![Page 1: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/1.jpg)
1
LZ01
-453
742
The AlpTransit Gotthard Project
Enginyers Industrials de Catalunya15 october 2014
Dr. Renzo SimoniCEO
AlpTransit Gotthard Ltd
![Page 2: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/2.jpg)
2
AlpTransit Gotthard AG
LZ01
-453
742
Final breakthrough
![Page 3: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/3.jpg)
3
AlpTransit Gotthard AG
LZ01
-453
742
Contents
1. Project overview
2. Challenges
3. Reminiscences from the construction period
4. The project today
![Page 4: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/4.jpg)
4
LZ01
-453
742
1. Project Overview
![Page 5: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/5.jpg)
5
AlpTransit Gotthard AG
LZ01
-453
742
Transalpine goods traffic
![Page 6: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/6.jpg)
6
AlpTransit Gotthard AG
LZ01
-453
742
Journey times Zurich - Lugano / Basel - Lugano
![Page 7: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/7.jpg)
7
AlpTransit Gotthard AG
LZ01
-453
742
NRLA decision 1991
![Page 8: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/8.jpg)
8
AlpTransit Gotthard AG
LZ01
-453
742
A flat railway route through the Alps
![Page 9: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/9.jpg)
9
AlpTransit Gotthard AG
LZ01
-453
742
Key features of the only flat railway route through th e Alps
• Newly constructed twin-track route• Mixed operation• Maximum speed passenger trains: 250 km/h• Maximum speed goods trains: 160 km/h• 50 – 80 passenger trains per day• 220 – 260 goods trains per day• Loaded vehicles: max. height 4.2 m• Max. gradient: ≤≤≤≤ 12.5 ‰• Min. radius: ≥≥≥≥ 5,000 metres• Useful life: 100 years• Max. temperature: 40 °°°° C
![Page 10: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/10.jpg)
10
LZ01
-453
742
2. Challenges
![Page 11: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/11.jpg)
11
AlpTransit Gotthard AG
LZ01
-453
742
Challenge – implementation organisation
• Direct management, simple control
• Transparency through direct parliamentary control
• Clear allocation of responsibilities, best governance
• Efficiency thanks to lean organisation (short paths, simple decision processes)
![Page 12: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/12.jpg)
12
AlpTransit Gotthard AG
LZ01
-453
742
Challenge planning and processes
![Page 13: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/13.jpg)
13
AlpTransit Gotthard AG
LZ01
-453
742
Allocation of Public Transport Financial Fund (FinöV)
Heavy road vehicletax (64%)
Heavy road vehicletax (64%)
Oil tax(23%)
Oil tax(23%)
Value added tax(VAT) (13%)
Value added tax(VAT) (13%)
Fund for the financing of public transport
Fund for the financing of public transport
NRLA (45%)New Rail Link through the Alps
NRLA (45%)New Rail Link through the Alps
Rail 2000 Phase 1and ZEB (44%)ZEB: Future Development of the Railway Infrastructure
Rail 2000 Phase 1and ZEB (44%)ZEB: Future Development of the Railway Infrastructure
HSR (4%)European High-Speed Rail Network
HSR (4%)European High-Speed Rail Network
Noise mitigation (7%)
Noise mitigation (7%)
![Page 14: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/14.jpg)
14
AlpTransit Gotthard AG
LZ01
-453
742
Swiss Government Decision
c. Gotthard route 13 157
Total 19 100
![Page 15: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/15.jpg)
15
AlpTransit Gotthard AG
LZ01
-453
742
Development of final cost and risk potential
![Page 16: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/16.jpg)
16
AlpTransit Gotthard AG
LZ01
-453
742
Erstfeld Amsteg Sedrun Faido Bodio
Access adit
Ventilation shaft
Shafts I & II
MFS Sedrun
MFS Faido
Access adit
Cable tunnel
Access adit
Waste airFresh air
Challenge safety
![Page 17: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/17.jpg)
17
AlpTransit Gotthard AG
LZ01
-453
742
Challenge geology I
![Page 18: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/18.jpg)
18
AlpTransit Gotthard AG
LZ01
-453
742
Challenge geology II
![Page 19: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/19.jpg)
19
AlpTransit Gotthard AG
LZ01
-453
742
Time-lapse - execution
![Page 20: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/20.jpg)
20
LZ01
-453
742
3. Reminiscences from the construction period
![Page 21: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/21.jpg)
21
AlpTransit Gotthard AG
LZ01
-453
742
Challenges – for example the Piora Syncline
![Page 22: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/22.jpg)
22
AlpTransit Gotthard AG
LZ01
-453
742
Faido 1996: exploratory bores, Piora
![Page 23: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/23.jpg)
23
AlpTransit Gotthard AG
LZ01
-453
742
Sedrun 1998: tunnel constructors in shaft
![Page 24: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/24.jpg)
24
AlpTransit Gotthard AG
LZ01
-453
742
Sedrun 2003: deformable steel inserts
![Page 25: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/25.jpg)
25
AlpTransit Gotthard AG
LZ01
-453
742
Lakefill Uri: 2003 - 2006
![Page 26: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/26.jpg)
26
AlpTransit Gotthard AG
LZ01
-453
742
Erstfeld 2006: preliminary cut, view towards portal
![Page 27: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/27.jpg)
27
AlpTransit Gotthard AG
LZ01
-453
742
Faido East 2008: rock-pressure damage
![Page 28: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/28.jpg)
28
AlpTransit Gotthard AG
LZ01
-453
742
Amsteg 2009: surface installations site
![Page 29: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/29.jpg)
29
LZ01
-453
742
4. The Project Today
![Page 30: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/30.jpg)
30
AlpTransit Gotthard AG
LZ01
-453
742
Installation progress railway technology, September 1, 2014
![Page 31: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/31.jpg)
31
AlpTransit Gotthard AG
LZ01
-453
742
Bodio: laid ballastless track, catenary, GSM-R cable
![Page 32: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/32.jpg)
32
AlpTransit Gotthard AG
LZ01
-453
742
Faido-Bodio: start of pilot operation
![Page 33: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/33.jpg)
33
AlpTransit Gotthard AG
LZ01
-453
742
Commissioning
![Page 34: The AlpTransit Gotthard Project - ENGINYERS · 1 LZ01-453742 The AlpTransit Gotthard Project Enginyers Industrials de Catalunya 15 october 2014 Dr. Renzo Simoni CEO AlpTransit Gotthard](https://reader030.vdocument.in/reader030/viewer/2022020303/5af982a97f8b9a44658ddd0b/html5/thumbnails/34.jpg)
34
AlpTransit Gotthard AG
LZ01
-453
742
Vision
•• Commercial openingCommercial openingGotthard Base Tunnel:Gotthard Base Tunnel:December 2016December 2016
•• Commercial openingCommercial openingCeneri Base Tunnel:Ceneri Base Tunnel:December 2019December 2019