For test number U1, U11 and U21, the compliance washers need to

be tested under specific known load for deflection (refer to section

2.2.1 – TC2).

13.Load the system to the amount specified in the test matrix. It is a good

practice to wait for 30-60 seconds and check the output on the VI after

loading the system. It is observed that the compliance material tends

to dampen the load once it is exerted initially. This load slowly

steadies out and needs to be rechecked and reconfigured.

14.After the system is loaded, check the system by dry-running it and

stopping it with the Kill Switch. Observe any unnecessary vibrations or

noises that may arise. If any, record them in section 2.2.4.

15.Only if everything works well, insert a sheet of pressure sensitive

paper (or unfused paper) according to the angle orientation from the

test matrix.

RIT KGCOE MSD Program Page 19 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

16.CAUTION: The device tends to pull the paper in the system very fast

(watch out for your fingers).

17.Collect the print of the other side of the device and mark the print with

Test Date, Time, Test number (from the Design Matrix) and team

members present.

18.Save the print in the group folder and unload the device.

2.5. Sponsor/Customer, Site Related, Requests2.5.1. Scanning of output prints at Xerox

2.5.1.1. Pressure sensitive paper

The outputs from the pressure sensitive paper scans would give an

indication of the uniformity of pressure over the length of the rollers. The

pressure sensitive paper outputs from the tests are to be scanned at the

Xerox facility in Webster, NY on Xerox equipment. The scanner scans

the film and assigns pressure values as a function of the density of the

pigments on the film. Higher density of pigments means that higher

pressure was applied to that area. The scanner can single out any point

on the film or take an average of the area density on the film. For the

experiments, it would be good to take two sets of measurements for

each condition:

Full sheet going through the rollers: The length of the film needs to

be at least 3.14 * 2 = 6.28 inches for each sample so that it covers one

complete rotation of the main roller.

Narrow nip impressions.

2.5.1.2. Unfused prints

The unfused prints will be tested based on the results of the Pressure

sensitive paper tests. The prints are provided by Xerox on Elite Digital

RIT KGCOE MSD Program Page 20 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

Coated Media paper (24lb) and printed in a chess board pattern. This

pattern will enable the team to easily perform and analyze the Xerox

smudge test. The smudge test is to be performed at the Xerox facility in

Webster, NY on Xerox equipment. The smudge test involves swiping the

area of the fused paper with a cloth and scanning the cloth to determine

the amount of toner that was removed from the paper. The outputs from

the smudge test are entered in the test matrix and the results are analyzed

to determine the optimal combination of settings that would fuse the print

on the paper.

2.6. DOE Test Matrix2.6.1. Test Matrix (Test for Uniformity)

S.No.

Skew Angle (deg.)

Compliance (lb/in)

Load

(lbs)Paper

orientationOutpu

t

S.No.

Skew Angle(deg.)

Compliance (lb/in)

Load

(lbs)Paper

orientationOutpu

t

RIT KGCOE MSD Program Page 21 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

U1 1.4 270 130 Landscape U13 1.9 560 130 Landscape

U2 1.4 270 130 Portrait U14 1.9 270 130 Portrait

U3 1.4 560 130 Portrait U15 1.9 560 170 Landscape

U4 1.4 270 170 Landscape U16 1.9 270 170 Landscape

U5 1.4 270 170 Portrait U17 2.4 270 130 Portrait

U6 1.4 560 170 Landscape U18 2.4 560 130 Landscape

U7 1.4 560 170 Portrait U19 2.4 560 170 Portrait

U8 1.4 560 130 Landscape U20 2.4 270 130 Landscape

U9 1.9 270 130 Landscape U21 2.4 270 170 Portrait

U10 1.9 270 170 Portrait U22 2.4 560 130 Portrait

U11 1.9 560 130 Portrait U23 2.4 270 170 Landscape

U12 1.9 560 170 Portrait U24 2.4 560 170 Landscape

2.7. Assumptions2.7.1. Sequential Skew Angle factor in test matrix – The skew angle factor in the

test matrix for the DOE is sequentially organized to reduce the time taken to

perform the tests. Each skew angle change requires an additional 10

minutes because it requires changing the end blocks on the prototype. This

sequential organization requires periodic skew angle verification tests (TC3)

as described in the Test Structure (section 2.1).

RIT KGCOE MSD Program Page 22 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

MSD II – WKS 3-10 DESIGN TEST VERIFICATION Note to Teams: Populate the templates and test processes established in Final Test Plan.

These elements can be integrated or rearranged to match project characteristics or personal/team preferences.

2.8. Test Results2.8.1. Component

2.8.2. Subsystem.

2.8.3. Integration

2.8.4. Reliability

2.8.5. Customer Acceptance

2.9. Logistics and DocumentationWhere are the test results being performed, logged (i.e. project notebook) and documented (i.e. excel spreadsheet)? EDGE team website structure (i.e. document names, file types, and header location).

2.10. Definition of a Successful Test, Pass / Fail Criteria2.11. Contingencies/ Mitigation for Preliminary or Insufficient Results2.12. Analysis of Data – Design Summary2.13. Conclusion or Design Summary

Can you explain why a particular function doesn’t work? Add here or remove how the conclusions are to be reported or summarized (i.e. significance with confidence, pass/fail, etc.) as applicable.

2.14. Function/ Performance ReviewsNote: Some teams organize reviews on a weekly bases starting in week 4 or 5 and other may wish to wait until week 10 or 11. Discuss with your Guide.

2.14.1. Debriefing your Guide and Faculty ConsultantsShare test results, conclusions, any follow-on recommendations, design summary.

2.14.2. Lab Demo with your Guide and Faculty Consultants Perform each of the specifications and features.

2.14.3. Meeting with Sponsor See Customer Acceptance above. Field Demonstration. Deliver the project. Demonstrate to the Sponsor. Customer needs met / not met.

2.15. References

RIT KGCOE MSD Program Page 23 Revision:

Document Revision No.: 2 Revised: 05/07/23 RIT KGCOE MSD Program

Add here or remove as applicable.

2.15.1.Add here or remove as applicable.

2.16. AppendicesAdd or remove as applicable.

2.16.1.Add here or remove as applicable.

RIT KGCOE MSD Program Page 24 Revision: