tidal power and the ‘seagen’ tidal stream turbine an overvie for download... · 2008. 10....
TRANSCRIPT
1
IWEA 3 October 2008
Tidal Power and the ‘SeaGen’ Tidal Stream Turbine
An Overview
by Martin WrightManaging Director
Marine Current Turbines Ltd The Court, The Green,
Stoke Gifford, Bristol BS34 8PD, UK.
www.marineturbines.com
Why use marine currents?
1. Predictability - driven by gravity - not weather
3. Minimal environmental impact - and favourable ERoEI - <8mths
4. Modular technology - short construction lead time
San Bernardino Straits - The Philippines
shown running at 3.5m/s or 7 knots
2. High Load Factor (works on both the ebb and the flood tides)
5. Technical feasibility - rapid development is possible
Why Do It?
■ Significant Comparative Advantage
Best Resource in Europe for Wind, Wave & Tidal
■ Strong Market Drivers
Peak Oil
Security of Supply
EU Directive 15% of ALL Energy
Climate Change
■ Leading Technologies
■ Industrial Assets
4
Potential Tidal Current Energy Sites (Irish Sea)
Scotland
N.I.
Wales
Strangford
Analysis of tidal flows was difficult but new techniques are making it easier.
This is a computer generated model of the entire Irish Sea tidal flow regime at Spring Tide, 3hrs after HW Belfast
However only areas shown in magenta (and ringed in blue) have enough energy to be useful
image courtesy Kirk McClure Morton
Belfast
State of the Art = Tidal Stream Technology1. Systems of more than 100kW
Engineering Business (UK) Stingray - reciprocating hydrofoil 150kW2002
MCT (UK) – Seaflow single axial flow rotor 300kW2003
Hammerfest Stroem (Norway) - Blue Concept – single axial flow rotor 300kW2003
MCT (UK) – Seagen twin axial flow rotors 1.2MW2008
2. Systems of less than 100kW
MCT (IT Power / NEL / Scottish Nuclear) (UK) - single axial flow rotor 10kW1994
Florida Hydro / - unconventional ducted axial flow rotorOpen Hydro (Ireland)
35kW~75kW
20032007
Verdant Power (USA) - single axial flow rotor 35kW2005?
Ponte di Archimedi (Italy) - Kobold Turbine - single Darrieus rotor 25 kW2004
UEK (USA /Canada) - two ducted axial flow rotors 40kW?2002?
Clean Current (Canada) - single axial ducted flow rotor 80kW?2007
3. Systems with no more than small-scale physical models tested
SMD Hydrovision (UK) / TiDel - 1/10 model tank tested 1MW ?
Lunar Energy (UK) / R1000 or R1500 – ~1/20 model tank tested 1 MW?
Tidal Hydraulic Generators (UK) ~1kW model tested ? ?
Swan Turbines ~1 kW model tested 1MW ?
4. Systems with no more than theoretical design work completed
SSE/Weir / RTVL Neptune - proposed 2MW twin axial flow rotors 2MW ?
Tidal Generation - proposed 1 MW single axial flow rotor 1MW ?
Tidal Stream - proposed group of 4 axial flow rotors 2MW 2010?
plus 20+ others ……
abandoned
The Effect of Velocity Shear
Velocity Power / EnergySea Level
Sea Bed
75% of the Energy is
in the upper 50% of
the water column
State-of-the-art: comparison of rotor sizes
Note: the swept area of the rotors governs the energy capture at any given location
9
Decentralised Marine RE Systems*:
What do we need for commercial success?
1. Scale – must be 1MW or more to be economic
2. Access – safe, affordable, reliable access for servicing
3. Reliability – need to minimise costly intervention
4. Life – several decades; otherwise not economic
… few technology developers are anywhere near to
delivering technology to fit these criteria
* i.e. wave and tidal stream energy systems
10
Background: 15kW Tidal Current Turbine (1994-5)
PROOF OF CONCEPT PROJECT
(IT Power. Scottish Nuclear & NEL)
Loch Linnhe, Scotland
World’s first tidal current turbine
11
Seaflow installed
30 May 2003rotor dia. 11m
rated power 300kW
pile dia. 2.1m
water depth 24m 5m
operational raised for access
12
the basic concept
Axial flow rotor
Marinised drive train
Surface breaking monopile
Structural integrity
Low cost intervention
No significant environmental impact
Seaflow: What has ‘worked’
SeaGen Prototype Some key features:-
rotors and nacelles raised above
sea level for maintenance
2 x 600kW rotors:16m diameter
installed on steel pile
transformer and electrical
connection to grid in accessible
and visible housing at top of pile
deployment in arrays or “farms”.
of hundreds of turbines
Gearbox, hub and generator
Seagen: Performance at Lynmouth & Strangford
Rotor assembly at H&W - 16m diameter - 2 x 600kW
Assembly at H&W - cross arm (above) pile (below)
Seagen - complete and ready for installation
at Harland & Wolff, Belfast - March 2007
Revised Jacket Foundation
■ Retain existing SeaGen
structure above the Mud-line
■ Create new Quadrapod
foundation
■ Install using a Crane Barge
■ Pin to seabed with Ø1m steel
piles, 8m-10m embedment
20
New Quadropod base for Seagen being fitted – Mar 2008
‘SeaGen’ arrives in Strangford Lough - April 2008
‘SeaGen’ positioned, ready for pinning to seabed
Construction Barge in Position
Drilling and Grouting Operations
SeaGen Raised
Marine Current Turbines Early Project Costs
Location RatedPower
(MW)
Capitalcost
(£k/MW)
Life CycleUnit cost
(p/kWh)
Strangford 1.2 5,191 16.8
Anglesey Skerries demo 10.5 2,537 11.7
Anglesey SkerriesCommercial
51.0 1,489 7.9
Anglesey Skerries ifdeveloped fully
(after 500MW installed)
30.0 923 5.2
Cost projections from due diligence report by Black & Veatch 2006/8 in an independent assessment
MCT Site Development Plan - Weighted Average Generation Cost
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
Ang
lese
y Ske
rries 1
- Pha
se 1
Ang
lese
y Ske
rries 1
- Pha
se 2
Ang
lese
y Ske
rries 1
- Pha
se 3
Mull o
f Galloway
2
Fair H
ead
- Nea
r Sho
re /
Torr H
ead
Mull o
f Galloway
3
Bisho
ps a
nd C
lerk
s 3
/ 4
Mull o
f Oa
San
da S
ound
Ang
lese
y Nor
th a
nd S
outh
Sta
ck
Bar
dsey
Sou
nd
Co
st
of
ele
ctr
icit
y g
en
era
ted
- p
/kW
h
Cost of MCT technology Cost of Offshore Wind
an indicator of cost-effectiveness
how many kWe per tonne of equipment?
Vestas V80 windturbine ~ 3.4 kWe per tonne
offshore at North Hoyle590t & 2000kWe
Wave energy devices << 1.0 kWe per tonne
MCT Seaflow tidal turbine ~ 2.3 kWe per tonne130t & 300kWe
MCT Seagen prototype ~ 3.1 kWe per tonne390t & 1200kWe
MCT 2nd Generation ~ 5.0 kWe per tonne1000t & 5000kWe
Commercialisation - The Next Stage
■ Requirements
Capital
Capability
Supply chain
Sites
Realistic and consistent market signals
Scotland and…………… the Rest….
Commercialisation - The Next Stage
■ The obstacles
Slow government progress - SEAs
Consents – Crown Estate
Unrealistic lease terms
Lack of Grid infrastructure
Competing for Capital……………??
31
Marine Current Turbines Ltdhttp://www.marineturbines.com
tel: (+44 or 0) 117 979 1888