tsnp general introduction aiea workshop - paris … general introduction aiea workshop - paris...

31
1 TSNP General Introduction AIEA Workshop - Paris 14/12/2011 Picture PhC 23/11/2011 Zhao Jian Ying Construction Manager Philippe Convert Deputy Construction Manager

Upload: vankien

Post on 29-Mar-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

1

TSNP General Introduction

AIEA Workshop - Paris 14/12/2011

Picture PhC 23/11/2011

Zhao Jian Ying – Construction Manager

Philippe Convert – Deputy Construction Manager

2

Contents

OverviewNI Civil

WorksConclusion

TSNP Video

Focus

3

TSNP is a project owned by CGNPC (70%) and EDF (30%).

Enterprises from both China and France are in charge of design,

procurement and construction :

NI: AREVA in France takes the lead of NI supply and design

contracts, while CNPEC (China Guangdong Nuclear Power

Engineering Co., Ltd. ) and CNPDC (China Guangdong Nuclear

Power Design Co., Ltd. ) also take part in.

CI: ALSTOM in France and DEC (Dongfang Electric Co. Ltd.) in

China are responsible for TG design and supply contracts.

Other contracts are in the charge of some domestic enterprises.

Cooperated construction

4

Design FabricationConstruction Commiss

ioningOperation Management

土建 安装

Overall plant CNPDC Domestic enterprises

TNPJVC

(CNPEC

supports)

TNPJVC

( DNMC

supports)

TNPJVC

( CNPEC

supports)

NI

PLP

ANP+CNPDC

ANP+DEC+SEC

(50% localization)HXCC/C

SCECC23

BNI

CNPEC

Mainly procured in

China

CI

TG ALSTOM+DEC

ALSOM+DEC

(China accounts for

2/3)CSCEC GPEC

BCICNPDC+ALST

OM+GEDI

CNPEC

Mainly procured in

China

BOP CNPDC

CNPEC

Mainly procured in

China

Domestic GPEC

enterprise

Note Sino-French cooperation; Domestic enterprises; CGNPC.

Industrial Scheme

Civil works Erection

5

Located at the Yaogu Village, Chixi Town, Taishan City of the Guangdong Province.

The site is 70km, 80km, and 40km respectively from Zhuhai, Yangjiang and Taishan.

6

Unit 1 & 2

Administration et auxiliary buildings.

Living area, including contractors living area

Heavy Jetty

Water

Outlet

Channel

Overall Site Arrangement

Water intake

Tunnels 4.4 km

Channel 2,4 km

7

EPR Main Quantities (for 1 Unit)

Civil Works: 400 000 m3 of concrete and 47000 t of rebars

Heaviest load Transport : Steam Generator 581 t

Electricity: 2500 km of cables :•IEG : 1700 km de cables (22000 cables) IED : 500 km•Turbine building: 300 km

Mechanical works : 102 km of pipingNuclear Island Piping(non AREVA) :67 km (75% stainless steel) representing 850t Supports excluded) and around 3 km of weldsPiping AREVA: 29 kmPiping conventional island : 6 km

8

Overall Schedule

CFT HFT

COD

2013-12-31NI FCD

2009-09-1

NI EP LOI

2007-9-1

NI Construction ,Erection & Commission 52m

CI Construction & Erection (43+1)m

NI Design and Preparatory Work

24m

CI FCD

=NI FCD

CI Design and

Preparatory Work 17m

TG SOC

LOI+6

FLG

Pumping Station Flooding

FCD+33

Construction & Erection

30m

Design and Preparatory

Work 20m

Pumping Station FCD

FCD+3CRF Pump LOI

NI FCD

NI Civil Works 34.5m

NI Erection 26m

Commission 22.5m

Dome lifting

FCD+20

CI

Pumping

Station

NI

24 Months

HFT

FCD+43

RPV Site Delivery

FCD+27RPV,SG Forge Order

52 Months

Main Traveling Crane Available

FCD+21.5

Lubricant oil Flushing

FCD+37.5

9

Contents

OverviewNI Civil

WorksConclusionFocus

10

Safeguard

Building 1

Safeguard

Building 2 & 3

Safeguard

Building 4

Fuel Building

Reactor BuildingPumping Station

Unit 1 general View 23-11-2011

Turbine Building

11

Unit 1 HRA building:

The liner dome has been lifted on

October the 23rd, welding and

controls are completed.

Reinforcement placing on lift 19th

is on going.

As to external containment,

completed the 7th layer (+19.15m).

The internal structures are

completed.

Construction on site

12

NI unit 1 – Blinding concrete

Works started 1/03/09

CEPR - Civil Works NI - Raft

13

NI unit 1 – Prestressing galery

7/05/09

CEPR - Civil Works NI - Raft

14

Reactor Building – 1 Raft reinforcement

CEPR - Civil Works

> 2,000 t of Steel

15

October 2009

Unit 1 - 87h

CEPR - Civil Works NI – Raft Concreting > 9,100 m3

April 2010

Unit 2 - 67 h

16

NI Unit 1 – Reactor Building - Bottom Liner

CEPR - Civil Works - Liner

January 2010

17

CEPR - Civil Works – Liner Modules

Modules

12 Plates/ring

18

Module 1 - 20/03/2010

Module 2 - 18/05/2010Module 3 - 28/07/2010

Module 4 - 07/09/2010

Ring 5 - 30/09/2010

CEPR - Civil Works – Liner Modules

19

Unit 1 Dome

Prefabrication

CEPR - Civil Works - Liner

Unit 1 Dome Lifting

23/10/2011

Weight 260t

20

CEPR - Civil Works – HRA Internal Structures

Structures from -7.85m up to level -4.50mRoof of the core catcher

Structures from 5.15m up to level 19.50mRIS tank introduction

21

CEPR - Civil Works – HRA Internal Structures

19.50m Slab 19.50m Slab

Structures above 19.50m

Polar crane and TLD in place. Dome in place

22

Contents

OverviewNI Civil

WorksConclusionFocus

23

CEPR - Civil Works - Concrete

HRA Raft example: One pour

Comprehensive method statement, main points:

– The C40/50 concrete mix,

– The global organization in order to avoid cold joint,

– The risk of delayed ettringite: in case in core temperature is

higher than 65 °C

Optimization of theC40/50 concrete mix: cement content, slag

and/or fly ash content, retarder admixture (minimize the heat of

hydration).

The mock-up tests to assess:

– The concrete placing organization

– The maximum in core temperature rise

Thorough preparation and follow-up

Importance of a good concrete curing (1 month).

24

Avancement des travauxCEPR - Civil Works Containment Buildings Sequence

Unit 1:

Outer containment after

Inner Containment :

Impact on peripheral

buildings

Unit 2:

Little time-lag between

Inner containment and

Outer containment

No Impact on peripheral

buildings

25

Avancement des travauxCEPR - Civil Works Reinforcement Density

Safeguard Building

1 - Raft

Reactor Building

Raft

26

CEPR - Civil Works Reinforcement Density

Safeguard Building

3 – APC Shell

Reactor Building

19,50m slab

27

Avancement des travauxCEPR - Civil Works Embedded Plates

NI Area :

More than 90,000

embedded plates

High reinforcement

density leads to

embedded plates

installation difficulties

FA3

28

Avancement des travauxCEPR - Civil Works Special Embedded Plates

HRA 19.50m slab –

Reactor Pool Top Edge

installation

29

Contents

OverviewNI Civil

WorksConclusionFocus

30

EPR Civil Works are complex mainly due to :

Large concrete quantity,

Large pours > 9,000 m3 for buildings rafts and > 5,900 m3 for TG pedestal raft,

Specific concretes, inner containment, APC Shell, core catcher (sacrificial concretes),

High reinforcement density,

Numerous embedded elements,

Formworks : little space between APC shell and buildings walls and roofs

Heavy lifting :

Dome (~ 260t)

Precast elements for APC Shell roof (>120t),

Main Control Room (>170t),

CEPR Civil Works - Conclusion

Experience Feed Back facilitates the progress of Taishan construction.

However, construction optimization will benefit to new EPR projects.

31

Develop Nuclear Power, Benefit Human Mankind

谢 谢!

Thanks !

Merci !