10/17/2014 1 Copyright © 2013 by Value Management Strategies, Inc. Total Value Optimization Total Value Optimization Presenter: Mark Watson, PE, CVSLife, PMP Presentation Outline Obstacles to Achieving Best Value Traditional Value Methodology Traditional Value Methodology VM Job Plan Function Analysis Advancements To Traditional VM Value Metrics Copyright © 2013 by Value Management Strategies, Inc. Cost and Schedule Analysis Techniques Risk Analysis Why use VM and who is using it?

Upload: others

Post on 30-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

1

Copyright © 2013 by Value Management Strategies, Inc.

Total Value OptimizationTotal Value Optimization

Presenter:  Mark Watson, PE, CVS‐Life, PMP

Presentation Outline

• Obstacles to Achieving Best Value

• Traditional Value MethodologyTraditional Value Methodology

– VM Job Plan

– Function Analysis

• Advancements To Traditional VM

– Value Metrics

Copyright © 2013 by Value Management Strategies, Inc.

– Cost and Schedule Analysis Techniques

– Risk Analysis

• Why use VM and who is using it?

Page 2: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

2

Value Theory – Obstacles to Value

Copyright © 2013 by Value Management Strategies, Inc.

Incorrect Assumptions

Copyright © 2013 by Value Management Strategies, Inc.

Poor Project Handoff

Page 3: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

3

Perceptions

Are the squares marked A and B different shades of gray?shades of gray?

Copyright © 2013 by Value Management Strategies, Inc.

Obstacles to Value

• If we have trouble judging simple things like color, one must ask what other mistakes are we making in perception? 

• Can we really believe everything we think we see?

• How do our perceptions affect our value d ?

Copyright © 2013 by Value Management Strategies, Inc.

judgments?

Page 4: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

4

Habitual Behavior

Copyright © 2013 by Value Management Strategies, Inc.

Obstacles to Value

• Habits and Attitudes

– The number one reason for poor value!p

“It is our habits that take us where we were yesterday, and our attitudes that keep us there!”

Copyright © 2013 by Value Management Strategies, Inc.

p

- Confucius

Page 5: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

5

Obstacles to Value

• Obstacles to Achieving Best Value:– Poor communication 

– Customers’ needs/wants change

– Outdated design standards or changing technology 

– Incorrect assumptions 

– Fixation with previous design 

Copyright © 2013 by Value Management Strategies, Inc.

– Temporary circumstances

– Honest wrong beliefs

– Habits and attitudes 

What is Value Methodology?

The application of systematic techniques by a multi-discipline team to improve value by

evaluating its functions to meet the project’s required performance at the lowest overall cost.

Copyright © 2013 by Value Management Strategies, Inc.

q p

Page 6: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

6

Terminology

Value Engineering 

Value Analysis   (VA)

(VE)

Value Management 

(VM)

Copyright © 2013 by Value Management Strategies, Inc.

Value Methodology

Value Engineering Process

Presentation

Implementation(Post‐Study)

Value StudyValue Study

Speculation(Creativity)

Evaluation

Development

Speculation and Evaluation tends to be cyclical in nature

Copyright © 2013 by Value Management Strategies, Inc.

Preparation(Pre‐Study)

Function (Analysis)

Information

Page 7: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

7

“If I ’ h d I’

Value Methodology

“If I can’t get the product, I’ve got to get the function. How can you provide the function by using some machine or labor or material that you can get?”

Copyright © 2013 by Value Management Strategies, Inc.

Larry MilesCreator of Value Analysis

• Equations for Value

– According to Miles:

Value Theory

– According to Miles:• “All cost is for function”

Value =Function

Cost + Time

Copyright © 2013 by Value Management Strategies, Inc.

Cost + Time

Page 8: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

8

Defining Functions

• A function is the basis for why something exists.

• In Function Analysis, functions are described using two words:

VERB NOUN+

Copyright © 2013 by Value Management Strategies, Inc.

What does it do? What does it do it to?

Function Analysis

Copyright © 2013 by Value Management Strategies, Inc.

Page 9: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

9

Function Analysis

Copyright © 2013 by Value Management Strategies, Inc.

Defining Functions

What is the basic function of these hammers?

Copyright © 2013 by Value Management Strategies, Inc.

Page 10: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

10

Functions or Activities?

• Both functions and activities can be described as a verb + noun

Activity Function

Construct Bridge Span River

Process Invoice Allocate Funds

Weld Joint Connect Components

Install Wall Retain Earth

Copyright © 2013 by Value Management Strategies, Inc.

• Which statement tells us more?• Which statement is more likely to lead to innovation?

Install Wall Retain Earth

Function Analysis

• Helps create joint understanding of project’s purpose and need

• Clarifies and builds consensus of project‐specific objectives

Aid i hi i di i i f ifi

Copyright © 2013 by Value Management Strategies, Inc.

• Aids in achieving dissociation from specifics

• Reduces possibility of faulty communication and misunderstanding

Page 11: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

11

Matagorda Ship Channel VE

Copyright © 2013 by Value Management Strategies, Inc.

Matagorda Ship Channel VE

Copyright © 2013 by Value Management Strategies, Inc.

Page 12: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

12

Copyright © 2013 by Value Management Strategies, Inc.

VE Developed Solution

Copyright © 2013 by Value Management Strategies, Inc.

Page 13: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

13

i l i d i i

Copyright © 2013 by Value Management Strategies, Inc.

Function Analysis and FAST Diagramming

• Equations for Value

– According to Miles:

Value Theory

– According to Miles:• “All cost is for function”

Value =Function

Cost + Time

Copyright © 2013 by Value Management Strategies, Inc.

Cost + Time

Page 14: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

14

Cost Analysis Techniques

Copyright © 2013 by Value Management Strategies, Inc.

Cost Analysis Techniques

• Pareto Modeling

– 80/20 Rule/

• Activity based costing

• Life Cycle Cost Analysis

• Component costing

– Individual project elements

Copyright © 2013 by Value Management Strategies, Inc.

p j

• Parametric Cost Modeling

• Cost‐Function Allocations

• …and many more!

Page 15: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

15

Why use LCC?Typical conflicts in most companies:• Project Engineering wants to minimize capital costs as the only criteria,costs as the only criteria,

• Maintenance Engineering wants to minimize repair hours as the only criteria,

• Production wants to maximize operation hours as the only criteria,

• Reliability Engineering wants to nullify failuresas the only criteria,

Copyright © 2013 by Value Management Strategies, Inc.

• Accounting wants to maximize project net present value as the only criteria,

• Shareholders want to increase stockholder wealth as the only criteria.

Life Cycle Cost Considerations

Initial Costs

Maintenance Implications

Salvage Externalities

Life Cycle Cost 

Analysis

Copyright © 2013 by Value Management Strategies, Inc.

Operational Performance

y

Page 16: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

16

Cost Estimate and LCC Analysis

Copyright © 2013 by Value Management Strategies, Inc.

Copyright © 2013 by Value Management Strategies, Inc.

Initial Cost and Life Cycle Cost Analysis

Page 17: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

17

Cost-Function Analysis

Copyright © 2013 by Value Management Strategies, Inc.

Copyright © 2013 by Value Management Strategies, Inc.

Cost‐Function Analysis Worksheet

Page 18: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

18

• Equations for Value

– According to Miles:

Value Theory

– According to Miles:• “All cost is for function”

Value =Function

Cost + Time

Copyright © 2013 by Value Management Strategies, Inc.

Cost + Time

Schedule Analysis Techniques

• Critical Path Method

• Detailed Work Breakdown StructureDetailed Work Breakdown Structure

• Horizontal and Vertical Schedule Integration

– Milestone‐based Planning

• Activity Based Scheduling

– Early Start / Late Start

Copyright © 2013 by Value Management Strategies, Inc.

y

– Early Finish / Late Finish

• …and many more!

Page 19: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

19

• Equations for Value

– According to Miles:

Value Theory

– According to Miles:• “All cost is for function”

Value =Function

Cost + Time

Copyright © 2013 by Value Management Strategies, Inc.

Cost + Time

How do you quantify or measure a function?

Value Theory

• Functional Value

Copyright © 2013 by Value Management Strategies, Inc.

Page 20: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

20

Value Metrics

• Value Metrics provides a proven process and set of techniques to effectively measure 

fperformance.

• Creates a model of the value‐based information

• Provides an important means of communication

E bli h f b i

Copyright © 2013 by Value Management Strategies, Inc.

• Establishes preferences between options through measurable criteria

• Allows comparisons to be made based on total value

Value Metrics Process

• Identify Performance Requirements and Attributes – Performance consists of two elements:

• REQUIREMENTS – Non‐Discretionary (no flexibility)

– Binary response – yes/no

• ATTRIBUTES– Discretionary (there is flexibility)

Copyright © 2013 by Value Management Strategies, Inc.

– Range of potential values 

– Attributes and Requirements must be discretely defined and should not overlap

Page 21: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

21

Performance Requirement?

Current Electrical Endurance Rating:  10,000 cycles

Copyright © 2013 by Value Management Strategies, Inc.

Min. Required Endurance Rating (Eur):  6,000 cycles

Min. Required Endurance Rating (US):  4,000 cycles

What does the customer really need?

Customer Performance…

0.9

1

Customer Preference for Electrical Cycles

0 1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

Perform

ance Rating

What are we paying for this additional 

performance?

Copyright © 2013 by Value Management Strategies, Inc.

0

0.1

0

10

25

50

75

100

200

500

1,000

5,000

10,000

Electrical Cycles

Page 22: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

22

Value Metrics

• Define Performance– Define performance attributes and requirements

l l f b– Develop scales for attributes

– Determine relative importance of attributes

• Assess Performance– Measure performance of alternative concepts

• Estimate Cost and Schedule

Copyright © 2013 by Value Management Strategies, Inc.

• Assess Value– Compare the relative value of all alternatives

Value Metrics Example - New VA Hospital

• 283,000 GSF Renovation project

• Multiple Layout Alternatives being considered

• Objective: Assist stakeholders in 

Copyright © 2013 by Value Management Strategies, Inc.

selecting a preferred alternative

Page 23: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

23

Performance RequirementsPerformance Requirement Definition

Code Requirements Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will be the minimum codes met.

Critical Schedule Milestones 

The project must meet the following critical milestones. July 2017 is the minimum date acceptable for beneficial occupancy.

LEED Certification / Sustainability 

Project must meet LEED Gold Certification. The design team is striving for LEED Platinum and utilization of 20% renewable energy for the facility.

Copyright © 2013 by Value Management Strategies, Inc.

Accessibility  Must meet ADA requirements for new construction. 

Environmental Approvals 

The project must adhere to all applicable environmental laws and regulations. 

Performance AttributesAttribute  Description 

Construction Impacts 

A measure of the impacts to ongoing operations and/or to the public in general.  This attribute considers delays, disruptions, noise, vibration, dust, visual and temporary environmental impacts related to construction. 

Program Compatibility 

An assessment of how well the building’s interior spaces meet their intended function and the objectives of the overall program.  This attribute considers the size and shape of spaces; sound attenuation; lighting characteristics; and special amenities (i.e., data, audio/visual, storage, etc.). 

Aesthetics An assessment of the building’s aesthetic appeal.  This attribute considers how well it responds to the site, surrounding structures, the locale and the building’s function. 

MaintainabilityA measure of the efficiency for long‐term operations and maintenance 

Copyright © 2013 by Value Management Strategies, Inc.

Maintainability considering a 50‐year service life.

Sustainability An assessment of the sustainability of the project in its efforts to reduce consumption of non‐renewable resources, minimize waste, and create healthy, productive environments.

Future Flexibility An assessment of the flexibility and adaptability of the interior building spaces to meet future program needs. 

 

Page 24: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

24

Performance Prioritization

24 0%

30.0%

Construction Impacts

Program Compatibility

7.0%

12.5%

18.5%

24.0%

Maintainability

Aesthetics

Site Organization

Construction Impacts

Copyright © 2013 by Value Management Strategies, Inc.

3.3%

4.7%

0% 5% 10% 15% 20% 25% 30% 35%

Future Flexibility

Sustainability

Performance Comparison

Baseline

Alt. 2

Alt. 1

Copyright © 2013 by Value Management Strategies, Inc.

0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8

Alt. 3

Program Compatibility Site Organization Aesthetics Sustainability

Maintainability Future Flexibility Construction Impacts

Page 25: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

25

Comparison of Value3.76

3 00

3.50

4.00

0 70

0.80

0.90

1.57

1.90

3.00

1.50

2.00

2.50

3.00

0.30

0.40

0.50

0.60

0.70

Chan

ge in

 Value

Relative Scores

Copyright © 2013 by Value Management Strategies, Inc.

0.00

0.50

1.00

0.00

0.10

0.20

Baseline Alt. 1 Alt. 2 Alt. 3

Performance Cost/Time Rating Value Index

(What happens to most presentation handouts from conferences)

Copyright © 2013 by Value Management Strategies, Inc.

Value Metrics

Page 26: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

26

Risk Analysis

Copyright © 2013 by Value Management Strategies, Inc.

Traditional Risk Management

Copyright © 2013 by Value Management Strategies, Inc.

Page 27: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

27

Traditional Risk Management

Response

Analysis

Problem Focused

Copyright © 2013 by Value Management Strategies, Inc.

Identification

Traditional Risk Management

ISSUES/PROBLEMS  OBSERVED:

• Limited number of risks identifiedLimited number of risks identified

• Risks identified tended to be too “general” and not relative to project specifics

• Low priority risks can take a majority of PM’s time

• Limited number of Risk Response Strategies

Copyright © 2013 by Value Management Strategies, Inc.

Limited number of Risk Response Strategies identified

• Risk Response Strategies not effective at managing risk

Page 28: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

28

Function Driven Risk Management

RResponse

AnalysisSolution Focused

Copyright © 2013 by Value Management Strategies, Inc.

Identification

Function Driven Risk Response Planning

Risk Object Identification

Brainstorming of Risk Response Strategies by Function

Secondary Risk Analysis

Copyright © 2013 by Value Management Strategies, Inc.

Evaluation of Risk Response Strategies

Development of Action Plans for Risk Response Strategies

Page 29: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

29

Function Driven Risk Response Planning

Copyright © 2013 by Value Management Strategies, Inc.

Pier 36, San Francisco– Risk Analysis

Copyright © 2013 by Value Management Strategies, Inc.

Page 30: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

30

Risk Management Plan

Copyright © 2013 by Value Management Strategies, Inc.

Caisson removal rate

Western gulls nest in the project area

Pier 36, San Francisco– Risk Analysis

Schedule Risk Ranking

Unforseen HAZMAT materials encountered

Salvaging and/or recycling of existing materials

Earthquake occurs during construction

Cultural resource is found during construction

Herring spawning is observed

Award of follow‐on construction contract prior to demolition completion

Bids come in higher than the budgeted amount

BCOE finalization is delayed

Construction contract award is delayed

Copyright © 2013 by Value Management Strategies, Inc.

‐1 ‐0.8 ‐0.6 ‐0.4 ‐0.2 0 0.2 0.4 0.6 0.8 1

0

0

Contractor unable to complete project

Public protest of project

Unforseen HAZMAT materials encountered

Opportunities <‐‐‐‐‐ Index   ‐‐‐‐‐> Threats

Pre‐Response

Page 31: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

31

Project Functional Overview

• Remove Obstacles

– Demolish Warehouse/Abate HAZMAT/

– Demolish Deck and Beams

– Remove Caissons/Piers 

• Prepare Site

– Remove Marginal Wharf

Copyright © 2013 by Value Management Strategies, Inc.

– Maintain Seawall Integrity

• Meet Schedule Requirements

– Coordinate Concurrent Projects

Caisson removal rate

Western gulls nest in the project area

Pier 36, San Francisco– Risk Analysis

Schedule Risk Ranking – Post‐Response

Unforseen HAZMAT materials encountered

Salvaging and/or recycling of existing materials

Earthquake occurs during construction

Cultural resource is found during construction

Herring spawning is observed

Award of follow‐on construction contract prior to demolition completion

Bids come in higher than the budgeted amount

BCOE finalization is delayed

Construction contract award is delayed

Copyright © 2013 by Value Management Strategies, Inc.

‐1 ‐0.8 ‐0.6 ‐0.4 ‐0.2 0 0.2 0.4 0.6 0.8 1

0

0

Contractor unable to complete project

Public protest of project

Unforseen HAZMAT materials encountered

Opportunities <‐‐‐‐‐ Index   ‐‐‐‐‐> Threats

Pre‐Response Post Response

Page 32: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

32

0.7The Cumulative Risk Score is next to each bubble

Schedule Risk Magnitude – Post-Response

0.30

0.21

0.3

0.4

0.5

0.6

Copyright © 2013 by Value Management Strategies, Inc.

0

0.1

0.2

0 0.1 0.2 0.3 0.4 0.5 0.6 0.7

Impact Score ‐‐‐‐>

Likelihood Score ‐‐‐‐>

Pre‐Response Post‐Response

Copyright © 2013 by Value Management Strategies, Inc.

Risk Analysis and Risk Response Planning

Page 33: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

33

Value Theory

How well?

Performance

TimeCost VALUEHow much? How long?

Copyright © 2013 by Value Management Strategies, Inc.

Risk

How certain?

Concepts of “Best Value”

• The Best Value results when the necessary functions to meet the required performance q pat the lowest overall cost and least amount of delivery time are performed in the least uncertain way.  – Performance, Cost and Schedule are Uncertain

– Performance includes requirements and 

Copyright © 2013 by Value Management Strategies, Inc.

qattributes

– Risk in costs and durations are comprised of estimating risk and event risk

Page 34: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

34

Why use Value Methodology?

Improve project value

Solve problems and innovate

Identify the “best value” alternative

Build consensus among stakeholders

Copyright © 2013 by Value Management Strategies, Inc.

Validate the baseline concept

In some cases, it’s the law!

How is Value Methodology different?

Solves problems by focusing on functionsSolves problems by focusing on functions

Utilizes multiUtilizes multi‐‐discipline teamsdiscipline teams

Organizes concepts and techniques into a specific Job PlanOrganizes concepts and techniques into a specific Job Plan

Copyright © 2013 by Value Management Strategies, Inc.

Seeks to achieve total value improvementSeeks to achieve total value improvement

Consensus basedConsensus based

Page 35: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

35

Who is using Value Methodology?

Federal GovernmentFederal Government

Copyright © 2013 by Value Management Strategies, Inc.

Who is using Value Methodology?

State GovernmentState Government

Copyright © 2013 by Value Management Strategies, Inc.

Page 36: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

36

Who is using Value Methodology?

Local GovernmentLocal Government

Copyright © 2013 by Value Management Strategies, Inc.

Who is using Value Methodology?

Copyright © 2013 by Value Management Strategies, Inc.

Page 37: Total Value Optimization PMI PDD 2014Building(s) will meet all appropriate building and zoning codes/regulations, including the London Specific codes. The most restrictive codes will

10/17/2014

37

Conclusion & Take Aways

• Value is a combination of performance, cost, time, and risk

• The analysis of all these elements and application of VE techniques can enhance value of any project, process, or product

• “Good” VM always increases value, it does h

Copyright © 2013 by Value Management Strategies, Inc.

not cheapen projects

Value Theory

How well?

Performance

TimeCost VALUEHow much? How long?

Copyright © 2013 by Value Management Strategies, Inc.

Risk

How certain?